IP Track Delivery Update The Railway Correspondence and Travel Society

4 September 2014 Steve Featherstone

/ Our Key Themes for CP5

. Safety and Performance go hand in hand

. Continuous Improvement

. Digitising the Railway

/ Safety and Performance go hand in hand – High Output

Initiative Safety benefit Performance benefit

Trains move when railway is FTAP 15 mins (TRS) operational

Removes need to access track ZKL(RC) 2 mins / line block when placing protection

Runway lights & Visual confirmation of adjacent 5 mins / line block 10:1 comms app line block Removes need to access 5-10 mins faster start for Lasers on tampers adjacent line to measure tampers

Removes risk of working at 15 mins CCTV on MFS height and in dust (Awaiting isolation)

Lean tool storage & well planned, More competent and strength 30 - 60 mins + lean, organised teams in depth

Prevents catastrophic failure of Magnetic drain plugs 4 shifts per annum hydraulics

More reliable and faster repair Proximity switches Better quality track at handback time

3 / Safety and Performance go hand in hand

Total - Rolling FWI vs %age of forecast volume delivered

0.140 140%

0.120 120%

0.100 100%

0.080 80%

0.060 60%

0.040 40%

0.020 20%

0.000 0% P1 P2 P3 P4 P5 P6 P7 P8 P9 P10 P11 P12 P13 P1 P2 P3 13/14 13/14 14/15

Rolling FWI %age volume achieved Linear (%age volume achieved) Linear (Rolling FWI)

/ Continuous Improvement - behaviour change

We need to:

Unlearn past behaviour

Copy great ideas / best practices “Copy with pride”

Share successes and learning's. “Share with pride”

Do things differently.

5 / 5 Structured Continuous Improvement at Network Rail Many different models:

- Total Quality Management - Six Sigma - Lean - Kaizen - Process Improvement - Process re engineering - 4 ation model: Eradication Simplification Rationalisation Automation

But all encompass….

6 / 6 Continuous Improvement - Concept of Marginal Gains

"The whole principle came from the idea that if you broke down everything you could think of that goes into riding a bike, and then improved it by 1%, you will get a significant increase when you put them all together"

Sir Dave Brailsford, CBE

 At the 2004 Olympic Games Great Britain won two cycling gold medals, their best performance since 1908.

 Won multiple world championships in road, track, BMX and

 Great Britain lead the cycling medal table at the 2008 and 2012 Olympic Games, winning 8 golds at both, while British cyclists won 59 World Championships from 2003-2013

 As Sky Team principal he oversaw both ' and 's victories in the 2012 and 2013 Tour de

 Won the BBC Sports Personality of the Year Coach Award on 14 December 2008 & 2012.

7 / 7 Digitising the Railway

ETCS BIM / 4D modelling ORBIS

RILA Traffic Management

8 / Our 10 Point Plan

/ 10 Point Plan

Unit cost

10. Improve 9. Improve 8. Significant 7. Re-tender 6. Re-org 5. Improve 4.Get eng 3. Improve 2. Improve 1. Improve Access Scope & technology contracts into specialist competence trains to planning plant safety Specification innovation teams & multi- site on time & lock reliability skilling downs

Network Network IP IP IP IP Network Network IP Track IP Track Ops Ops Track Track Track Track Ops Ops

/ 1. Safety – Adjacent Line Open Working, Ballast Dust and Fatigue are key issues

/ 2. Improved Plant Reliability

/ 2. Improved Plant Reliability

/ 3. Improved Planning and Lock Downs

Access Haulage

Specification Work method

/ 4. Get Engineering Trains to and From Site on Time

PAP ETPM MAA from April 2012 to June 2014

90%

80%

70%

60% Anglia Kent LNE LNW 50% East Mids Scotland Sussex 40% Wessex Western National National target

30% 1

2012 2013 2014 2015

/ 5. Competencies & Multiskilling

/ 6. Organise Track Delivery into specialists units

Previous organisation New specialist organisation

S&C • •

• activities • •

PL conventional

PL High Output

/ 7. Tender new contracts - S&C Procurement Outcome

PREVIOUS POSITION NEW LANDSCAPE

NORTH - EM, LNE, LNW EM, LNE, LNW (N) (N), Scotland & Wales (N) & Scotland AMEY SERSA BABCOCK

LNW (S), Wales & Western AmeyCOLAS SOUTH - Anglia, Kent, LNW (S), Sussex, Wales (S), Wessex & Anglia, Kent, Sussex & Western Wessex COLAS URS BALFOUR BEATTY 7. Tender new contracts - Plain Line Procurement Outcome

PREVIOUS POSITION NEW LANDSCAPE

2 2 EM, LNE, LNW (N) & Scotland EM, LNE & LNW BABCOCK (N) CARILLION

4 4 5 5 LNW (S), Scotland, Wales, Wessex LNW (S), Wales & 5 5 and Western 1 7 Western 1 7 3 3 BABCOCK AmeyCOLAS

1 1 6 6 1 6 1 6 Anglia, Kent, Sussex & Wessex Anglia, Sussex & Kent BALFOUR BEATTY COLAS 7. Tender new contracts - High Output In-Sourcing High Output Video 8. Significant Technology Innovation

S&C ballast treatment Modular slab track

RILA Micro-piling

/ 8. Significant Technology Innovation

App development Remote TCOD

Flexible Train Arrival Point Use of Unimogs

/ 9. Improved Scope and specification

Future position with Plain Line Current position Efficient Delivery Techniques (EDT)

campaigns £ £ £ £ campaigns £ £ £ £

£ £ £ £ £ £ £ £ £ £ £ £ Scope Scope short £ £ £ £ £ £ £ £ short £ £ £ £ £ £ worksites worksites

< 8 hrs blockades < 8 hrs blockades

Access Access

/ Plain Line Video

/ 10. Improved Access

High Output work in Wessex - what good really looks like:

10hrs access per night Adjacent line open working Signallers stop trains on request when all lines blocked is required Opening at 50 mph rather than 80mph 700 yards per night on jointed track 1,000 yards per night on CWR Every production record smashed

/ 10 Point Plan

Unit cost

10. Improve 9. Improve 8. Significant 7. Re-tender 6. Re-org 5. Improve 4.Get eng 3. Improve 2. Improve 1. Improve Access Scope & technology contracts into specialist competence trains to planning plant safety Specification innovation teams & multi- site on time & lock reliability skilling downs

Network Network IP IP IP IP Network Network IP Track IP Track Ops Ops Track Track Track Track Ops Ops

/ S&C Video

/ IP Track Delivery Update The Railway Correspondence and Travel Society

4 September 2014 Steve Featherstone

/