SECTION 1 INTRODUCTION

CONTENTS

1 INTRODUCTION 1-1 1.1 PROJECT OVERVIEW 1-1 1.1.1 Purpose of this Report 1-1 1.1.2 Background 1-2 1.1.3 Project Summary 1-2 1.1.4 Site Location and Tenure 1-9 1.1.5 Interaction with Other Operations and Projects in the Vicinity of the Site 1-9 1.1.6 Proponent 1-13 1.2 SECRETARY’S ENVIRONMENTAL ASSESSMENT REQUIREMENTS 1-13 1.3 PROJECT CONSULTANTS 1-16 1.4 DOCUMENT STRUCTURE 1-16

LIST OF TABLES

Table 1-1 Project Summary Table 1-2 Secretary’s Environmental Assessment Requirements – Reference Summary Table 1-3 Content Requirements of an EIS – Clause 7 of Schedule 2 of the EP&A Regulation Table 1-4 EPBC Act Controlling Provisions – Reference Summary

LIST OF FIGURES

Figure 1-1 Regional Location Figure 1-2 Project Location Figure 1-3 Aerial Photograph of the Wilpinjong Coal Mine and Surrounds Figure 1-4 Project General Arrangement Figure 1-5a Relevant Land Ownership Plan Figure 1-5b Relevant Land Ownership Plan Wollar Inset Figure 1-5c Relevant Landholder List

LIST OF PLATES

Plate 1-1 Wilpinjong Coal Mine Plate 1-2 Front End Loader Handling Coal

Wilpinjong Extension Project Environmental Impact Statement Section 1 - Introduction Document Number: 00659084 Version: A 1-i

1 INTRODUCTION 1.1 PROJECT OVERVIEW

This document is an Environmental Impact 1.1.1 Purpose of this Report Statement (EIS) for the Wilpinjong Extension Project (the Project). The Project would involve the This EIS has been prepared to accompany a continuation and extension of open cut mining Development Application made for the Project, in operations at the Wilpinjong Coal Mine (Plate 1-1). accordance with Part 4 of the NSW Environmental Planning and Assessment Act, 1979 (EP&A Act). The Wilpinjong Coal Mine is located approximately 40 kilometres (km) north-east of , near the This EIS considers the potential environmental Village of Wollar, within the Mid-Western Regional impacts of the Project in accordance with the Local Government Area (LGA), in central New Secretary’s Environmental Assessment South Wales (NSW). Requirements (SEARs) issued by the NSW Department of Planning and Environment (DP&E) The Wilpinjong Coal Mine is owned and operated by on 9 December 2014 (Attachment 1), the Wilpinjong Coal Pty Ltd (WCPL), a wholly owned supplementary SEARs issued by the DP&E on subsidiary of Peabody Energy Pty Limited 22 June 2015 (Attachment 1) and clauses 6 and 7 (Peabody Energy). of Schedule 2 of the NSW Environmental Planning and Assessment Regulation, 2000 (EP&A Regulation).

The SEARs were issued in accordance with the requirements of clause 3 of Schedule 2 of the EP&A Regulation. A summary of the SEARs is provided in Section 1.2.

Plate 1-1: Wilpinjong Coal Mine

Wilpinjong Extension Project Environmental Impact Statement Section 1 - Introduction Document Number: 00659084 Version: A 1-1

1.1.2 Background A summary indicating where the supplementary SEARs have been addressed in the EIS is provided The Wilpinjong Coal Mine extracts run-of-mine in Attachment 2. (ROM) coal that is either processed on site at the Coal Handling and Preparation Plant (CHPP) or 1.1.3 Project Summary bypassed directly to product stockpiles.

The proposed life of the Project is approximately Coal products are transported by rail on the existing 17 years and would extend the life of the approved Sandy Hollow Gulgong Railway to local energy Wilpinjong Coal Mine by approximately seven years generators and to the Port of Newcastle for export. (i.e. from approximately 2026 to 2033).

The location of the existing Wilpinjong Coal Mine is The main activities associated with the Project shown on Figures 1-1 and 1-2, and Figure 1-3 would include: provides an aerial photograph of the existing mine.

A description of the existing mining operations and • open cut mining of ROM coal from the Ulan history of approvals is provided in Sections 2.1 and Coal Seam and Moolarben Coal Member in 2.2, respectively. Mining Lease (ML) 1573 and in new Mining

Lease Application (MLA) areas in Exploration WCPL is seeking approval from the NSW Minister Licence (EL) 6169 and EL 7091; for Planning for Development Consent under Division 4.1 of Part 4 of the EP&A Act for the • approximately 800 hectares (ha) of open cut Project, which would replace the existing Wilpinjong extensions, including (Figure 1-4): Coal Mine Project Approval (Project - approximately 500 ha of incremental Approval 05-0021). extensions to the existing open cut pits in

areas of ML 1573 and EL 6169; and The approved Wilpinjong Coal Project was referred to the Department of the Environment and Heritage - development of a new open cut pit of in 2005, and was determined as not a controlled approximately 300 ha in EL 7091 (Pit 8); action (EPBC 2005/2309). The proposed action to • continued production of up to 16 million tonnes extend open cut coal mining and processing per annum (Mtpa) of ROM coal (Plate 1-2); operations at the Wilpinjong Coal Mine was referred to the Commonwealth Minister in February 2015 • continued use of the approved Wilpinjong Coal (EPBC 2015/7431) (the proposed action). Mine CHPP and general coal handling and rail loading facilities and other existing and A delegate of the Commonwealth Minister approved supporting mine infrastructure; determined on 12 March 2015 that the proposed • rail transport of approximately 13 Mtpa of action is a ‘controlled action’ and therefore the thermal product coal to domestic and export action also requires approval under the customers (within existing maximum and Commonwealth Environment Protection and annual average daily rail limits); Biodiversity Conservation Act, 1999 (EPBC Act). • relocation of a section of the TransGrid Wollar The proposed action is to be assessed pursuant to to Wellington 330 kilovolt (kV) electricity the assessment bilateral agreement with the NSW transmission line (ETL) to facilitate mining in Government. Therefore, this EIS provides an Pit 8; assessment of potential impacts (in accordance with • the supplementary SEARs) to the following various local infrastructure relocations to controlling provisions considered by the facilitate the mining extensions Commonwealth Minster to be relevant to the action: (e.g. realignment of Ulan-Wollar Road and associated rail level crossing, relocation of • EPBC Act listed threatened species and local ETLs and services); communities; and • construction and operation of additional mine • water resources. access roads to service new mining facilities located in Pits 5 and 8;

Wilpinjong Extension Project Environmental Impact Statement Section 1 - Introduction Document Number: 00659084 Version: A 1-2 Gunnedah !

! Tamworth

Coonabarabran ! GUNNEDAH BASIN

! Gilgandra GLOUCESTER Dunedoo BASIN ! Gloucester !

! Muswellbrook ! Dubbo B Dungog ! Gulgong 4

! Wilpinjong Mudgee Singleton Coal Mine !

! Rylstone ! BASIN NEWCASTLE<= Western 4 Parkes Coalfield !

! Orange

! Gosford Forbes ! Lithgow !

! ! SYDNEY Cowra

NEW SOUTH WALES

! Young ! WOLLONGONG<= ! Temora

! Cootamundra Goulburn !

Yass !

B

1

0

2

_

1

n

tio

c

e

S

_

IS

E

_ 0100

P ±

E

W ! _ CANBERRA

2

1

- Kilometres

2

1

- ACT MGA 94 ZONE 55

IL

W

LEGEND Highway Major Railway Coalfield

Source: Geoscience Australia (2011)

WILPINJONG EXTENSION PROJECT Regional Location

Figure 1-1 !

# GOLDEN Durridgere ! HIGHWAY State Conservation Area GOLDEN WARRUMBUNGLE RIVER Black # SHIRE COUNCIL Hill Durridgere Turill State Conservation Area ! UPPER HUNTER HIGHWAY # Cockabutta Durridgere Hill Road State Conservation Area SHIRE COUNCIL #Summer Hill Ulan

KRUI

Comiala! Flat GOULBURN # Box Hill ! Ulan Mine RIVER The Hulks Complex B Goulburn River Creek Wilpinjong National Park Cope Cope State Forest Ulan ! State Forest Wilpinjong Goulburn River WALLERAWANG National Park Road Moolarben Coal Coal Mine Complex #Round Top Creek Cope B Ulan-Wollar Creek # Cope Mountain Wilpinjong Wollar Lees State Forest SANDY Pinch SANDY HOLLOW GULGONG RAILWAY Moolarben Road HOLLOW # RIVER GULGONG GOULBURN Dexter GULGONG Cooyal RAILWAY Mountain Wollar ! # # Meads Crossing Henry ! Road Magazine Mount Flirtation Lawson Wollar Hill GWABEGAR ! Creek # Hill Cooks Gap Creek Misery

Drive Wollar Road

HIGHWAY Home Rule # ! Munghorn Gap Mount# Way # Creek Betealween Barigan Cumbo Ulan Nature Reserve Penny Mountain BYLONG! RIVER Bylong

#Magpie Road Creek Bylong State Forest Barigan # Hill ! Garrison Hill RAILWAY CASTLEREAGH B Cooyal SANDY HOLLOW GULGONG RAILWAY # Bylong Valley Box Hill Bylong Coal #Mount Project Galambine Drive # Creek # Wollar Road Tal Tal Lowes Stony Mountain Peak MID-WESTERN Bald# Botobolar GROWEE Hill Creek REGIONAL COUNCIL #Oaky # ! Road Red Hill

Lawson Mountain Budgee Budgee # # Mudgee #Porcupine # #Big # Box Hill Mountain Mountain #Mount Red Hill Oakys #Round Stormy # Hill # Bald Hill Mount Henry #Mount # Buckaroo #Davids Bombira Hill Bara Lue Mountain MUDGEE Bowdens # Lawsons Flirtation Silver Project Wollemi Mount# Mount Hill # WALLERAWANG B National Park Misery # Frome Road #Jimmy Jimmy Colliers Creek # Growee # Hawkins Mountain # Avisford Hill Mountain Oz Mountain # Nature Reserve GWABEGAR Pinnacle CASTLEREAGH #Mount #Lion RIVER Cannibal Way Goat CUDGEGONG Knowles Mountain Hill ! # Mountain Lue Elephant # RAILWAY Mountain Avisford HIGHWAY Nature Reserve Lue Mount # # #Bald Graham RIVER Road Mountain Tongbong ± Sailors Peak 0 10 # Bylong Valley # #Mount Mountain # Margaret # Rumkers Oak Hill Peak # Kilometres # Monkey Taylors Lake Dungeree MGA 94 ZONE 55 Mt Echoe # Windamere # Spring Dairy WIL-12-12_WEP_EIS_Section 1_202B State Forest # ## #Hill Hill Mountain Mountain Coxs Crown # # # # LEGEND Mining Lease Boundary Exploration Licence Boundary Authorisation Boundary Local Government Boundary NSW State Forest National Park, Nature Reserve or State Conservation Area B Mining Operation WILPINJONG EXTENSION PROJECT Source: NSW Land & Property Information (2015); NSW Dept of Industry (2015); Project Location Geoscience Australia (2011)

Figure 1-2 LEGEND Mining Lease Boundary Approximate Extent of v Exploration Licence Boundary Approved Local Road Approved/Existing Open Cut and Contained v and ETL Relocations v Infrastructure Area v Approved Block Bank and Cumbo Creek MOOLARBEN v COAL COMPLEX U Relocation Disturbance Area v la OPEN CUT n v

-W Goulburn River Approved Elevated In-Pit o 4 Goulburn River MINING AREA ll ar National Park v R E National Park Waste Rock Emplacement Area o v W L 6 ad 169 v i l Existing Local ETL v p i

n v

j Existing TransGrid 330 kV ETL Creek v on rs v te v g lan Enhancement and Conservation Area P v

v v v v Source: WCPL (2015); NSW Dept of Industry (2015) Cr Approximate Extent of eek Orthophoto: WCPL (Jun 2015; Jun 2014)

v v Approved Local Road v v v v and ETL Relocations EL Wi 6169 lpi njo M ng Pit 6 L 15 Creek Light Vehicle 4 73 v d v a Workshop o R

v

s

n v v o v s v v n ECA-B v i v v b

AY v o v AILW vONG R R v GULG k LvLOW e O e v ANDY H Sv v Pit 5 v k Cr v e v v re v C

r a U v l

o Pit 3 la ol v b n-W W

m o E u lla

L 62 C r 88 v

Pit 4 R v Pit 1 oa v Pit 2 Water Treatment d d v v oa d Facility R a y v o Rail Loop l R

l v v u G o e og k at v ee Mine Access Road l M

Cr S v v Mine Facilities Area v g v in pr S v v

v d a o ROM Pad R

Product Coal ECA-C g v

on Stockpiles j n i p l EL 6169 i W ECA-A

CHPP Pit 7 v v

d a ROM Pad o R

v n Munghorn Gap a EL 6169 rig Nature Reserve a B

v k e Munghorn Gap e EL 6169 EL 70 WOLLAR vv r E 91 C Nature Reserve L 616 v Wollar 9 Road r a l l

d o v a v o W

R

v WILPINJONG EXTENSION PROJECT o b v m u v C Aerial Photograph of the

ek v r e 02 p ± Cre p Wilpinjong Coal Mine and Surrounds

d v U oa v v r R olla o Kilometres W b

v m

u MGA 94 ZONE 55 C v v v v v Figure 1-3 WIL-12-12_WEP_EIS_Section 1_203D Figure 1-4 Project General Arrangement Project LEGEND Mining Lease Boundary Mining Lease Application Boundary Open Cut and Contained Approved/Existing Area Infrastructure Bank and Cumbo Creek Block Relocated Disturbance Area Area Open Cut Extension Proposed Realignment Road Public Proposed Pit 3/8 Haul Road Proposed Road Service Proposed ETL Realignment/Relocation Local Proposed kV ETL 330 Relocated TransGrid Proposed Existing Local ETL kV ETL 330 TransGrid Existing v v v v

WILPINJONG EXTENSION PROJECT Source: WCPL (2015); NSW Dept of Industry (2015) 2014) Jun 2015; (Jun WCPL Orthophoto:

k

e

e

r

v C r

a

l l

o

W

v

v

d

a

6420000 k 6415000 o

e e

R

r

C

n

a

r rig a

a B

l l

v vv o

W

v

d

a

o

R

o

og M v

v

v v v WOLLAR

v v National Park Goulburn River

v v v

2

v ± Kilometres

v A

L v

v 55 94 ZONE MGA

M v

v

k v

e

v

v ad

e d

a o d

r R

o a

R y

l o C

r l

a v u R

l G

l

e

d o a

t

o R

v s

a n

o r l s

n i -W b v o S R n a la l l U 02 v v v 1 o A W g L

n Pit 8 M o v j n i p l

i

1 v

775000

W 2

A

775000 L A L

M

M

v

d

a

o

R

o

b

m u

C

r e

v p p

U v Pit 7

4 v

Pit 3

k v

e

AY e

r

W

C

L

I

C

u

m

b A

o

R

G

v

N

d

a

o

R

O

g

n o j n i p

l G i

W and ETL Relocations L Approved Local Road

Approximateof Extent U

Pit 4

G

W

v

O

L

L

O

H

Y

D

vv

AN

S National Park v

Goulburn River

v v

v

ek

Cre

o

v

Pit 2 b m

u v 1 C

A

L

M v

v v v

v

v v v v

v

v v v

770000 v

770000 Pit 1

v v

v

v v

2

v A

L v 3 M

7 d

a

v15 v o

R

L

k

e r

and ETL Relocations M

Approved Local Road

e v a

Approximateof Extent l

r l

C o v W

jong in Pit 5 lp v v

i Gap Munghorn W Nature Reserve

4 v

v v

1

A v

L k

M e

Pit 6 e

3

v r

C

A

L

M

v

s

Road and Road ETL Realignments r

v e t

Moolarben Coal Complex Stage 2 Stage Complex Coal Moolarben

an k

l

ee P Cr

v

1

A

L

g 1

n

d i M

oa r A

v R p L r S Munghorn Gap Munghorn Nature Reserve

la M

ol OPEN CUT

W MOOLARBEN

- MINING AREA COAL COMPLEX v an 6420000 6415000 Ul WIL-12-12_WEP_EIS_Section 1_207A WIL-12-12_WEP_EIS_Section

• construction and operation of new ancillary It should be noted that the action that requires infrastructure in support of mining including: assessment under the EPBC Act relates to those mine infrastructure areas, ROM pads, haul aspects of the proposed Project that would include roads, electricity supply, communications extension of open cut mining operations and installations, light vehicle roads, access tracks, consequent additional disturbance areas, and remote crib huts, up-catchment diversions, associated surface infrastructure that is necessary dams, pipelines and other water management to support the extension of open cut mining. structures; The action does not include the approved • extension of the approved mine life by Wilpinjong Coal Mine that has either been approximately seven years (i.e. from previously referred and determined not to be a approximately 2026 to 2033); Controlled Action or previously determined not to • a peak operational workforce of approximately require referral under the EPBC Act but has 625 people; received all relevant State approvals. In addition, the elements of the Project which require EPBC Act • ongoing exploration activities; and approval exclude the continuation of mining • other associated minor infrastructure, plant operations in the open cut pits and associated and activities. activities which are currently authorised by existing approvals (including modifications and exploration Table 1-1 provides a summary comparison of the activities). approved Wilpinjong Coal Mine and Project components.

Plate 1-2: Front End Loader Handling Coal

Wilpinjong Extension Project Environmental Impact Statement Section 1 - Introduction Document Number: 00659084 Version: A 1-7

Table 1-1 Project Summary

Project Summary of Existing/Approved Wilpinjong Coal Mine Summary of the Project Component

Mining Method • Open cut mining operation extracting ROM coal. • Unchanged.

Open Cut • Seven1 contiguous open cut pits and associated contained • Eight open cut pits, including a new Extent infrastructure area comprising approximately 1,990 ha. open cut pit in Slate Gully (Pit 8). • Approximately 800 ha of open cut extensions.

Annual ROM • 16 Mtpa of ROM coal. • Unchanged. Coal Production

Waste Rock • Waste rock is placed predominantly within mine voids. • Unchanged. Management

Annual Waste • Annual waste rock production of approximately 34.1 million • Approximately 43 Mbcm. Rock bank cubic metres (Mbcm). Production

Coal Washing • Beneficiation of ROM coal in the CHPP. • Unchanged. and Handling • Facilities for the handling and stockpiling of both washed and unwashed (bypass) coal.

Product Coal • Approximately 12.6 Mtpa of thermal product coal for • Approximately 13 Mtpa. domestic electricity generation and export.

Coal • An average of six and a maximum of 10 laden trains per day • Unchanged (WCPL intends to retain Transport leaving the mine. current daily train movement limits but remove the current annual limit for total product coal railed [Section 2.9]).

• Transport via the Sandy Hollow Gulgong Railway. • Unchanged.

Coal Rejects • Coal rejects placed predominantly within mine voids. • Unchanged. (tailings and • coarse rejects) Tailings filter press to allow co-disposal of the tailings with coarse rejects.

Water Supply • Make-up water demand to be met from runoff recovered • No change to key sources of water from mine operational areas, recovery from tailings, open supply. cut dewatering, advanced dewatering of pit areas and supply from a borefield. • Recovery of water from tailings via tailings filter press.

Water • Mine water treated in a reverse osmosis plant/water • No change to key aspects of water Disposal treatment facility and discharged to Wilpinjong Creek in disposal. accordance with Environment Protection Licence (EPL) 12425.

Mine Life • 21 years (from the date of grant of ML 1573). • 28 years (seven year extension).

Hours of • Open cut mining, handling and processing of ROM coal at • Unchanged. Operation the CHPP and train loading at the Wilpinjong Coal Mine is currently undertaken 24 hours per day, seven days per week.

Wilpinjong Extension Project Environmental Impact Statement Section 1 - Introduction Document Number: 00659084.docx Version: A 1-8

Table 1-1 (Continued) Project Summary

Project Summary of Existing/Approved Wilpinjong Coal Mine Summary of the Project Component

General • Access roads, electricity supply and distribution, rail loop, • Continued use of existing approved Infrastructure CHPP, train loading infrastructure, ROM coal stockpiles, infrastructure and coal handling equipment, diesel storage, administration, modifications/extensions to support the workshop, ablution buildings, stores, heavy vehicle Project as required. workshop, and parking and washdown facilities. • Realignment of a 330 kV ETL, Ulan-Wollar Road and associated rail level crossing and local ETLs and services.

Operational • Approximately 550 people. • Approximately 625 people at peak. Workforce

1 Note that for the purposes of WCPL internal mine planning, Pit 3 has been divided into two separate pits (Pit 3 in the north and Pit 7 in the south) (Figure 1-3).

1.1.4 Site Location and Tenure 1.1.5 Interaction with Other Operations and Projects in the Vicinity of the Site Operations at the approved Wilpinjong Coal Mine are covered by the existing ML 1573. Exploration Existing and proposed mining and processing activities for future operations are covered under operations and exploration activities in the vicinity of EL 6169 and EL 7091. The Project would extend the Project that may potentially interact with the into three new MLA areas within both EL 6169 and Project comprise: EL 7091 (Figure 1-4). • The Ulan Mine Complex, operated by Ulan WCPL has lodged MLAs with the Division of Coal Mines Limited (UCML). Resources and Energy (DRE) (within the NSW • Department of Industry, Skills and Regional The Moolarben Coal Complex, operated by Development [NSW Department of Industry]) for Moolarben Coal Operations Pty Ltd on behalf Project development areas outside of the of the Moolarben Joint Venture (Moolarben existing ML. WCPL will also renew existing ELs and Coal Mines Pty Ltd, Sojitz Moolarben ML 1573 as required. Resources Pty Ltd and a consortium of Korean power companies). For ease of reference in Relevant land ownership information for land this EIS, Moolarben Coal Operations Pty Ltd parcels within the immediate vicinity of the Project is and Moolarben Coal Mines Pty Ltd will be provided on Figures 1-5a, 1-5b and 1-5c. The collectively referred to as Moolarben Coal. Project Development Application area (Figure 1-5a) Moolarben Coal Operations Pty Ltd and includes those lands listed in the real property Moolarben Coal Mines Pty Ltd are wholly descriptions provided in support of the Development owned subsidiaries of Yancoal Australia Application submitted to the DP&E (Attachment 3). Limited. • The Bowdens Silver Project, proposed by The Project Development Application area is within Kingsgate Bowdens Pty Limited. the Mid-Western Regional LGA. A description of the land zoning under the Mid-Western Regional • The Bylong Coal Project, proposed by KEPCO Council (MWRC) Local Environmental Plan (LEP) Bylong Australia Pty Ltd (KEPCO). 2012 in the Development Application area is • The approved Cobbora Coal Project, owned provided in Section 6.2. by Cobbora Holding Company Pty Limited.

Descriptions of potential Project interactions and cumulative impacts with these other developments are provided in Section 2.5, and where relevant, Section 4 and supporting appendices.

Wilpinjong Extension Project Environmental Impact Statement Section 1 - Introduction Document Number: 00659084 Version: A 1-9 LEGEND 32 264 265 32 262 263 203 264 204 Development Application Area

)" 202 Peabody Energy 204 32 201 Bylong Coal Project )" 264 )" Moolarben Coal Mine 117 115 200 114 )" Ulan Coal Mine 32 1 113 Crown Land (Special Lease) 32 176 Crown Land )" )" )" 167 )")" 32 )" TransGrid )" 109 32 Goulburn River 108 Goulburn River Railway Land 205 National Park 107 )" National Park Relevant Private Landholder 32 32 Other Land (Ownership not identified) )" 105 )" )" National Parks and Wildlife Service )" )" )" 1 1 )" 103 206 Landholder Number 32 104 )" Peabody Energy Dwelling 32 )" 258 Ulan/Moolarben Dwelling 32 )" 1 Private Dwelling 32 )" Community Building 1 32 32 32 )" 1 Source: WCPL (2015); NSW Dept of Industry (2015); )" 32 1 )" 1 102 )" NSW Land & Property Information (2015) )" 1 101 1 * Refer Figure 1-5c for List of Landholders. 1 1 )" 160 1 )" 32 )" 1 1 )" 1 )" 61 )" 207 80 32 1 1 )" Refer Figure 1-5b )" )" )" )" 207 )" )" 32 )" )" Munghorn Gap 169 Nature Reserve 1 208 0 )" 1 )" )" 80 1 208 32 80 )" )" 1 170 WOLLAR 1 80 )" 208 32 1 1 80 270 )" 32 69 1 )" )" )" 1 )" 80 1 )" )" 175)" 69 1 208 32 1 1 )" 1 " 1 1 ) 32 )" 1 )" 208 )" )" 1 1 274 32 255 )"

252 )" 252 )" )" 251 248 274 249 )" 246 247 250 )" )" Munghorn Gap 153 178 249 1 )" )" Nature Reserve 246)" 1 248 248 153 281 245 242 225 153 153 )" 1 209 281 227 )" 209 227 227 242 )" 233 227 )" )" 232 ") )" )" ) )" 224 234 )" )" 240 )" )" 231 227 209 209 WILPINJONG EXTENSION PROJECT )" )" 224 908 229 228 223 1 209 239 )" 231 226 211 209 )" 235 230 222 1 209 Relevant Land Ownership Plan* 237 223 223 236 222 214 ± 02.5 238 )" )" 223 214 )" 211 )" 32 221 218 210 )" 218 908 Kilometres )" 1 32 217 )" )" 216 )" 1 MGA 94 ZONE 55 212 220 219 218 215 213 212 212 Figure 1-5a WIL-12-12_WEP_EIS_Section 1_204G U la n - )" W )" ol la r )" Ro ad 1 1

1

)" S AN DY H OLLO W G ULG O NG 1 R 1 AILW W AY 1 Goulbu o rn St l reet l a

r

C 1 r e

ek

d )" a t o e

R e r 1 t

S

n

a

g i t t

ar e n B 1 r a 1 B )" 952 1 1 Munghorn )" Wollar Street Public School 1 1 )" )"

)" 1 1 1 Armstro ng Street 1 1 1)" 942 )" )" )" WOLLAR )" )" Community Hall Pric )" e Street 1 )" )" 1 933 )" 933 St Laurence O'Toole " ) )" 1 Catholic Church 900 921)" )" 1 )" )" Mai 1)" tland Stre 1 )" et )" W treet olla ip S 908 Phill 1 1 914 )" 959 W )" ollar Road 1)" )" 903

)" 150 1

St Luke's

I

5

0 Anglican Church

2

_ 1 B a 1 r n ig

tio a c n e

S R _ oad

IS

E

_ 00.5

P ±

E

W

_

2

1

- Kilometres

2

1

- 1 MGA 94 ZONE 55

IL

W

LEGEND * Refer to Figure 1-5c for List of Landholders. Peabody Energy Crown Land (Special Lease) Crown Land Railway Land Relevant Private Landholder 1 Landholder Number )" Peabody Energy Dwelling WILPINJONG EXTENSION PROJECT )" Community Building )" Private Dwelling Relevant Land Ownership Plan Wollar Inset* Source: WCPL (2015); NSW Dept of Industry (2015); NSW Land & Property Information (2015) Figure 1-5b REF NO LANDHOLDER REF NO LANDHOLDER 1 PEABODY ENERGY 221 HC & E VON BISCHOFFSHAUSEN 32 ULAN/MOOLARBEN/CASCADE COAL CONTROLLED LAND 222 RT & JM BILES 61 J SZYMKARCZUK 223 NAGERA PTY LIMITED 69 DJ & JG STOKES 224 CR & VK HARTAS 80 RB COX 225 JW CAMPBELL 101 NAB PIERCE 226 RD BALL 102 W FILIPCZYK 227 JB & J BAKER 103 MR MOLLOY 228 KA ROSS 104 J & IBD HARTIG 229 DE & JI SMITH 105 DL & EH TOOMBS 230 TA & RN STAIT 107 RJ LEE 231 MR FIELD 108 PA CROSSE 232 J TAYLOR 109 MO VAISEY 233 CDR & ASE MARTIN 113 AJ BRETT, S & D HILT 234 MP & KA REEDY 114 C WARE, N PARKER 235 PJ HOLLOW & SG MCNALLY 115 T AUDRETSCH 236 JIM & CG STEVENSON 117 S MCHUGH 238 M ANDONOVSKI 150 E TINDALE, A MCDONALD & WS WILSON 239 MJ BRYANT 153 TW MARSKELL 240 KJ & SJ DUGGAN 160 B SMILES & A SMILES-SCHMIDT 242 RR HOLLOW 167 GJ JAQUES 245 FS FAZIO 169 J ASZTALOS 246 AJ & JA BOLAND 170 MB COX 247 DA BOLAND 175 SF & MR ANDREWS 248 GA, MA, CJ & CM LANG 176 S RAYNER 249 AP & DE BOLAND 178 TRANSGRID 250 CJ WARD 200 BJ HUGHES, CA BEINSSEN, K ASLETT 251 PD FRENCH & LE SATTLER 201 SJ CUTHBERT 252 CM POOLMAN, A&W CREIGHTON 202 SV MCGUINESS & RL PRYOR 255 YR JONES 203 WP PRATT, CB & EA TOBIN 258 ICI AUSTRALIA OPERATIONS PTY LIMITED 204 RON POTTER (FARMS) PTY LTD 262 JE MULLINS & CD IMRIE 205 AJ O'BRIEN 263 T NEVELL 206 EA HUNT 264 TURILL TC PTY LTD 207 AL DUNN 265 J & SJ HORVATH 208 JUSTIN KENNEDY LEWIS PTY LIMITED 270 MT PENNY PROPERTIES PTY LTD 209 ICELINK PTY LIMITED 274 GEBLE PTY LTD 210 TIMNATH PTY. LIMITED 281 LOCAWAY PTY LTD 211 MJ & BH PERRY 900 THE TRUSTEES OF THE ROMAN CATHOLIC CHURCH FOR THE DIOCESE OF BATHURST 212 BONGALONG PTY LTD 903 MJ HARDIMAN & DM HOGAN 213 IWI CATTLE CO.PTY.LIMITED 908 AE & AW LYNCH 214 A ISAAC 914 S NICOD 215 TM LARKIN & ET MONAGHAN 921 EH TOOMBS 216 RJ WAUGH 933 CR FAULKNER 217 AE MCDONALD 942 RWM & SM SCHNEIDER 218 RE, MR & H LUESCHER 952 BJ & DM O'HARA 219 JA LUCKETT 959 CJ CLARKE 220 V & N STANKOVIC

WIL-12-12 WEP_EIS_Section 1_001D

* Refer to Figures 1-5a and 1-5b for Land Ownership Plan and Wollar Inset.

Source: WCPL (20 15); NSW Land & Property Information (2015)

WILPINJONG EXTENSION PROJECT Relevant Landholder List*

Figure 1-5c

1.1.6 Proponent 1.2 SECRETARY’S ENVIRONMENTAL ASSESSMENT REQUIREMENTS The Project is being developed by WCPL (ABN: 87 104 594 694), a wholly owned subsidiary The SEARs for the Project were issued by the of Peabody Energy. DP&E on 9 December 2014 and 22 June 2015 (Attachment 1). The registered office for Peabody is: A summary of the SEARs is provided in Tables 1-2 Peabody Energy Australia Pty Ltd and 1-3, as well as the relevant section of the EIS 100 Melbourne Street where the SEARs are addressed. SOUTH BRISBANE QLD 4101 In addition, a summary indicating where controlling provisions under the EPBC Act have been addressed in the EIS is provided in Table 1-4, and a summary indicating where the supplementary SEARs have been addressed in the EIS is provided in Attachment 2.

Table 1-2 Secretary’s Environmental Assessment Requirements – Reference Summary1

Summary of EIS Requirements EIS Reference

General Requirements

The EIS must include:

• Form requirements in clause 6 of Schedule 2 of the EP&A Regulation. Front of EIS and Attachment 3

• Content requirements in clause 7 of Schedule 2 of the EP&A Regulation. Refer to Table 1-3

• Description of the Project, including staging of the Project. Section 2

• Plans of proposed surface infrastructure and facilities. Section 2

• A waste management strategy. Sections 2.10 and 2.15

• A water management strategy. Section 2.12

• A rehabilitation strategy. Section 5

• Interaction of the Project with existing, approved and proposed mining Section 2.5 operations.

• A list of approvals that must be obtained before the development may Section 6 and Attachments 5 and 6 commence.

• A description of the existing environment. Section 4

• Assessment of the potential environmental impacts of all stages of the Project, Section 4 including cumulative impacts.

Wilpinjong Extension Project Environmental Impact Statement Section 1 - Introduction Document Number: 00659084 Version: A 1-13

Table 1-2 (Continued) Secretary’s Environmental Assessment Requirements – Reference Summary1

Summary of EIS Requirements EIS Reference

• A description of the measures that would be implemented to mitigate and/or Sections 4, 5 and 7 offset the potential impacts of the Project including: - whether the measures are consistent with industry best practice and represent the full range of reasonable and feasible mitigation measures; - the likely effectiveness of the measures; and - contingency plans.

• A description of the measures that would be implemented to monitor and Sections 4, 5 and 7 report on the environmental performance of the Project.

• A consolidated summary of all proposed environmental management and Section 7 monitoring measures.

• Consideration of relevant environmental planning instruments. Section 6 and Attachments 5 and 6

• Project justification. Section 6.7

• An estimate of the capital investment value of the Project. Attachment 7

• An estimate of the jobs that would be created during each stage of the Project. Sections 2.17 and 4.16

Specific Issues

• Noise. Sections 4.3, 4.5 and 4.14 and Appendix A

• Air. Sections 4.4, 4.6 and 4.18 and Appendix B

• Water. Sections 4.7 and 4.8 and Appendices C and D

• Biodiversity. Section 4.9 and Appendices E and F

• Heritage. Sections 4.10 and 4.11 and Appendices G and H

• Land. Section 4.12, Appendices I, K, and L and Attachment 8

• Transport. Section 4.13 and Appendix J

• Visual. Section 4.15 and Appendix O

• Social and Economic. Sections 4.16 and 4.17 and Appendices M and N

• Public Safety. Section 4.19 and Appendices P and Q

Consultation

• Describe the consultation that was carried out, identify issues raised during Section 3 this consultation, and explain how these issues have been addressed in the EIS.

1 The complete version of the SEARs is presented in Attachment 1.

Wilpinjong Extension Project Environmental Impact Statement Section 1 - Introduction Document Number: 00659084 Version: A 1-14

Table 1-3 Content Requirements of an EIS – Clause 7 of Schedule 2 of the EP&A Regulation

Summary of Clause 7 of Schedule 2 of the EP&A Regulation EIS Reference

The EIS must include:

• Summary of the EIS. Executive Summary

• Objectives of the Project. Section 6.7.1

• Analysis of any feasible alternatives to the Project, including the consequences of not Section 6.7 carrying out the Project.

• Description of the Project. Section 2

• Description of the environment likely to be affected by the Project. Section 4

• The likely impact on the environment of the Project. Section 4

• Description of the measures proposed to mitigate any adverse effects of the Project on the Sections 4, 5 and 7 environment.

• A list of any approvals that must be obtained under any other Act or law before the Project Section 6.4 may lawfully be carried out.

• Compilation (in a single section of the EIS) of the measures proposed to mitigate any Section 7 adverse effects of the Project on the environment.

• Justification of the Project, having regard to biophysical, economic and social Section 6.7 considerations, including the principles of ecologically sustainable development (ESD).

Table 1-4 EPBC Act Controlling Provisions – Reference Summary

EPBC Act Controlling Provisions1 EIS Reference

Threatened species and ecological communities, including:

• White Box-Yellow Box-Blakely’s Red Gum Grassy Woodland and Derived Native Grassland (Box-Gum Woodland).

• Anthochaera phrygia (Regent Honeyeater).

• Ozothamnus tesselatus. • Section 4.9 and Lathamus discolor (Swift Parrot). Appendix E • Dasyurus maculatus maculatus (Spot-tailed Quoll, Spotted-tail Quoll, Tiger Quoll: south-eastern mainland population).

• Chalinolobus dwyeri (Large-eared Pied Bat, Large Pied Bat).

• Nyctophilus corbeni (South-eastern Long-eared Bat).

Water resources:

• Impacts to the surface water quality and/or hydrology of Wollar, Wilpinjong and Cumbo Section 4.8 and Creek. Appendix D

• Impacts to Groundwater, Groundwater Users and Groundwater Dependant Ecosystems Sections 4.7 and 4.9 and (GDEs). Appendices C and E

• Sections 4.7 and 4.8 and Cumulative impacts on water resources. Appendices C and D 1 Refer to Attachment 1.

Wilpinjong Extension Project Environmental Impact Statement Section 1 - Introduction Document Number: 00659084 Version: A 1-15

1.3 PROJECT CONSULTANTS • Deloitte Access Economics (economic assessment); This EIS was prepared by Resource Strategies Pty • Elliott Whiteing (social impact assessment); Ltd with specialist input provided by the following organisations: • Marc & Co (visual simulations);

• • Palaris (mine scheduling, sequencing and final Safe Productions Solutions (environmental risk landform); assessment); and • • WCPL (project design, alternatives and McCullough Robertson (legal review). justification, preliminary hazard analysis, background data, resource economics, In addition to the above, peer review was consultation, rehabilitation and environmental undertaken by the following specialists monitoring and management); (Attachment 4):

• SLR Consulting (noise and blasting • Mr Richard Heggie (noise and blasting); assessment); • Mr Nigel Holmes (air quality); • Todoroski Air Sciences (air quality and • greenhouse gas assessment); Dr Frans Kalf (groundwater); • • HydroSimulations (groundwater assessment); Emeritus Professor Thomas McMahon (surface water); and • Groundwater Imaging Pty Ltd (transient • electromagnetic [TEM] survey); Dr Brian Fisher (economics).

• Groundwater Exploration Services (groundwater investigations); 1.4 DOCUMENT STRUCTURE

• WRM Water & Environment (surface water This EIS comprises a main text component and assessment); supporting studies, which includes Appendices A • Hunter Eco (terrestrial flora baseline report through Q. An overview of the main text is [development site], terrestrial flora baseline presented below: report [potential offset areas] and biodiversity assessment report and biodiversity offset Section 1 Provides an introduction to the strategy); Project and the EIS. • Biodiversity Monitoring Services (terrestrial Section 2 Describes the various components fauna baseline report [development site], and stages of the Project. terrestrial fauna baseline report [potential Section 3 Describes the consultation offset areas]); undertaken in relation to the EIS and • Bio-Analysis (aquatic ecology assessment); ongoing community involvement. • South East Archaeology (Aboriginal cultural Section 4 Details the environmental heritage assessment); assessment for the Project including a description of the existing • Niche Environment and Heritage (Niche) environment, an assessment of (historical heritage assessment); potential impacts and a description of • McKenzie Soil Management (land and soil measures that would be implemented assessment); to avoid, minimise, mitigate, offset, manage and/or monitor the potential • GTA Consultants (road transport assessment); impacts of the Project. • Geo-Environmental Management Section 5 Describes the rehabilitation strategy (geochemistry assessment); for the Project. • Lloyd Consulting (land contamination Section 6 Outlines the statutory provisions assessment); relevant to the Project, describes the alternatives considered and provides a Project justification.

Wilpinjong Extension Project Environmental Impact Statement Section 1 - Introduction Document Number: 00659084 Version: A 1-16

Section 7 Provides a summary of the proposed Appendices A to Q contain supporting environmental management, documentation, including a number of specialist mitigation, monitoring and reporting in reports: relation to the Project. Appendix A Noise and Blasting Assessment. Section 8 Lists documents referenced in Sections 1 to 7 of this EIS. Appendix B Air Quality and Greenhouse Gas Assessment. Section 9 Defines abbreviations, acronyms and terms used in Sections 1 to 7 of this Appendix C Groundwater Assessment. EIS. Appendix D Surface Water Assessment.

Attachments to the main text are also provided as Appendix E Biodiversity Assessment Report follows: and Biodiversity Offset Strategy.

Appendix F Aquatic Ecology Assessment. Attachment 1 Secretary’s Environmental Assessment Requirements. Appendix G Aboriginal Cultural Heritage Assessment. Attachment 2 Matters of National Environmental Significance Cross Reference Appendix H Historical Heritage Assessment. Table. Appendix I Land and Soil Assessment. Attachment 3 Development Application Area and Real Property Descriptions. Appendix J Road Transport Assessment. Attachment 4 Peer Review Letters. Appendix K Geochemistry Assessment. Attachment 5 Planning Instruments Addendum. Appendix L Land Contamination Assessment. Attachment 6 Aquifer Interference Policy Appendix M Economic Assessment. Considerations and Water Appendix N Social Impact Assessment. Licensing Addendum. Appendix O Visual Assessment. Attachment 7 Capital Investment Value Estimate Report. Appendix P Environmental Risk Assessment. Attachment 8 Geotechnical Advice. Appendix Q Preliminary Hazard Analysis. Attachment 9 Community Information. Attachment 10 Site Verification Certificate. Attachment 11 Relevant Division of Resources and Energy Correspondence. Attachment 12 Aboriginal Cultural Heritage Assessment Additional Assessment Information.

Wilpinjong Extension Project Environmental Impact Statement Section 1 - Introduction Document Number: 00659084 Version: A 1-17