Environmental Monitoring Report

Project Number: 47270-001 January 2018

Period: January 2017 – June 2017

IND: District Connectivity Sector Project

Submitted by Madhya Pradesh Road Development Corporation Limited,

This report has been submitted to ADB by the Madhya Pradesh Road Development Corporation Limited, Bhopal and is made publicly available in accordance with ADB’s Public Communications Policy (2011). It does not necessarily reflect the views of ADB. This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

MADHYA PRADESH ROAD DEVELOPMENT CORPORATION

Madhya Pradesh District Connectivity Sector Projects (MPDCSP) Under ADB Loan No – 3189- IND

ENVIRONMENTAL MONITORING REPORT (January - June 2017)

Environmental Monitoring Report

Loan Number : 3189-IND Reporting period: January – June 2017

Madhya Pradesh District Connectivity Sector Project

(MPDCSP)

Prepared by : Madhya Pradesh Road Development Corporation Executing Agency : Madhya Pradesh Road Development Corporation

Signed by:-

(Narendra Kumar) Chief Engineer (ADB) Authorized Signatory from Executing Agency

ABBREVIATION

ADB = Asian Development Bank AIDS = Acquired Immune Deficiency Syndrome BOD = Biochemical Oxygen Demand BDL = Below Detection Limit. COD = Chemical Oxygen Demand DG = Diesel Generator EIA = Environmental Impact Assessment EMMP = Environmental Management & Monitoring Plan EMP = Environmental Management Plan FIDIC = Federation International D'Ingineure Conseil GRC = Grievance Redress Committee HIV = Human Immunodeficiency Virus HMP = Hot Mix Plant IEE = Initial Environmental Examination IPP = Indigenous People Planning IRC = Indian Road Congress Km = Kilometer Ltd. = Limited MOEF = Ministry of Environment and Forests MPRDC = Madhya Pradesh Road Development Corporation NABL = National Accreditation Board for Laboratories

NO2 = Nitrogen Dioxide NOC = No Objection Certificate NOx = Oxides of Nitrogen pH = Negative log of H+ activity Pkg = Package PPE = Personal Protective Equipment Pvt. = Private RSPM = Respirable Suspended Particulate Matter RP = Resettlement Plan SC = Supervision Consultant SH = State Highway

SO2 = Sulfur dioxide SPCB = State Pollution Control Board SPM = Suspended Particulate Matter TDS = Total Dissolved Solids TSS = Total Suspended Solids WMM = Wet Mix Macadam

TABLE OF CONTENTS

S.No. Title Page no. I Introduction and Project progress during the reporting period 1-6 II Compliance on Environment Safeguards Requirements 7 (A) Status of Compliance with National / State/ Local 7 government statutory environmental requirements. (B) Status of Environmental Compliance with ADB loan 7-10 covenants as Stipulated in the Loan Agreement. III Change in project scope 10 IV Implementation of Environment Management Plan. 10-17 Approach and Methodology for environmental parameters V 18 monitoring Environment Monitoring (e.g Ambient air, surface water, VI 18-27 ground water and Noise) Status and findings Any other environmental aspects, impacts observed during VII 28 implementation which was not covered earlier Details of Redress committee and complaints received from VIII 28 public and actions taken thereof to resolve. IX Follow-up action and conclusion 28 Annexure-I (a) 29-49 Annexure-I (b) 50-91 Annexure-I (c) 92-122 X Annexure-II (EMP Implementation photographs) 123-138

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

ENVIRONMENT MONITORING REPORT

I. Introduction

1. Asian Development Bank (ADB) has approved a project loan of U$ 350 Millions in November 2014 for the reconstruction and rehabilitation of about 1600 km of major district roads. The Project was approved by ADB on 19thNovember 2014. The Loan Agreement signed on 20th February 2015 and declared effective on 27th March 2015.The project is divided into three packages,comprising of 18 civil work contracts i.e. package-1 (Bhopal-1)Package-2 (Jabalpur) and Package-3 (Bhopal- 2). Package-1 civil work construction supervision is awarded to Intercontinental Consultant and Technocrats Pvt. Ltd. (ICT), Package-2 Projects is awarded to AECOM Asia Company Ltd. and Package-3 is awarded to Indian Technocrate Ltd.

2. These projects will improve transport efficiency of the State road network which will contribute to expansion of economic opportunities and poverty reduction. All above packages awarded under the project titled Madhya Pradesh District Connectivity Sector Projects (MPDCSP) and Madhya Pradesh Road Development Corporation (MPRDC) is the executing agency for the projects. The total project length is 1530.416 Km.

3. The Package-1 comprising of 7packages consisting 7 civil work contracts i.e. A, B, C, D, E, F and G,consisting 7 roads, covering 380.58 km length of MDRs. Package- 1 Projects awarded under the project titled “Madhya Pradesh District Connectivity Sector Projects Package-1, Bhopal-1”.

4. The Package-2, comprising of 4 civil work contract packages H,I,J and K, having 12 roads covering length of 375.59 Kms.Package-2 projects awarded under the project titled “Madhya Pradesh District Connectivity Sector Projects-Package- 2, Jabalpur”.

5. The Package-3, comprising of 7 civil work contract packages, L,M,N,O,P,Q and R having 22 roads covering length of 774.246 Kms. Package-3 projects awarded under the project titled “Madhya Pradesh District Connectivity Sector Projects- Package-3, Bhopal-2”.

6. As per ADB’s Safeguard Policy Statement (2009) and environmental assessment guidelines 2003, All the sub projects have been categorized as category B. The project has been divided into 18 packages consisting of 41 roads. Details of Civil work contracts and supervision consultants aregiven in table-1:-

Table: 1

Civil Work Contracts Under Package -1 (Bhopal-1)(Total Length 380.58 Km) Package Name of Project Name of Contract Schedule Construction No. Road and Length Contractor Signing date of Status at the completion end of reporting period Pkg-A Mahua-Chuwahi Dilip 11-Dec- 31-Mar-16 Project road (Length - Buildcon., 14 Competed on 48.90 Km) (DBL) date 07-Dec- 2015. 1

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Package Name of Project Name of Contract Schedule Construction No. Road and Length Contractor Signing date of Status at the completion end of reporting period Pkg -B Chitrangi-Kasar Madhav 15-Dec- 02-April-16 Project road(Length -39.93 Infra 14 Competed on Km) Projects Ltd. date 20-June- –Chetak 2016. Enterprises Ltd. JV, India (MIPL- CEL) Pkg -C Dabra-Bhitarwar- KNR 15-Dec- 08-Oct-16 Project Harsi road(Length - Constrcution 14 Competed on 62.40 Km) Ltd. –Tomar date 14-Mar- Builder & 2017. Contractors Pvt. Ltd. JV, India (KNR- TBCPL) Pkg -D Ujjain-Makshi Dilip 11-Dec- 15-Mar-16 Project road(Length -36.50 Buildcon., 14 Completed on Km) India (DBL) date 28-Dec- 2015. Pkg -E Hardua-Chakghat Gangotri 14-May - 31-Aug-17 Ongoing road(Length -92.26 Enterprises 15 52.16% of Km) Ltd. India construction (GEL) work completed Pkg -F Persauna-Mahua Montecarlo 01-May- 31-May-17 Project (upto Barkha), Ltd. –Shreeji 15 Completed on road(Length -67.26 Infrastruture date 16-Jan- Km) India Pvt. 2017. Ltd. JV, India (NCL- SIIPL) Pkg -G -Bankuia- Prakash 14-May- 30-Aug-16 Project Samariya. Asphaltings 15 Competed on road(Length -33.41 & Tol date 15-July- Km) Highways 2016. (India) Ltd., India (PATH) Civil Work Contracts Under Package -2 (Jabalpur) (Total Length 375.59 Km) Pkg -H 1. Rani Durgawati Gannon 10-Nov- 01-Sep-17 Project Samadhi Dunkerley & 15 Completed on Road(MDR-36-19) Co. Ltd. date 23-04- (GDCL) 2017. 2. Tilwara- Project Chargaon(DR-36- Completed on 05) date 23-04- 2

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Package Name of Project Name of Contract Schedule Construction No. Road and Length Contractor Signing date of Status at the completion end of reporting period &Gotegaon(MDR- 2017. 41-01) 3. Katni- Project Vijayraghavgarh- Completed on Barhi(MDR-39-01) date 23-04- (Total Length 2017. 118.70 Km ) Pkg -I 1. Bandri- Madhav 06-Nov- 27-May-17 Ongoing Jharuwakheda Infra 15 85.33 % of (MDR-31-32) Projects Ltd. construction India (MIPL) work completed 2.Nirtala-Mandi Ongoing Bamora(MDR-31- 87.09% of 32) construction work completed 3. Damoh- Ongoing Hindoriya- 73.66 % of Patera(MDR-32-12) construction (Total Length 76.23 work Km ) completed Pkg -J 1. Prithvipur-Niwari Madhav 06-Nov- 27-May-17 Ongoing (MDR-35-05) Infra 15 80.99 % of Projects Ltd. construction –M.S. work Khurana completed 2. Ajaygarh-Toriya- Engineering Ongoing Bariyarpur(MDR-33- Ltd. JV, 86.45 % of 05) India (MIPL- construction MSKEL) work completed 3. Palera- Ongoing Baldeogarh MDR- 83.82 % of 35-25) (Total construction Length 84.89 Km ) work completed Pkg -K 1. Sidhi-Tikri (MDR Dilip 3-Aug-15 01-June-17 Project 45-02) Buildcon., Completed on India (DBL) date 20-09- 2016. 2. Kyothi Katra- Project Lalgaon (MDR 43- Completed on 02) date 20-Sep- 2016. 3. Mauganj-Katra Project (MDR-43-04). (Total Completed on 3

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Package Name of Project Name of Contract Schedule Construction No. Road and Length Contractor Signing date of Status at the completion end of reporting period Length 95.77 Km ) date 20-09- 2016. Civil Work Contracts Under Package -3 (Bhopal-2) (Total Length 774.246 Km.) Pkg -L 1. Mohanpur Behat KNR 06-Aug- 20-Dec-17 Ongoing Mau (MDR-01 -01) Construction 2015 70% & Behat Mau Ltd. of construction (MDR-02-03) – (159.82) Km work 51.651 Km completed 2. Murar - Chitora Ongoing (MDR-01 -08) , 47% Murar-Chitora of construction (MDR-02-08) & work Gatha Amayani completed (MDR-02-06)- 45.670 Km 3. Mohana Pohri Ongoing (MDR-07-06) 65% (Length 159.82 Km of construction )- 62.36 Km work completed Pkg -M 1.Pachawali- Path-Wagad 09-Nov- 24-Aug-17 Miscellaneous Rannod(MDR-07- (J.V.) 2015 work pending 10) & Rannod (110.62)Km Project Pichhore (MDR-07- Completed 04)- 60.62 Km 2.Bhasula Miscellaneous Chainpur work pending VijaypurDhanrawad Project (MDR-06-09)- 20 Completed Km 3.Ashoknagar- Miscellaneous Thubon (i/c Kolua work pending Road) (MDR-08- Project 11) – 30 Km Completed Pkg -N 1.Masudanganj KCC 06-Aug- 10-June-17 Project Najeerabad (MDR- Buildcon 2015 Completed on 06-03) Pvt. Ltd. date 10-June- &Najeerabad (98.75)Km 17. Maksudangarh (MDR-23-08)- 31.225 Km 2. Project Najeerabad (MDR- Completed on 23-06)- 30.67 Km date 10-June- 17. 3. Berasia Project

4

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Package Name of Project Name of Contract Schedule Construction No. Road and Length Contractor Signing date of Status at the completion end of reporting period (MDR-23-10) & Completed on Vidisha Berasia date 10-June- (MDR-27-01)- 17. 36.850 Km Pkg -O 1.Dewas Newari Gannon 01-Nov- 03-Dec-17 Ongoing (MDR-10-02)- Dunkerly & 2015 90% 26.775 Km Co. Ltd of construction (129.14) Km work completed 2.Mahidpur Ongoing Panvihar Jeevaji 89% Nagar (MDR-09- of construction 04) – 31.935 Km work completed 3.Shajapur Bercha Ongoing (MDR-11-02)– 91% 16.435 Km of construction work completed 4.Shajapur Dupada Ongoing Kanad Pachlana 87% Pilvas Nalkhed of construction (MDR-11-13)- work 53.990 Km completed Pkg -P 1.Sanver Khipra Ranjeet 07-Aug- 16-June-17 Ongoing (MDR-15-18)- Buildcon 2015 81% 19.619 Km Ltd. (102.71) of construction Km work completed 2.Kanvan Mangod Ongoing (MDR-16-11)- 84% 47.434 Km of construction work completed 3.Mahu Simrol Ongoing (MDR-15-02)- 51% 15.542 Km of construction work completed 4.Depalpur Betama Ongoing (MDR-15-07)- 31%of 20.117 Km construction workcompleted Pkg -Q 1.Sanawad GHV 04-Aug- 21-May-17 Project Khargone (MDR- (INDIA) Pvt. 2015 Completed on 20-01)- 66 Km Ltd. (108.71) 18-May 2017

5

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Package Name of Project Name of Contract Schedule Construction No. Road and Length Contractor Signing date of Status at the completion end of reporting period 2.Rajpur Khetiya Km Project (MDR-22-05)- Completed on 42.18 Km 18-May 2017 Pkg -R 1.Hathnapur Sorathia 02-Aug- 10-Aug-17 Ongoing Anwalighat Velji Ratna 2015 70% Salkanpur (MDR- & Co. of construction 30-19)- 28.180 Km (65.03) Km work completed 2.Tawa Bridge Ongoing Itarasi Mandi 89% (MDR-30-06)- of construction 11.150 Km work completed 3.Itarasi Dulariya Ongoing 65% Tigariya (MDR-30- of construction 04) – 25.700 Km work completed Total Length of all packages-1530.416Km.

7. Details of Supervision Consultants assigned above packages are given below table no.2. Table: 2 Details of Supervision Consultants

Details of Supervision Consultants Date of Package Name Consulting firm Appointment Supervision Consultant for Intercontinental Consultant & 11-Mar-15 package-1 Bhopal-1 Technocrats Pvt. Ltd., India (ICT) AECOM Asia Company Ltd. Hong Supervision Consultant for Kong in Association with Vaishnavi 18-Aug-15 package-2 (Jabalpur) Infratech Services Pvt. Ltd, India (AECOM) Supervision Consultant for Indian Technocrat Ltd., India (ITL) 14-Sept-15 package-3 (Bhopal -2)

8. Changes in project scope: There is a change of scope anticipated during reporting period in Package3/P (Kanwan-Mangod) and package-1/F parsona – Mahua upto Barkha due to change of road length. Updation of ADB approved IEE Reports are in progress after updation the IEE report will be submitted to ADB for review and approval. II. Compliance on Environment Safeguards Requirements: 9. As per ADB Safeguard Policy and prepared Environment Assessment and Review Framework (EARF), compliance of environment safeguard status has been evaluated in two sections given as under:

6

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

(A) Status of Compliance with National /State/ Local government statutory environmental requirements:

10. MPRDC has obtained permissions required for working in the forest area. Permission for cutting trees are also obtained by MPRDC, where tree cutting is unavoidable. MPRDC and supervision consultants have regularly asked civil work contractors to obtain all the permission required under the existing statuary environmental regulations and submit the complete details regarding the status of clearances/approvals/ consents applied for/obtained. Supervision consultants are also regularly monitoring and periodically writing to contractors to obtain statuary clearances/consents for Quarry sites from Mining Departments/SEIAA/DEIAA. Contractors are also continually reminded about pending Consent to establish and operate Crusher, Batching plant, Hot mix plant, DG set and WMM plants etc. at their respective sites from State Pollution Control Board.Contractors who have not yet obtained SEIAA/DEIAA clearance for quarry/borrow area advised to obtained & submit the clearance at the earliest. 11. In the Package-1, Bhopal-1, construction of Package- A,B,C,D,F and G has completed till the month of June 2017. The contractors of Package-B and D has been obtained all the applicable NOCs/Permissions and Contractor of Package C, E, and F has obtained all the required statuary permissions, borrow area SEIAA/DEIAA clearance either obtained from concerned DEIAA Committee or material is being outsourced from valid source. Permission for borrow earth is also granted from concern district collector (mining). Contractor of package-E is advised to meet compliance as per EMP and other contractual provisions. Package wise status (obtained/pending clearances/consents) of “Compliance with Environmental Regulations” is detailed in Annexure- I (a). 12. There are four packages in Package-2, Jabalpur (H, I, J and K) comprising 12 roads. The contractor of Package-K has completed civil construction works in month September 2016 and Package-H has completed civil construction works in month April 2017. The status of “Compliance with Environmental Regulations” of Package- 2, Jabalpur is detailed in Annexure- I (b). 13. There are seven packages in Package-3, Bhopal-2, comprising 22 roads. All the Applicable permissions/ compliances/ NOCs/clearances are obtained by contractors of Pkg. L,M,N,O,P,Q and R. Contractors of all the packages were instructed to start the plantation before commence of monsoon period. Package wise status (obtained/pending clearances/consents) of “Compliance with Environmental Regulations” of Package-3, Bhopal-2 is detailed in Annexure- I(c).

B) Status of environmental compliance with ADB loan covenants as stipulated in the Loan Agreement given in Table -3

Table: 3 Status of Environmental Compliance with ADB loan covenants S. No Particulars Remarks 1 Environment The Borrower shall ensure or cause the EA to ensure that the preparation, design construction, implementation, operation and decommissioning of the Project facility comply with- (i) All applicable laws and regulations of the All Permissions required under borrower and the State relating to existing environmental statuary

7

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Environment, health and safety. have been/are being obtained. (ii) The Environmental Safeguards Ongoing (iii) All measures and requirements set forth Being Implemented, the EARF, respective IEE and the EMP, Depending on the findings of and any corrective or preventative actions feasibility study and detailed set forth in a Safeguards Monitoring project report (DPR) EARF has Report been prepared to guide the implementation of all safeguards requirements in accordance with relevant policies and regulations of the Government of India, state government of Madhya Pradesh and the ADB Safeguard Policy statement 2009 (SPS). 2 Human and Financial Resources to Implement Safeguards Requirements (a) The Borrower shall make available or cause Budgetary provision for the EA to make available all necessary budgetary Implementation of EMP and and human resources to fully implement the EMP, Environment Monitoring Plan is the RP and the IPP as required. included in construction contract civil cost of contract agreement. (b) The EA shall designate at latest one expert MPRDC Environment Social each to supervise implementation of the EMP and Cell, PIU designated person RP if any. and supervision consultant are supervising EMP implementation. 3 Safeguard – Related provisions in Bidding Documents and Works Contract :- The Borrower shall ensure or cause the EA to ensure that all bidding documents and contracts for Works contain provisions that require contractors to : (a) Comply with the measures and requirement Safeguard related provisions relevant to the Contractor set forth in IEE, the included in project bid EMP, and the RP and the IPP as applicable (to documents and EMP is part of extent they concern Impacts on affected people contract document. during construction), and any corrective or preventative actions set out in a Safeguards Monitoring Report; (b) Make available a budget for all such Budgetary provision provided environmental and social measures; in Environment Monitoring Plan as a part of contract document. (c) Provide MPRDC with a written notice of any No such impacts observed unanticipated environmental, resettlement or during this reporting period. indigenous people risks if any, or impacts that arise during construction, implementation or operation of the project that were not considered in the IEE, the EMP and the RP or the IPP if any; 8

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

(d)adequately record the condition of roads, land Being followed. and other infrastructure prior to starting to transport materials and constructions and; (e) Fully reinstate pathways, other local infrastructure, and agricultural land to at least their pre-project condition upon the completion of construction. 4 Safeguards Monitoring and Reporting The Borrower shall do or causes the EA to do the following: (a) Submit semi-annual Safeguards Monitoring Environment monitoring Reports to ADB and disclose relevant information reportssubmitted for the period from such reports to affected persons promptly of April to December upon submission; 2015,January to June 2016 and July to December 2016. This Environment monitoring report is prepared for the period of January to June 2017 (b) If any unanticipated environmental and/or There is no such impact raised social risk and impacts arise during construction, during this reporting period. implementation or operation of the project that were not considered in the IEE, the EMP, and the RP or the IPP as applicable, promptly inform ADB of the corrective action plan; and (c) Report any breach of compliance with the There is nobreach of measures the requirements set forth in the EARF, provisions / compliances were IEE the RF, RP and the IPPF, IPP (if any), raised / reported during this promptly after becoming aware of the breach. reporting period. 5 Labor Standards The Borrower, State and MPRDC shall ensure Being implemented that works contracts under the Project follow all applicable labor laws of the Borrower and the State and that these further include provisions to the effect that Contractors; (i) Carryout HIV/AIDS awareness programs for The provisions related to labor and disseminate information at worksites on HIV/AIDS awareness risk of sexually transmitted diseases and programme for labor/ HIV/AIDS as part of health and safety measures construction crew, equal pay for those employed during construction; and for equal work, non- (ii) Follow and implement all statutory provisions employment of child labor, on labor (including not employing or using health/safety of worker etc. children and labor, equal pay for equal work), have been made in work health safety, welfare, sanitation, and working contract. If any lacuna / conditions. Such contracts shall also include shortcoming is observed in clauses for termination in case of any breach of implementation of same by the stated provisions by the Contractors. contactors then contractors are advised to take corrective action promptly 6 Communications and Participation The EA shall ensure that the Projects is Being followed. undertaken in conformity with the Communication 9

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Strategy as agreed between ADB, the Borrower, the State and MPRDC and referred in the PAM. 7 Governance and Anticorruption The Borrower, State and MPRDC shall comply The existing MPRDC with ADB’s Anticorruption policy (1998, as grievance redresal mechanism amended to date) and is being used to receive and resolve complaints/grievances and following ADB anticorruption policy.

III. Implementation of Environment Management Plan:

14. The IEE duly showed that the environmental impact would mostly occur during construction due to clearing for widening the carriageway, construction work related to compaction of the embankment and cut and fill, as well as the quarrying and borrowing to support construction activity. The overall environment categorization for the all roads of projects was categorised as category B, which were not expected to have adverse environmental impacts as shown in the findings of the initial environmental examination (IEE). During implementation, MPRDC implemented the overall mitigation measures, Environmental and Social Cell of MPRDC was responsible for monitoring of EMP implementation. MPRDC and Civil works contractors obtained all permissions required from related government agencies according to the applicable statutory environmental regulations to enable them to carry out without abiding country rules and regulations. MPRDC through its environmental expert and environmental specialist of supervision consultants closely monitors the implementation of environmental issues of all packages. Regular site visits and review meetings are being held with the nominated Environmental Officers of Contractor’s staff of each project site. In addition to this, for effective day to day supervision of implementation of environmental aspects, the supervision consultants have designated their existing site staff (site engineer) to look after these aspects. The contractors have appointed Accident prevention officer (APO) at their construction sites. Contractors, who have yet to appoint the APO, are advised to designate safety officer for the respective contracts. Structure of Institutional setup to monitor EMP implementation on each project is being shown below:-

10

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

11

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

15. The supervision consultants submit Monthly and Quarterly progress report to MPRDC that includes information on implementation of environmental issues. The environmental information captured in these reports includes environmental monitoring status of construction sites, pollution control measure being adopted, and measures for workers safety at construction site and camp site, safety of road user/public etc. Copy of permission/NOCs/Consent obtained during reporting period and site EMP implementation photographs also supplements with these reports. The Supervision Consultants have assessed the implementation of EMMP during the reporting period is satisfactory. However, use of personal protective equipment (PPEs) by the construction workers, safety arrangements, and construction zone traffic safety management of Package-E, M and O are required further up-gradation. Some of the photographs showing EMP implementation on site are provided in Annexure-II.

16. HIV/AIDS awareness and health checking campaign organised with the aim to reduce transmission risk of HIV infection among the construction workers and population living along the project roads. Awareness campaigns were conducted by the contractors of Package-1, Bhopal-1 on package-E. Contractors of Package-2, Jabalpur, pkg-H, I, and J conducted AIDS awareness campaign during reporting period. Contractors of Package-3, Bhopal-2 also organised such programmes at their respective construction sites through designated agencies. Dates and location of conducted HIV/AIDS awareness program are listed in below given table-4 and photographs of campaigns are provided in Annexure-II.

Table: 4 Details of AIDS Awareness Health Check-up Programs conducted at Project Sites

Package and Road Date of awareness program and Location Name Package-1, Bhopal-1 Package-E (Hardua- 14/06/2017, at Contractor’s construction camp Chackghat) Packages-2, Jabalpur Package –H Rani Durgawati Samadhi 14/03/2017, Construction Camp, Mageli Road 14/03/2017, Construction Camp Tilwara- Chargaon(DR- 36-5) & Gotegaon(MDR- 18/03/2017, Construction Camp Gram Katni 41-01), Katni- Vijayraghavgarh- Barhi(MDR-39-01) Package -I Bandri-Jharukheda(MDR- 18/04/2017, Construction Camp Gram Bisraha 31-32) Nirtala-Mandi Bamora(MDR-31-32) Damoh-Hindoriya- Patera(MDR-32-12) Package -J Prithvipur-Niwari (MDR- 07/03/2017 & 07/06/2017, Construction Camp Gram Jer 35-05) 07/03/2017 & 04/06/2017, Construction Camp Gram Sinhai 12

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Package and Road Date of awareness program and Location Name Ajaygarh-Toriya- Bariyarpur(MDR-33-05) 07/03/2017 & 07/06/2017, Construction Camp Gram Kasa

Palera-Baldeogarh MDR- 35-25) Package-3, Bhopal-2 Package-L Mohanpur-Behat-Mau 20/05/2017 at Village-Sora, Tehsil-Gohad, District-Bhind Road. 24/05/2017 at Village-Magrouni, Tehsil-Bairad, District- Shivpuri Mohana-Pohri Road Package-M Pachawali-Rannod- 02/03/2017 at Village-Hurry, Tehsil-, Pichhore Road District-Shivpuri 11/04/2017 atVillage-Rajebmora, Tehsil-Shadoura, Ashoknagar-Thubon Road District-Ashok Nagar 21/05/2017 at Village Balabhet Guna, village Balabhet Bhasula Chainpur Raghogarh Distt Guna. Vijaypur Dharnawad Road Package-N Berasia Najeerabad Road 24/04/2017 at Village& Post-Runaha, District-Bhopal Package-O Dewas Newari Road 05/05/17 at Dhamanda Village at chainage km. 11.500.

Shajapur-Dupada-Kanad- 10/05/2017 at Village-Dupara,Tehsil-Mohan Badodia, Pachlana Pilvas-Nalkheda District-Shajapur. Road 28/03/2017 at Mahidpur Panvihar Road Project Camp Mahidpur-Panvihar-jivaji Tajpur. Nagar Road Package-P Sanwer-Kshipra Road. 28/04/2017 at Village-Keshripura, Tehsil-Sanwer, District- . Kanwan-Mangod Road 10/05/2017 at Near Village-Khileri, Tehsil-Sardarpur, District-Dhar. Depalpur Betama Road 12/05/2017 at Village Rangwasa, Depalpur Betma Road Indore Package-Q Sanawad-Khargone Road 19/03/2017 at Village-Jamnya, Tehsil-Bhikhangoan, District-Khargone. Rajpur-Khetia Road 20/03/2017 at Village-Palsood, Tehsil-Rajpur, District- Barwan. Package-R Itarsi-Dolariya-Tigariya 23/06/2017 at Village-Temlakala, Tehsil-Dularia, District- Road Hoshangabad

17. Public consultations were held at several locations during the site visit of Social Safeguard and Environmental Specialist of supervision consultant for ongoing contract package-E and Completed package-G of Package-1, Bhopal-1. Supervision consultant has gathered the participant’s views with regards to all 13

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

aspects of environment, social, health and safety which may have direct or indirect impact. Public consultant conducted on pkg H,I and J under Package-2 Jabalpur project. Construction packages of Pacakge-3, Bhopal-2 (pkg-L to R) conducted public consultation in all packages during this reporting period. Issues / problems raised in all the consultation are being addressed with appropriate feasible manner by the project authorities. Summary of public consultation conducted in reporting period are provided in table-5 and some photographs of public consultations are given in Annexure-II. The complaint handling system has been established at each construction site for effective and timely redressal of public grievances. During implantation, MPRDC didn’t receive any compliant from the public. The Supervision Consultants and contractors also not received any complaint from the public during this reporting period i.e. from January to June 2017.

14

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Table: 5 - Details of Public Consultations Conducted during Reporting Period (Pkg-1, Bhopal-1) S.No. Pkg and Name of Date Location / Chainage No. of Issues Discussed / remedy suggested Project Road Participa nts 1 Pkg-E (Hardua- 13/060/2017 1.Boliya Ghati (Ch.18.530) 17 < Shifting of Hand pumps at appropriate locations; (will Chakghat) be sifted as per BOQ provision and actual site survey). 2. Kureli (Ch.23.300)

S.No. Pkg and Name of Date Location / Chainage No. of Issues Discussed / remedy suggested Project Road Participa nts Mohna-Pohri Road Camp Magroni 17 living standards; 22/04/2017 < For road safety measures, there is requirement of rumble strips in settlement areas/ market areas to avoid the accidents;(project road will be developed following with IRC safety codes). < Shifting of Hand pumps at appropriate locations; (will be sifted as per BOQ provision and actual site survey). 9 Package-M 21 < For road safety measures, there is requirement of Pacchawali- 15/03/2017 Rajapur rumble strips in settlement areas/ market areas to avoid Rannod- Picchore the accidents;(project road will be developed following Road with IRC safety codes). Ashoknagar- 15 < The majority of the people have appreciated the 16/03/2017 Rajebamora Thubon Road project road construction work;

rumble strips in settlement areas/ market areas to avoid the accidents;(project road will be developed following with IRC safety codes). < Maintain proper slope and speed breakers. 11 Pkg-O

16

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

S.No. Pkg and Name of Date Location / Chainage No. of Issues Discussed / remedy suggested Project Road Participa nts Road) culverts as water flows above head level during monsoon. 12 Pkg-P 19/03/2017 Village Khiledi 15

17

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND IV. Approach and Methodology engaged for environmental monitoring of the project.

18. The Supervision Consultant instructed the civil work contractors to ensure the monitoring of ambient air quality, water quality and noise level as per the agreed monitoring plans.The sampling location for these components have been identified based on environmental sensitive locations like school, hospital, construction sites, pollution sources, discharge points, camp sites, forest area (If any) etc. The details on environmental components, parameters, methodology, duration of monitoring and instruments are described in following table-6.

Table: 6 ADB Approved environmental monitoring plan

Env. Parameters Method of Monitoring Duration/Fr Instrument Component ( As given in IEE) equency of used Monitoring

Air PM2.5, PM10, SO2, High volume sampler to be 24 hrs/ 8 hrs High NOX, CO. located 50 m from the for CO. volume plant in the downwind thrice in a sampler direction. Use method year specified by CPCB for analysis

Water PH, BOD, COD, Grab sample collected Random - TDS, TSS, DO, from source and analyzed sample Total coliform, as per Standard Methods thrice in a Conductivity, Oil & for Examination of Water year. Grease. and Wastewater Noise Equivalent Noise By using Noise meter 24 hrs. Noise Meter levels on dB (A) Thrice in a scale for day and year. night

V. Environmental Monitoring (e.g. ambient air, surface water, ground water and Noise) status and findings:

19. The contractors hired the services of environmental monitoring laboratories, accredited by NABL/MoEF/SPCB, to monitor air, water and noise parameters. The contract package wise monitoring details are provided in table-7. 20. During this reporting period, monitoring of components such as ambient air quality, water quality and noise level was carried out by the civil work contractors. Contractors of Package-1, Bhopal-1, Package-C and E conducted environmental monitoring in the month of May at their project road. Rest of Packages of Bhopal-1 pkg-A,B,D,F and G have been completed.Contractors of Package-2, Jabalpur,Package-(H,I and J)conducted environmental monitoring in the month of January, February & May at their project road.All civil work contractors of Package-3, Bhopal-2 of packages (L,M,N,O,P,Q and R) have conducted environmental monitoring during reporting period. Pkg-L in the month of February and May 17, Pkg-M in the month of Feb-17, Pkg-N in the month of March and June 2017, Pkg-O in the month of March-17, Pkg-P in the month of June-17, Pkg-Q in the month of May-17 and Pkg-R in the month of February-17.

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND Table: 7 Status of Environmental Monitoring during Reporting Period (Package-1, Bhopal-1) Package Monitoring Parameter Month Remarks/Observations Location

Package- Air and Noise Air- PM10, May 2017 PM-10 and PM-2.5 at C Sampling :- PM2.5,SO2, NOX, CO Bhitarwar, Narwar and 1. Dabra, 1+650 Magroni locations exceeded the permissible limit due to 2. Bhitarwar, traffic congestion in market 27+950 Noise:- 24 hours area, this is not due to monitoring, Leq (Day), construction activity of 3. Narwar, 64+140. Leq (Night) project road as project is completed in march 2017 4. Magroni, 56+100 and road is in operation stage.All others parameters Water Sampling:- Water:- Parameter (Air, Water, Noise) are within Ground water for drinking water as their permissible limit. collected from Bore per IS:10500, well at – pH, Turbidity, TDS, 1. Dabra, 1+650 TSS, Alkalinity, Total Hardness, 2. Bhitarwar, Chloride, Sulphate, 27+950 Sodium, Phosphate, Silica 3. Narwar, 64+140. Iron, Total Coliform, etc.

Pkg-E Air Sampling :- Air- PM10, May 2017 All the Parameters (Air, 1. Km-52.760 PM2.5,SO2, NOX, CO Water, Noise) are found 2. Km-52.760 within their permissible limit. 3. Km-32.870 4. Km-34.828 5. Km-36+730 6. Km-45+210 7. Km-24+960 Noise Sampling :- 1. 34+828, (slab Noise:- 24 hours culvert construction monitoring, Leq (Day), site) Leq (Night) 2. 34+870, (slab culvert construction site) 3. Km-37+150 4. Km-52+060 5. Km-24+960 6. Km-46+190 7. Km-54+430

Water Sampling:- Water:- Parameter Ground water for drinking water as collected from Bore per IS:10500, well at Crusher site pH, Turbidity, 23+560. TDS, TSS, Total Hardness, Sulphate, Sodium, Potassium, 19

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND Package Monitoring Parameter Month Remarks/Observations Location Chloride, Nitrates, Phosphate, COD, DO, BOD, and Total Coliform etc.

(Package-2, Jabalpur)

Package- Noise Sampling:- Air- PM10, February All the Parameters (Air, H 1. Village Dokariya PM2.5,SO2, NOX, CO 2017 Water, Noise) are found 2. Near Plant Site within their permissible limit. 3. Village Noise:- 24 hours Manegaon monitoring, Leq (Day), 4. Near Plant Site Leq (Night)

Water:- Parameter Air Sampling : for drinking water as Village Dokariya per IS:10500, Village Manegaon pH, Turbidity, TDS, TSS, Total Hardness, COD, Water Sampling:- BOD, Oil and Ground water Grease, Total Dokariya Coliform (MPN Manegaon Count). Kanchanpuri

Soil Sampling:- 1. Village Dokariya 2. Village Manegaon Package-J Air Sampling:- Air- PM10, PM2.5, May 2017 All the Parameters (Air, 1. Kulua SO2, NOX, CO Water, Noise) are found 2. rathvipur(Plant) within their permissible limit. 3. Banhari Kalan Noise:- 24 hours 4. Ajaygarh (Camp) monitoring, Leq 5. Phuter (Day), Leq (Night) 6. Baldevgarh (Plant) Water:- Parameter Noise Sampling:- pH, Acidity, 1. Kulua Alkalinity, Organic 2. Prathvipur solid, Inorganic (Plant) solid, Chloride, 3. Banhari Kalan Sulphate, 4. Ajaygarh (Camp) Suspended Material. 5. Phuter 6. Baldevgarh (Plant)

Water Sampling:- 1. Kulua 2. rathvipur(Plant)

20

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND Package Monitoring Parameter Month Remarks/Observations Location 3. Banhari Kalan 4. Ajaygarh (Camp) 5. Phuter 6. Baldevgarh (Plant) 7. Lohara

Package-I Air Sampling:- Air- PM10, January 17 All the Parameters (Air, 1. Moodra PM2.5,SO2, NOX, CO Water, Noise) are found 2. Pithoria within their permissible limit. 3. Bandri Noise:- 24 hours 4. Mandi Bamora monitoring, Leq (Day), 5. Dhansara Leq (Night) 6. Nirtala 7. Near Plant Site Water:- Parameter 8. Lohara for drinking water as 9. Hindoriya per IS:10500, 10. Patera pH, Turbidity, TDS, TSS, Total Noise Sampling:- Hardness, COD, 1. Mandi Bamora BOD, Oil and 2. Dhansara Grease, Total 3. Nirtala Coliform (MPN 4. Plant Site Count). 5. Moodra 6. Pithoria 7. Bandri 8. Lohara 9. Hindoriya 10. Patera Water Sampling:- 1. Mandi Bamora 2. Dhansara 3. Nirtala 4. Chopra 5. Moodra 6. Pithoria 7. Bandri 8. Lohara 9. Hindoriya 10. Patera Surface Water Sampling:- 1. Bina Dhansan River (Package-3, Bhopal-2)

Package Air Sampling Air-PM10, PM2.5, Feb- 2017 All the parameters (Air,

L 1. Gram Jiganiya SO2, NOx, CO May- 2017 Water and Noise) are within Site: Sora Camp. their permissible limit. 2. Murar Chittora Ch. 25+000 21

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND Package Monitoring Parameter Month Remarks/Observations Location 3.Gatha Amayan Ch. 10+500. 4. Mohana. 5. Pohri 6. Magroni Camp Noise Sampling Noise-24 hourly 1. Gram Jigniya noise levels, Leq 2.Murar Chittora, (Day) & Leq (Night). Ch.20+490. 3.Gatha Amayan Ch.05+450 5.Mohana Pohri. 6.Pohri. 7.Magroni. Water-pH, Water Sampling: Turbidity,Total 1.Gram Jiganiya Dissolved Solid, location Gatha Total Suspended Amayan Ch. Solid, Total 11+500. Alkalinity, Chemical 2.Gram Jiganiya, Oxygen Demand, Location Murar Biological Oxygen Chitora. Ch.25+400 Demand, Total 3.Gram Jigania, Hardness, Chloride, Location Jigania. Sulphate, Sodium, 4.Magroni. Phosphate, Silica, Iron, Total Coliform

Package- Air Sampling Air-PM10, PM2.5, Feb- 2017 All the parameters (Air,

M 1.Tehsil Shasora SO2, NOx Water and Noise) are within Ashoknagar (Near their permissible limit. Plant Area). 2.Tehsil Khaniadhana Shivpuri. (Near Plant Area).

Noise Sampling Noise-24 hourly 1.Tehsil Shasora Noise levels, Leq Ashoknagar (Near (Day) & Leq (Night). Plant Area). 2.Thesil Khaniadhana, Shivpuri (Near Plant Area).

Water Sampling: Water-pH, 1.Tehsil Shasora Conductivity, Ashoknagar. Turbidity, Total 22

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND Package Monitoring Parameter Month Remarks/Observations Location 2.Tehsil Dissolved Solid, Khaniadhana, Total Alkalinity, Shivpuri (Bore Total Hardness, well). Chloride, Sulphate, Calcium, Magnesium, Potassium, Sodium, Phosphate, Nitrates, Iron Package- Air Sampling March- 2017 All the parameters (Air, Air-PM10, PM2.5, N 1.Near Berasia June- 2017 Water and Noise) are within SO2, and NO2 Town Ch. 39+000 their permissible limit 2.Near Batching and WMM plant Ch. 61+000 3.Near Najeerabad Ch. 69+500 Water Sampling 1.Near Ruhana. Water- pH, Vidisha-Berasia- Conductivity, Najeerabad Road Turbidity, Total Ch. 61+000 near Alkalinity, Total WMM and Batching Hardness CaCo3, Plant Total Hardness MgSo4, Ca, Mg, SO4, Chloride, Sulphate, Iron (Fe), Nitrate (NO3), Fluoride Phosphate, Cu, Mn, Cr+, Phosphate.

Noise Sampling Noise-24 hourly 1.Near Berasia Noise levels, Leq Town Ch. 39+000 (Day) & Leq (Night). 2.Near Batching and WMM plant Ch. 61+000 3.Near Najeerabad Ch. 69+500

Package- Air Sampling Air-PM10, PM2.5, Mar- 2017 All the parameters (Air,

O 1.RMC Plant- SO2, and NO2& HC Water and Noise) are within Barkheda Distt their permissible limit Dewas Ch. 11+000_RHS. 23

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND Package Monitoring Parameter Month Remarks/Observations Location 2. Tehsil Tarana Water pH, turbidity, Camp Tajpur near Total Dissolve Admn. Building. Solids, Total 3. Dupada Ch. Suspended Solids, 22+000_LHS Total Hardness Water Sampling CaCO3, Chemical 1.RMC Plant- Oxygen Demand, Barkheda Distt Biochemical Oxygen Dewas Ch. Demand, Oil & 11+000_RHS. Grease and Total (River Water Coliform. Jamarahar River). 2. Tahsil Tarana Camp Tajpur (Bore

Well Water).

3. R.M.C. Plant Dupada Ch. 22+000_LHS Noise-24 hourly Noise Sampling Noise levels, Leq 1.Near RMC Plant (Day) & Leq (Night). Dupada 2.Ch.22+000 LHS. Near Admn. Building. 3. Near R.M.C. Plant. 4. Near Admn. Building.

Package- Air Sampling Air-PM10, PM2.5, June-2017 All the parameters (Air,

P 1.Village Sanwer, SO2,, CO and NOx Water and Noise) are within

Sanwer Khsipra their permissible limit

Road 2.Village Khiledi- Inside of Camp. Kanwan Mangod Road. 3.Village Ambachandan, Mhow Simrol Road. 4.Village

Rangwasa,

Depalpur Betama Road.

Noise Sampling 1.Village Sanwer, Noise-24 hourly 24

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND Package Monitoring Parameter Month Remarks/Observations Location Sanwer Khsipra Noise levels, Leq Road. (Day) & Leq (Night). 2.Village Khiledi- Kanwan Mangod Road. 3.Village Ambachandan, Mhow Simrol Road. 4.Village Rangwasa, Depalpur Betama Road. Water Sampling 1. RO water Village Water- Colour, Sanwer, Sanwer Odour, Taste, pH, Khsipra Road. Turbidity, Total 2.Village Khiledi- Dissolved Solids, Inside of Camp. Total Hardness, Kanwan Mangod Iron, Chloride, Free Road. Residual Chlorine, 3.Village Calcium, Ambachandan, Magnesium, Mhow Simrol Road Sulphate, Nitrate, (Bore Well Water). Mineral Oil, Total 4. RO water, Village Alkalinity, Total Rangwasa, Coliform Bacteria. Depalpur Betama Road. Package Air Sampling Air-PM ,PM , SO May- 2017 10 2.5 2 All the parameters (Air, Q 1.Sanawad and NO x Water and Noise) except Khargone Camp PM are within permissible No-1 (Crusher 10 limit. Contractor has been Site). recommended to increase 2.Rajpur Khetia the frequency of water Camp No-2 sprinkling at Construction (Crusher Site). site. Noise Sampling 1.Sanawad Noise-24 hourly Khargone Camp Noise levels, Leq No-1 (Day) & Leq (Night). 2. Rajpur Khetia Camp No-2 Water- pH, Color, (Crusher Site). Odor Water Sampling Turbidity, Total 1.Sanawad Dissolved Solids, Total Alkalinity, 25

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND Package Monitoring Parameter Month Remarks/Observations Location Khargone Camp Total Hardness, Ca, No-1 (Tanker Mg, Chlorides, Water) Sulphate, Fluoride, 2. Rajpur Khetia Nitrate, Camp No-2 (Tanker Arsenic, Lead, Mn, Water) Zn, Total Chromium, Cu, Fe, Total Coliform, E. coli

Package- Air Sampling Feb- 2017 All the parameters (Air, R 1.Gondi Kharar Air-PM10, PM2.5, Water and Noise) are within Camp, Dolariya SO2, NOx, and HC. their permissible limit Tehsil Hoshangabad pH, Turbidity, Total Water Sampling Dissolved Solids, 1. RO (Gondi Total Suspended Kharar, Dolariya Solids, Total Tehsil Hardness, COD, Hoshangabad) BOD, Oil & Grease, Noise Sampling Total coliform. 1. Inside of Camp Noise-24 hourly Noise levels, Leq Area Gondi Kharar, (Day) & Leq (Night). Dolariya Tehsil

Hoshangabad. 2. Village Ch. 23+000.

21. The environmental monitoring was carried out on parameters of ambient air quality, noise and water quality. The whole process generated lots of data. To briefly represent the data, the highest values of recent monitoring reports are being shown in table, 8, 9, 10 and 11.

Table: 8 Ambient Air Quality Monitoring results.

Pkg-1 Bhopal-1 3 3 3 3 Parameters PM10(µg/m ) PM2.5(µg/m ) SO2(µg/m ) NO2(µg/m ) CO Package (mg/m3) C 289 115 14.8 27.23 0.71 E 90 59 8.4 17.8 0.455 Pkg-2 Jabalpur H 81.42 30.42 44.71 32.10 - I 66.4 42.4 22.6 26.2 <1 J 48.2 22.6 20.6 26.4 <1 Pkg-3 Bhopal-2 L 84.2 28.3 12.5 25.56 0.560 M 96.5 54 13.92 31.26 - N 84.2 24.94 10.65 28.78 0.850 O 89.85 33.10 12.44 15.33 BDL 26

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND P 94.78 54.26 24.80 38.14 1.43 Q 98.0 48.0 16.6 36.2 - R 88.25 46.78 17.38 25.26 1.18 Standard 100 60 80 80 4 (NAAQS)

Table: 9 Ambient Noise Level Monitoring results. Pkg-1 Bhopal-1 Parameters Day Night Package C 74.2 72.2 E 70.6 55.0 Pkg-2 Jabalpur H 67.6 59.5 I 62.5 47.2 J 53.2 38.4 Pkg-3 Bhopal-2 L 72.9 60.09 M 70.6 60.3 N 65.28 46.15 O 72.1 67.4 P 63.6 54.3 Q 73.2 68.5 R 62.20 46.10 Prescribed Standards dB(A) 75 70

Table: 10 Ground Water Quality Test Results.

Pkg-1 Bhopal-1 Parameters pH TDS TSS DO BOD COD Conduc Total Oil and tivity Coliform Grease Package C 7.74 422 - 3.24 <1 1.2 - 4.8 - E 7.38 576 <1.0 3.8 BDL BDL 960 Absent Pkg-2 Jabalpur H 8.62 1104 56 - 15 47 - 6.0 0.45 Pkg-3 Bhopal-2 L 7.15 440 22 2.2 0.89 7 - <2 - N 7.02 475 43 2.5 06 21 604.30 Absent Nil O 7.52 1841 63 - 08 36 - Absent BDL Desirable 6.5-8.5 500 - - - - - Absent - Limit Permissible No 2000 - - - - - 10 - Limit relaxati on Prescribed Standard (Requirement as per IS-10500-2012)

27

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

VI. Any other environmental aspects, impacts observed during implementation which was not covered earlier.

22. There is no such environmental aspect, which was not covered earlier.

VIII. Details of Redress Committee and complaints received from public and actions taken thereof to resolve.

23. The GRC (Grievance Redress Committee) for both State (MPRDC) and Divisional level (PIU) have been constituted for each road packages. In addition, a register of grievances is also placed in construction camp to register people’s grievances, but none of the grievances were received till the end of reporting period neither in the PIU nor the Construction camp.

IX. Follow-up actions and conclusions

24. The Contractors of all packages has been advised to make compliance as per EMP and other contractual provisions. The contractors are continuously reminded to take care of environmental issues emerging by execution of project and strictly adhere to the provisions of EMP and FIDIC (conditions of contract for construction)to minimize negative impact on surroundings. EMP compliance status of all construction packages are satisfactory, though Construction zone safety, construction camp management and rehabilitation and restoration activity after completions of project arethose areas which needs more attention. Contractor of Package-A, F, G, L, M, N, O, P, Q and R has been advised to complete plantation activity along the project road as construction of these projects has been already completed.The contractors are advised to obtain NOCs/Permissions those are still pending or applied. Contractors advised to conduct air, water and noise monitoring at their packages as per agreed monitoring plan. All contactors have been advised for timely renewal of labour license, consents/NOCs/Permissions which are nearing expiry date. Contractors who have not yet obtained DEIAA clearances for quarry / borrow area for the extraction of natural resources advised to obtained & submit the clearance at the earliest.

28

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (a)’ MPDCSP PACKAGE-1, BHOPAL-1 Status of Compliance with Environment Regulations (January – June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor Env. cutting as Diesel Clearance per IEE / Forest Batching Hot Mix Pollution Crusher WMM Plant Generator Permission Name of the for the actual Clearance/ Plant Plant Under S. No. (Ref (Ref Set obtained from Sub-Project Project trees felled Tree cutting (Ref (Ref Control other / Pkg. Agreement Agreement (Ref Road from (As per EMP Agreement Agreement (PUC) regulators clause No- Clause- Agreement certificates MoEF/ and Agreement) Sub-clause Sub-clause (RefAgreement 4.18) 111.16) Sub-clause for vehicle SEIAA No-111.15) No-111.15) Clause-4.18) No-111.15) Pkg-A Mahua-Chuwai As per Six Permission of Consent to Consent to Consent to Consent to Consent to PUC Labor license: MoEF numbers of work in forest establish operate operate operate operate certificates Issued by Agreement amendme trees to be area under Sidhi and operate obtained from obtained obtained obtained obtained for district labor Signed date nt in EIA fell as per district DFO is obtained pollution from from from 40 vehicles officer Sidhi 11.12.2014 notification IEE report issued vide from control board pollution pollution pollution valid upto- district, on date 2006, EC letter no. 4307 pollution vide- control control control board 26/1/2016. 25/04/2015 Commenceme is not dated control Consent No- board vide- board vide- under air act vide license no. nt date- required. 24/06/202015. board vide- 1268/RO/MP Consent No- Consent 1981, vide 47585, valid 01.01.2015 Trees Consent No- PCB/TECH/E 1087/RO/MP No- consent no- upto 31-12- cutting is Permission of 1088/RO/MP /2015 Rewa, PCB/TECH/ 1265/RO/M 1092/RO/M/ 2015. Work Contracter- not required work in forest PCB/TECH/ dated E/2015 PPCB/TEC PPCB/TEC/ completed thus Dilip Buldcon as per site area under E/2015 10/08/2015, Rewa, date H/E/2015 H/E/2015 renewal of survey, Singrauli district Rewa, date Under Water 10/07/2015V Rewa, date Rewa, date labour license Length- Existing DFO issued vide 10/07/2015V act 1974. alid upto 10/08/2015, 10/07/2015. is not required. 48.900km. trees have letter no.1835, alid upto Valid upto 09/07/2016. Under DG Set no. Blasting been dated 09/07/2016. 09/08/2016. Capacity- Water act 78-500 KVA. Permission – Construction saved. Tree 04/07/2015. Capacity- Capacity- 48000 1974. Valid and DG Set Receivedby Period-15 on unpaved 48000 40000 M.T./Year upto no. 41-180 person involve months shoulders M.T./Year M.T./Year 09/08/2016. KVA. Valid in blasting and beyond Capacity- upto 09-07- certificate no. Completed on edge of Consent to 40000 2016. BR/SEZ/0012 date- shoulders operate M.T./Year dated 07/12/2015. have not obtained from 15/09/2011. been pollution Authorization Sand Source removed. control board Consent to obtained and Water vide- operate under source: Consent No- obtained Hazardous Sand and water 1267/RO/MP from Waste purchased from PCB/TECH/E pollution (Manageme local vendors. /2015 Rewa, control nt, Handling Sand dated board vide- and Trans- purchased with 10/08/2015. Consent Boundary valid transit Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (a)’ MPDCSP PACKAGE-1, BHOPAL-1 Status of Compliance with Environment Regulations (January – June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor Env. cutting as Diesel Clearance per IEE / Forest Batching Hot Mix Pollution Crusher WMM Plant Generator Permission Name of the for the actual Clearance/ Plant Plant Under S. No. (Ref (Ref Set obtained from Sub-Project Project trees felled Tree cutting (Ref (Ref Control other / Pkg. Agreement Agreement (Ref Road from (As per EMP Agreement Agreement (PUC) regulators clause No- Clause- Agreement certificates MoEF/ and Agreement) Sub-clause Sub-clause (RefAgreement 4.18) 111.16) Sub-clause for vehicle SEIAA No-111.15) No-111.15) Clause-4.18) No-111.15) Under Air act No- Management passes. 1981, Valid 1267/RO/M ) Rules Quarry and upto PPCB/TEC 2008. For borrow 09/08/2016. H/E/2015 two DG sets Permission – Capacity- Rewa, date 1.Vide letter Permission of 40000 10/08/2015. no. Borrow M.T./Year Under Air 1091/RO/MP Earth(Mining) act 1981, PCB/2015, has issued by Valid upto Rewa, Date- Collector(Minin 09/08/2016. 10/07/2015. g) Sidhi vide Capacity- 2. Vide letter letter number 40000 no. 431/kahanij/201 M.T./Year 1090/RO/MP 5 dated Capacity- PCB/2015, 30/04/2015, 40000 Rewa, Date who is also the M.T./Year 10/07/2015. chairman of DEIAA.

Permission of Borrow Earth(Mining) has issued by Collector(Minin g) Singrauli vide letter number/717/ka hanij/2015 dated 30/04/2015, Who is also the chairman of DEIAA.

30

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (a)’ MPDCSP PACKAGE-1, BHOPAL-1 Status of Compliance with Environment Regulations (January – June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor Env. cutting as Diesel Clearance per IEE / Forest Batching Hot Mix Pollution Crusher WMM Plant Generator Permission Name of the for the actual Clearance/ Plant Plant Under S. No. (Ref (Ref Set obtained from Sub-Project Project trees felled Tree cutting (Ref (Ref Control other / Pkg. Agreement Agreement (Ref Road from (As per EMP Agreement Agreement (PUC) regulators clause No- Clause- Agreement certificates MoEF/ and Agreement) Sub-clause Sub-clause (RefAgreement 4.18) 111.16) Sub-clause for vehicle SEIAA No-111.15) No-111.15) Clause-4.18) No-111.15) Prior Environmental Clearance ( EC) granted by MP-SEIAA for extraction of natural resources (stone boulder quarry) for two mining sites- 1. Hardi village- Vide letter no 6559/SEIAA/15, dated 20.10.2015. 2. Kahjuriya village vide letter no. 6438/SEIAA/15, dated 19.10.2015. Workmen compensation insurance/CA R policy- submitted, valid upto- 02.06.2016 plus 60 month maintenance period.

31

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (a)’ MPDCSP PACKAGE-1, BHOPAL-1 Status of Compliance with Environment Regulations (January – June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor Env. cutting as Diesel Clearance per IEE / Forest Batching Hot Mix Pollution Crusher WMM Plant Generator Permission Name of the for the actual Clearance/ Plant Plant Under S. No. (Ref (Ref Set obtained from Sub-Project Project trees felled Tree cutting (Ref (Ref Control other / Pkg. Agreement Agreement (Ref Road from (As per EMP Agreement Agreement (PUC) regulators clause No- Clause- Agreement certificates MoEF/ and Agreement) Sub-clause Sub-clause (RefAgreement 4.18) 111.16) Sub-clause for vehicle SEIAA No-111.15) No-111.15) Clause-4.18) No-111.15) Pkg-B Chitrangi-Kasar As per There is no Permission of Consent to 1. Consent to establish and operate granted Consent to 1. PUC Labor License: MoEF tree cutting work in forest establish by pollution control board, vide letter no. establish certificates Issued by Agreement amendme involve as area under obtained 539/RO/SGRL/MPPCB/TECH/2015, obtained obtained for district labor Signed date nt in EIA per IEE Sigrauli district from Singrauli, Dated 19/06/2015, under Air act from 10 vehicles. officer singrauli, 15.12.2014 notification report. DFO is issued pollution 1981, valid upto 18/06/2016. pollution Certificates vide letter no 2006, EC vide letter no. control control board expired on 445/R/BOC/SG Commenceme is not 2106, dated board vide Capacity- vide letter no Sep. 2015. RL/2015 dated nt date- required Trees 27/07/2015. letter no HMP-60000 MT/Year 468/RO/SG 2. Total 62 20/04/2015, 01.01.2015 felling are 468/RO/SG RMC-10000 m3/Year RL/Tech/MP PUC valid upto not required RL/Tech/MP WMM-90000 MT/Year PCB/ certificates 31/12/2015. as per site PCB/ Singrauli obtained Renewed on Contracter- survey. Singrauli 2. Consent to establish and operate granted dated along with date Madhav Infra dated by pollution control board, vide letter no. 29/05/2015, above 01/12/2015 29/05/2015, 540/RO/SGRL/MPPCB/TECH/2015, valid upto certificate valid upto 31- Length-39.930 valid upto Singrauli, Dated 19/06/2015, under Water 28/05/2020, renewals. 12-2016. km. 28/05/2020, act 1974, valid upto 18/06/2016. under air act. Valid upto Blasting under Air Capacity- 07-04- Permission: Construction act. 500 KVA. 2016. Obtained by Period-15 Capacity- material months. 120,000 Consent to 2.Certificat outsourced firm M3/Year operate es renewed (Dynamic Infra) Completed on obtained, / obtained vide letter no date- Consent to vide letter on date 24- 313/miniral/201 20/06/2016. operate no. AW- 04-2016 for 5 date 09 June obtained, 32174/RO/P 77 vehicles 2015. Valid vide letter CB/sgrl- with validity from 10-06- no. AW- /2015, upto. 23- 2015 to 32174/RO/P Sigrauli / 10-2016. 09/12/2015. CB/sgrl- Dated 2. Blasting /2015, 31/07/2015 Permission Sigrauli / renewed on Dated date 23-12-

32

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (a)’ MPDCSP PACKAGE-1, BHOPAL-1 Status of Compliance with Environment Regulations (January – June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor Env. cutting as Diesel Clearance per IEE / Forest Batching Hot Mix Pollution Crusher WMM Plant Generator Permission Name of the for the actual Clearance/ Plant Plant Under S. No. (Ref (Ref Set obtained from Sub-Project Project trees felled Tree cutting (Ref (Ref Control other / Pkg. Agreement Agreement (Ref Road from (As per EMP Agreement Agreement (PUC) regulators clause No- Clause- Agreement certificates MoEF/ and Agreement) Sub-clause Sub-clause (RefAgreement 4.18) 111.16) Sub-clause for vehicle SEIAA No-111.15) No-111.15) Clause-4.18) No-111.15) 31/07/2015. 2015, Valid Valid upto from 25-12- 31-06-2016. 2015 to 24-06- 2016. Sand Source and Water source: Sand purchased with valid transit passes. Water Bore well established by the contractor, declaration for fulfillment of legal obligations is submitted by the contractor Quarry and borrow Permission – Permission of Borrow Earth(Mining) has issued by Collector(Minin g), Singrauli vide letter - 1. Vide letter no 691/kahanij/201

33

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (a)’ MPDCSP PACKAGE-1, BHOPAL-1 Status of Compliance with Environment Regulations (January – June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor Env. cutting as Diesel Clearance per IEE / Forest Batching Hot Mix Pollution Crusher WMM Plant Generator Permission Name of the for the actual Clearance/ Plant Plant Under S. No. (Ref (Ref Set obtained from Sub-Project Project trees felled Tree cutting (Ref (Ref Control other / Pkg. Agreement Agreement (Ref Road from (As per EMP Agreement Agreement (PUC) regulators clause No- Clause- Agreement certificates MoEF/ and Agreement) Sub-clause Sub-clause (RefAgreement 4.18) 111.16) Sub-clause for vehicle SEIAA No-111.15) No-111.15) Clause-4.18) No-111.15) 5 dated 29/04/2015. 2.Vide letter no 689/kahanij/201 5 dated 29/04/2015. 3. Vide letter no 715/kahanij/201 5 dated 30/04/2015. 4. Vide letter no 754/kahanij/201 5 dated 08/05/2015. 5. Vide letter no 1437/kahanij/as thai anu./2015 Singrauli, dated 14/08/2015.

Environmental Clearance (EC) granted from MP-SEIAA for extraction of natural resources (Soil and Murum) for three mining sites- 1. Basaniya village

34

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (a)’ MPDCSP PACKAGE-1, BHOPAL-1 Status of Compliance with Environment Regulations (January – June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor Env. cutting as Diesel Clearance per IEE / Forest Batching Hot Mix Pollution Crusher WMM Plant Generator Permission Name of the for the actual Clearance/ Plant Plant Under S. No. (Ref (Ref Set obtained from Sub-Project Project trees felled Tree cutting (Ref (Ref Control other / Pkg. Agreement Agreement (Ref Road from (As per EMP Agreement Agreement (PUC) regulators clause No- Clause- Agreement certificates MoEF/ and Agreement) Sub-clause Sub-clause (RefAgreement 4.18) 111.16) Sub-clause for vehicle SEIAA No-111.15) No-111.15) Clause-4.18) No-111.15) vide letter no. 6833/SEIAA/15 dated 28.10.15 2. Dudhmaniya village Vide letter no. 6460/SEIAA/15, dated 19.10.2015. 3. Parsohar village vide- letter 9854 / SEIAA/15, dated 26.12.15. Copy attached in December 2015 MPR. Environmental Clearance (EC) for Stone and bolder extraction is applied to SEIAA, for two sites- 1. Vide letter no. 01/DEIAA/UP/2 016, dated 30/05/2016. 2.Vide letter no. 03/DEIAA/UP/2

35

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (a)’ MPDCSP PACKAGE-1, BHOPAL-1 Status of Compliance with Environment Regulations (January – June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor Env. cutting as Diesel Clearance per IEE / Forest Batching Hot Mix Pollution Crusher WMM Plant Generator Permission Name of the for the actual Clearance/ Plant Plant Under S. No. (Ref (Ref Set obtained from Sub-Project Project trees felled Tree cutting (Ref (Ref Control other / Pkg. Agreement Agreement (Ref Road from (As per EMP Agreement Agreement (PUC) regulators clause No- Clause- Agreement certificates MoEF/ and Agreement) Sub-clause Sub-clause (RefAgreement 4.18) 111.16) Sub-clause for vehicle SEIAA No-111.15) No-111.15) Clause-4.18) No-111.15) 016, dated 30/05/2016. Insurance CAR insurance policy- Received.Valid upto 14.02.2016 for construction period. Pkg-C Dabra- As per 60 tree Project is not Consent to Consent to establish granted by pollution Permission 1.PUC Labor License: Bhitarwar- MoEF need to be passing through Establish control board, vide Consent no. CTE-32655, obtained certificates Issued by Labor Harsi amendme cut as per forest area. granted by dated 20/09/2015. Under air (1981) and from office of obtained for licensing officer nt in EIA IEE report. pollution water (1974) Act. Add. District 15 vehicles. District Gwalior Agreement notification control Capacity- Magistrate Valid upto (M.P.) vide Signed date 2006, EC Trees board for Bitumin Mix-112000 Cum./Yr. vide letter 24-12- letter no. 15.12.2014 is not felling are stone bolder Cancrete batching Plant-20M3 / Hr. no. Q/reder- 2015. 1249/G/L/2015 required not required mine vide WMM Plant- 100 Tonne / Hr. ADM/g- 2. PUC dt 20-04-2015 Commenceme as per site consent no. 18/04/2015 renewed/ob valid upto 31- nt date- survey. 33732. Consent to Operate granted by pollution Gwalior, tained for /12/2015.renew 08.01.2015 under Air control board, vide Consent no. AW-33733, date 50 vehicals ed on Date 14- (1981) and Valid upto 31-10-2016. 03/06/2015. on date 31- 01-2016 valid water (1974) Under air (1981) and water (1974) Act. 12-2015. upto 31-12- Contracter- Act. Authorization Valid upto 2016. KNR-TMCPL Capacity- Construction activity related with these Order for DG 30-06- Blasting 100247 plants is completed therefore further set obtained 2016. Permission: Length-62.400 cubic renewal for the plants consents were not from Certificates Received, vide km. meter/year needed. pollution renewed letter no. control board and valid Q/Reder- Construction Consent to under upto ADM/9- Period-21 Operate Hazardous Feb/March 18/34/15,

36

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (a)’ MPDCSP PACKAGE-1, BHOPAL-1 Status of Compliance with Environment Regulations (January – June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor Env. cutting as Diesel Clearance per IEE / Forest Batching Hot Mix Pollution Crusher WMM Plant Generator Permission Name of the for the actual Clearance/ Plant Plant Under S. No. (Ref (Ref Set obtained from Sub-Project Project trees felled Tree cutting (Ref (Ref Control other / Pkg. Agreement Agreement (Ref Road from (As per EMP Agreement Agreement (PUC) regulators clause No- Clause- Agreement certificates MoEF/ and Agreement) Sub-clause Sub-clause (RefAgreement 4.18) 111.16) Sub-clause for vehicle SEIAA No-111.15) No-111.15) Clause-4.18) No-111.15) months granted by waste 2017. Gwaliar, Dated pollution amended 30-10-2015. control rule, 2008. Valid upto 31- boardvide Vide consent 12-2016. consent no. no H-39099, Sand Source 34111. dated 30-08- and Water Dated 2016. source: 16/12/2015. Sand under Air purchased with (1981) and valid transit water (1974) passes. Act. Valid Water Bore well upto 31-10- established by 2016. the contractor, declaration for Adequate fulfillment of material legal processed obligations is and stored given by the by the contractor contractor at Quarry and construction borrow camp Permission – therefore Permission of further Borrow renewal for Earth(Mining) plant has issued by consents Collector(Minin was not g), Gwalior vide needed. letter - 1. Vide letter no Q/3/Ma

37

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (a)’ MPDCSP PACKAGE-1, BHOPAL-1 Status of Compliance with Environment Regulations (January – June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor Env. cutting as Diesel Clearance per IEE / Forest Batching Hot Mix Pollution Crusher WMM Plant Generator Permission Name of the for the actual Clearance/ Plant Plant Under S. No. (Ref (Ref Set obtained from Sub-Project Project trees felled Tree cutting (Ref (Ref Control other / Pkg. Agreement Agreement (Ref Road from (As per EMP Agreement Agreement (PUC) regulators clause No- Clause- Agreement certificates MoEF/ and Agreement) Sub-clause Sub-clause (RefAgreement 4.18) 111.16) Sub-clause for vehicle SEIAA No-111.15) No-111.15) Clause-4.18) No-111.15) Sa./T.P.- 03/2014 dated 13/02/2015. 2. NOC is issued by the office of district collector (Mineral branch) district Gwalior (M.P.). Vide letter no Q/3/Ma Sa./T.P./2015 dated 28/04/2015. Who is also the chairman of DEIAA. Environmental Clearance (EC) for stone quarry granted from MP-SEIAA, Vide letter no. 3254/SEIAA/15 on date 08/07/2015. Insurance CAR policy- submitted, Valid from 01.05.2015 to

38

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (a)’ MPDCSP PACKAGE-1, BHOPAL-1 Status of Compliance with Environment Regulations (January – June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor Env. cutting as Diesel Clearance per IEE / Forest Batching Hot Mix Pollution Crusher WMM Plant Generator Permission Name of the for the actual Clearance/ Plant Plant Under S. No. (Ref (Ref Set obtained from Sub-Project Project trees felled Tree cutting (Ref (Ref Control other / Pkg. Agreement Agreement (Ref Road from (As per EMP Agreement Agreement (PUC) regulators clause No- Clause- Agreement certificates MoEF/ and Agreement) Sub-clause Sub-clause (RefAgreement 4.18) 111.16) Sub-clause for vehicle SEIAA No-111.15) No-111.15) Clause-4.18) No-111.15) 31.01.2017 for construction period and 60 month of extended maintenance period. Pkg-D As per 586 no. of 1. Tree felling Initial consent under Air & water act issued by pollution 1.Consent to 1. PUC Labor License Ujjain-Makshi MoEF tree need to permission is control board vide letter no.2880 & 2882 dated 11.03.2015. operate certificates Issued by Labor

amendme be cut as issued by Upper Consents Renewed on date 17.08.2015- obtained obtained for licensing officer Agreement nt in EIA per IEE district 1. Pollution control board granted Consent to Operate for from 70 vehicles, Ujjain, vide Signed date notification report. magistrate Crusher, HMP, RMC, WMM vide letter no. pollution valid up to letter no. 25692 11.12.2014 2006, EC Ujjain office vide 1429/RO/MPPCB/15. (Gram Molga location). Under Water control board 13/10/2015 dated

is not Total 291 letter no. 03/A- (Prevention & Control of Pollution) Act 1974. Valid upto on vide 2. Above 23.01.2015.Vali Commenceme required no. of trees 62/2014-2015 16/08/2016. consent no Certificates d upto nt date- cut and 295 for 110 no. of 3883/RO/MP Renewed 31/12/2015. 08.01.2015 trees trees. 2. Pollution control board granted Consent to Operate for PCB/15, and total Project

saved. Crusher, HMP, RMC, WMM vide letter no. Ujjain, Dated 104 completed on

2. Tree felling 1431/RO/MPPCB/15. (Gram Molga location). Under Air 10/06/2015 vehicles date 31-12- Contracter- permission is (Prevention & Control of Pollution) Act 1981. Valid upto Valid upto certificates 2015. Dilip Buildcon issued by Upper 16/08/2016. 09/06/2016. obtained

district Capacity- DG Set valid upto Blasting Length-36..494 magistrate Crusher-200MT/hr. no.478- 06/05/2016 Permission– km. Ujjain office vide Hot Mix-90MT/hr. 500KVA and . 1. Obtained by

letter no. 02/A- RMC-60MT/hr. DG Set involved Construction 62/2014-2015 WMM-5000 MT/Year no.415- persons, vide Period-15 for 38 no. of 180KVA. letter no 87552 months trees. dated

3.Tree felling Authorization 02.05.2011 Completed on permission is obtained valid till date- issued by under 31.03.2016, 28/12/2015. District Hazardous 2.

39

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (a)’ MPDCSP PACKAGE-1, BHOPAL-1 Status of Compliance with Environment Regulations (January – June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor Env. cutting as Diesel Clearance per IEE / Forest Batching Hot Mix Pollution Crusher WMM Plant Generator Permission Name of the for the actual Clearance/ Plant Plant Under S. No. (Ref (Ref Set obtained from Sub-Project Project trees felled Tree cutting (Ref (Ref Control other / Pkg. Agreement Agreement (Ref Road from (As per EMP Agreement Agreement (PUC) regulators clause No- Clause- Agreement certificates MoEF/ and Agreement) Sub-clause Sub-clause (RefAgreement 4.18) 111.16) Sub-clause for vehicle SEIAA No-111.15) No-111.15) Clause-4.18) No-111.15) magistrate Waste E/CB/MP/30/42 Devas office (Manageme 33 (E 6840) vide letter no. nt, Handling dated 03/A-62/2014- and Trans- 24/09/2012 2015 for 98 no. Boundary valid till of trees. Management 24/09/2017. 4. Tree felling ) Rules Sand Source permission is 2008. For and Water issued by two DG sets source: District 1.Vide Sand and water magistrate Authorization purchased from Shajapur office no. H-33987, local vendors. vide letter no. Valid upto Sand 03/A-62/2014- 21/12/2016 purchased with 2015 dated Date- valid transit 27/03/2015. 10/12/2015. passes. for45 no. of Quarry and trees. Borrow area Permission- Prior Environmental Clearancel ( EC) granted by MP-SEIAA vide clearance no 9945/SEIAA/15, dated 29.12.15. for extraction of bolder Stone & Murum Quarry at Surjanwasa village, Tehsil-

40

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (a)’ MPDCSP PACKAGE-1, BHOPAL-1 Status of Compliance with Environment Regulations (January – June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor Env. cutting as Diesel Clearance per IEE / Forest Batching Hot Mix Pollution Crusher WMM Plant Generator Permission Name of the for the actual Clearance/ Plant Plant Under S. No. (Ref (Ref Set obtained from Sub-Project Project trees felled Tree cutting (Ref (Ref Control other / Pkg. Agreement Agreement (Ref Road from (As per EMP Agreement Agreement (PUC) regulators clause No- Clause- Agreement certificates MoEF/ and Agreement) Sub-clause Sub-clause (RefAgreement 4.18) 111.16) Sub-clause for vehicle SEIAA No-111.15) No-111.15) Clause-4.18) No-111.15) Ujjain, District Ujjain. Insurance CAR policy:- submitted,valid from 06.02.2015 to 05.05.2016 for construction period. and 60 month of extended maintenance period. (till 04- 05-2021). Pkg-E Hardua- As per 668 no. of Working 1. Consent Consent to 1. Consent 1.Consent to 1.Consent to PUC Labor License: Chakghat MoEF tree need to permission in to Establish Operate to Establish Establish Establish certificates Issued by amendme be cut as forest area granted by granted by granted by granted by granted by obtained for licensing officer Agreement nt in EIA per IEE granted by pollution pollution pollution pollution pollution 23 vehicles. Rewa, District: Signed date notification report. forest control control vide control control control board Valid upto vide letter no. 11.05.2015 2006, EC department board vide consent no board vide board vide vide consent 25-07- 250/RWA/CLA/ is not Tree cutting (DFO Rewa), consent no AW-35016. consent no consent no no CTE- 2016. 2015 dated Commenceme required is not vide letter no. CTE- 34294 Dated 01- CTE- 34295 CTE- 34296 34297dated Certificates 11.08.2015.Vali nt date- required as 8864, Rewa, dated 02-2016. dated dated 30/12/2015. renewed / d upto 29.06.2015 per site. dated 18-12- 30/12/2015 Valid upto- 30/12/2015. 30/12/2015C Capacity 125 obtained for 31/12/2015. 2015. Capacity- 14-12-2016 Capacity- apacity- KVA 27 vehicles 2. Labor license Contracter- 300000 Capacity- 100000 200000 valid upto renewed on Gangotri MT/Yr. 35000 MT/Yr. MT/Yr. 2. Consent 03-04- date Enterprises Cum/Year. 2. Consent 2. Consent to Operate 2017. 11/12/2015 and Ltd. Consent to 2. Consent to Operate to Operate granted by Submission valid upto 31- Operate to Establish granted by granted by pollution of renewal 12-2016. Length-92..260 granted by for same pollution pollution control board certificates 3. Labor license

41

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (a)’ MPDCSP PACKAGE-1, BHOPAL-1 Status of Compliance with Environment Regulations (January – June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor Env. cutting as Diesel Clearance per IEE / Forest Batching Hot Mix Pollution Crusher WMM Plant Generator Permission Name of the for the actual Clearance/ Plant Plant Under S. No. (Ref (Ref Set obtained from Sub-Project Project trees felled Tree cutting (Ref (Ref Control other / Pkg. Agreement Agreement (Ref Road from (As per EMP Agreement Agreement (PUC) regulators clause No- Clause- Agreement certificates MoEF/ and Agreement) Sub-clause Sub-clause (RefAgreement 4.18) 111.16) Sub-clause for vehicle SEIAA No-111.15) No-111.15) Clause-4.18) No-111.15) km. pollution plant at new control control vide consent awaited renewed on control construction board vide board vide no. A-35017, from date Construction board vide site of consent no. consent no. Valid upto contractor. 11/01/2017 and Period-24 consent no. project road AW-35015, AW-35016, 14/12/2016. valid upto 31- months AW-35014, granted by dated 01-02- dated 01-02- Renewal 12-2017. dated 01-02- MP Pollution 2016. Valid 2016. Valid applied by 2016. Valid control upto upto the Blasting upto board vide 14/12/2016. 14/12/2016. contractor license: 14/12/2016. consent no. 2. Consent Renewal obtained by 2. Consent CTE-42659, to Establish applied by involved to Establish dated for same the persons for same 07/02/2017. plant at new contractor License No- plant at new Valid upto construction E/HQ/MP/22/30 construction 06-02-2018. site of 8 (E38391) site of project road valid upto- 31- project road Consent to granted by 03-2019. granted by Operate MP Pollution Sand Source MP Pollution received control and Water control vide consent board vide source: board vide no. AW- consent no. Sand consent no. 43821, on CTE-42658, purchased with CTE-42660, date dated valid transit dated 28/03/2017 07/02/2017. passes. 07/02/2017. Valid upto Valid upto Water Bore well Valid upto 23/03/2018. 06-02-2018. established by 06-02-2018. the contractor, Consent to declaration for Consent to Operate fulfillment of Operate receivedvide legal received consent no. obligations is vide consent A-43817, on given by the no. AW- date contractor

42

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (a)’ MPDCSP PACKAGE-1, BHOPAL-1 Status of Compliance with Environment Regulations (January – June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor Env. cutting as Diesel Clearance per IEE / Forest Batching Hot Mix Pollution Crusher WMM Plant Generator Permission Name of the for the actual Clearance/ Plant Plant Under S. No. (Ref (Ref Set obtained from Sub-Project Project trees felled Tree cutting (Ref (Ref Control other / Pkg. Agreement Agreement (Ref Road from (As per EMP Agreement Agreement (PUC) regulators clause No- Clause- Agreement certificates MoEF/ and Agreement) Sub-clause Sub-clause (RefAgreement 4.18) 111.16) Sub-clause for vehicle SEIAA No-111.15) No-111.15) Clause-4.18) No-111.15) 43823, on 28/03/2017 Quarry and date Valid upto Borrow area 28/03/2017 23/03/2018. permissions- Valid upto Permission of 23/03/2018. Borrow Earth (Mining) has issued by Collector(Minin g), Rewa vide letter - 1476/Minrals/20 15, dated 05/09/2015Who is also the Chairman of DEIAA.

Prior Environmental Clearance for Stone Quarry from Village- Padariya, Tehsil- Samariya, District- Rewa is granted by SEIAA. M.P. vide letter no 3003/SEIAA/16, dated 31.03.2016.

43

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (a)’ MPDCSP PACKAGE-1, BHOPAL-1 Status of Compliance with Environment Regulations (January – June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor Env. cutting as Diesel Clearance per IEE / Forest Batching Hot Mix Pollution Crusher WMM Plant Generator Permission Name of the for the actual Clearance/ Plant Plant Under S. No. (Ref (Ref Set obtained from Sub-Project Project trees felled Tree cutting (Ref (Ref Control other / Pkg. Agreement Agreement (Ref Road from (As per EMP Agreement Agreement (PUC) regulators clause No- Clause- Agreement certificates MoEF/ and Agreement) Sub-clause Sub-clause (RefAgreement 4.18) 111.16) Sub-clause for vehicle SEIAA No-111.15) No-111.15) Clause-4.18) No-111.15)

Insurance CAR policy:Submitt ed,valid from 01.07.2015 to 30.06.2017 for construction period. Pkg-F Persauna- As per 2582 no. of Permission of 1. Consent Plant not Plant Permission for Electricity PUC Labor License: Mahua MoEF tree need to work in forest to establish established establishment of HMP and Outsourced certificates Issued by amendme be cut as area under and operate by the WMM Plant granted by with valid obtained for licensing officer Agreement nt in EIA per IEE Sigrauli district. granted by contractor. Pollution control board vide agreement 8 Sigrauli district, Signed date notification report. Issued by DFO pollution consent no. 34254, validity: constructio vide letter no. 01.05.2015 2006, EC Sigrauli vide control 20/12/2020. Dated n vehicles, 765/L/SGRL/20 is not Tree of letter no. 90, board, vide 24.12.2015. valid up to 15 dated Commenceme required cutting have Singrauli, dated letter no. HMP CTE Quantity-345600 04/02/2016. 22.08.2015.Vali nt date- avoided by 06/01/2016. 1294/RO/SG MT. Certificates d upto 01.09.2015 the RL/MPPCB/ WMM CTE Quantity- renewed for 31/12/2015. restriction TECH/2014, 172800 MT. 15 vehicles Labor license of widening Dated Consent to operate granted valid upto renewed on Contracter- within 30/12/2014, by pollution control board 24-08- date M/s Montecarlo available under Air act on date 08/02/2016, valid 2016. 05/01/2016 and Ltd Jv Shree Ji ROW 1981, valid uptp 22/01/2017. Certificates valid upto 31- Infra. upto renewed for 12-2016. 31/12/2015. 12 vehicles Length-67..20 2. Consent valid upto Blasting km. to establish 14-08- Permission – and operate 2017. granted from Construction granted by district Period-21.33 pollution magistrate months control Sigraulli vide

44

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (a)’ MPDCSP PACKAGE-1, BHOPAL-1 Status of Compliance with Environment Regulations (January – June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor Env. cutting as Diesel Clearance per IEE / Forest Batching Hot Mix Pollution Crusher WMM Plant Generator Permission Name of the for the actual Clearance/ Plant Plant Under S. No. (Ref (Ref Set obtained from Sub-Project Project trees felled Tree cutting (Ref (Ref Control other / Pkg. Agreement Agreement (Ref Road from (As per EMP Agreement Agreement (PUC) regulators clause No- Clause- Agreement certificates MoEF/ and Agreement) Sub-clause Sub-clause (RefAgreement 4.18) 111.16) Sub-clause for vehicle SEIAA No-111.15) No-111.15) Clause-4.18) No-111.15) board, vide letter letter no. no.96/RDM/201 1295/RO/SG 6 dated 05-02- RL/MPPCB/ 2016 valid upto. TECH/2014, 04.08.2016. Dated Renewal of 30/12/2014, permissionis under water not needed as act 1974, blasting is not valid upto required further. 31/12/2015 Sand Source (Existing and Water crusher unit source: hired by the Sand and water contractor) purchased from Consentrene local vendors. wed on date Sand 25-08-2015 purchased with under air act valid transit vide consent passes. A- Petroleum 32469/RO/P product CB/Singhruli storage /2015. Valid Permission- upto 28-02- Prior 2017. Permission for Under air consumer and water Pump is act vide approved by consent no. Petroleum & AW-32467 Explosives dated 25-08- Safety

45

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (a)’ MPDCSP PACKAGE-1, BHOPAL-1 Status of Compliance with Environment Regulations (January – June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor Env. cutting as Diesel Clearance per IEE / Forest Batching Hot Mix Pollution Crusher WMM Plant Generator Permission Name of the for the actual Clearance/ Plant Plant Under S. No. (Ref (Ref Set obtained from Sub-Project Project trees felled Tree cutting (Ref (Ref Control other / Pkg. Agreement Agreement (Ref Road from (As per EMP Agreement Agreement (PUC) regulators clause No- Clause- Agreement certificates MoEF/ and Agreement) Sub-clause Sub-clause (RefAgreement 4.18) 111.16) Sub-clause for vehicle SEIAA No-111.15) No-111.15) Clause-4.18) No-111.15) 2015 valid Organization upto 28-02- (PESO) vide 2017. prior approval No: A/P/CC/MP/14/ 7671 (P365330) dated 22-09- 2015. Quarry and borrow Permission – Prior Environmental Clearance (EC) from DEIAA for extraction of natural resources (stone crusher) is granted vide- 1. Letter no. 27/DEIAA/UP/2 016, Singhruli, dated 30/05/2016. (Village Bharsendi, Sarai). 2. Letter no. 47/DEIAA/UP/2 016, Singhruli,

46

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (a)’ MPDCSP PACKAGE-1, BHOPAL-1 Status of Compliance with Environment Regulations (January – June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor Env. cutting as Diesel Clearance per IEE / Forest Batching Hot Mix Pollution Crusher WMM Plant Generator Permission Name of the for the actual Clearance/ Plant Plant Under S. No. (Ref (Ref Set obtained from Sub-Project Project trees felled Tree cutting (Ref (Ref Control other / Pkg. Agreement Agreement (Ref Road from (As per EMP Agreement Agreement (PUC) regulators clause No- Clause- Agreement certificates MoEF/ and Agreement) Sub-clause Sub-clause (RefAgreement 4.18) 111.16) Sub-clause for vehicle SEIAA No-111.15) No-111.15) Clause-4.18) No-111.15) dated 30/05/2016. (Village Katheri, Sarai).

Prior Environmental Clearance from DEIAA for borrow earth / murrum is Applied for 4 borrow areas to Singhruli district collector office. Insurance CAR policy submitted,valid from 10.09.2015 to 09.06.2017 for construction period and 60 month of extended maintenance period. Pkg-G Rewa-Bankuia- As per 278 no. of Project road is Consent to Not Installed Consent to establish and Authorization Certificates Labor License- Samariya MoEF tree need to not passing establish by the operate obtained obtained for Obtained amendme be cut as through forest and operate contractor obtained from pollution under 8 Valid upto to Agreement nt in EIA per IEE area. obtained control board vide- Hazardous constructio 31-12-2016. Signed date notification report. from Consent No- Waste n vehicles, Sand Source

47

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (a)’ MPDCSP PACKAGE-1, BHOPAL-1 Status of Compliance with Environment Regulations (January – June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor Env. cutting as Diesel Clearance per IEE / Forest Batching Hot Mix Pollution Crusher WMM Plant Generator Permission Name of the for the actual Clearance/ Plant Plant Under S. No. (Ref (Ref Set obtained from Sub-Project Project trees felled Tree cutting (Ref (Ref Control other / Pkg. Agreement Agreement (Ref Road from (As per EMP Agreement Agreement (PUC) regulators clause No- Clause- Agreement certificates MoEF/ and Agreement) Sub-clause Sub-clause (RefAgreement 4.18) 111.16) Sub-clause for vehicle SEIAA No-111.15) No-111.15) Clause-4.18) No-111.15) 14.05.2015 2006, EC Actual tree pollution 1235/RO/MPPCB/TECH/E/ (Manageme valid up to and Water is not cutting is control 2016 Rewa, date nt, Handling 07/07/2016 source: Commenceme required not required board vide- 18/02/2016Valid upto and Trans- and Sand nt date- as per site Consent No- 17/02/217. Boundary 06/07/2016. purchased with 29.06.2015 survey. 1235/RO/MP Management valid transit PCB/TECH/ ) Rules passes. E/2016 2008. For Water Bore well Contracter- Rewa, date two DG sets established by M/s Prakash 18/02/2016V 1. Vide the contractor, Asphalting alid upto Authorization declaration for 17/02/217. no. CTE- fulfillment of Length-33..410 38316, Valid legal km. upto12/05/20 obligations is 17 Date- given by the Construction 02/06/2016. contractor Period-12 Quarry and months. borrow Permission – completed on Permission of date- Stone Quarry 15/07/2016. (Mining) has issued by Collector(Minin g), Rewa vide letter - 1836/khanij/201 2,Rewa dated 22/02/2012

Environmental Clearance (EC) form SEIAA for

48

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (a)’ MPDCSP PACKAGE-1, BHOPAL-1 Status of Compliance with Environment Regulations (January – June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor Env. cutting as Diesel Clearance per IEE / Forest Batching Hot Mix Pollution Crusher WMM Plant Generator Permission Name of the for the actual Clearance/ Plant Plant Under S. No. (Ref (Ref Set obtained from Sub-Project Project trees felled Tree cutting (Ref (Ref Control other / Pkg. Agreement Agreement (Ref Road from (As per EMP Agreement Agreement (PUC) regulators clause No- Clause- Agreement certificates MoEF/ and Agreement) Sub-clause Sub-clause (RefAgreement 4.18) 111.16) Sub-clause for vehicle SEIAA No-111.15) No-111.15) Clause-4.18) No-111.15) extraction of natural resources- for stone quarry is out sourced by contractor from other agency with valid agreement. Borrow earth permission – Over bourdon of quarry site has been utilized to fulfill requirement of earth material. Insurance CAR policy: Obtained,valid from 02.02.2016 to 14.07.2016 for construction period and 60 month of extended maintenance period.

49

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) Rani Existing Consent to 1. Consent to Electric PUC Labour Pkg-H Durgawati crusher establish Consent establish connection certificate License- Samadhi plant used obtained from to obtained obtained from obtained Vide License Road by pollution establish from MPEB via for 32 Number – 899 contractor control board obtained pollution temporarily Vehicles Dated (MDR-36-19) renewal vide Consent from control connection valid upto 29/03/2016 Length- from No.- 42429 pollution board vide from the July 2017 Valid upto 21.13km pollution Outward No. control Consent nearby Electric 31/12/2016 for Agreement control 14134 dated board vide No.- pole. 80 Labours

Signed date- board vide 09/02/2016, Consent 42428, Renewal 136- trees to 10.11.2015 Working letter Village No.- Outward Labour be cut as Permission in number no. LamehtaghKh CTE/3615 No. 13314 License- Commencement As per per IEE forest area 1769/RO/P .No. 132/2 1, dated Vide License date- 02.12.2015 MoEF report granted by DFO CB/2012 and 137, Outward 02/09/2016, Number – 899 amendme Contractor- Jabalpur vide Dated Capacity- No. 13280 Village Dated nt in EIA Tree Cutting M/s Ganon letter 19/07/2012( 10000 MT dated Chargawan 16/01/2017 notificatio is not Dunkerley No./DM/1678 AW-16491 Valid upto 22/03/201 Kh.No. 101, Valid upto n 2006, required as Dated dated 01/01/2021 6 Valid upto 31/12/2017 for Construction EC is not per site 04/06/2016 18/07/2012) Capacity- 01/01/2022 80 Labours Period- 18 required. survey. valid till 10000 MT Months 31/07/2016 Village Petroleum Village Mageli License – Manegaon Kh. No. Purchase from Kh. No.-53, 122/4 nearby local Area-3.35 Consent to valid upto area patrol Ha operate 30/11/202 pump. Capacity- obtained from 0 Consent to 10000 MT pollution operate Blasting under Air control board 2. obtained Permission – (1981) and vide Consent Consent from Vide letter

50

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) water No. 62492 to pollution Number- (1974) Act. Outward No. establish control 377/Shastra 16141 dated obtained board vide Shakha/2016 Consent to 08/04/2016, from Consent dated operate Village pollution No.- 07/09/2016 valid obtained LamehtaghKh control 54282, upto 07/06/2017 from . No. 132/2 board vide Outward pollution and 137, Consent No. 13411 control Capacity- No.- dated Sand Source board vide 27998 42428, 04/11/2016, and Water Consent MT3/Yr, Valid Outward Village source: No.- AW- upto No. 13314 Chargawan Sand and water 42178 08/04/2017 dated Kh.No. 101, purchased from Outward 02/09/201 Valid upto local vendors. No.- 13718 6 Village 01/01/2022 Sand purchased Dated Chargawa (Hot Mix with valid transit 13/10/2016 n Kh. Plant CTE passes. Valid upto No. 101, and CTO 21/12/2017. Capacity has been Quarry and (Agreement 700 obtained borrow basis M/s MT/Yr, village Permission – Buddhu Lal Valid upto chargwan Environmental Gond 01/01/202 has been Clearance (EC) Bolder 2 used for granted from Mine) at making DEIAA- Khasra 1. WMM Mix 11/DEIAA/2016 Number- Consent as it was Dated 300,301 to operate permitted in 10/05/2016 Area 2.52 obtained the concent Village-Ghaghra Ha., Village from orders) Kh. No. 105

51

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) Kohla pollution Area-1.72 Capacity- control Ha.(Stone 25005 board vide Crusher) CuM/Yr Consent No.- AW- Environmental Consent to 43143, Clearance (EC) establish Outward granted from obtained No. 14182 SEIAA- from dated 558/SEIAA/16 pollution 07/03/201 Dated control 7 06/04/2016 board vide Capacity- Village- Consent 10000 MT Manegaon No.- AW- Village Kh.No.-53 42479, Mageli (Metal Quarry Outward Kh. No. Stone) No.- 13810 122/4 Dated valid upto Environmental 31/07/2016, 16/02/201 Clearance (EC) Kh. No. 8 granted from 846,858,85 DEIAA- 9,860 Area 2. 61/DEIAA/2016 1.89 Ha Consent Dated Village- to operate 03/09/2016 Dungariya obtained Villgae- Mining of from Dungariya Boulder pollution Kha.No. Capacity control 846,859,858,86 27998 board vide 0,861,Area-4 MCube/Yr, Consent Ha.(Stone

52

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) Valid upto No.- &Murrum) 01/01/2021 54282 Village Environmental Consent to Chargawa Clearance (EC) operate n Ph. granted from obtained No. 63 DEIAA- from Khasra 56/DEIAA/2016 pollution No. 101 Dated control Outward 03/09/2016 board vide No. 13411 Village-Kohla Consent dated Kha.no.- No.- AW- 04/11/201 300,301Area- 43502, 6 capacity 2.52 Ha.(Stone) Outward 700 No.- 13315 MT/Yr, Dated Valid upto CAR policy- 21/09/2016, 01/01/202 Policy No- Kh. No. 2 9131020061266 846,858,85 00000 Dated 9,860 Area 22/12/2015 1.89 Ha Valid Village- 15/12/2015 to Dungariya 14/12/201 Mining of Boulder Tree /Murrum Plantation- Capacity Total 862 Trees 27998 Planted MCube/Yr., Valid upto

53

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) 10/03/2018 Tilwara- Existing Consent to 1. Consent to Electric PUC Labour Pkg-H Chargaon crusher establish Consent establish connection certificate License- (MDR-36-05) plant used obtained from to obtained obtained from for 32 Vide License & Gotegaon by pollution establish from MPEB via Vehicles Number – 899 contractor control board obtained pollution temporarily valid up to Dated (MDR-41-01) renewal vide Consent from control connection July 2017 29/03/2016 Length- from No.- 42429 pollution board vide from the Valid upto 46.18 Km pollution Outward No. control Consent nearby Electric 31/12/2016 for control 14134 dated board vide No.- pole. 80 Labours Agreement board vide 09/02/2016, Consent 42428, Renewal Signed date- 546- trees Working letter Village No.- Outward Labour 10.11.2015 need to be As per Permission in number no. LamehtaghKh CTE/3615 No. 13314 License- cut as per Commencement MOEF forest area 1769/RO/P .No. 132/2 1, dated Vide License IEE report date- 02.12.2015 amendme granted by CB/2012 and 137, Outward 02/09/2016, Number – 899

Contractor- nt in EIA forest Dated Capacity- No. 13280 Village Dated Tree Cutting notificatio department 19/07/2012( 10000 MT dated Chargawan 16/01/2017 M/s Ganon is not n 2006, DFO Jabalpur AW-16491 Valid upto 22/03/201 Kh.No. 101, Valid upto Dunkerley required as EC is not vide letter no.- dated 01/01/2021 6 Valid upto 31/12/2017 for per site Construction required. DM/1698 Dated 18/07/2012) Capacity- 01/01/2022 80 Labours survey. Period- 18 08/06/2016 valid till 10000 MT

31/07/2016 Village Blasting Village Mageli Permission – Manegaon Kh. No. Vide letter Kh. No.-53, 122/4 Number- Area-3.35 Consent to valid upto 377/Shastra Ha operate 30/11/202 Shakha/2016 Capacity- obtained from 0 Consent to dated 10000 MT pollution operate 07/09/2016 valid under Air control board 2. obtained

54

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) (1981) and vide Consent Consent from upto 07/06/2017 water No. 62492 to pollution (1974) Act. Outward No. establish control Petroleum 16141 dated obtained board vide License – Consent to 08/04/2016, from Consent Purchase from operate Village pollution No.- nearby local obtained LamehtaghKh control 54282, area patrol from . No. 132/2 board vide Outward pump. pollution and 137, Consent No. 13411 control Capacity- No.- dated Sand Source board vide 27998 42428, 04/11/2016, and Water Consent MT3/Yr, Valid Outward Village source: No.- AW- upto No. 13314 Chargawan Sand and water 42178 08/04/2017 dated Kh.No. 101, purchased from Outward 02/09/201 Valid upto local vendors. No.- 13718 6 Village 01/01/2022 Sand purchased Dated Chargawa (Hot Mix with valid transit 13/10/2016 n Kh. Plant CTE passes. Valid upto No. 101, and CTO 21/12/2017. Capacity has been Quarry and (Agreement 700 obtained borrow basis M/s MT/Yr, village Permission – Buddhu Lal Valid upto chargwan Environmental Gond 01/01/202 has been Clearance (EC) Bolder 2 used for granted from Mine) at making DEIAA- Khasra 1. WMM Mix 11/DEIAA/2016 Number- Consent as it was Dated 300,301 to operate permitted in 10/05/2016 Area 2.52 obtained the concent Village-Ghaghra

55

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) Ha., Village from orders) Kh. No. 105 Kohla pollution Area-1.72 Capacity- control Ha.(Stone 25005 board vide Crusher) CuM/Yr Consent No.- AW- Environmental Consent to 43143, Clearance (EC) establish Outward granted from obtained No. 14182 SEIAA- from dated 558/SEIAA/16 pollution 07/03/201 Dated control 7 06/04/2016 board vide Capacity- Village- Consent 10000 MT Manegaon No.- AW- Village Kh.No.-53 42479, Mageli (Metal Quarry Outward Kh. No. Stone) No.- 13810 122/4 Dated valid upto Environmental 31/07/2016, 16/02/201 Clearance (EC) Kh. No. 8 granted from 846,858,85 DEIAA- 9,860 Area 2. 61/DEIAA/2016 1.89 Ha Consent Dated Village- to operate 03/09/2016 Dungariya obtained Villgae- Mining of from Dungariya Boulder pollution Kha.No. Capacity control 846,859,858,86 27998 board vide 0,861,Area-4

56

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) MCube/Yr, Consent Ha.(Stone & Valid upto No.- Murrum) 01/01/2021 54282 Village Environmental Consent to Chargawa Clearance (EC) operate n Ph. granted from obtained No. 63 DEIAA- from Khasra 56/DEIAA/2016 pollution No. 101 Dated control Outward 03/09/2016 board vide No. 13411 Village-Kohla Consent dated Kha.no.- No.- AW- 04/11/201 300,301Area- 43502, 6 capacity 2.52 Ha.(Stone) Outward 700 No.- 13315 MT/Yr, Sand Source Dated Valid upto Details – 21/09/2016, 01/01/202 Royalty basis Kh. No. 2 purchased 846,858,85 9,860 Area CAR policy- 1.89 Ha Policy No- Village- 9131020061266 Dungariya 00000 Dated Mining of 22/12/2015 Boulder Valid /Murrum 15/12/2015 to Capacity 14/12/2017 27998 MCube/Yr.,

57

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) Valid upto Tree 10/03/2018 Plantation- Total 2800 Trees Planted Katni-Vijay Project is not Consent to Consent to Consent Consent to Electricity PUC Labour Pkg-H Raghavagarh passing through operate establish to establish Obtained from certificate License- - –Barhi Road forest area. obtained obtained from establish obtained MPEB Nearby obtained Issued by from pollution obtained from electric pole on for 18 district labour (MDR-39-01) pollution control board from pollution Temporary Vehicles officer Katni, Length- control vide Consent pollution control Connection valid upto vide license 51.40 Km board vide No.- control board vide August number –782 Consent CTE/37515, board vide Consent 2017 Dated Agreement 226 -trees No.- AW- Outward Consent No.- 22/03/2016 Signed date- need to be As per 30404, Number – No.- CTE/42492, Valid upto 10.11.2015 cut as per MOEF Outward 12248, Dated CTE/3751 Outward 31/12/2016 for IEE report Commencement amendme Number – 01/06/2016 4, Number – 50 Labours.

date- 02.12.2015 nt in EIA 12149 Kh. 480/1, Outward 12500, Renewal Tree Cutting Contractor- notificatio Dated 481/2, 479/1 Number – Dated Labour is not n 2006, 04/04/2016 Village- 12247, 14/02/2017 License- M/s Ganon required as EC is not Kh. No.- Dokariya, Dated Kh. 480/1, Vide License Dunkerley per site required. 1002,1003, Capacity- 01/06/201 481/2, Number – 782 survey. Construction 1019,1020, 5000 CuM/Yr 6Kh. 479/1 Dated

Period- 18 1022,1023 (Mix 480/1, Village- 13/02/2017 Area 4 Ha. Concrete), 481/2, Dokariya, Valid upto Village- valid upto 479/1 Capacity- 31/12/2017 for Bichpura 27/05/2017 Village- 400000MT/ 50 Labours Mining of Dokariya, Yr (Water Boulders Capacity- Mixed Petroleum 80182 20000 Mecedum License – M3/Yr, Valid CuM/Yr WMM), Purchase from

58

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) upto Consent to (Mix valid upto nearby local 01/04/2017 operate Bitumen), 31/01/2018 area patrol (Agreement pollution valid upto pump. basis- M/s control board 27/05/201 Consent to Shri vide Consent 7 operate Sand Source Mahalaxmi No.-AW- pollution and Water mines & 38802, control source: Minerals dt outward board vide Sand and water 26/12/2015) number- Consent purchased from 12320 Dated Consent No.- local vendors. 09/08/2016 to operate AW/43891, Sand purchased Kh. 480/1, pollution Outward with valid transit 481/2, 479/1 control Number – passes. Village- board vide 12573, Quarry and Dokariya, Consent Dated borrow Capacity- No.- AW- 29/03/2017 Permission – 5000 CuM/Yr 38801, Kh. 480/1, Permission of (Mix Outward 481/2, Borrow Concrete), number- 479/1 Earth(Mining) Valid upto 12319 Village- has issued by 07/08/2017 Dated Dokariya, Collector(Mining 09/08/201 Capacity- ) Katni on 6 Kh. 400000MT/ Royalty basis 480/1, Yr (Water vide letter 481/2, Mixed 1170/Khanij/201 479/1 Mecedum 6 Dated Village- WMM), 21/03/2016 Dokariya, valid upto Village Parasi Capacity- 23/03/2018 Khasra Number- 20000 144/3 & 144/4

59

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) CuM/Yr Area-1.87 Ha. (Mix For Stone, Bitumen), Soil/Murram Valid (Royalty Amount 31/05 85 Lakhs), Who 2017 is also the Chairman of DEIAA.

Permission of Borrow Earth(Mining) has issued by Collector(Mining ) Katni (Transportation Permission) 1. Vide letter number/1251/Pri /16 Dated 31/03/2016 Kha.No. 69 Area 2.14 Village- Bhainswahi(Soil/ Murrum) 2.Vide letter number /1293/Pri/16 Dated 31/03/2016

60

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) Kha.No. 552,553,554 Area 0.56, 1.36, 0.39 Ha. Village- Jijnaudi (Soil/Murrum), Who is also the Chairman of DEIAA.

Outsource Material Agreement Details – Agreement Date 20/12/2015 Agreement Valid upto 20/12/2017

CAR policy- Policy No- 9131020061266 00000 Dated 22/12/2015 Valid 15/12/2015 to 14/12/2017

Tree Plantation-Total

61

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) 3000 Trees Planted Consent to Consent to establish obtained from Consent to PUC Labour Pkg-I establish pollution control board vide Consent No.- establish certificate License- Issued obtained CTE/36812, Outward Number – 13664, obtained from obtained by district labour from Dated 25/04/2016 pollution for 28 officer Sagar, Bandari- pollution Kh. 47/2/1,48/2,51/2 Village- Chopra, control board Vehicles vide license Jaruwakheda control Valid upto 23/04/2017 vide Consent valid upto number – board vide No.- September 336/SDS/CL/20 (MDR-31-32) Working Consent Capacity- CTE/36811, 2017 16 Dated Length- Permission in No.- Ready Mix Material-15000 MT3 Outward 22/01/2016 24.93 Km Only 46 forest area CTE/36811, Hot Mix Material- 11500 MT3 Number – Valid upto Agreement As per trees need granted by Outward Wet Mix Material- 57000 MT3 13663, Dated 31/12/2016 for Signed date- MOEF to be cut in forest Number – 25/04/2016 75 Labours. 27.11.2015 amendme department in 13663, Consent to operate obtained from Kh. 32,310/1/2 Renewal nt in EIA Tree Cutting Sagar district, Dated pollution control board vide Consent No.- Village- Labour Commencemen notificatio is not DFO(North 25/04/2016 AW-38296, Outward Number – 13989, Chopra, License- t date- n 2006, required as Sagar) vide Kh. Dated 14/07/2016 Capacity- Vide License 06.11.2015 EC is not per site letter no. 32,310/1/2 Kh. 47/2/1,48/2,51/2 Village- Chopra, 500KVA (DG Number – 5208 Contractor- required survey. /DM/16/1026, Village- Valid upto 13/06/2017 Set), Valid upto Dated M/s Madhav Dated Chopra, 17/04/2017 04/01/2017 Infra 01/04/2016 Capacity- Capacity- Valid upto Construction 225000 Ready Mix Material-15000 MT3 Consent to 31/12/2017 MT/Yr Hot Mix Material- 11500 MT3 operate Period- 18 (Stone Wet Mix Material- 57000 MT3 pollution Blasting months Gitti), Valid control board Permission – upto vide Consent Permission 17/04/2017 No.- AW- granted by 38875, Collector(Khanij) Consent to Outward Vidisha vide

62

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) operate Number – letter No.- Q/14- pollution 14092, Dated Arms/2016/8012 control 12/08/2016 Kh. Dated board vide 32,310/1/2 28/04/2016 Consent Village- No.- AW- Chopra, Petroleum 38875, Capacity- License – Outward 500KVA (DG Granted by Number – Set), Valid upto Petroleum and 14092, 24/05/2017 Explosives Dated Safety 12/08/2016 Organisation(PE Kh. SO) Vide Letter 32,310/1/2 Number – Village- A/P/CB/MP/15/4 Chopra, 9(P380027) Capacity- Dated 225000 17/05/2016 Plot MT/Yr No.- (Stone 47/2/1,48/2,51/2 Gitti), Valid Village- Chopda. upto Capacity 40 KL. 24/05/2017 Quarry and borrow Permission –

Environmental Clearance (EC) granted from

63

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) DEIAA- 1535/DEIAA/20 16 Dated 24/06/2016 (Stone & Murram) Area- 3.994 Ha., Khasra no. 32,310/1/2 Village Chopra

Sand Source Details – Royalty basis purchased

CAR policy- Policy No.- 4521004415030 0000004 Valid 14/01/2016 to 06/05/2017 Renewal CAR Policy- Policy No. 4521004416040 0000002 Valid from 10/05/2017 to 09/11/2017

64

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) Tree Plantation- Total 500 Trees Planted Consent to Consent to establish obtained from Consent to PUC Labour Pkg-I establish pollution control board vide Consent No.- establish certificate License- Issued obtained CTE/36812, Outward Number – 13664, obtained from obtained by district labour Nirtala-Mandi from Dated 25/04/2016 pollution for 28 officer Sagar, Bamora road pollution Kh. 47/2/1,48/2,51/2 Village- Chopra, control board Vehicles vide license control Valid upto 23/04/2017 vide Consent valid upto number – (MDR-31-32) board vide No.- September 336/SDS/CL/20 Length- 24.90 Consent Capacity- CTE/36811, 2017 16 Dated km No.- Ready Mix Material-15000 MT3 Outward 22/01/2016 Agreement As per CTE/36811, Hot Mix Material- 11500 MT3 Number – Valid upto Signed date- MOEF Outward Wet Mix Material- 57000 MT3 13663, Dated 31/12/2016 for amendme Number – 25/04/2016 75 Labours. 27.11.2015 Project is not nt in EIA Tree cutting 13663, Consent to operate obtained from Kh. 32,310/1/2 Renewal Commencemen passing through notificatio not required Dated pollution control board vide Consent No.- Village- Labour t date- forest area. n 2006, 25/04/2016 AW-38296, Outward Number – 13989, Chopra, License- 06.11.2015 EC is not Kh. Dated 14/07/2016 Capacity- Vide License Contractor- required 32,310/1/2 Kh. 47/2/1,48/2,51/2 Village- Chopra, 500KVA (DG Number – 5208 M/s Madhav Village- Valid upto 13/06/2017 Set), Valid upto Dated Infra Chopra, 17/04/2017 04/01/2017 Construction Capacity- Capacity- Valid upto 225000 Ready Mix Material-15000 MT3 Consent to 31/12/2017 Period- 18 MT/Yr Hot Mix Material- 11500 MT3 operate months (Stone Wet Mix Material- 57000 MT3 pollution Blasting Gitti), Valid control board Permission – upto vide Consent Permission 17/04/2017 No.- AW- granted by

65

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) 38875, Collector(Khanij) Consent to Outward Vidisha vide operate Number – letter No.- Q/14- pollution 14092, Dated Arms/2016/8012 control 12/08/2016 Kh. Dated board vide 32,310/1/2 28/04/2016 Consent Village- No.- AW- Chopra, Petroleum 38875, Capacity- License – Outward 500KVA (DG Granted by Number – Set), Valid upto Petroleum and 14092, 24/05/2017 Explosives Dated Safety 12/08/2016 Organisation(PE Kh. SO) Vide Letter 32,310/1/2 Number – Village- A/P/CB/MP/15/4 Chopra, 9(P380027) Capacity- Dated 225000 17/05/2016 Plot MT/Yr No.- (Stone 47/2/1,48/2,51/2 Gitti), Valid Village- Chopda. upto Capacity 40 KL. 24/05/2017 Quarry and borrow Permission –

Environmental

66

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) Clearance (EC) granted from DEIAA- 1535/DEIAA/20 16 Dated 24/06/2016 (Stone & Murram) Area- 3.994 Ha., Khasra no. 32,310/1/2 Village Chopra

Sand Source Details – Royalty basis purchased

CAR policy- Policy No.- 4521004415030 0000004 Valid 14/01/2016 to 06/05/2017 Renewal CAR Policy- Policy No. 4521004416040 0000002 Valid from 10/05/2017

67

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) to 09/11/2017 Tree Plantation- Total 2000 Trees Planted Consent to Consent to establish obtained from Consent to PUC Labour Pkg-I establish pollution control board vide Consent No.- operate certificate License- obtained CTE/40587 Outward No.: 12621 Dated obtained from obtained Issued by Damoh- from 24/11/2016, Kh. No.- 1127/1/1 Area – 2 pollution for 12 district labour Hindoriya – pollution Ha. Village- Hindoriya control board Vehicles officer Damoh, Patera road control Valid upto 31/10/2017 vide Consent valid upto vide license (MDR-32-12) board vide No.- AW- September number –592 Length- 26.40 Consent Capacity- 45571 Outward 2017 Dated only 113 Km No.- Batching Plant-20.000 Cum/Hr No.: 13092 10/03/2016 As per trees need Agreement CTE/40560 Hot Mix Plant-45.000 Cum/Hr Dated Valid upto MOEF to be cut Signed date- Outward Wet Mix Plant- 100.000 MT/Hr 30/05/2017 Kh. 31/12/2016 for amendme 27.11.2015 Project is not Number.- No.- 1652,1653 50 Labours. nt in EIA Tree Cutting passing through 12617 Area – 1.035 Renewal Commencemen notificatio is not forest area. Dated Consent to operate obtained from pollution Ha. Village- Labour t date- n 2006, required as 23/11/2016 control board vide Consent No.- AW- Sampoorna, License- 06.11.2015 EC is not per site (Stone Gitti 45572, Outward No.: 13093 Dated Capacity- 600 Vide License required survey. Contractor- by stone 30/05/2017, Kh. No.- 1127/1/1 Area – 2 KVA, Valid Number – 592

M/s Madhav crusher) Ha. Village- Hindoriya upto Dated Infra 200000 Valid upto 31/10/2017 31/10/2017 30/01/2017 Construction TPH/Yr Valid upto Kh. No.- Capacity- 31/12/2017 for Period- 18 1652,1653 Batching Plant-20.000 Cum/Hr 50 Labours. months Area – Hot Mix Plant-45.000 Cum/Hr 1.035 Ha. Wet Mix Plant- 100.000 MT/Hr Blasting Village- Permission –

68

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) Sampoorna Permission Valid upto granted by 31/10/2017 Collector(Khanij) Vidisha vide Consent to letter No.- Q/14- operate Arms/2016/8012 obtained Dated from 28/04/2016 pollution control Petroleum board vide License – Consent Granted by No.- AW- Petroleum and 45571 Explosives Outward Safety Number.- Organisation(PE 13092 SO) Vide Letter Dated Number– 30/05/2017 P/CC/MP/14/67 (Stone Gitti) 96(P376166) 200000 Dated MT/H 29/03/2016 Kh. No.- 1127/1/1 1652,1653 Village- Area – Hindoriya. 1.035 Ha. Capacity 40 KL Village- Renewal Sampoorna Petroleum Valid upto License – 31/10/2017 Granted by

69

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) Petroleum and Explosives Safety Organisation(PE SO) Vide Letter Number– P/CC/MP/14/67 96(P376166) Dated 02/02/2017 1127/1/1 Village- Hindoriya. Capacity 40 KL Valid upto 31/12/2017

Quarry and borrow Permission – Environmental Clearance (EC) granted from DEIAA- 1535/DEIAA/20 16 Dated 24/06/2016 (Stone & Murram) Area- 3.994 Ha.,

70

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) Khasra no. 32,310/1/2 Village Chopra

CAR policy- Policy No.- 4521004415030 0000004 Valid 14/01/2016 to 06/05/2017 Renewal CAR Policy- Policy No. 4521004416040 0000002 Valid from 10/05/2017 to 09/11/2017

Tree Plantation- Total 1000 Trees Planted As per 48- tree Consent to Consent to establish obtained from pollution control board PUC Labour Prithvipur – Permission Pkg-J MOEF need to be operate vide Consent No.- CTE/39629, Outward Number – 12531, certificate License- Niwari road Granted from amendme cut as per obtained Dated 28/09/2016 Kh. 103/k Village- Jer, Valid upto obtained Issued by (MDR-35-05) DFO(Tikamgarh nt in EIA IEE report from 26/09/2017. for 18 district labour ) vide letter Length- 22.57 notificatio pollution Vehicles officer Number/DM/20 KM n 2006, Tree Cutting control Capacity- valid upto Tikamgarh, vide 16/4484, Dated Agreement EC is not is not board vide Batching Plant-30000 MT/Yr November license number 03/10/2016 Signed date- required required as Consent Hot Mix Plant-15000 MT3/year 2017 –41/tkg/2016

71

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) 27.11.2015 per site No.- AW- Wet Mix Plant- 75000 m3/year Dated Commencemen survey. 40292, D.G Sets- 125 KVA 04/02/2016 t date- Outward Valid upto 27.11.2015 Number- Consent to operate obtained from pollution control board 31/12/2016 for 12576, vide Consent No.- AW-44611, Outward Number – 13018, 100 Labours. Contractor- Dated Dated 25/04/2017 Kh. 103/k Village- Jer, Valid upto Renewal M/s Madhav 31/10/2016 30/09/2017. Labour Infra Project Kh. 612 License- Construction Village- Capacity- Issued by Period- Manikpura Batching Plant-30000 MT/Yr district labour 18months Dumduma, Hot Mix Plant-15000 MT3/year officer Capacity- Wet Mix Plant- 75000 m3/year Tikamgarh, vide 18000CF/Yr D.G Sets- 125 KVA license number (Stone –6525 Dated Gitti), Valid 03/02/2017 upto Valid upto 31/05/2017 31/12/2016 for (Agreement 100 Labours. basis- M/s Janhavi Petroleum Granite License – Industries) Purchase from nearby local Renewal of area patrol -Consent to pump. operate (M/s Quarry and Janhavi borrow Granite Permission – Industries Environmental

72

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) )obtained Clearance (EC) from granted from pollution DEIAA- control Khanij/DEIAA/2 board vide 016/11 Dated Consent 26/05/2016Quar No.- AW- ry area 2.0 Ha., 46615, Khasra no. 611 Outward Village Number- Manikpur(Stone 13163, Crusher) Dated 13/07/2017 Permission of Kh. 612 Borrow Village- Earth(Mining) Manikpura has issued by Dumduma, Collector(Mining Capacity- ) Tikamgarh 18000CF/Yr 1. Vide letter (Stone number - Gitti), Valid 11/Khanij//Teen- upto 06/2016/997 31/05/2018 dated13/10/201 6 for Murram/Soil Village-Jer Khasra Number- 190/5/1 Area 2 Ha. 2.Vide letter

73

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) number - 11/Khanij//Teen- 06/2016/1000 dated 13/10/2016 for Murram/Soil Village-Jer Khasra Number- 406/2B/3 Area 1.214 Ha. 3.Vide letter number - 11/Khanij//Teen- 06/2016/ 999 dated 13/10/2016 for Murram/Soil Village- Nayakhera Khasra Number- 556 Area 2Ha. 4.Vide letter number - 11/Khanij//Teen- 06/2016/ 998 dated 13/10/2016 for Murram/Soil Village-Churara Khasra Number-

74

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) 534/2Area 4Ha., Who is also the Chairman of DEIAA.

Sand Source Details – Work order basis

CAR policy- Policy No.- 4521004415030 0000005 Valid 14/01/2016 to 06/05/2018

Tree Plantation- Total 200 Trees Planted 169 -trees Permission Consent to Consent to Consent Consent to establishment PUC Labour Ajaygarh- As per Pkg-J need to be Granted from operate operate to operate pollution control board vide certificate License- Toriya- MOEF cut DFO(North pollution pollution pollution Consent No.- CTE/41160, obtained Issued by Bariyapur road amendme Panna) vide control control board control Outward Number – 12651, for 13 district labour (MDR-33-05) nt in EIA Tree Cutting letter board vide vide Consent board vide Dated 22/12/2016 Vehicles officer notificatio Length-23.92 is not Number/DM/20 Consent No.- AW- Consent Kh. 210/1,Village- Sinhai, valid upto Tikamgarh, vide n 2006, Km required as 16/3121, Dated No.- AW- 38004, No.- AW- Valid upto 30/11/2017 November license number EC is not Agreement per site 23/07/2016 and 38003, Outward 41337, 2017 – 562 Dated required Signed date- survey. Permission Outward Number – Outward Capacity- 14/03/2016 valid

75

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) 27.11.2015 Granted by Number – 12394, Dated Number – WMM Plant- 50.000 CuM/Hr upto 31/12/2016 Commencemen Forest 12394, 25/06/2016 12668, DG Set-250KVA for 50 Labours. t date- Department, Dated (Agreement (Agreeme Renewal 27.11.2015 vide letter no. 25/06/2016 basis- M/s nt basis- Consent to operate pollution Labour No./DM/2016/1 (Agreement Abc M/s control board vide Consent License- Contractor- 086Dated basis- M/s Associates) Bharat No.- AW-44612, Outward Issued by M/s Madhav 20/06/2016 Bira Stone Kh. Milan Number – 13019, Dated district labour Infra Project Mine) 1949,1950 Pandey) 25/04/2017 officer Construction Kh. 2945/1 &1951 Dated Kh. 210/1,Village- Sinhai, Tikamgarh, vide Period- Village- Bira Village- Bira 26/12/201 Valid upto 30/11/2017 license number 18months Capacity- Capacity- 6Kh. 2161 Capacity- – 7002 Dated 50000 2111160 Village- WMM Plant- 50.000 CuM/Hr 20/03/2017 valid CuM/Yr MT/Yr Pista DG Set-250KVA upto 31/12/2016 (Mining of (Batching Capacity- for 50 Labours. Stone Plant), Valid 25000 Boulder), upto MT/Yr Petroleum Valid upto 24/06/2017 (Bitumen License – 24/06/2017 Mix), Valid Purchase from upto nearby local 30/11/201 area patrol 7 pump.

Quarry and borrow Permission – Environmental Clearance (EC) granted from DEIAA- Khanij/DEIAA/2

76

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) 016/03 Dated 20/05/2016 Quarry area 1.20 Ha., Khasra no. 1945/1 Village Bira)(Stone Quarry)

Permission of Borrow Earth(Mining) has issued by Collector(Mining ) Tikamgarh vide letter number - 11/Khanij//Teen- 06/2016/ 998 dated 13/10/2016 for Murram/Soil Village-Churara Khasra Number- 534/2Area 4Ha., Who is also the Chairman of DEIAA.

Sand Source

77

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) Details – Work order basis

CAR policy- Policy No.- 4521004415030 0000005 Valid 17/01/2016 to 06/05/2018

Tree Plantation- Total 100 Trees Planted Palera- Working Consent to Consent to establish from pollution control board vide PUC Labour Pkg-J Baldeogarh Permission establish Consent No.- CTE/38240,Outward Number – 12405, Dated certificate License- road Granted from from 08/07/2016 obtained Issued by DFO(Tikamgarh pollution Kh. 13/1,13/2,13/3,13/4 Village- Hanumantpura, Valid upto for 69 district labour (MDR-35-25) As per 63- trees ) vide letter control 31/12/2016 Vehicles officer MOEF 38.40 Km need to be Number/DM/20 board vide valid upto Tikamgarh, vide amendme cut . 16/1751, Dated Consent Capacity- November license number Agreement nt in EIA 31/12/2016 No.- Batching Plant- 30000 MT3 2017 –41/tkg/2016 Signed date- notificatio Only 49 CTE/38119, Hot Mix Plant- 15000 MT3 Dated 27.11.2015 n 2006, Trees need Tree Cutting Outward WMM Plant- 100000 CuM 04/02/2016 Commencemen EC is not to be cut. permission Number – DG Set- (1x 160KVA, 1X100 KVA, 1X 82.5 KVA) Valid upto t date- required 27.11.2015 granted from 12401, 31/12/2016 for Collector(Tikam Dated Consent to operate from pollution control board vide Consent 100 Labours Contractor- garh) vide letter 01/07/2016 No.- AWH-39631,Outward Number – 12533, Dated Renewal M/s Madhav order number Kh. 28/09/2016 Labour

78

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) Infra Project 183/V- 370,Village- Kh. 13/1,13/2,13/3,13/4 Village- Hanumantpura, Valid upto License- Construction 121/2016-17 Vaisa ugad, 27/09/2021 Issued by Dated Capacity- district labour Period- 09/05/2017 for 200000 Capacity- officer 18months 49 Trees. MT/Yr(Ston Batching Plant- 30000 MT3 Tikamgarh, vide e Gitti), Hot Mix Plant- 15000 MT3 license number Valid upto WMM Plant- 100000 MT3 –6525 Dated 31/12/2016 DG Set- (1x 160KVA, 1X100 KVA, 1X 82.5 KVA) 03/02/2017 Valid upto Consent to 31/12/2016 for operate 100 Labours from pollution Petroleum control License – board vide Granted by Consent Petroleum & No.- Explosives AWH/39630 Safety , Outward Organisation(PE Number – SO) Vide Letter 12532, Number – Dated A/P/CB/MP/15/5 28/09/2016 1 (P380159) - Kh. Dated 370,Village- 27/05/2016 Plot Vaisa ugad, No.- Capacity- 13/1,13/2,13/3,1 200000 3/4 Village- MT/Yr(Ston Hanumantpura e Gitti), Capacity 40 KL.

79

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) Valid upto 31/07/2017 Quarry and borrow Permission –

Environmental Clearance (EC) granted from DEIAA- Khanij/DEIAA/2 016/59 Dated 26/06/2016(Soil/ Murram Quarry area 4.00 Ha., Khasra no. 300/1,300/2 Village Bhelsi)

Environmental Clearance (EC) granted from DEIAA- Khanij/DEIAA/2 016/102 Dated 09/01/2017(Ston e Crusher Quarry)Quarry area 4.00 Ha., Khasra no. 370, Village

80

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) Besaugad)

CAR policy- Policy No.- 4521004415030 0000005 Valid from 14/01/2016 to 06/05/2018

Tree Plantation- Total 300 Trees Planted

Sidhi-Tikari Consent to Consent to Consent Consent to Consent to PUC Labour Pkg-K operate operate to operate operate establishment certificate License- Road Working 213 -of tree obtained obtained from obtained obtained & operate obtained Issued by (MDR 45-02) Permission in As per need to be from pollution from from (Authorization for 20 district labour forest area Length- MoEF cut as per pollution control board pollution pollution obtained under Vehicles officer Rewa, granted by 31.85 km amendme IEE report. control vide Consent control control Hazardous valid upto vide license forest nt in EIA board vide No.- AW- board vide board vide Waste June 2016 number – department notificatio Tree Cutting Consent 37391, Consent Consent (Management, 282/RWA/CLA/2 Agreement in Sidhi district n 2006, not required No.- AW- Outward No.- AW- No.- AW- Handling and 016 Dated Signed date- DFO SIdhi vide EC is not as per site 37401,Outw Number – 37395, 37402, Trans 13/01/2016 03.8.2015 letter no. required survey. ard Number 12138, Dated Outward Outward Boundary Valid upto /DM/178, Dated – 12138, 26/05/2016 Number – Number – movement 31/12/2016 for 04/01/2016 Commencemen Dated Kh. 12136, 12139, rules 2008) 100Labours. t date- 26/05/2016 346,361,363,3 Dated Dated obtained from

81

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) 01.09.2015 Kh. 64 Village- 26/05/201 26/05/2016 pollution Blasting 346,361,36 Dolkothar, 6 Kh. control board Permission – 3,364 Capacity- Kh. 346,361,36 vide Consent Blasting Contractor- Village- 50000 MT/Yr 346,361,3 3,364 No.- CTE/ Agreement M/s Dilip Dolkothar, (Ready Mix 63,364 Village- 37398, between Dilip Buildcon Capacity- Concrete) Village- Dolkothar, Outward Buildcon Ltd., Construction 100000 valid upto Dolkothar, Capacity- Number – and Hanumana MT/Yr(Ston 14/01/2017 Capacity- 100000 12137, Dated Explosive(Licen e Gitti) 50000 MT/Yr 26/05/2016 se No. Period- 18 valid upto MT/Yr (WMM) Capacity – DG E/HQ/MP/22/40 months 14/01/2017 (Bitumino valid upto Set Unit 6(E69894) Valid us Mix) 14/01/2017 125KVA up to valid upto Kh. 31/03/2020 14/01/201 346,361,363,3 Agreement 7 64 Village- Place : Mauganj Dolkothar, Dated valid upto 13/11/2015 17/05/2021 Petroleum License – Granted by Patroleum & Explosives Safety Organisation(PE SO) for Village Mangawa- Chakghat Road(410/1,410 /2,410/3,410/4,4

82

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) 10/5), Rewa with letter no P/CC/MP/14/66 43(P344817) dt 27/11/2015 referring letter dated 26/11/2015 Licensed Qt 40KL.

Quarry and borrow Permission – Permission of Borrow Earth(Mining) has issued by Collector(Mining ) Sidhi (Transportation Permission) vide letter number - 405/Khanij/2016 Dated 29/03/2016 Village- Badera, Khasra Number – 488,489,484,49

83

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) 0,487 Area 1.750 Ha. (Stone), Who is also the Chairman of DEIAA.

Environmental Clearance (EC) for stone quarry granted from DEIAA, Vide letter no. 71/DEIAA/16 Dated 29/06/2016 Village- Pangadi, Khasra Number – 3/11,3/6 Area 1.618 Ha.

CAR policy- Policy Number 0605004415P10 8620501 Date 26/10/2015 Period of Insurance 26/10/2015 to

84

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) 25/08/2017 Tree Plantation- Total 1040 Trees Planted Consent to Consent to Consent Consent to establishment PUC Labour Pkg-K operate operate to operate operate & operate certificate License- obtained obtained from obtained obtained (Authorization obtained Issued by Kyothi-Katra- from pollution from from obtained under for 20 district labour Lalgaon Road pollution control board pollution pollution Hazardous Vehicles officer Rewa, (MDR 43-02) control vide Consent control control Waste valid upto vide license Length- 25.91 board vide No.- AW- board vide board vide (Management, June 2016 number – Consent 35285, Consent Consent Handling and 282/RWA/CLA/2 Km 77 -trees No.- AW- Outward No.- AW- No.- AW- Trans 016 Dated Agreement As per need to be 35281, Number – 35242, 35284, Boundary 13/01/2016 Signed date- MOEF cut Outward 12049, Dated Outward Outward movement Valid upto 03.8.2015 amendme Project is not Number – 10/02/2016 Number – Number – rules 2008) 31/12/2016 for nt in EIA Commencemen passing through 12046, Kh. 12043, 12048, obtained from 100Labours. notificatio Tree Cutting t date- forest area. Dated 3/15,3/5,3/7 Dated Dated pollution n 2006, not required 01.09.2015 10/02/2016 Village- 09/02/201 10/02/2016 control board Blasting EC is not as per site Kh. Pangadi, 6 Kh. 3/36 vide Consent Permission – Contractor- required survey. 3/15,3/5,3/7 Capacity- Kh. Village- No.- 34643, Blasting M/s Dilip Buildcon Village- 150000 3/15,3/5,3/ Shivrajpur, Outward Agreement Pangadi, SCM/Yr 7 Village- Capacity- Number – between Dilip Construction Capacity- (Ready Mix Pangadi, 100000 12006, Dated Buildcon Ltd., Period- 18 100000 Concrete) Capacity- MT/Yr 09/01/2016 and Hanumana months MT/Yr Valid upto 100000 (WMM), Capacity – DG Explosive(Licen (Stone 31/12/2016 MT/Yr Valid upto Set Unit se No. Gitti), , Valid (Hot Mix 31/12/2016 85KVA E/HQ/MP/22/40 upto Bituminou Village- 6(E69894) Valid

85

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) 31/12/2016 s), Valid Shivrajpur up to upto 31/03/2020 31/12/201 Agreement 6 Place : Mauganj Dated 13/11/2015

Petroleum License – Granted by Petroleum & Explosives Safety Organisation(PE SO) for Village Mangawa- Chakghat Road(410/1,410 /2,410/3,410/4,4 10/5), Rewa with letter no P/CC/MP/14/66 43(P344817) dt 27/11/2015 referring letter dated 26/11/2015 Licensed Qt 40KL. Quarry and

86

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) borrow Permission – 1. Environmental Clearance (EC) for stone quarry granted from DEIAA, Vide letter no. 71/DEIAA/16 Dated 29/06/2016 Village- Pangadi, Khasra Number – 3/11,3/6 Area 1.618 Ha. 2. Camp Establishment - Agreement obtained for Village- Pangarhi, Rewa Area 10 Ha.on 22/09/2015 CAR policy- Policy Number 0605004415P10 8620501 Date 26/10/2015

87

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) Period of Insurance 26/10/2015 to 25/08/2017 Tree Plantation- Total 1000 Trees Planted Mauganj-Katra Consent to Consent to Consent Consent to establishment 20 Nos. Labour Pkg-K Road operate operate to operate operate & operate Valid upto License- obtained obtained from obtained obtained (Authorization June 2016 Issued by (MDR-43-04). from pollution from from obtained under district labour Length- 38.01 pollution control board pollution pollution Hazardous officer Rewa, Km control vide Consent control control Waste vide license board vide No.- AW- board vide board vide (Management, number – 86- trees As per Consent 35245, Consent Consent Handling and 282/RWA/CLA/2 AgreementSign need to be MOEF No.- AW- Outward No.- AW- No.- AW- Trans 016 Dated ed date- cut. amendme Project road is 35282, Number – 35240, 35284, Boundary 13/01/2016 03.8.2015 nt in EIA not passing Outward 12045, Dated Outward Outward movement Valid upto Tree Cutting notificatio through forest Number – 09/02/2016 Number – Number – rules 2008) 31/12/2016 for not required Commencemen n 2006, area 12047, Kh. 3/36 12042, 12048, obtained from 100Labours. as per site t date- EC is not Dated Village- Dated Dated pollution Blasting survey. 01.09.2015 required 10/02/2016 Shivrajpur, 09/02/201 10/02/2016 control board Permission –

Kh. 3/36 Capacity- 6 Kh. 3/36 vide Consent Blasting Village- 80000 Kh. 3/36 Village- No.- Agreement Contractor- Shivrajpur, SCM/Yr Village- Shivrajpur, CTE/34643Out between Dilip M/s Dilip Capacity- (Ready Mix Shivrajpur Capacity- ward Number – Buildcon Ltd., Buildcon 100000 Concrete), , 100000 12006, Dated and Hanumana MT/Yr Valid upto Capacity- MT/Yr 09/01/2016 Explosive(Licen (Stone 31/12/2016 100000 (WMM), Capacity – DG se No.

88

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) Construction Gitti), Valid MT/Yr Valid upto Set Unit E/HQ/MP/22/40 Period- 18 upto (Hot 31/12/2016 85KVA Village- 6(E69894) Valid months 31/12/2016 MixBitumi Shivrajpur, up to nous), Valid from 31/03/2020 Valid upto 01/11/2015 to Agreement 31/12/201 31/10/2020 Place : Mauganj 6 Dated 13/11/2015 Petroleum License – Granted by Patroleum & Explosives Safety Organisation(PE SO) for Village Mangawa- Chakghat Road(410/1,410 /2,410/3,410/4,4 10/5), Rewa with letter no P/CC/MP/14/66 43(P344817) dt 27/11/2015 referring letter dated 26/11/2015 Licensed Qt 40KL.

89

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) Quarry and borrow Permission – 1. Environmental Clearance (EC) for stone quarry granted from DEIAA, Vide letter no. 73/DEIAA/16 Dated 29/06/2016 Village- Shivrajpur, Khasra Number – 3/36,6/10 Area 4.352 Ha. 2. Gram Panchayat permission(NOC ) obtained from Gram Sarpanch, Shivrajpur, Rewa Khasra Number – 3/36 & 6/10 Dt 25/10/2015 3.CampEstablis hment

90

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (b)’ MPDCSP PACKAGE-2, Jabalpur Status of Compliance with Environment Regulations (January - June 2017)

Environmental Consents/Clearances to be obtained by Contractor

Env. Hot Mix Tree cutting Pollution Clearanc Forest Batching Plant Diesel as per IEE / Crusher WMM Plant Under Permission Name of the e for the Clearance/ Plant (Ref Generator Set S. No. / actual trees (Ref (Ref Control obtained from Sub-Project Project Tree cutting (Ref Agreemen (Ref other Pkg. felled Agreement Agreement (PUC) Road from (As per EMP Agreement t Sub- Agreement certificate regulators clause No- Clause- MoEF/ and Agreement) Sub-clause clause Sub-clause No- s for (Ref Agreement 4.18) 111.16) SEIAA No-111.15) No- 111.15) vehicle Clause-4.18) 111.15) Permission- Collector, Rewa issued the letter 749 dt 7.11.2015 for establishment of WMM plant, Crusher, Batching plant at Khasra No. 3/36 Area 20Ha./59.95Ha. Village- Shivrajpur CAR policy- Policy Number 0605004415P10 8620501 Date 26/10/2015 Period of Insurance 26/10/2015 to 25/08/2017 Tree Plantation- Total 1000 Trees Planted

91

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (c)’ MPDCSP PACKAGE-3, Bhopal-2 Status of Compliance with Environment Regulations (January-June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor cutting as Diesel per IEE / Forest Hot Mix Pollution WMM Generat Env. actual trees Clearance/ Batching Plant Under S. Crusher Plant or Set Name of the Clearance for felled Tree Plant (Ref Control No. (Ref (Ref (Ref Permission obtained from other Sub-Project the Project cutting (Ref Agreeme (PUC) / Agreement Agreeme Agreeme regulators Road from MoEF/ (As per EMP Agreement nt Sub- certificate Pkg. clause No- nt nt Sub- (Ref Agreement Clause-4.18) SEIAA and Sub-clause clause s for 4.18) Clause- clause Agreement) No-111.15) No- vehicle 111.16) No- 111.15) 111.15)

92

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (c)’ MPDCSP PACKAGE-3, Bhopal-2 Status of Compliance with Environment Regulations (January-June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor cutting as Diesel per IEE / Forest Hot Mix Pollution WMM Generat Env. actual trees Clearance/ Batching Plant Under S. Crusher Plant or Set Name of the Clearance for felled Tree Plant (Ref Control No. (Ref (Ref (Ref Permission obtained from other Sub-Project the Project cutting (Ref Agreeme (PUC) / Agreement Agreeme Agreeme regulators Road from MoEF/ (As per EMP Agreement nt Sub- certificate Pkg. clause No- nt nt Sub- (Ref Agreement Clause-4.18) SEIAA and Sub-clause clause s for 4.18) Clause- clause Agreement) No-111.15) No- vehicle 111.16) No- 111.15) 111.15) Pkg- 1. Mohanpur- Environmental As per IEE Permission Consent to Establish obtained from pollution control board PUC Labour License issued by Licensing L Behat-Mau (MDR- Clearance is report 286 to work in vide Consent No. CTE-36834 dated 26/04/2016 for Certificate Officer Gwalior district vide License not required as the forest No. 1249/G/L/2015 dated 15-01-2016; 01-02) & Behat numbers of crusher, batching plant, hot mix plant, DG sets and WMM s obtained Mau (MDR-02-03) per EIA trees to be area under plant at village-Sora, Tehsil-Gohad, District-Bhind. for 23 valid up to 31/12/2017. notification Gwalior Length-51.651km cut.Tree vehicles Blasting permission had been 2006 and its cutting District DFO on obtained from the Chief Controller of Agreement Signed amendments permission is issued vide Valid up to 25-04-2017. 25/10/16; Explosive vide License No. date- 06.08.2015 applied by letter No. valid up to 340(54856) dated 06.04.2015. Valid /Ma.Chi./481 Commencement Divisional Consent to Operate obtained from pollution control board 25/05/17 up to 31/03/2020. 5 dated date- Manager, vide Consent No. AW-38085 dated 29/6/2016 for crusher, Petroleum Storage Permission 26/06/2015 09.09.2015 Gwalior to batching plant, hot mix plant and WMM plant at village- Approval from Jt Chief Controller of Gwalior/Bhin Contractor- Sora, Tehsil-Gohad, District-Bhind. Explosives obtained for the installation d/Shivpuri/S of Consumer Diesel Pump at village - M/s KNR Const. Valid upto 31-03-2017 hurepur Sora, Tehsil-Gohad, District-Bhind

Ltd Hyderabad district vide approval No. A/P/CC/MP/14/ Total number of Collector Capacity- 7811(P373899) dated 02/02/2016. Office vide projects roads: 4 Crusher- 10000 MT per year, Sand Source and Water source: letter Total Length-159.82 No.2027/MP Batching Plant-10000 MT per year, Sand and water purchased from local km RDC/2015 Hot MixPlant-335000 m3 per year, vendors Construction dated 16-10- WMMPlant-15000 MT per year. Quarry and Borrow Earth 15. Period- 730 days DG set – 500 KVA and 180 KVA. Permission: As per site Environmental Clearance (EC) survey tree obtained from MP-DEIAA vide letter cutting not No. Q/Khanij/DEIAA/2016 for mines required. located at villages Jiganiafor extraction of stone while Bilheti, Tankoli and Utila for extraction of murrum at Tehsil & District-Gwalior. Contractor’s All Risks Insurance Policy: from the New India Insurance Policy received vide policy No. 45190044160300000001 dated 06/07/2016. Valid up to 31/08/2017. 93

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (c)’ MPDCSP PACKAGE-3, Bhopal-2 Status of Compliance with Environment Regulations (January-June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor cutting as Diesel per IEE / Forest Hot Mix Pollution WMM Generat Env. actual trees Clearance/ Batching Plant Under S. Crusher Plant or Set Name of the Clearance for felled Tree Plant (Ref Control No. (Ref (Ref (Ref Permission obtained from other Sub-Project the Project cutting (Ref Agreeme (PUC) / Agreement Agreeme Agreeme regulators Road from MoEF/ (As per EMP Agreement nt Sub- certificate Pkg. clause No- nt nt Sub- (Ref Agreement Clause-4.18) SEIAA and Sub-clause clause s for 4.18) Clause- clause Agreement) No-111.15) No- vehicle 111.16) No- 111.15) 111.15) Pkg- 2. Murar- Chittora Environmental As per IEE Project Road All the permissions are same as of Road Mohanpur-Behat- PUC All the permissions are same as of L (MDR-01-08) & Clearance is report 80 is not Mau (MDR-01-02) & Behat Mau (MDR-02-03). Certificate Road Mohanpur-Behat-Mau (MDR-01- (MDR-02-08) not required as numbers of passing s obtained 02) & Behat Mau (MDR-02-03). per EIA for 23 Length- 29.25 km trees to be through any notification cut.Tree forest areas. vehicles Agreement Signed 2006 and its on cutting date- 06.08.2015 amendment permission is 25/10/16; Commencement applied by valid up to date- Divisional 25/05/17 09.09.2015 Manager, Gwalior to Contractor- Gwalior/Bhin M/s KNR Const. d/Shivpuri/S Ltd Hyderabad hurepur Total number of district projects roads: 4 Collector Office vide Total Length-159.82 letter km No.2027/MP Construction RDC/2015 Period- 730 days dated 16-10- 15. As per

site survey tree cutting not required. 3.Gata Amayan Environmental As per IEE Project Road All the permissions are same as of Road Mohanpur-Behat- PUC All the permissions are same as of Pkg- (MDR-02-06) Clearance is report 240 is not Mau (MDR-01-02) & Behat Mau (MDR-02-03). Certificate Road Mohanpur-Behat-Mau (MDR-01- L s obtained 02) & Behat Mau (MDR-02-03). Length- 16.42km not required as numbers of passing per EIA trees to be through for 23 Agreement Signed notification vehicles

94

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (c)’ MPDCSP PACKAGE-3, Bhopal-2 Status of Compliance with Environment Regulations (January-June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor cutting as Diesel per IEE / Forest Hot Mix Pollution WMM Generat Env. actual trees Clearance/ Batching Plant Under S. Crusher Plant or Set Name of the Clearance for felled Tree Plant (Ref Control No. (Ref (Ref (Ref Permission obtained from other Sub-Project the Project cutting (Ref Agreeme (PUC) / Agreement Agreeme Agreeme regulators Road from MoEF/ (As per EMP Agreement nt Sub- certificate Pkg. clause No- nt nt Sub- (Ref Agreement Clause-4.18) SEIAA and Sub-clause clause s for 4.18) Clause- clause Agreement) No-111.15) No- vehicle 111.16) No- 111.15) 111.15) date- 06.08.2015 2006 and its cut. forest area. on Commencement amendments. As per site 25/10/16; date- survey tree valid up to 25/05/17. 09.09.2015 cutting is not required. Contractor-

M/s KNR Const.

Ltd Hyderabad Total number of projects roads: 4 Total Length-159.82 km Construction Period- 730 days 4. Mohna Pohri Environmental As per IEE Permission Consent to Establish obtained from pollution control board PUC Labour License issued by Licensing Pkg- (MDR-07-06) Clearance is report 237 of work in vide Consent No. CTE-36817 dated. 25/04/2016 for Gitti Certificate Officer Gwalior district vide License L Nirman (crusher), RMC, hot mix plant and WMM plant at Length- 62.36 km not required as numbers of the forest s have No. 1249/G/L/2015 dated 15-01-2016; per EIA trees to be area under village- Magrouni, Tehsil-Bairad, District-Shivpuri. been valid up to 31/12/2017 Agreement Signed notification cut. Tree Shivpuri Valid upto 24/04/2021 obtained date- 06.08.2015 Blasting license obtained by person 2006 and its cutting district DFO Capacity – for 15 involved in activity from the Chief Commencement amendments. permission is is issued vehicles Crusher-50000 m3 per year, Controller of Explosive vide License date-09.09.2015 applied by vide letter on No. E/HQ/MP/ 22/340 (54856) dated Contractor- Divisional No. RMC- 15000 m3 per year, 15/09/16 06.04.2015; Valid up to 31/03/2020. Manager, DM/1722 (valid up to M/s KNR Const. Hot Mix Plant-20000 m3 per year, Consumer diesel pump installation Gwalior to dated. 20/06/17) WMM Plant-15000 m3 per year. Ltd Hyderabad Gwalior/Bhin 03/03/16. approval from Jt Chief Controller of Explosives obtained vides approval Total number of d/Shivpuri/S DG set – 500 KVA and 180 KVA No. AP/CC/MP/14/7816 (P373914) projects roads: 4 hurepur Consent to Operate obtained from pollution control board dated 02/02/201 at village- Magrouni,

95

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (c)’ MPDCSP PACKAGE-3, Bhopal-2 Status of Compliance with Environment Regulations (January-June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor cutting as Diesel per IEE / Forest Hot Mix Pollution WMM Generat Env. actual trees Clearance/ Batching Plant Under S. Crusher Plant or Set Name of the Clearance for felled Tree Plant (Ref Control No. (Ref (Ref (Ref Permission obtained from other Sub-Project the Project cutting (Ref Agreeme (PUC) / Agreement Agreeme Agreeme regulators Road from MoEF/ (As per EMP Agreement nt Sub- certificate Pkg. clause No- nt nt Sub- (Ref Agreement Clause-4.18) SEIAA and Sub-clause clause s for 4.18) Clause- clause Agreement) No-111.15) No- vehicle 111.16) No- 111.15) 111.15) Total Length-159.82 district vide Consent No. AW-37944 dated 23/06/2016 for Gitti Tehsil-Bairad, District- Shivpuri. km Collector Nirman (crusher), RMC, hot mix plant and WMM plant, at Sand Source and Water source: Office vide vill Magrouni, Teh-Bairad, Dist-Shivpuri. Construction Stone dust used in place of sand and letter Valid up to 29/05/2017. Period- 730 days No.2027/MP water purchased from local vendors. RDC/2015 Capacity – Quarry and Borrow Earth dated 16-10- Gitti Nirman (Crusher)-50000 m3 per year, Permission: 15. RMC- 15000 m3 per year, Environmental Clearance granted from As per site Hot Mix Plant-20000 m3 per year, DEIAA vide letter No.K/524/Khani/ survey tree (DEIAA)/ 4661/ 15/16 dated 13/06/16 WMM Plant-15000 m3 per year. cutting is not for extraction of Morrum/Boulder/Sand required. DG set – 500 KVA and 180 KVA mineral at village-Nainagarh, Tehsil- Bairagarh, District-Shivpuri. Environmental Clearance granted from DEIAA vide letter No. K/525/Khani/(DEIAA)/4889/16 dated 13/06/16 for extraction of Morrum/Boulder/Sand at village- Magrauni, Tehsil-Bairagrh, District- Shivpuri. Insurance Policy Contractor’s All Risks Insurance Policy from the New India Insurance Policy received vide policy No. 45190044160300000001 dated 06/07/2016. Valid up to 31/08/2017.

96

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (c)’ MPDCSP PACKAGE-3, Bhopal-2 Status of Compliance with Environment Regulations (January-June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor cutting as Diesel per IEE / Forest Hot Mix Pollution WMM Generat Env. actual trees Clearance/ Batching Plant Under S. Crusher Plant or Set Name of the Clearance for felled Tree Plant (Ref Control No. (Ref (Ref (Ref Permission obtained from other Sub-Project the Project cutting (Ref Agreeme (PUC) / Agreement Agreeme Agreeme regulators Road from MoEF/ (As per EMP Agreement nt Sub- certificate Pkg. clause No- nt nt Sub- (Ref Agreement Clause-4.18) SEIAA and Sub-clause clause s for 4.18) Clause- clause Agreement) No-111.15) No- vehicle 111.16) No- 111.15) 111.15) 1. Pachwali Environmental As per IEE Permission Consent to Establish from pollution control board PUC Labour License obtained from Pkg- Rannod (MDR-07- Clearance is report 525 of work in videConsent No. CTE-37370 dated 25/05/2016 for Stone Certificate Licensing Officer vide No. 489 dated M 10) & Rannod not required as numbers of the forest Gitti village- Hurry, Tehsil- Khaniyadhana, District- Shivpuri. s have 28/02/2016 obtained from the Pichhore (MDR- per EIA trees to be area under Valid up to 24-05-2021. been Licensing Officer. Valid up to

07-04) notification cut. Shivpuri Consent to Operate from pollution control board obtained 31/12/2016. Length- 60.62 km 2006 and its As per site district DFO videConsent No. AW-42949 dated 15-11-16 for Stone Gitti for 09 Blasting permission obtained vide amendments is issued vehicles Agreement Signed survey tree village- Hurry, Tehsil- Khaniyadhana, District- Shivpuri. Pass No: RE-13/2016/2467332 dated cutting is not vide letter Valid up to 15-11-2017. (valid up to 28/04/16. date- 09.11.2015 No. 27/05/17 required. Petroleum Storage Permission: Commencement DM/7394 Capacity- date-24.11.2015 Shivpuri Crusher-40000 m3 per year, Diesel purchased from local vendor Contractor- dated Batching Plant-500 m3 per year, hence permission for petroleum 07/11/16. 3 storage is not required. M/s PATH -WARAD Hot Mix Plant-15000 m per year, 3 Infra projects (JV) WMM-3000 m per year Sand Source and Water source: Sand and water purchased from local Total number of projects Roads: 3 CTE & CTO for DG Set is not required due to electricity vendors. Sand purchased with valid transit passes. Total Length- purchased from MP electricity Board. 110.620 km Quarry and Borrow Earth Permission: Construction Permission from DEIAA Distt Shivpuri Period- 640 days obtained vide letter क्रम /車क 1556/खनि/(DEIAA)/10/16 शिवपुरीdated 16-11-16 for extraction of Gitti/ Stone. Permission from DEIAA distt Shivpuri obtained vide letter क्र./1557/ खनि/(DIEAA) /11/16 शिवपुरीdated 16- 11-16 for extraction of Mitti/Murom.

97

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (c)’ MPDCSP PACKAGE-3, Bhopal-2 Status of Compliance with Environment Regulations (January-June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor cutting as Diesel per IEE / Forest Hot Mix Pollution WMM Generat Env. actual trees Clearance/ Batching Plant Under S. Crusher Plant or Set Name of the Clearance for felled Tree Plant (Ref Control No. (Ref (Ref (Ref Permission obtained from other Sub-Project the Project cutting (Ref Agreeme (PUC) / Agreement Agreeme Agreeme regulators Road from MoEF/ (As per EMP Agreement nt Sub- certificate Pkg. clause No- nt nt Sub- (Ref Agreement Clause-4.18) SEIAA and Sub-clause clause s for 4.18) Clause- clause Agreement) No-111.15) No- vehicle 111.16) No- 111.15) 111.15) Permission from DEIAA distt Shivpuri obtained vide letter क्र./1558/ खनि/(DIEAA) /11/16 शिवपुरीdated 16- 11-16 for extraction of Mitti/Murom. Permission from DEIAA distt Shivpuri obtained vide letter क्र./1562-1564/ खनि/(DIEAA) /11/16 शिवपुरीdated 27- 12-2016 for extraction of Mitti/Murom.

Permission of Borrow Earth(Mining) has issued by Collector(Mining) Shivpuri vide letter number – 1.क्र./ 1645-47/ अथ ईअिज्ञु /15/16 शिवपुरीदिि क26-11-16 for extraction of Boulder/stone. 2.क्रम /車क 751/अथ ईअिुज्ञ /2015 शिवपुरीdated 05-07-16.forextraction of Boulder/stone. Who is also the Chairman of DEIAA.

Car Insurance Policy Car Insurance Policy No- 380203/44/16/5600000012 issued by National Insurance Company Limited. Contractor Plant and Machinery

98

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (c)’ MPDCSP PACKAGE-3, Bhopal-2 Status of Compliance with Environment Regulations (January-June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor cutting as Diesel per IEE / Forest Hot Mix Pollution WMM Generat Env. actual trees Clearance/ Batching Plant Under S. Crusher Plant or Set Name of the Clearance for felled Tree Plant (Ref Control No. (Ref (Ref (Ref Permission obtained from other Sub-Project the Project cutting (Ref Agreeme (PUC) / Agreement Agreeme Agreeme regulators Road from MoEF/ (As per EMP Agreement nt Sub- certificate Pkg. clause No- nt nt Sub- (Ref Agreement Clause-4.18) SEIAA and Sub-clause clause s for 4.18) Clause- clause Agreement) No-111.15) No- vehicle 111.16) No- 111.15) 111.15) insurance vide policy No: 380203/11/16/ 3100000053 by National Insurance Company Limited.

2.Bhashula Environmental As per IEE Permission Consent to Establish from pollution control board PUC Labour License obtained from Pkg- Chainpur Clearance is report 506 of work in videConsent No. CTE-13897 dated 26.03.17 for Stone Gitti Certificate Licensing Officer vide No. 2811 dated M Vijayapur not required as numbers of the forest village- Hurry, Tehsil- Khaniyadhana, District- Shivpuri. s have 12.01.2017 obtained from the Dhanrawad (MDR- per EIA trees to be area under Valid up to 25-03-2018. been Licensing Officer. Valid up to 06-09) notification cut. Guna district obtained 12/12/2017. Consent to Operate from pollution control board videreceipt 2006 and its DFO is for 09 Blasting permission obtained On the Length-20 km As per site No. 298329 dated on 28-02-17 for Stone Gitti village- amendments survey tree issued vide vehicles name of person involve in blasting Agreement Signed letter No. Hurry, Tehsil- Khaniyadhana, District- Shivpuri. (valid up to date- 09.11.2015 cutting is not Valid up to 25-03-2018. activities vide Pass No: RE- required. DM/ 2017/ 27/05/17 13/2016/1220508 dated 28/02/16. Commencement 1356 Guna Petroleum Storage Permission: date- dated Capacity- Stone gitti-50000 m3 per year Diesel purchased from local vendor 24.11.2015 08/02/2017. Hot Mix Plant-20000 m3 per year hence permission for petroleum Contractor- Crusher-2,50,000 m3 per year storage is not required. M/s PATH -WARAD WMM Plant-3000 m3 per year Sand Source and Water source: Infra projects (JV) RMC Plant-1000 m3 per year Sand and water purchased from local vendors. Sand purchased with valid Total number of transit passes. projects Roads: 3 DG Set is not established by the contractor, electricity purchased from MP electricity Board. Quarry and Borrow Earth Total Length- Permission: 110.620 km Permission from DEIAA Distt Shivpuri

99

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (c)’ MPDCSP PACKAGE-3, Bhopal-2 Status of Compliance with Environment Regulations (January-June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor cutting as Diesel per IEE / Forest Hot Mix Pollution WMM Generat Env. actual trees Clearance/ Batching Plant Under S. Crusher Plant or Set Name of the Clearance for felled Tree Plant (Ref Control No. (Ref (Ref (Ref Permission obtained from other Sub-Project the Project cutting (Ref Agreeme (PUC) / Agreement Agreeme Agreeme regulators Road from MoEF/ (As per EMP Agreement nt Sub- certificate Pkg. clause No- nt nt Sub- (Ref Agreement Clause-4.18) SEIAA and Sub-clause clause s for 4.18) Clause- clause Agreement) No-111.15) No- vehicle 111.16) No- 111.15) 111.15) Construction obtained vide letter क्रम /車क Period- 640 days 2026/DEIAA / 2017गुि दिि 車क8/03/2017 for extraction of Gitti/ Stone. Permission for extraction of Boulder stone obtainedfrom Municipal Corporation vide letter क्रम /車क 3186 / ि. प . / र - वव/2016दिि 車क 16/12/2016. Environmental clearance granted by DIEAA for extraction of Mitti/Murom vide letter No. क्रम /車क 2027 /DIEAA/ 2017 Guna dated 08.03.2017. letter No. क्रम /車क 2030 /DIEAA/ 2017 Guna dated 08.03.2017. letter No. क्रम /車क 2032/DIEAA/ 2017 Guna dated 08.03.2017. letter No. क्रम /車क 2033 /DIEAA/ 2017 Guna dated 08.03.2017. letter No. क्रम /車क 2035 /DIEAA/ 2017 Guna dated 08.03.2017 Car Insurance Policy Car Insurance Policy No-

100

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (c)’ MPDCSP PACKAGE-3, Bhopal-2 Status of Compliance with Environment Regulations (January-June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor cutting as Diesel per IEE / Forest Hot Mix Pollution WMM Generat Env. actual trees Clearance/ Batching Plant Under S. Crusher Plant or Set Name of the Clearance for felled Tree Plant (Ref Control No. (Ref (Ref (Ref Permission obtained from other Sub-Project the Project cutting (Ref Agreeme (PUC) / Agreement Agreeme Agreeme regulators Road from MoEF/ (As per EMP Agreement nt Sub- certificate Pkg. clause No- nt nt Sub- (Ref Agreement Clause-4.18) SEIAA and Sub-clause clause s for 4.18) Clause- clause Agreement) No-111.15) No- vehicle 111.16) No- 111.15) 111.15) 380203/44/16/5600000012 issued by National Insurance Company Limited. Contractor Plant and Machinery insurance vide policy No: 380203/11/16/ 3100000053 by National Insurance Company Limited. 3.Ashok Nagar Environmental As per IEE Permission Consent to Establish from pollution control board obtained PUC Labour License obtained from Pkg- Thubon (i/c Kolua Clearance is report 679 obtained vide Consent No. CTE-37946 dated 23/06/2016 for Stone Certificate Licensing Officer vide letter No. M road) (MDR-08- not required as numbers of from DFO Gitti at village- Rajebamora, Tehsil- Shadoura, and District- s have 17/ASKN/CL/16 dated 15.01.16 11) Length-30.00 per EIA trees to be forest Ashok Nagar. been obtained from the Licensing Officer. km notification cut. department Valid upto-22-06-2021. obtained Valid upto 31/12/2016. 2006 and its Ashok-nagar for 10 Blasting permission obtained vide Agreement Signed As per site (M.P.) vide Consent to Operate obtained from pollution control board date- 09.11.2015 amendments survey tree vehicles Pass No: RE/13/2016/1220508 dated their letter vide Consent No. AW-38456 dated 23/07/2016 for Stone (valid up to 28/02/16. Commencement cutting is not No: क्रम /車क Gitti at village- Rajebamora, Tehsil- Shadoura, and District- 25/07/17 Petroleum Storage Permission: date- required. Ashok Nagar. Diesel purchased from local vendor 24.11.2015 डी. एम./ Valid up to 30-06-2017. hence permission for petroleum Contractor- 17/122 Capacity- storage is not required. M/s PATH -WARAD अिोकिगर Crusher-50000 m3 per year, Sand Source and Water source: 3 Infra projects (JV) Batching Plant-1000 m per year, Sand and water purchased from local 3 Total number of Hot Mix Plant-20000 m per year vendors. Sand purchased with valid 3 projects Roads: 3 WMM-3000 m per year. transit passes. Total Length- Quarry and Borrow Earth 110.620 km DG Set is not established by the contractor, electricity Permission: purchased from MP electricity Board. Construction Permissions from Office of District Period- 640 days Collector (Mineral Branch) for borrow area/quarry obtained vide letter.क्रम /車क

101

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (c)’ MPDCSP PACKAGE-3, Bhopal-2 Status of Compliance with Environment Regulations (January-June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor cutting as Diesel per IEE / Forest Hot Mix Pollution WMM Generat Env. actual trees Clearance/ Batching Plant Under S. Crusher Plant or Set Name of the Clearance for felled Tree Plant (Ref Control No. (Ref (Ref (Ref Permission obtained from other Sub-Project the Project cutting (Ref Agreeme (PUC) / Agreement Agreeme Agreeme regulators Road from MoEF/ (As per EMP Agreement nt Sub- certificate Pkg. clause No- nt nt Sub- (Ref Agreement Clause-4.18) SEIAA and Sub-clause clause s for 4.18) Clause- clause Agreement) No-111.15) No- vehicle 111.16) No- 111.15) 111.15) खनि/ 3-6/ अथ ईअिुज्ञ -पत्र /2016. Environmental Clearance granted by DEIAAvide letter No. 1-8/DEIAA/16 dated 30/05/2016 for the extraction of Basalt Stone at village- Rajebamora, Tehsil- Shadoura, District-Ashok Nagar. Capacity-73549 m3 per year. Permission from DEIAA distt Ashoknagar obtained vide Letter No. 07/DIEAA/16 dated 20.07.2016 for extraction of Mitti/Murom. Permission from DEIAA distt Ashoknagar obtained vide Letter No. 07/DIEAA/16 dated 20.07.2016 for extraction of Mitti/Murom. Environmental Clearance granted by DEIAAvide letter No. 1-8/DEIAA/16 dated 30/05/2016 for the extraction of Basalt Stone at village- Rajebamora, Tehsil- Shadoura, District-Ashok Nagar. Capacity-73549 m3 per year. CAR Policy Car Insurance Policy No- 380203/44/16/5600000012 issued by National Insurance Company Limited. Contractor Plant and Machinery insurance vide policy No:

102

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (c)’ MPDCSP PACKAGE-3, Bhopal-2 Status of Compliance with Environment Regulations (January-June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor cutting as Diesel per IEE / Forest Hot Mix Pollution WMM Generat Env. actual trees Clearance/ Batching Plant Under S. Crusher Plant or Set Name of the Clearance for felled Tree Plant (Ref Control No. (Ref (Ref (Ref Permission obtained from other Sub-Project the Project cutting (Ref Agreeme (PUC) / Agreement Agreeme Agreeme regulators Road from MoEF/ (As per EMP Agreement nt Sub- certificate Pkg. clause No- nt nt Sub- (Ref Agreement Clause-4.18) SEIAA and Sub-clause clause s for 4.18) Clause- clause Agreement) No-111.15) No- vehicle 111.16) No- 111.15) 111.15) 380203/11/16/ 3100000053 by National Insurance Company Limited.

1.Maksudanganj- Environmental As per IEE Project road Consent to Establish obtained from pollution control board PUC All the permissions are same as Pkg- Najeerabad Clearance is report 169 is not vide Consent No.-CTE-35741, dated 03/03/2016 at Village Certificate Berasia Najeerabad Road (MDR-23- N (MDR-06-03) & not required as numbers of passing & Post - Runaha, District-Bhopal. s obtained 06) for 35 Najeerabad per EIA trees to be through Valid upto- 14/02/2017 Maksudangarh notification cut. forest area. vehicles on (MDR-23-08) 2006 and its Length-31.225 km amendments Consent to Operate obtained from pollution control board 10/08/16 As per actual (valid up to Agreement Signed vide Consent No. AWH-36684 dated 20/04/2016 at Village site survey & Post - Runaha, District-Bhopal. 25/03/17 date- 06.08.2015 tree cutting Commencement is not Valid upto-09/03/2017 date- required. Capacity- 3 09.09.2015 Crusher-100000 m per year, Contractor- Batching Plant-15000m3 per year, 3 M/s KCC Buildcon Hot Mix Plant-25000 m per year, Ltd WMM-25000 m3 per year Total number of DG set-452 KLW project roads;3 Total Length-98.750 km Construction Period- 640 days

103

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (c)’ MPDCSP PACKAGE-3, Bhopal-2 Status of Compliance with Environment Regulations (January-June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor cutting as Diesel per IEE / Forest Hot Mix Pollution WMM Generat Env. actual trees Clearance/ Batching Plant Under S. Crusher Plant or Set Name of the Clearance for felled Tree Plant (Ref Control No. (Ref (Ref (Ref Permission obtained from other Sub-Project the Project cutting (Ref Agreeme (PUC) / Agreement Agreeme Agreeme regulators Road from MoEF/ (As per EMP Agreement nt Sub- certificate Pkg. clause No- nt nt Sub- (Ref Agreement Clause-4.18) SEIAA and Sub-clause clause s for 4.18) Clause- clause Agreement) No-111.15) No- vehicle 111.16) No- 111.15) 111.15) Pkg- 2. Berasia Environmental As per IEE Project road Consent to Establish obtained from pollution control board PUC Labour Licence obtained from N Najeerabad Clearance is report 108 is not vide Consent No.-CTE-35741, dated 03/03/2016 at Village Certificate Licensing Officer vide letter (MDR-23-06) not required as numbers of passing & Post - Runaha, District-Bhopal. s have No.1536/BPL/2016 dated per EIA been 21/04/20166. Valid up to 31/12/2016 Length-30.675 km trees to be through Valid up to- 14/02/2017 notification cut. forest area obtained Blasting permission: Agreement Signed 2006 and its for 30 There is no mining involve in the As per site date- 06.08.2015 amendments Consent to Operate obtained from pollution control board vehicles project hence blasting permission not survey tree on01/08/1 required. Commencement cutting is not vide Consent No. AWH-36684 dated 20/04/2016 at Village date- & Post - Runaha, District-Bhopal. 6. Valid up Petroleum Storage Permission: required to- Diesel purchased from local vendor 09.09.2015 Valid upto-09/03/2017 01/08/17. hence permission for petroleum Contractor- Capacity- storage is not required. M/s KCC Buildcon Crusher-100000 m3 per year, Sand Source and Water source: Ltd Batching Plant-15000m3 per year, Sand and water purchased from local Total number of 3 vendors. Sand purchased with valid Hot Mix Plant-25000 m per year, transit passes. project roads;3 3 WMM-25000 m per year Quarry and Borrow Earth Total Length-98.750 DG set-452 KLW Permission: km Soil, Murom, Stone Bolder are being Construction purchased by the contractor form Period- 640 days outsource agencies with valid Transit Pass (TP). Collector Permission for Borrow area: Permission obtained from the Office of District Collector (Mineral Branch) for transportation of Soil/Murom/Boulder from village-Barchhikhera, Tehsil- Berasia, District-Bhopal vide letter No.789/khanij/2016 dated 16/03/2016.

104

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (c)’ MPDCSP PACKAGE-3, Bhopal-2 Status of Compliance with Environment Regulations (January-June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor cutting as Diesel per IEE / Forest Hot Mix Pollution WMM Generat Env. actual trees Clearance/ Batching Plant Under S. Crusher Plant or Set Name of the Clearance for felled Tree Plant (Ref Control No. (Ref (Ref (Ref Permission obtained from other Sub-Project the Project cutting (Ref Agreeme (PUC) / Agreement Agreeme Agreeme regulators Road from MoEF/ (As per EMP Agreement nt Sub- certificate Pkg. clause No- nt nt Sub- (Ref Agreement Clause-4.18) SEIAA and Sub-clause clause s for 4.18) Clause- clause Agreement) No-111.15) No- vehicle 111.16) No- 111.15) 111.15) Permission obtained from the Office of District Collector (Mineral Branch) for transportation of Soil/Murrum /Boulder from village-Pipalia Husnabad, Tehsil- Berasia, District-Bhopal vide letter No. 796/Khanij/2016 dated 16/03/2016. Valid upto-15.03.2016. Permission obtained from the Office of District Collector (Mineral Branch) for transportation of Murrum/Boulder from village-Daamkheda Tehsil-Berasia, District-Bhopal vide letter No. 2373/खनिज/आ.अि./ु 2015 भोप लdated 04/09/2015. Valid upto-03.09.2017. CAR Policy Car Insurance Policy No- 913102006127950000 issued by L & T Insurance Company Limited.

105

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (c)’ MPDCSP PACKAGE-3, Bhopal-2 Status of Compliance with Environment Regulations (January-June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor cutting as Diesel per IEE / Forest Hot Mix Pollution WMM Generat Env. actual trees Clearance/ Batching Plant Under S. Crusher Plant or Set Name of the Clearance for felled Tree Plant (Ref Control No. (Ref (Ref (Ref Permission obtained from other Sub-Project the Project cutting (Ref Agreeme (PUC) / Agreement Agreeme Agreeme regulators Road from MoEF/ (As per EMP Agreement nt Sub- certificate Pkg. clause No- nt nt Sub- (Ref Agreement Clause-4.18) SEIAA and Sub-clause clause s for 4.18) Clause- clause Agreement) No-111.15) No- vehicle 111.16) No- 111.15) 111.15) 3. Vidisha Berasia Environmental As per IEE Project road All the permissions are same as Berasia Najeerabad Road PUC All the permissions are same as Pkg- (MDR-23-10) & Clearance is report 108 is not (MDR-23-06). Certificate Berasia Najeerabad Road (MDR-23- N (MDR-27-01) not required as numbers of passing s have 06). per EIA been Length- 36.85 km. trees to be through notification cut. forest area obtained Agreement Signed 2006 and its for 40 date- 06.08.2015 amendments vehicles Commencement As per site on date- 09.09.2015 survey tree 10/08/16 cutting is not (valid up to Contractor- required 25/03/17 M/s KCC Buildcon Ltd Total number of project roads;3 Total Length-98.750 km Construction Period- 640 days

1. Dewas Newari Environmental As per IEE Project road Consent to Operate obtained from pollution control board PUC Labour License obtained from Pkg- (MDR-10-02) Clearance is report 94 is not vide Consent No. AWH-3381 dated 09.03.2014 at Village & Certificate Licensing Officer vide License No: 669 O Length- 26.775 km not required as numbers of passing Post –34/1, Bus Stand Shajapur s have dated 24-03-17 valid up to 31/12/2017. Agreement Signed been Blasting permission: per EIA trees to be through Valid up to- 09.03.2018 date- 10.11.2015 notification cut. forest area. obtained There is no mining involve in the 2006 and its Capacity- for 05 project hence blasting permission not Commencement As per site 3 date- 05.12.15 amendments Crusher-100000 MT per year, vehicles required. survey tree on 3/06/16 Petroleum Storage Permission: Batching Plant-15000 MT3 per year, Contractor- cutting is not (valid up to Diesel purchased from local vendor required 3 M/s Gannon Hot Mix Plant-25000 MT per year, 12/12/16) hence permission for petroleum

106

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (c)’ MPDCSP PACKAGE-3, Bhopal-2 Status of Compliance with Environment Regulations (January-June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor cutting as Diesel per IEE / Forest Hot Mix Pollution WMM Generat Env. actual trees Clearance/ Batching Plant Under S. Crusher Plant or Set Name of the Clearance for felled Tree Plant (Ref Control No. (Ref (Ref (Ref Permission obtained from other Sub-Project the Project cutting (Ref Agreeme (PUC) / Agreement Agreeme Agreeme regulators Road from MoEF/ (As per EMP Agreement nt Sub- certificate Pkg. clause No- nt nt Sub- (Ref Agreement Clause-4.18) SEIAA and Sub-clause clause s for 4.18) Clause- clause Agreement) No-111.15) No- vehicle 111.16) No- 111.15) 111.15) Dunkerly WMM-25000 MT3 per year storage is not required. Total number of DG set-452 KLW Sand Source and Water source: project roads:4 Sand and water purchased from local vendors. Sand purchased with valid Total Length- transit passes. 129.135 km Quarry and Borrow Earth Construction Permission: Period- 730 days Permission obtained from Office of District Collector (Mineral Branch) Distt Dewas for the extraction of Stone/Boulder vide letter No.क्रम 車क 1966/ खनिज/ लीज/2015-16 Dewasदिि 車क 30.10.15. Prior environmental clearance granted by DEIAA vide letter No. 4926/SEIAA/15 dated 18.08.15 for extraction of Stone/Boulder at village- Rabadiya, Tehsil-Dewas, District Dewas for the capacity of 10260 cum/yr. Prior environmental clearance granted by DEIAA Distt Shajapur (M.P.)vide letter No. 726/Mining/ DEIAA/2016 Shajapur dated 17.06.2016 for extraction of Soil/ Murrum Quarry in area of 04 hectare with the capacity of 1,30,000 Cum/yr. Insurance Policy: Obtained from L & T Insurance

107

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (c)’ MPDCSP PACKAGE-3, Bhopal-2 Status of Compliance with Environment Regulations (January-June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor cutting as Diesel per IEE / Forest Hot Mix Pollution WMM Generat Env. actual trees Clearance/ Batching Plant Under S. Crusher Plant or Set Name of the Clearance for felled Tree Plant (Ref Control No. (Ref (Ref (Ref Permission obtained from other Sub-Project the Project cutting (Ref Agreeme (PUC) / Agreement Agreeme Agreeme regulators Road from MoEF/ (As per EMP Agreement nt Sub- certificate Pkg. clause No- nt nt Sub- (Ref Agreement Clause-4.18) SEIAA and Sub-clause clause s for 4.18) Clause- clause Agreement) No-111.15) No- vehicle 111.16) No- 111.15) 111.15) Company vide Policy No. 91310200612750000 dated 22/12/2015. Valid upto 14/12/2017. 2. Mahidpur- Environmental As per IEE Project road Consent to Operate obtained from pollution control board PUC Labour License obtained from Pkg- Paanvihar-Jeevaji Clearance is report 202 is not vide Consent No. AWH-3381 dated 09.03.2014 at Village & Certificate Licensing Officer vide License No: 669 O Nagar (MDR -09- not required as numbers of passing Post –34/1, Bus Stand Shajapur s have dated 24-03-17 valid up to 31/12/2017. 04) per EIA trees to be through been Blasting permission: Length- 31.935 km notification cut. Capacity- obtained There is no mining involve in the forest area. 3 Agreement Signed 2006 and its Crusher-100000 MT per year, for 05 project hence blasting permission not

date- 10.11.2015 amendments As per site Batching Plant-15000 MT3 per year, vehicles required. Commencement survey tree 3 on 3/06/16 Hot Mix Plant-25000 MT per year, Petroleum Storage Permission: date- 05.12.15 cutting is not 3 (valid up to Contractor- required WMM-25000 MT per year 12/12/16) Diesel purchased from local vendor hence permission for petroleum M/s Gannon DG set-452 KLW Dunkerly storage is not required. Sand Source and Water source: Total number of project roads:4 Sand and water purchased from local Total Length- vendors. Sand purchased with valid 129.135 km transit passes. Construction Borrow and Qarry Permissions: Period- 730 days Prior environmental clearance granted by DEIAA Distt Shajapur (M.P.)vide letter No. 721/ खनिज/ DEIAA/2016 Shajapur dated 17.06.2016 for extraction of Stone Quarry in area of 3.994 hectare with the capacity of 2,80,000 Cum/yr. Prior environmental clearance granted by DEIAA Distt Shajapur (M.P.)vide letter No. 726/Mining/ DEIAA/2016

108

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (c)’ MPDCSP PACKAGE-3, Bhopal-2 Status of Compliance with Environment Regulations (January-June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor cutting as Diesel per IEE / Forest Hot Mix Pollution WMM Generat Env. actual trees Clearance/ Batching Plant Under S. Crusher Plant or Set Name of the Clearance for felled Tree Plant (Ref Control No. (Ref (Ref (Ref Permission obtained from other Sub-Project the Project cutting (Ref Agreeme (PUC) / Agreement Agreeme Agreeme regulators Road from MoEF/ (As per EMP Agreement nt Sub- certificate Pkg. clause No- nt nt Sub- (Ref Agreement Clause-4.18) SEIAA and Sub-clause clause s for 4.18) Clause- clause Agreement) No-111.15) No- vehicle 111.16) No- 111.15) 111.15) Shajapur dated 17.06.2016 for extraction of Soil/ Murrum Quarry in area of 04 hectare with the capacity of 1,30,000 Cum/yr. Insurance Policy: Obtained from L & T Insurance Company vide Policy No. 91310200612750000 dated 22/12/2015. Valid up to 14/12/2017. Pkg- 3. Shajapur- Environmental As per IEE Project road All the permissions are same as of Mahidpur Panvihar PUC All the permissions are same as of O Bercha (MDR -11- Clearance is report 202 is not Jeevaji Nagar Road ( MDR-09-04) permission Mahidpur Panvihar Jeevaji Nagar 02) not required as numbers of passing s are same Road ( MDR-09-04) Length- 16.435 km per EIA trees to be through as of Agreement date- notification cut. forest area Mahidpur 10.11.2015 2006 and its Panvihar Commencement amendments As per site Jeevaji date- 05.12.15 survey tree Nagar Contractor- cutting is not Road ( M/s Gannon required MDR-09- Dunkerly 04) Total number of project roads:4 Total Length- 29.135 km Construction Period- 730 days

109

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (c)’ MPDCSP PACKAGE-3, Bhopal-2 Status of Compliance with Environment Regulations (January-June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor cutting as Diesel per IEE / Forest Hot Mix Pollution WMM Generat Env. actual trees Clearance/ Batching Plant Under S. Crusher Plant or Set Name of the Clearance for felled Tree Plant (Ref Control No. (Ref (Ref (Ref Permission obtained from other Sub-Project the Project cutting (Ref Agreeme (PUC) / Agreement Agreeme Agreeme regulators Road from MoEF/ (As per EMP Agreement nt Sub- certificate Pkg. clause No- nt nt Sub- (Ref Agreement Clause-4.18) SEIAA and Sub-clause clause s for 4.18) Clause- clause Agreement) No-111.15) No- vehicle 111.16) No- 111.15) 111.15) Pkg- 4. Shajapur- Environmental As per IEE Project road Consent to Operate obtained from pollution control board PUC Labour License obtained from O Dupada-Kanad- Clearance is report 421 is not vide Consent No. AWH-3381 dated 09.03.2014 at Village & Certificate Licensing Officer vide License No: 669 Pachlana Pilvas- not required as numbers of passing Post –34/1, Bus Stand Shajapur s have dated 24-03-17 valid up to 31-12- Nalkheda (MDR- per EIA trees to be through been 2017. notification Capacity- obtained Blasting permission: 11-13) cut. forest area 3 2006 and its Crusher-100000 MT per year, for 05 There is no mining involve in the Length- 53.99 km amendments As per site vehicles project hence blasting permission not survey tree Batching Plant-15000 MT3 per year, Agreement Signed 3 on required. date- 10.11.2015 cutting is not Hot Mix Plant-25000 MT per year, 3 13/06/201 Petroleum Storage Permission: required WMM-25000 MT per year Commencement 6 (valid up Diesel purchased from local vendor date- 05.12.15 DG set-452 KLW to hence permission for petroleum 12/12/201 Contractor- storage is not required. 6) Sand Source and Water source: M/s Gannon Sand and water purchased from local Dunkerly vendors. Sand purchased with valid Total number of transit passes. project roads:4 Quarry and Borrow Earth Total Length- Permission: 129.135 km Permission obtained from Office of Construction District Collector (Mineral Branch) Distt Shajapur for the extraction of Period- 730 days Soil/Murom vide letter No.क्रम /車क खनिज/ 2016/474 Shajapur दिि 車क 11.04.16 Prior environmental clearance granted by DEIAA Distt Shajapur (M.P.) vide letter No. 721/ खनिज/ DEIAA/2016 Shajapur dated 17.06.2016 for extraction of Stone

110

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (c)’ MPDCSP PACKAGE-3, Bhopal-2 Status of Compliance with Environment Regulations (January-June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor cutting as Diesel per IEE / Forest Hot Mix Pollution WMM Generat Env. actual trees Clearance/ Batching Plant Under S. Crusher Plant or Set Name of the Clearance for felled Tree Plant (Ref Control No. (Ref (Ref (Ref Permission obtained from other Sub-Project the Project cutting (Ref Agreeme (PUC) / Agreement Agreeme Agreeme regulators Road from MoEF/ (As per EMP Agreement nt Sub- certificate Pkg. clause No- nt nt Sub- (Ref Agreement Clause-4.18) SEIAA and Sub-clause clause s for 4.18) Clause- clause Agreement) No-111.15) No- vehicle 111.16) No- 111.15) 111.15) Quarry in area of 3.994 hectare with the capacity of 2,80,000 Cum/yr. Prior environmental clearance granted by DEIAA Distt Shajapur (M.P.) vide letter No. 719/Mining/DEIAA/2016 Shajapur dated 17.06.2016 for extraction of Soil/ Murrum Quarry in area of 04 hectare with the capacity of 1,40,000 Cum/yr. Car Policy Obtained from L & T Insurance Company vide Policy No. 91310200612750000 dated 22/12/2015. Valid upto 14/12/2017. Pkg- 1. Sanver-Kshipra Environmental As per IEE Project road Material Consent to Consent to Establish obtained PUC 1 Labour License obtained from P (MDR-15-18) Clearance is report 93 is not purchased Establish from pollution control board vide Certificate Licensing Officer vide License from Jindal obtained s have Length- 19.619 km not required as numbers of passing CTE-36641, application dated No.1090/DR/2016 dated 15.02.2017. per EIA trees to be through Arth Mines from 04.04.16 at Village Hatunia, been Valid up to 31.12.2017. Agreement Signed Partner pollution obtained notification cut. forest area Tehsil-Sanwer, Distt Indore Blasting Permission date- 07.08.2015 2006 and its Nyya control (M.P.) valid up to 31.08.17 for 14 As per actual Jindal and board vide vehicles Blasting permission obtained by vide Commencement amendments survey no Consent to Operate from date-15.09.15 Mansh CTE- on License No.E/CC/MP/25/507 tree cutting Jindal 36641, pollution control board vide 18/08/16 (E66670), Registration No. MP-11/G- Contractor- is required. having application AWH-37385, application dated (valid up to 0698. 11.05.16 at Village Keshripura Ranjit Buildcon third party dated 18/08/17) Petroleum Storage Permission: Ltd. agreement 04.04.16 (Sanwer), Thesil-Sanwer, Distt Indore (M.P.) valid up to Diesel purchased from local vendor Total number of with the at Village 31.03.17 hence permission for petroleum project roads: 4 contractor. Hatunia, storage is not required. Capacity- Total Length- Material Thesil- Sand Source and Water source: 102.712 km purchased Sanwer, Hot Mix Plant- 60000 m3/yr Sand and water purchased from local

111

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (c)’ MPDCSP PACKAGE-3, Bhopal-2 Status of Compliance with Environment Regulations (January-June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor cutting as Diesel per IEE / Forest Hot Mix Pollution WMM Generat Env. actual trees Clearance/ Batching Plant Under S. Crusher Plant or Set Name of the Clearance for felled Tree Plant (Ref Control No. (Ref (Ref (Ref Permission obtained from other Sub-Project the Project cutting (Ref Agreeme (PUC) / Agreement Agreeme Agreeme regulators Road from MoEF/ (As per EMP Agreement nt Sub- certificate Pkg. clause No- nt nt Sub- (Ref Agreement Clause-4.18) SEIAA and Sub-clause clause s for 4.18) Clause- clause Agreement) No-111.15) No- vehicle 111.16) No- 111.15) 111.15) Construction with valid Distt Wet Mix Plant- 120000 m3/yr vendors. Sand purchased with valid Period- 640 days transit Indore DG Sets- 180 KVA transit passes. passes. (M.P.) Quarry and Borrow Earth valid up to Permission: 31.08.17 Consent to Permission obtained from Office of Operate District Collector (Mineral Branch) from Indore for the extraction of Murom pollution vide letter No.क्रम 車क 2551/ खनिज/ control 2015 इ車िौरदिि 車क 24.11.15. board vide Prior environmental clearance AWH- granted by DEIAA Distt Indore 37386 (M.P.) vide letter No. Endt valid up to no./DEIAA/2016/960 dated 31.03.17 19.05.2016 for extraction of Stone Capacity- Quarry in area of 3.20 hectare with 28000 the capacity of 81,000 Cum/yr. m3/yr Prior environmental clearance granted by DEIAA Distt Indore (M.P.) vide letter No. Endt No. 788/Mining /DEIAA/2016 Indore dated 19.07.2016 for extraction of Soil/Morum in area of 4.00 hectare with the capacity of 1,30,000 Cum/yr. Insurance Policy Contractor’s All Risks Insurance Policy obtained from The New India Assurance Co. Ltd. obtained vide Policy No. 2106004415030000023 dated

112

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (c)’ MPDCSP PACKAGE-3, Bhopal-2 Status of Compliance with Environment Regulations (January-June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor cutting as Diesel per IEE / Forest Hot Mix Pollution WMM Generat Env. actual trees Clearance/ Batching Plant Under S. Crusher Plant or Set Name of the Clearance for felled Tree Plant (Ref Control No. (Ref (Ref (Ref Permission obtained from other Sub-Project the Project cutting (Ref Agreeme (PUC) / Agreement Agreeme Agreeme regulators Road from MoEF/ (As per EMP Agreement nt Sub- certificate Pkg. clause No- nt nt Sub- (Ref Agreement Clause-4.18) SEIAA and Sub-clause clause s for 4.18) Clause- clause Agreement) No-111.15) No- vehicle 111.16) No- 111.15) 111.15) 05/10/2015. Valid upto 04/07/2017. Pkg- 2. Kanvan- Environmental As per IEE Project road Consent to Establish obtained from pollution Electricit PUC Labour License is same as for P Mangod (MDR-26- Clearance is report 397 is not control board vide Survey No- 50/3/1, CTE- y Certificate Sanver-Kshipra (MDR-15-18) Road. 22) Length- not required as numbers of passing 39694, application dated 21.03.16 at Village purchase s have Blasting Permission 47.434 km per EIA trees to be through Khiledi, Thesil-Badnawar, Distt Dhar (M.P.) d from been Blasting permission (Third party) Agreement Signed notification cut. forest area valid up to 31.08.17 MPEB. obtained obtained vide License No. date- 07.08.2015 2006 and its Hence for 14 E/HQ/MP/22/368/E62129 Registration Commencement Permission Consent to Operate obtained from pollution no DG vehicles dated 13-06-11. amendments of tree control board vide Consent No. AW-41838 at date-15.09.15. sets are on Petroleum Storage Permission: Contractor- cutting for Village Khiledi, Thesil-Badnawar, Distt Dhar establish 18/08/16 264 trees (M.P.) Diesel purchased from local vendor Ranjit Buildcon ed for (valid up to hence permission for petroleum Ltd. obtained Valid upto-09/03/2017 electricity 18/08/17) from Distt storage is not required. Total number of Capacity- generatio Sand Source and Water source: project roads: 4 Collector 3 n. Office Crusher-99750 m per year, Sand and water purchased from local Total Length- Batching Plant-10000 m3 per year, vendors. Sand purchased with valid revenue 3 102.712 km Hot Mix Plant-30000 m per year. transit passes. Construction department 3 vide letter WMM-60000 m per year. Quarry and Borrow Earth Period- 640 days. Permission: No पुक्रम क車 Permission obtained from Office of /159/ा .क./ District Collector (Mineral Branch) Distt Dhar for the extraction of रीडर/ 16 Gitti/Boulder vide letter ध र, दिि 車क No.क्रम /1788車क /टी.पी./खनिज/ 2015-16

19-07-16 ध रदिि 車क 28.09.15 Prior environmental clearance granted by DEIAA vide letter No. 16/DEIAA/2016 dated 30.05.2016 for extraction of boulder/ stone at village- Khileri, Tehsil-Sardarpur District Dhar.

113

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (c)’ MPDCSP PACKAGE-3, Bhopal-2 Status of Compliance with Environment Regulations (January-June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor cutting as Diesel per IEE / Forest Hot Mix Pollution WMM Generat Env. actual trees Clearance/ Batching Plant Under S. Crusher Plant or Set Name of the Clearance for felled Tree Plant (Ref Control No. (Ref (Ref (Ref Permission obtained from other Sub-Project the Project cutting (Ref Agreeme (PUC) / Agreement Agreeme Agreeme regulators Road from MoEF/ (As per EMP Agreement nt Sub- certificate Pkg. clause No- nt nt Sub- (Ref Agreement Clause-4.18) SEIAA and Sub-clause clause s for 4.18) Clause- clause Agreement) No-111.15) No- vehicle 111.16) No- 111.15) 111.15) Capacity-99750 m3per year.Valid up to 31/12/2016. Prior environmental clearance granted by DEIAA Distt Indore (M.P.) vide letter No. Endt No. 821/Mining /DEIAA/2016 Dhar dated 30.07.2016 for extraction of Soil/Morum in area of 4.00 hectare with the capacity of 1,30,000 Cum/yr. Contractor’s All Risks Insurance Policy obtained from The New India Assurance Co. Ltd. vide Policy No. 2106004415030000023 dated 05/10/2015. Valid up to 04/07/2017. Pkg- 3. Mhou-Simrol Environmental As per IEE Project road Stone/ Consent to Operate obtained from pollution PUC Labour License obtained from P (MDR-15-02 Clearance is report 84 is not Boulder control board vide Consent No. AWH-44176 Certificate Licensing Officer vide License s have No.1090/DR/2016 dated 15.02.2017. Length-15.542 km not required as numbers of passing purchased at Village Khiledi, Ambachandan, Teh-Mhow, per EIA trees to be through from third Distt Indore (M.P.) been Valid up to 31.12.2017 Agreement Signed obtained Blasting Permission: notification cut. forest area party Valid upto-28/02/2018 date- 07.08.2015 2006 and its through for 10 Stone/ Boulder purchased from third As per site Capacity- vehicles party through valid transit passes. Commencement amendments survey 48 valid date-15.09.15 transit Batching Plant-10000 MT per year, on Hence there is no crushing involve in number of Hot Mix Plant-3000 MT per year. 18/08/16 the project. Therefore, blasting is not Contractor- trees to be passes. Hence WMM-10000MT per year. (valid up to involved. Petroleum Storage Ranjit Buildcon cut there is no D.G. Sets- 75 Kva 18/08/17) Permission: Ltd. crushing Diesel purchased from local vendor Total number of involve in hence permission for petroleum project roads: 4 the project storage is not required. Total Length- Sand Source and Water source: Sand and water purchased from local

114

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (c)’ MPDCSP PACKAGE-3, Bhopal-2 Status of Compliance with Environment Regulations (January-June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor cutting as Diesel per IEE / Forest Hot Mix Pollution WMM Generat Env. actual trees Clearance/ Batching Plant Under S. Crusher Plant or Set Name of the Clearance for felled Tree Plant (Ref Control No. (Ref (Ref (Ref Permission obtained from other Sub-Project the Project cutting (Ref Agreeme (PUC) / Agreement Agreeme Agreeme regulators Road from MoEF/ (As per EMP Agreement nt Sub- certificate Pkg. clause No- nt nt Sub- (Ref Agreement Clause-4.18) SEIAA and Sub-clause clause s for 4.18) Clause- clause Agreement) No-111.15) No- vehicle 111.16) No- 111.15) 111.15) 102.712 km vendors. Sand purchased with valid Construction transit passes. Quarry and Borrow Earth Period- 640 days Permission: Permission obtained from Office of District Collector (Mineral Branch) Distt Indore for the extraction of Murrum vide letter No.क्रम /625車क / खनिज/ 2015 इ車िौरदिि 車क 23.05.16. Permission obtained from Office of District Collector (Mineral Branch) Distt Indore for the extraction of Murrum vide letter No.क्रम /628車क / खनिज/ 2016 इ車िौरदिि 車क 23.05.16. Prior environmental clearance granted by DEIAA Distt Indore (M.P.) vide letter No. Endt No. 790/Mining /DEIAA/2016 Indore dated 19.07.2016 for extraction of Soil/Morum in area of 4.00 hectare with the capacity of 1,30,000 Cum/yr. Contractor’s All Risks Insurance Policy obtained from The New India Assurance Co. Ltd. vide Policy No. 2106004415030000023 dated 05/10/2015. Valid up to 04/07/2017 Pkg- 4. Depalpur- Environmental As per IEE Project road Stone/ Consent to Operate obtained from pollution PUC Labour License obtained from P Betma (MDR-15- Clearance is report 29 is not Boulder control board vide Consent No. AWH-43229 Certificate Licensing Officer vide License at Village Khiledi, Ambachandan, Teh-Mhow, No.1090/DR/2016 dated 15.02.2017.

115

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (c)’ MPDCSP PACKAGE-3, Bhopal-2 Status of Compliance with Environment Regulations (January-June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor cutting as Diesel per IEE / Forest Hot Mix Pollution WMM Generat Env. actual trees Clearance/ Batching Plant Under S. Crusher Plant or Set Name of the Clearance for felled Tree Plant (Ref Control No. (Ref (Ref (Ref Permission obtained from other Sub-Project the Project cutting (Ref Agreeme (PUC) / Agreement Agreeme Agreeme regulators Road from MoEF/ (As per EMP Agreement nt Sub- certificate Pkg. clause No- nt nt Sub- (Ref Agreement Clause-4.18) SEIAA and Sub-clause clause s for 4.18) Clause- clause Agreement) No-111.15) No- vehicle 111.16) No- 111.15) 111.15) 07) Length- not required as numbers of passing purchased Distt Indore (M.P.) s have Valid up to 31.12.2017 20.117 km per EIA trees to be through from third Valid upto-31/01/2018 been Blasting Permission: Agreement Signed notification cut. forest area party obtained Stone/ Boulder purchased from third date- 07.08.2015 2006 and its As per site through Capacity- for 10 party through valid transit passes. amendments survey 48 valid Batching Plant-10000 MT per year, vehicles Hence there is no crushing involve in Commencement transit Hot Mix Plant-3000 MT per year. on the project. Therefore, blasting is not date-15.09.15 numbers of trees to be passes. WMM-10000MT per year. 18/08/16 involved. Petroleum Storage Contractor- cut. Hence D.G. Sets- 125 Kva. Permission: there is no Diesel purchased from local vendor Ranjit Buildcon Tree cutting Ltd. crushing hence permission for petroleum permission is involve in storage is not required. Total number of obtained the project. Sand Source and Water source: project roads: 4 from Upper Sand and water purchased from local Total Length- Collector vendors. Sand purchased with valid 102.712 km Indore vide transit passes. letter Construction Quarry and Borrow Earth No.22/A.K/Ri Permission: Period- 640 days /1/15 dated 31.03.2016 Permission obtained from Office of District Collector (Mineral Branch) Distt Indore for the extraction of Murrum vide letter No.क्रम /1660車क / खनिज/ 2016 इ車िौरदिि 車क 29.12.16.

Prior environmental clearance granted by DEIAA Distt Indore (M.P.) vide letter No. Endt No. 792/Mining /DEIAA/2016 Indore dated 19.07.2016 for extraction of Soil/Morum in area of 4.00 hectare

116

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (c)’ MPDCSP PACKAGE-3, Bhopal-2 Status of Compliance with Environment Regulations (January-June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor cutting as Diesel per IEE / Forest Hot Mix Pollution WMM Generat Env. actual trees Clearance/ Batching Plant Under S. Crusher Plant or Set Name of the Clearance for felled Tree Plant (Ref Control No. (Ref (Ref (Ref Permission obtained from other Sub-Project the Project cutting (Ref Agreeme (PUC) / Agreement Agreeme Agreeme regulators Road from MoEF/ (As per EMP Agreement nt Sub- certificate Pkg. clause No- nt nt Sub- (Ref Agreement Clause-4.18) SEIAA and Sub-clause clause s for 4.18) Clause- clause Agreement) No-111.15) No- vehicle 111.16) No- 111.15) 111.15) with the capacity of 1,30,000 Cum/yr. Contractor’s All Risks Insurance Policy obtained from The New India Assurance Co. Ltd. vide Policy No. 2106004415030000023 dated 05/10/2015. Valid up to 04/07/2017 Pkg- 1. Sanawad- Environmental As per IEE Permission Consent to Establish obtained from pollution control board PUC Labor License obtained from Q Khargone (MDR Clearance is report 251 of work in obtained vide survey No. 150/1, 150/2 dated 16.12.15 Certificate Licensing Officer vide license No. 20-01) not required as number of the forest Application No- 122045 dated 03.12.15 Village-Jamnya s have 6933 dated 09-03-2017. Valid up to Length- 66.00 km per EIA trees to be area under Tehsil-Bhikhangoan District-Khargone. been 31/12/2017 Agreement Signed As per site obtained notification Khargone Consent to Operate from pollution control board obtained Blasting License obtained by person date- 04.08.2015 2006 and its survey 122 District DFO for 25 Commencement trees to be vide Consent No. AWH-34831 dated 21/01/2016 at Village- vehicles involved in activity from Chief amendments is issued Jamnya Tehsil-Bhikhangoan District-Khargone. Controller of Explosives vide License date- 20.08.2015 cut. vide letter on Contractor- Tree cutting Valid upto-18/01/20117 19/10/16. No. E/HQ/MP/22/241(E35182) dated No. 10/04/2002. Renewed on 06/03/2014. GHV (India) Ltd. permission Ma.Chi/2016 Capacity- Valid up to Total number of obtained 08/03/17 Date of Expiry 31/03/2019. /2250 dated Crusher-240000 MT per year, project roads: 2 from Office 26/03/2016 3 Petroleum Storage Permission: Total Length- of Collector Batching Plant-19000 m per year, Diesel purchased from local vendor 108.178 km vide letter Hot Mix Plant-100000 MT per year hence permission for petroleum Construction No. WMM-115000 MT per year storage is not required. Period- 640 days 480/Vachak/ Sand Source and Water source: DG sets – 100KVA & 250 KVA -2/2016 Sand and water purchased from local dated vendors. Sand purchased with valid 29/03/2016 transit passes. Quarry and Borrow Earth Permission: Permission obtained from Office of District Collector (Mineral Branch) Distt Khargone for the extraction of

117

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (c)’ MPDCSP PACKAGE-3, Bhopal-2 Status of Compliance with Environment Regulations (January-June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor cutting as Diesel per IEE / Forest Hot Mix Pollution WMM Generat Env. actual trees Clearance/ Batching Plant Under S. Crusher Plant or Set Name of the Clearance for felled Tree Plant (Ref Control No. (Ref (Ref (Ref Permission obtained from other Sub-Project the Project cutting (Ref Agreeme (PUC) / Agreement Agreeme Agreeme regulators Road from MoEF/ (As per EMP Agreement nt Sub- certificate Pkg. clause No- nt nt Sub- (Ref Agreement Clause-4.18) SEIAA and Sub-clause clause s for 4.18) Clause- clause Agreement) No-111.15) No- vehicle 111.16) No- 111.15) 111.15) Murom vide letter No. 781/खनिज/16 खरगोिदिि 車क 03.10.16 Car Insurance Policy Obtained vide policy No;43132864 from IFFCO Tokio General Insurance Co. Ltd. Pkg- 2. Rajpur Khetiya Environmental As per IEE Permission Consent to Establish obtained from pollution control board PUC Labor License obtained from Q Road (MDR 22- Clearance is report 351 of work in obtained vide survey No. 1096/2, 1097 village Palsood toll Certificate Licensing Officer vide license No. 05) not required as numbers of the forest Plaza SH-29, Rajpur Distt Badwan Aplication - 122046 s have 6933 dated 09-03-2017. Valid up to Length- 42.178 per EIA trees to be area under dated 04.12.15 been 31/12/2017 Km notification obtained cut. Barwani Consent to Operate obtained from pollution control board Blasting License obtained by person Length- 66.00 km 2006 and its District DFO for 15 Agreement Signed amendments As per site vides consent No.AWH-34441 dated 11/01/2016 at Village- vehicles involved in activity from Chief survey tree is issued Palsood, Tehsil- Rajpur, District-Barwani. Controller of Explosives vide License date- 04.08.2015 vide letter on Commencement cutting is not Valid upto-30/12/2016 19/10/16. No. E/HQ/MP/22/241(E35182) dated required No. 10/04/2002. Renewed on06/03/2014. date- 20.08.2015 Capacity- Valid up to 2016/1/1001 Date of Expiry 31/03/2019. Contractor- dated 08/03/17 Crusher-240000 MT per year, Petroleum Storage Permission: GHV (India) Ltd. 24/03/2016 3 Total number of Batching Plant-19000 m per year, Diesel purchased from local vendor project roads: 2 Hot Mix Plant-100000 MT per year hence permission for petroleum storage is not required. Total Length- WMM-115000 MT per year 108.178 km Sand Source and Water source: Construction DG sets – 100KVA Sand and water purchased from local Period- 640 days vendors. Sand purchased with valid transit passes. Quarry and Borrow Earth Permission: Permission from District Collector (Mining Department) obtained vide

118

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (c)’ MPDCSP PACKAGE-3, Bhopal-2 Status of Compliance with Environment Regulations (January-June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor cutting as Diesel per IEE / Forest Hot Mix Pollution WMM Generat Env. actual trees Clearance/ Batching Plant Under S. Crusher Plant or Set Name of the Clearance for felled Tree Plant (Ref Control No. (Ref (Ref (Ref Permission obtained from other Sub-Project the Project cutting (Ref Agreeme (PUC) / Agreement Agreeme Agreeme regulators Road from MoEF/ (As per EMP Agreement nt Sub- certificate Pkg. clause No- nt nt Sub- (Ref Agreement Clause-4.18) SEIAA and Sub-clause clause s for 4.18) Clause- clause Agreement) No-111.15) No- vehicle 111.16) No- 111.15) 111.15) letter No. 1312/ खनिज/2015 बड़व िीदिि 車क 5.11.15. Prior environmental clearance from DEIAA granted for extraction of stone vide letter No. 46/DEIAA/16 dated 31/05/2016 at village-Palsud, Tehsil- Rajpur, District-Barwani. Car Insurance Policy Obtained vide policy No;43132864 from IFFCO Tokio General Insurance Co. Ltd. Pkg- 1. Hathnapur- Environmental As per IEE Project Road Permission obtained for Itarsi Dolariya Tigariya (MDR-30- PUC Contractor has planned to complete R Anwalighat- Clearance is report 156 is not 04) Road No-3, Pkg-R, plant are being used in this road Certificate the civil construction works by Salkanpur,(MDR- not required as numbers of passing project s obtained establishing only single plant situated 30-19) per EIA trees to be through for 07 at itarsi Dolariya Tigariya Road. Hence notification cut. forest area vehicles permissions remains the same as Length- 28.18 km 2006 and its on 10Feb used for Itarsi Dolariya Tigariya (MDR- Agreement Signed amendments 2016 valid 30-04) Road No-3, Pkg-R date- 24.08.2015 As per site up to

Commencement survey tree 21/03/17 date-28.09.2015 cutting is not PUC Contractor- required Certificate Sorathia Velaji s obtained Ratan & Kunal (JV) for 05 Construction vehicles Total number of on project roads: 3 28/05/17va Total Length- lid up to

119

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (c)’ MPDCSP PACKAGE-3, Bhopal-2 Status of Compliance with Environment Regulations (January-June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor cutting as Diesel per IEE / Forest Hot Mix Pollution WMM Generat Env. actual trees Clearance/ Batching Plant Under S. Crusher Plant or Set Name of the Clearance for felled Tree Plant (Ref Control No. (Ref (Ref (Ref Permission obtained from other Sub-Project the Project cutting (Ref Agreeme (PUC) / Agreement Agreeme Agreeme regulators Road from MoEF/ (As per EMP Agreement nt Sub- certificate Pkg. clause No- nt nt Sub- (Ref Agreement Clause-4.18) SEIAA and Sub-clause clause s for 4.18) Clause- clause Agreement) No-111.15) No- vehicle 111.16) No- 111.15) 111.15) 65.030 21/11/17 Period- 455 days Pkg- 2. Tawa Bridge– Environmental As per IEE Project Road Permission obtained for Itarsi Dolariya Tigariya (MDR-30- PUC Contractor has planned to complete R Itarsi Mandi Clearance is report 62 is not 04) Road No-3, Pkg-R, plant are being used in this road Certificate the civil construction works by (MDR-30-06) not required as numbers of passing project s obtained establishing only single plant situated Length- 11.15 km per EIA trees to be through for 05 at itarsi Dolariya Tigariya Road. Hence Agreement Signed notification cut. forest area vehicles permissions remains the same as for date- 24.08.2015 2006 and its valid till 25 Itarsi Dolariya Tigariya (MDR-30-04) Commencement amendments June 2017 Road No-3, Pkg-R date-28.09.2015 As per site Contractor- survey tree Sorathia Velaji cutting is not Ratan & Kunal (JV) required Construction Total number ofproject roads: 3 Total Length- 65.030 Period- 455 days Pkg- 3. Itarsi-Dulariya- Environmental As per IEE Project Road Consent to Establish obtained vide CTE-220248 PCB ID- PUC Labour License obtained from R Tigariya (MDR-30- Clearance is report 108 is not 107869 Dated 21.06.16 valid up to 21.05.17 Certificate Licensing Officer videlicense No. 04) not required as numbers of passing Consent to Establish obtained vide AW-38843 application s obtained 203/HBP/2015 dated 16/12/2015. per EIA trees to be through No-231121 Dated 23.07.2016 valid up to 31.07.17 for 07 Valid up to 15/12/2017. Length- 25.70 km notification Capacity- vehicles cut. forest area Blasting License obtained by person Agreement Signed 2006 and its Crusher Plant-135000 m3/year on 10Feb date- 24.08.2015 amendments As per site Batching Plant-25000 m3/year 2016 valid involved in activity from Chief survey tree Hot Mix Plant-12000 m3/year up to Controller of Explosives vide License Commencement cutting is not No. E/CC/MP/ 28/484 (E64446) dated date-28.09.2015 Wet Mix Plant- 40000 m3/year 23/11/16 required D.G Sets- 100 KLW& 62.500 KLW PUC 31.10.2011 Contractor- Certificate Date of Expiry 31/03/2021. Sorathia Velaji Petroleum Permission

120

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (c)’ MPDCSP PACKAGE-3, Bhopal-2 Status of Compliance with Environment Regulations (January-June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor cutting as Diesel per IEE / Forest Hot Mix Pollution WMM Generat Env. actual trees Clearance/ Batching Plant Under S. Crusher Plant or Set Name of the Clearance for felled Tree Plant (Ref Control No. (Ref (Ref (Ref Permission obtained from other Sub-Project the Project cutting (Ref Agreeme (PUC) / Agreement Agreeme Agreeme regulators Road from MoEF/ (As per EMP Agreement nt Sub- certificate Pkg. clause No- nt nt Sub- (Ref Agreement Clause-4.18) SEIAA and Sub-clause clause s for 4.18) Clause- clause Agreement) No-111.15) No- vehicle 111.16) No- 111.15) 111.15) Ratan & Kunal (JV) Consent to Operate obtained vide Consent No AW-38843 s obtained Approval from Jt Chief Controller Construction PCB ID- 107568 valid up to 31.07.17 for 02 ofExplosives obtained for storage of Capacity- vehicles petroleum. vide Approval Total number of Crusher Plant-135000 m3/year on 22 May No.A/P/CC/MP/15/47(P378201) dated project roads: 3 Batching Plant-25000 m3/year 2016 valid 12/04/2016.. Total Length- Hot Mix Plant-12000 m3/year up to Sand Source and Water source: 65.030 Wet Mix Plant- 40000 m3/year 21/1116 Sand and water purchased from local Period- 455 days D.G Sets- 100 KLW& 62.500 KLW vendors. Sand purchased with valid transit passes Quarry and Borrow Earth Permission: Prior environmental clearance from SEIAA obtained vide Endt No. 188/ SEIAA/ 15dated13/04/2015 for extraction of sand village-. Gondikharar Tehsil-Dolariya, District- Hoshangabad. Permission obtained from Office of District Collector (Mineral Branch) Distt Hoshangabad for the extraction of Sand vide letter क्रम /18車क / खनिज/2016 होि車ग ब िदिि 車क 11.04.16 Prior environmental clearances from DEIAA obtained vide No. 559/DEIAA/16 dated10/06/2016 for extraction of boulder & Murrum village- . Gondikharar Tehsil-Dolariya, District- Hoshangabad. Prior environmental clearances from DEIAA obtained vide No.

121

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Annexure ‘I (c)’ MPDCSP PACKAGE-3, Bhopal-2 Status of Compliance with Environment Regulations (January-June 2017) Tree Environmental Consents/Clearances to be obtained by Contractor cutting as Diesel per IEE / Forest Hot Mix Pollution WMM Generat Env. actual trees Clearance/ Batching Plant Under S. Crusher Plant or Set Name of the Clearance for felled Tree Plant (Ref Control No. (Ref (Ref (Ref Permission obtained from other Sub-Project the Project cutting (Ref Agreeme (PUC) / Agreement Agreeme Agreeme regulators Road from MoEF/ (As per EMP Agreement nt Sub- certificate Pkg. clause No- nt nt Sub- (Ref Agreement Clause-4.18) SEIAA and Sub-clause clause s for 4.18) Clause- clause Agreement) No-111.15) No- vehicle 111.16) No- 111.15) 111.15) 561/DEIAA/16 dated10/06/2016 for extraction of boulder & Murrum village- Temlakala Tehsil-Dolariya, District- Hoshangabad. Car Insurance Policy Employees Compensation Insurance Policy obtained from The New India Assurance Co. Ltd vide Policy No. 22030048166800000019 Valid up to 22/01/2018.

122

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND Annexure: II MPDCSP Package-1, Bhopal-1, Photographs:

View of Completed road Package-A (Mahua-Chuwahi)

View of completed road Package-B Chitrangi -Kasar

View of completed Project Road Pkg-C (Dabra-Bhitarwar-Harsi) 123

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

Borrow area Rehabilitated at chainage 42.300 LHS, Pkg- View of Closed Borrow area: Pkg-C: rehabilitated and C, with slop maintenance and levelling. restored (with crop cultivation)

A View of Construction Camp. Pkg-E A View of Labor Camp.Pkg- E (Hardua-Chakghat)

Drinking water facility provided at construction camp. DG. Set with silencer is being established at construction camp at Pkg-E. 124

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

View of HIV/AIDs Awarness camp conducted at construciton camp site (Package-E) on date 13-06-2017.

View of Health Checkup comp organized during reporting period at construction camp of Pkg-E

A view Community Consultation conducted in Pkg-E at A view Community Consultation conducted in Pkg-E at Garwah village (Ch. 53.200) Aakoli village (Ch. 62.850) 125

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

A view Community Consultation conducted in Pkg-E at Kureli village (Ch. 23.300)

View of stating point of completed project road. Pkg-F. View of completed project road. Pkg-F.

View of saved trees along the project road section, passes View of Plantation along the project road. through forest area.

126

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

View of stating point of completed project road. Pkg-G. View of completed project road. Pkg-G.

Community Consultation with Shopkeepers along the A view of consultation along the project road at chainage project road at chainage 22.500 km, LHS. Pkg-G 09.00 km, LHS. Pkg-G

127

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND MPDCSP Package-2 Jabalpur-Package (H,I, J and K) (Photographs) (View of completed Roads –PKG-H)

View of completed Roads –PKG-H

View of completed Roads –PKG-H

View of completed Roads –PKG-H

128

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

View of completed Roads –PKG-H

View of completed Roads –PKG-H

View of completed Roads –PKG-H

129

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

(View of completed Roads –PKG-K)

View of completed Roads –PKG-K

View of completed Roads –PKG-K

View of completed Roads –PKG-K 130

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

View of completed Roads –PKG-K

View of completed Roads –PKG-K

View of completed Roads –PKG-K

131

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND (View of AIDS Awareness Program)

View of AIDS Awareness Program Construction Labor Camp.

View of AIDS Awareness Program Construction Labor Camp.

View of AIDS Awareness Program Construction Labor Camp.

132

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND Photographs- Construction Camps, Accommodations, Safety Status

View of Construction Camp. View of road safety sinages and Diversion.

View of Personnel Protective Equipment during Construction.

View of First Aid Kit Availability work construction View of Fire Protection Construction Camp and labor camp site.

133

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

View of TreePlantation

View of TreePlantation

View of TreePlantation

134

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

View of TreePlantation

View of TreePlantation

View of TreePlantation

135

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND MPDCSP Package-3 Bhopal-2 Package (L,M,N,O,P,Q& R) (Photographs)

A view of safety implementation during BC works Accommodation provided to the workers

Accommodation provided to the workers Used of PPE during plant operations

A view of Public Consultation Program. A view of HIV/AIDS awareness Program.

136

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

A view of Labor wages display board Use of PPE during Civil Construction Works

A view of Diversion used during civil construction A view of display board at camp site at village work. Runaha.

A view of water sprinkling to remove acute problem A view of tree plantation along with tree guards of dust and residual particles in air during the along the ROW reporting period.

137

Semiannual Environmental Monitoring Report Construction of ADB Assisted January - June 2017, Madhya Pradesh District Connectivity Sector Projects-Under ADB Loan No. 3189-IND

A view of informatory board along with the Accommodation provided to workers at camp road construction works. site along with first aid box.

Free Medical / Health Camp arranged at camp Water sprinkling during civil construction works site.

Use of PPE during Civil Construction works A view of HIV/AIDS awareness program.

138