COACHELLA VALLEY WATER DISTRICT

Construction Update for February 15-19

THIS WEEK, the contractor will begin the abandonment process for the old water mains. Crews have been cleared to work on President’s Day on Monday, February 15. They will be breaking up concrete around the valves at intersections and around old fire hydrants along Pineknoll Avenue, Turnberry Isle Drive, Skycrest Road and Wyndham Road. The work is preparation for next week, when the pipes will be emptied of any residual water, capped off and filled with slurry. On Wednesday, February 17, the exit at Avenue 38 and Adams Street will be closed to traffic. Please watch for crews working in streets and follow traffic control signs.

Purple Sagebrush Ave Looking ahead Crystal Falls Rd Turnberry Isle Dr

Street grinding to prepare for Wyndham Rd paving on Pineknoll Avenue and Waterfall Dr the streets east is expected during the first week of March; Bougainvillea Dr Skycrest Rd paving is tentatively scheduled Abalo ne Wa to begin March 11. Pleasant Dr y

Silver Lake Festival Dr T err Golden Pebble Ave a ce

Pineknoll Ave

Hidden Palms Dr Ta marin d P od C t

Autumn Ln Tamarisk Flower Dr ADAMS ST

Dancing Waters Rd Tang erine Ct

Sandalwood Pl

Avenue 38

Signal CT Mimosa Dr

Fountain Hills Dr

Naranja Dr Rancho Los Coyotes Dr Dr Coyotes Los Rancho

Edgebrook Ln

ATTENTION!

PROPERTY DAMAGE RELEASE FORM Homeowners in areas where construction is complete (Phases 1A and 1B) have been sent a Property Damage Release Form by the contractor, DCI Construction. Those who have not signed and returned the form will be sent another copy by email and/or mail.

If the signed form is not returned in 30 days, it will be assumed that private property and landscaping have been returned to pre-construction condition and the contractor will be released from liability. For additional information, contact Corrie Pettit at DCI Construction, [email protected] or 909-797-7444.

Mail Deliveries

Mail for homes in the construction area will be delivered day to the Sun City Postal Center, where it will be held for pick up. Any mail delivery deemed undeliverable About the SCPD Pipeline will be available at the Postal Replacement Project Center the following day. The Postal Center is located in the Coachella Valley Water District is replacing ductile Mountain View Clubhouse at iron pipelines throughout the community that are Avenue 38 and Del Webb failing because of soil corrosion. The 10-year Boulevard and is open Monday project includes new water mains, water service through Friday, 9 a.m. to laterals, valves, fire hydrants and street paving. 3:30 p.m.

THE WORK WILL IMPROVE WATER For more information, RELIABILITY FOR THE COMMUNITY BY please contact the Postal Center at 760-200-2236. REDUCING MAIN BREAKS AND EMERGENCY REPAIRS.

Contact Us Stay up-to-date on the latest Questions and concerns can be directed to: construction news! Project hotline: 760-392-4006 Website: www.cvwd.org/suncity Email: [email protected]

YOUR WATER IS OUR PROMISE.