<<

Parish

Community Flood Plan

April 2016 - Version 6 GETTING THERE Community Flood Group Organisation Structure

Patterdale Parish Community Flood Group Flood

EA Area Flood Groups – Rob Shephard Howard Lawton Jon Holdsworth Glencoyne Greenside Grisedale Patterdale Deepdale Hartsop Steve Dowson Suzy Hankin Steve Sykes James Sowerby Kevin Jackson Chris Brown Robert Wear ERT Simon Johnson Resilience and Emergency Planning Team Natural Jon Holdsworth / Fra Cooke TBC Property Flood Defences EDC Paul Turner / Dennis Henderson Jane Langston Beck, Gulley, Drain and Culvert Maintenance Programme LDNP Carl Scrivens / Kevin Jackson Suzy Hankin Upstream River, Beck and Land Management NT Danny Teasdale Steve Dowson

CCC TBC Community Flood Group so far…. ACTion Hellen Aitken Carl Scrivens, Danny Teasdale, Kevin Jackson, Jon Holdsworth, Fra Cooke, Steve Sykes, Robert Wear, Mary Lightfoot, Paul Turner, Chris Brown, James Sowerby, Rob Shephard, Suzy Hankin (LDNP) 2 If you want to be part of it please contact Rob 07767 794225… Community Flood Plan Objectives Understand what happened where and why and use that to……. 1. Current 2. Future 3. Future Recovery Planning Resilience

Sort out the Try and Stop If it does mess we it happening happen then have now again be prepared

3 Community Flood Plan Tasks 1. Set up a Community Flood Group with volunteers from all areas of the community and input from key agencies

2. Confirm problem areas, and for each identify what happened, why, what has been done, what still needs to be done and what needs to be done on a regular basis to make sure it doesn’t happen again

3. Agree these actions with the landowner, EA and other relevant agencies, secure the necessary funding, get the immediate stuff done, get sign off on regular maintenance work and commitment to future projects where required

4. Set up ongoing monitoring and emergency plans for future events 4 5 December Floods Timeline – First 7 Days Key Recovery Jobs Done Local Volunteers start clearing Glenridding Bridge Dredge Glenridding Beck c.10:00 in the village and down 30 sandbags to the Lake Pooley Army delivered to Glenridding Glenridding Bridge Arrives with Glenridding Beck burst Beck burst Collapses Food & c.14:00 in village again in Clear Beck at Gillside c.16:00 Water c.20:00 village c.23:00 and reinforce bank Met Office Beckside c.19:00 Goldrill under landslips warning issued for construction Bridge burst Storm Desmond arrive from c.23:00 Hartsop c.14:00 Reinstate roads to Village Clean Up I Village Clean Up 2 Steamers and Sailing Centre Friday Sat Sun Mon Tues Wed Thurs Dec 4th Dec 5th Dec 6th Dec 7th Dec 8th Dec 9th Dec 10th Dredge Grisedale Beck from PHE to beck mouth External Water Cut Vodafone Off/ Landlines Vodafone Mast offline Contaminated External Clear beck and stabilise c.21:00 Offline c.17:00 Landlines Mast online Restored c.16:00 bank in Grisedale Valley Glenridding to Patterdale Road Flooded 22:00 (x2) A592 from A592 from the north the north inaccessible accessible Reinforce beck bank c.17:00 c.15:00 behind Lanefoot cottages A592 from A592 from the south the south Domestic Flood Impact inaccessible accessible Dredge beck at Cow c.17:00 c.07:00 At least 70 properties and businesses in the Parish directly affected by flood Bridge Hartsop 3.5 inches of 8 inches of damage – ranging from the catastrophic rain at rain at Gillside Gillside to the marginal. Some properties flooded Clear drains and culverts up to 3 times at Grisedale Bridge Community Flood Plan - Progress to Date

• Draft list of key issues and actions produced (Community Flood Plan version 5) • Website created (www.parishfloodgroup.org) • Discussions held with other communities with existing flood groups (Stockdalewath, Talybont) • Discussions held with National Flood Forum and request for assistance on resilience work made • Initial community meeting held 29th January at Patterdale School • Meeting held with EA, National Trust, LDNP, Eden Rivers Trust & Natural England to agree approach • Area Flood Group meetings held at Rookings (Patterdale), Grisedale Bridge and Glenridding • Regular attendance at Eden Flood Recovery Forum • Attendance at last Cumbria Flood Partnership (CFP) Meeting • Attendance at Upstream Water Mgt workshop of CFP • Ongoing negotiation with EA on Glenridding Beck Wall repair and Jenkins Field • Ongoing discussion with EDC on Jenkins Field • Ongoing discussions with LDNP on Car Park, TIC, Footpaths etc • Ongoing discussions with National Trust on repair work needed on NT Land and also on water management in other areas of the Dale • Ongoing discussions with Eden Rivers Trust on work • Ongoing discussions with EDC on flood recovery work, resilience grant applications, and potential funding • Ongoing discussions with CCC/Highways on drainage work, road repair and tree work • Ongoing discussions with landowners re: work required….. 6 Community Flood Plan – Key Issues • Inter-agency cooperation & communication – with each other and the community • Future of Jenkins Field • Timetable for repair of Glenridding Beck Wall • Funding for repairs not covered by insurance/resilience grants (eg Lanefoot) • DEFRA agreement on protection of HLS payments where flood protection work required upstream • Simple, single & speedy consent for beck work now and in the future • Funding for current project and future maintenance tasks

7 Future Planning – Some Possible Key Principles 1. Upstream in all the valleys - try and slow the flow, store overspill, and absorb as much as possible

2. Downstream keep the capacity levels high to allow quick outflow into the lake, and make sure the beck walls are high enough and strong enough

3. Downstream as a general rule trees on the bank are good (but should be pollarded), trees in the beck are bad

4. Remove gravel only at key laying points, to agreed levels, using agreed process at agreed times!

5. Regular clearance of all drains and culverts

6. Take control for maintenance locally where possible 8 Resilience Team

Team Leaders - Jon Holdsworth / Fra Cooke

9 Resilience Team Update 10

The dale is being divided up in to six designated flood areas. We hope to appoint two or more flood wardens to look after each area

The wardens will help set up and maintain systems for their specific area including: • Buddy system to look after vulnerable people • Cascade communication system to more easily disseminate information • Inspection regimes on water courses and paths to help monitor conditions, spot problems early, and recognise danger signs that can act as triggers (eg: beck height) • Action plans to follow in the event of a trigger point being reached • Helping organise and maintain equipment and locate strategically positioned storage for it

We are compiling a definitive inventory of emergency equipment that we’d like located in each flood area all-year-round

Communications resilience is being looked at by Graeme Connacher and Martin Butcher with the intention of setting up satellite links at key strategic locations. These will need generator back up and if anybody already has and maintains a generator and is willing to have satellite comms then please contact Graeme

We are compiling a list of emergency contacts, and looking in to how our flood plan can work alongside and actually help the police, EA, LDNPA, PMRA, HA etc

We are also compiling a list of contractors and key local people that can help in an emergency

We are looking in to the potential for a ‘Press Officer’ role to organise liaisons with the media better and make sure that the correct messages are sent out to maximise benefit and minimise impact on the dale

We are liaising with the Health Centre to see if we can help monitor, look after and distribute medicines to vulnerable people in the event of any emergency

We are liaising with businesses to see whether they are happy to be kept in our communication loop but to essentially ‘look after themselves’ and not need community support for any emergency preparations in a flood situation Resilience Plan – Some Ideas 11

Issue Cause Solution Responsibility

Loss of Mobile Phone Electricity outage at Glenridding Hotel where Have back up power source for the mast Graeme M and Martin B Signal mast is Loss of Landline Signal Pooley Bridge collapse Have separate comms from Mountain Rescue to Graeme M and Martin B the outside world Loss of water Pumping station underwater at Haweswater Ensure resilience at the pumping station and have United Utilities and supplies of bottled water Community Flood Group Loss of power General outage although not for long Ensure resilience and have generators in key points Community Flood Group Lack of Sandbags Council stretched and only delivered 30 on day 1 Ensure supply of sand and empty sandbags (plastic Community Flood not hessian) at key points Group Roads cut-off Underwater from Aira Force to Glenridding and See long term plan - empty culverts & drains on Highways and Council Glenridding to Patterdale regular basis No idea who to call Lack of information Emergency contact list for all residents - paper copy Community Flood in homes plus on web, list of vulnerable residents, Group designated helpers etc. Local command & control

No proper warning of Lack of agreed levels of beck, rainfall etc which Agree and monitor beck levels, rainfall levels and Community Flood impact are a "threat" define threat and action levels Group Homes & Businesses Lack of flood defences for most homes and Assist all home and business owners with most Community Flood unprotected villages effective way to spend their £5k flood prevention Group grant and pool where necessary Set up emergency supply centres at Glenridding Village Hall, Patterdale Mountain Rescue and Howe Green Farm Hartsop and appoint “Flood Marshalls” for maintenance of each. Equip with generator, fuel, sand, sandbags, water Upstream Team

Team Leader – Danny Teasdale

12 Upstream Team Update 13 Progress To Date

• Attendance at CFP Upstream Mitigation Workshop

• Discussions held with NT Geomorphologist

• Ongoing discussions with ERT on their involvement

• Visit arranged to Ennerdale for 29th Feb

Key Open Issues

• Need to pilot an upstream area – suggestion Deepdale

• Need confirmation from DEFRA that any upstream work will not impact existing HLS agreements Eden Rivers Trust Zoned Approach

14 Maintenance Team

Team Leaders – Carl Scrivens / Kevin Jackson

15 Maintenance Team Update 16

Progress To Date

• Ongoing work with Highways on road drain and culvert clearing

• Beck depths taken and levels set for Glenridding, Grisedale, Goldrill, Deepdale and Cow bridges

Key Open Issues

• Agreement on ongoing process and funding for maintenance work, including “Gravel Management” Beck Depths 17 Measurements taken by Carl Scrivens – 14th Feb 2016 Beck Depths 18 Measurements taken by Carl Scrivens – 14th Feb 2016

• 100mm of gravel deposited over a 3 day period from 20th -22nd Feb

• Need to agree the level at which we need to get in an actively “manage the gravel” again…. Property Flood Defence Team

Team Leaders – Paul Turner / Dennis Henderson

19 Property Flood Defence Team Update 20

Progress To Date

• Ongoing discussion with EDC regarding resilience grants

• Discussions held with residents of Grisedale and Deepdale on flood issues

Key Open Issues

• Eligibility Criteria for Resilience Grants to be made more flexible

• Alternative sources of funding for individual resilience work Hartsop Team

Team Leader – Robert Wear

21 Hartsop Team Update 22

Progress To Date

• NT Volunteer clean up of fields by Cow Bridge

• Plans drawn up for Hartsop Hall Farm repairs

• Initial meeting held for Howe Green Farm – draft recovery plan produced

Key Open Issues

• Solution to protection of Hartsop Road End and Cow Bridge Road

• Undermining of road beck bank down from Cow Bridge Hartsop Flood Issues - 1 23

# Location Where Landowner / Issue/Impact Cause Steps Already Taken Short Term Actions Maintenance Long Term Actions Responsibility Required 1Hartsop Hartsop Hall - Jimmy Hodgson/ Beck breaches and Volume of water and Clear debris rebuild Pollard tress on Caiston Beck National Trust debris in fields, debris in beck walls beck edge walls/fences down

2Hartsop Hartsop Hall - Jimmy Hodgson/ Beck infilled by Caudale Volume of water and Dig out beck channel, Monitor beck Caudale Beck National Trust Beck Farm and flowing debris in beck rebuild south side beck levels and clear through field wall, strengthen north as required. side beck wall with Pollard trees on cleared debris. Fence beck edge off beck banks

3Hartsop Hartsop Hall - Jimmy Hodgson/ Beck breaches and Volume of water and Clear debris rebuild Dovedale Beck National Trust debris in fields, debris in beck walls walls/fences down

4Hartsop Hartsop Hall - Jimmy Hodgson/ Beck breaches and Volume of water and Clear debris rebuild Pollard tress on Kirkstone Beck National Trust debris in fields, debris in beck walls clear channels. beck edge walls/fences down Fence beck banks

5Hartsop Harstop Hall - Jimmy Hodgson/ Bridge washed away Volume of water and Temporary bridge in Agree plans for bridge - Agree beck level Install Permanent Bridge Farm Bridge National Trust debris in beck place consider formalising and Clear under temporary bridge and bridge as removing old supports required to increase capacity under bridge

6Hartsop Hartsop Hall Jimmy Hodgson/ Gravel deposits in fields Clear debris and rebuild Farm National Trust and walls/fences gone walls

7Hartsop Hartsop Village Various Overflow into village Volume of Some limited Look at possible Agree correct - Hartsop Beck water/capacity of dredging above and dredging of beck beck depth and beck below Horsemans through village dredge as Bridge required Hartsop Flood Issues - 2 24 # Location Where Landowner / Issue/Impact Cause Steps Already Taken Short Term Actions Maintenance Long Term Actions Responsibility Required 8Hartsop Hartsop Road National Landslip and road Water from Hartsop Road repaired and Potentially create End Trust/Highways surface break up Beck hole filled overflow culvert by bus shelter and across/under roasd end road. Build wall around substation to protect it

9Hartsop Hartsop Road Highways Road closed due to Water from Hartsop Some limited Clear culverts under Solution to Hartsop volume of water Beck and from dredging on the the road. Aim to Beck and Brotherswater Hartsop Road end corner of Hartsop strengthen bank from from Road end to Cow Beck Horsemans bridge to Bridge - possible new Goldrill junction large scale culvert under the road

10Hartsop Packhorse National Trust Gravel/stone in beck Dredging of beck Agree correct Bridge to Cow reducing flow under between bridges beck depth and Bridge bridges dredge as required 11Hartsop Fields by Cow National Debris in fields, Water from Hartsop Volunteers have Clear Debris/Repairs Solution to Hartsop Bridge Trust/Wear Walls/fences down Beck/Brotherswater cleared debris into Walls & fences Beck and Brotherswater Family/Jackson bags from Road end to Cow Family Bridge

12Hartsop National Trust Greater flow of water Removal of dam has Consider reinstatement down Hartsop Beck caused greater flow of dam as catchment up of water down the valley or alternative Hartsop Beck methods to hold and slow the flow of water

65Hartsop Myers Head NT/Historic England Hayeswater Gill/Pasture Volume of water Water returned to Mine Beck confluence causing Hayeswater Hayeswater Gill created new channel Beck to change threatening the course monument

67Hartsop Goldrill Beck Highways/EA Beck has scoured Velocity of water Carry out inspection Pollard tress on Either shutter along north of Cow causing undermining of from cow bridge assess severity beck edge and beck wall bottom or Bridge bank under the road monitor beck infill with stones/gravel depth to protect it

13Hartsop Goldrill Beck at National Trust Beck breach causing Velocity of water Remove gravel in the Consider turning Goldrill gravel deposit in from cow bridge beck channel, scrape meadow into bunded Bottoms meadow field clear of debris and "overspill basin" using use to create bund gravel deposited around the field Hartsop Flood Issues 25

67

11 10

9 8 7

65 12

6

4 5

3

2 1 Hartsop Flood Issues 26

11 10 9 8

7 12

65

6

4 5

3

1 2 Hartsop Flood Photos 27 9 Courtesy of Di Wear 7

11

7 8

8 11 Deepdale Team

Team Leader – Chris Brown

28 Deepdale Team Update 29

Progress To Date

• Quotes received for work to repair Lanefoot Beck Bank

• New culverts installed on the road by Noran Bank Farm

• ERT/Outward Bound Volunteer work party on clean up at Deepdale Hall & Beckstones

Key Open Issues

• Funding for Lanefoot Beck repair work Deepdale to Patterdale Flood Issues

# Location Where Landowner / Issue/Impact Cause Steps Already Taken Short Term Actions Maintenance Long Term Actions Responsibility Required 14 Deepdale Lane Foot Various Beck wall collapse, Volume of water, Dredging of beck Remove trees from in Agree correct Rebuild beck wall and Cottages and gardens lost, houses stone/gravel in beck and build up of the beck on Manor beck depth and reinstate gardens Deepdale flooded and trees in the beck banks to protect Barn side dredge as Bridge on the opposite bank houses and gardens required. Pollard trees

15 Deepdale Fields below Deepdale Hall Fences down and gravel Volume of water Fences reinstated Clear Gravel from Lanefoot in fields fields 16 Noran Bank Noran Bank Jackson Family Trees in beck Clear trees Farm 17 Green Bank Green Bank Iredale Family Trees in beck Clear trees Farm 18 Noran Bank Road between Highways Landslip Landslip cleared, Regular clearing Fill the holes and Noran Bank culvert cleared, new of culvert and stabilise the bank and Greenbank drains installed drain

21 Patterdale Beckstones National Trust/Side Gravel in fields, debris Farm in beck

30 Deepdale to Patterdale Flood Issues

21

18

16

17

15

14

13 31 Deepdale Flood Issues

21

18

17

16

15

14

13 32 Deepdale Flood Photos Courtesy of Di Wear & Rob Shephard

18

14

14

14

33 Patterdale Team

Team Leader – Kevin Jackson

34 Patterdale Team Update 35 Progress To Date

• Rookings Flood Group Established

• New field drain being installed opposite Wordsworth Cottage

• ERT/Outward Bound workparty at Rookings, Side Farm, Crookabeck, Beckstones

• Footpath at foot of sorted (Phase 1) Key Open Issues

• Stability of landslips on Place Fell

• Removal of trees in the beck by Goldrill Cottage

• Agreement on downstream management of Goldrill Beck

• Getting residents back into Rooking Cottage! Patterdale Flood Issues 36 # Location Where Landowner / Issue/Impact Cause Steps Already Taken Short Term Actions Maintenance Long Term Actions Responsibility Required 19Patterdale upstream of Goldrill Cottage/Old Erosion of bank with Trees in beck on Goldrill Remove trees from the Goldrill Bridge Water View potential to undermine Cottage side causing beck on Goldrill cottage wall and road water to flow into side. Residents to instruct opposite beck bank solicitor to resolve ownership issue of the beck 20Patterdale Goldrill Bridge Highways Road surface broken up Volume of water Road repaired Clear trees and debris Consider "overflow" route overflowing from Goldrill around bridge from through Goldrill cottage Beck Goldrill Cottage. Consider garden - so rather than dredging of beck either rebuild the wall by the side of the bridge bridge build a fence instead to allow water through

22Patterdale Crookabeck Crookabeck Gravel in fields, debris in beck 23Patterdale Path to Blowick NT/LDNP Path washed away Path filled in with material from Jenkins Field 24Patterdale Side Farm by National Trust/Side Fences down and gravel in Goldrill Beck breach Clear debris and reinstate Goldrill Beck Farm fields fences. Consider dredge of Goldrill Beck 25Patterdale Place Fell Dalemain Estate 2 major landslips causing Destabilisation of fell Debris cleared, culvert Complete survey of mud/debris to cover road cleared landslips. Reinstate up to Rookings and into footbridge over path at gardens of Place Fell the base of Place Fell. Cottage, GreenRigg and Clear debris from Broad Broad How. Also footpath How washed away

26Patterdale Rookings Various Blocked culverts & drains Blocked culverts/drains Culverts cleared. New Clear Culverts. caused flooding in Rooking and volume of water drain being installed in Cottage and washed road front of Wordsworth surface to Crookabeck cottage

66Patterdale Rookings Various Several overspills and flow Build up of stones, Ghyll bed and culverts Continue to keep Increase capacity where diversions depositing many blockages and force of cleared of debris. Ghyll clear. necessary, consider relief tons of stones/gravel water flow. channels. across properties, ground erosion and some water ingress to homes.

27Patterdale Between White Highways Significant flooding on the Blocked culverts/drains Drain cleared Regular clearing of Lion and Goldrill road and volume of water drain Bridge 28Patterdale In front of Highways Road flooding due to Volume of water from Some minor dredging Consider further clearance Patterdale Hotel volume of water behind Patterdale Hotel behind the hotel of becks around Mill Moss 29Patterdale Home Farm Patterdale Hall Estate Overflow of beck leading to Volume of water and Beck dredged and bank debris into KGV capacity issue in beck built up Grisedale Team

Team Leader – James Sowerby

37 Grisedale Team Update 38

Progress To Date

• Grisedale Bridge Flood meeting held

• Need for Tree work on Oak Tree above Close Cottage agreed with Highways

Key Open Issues

• Gravel deposits below Grisedale Bridge and scouring of beck wall to Goldrill Bridge, which is in danger of undermining.

• Clean up work up the valley at Braesteads (possible volunteer work party) Grisedale Flood Issues 39

# Location Where Landowner / Issue/Impact Cause Steps Already Taken Short Term Actions Maintenance Long Term Actions Responsibility Required 30Patterdale Church Corner Various Road flooded, flooding to Blocked culverts/drains Clear culvert all the way Clear Culverts. Church, Rectory and and volume of water to the road from Decollage Grisedale Beck

31Patterdale Braesteads Farm Matson Ground Landslips beyond Eagle Estate Cottage 32Patterdale Braesteads Farm Matson Ground Blocked Field Drains Estate 33Patterdale Grisedale Beck Patterdale Hall Kennel Bridge road Rebuild road surface Estate scoured 34Patterdale Grisedale Beck - Patterdale Hall Landslip and trees in Trees cleared and Ongoing tree close to Kennels Estate beck beck wall stabilised management in short term Patterdale Hall Estate and bank stabilisation strategy 35Patterdale Grisedale Beck - Patterdale Hall Landslip and trees in Trees cleared and Oak tree on bank to be Ongoing tree above Close Estate beck - potential threat of beck wall stabilised pollarded from road side management in Cottage road being undermined short term Patterdale Hall Estate and bank stabilisation strategy 36Patterdale Grisedale Beck Patterdale Hall Major beck breach, with Volume of water and Beck dredging either Ongoing tree by caravan park Estate beck bank destruction tree stumps being side of the bridge and management in and road surface stored which tore up rebuilding of beck Patterdale Hall Estate destruction outside the road surface bank and bank stabilisation Patterdale Hall and strategy. flooding of properties in Patterdale Hall Estate 37Grisedale Grisedale Bridge Various Grisedale Beck breach on Volume of water and Beck dredged and Agree correct Bridge both sides causing debris in the beck bank built up by beck depth and flooding of Grisedale Mountain Rescue dredge as Bridge properties, base required Mountain Rescue Base and Fire station 38Grisedale Church Flats Various Debris in fields, and Volume of Beck Dredged Remove debris from Agree correct Bridge Field water backing up causing water/debris in beck side of beck - gravel and beck depth and secondary flooding to reducing capacity trees dredge as properties at Grisedale required Bridge 39Glenridding A592 between Highways Lake overspill onto the Volume of water in the Debris cleared from & Patterdale Glenridding and road leading to road lake the lake Patterdale closure for 2 days Patterdale & Grisedale Flood Issues 40 23 39

37 38 25 30 36

26

35 29 24 28 20 27

34 19

33

31 32 22 Patterdale & Grisedale Flood Issues

39 23

38 37 25 36 30 29 26

35 28 27 24 20 34 33 19

22

32

31

41 Patterdale & Grisedale Flood Photos Courtesy Rob Shephard

25

35 20

39

25

25

36

42 Glenridding Team

Team Leader – Steve Sykes

43 Glenridding Team Update 44 Progress To Date

• Team meeting held

• Ongoing discussions with EA/LDNP/EDC on beck wall repairs and Jenkins Field

• Repair of Rattlebeck bridge started & work continues on Gillside Beck repairs

• “Help Glenridding Spring Back into Action” campaign launched

Key Open Issues

• Glenridding Beck Wall repair – nature and timetable

• Road to Village Hall – drainage and resurfacing

• Jenkins Field Plans

• Complete Gillside Beck repairs Glenridding Flood Issues - 1 45

# Location Where Landowner / Issue/Impact Cause Steps Already Taken Short Term Actions Maintenance Long Term Actions Responsibility Required 40Glenridding Jenkins Field Council Major erosion caused by Glenridding beck and Material removed for Confirm EA test results on Agree long term plan for overflow of lake and overflows local rebuild projects debris. Continue using relandscaping of Jenkins Glenridding Beck. Also now material locally as required field to include overspill has 20k tons of material on parking and overflow it from the beck dredging channel 42Glenridding Steamer Road Eden District Council Glenridding Beck overflow Glenridding Beck Road cleared and Rebuild beck wall where Retarmac road on agreed caused road to be washed overflow reinstated temporarily breached route as part of Jenkins away Field discussions. Consider overflow channel through Jenkins field for Glenridding Beck 43Glenridding Steamer Pier Ullswater Steamers Major damage to Steamer Glenridding Beck Remedial repair work Complete repair work Regular clearing of pier and facilities overflow and Lake completed beck mouth by lake overflow 44Glenridding Sailing Centre Sailing Centre Track washed away Glenridding Beck Track reinstated Regular clearing of Track overflow beck mouth by lake

45Glenridding Sailing Centre Sailing Centre Major damage to sailing Glenridding Beck Muck cleared and work Complete repair work centre ground and facilities overflow and Lake underway to rebuild overflow facilities 46Glenridding Glenridding Beck EA Catastrophic overflow by Glenridding beck Volume Trees cleared from Rebuild beck walls Agree correct beck As part of the beck wall from Village Hall Village Hall and behind the of water and material in under bridge on day 1, depth and dredge rebuild create ramps either to Bridge TIC and trees under bridge Glenridding Beck significant and repeated as required side of Glenridding Bridge dredging of beck, shoring and consider an overflow up of beck bank with channel on the north side of dumpy bags the bridge. Ensure beck wall on south side of sufficient height and goes up past the village hall. Consider raising bridge?? 47Glenridding Glenridding Hotel Glenridding Hotel Catastrophic Flooding of Glenridding Beck Debris cleared - Complete repair work to Hotel basement, kitchen, overflow insurance team on with include tanking Ratchers Bar the rebuild cellar/kitchen area and new pumps. Repair beck wall by beer garden 48Glenridding Road to village Highways Road washed away by Glenridding Beck Debris cleared, drains Reinstate drains. Resurface Hall material from Glenridding overflow cleared road before beck wall Beck, drains blocked and being rebuilt due to time broken proposed 49Glenridding Village Hall Village Hall Committee Significant flooding to hall Glenridding Beck Debris cleared. Oil tank Build retaining wall around and caretakers cottage - oil overflow reinstated Oil Tank. Resurface track tank washed away behind hall 50Glenridding Tourist LDNP Beck breached at the top of Glenridding Beck Some of debris cleared. Based on results of Information TIC and washed debris into overflow TIC blocked off. Survey structural survey decide on Centre it. Beck wall undermined to undertaken future of the TIC - rebuild, the side of it move Glenridding Flood Issues - 2 46

# Location Where Landowner / Issue/Impact Cause Steps Already Taken Short Term Actions Maintenance Long Term Actions Responsibility Required 51Glenridding Glenridding Car EDC/Parish Council Recycling centre Glenridding Beck Cordoned off Rebuild beck bank Park Recycling damaged by flood - overflow under the TIC and then Centre needs rebuilding rebuild the recycling centre

52Glenridding Glenridding United Utilities Undermining of beck Glenridding Beck Beck bank Rebuild beck bank and Sewage bank by the Treatment overflow strengthened strengthen against Treatment Plant Plant future flooding

53Glenridding Footpath to LDNP Undermining of beck Glenridding Beck Beck bank Further rebuild of beck Gillside Farm bank by footpath strengthened bank wall 54Glenridding Gillside LDNP/Gillside Major landslip by Glenridding Beck Beck bank wall Complete beck bank Campsite campsite destroying rebuild started and rebuild and then infill Footpath footpath beck cleared landslip

55Glenridding Wallbank EA/Gillside Major landslip below Glenridding Beck Beck bank stabilised Plan scheme for formal Rebuild beck wall and Wallbank short term and beck reinstatement of beck infill landslip and work dredged wall under wall bank on stabilisation of the (EA) bank

56Glenridding Rattlebeck LDNP/Gillside Severe undermining of Glenridding Beck Stabilise bridge with Bridge Gillside the bridge stone/concrete Farm

57Glenridding Gillside Caravan Gillside Beck bank collapse Glenridding Beck beck cleared and bank Park strengthened 58Glenridding Glenridding Highways Flooding of both the Blocked/Inadequate Review drains and Regular clearance Garage and garage and Glenridding drainage off the road culverts including ones of drains and Glenridding house grounds at the foot of Hollin culverts House Bush Lane

66Glenridding Barraclough Various Beck breach caused Beck Overflow Consider need for Fold some flooding in houses clearing beck and raising bank height

68Glenridding Hollin Bush Highways Culvert under road Debris washed down Clear culvert and Regular clearance Corner blocked replace pipes as of drains and required culverts Greenside/Glencoyne Teams

Team Leaders – Suzy Hankin/Steve Dowson

47 Greenside/Glencoyne Team Update 48 Progress To Date

• Glencoyne – Discussions held with residents of Seldom Seen

• Greenside – update received on all required LDNP repairs – central funding request submitted

• Statement made on stability of Tailings above Greenside

Key Open Issues

• Confirmation of LDNP funding for repair work Greenside/Glencoyne Flood Issues 49 # Location Where Landowner / Issue/Impact Cause Steps Already Taken Short Term Actions Maintenance Long Term Actions Responsibility Required 59Glenridding Greenside LDNP Major scouring of the Water flow Patch repairs completed. Finish with more solid top Regular cleanrace of LDNP looking to ideally Bridlepath Bridlepath layer drains. Patch surface increase the length of concrete where necessary and improve the drainage in places. This is a long term aim and subject to funding. 73Glenridding Greenside - Tailings LDNP/Coal Board Working with the Coal Authority the LDNP have a capital works programme to ensure the long term sustainability of the tailings dams. There is a capital budget allocated to Dams repair/replace the main open drain at the top of tailings dam 1, the tailings dam on the East. This is scheduled to be completed this year, and will involve engagement with residents and parish council to outline the works up there. Our work with the Coal Authority includes quarterly reviews and inspections of the whole site.

60Glenridding Greenside - Swarth LDNP Beck wall collapse by Striding Water flow Swarth Beck was inspected Repair beck wall and carry out Beck and bridge Edge Hostel by a structural engineer upstreams reapirs subject to and deemed safe for use. LDNP funding Some advisory comments were made about the hole on the downstream side and the upstream abutments 70Glenridding Public Bridleway LDNP Damage to footpath and Water flow Whilst there is surface damaged in places the track up to Kepple Cove dam is accessible for quads and 4x4. The from Greenside bridges bridge over Rowten Beck will be replaced hopefully in the next 18 months, with a wider bridge allowing greater Mine to Kepple capacity beneath. The zig zags along the bridleway up Keppel Cove towards has had some path surface Cove loss. This will need a skilled digger operator to repair and potentially some materials importing. This has been costed into our flood recovery bid and will prioritised accordingly. The track up to Kepple Cove dam needs some maintenance work which will be prioritised in our work programme. 71Glenridding Public footpath from LDNP This is OK. One of the footbridges over Red Tarn Beck has been damaged, but is safe and passable for walkers. Greenside Mine to Repaire and improvements have been costed in our recovery bid. Red Tarn 72Glenridding Glenridding LDNP Landslides, footpath erosion Glenridding Common is owned by the National Park and we work with the graziers (Peter Iredale & Common Mary Lightfoot) to manage the land. Currently, the common is managed as part of a 10 year HLS agri- environmental agreement. This started in May 2013 and involved the owner (LDNP) completing capital works such as fencing and tree planting and the graziers to sheep numbers and grazing management plans.

Certainly the Glenridding Common forms the majority land of the catchment for Glenridding Beck, and potentially offers significant opportunities for catjhment management. We will need to work with our partners, graziers and the local community to identify opportunities and seek funding.

There are 3 main landslides (I know of) 2 near Red Tarn Beck beneath Catstye Cam and 1 beneath Kepple Cove. As neither have caused any damage to the paths nearby, at this time we are unlikely to do anything there, but future management of the Common might dictate otherwise.

61Glenridding Greenside Hydro United Utilities Hydro dam filled with debris, Some debris removed, Complete debris removal Plant water cut off from properties water supply restored at Greenside 69Glencoyne Seldom Seen Various Flood damage Flooding due to blocked Clear two culverts - one NT Regular clearance of culverts one Highways drains and culverts 63Glencoyne Glencoyne Beck by National Trust Beck filled with gravel causing Beck dredged by bridge Review beck further up Agree correct beck Car Park flooding of fields and road next to Car Park towards the farm to see if depth and dredge as further clearance work required required. 64Ullswater A592 Highways et al Road closed due to volume of Ullswater levels Debris cleared Clear drains and culverts. Regular clearance of Consider ability to pump down water, debris on road, Consider new ones where drains and culverts lake water level when required collapsed walls on roadside required. Glenridding/Greenside/Glencoyne Flood Issues 64

63

60

62

61

59 58

45

66 44 57 43 51 50 46 42 56 55 49 48 54 47 52 53 40

41 50 Glenridding/Greenside/Glencoyne Flood Issues

59

58

45

66

44 57 43

52 50 46 55 49 42 48 56 51 47 54 40 53

41

51 Glenridding Flood Photos Courtesy of Charlene Bell and Rob Shephard

46 46

43 45

46 47

47

40

55 45 60

52