Upper Eskdale Community Group Community Hub, Eskdalemuir Next Stage Big Lottery Requirements

Architects Plus (UK) Ltd 1.0 Project Team

Individual consultant CV’s, as outlined below and proof of professional indemnity insurances are appended to this report.

Architect and lead consultant

Architects Plus (UK) Ltd Victoria Galleries, Victoria Viaduct, Carlisle CA2 5DT Tel: 01228 515144 Fax:01228 515033 Email: [email protected] or [email protected]

Tom Langlands: Director in overall charge of the project. Dan Clements: Chartered Technologist responsible for contract administration and production drawings and specifications.

Quantity Surveyor

McGowan Miller Partnership 36 George Street, DG1 1EH Tel:01387 254283 Fax:01387 263471 Email: [email protected]

Stuart Callander: Partner in overall charge of Quantity Surveying requirements. Alan Thomson: Quantity Surveyor

Structural Engineer

Bingham Yates & Partners 38 Victoria Place, Carlisle, Cumbria CA1 1EX Tel:01228 521436 Fax:01228 515579 Emai: [email protected] Chris Walters: Director in charge of structural engineering detailed design calculations and detailing.

Mechanical & Electrical Engineer

TTS Renewable Energy Ltd Suite 33, Geddes House, Kirkton Road North, Livingston EH54 6GU Tel: 01506 420198 Email:[email protected] John Benson: Responsible for overall design philosophy monitoring agreed project targets and financial performance. Marcus Stout: Responsible for electrical system design Compliance with appropriate codes of practice including safety and liaison with utility suppliers Execution of lighting design. Kenny Lunn: Design of full mechanical services covering heating, internal water services and drainage, ventilation & reinstatement of existing services. Liaison with proposed Biomass equipment supplier. Keith Campbell: Review and selection of renewable energy equipment including Biomass boiler specification and fuel selection. Review of existing air source heat pump and specification of Installation.

CDM-C

AP Project Safety Victoria Galleries, Victoria Viaduct, Carlisle CA2 5DT Tel: 01228 515144 Fax:01228 515033 2.0 The following Architects drawings should be read in conjunction with this report:

• 08006-07 Plans, Sections and Elevations Proposed 1:100 • 08006-08 Proposed Site Plan and Car Park 1:200 • 08006-09 Proposed Location Plan 1:1250 • 08006-10 Existing Plans and Elevations 1:100

• Existing site photographs are included at the end of this report.

3.0 Design Brief and User Requirements

The initial design brief was broadly divided into three separate approaches to the existing buildings and site, which were:-

• Utilising the existing building in its entirety with internal alterations and possible small extension to provide the accommodation requirements. • Rebuild the brick extension to the same footprint as existing, retaining the original stone building as original and working the single storey interior to provide the required accommodation. • Redesign and rebuild the brick extension to provide two storeys of accommodation whilst maintaining the original stone school building.

Following the feasibility study undertaken in March 2008, the end user requirements were modified as part of the detailed design process, forming a new client brief (outwith the initial Upper Eskdale Development Group, design concepts document). Whereby the overall approach to sustainability was very much retained as part of the detailed design proposal, the accommodation requirements were refined to the following specification:-

• Multi purpose space (as existing in original stone building). • Art room/activity space that could also provide café overflow. • Café area including kitchens. • Male, female and disabled WC’s. • Office reception for UEDG worker. • Consulting space for visiting health practitioners. • Letting office space. • Community office space (community energy project). • Biomass boiler room.

The existing footprint could not be suitably reconfigured to accommodate the client’s space requirements. However, it has proved possible to provide all the space, with phasing potential, by the addition of a first floor extension that offers the required accommodation at relatively low additional cost. The initial designs for the building, utilising as much of the existing structure as possible, had to be developed and modified to meet some of the planning considerations, relating to neighbouring premises. The design had to make allowance for the impact additional height may have on adjacent properties, part of the overall holistic approach to sustainability and community.

In order to accommodate the design requirements, it was decided to demolish the existing 1970’s structure (as Option 3 of the original brief proposal) and rebuild to roughly the same footprint, whilst being careful to keep the structure in harmony with the existing stone building and neighbouring properties. As part of the environmental requirements of the build, we elected to construct new so that we could maximise the use of material and efficiency of the thermal envelope, whilst recycling as much of the material as possible on site. The long term benefits of creating a highly efficient and sustainable structure, outweigh those of retaining the original extension, given its current poor state.

Detailed consideration was given as to how the client will use the various differing accommodation. In response the first floor area is essentially stand-alone, with both community and letting offices, consulting room and 2 no. disabled compliant toilets. This enables the accommodation to be accessed, without the requirement for reception or the public areas on the ground floor to be occupied, and be separately secured. The subdivision of accommodation in this way, allows for the function based activities to be housed on the ground floor, creating a suitable subdivision between usage and usage groups (essential also for the differing requirement for fire safety and subdivision). In designing the ground floor accommodation we have tried to ensure that the space is as flexible as possible. This is vital in ensuring that the needs of the different community projects are recognised and also that any changes in community requirements can be accommodated in the future. The café/art room area is effectively a single space, subdivided by sliding partitions and glazed screens, allowing them to be combined or divided according to the usage requirements at any one time. This has the added advantage of providing for the possibility of another larger multi-purpose space with catering, should this be required by the community or dictated by functions. The overall ground floor layout has been designed to provide for minimum staff supervision requirements whilst maintaining control over incoming and outgoings throughout the public area of the premises. It is possible for the person or persons manning reception to effectively close down access to all the ground floor areas to allow them to fulfil multiple roles, e.g. still controlling access whilst serving in the kitchen/café area. The foyer serves as a secure (but dry) holding area as required depending on activities and functions.

4.0 Access Arrangements

As with any public building in , it is proposed that the hub premises be fully DDA compliant. This includes certain measures to make the building accessible to wheelchair users and others with visual and other impairments. The design of the building will, where possible, incorporate the best practice indicated in BS 8300:2009 Design of buildings and their approaches to meet the needs of disabled people – code of practice. Among the disability features included in the building are the following:-

·• Circulation and assembly areas and facilities as BS 8300:2009, including • 926 mm doors fitted throughout. • A total of 3 accessible disabled toilets (1 on ground and 2 on first). • Level and ramped access to the building. • Lift provision to first floor. • Contrasting doors, floors, walls and ironmongery. • Warm touch fittings. • Contrasting stair nosings and handrails and warm touch coverings to all handrails. • Accessible light switch and socket height throughout the new build. • Clear internal signage including tactile letters. • Non-slip surfaces to stairs and ramps.

The site, by its nature and location, will predominantly be accessed by vehicle, although there are footpaths from the village in the vicinity of the existing property. The remote nature of the community restricts walking to the proposed hub, As such, provision has been proposed, in the existing parking area for a fully disabled parking space with suitable hard surfacing, leading to the proposed community hub. In addition to this, there is a substantial hard surface area to the front of the building allowing for a drop off – pick up point. As previously mentioned graded ramped access and level platforms provide full disability compliant access to the new building.

5.0 Construction and Materials

It is proposed that the new build construction section of the project will be of semi-traditional construction. External walls will be predominantly concrete block construction with external cladding and insulation. This construction is proposed to provide a high thermal mass internally with a highly efficient thermal envelope. Externally this will be achieved by using a solid internal block wall, which is cocooned in external insulation and clad with local larch timber. External insulation of this nature is highly efficient and when clad around a concrete or concrete block shell, the overall heat retention is considerably improved. It is preferable to reduce the distance that any materials travel, so the use of local larch will help reduce the overall carbon footprint of the development. Larch is also moderately durable and is better at withstanding knocks and scratches than the more usually sourced, imported Cedar. It is recognised that concrete block, although manufactured locally, (product can be sourced within 20 miles of the proposed site), it is not considered the most environmentally friendly of materials. It does however have benefits in terms of its thermal mass properties and this will go some way (when incorporated into the proposed construction) to mitigating the environmental impact of block manufacture. It should also be noted that due to planning constraints requiring for considerable flood mitigation in the construction, the use of alternative structure materials such as timber is not suitable for either the building or location. The use of local larch as a cladding material provides a number of benefits over and above the aesthetic appeal, these include, low embodied energy, support of local supply chain, good environmental credentials and a suitable sacrificial, easily replaced cladding material in the event of damage. Due to the proposed mixed usage of the building we are subject to strict fire and sound regulation. With this in mind, the use of concrete beam and block or precast flooring slabs is preferred over an alternative build up. The use of the proposed materials substantially adds to the overall thermal mass of the building. The use of timber flooring has been considered, primarily due to potential site constraints, but this involves a complex build up with specialist components (resilient bars and pads and multiple plasterboard layers) impacting both on the carbon footprint and available headroom. Roof construction is proposed as structural timber (local is preferred) with slate and single ply membrane to flat areas specified for both planning and ecological reasons (it is proposed that slate should be sourced from as close to the project as possible and reclaimed should be considered). High performance double glazed timber doors and windows are specified and it is hoped that these too can be sourced locally from any one of a number of local joiners and suppliers in the area.

Wherever possible, it is intended that materials should be salvaged from the existing property following demolition and recycled within the new construction. Existing brick and masonry should either be re-used as internal walls, hardcore fill or landscape material or recycled as part of a detailed waste management plan. Potential contractors will be required to minimise the production of landfill material through accurate planning and procurement policies. As part of the construction stage and project management, the client has also indicated a preference for the following environmentally positive procedures (where applicable):-

• Design and construction documents distributed over the internet (partially implemented). • The use of video linking for site and design meetings. • Investigate the working of 4 longer days rather than 5 normal to minimise travel to and from site (as a very rural location). • Local sourcing of materials. • Substantial on-site storage to minimise number and frequency of deliveries. • Consideration to sustainable travel arrangements. • Environmental issues to be at the forefront of construction planning.

6.0 Project Constraints

There are constraints relating to the site and access for heavy lifting. These are or will be dealt with in a number of ways including:-

• The re-routing of overhead power cables to reduce site risks to personnel and machinery. • Detailed CDM planning both prior to and during the construction phase in conjunction with the cho sen contractor. • Liaison with local community and interested parties to manage and reduce any disruption.

7.0 Site Appraisals

• The existing building services were surveyed by TTS in May 2010 and a copy of their report dated 18/05/2010 is appended to this document. • Structural engineers trial excavation report of 17th November 2010 • Historical review of community hub and adjacent car park (desk top study) by arc environmental, dated 6th May 2010 • Structural engineers existing building survey dated 23rd April 2010 • Summary of West Coast Surveys Ltd asbestos report dated 14th April 2010 • Schools condition Survey Report dated 27th May 2002

8.0 Building Services (TTS Renewable Energy)

Summary of Renewable Energy Recommendations

The main recommendations are the implementation of a variety of energy efficiency measures taking advantage of current renewable energy technology.

1. Relocate and reuse existing hand fed heater to cafe area. 2. Install LPHW wet system throughout building, served by a wood chip/wood pellet biomass boiler. 3. Two Mitsubishi air to air heat pumps retained and reinstalled to provide supplementary heating. 4. Lighting systems to be installed to give minimum running costs consistent with correct levels of illumination and using a combination of LED equipment for task. lighting and compact fluorescent lamps for general use.

Brief Commentary on Individual recommendations

(a) The existing hand fed pellet biomass style heater to be relocated to the café area to provide heating to the area as and when the café is operational.

(b) For ease of operation and flexibility an LPHW wet system will be installed in the building, this being served by a biomass boiler of 40/50 Kw capacity using wood chip or wood pellet from a storage area adjacent to the boiler position as shown on site plans. The biomass option has been chosen in keeping with the communities desire to source fuel from a local source and support the proposed pelleting operation in the future. (c) The two Mitsubishi air to air heat pumps will be retained in the services design and incorporated in the building design as a source of supplementary heating and reducing demand on the boiler. (d) Lighting systems will be provided in the building to take advantage of current technology to give minimum running cost. This will be achieved by a combination of LED task lighting and CFL systems for the more general areas, to give maximum light quality and correct cooler temperature. (e) 12 existing solar PV panels have been used in the design of the PV system, with panels being installed directly on the roof or alternatively directly to the sarking and integrated into the roof profile. The remaining 30 panels mounted adjacent to the building on a frame leaving adequate ground clearance. In the final design considerations as to the size and location of the inverter will require to be established to minimise running costs.

Running Costs

1. Biomass Boiler The annual running cost for the biomass boiler will be of the order of £3,900 per annum. This is based on consumption of 39 tonnes of wood chip (195m3) per year which is equivalent to 0.75 tonnes or 3.75 m3 per week. This quantity of fuel will supply 120,000 kwh per annum. The boiler rating will be 50kw. 2. Electrical Energy Costs Based on a total area of 542 m2 and opening hours of 12 hours per day throughout the year the electrical energy costs will be of the order of £4943 per annum. This is based on a consumption of approximately 45,000 kwhs per annum. 3. PV Generation The installed PV system is capable of generating 7000 Kwh per annum. The income generated by exporting 7000 Kwh per annum to the Grid is £2,885 per annum. The estimated cost of the electrical consumption of the building is £4,943 and if the generated energy of 7000 Kwh is used to offset the consumption from the Grid the saving will be £700 per annum.

4. Renewable Heat Incentive

Systems installed from 15 th July 2009 onwards – will receive RHI payments for a period of 20 years from date of registration. However, registration will not be possible until the scheme is introduced in July 2011 (or sometime thereafter as the deadline has not been confirmed). The Government appear to be aiming for a late August or early September introduction. Provisional tariff has been calculated to give a return of about 12% on investment, except for solar thermal where the figure is much lower at about 5%.

Electrical Services Summary

The electrical services shall comprise the following elements:

• Low voltage switchgear shall comprise the installation of a new cubicle switchboard. • Normal lighting shall be energy efficient fluorescent and/or discharge style luminaires. • Emergency lighting shall be self contained luminaires and “EXIT” SIGNS or conversion packs in normal luminaires. • Small power shall be provided by low voltage (230 volt) socket outlets located throughout the building. • Earthing of the electrical network shall be achieved by earth conductors on all final circuits and by a connection to the incoming supply. • Fire alarms shall comprise a Category L1 automatic addressable system. Perimeter security alarms system shall be magnetic contacts on all perimeter doors and windows and presence detectors within the building. • IT and telephone Wiring shall comprise a ”Structured” wiring system terminated in a patch panel. • Mechanical services Supplies shall be derived from the main switchboard • The installation of 12 No. PV panels on the roof shall be configured into a separate network and connected to the electrical system through a new inverter. The remaining external PV panels (ground array) shall be reconfigured and connected to the electrical system through a new inverter.

Mechanical Services Summary

• Hot & cold water services shall be provided to all toilets and kitchen areas. • Heat recovery ventilation systems shall comprise supply and extract ventilation system with heat exchanger units linking the supply and extract air flows. Low pressure hot water heating shall be the main means of heating the building via panel radiators located throughout the building. • Biomass boiler shall be the main source of heating for the building (Excluding Plant Room and Fuel Store) • The installation of 2 No. existing air source heat pumps shall provide supplementary heating within the building at an appropriate time of the year. Air source heat pumps will not be efficient during the coldest time of the year. • The Existing Wood Burning Stove shall be relocated to the cafe area.

9.0 Schedule of Accommodation Areas

The following are the internal areas (in m²) of the proposed internal accommodation by floor:

Ground Floor Existing multi purpose areas 75m² Foyer/reception office 41m² Disabled WC 6m² Female WC 10m² Male WC 13m² Kitchen 13m² Boiler room 12m² Café 61m² Art room 55m² Store 2m² Circulation 52m² First Floor Community Energy office 47m² Letting office 28m² Consulting room 13m² Disabled WC x 2 3m² Circulation 25m² Other External areas around existing school 1032m² (not including building footprint) Car park and landscaping 2544m² (includes existing field) 10.0 Capital Cost Estimate

JOB REF: DQ2197 SUMMARY OF ELEMENT COSTS

Eskdalemuir Community Hub Client: Upper Eskdale Development Group Ltd 2 Gross Internal Floor Area (m ) : 407 Date: 2nd August 2011 (extension only) Stage: Cost Plan 1

ELEMENT COMMENTS Total Cost Cost/m 2 of of Element (£) Gross Floor Area (£) 1. SUBSTRUCTURE 1.A Substructure 10,635.80 26.13 Strip founds assumed 1.B Lowest Floor Slab 26,693.50 65.59 Concrete suspended floors Group Element Total 37,329.30 91.72 2. SUPERSTRUCTURE 2.A Frame 15,000.00 36.86 Allowance for structural steel requirements 2.B Upper floors 17,712.00 43.52 Suspended concrete slab 2.C Roof 86,397.00 212.28 2.D Stairs & walkways 5,000.00 12.29 Staircase, handrails and balusters 2.E External walls 25,335.00 62.25 2.F Windows, screens & external doors 28,680.00 70.47 Timber double glazed 2.G Internal walls & partitions 29,225.00 71.81 2.H Internal doors and screens 22,135.00 54.39 Group Element Total 229,484.00 563.84 3. INTERNAL FINISHES 3.A Wall finishes 1,200.00 2.95 Isolated tiling in WC areas 3.B Floor finishes 16,319.80 40.10 Carpet & vinyl generally 3.C Ceiling finishes 10,073.00 24.75 3.D Decoration 10,175.00 25.00 Assume windows pre finished and larch cladding not treated. Group Element Total 37,767.80 92.80 4. FITTINGS & FURNISHINGS 4.A Fittings & furnishings 25,250.00 62.04 Kitchen allowance £17.5k, Reception Counter allowance £3.5k Group Element Total 25,250.00 62.04

SUB-TOTAL OF ELEMENTS 1,2,3 & 4 329,831.10 810.40

JOB TITLE: Eskdalemuir SUMMARY OF ELEMENT COSTS Community Hub JOB REF: DQ2197 SUB-TOTAL OF ELEMENTS 1,2,3 & 4 329,831.10 810.40

5. SERVICES 5.A Sanitary appliances 9,760.00 23.98 5.B Services equipment 0.00 5.C Disposal installations 2,250.00 5.53 5.D Water installations 0.00 5.E Heat source 0.00 5.F Space heating & air treatment 101,442.00 249.24 Based on TTSRE budget costs (excl underfloor heating) 5.G Ventilating systems 0.00 5.H Electrical installations 67,850.00 166.71 Based on TTSRE budget costs 5.I Gas installations 0.00 5.J Lift & conveyor installations 20,000.00 49.14 Platform open type lift 5.K Protective installations 7,500.00 18.43 Lightning protection 5.L Communication installations 0.00 5.M Special installations 0.00 5.N Builders work in connection with services 3,000.00 7.37 5.O Work to existing building 30,181.00 74.15 Repointing, new windows/bargeboards, internal/external decoration Group Element Total 241,983.00 594.55 6. EXTERNAL WORKS 6.A Site work 53,565.00 131.61 6.B Drainage 14,500.00 35.63 Assumed foul to existing septic tank, surface to soakaways 6.C External services 27,500.00 67.57 Allowance of £15k for diversion of overhead cables 6.D Other building works 23,000.00 56.51 Demolition and asbestos removal Group Element Total 118,565.00 291.31 SUB-TOTAL OF ELEMENTS 1,2,3,4,5 & 6 690,379.10 1,696.26 PRELIMINARIES 12 % 82,845.49 203.55

TOTALS (less contingencies) 773,224.59 1,899.81 Contingencies (10%) 77,322.46 Building Warrant Fee 3,580.00

Notes :- 1. The above costs make no allowance for loose furniture/equipment, professional fees or VAT. 2. The above costs make no allowance for Consulting Room fit-out. 3. The above costs assume tenders will be sought no later than 1st Quarter 2012. 4. The above costs are based on drawing numbers 08006-07B, 08006-08A and TTSRE budget costs.

The BCIS is forecasting tender prices will increase by 3.1% between 2Q12 and 2Q13. Therefore an allowance in the application form for inflation should be considered. The cost plan takes us to the end of 1Q12 therefore if a start in say the summer/autumn of 2012 is possible then 2% would seem a reasonable addition to the construction costs.

Construction costs furniture/equipment and professional fees will attract VAT at 20% (on top of summary of costs) based on present rates (August 2011). 1.A Substructure Excavate trenches/disposal m3 46.305 £15.00 £694.58 Concrete trench found m3 15.435 £25.00 £385.88 Backfill, hardcore m3 17.64 £30.00 £529.20 Basecourse facing brick m2 26 £80.00 £2,080.00 Clay brickwork m2 66.38 £50.00 £3,319.00 Block m2 66.38 £35.00 £2,323.30 Forming cavities m2 33.19 £6.00 £199.14 Fill cavity with concrete m3 6.615 £135.00 £893.03 DPCS m2 17.64 £12.00 £211.68 £10,635.80 1.B Lowest Floor Slab 75mm concrete floor screed m2 271 £25.00 £6,775.00 Insulation m2 271 £25.00 £6,775.00 Visqueen m2 271 £3.50 £948.50 Beam and block floor m2 271 £35.00 £9,485.00 Hardcore upfill m3 135.5 £15.00 £2,032.50 350 topsoil strip 400 to ffl ddt slab & insulation 250mm so 500mm deep hardcore Compact m2 271 £2.50 £677.50 £26,693.50 2.A Frame Allowance for structural steel requirements £15,000.00

2.B Upper floors Bison Slab m2 216 £45.00 £9,720.00 Tongued and grooved flooring m2 216 £15.00 £3,240.00 50mm insulation m2 216 £10.00 £2,160.00 Brandering forming service void m2 216 £12.00 £2,592.00 £17,712.00 2.C Roof Additional Structural support to roof £3,500.00 Carcassing Flat & Pitched Roof m2 385 £50.00 £19,250.00 Pitched roof Sundry infil timbers £2,500.00 Sarking m2 208 £15.00 £3,120.00 Insulation m2 208 £30.00 £6,240.00 Natural slate roof, felt etc m2 208 £60.00 £12,480.00 Hips m 15.6 £20.00 £312.00 Flat roof Firring pieces £1,500.00 Sundry infill timbers £2,500.00 Plywood m2 177 £15.00 £2,655.00 Insulation m2 177 £25.00 £4,425.00 Single ply membrane roof (Sarnafil assumed) m2 177 £60.00 £10,620.00 Overhanging eaves m 84 £25.00 £2,100.00 Fascia m 84 £25.00 £2,100.00 Velux roof windows nr 9 £500.00 £4,500.00 Black aluminium gutters incl. fittings m 84 £30.00 £2,520.00 Black aluminium downpipes incl fittings m 17 £30.00 £510.00 Sunpipes nr 14 £350.00 £4,900.00 Leadwork m 19 £35.00 £665.00 £86,397.00

2.D Stairs & walkways £5,000.00

2.E External walls Larch Cladding/insulation m2 106 £75.00 £7,950.00 Framing, plugged and screwed m2 106 £10.00 £1,060.00 100 block m2 212 £35.00 £7,420.00 Form cavities with insulation m2 106 £20.00 £2,120.00 Render finish internally m2 106 £25.00 £2,650.00 Closing cavities/dpcs £1,000.00 Cills nr 19 £75.00 £1,425.00 Lintels nr 38 £45.00 £1,710.00 £25,335.00 2.F Windows, screens & external doors Windows; 1200x400mm nr 3 £400.00 £1,200.00 2200x1600mm nr 6 £1,000.00 £6,000.00 Screens; 3200x2300mm nr 1 £2,750.00 £2,750.00 2100x2300mm nr 1 £2,000.00 £2,000.00 7200x2300mm nr 1 £3,500.00 £3,500.00 Timber Doors; 1000x2100mm, single nr 3 £750.00 £2,250.00 1800x2100mm, double nr 1 £1,250.00 £1,250.00 2100x2100, double nr 1 £1,250.00 £1,250.00 2400x2100mm, sliding double nr 2 £1,800.00 £3,600.00 Sillboards, finishes etc £2,380.00 Flood barriers to external doors £2,500.00 £28,680.00 2.G Internal walls & partitions Partitions(re cycled brick/render) m2 163 100 £ 16,300.00 Stud partitions m2 61 £65.00 £3,965.00 Oxters m2 88 £45.00 £3,960.00 Glazed wall (screen?) £5,000.00 £29,225.00 2.H Internal doors and screens Timber Doors; 900x2100mm, single nr 13 £500.00 £6,500.00 1800x2100mm, double nr 2 £1,000.00 £2,000.00 700x2000, single nr 2 £500.00 £1,000.00 Glazed sliding partition nr 1 £10,000.00 £10,000.00 Architraves m 170 £8.00 £1,360.00 Ironmongery nr 17 £75.00 £1,275.00 £22,135.00 3.A Wall finishes

Tiling to WC areas m2 20 £60.00 £1,200.00 £1,200.00 3.B Floor finishes Carpet/Vinyl m2 367 £25.00 £9,175.00 Hardwood m2 40.88 £60.00 £2,452.80 Skirtings m 399 £8.00 £3,192.00 Floor screed m2 271 £0.00 £0.00 Hardwood flooring at reception £1,500.00 £16,319.80 3.C Ceiling finishes Ceilings, flat m2 337 £18.00 £6,066.00 Ceilings,coombed m2 86 £22.00 £1,892.00 Dwangs m2 423 £5.00 £2,115.00 £10,073.00 3.D Decoration m2 407 £25.00 £10,175.00 £10,175.00 4.A Fittings & furnishings Reception counter £3,500.00 Commercial Kitchen/Servery incl appliances £17,500.00 Wood Burning stove, hearth and surround, flues £3,750.00 Display boards £500.00 £25,250.00 5.A Sanitary appliances WC nr 4 £550.00 £2,200.00 WHB & taps nr 4 £310.00 £1,240.00 Urinals nr 2 £235.00 £470.00 Doc M Pack nr 3 £950.00 £2,850.00 Toilet cubicles nr 4 £750.00 £3,000.00 £9,760.00 5.C Disposal installations Sanitary appliances nr 13 £150.00 £1,950.00 kitchen fittings nr 2 £150.00 £300.00 £2,250.00 5.D Water installations Included in 5.F 5.F Space heating & air treatment £101,442.00 5.G Ventilating systems Included in 5.F 5.H Electrical installations £67,850.00 5.J Lift & conveyor installations £20,000.00 5.K Protective installations £7,500.00 5.L Communication installations Included in 5.F 5.N Builders work in connection with services £3,000.00 £199,792.00 5.O Work to existing building Re pointing external walls m2 134 £45.00 £6,030.00 New windows (casement) nr 11 £1,000.00 £11,000.00 Replace barge boards/remove ex. m 21 £25.00 £525.00 Redecorate - internal m2 75.04 £25.00 £1,876.00 Decoration - external £750.00 Acoustic treatment £10,000.00 £30,181.00 6.A Site work Allowance for removal of old foundations £ 1,800.00 Grubbing up/sealing stand pipe £ 250.00 Tar m2 61 25 £ 1,525.00 Kerbs m 28 25 £ 700.00 Hardcore m3 212 40 £ 8,480.00 Compacting m2 532 2.5 £ 1,330.00 Excavating m3 212 0 £ - Disposal m3 212 0 £ - Post&wire fence to car park m 148 15 £ 2,220.00 Bike rack nr 1 £ 1,500.00 Picnic tables/planters/signage etc £ 5,000.00 Geotextile membrane m2 532 5 £ 2,660.00 Meadow planting £ 500.00 Main entrance ramp/steps and handrail £ 3,500.00 Raised patio, steps and ramp £ 3,500.00 Rear entrance steps £ 600.00 Form entrance to car park £ 1,000.00 Soft landscaping £ 3,000.00 Fencing/hedging repairs £ 1,000.00 Dyke repairs £ 2,500.00 Field gate/cattle grid £ 2,500.00 Break up tar/fruit plants and allotments to rear of building £ 10,000.00 £ 53,565.00 6B Drainage Foul drainage to existing septic tank Surface water to soakaways £12,000.00 Extra cost of anti flood valves £2,500.00 £14,500.00 6.C External services Car park entrance lighting £2,500.00 Move overhead line £20,000.00 BT for data transmission £2,000.00 Alterations to electrical/water supplies £3,000.00 £27,500.00 6.D Other building works Demolish ex flat roof extension £15,000.00 Remove asbestos £8,000.00 £23,000.00

Total £690,379.10 11.0 Cash Flow Forecast 12.0 Design Team Fees

Funding Approval: Remaining Activities Total £ Total % RIAS Stages A-D+ RIAS Stages E-L (based on updated construction costs of £751,000) Architect £6850 £28822.5 £35672.5 4.75% Project Manager E-L Included in above Included in above Incl in Included in above above Civil & Structural £500 £6409.2 £6909.2 0.92% Engineering Building Services £1000 £6885.5 £7885.5 1.05% Engineer Quantity Surveyor £2208 £15816 £18024 2.4% CDM-c £500 £2504 £3004 0.4% Total £ £11058 £60437.2 £71495.2 9.52% Total % 1.47% 8.05% 9.52% (based on £751k construction cost)

Grade Architect Project Civil & Building Quantity CDM-c Manager E-L Structural Services Surveyor Engineering

£/hour £/hour £/hour £/hour £/hour £/hour Director £70 £70 £60 £85 £50 £70 Assoc Director £65 £65 £60 £75 N/A N/A Senior £55 £55 £60 £60 £40 N/A Consultant Project £55 £55 £60 £55 £30 £70 Consultant

Cost of Additional Surveys and extra over costs etc

Asbestos £625

Intrusive Services Condition Survey £980

Intrusive Structural Condition Survey £1800 Desktop Study by ARC Environmental £250 Flood Risk Assessment £1300 Additional works associated with extra planning matters £1800 Total for additional surveys / technical advice £6755

14.0 Project Management Strategies and Procedures

Procurement is expected to be by single stage selective tendering (stage H of RIBA. plan of works), with full construction issue and bill of quantities. The contract will take the form of traditional general contracting with lump-sum reimbursement based on tendered unit rates in contractual bill of quantities (such as SBC/Q, JCT, II.C.E conditions or The engineering and construction contract, formally NEC).

Architects Plus (UK) Ltd will act as the contract administrator (CA) throughout the project ensuring change control and risk management continuity. Variations to the contract will be dealt with via Architects Instruction, this will enable the management of design and cost alongside the full design team. Regular design and site meetings will be held throughout the course of the project with site inspections at approximately two week intervals and formal site meetings at four week intervals. Minutes will be prepared following formal site meetings and distributed to an agreed project team/client distribution list with required actions highlighted.

Risk will be managed by the close control of contract progress, full specification and planning prior to construction commencement and tight cost control. Substantial surveys of the existing properties, surrounding area and services and ground conditions have been undertaken at design stage. A project risk log has been prepared (see project risk management ownership plan) which has identified project risks with measures for consolidation. The risk ownership plan is based on identification, assessment and prioritisation to ensure adequate and timely action can be undertaken to mitigate any issues which may arise.

Individual health and safety risks are dealt with under the CDM regulations by designing out at source and recording any significant or residual risks on a health and safety design risk register for circulation amongst the design team. Wherever possible all health and safety risks will be designed out. Those residual risks that remain will be fed into the final health and safety and operation and maintenance files for the building. The CDM-c (notifiable project) will assign risk ownership to the design team as required and attend site meetings to ensure compliance with the regulations.

Management of Projects Costs

The better the design and tender documentation at tender stage, the easier the project costs will be able to be managed. Therefore the design team has assumed that procurement will follow traditional procurement lines whereby the designers fully design the project and the Quantity Surveyors prepare Bills of Quantities based on these designs. Before reaching that stage however effective cost planning is required to ensure, as the design develops, that the budget is not being compromised. Therefore regular cost plan updates at certain design milestones will be undertaken.

Once tenders have been received the Quantity Surveyor will analyse the tenders to ensure they have been well priced and recommend a contractor for acceptance. At this stage some value engineering may be required to ensure the budget is not exceeded. The contract chosen will stipulate the cost control procedures applicable including change control procedures to ensure the client is kept informed of any variations which could affect the overall costs. At monthly intervals, whilst preparing interim payment certificates, cost reports will be prepared which indicate the estimated final cost, taking into account all variations up to that time. It is important that a contractor is engaged who is willing to work with the design team to ensure tight control of the costs is achieved. This process will continue throughout the construction period until project completion when the Quantity Surveyor will agree the final costs with the contractor.

16.0 The Project Team CV_TL Architects Plus

Proposed Staff - Director in Charge -Tom Langlands

Name Tom Langlands

DOB 1954

Academic Qualifications Bachelor of Science Bachelor of Architecture (Hons) Master of Architecture

Professional Memberships Royal Institute of British Architects Royal Incorporation of Architects in Scotland Registered Member of Association for Project Safety

Position Director

Employing Firm Architects Plus (UK) Ltd. Sherwood Crescent,

Nationality British East Cluden Mill, Dumfries email [email protected]

Employment History 2001 - present Architects Plus (UK) Limited Director 1988 - 2001 Architects Plus Partner 1987 - 1988 Johnston and Wright, Carlisle Project Architect 1982 - 1987 Annandale & Eskdale District Senior Architect 1980 - 1982 Council Architect Ronald Fielding Partnership, London Tom Langlands graduated with a B.Sc and a B.Arch from Dundee University and then an M.Arch from Heriot Watt University. After graduation he worked on large scale multi million pound commercial office developments in London.

In 1982 he returned to Scotland and worked as a senior architect with the housing department of the District Council in Annan. He was responsible for many local authority new build and refurbishment projects including repair works, external renovations and landscaping projects. He was also involved with community council forums and local enterprise groups and is aware of the importance of consultative processes.

During this time his award winning competition scheme for Gloucester Park was featured in several international magazines.

In 1987 he joined Johnston and Wright in Carlisle and in 1988 he was a founder partner of Architects Plus. He has considerable experience of schemes involving the refurbishment of old listed buildings and properties in conservation and historic areas and has worked on education, housing, commercial, industrial, healthcare, town centre facelift and environmental improvement projects. He was also responsible for much of the rebuilding of Lockerbie following the Pan-Am disaster of 1988.

In the 1990’s served on the Dumfries and Galloway panel of The Architectural Heritage Society of Scotland.

Tom has experience of working on outstanding conservation area sites, notably the former mental health “campus” in Dumfries - The Crichton Estate. This is an “outstanding conservation area” comprising numerous Grade A and B listed buildings. Working on this estate involves developing unusual and imaginative approaches to finding alternative uses and innovative designs for existing buildings. With the assistance of Architects Plus the estate has won several national planning and architecture awards including a British Urban Regeneration Award.

Tom Langlands is also a CDM-Co-ordinator and Registered Member of the Association for Project Safety. CV Architects Plus

Curriculum Vitae - Dan Clements

Name Dan Clements

DOB 1974

Academic Qualifications BSc (Hons) Architectural Technology HND (HNC) Spatial Design

Professional Memberships Member of the Chartered Institute of Architectural Technologists. Associate member of the Association for Project Safety. STROMA OCDEA

Position Chartered Architectural Technologist

Employing Firm Architects Plus (UK) Ltd. Foxdale, Wetheral Nationality British

email [email protected]

Employment History 2006 – Architects Plus (UK) Architectural Technologist present Limited Architectural Technician 2004-2005 White Hill Design Technician 2003-2004 Conservatory Advisory Centre Dryfemount Care Facility

Following a move north from London where he had previously worked for various companies involved in Design and Construction, Dan Clements joined the Conservatory Advisory Centre in Dumfries in April 2003 as a technician. He was responsible for the day to day management of the office and projects and worked on a variety of specification, building warrant and planning applications.

In February 2004 Dan joined White Hill Design Studio LLP located in as an architectural technician. Whilst at White Hill, Dan undertook various projects for both domestic and non-domestic clients. He was responsible for the design of new build properties, extensions and alterations from client briefs through to completion. He also undertook development in new and experimental building techniques, materials and ecological design projects. As well as conventional technical work Dan was also involved in planning some unusual projects, ranging from the UK’s first private earthship development to full permaculture landscaping schemes.

Dan joined Architects Plus (UK) Ltd in January 2006 and has worked on several successful commercial and residential projects from historical conversions to state of the art care facilities. Some of Dan’s recent projects include the extensive residential extension to Kagyu Samye Ling Tibetan Centre, the Upper Eskdale Community Group feasibility study into a new community centre, feasibility work for the RSPB and care units and riding for the disabled facilities in .

Having elected to update his formal qualifications, Dan graduated top of his year with a first class Hons degree in Architectural Technology from the University of Northumbria. Dan has particular interests in design management and sustainable technology. Dan is a Chartered Architectural Technologist (MCIAT) having become a full member of the Institute of Architectural Technologists (CIAT) in 2011.

Partner’s CV

Name Stuart Callander

Professional Qualifications MRICS

Professional Memberships Member of the Royal Institution of Chartered Surveyors

Employment History

1998 - Present Day Partner - McGowan Miller Partnership 1990 - 1998 Senior Quantity Surveyor - McGowan Miller Partnership 1989 - 1990 Senior Quantity Surveyor - Kean, Kennedy and Partners 1988 - 1989 Building Officer - Dumfries and Galloway Health Board 1980 - 1988 Assistant Quantity Surveyor - Kean, Kennedy and Partners

General

Stuart Callander commenced working as a Trainee Quantity Surveyor with Kean, Kennedy and Partners, Chartered Surveyors in Dumfries in 1980.

In 1988 he moved to work for Dumfries and Galloway Health Board as an Estates Building Officer.

He returned to Kean, Kennedy and Partners in 1989 to take up the post of Senior Quantity Surveyor.

In 1990 McGowan Miller Partnership were formed when Robert McGowan and David Miller bought out the Dumfries office of Kean, Kennedy and Partners. Stuart carried on the role of Senior Quantity Surveyor.

In 1995 Stuart qualified as a Chartered Surveyor, obtaining his MRICS qualification.

In 1998 he became a Partner with McGowan Miller Partnership.

Throughout his career in Quantity Surveying he has been involved in all aspects of construction including New Build, Alterations and Refurbishments. The range of projects he has been directly involved with have included retail and commercial, educational, health sector, residential and industrial.

For the Eskdalemuir Community Hub project Stuart has been the Partner in charge and has been responsible for preparing the cost plans, revenue cost predictions and liaising with all other members of the design team and client. Quantity Surveyor’s CV

Name Alan Thomson

Professional Qualifications Diploma in Surveying, The College of Estate Management

Employment History

1999 – Present McGowan Miller Partnership

General

Alan Thomson joined McGowan Miller Partnership in 1999. He obtained a Diploma in Surveying from The College of Estate Management, through a distance learning course between 2000 and 2003. He is currently undertaking his Assessment of Professional Competence (APC) with the view of gaining membership to the R.I.C.S.

Alan has been involved in a range of projects from small scale to large scale, ranging from refurbishment and alteration projects to new build projects. He also has experience of Building Warrants and Planning Application.

In 2002 he gained a City and Guilds in AutoCAD at Dumfries and Galloway College.

For the the Eskdalemuir Hub project Alan has been responsible for providing the quantities for the cost plans prepared and also for some of the costing. Throughout the process he has been liasing with Stuart Callander.

Curriculum Vitae

Christopher John Walters C.Eng., B.Sc.(Hons) Civ. Eng., M.I.C.E., F.Cons.E.

Qualifications

• Sept 1968 to June 1973 Hummersknott School Darlington O'Levels Maths, Physics, Chemistry, Biology, Art & Geography • Sept 1973 to June 1975 Queen Elizabeth Sixth Form O'Levels English Lang, Additional Maths College, Darlington A'Levels Maths, Physics & Chemistry

• Sept 1975 to June 1977 Darlington College of Technology O.N.C. Building Construction Cleveland Terrace, Darlington (Day Release)

• Dec 1977 to June 1979 Darlington College of Technology H.N.C. Building Construction (Day Release)

• October 1979 to June 1983 B.Sc. (Hons) C.Eng. (Upper Second CNAA Class) Sunderland Polytechnic

Employment

• October 1975 to March 1977 - Trainee Draughtsman - Design Trent Concrete Ltd, Precast Concrete Engineers, Bishop Auckland Detailing of precast concrete flooring and portal frames. Testing of precast flooring and concrete quality control Reason for Leaving - Factory closed making employees redundant

• May 1977 to November 1977 - Civil/Building/Mechanical Technician Union Carbide (UK) Ltd, Electronics Engineers, Aycliffe Ind Est, Darlington Worked with 2 factory Engineers on factory improvements, fig and tool design and supervision of sub-contractors labour Reason for Leaving - Returned to civil engineering to work with former colleague and to continue day release course which was not possible at Union Carbide Ltd

• November 1977 to October 1979 - Civil Engineering Technician W S Atkins & Partners, Church House, Grange Road Middlesborough Member of regional drawing office for firm of worldwide Consulting Engineers. Experience gained in design and detailing of reinforced concrete, structural steelwork, roadworks, drainage, structural surveying Reason for Leaving - Commenced a degree in Civil Engineering

• March 1980 to October 1980 - Industrial Training W S Atkins & Partners Employed as previous

• March 1981 to October 1981 - Site Engineer - South Tyne Metro Balfour Beatty Construction, Croythorn House, Ravelston Road, Initially employed on a 10 span prestressed concrete viaduct under a section Engineer. Following a 6 week period a reorganisation of the site staff meant that I was relocated at South Shields station. The work involved sole supervision of 30 B.B. employees and 10 subcontractors, Bonus calculations, planning of work ahead, ordering of materials and plant hire.

• March 1982 to October 1982 - Durham University Library Extension - Site Engineer Balfour Beatty Construction, Graduated June 1983 Member of small team of site staff constructing a 5 storey reinforced concrete frame with p.c. concrete/glazed infill cladding. Also the refurbishment of the existing library building. Duties included supervision of completion of finishes.

• June 1983 to February 1986 - Site Engineer/Sub-Agent Eden Construction, A595 Access Road - Construction of Trunk Road into BNFL Sellafield. Workington Marsh Development - Construction of roads/drainage and general land reclamation on former steelworks site - Contract on behalf of and supervised by Cumbria County Council. Reason for Leaving - Offered opportunity to gain design experience suitable to take Professional Interview (Chartered Engineer)

• February 1986 to Present - Senior Engineer/Associate Partner (1989) Partner (1992) Partner (1992 to Present) Bingham Yates & Partners, 38 Victoria Place, Carlisle

Refer to Practice Information for typical experience.

Practice Information

Name: Bingham Yates and Partners Date Founded: 1 June 1978 (The Bingham Yates & Partners practice was established on 1 June 1978 from the Edinburgh branch of Bingham Blades and Partners, (now part of the Mott Macdonald Group). The Carlisle office was opened in 1980. Partners: Christopher J. Walters B.S.c (Hons), C.Eng., M.I.C.E.,F Cons.E. Jonathan W Begg B.S.c., C.Eng., M.I.C.E., F.Cons.E.

The practice is a member of the Quality Guild, and the Association of Consulting Engineers.

Practice Description

The practice has always tried to maintain, wherever possible, a considerable client base and the company's expertise generally encompasses a wide and divers spectrum of commissions associated with Civil, Structural and Water Engineering. Our longstanding and well respected expertise also includes work on historic and listed buildings.

In addition, the practice completes regular checking of Local Authority Building Regulation Submissions on behalf of the following authorities:-

• Borough of Allerdale • Copeland Borough Council • South Lakeland District Council • Carlisle City Council

The practice has also been engaged by the majority of the above authorities to supervise site works and offer technical advice, particularly in the following areas :-

• Location of and temporary works, underpinning, foundation problems and the • location of grouting and old mine workings. • Historic buildings and dangerous structures • The practice has been appointed by Local Authorities in Scotland, to design and supervise highway works with a view to obtaining, Construction Consent and subsequent Adoption of the works and the practice is fully certified under the ‘Scheme for the Certification of Design’ (Building Structures) in accordance with the Scottish Building Regulations 2004.

JOHN T BENSON

Qualifications and Accreditations

Chartered Engineer Chartered Environmental Engineer CEnv Member, Institution of Mechanical Engineers, Institution of Electrical Engineers (IET) Trade Member, International Association of Amusement Parks and Attractions Member, Construction Line Past Chairman of European Brewery Convention Energy Committee Past Committee Member for Brewers Society Environmental Committee

John has a considerable in-depth knowledge and experience, gained over a period of 40 years, of project, technical and managerial issues related to building construction and building services. He was also responsible for the design, construction and project management of buildings and facilities in Germany, USA and Australia, covering the whole range of building services involving the control and management of multi-disciplinary teams, with relevance to Pharmaceutical and Health Care Industries. Many years experience in local authority education and housing developments, hotels, shops and offices.

Key Projects

M&E services to various schools, i.e. WLC locations including Ground Source Heat Pumps to Longridge and Torphichen Schools Biomass Boiler installation at Eskdalemuir, Clairmount Church and Dumfries Royal Infirmary Initiation of leisure projects for S&N Plc involving feasibility study, scheme design & liaison with tenants to achieve programmed completion Construction of leisure swimming pool facilities for City of Edinburgh Council Construction of Collagen manufacturing facilities in Germany, USA, Canada & Australia for Johnson & Johnson for Pharmaceutical & Health Care Products Design and construction of laboratory facilities for research establishments, covering Pharmaceutical and Health Care Products M&E services to Midlothian Housing (8 sites) incorporating renewable energy Design and build of corporate offices incorporating renewable energy

Relevant Experience & Skills

Responsible for the technical & financial performance of projects in varied industries examples being:

Feasibility Studies for micro hydro schemes, wind turbine and group source heat pumps Development of Energy Conservation Schemes for industrial applications at Michelin Tyres Plc, Interfloor Ltd, S&N and Gates Power Transmissions Ltd Direction and supervision of over 50 energy audits including renewable energy for the EST Energy Management and Provision of Innovative solutions to Local Authorities and Commercial Developments Sterilising Unit Edinburgh Royal Infirmary to achieve audit compliance Electrical design for schools West Lothian Council BREAAM assessment for hotels Corporate Head Quarters development – Dumfries & Galloway Council Knowledge of Care Home Standards and DDA Requirements Knowledge of SPP6 & application of sustainable development issues MARCUS STOUT

Qualifications

Chartered Engineer Member, Institution of Engineering and Technology (MIET)

Marcus has extensive experience in the design of electrical installations within the construction industry and has been involved in many major projects with Blyth & Blyth Consulting. His expertise including the following elements: high voltage and low voltage switchgear and distribution networks, conventional office lighting, specialist lighting systems, theatre stage lighting and luminaire design, communications systems including broadcast radio and television services, telephone networks, data communication systems, security systems including CCTV, intruder alarms, lifts, escalators and building management systems.

Key Projects

Phased refurbishment of the National Archive Building for Scotland. The building is Grade A listed and will benefit from new IT infrastructure system, voice evacuation fire alarm system and specially designed light fittings to compliment the building features A full refurbishment of the Trust premises at 26-31 Charlotte Square, Edinburgh to provide modern office accommodations for the new Millennium. The building is Grade A lists and a major part of the brief was to maximise concealment of new services within the building frame. A fully co-ordinated mock-up was built to act as the acceptable benchmark Refurbishment of five lighthouses in Hebrides, Orkney and Shetland for Northern Lighthouse Board. The work encompassed the conversion of each lighthouse from gas power to solar and wind power Design of enhanced distribution systems of Leeds Local Authority including fire alarms and lighting systems for schools St Enochs , St John’s Perth, design of electrical distribution, IT infrastructure & lighting systems M&E design to Perth Leisure Pool and Bells Leisure Centre

Relevant Experience & Skills

Installations of turbines on five lighthouses Self sustaining energy systems for lighthouses including photovoltaic & wind turbine technology Corporate headquarters rebuilding – Scottish & Newcastle using ice storage systems Knowledge of sustainable development and SPP6 Extensive knowledge of High, Medium and Low voltage supply and distribution systems KEITH CAMPBELL

Qualifications

Postgraduate diploma in Sustainable Energy Systems – University of Edinburgh 2005-2006 Bachelor of Mechanical Engineering (BEng.) 2/1 – University of Edinburgh 2001-2005

Keith has a thorough understanding of mechanical systems, renewable technology, sustainability and economics of the UK energy industry which have been developed during his years at university. His university education also introduced skills in project management, collaborative assignments, presentations and report writing.

Since joining Turner Technical Services in April 2008 Keith has worked on a variety of projects in locations throughout Scotland including renewable projects such as wind turbine and solar panel installation, rain water harvesting, energy efficient heating system upgrades and contributed to a number of energy audits performed on behalf of the Crichton Carbon Centre and Energy Saving Trust.

Key Projects

Gained experience through involvement in the TTS installation of an 11kW wind turbine at Currie Community High School near Edinburgh. Currently progressing a project for multiple solar thermal panel installations at Oatridge College in Broxburn, West Lothian. Planned the design and installation of a replacement energy efficient boiler, system and controls at the Rowan Tree Nursery in Edinburgh. Conducting a feasibility study into a potential rain water harvesting scheme near Falkirk.

Relevant Experience & Skills

Contributed to approximately 20 energy audits and design advice reports on behalf of the EST. Knowledge of a variety of renewable energy technologies and able to assess their suitability for a project based on location, practicality, economics and available resources. Ability to perform feasibility studies including data gathering, analysis and preparation of reports for a number of different technologies. Attended seminars and training events such as the Gaia Wind seminar entitled “Wind Energy and Marketing & Sales. Familiarisation with thermal camera imaging and related software gained during a training seminar provided by thermal camera experts FLUKE. Able to plan projects and manage contractors to ensure satisfactory results and timeous completion of works. Attended Health & Safety training to ensure up to date knowledge of health and safety regulations. Organisation and compilation of accident report file following an incident involving a contractor during a TTS project at the Gates Power Transmission facility in Dumfries. Preparation of documentation for proposed projects including method statements and risk assessments in order to comply with Health & Safety regulations. KENNY LUNN

Qualifications

B Eng (Hons) Energy and Environmental Engineering HNC - Heating, Ventilation and Air-conditioning

Kenny has extensive experience in the design of mechanical building services installations within the construction industry and has been involved in many major projects over the past 5 years. His expertise includes the following elements: ventilation design, heating design, water services design, air-conditioning design, renewable energy technologies.

Key Projects

Original C & A Building, Princes Street, Edinburgh Phased refurbishment and full mechanical design to old C&A building on Princes Street,, Edinburgh. All designed under strict guidelines laid out by planners.

Ninewells Hospital, Dundee Survey and design work undertaken throughout the whole of Ninewells Hospital in Dundee. Many extensions and upgrades to meeting rooms and plant rooms. Worked directly for client and met all his needs.

Perth Royal Infirmary, Perth Perth Royal Infirmary, two new extensions to the building with full mechanical and electrical design. Shared plant room with other designers.

John McIntyre Centre at Pollock Halls, Edinburgh John McIntyre Centre at Pollock Halls, Edinburgh. Extension to existing building which phased throughout the project due to building being used by the students all year round. Very challenging for phasing works throughout entire project.

Relevant Experience & Skills

Survey and report writing skills at high level Rain water harvesting system design and installation Ground source heat pump design carried out on various projects Produce design drawings to a high standard High standard when it comes to client care issues Knowledge of renewable energy technologies Knowledge of BREAM and SBEM calculation method

17.0 Photographs of existing building and site North elevation from adjacent property Existing south entrance to extension

Junction of existing extension and original school building, north elevation South elevation looking towards the public road

Junction of existing extension and original school building, south elevation North Elevation

West Elevation Existing classroom

Existing classroom Existing entrance Existing rear corridor

Existing WC and store 18.0 Outline Technical Specification 08006 ESKDALEMUIR COMMUNITY HUB - OUTLINE CONSTRUCTION SPECIFICATION

Demolition

Existing Extension To Be Demolished As Indicated, Contractor To Retain As Much Recyclable Material As Possible (To Be Agreed With Ca)

Demolition Procedures Described In Bs 6187, Section 19 Should Be Followed. See Also Hse Guidance Hs(G) 150 , 151, And Hse L144 'Construction And Design Management 2007 Approved Code Of Practice' Particularly In Relation To The Construction (Design And Management) Regulations 10, 20 And 29, And Bs 6187, Sections 7, 9 And 10. Risk Assessments (Ras) For The Removal And Disposal Of Asbestos-Containing Materials.

Foundations

Gen 3 (C20) Strip Foundations Sized In Accordance With Structural Engineers Specification 150Mm Scarcement With A393 Mesh (T) With Min 50Mm Cover. Foundations In Accordance With Bs En 1997-1:200 And Bs 8804:1986 (Superceeded But Still Referenced In Building Regulations) Bottom Of Foundation Trench To Be Inspected By Building Control Before Concrete Is Poured. Concrete To Bs5328;1990 To Achieve 20N/Mm Crushing Strength At 28 Days Or Equal Mix Prepared On Site. Trench Excavation 600Mm Below Proposed Ground Level Or Deeper When Required To Reach Good Foundation Bearing Strata To Architects Satisfaction. Where Site Levels Have Been Reduced To Remove Topsoil The Depth Of The Excavation To Be Minimised To Provide 450Mm Minimum Final Cover. Localised Soft Or Wet Spots To Be Fully Excavated And Filled With Weak Mix Concrete. Supervising Architect/Engineer To Be Called To Advise If Unusually Wet Or Inconsistent Subsoil'S Encountered During Excavations.

Substructure

Clay Bricks To The External Leaf Of A Cavity Wall Below Dpc (The Visible Portion Of Facing Brickwork From Below Dpc To, Usually, 150 Mm Below The Finished Ground/ Paving Level). Built Off A Common Concrete Blockwork Leaf, Or Foundation Blockwork, Clay Bricks To Bs En 771-1 . Existing Second Hand Bricks From Demolition To Be Inspected By Engineer And If Suitable Re-Used As The Visible Building Basecourse. Below Ground Blockwork In Accordance With Bs5268 (7 N/Mm2 Min. Density 1950 Kg/M3 . Mortar For Use Below Dpc Level To Comply With The Recommendations Of Bs5628 Part 3. Where Sulphate Contamination Is Encountered, The Mortar Is To Contain Sulphate Resisting Cement To Comply With Bs4027. Fill Walling To 300Mm Below Dpc Level. Cavity To Remain Clear For 225Mm From Lowest Dpc As Part C Requirements. Lintols Over All Pipe/Drain/Service Entries With Precast Concrete Lintols In Each Leaf With Minimum End Bearing Of 150Mm. 08006 ESKDALEMUIR COMMUNITY HUB - OUTLINE CONSTRUCTION SPECIFICATION

Ground Floors

Min 75Mm Thickness Fine Concrete Floor Screed To Be Laid On 150Mm Rockwool Rockfloor Insulation On A 1200 Gauge Dpm On Proprietory Beam And Block Floor By Acp Concrete Or Similar. 150Mm Prestressed Concrete Beams At 525Mm C/C In Accordance With B.S.8110 1985 Using Grade C60 Concrete And A Cover To Reinforcement To Satisfy The ‘Moderate’ Exposure Condition As Defined In B.S.8110.Blocks To Be 100Mm Thick, Manufactured In Accordance With B.S.6073 1981. Block Strength Shall Be A Minimum Of 7.0 N/Mm2.

To Provide A Min 'U' Value Of 0.20 (W/M2K). Min 25Mm Rigid Perimeter Insulation To Edge Of Screed To Prevent Cold Bridging

Superstructure

New Walls Above Dpc To Be Generally 250Mm Wide Cavity Construction (50Mm Cavity) In Dense Concrete Block Finished With Cement Render Internally (To Maximise Internal Thermal Mass). External Walls To Be Overclad In Min 150Mm Rockwool Rainscreen Duo Clad Insulation Between 150X38Mm Vertical Treated Timbers At 600Mm C/C Or Specialist Metal Cladding System With 25Mm Battens Over To Fix Larch Cladding (Locally Sourced) Structural Masonry In Accordance With Bs 5628: Part 1: 1992, Part 2: 1995 & Part 3: 1985 - Target U-Value 0.20W/M2K

All New Glazing To Comply With The Following: Toughened Glass Within 800Mm Of Floor Level At Windows, Doors And Sidescreens. All Glass To Resist Human Impact As Set Out In Bs 6262: Part 4: 2005 All Toughened Glass Panels To Be Individually Marked To Conform With Bs 6206: 1981. Target U Value Of Windows 1.6 W/M²K

First Floor

Hollowcore Precast Or Solid Composite Floor Beams (Depth Depending On Strucutral Engineer Calculations) Supported On Steel To Engineers Specification. Concrete Foor Slab Soffit To Remain Exposed (Painted). Tongue And Groove Chipboard On Circa 50Mm Rockwool Rockfloor Insulation To First Floor Level With Floor Covering To Be Confirmed.

Roof

All Structural Timber To Be Treated Against Insect And Fungal Attack; Roof Trusses To Be Designed & Braced In Accordance With Bs 5268 Part-2:2002 And Part 3:2006; Where Applicable Truss Manufacturer Is To Issue Certificate Of Compliance Before Manufacture; Designed For Loadings As In Bs6399: Part 1: 1996, Part 2:1997 & Part 3: 1988.

All Trusses To Have Full Support On Load Bearing Walls; Wall Plate To Be Securely Fixed To Inner Leaf Using 30X5Mm Galvanised Ms Angle Straps To Bs2989:1982: Class 22 Coating Type 0275 Fixed Either Side Of Openings At Max 1200Mm Centres Length Of Strap 1000X150Mm With 5No Fixings; Rafter Legs Secured To Wall Plate Using Galvanised Truss Clips At Each Truss

Gable Restraint Straps To Be Provided At 2.0M Max Centres At Both Rafter And Ceiling Tie Level. Straps To Be Fixed Over 2 No. Min. Trusses And Carried Down And Secured Min. 500Mm Down The Cavity With Noggins (50X50Mm) Between Rafters. 08006 ESKDALEMUIR COMMUNITY HUB - OUTLINE CONSTRUCTION SPECIFICATION

Roof Coverings

Sloped Roof Section Comprises Natural Slate On Proctor Roofshield Breathable Memberane On 20Mm Sarking Board On 50Mm Rockwoo Rockfall Warm Pitched Roof Insulation. 140Mm Rockwool Flexi Insulation Between Rafters With (Duplex Or Vapour Barrier Below) Plasterboard Fixed Internally Below Rafters And Finished With A 3Mm Gypsum Plaster Skim Coat. Roof Insulation To Give Minimum U-Value Of 0.20W/M2K Flat Roof Sections = Circa 170Mm Rockwool Hardrock Dual Density Roofing Boards In Combination With Mechanically Fastened Single Ply Membrane System (Sarnafil Or Similar), 19Mm Timber Deck With 12.5Mm Plasterboard And Skim Fixed To Timber Joists To Give Min U-Value Of 0.20W/M2K

Internal Partitions

Structural Ground Floor Partitions To Be Recycled Brick (From Demoliton) With Sand Cement Render (Painted). Thickness And Support To Engineers Details.

Non-Load Bearing Partitions Constructed With 100Mm Timber Studs (Generally) With 50Mm Acoustic Mineral Wool Insulation Between. 1No Layers Of 12.5Mm Gyproc Soundbloc Or Similar Sound Deadening Plasterboard To Either Face Of Partition. Wedi Board Tile Backer To Be Used In Wet Areas. Internal Partitions To Be Butted Tight Against Existing/New Ceiling.

Electrics

All Electrical Work To Be Designed By M&E Engineer And Be Carried Out By A Competent Electrical Contractor. The Installation, Ie The Design, Construction, Inspection And Testing Will Be Completed In Strict Accordance With Bs7671:2008 (Iee Wiring Regulations, 17Th Edition). And In Compliance With Other Building Regulations, In Particular, Will Not Compromise Fire-Stopping, Structural Integrity, Sound Insulation, Thermal Insulation And Other Related Matters. The Contractor Will Provide The Relevant Certification At The Completion Of This Part Of The Work. The Electrical Services Shall Comprise The Following Elements: Low Voltage Switchgear Normal And Emergency Lighting Small Power Earthing Fire Alarms Perimeter Security Alarms It And Telephone Wiring Mechanical Services Supplies Relocation Of 12No. Pv Panels On The Roof

Mechanical Services

The Mechanical Services Shall Comprise The Following Elements: Hot & Cold Water Services Heat Recovery Ventilation Systems Low Pressure Hot Water Heating Biomass Boiler (Excluding Plant Room And Fuel Store) Installation Of 2 No. Existing Air Source Heat Pumps Relocate Existing Wood Burning Stove 08006 ESKDALEMUIR COMMUNITY HUB - OUTLINE CONSTRUCTION SPECIFICATION

Internal Fittings

Commercial Kitchen To Have Walls Clad In Stainless Steel Commercial Grade Stainless Steel Worktops And Appliances

Sanitary Fittings By Armitage Venesta Or Similar, Full Doc M Pack To Be Fitted As Indicated

External Works

External Works Around The Building Comprise Of Re-Instatement Of Footways And Construction Of Ramps, Predominently In Tarmac And Flags To Match The Existing. The Land Directly To The Rear Of The Property Is Mostly Taken Up With The Current Solar Array, But It Is The Intention To Remove Some Of The Existing Hardstanding And Turn The Ground Over To Community Gardens. Car Park To Be Laid In Hardcore With Tarmac To Entrance Bell Curve Only In Accordance With Highways Requirements.

Additional Landscaping Works Around Car-Park With Seating Area And Edible Landscape Made Up Of Indigiounous Planting. Car Park Levels To Remain Unaffected To Maintain Existing Flood Plain Capacity.

Lift

Buckingham' Platform Lift By 'Ability Lifting Solutions' Or Similar Approved Dda Compliant Freestanding Vertical Plaform Lift Installed In Location As Indicated On Plan. 19.0 Planning Permission

20.0 Appendix