<<

Bartlesville Skate Park at Lee Lake Bid # 2019-2020-026

ADDENDUM NO. 1 14 APR 2020

ISSUED TO ALL BID DOCUMENT HOLDERS OF RECORD: This Addendum forms a part of the Contract Documents and Specifications described above. The original Contract Documents and Specifications remain in full force and effect, except as modified by the following, which shall take precedence over any contrary provisions in the prior documents.

I. ADDENDUM ACKNOWLEDGEMENT: The Addendum Acknowledgement included at the back of this Addendum must be signed and returned with your bid proposal. Failure to return this form acknowledging receipt of the addendum shall be grounds to reject the bid proposal.

II. SPECIFICATION REVISIONS: A. Section: Summary of Work For Bid Packages: 1. ADDED Bid Package 1 Bid Alternate 2 for the Diamond Grind Coping, DG-50 in lieu of Steel Coping as shown on Sheet SP-7. 2. MODIFIED Bid Package 2 General Scope of Work Note 8 to include estimated earthwork quantities for the Base Bid and also an Alternate Bid for the Peanut Bowl earthwork. 3. DIVIDED Bid Package 2 into a Base Bid item and an Alternate Bid Item. The Base Bid item covers Clearing, Grubbing, Earthwork & Drainage for the Bid Package 1 Base Bid Item (Skate Park Fish Bowl and Street Section). The Alternate Bid Item covers Clearing, Grubbing, Earthwork & Drainage for the Bid Package 1 Alternate Bid Item (Peanut Bowl). 4. Pages BPF-1 thru BPF-9 have been included with this Addendum and shall replace BPF-1 thru BPF-8 that were included with the original documents.

III. GENERAL CLARIFICATIONS:

A. The Geotechnical Report associated with this project has been provided with this Addendum.

B. The 5’ wide concrete sidewalk and 2’ wide concrete capping located at the north side of the skate park site shall be included in the Bid Package 1 Base Bid. This includes all items of work necessary to construct the sidewalk and concrete capping.

1

Bartlesville Skate Park at Lee Lake Bid No. 2019-2020-026

ADDENDUM NO. 1 14 APR 2020

C. Power and water supply are in the vicinity of the site but are limited. There is a hose bib and electrical panel on the restroom building located approximately 150 feet northeast of the site. The building is white with a blue roof and can be seen in the aerial on Sheet L- 3. Power and water is likely not sufficient for a job trailer or other large usage, but is available for minor power and water needs. If larger quantities of water are required, the contractor can obtain a fire hydrant meter from the City of Bartlesville, however the closest hydrant is on the south side of Adams Boulevard that lies adjacent to the south side of the Lee Lake Park site. A deposit is required for the hydrant meter that will be reimbursed upon return of the meter. Water used in association with this project is free of charge. If additional power needs are required, the contractor shall be responsible for coordinating temporary construction site power with AEP/PSO.

(Sign Addendum Acknowledgement on next page and turn in with Bid Proposal)

2

Bartlesville Skate Park at Lee Lake Bid No. 2019-2020-026

ADDENDUM NO. 1 14 APR 2020

ADDENDUM ACKNOWLEDGEMENT

The undersigned acknowledges receipt of Addendum No. 1, and the bid submitted is in accordance as set forth herein.

Name of Bidder

By:

Date:

3

BID PROPOSAL FORM Bartlesville Skate Park at Lee Lake Bid No. 2019-2020-026

THE UNDERSIGNED BIDDER, having examined the plans, specifications, the locations, arrangements and conditions of , streets, utilities and other facilities or appurtenances which affect or may be affected by the proposed work, the actual sites of the proposed improvements and being acquainted with and fully understanding: (1) the extent and character of the work covered by this proposal; (2) the locations and specified requirements of and for the proposed improvements and other items of work appurtenant thereto; (3) the normal existing, and probable construction difficulties, hazards or all other factors or conditions which may or may not be apparent, which may affect or be affected by the specified work. HEREBY PROPOSES to furnish all required supplies, equipment, tools, and plant; to perform all necessary labor; and to install, construct, and complete all work stipulated in, required by, and in accordance with the contract documents hereto attached, for and in connection with the contract for which this proposal is herein submitted for and in consideration of the prices set out herein. The undersigned bidder hereby agrees to furnish the required Performance Bond, Statutory Bond, Maintenance Bond, and proof of insurance and to enter into a contract within fourteen (14) days after the acceptance of this proposal, and further agrees to complete the work within a period of time not to exceed One Hundred (100) working days following receipt of the Owner’s Work Order authorizing the Contractor to commence work. Attached hereto is a Certified Check, Cashier’s Check or Bidder’s Surety Bond in the amount of: DOLLARS $ which the undersigned agrees is to be forfeited to and become the property of the City, as liquidated damages, should this proposal be accepted and the contract be awarded to him, he fails to enter into a contract in the form prescribed and to furnish the required bonds and proof of insurance within fourteen (14) days as above stipulated, but otherwise the proposal guarantee shall be returned to the undersigned upon the signing of the contract and delivery of the approved bonds and evidence of insurance to said Owner. DATED this day of , 2020

If an Individual: d. b. a.: Signature: If a Partnership: Signature: Typed Name: If a Corporation: Signature: Typed Name: Title

ATTEST:

Secretary

(CORPORATE SEAL)

Bid Packages on following pages.

BPF-1 BID PROPOSAL FORM Bartlesville Skate Park at Lee Lake Bid No. 2019-2020-026

BID PACKAGE 1: SKATE PARK

PROJECT: Bartlesville Skatepark at Lee Park

Scope of Work

The proposed work consists of construction of the New Skatepark at Lee Park in the City of Bartelsville, Oklahoma. Qualified Skatepark Contractor to provide all labor, material, transportation, coordination, competent supervision, miscellaneous material and incidentals, inspections & fees, freight, incidental material handling, equipment, equipment rental, tools, etc. to complete the New Skatepark at Lee Lake and related site improvements.

Work shall include:

The “work” as specified in this agreement is defined as complete “turnkey” installation. The term “provide” under these terms and conditions shall mean to furnish and install the work. The work as specified in this agreement specifically includes but is not limited to the following:

Scope of Work not included

(1) Preliminary site preparation of site including excavation of native , importing of compactible fill dirt, compacting fill in lifts, and laying drain pipes.

General Scope of Work

(1) Provide all mobilizations necessary to complete this scope of work. (2) Contractor will be responsible for all field measurements and coordination with any and all other trades related to the skatepark construction, including the contractor completing the preliminary site work. (3) All work under this subcontract shall be scheduled and performed in accordance with an overall schedule that will allow the project to be completed per the schedule attached in bid manual. Subcontractor agrees to work as and when directed by the City of Bartlesville. Coordination with the City of Bartlesville project manager, superintendent, and with other subcontractors is mandatory, and deviations from the construction schedule resulting from subcontractor’s failure to timely perform its work and/or to coordinate its work as required herein are not acceptable, and may be grounds for termination of contract. The construction schedule may be revised from time to time, and may require Contractor to perform work outside of normal business hours, on weekends and/or include more than 40‐hour work weeks. The cost of all resources needed to maintain the overall scheduling goals, as reflected in the original or any revised schedules, is included in Contractor’s price, and Contractor shall not be entitled to additional compensation resulting from such effort unless and except to the extent Contractor receives additional compensation from the Owner. All efforts shall be made by the Contractor to overcome and mitigate any inclement weather, regardless of whether an extension of time is allowed in the overall schedule. (4) Clean up debris generated by this work daily and deposit in a container or location designated by the City of Bartlesville. Dispose of any hazardous material debris offsite in a legal manner. (5) Protect other work, adjacent surfaces, and equipment from damage. (6) The City of Bartlesville is not responsible for the theft or vandalism of any materials or equipment. Contractor is to take all measure necessary to prevent losses without negatively affecting the schedule. (7) This contract is exempt from sales tax for materials incorporated into the project. (8) This contract shall include attendance of weekly Contractor coordination meetings. The Contractor shall send a representative with the authority to make decisions on behalf of the Contracting company. (9) This Contractor shall include weekly construction reports. (10) This Contractor shall include a full time competent superintendent/foreman that has the ability to act on behalf of this Contractor. This full time superintendent/foreman will be an employee of the contracted company and must be onsite anytime work for this scope of work is being performed. Documentation of this will be required. (11) Provide mock‐ups as required. (12) Skate Park Contractor will be responsible for completing finish adjacent to skate park amenities once complete, including seeding and mulching remaining disturbed areas. (13) Upon award of contract, Skate Park contractor shall coordinate all items of work and schedule with City of Bartlesville representatives and contractor responsible for Bid Package 2 scope of work (clearing & grubbing, earthwork, and drainage) to facilitate a complete project.

The bid items shall include all improvements specified with the scope of work for the bid package. Any item not specifically listed as a pay item shall be considered subsidiary to other bid items of work.

BPF-2 BID PROPOSAL FORM Bartlesville Skate Park at Lee Lake Bid No. 2019-2020-026

BID PROPOSAL FORM – BID PACKAGE 1: Skatepark

THE UNDERSIGNED BIDDER, having examined the plans, specifications, the locations, arrangements and conditions of roads, streets, utilities and other facilities or appurtenances which affect or may be affected by the proposed work, the actual sites of the proposed improvements and being acquainted with and fully understanding: (1) the extent and character of the work covered by this proposal; (2) the locations and specified requirements of and for the proposed and other items of work appurtenant thereto; (3) the normal existing, and probable construction difficulties, hazards or all other factors or conditions which may or may not be apparent, which may affect or be affected by the specified work.

HEREBY PROPOSES to furnish all required supplies, equipment, tools, and plant; to perform all necessary labor; and to install, construct, and complete all work stipulated in, required by, and in accordance with the contract documents hereto attached, for and in connection with the contract for which this proposal is herein submitted for and in consideration of the prices set out herein.

The undersigned bidder hereby agrees to furnish the required Performance Bond, Statutory Bond, Maintenance Bond, and proof of insurance and to enter into a contract within fourteen (14) days after the acceptance of this proposal.

List Name and Contact Information for Key Subcontractors Performing 10% or More of the Work in this Scope ______

______

Earliest Date Available to Start: ______

Proposed Duration of this Scope of Work: ______

Addendum No. ______Date Received______

Addendum No. ______Date Received______

Addendum No. ______Date Received______

Signature______

BID PACKAGE 1 BASE BID

PAY ESTIMATED UNIT DESCRIPTION OF PAY ITEM UNIT PRICE BID AMOUNT ITEM QUANTITY

1 1 LS Flow Bowl and Street Section

2 1 LS Engineer’s Allowance $5,000.00 $5,000.00

TOTAL BASE BID $ TOTAL BASE BID (IN WORDS)

BPF-3 BID PROPOSAL FORM Bartlesville Skate Park at Lee Lake Bid No. 2019-2020-026

BID PACKAGE 1 BID ALTERNATE 1

PAY ESTIMATED UNIT DESCRIPTION OF PAY ITEM UNIT PRICE BID AMOUNT ITEM QUANTITY

1 1 LS Peanut Bowl

TOTAL BID ALTERNATE $ BID PACKAGE 1 - TOTAL BID ALTERNATE 1 (IN WORDS)

Company:______Date:______

Contact Name: ______Phone Number:______

Email:______

BID PACKAGE 1 BID ALTERNATE 2

PAY ESTIMATED UNIT DESCRIPTION OF PAY ITEM UNIT PRICE BID AMOUNT ITEM QUANTITY Diamond Grind Coping, DG-50 in 1 1 LS lieu of Steel Coping as shown on Sheet SP-7

TOTAL BID ALTERNATE $ BID PACKAGE 1 - TOTAL BID ALTERNATE 2 (IN WORDS)

Company:______Date:______

Contact Name: ______Phone Number:______

Email:______

BPF-4 BID PROPOSAL FORM Bartlesville Skate Park at Lee Lake Bid No. 2019-2020-026

BID PACKAGE 2: Clearing & Grubbing, Earthwork and Drainage

PROJECT: Bartlesville Skate Park at Lee Lake

Scope of Work

Provide all labor, material, transportation, coordination, competent supervision, miscellaneous material and incidentals, inspections & fees, freight, incidental material handling, equipment, equipment rental, tools, etc. to complete the Clearing & Grubbing, Earthwork and Drainage portion of the Work.

Work shall include:

The “work” as specified in this agreement is defined as complete “turnkey” installation. The term “provide” under these terms and conditions shall mean to furnish and install the work. The work as specified in this agreement specifically includes but is not limited to the following:

Scope of Work not included (1) Construction of the skate park amenities including paving, aggregate for skate park pavement, excavation of skate park bowls, placement of sidewalk, and any other items of work directly associated with the final skate park construction beyond clearing & grubbing, earthwork, and drainage.

General Scope of Work (1) The earth moving scope of work includes but is not limited to rough grading, fine grading, finish grading, final grading, unclassified excavation, compaction, low volume change fill, engineered fill, common fill, drainage swales, berms, method B, and staking. (2) Provide temporary construction entrances and exits and maintain throughout construction. Remove and dispose at Construction Manager’s request. (3) All excess material to be disposed of offsite. (4) Provide potholing as required to locate existing utilities. (5) Provide dust control during demolition operations. (6) Provide all site clearing complete. (7) The site clearing scope of work includes but is not limited to clearing and grubbing, removal and disposal of surface debris, trees, shrubs, stripping and stockpiling , and disposal of excess materials. (8) Provide the earth moving complete. The Base Bid includes 2,100 CY estimated fill on skate park site. This is an estimated quantity and shall be used for bidding purposes as part of the lump sum contract. No additional compensation will be made for quantity overrun of the 2,100 CY estimated. The site is located within the regulated floodplain. The City of Bartlesville has a net zero fill policy in the floodplain. Therefore any imported fill material meeting the fill specifications will be removed from the compensatory storage area adjacent to the site and disposed of at an approved location not located within the floodplain. Final volume of material removed from this location will be dependent upon final volume of fill at skate park site based upon whether fill material is imported ODOT Select Borrow or if on site materials are modified and approved for use as fill. All items are part of the bid package. The Alternate Bid includes an additional 800 CY estimated fill for the peanut bowl and the same rules apply to the alternate bid item if awarded. (9) Provide the final grading of the skate park building pad area to facilitate installation of skate park. (10) Provide fine grading, seeding, and mulching for disturbed areas, estimated at 1.75 Acres. This is an estimated quantity and shall be used for bidding purposes as this is a lump sum contract. No additional compensation will be made for overrun of estimated value of disturbed areas for seeding and mulching. (11) Provide all site surveying, layout, and staking required by the contract documents. (12) Provide dewatering systems as required for completing this scope of work. (13) Provide final and finish grading of stockpiled topsoil. Import additional topsoil as required. (14) Notify utility locate company before any excavation commences. (15) Clean up debris and spoils generated by this work and legally dispose of materials and spoils. Dispose of any hazardous material debris offsite in a legal manner. (16) Provide daily street cleaning as required to maintain clean public streets. (17) Provide the storm sewer system complete. (18) The storm sewer system scope of work includes but is not limited to excavation, piping, pipe bedding material and placement, end sections, outflow structures, inlet structures, headwalls, sloped walls, and filter fabric. (19) Excluded from this subcontract are the following: concrete paving, asphalt paving, excavation of bowls for skate park construction, and aggregate under skate park pavement (20)Upon award of contract, earthwork contractor shall coordinate all items of work and schedule with City of Bartlesville representatives and contractor responsible for Bid Package 1 scope of work (skate park) to facilitate a complete project.

The bid items shall include all improvements specified with the scope of work for the bid package. This bid package is a lump sum, complete in place pay item. Any item not specifically listed above but required for a complete project shall be considered as part of the lump sum contract.

BPF-5 BID PROPOSAL FORM Bartlesville Skate Park at Lee Lake Bid No. 2019-2020-026

BID PROPOSAL FORM

THE UNDERSIGNED BIDDER, having examined the plans, specifications, the locations, arrangements and conditions of roads, streets, utilities and other facilities or appurtenances which affect or may be affected by the proposed work, the actual sites of the proposed improvements and being acquainted with and fully understanding: (1) the extent and character of the work covered by this proposal; (2) the locations and specified requirements of and for the proposed and other items of work appurtenant thereto; (3) the normal existing, and probable construction difficulties, hazards or all other factors or conditions which may or may not be apparent, which may affect or be affected by the specified work. HEREBY PROPOSES to furnish all required supplies, equipment, tools, and plant; to perform all necessary labor; and to install, construct, and complete all work stipulated in, required by, and in accordance with the contract documents hereto attached, for and in connection with the contract for which this proposal is herein submitted for and in consideration of the prices set out herein. The undersigned bidder hereby agrees to furnish the required Performance Bond, Statutory Bond, Maintenance Bond, and proof of insurance and to enter into a contract within fourteen (14) days after the acceptance of this proposal.

List Name and Contact Information for Key Subcontractors Performing 10% or More of the Work in this Scope

______

______

______

Earliest Date Available to Start: ______Proposed Duration of this Scope of Work: ______

BID PACKAGE 2 BASE BID PAY ESTIMATED UNIT DESCRIPTION OF PAY ITEM UNIT PRICE BID AMOUNT ITEM QUANTITY Clearing & Grubbing, Earthwork, and 1 1 LS Drainage for Skate Park covered in Bid Package 1 Base Bid 2 1 EA Engineer's Allowance $5,000.00 $5,000.00

TOTAL BASE BID $ BID PACKAGE 2 - TOTAL BASE BID (IN WORDS)

Company:______Date:______

Contact Name: ______Phone Number:______

Email:______

BPF-6 BID PROPOSAL FORM Bartlesville Skate Park at Lee Lake Bid No. 2019-2020-026

BID PACKAGE 2 BID ALTERNATE 1

PAY ESTIMATED UNIT DESCRIPTION OF PAY ITEM UNIT PRICE BID AMOUNT ITEM QUANTITY Clearing & Grubbing, Earthwork, and Drainage for Skate Park 1 1 LS covered in Bid Package 1 Bid Alternate 1 (Peanut Bowl)

TOTAL BID ALTERNATE $ BID PACKAGE 2 - TOTAL BID ALTERNATE 1 (IN WORDS)

Company:______Date:______

Contact Name: ______Phone Number:______

Email:______

BPF-7 BID PROPOSAL FORM Bartlesville Skate Park at Lee Lake Bid No. 2019-2020-026

BID AFFIDAVIT

The following Non-Collusion Affidavits must accompany bid:

A. Non-Collusion Affidavit

STATE OF ) ) ss. COUNTY OF )

, of lawful age being first duly sworn on oath says that he is the agent authorized by the bidder to submit the attached bid. Affiant further states that the bidder has not been a party to any collusion among bidders in restraint of freedom of competition by agreement to bid at a fixed price or to refrain from bidding; or with any municipal official or employee as to quantity, quality, or price in the prospective contract, or any other terms of said prospective contract; or in any discussions between bidders and any municipal official concerning exchange of money or other thing of value for special consideration in the letting of a contract.

Name of Company

Signature of Authorized Agent

Subscribed and sworn to before me on this day of 20

(Seal) Notary Public

My Commission Expires:

BPF-8 BID PROPOSAL FORM Bartlesville Skate Park at Lee Lake Bid No. 2019-2020-026

BID AFFIDAVIT

B. Business Relationship Affidavit

STATE OF ) ) ss. COUNTY OF )

, of lawful age being first duly sworn on oath says that he is the agent authorized by the bidder to submit the attached bid. Affiant further states that the nature of any partnership, joint venture, or other business relationship presently in effect or which existed within one (1) year prior to the date of this statement with the architect, engineer, or other party to the project is as follows:

Affiant further states that any such business relationship presently in effect or which existed within one (1) year prior to the date of this statement between any officer or director of the bidding company and any officer or director of the architectural or engineering firm or other party to the project is as follows:

Affiant further states that the names of all persons having any such business relationships and the positions they hold with their respective companies or firms are as follows:

(If none of the business relationships hereinabove mentioned exist, affiant should so state.)

Subscribed and sworn to before me on this day of 20

(Seal) Notary Public

My Commission Expires:

BPF-9

June 15, 2018 Kleinfelder Project No.: 20190806.001A

Mr. Micah Siemers, P.E. City of Bartlesville, Oklahoma 401 South Johnstone Avenue Bartlesville, Oklahoma 74003 E-mail: [email protected]

Subject: Subsurface Exploration and Laboratory Test Results Proposed Bartlesville Skate Park Bartlesville, Oklahoma

Dear Mr. Siemers:

In accordance with your request, Kleinfelder has completed the authorized subsurface exploration and laboratory testing for the above referenced project. It is our understanding that City of Bartlesville is planning to build a Stake Park south of the Bartlesville Soccer Field and west of Cooper Dog Park at northeast corner of SE Adams Boulevard and Silver Lake . No plan has been provided to Kleinfelder at time of this report. However, it is expected that the Stake Park will have a footprint of approximately 100 feet by 100 feet.

Kleinfelder was retained to perform two borings and subsequent laboratory testing for the soil samples. recommendations for the proposed Skate Park were not requested and therefore were not included in our scope of work. Kleinfelder conducted the field work by drilling two borings on June 11, 2018 at locations shown on Figure 1, Boring Location Plan and Vicinity Map. A hand-held GPS unit was used to locate the explorations with an accuracy of 15 feet or less. The general site location is shown on top right corner of Figure 1, Boring Location Plan and Vicinity Map.

The borings were advanced using a 4-inch diameter hand auger to approximately 5 feet below existing ground surface. The samples were sealed and returned to our laboratory for future examination, classification, and testing. The borings were backfilled in accordance with the appropriate Oklahoma Water Resources Board Regulations.

Laboratory tests including sieve analyses, , and moisture contents were performed on four of the samples for classification purposes in general accordance with applicable standards. The results of the tests are presented on the respective boring logs and in attached Laboratory Test Results Summary Sheet.

Groundwater observations were made during and at completion of our drilling operations, and no groundwater seepage was observed. Field logs included visual classification of the materials encountered during drilling, as as drilling characteristics. Our final boring logs represent the engineer’s interpretation of the field logs combined with laboratory observation and testing of the

20190806.001A / TUL18L79922 Page 1 of 2 June 15, 2018 © 2018 Kleinfelder www.kleinfelder.com Interchange Business Park, 10835 East Independence, Suite 102, Tulsa, OK 74116-5680 p| 918.627.6161 f| 918.627.6262

samples. Stratification boundaries indicated on the boring logs were based on observations during our field work, an extrapolation of information obtained by examining samples from the borings, and comparisons of with similar engineering characteristics. Locations of these boundaries are approximate, and the transitions between material types may be gradual rather than clearly defined. Boring logs are attached.

Boring B-1 and B-2 consisted of primarily fat to the termination depth of the borings, which is 5 feet below existing ground surface. The plastic limit of the fat clay ranged from 56 to 70 while the plasticity index ranged from 32 to 44.

Clay soils that have a moderate to high shrink-swell potential were encountered in both of the borings. Depending upon the design grades, these materials could be exposed at the finish subgrade level. Undercutting or stabilization of these soils should be anticipated. Typical remedial measures include treating the material with hydrated lime, cement kiln dust (CKD) or Class C fly ash in accordance with ODOT Method OHD L-50. A mix design is beyond the scope of this project. However, Kleinfelder can assist during the construction phase of the project if required.

We recommend that all structural fill placed required to achieve design grades consist of approved materials, free of organic matter and debris. All structural fill placed within the pavement area should consist of lower plasticity soil with a maximum Plasticity Index (PI) of 18 as determined by the Atterberg Limits test ASTM D 4318. In areas where high plasticity clay is present at design subgrade elevation, undercutting is recommended to allow placement of a minimum of 8 inches of low plasticity structural fill below the pavement section.

Information presented in this letter is based on our field observations, subsurface explorations, and limited laboratory tests. It is possible that subsurface conditions could vary between or beyond the points explored. We appreciate the opportunity to be of service to you on this project. Please call us if you have any questions concerning the information presented within this letter.

Sincerely, KLEINFELDER, INC. Certificate of Authorization #7292, Expires 6/30/19

Simon Wang, PE Joe Duin, CET Project Engineer Project Manager

SYW/JD: PAB

Attachments:

Figure 1. Exploration Location Plan and Vicinity Map Boring Logs Laboratory Test Results Summary Sheet

20190806.001A / TUL18L79922 Page 2 of 2 June 15, 2018 © 2018 Kleinfelder www.kleinfelder.com Interchange Business Park, 10835 East Independence, Suite 102, Tulsa, OK 74116-5680 p| 918.627.6161 f| 918.627.6262 g LEGEND n a W S

: %

Y SOIL BORING B

SITE M A

4 ! 5 : 0

1 * : 0 1

8 1 0 2 / 5 1 / 6

NOTE: :

D BASE MAPPING AND VICINITY MAP CREATED FROM LAYERS

E £

T COMPILED BY ESRI PRODUCTS AND 2018 MICROSOFT T

O CORPORATION. COORDINATE SYSTEM: GCS WGS 1984 N L VICINITY MAP NOT TO SCALE P d x m . e r u g i F _ 6 0 8 0 9

1 The information included on this graphic representation has been compiled from a

0 variety of sources and is subject to change without notice. Kleinfelder makes no 2 \ representations or warranties, express or implied, as to accuracy, completeness, p 0 200 400 o timeliness, or rights to the use of such information. This document is not intended t k for use as a land survey product nor is it designed or intended as a construction s e design document. The use or misuse of the information contained on this graphic D \ representation is at the sole risk of the party using or misusing the information. 1 " = 200 SCALE IN FEET g n a PROJECT NO. 20190806 W FIGURE

S EXPLORATION LOCATION PLAN \ s r e DRAWN BY: SYW AND VICINITY MAP s U \ : CHECKED BY: JD C

City of Bartlesville Stake Park : 1 E L

I DATE: 06-15-2018 NE Corner of Hyw 60 and Silver Lake Rd. F

S

I Bartlesville, Oklahoma REVISED: - G Date Begin - End: 6/11/2018 Drilling Company: Kleinfelder BORING LOG B-1 Logged By: Arpan C. Drill Crew: Arpan C. Hor.-Vert. Datum: Not Available Drilling Equipment: Hand Auger Plunge: -90 degrees Drilling Method: Hand Auger Weather: Not Available Auger Diameter: 4 in. O.D. FIELD EXPLORATION LABORATORY RESULTS

Latitude: 36.74406° N Longitude: -95.95103° W PLOTTED: 06/15/2018 10:05 AM BY: SWang BY: AM 10:05 06/15/2018 PLOTTED:

Depth (feet) GraphicalLog Lithologic Description Sample Number Sample Type Counts(BC)= Blow in. Blows/6 Uncorr. Recovery (NR=No Recovery) USCS Symbol (%) UnitDry Wt. (pcf) Passing#4 (%) Passing#200 (%) Liquid Limit Index Plasticity (NP=NonPlastic) AdditionalTests/ Remarks TOPSOIL AS-1 4"

Fat CLAY (CH): dark brown, moist AS-2 4"

AS-3 4"

AS-4 4"

AS-5 4"

AS-6 4"

AS-7 4" CH 27.1 85 62 37

AS-8 4"

AS-9 4"

AS-10 4"

AS-11 4"

AS-12 4" CH 24.5 87 56 32

AS-13 4"

AS-14 4"

AS-15 4" 5 The hand exploration was terminated at GROUNDWATER LEVEL INFORMATION: approximately 5 ft. below ground surface. The Groundwater was not observed during drilling or after hand exploration was backfilled with auger completion. GENERAL NOTES: cuttings and bentonite on June 11, 2018.

BORING PROJECT NO.: 20190806 BORING LOG B-1 DRAWN BY: SYW

CHECKED BY: JD City of Bartlesville Skate Park B-1 DATE: 6/15/2018 NE Corner of Hwy 60 and Silver Lake Rd. Bartlesville, Oklahoma REVISED: - PAGE: 1 of 1 gINT FILE: Klf_gint_master_2017 PROJECT NUMBER: 20190806 OFFICE FILTER: TULSA OFFICE 20190806 NUMBER: PROJECT gINTKlf_gint_master_2017 FILE: LOG] SOIL PIT [__KLF_BORING/TEST E:KLF_STANDARD_GINT_LIBRARY_2017.GLB gINT TEMPLATE: Date Begin - End: 6/11/2018 Drilling Company: Kleinfelder BORING LOG B-2 Logged By: Arpan C. Drill Crew: Arpan C. Hor.-Vert. Datum: Not Available Drilling Equipment: Hand Auger Plunge: -90 degrees Drilling Method: Hand Auger Weather: Not Available Auger Diameter: 4 in. O.D. FIELD EXPLORATION LABORATORY RESULTS

Latitude: 36.74379° N Longitude: -95.95070° W PLOTTED: 06/15/2018 10:06 AM BY: SWang BY: AM 10:06 06/15/2018 PLOTTED:

Depth (feet) GraphicalLog Lithologic Description Sample Number Sample Type Counts(BC)= Blow in. Blows/6 Uncorr. Recovery (NR=No Recovery) USCS Symbol Water Content(%) UnitDry Wt. (pcf) Passing#4 (%) Passing#200 (%) Liquid Limit Index Plasticity (NP=NonPlastic) AdditionalTests/ Remarks TOPSOIL AS-1 4"

Fat CLAY (CH): dark brown, moist AS-2 4"

AS-3 4"

AS-4 4" CH 30.9 92 70 44

AS-5 4"

AS-6 4"

AS-7 4"

AS-8 4"

AS-9 4"

AS-10 4"

AS-11 4"

AS-12 4"

AS-13 4" CH 27.3 92 63 40

AS-14 4"

AS-15 4" 5 The hand exploration was terminated at GROUNDWATER LEVEL INFORMATION: approximately 5 ft. below ground surface. The Groundwater was not observed during drilling or after hand exploration was backfilled with auger completion. GENERAL NOTES: cuttings and bentonite on June 11, 2018.

BORING PROJECT NO.: 20190806 BORING LOG B-2 DRAWN BY: SYW

CHECKED BY: JD City of Bartlesville Skate Park B-2 DATE: 6/15/2018 NE Corner of Hwy 60 and Silver Lake Rd. Bartlesville, Oklahoma REVISED: - PAGE: 1 of 1 gINT FILE: Klf_gint_master_2017 PROJECT NUMBER: 20190806 OFFICE FILTER: TULSA OFFICE 20190806 NUMBER: PROJECT gINTKlf_gint_master_2017 FILE: LOG] SOIL PIT [__KLF_BORING/TEST E:KLF_STANDARD_GINT_LIBRARY_2017.GLB gINT TEMPLATE: Test Results ASTM D-422, D-2216, D-4318

Project Name: Bartlesville Skate Park Date Sampled: 6/12/2018 Project No. 20190806 Date Tested: 6/12/2018 Client: City of Bartlesville Date Reported: 6/14/2018 Prep Method: Dry Reviewed: JD Title: PM Additional Notes:

B-1 B-1 B-2 B-2 Sample Site

1 2 3 4 Sample No.

24" - 28" 44" - 48" 12" - 16" 48" - 52" Depth (ft)

CH CH CH CH USCS Class

Fat Clay, dark brown Fat Clay, dark brown Fat Clay, dark brown Fat Clay, dark brown

Atterberg Limits Liquid Limit (LL) 62 56 70 63 Plastic Limit (PL) 25 24 26 23 Plasticity Index 37 32 44 40

% Moisture 27.1 24.5 30.9 27.3 % Passing 3" N/A N/A N/A N/A % Passing 3/4" N/A N/A N/A N/A % Passing 3/8" N/A N/A N/A N/A % Passing #4 N/A N/A N/A N/A % Passing #10 N/A N/A N/A N/A % Passing #40 N/A N/A N/A N/A % Passing #100 N/A N/A N/A N/A % Passing #200 85.3 86.7 92.2 91.7

This report and/or any portion shall not be reproduced without written approval of Kleinfelder All documents shall remain the property of Kleinfelder as detailed in contract provisions. Results only related to items tested. Important Information about This Geotechnical-Engineering Report

Subsurface problems are a principal cause of construction delays, cost overruns, claims, and disputes.

While you cannot eliminate all such risks, you can manage them. The following information is provided to help.

The Geoprofessional Business Association (GBA) Typical changes that could erode the reliability of this report include has prepared this advisory to help you – assumedly those that affect: a client representative – interpret and apply this • the site’s size or shape; geotechnical-engineering report as effectively • the function of the proposed structure, as when it’s as possible. In that way, clients can benefit from changed from a parking garage to an office building, or from a light-industrial plant to a refrigerated warehouse; a lowered exposure to the subsurface problems • the elevation, configuration, location, orientation, or that, for decades, have been a principal cause of weight of the proposed structure; construction delays, cost overruns, claims, and • the composition of the design team; or disputes. If you have questions or want more • project ownership. information about any of the issues discussed below, contact your GBA-member geotechnical engineer. As a general rule, always inform your geotechnical engineer of project Active involvement in the Geoprofessional Business changes – even minor ones – and request an assessment of their Association exposes geotechnical engineers to a impact. The geotechnical engineer who prepared this report cannot accept wide array of risk-confrontation techniques that can responsibility or liability for problems that arise because the geotechnical be of genuine benefit for everyone involved with a engineer was not informed about developments the engineer otherwise would have considered. construction project. This Report May Not Be Reliable Geotechnical-Engineering Services Are Performed for Do not rely on this report if your geotechnical engineer prepared it: Specific Purposes, Persons, and Projects • for a different client; Geotechnical engineers structure their services to meet the specific • for a different project; needs of their clients. A geotechnical-engineering study conducted • for a different site (that may or may not include all or a for a given civil engineer will not likely meet the needs of a civil- portion of the original site); or works constructor or even a different civil engineer. Because each • before important events occurred at the site or adjacent geotechnical-engineering study is unique, each geotechnical- to it; e.g., man-made events like construction or engineering report is unique, prepared solely for the client. Those who environmental remediation, or natural events like floods, rely on a geotechnical-engineering report prepared for a different client droughts, , or groundwater fluctuations. can be seriously misled. No one except authorized client representatives should rely on this geotechnical-engineering report without first Note, too, that it could be unwise to rely on a geotechnical-engineering conferring with the geotechnical engineer who prepared it. And no one report whose reliability may have been affected by the passage of time, – not even you – should apply this report for any purpose or project except because of factors like changed subsurface conditions; new or modified the one originally contemplated. codes, standards, or regulations; or new techniques or tools. If your geotechnical engineer has not indicated an “apply-by” date on the report, Read this Report in Full ask what it should be, and, in general, if you are the least bit uncertain Costly problems have occurred because those relying on a geotechnical­ about the continued reliability of this report, contact your geotechnical engineering report did not read it in its entirety. Do not rely on an engineer before applying it. A minor amount of additional testing or executive summary. Do not read selected elements only. Read this report analysis – if any is required at all – could prevent major problems. in full. Most of the “Findings” Related in This Report Are You Need to Inform Your Geotechnical Engineer Professional Opinions about Change Before construction begins, geotechnical engineers explore a site’s Your geotechnical engineer considered unique, project-specific factors subsurface through various sampling and testing procedures. when designing the study behind this report and developing the Geotechnical engineers can observe actual subsurface conditions only at confirmation-dependent recommendations the report conveys. A few those specific locations where sampling and testing were performed. The typical factors include: data derived from that sampling and testing were reviewed by your • the client’s goals, objectives, budget, schedule, and geotechnical engineer, who then applied professional judgment to risk-management preferences; form opinions about subsurface conditions throughout the site. Actual • the general nature of the structure involved, its size, sitewide-subsurface conditions may differ – maybe significantly – from configuration, and performance criteria; those indicated in this report. Confront that risk by retaining your • the structure’s location and orientation on the site; and geotechnical engineer to serve on the design team from project start to • other planned or existing site improvements, such as project finish, so the individual can provide informed guidance quickly, retaining walls, access roads, parking lots, and whenever needed. underground utilities. This Report’s Recommendations Are perform their own studies if they want to, and be sure to allow enough Confirmation-Dependent time to permit them to do so. Only then might you be in a position The recommendations included in this report – including any options to give constructors the information available to you, while requiring or alternatives – are confirmation-dependent. In other words,they are them to at least share some of the financial responsibilities stemming not final, because the geotechnical engineer who developed them relied from unanticipated conditions. Conducting prebid and preconstruction heavily on judgment and opinion to do so. Your geotechnical engineer conferences can also be valuable in this respect. can finalize the recommendationsonly after observing actual subsurface conditions revealed during construction. If through observation your Read Responsibility Provisions Closely geotechnical engineer confirms that the conditions assumed to exist Some client representatives, design professionals, and constructors do actually do exist, the recommendations can be relied upon, assuming not realize that geotechnical engineering is far less exact than other no other changes have occurred. The geotechnical engineer who prepared engineering disciplines. That lack of understanding has nurtured this report cannot assume responsibility or liability for confirmation- unrealistic expectations that have resulted in disappointments, delays, dependent recommendations if you fail to retain that engineer to perform cost overruns, claims, and disputes. To confront that risk, geotechnical construction observation. engineers commonly include explanatory provisions in their reports. Sometimes labeled “limitations,” many of these provisions indicate This Report Could Be Misinterpreted where geotechnical engineers’ responsibilities begin and end, to help Other design professionals’ misinterpretation of geotechnical- others recognize their own responsibilities and risks. Read these engineering reports has resulted in costly problems. Confront that risk provisions closely. Ask questions. Your geotechnical engineer should by having your geotechnical engineer serve as a full-time member of the respond fully and frankly. design team, to: • confer with other design-team members, Geoenvironmental Concerns Are Not Covered • help develop specifications, The personnel, equipment, and techniques used to perform an • review pertinent elements of other design professionals’ environmental study – e.g., a “phase-one” or “phase-two” environmental plans and specifications, and site assessment – differ significantly from those used to perform • be on hand quickly whenever geotechnical-engineering a geotechnical-engineering study. For that reason, a geotechnical- guidance is needed. engineering report does not usually relate any environmental findings, conclusions, or recommendations; e.g., about the likelihood of You should also confront the risk of constructors misinterpreting this encountering underground storage tanks or regulated contaminants. report. Do so by retaining your geotechnical engineer to participate in Unanticipated subsurface environmental problems have led to project prebid and preconstruction conferences and to perform construction failures. If you have not yet obtained your own environmental observation. information, ask your geotechnical consultant for risk-management guidance. As a general rule, do not rely on an environmental report Give Constructors a Complete Report and Guidance prepared for a different client, site, or project, or that is more than six Some owners and design professionals mistakenly believe they can shift months old. unanticipated-subsurface-conditions liability to constructors by limiting the information they provide for bid preparation. To help prevent Obtain Professional Assistance to Deal with Moisture the costly, contentious problems this practice has caused, include the and Mold complete geotechnical-engineering report, along with any attachments While your geotechnical engineer may have addressed groundwater, or appendices, with your contract documents, but be certain to note water infiltration, or similar issues in this report, none of the engineer’s conspicuously that you’ve included the material for informational services were designed, conducted, or intended to prevent uncontrolled purposes only. To avoid misunderstanding, you may also want to note migration of moisture – including water vapor – from the soil through that “informational purposes” means constructors have no right to rely building slabs and walls and into the building interior, where it can on the interpretations, opinions, conclusions, or recommendations in cause mold growth and material-performance deficiencies. Accordingly, the report, but they may rely on the factual data relative to the specific proper implementation of the geotechnical engineer’s recommendations times, locations, and depths/elevations referenced. Be certain that will not of itself be sufficient to prevent moisture infiltration. Confront constructors know they may learn about specific project requirements, the risk of moisture infiltration by including building-envelope or mold including options selected from the report, only from the design specialists on the design team. Geotechnical engineers are not building- drawings and specifications. Remind constructors that they may envelope or mold specialists.

Telephone: 301/565-2733 e-mail: [email protected] www.geoprofessional.org

Copyright 2016 by Geoprofessional Business Association (GBA). Duplication, reproduction, or copying of this document, in whole or in part, by any means whatsoever, is strictly prohibited, except with GBA’s specific written permission. Excerpting, quoting, or otherwise extracting wording from this document is permitted only with the express written permission of GBA, and only for purposes of scholarly research or book review. Only members of GBA may use this document or its wording as a complement to or as an element of a report of any kind. Any other firm, individual, or other entity that so uses this document without being a GBA member could be committing negligent