FORM-1, PRE FEASIBILITY & APPROVED MINING PLAN

KURICHIPATTI GRAVEL QUARRY

S.F.NO: 172/1(1.31.0), 172/4(1.35.0), & 172/5(1.17.5)

Kurichipatti Village, Taluk,

Madurai District, Tamilnadu

Quarry lease area - 3.83.5Ha

Gravel Production – 50,414m3

Period – (One) 1 year only

Thriu.S.MUTHUKUMARAN, S/o A.M.SUBBIAH, 2/276, POS MELUR TALUK, –625105.

CONTENTS

S.NO PARTICULARS PAGE NO

1. Form 1 1 2. Pre Feasibility Report 35 3. Approved Mining Plan Letter with seal by the 71 Department of Geology and Mining. 4. Precise Area Communication Letter from Madurai 149 District Collector. 5. Letter from the Department of Geology and 169 Mining of other quarries within 500m Radius from the proposed quarry site. 6. Affidavit from the Applicant regarding general 171 Conditions,Habitation,other quarry, Permanent structure ,Child Labour ,etc 7. Documents of Village records, FMB and 1Km & 151 10Km Radius Map.

Form 1 as per EIA Notification 2006 for Kurichipatti Gravel Quarry of Thriu.S.Muthukumaran, Kurichipatti Village, Melur Taluk and , Tamilnadu

Form 1

Application Form for Obtaining Environmental Clearance from State Level Environment Impact Assessment Authority (SEIAA), S. No Item Details 1 Name of the project/s Kurichipatti Gravel Quarry project 2 S. No. in the schedule 1 (a) Proposed capacity = 50,414m3 for a period of (One) 1 year only. Area =3.83.5Ha. Dimensions of the area Proposed capacity/area/length/ Length in Width in Depth 3 tonnage to be handled / (m) (M) in (m) command area/lease Avg area/number of wells to be drilled 381 99 2m It is open cast shallow quarrying the Gravel is clearly visible right from the surface hence No wells are proposed not drilled. 4 New/ Expansion/ Modernization It’s a new Project ( Kurichipatti Gravel quarry) Existing capacity / Area etc. The proposed capacity is only 50,414m3 for 2m. The total Geological reserve is about 5 1,91,750m3. Area = 3.83.5Ha. 6 Category of project i.e. `A’ or ‘B’ Category - B (B2) Does it attract the general 7.5m & 10m safety distance from the adjacent 7 condition? If yes, please specify. patta lands. Does it attract the specific The project does not attract any specific 8 condition? If yes, please specify. condition. Location Kurichipatti Village, Melur Taluk and Madurai District. Plot/ Survey/ Khasra No. 172/1(1.31.0), 172/4(1.35.0),172/5(1.17.5)

7 Village Kurichipatti Taluk Melur District Madurai State Tamilnadu Nearest railway station/ airport Railway station -25km - SW 10 along with distance in km. Madurai Airport - 40.5km - SW Nearest Town, city, Madurai Nearest Town: Melur - 13.0km - NW 11 District Headquarters along with Nearest City : Melur - 4.0km - NE distance in kms. District : Madurai - 34.5km - SW

Village Panchayats, Zila Parishad, Village Panchayat - Kurichipatti Municipal Corporation, Local Panchyat Union - Melur 12 body (Complete postal addresses Taluk - Melur with telephone nos. to be given) District - Madurai 13 Name of the applicant Thiru. S.Muthukumaran S/o A.M.Subbiah,

Kurichipatti Village,

14 Registered Address 2/276, Vellalur Post , Melur Taluk, Madurai –625105 Cell No. 9840666600

Address for correspondence Thiru. S.Muthukumaran Designation Proprietor/Owner (Owner/Partner/CEO) S/o A.M.Subbiah, Address Kurichipatti Village, 2/276, Vellalur Post , Melur Taluk, 15 Madurai –625105 Pin code 625105

E-mail [email protected]

Telephone No. Cell No: 9840666600

Fax No. -

Details of Alternative Sites examined, if any. Location of There is no alternative site examined. The 16 these sites should be shown on a project is site specific. Topo sheet 17 Interlinked Projects There is no interlinked projects Whether separate application of As there is no interlinked project, no 18 interlinked project has been application has been submitted submitted? If yes, date of submission As there is no interlinked project hence no 19 application has been submitted. If no, reason 20 The project involves Gravel Quarry only. Whether the proposal involves (a) The project does not attract the Forest approval/ clearance under: if yes, (Conservation) Act 1780. There is no details of the same and their Forestland involved within the quarry lease- status to be given. applied area. (a) The Forest (Conservation) Act, (b) There is no wild life within the 10km 21 1780? radius from applied area and does not fall (b) The Wildlife (Protection) Act, under the Wildlife (protection) Act 1772. 1772? (C) The project doesn’t attract the C.R.Z. (c) The C. R. Z. Notification, 1771? Notification, 1771.

The applicant has obtained precise area communication from the District Collector, Madurai vide (Rc.No.977/2016-Mines dated

30.11.2016) Whether there is any Government 22 The Mining Plan was got approval by the Order/ Policy relevant/ relating to the site? Deputy Director, Department of Geology and Mining, Madurai vide (Rc.No.977/2016-Mines dated 03.02.2017.)

23 There is no forest land involved in this lease Forest land involved (hectares) area. Whether there is any litigation pending against the project and/ or land in which the project is propose to be set up? There is no court case pending, litigations 24 (a) Name of the Court relating to the project directly and indirectly. (b) Case No. (c) Orders/ directions of the Court, if any and its relevance with the proposed project.

I. Basic information II. Activity 1. Construction operation or decommissioning of the project involving actions, which will cause physical changes in the locality (Topography, land use changes in water bodies, etc.) Details thereof (with approximate Information/Checklist Yes/ S. No quantities/rates, wherever possible) with confirmation No sources of information data Permanent or temporary change in land use, land The topography will be slightly changed cover or topography after the quarrying of Gravel as per the 1.1 including increase in Yes Mining Plan, Gravel formation is seen intensity of land use (with right from the surface to a depth of 10m respect to local land use Below ground level. plan)

Clearance of existing land, The quarry lease applied area is devoid of 1.2 vegetation and building? No vegetation’s, Human settlement and buildings hence clearance is redundant.

The quarrying activity is proposed to carry out within the quarry lease applied area. Temporary approach road within 1.3 Creation of new land uses? No the area will be form for the easy access of men and machinery which will be well maintained. The Gravel deposits are clearly visible Pre-construction right from the surface hence pre- 1.4 investigations e.g. bore No construction investigation and soil houses, soil testing? testing is not proposed before quarrying operation. There will be no major civil work in this project involved. The infrastructure Construction works? Yes 1.5 facilities are proposed in the quarry site on semi-permanent structures. There is no existing building within the 1.6 Demolition works? No quarry lease applied area; hence no demolition work is involved. Temporary sites used for Sites service on semi-permanent construction works or Yes structure will be constructed only after 1.7 housing of construction grant of quarry lease. workers? There are no tall buildings or linear Above ground buildings, structure found in and around the structures or Red quarry site. There is no requirement of 1.8 Earthworks including linear No cutting and filling in the site. The structures, cut and fill or proposed quarry is to exploit Gravel from excavations. consolidated sediments for 2m Below ground level.

Open cast semi mechanized method of Underground works quarrying will be adopted. No including mining or No 1.9 underground mining or tunneling is tunneling? proposed. The quarry operation is restricted up to a depth of 2m Below ground level. after Reclamation works? removing the Gravel there is no proposal 1.10 No for backfilling or reclamation. The quarried out land will be leveled and used for agricultural purpose. There is no such type of activities 1.11 Dredging? No involved in this opencast quarrying operation. There is no such type of activities 1.12 Offshore structures? No involved; It is an inland quarrying project.

No production and manufacturing is Production and No involved in the Gravel Quarrying. 1.13 manufacturing processes?

There is no proposal for storage of material within the quarry lease applied area. The Gravel will be loaded directly to the trucks / Lorries for transportation to Facilities for storage of 1.14 No the needy customer’s site for goods or materials? construction industries for Government & Public sector projects besides catering domestic housing and infrastructure projects in and around the Madurai District. There is no wastage encountered during the quarrying operation, the entire excavation will be used for construction industries for Government & Public Facilities for treatment or 1.15 disposal of solid waste or No sector projects besides catering domestic liquid effluents? housing and infrastructure projects in and around the Madurai District. The Gravel will not produce toxic effluence in the form of solid, liquid or gas. The proposed project is 3.83.5Ha for a period of (One) 1 year only. The required Facilities for long term employees (7Nos.) are available in the 1.16 housing of operational No nearby villages, hence long term housing workers? of operational workers are not proposed.

No new roads, rail or sea traffic is New road, rail or sea traffic proposed during operation, the existing during construction or road will be utilized for transportation of operation? No the Gravel. 1.17 However, internal roads within the quarry

lease applied area will be developed and

maintained.

New road, rail, air There is no such type of activities waterborne or other involved in this project. transport infrastructure No Existing road will be utilized for the 1.18 including new or altered transportation of Gravel to the needy routes and stations, ports, customer’s site. airports etc.?

Closure or diversion of existing transport routes or The project will not cause any changes 1.19 infrastructure leading to No and hindrance in the existing traffic changes in traffic movements. movements? New or diverted The project does not involve diversion of 1.20 transmission lines or No transmission/pipe lines. pipelines? The quarrying operation is restricted up Impoundment, damming, to a depth of 2m Below ground level; 1.21 culverting, realignment or No Ground water occurrence in this area is other changes to the at 20m depth from ground profile. Hence hydrology of watercourses there is no damage for ground water or aquifers? hydrology or aquifers.

There is no stream crossing within the 1.22 Stream crossings? No quarry lease applied area.

Abstraction or transfers of The proposed quarrying does not require 1.23 water form ground or No any abstraction or transfer of water from surface waters? the ground or surface water bodies. The quarry operation is restricted up to a Changes in water bodies or depth of 2m. Quarry operation will not 1.24 the land surface affecting No affect the drainage pattern of the area. drainage or run-off? There is no change in water bodies or the land surface affected during run off. During operation phase, after grant of lease quarrying personnel will be brought from surrounding villages by jeep or van. Transport of personnel or materials for construction, The materials and tools shall be 1.25 No operational or transported by trucks and tippers, the decommissioning? existing road and infrastructure facilities are sufficient. No construction operation or decommissioning envisaged.

Long-term dismantling or There is no Dismantling or 1.26 decommissioning or No decommissioning is proposed in this restoration works? project. Ongoing activity during decommissioning which There is no such type of activities involved No 1.27 could have an impact on in this project. the environment? During operational phase, the manpower requirement will be around 7. Local people are envisaged in this quarry Influx of people to an area operation. No child labor will be deployed 1.28 in either temporarily or Yes for any type of quarrying operation. All the permanently? labors engaged for quarrying operations will be trained, equipped with protective devices and insured till the end of life of quarry. . Introduction of alien There are no causes to develop the alien No 1.29 species? species. There will no loss of native species or genetic diversity taken during the Loss of native species or No quarrying operation as the lease applied 1.30 genetic diversity? area is devoid of vegetation and agriculture.

1.31 Any other actions? No There is no any other actions

2. Use of Natural resources for construction or operation of the project (such as land, water, materials or energy, especially any resources which are non - renewable or in short supply): Details thereof (with approximate Information/Checklist Yes S. No quantities/rates, wherever possible) with confirmation /No sources of information data

It’s a Patta land registered in the name Thiru.S.Muthukumaran Vide Patta No- 2514. The Applicant has obtained surface rights to lease applied area. Please refer the Annexure No – IV. The lease applied area is exhibits almost plain terrain topography covered Land especially undeveloped No with Gravel which does not sustain any 2.1 or agricultural land (ha) type of vegetation due to the topography of the land. The altitude of the area is 125m (Maximum) from MSL, the slope of the area is gentle towards southeastern side. Please refer the Topography, Geological plan and sections (Plate No –VII & VII A).

The project does not require huge water for quarrying operation, about 1 KLD of water will be used for the project. 1. Drinking Water – 0.3 KLD & Domestic purpose 2. Dust Suppression – 0.3 KLD 3. Green belt – 0.4 KLD Total – 1 KLD 0.3 KLD of Packaged Drinking water and Water (expected source & Domestic purpose will be brought from Yes 2.2 competing users) unit: KLD the approved water vendors in Kurichipatti which is about 2.0km on the Northeastern side of the area. 0.3 KLD of water for dust suppression and 0.4KLD of water for Green developments will be brought from approved water venders or existing borehole on nearby quarry. Total requirement for the project is around 1KLD. There is no Minerals used for 2.3 Minerals (MT) No construction purposes

Construction material - two, There is no Construction material 2.4 aggregates, and/Soil No proposed. (expected source-MT) Forests and timber There are no forests and timber material No 2.5 (source-MT) is proposed.

The limited scale of activities adopted in Gravel Quarrying does not require high- Energy including electricity tension electric power supply. Fuels are and fuels (source, competing Yes used for operating vehicles during 2.6 users) unit: fuel (MT),Energy (MW) quarrying process. Fuels required for excavator for the entire project life 8400 liters of HSD. 2.7 Any other natural resources There is no other natural resource will (use appropriate standard No be required. units)

3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health. Details thereof (with approximate Information/Checklist Yes S. No quantities/rates, wherever possible) with confirmation /No sources of information data Use of substances or There is no proposal for storage, materials, which are handling or transportation of any hazardous (as per MSIHC No hazardous materials or substances as 3.1 rules) to human health or the per MSIHC rules in this Gravel Quarry environment (flora, fauna, project. and water supplies) The Gravel does not produce any toxic Changes in occurrence of effluent in the form of solid, liquid and disease or affect disease 3.2 No gas, hence the diseases related to insect vectors ( e.g. insect or water or water borne diseases is not borne diseases) envisaged. Welfare of people will get positive change due to the project, where a number of Welfare activities are being undertaken. Due to increase of the employment earning of local people and lifestyle of the people will enhance, Affect the welfare of people around 7 peoples will be directly benefit e.g. by changing living No 3.3 to this project. conditions? No child labor will be engaged for any type of quarrying operation. All the labor will be insured and the salary and benefits will be paid as per the Labor enforcement officers (Ministry of labor and welfare) Norms. Vulnerable groups of people There is no effect envisaged for the who could be affected by the No vulnerable groups of people who could 3.4 project e.g. hospital patients, be affected by the project. children’s, the elderly etc., 3.5 Any other causes No There is no other cause are envisaged 4.0 Production of solid wastes during construction or operation or decommissioning (MT/mounts) Details thereof (with approximate Information/Checklist Yes S. No quantities/rates, wherever possible) with confirmation /No sources of information data The Gravel Quarrying does not produce any waste. The entire Gravel will be Spoil, overburden or mine No excavated. There are no wastages 4.1 wastes encountered during the quarrying period (One) 1 year only.

Small quantity of Municipal waste will be Municipal waste (domestic Yes generated which shall be disposed as per 4.2 and or commercial wastes) guidelines. In this quarrying activities waste oil will be generated during the operation period it will be sent to authorize Re- Circulars Hazardous wastes (as per as per SPCB/ CPCB norms. Care and Hazardous Waste No 4.3 maintenance of vehicles by experience Management Rules) qualified mechanics will be undertaken to prevent breakdown and spillage of oils and lubes.

Other industrial process Industrial wastages are not generated 4.4 No wastes during the quarrying operation. There is no such type of activities in this Surplus product No 4.5 quarry. Sanitary facilities will be constructed as Sewage sludge or other semi-permanent structure and the 4.6 sludge form effluent Yes sewage waste will be disposed as per the treatment norms. Construction or demolition There are no Construction or demolition 4.7 No wastes wastes involved in this quarry.

No redundant machineries involved in Redundant machinery or No this project, only Excavator and tipper 4.8 equipment are involved in this quarry operation.

Contaminated soils or other There is no contaminated material or soil No 4.9 materials observed in the quarry area. There is no agricultural waste Agricultural wastes No 4.10 anticipated.

4.11 Other solid wastes No There is no other solid waste anticipated.

5.0. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr) Details thereof (with approximate Information/Checklist Yes/ S. No quantities/rates, wherever possible) confirmation No with sources of information data The emissions of SO2 (Sulfur dioxide) &

NO2 (Nitrogen dioxide) may be due to Emissions form combustion of use of diesel operated quarry 5.1 fossil fuels from stationary or Yes machinery and vehicles. Better mobile sources maintenance of equipment in good condition will help to reduce such emissions. Dust is the main pollutant produced in the proposed activity. Emission from loading and plying of tippers can take place but they will be maintained Emissions from production Yes 5.2 processes within limits by proper maintenance and sprinkling of water on haul roads, Tarpaulin covers during Transportation.

Fugitive dust will be generated from material handling activities. Dust suppression by water Emissions from materials sprinkling will be provided to prevent handing including storage or Yes 5.3 the fugitive dust emissions during transport loading. Tarpaulin covers will be covered in vehicles during transportation. Emissions form construction There is no major construction activities including plant and No 5.4 activities are envisaged. equipment Minor Dust will be generated during loading of material, transportation of Dust or odors form handling of materials including Gravel and it will be controlled. 5.5 No construction materials, However, there is no possibility of any sewage and waste odor generation as there are no organic solvents/processes involved.

Emissions from incineration The Gravel Quarrying does not 5.6 No of waste produce any toxic effluents. Emissions from burning of waste in open air (e.g. slash There is no such type of activities No 5.7 materials, construction involved in this project. debris) 5.8 Emissions from any other Emissions from other sources are not No sources envisaged.

6.0. Generation of Noise and Vibration, and Emissions of Light and Heat: Details thereof (with approximate Information/Checklist Yes/ S. No quantities/rates, wherever possible) confirmation No with sources of information data Due to operation of machinery there is likely hood of some increase in noise level. The noise level at site will be maintained Above permissible limit. Measures like lubrication and From operation of equipment preventive maintenance shall be e.g. engines, ventilation plant, Yes 6.1 taken to control noise from the crushers machinery. The vibration during the movement of machinery will be minimal for a short span which will be well within the prescribed limits. From industrial or similar There is no proposal of processing No 6.2 processes plant From construction or No construction or demolition work No 6.3 demolition takes place. No drilling or blasting is proposed for 6.4 From blasting or piling No this Gravel Quarrying operation. The transport of Gravel through tippers can produce noise but are maintained within permissible limits, From construction or 6.5 Yes by keeping machinery in proper operational traffic condition as per RTO &TNPCB norms and maintenance under experience and qualified mechanics.

The quarry operation will be carried From lighting or cooling out at the daytime only between 7Am 6.6 No systems to 6Pm hence; the lighting and cooling systems are not required. 6.7 From any other sources No Not envisaged

7.0. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface water, ground water, coastal water or the sea: Details thereof (with approximate Information/Checklist Yes/ S. No quantities/rates, wherever possible) confirmation No with sources of information data No hazardous materials will be used in the process. From handling, Storage, use Oiling and lubrication of hauling 7.1 or spillage of hazardous No vehicles will be done by using oil tray materials to prevent spillage of oil. Vehicles and machinery will be well maintained to prevent leakage of oil. The discharge of sewage will The Discharge of sewage will be be collected on soak pits will collected on soak pits and will be 7.2 be discharge to a place No discharge to a place authorized by authorized by municipal Municipal Authorities as per guide authorizes as per guidelines lines. There is likely hood of increase of By deposition of pollutants particulate matter due to quarrying 7.3 emitted to air into the land or No operations. Regular sprinkling of into water water will suppress dust at points/places of generation.

An efficient and effective management plan is proposed for the project; 7.4 From any other sources No hence it may not have any significant impact on the surrounding environment. Is there a risk of long term There is no such type of activities buildup of pollutants in the involved in this quarry. No 7.5 environment from these sources?

8.0. Risk of accidents during construction or operation of the project, which could affect human health or the environment Details thereof (with approximate Information/Checklist Yes/ S. No quantities/rates, wherever possible) confirmation No with sources of information data No explosions and spillages are From explosions, spillages, proposed for quarry operation. The fires etc., form storage, Gravel will be directly excavated with 8.1 No handling, use or production of the help of excavator. hazardous substances The quarry operation does not produced hazardous material. Limited vehicles are only used for quarrying operation up to a depth of 2m Below ground level. Hence the accident is anticipated minimal. However, all safety measures 8.2 From any other causes Yes shall be taken to prevent any accidents. The quarrying activities will be monitored under the supervision of experienced and qualified competent mines foreman.

There is no Earth quake, floods, Landslides, cloud burst Could the project be affected recorded in the area. Its opencast by natural disasters causing quarrying proposed only for 2m depth 8.3 environmental damage (e.g. No floods, Earth quakes, Below ground level which will not landslides, cloudburst etc.)? cause any adverse environmental damage due to natural disasters.

9. Factors which should be considered (such as consequential development) which could lead to environmental effects to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality

Details thereof (with approximate Information/Checklist Yes/ S. No quantities/rates, wherever possible) confirmation No with sources of information data

Lead to development of Living standard will be improved supporting. cities, ancillary development or development of the nearby villagers. stimulated by the project This short span of project does which could have impact on not require any supporting

the environment e.g.: infrastructures like roads, power

9.1  Supporting infrastructure supply, waste treatment, etc., (roads, power supply, waste The workers are available from or waste treatment, etc.) No the nearby villages, hence the project  housing development will not attract housing Development,  extractive industries  supply industries Extractive industries, supply  other industries or any other activities.

The quarry operation is restricted up to a depth of 2m Below ground level, Lead to after- use of the site, after removing the Gravel there is no 9.2 which could heaven impact on No proposal for backfilling or environment reclamation. The quarried out land will be leveled and used for agricultural purpose.

Set a precedent for later No There is no later developments 9.3 developments Have cumulative effects due to proximity to other existing There is no cumulative impacts are 9.4 No or planned projects with envisaged. similar effects

(I) Environmental Sensitivity S. Name/ Aerial distance (within 15 km.) Areas No Identity Proposed project location boundary

Areas protected under international conventions, national or local No protected areas to be identified with in 15 km No 1 legislation for distance. their ecological, landscape, cultural or other related value Areas which are important or There is no wild life, bird sanctuary, Reserve or sensitive for Social forest 15km near the quarrying lease applied ecological reasons area. - Wetlands,

watercourses or No 2 There is no coastal, Forest, Eco sensitive Zone other water within the radius of 15Km, the area does not fall in bodies, coastal HACA region. zone, biospheres,

mountains, forests Areas used by protected, important or sensitive species of flora or fauna There is no protected sensitive species identified 3 No for breeding, within the 15km radius. nesting, foraging, resting, over wintering, migration Inland, coastal, marine or There is no Inland, coastal, marine or underground No 4 underground water around the site. waters

State, National There is no State or National boundaries within a 5 No boundaries radius of 15Km.

Routes or facilities used by the public for access to There is no Tourist, pilgrim areas within 15Km Yes 6 recreation or radius other tourist, pilgrim areas

Defense 7 No No defense installation found 15km near the site installations Melapoongudi is a densely populated village which is about at a distance 3.5km SE side.

Approximate distance & Approximate S.No Name of the Village Direction population from lease applied area Densely populated 8 or built-up area Yes 1. Koolipatti 1.0km – SW 200

2. Kurchipatti 1.0km – NE 150

3. Melapoongudi 3.5km – SE 250

4. Palaiyurpatti 3.0km - NW 200

Areas occupied by sensitive man- Vellalore is having all the facilities, which are at a made land uses distance of 4.0km on the Northwestern side from the 9 (hospitals, schools, Yes lease-applied area. places of worship, community facilities) Areas containing important, high quality or scarce resources The quarry operation is restricted to only 2m Below (ground water ground level. Hence the ground water will not be 10 No resources, surface affected beside the area is devoid of agriculture, resources, Forestry, Tourist place etc., forestry, agriculture, fisheries, tourism, minerals) This is a fresh quarry lease applied area.

Areas already subjected to pollution or environmental damage. (those 11 No where existing legal environmental standards are exceeded)

Areas susceptible to natural hazard which could cause the project to present environmental problems The area is not susceptible to natural hazards like 12 No (Earth quakes, landslides, Earth quake; it is a high stable land. subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions)

“I hereby given undertaking that the data and information given in the application and enclosures are true to the best of my knowledge and belief and I am aware that if any part of the data and information submitted is found to be false or misleading at any stage, the project will be rejected and clearance give, if any to the project will be revoked at our risk and cost.

Signature of the applicant with Name and Full Address

Thiru. S.Muthukumaran, S/o A.M.Subbiah, Kurichipatti Village, 2/276, Vellalur Post, Melur Taluk, Madurai –625105

Signature of the Recognized qualified person

S.LAKSHMIKANTHAN.M.Sc., RQP/MAS/262/2014/A

Place: Salem Date: