Prefeasibility Report For Environment Clearance from MOEF under EIA Notification Dated 14th September, 2006 as Amended Pre - Feasibility Report For Darritola Ordinary Stone Temporary Permit Quarry at Village - Darritola Tehsil- & District- Koriya, State- . 1. SUMMARY Project - Darritola Ordinary Stone Temporary Permit Quarry Name of Company/Mine - M/s. NSPR - PLR Joint Venture Location: Village - Darritola Tehsil/Taluka - Manendragarh District - Koriya State - Chhattisgarh 1. Temp. Permited Area & Type of Land - 1 hect./ Government Land 2. Geographical Co-ordinates BOUNDRY POINT LATITUDE LONGITUDE BL1 23°16'48.84"N 82°22'37.43"E - BL2 23°16'49.17"N 82°22'40.39"E BL3 23°16'45.36"N 82°22'40.74"E BL4 23°16'45.16"N 82°22'37.71"E 3. Name of River/ Nallahs /Tanks /Spring - River - 6.80 km ( at west) / Lakes etc. Nalla - 420 m Halphall Nalla towards north Tanks - 1.20 km Pond towards north Canal - 1.40 km Canal towards south near Keradol village area Reservoir - 2.00 km Reservior towards south near Keradol village area 4. Name of Reserve Forest(s), Wild Life - Forest boundary is more than 250 m away from the lease Sanctuary/National Park area. However, NOC from DFO Manendragarh is obtained and enclosed. 5. Topography of the area - Hilly Land devoid of vegitation Altitude - Max. 590 aMSL and Min. 581 aMSL Surface slope - Towards North Toposheet No.- 64I/7 6. Project Proposal - Scientific mining of Ordinary Stone for proposed capacity of maximum 143305.7 MT per year. 7. Name of Mineral Mined - Ordinary Stone (Minor Mineral) 8. Rate of Production (in tons) - Maximum 143305.7 MT/year 9. Mineral Reserve (in tons) - Geological Reserve (from the normal surface level till 6m depth)-297585.57tons. Recoverable Reserve (from the normal surface level till 6m depth) - 148306.73 tons. 10. Life of Mine - 2 years for the excavation of recoverable reserve of 148306.73 MT 11. Drilling/Blasting - yes - Jack hammer drill / low capacity scientific controlled blast is proposed to be conducted.

Signature of Project Proponent ______2 Pre - Feasibility Report For Darritola Ordinary Stone Temporary Permit Quarry at Village - Darritola Tehsil- Manendragarh & District- Koriya, State- Chhattisgarh. 12. Mining Method - Open Cast Semi Mechanized 13. Ground Water table Intersection - Below 30 meter from surface level 14. Drainage Pattern/ Water Courses - Natural drainage towards North 15. Break-up of Land Utilization Pattern - 1. Total Lease Area 1 Hect. 2. Area proposed under mining pits 0.72 Hect. 3. Area covered by statuary/mine boundary 0.28 Hect. 4 Area for road 0 Hect. 5 Area covered by crusher 0 Hect. 6 Area Kept for storage of stone 0 Hect. 7 Unused Area within Lease area 0 Hect. Total Area (2+3+4+5+6) = 1 Hect. Dumping Area proposed within proposed 8 0.17 Hect. Statutory/mine Boundary Plantation Area proposed over the dump 9 0.17 Hect. on dumping area No Activity Zone on Mine Boundary as per 10 0.11 Hect. MMR 1961 16. Water Requirement & Source - Requirement - 10 kilo litre per day, Source - Mine pit/Setting tank, dug well and tube well of nearby village within permited limits. 17. Solid waste/Tailings - Top Soil & OB - total 3580.35 cum (Maximum yearly generation @ 3580.35 cum). 18. IBM approval: Date - Not Applicable 19. Cost of Project (Rs. Lacs) - Rs. 13 lacs 20. Any Other (Specify) - NIL Name and Address of the company / M/s. NSPR - PLR Joint Venture Proponent Registered office M/s. NSPR - PLR Joint Venture Village/Post - Baikunthpur Tehsil - Baikunthpur District - Koriya State - Chhattisgarh Mine Office Village - Darritola E-Mail Nil Prospecting Agency Not Applicable Type of Activity Open Cast Semi Mechanized Ordinary Stone Quarry Mining

Utilities (Power, Water Requirement) Power - 5 HP . Water – 10 KLD for Domestic, Dust Suppression & Plantation Purpose Manpower requirement 35 workers per day

Signature of Project Proponent ______3 Pre - Feasibility Report For Darritola Ordinary Stone Temporary Permit Quarry at Village - Darritola Tehsil- Manendragarh & District- Koriya, State- Chhattisgarh. 2. INTRODUCTION OF PROJECT/BACK INFORMATION Proposed Ordinary Stone Deposit is located at village Darritola, Tehsil Manendragarh, District Koriya and state Chhattisgarh over an area of 1 ha. The proposed capacity of the project is maximum 143305.7 tones/annum. Proposed land is Government non forest revenue land. Open Cast Semi Mechanized with low level intensity scientific controlled blasting method of mining is the most suitable mining procedure for this mine. This method of mining is used for highest productivity and the lowest cost of any of the broadly used mining methods Brief description of the project is described below –

(i) Identification of Project and Project Proponent (a) Name of the Project: Darritola Ordinary Stone Temporary Permit Quarry (b) Project Proponent : M/s. NSPR - PLR Joint Venture (c) Postal /Correspondence Address of Project Proponent: M/s. NSPR - PLR Joint Venture

8-2-120/86/5-B, 2nd Floor, Sneha House, Banjara Hills, Road No. 3, Hyderabad 500034

H.No.- 63, MLA Colony, Near Koriya Palace Village/Post - Baikunthpur Tehsil - Baikunthpur District - Koriya State - Chhattisgarh (ii) Brief Description of Nature of the Project The proposed project is mining activity of Ordinary Stone (Minor Mineral) with the name of 'Darritola Ordinary Stone Temporary Permit Quarry ' which is situated at Khasra no. 199/1 (P) at village Darritola, tehsil Manendragarh and district Koriya (C.G.). This site is 18.00 km away from district office Koriya. The LOI for permit of Ordinary Stone mining has been sanctioned for 2 Years to project proponent M/s. NSPR - PLR Joint Venture of Baikunthpur district Koriya (C.G.). The granted temp. permit area is on 1 hect. land for the proposed maximum production capacity of 143305.7 t. per annum. The excavation of Ordinary Stone will be done by Open Cast Semi Mechanized method with low level intensity scientific controlled blasting.

Letter of Intent for sanction of T.P. has been granted by collectorate mining branch vide letter No. 2842/Khanij/Asthayi Anugya Patra/2018/Koriya, Baikunthpur, Dated 11/01/2018. For compliance of Rule 24 and 63 to 66 of MMR 2015 proponent was submitted T.P. quarry plan before mining authorities and the plan so submitted has been duly approved by the sanctioning authority vide letter no. 235/Khanij/2018, Surajpur Dated 07/02/2018.

Signature of Project Proponent ______4 Pre - Feasibility Report For Darritola Ordinary Stone Temporary Permit Quarry at Village - Darritola Tehsil- Manendragarh & District- Koriya, State- Chhattisgarh. The proposed project is < 5 hect. Minor mineral and non-coal mining project thus it is classified as “CATEGORY – B2” project under activity 1(a) of the schedule of EIA notification dated 14th September 2006 as amended by Ministry of Environment, Forests and Climate Change, New Delhi by S.O. 141(E) dated 15 January 2016, hence it comes under jurisdiction of DEIAA.

Therefore application is being filed before jurisdictional DEIAA of district Koriya for getting permanent environmental clearance before starting of mining activity on granted temp. permit area. All the other necessary permission and noc’s has been taken by the proponent. Consent to establish & operate/Air/Water clearances from CGCECB will also be taken if instructed by jurisdictional DEIAA. (iii) Need for the Project and its Importance to the Country and/or Region Mineral resources of any country are the “TREASURE-TROVE” of its national economy; Chhattisgarh is one of the richest states in the country with its sparkling mineral wealth. The Chhattisgarh State has enormous reserves of stone & its variety of varies grades spread over mainly in , Mungeli, , Balodabazar-Bhatapara, Janjgir-Champa, , , Korba and Bilaspur districts. Stone is basic material for civil building & civil construction works. The project shall also provide additional revenue to State Government and create direct and indirect employment opportunities, which will catalyze overall growth of the State and improve the quality of life of the people living in the region and transform the region’s economy from predominantly agricultural to significantly industrial and accelerate the pace of regional development of region. There is huge demand of stone chip in the region as well as throughout country for the use in construction of House, Canal, Dam, Pachri and other infrastructure etc.

(iv) Demand - Supply Gap Stone Chip is basic raw material of civil construction works likes building, dams, roads, etc. for construction of walls/base. Proponent has a government order to construct concreet road. The contract requirs stone chip and boulders for the road construction. (v) Demand - Supply Analysis Exploiting this Ordinary Stone deposit the proponent will get sufficient stone for fulfilment of his Govt. contract work . Therefore, a ready use is available for the proposed project hence looking to the use of Ordinary Stone boulders which exist a good scope for the proposed project. (vi) Employment Generation (direct and indirect) due to the Project Labors will be required for various purposes like excavation of stone and loading of stone in various vehicle, management, maintenance & development of mine, making & maintenance of ramp, transportation of material and book keeping. Experienced personals will be employed as per the requirement.

Signature of Project Proponent ______5 Pre - Feasibility Report For Darritola Ordinary Stone Temporary Permit Quarry at Village - Darritola Tehsil- Manendragarh & District- Koriya, State- Chhattisgarh. The mining establishment presents opportunities of employment to various posts under various cedars viz. supervisory, skilled workmen, semiskilled workmen and unskilled workmen beside casual workmen. However the maximum required labours at the site to justify the production of stone at applied land are detailed below- a) Direct Employment Taking standard O.M.S. to be one the strength of labour, a labour can work for 15 tons of mineral in one sift of 8 hours a day. Considering this parameter the manpower need for project is –

S.N. Particulars No of Workers 1 Permit Manager 1 2 Mining Mate 1 3 Chowkidars 1 4 Skilled labours 32 Total 35 b) Indirect employment - Driver, cleaner for loader & dumper are the points were labors are required. Moreover, manager, accountants will also be appointed as per need. 3. PROJECT DESCRIPTION (i) Type of Project (Including interlinked and interdependent projects, if any): The proposed project is < 5 hect. Minor mineral and non-coal mining project thus it is classified as “CATEGORY – B2” project under activity 1(a) of the schedule of EIA notification dated 14th September 2006 as amended by Ministry of Environment, Forests and Climate Change, New Delhi by S.O. 141(E) dated 15 January 2016, hence it comes under jurisdiction of DEIAA.

(ii) Location (map showing general location, specific location, and project boundary & project site layout) with coordinates. The details of the temp. permit area are as under: District / State Koriya / Chhattisgarh Tehsil Manendragarh Village Darritola Area(ha) 1 The Coordinates of the area are: BOUNDARY LATITUDE LONGITUDE POINT BL1 23°16'48.84"N 82°22'37.43"E BL2 23°16'49.17"N 82°22'40.39"E BL3 23°16'45.36"N 82°22'40.74"E BL4 23°16'45.16"N 82°22'37.71"E

Signature of Project Proponent ______6 Pre - Feasibility Report For Darritola Ordinary Stone Temporary Permit Quarry at Village - Darritola Tehsil- Manendragarh & District- Koriya, State- Chhattisgarh. The site can be depicted in the toposheet number 64I/7 of Survey of . Study area map in Khasra map, toposheet and site specific surface map is attached as Plate-1, Plate -2 and Plate -4 of enclosed mine plan respectively. (iii) Details of alternate sites considered and the basis of selecting the proposed site, particularly the environmental considerations gone into should be highlighted: It is naturally occurring rocks which is site specific due to its geological origin. Mining is site specific project. This temp. permit is being granted by the state govt., hence alternative site is not applicable. (iv) Size or Magnitude of Operation: The total applied temp. permit area is 1 hectare and total proposed maximum production capacity will be 143305.7 TPA through Open Cast Semi Mechanized method of mining with low level intensity scientific controlled blasting. Proposed production details during temp. permit period are shown in below - Production During Plan Period Year Stone (ROM) Top Soil & OB Waste in Stone in tonne in cum in cum 1st Year 143305.70 3580.35 5897.35 2nd Year 5001.01 - 205.8 Total 148306.71 t 3580.35 cum 6103.15 cum (v) Project description with process details (a schematic diagram/flow chart showing the project layout, components of the project etc. should be given)- - It is proposed to carry out mining operation Open Cast Semi Mechanized method. The development has been proposed for systematic and scientific mining. - The excavation activity will be carried out till the depth of 6 m below general ground level or occurrence of ground water table at the site which ever encountered earlier. - 7.5 boundary will be left from the temp. permit area boundary around 4 sides (N, E, S, W) as barrier for safety provisions, dumping of top soil & OB and afforestation. The quarry will be worked in 2 benches below the normal surface and 3 layers above the normal surface of 3m height x 3 m width in total but during advancement of mining the mine will be worked into 1.5m x 1.5 m sub-benches. But at the final stage of mining the benches will be of 3m x 3m each as detailed in table below- Bench Number Bench Specification Bench Height Bench Width along the periphery of mine

1st Quarry Layer Soil + Stone Layer - 1 3.00 m 3.00 m 2nd Quarry Layer Soil + Stone Layer - 2 3.00 m 3.00 m 3rd Quarry Layer Soil + Stone Layer - 3 3.00 m 3.00 m 1st Quarry Bench Stone Bench - 1 3.00 m 3.00 m 2nd Quarry Bench Stone Bench - 2 3.00 m -

Signature of Project Proponent ______7 Pre - Feasibility Report For Darritola Ordinary Stone Temporary Permit Quarry at Village - Darritola Tehsil- Manendragarh & District- Koriya, State- Chhattisgarh.

- Overall bench slope will be less than 450 with the horizontal. - Adequate slope and water sump will be gradually developed at the working pit. Various deduction in lease area were considered while measuring to arrive the " benchwise available area for mining" i.e. Area occupied for maintaining statutory boundary. - Large size of stone boulders will be manually sized in to 10 to 12 inches as per the demand. - Loading will be done manually or with the help of excavator and J.C.B and the transporting will be done by 4.5 tones tractor or 10 tones tippers. Flow chart of the Project Removal of Overburden & Top Soil

Drilling

Controlled Blasting

Resizing of stone manually

Loading by Excavator or Manually

Transportation by Tractor or Tipper Drilling & Blasting Low level intensity scientific and controlled blasting is proposed to be carried out for production of Ordinary Stone. No deep hole drilling & blasting will be done. Drilling: Drilling will be done initially with hand holes and later with the help of jack hammer and compressed air. Machines specification is given below- Drilling and blasting pattern will be d x b x s =depth 3.0 m x Burden 1.1 m x Spacing 1.2 m Drilling equipment’s to be deployed is as under- Type No Dia of Size/capacity Make Motive Power hole Compressor 2 32 mm 210CFM Atlas Copco Diesel Jack Hammer 2 32 mm Blasting: Low level intencity, scientific and controlled blasting will be done. The Small blast hole will be charged with explosives. Details of blasting parameters & blast impact and control measure are discussed below-

Signature of Project Proponent ______8 Pre - Feasibility Report For Darritola Ordinary Stone Temporary Permit Quarry at Village - Darritola Tehsil- Manendragarh & District- Koriya, State- Chhattisgarh. Broad Blasting Parameters : Blast pattern d x b x s =depth 3.0 m x Burden 1.1 m x Spacing 1.2 m Dia. of the hole 32 mm Powder Factor 4-5 ton per kg Total Production 143305.70 Daily Production 477.69 tons Tonnage per blast hole 5.35 MT Total Blast Hole per day 90 Drill Meterage 270 m Type of explosive: Special Gelatin Ordinary Detonator Safety Fuse Storage of Explosives : The blasting will be conducted on the contract basis through approved blasting contractor, therefore no need to install magazine at quarry site. (vi) Raw material/consumables required along with estimated quantity, likely source, marketing area of final products/s, Mode of transport of raw Material and Finished Product.

No raw material is required for the mining of Ordinary Stone. Marketing area: Ordinary Stone will be used in form of stone chips as building material in civil constructions activity. The excavated mineral will be transported to the destination by tipper/dumper/trucks and broken Ordinary Stone will be loaded manually or by loaders. (vii) Availability of Water, its source, Energy/power requirement and source should be given -

Water Requirement: It is expected that the total water need is about 10 kilo litter per day in the mine. The details of water balance of existing / proposed mining project are given below: Water Balance of Project Process Total (KLD- Kilo Litter Per Day) Mine Site Dust Suppression 6.00 KLD Green Belt 1.90 KLD Domestic Sanitation & Drinking 2.10 KLD Total 10.00 KLD

Signature of Project Proponent ______9 Pre - Feasibility Report For Darritola Ordinary Stone Temporary Permit Quarry at Village - Darritola Tehsil- Manendragarh & District- Koriya, State- Chhattisgarh. Sources of water: I) For Green belt and dust suppression: Water will be made available from quarry mine pit which is accumulated during the rainy season and shall be collected in settling tank for utilization in green belt and dust suppression. However, if required, water might be supplied from tube well.

II) Domestic usage: Water might be supplied from tube well. Energy & Power Requirement and Source A) Fossil Fuels : Fuel is to be used in form of diesel for mining operations, compressors and running of tractors and other transportation vehicles. Quantity for fuel will depend upon the usage of transportation vehicle and other machineries and level of achievement of estimated production. Diesel will be outsourced from nearby diesel pumps.

B) Electricity : Electricity will be required for Pumping of water and for administrative building & rest shelters. The requirement of Power is estimated as under- S.N. Particulars Power 1 Domestic Purpose requirement5 HP

C) Source of Electricity: The power requirement for the project will be met by electricity lines of Chhattisgarh State Power Distribution Copany Limited available at village or nearby site area. (viii) Quantity of wastes to be generated (liquid and solid) and scheme for their management/disposal – Solid Waste: a) Top Soil & overburden: Top soil & OB. 3580.35 cum will be generated in total at the rate of maximum 3580.35 cum per year for period of approved mine plan. b) Mining Loss or Unusefull Waste Material: All ROM mineral is useful and saleable. 6103.15 cum material may be generated or could not be recovered as unusefull waste material or mining loss respectivelly during the plan period. c) Sub grade material: No sub-grade mineral will be generated during excavation of stone. All ROM mineral will be used.

Liquid Effluent: Only domestic effluent is expected to be generated which will be treated through septic tank followed by soak pits.

Signature of Project Proponent ______10 Pre - Feasibility Report For Darritola Ordinary Stone Temporary Permit Quarry at Village - Darritola Tehsil- Manendragarh & District- Koriya, State- Chhattisgarh. Selection of Dumping Site: a) Top Soil & overburden: Whatsoever quantity of top soil and overburden generated during the quarrying operation will be stacked at the periphery of mine along the statutory/mine boundary in such manner that no stacking will be done at the area of 3 meter from the edge of quarry pit. Mine/Statutory boundary is 7.50 m wide in order to comply the rules of MMR1961. Out of this mine/statutory boundary 3.0 m wide area from the edge of mine pit is proposed to left to comply the provisions of MMR1961. Dumping area is proposed on balance outer 4.50 m wide area of mine/statutory boundary i.e. after 3.0 m of no activity zone. Threfore saperate dumping area in the mine is not proposed. Rather outer 4.50 meter wide area under mine/statutory boundary is itself considered as dumping area. plantation is also proposed on the same dumping area over the dump. Roads within mine area is also proposed to be constructed within mine boundary only.

Further if the area for dumping of OB gets short then the land adjoining or nearby the mine will be utilised with due permission of district mining office for dumping of excess OB. Such excess OB dump will be utilised in priority for reclamation at the time of reclalation of mine. b) Waste: No mining waste except from mining losses & OB will be generated during excavation of Ordinary Stone. All ROM mineral will be used. Ordinary Stone is usable as building material hence saleable therefore no mineral waste will be generated which requires their due management.

c) Sub grade material: No sub-grade mineral will be generated during excavation of Ordinary Stone. All ROM mineral will be used. Ordinary Stone is usable as building material hence saleable therefore no mineral reject will be generated which requires their due management. Manner of waste disposal & configuration: a) Top Soil & Overburden : Top Soil initially removed will be temprerorly stacked on mine boundary or other location within temp. permit area. Then whatsoever quantity of overburden & unusefull waste generated during the quarrying operation will be spread at the periphery of mine along the mine boundary on specified dumping areas. After proper dumping of OB and unusefull waste on mine boundary the preserved Top Soil will be spreyed over the OB and/or unsuefull waste dump. Stack of dump OB, waste & Top soil so developed is proposed to be stabilized the by grass plantation or cutting of local bushes and dence plantation on it as per plantation programme so that spillage of dump does not occur in the surroundings. Further if the area for dumping of OB gets short then the land adjoining or nearby the mine will be utilised with due permission of district mining office for dumping of excess OB. Such excess OB dump will be utilised in priority for reclamation at the time of reclalation of mine.

Signature of Project Proponent ______11 Pre - Feasibility Report For Darritola Ordinary Stone Temporary Permit Quarry at Village - Darritola Tehsil- Manendragarh & District- Koriya, State- Chhattisgarh. b) Waste & Subgrade Material : No need of planing for dumping management of waste and subgrade material as all ROM is saleable except Top Soil and Overburden. 4. SITE ANALYSIS Connectivity The area is approachable from district office Koriya by fair weather road. The area is 18.00 km from Baikunthpur. The applied area is 1.50 km away from Darritola bus stand. Hospital is available at Darritola at 1.50 km/Semara at 2.00 km distance. The nearest railway station is at Darritola (2.10 km) (S.E.C.RLY) and Nearest active airport is Raipur (241.00 km). (i) Land form, Land Use & Land Ownership Form & Use : Hilly, Non Forest, Revenue land. Ownership : Government land. Existing land use pattern: Existing land use pattern of the proposed mining area is given in below table. Forest Area Non-forest Area Forest - Nil Area (ha)- Nil (i) waste land (Government), 1 Hect. Area (ii) grazing land, Nil (iii) Agriculture land, Nil (iv) others (specify) Nil (ii) Climate Data from Secondary Sources: The climate of in general and the Manendragarh in particular is characterized by a hot summer and a well-distributed rainfall during the southwestern monsoon season extending from end of June to October. The area has 4 well-defined seasons in a year. The winter season commences from early December and continues up to the end of February, summer season extends from March to early June, rainy season generally from mid-June to September and the post-monsoon season from October to November. Topography: The study area consists of essentially Hilly land . Gentle slope towards North, Maximum elevation of the temp. permit area is 590 meters above MSL towards South while the lowest elevation is 581 m in the Northern part of temp. permit area. (iii) Social Infrastructure Available Power line, telephone line, school, bank, govt. office, Hospital, Police station etc. at Baikunthpur.

The road facility is already available which shall be used and properly maintained. Preference will be given to local labor from nearby villages. Other requisite infrastructure as transport of mine labors is available by way of jeep, two-wheeler. Medical facility is available for first aid at project site.

Signature of Project Proponent ______12 Pre - Feasibility Report For Darritola Ordinary Stone Temporary Permit Quarry at Village - Darritola Tehsil- Manendragarh & District- Koriya, State- Chhattisgarh. 5. PLANNING BRIEF Planning concept (type of industries, facilities, transportation etc.) Town and country Planning/Development authority Classification- Planning concept: It is a Ordinary Stone mining project, for safe, scientific & systematic working to follow the principles of safety & conservation of human health & mineral the planning for mining of stone shall be governed by the approved Quarry Plan under Chhattisgarh Minor Mineral Rules, 2015 vide letter no. 235/Khanij/2018, Surajpur Dated 07/02/2018.

(i) Population projection: The project is very small in magnitude. The project will employ most of the workers from nearby villages. There will not be any increase in population of the area due to the establishment of project. However, few people from other area may migrate in this area for business opportunities.

(ii) Proposed Land Use Planning Proposed Land Use Pattern of Proposed Quarry temp. permit Area 1. Total Lease Area 1 Hect. 2. Area proposed under mining pits 0.72 Hect. 3. Area covered by statuary/mine boundary 0.28 Hect. 5 Area covered by crusher 0 Hect. 6 Area Kept for storage of stone 0 Hect. 7 Unused Area within Lease area 0 Hect. Total Area (2+3+4+5+6) = 1 Hect. 8 Dumping Area proposed within proposed 0.17 Hect. Statutory/mine Boundary 9 Plantation Area proposed over the dump on dumping 0.17 Hect. area 10 No Activity Zone on Mine Boundary as per MMR 1961 0.11 Hect.

(iii) Assessment of infrastructure demand (physical and social) Site Services: Site services are required per the statutory provisions i.e rest shelters, toilets, drinking water facilities, safety appliances, and regular medical checkup facilities are suitably needs to be provided for labors and their families. The health and safety of the employees is required to be given first priority during the mining operation. Training program organize for first aid. First aid: Specified first Aid station is needed to be maintained at the site office and the rest shelter as per applicable statutory provision. Office and stores: Office and stores is needed to be provided as per applicable statutory provision.

Signature of Project Proponent ______13 Pre - Feasibility Report For Darritola Ordinary Stone Temporary Permit Quarry at Village - Darritola Tehsil- Manendragarh & District- Koriya, State- Chhattisgarh. Amenities / Facilities: Specific amenities / facilities are not required in this mining project. However the same can be provided as per prescribed instructions. Road & Connectivity: The road facility is already available around 570 m from the site which shall be used and properly maintained. Manpower Requirement: Apart from indirect manpower requirement for Driver, cleaner for loader & dumper, manager, accountants; approx. 35 labours will be required directly for mining operation. Other requisite infrastructure: Transport of mine labors is available by way of jeep, two-wheeler. Medical facility is available for first aid at project site. Power line, telephone line, school, bank, govt. office, Hospital, Police station etc. are the other requisites needed for mine operation and social facilitation. 6. PROPOSED INFRASTRUCTURE (i) Industrial Area (Processing Area) Not Applicable (ii) Residential Area (Non Processing Area) No residential area is proposed for the project except temporary rest shelters proposed for labors.

(iii) Green belt Under the afforestation plan, plantation in nearby villages and connecting roads be undertaken. The implementation for development of greenbelt will be of paramount importance as it will not only add up as an aesthetic feature but will also act as a pollution sink. The species to be grown in the areas should be dust tolerant and fast growing species so that a permanent greenbelt is created. Plantation in the barrier zone and roads is necessary as these areas will contain fine particulates resulting from mining operation and vehicle movement Plantation will also be carried out as social forestry programme in village, school and the areas allocated by the Panchayat/State authorities. Native plants like Neem, Peepal, Khejri and other local species will be planted. A suitable combination of trees that can grow fast and also have good leaf cover shall be adopted to develop the greenbelt. Afforestation program shall be started with the commencement of mining operation with simultaneous clearing of land by spreading of soil along barrier of proposed lease boundary. 2.0m X 2.0m spacing with 0.6m depth have been suggested for sapling pits on which local species will be planted. Year PROPOSED SITE SPECIES No. OF SAPLING 1st Year Along boundary of quarry area Seesam, Bargad, Neem, Aam, 190 Pipal, etc.

Signature of Project Proponent ______14 Pre - Feasibility Report For Darritola Ordinary Stone Temporary Permit Quarry at Village - Darritola Tehsil- Manendragarh & District- Koriya, State- Chhattisgarh. If/Where no plantation is possible within the mine due to rocky nature of lease area then plantation on transportation road side or on the Government waste land as suggested/demarked by Gram Panchayat/Nagar Panchayat/ local body will be done as per above plantation program.

(iv) Social infrastructure For the social developmental program on the need base assessment some development program will be undertaken by the project proponent i.e. development of or maintenance of urinals, toilets, safety appliances & training program, confirming availability of pure and clean drinking water, periodic health checkup program, transportation facility to labours and their children’s to schools etc. OCCUPATIONAL HEALTH AND SAFETY Occupational Health and Safety are important. Periodic assessment of it will be useful. Identifying workplace hazards, assessing risks to employee health and safety, are important. Health and Safety points are also important in many of the environmental aspects of the workplace.

Occupational Health and Safety works as follow- 1) Except dust generation there is no source which can show a probability for health related diseases and proper dust suppression will control dust generation and dispersion.

2) Awareness program be conducted about likely occupational health hazards so as to have preventive action in place. 3) Promote occupational health and safety within workers in mine and develop safer and healthier ways of working; 4) Develop and implement training sessions for management, supervisors and workers on health and safety practices and legislation; (v) Drinking Water Management (source & supply of water): Drinking water is available in dug well and tube well at nearby village of the applied area which is portable, pure and clean. It is also proposed to provide hand pump if needed in the temp. permit area for mitigating of drinking water, such hand pump will be arranged after taking statutory permission. (vi) Sewerage System: No construction or sewage waste is expected from the mining process. However the domestic waste from the toilets shall be given treatment through septic tank and soak pit arrangement. (vii) Industrial waste management: No industrial waste will be generated. (viii) Power requirement & supply/source: A) Fossil Fuels : Fuel is to be used in form of diesel for mining operations, compressors and running of tractors and other transportation vehicles. Quantity for fuel will depend upon the usage of transportation vehicle and other machineries and level of achievement of estimated production. Diesel will be outsourced from nearby diesel pumps.

Signature of Project Proponent ______15 Pre - Feasibility Report For Darritola Ordinary Stone Temporary Permit Quarry at Village - Darritola Tehsil- Manendragarh & District- Koriya, State- Chhattisgarh. B) Electricity : Electricity will be required for Pumping of water and for administrative building & rest shelters. The requirement of Power is estimated as under- S.N. Particulars Power requirement 1 Domestic Purpose 5 HP C) Source of Electricity: The power requirement for the project will be met by electricity lines of Chhattisgarh State Power Distribution Copany Limited available at village or nearby site area. 7. REHABILITATION AND RESETTLEMENT (R&R) PLAN: No R&R plan is required as the mine area does not cover any habitation. Hence the mining activity does not involve any displacement of human settlement. No public buildings, places, monuments etc. exist within the temp. permit area or in the vicinity of the mine temp. permit area. The mining operation will not disturb/ relocate any village or need resettlement. Thus no adverse impact is anticipated.

Impact of the stone mining will be positive, as it will upgrade the socio-economic status of local inhabitants in the nearby areas by giving employments to poor people of nearby villages. Due to this positive impact the living standard will increase and will lead to educational upliftment.

Effect on Flora & Fauna: Mining is restricted to very small area. No study have been conducted or record found on effect on Floora & Fauna for mine area. However mining activity causes impact on flora and fauna due to land degradation/deforestation etc., 8. PROJECT SCHEDULE AND COST ESTIMATES A) Likely date of start construction and likely date of completion (time schedule for project) – The proposed mining project will be started after obtaining Environmental Clearance of quarry temp. permit and order to enter in temp. permit area by District Collector (Mining Branch). Consent to establish & operate from CGCECB will also be taken if instructed by DEIAA.

B) Estimated project cost of the project - S.N. Particulars Amount in Lacs 1 Land Cost ( Government land) - 2 Administrative Building & Rest Shelters 1.00 3 Mining Machineries & Equipment’s 10.00 4 Land Development & Establishment cost 1.00 5 Others 1.00 Total Cost of Project : 13.00

Signature of Project Proponent ______16 Pre - Feasibility Report For Darritola Ordinary Stone Temporary Permit Quarry at Village - Darritola Tehsil- Manendragarh & District- Koriya, State- Chhattisgarh. 9. CONCLUSION In any human activity there are always possibilities of finding various options. Project proponent has decided to examine and adopt one such option that will be both environment friendly and best suited for Ordinary Stone production. Various alternatives in terms of site, technology, and equipment are considered. A final selection is thus arrived– (a) The Proposal is for the Environment Clearance of the Proposed Mine. (b) The quarry project will create local employment to the villagers and they will get employment in nonagricultural season. (c) The Proposal does not require further Infrastructure facilities other than few Mining Machineries. (d) The Project is viable and environmental friendly as it’s a development project for the State & Country. (e) Increased financial benefits accruing to state and central agencies by ways of taxes, royalties, cesses etc. Signature of the applicant For, NSPR-PLR Joint Venture

Mr. Mallapuram Babu Project manager Baikunthpur Date : / /2018 Place : Baikunthpur

Signature of Project Proponent ______17