Environmental Monitoring Report

Project Number: 47101-003 March 2019

Period: January 2018 – June 2018

IND: Power Sector Investment Program - Tranche 2

Submitted by Assam Power Distribution Company Limited,

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Assam Power Sector Investment Program Tranche – 2 (Loan No.: 3327-IND)

Bi-Annual Environmental Safeguard Monitoring Report (January-June 2018)

February 2019

Prepared by the Assam Power Distribution Company Limited for the Asian Development Bank

This environmental safeguard monitoring report is a document of the borrower and made publicly available in accordance with ADB’s Public Communications Policy 2011 and the Safeguard Policy Statement 2009. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff.

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Abbreviation ADB Asian Development Bank AEGCL Assam Electricity Grid Corporation Ltd. AP Affected People APSEIP Assam Power Sector Enhancement Investment Program ASEB Assam State Electricity Board D.C. District Collector EA Executing Agency EMP Environmental Management Plan ESMU Environmental and Social Management Unit GoA GoI Government of GRC Grievance Redress Committee GWSP Guwahati Water Supply Project IA Implementing Agency IEE Initial Environmental Examination Ltd. Limited LAA Land Acquisition Act LAO Land Acquisition Officer MFF Multi-Tranche Financing Facility PAP Project Affected Persons PMU Project Management Unit RoW Right of Way RF Resettlement Framework RP Resettlement Plan RPD Resettlement Planning Document S/S Sub Station SEIA Summary Environmental Impact Assessment SIEE Summary Initial Environmental Examination SRPD Short Resettlement Planning Document T&D Transmission and Distribution T/L Transmission Line T & T Transmission and Transformation

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 ii

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Contents A. PROJECT INFORMATION ...... 2 A-1: General ...... 2 B. IMPLEMENTATION STATUS ...... 10 B.1 Procurement Status ...... 10 B.2 Sub-Project Implementation Status ...... 10 C. DESIGN AND ENGINEERING STATUS ...... 13 D. COMPLIANCE STATUS ...... 14 D.1 Compliance with National and State Statutory Environmental Requirement ..... 14 D.2 Compliance with ADBs Environmental Safeguards (SPS, 2009) ...... 16 D.3 Compliance with Covenant ...... 18 D.4 Compliance with Environment Impact Management Plan ...... 21 D 5 Compliance with Environmental Monitoring Plan ...... 35 ANY OTHER ENVIRONMENTAL ASPECT NOT COVERED IN INITIAL ENVIRONMENTAL EXAMINATION ...... 41 E. INSTITUTIONAL MECHANISM ...... 42 F. GRIEVANCE REDRESS AND THEIR RESOULTION ...... 42

Annexure

Annexure 1A Output 1 Expansion and upgradation of the distribution system

Annexure 1B Output 2 Strengthening institutional capacity of APDCL

Annexure 2A Field visits observations

Annexure 2B Project progress photographs

Annexure 3 Details of PIU (Electrical Circle-wise)

Annexure 4 GRC reminder

Annexure 5 ESMU new Assistant Manager

Annexure 6 GRC formation under Electrical Circle

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 1

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

A. PROJECT INFORMATION A-1: General

i. Name of Project Assam Power Sector Investment Program ii. Loan Number 3327-IND Director, Project Management Unit (PMU) Name of Assam Power Distribution Company Limited iii. Monitoring/Reporting Agency (APDCL), 4th Floor, Bijulee Bhawan, Guwahati, and address 781001, Assam Monitoring Period iv. January-June 2018 (Season/month) v. Report No. 03 vi. Report for the period January-June 2018

vii. Date of reporting 01 December 2018

viii. Type of Contract Multi-Tranche Financing Facility (MFF)

A-2 Project progress highlights During the reporting period, considerable progress was made in the execution of project components. All the outputs: main and sub-components as outlined in the project’s Bid documents are included in the final estimation based on the route surveys etc. There are a few changes in the planned outputs, chiefly arising from revision in the scope (quantity) of select sub-outputs. These changes are attributed to detailed technical assessment conducted during the route/final surveys. The route surveys are a corollary of IEE, and forms the basis of the implementation. Among all the outputs, amendments are mostly in the line lengths under various categories. The Section 6, item 1.3 of the Bid document Vol. 1 outlines that quantities of supply of plant and services may vary to the extent of +/- 15% in terms of contact price. In this context, the effected changes with impact on the costs, are well within the acceptable limits thus mentioned. The details of outputs generated after the route and final surveys are as follows (Annexure 1A & 1B, Table A1). The progress achieved during the reporting period reflects the changes in the outputs (Table B2). Output 1 Expansion and up-gradation of the distribution system

 Sub-output 1: Construction of one new 33 kV/11kV substation, install the associated terminal equipment, and associated 33 kV lines (4 km) and 11 kV (6 km): alternative site identification is still in progress as the planned site at Kharguli is no longer tenable. Delays are expected owing to paucity of suitable land. It is anticipated that the site will be finalized before the year end.

 Sub-output 2: Construction of 130.22 km of new 33 kV line: following the route survey (RS) there is an increase in line length by 1.73 km with respect to the previous length 128.94 km,

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 2

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

the revised length being 130.22 km, within acceptable limit. This change has been effected at three (3) locations across three Electrical Circles (GEC I, and Sibsagar). Material supply and pole erection in progress.  Sub-output 3: Construction of 7 no. 33 kV railway line (1.15 km) and 2 no. river crossing (0.70 km): after the route survey, there is no change in the total crossings. Permission from Railways Department is waited.  Sub-output 4: Construction of 12 new 33 kV bays at existing 33kV/11kV substations: no change in the number of bays. Material supply in progress and construction underway in Barpeta Circle.  Sub-output 5: Construction of 7 km of 11 kV lines for the segregation of the rural and agricultural feeders: after RS, no change in line length. Material supply in progress and construction to commence after monsoons.  Sub-output 6: Re-conductoring/ refurbishment of 1024.31 km of 33 kV lines (there is increase in line length by 68.31 km after the RS as compared to previous length of 956 km). Material supply in progress and construction to commence after monsoons; except for pole erection and stringing (7.35 km) completed in EC. The feeder from Chirakhundi (Rangiya) GSS has been renamed to Rangiya GSS to . Under GEC I and Barpeta EC, 6 km (Kahilipara GSS to Ulubari S/S) and 0.5 km (Simlaguri to feeder Barpeta S/S), respectively removed from scope because of overlap with another scheme.  Sub-output 7: Rehabilitation and renovation of six (6) new 33 kV bays at existing 33 kV/11kV substations: no change in the scope. Survey completed and approval is pending.  Sub-output 8: Re-conductoring/ refurbishment of 1080.71 km of 11 kV lines (there is increase in line length by 80.71 km after RS as compared to previous length of 1000 km) in five Electrical Circles GEC I & II, , Rangiya, ). Change is within the acceptable limit. Material supply and pole erection in progress.  Sub-output 9: Re-conductoring/ refurbishment 1635.52 km of LT lines (there is increase in line length by 80.52 km after RS as compared to previous length 1555km in four Electrical Circles (GEC I & II, Bongaigaon, Rangiya) after the route survey but under the limit. Material supply, pole erection and stringing in progress.  Sub-output 10: Replacement of 204 existing oil-filled distribution transformers with dry-type transformers: no change in number, however, change in location effected, from GEC II to a new location in Bongaigaon. Work yet to commence.  Sub-output 11: Replacement of existing 14 km of overhead 11 kV & LT line with underground cable: change in scope anticipated as there is no resolution of the cable laying method yet. APDCL had requested the Public Works Department (PWD), Assam Govt.'s approval and estimate for reinstatement of roads in Guwahati for open cut trenches. In response, PWD recommended the Trenchless method for laying of all cables. To further explore the suitability of this method for Guwahati, APDCL visited an ongoing trenchless cable laying project in Bhubaneswar, Orissa. However, it was revealed that the trenchless method is not appropriate

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 3

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327 for the proposed 11kV and 33kV underground distribution cable laying process. Discussions between APDCL and the contractor are in progress to resolve this issue. Hence, no work in this regard has been initiated till date. Output 2 Strengthening institutional capacity of APDCL

 Sub-output 1: Setting up of one (1) independent meter testing laboratory: no change in scope.  Sub-output 2: Establishing one (1) IT module for the introduction of centralized uniform revenue billing system for all consumers: package stands cancelled.  Sub-output 3: Establishing two (2) area load dispatch centers: no change in scope.

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 4

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Table A1: Subproject Details

Name of the PIU Details covered as per IEE Remarks, reference Sl.No. List of Sub-projects (Annexure3)

Package-1: Construction of New 33/11kV Sub-Station for system strengthening, new 33kV & 11kV Lines, 33kV Terminal Equipment and 33kV& 11kV Railway/River Crossings New 2x5 MVA, 33/11 kV Substation (1) Substation (1 no.) One substation Kharguli Associated New 33 kV Lines (4 km) Terminal equipment (1) was identified or not Associated New 11 kV Lines (6 km) Associated New 33 kV Lines (4 km) identified it will be Guwahati Electrical Circle updated in IEE after i. New 33 kV line (8 km)1 Associated New 11 kV Lines (6 km) I final site selection. RS 33 kV bay terminal equipment (2) New 33 kV line (8 km) for associated lines of New 33 kV underground cable to replace existing Associated 11 kV (6 km) 33 and 11 kV is yet to overhead line and at railway track crossing (1) Railway track crossing (1) be undertaken. New 33 kV Lines (6+3.91 km=9.91 km) New 33 kV Lines (6+4=10 km) New 11 kV lines (3+4 km = 7 km)2 Guwahati Electrical Circle New 11 kV Lines (3+4=7 km) ii. 33 kV bay terminal equipment (1) II 33 kV bay terminal equipment (1) Railway crossing (1) Railway crossing (1) iii. New 33 kV lines Barpeta Electrical Circle New 33 kV Lines (20+30+18+7.5) =75.5 (16+30+15.19+7.12) = 68.31 km)3 km) 33 kV bay terminal equipment (6) 33 kV bay terminal equipment (6) Railway crossing (1 x 0.15 km) Railway crossing (1 x 0.15 km) River crossing (1 x 0.35 km) River crossing (1 x 0.35 km)

1 7.88 km was reported in Jul.-Dec.17 EMR as covered in bid document, actual length after RS is 8 km which is same as reported in IEE. 2 8.94 km was reported in Jul.-Dec.17 EMR as covered in bid document, actual length after RS is 7 km which is same as reported in IEE. 3 65.55 km was reported in Jul.-Dec.17 EMR as covered in bid document, actual length after RS is 68.31km. No change in alignment but line length is reduced when compared to IEE. 5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 5

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Name of the PIU Details covered as per IEE Remarks, reference Sl.No. List of Sub-projects (Annexure3) New 33 kV Lines (20+24 km = 44 km)4 New 33 kV Lines (20+24=44 km) Railway crossings 33 kV bay terminal equipment (4) 33 kV bay terminal equipment (4) increased by 2 x 0.15 iv. Railway crossing (4x 0.15 km) Sibsagar Electrical Circle Railway crossing (2 x 0.15 km) km River crossing (1) River crossing (1)

Package 2: R & M and Reconductoring of 33 kV, 11kV and LT lines; Rehabilitation of 33 kV bays, Replacement of Oil-Filled distribution transformers with Dry Type Distribution Transformers Lot I Restringing, repair and maintenance (R & M) and 33 kV lines R&M, re-conductoring After RS, change in line Re-conductoring of 33 kV (60+27.5+125+34+105.5+62.5+17=431.5 length (increase) (67.2+41.3+147.1+42.61+122.6+48.2+21.1= Guwahati I & II, km) Mangaldai, Rangiya, 33 kV: by 58.61 km 490.11km) 11 kV lines R&M, re-conductoring i. Barpeta, Bongaigaon, 11 kV: by 40.71 km 11kV (123.6+115.41+40+51.30+50.40 = Kokrajhar Electrical (100+100+40+50+50= 340 km) 380.71 km) Circles LT lines R&M, re-conductoring LT: by 80.52 km LT (219.45+191.37+100+101.50+100+118.2 = (200+150+100+100+100+100 = 750 km) 830.52 km) lines

4 45.15 km was reported in Jul.-Dec.17 EMR as covered in bid document, actual length after RS is 44 km which is same as reported in IEE.

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 6

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Name of the PIU Details covered as per IEE Remarks, reference Sl.No. List of Sub-projects (Annexure3) Replacement with DTR After final survey, one Guwahati I & II, Kokrajhar, (50+30+7+10+10= 107 units) (1) DTR dropped from Replacement of Oil-Filled transformers with Dry Rangiya, Barpeta, GEC II and a new one ii. Type Distribution Transformers Bongaigaon Electrical (1) added in (50+29+7+10+10+1 =107 units) Circles Bongaigaon EC.

Lot II After RS, no change Restringing, repair and maintenance (R & M) and Tezpur, , North 33 kV lines R&M, re-conductoring except for increase in Re-conductoring of Lakhimpur, Cachar, (66+53+78+19.5+55 = 271.5 km) 33 kV line length by 7.7 Badarpur, Morigaon 33 kV (70+54.3+80.4+19.5+55 =279.2 km) 11 kV lines R&M, re-conductoring i. Electrical Circles km. 11kV (60+60+50+50+50+50=320 km) (60+60+50+50+50+50= 320 km)

LT (100+30+50+50+100=330 km) lines LT lines R&M, re-conductoring (100+30+50+50+100 = 330 km)

Replacement of Oil-Filled transformers with Dry Tezpur, Nagaon, Cachar Replacement with DTR (15+3+10+5 = 33 No change ii. units) Type Distribution Transformers (33 units) Badarpur Electrical Circles Lot III After RS, increase in Restringing, repair and maintenance (R & M) and 33 kV lines R&M, re-conductoring Re-conductoring of , Golaghat, (75+22+85+70+1= 253 km) line length i. Sibsagar, , 33 kV (75+22+85+72+1=255 km) 11 kV lines R&M, re-conductoring 33 kV by 2 km Electrical Circles 11kV (100+100+60+60+60=380 km) (100+60+60+60+60= 340 km) 11 kV by 40 km

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 7

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Name of the PIU Details covered as per IEE Remarks, reference Sl.No. List of Sub-projects (Annexure3) LT (150+75+50+100+100 =475 km) lines LT lines R&M, re-conductoring The 33 kV Mariani- (150+75+50+100+100 = 475 km) Nakachari (15 km) line is under review.

Replacement of Oil-Filled transformers with Dry Jorhat, Golaghat, Replacement with DTDT After final survey, no ii. Type Distribution Transformers (20+10+4+10+20 Sibsagar, Dibrugarh, (20+10+4+10+20) = 64 units) change = 64 units) Tinsukia Electrical Circles Package 3: Replacement of existing overhead 33kV, 11kV and LT lines by underground cable along with optical fibre cable for communication 33kV, 11kV and LT underground cable network 33kV, 11kV and LT underground cable After RS, no change in (with optical fibre cable): 7.3 km in and around network (7.3 km) length. i. Capital complex. GEC I

33kV, 11kV and LT underground cable network 33kV, 11kV and LT underground cable After RS, no change in (with optical fibre cable): 6.8 km GS Road from network (6.8 km) length. ii. Paltan Bazar to Ganeshguri. GEC I

Package 4: Area Load Dispatch Centres and Independent Meter Testing Laboratory Construction of two Area Load Dispatch Centers GEC I and Jorhat GEC I (1 no.) and Jorhat EC (1 no.) After final survey, no i. at Guwahati and Jorhat Electrical Circle change

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 8

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Name of the PIU Details covered as per IEE Remarks, reference Sl.No. List of Sub-projects (Annexure3) Setting up of independent meter testing Meter testing laboratory(1) After final survey, no ii. laboratory(1) at Assam Engineering College, GEC II Jalukbari, Guwahati change Package 5:IT Module for Setting up of Centralized uniform revenue Billing System

Jorhat, Dibrugarh, Establishing IT module (1) for the This component has Tinsukia, Sibsagar, introduction of centralized uniform been removed from the Kanch, Tezpur, Nagaon, revenue billing system for all consumers scope of project. i. Package dropped Cachar, , Guwahati I, Rangiya, Kokrajhar, Mangaldai Electrical Circles.

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 9

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

B. IMPLEMENTATION STATUS B.1 Procurement Status Based on the discussions and information provided by the PMU, the package-wise procurement status is as follows.  Package 1: the Contract Agreement was signed with M/s NECCON Infra & Power Ltd. On 16 December 2016, and the mobilization advance received on 28 April 2017. Subsequently, NECCON initiated the work and the review of technical design and drawings is under progress. The identification of new sub-station site is under progress following the withdrawal of Kharguli site owing to technical reasons.  Package 2: Lot I contract was awarded to M/s Hemen Deka/JV M/s T&T Projects on 17 December 2016 but effective from 17 February 2017. For Lots II and III, M/s N.K. Power JV and M/s T&T Projects were successful bidders. Contract agreements were signed on 17 December 2016 with effect from 5 May 2017. The review of technical design and drawings are in progress for all the three Lots.  Package 3: M/s NECCON Infra & Power Ltd. Signed the contract on 16 December 2016, and the mobilization advance was received on 28 April 2017. The technical design and drawings are complete and under review.  Package 4: M/s NECCON JV, M/S Scope JV M/S Survalent Technology were recipients of this contract signed on 17 December 2016mobilization advance received on 28 April 2017.

 Package 5: ADB’s No Objection on draft bid document for Smart Meters was received on 30 March 2017. This package now stands cancelled.

B.2 Sub-Project Implementation Status

Sl.No. Name of Subprojects Progress as on date of Report

Package 1

 The construction of the sub-station has been Guwahati Electrical Circle I delayed owing to the ongoing search for New 2x5 MVA, 33/11 kV Substation (1 no.) suitable alternative site. Negotiations for finalization of land underway. Associated 33 kV lines for new substation (4 km)  Route survey (RS) for 33 kV and 11 kV lines Associated 11 kV lines for new substation (6 not initiated. km)

 For bay (1) associated with new substation, no work initiated. 33 kV bay terminal equipment (2)  Material supply in progress. Construction yet to begin. New 33 kV underground cable to replace  Permission from NF Railway Division pending. existing overhead line and at railway track Construction yet to begin. crossing (1)

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 10

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Sl.No. Name of Subprojects Progress as on date of Report  RS complete. Material supply in progress; pole New 33 kV Line (8 km) erection yet to start.  33 kV: RS complete, material supply in progress Guwahati Electrical Circle II and 15 poles erected in3.91 km section. New 33 kV Lines (9.91 km)  11 kV: RS complete, material supply in New 11 kV lines for feeder segregation (7 progress; construction yet to begin. km)  Permission from NF Railway Division pending. Railway crossing (1) Construction yet to begin.  Material supply in progress. Construction yet to 33 kV bay terminal equipment (1) begin.  33kV: RS complete, material supply and pole Barpeta Electrical Circle (469) erection complete. New 33 kV Lines (68.31 km)  Permission from NF Railway Division pending. Railway crossing (1) Construction yet to begin. River crossing (1)  Tower foundation complete; construction suspended owing to rains and flooding.  Material supply in progress and foundation complete (1 bay).  Material supply and foundation work in progress (3 bays). 33 kV bay terminal equipment (6)  Material supply in progress. Construction yet to begin (1 bay).  Foundation layout marking complete, material supply in progress (1 bay).  33 kV: RS complete, material supply and pole Sibsagar Electrical Circle (32) erection complete. New 33 kV Lines (44 km)  Railway crossing: Permission from NF Railway Railway crossing (4) Division pending. Construction yet to begin. River crossing (1)  River crossing: Tower foundation complete.  3 bays: material supply in progress. Construction yet to begin. 33 kV bay terminal equipment (4)  1 bay: revised layout drawing pending submission. Package 2, Lot- I  33 kV: RS complete. Material supply in progress. Construction to commence after monsoons except for completion of Rangiya Guwahati I & II, Mangaldai, Rangiya, EC: pole erection and stringing (7.35 km) Barpeta, Bongaigaon, Kokrajhar GEC II : pole erection in 2 km complete Electrical Circles GEC I: 6 km (Kahilipara GSS to Ulubari S/S) Restringing, repair and maintenance (R & M) removed from scope because of overlap of and re-conductoring of 33 kV (490.11 km), schemes. 11kV (380.7 km), LT lines (830.52 km)  11 kV: Material supply in progress. Pole (540) complete. Mangaldai EC: stringing complete for 4.54 km.

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 11

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Sl.No. Name of Subprojects Progress as on date of Report  LT: Material supply in progress. Pole erection in 465.36 km complete.

Replacement of Oil-Filled transformers with Dry Type Distribution Transformers (107  Design and drawing under review. Equipment units) not procured. Work yet to commence

Package 2, Lot II  33 kV: Except for Cachar and Badarpur EC, RS Tezpur, Nagaon, Morigaon, North complete. Material supply in progress. Pole Lakhimpur, Cachar, Badarpur Electrical erection (118) and stringing for 23.95 km Circles complete. Restringing, repair and maintenance (R & M)  11 kV: RS complete. Material supply in and Re-conductoring of 33 kV (279.2km), progress in two ECs. Pole erection (172) and 11kV (320 km), LT lines (330 km) stringing for 34.32 km complete.  LT: RS complete. Except for Cachar and Badarpur, material supply complete. Construction yet to begin. Morigaon EC: pole (24) erection and stringing (3.33km) complete.

Replacement of Oil-Filled transformers with  Design and drawing under review. Equipment Dry Type Distribution Transformers (33 not procured. Work yet to commence units)

Package 2, Lot III

Jorhat, Golaghat, Tinsukia, Sibsagar,  33 kV: RS complete. Material supply nearing Dibrugarh Electrical Circles completion. Construction to commence after Restringing, repair and maintenance (R & M) monsoons. and Re-conductoring of 33 kV (255 km),  11 kV: RS complete. Material supply in 11kV (380 km) LT lines (475 km) progress. Pole erection (13) in progress.  LT: RS complete. Material supply and construction yet to begin in Dibrugarh EC. Material supply in progress and construction yet to start in 4 EC.

Replacement of oil-Filled transformers with  Design and drawing under review. Equipment Dry Type Distribution Transformers (64 not procured. Work yet to commence units)

Package 3 Capital Electrical Circle Replacement of 33kV, 11kV and LT  Design and drawing review in progress. No overhead lines (7.3 + 6.8 km) with decision taken on method (trench or trench- underground cable network with Optical less) of laying cables. Work yet to commence. Fibre Cables (7.3 + 6.8 km).

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 12

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Sl.No. Name of Subprojects Progress as on date of Report

Package 4

Construction of two Area Load Dispatch  Design review completed, supply of material Centers at Guwahati and Jorhat nearing completion, and construction in progress. Setting up of independent meter testing laboratory at Assam Engineering College,  Material supply in progress. Jalukbari, Guwahati

Package 5

IT module for introduction of centralized uniform billing system for all consumers  This package stands cancelled and is no longer under APDCL – 12 lakh consumers under in the scope of Tranche 2. SMART Meter Package Note: Details of sub-projects is provided in Table A1 and Annex1A

C. DESIGN AND ENGINEERING STATUS

Follow up Item Status Required Type of Required Action (Y/N) For underground cable laying of 33kV, 11kV, LV and Fiber Optic (SCADA) Cables using trench cut method, under Package 3, APDCL had requested the Public Works Department (PWD), Assam Govt.'s approval and estimate for reinstatement of roads in Guwahati Detailed for open cut trenches. In response, engineering PWD's recommended the design of the Trenchless method for laying of all In Progress Yes cables. sub-project submitted by An exposure visit to a project in the Contractor. Bhubaneswar, Orissa revealed the unsuitability of trenchless method for the proposed 11kV and 33kV underground distribution cable laying. Discussions between APDCL and the contractor are in progress to resolve this issue. Hence, no work in this regard has been initiated till date. Changes in Changes in Yes. Package 1: site for substation is yet project package 1,2, 3 to be finalized. design/scope are being (Occurred or incorporated. Package 5 has Package 2: Change in line length to envisaged). been dropped. be effected and pending route surveys under Lot II may result in revision of line length.

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 13

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Follow up Item Status Required Type of Required Action (Y/N)

Package 3: The selection of method for laying the underground cabling is expected to get resolved in the coming months.

D. COMPLIANCE STATUS D.1 Compliance with National and State Statutory Environmental Requirement

S No Notification/Rule Requirements Compliance Status

1. The Environment All development project Power distribution projects are excluded Impact Assessment listed in Schedule 1 of EIA from the Schedule 1 list of EIA Notification, 2006, as notification require getting notification, 2006. amended prior Environmental Clearance. Package 1: Measurement of 2. The Water Water quality and impacts will be undertaken once (Prevention and discharge of sewage from the construction of the sub-station Control of Pollution) project or any other site commences. Site yet to be finalised. Act, 1974, with Rules establishment such as labour camp. For other components of package 1 and packages 2 and 4, no major impact is expected as local labour is employed, residing in the vicinity of the sub-project sites, involving daily commutes.

Package 3: Work yet to begin.

Package 1: The activities associated with 3. The Air (Prevention Compliance to National sub-station construction will lead to dust and Control of Ambient Air Quality generation. Monitoring to commence Pollution) Act, 1981, Standard once construction begins. For tower with Rules foundation and pole erection where civil work is involved the impact is minimal as dust generation is very localized.

Package 2: largely entails electrical work with no major civil work involved. Thus, low impact is observed. Package 3: Monitoring to commence with civil work. Package 4: Minimal impact Package 5: dropped, not applicable. The details of air quality monitoring not provided by the contractor.

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 14

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

S No Notification/Rule Requirements Compliance Status The Ozone Avoid equipment using 4. Monitoring will be carried out to check use Depleting VFCs/PCBs Substances of CFCs/PCBs in equipment, if any.

(Regulation and Handling) Rules, 2001 as amended .

5. The Batteries Bulk consumer is Given the scale of construction, (Management and responsible to (i) ensure generation of battery waste is not Handling) Rules, 2010 that used batteries are not envisaged. Compliance will be monitored disposed of in any manner if required. other than by depositing with the registered dealer/manufacturer/recycl er or at designated collection centers and (ii) file half yearly return in Form VIII to the SPCB.

6. Hazardous and other Used/burned transformer In accordance with requirements set in Waste (Management oils to be disposed off in the EMP, the disposal of hazardous and Transboundary accordance with the Rules. waste (Transformer oil) will be undertaken Movement) rules, when the replacement work begins. Disposal and 2016 Decontamination of empty containers contaminated with hazardous chemicals/waste in accordance to rules. (As per schedule 1) Package 1: No major impact is 7. Noise Pollution Compliance with Ambient anticipated. Monitoring to (Regulation & Control) Noise Standards in commence after the start of the Rules, 2000 accordance to land use of substation construction activities. Tower the area foundation construction is away from residential areas. Package 2: Negligible impact as minimal civil work is involved. Package 3: impact to be monitored with commencement of civil work. Package 4: Construction entails mostly manual procedures with intermittent machine use. Minimal impact observed.

Package 5: dropped Noise Level Monitoring details not provided by the contractor.

8. The Forest Clearance from MoEFCC/ Package 1: The yet to be finalized sub- (Conservation) Act, Forest Department if the station site will not require diversion of

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 15

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

S No Notification/Rule Requirements Compliance Status 1980 line passes through the forest land. Tree cutting permission will forest area. be obtained on case basis. Package 2- 4: Not applicable

D.2 Compliance with ADBs Environmental Safeguards (SPS, 2009)

ADB’s Sl.No Safeguard Compliance Requirement Status Requirements 1. Environmental Identify potential environmental EMP prepared for the project Assessment impacts outlines the envisaged impacts. on various resources and determine Construction activities likely to its result in various impacts will be significance in consultation with all monitored based on the EMP. stakeholders

2. Environmental The borrower will prepare an EMP Owing to changes in some outputs (line Planning and that length, alignment, etc.), the IEE will be Management address the potential impacts and updated. For civil and electrical works risks in progress, the contractors have identified in IEE. delayed submission of respective EMP compliance reports.

3. Information The borrower will submit to ADB, the The final IEE is disclosed on the ADB Disclosure final IEE and environmental website. PMU has uploaded all EMR to monitoring date on APDCL website. With changes report. in line length, alignment, etc. after the route surveys, the IIE is to be updated. 4. Consultation and The borrower will carry out Public consultation was carried out Participation consultation with affected persons during IEE preparation. and other stakeholders. The . consultation process and its results Field visits were undertaken and review are to be documented and reflected meetings held with PMU and PIU in environmental report. officials, as well as contractors, for compliance status (Annex 2A). 5 Grievance The borrower will establish a Except for Tezpur Electrical Circle, Redress mechanism to receive and facilitate Grievance Redress Committees Mechanism resolution of affected persons (GRCs) in respective Electrical Circles concerns, complaints and grievance not yet formed despite reminders from about the project’s environmental PMU (Annex 4). performance. 6 Monitoring and The borrower will prepare periodic Current EMR (Report 3) for Jan. to Reporting monitoring reports that describe June 2018 captures the progress of progress with implementation of EMP implementation of each sub- EMP and compliance issues and project. corrective actions. 7 Unanticipated The borrower will update the Completed route surveys reveal environmental environmental assessment and EMP changes in line length in variation with impacts where unanticipated environmental quantities provided in IEE. However, no . impacts become apparent

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 16

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

ADB’s Sl.No Safeguard Compliance Requirement Status Requirements major environmental impact is anticipated from such changes. Any obstructions Identified during the finalized survey reports will be assessed and EMP will be updated accordingly, if needed. 8 Biodiversity The borrower will assess major The sub-projects are not located inside conservation threat to the biodiversity. any Protected Areas (National Parks, and sustainable Wildlife Sanctuaries and Reserved

NRM Forests), hence, threat to and . degradation of critical habitat is not envisaged. 9 Pollution Pollution prevention and control The implementation of various Prevention and technologies consistent with preventive and mitigation measures Abatement international good practices such as listed in the EMP for pollution group. EHS guidelines of the World Bank abatement in the project will be monitored. 10 Occupational, The borrower will provide workers Personal protective equipment (PPE), Health and with safe and healthy working training, health checks, etc. have Safety environment, provide PPE to reportedly been provided by minimize risks, render training, contractors. However, non-compliance document the accidents, diseases & has been observed during monitoring in incidents, and provide emergency some cases such as health checks, and prevention and response reluctance of workers to comply with managements. use of PPE. 11 Physical Cultural The borrower to avoid significant No significant impact on CPR has been Resources damage to physical and cultural observed to date. (CPR) resources.

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 17

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

D.3 Compliance with Covenant

Item No. Covenants Status of Compliance

The Borrower shall ensure or cause EA to ensure that the preparation, design, construction, implementation, operation and decommissioning of the Project, and all Subprojects’ facilities comply with

(a) all applicable laws and regulations of the Borrower and the State relating to environment, health, and safety; Schedule The details of environmental safeguard implementation activities 5, para. 9 (b) the Environmental Safeguards; performed during this reporting period are provided in Annex 2A. (c) the EARF; and

(d) All measures and requirements set forth in the respective IEE and EMP, and any corrective or preventative actions set forth in a Safeguards Monitoring Report.

The Borrower shall ensure or cause EA to ensure that all necessary Schedule The budget for RP shall be through counterpart funding and that of budgetary and human resources to fully implement the EMP, the RP 5, para. 11 EMP has been included in the contracts of works. and the IPP as required, are made available.

The Borrower shall ensure or cause EA to ensure that all bidding The contract includes provisions of EMP as well as a budget for documents and contracts for Works contain provisions that require Environmental safeguard measures through counterpart share. contractors to: All necessary steps will be taken for any unanticipated risks or (a) comply with the measures and requirements relevant to the Impacts on environment, resettlement of indigenous people during Schedule contractor set forth in the IEE, the EMP, and the RP (to the extent they implementation of project activities, if applicable, as per provision in 5, para. 12 concern impacts on affected people during construction), and any EARF and RF. corrective or preventative actions set out in a Safeguards Monitoring Report; Contractors have reported compliance as stipulated, with the commencement of civil and electrical works. (b) make available a budget for all such environmental and social measures;

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 18

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Item No. Covenants Status of Compliance

(c) provide the Borrower with a written notice of any unanticipated environmental, resettlement or indigenous peoples risks or impacts that arise during construction, implementation or operation of the Project that were not considered in the IEE, the EMP, or the RP;

(d) adequately record the condition of roads, agricultural land and other infrastructure prior to starting to transport materials and construction; and

(e ) fully reinstate pathways, other local infrastructure, and agricultural land to at least their pre-project condition upon the completion of construction;

The Borrower shall ensure or cause EA to ensure the following:

(a) submit semi-annual Safeguards Monitoring Reports to ADB and The second bi-annual Environmental Safeguard Monitoring Report disclose relevant information from such reports to affected persons for the period July - December 2017 has been submitted to ADB. promptly upon submission; This report is third bi-annual Environmental Safeguard Monitoring Report for period January – June 2018. The IA (APDCL) has (b) if any unanticipated environmental and/or social risks and impacts Schedule disclosed monitoring report on its website for public sharing. arise during construction, implementation or operation of the Project 5, para. 13 that were not considered in the IEE, the EMP, or the RP, promptly There is delay in submission of reports on compliance by the inform ADB of the occurrence of such risks or impacts, with detailed contractors, who have been advised to honour the deadlines. description of the event and proposed corrective action plan; and Updating of IEE report is under process.

(c) Report any actual or potential breach of compliance with the measures and requirements set forth in the EMP or the RP promptly after becoming aware of the breach.

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 19

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Item No. Covenants Status of Compliance

The Borrower and EA shall ensure that Works contracts under the Project follow all applicable labour laws of the Borrower and the State Civil and electrical work is in progress under Packages 1 (except for and that these further include provisions to the effect that contractors; substation and associated line), 2 and 4 across electrical circles. (a) carry out HIV/AIDS awareness programs for labour and However, contractors' compliance to statutory requirements requires disseminate information at worksites on risks of sexually transmitted further action. Schedule diseases and HIV/AIDS as part of health and safety measures for Awareness programme for HIV/AIDS for workers is pending. 5, para. 15 those employed during construction; and Contractors were urged to expedite such action and submit reports to this effect. (b) Follow and implement all statutory provisions on labour (including not employing or using children as labour, equal pay for equal work), Contractors’ compliance to regulatory requirement and provision of health, safety, welfare, sanitation, and working conditions. Such sanitation facilities, hygienic and safe working conditions is being contracts shall also include clauses for termination in case of any monitored. breach of the stated provisions by the contractors.

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 20

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

D.4 Compliance with Environment Impact Management Plan Environmental Description of Potential Social Responsible Project Activity Component Likely Mitigation/Enhancement Measures Compliance status Impact Unit to be Affected

Pre-Construction Stage

1. New substation and new distribution lines for 33 kV and 11 kV  Fragmentation and/or loss of  Strict adherence to APDCL’s criteria Sub-station: The PMU, APDCL habitat for site and route selection, EARF, selection of sub-  Land and  Tree cutting and vegetation and relevant section from the FFA. station site is in vegetation clearing  All OH tension lines and progress. associated structures to follow the Monitoring will  Loss of agricultural land and commence once crops design practice for typhoon risk as covered by best engineering the site is finalized. Increase in dust and noise levels Likewise, the  Air and Noise practice. Vibration associated 11 and  Informal consultations to potentially- 33 kV line work is Flooding affected persons during preliminary pending. Sedimentation site/route survey on type and scale of subprojects, and benefits from New 33 kV and 11 Soil erosion  Location of  Water the entire project. kV lines: The completed route substation and  Degradation of existing water  Compliance to relevant provisions of surveys reveal no route selection of quality Forest Conservation Act 1980, potential impact on distribution lines Local drainage alteration Guidelines for Declaration of Eco- air, noise, water sensitive zones around national  Displacement of housing, and people. As parks and wildlife sanctuaries of other structures, and these lines are MOEF, and Guidelines for linear economic activities being aligned infrastructure intrusions in natural along existing 11  Concern/fear on the type areas by the National Board of kV lines, there is and scale of the Wildlife (NBW).  People subprojects no loss of land.  Reference to relevant provisions in The impact on  Interference to existing utilities the World Bank Environment, Health vegetation will be and Safety Guidelines (EHS) 2007, minimal but the and the International Finance extent of damage Corporation (IFC) EHS Guidelines to trees and crops for Electric Power Transmission and will be ascertained

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 21

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Environmental Description of Potential Social Responsible Project Activity Component Likely Mitigation/Enhancement Measures Compliance status Impact Unit to be Affected Distribution (2007). during stringing.  Inclusion of specific conditions to mitigate potential impacts in Tender Documents for New 33 kV and 11 kV lines.

 Choice of  People  Release of chemicals and toxic  Require suppliers or manufacturers Sub-station and equipment and gases that equipment specifications and/or associated lines: technology  Noise generation and vibration guaranteed emissions comply with The procurement of relevant standards of WB EHS equipment to be Guidelines 2007 and CPCB/ PCB, undertaken after Assam environmental standards finalisation of site. PMU,  Include specific conditions of APDCL compliance in Tender Documents New 33 kV and 11 kV lines: Equipment does not generate any toxic pollutants; and noise generation is intermittent and negligible only during offloading of material by trucks.

2. Rehabilitation and renovation of distribution systems  Replacement  Land and  Residual oil spill during  Strict adherence with plan for oil spill Drawing review is in PMU, of oil-filled vegetation dismantling and prevention and emergency response progress. The APDCL distribution transportation  Dismantled oil-filled DTRs to be monitoring will be transformer transported to designated Central  Increase in waste/scrap material undertaken after (DTR) with warehouses in Guwahati and commencement of dry- type DTR Jorhat/Divisional stores under each work. Electrical Circles Dismantled DTRs will be transported in

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 22

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Environmental Description of Potential Social Responsible Project Activity Component Likely Mitigation/Enhancement Measures Compliance status Impact Unit to be Affected closed containers to identified sites.

 Air and Noise  No impact on air quality  Dry-type DTR specifications that Contractors to audible sound levels should be  Generation of noise from ensure purchase of below ANSI/NEMA Standard ST-20 transformer equipment as per  Specific conditions to be specifications in included in Tender Document tender documents.  Water  No impact (location far from Not applicable water (bodies)  People  Lesser risk of fire hazard  Storage area will have Sites for storing impermeable flooring or dismantled oil-filled bunded area of 110% volume DTRs have been identified by respective electric circles.  Rehabilitation  Land and  Trimming/destruction of  All OH tension lines and associated The 33 kV Mariani - PMU, APDCL and vegetation vegetation in the RoW structures to follow the design Nakachari section under modernization  Air and Noise  Vehicular emissions practice for typhoon risk as covered Package 2, Lot III is under of existing 33 by best engineering practice review in anticipation of kV and 11 kV  Disturbance to irrigation  Water  Strict compliance to relevant CPCB/ disturbance at the HGWS. lines, and channels PCB, Assam environmental terminal bays  People  Interruptions in power supply standards and WB EHS Guidelines Route surveys highlight services 2007 minimal damage to land as the work entails existing No intrusion to HGWS – strict lines and bays. compliance to the relevant provisions of the Guidelines for linear The extent of damage to infrastructure intrusions in natural trees and crops will be areas by the NBW assessed during stringing  Specific conditions of Contractors to follow waste scrap/debris/waste management to management protocol as be included in Tender Documents advised by APDCL.  Adequate buffer between rehab

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 23

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Environmental Description of Potential Social Responsible Project Activity Component Likely Mitigation/Enhancement Measures Compliance status Impact Unit to be Affected works and irrigation channels, Contractors inform the local wherever possible APDCL in advance about  Compensation for crop / vegetation construction plans. damages (if any) There is provision in APDCL  Communications strategy plan in to give prior notice to the engaging project stakeholders (e.g., public about construction inform the public of power service activities. disturbances, hauling of replaced poles and lines, etc.)  Replacement of  Land and  Loss of some  Specify trenching activities be done Monitoring to follow once overhead high vegetation vegetation/ornamental plants in phased manner at 30 m-section work is initiated.

tension 33 kV intervals

and 11 kV lines with underground  Require Contractor(s) to PMU, APDCL cables incorporate dust suppression measures and road work enclosures  Water  Damage to water supply Monitoring to follow once PMU, APDCL pipelines that may affect water work is initiated. quality

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 24

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Environmental Description of Potential Social Responsible Project Activity Component Likely Mitigation/Enhancement Measures Compliance status Impact Unit to be Affected  People  Disturbance to high density area, Monitoring to follow once i.e., commercial work is initiated properties/business due to trenching and fill operations  Inconvenience to people due to traffic in commercial areas affected  Interference to existing utilities

Construction Stage Prepare People Avoid effects of EPC  A construction schedule (e.g., civil Contractors have reported EPC construction Land Contractor(s) unplanned works on substation and trenching submission of construction Contractor(s), management work activities activities, erection of poles, R&M schedules based on PMU, APDCL, plan activities, hours of construction) approval of route surveys for Smooth work implementation PIU, ESMU  Traffic management plan respective packages.  Community/pedestrian safety plan  Workers’ safety plan People  Social conflict due to potential  EPC Contractor(s) will be required to Local labour available Hiring of project EPC workers’ migration use local labour for manual work and (within 5 km) is being staff and workers Contractor(s),  Dispute over transparency eligible local workforce for clerical employed by contractors for PMU, APDCL, of hiring and office jobs various construction PIU, ESMU activities. Thus no long distance migration is involved. Labour gangs (3-4) of 10-12 workers each are recruited in respective sub- divisions. Weekly wages are paid through bank transfers.

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 25

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Environmental Description of Potential Social Responsible Project Activity Component Likely Mitigation/Enhancement Measures Compliance status Impact Unit to be Affected Orientation for  People  Awareness of workers on  Conduct briefing on EMP, records Contractors have been EPC contractor and the environmental management, monitoring, and briefed about environmental Contractor(s), workers requirements and their reporting compliance and measures PMU, responsibility  Identify critical areas to be monitored through discussions and APDCL, PIU,  Familiarity of wildlife- and the required mitigation measures review meeting attended by ESMU associated issues to minimize  Create awareness of sexually- PMU staff and consultant. conflict transmitted diseases such as Orientation of workers on  Awareness of EPC HIV/AIDs Staff of NBW health issues has been Contractor(s) of their  Create awareness of potential man- and/or delayed by the contractors. responsibility in wildlife conflict along the existing 33 representative implementing the EMP kV line from Mariani-Nakachari The Mariani-Nakachari from Village (about 3 km runs parallel to the section is under review, Protection entrance of HGWS; existing line and thus awareness generation Committee of entrance to sanctuary separated by on man-animal conflict will Mariani, Dhodar Ali Road) follow. Dihingia Para Grant, and/or Chintali Gaon as resource persons on man-wildlife concerns. Site preparation, Land and vegetation  Clearing of vegetation along the  Landscaping/replanting of trees of Land for substation not yet land and vegetation ROW and substation site native species will be done at the finalized; associated 33 kV clearing  Disturbance/alteration of Kharghuli substation site after and 11kV line work yet to  Kharghuli habitat along the RoW and completion of construction works start. Monitoring of impacts

Substation destruction of habitat in substation  No trees clearing in Kharghuli site; and remedial measures will  Poles/towers  Breaking of paved/asphalt minimal vegetation clearing along the be undertaken with the for 33 kV and 11 RoW commencement of roadside due to trenching kV distribution required for UG cabling  EPC contractor will provide a construction. lines  Soil erosion and surface runoff diagram of the site to ensure EPC  Laying and  Increase in waste compliance to the provisions of the UG cabling work not Contractor(s), alignment of UG generation EMP. The diagram will specify where initiated. PMU, cabling the stockpiles are stored and APDCL, PIU, handled, and spoils disposed. It will ESMU lay out boundaries, especially in terms of the site / facility’s proximity 5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 26

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Environmental Description of Potential Social Responsible Project Activity Component Likely Mitigation/Enhancement Measures Compliance status Impact Unit to be Affected and/or distance from the .  Controlled backfilling at the Kharghuli substation and erosion- control measures(e.g., preserve topsoil and reinstate after construction completed) will be installed  Debris from trenching will be hauled to designated dumping area and/or landfill sites  Excavated soil for the poles/towers and UG cabling will be reused  Water  Localized flooding at Kharghuli  Earth-moving works/excavation will Excavation and tower substation, river crossing for be scheduled during the dry season foundation complete for river new 33 kV line Barnagar GSS  Install erosion-control measures crossings before the onset to Howly line (20 km); River such as silt traps, as needed of monsoons (March 2018). Beki crossing by B+6 tension  Spoils from Kharghuli substation will Further construction type tower be stored away from the edge of suspended owing to floods.  Oil spillage due to construction Brahmaputra River equipment  The EPC Contractor(s) will strictly Sub-station work yet to adhere to the plan for oil spill begin. prevention and emergency response of APDCL  Air and Noise  Increase in vehicular  Provide temporary enclosures to Monitoring of impacts and emissions areas generating noise and dust remedial measures will be  Increase in dust and noise  Monitor smoke-belching vehicles undertaken with the levels  Require vehicles to observe low- commencement of speed to minimize noise, no construction of substation. blowing of horns River crossing tower construction sites are away from habitation with low air and noise pollution. .

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 27

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Environmental Description of Potential Social Responsible Project Activity Component Likely Mitigation/Enhancement Measures Compliance status Impact Unit to be Affected  People  Inconvenience in commercial  Compensation for temporary Sub-station and associated areas in Guwahati affected by damages to crops/plants along the distribution lines: remedial trenching RoW measures will be undertaken  Disturbance to usual traffic flow  Schedule site preparation activities with the commencement of  Loss of crops and disturbance to along RoW to avoid farming and construction. agricultural activities harvesting seasons, whenever possible  Inform the public of work schedule of site preparation Construction and  Land and  Loss of habitat/vegetation  Compensation for temporary Construction of substation civil works at vegetation clearing for new 33 kV and 11 kV damages to crops/plants along the site and associated 33 and Kharghuli lines ROW 11 kV lines yet to APDCL, PMU, substation, erection  Temporary disturbance/trimming  Schedule construction works along commence. PIU, ESMU of and stringing of of vegetation in the ROW of ROW (new 33 kV and 11 kV lines) conductors of new existing 33 kV and 11 kV lines to avoid farming and harvesting New 33 and 11kV line: the 33 kV and 11 kV  Increase in waste/scrap material seasons, whenever possible alignment in most sections is lines, replacement  Breaking of paved/asphalt  No tree cutting in Kharghuli along existing distribution of overhead 11 kV roadside due to trenching substation and only lopping of trees lines. Thus impact on with UG cabling,  Disturbance to wildlife at along ROW of distribution lines to vegetation is low. Final and re- conductoring HGWS – about 3 km of existing keep the 3m clearance assessment of vegetation of existing 33 kV 33 kV line from Mariani to  Road repair/re-pavement after damage is will be and 11 kV lines Nakachari parallel to the completion of trenching activities undertaken during stringing. entrance of the reserve  Construction debris/waste will be disposed in designated dumpsites Pole erection and limited and/or landfill stringing is in progress  Provide garbage bins at strategic under new lines and re- locations conductoring of existing  Rehabilitation/re-conductoring works lines. Excavated soil has and schedule of 33kV line parallel to been reused. Scrap material HGWS will be coordinated with the generated is being disposed DFO and Village Protection of at sites identified by Committee Dihingia Para Grant, and APDCL concurrently with ChintaliGaon construction, by the contractors.  Designate staff to monitor traffic along Dhodar Ali Road parallel to Pole erection was

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 28

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Environmental Description of Potential Social Responsible Project Activity Component Likely Mitigation/Enhancement Measures Compliance status Impact Unit to be Affected HGWS and to restrict access of undertaken in dry months. workers to HGWS during Work suspended in some rehabilitation works along the 33 kV sub-divisions because of Mariani-Nakachari distribution line rains (annex 1A). Compensation for vegetation damage will finalised during stringing.  Air and Noise  Increasing dust from earth-  Select low-noise portable trencher Construction work yet to moving works for trenching commence for substation  Increase in vehicular  Observe low speed by construction and associated lines. emissions from construction vehicles to reduce noise and no vehicles and transport of blowing of horns materials  Implement traffic management plan  Increase in noise levels from  Require EPC Contractor(s) to construction vehicles, equipment maintain and tune up construction and trencher vehicles and heavy equipment regularly to reduce emissions  Provide construction vehicles with tire-washing area to reduce dust  Transport of dust-generating materials will be covered  Provide temporary enclosures to dust and noise-generating construction works  Open land area in Kharguli substation and along the 33 kV and 11 kV lines will be sprayed with water, as needed  Provide warehouse of materials onsite at Kharguli substation to reduce trips of material delivery  Water  Generation of sewage at Kharguli  Significant ground disturbance will Work yet to commence site be done during the dry season under substation.  Localized flooding at Kharguli,  Provide sanitary facilities and safe Work under river crossings 5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 29

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Environmental Description of Potential Social Responsible Project Activity Component Likely Mitigation/Enhancement Measures Compliance status Impact Unit to be Affected along the RoW of new 33 kV and drinking water to workers suspended after March 2018 11 kV lines, and trenching  Enforce good housekeeping at all because of floods.  Increase in turbidity in times in construction sites Brahmaputra River, Beki River,  Implement drainage and storm and other perennial surface water management waters along the 33 kV and 11 kV  Adequate buffer between the lines surface water bodies and earth- moving works will be imposed  Substation transformer installed on an impermeable floor.  People  Exposure to health and safety  Use of proper safety Substation and underground risks to workers and the public clothes/equipment for workers cabling work yet to  Interference to existing roads  Provide first aid kits and fire commence. (e.g., Dhodar Ali) and railway extinguishers at all sites with crossings construction works (i.e. Kharguli, New 33 and 11 kV lines:  Disturbance to high density area along new 33 kV and 11 kV lines, stringing yet to commence. (mainly commercial businesses) and UG cabling in Guwahati City due to trenching  Provide appropriate grounding and Refurbishment and re-  Inconvenience due to traffic ensure deactivation of live power conductoring of existing lines for existing 33 kV and11 kV re- lines: (i) workers provided conductoring with safety equipment and  Conduct health and fitness for clothing but reluctant to wear workers once every two months gear constantly during work;  Inform the public of construction (ii) delay in health and work schedules in a timely manner fitness check-up; (iii)  Construction management work warning signs near plan to be strictly implemented construction posted and  Scaffoldings will be placed over road pedestrian road crossings points provided;(v) public informed of upcoming construction  Danger and clearly visible warning activities through public signs will be posted at designated address system operated by sites APDCL ECs.  Designate staff to direct pedestrians

crossing and flow of construction

vehicles 5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 30

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Environmental Description of Potential Social Responsible Project Activity Component Likely Mitigation/Enhancement Measures Compliance status Impact Unit to be Affected  Pedestrian road crossings will be provided  Perform exercises among workers every day before start of work  Strictly impose construction vehicles to follow road traffic regulations Replacement of oil-  Land and  Oil spill during dismantling and  Inform affected areas timely of Work yet to commence. filled DTR with dry vegetation transportation power outages schedule, if any APDCL, PMU, type DTR  Increase in scrap/waste material  Dismantling process will follow PIU, ESMU  Oil spill during transportation manufacturers’ specifications  Water  Strict adherence with the plan for oil  People  Interruptions to power supply spill prevention and emergency services response  Dismantled DTR to be transported and stored in designated Central warehouses in Guwahati and Jorhat/Divisional Stores under each Electrical Circle  Storage area of dismantled DTRs will have impermeable floor on a bunded area of 110% volume

Operation and Maintenance Stage Use of mineral oil for  Land  Accidental spillage that would  Substation transformer installed in a Not applicable transformers (sub-  Water contaminate land and water bunded area of 110% volume APDCL, PMU, station)  Fuel and lubricants stored in drums PIU, ESMU or tanks will be placed on impermeable surface  People  Occupational health risks to  Acceptance of mineral oil should be workers due to exposure accompanied with Material Data  Fire hazards Safety Sheets and/or be certified that it is PCB-free  Fire extinguishers readily available in storage areas for mineral oil.

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 31

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Environmental Description of Potential Social Responsible Project Activity Component Likely Mitigation/Enhancement Measures Compliance status Impact Unit to be Affected Maintenance of  People  Hazards such as electrocution,  Signage meeting the IEEE Not applicable substation and lightning strike, etc. due to standards will be placed on all APDCL, PMU, distribution lines accidental failure of distribution overhead lines warning of electrical PIU, ESMU lines hazards  Provide security and inspection personnel to avoid pilferage and vandalism of equipment and lines  Appropriate grounding and deactivation of live power lines during maintenance work  Substations designed with protection system that shuts off during power overload or similar emergencies  Maintain and comply with electrical standards  33 kV and 11 kV distribution lines entering and leaving the Kharguli substation, and 11 kV UG cables are insulated (or covered) to minimize hazards  Conduct information briefing to affected stakeholders/dwellings within and around the project activity area to enhance awareness on safety practices of living near the Kharguli substation and the 33 kV and 11 kV distribution lines at the time of pre-commissioning.  Safety-related risks  Kharguli substation will be provided Not applicable. with modern fire control APDCL, PMU, systems/firewall PIU, ESMU  Property boundary of the Kharguli substation will be fenced for safety and will be provided with security

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 32

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Environmental Description of Potential Social Responsible Project Activity Component Likely Mitigation/Enhancement Measures Compliance status Impact Unit to be Affected personnel to regulate entry and exit  Kharguli substation will be designed to comply with fire prevention and control codes  Route setback of 33 kV and 11 kV overhead distribution lines from dwellings will be in accordance with permitted level of power frequency  Accident working in elevated  Provide safety belts and personal Not applicable heights protection gears/equipment  Conduct orientation/training on safety  Prepare and implement workers’ safety plan consistent with Indian Factories Act 1948 and WB EHS Guideline 2007  Potential exposure to electric  EMF levels expected to be way Not applicable and magnetic fields (EMF) below the limits set by International Commission on Non-Ionizing Radiation Protection (ICNRP) which is 4.17 kV/m for electric field and 833 mG for magnetic field  Sub-stations will be fenced and security staff assigned to prevent unauthorized public access  Conduct information briefing to affected stakeholders/dwellings within and around the project activity area to enhance awareness on safety practices  Land and  Danger to wildlife that may  Periodic maintenance of maximum Not applicable vegetation cross south of Dhodar Ali Road sag condition (ground vertical APDCL, PMU, from HGWS along the 33 kV clearance) to ensure compliance to PIU, ESMU Mariani- Nakachari line from Guidelines of NBW (about 3 km parallel to entrance  Maintenance of spikes from 1.21 5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 33

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Environmental Description of Potential Social Responsible Project Activity Component Likely Mitigation/Enhancement Measures Compliance status Impact Unit to be Affected of HGWS) m-2.1 m at the poles to ward off animals  Coordinate with assigned Divisional Forest Officer, NBW and the Village Protection Committee at Mariani, Dihingia Para Grant, and Chintali Gaon on efforts/programs to deter wildlife crossings  Air  Fugitive emissions of SF6  Fugitive emissions will be monitored Not applicable following protocols consistent with APDCL, PMU, IEEE and IEC PIU, ESMU  Conduct annual inventory of supply and usage  Conduct measurement using hand held devices  EPC contractor will follow guidelines for proper handling of SF6 at the substation site to avoid any untoward incidents.  Noise  Disturbance to settlements near  Periodic maintenance of equipment Not applicable the Kharguli substation such as transformers and capacitors APDCL, PMU, to minimize noise generation PIU, ESMU  Provide enclosure of noise- generating equipment  Monitor ambient noise levels to meet noise regulations standards

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 34

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

D 5 Compliance with Environmental Monitoring Plan The ADB approved monitoring plan and its status is as follows.

Project Parameter / Method of Responsible Compliance Stage Location Measurement Frequency Unit status Indicator Pre- Noise level of Substation site Machinery and Once APDCL PMU, Monitoring to Construction equipment and UG cabling / equipment PIU, ESMU start after machineries Trenching specifications commencement Site where Compliance to of work. DTR will be ambient noise dismantled levels and replaced

Soil quality Substation site Ocular inspection Once APDCL PMU, Substation: B+ Tension PIU, ESMU monitoring yet towers at River to start. Beki crossing River crossing foundation: soil quality test undertaken.

Loss of Substation site Ocular Once To be terrestrial Erection of inspection, undertaken habitat; Tree poles; transect survey after handing felling; Stringing of over of land Clearing of conductors: for substation. vegetation RoW of new 33 kV and 11 APDCL PMU, To be kV lines) PIU, ESMU conducted RoW of during existing stringing of 33kV, 11kV new and and LT lines existing lines. for proposed R&M) Water quality Substation site Water quality Once To be testing for pollution before undertaken constructi- after handing on, once over of land during for substation. constructio APDCL PMU, n and once PIU, ESMU after constructio n

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 35

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Project Parameter / Method of Responsible Compliance Stage Location Measurement Frequency Unit status Indicator Proximity to Substation Ocular Once APDCL PMU, Substation site water resources site inspection PIU, ESMU yet to be (boundary to Maps finalised. be at a distance of Tension tower 10m) footings Location of impacted only proposed B+ during floods. Tension towers footing Route survey (river Beki maps finalised crossing); no for pole footing in erection. water Erection of poles: (RoW of new 33 kV and Wildlife crossing Along RoW of Ocular survey/ Quarterly APDCL PMU, The existing 33 kV observation, to PIU, ESMU alignment of lines at Secondary data capture this line under Nakachari to seasonal review for Mariani near variations changes. Hoollongapar Gibbon Sanctuary

Loss of RoW of new Ocular Once Extent of loss agricultural 33 kV and inspection, to be land/crops, 11 kV lines transect assessed tea RoW of survey APDCL PMU, during plantations existing PIU, ESMU stringing, not 33kV, 11kV complete. and LT lines for R&M Setback Substation site Ocular Once To be distances to RoW of new inspection, undertaken nearest 33 kV and transect after sub- dwellings / 11 kV lines survey station and commercial Laying of UG UG cabling businesses / cabling APDCL PMU, sites drainage lines PIU, ESMU finalization. New 11 and 33 kV line RoW: complete. Hiring / Local Substation site Log of Number of Monthly Substation and Construction recruitment of Erection of local workers and DTR: work not workers and staff poles; Stringing staff recruited initiated. of conductors Pole erection DTR EPC and stringing: dismantling contractors, local labour and APDCL PMU, recruited from replacemen PIU, ESMU radius of 5 km t of construction sites.

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 36

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Project Parameter / Method of Responsible Compliance Stage Location Measurement Frequency Unit status Indicator Orientation of Substation site Log of number Once EPC To be Contractor(s) and Erection of of participants before contractors, undertaken. hired workers on poles; Stringing constructio APDCL PMU, issues like of conductors n, and as PIU, ESMU HIV/AIDS DTR needed dismantling and replacemen t Orientation of Substation site Log of Number Once Orientation of EPC Contractor(s) Erection of of participants before contractors, contractors at and hired poles; construct APDCL PMU, individual workers on Stringing of -ion and PIU, ESMU level Compliance to conductors once undertaken. Environmental (new and during Management existing power construct Plan (EMP) etc. lines) -ion, as DTR needed dismantling and replacemen t Sprinkling/ Substation site Ocular inspection / Once a day To be

spraying water Trenching spot checks at undertaken on open land activities for Substation after sub- areas, and laying of UG site during station and before cabling dry season UG cabling movement of Road Weekly at sites construction easements road finalization. vehicles for dust affected by easements suppression delivery of (or as EPC Complied with equipment needed) contractors, by contractors and Once a APDCL PMU, for other sub- construction day PIU, ESMU projects. material during Erection of trenchin poles; g for Stringing of laying of conductors UG (new and cabling existing power lines) Solid / Sub-station Ocular Every week To be undertaken. Liquid site workers’ inspection/ spot waste camps checks management Erection of poles; EPC Stringing of contractors, conductors APDCL PMU, (new and PIU, ESMU existing power lines) Trenching site for laying of UG

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 37

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Project Parameter / Method of Responsible Compliance Stage Location Measurement Frequency Unit status Indicator Danger and Sub-station site Ocular Once a PMU, To be

warning signs for Road affected inspection/ spot month for ESMU, undertaken safety of workers by delivery of checks substation APDCL, as work yet and the public equipment and site and EPC to begin. construction road contractor material easements Trenching affected by site for laying delivery of of UG equipment cabling and Erection of construction poles; Stringing material of conductors Bi-weekly DTR dismantling for and trenching replacement site for easements laying of UG cabling Once at the time of dismantling of DTR

Announcement to Substation site Work As needed PMU, Complied with

the public of Trenching schedule log sheet One ESMU, for pole proposed works site for laying month APDCL, erection and schedule UG cabling prior to EPC stringing. Other Along the road commenc contractor components easement ement of yet to begin. affected by trenching interconnectio operations ns of 24 hours distribution prior for lines any Erection of scheduled poles; Stringing power of conductors outage

Oil spill control Substation site Ocular inspection Once a PMU, To be

Site of DTR month for ESMU, undertaken as dismantling Substation APDCL, work yet to and site and EPC begin. replacemen once at contractor t the time of DTR dismantlin g

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 38

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Project Parameter / Method of Responsible Compliance Stage Location Measurement Frequency Unit status Indicator Erosion Substation site Ocular inspection Once a PMU, To be

control Erection month ESMU, undertaken measures of poles APDCL, such as silt EPC traps contract or Flood prevention Substation site Ocular inspection Once PMU, To be

measures Location of ESMU, undertaken B+ Tension APDCL, tower at River EPMU,PC

ESMU, APDCL, Smoke belching Substation site Ocular Weekly EPC To be undertaken contracto r

Construction inspection / spot Once at the PMU, To be Erection of vehicles poles; checking time of DTR ESMU, undertaken Stringing of dismantling APDCL, conductors EPC (new and contractor existing power lines) Site where DTR will be dismantled and replaced Noise and Substation Measurement of Quarterly PMU, To be

dust level site; periodic noise level at the Once a ESMU, undertaken maintenance substation site week for APDCL, of equipment during trenching EPC such as construction and and twice contract transformers after a month or and commissioning of for the capacitors to substation rest minimize Ocular noise inspection/spot generation checks Along the road easement affected by inter- connection of distribution lines

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 39

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Project Parameter / Method of Responsible Compliance Stage Location Measurement Frequency Unit status Indicator OPERATI Failure of Along Maintenance log Monthly PMU, To be undertaken ON distribution lines the sheet ESMU, (including UG RoW/ APDCL cabling) alignmen Substation t transformer Substation site Site where DTR is replaced Noise Substation Noise meter Quarterly PMU, To be undertaken ESMU, APDCL SF6 fugitive 33 kV bay with Inventory of in/out Yearly / PMU, To be undertaken emissions terminal Measurement by Quarterly ESMU, equipment hand held devices APDCL utilizing SF6 circuit breaker Substation site

Occupational Substation site Number of Semi- PMU, To be undertaken health, and Along the accidents and/or annually ESMU, safety alignment of injuries APDCL power lines

Road re- Trenching Ocular inspection Monthly PMU, To be undertaken pavement site for laying ESMU, UG cabling APDCL

Tree planting, Substation site Ocular inspection Quarterly PMU, To be undertaken maintenance of ESMU, green landscape APDCL Housekeeping Substation site Spot checks Monthly PMU, To be undertaken

ESMU, APDCL Collection of Substation site O & M log Monthly PMU, To be undertaken waste (i.e., sheet ESMU, oil, garbage, APDCL etc.)

Along RoW of Spot checks/ Monthly PMU, To be undertaken new 33 kV observation ESMU, and 11 kV APDCL lines Along RoW of existing 33kV, 11kV and LT lines for R&M

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 40

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Project Parameter / Method of Responsible Compliance Stage Location Measurement Frequency Unit status Indicator Pilferage Along RoW of Ocular inspection Quarterly PMU, To be undertaken of cables new 33 kV O&M log sheet ESMU, and 11 kV (security APDCL lines operations) Along ROW of existing 33kV, 11kV and LT lines for R&M

ANY OTHER ENVIRONMENTAL ASPECT NOT COVERED IN INITIAL ENVIRONMENTAL EXAMINATION Not applicable at this stage

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 41

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

E. INSTITUTIONAL MECHANISM

Sl. Parameters Compliance Status No.

To oversee responsibilities for monitoring all sub-projects in areas such as environmental, R&R and social safeguards, the PMU has designated One Assistant Manager in charge of ESMU. The duties of the ESMU include at a minimum (i) oversee field offices and construction contractors for monitoring and implementation of Numbers of Staff deputed/ mitigation measures, (ii)Liaise with the field officers and 1 employed for environment contractors and seek their help to solve environmental related safeguards issues of subproject implementation and (iii) preparation of environmental monitoring reports every six months (as required by ADB). ESMU will coordinate with PIU for monitoring as well as designing appropriate mitigation measures to address environmental and social concerns. A new Assistant Manager has taken charge since January 2018 (Annexure 5).

PMU/PIU established as per The ESMU has been reconstituted vide Office Order No. 2 proposed institutional mechanism APDCL/PMU/APSEIP/ESMU/2015-16/249/Dated19-March-2016.

The Grievance Redressal Committees (GRCs) are yet to be 3 GRC formation formed except for Tezpur EC (Annexure 6).

Consultant was recruited in February 2017 for 8 man-months for 4. Environmental Safeguard Specialist monitoring of environmental and social safeguards.

F. GRIEVANCE REDRESS AND THEIR RESOULTION

Sl. Complainant Name and Date of Subject/ Remarks No Address receipt Issue No Complaint received till I None None GRC formation pending date.

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 42

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Output 1: Expansion and upgradation of the distribution system Annexure-1A

Sub-output Electrical Package Location Quantity/proposed Quantity/length Quantity/length Compliance Execution Circle no.; Lot length as per IEE as per as per Route status (IEE no. Bid/contract survey and RS)

Package I

1 Construction GEC I Package Kharguli, Substation (1 no.) Substation (1 Route survey No None: substation site of one new 33 1 Guwahati no.) not yet yet to be finalized; Terminal kV/11kV conducted. negotiations 33KV bay with equipment. (1 no.) Terminal substation, underway; no terminal equipment. (1 install the 33 kV lines (4 km) construction equipment, Uzan no.) associated Bazar substation undertaken yet. 11 kV (6 km) terminal 33 kV lines (4 Uzan Bazar equipment, km) Substation to and New 33/11 kV 11 kV (6 km) associated 33 Kharguli kV lines (4 km) Substation and 11 kV (6 km)

Construction 2 GEC I Package Kamakhaya GSS 8 km 7.88 km 8 km Yes Route survey of 137.5 km of 1 to Fancy Bazaar complete. Material new 33 kV supply in progress; lines pole erection yet to start.

GEC II Package Kamakhaya 4 km 3.91 km 3.91 km No, increase Route survey 1 GSS to Maligaon in line length complete, supply in Rly 33/11kV SS progress and 15 poles (to link existing erected. 33kV line of

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 43

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Sub-output Electrical Package Location Quantity/proposed Quantity/length Quantity/length Compliance Execution Circle no.; Lot length as per IEE as per as per Route status (IEE no. Bid/contract survey and RS)

33/11 kV by 0.09 km Jalukbari S/S)

Package Saraighat Bridge 6 km 6 km 6 km Yes Route survey GEC II 1 to link between complete. Material Jalukbari to supply in progress; Amingaon pole erection yet to start. Package Baranagar GSS 20 km 16 km 16 km Route survey Barapeta EC No, there is a 1 to Howly with complete, supply in reduction in connectivity to progress and 295 the length by existing 33kV poles erected. 4 km. Pathsala feeder at Howly

Package Sarihtoli GSS to 30 km 27.24 km 30 km Route survey Barapeta EC Yes 1 Nathkuchi S/S complete, supply in progress and 140 poles erected.

Package Pathsala SS to 18 km 15.19 km 15.19 km Route survey Barapeta EC No, there is a 1 SS complete, supply in reduction in the progress and 9 poles length by 3.19 erected. km. Package Barjhar(Barama) 7.5 km 7.12 km 7.12 km Route survey Barapeta EC No, there is a 1 to Katahbari complete, supply in reduction in the progress and 25 poles 5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 44

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Sub-output Electrical Package Location Quantity/proposed Quantity/length Quantity/length Compliance Execution Circle no.; Lot length as per IEE as per as per Route status (IEE no. Bid/contract survey and RS) length by 0.38 erected. km. Package Khowang S/S to 20 km 20 km 20 km Yes, no change Route survey I Behiating GSS EC complete, supply in progress and 22 poles erected.

Package Demow S/S to 24 km 25.15 km 24 km Sivasagar Yes, no change Route survey I Moran S/S EC complete, supply in progress and 10 poles erected.

TOTAL LENGTH 137.5 km 128.49 km 130.22 km No, decrease in total line length by 7.28 km Package Paltan Bazar 1no. (0.25 km) 1no. (0.25 km) 1no. (0.25 km) 3 Construction of GEC I Yes, no change Permission from 1 Railway Station, 33 kV railway Railways Dept. line and river [Chunagudam to awaited. Construction crossing DP structure yet to begin. near transit camp, Guwahati Club]

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 45

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Sub-output Electrical Package Location Quantity/proposed Quantity/length Quantity/length Compliance Execution Circle no.; Lot length as per IEE as per as per Route status (IEE no. Bid/contract survey and RS) Package Kamakhaya 1 no. (0.15 km) 1 no. (0.15 km) 1 no.(0.15 km) GEC II Yes, no change Permission from 1 GSS to Maligaon Railways Dept. Railways/S awaited. Construction yet to begin.

Package Sarihtoli GSS to 1 no. (0.15 km) 1 no. (0.15 km) 1 no. (0.15 km) Barapeta Yes, no change Permission from I Nathkuchi S/S Electrical Railways Dept. Circle awaited. Construction yet to begin. Package Behiating GSS 1 no. (0.15 km) Sivasagar 2 no. (0.15x 2 = 2 no. (0.15x 2 = No, increase Permission from I to Khowang S/S EC 0.3 km) 0.3 km) in number of Railways Dept. crossing awaited. Construction yet to begin.

Package Demow S/S to Sivasagar 1 no. (0.15 km) 2 no. (0.15x 2 = 2 no. (0.15x 2 = No, increase Permission from I MoranS/S EC 0.3 km) 0.3 km) in number of Railways Dept. crossing awaited. Construction yet to begin.

7 nos. 7 nos. No, change in TOTAL LENGTH 5 nos. (0.85 km) (1.15 km) (1.15 km) the total quantity.

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 46

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Sub-output Electrical Package Location Quantity/proposed Quantity/length Quantity/length Compliance Execution Circle no.; Lot length as per IEE as per as per Route status (IEE no. Bid/contract survey and RS) Package Beki River Barapeta EC 0.35 km 0.35 km 0.35 km Yes, no Tower foundation I crossing for change complete; erection Baranagar- work suspended Howly Line owing to rains and flooding.

Buri Dihing River Sibsagar 0.35 km 0.35 km 0.35 km Tower foundation crossing for EC complete. Behiating- Yes, no Khowang Line change

Yes, no TOTAL LENGTH 0.70 km 0.70 km 0.70 km change in the total quantity Package Fancy Bazar S/S 1 1 No, one (1) new 4 Construction GEC I 0 Material supply in I of eleven (11) progress. new 33 kV Construction yet to bays at begin. existing 33kV/11kV substations Package Jalukbari S/S 1 1 GEC II 1 Yes, no Material supply in I change progress. Construction yet to begin. Package Barnagar GSS Barpeta 1 1 1 Yes, no Material supply in I Electrical progress. Foundation

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 47

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Sub-output Electrical Package Location Quantity/proposed Quantity/length Quantity/length Compliance Execution Circle no.; Lot length as per IEE as per as per Route status (IEE no. Bid/contract survey and RS)

Circle change work in progress.

Sarihtoli GSS 1 1 1 Yes, no change Material supply in progress. Foundation layout marking complete. Nathkuchi S/S 1 1 1 Yes, no change Material supply in progress. Foundation work in progress. Barjhar (Barama) 1 1 1 Yes, no change Material supply in progress. Foundation complete. Pathshala S/S 1 1 1 Yes, no change Material supply in progress. Foundation work in progress. Sarupeta S/S 1 1 1 Yes, no change Material supply in progress. Construction yet to begin. Package Behiating GSS 1 1 Sivasagar 1 Yes, no change Revised layout I EC drawing yet to be submitted. Construction not started.

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 48

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Sub-output Electrical Package Location Quantity/proposed Quantity/length Quantity/length Compliance Execution Circle no.; Lot length as per IEE as per as per Route status (IEE no. Bid/contract survey and RS) Khowang S/S 1 1 1 Yes, no change Material supply in progress. Construction yet to begin. Demow S/S 1 1 1 Yes, no change Material supply in progress. Construction yet to begin.

Moran S/S 1 1 1 Yes, no change Material supply in progress. Construction yet to begin.

TOTAL 11 12 12 No, increase in quantity Package Sualkuchi S/S to 5 Construction GEC II 3 km 3 km 3 km Yes, no change Material supply in I Sualkuchi Town of 7 km of 11 progress. kV lines for the Construction yet to segregation of begin. the rural and agricultural feeders

Package Boko S/S to GEC II 4 km 5.94 km 4 km Yes, no change Material supply in I Boko Town progress. Construction yet to begin.

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 49

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Sub-output Electrical Package Location Quantity/proposed Quantity/length Quantity/length Compliance Execution Circle no.; Lot length as per IEE as per as per Route status (IEE no. Bid/contract survey and RS)

TOTAL 7 km 8.94 km 7 km Yes, no change LENGTH

Package II

Package Jawaharnagar 60 km 60 km 67.20 km No, line length Kahilipara GSS to 6 Re- GEC I II/LOT I S/S to Sonapur increased in Ulubari S/S (6 km ) conductoring/ s/s (11 km) removed from scope refurbishment Jawaharnagar as this will be of 956 km of Chandrapur S/S to Sonapur implemented under 33 kV lines GSS to Narengi s/s (16.6 km) another scheme. S/S ( 3 km) Chandrapur Material supply in Sarusajai GSS GSS to progress. to Fatashil (12 Narengi S/S Construction yet to km) (4.3 km) begin. Work to start Kahilipara GSS Sarusajai GSS after monsoons. to Ulubari S/S (6 to Fatashil km ) (13.2 km) Kahilipara GSS Kahilipara to Paltanbazar GSS to S/S (16 km) Ulubari S/S (6 km ): no Kahilipara GSS longer in to Fatashil S/S scope. (8 km) Kahilipara GSS Kalapahar S/S to to Paltanbazar 5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 50

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Sub-output Electrical Package Location Quantity/proposed Quantity/length Quantity/length Compliance Execution Circle no.; Lot length as per IEE as per as per Route status (IEE no. Bid/contract survey and RS) Fatashil S/S (4 S/S (18.2 km) km) Kahilipara GSS to Fatashil S/S (9.6 km) Kalapahar S/S to Fatashil S/S (5.3 km) Package to 27.5 km 27.5 km 41.30 km GEC II No, Material supply in II/LOT I BIP, Amingaon increase in progress. (0.5km) line length. Construction yet to Mirza S/S to begin. Changsari to Bulla near VIP BIP,Amingaon Material supply in (27 km) (8.9 km) progress. Pole erection complete for 2 MirzaS/S km. Construction toBulla near suspended because of VIP (32.4 km) rains.

Package Mangaldai Kathalguri to 125 km 125 km 147.1 km No, increase in Material supply in II/LOT I EC Udalguri S/S (7 line length progress. Construction km) to begin after Kathalguri to monsoons. Rowta to Udalguri S/S Burigaon (25 km) (9.8 km) Barigaon to Rowta to Chapai (28 km) Burigaon (29.9 km) Rangia to Tangla

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 51

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Sub-output Electrical Package Location Quantity/proposed Quantity/length Quantity/length Compliance Execution Circle no.; Lot length as per IEE as per as per Route status (IEE no. Bid/contract survey and RS) (50 km) Barigaon to Chapai (31.2 Tangla to Kasubil km) (15km) Rangia to Tangla (58.8km) Tangla to Kasubil (17.4 km) Package Material supply in Rangia EC Tangla feeder 34 km 34 km 42.61 km No, increase in II/LOT I progress. Construction from Chirakhundi line length to begin after (Rangia) GSS Tangla feeder monsoons. Only (20 km) renamed to Under Kamalpur to Kamalpur to Rangia GSS to Alipub, pole erection Alipub (6 km) Goreswar (23 and stringing complete km) for 7.35 km. Alipub to Bezera (3 km) Kamalpur to Alipub (7.35km) Chirakhundi . (Rangia) to Alipub to Balagaon (5 km) Bezera (5.46km) Chirakhundi (Rangia) to Balagaon (6.80 km)

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 52

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Sub-output Electrical Package Location Quantity/proposed Quantity/length Quantity/length Compliance Execution Circle no.; Lot length as per IEE as per as per Route status (IEE no. Bid/contract survey and RS) Package 105.5 km 105.5 km 122.60 km Barpeta EC Nathkuchi to No, increase in Material supply in II/LOT I Pathsala S/S (20 line length progress. Construction km) to begin after Nathkuchi to monsoons. Barpeta S/S to Pathsala S/S Changa S/S (26 (23.8 km) Simlaguri to Howly km) feeder Barpeta S/S Barpeta S/S to Simlaguri to Changa S/S removed from scope Howly feeder (29.2 km) as this will be Barpeta S/S (0.5 implemented under Simlaguri to km) another scheme. Howly feeder Barnagar GSS to Barpeta S/S Sorbhog S/S (4 (0.5 km) no km) longer in scope Barnagar GSS to Manikpur S/S (20 Barnagar GSS km) to Sorbhog S/S Barpeta to (4.8 km) Sarthebari S/S Barnagar GSS (35 km) to Manikpur S/S (24.2 km) Barpeta to Sarthebari S/S (40.6 km)

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 53

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Sub-output Electrical Package Location Quantity/proposed Quantity/length Quantity/length Compliance Execution Circle no.; Lot length as per IEE as per as per Route status (IEE no. Bid/contract survey and RS) Package Birjhara to Bijni Bongaigaon 62.5 km 62.5 km 48.2 km No, decrease in Material supply in II/LOT I (35 km) EC line length progress. Construction to begin after Kokrajhar to Birjhara to Bijni monsoons. Kajolgaon feeder (39 km) (5km) APM to Kokrajhar to Chapaguri shifted to other Kajolgaon scheme. feeder (2.5km) feeder (6.2 APM to km), Abhayapuri (20 reassigned as km) Kajalgaon S/S to Dhaligaon SS Chapaguri feeder (3 km) changed to Bongaigaon to Dhaligaon feeder. APM to Abhayapuri (20 km) dropped from package Kokrajhar Package Gauripur to 17 km 17 km 21.1 km No, increase in Material supply in EC II/LOT I (12 km) line length progress. Construction to begin after Matibag to Gauripur to monsoons. Gauripur (5 km) Dhubri

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 54

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Sub-output Electrical Package Location Quantity/proposed Quantity/length Quantity/length Compliance Execution Circle no.; Lot length as per IEE as per as per Route status (IEE no. Bid/contract survey and RS) (14.6km) Matibag to Gauripur (6.5 km) No, increase in total line TOTAL LENGTH (LOT I) 431.5 km 431.5 km 490.11 km length by 58.61 km Tezpur EC Package Rowta-Mizibari- 66 km 66 km 70 km No, Increase in Completed RS II/LOT II Dhekiajuli feeder total line length submitted. Material (20 km) supply near Rowta-Mizibari- completion. Depota- Dekiajuli Dhekiajuli feeder (46 km) feeder (22 km) Rowta-Dhekiajuli: 40 poles erected and 8.03 Deepota- km stringing complete. Dhekiajuli feeder(48 km) Deepota-Dhekiajuli feeder: Pole erection

(43) complete; stringing of 8.64 km complete.

Nagaon EC Package Samuguri GSS 53 km 53 km 54.3 km No, line length RS completed & II/LOT II to Rangagara increase submitted. Material (8km) supply in progress. Samuguri GSS Amoni CR to to Rangagara Samuguri GSS to Garubandha (9.3 km) Rangagara Pole erection (20) (30km) complete; 4.25 km

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 55

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Sub-output Electrical Package Location Quantity/proposed Quantity/length Quantity/length Compliance Execution Circle no.; Lot length as per IEE as per as per Route status (IEE no. Bid/contract survey and RS) Barapujia to J B stringing achieved. Garh (15 km) Amoni CR to Garubandha: construction not started. Barapujia to J B Garh: Pole erection (15) and stringing of 3.03 km complete. North Package Gohpur- 78 km 78 km 80.4 km No, line length Gohpur- Narayanpur- Lakhimpur II/LOT II Narayanpur- increased. Bihpuria: Material EC Bihpuria (70km) supply in progress. Gohpur- Construction yet to Hatigarh- Narayanpur- begin. Dhemaji (8km) Bihpuria (71.2 km) Hatigarh- Dhemaji: pole erection and Hatigarh- stringing in progress. Dhemaji (9.2 km) Cachar EC Package Panchgram- 19.5 km 19.5 km RS in progress No Route survey in II/LOT II Kalain feeder progress. from Panchgram to Bank of the Barak (0.5 km) Panchgram- Kalain feeder from Katigora Chowrangi to Kalian S/S (15

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 56

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Sub-output Electrical Package Location Quantity/proposed Quantity/length Quantity/length Compliance Execution Circle no.; Lot length as per IEE as per as per Route status (IEE no. Bid/contract survey and RS) km) Pailapool- Paingram feeder No.1 from Pailapool to Bandhu (4km) Badarpur Package S/S to 55 km 55 km RS in progress No Route survey in EC II/LOT II Patharkandi S/S progress. (32km) Badarpurghat S/S to Panchgram GSS (5km) Hailakandi S/S to Lala S/S (18km)

TOTAL LENGTH (LOT II) 271.5 km 271.5 km 279.2 km No, increase in line length by 7.7 km

Jorhat EC Titabar to 75 km 75 km 75 km Yes, The Material supply in Barhola (24km) Mariani- progress; construction Package Mariani to Nakachari yet to begin. Nakachari (15 II/LOT III alignment is km) under review Jorhat (RRL) to Dergaon S/S (28

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 57

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Sub-output Electrical Package Location Quantity/proposed Quantity/length Quantity/length Compliance Execution Circle no.; Lot length as per IEE as per as per Route status (IEE no. Bid/contract survey and RS) km) Jorhat (RRL) to Pulibor (8 km) Golaghat Material supply in Tetelitol to Usha 22 km 22 km 22 km Yes EC progress. Construction S/S (12km) Package yet to begin. II/LOT III Tetelitol GSS to Komarbondha S/S (10km)

Moran SS to 85 km 85 km 85 km Yes Except for Moran- Khowang S/S Demow where work is (22km) yet to begin, material supply in progress. Moran S/S to Construction yet to Demow S/S begin. Sivsagar Package (22km)

EC II/LOT III Gargoan to S/S (26 km) Salkathoni S/S to GSS (15km) No, increase in Moran GSS to 70 km 70 km 72 km Material procurement line length Rajgarh S/S pending. Construction Dibrugarh Package (40km) Nadua feeder yet to begin. EC II/LOT III Tinsukia GSS to from H/bank to Air Force Bordubi S/S station Nadua (22km) (8 km) 5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 58

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Sub-output Electrical Package Location Quantity/proposed Quantity/length Quantity/length Compliance Execution Circle no.; Lot length as per IEE as per as per Route status (IEE no. Bid/contract survey and RS) Nadua feeder from H/bank to Air Force station Nadua (6 km) Mohanbari feeder from H/Bank to Mohanbari MES (2 km) Tinsukia 1 km 1 km 1 km Yes Material near EC Tinsukia S/S to Package completion. Borguri tapping II/LOT III Construction yet to point (1km) begin.

No, increase TOTAL LENGTH (LOT III) 253 km 253 km 255 km in total line length by 2 km

No, increase in total line Grand Total of 33kV line (Lot I, II & III) 956 km 956 km 1024.31 km length by 68.31 km

7 Rehabilitation GEC-I Package Fatasil S/S 1 no 1 no 1 no Yes Survey completed and and II/LOT I submitted. Approval renovation of awaited. Construction six (6) new 33 yet to begin. kV bays at existing 33 kV/11kV substations 5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 59

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Sub-output Electrical Package Location Quantity/proposed Quantity/length Quantity/length Compliance Execution Circle no.; Lot length as per IEE as per as per Route status (IEE no. Bid/contract survey and RS)

GEC-I Package Sarusajai GSS 1 no 1 no 1 no Yes Survey not conducted II/LOT I owing to pending approval from AEGCL. Construction yet to begin.

GEC-I Package Kahilipara GSS 2 nos. 2 nos. 1 no No, decrease in Survey completed and II/LOT I number of submitted. Approval bays. awaited. Construction yet to begin.

GEC-I Package Ulubari S/S 1 no. 1 no. 2 nos. No, increase Survey completed and II/LOT I in number of submitted. Approval bays. awaited. Construction yet to begin.

GEC-I Package Paltan Bazar S/S 1 no. 1 no. 1 no. Yes Survey completed and II/LOT I submitted. Approval awaited. Construction yet to begin.

Yes, no TOTAL 6 no. 6 no. 6 no change in total quantity.

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 60

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Sub-output Electrical Package Location Quantity/proposed Quantity/length Quantity/length Compliance Execution Circle no.; Lot length as per IEE as per as per Route status (IEE no. Bid/contract survey and RS)

8 Re- GEC-I Package No, line length Material supply in conductoring/ II/LOT I increase progress. Pole (120) refurbishment Guwahati-I 100 km 100 km 123.6 km erection complete.

of 1000 km of 11 kV lines

GEC-II Package No, line length Material supply in II/LOT I increase progress. Pole (83) Guwahati-II 100 km 100 km 115.41 km erection complete.

Bongaigaon Package Material supply No, line length EC II/LOT I 50.4 km complete. Pole (250) Bongaigaon 50 km 50 km increase erection complete.

Rangia EC Package Material supply No, line length II/LOT I complete. Pole (67) increase Rangia 50 km 50 km 51.3 km erection complete.

Mangadoi Package Material supply in Yes EC II/LOT I progress. Pole (20) Mangaldai 40 km 40 km 40 km erection and stringing (4.54 km) complete.

No, there is increase in the TOTAL LENGTH (LOT I) 340 km 340 km 380.71 km total line length by 40.71 km

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 61

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Sub-output Electrical Package Location Quantity/proposed Quantity/length Quantity/length Compliance Execution Circle no.; Lot length as per IEE as per as per Route status (IEE no. Bid/contract survey and RS) Tezpur EC Package 60 km 60 km 60 km Yes Material supply in II/LOT II progress and pole (26) Tezpur erection and stringing (5.12 km) complete. Nagaon EC Package 60 km 60 km 60 km Yes Material supply in II/LOT II progress; pole (101) Nagaon erection and 20.20 km stringing complete. Morigaon Package 50 km 50 km 50 km Yes Material supply in EC II/LOT II Morigaon progress. Construction yet to begin. North Package 50 km 50 km 50 km Yes Material supply in Lakhimpu-r II/LOT II progress; 45 poles North Lakhimpur EC erected and 9 km stringing complete. Cachar EC Package 50 km 50 km 50 km Yes Route survey II/LOT II Cachar completed. Work yet to begin. Badarpur Package 50 km 50 km 50 km Yes Route survey EC II/LOT II Badarpur completed. Work yet to begin.

320 km Yes, total line TOTAL LENGTH (LOT II) 320 km 320 km length remains same.

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 62

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Sub-output Electrical Package Location Quantity/proposed Quantity/length Quantity/length Compliance Execution Circle no.; Lot length as per IEE as per as per Route status (IEE no. Bid/contract survey and RS) Package 100 km 100 km 100 km Yes Material supply in II/LOT III Jorhat EC Jorhat progress. Construction yet to begin. Package 60 km 60 km 100 km No, line length Material supply in Golaghat II/LOT III Golaghat increase progress. Construction EC yet to begin. Package 60 km 60 km 60 km Yes Material supply in II/LOT III SivsagarEC Sibsagar progress. Erection yet to begin. Package 60 km 60 km 60 km Yes Material supply; pole II/LOT III Dibrugarh (13) erection and Dibrugarh EC stringing in 2.51 km in progress. Package Tinsuka EC Tinsukia 60 km 60 km 60 km Yes Material supply in II/LOT III progress. Erection yet to begin.

No, total line TOTAL LENGTH (LOT III) 340 km 340 km 380 km length increase by 40 km. No, total line length Grand Total of 11kV line(Lot I, II & III) 1000 km 1000 km 1080.71 increase by 80.71 km.

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 63

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Sub-output Electrical Package Location Quantity/proposed Quantity/length Quantity/length Compliance Execution Circle no.; Lot length as per IEE as per as per Route status (IEE no. Bid/contract survey and RS) GEC-I Package 9 Re- 200 km 200 km 219.45 km No, increase in Material supply II/LOT I conductoring/ line length complete. Pole (500) refurbishment Guwahati-I erection complete and

1555 km of LT stringing in progress. lines GEC-II Package 150 km 150 km 191.37 km No, increase Material supply II/LOT I in line length complete. Pole (400) Guwahati-II erection and stringing (95.7 km) complete.

Bongaigaon Package 100 km 100 km 118.20 km No, increase Material supply EC II/LOT I in line length complete. Pole (150) Bongaigaon erection and stringing (50.09 km) complete. Rangia EC Package 100 km 100 km 101.50 km No, increase in Material supply II/LOT I line length complete. Pole (239) Rangia erection and stringing (86.36 km) complete. Mangadoi Package 100 km 100 km 100 km Yes Material supply in EC II/LOT I progress. Pole (65) Mangaldai erection and stringing (9.09 km) complete. Barpeta EC Package Barpeta 100 km 100 km 100 km Yes Material supply in II/LOT I progress. Pole (95) erection and stringing (40.9 km) complete.

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 64

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Sub-output Electrical Package Location Quantity/proposed Quantity/length Quantity/length Compliance Execution Circle no.; Lot length as per IEE as per as per Route status (IEE no. Bid/contract survey and RS)

No, total line length TOTAL LENGTH (LOT I) 750 km 750 km 830.52 km increases by 80.52 km. Tezpur EC Package 100 km 100 km 100 km Yes Material supply in II/LOT II Tezpur progress. Construction yet to begin. Nagaon EC Package 30 km 30 km 30 km Yes Material supply in II/LOT II Nagaon progress. Construction yet to begin. Morigaon Package 50 km 50 km 50 km Yes Material supply in EC II/LOT II progress. Pole (24) Morigaon erection and stringing (3.33 km) complete. Cachar EC Package 50 km 50 km 50 km Yes Material supply in II/LOT II Cachar progress. Construction yet to begin. Badarpur Package 100 km 100 km 100 km Yes Material supply in EC II/LOT II Badarpur progress. Construction yet to begin.

Yes, total line TOTAL LENGTH (LOT II) 330 km 330 km 330 km length remains same.

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 65

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Sub-output Electrical Package Location Quantity/proposed Quantity/length Quantity/length Compliance Execution Circle no.; Lot length as per IEE as per as per Route status (IEE no. Bid/contract survey and RS) Package 150 km 150 km 150 km Yes Material supply in II/LOT III Jorhat EC Jorhat progress. Construction yet to begin. Package 75 km 75 km 75 km Yes Material supply in Golaghat II/LOT III Golaghat progress. Construction EC yet to begin. Package 50 km 50 km 50 km Yes Material supply in Sivsagar II/LOT III Sivsagar progress. Construction EC yet to begin. Package 100 km 100 km 100 km Yes Material supply in Dibrugarh II/LOT III Dibrugarh progress. Construction EC yet to begin. Package 100 km 100 km 100 km Tinsuka EC Tinsukia Yes Material supply in II/LOT III progress. Construction yet to begin.

Yes, total line TOTAL LENGTH (LOT III) 475 km 475 km 475 km length remains same.

No, total line length Grand Total of LT line (Lot I, II & III) 1555 km 1555 km 1635.52 increases by 80.52 km. Package 10 Replacement GEC-I 50 nos. 50 nos. Yes Work yet to begin. II/LOT I Guwahati-I 50 nos. of 204 existing

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 66

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Sub-output Electrical Package Location Quantity/proposed Quantity/length Quantity/length Compliance Execution Circle no.; Lot length as per IEE as per as per Route status (IEE no. Bid/contract survey and RS) oil-filled distribution transformers with dry-type transformers GEC-II Package 29 nos. No, reduction in Work yet to begin. II/LOT I Guwahati-II 30 nos. 30 nos. number Kokrajhar Package 7 nos. 7 nos. 7 nos. Yes Work yet to begin. EC II/LOT I Kokrajhar Rangia EC Package 10 nos. 10 nos. 10 nos. Yes Work yet to begin. II/LOT I Rangiya Barpeta EC Package Barpeta 10 nos. 10 nos. 10 nos. Yes Work yet to begin. II/LOT I Bongaigaon Package Bongaigaon EC 1 no No, increase in Work yet to begin EC II/LOT I 0 0 number

TOTAL (LOT-I) 107 nos. 107 nos. 107 nos. Yes, total number same. Tezpur EC Package Yes Work yet to begin. II/LOT II Tezpur 15 nos. 15 nos. 15 nos. Nagaon EC Package Yes Work yet to begin. II/LOT II Nagaon 3 nos. 3 nos. 3 nos. Cachar EC Package Work yet to begin. Yes II/LOT II Cachar 10 nos. 10 nos. 10 nos.

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 67

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Sub-output Electrical Package Location Quantity/proposed Quantity/length Quantity/length Compliance Execution Circle no.; Lot length as per IEE as per as per Route status (IEE no. Bid/contract survey and RS) Badarpur Package Yes Work yet to begin. EC II/LOT II Badarpur 5 nos. 5 nos. 5 nos.

Yes, total TOTAL (LOT-II) 33 nos. 33 nos. 33 nos. number remains same. Package Yes Work yet to begin. Jorhat EC II/LOT III Jorhat 20 nos. 20 nos. 20 nos. Package Golaghat Yes Work yet to begin. II/LOT III Golaghat 10 nos. 10 nos. 10 nos. EC Package Sivsagar Yes Work yet to begin. II/LOT III Sibsagar 4 nos. 4 nos. 4 nos. EC Package Dibrugarh Yes Work yet to begin. II/LOT III Dibrugarh 10 nos. 10 nos. 10 nos. EC Package Tinsuka EC Tinsukia Yes Work yet to begin. II/LOT III 20 nos. 20 nos. 20 nos.

Yes, total TOTAL (LOT-III) 64 nos. 64 nos. 64 nos. number remains same.

Yes, total number Grand Total (Lot I, II & III) 204 nos. 204 nos. 204 nos. remains same.

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 68

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Sub-output Electrical Package Location Quantity/proposed Quantity/length Quantity/length Compliance Execution Circle no.; Lot length as per IEE as per as per Route status (IEE no. Bid/contract survey and RS)

Package III

GEC I Package 11 Replacement In & Around 7.3 km 7.3 km 7.3 km Yes Work yet to begin. III of existing 14 Dispur Capital km of Complex, overhead 11 Guwahati kV & LT line

with underground cable GEC I Package 6.8 km 6.8 km 6.8 km G.S Road from Yes Work yet to begin. III Paltan Bazar to Ganeshguri, Guwahati

Yes, total line TOTAL LENGTH 14.1 km 14.1 km 14.1 km length remains same.

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 69

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Annexure-1B Output 2: Strengthening institutional capacity of APDCL

Sl.No Sub-output Electrical Package Location Quantity/proposed Quantity/length as Compliance Execution Circle no.; Lot no. length as per IEE per Bid/contract status

Setting up of one (1) Assam Engineering 1 independent meter GEC-II Package IV 01 01 Yes Work yet to begin. College, Jalukbari testing laboratory Establishing two (2) Jorhat EC Package IV Area Load Dispatch Design review area load dispatch Centre in : completed, supply centers At Bidyut Bhawan, Na-ali, of material nearing 2 1 no. 1 no. Yes Jorhat under Jorhat completion. Electrical Circle, APDCL. Construction in progress. GEC-I Package IV Area Load Dispatch Design review Centre in Guwahati completed, supply District: Six Mile, APDCL 1 no. 1 no. Yes of material nearing

Complex completion. Construction in progress. Establishing one (1) IT IT module for introduction module for the of centralized uniform Package stands introduction of revenue billing system cancelled (ref. 3 GEC II Package-V 01 01 Not applicable centralized uniform under Jorhat, Dibrugarh, discussion dated 8 revenue billing system Tinsukia, Sibsagar March 2018) for all consumers Electrical Circle

Yes, no change in location and TOTAL number 2 nos. 2 nos. number.

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 70

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Annexure-2A Site visits conducted between January - June 2018 for inspection and progress update

Sl No Site visit Package Item, Location Observations Date Area/space for control room handed over to the contractor by CEO, Guwahati Circle I, APDCL. 1 17/03/2018 4 Inspect construction of All associated civil work was executed as per original approved ‘G+4’ data center building at Control Room Building for Sixmile, ASEB complex. However, a revised drawing was prepared thereafter and the contractor is ALDC (SCADA) at Sixmile now to execute all civil work as per revised approved drawing. under Guwahati EC - I.

2 28/03/2018 1 Assess availability of space 1.Barnagar Grid Substation: The area demarcated for bay was found suitable. for construction of 33 kV Bay 2.Pathsala Substation: The area demarcated for bay has existing equipment and materials. at Barnagar GSS, Sarihtoli Contractor advised to clear the same prior to commencement of work. GSS, Nathkuchi SS and Pathsala SSunder Barpeta 3. Sarihtoli Grid Substation: The area demarcated for bay is found suitable. EC. 4.Nathkuchi Substation: The area demarcated for bay has existing Joist structure which is to be utilized. Space demarcated is congested. Very narrow corridor for 33 kV new incoming line up to take off structure. Proper safe electrical clearance to be ensured for 33 kV incoming line prior to commencement of work.

3 03/04/2018 1 Inspect construction work of 1. Barnagar GSS – Howly to connect with existing 33 kV Pathsala feeder: In one of the span new 33KV lines under (near Barnagar GSS, 50 m approx.), there is crossing of existing 132kV transmission line. There Barpeta EC. may not be sufficient clearance between 132kV and the new 33kV lines. To rectify, the Contractor shall create required clearance and if found inadequate may consider laying this section of the 33kV line underground using XLPE cable. 2.Beki river crossing for Barnagar GSS – Howly 33kV Line using DB+6 Tower: Contractor has flouted the approved design/drawing by reducing the number and specifications of bars/reinforcement for the chimney/column of the tower. Strict instructions were issued to Contractor to dismantle all the constructed columns and rectify the mistake as per the approved drawing. Contractor was also advised to perform cube test for foundations and maintain the test cubes at site. Likewise, the Steel Tubular SP76 Poles were not erected as per technical specifications, thus

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 71

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Contractor was advised to rectify the same. 3. Sarihtoli GSS – Nathkuchi S/S: SP 76 Pole delivery work is in progress at site. 4. Pathsala S/S – Sarupeta S/S: Work is not yet started. 5. Barjhar (Barama) S/S – Katahbari S/S: SP 76 Pole delivery work is in progress at site.

4 12/04/2018 1 Inspect the rectification work Beki river crossing for Barnagar GSS – Howly 33kV Line using DB+6 Tower: Contractor has of new 33KV river crossing executed the rectification work as per advice and drawings. Work completed towards Barnagar line under Barpeta EC. GSS, and under progress towards Howly SS section.

5 25/04/2018 2, Lot-1 Inspect general progress of The quantity of poles erected as reported by the Contractor does not tally with the field site R&M (Re conductoring work inspection. for 11kV and LT lines under Contractor was advised also to checkpole straightness, foundation depth and proper binding of GEC-I. conductor with insulator. For Bamunimaidam, Chandmari, Luit Nagar, Noonmati (Water treatment plant) and Salbari, Noonmati conductor binding method with insulator was found to be incorrect. The overlapping tied portion of the conductor was insufficient. Contractors were advised to provide adequate overlapping accordingly.

6 15/05/2018 1 Inspect strengthening of General: pole erection not undertaken as per specified procedures, hence deemed incomplete; distribution network under certain serious shortcomings found in erection quality and workmanship, and Contractor to rectify the Barpeta EC for three the shortcomings at the earliest. new 33kV lines. Specific: Grouting and PCC base of pole foundation not as per specifications and APDCL approved design; planting depth requirement not adhered to during pole erection; and average pole span maintained (approx. 36-48 m) appears to be on lower side. The above mentioned non-compliances might affect stability of heavy steel pole(approximate weight 380 kg). In the absence of PCC grouting, erected pole might not get adequate support as the total axial load is not properly distributed over a sufficient area as per soil bearing capacity. Lesser planting depth also may tilt the pole during conductor stringing. Hence the completed line could be unsafe and as a result such sections are not acceptable. APDCL may kindly take a final decision on pole span based on approved survey report. The Contractor M/s NECCON was advised to take necessary steps for rectification of above non-compliances and strict adherence to APDCL approved designs and contract specifications/procedures.

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 72

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

7 21/05/2018 1 Inspect strengthening of General: pole erection not undertaken as per specified procedures, hence deemed incomplete; distribution network under certain serious shortcomings found in erection quality and workmanship, and Contractor to rectify the Barpeta Electrical the shortcomings at the earliest. Circle for two new 33kV Specific: Grouting and PCC base of pole foundation not as per specifications and APDCL approved lines. design; planting depth requirement not adhered to during pole erection; and average pole span maintained (approx. 36-48 m) appears to be on lower side. The above-mentioned non-compliances might affect the stability of heavy steel pole (approx. weight 380 kg). In the absence of PCC grouting, erected pole might not get adequate support as the total axial load is not properly distributed over a sufficient area as per soil bearing capacity. Lesser planting depth also may tilt the pole during conductor stringing. Hence the completed line could be unsafe and as a result such sections are not acceptable. APDCL may kindly take a final decision on pole span based on approved survey report. The Contractor M/s NEECON was advised to take necessary steps for rectification of above non-compliances and strict adherence to APDCL approved designs and contract specifications/procedures.

8 24/05/2018 2,Lot-1 Inspect general progress of General: pole erection not undertaken as per specified procedures, hence deemed incomplete; R&M (Re conductoring work certain serious shortcomings found in erection quality and workmanship, and Contractor to rectify for 11kV and LT lines under the shortcomings at the earliest. GEC-I and GEC II. Specific: planting depth requirement of pole length not followed in almost all erected poles. Brick soling and boulder packing, ramming is poorly done in many poles. In some locations, poles engraved with markings not related to the project. The above-mentioned non-compliances might affect stability of PSC pole. Lesser planting depth also may tilt the pole during conductor stringing as well as during rainy season rendering the poles unsafe. Contractor (M/s Hemen Deka was advised to take necessary steps for rectification of above non-compliances and strict adherence to APDCL approved designs and contract specifications/procedures.

9 9/06/2018 & 1 Inspect construction of 33 The foundation work of 33kV SF6 Circuit Breaker structure is in progress. However, the Contractor 10/06/2018 KV terminal bay at 132/33 has not adhered to technical specifications with regard to reinforcement as well as the approved KV Barnagar GSS, 33/11KV drawing. The Contractor was advised to halt all construction and address the issues identified. Barjhar- Barama SS and 33/11 KV Pathsala SS under Barpeta EC.

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 73

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

10 16/06/2018 1 Inspect the construction of The contractor has recast the foundation of the 33 KV SF6 Circuit 33 KV terminal bay at 132/33 Breaker but the height of the foundation does not comply with the drawing. Instructions were issued KV Barnagar GSS. to contractor to conform to specifications and make necessary changes with immediate effect.

11 21/06/2018 1 Assess availability of space 1.Behiating Grid Substation: The area demarcated for bay is found suitable. However, the Bay for construction of 33 kV Bay orientation shown in the drawing is not correct; existing switchyard drain in the proposed bay at Behiating GSS, position needs to be relocated and side fencing is to be removed. Khowang SS, Moran SS 2.Khowang Substation: the proposed Bay orientation shown in the drawing is not correct. Some and Demow SS as well as1 portion of the bay already occupied under another scheme. Thus, proposed site not viable. Request no 33kV D/C river crossing for with B+6 tension tower for the Behiating –Khowang SS resurvey and resubmission of new proposal advised. line. 3.Moran Substation: proposed site for bay not viable as width of the proposed bay is not adequate and cable trench route from control room shown in the drawing is incorrect. Request for resurvey and resubmission of new proposal advised. 4.Demow Substation: contractor has not submitted any drawing for 33 kV proposed bay for approval as on date. Owing to paucity of space inside the switch yard, it may be difficult to accommodate another 33 kV bay. Further clear corridor for incoming 33 kV line is also not available. 5.33kV line - Buridihing River crossing: improper STUB member setting under foundation work for the two B+6 Tension D/C towers at 33kV Behiating – Khowang line river (Buridihing ) crossing. Contractor advised to submit proof that all the STUB members are properly installed and fitted in the sub structure as per above referred drawing.

12 21/06/2018 4 Inspect progress of erection i) The Control room for installation of RTU along with 48V DCPS with VRLA batteries is complete. & of RTU panels and other However, fixing of Air Conditioner is pending. No Cable Trench is constructed inside the Control 22/06/2018 related works for ALDC room for laying of cable for RTU and DCPS and neither any provision for entry of cable from (SCADA) under Jorhat switchyard to the Control room is made. Contractor was advised to construct a cable trench inside Electrical Circle. the Control room to accommodate all the required cables and provide an entry for the cables from switchyard to Control room. 2. 33/11kV Borhola Substation: construction of Control room is in progress. No provision for Cable

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 74

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Trench inside the Control room for laying of cable for RTU and DCPS and entry of cable from switchyard to the Control room made. Contractor was suggested to construct a cable trench inside the Control room to accommodate all the required cables and provide an entry for the cables from switchyard to Control room. The quality of the civil work for construction of Mast Tower foundation is found to be poor and no cube test has been conducted. 3. Jorhat Bidyut Bhawan (Control Center): The construction of Control Center is complete. However, fixing of Air Conditioner is not yet done. 4. 33/11kV Pulibor Substation: this Substation is now to be constructed afresh under a different scheme. Construction work is yet to commence. APDCL is requested to commence with the construction activities for this Substation immediately, so that the RTU can be installed in this Substation within the completion period of this package which is April 2019.

26/06/2018 1 Inspect construction The foundation of 33KV Isolator (without earth switch) was recast but there is presence of & construction of 33 KV honeycombs on the surface, which needs to be removed. Contractor should be advised to fill up the 13 27/06/2018 terminal bay at 33/11KV area of new terminal bay so as to maintain the equipment foundation height of 300mm above the Pathsala substation & finished ground level. The planting depth of erected poles is less than prescribed norms. Nathkuchi substation

14 28/06/2018 1, Lot 1 Site visit was conducted to 1.Kahilipara Grid Substation: the area demarcated for bay was found suitable. inspect the space available 2.Fatashil Substation: dismantling of existing structures, store rooms is required to accommodate for construction of 33 kV Bay the new bay. at Kahilipara GSS, Fatashil SS, Paltan Bazar SS and 3.Paltan Bazar Substation: dismantling of existing structures and store rooms is required to Ulubari SS under Guwahati accommodate the new bay. Electrical Circle I 4. Ulubari Substation: dismantling of existing structures and equipment is required to accommodate the new bay.

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 75 Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Project progress photographs Annexure-2B

Tower foundation at Beki river crossing 33kV Terminal Bay Foundation at Barjhar (Barama) S/S

New 33kV pole erection in progress from Sarihtoli to Material procurement in progress for 33kV refurbishment Natkhuchi S/S under GEC-I

Guwahati ALDC Building construction work in progress Jorhat ALDC Building construction work in progress

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Annexure-3

Details of Implementing Agency, APDCL Sl. List of Sub- Projects Electrical Circle Electrical Division Name of the CEOs Contact No. No. Package-1: Construction of New 33/11 kV Sub Station forsystem strengthening, new 33kV & 11kV Lines, 33kV Terminal Equipment and 33kV & 11kV Railway/River Crossings Guwahati Electrical i. New 2X5 MVA, 33/11kV Sub Station (1 no.) Division , Electrical ii. New 33 kV Lines (12 km) Division ,North 0361 2523916(O), Guwahati Electrical Guwahati Electrical Munindra Narayan Dutta 1 iii. New 11 kV Lines (6 km) 9864094208 Circle-I Division ,North CEO ,GEC-I [email protected] Guwahati Electrical iv. 33kV bay terminal equipment (2 nos.) Division ,North Guwahati Electrical v. Railway Crossing (1 no.) (0.15KM) Division ,Central i. New 33 kV Lines (10 KM) ii. New 11 kV Lines (7 km) GED-West &Mirza 0361 2700723(O) Guwahati Electrical Manoranjan Kalita 2 iii. 33kV bay terminal equipment(1 no.) 9435137602 Circle- II CEO,GEC-II [email protected] Guwahati Electrical iv. Railway Crossing (1)0.25KM Division ,West i. New 33 kV Lines (75.5 KM) ii. 33kV bay terminal equipment(4nos.) iii. Railway Crossing (1) (0.15km) Barpeta Electrical Nirmaljit Das 03665 5252244(O) 3 Barpeta iv. River Crossing (1) Circle CEO, Barpeta [email protected] 33 kV GOAB & DO v.

4 i. New 33 kV Lines (44 KM) Sibsagar Electrical Sibsagar Dhruba Bora 03772 222346(O),

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 77 Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Sl. List of Sub- Projects Electrical Circle Electrical Division Name of the CEOs Contact No. No. ii. 33kV bay terminal equipment(4) Circle CEO, Sibsagar 9854653966 [email protected] iii. Railway Crossing (2)0.6KM iv. River Crossing (1) Package-2:R&M and Reconductoring of 33kV ,11 kV and LT lines; Replacement of Oil-Field distribution Transformers with Dry Type Distribution Transformers (Lot-I)

GED-North,GED- 0361 2523916(O), Guwahati Electrical Munindra Narayan Dutta i South,GED- 9864094208 Circle- I CEO ,GEC-I Central,GED-East [email protected]

0361 2700723(o) Guwahati Electrical ManoranjanKalita ii GED-West &Mirza 9435137602 Circle- II CEO,GEC-II [email protected]

Mangaldoi Sonit Kr. Neog 03713 222125(O),9435046186 iii. Electrical Circle CEO, Mangaldoi [email protected] 03621 240532(O) Restringing, repair and maintenance (R&M) Rangia Electrical Mihir Bikram Choudhury iv. Rangia 9864012189 1 and Re-Conductoring of 33kV , 11kV LT Circle CEO,Rangia lines [email protected] 03664 230282 (O) Bongaigaon Bipul 9435553335 v. Bongaigaon Electrical Circle CEO, Bongaigaon [email protected]. in 03661 270431(O), Kokrajhar Electrical Mukul Patowary 9435123373 vi. Kokrajhar Circle CEO,Kokrajhar [email protected] [email protected] Barpeta Electrical Nirmaljit Das 03665 5252244(O) vii. Barpeta Circle CEO, Barpeta [email protected] Replacement of Oil-Filled transformers with GED-North,GED- Guwahati Electrical Munindra Narayan Dutta 0361 2523916(O),9864094208 i Dry Type Distribution Transformers (50 South,GED- Circle- I CEO ,GEC-I [email protected] units) Central,GED-East 2 Replacement of Oil-Filled transformers with 0361 2700723(o) Guwahati Electrical Manoranjan Kalita ii Dry Type Distribution Transformers (30 GED-West &Mirza 9435137602 Circle- II CEO,GEC-II units) [email protected]

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 78 Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Sl. List of Sub- Projects Electrical Circle Electrical Division Name of the CEOs Contact No. No. 03661 270431(O), Replacement of Oil-Filled transformers with Kokrajhar Electrical Mukul Patowary 9435123373 iii. Kokrajhar Dry Type Distribution Transformers (7 units) Circle CEO ,Kokrajhar [email protected] [email protected] Replacement of Oil-Filled transformers with 03621 240532(O) Rangia Electrical Mihir Bikram Choudhury iv. Dry Type Distribution Transformers (10 Rangia 9864012189 Circle CEO ,Rangia units) [email protected] Replacement of Oil-Filled transformers with Barpeta Electrical Nirmaljit Das 03665 5252244(O) v. Dry Type Distribution Transformers (10 Barpeta Circle CEO, Barpeta [email protected] units) Package-2:R&M and Reconducting of 33kV ,11 kV and LT lines; Replacement of Oil-Field distribution Transformers with Dry Type Distribution Transformers (Lot-II) Badarpur Electrical Aniruddha Kar CEO, 03843 268069 (O) 9435347824 i Badarpur Circle Badarpur [email protected] Tezpur Electrical Pankaj Kr. 03712 220302(O) ii Tezpur Circle CEO, Tezpur [email protected] 03672 255413(O) 9954071956 Restringing, repair and maintenance (R&M) Nagaon Electrical Krishnananda Saikia iii. Nagaon [email protected];dgmnaga 1 and Re-Conductoring of 33kV , 11kV LT Circle CEO, Nagaon lines [email protected] North Lakhimpur Jibeswar Das 03752 230190(O) iv. North Lakhimpur Circle CEO, North Lakhimpur [email protected] 03842 2420310 Cachar Electrical Krishnendu Nath v. Cachar 9435073549 Circle CEO, Cachar [email protected] Replacement of Oil-Filled transformers with Badarpur Electrical Aniruddha Kar 03843 268069 (O) 9435347824 2 i Dry Type Distribution Transformers (15 Badarpur Circle CEO, Badarpur [email protected] units) Replacement of Oil-Filled transformers with Tezpur Electrical Pankaj Kr. Saikia 03712 220302(O) ii Tezpur Dry Type Distribution Transformers (3 units) Circle CEO, Tezpur [email protected] Replacement of Oil-Filled transformers with 03672 255413(O) 9954071956 Nagaon Electrical Krishnananda Saikia iii. Dry Type Distribution Transformers (10 Nagaon [email protected]; Circle CEO, Nagaon units) [email protected]

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 79 Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Sl. List of Sub- Projects Electrical Circle Electrical Division Name of the CEOs Contact No. No. 03842 2420310 Replacement of Oil-Filled transformers with Cachar Electrical Krishnendu Nath iv. Cachar 9435073549 Dry Type Distribution Transformers (5 units) Circle CEO,Cachar [email protected] Package-2:R&M and Reconducting of 33kV ,11 kV and LT lines; Replacement of Oil-Field distribution Transformers with Dry Type Distribution Transformers (Lot-III) 0376 2320184 (O) Jorhat Electrical Pradip Kr. Dutta i Jorhat-I &II 9435105095 Circle CEO, Jorhat [email protected] 03774 281078(O) Golaghat Electrical Hemanta Kr Buzarbaruah ii Golaghat [email protected] Circle CEO, Golaghat m Restringing, repair and maintenance (R&M) Tinsukia Electrical D Das 0374 2352389 (O) 9864035124 1 iii. and Re-Conductoring of 33kV , 11kV LT Tinsukia lines Circle CEO Tinsukia [email protected] Sibsagar Electrical Dhruba Bora 03772 222346(O), 9854653966 iv. Sibsagar Circle CEO, Sivasagar [email protected]

Dibrugarh Electrical Nekibuddin Ahmed 0373 2324388 (O) 9435162084 v. Dibrugarh Circle CEO, Dibrugarh [email protected] 0376 2320184 (O), Replacement of Oil-Filled transformers with Jorhat Electrical Pradip Kr. Dutta 9435105095 i Dry Type Distribution Transformers (20 Jorhat-I &II Circle CEO, Jorhat [email protected] units) m Replacement of Oil-Filled transformers with 03774 281078(O) Golaghat Electrical Hemanta Kr Buzarbaruah ii Dry Type Distribution Transformers (10 Golaghat [email protected] Circle CEO, Golaghat units) m 2 Replacement of Oil-Filled transformers with Tinsukia Electrical Debajyoti Das 0374 2352389 (O) 9864035124 iii. Tinsukia Dry Type Distribution Transformers (4 units) Circle CEO Tinsukia [email protected] Replacement of Oil-Filled transformers with Sibsagar Electrical Dhruba Bora 03772 222346(O), 9854653966 iv. Dry Type Distribution Transformers (10 Sivasagar Circle CEO, Sivasagar [email protected] units) Replacement of Oil-Filled transformers with Dibrugarh Electrical Nekibuddin Ahmed v. Dry Type Distribution Transformers (20 Dibrugarh 0373 2324388 (O) Circle CEO, Dibrugarh units) 9435162084dbr_electrical_circle

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 80 Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Sl. List of Sub- Projects Electrical Circle Electrical Division Name of the CEOs Contact No. No. @yahoo.com

Package 3:Replacement of 33kV ,11kV and LV Overhead lines with Underground Cable network and Laying of Fibre Optic Cable System

Replacement of 33kV , 11kV and LV 1 i overhead lines with Underground Cable network Guwahati Electrical Guwahati Electrical Munindra Narayan Dutta 0361 2523916(O), 9864094208 Circle- I Division Capital CEO, GEC-I [email protected] Laying of Fibre Optic Cables along with UG ii cable System

Package 4: Area Load Dispatch Centers and Independent Meter Testing Laboratory

Construction of Area Load Dispatch Guwahati Electrical Guwahati Electrical Munindra Narayan Dutta 0361 2523916(O), 9864094208 1 i Centers at Guwahati Circle- I Division South CEO, GEC-I [email protected] 0376 2320184 (O) Construction of Area Load Dispatch Jorhat Electrical Pradip Kr. Dutta ii Jorhat-I 9435105095 Centres at Jorhat Circle CEO, Jorhat [email protected] Setting up of independent meter testing 0361 2700723(O) Guwahati Electrical Guwahati Electrical Manoranjan Kalita 2 i laboratory at Assam Engineering College, 9435137602 Circle- II Division West CEO, GEC-II Jalukbari , Guwahati [email protected]

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 81

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Annexure-4 GRC formation reminder

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 82

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Annexure- 5

New Assistant Manager for ESMU

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 83

Assam Power Sector Investment Program, Tranche - 2 Loan No. IND-3327

Annexure-6 GRC formationTezpur Electrical Circle

5061168 | A P D C L | Bi annual Report (Environmental Safeguard Monitoring) | Report No.03 84