Transportation Peel Holdings January 2011

Manchester Ship Company Water Level Control - Operational Protocol

Private and Confidential

Prepared by: ...... Checked by: ...... David Stork Roy Lobley Associate Director Associate Director

Approved by: David Stork Associate Director

Manchester Company Water Level Control - Operational Protocol

3rd Floor, 8 Princes Parade, Princes Dock, Liverpool, L3 1QH Telephone: 0151 331 8900 Website: http://www.aecom.com

Job No 60144094 Reference 60144094/REPORT/001 Date Created January 2011

This document is confidential and the copyright of AECOM Limited. Any unauthorised reproduction or usage by any person other than the addressee is strictly prohibited.

Table of Contents

1 Introduction ...... 2 2 Overview of the Manchester Ship Canal Water Level Control Structures ...... 4 2.1 The Water Level Control Structures from West to East ...... 4 3 Detailed Description of the Water Level Control Structures ...... 10 3.1 Overall Description of the Sluices ...... 10 3.2 Upper Reaches Sluices ...... 10 3.3 Weaver Sluices ...... 10 3.4 Gate Description ...... 10 3.5 Operating Machinery ...... 11 3.6 Control System ...... 12 3.7 Control System Communications...... 13 3.8 Other Water Level Control Structures ...... 13 4 Description of Normal Water Level Control ...... 16 4.1 Water Level ...... 16 4.2 Sluice Gate Control ...... 16 4.3 Effect of Tidal Conditions ...... 17 5 Description of Operational Control During High Water Flows ...... 19 5.1 Monitoring for High Water Flows ...... 19 5.2 Environment Agency Flood Warning Procedure ...... 19 5.3 Procedure in the Event of Anticipated High Water Flows ...... 20 5.4 Resources available ...... 21 5.5 Communication ...... 21 5.6 Training ...... 21 5.7 Testing of Backup Procedures ...... 21 6 Routine Maintenance and Major Maintenance/Capital Renewal Programme ...... 23 6.1 Routine Maintenance ...... 23 6.2 Major Maintenance ...... 24 6.3 Capital Renewal Programme ...... 24 7 Reliability of Sluice Operation ...... 26 7.1 Reliability Analysis ...... 26 7.2 Blockage of sluices and weirs by debris ...... 27 8 Working Arrangements ...... 29

AECOM

1 Introduction

AECOM 2

1 Introduction

The purpose of this document is to provide a robust operational protocol which recognises the close working relationship between the Environment Agency and the Manchester Ship Canal Company (MSCC) as it affects the control of water levels in the Manchester Ship Canal (MSC). The MSCC is part of Peel (Peel). It is the responsibility of the MSCC, to control the water levels in the Canal. The following is a brief description of the powers under which the Canal operates. The Manchester Ship Canal was authorised in 1885 under the Manchester Ship Canal Act 1885 (the 1885 Act). This gave MSCC various powers to build, manage and operate the Canal. Once constructed, the Canal facilitated navigation from the to Manchester. Subsequent Private Acts of Parliament were promoted to authorise new construction along the Canal and to regulate its operation. However, the main provisions relevant to the upper part of the Canal are set out in the 1885 Act. The 1885 Act provided, amongst other things, for the Company to be granted powers to work weirs, sluices, machinery, appliances and apparatus. Section 17 of the Regulation of Railways Act 1873 applies to the Company. This provision requires “every railway company owning or having the management of a canal to keep it at all times such canal and the works belonging thereto thoroughly repaired and dredged and in good working condition so that it may be at all times open to navigation for the use of all persons desirous to use and navigate the same”. The Company remains bound by this requirement as a statutory railway company. The Company is therefore required to ensure the Canal is at all times properly maintained. The controlling of the water level is part of this responsibility. Since the MSC was opened there have been many changes in the surrounding environment, especially the growth of Manchester, changes in weather patterns and changes in our understanding of flooding and its causes. The MSCC has successfully controlled the water levels since its opening but it is recognised that there is a need for a wider understanding of this process and how this successful record will be maintained. The sluice control system is used to control the water level for navigation purposes and in doing so it is also effective in preventing flooding in the locations surrounding the Canal. Sections 1 to 7 of this document describe the sluices, the risk of failure in a quantifiable form, the maintenance and refurbishment regime in place and MSCC procedures that need to be in place. Section 8 discusses the cooperation that is in place between the Environment Agency and Peel. MSCC is a Professional Partner of the Environment Agency. This will enable all stakeholders to have confidence in and recognise the effectiveness and reliability of the water level control system in providing a flood risk management capability. It will inform flood defence strategies for the land bordering on the Canal.

AECOM

2 Overview of the Manchester Ship Canal Water Level Control Structures

AECOM 4

2 Overview of the Manchester Ship Canal Water Level Control Structures

2.1 The Water Level Control Structures from West to East The Ship Canal was constructed by canalising the Rivers Irwell and Mersey above (the Upper Reaches) and by constructing a new water course between Latchford and Eastham (the Lower Reaches). See figure 9 for a schematic of the canal and the location of the various structures.

In addition to the Rivers Irwell and Mersey, main rivers such as the Salteye Brook, Sinderland Brook and run into the Canal in the Upper Reaches and the in the Lower Reaches. A large number of outfalls, including storm water outfalls, also discharge into the Canal.

In the Lower Reaches the Canal also receives water from two other sources:

• When High Water at the Weaver sluices is above the top of the gate, the River Mersey will overtop the sluice structure into the Canal. In these circumstances there will also be overtopping of the gates at Eastham;

• A set of what are referred to as ‘storm gates’ are fitted at Eastham Locks. They are designed so that when closed they prevent the River Mersey flowing into the Canal when it is at a higher level than the Canal during Spring High Waters. Under normal operations these gates are closed when the river is predicted to reach a higher level than the Canal. If they are not closed for any reason the River Mersey will flow into the Canal resulting in an increase in the water level to that of the river at Eastham, with a hydraulic gradient upstream of Eastham. The gates are occasionally kept open for operational reasons. They are kept closed if a storm surge is predicted.

The water level in the Canal is controlled by five sets of sluices and two weirs. On the Upper Reaches they consist of:

• Mode Wheel Locks - 4No sluices control the water level in the Mode Wheel Pond upstream of Mode Wheel Locks– See Figure 1;

Fig 1

• Barton Locks – 4No sluices control the water level in the Barton Pond, between Barton Locks and Mode Wheel Locks. In addition there is a hydro-generation plant located at Barton which can contribute to the available capacity. This is located in a building just downstream and separate to the sluices. It is fed from the sluice way through the 45ft lock wall - See Figure 2; Fig 2 AECOM 5

Locks – 5No sluices control the water level in the Irlam Pond, between Irlam Locks and Barton Locks – Figure 3;

Fig 3

• Latchford Locks – 3No sluices control the water level in the Latchford Pond, between Latchford Locks and Irlam Locks – See Figure 4;

Fig 4

• Woolston Weir - This weir contributes to the control of the water level in the Latchford Pond – See Figure 5;

Fig 5

AECOM 6

• Woolston Guard Weir. This weir is used to enable maintenance to be carried out on the Woolston and Howley weirs. It consists of 16 radial gates which are kept open in normal conditions. If maintenance is required on the weirs the gates are closed which reduces the flow of the River Mersey over Woolston and Howley Weir. This lowers the river level between the two weirs allowing maintenance work to be carried out. The gates would not be closed during periods of heavy sluicing - see Figure 6; Fig 6

• Howley Weir. This weir, although downstream of Woolston Weir can have an effect on the volumes Woolston Weir can handle in extreme tidal events. When this weir is overtopped the downstream water level at Woolston Weir is raised, so reducing the flow through the weir - see Figure 7;

Fig 7

The sluices at Mode Wheel, Barton, Irlam and Latchford control the water level by enabling the waters coming into the Canal from the Rivers Irwell, Mersey, and others detailed above, to be passed down the Canal in a controlled manner. In all but the most extreme low rainfall conditions there will be sluices operating on a regular basis at all locations apart from Latchford where they do not operate until flows down the River Mersey exceed 140cumecs.

The water level in the lower reaches is controlled by the following:

• Weaver Sluices – 8No sluices control the water level in the Eastham pond (Lower Reaches) between Latchford Locks and Eastham Locks – See Figure 8.

These sluices control the water level by enabling the waters coming into the Canal from the Rivers Weaver and from the Upper Reaches via Latchford Locks and sluices to be passed down the Canal in a controlled manner. Note that although there are 10 sluice positions only eight are fitted with machinery with which to operate the gates.

AECOM 7

Fig 8

A comprehensive study of the Canal and its operation in various flow conditions is provided in a Hydraulic Modelling Study carried out, and maintained for the Company, by consulting engineers Halcrow Group Ltd. The study explains how the various structures affect the canals hydrology during both fluvial and tidal events.

Section 4 & 5 of this Protocol includes a description of the sluice control system.

Comprehensive drawings of the sluice machinery are held by the MSCC.

Figure 9 shows the arrangement schematically. AECOM 8

Schematic of Manchester Ship Canal showing assets that contribute to managing flood risk Key Manchester Ship Canal (MSC)

X Lock

Sluice Gate

H Hydro Generation Unit < River Irwell

< Direction of flow

Weir/Sluice System Pond < MSC

Major Main River Mose Wheel Mode Wheel Locks X X 1 2 3 4 Major Non-main River

Tidal River < MSC X Lock (Barton Pond)

Barton Locks XX H 1 2 3 4 Salteye Brook >

< MSC

River Glaze > < Red Brook < MSC < River Mersey < River Bollin (Latchford Pond) Woolston Guard weir

Latchford Locks X X 1 2 3 Woolston Weir

Howley Weir & Sluice < Ketwick Brook Flows out of the canal influenced by the

Weaver Sluice < MSC height of 1 2 34 5 67 8 910 < River Weaver tide in the (Fastham Pond) River Note that 1 & 10 are not in use Mersey

XXX Eastham Locks < River Mersey (TIDAL) < River Mersey Estuary (TIDAL) Fig 9 Schematic of Manchester Ship Canal

AECOM

3 Water Level Control Structures

AECOM 10

Capabilities on project: Transportation

3 Detailed Description of the Water Level Control Structures

3.1 Overall Description of the Sluices The sluices at Mode Wheel, Barton, Irlam, Latchford and Weaver consist of vertical steel counterbalanced roller gates operated by machinery located on a gantry above the sluices. The gantry sits on masonry piers which transfer all loading onto a masonry base.

The general arrangement of the sluices is generally similar at all locations. There are some differences in the height of the gates but apart from that the gates are similar. A programme of replacement of the sluice gates means that there are two forms of construction, but overall dimensions of the sluices remain the same. These are described in section 3.4.

Stop logs are provided to enable each sluice to be isolated from the canal/river for maintenance purposes. The stop logs are of steel construction with either timber and felt seals or timber and composite rubber seals.

3.2 Upper Reaches Sluices The sluices are all of similar overall construction, with a variation in the number at each site and small variations in heights. A masonry ‘boom’ is located on the upstream side to protect the sluices from errant vessels.

A diesel-hydraulic semi-goliath gantry crane is located on the upstream side of the sluices, one rail set onto the boom and the other running across the piers at top gantry level. This crane is used to install and remove the upstream stop logs. The stop logs are installed using a beam that is hooked onto the stop logs lifting lugs with a remote release mechanism. This enables the stop logs to be installed in the event of a gate jamming in the raised position, when divers would not be able to enter the water. The stop logs can be removed by the same beam, again without divers needing to enter the water.

The downstream stop logs can be installed by a floating crane such as MSCC’s CB Buffalo, or in some locations a land based all terrain mobile crane.

3.3 Weaver Sluices The Weaver Sluices are located between the Canal and the River Mersey, opposite the River Weaver. They are accessed by boat.

A floating crane is used to install the canal-side stop logs. A diesel-hydraulic semi-goliath crane is situated on the river side of the sluices. This is used to install the riverside stop logs.

A walkway is located on the river side of the sluice to gain access from one end of the structure to the other. A landing stage is provided at the upstream and downstream end of the structure for berthing vessels. This allows access to the sluices even at times of heavy sluicing.

3.4 Gate Description There are two types of gate construction. a) Ransom & Rapier Gates - see Figure 10 This type of gate is fitted to the sluices at Mode Wheel (4No), Barton (3No), Irlam (4No), Latchford (3No) and Weaver (5No). These gates are of riveted and bolted steel construction. The upstream side of the gate is flat and the downstream side has a lattice-work beam arrangement. The gates are guided by cast steel wheels with phosphor bronze bearings which run on steel tracks set into the masonry. On the upper reaches gates there are seven pairs of wheels, and on the Weaver gate there are five pairs. Steel staunching rods hang from the upstream side of the gate in the upper reaches and on both sides of the gates at Weaver to provide a sealing

Fig 10 AECOM 11

Capabilities on project: Transportation

arrangement. The sill seal comprises a timber seal on the gate sealing against a timber seal set into the masonry. The residual life of the gates is estimated to be between 5 and 10 years with the current maintenance regime in place. This period could be

extended by undertaking some major refurbishment work. b) Halcrow Gate – See Figure 11 These gates are fitted at Barton (1No), Irlam (1No) and Weaver (3No) and are of an all welded construction. The upstream side of the gate is flat and the downstream side has a fabricated beam arrangement. The gates are guided by cast steel wheels with Orkot bearings (resin impregnated marine bearing material) which run on steel tracks set into the masonry. On the upper reaches gates there are seven pairs of wheels, and on the Weaver gate there are five pairs. Steel staunching rods hang from the upstream side of the gate in the upper reaches and on both sides of the gates at Weaver to provide a sealing arrangement. All the wheels have an automatic lubrication system for the bearings. The residual life of these gates between refurbishment is estimated at a minimum of 20 years.

Fig 11

3.5 Operating Machinery The sluices are operated by an electric motor driven gearbox, see Fig 12.

Fig 12 The gearbox drives two drive shafts that are connected to side gearboxes which drive leaf chains. The side gearboxes have sprockets driven from the main gearbox over which leaf chains sit. The sprockets drive the leaf chains which are connected between the gate and counterbalance.

AECOM 12

Capabilities on project: Transportation

Limit switches are fitted to the main gearbox which stops the sluice gates at the limit of their travel in both directions to prevent the gate clashing with the top gantry whilst being raised and the counterbalance similarly clashing whilst the gate is being lowered. The sluices are electrically powered and normally operate in automatic control mode. Each location has two independent power supplies with an automatic change over if one should fail. If this should occur this is notified to the Operations Controller (POC) as a fault condition via the Supervisory Control and Data Acquisition (SCADA) system which allows the maintenance team to be alerted, see Section 3.6. This function is checked during routine maintenance visits. There are three levels of backup for the operation of the sluices:

• Main electrical power supply in manual control mode Each sluice can be operated from a local control station located on the platform on which the operating machinery is installed. This facility is used during routine maintenance whilst checking the operation of the sluices. To enable the local control requires a key switch to be operated in the main control panel. This change in status is monitored by the SCADA system and will be notified as an event to the POC.

• Hydraulic drive If there is a power failure to the sluices each sluice can be individually operated by a hydraulic drive that is powered by the semi-goliath gantry crane petrol engine driven hydraulic power pack. The drive is through the main gearbox using the manual drive connection. This device fits on the hand winding drive shaft. A limit switch is fitted to this shaft and if the device is fitted the electrical operation of the sluice is disabled and an alarm is raised by the SCADA system and will be notified as an alarm to the POC. It takes 27 turns of the handle to move the gate 100mm.

• Manual operation A further backup if the hydraulic drive fails is that each sluice can be manually operated through the main gearbox to which a hand lever can be fitted. The winding handle is slid onto the hand winding drive shaft. A limit switch is fitted to this shaft and if the handle is fitted the electrical operation of the sluice is immediately disabled and an alarm is raised by the SCADA system and will be notified as an alarm to the POC. Operators are required to put into place the backup arrangements, see Section 5.

3.6 Control System

The sluices were originally manually operated Stony Sluices. These sluices were replaced in the 1950’s with sluices manufactured by Ransom and Rapier which are electrically operated. In 1989 the Mode Wheel sluices were automated by installing PLC’s (Programmable Logic Controllers). Barton and Irlam were automated in 1991 and Latchford in 1992. At this time a ‘Linklaser’ SCADA system was installed. Weaver was automated in 2000 and added to the SCADA system.

The sluices have a local power supply and are normally controlled locally by the PLC. The control equipment is located in a control room situated by the sluice structure. Access to this control room is via a high security lock with the key held by authorised persons. Similarly access to the top gantry where the machinery is located is by authorised persons only. A CCTV system is installed that enables the POC to monitor the activities at the sluices. The SCADA system provides a central monitoring and limited control capability which allows the operators to monitor the water levels remotely, monitor the performance of the sluices themselves and provides some limited control capability. The SCADA system continuously monitors the status of all the sluices, whether they are in auto, local or off, their position and water levels. The availability of the sluice is also inputted into the SCADA system by the POC so that if a sluice is under maintenance this is recorded in the system. The POC cannot turn the sluices off, this being undertaken locally from the Sluice Control Room building. The control system is currently being updated with new PLC’s being installed along with a new SCADA System. This provides a similar level of supervision and control for the POC based at Eastham as the Linklaser system it replaces. A more detailed explanation of how the sluices are controlled is provided in Section 4.

AECOM 13

Capabilities on project: Transportation

Data is collected by the SCADA system monitoring the status of the system and reporting faults. These include: • Gate positions; • Water levels; • Gate availability; • Power supply in use; • Position discrepancy. This is monitored by checking between the gate and counterbalance. If the difference between the two strays outside a predefined setting a position discrepancy signal is generated and the gate will not be asked to move again; • Switchgear faults; • Motor overload – caused by a motor fault of sluice jamming; • Triple validation of the water level sensors; • Loss of communication with the SCADA system, and; • Hand gear sensed to be in place.

All faults are automatically sent to the POC via the SCADA system. A detailed explanation on the above can be found in the Operation and Maintenance (O&M) manual for the sluices SCADA System. Those with the appropriate authority can intervene in the automatic sluice control using the SCADA system as follows: • At Weaver Sluices the gates can be lowered to allow a vessel to safely pass without affecting the navigation of the Canal. When this hold is removed the sluices automatically return to the required position. This is a routine procedure and is the responsibility of the POC; • All gates can be held at their current position. This requires the Harbour Masters permission; • The water level in each pond can be adjusted within predefined limits by modifying the set point of the control system. This requires the Harbour Masters permission.

3.7 Control System Communications The PLC's are stand alone and do not communicate with each other. There is communication with the iFix SCADA system via a Wide Area Network connection. This provides inbuilt redundancy as it makes use of British Telecom’s communication network, IP Clear. This is fully monitored by British Telecoms Global Services who monitor the BT circuits raising alarms when circuits are not responding so any faults are reported and attended to as they occur.

3.8 Other Water Level Control Structures In addition to the sluices the following structures contribute to the control of the water levels a) Woolston Siphon Weir This structure, along with the sluices at Latchford, maintains the water level in the Latchford Pond. It is located on the River Mersey and all the water flowing into the River Mersey passes over the weir. It was constructed in 1994 and replaces a weir built in the 1890’s.

It consists of two ogee weirs and nine air regulated siphon weirs. This automates the process of maintaining the water levels upstream of the weir. Flows of up to 140cumecs can flow over the weir before Latchford Sluices are required to operate. Once the flow through the Latchford sluices reaches capacity additional flow will then pass through Woolston Weir. The performance of the weir is dependent on the downstream levels and this is controlled by Howley Weir.

AECOM 14

Capabilities on project: Transportation

b) Howley Weir Howley Weir is the normal tidal limit for the River Mersey. It maintains water levels downstream of Woolston Weir. Extreme tides can overtop Howley and raise the water level in the river downstream of Woolston Weir. This will reduce the efficiency of the siphons until the tide recedes and restore the normal water level. c) Woolston Guard Weir This structure is provided to enable the maintenance of Woolston and Howley Weirs. It has 16 radial gates which when closed reduces flow down the Mersey to enable essential maintenance work to be safely undertaken. This would only be carried out only during periods of low flow. Normally the gates are kept open. The guard weir also reduces the flow of debris into the siphon weirs reducing the blockages in the structure. There is a regular maintenance regime in place to clear the guard weir and siphon weir of debris.

AECOM

Capabilities on project: Transportation

4 Description of Normal Water Level Control

AECOM 16

Capabilities on project: Transportation

4 Description of Normal Water Level Control

4.1 Water Level Under normal flow conditions in the Canal the sluices automatic control system is designed to control the water levels within the Canal to enable safe navigation of vessels using the Port. In achieving this, water levels are maintained so that the risk of flooding is also minimised. This automatic control system replaced the local control of the sluices by a team of operators permanently located at each lock and at Weaver Sluices. The local control system was retained at each of the sluices. It is used for the maintenance of the sluices and as a backup system. The water level in each pond is controlled locally and independently, i.e. no water level or sluice gate positions from the sluice upstream are used to determine gate opening. The water level control is achieved by the control system continuously monitoring the water level and comparing this to a level set in the PLC software, the set point. The sluice gate opening is adjusted, either being raised if the measured water level is above the set point, or lowered if the water level is below the set point. The set point can be adjusted remotely by the POC at Eastham within certain limits. Altering the set point can only be done with the authority of the Harbour Master. The water levels are monitored by ultrasonic sensors. Mode Wheel, Barton and Irlam have 3No transducers each, thus providing a system of triple validation. Provided at least one is operating the control system will operate. If all level sensors fail the gates will freeze in their last position until the fault is rectified. As soon as one sensor fails or there is a discrepancy between any two sensors an alarm is raised on the SCADA system Latchford has two sets of transducers one local at Latchford and one at Rixton Junction where the River Mersey leaves the Canal. This communicates with the Latchford PLC via a BT private wire. The Rixton water level is the default measurement used to control the sluices but if these should fail then the Latchford water level is used and the control system makes allowances for this. Weaver has two sets of transducers, three on the river side and three on the canal side. The water levels are captured and monitored by the SCADA system and an alarm is raised if the water level rises above an alarm point. The POC also visually monitors the water levels via the VDU screens in the control room and also by the images from the CCTV cameras at each sluice location. The experience of the POC operatives enables them to recognise if water levels are incorrect. Generally the sluice control system is not modified for normal flows down the Canal. The only exceptions to this are: • Depending on the prevailing weather conditions the set point on the Eastham Pond is lowered to a winter level between October to April. This is done due to the effect of the changing water level in the River Mersey affecting the effectiveness of the sluices, as explained in section 4.3. Reducing the water level provides a larger available volume for the water from the River Weaver to be stored, whilst waiting for the tide to drop in the River Mersey and the Weaver Sluices to become available for discharging the water; • If engineering works are being undertaken which require the water level to be altered from its normal level.

The Halcrow Hydraulic Modelling Study provides additional information on how the system operates as does the sluice O&M Manual.

4.2 Sluice Gate Control At each location each gate can be set to automatic, manual and off. In manual control the gate is raised and lowered from a control station located on the top gantry at each sluice position. The height the sluice is opened is read off an indicator board marked off in metres located on the top gantry.

AECOM 17

Capabilities on project: Transportation

The number of sluices in automatic is dependent on the flows down the Canal. The POC arranges for the use of the sluices to be distributed evenly. Generally the aim is for each sluice to be raised no more than 1000mm as this limits vibration, and therefore wear, within the sluice. Also to limit possible damage to the Canal embankment, the landside sluices are manually operated by opening once per month by no more than 300mm, unless all other sluices were fully raised. This sluice is given preferential use during low flow periods so that automatic operation is tested on a regular basis. During periods of normal flow all sluices are operated at least once every 4 weeks if they have not been in automatic mode. During periods of low flow, when the sluices are staunched to conserve water, they are not operated unless to control the water level. Once flows are experienced down the Canal the sluices are operated to prove their availability. The weather forecast will be closely monitored during this period so that additional sluices can be operated to prove their availability. Normally the PLC controls the position of the sluice gate depending on the information it receives from the water level sensors. It operates as follows: • PLC reads upstream water level; • If this is above the set point the system recognises the need to raise the sluice gate; • A signal is sent to the gate motor controller to run for a fixed period. This period moves the gate a fixed distance; • Each gate that is set to automatic operation will be operated in turn; • After a set period, approximately 6 minutes, if the water level is still above the set point a gate will be raised; • Due to the turbulent flow of water under the gates when they are open the gate can experience high levels of vibration. This severe vibration occurs at certain heights, generally between 100mm and 250mm above the sill. To avoid damage to the gate, when in automatic mode, an exclusion zone has been created in which the gate is not stopped; • The sluices can be raised a maximum of 2.44m in automatic mode; • At Weaver Sluices the gates will automatically close when the rising tide level in the River Mersey reaches a pre-set difference with the water level in the Canal. Otherwise when the water level in the river rises above the water level in the Canal water will flow into the Canal through the sluices potentially affecting vessel navigation and also allowing silt to enter the Canal. When these sluice gates are open there is considerable flow across the Canal which potentially creates a hazard to shipping. These gates can therefore be closed by the POC to allow shipping to safely pass.

4.3 Effect of Tidal Conditions For the Eastham Pond section of the Canal the flows through Weaver Sluices are dependent not only on the sluice gates being raised but also on the water level in the River Mersey. At High Water no flow out of the Canal is possible so if there are high flows down the Canal into this pond then this water cannot be released until the water level in the river drops. High Water can last for three hours depending on the tide level and weather conditions.

AECOM

Capabilities on project: Transportation

5 Description of Operational Control During High Water Flows

AECOM 19

Capabilities on project: Transportation

5 Description of Operational Control During High Water Flows

5.1 Monitoring for High Water Flows As explained in section 4 the water level on the Canal is continuously monitored. If water levels started to increase this situation would be identified in a number of ways • By the SCADA system alarming at the VTS Control Room; • By the POC. It is part of the operator’s duties to actively monitor weather conditions and water levels in the Canal. For the weather forecasts they obtain data from the Met Office. The water levels are monitored by checking the SCADA System outputs which show the water level trend along the Canal, by CCTV located at each sluice, by discussion with the operators who attend to operate the locks to allow vessels to pass through and by discussion with ships pilots and captains; • By the various flood warnings that are issued by the Environment Agency. 5.2 Environment Agency Flood Warning Procedure In England and Wales the Environment Agency operates a flood warning service in areas at risk of flooding from rivers or the sea. The system in place is described below. This may change and the Company will modify its procedures to in line with any flood warning systems implemented in the future. If flooding is forecast, warnings are issued using a set of three easily recognisable codes. Each of the four codes indicates the level of danger associated with the warning. The codes are not always used in sequence; for example in the case of a flash flood, a Severe Flood Warning may be issued immediately, with no other warning code preceding it. The four codes are:

Flood Alert Flooding is possible. Be prepared.

Flood Warning Flooding is expected. Immediate action is required.

Severe Flood Warning Severe flooding. Danger to life. MSCC are included in warnings The system of warnings issued by the Environment Agency may change from time to time. MSCC will keep up to date with whatever system is in place.

AECOM 20

Capabilities on project: Transportation

5.3 Procedure in the Event of Anticipated High Water Flows

When high water flows are anticipated or a Flood Alert is received by the POC the; a) Operator’s availability will be confirmed and they will be put on standby; b) Duty Harbour Master will be informed; c) POC are instructed to continuously monitor the SCADA System, CCTV and liaise with pilots and Ships Masters. If a Flood Warning or Severe Flood Warning is issued or the POC gains other intelligence the; a) Duty Harbour Master is informed; b) Depending on the number of sluices in automatic mode and what the weather conditions are the operators are instructed to attend site to put additional sluices into automatic mode. They will be instructed to attend on site if all sluices are made available; c) Depending on shipping activity and the Canals water level the set point may be set to its lowest level. This will be on the instruction of the Duty Harbour Master; d) All vessels wanting to move will be advised that they may not be able to transit the Canal. The POC will liaise with Ships Captains to discuss at what point transit for the vessel will not be advisable. The following general rules apply:

• Pleasure craft, rowing boats and narrow boats, anything above a total of 1500mm of sluicing is hazardous and they are not allowed to move; • Commercial Ships – at approximately a total of 3000mm of sluicing special consideration will be made where size, draft, available power, manoeuvrability, location of the vessel would be considered. This would be particularly so if they were swinging downstream of the sluices. The 3000mm is equal to one sluice being nearly fully open and equates to water flows of approximately 180cumecs. e) If all sluices are in use then Maintenance Personnel will be called out. In automatic mode the sluices are limited to opening 2.44m by a limit switch. The maintenance personnel bypass the limit switch allowing the sluice to be raise to 3.05m. This will enable the sluices to be raised to the 3.05m by the local manual electrical control; f) All sluices are put into automatic apart from the landside sluice. This is left in manual and raised 300mm in order to reduce possible damage to the canal bank. This sluice will be raised if water flows dictate; g) If the sluices reach the upper limit on the electrical control system and the limit switch has not been bypassed the operators can raise them to the maximum height by hand winding if required; h) If the automatic control system fails in anyway the backup system will be initiated. The time taken to implement alternative operating methods is as follows: i. Local Electrical Operation – the time it takes to walk from the shelter on the locks to the sluices, approximately 5 minutes. This is considered the most appropriate location as they will be informed by the POC if a fault develops;

ii. Hydraulic drive – this equipment requires setting up on each individual sluice by two operators. Time to set up 30 minutes. In the event of a Severe Flood Warning or anticipated high flows the equipment will be made ready; iii. Manual Operation - the time it takes to walk from the shelter to the sluices approx 5min. It takes 27 turns of the handle to raise the sluice gate 50mm. Winding handles are available at all locations and are located in the Control Room building.

AECOM 21

Capabilities on project: Transportation

i) The operators will report back to the POC that sluices have been raised as required. The Duty Harbour Master will advise the height the sluices should be raised to. Generally this will be to ensure all sluices, including those in automatic are raised an equal amount. 5.4 Resources available • In Respect of the Upper Reaches: o The operators are Billway Ltd and S&F. Between them they have 29 personnel. They are on 24 hour call for the operation of the locks for shipping so attend each site on a daily basis. In the event of a predicted flood event they would be put on standby and then called to site as required, but prior to urgent action being taken if there is a sluice failure. They each have three operators on call at all times. See section 5.5 for an explanation of arrangements if high water flows were being predicted; o MSCC Maintenance Personnel. There are ten personnel available who can operate the sluices in the event of a sluice failure. Seven operators are available at any time. • Weaver Sluices. These are operated by MSCC Maintenance Personnel. There are up to seven personnel available who can operate the sluices in the event of a sluice failure.

5.5 Communication The following arrangements are in place for contacting operators in an emergency. The operators are in regular contact with the POC via mobile phone during the normal course of the day to make arrangements for the operation of the locks. If high water flows are predicted the operator will be put on standby at this point. The POC and operator will agree who is to attend which site. Both the POC and operator will monitor the local roads via local radio to ensure that there will be no delay in attending the sluices. If there is a special event occurring in the location then the operator would be requested to attend the sluice at an earlier stage in the process. This will depend on the particular circumstances prevailing at the time. Once at the site in addition to mobile phone communication there are land line telephones at the operator shelters and in the Sluice Control Room. VHF radio is available at each lock. All locations can be accessed from either side of the Canal so that if for some reason access is blocked on one side then access can be gained from the other side.

5.6 Training All operators and MSCC maintenance personnel are given training enabling them to operate the sluices in the various back up methods available.

5.7 Testing of Backup Procedures This is undertaken as part of the routine maintenance, see Section 6.

AECOM

Capabilities on project: Transportation

6 Routine Maintenance and Major Maintenance/Capital Renewal Programme

AECOM 23

Capabilities on project: Transportation

6 Routine Maintenance and Major Maintenance/Capital Renewal Programme

6.1 Routine Maintenance Peel Ports operate a comprehensive maintenance planning system which was introduced in 2004. It is used to control the frequency of inspections, what to inspect and provides a means of recording the results of the inspections and other work undertaken on the asset. Table1 below shows how the various components of the sluices are structured for the planned maintenance system, in this case Mode Wheel. The other sluices are similar. Table 2, the Work Specifications, detail what type of inspection and maintenance is undertaken as part of the planned maintenance work.

Equipment No (Plant) Description S/MW/SLUICE Mode Wheel Flood Sluice Gates S/MW/SLUICE/ESE Mode Wheel Sluice Emergency Equip S/MW/SLUICE/GATE/1 Mode Wheel Flood Sluice Gate No1 S/MW/SLUICE/GATE/2 Mode Wheel Flood Sluice Gate No2 S/MW/SLUICE/GATE/3 Mode Wheel Flood Sluice Gate No3 S/MW/SLUICE/GATE/4 Mode Wheel Flood Sluice Gate No4 S/MW/LCK/SCADA/SYS Mode Wheel Lock Sluice Control System (SCADA System)

Table 1 – Mode Wheel Sluice Assets Covered by the Planned Maintenance System

PM No Work Spec Cat Work Specification Description PM004802 Contractor SCADA System Inspection – 52 WEEKLY S/PM000923 Mechanical Sluice Gate Machinery - Mechanical Inspection - (A) Service ALL POSITIONS 8 WEEKLY S/PM000922 Mechanical Sluice Gate Machinery - Mechanical Inspection - (B) Service 26 WEEKLY PM005055 Lubrication Flood Sluice Chain Lubrication – (A) Service 52 WEEKLY PM005079 Electrical Electrical (General) - Motor Maintenance Service - (A) Service ALL POSITIONS 8 WEEKLY PM005078 Electrical Electrical (General) - Motor Maintenance - (B) Service 26 WEEKLY S/PM002243 Condition Sluice Engineers Inspection (Upper Lock Sluices) - Monit (A) Service ALL POSITIONS 8 WEEKLY oring Table 2 – Mode Wheel Sluice Planned Maintenance Work Specifications Included in the maintenance regime are specific tests to confirm the sluices availability. These are;

• Normal Operation The automatic change over of the electrical supply. This is undertaken 3 monthly;

• Hydraulic drive This is tested at each location annually by installing, operating and raising a sluice gate. All sluices are checked to ensure that when the drive is fitted to the manual winding shaft it disables the electrical drive;

AECOM 24

Capabilities on project: Transportation

• Manual operation Manual operation is tested at each location annually. The winding handles are securely stored in the control room. All sluices are checked to ensure that when the winding handle is fitted to the manual winding shaft it disables the electrical drive. In addition there is a programme of debris clearance. This includes: • Mode Wheel – system of barrages to contain the considerable amount of debris allowed to transit down from the Rivers Irwell, Irk and Medlock that collect at Mode Wheel locks, generally in front of the sluices. The debris is collected by a bespoke vessel that corrals the debris to enable a 360° excavator to recover and deposit in skips for disposal to landfill; • Remaining sluices – debris clearance as and when by MSCC’s floating crane; • Woolston Weir – six monthly debris clearance by a diving team; All maintenance schedules are available for inspection at the Companies Workshops.

6.2 Major Maintenance A continual programme of major maintenance has been in place for many years. This remains in place and includes: 6.2.1 Refurbishment of the sluice operating machinery when the sluice is renewed under the capital renewal programme; 6.2.2 Comprehensive annual sluice gate inspections and the implementation of any required remedial work. These inspections determine the order in which the sluices would be replaced;

6.3 Capital Renewal Programme

Since 2007 a capital renewal programme of major components has been implemented. This includes sluice gates, counter balances and top gantries. To date (December 2010) the sluices replaced during this programme of work are: • Irlam No1 - 2007 • Barton No4 - 2009 • Weaver No2 – 2007 • Weaver No3 – 2010 Weaver No5 is currently being replaced and will be completed in the first quarter of 2011.

Whilst a gate is being renewed the sluice is unavailable for approximately three months. A maximum of one sluice at each location will be unavailable during this replacement programme. The work would normally be undertaken between April and September of each calendar year.

The control system hardware and the SCADA system are also in the process of being replaced and this work is expected to be substantially completed early January 2011.

AECOM

Capabilities on project: Transportation

7 Reliability of Sluice Operation

AECOM 26

Capabilities on project: Transportation

7 Reliability of Sluice Operation

7.1 Reliability Analysis The reliability of the sluice operation can be considered in terms of the different components of the operation. These are;

• Failure of the sluice mechanically, electrically or structurally; • Failure due to no operator available.

Det Norske Veritas (DNV) have undertaken a reliability analysis of the complete sluice operation to determine the probability of the sluices not operating normally.

The chance of the sluice system at each of the sites on the Canal failing to operate adequately is explored through reliability analysis. Reliability analysis builds up the probability of the failure of the system to perform normally by considering all potential causes of failure in the system components. These components are diverse and include:

• physical components such as the gate motors; • external infrastructure such as the power supply; • human sources such as decision making.

A review group comprising representatives from Peel Ports, Peel Land and Property, DNV and AECOM considered the failure modes and agreed the factors that would contribute to the failure of the sluice system. The following identifies the various failure modes considered and the assumptions agreed by the review group.

Note: For standard elements such as gear boxes readily available reliability data has been used.

Table 3 is taken from the DNV Report showing the results of the reliability assessment.

For a location with a set of four sluice gates Probability of all four sluice gates opening on demand 92.8% Probability of at least 3 gates opening on demand 99.11% Probability of at least 2 gates opening on demand 99.255% Probability of at least 1 gate opening on demand 99.256%

Table 3- Results of reliability assessment The assumptions which have lead to these results can be found in the DNV Report, ‘MSC Final Report’ dated 28 th October 2010.1

The analysis has shown that, for the following reasons, the sluice reliability is very high: • Each set of sluices incorporates some redundancy in the form of multiple individual sluice gates; • There is redundancy at each location in terms of monitoring systems that detect the water levels and the state of operation of the sluice gates; • There is redundancy at each location in terms of the systems for operating the gates, including the option of purely manual, unpowered control;

1 Sluice Gate Reliability of the Manchester Ship Canal, Reference 244 27814, 28th October 2010 – Det Norse Veritis

AECOM 27

Capabilities on project: Transportation

• The sluices are used in routine canal operations to maintain the operating water levels, which indicate a level of testing that far exceeds typical dedicated flood defence systems.

7.2 Blockage of sluices and weirs by debris

Blockage of a sluice does not occur in the same way as say a culvert blockage. It will build up over time and is monitored by regular inspections of the sluices and weirs. It is in fact most likely to be most significant after a flood with the risk of not being able to close the sluice gate being the main problem. For this reason the probability of failure due to a blockage has been discounted.

8 Working Arrangement

AECOM 29

Capabilities on project: Transportation

8 Working Arrangements

Peel and the Environment Agency are committed to working together. The MSCC can be considered a Professional Partner with the Environment Agency. There are a number of ways in which this working relationship can develop: 1. Working together on ensuring the Hydraulic Model is updated as new information and data becomes available; 2. Sharing of data relevant to water level control and that of the rivers that feed into the Ship Canal; 3. Continue with regular meetings to discuss matters of mutual interest; 4. Ensuring that the Local Authorities whose land through which the Canal runs through have a proper understanding of the flood risks so that appropriate development decisions can be taken.