Draft Environmental Impact Report/ Environmental Assessment and Section 4(f) Statement Green Line Extension Project EEA #13886
Volume 1 | Text
October 2009
Executive Office of Transportation and Public Works
U.S. Department of Transportation Federal Transit Administration DRAFT ENVIRONMENTAL IMPACT REPORT/ ENVIRONMENTAL ASSESSMENT (DEIR/EA) AND DRAFT SECTION 4(F) EVALUATION
FOR THE
GREEN LINE EXTENSION PROJECT
CAMBRIDGE, SOMERVILLE, MEDFORD, MASSACHUSETTS
STATE PROJECT NO. 13886
Prepared Pursuant to the Code of Federal Regulations, Title 23, Part 771, Section 119 (23 CFR 771.119); 49 U.S.C. Section 303 [formerly Department of Transportation Act of 1966, Section 4(f)] and the Massachusetts Environmental Policy Act M.G.L. CH 30 Sec. 61 through 62H
by the
FEDERAL TRANSIT ADMINISTRATION U.S. DEPARTMENT OF TRANSPORTATION
and the
COMMONWEALTH OF MASSACHUSETTS EXECUTIVE OFFICE OF TRANSPORTATION AND PUBLIC WORKS (EOT)
Draft Environmental Impact Report/Environmental Green Line Extension Project Assessment and Draft Section 4(f) Evaluation
Table of Contents
Acronyms and Abbreviations
Secretary’s Certificate on the EENF
Executive Summary
1 Introduction and Background ...... 1-1 1.1 Introduction ...... 1-1 1.2 Project Summary ...... 1-2 1.3 Permits and Approvals ...... 1-7 1.4 Consistency with Federal, State, and Local Planning ...... 1-8 1.5 Public Involvement and Agency Coordination ...... 1-9 1.6 Requirements of Secretary's Certificate ...... 1-15
2 Purpose and Need ...... 2-1 2.1 Overview ...... 2-1 2.2 Project Purpose ...... 2-2 2.3 Need for Transit Improvements ...... 2-2 2.4 Goals and Objectives ...... 2-6
3 Alternatives ...... 3-1 3.1 Introduction ...... 3-1 3.2 No-Build Alternative ...... 3-2 3.3 Project Elements ...... 3-2 3.4 Ridership Methodology ...... 3-11 3.5 Baseline Alternative ...... 3-12 3.6 Build Alternatives ...... 3-16 3.7 Project Description – Preferred Alternative ...... 3-39 3.8 Community Paths ...... 3-56 3.9 Coordination with Regional Projects ...... 3-60 3.10 Summary ...... 3-63
4 Affected Environment ...... 4-1 4.1 Introduction ...... 4-1 4.2 Land Use ...... 4-1 4.3 Socioeconomic Conditions ...... 4-22 4.4 Environmental Justice ...... 4-25 4.5 Existing Transportation Systems ...... 4-29 4.6 Traffic ...... 4-40
Table of Contents i Prepared by Vanasse Hangen Brustlin, Inc. – 10/15/2009
Draft Environmental Impact Report/Environmental Green Line Extension Project Assessment and Draft Section 4(f) Evaluation
4.7 Air Quality ...... 4-57 4.8 Noise ...... 4-62 4.9 Vibration ...... 4-70 4.10 Stormwater ...... 4-76 4.11 Wetlands ...... 4-79 4.12 Fish, Wildlife and Plants ...... 4-80 4.13 Parks and Recreation ...... 4-81 4.14 Visual Environment ...... 4-83 4.15 Historic and Archaeological Resources ...... 4-83 4.16 Hazardous Materials ...... 4-99
5 Environmental Consequences ...... 5-1 5.1 Introduction ...... 5-1 5.2 Land Use ...... 5-1 5.3 Socioeconomic Impacts ...... 5-10 5.4 Environmental Justice ...... 5-20 5.5 Traffic ...... 5-34 5.6 Air Quality ...... 5-79 5.7 Noise ...... 5-103 5.8 Vibration ...... 5-120 5.9 Stormwater ...... 5-132 5.10 Fish, Wildlife, and Plants ...... 5-139 5.11 Parks and Recreation Areas ...... 5-141 5.12 Visual Environment ...... 5-144 5.13 Historic and Archaeological Resources ...... 5-148 5.14 Hazardous Materials ...... 5-160 5.15 Indirect and Cumulative Effects ...... 5-169
6 Draft Section 61 Findings and Mitigation Commitments ...... 6-1 6.1 Introduction ...... 6-1 6.2 Project Benefits ...... 6-1 6.3 Project Mitigation ...... 6-1 6.4 Construction Period Mitigation ...... 6-3 6.5 Proposed Section 61 Findings ...... 6-4
7 Distribution List ...... 7-1 7.1 Federal Agencies and Elected Officials ...... 7-1 7.2 State and Regional Agencies and Elected Officials ...... 7-3 7.3 Municipalities ...... 7-7 7.4 Libraries ...... 7-12 7.5 Advisory Group Members ...... 7-13 7.6 Additional EENF Commenters and Other Interested Parties ...... 7-15
Figures ...... VOLUME 2
Table of Contents ii Prepared by Vanasse Hangen Brustlin, Inc. – 10/15/2009
Draft Environmental Impact Report/Environmental Green Line Extension Project Assessment and Draft Section 4(f) Evaluation
Appendix A: Responses to Comments on the EENF ...... VOLUME 3 Appendix B – Appendix J ...... on CD Appendix B: Station and Alignment Selection Analysis Appendix C: Green Line Support Facility Alternatives Analysis Appendix D: Travel Demand Modeling Methodology Appendix E: Plans and Feasibility Analysis for Proposed Community Paths Appendix F: Traffic Analysis Appendix G: Transit Access for Environmental Justice and Disability Populations Appendix H: Air Quality Analysis Appendix I: Draft Section 4(f) Evaluation Appendix J: Draft Memorandum of Agreement
Table of Contents iii Prepared by Vanasse Hangen Brustlin, Inc. – 10/15/2009
Draft Environmental Impact Report/Environmental Green Line Extension Project Assessment and Draft Section 4(f) Evaluation
List of Tables
Table No. Description Page 1-1 Comparison of DEIR/EA Build Alternatives ...... 1-3 1-2 Meeting Summary (as of August 5, 2009) ...... 1-14 1-3 Requirements of the Secretary’s Certificate ...... 1-16 3.5-1 Estimated Enhanced Route 80 Travel Time ...... 3-14 3.6-1 Alternative 1: Medford Branch Travel Times ...... 3-18 3.6-2 Alternative 2: Medford Branch Travel Times ...... 3-23 3.6-3 Alternative 3: Medford Branch Travel Times ...... 3-27 3.6-4 Alternative 4: Medford Branch Travel Times ...... 3-31 3.6-5 Alternative 5: Medford Branch Travel Times ...... 3-34 3.6-6 Build Alternative Evaluation ...... 3-39 3.7-1 Land Acquisition Summary ...... 3-43 3.7-2 Travel Times for the Preferred Alternative ...... 3-51 3.8-1 Pinch Points for Somerville Community Path ...... 3-59 4.2-1 Population, Housing and Employment within ½-Mile Radius of the Relocated Lechmere Station Site ...... 4-4 4.2-2 Population, Housing and Employment within ½-Mile Radius of the Brickbottom Station Site ...... 4-5 4.2-3 Population, Housing and Employment within ½-Mile Radius of the Gilman Square Station Site ...... 4-6 4.2-4 Population, Housing and Employment within ½-Mile Radius of the Lowell Street Station Site ...... 4-8 4.2-5 Population, Housing and Employment within ½-Mile Radius of the Ball Square Station Site ...... 4-9 4.2-6 Population, Housing and Employment within ½-Mile Radius of the College Avenue Station Site ...... 4-10 4.2-7 Population, Housing and Employment within ½-Mile Radius of the Mystic Valley Parkway/Route 16 Station Site ...... 4-11 4.2-8 Population, Housing and Employment within ½-Mile Radius of the Union Square Station Site ...... 4-12 4.3-1 Social and Economic Statistics for Cambridge, Somerville, and Medford .. 4-23 4.4-1 State-Listed Environmental Justice Areas in Cambridge, Somerville, and Medford ...... 4-27 4.4-2 State-Listed Environmental Justice Populations in Cambridge, Somerville, and Medford ...... 4-27 4.4-3 Minority Populations in Cambridge, Somerville, Medford, and Middlesex County ...... 4-28 4.5-1 Span of Service Standards ...... 4-32 4.5-2 Minimum Frequency of Service Standards ...... 4-32 4.5-3 Bus Service Frequency and Ridership ...... 4-33
Table of Contents iv Prepared by Vanasse Hangen Brustlin, Inc. – 10/15/2009
Draft Environmental Impact Report/Environmental Green Line Extension Project Assessment and Draft Section 4(f) Evaluation
Table No. Description Page 4.5-4 MBTA Bus Loading Standards ...... 4-33 4.5-5 Summary of Bus Schedule Adherence Standards ...... 4-34 4.5-6 Bus Cost-Effectiveness Service Standard ...... 4-35 4.5-7 MBTA Lowell Line Daily Weekday Boardings by Station ...... 4-37 4.5-8 MBTA Fitchburg Line Daily Weekday Boardings by Station ...... 4-38 4.6-1 Existing Daily Traffic Volumes on Study Area Roadways ...... 4-43 4.6-2 Vehicular Level of Service Thresholds ...... 4-47 4.6-3 Existing Condition Signalized Intersection Traffic Operations ...... 4-48 4.6-4 Existing Condition Unsignalized Intersection Traffic Operations ...... 4-49 4.6-5 Pedestrian Level of Service Thresholds ...... 4-50 4.6-6 Existing Condition Pedestrian Level-of-Service ...... 4-51 4.6-7 Parking Inventory ...... 4-56 4.6-8 Restricted Parking Allocation ...... 4-56 4.8-1 Existing Noise Measurement Results ...... 4-67 4.13-1 Existing Park and Recreation Areas within the Study Area ...... 4-82 5.2-1 Land Acquisitions for Extension to Medford Hillside………………………….5-3 5.2-2 Land Acquisitions for Extension to Union Square (via commuter rail right-of-way) ...... 5-4 5.2-3 Land Acquisitions for Extension to Mystic Valley Parkway/Route 16 ...... 5-5 5.2-4 Land Acquisitions for Extension to Union Square (via McGrath Highway/Route 28 and Somerville Avenue) ...... 5-7 5.2-5 Summary of Land Acquisitions by Alternative ...... 5-10 5.3-1 Property Tax Effects for Alternative 1 ...... 5-12 5.3-2 Property Tax Effects for Alternative 2 ...... 5-13 5.3-3 Property Tax Effects for Alternative 3 ...... 5-15 5.3-4 Property Tax Effects for Alternative 4 ...... 5-16 5.3-5 Property Tax Effects for Alternative 5 ...... 5-17 5.3-6 Property Tax Effects for Alternative 6 ...... 5-18 5.3-7 Property Taxes of Real Estate Acquired For Each Alternative ...... 5-19 5.3-8 Property Tax Decreases by City ...... 5-19 5.3-9 Estimated Job Decreases or Relocations ...... 5-20 5.4-1 Changes in Transit Access for Disability and Environmental Justice Populations under the Baseline Alternative ...... 5-23 5.4-2 Changes in Transit Access for Disability and Environmental Justice Populations under a Light Rail Extension to Mystic Valley Parkway/Route 16 and Union Square ...... 5-24 5.4-3 Building Acquisitions and Local Demographics for Extension to Medford Hillside ...... 5-25 5.4-4 Building Acquisitions and Local Demographics for Extension to Union Square (via commuter rail right-of-way) ...... 5-25 5.4-5 Building Acquisitions and Local Demographics for Extension to Mystic Valley Parkway/Route 16 ...... 5-27 5.4-6 Building Acquisitions and Local Demographics for Extension to Union Square via McGrath Highway and Somerville Avenue ...... 5-29 5.4-7 Summary of Project Impacts in Environmental Justice Areas ...... 5-34 5.5-1 No-Build Alternative Signalized Intersection Traffic Operations Results ..... 5-41 5.5-2 No-Build Alternative Unsignalized Intersection Traffic Operations Results . 5-42
Table of Contents v Prepared by Vanasse Hangen Brustlin, Inc. – 10/15/2009
Draft Environmental Impact Report/Environmental Green Line Extension Project Assessment and Draft Section 4(f) Evaluation
Table No. Description Page 5.5-3 Baseline Alternative Signalized Intersection Traffic Operations Results ..... 5-44 5.5-4 Baseline Alternative Unsignalized Intersection Traffic Operations Results . 5-45 5.5-5 Alternative 1 Peak Hour Trip Summary by Station ...... 5-46 5.5-6 Alternative 1 Signalized LOS Summary Comparison ...... 5-48 5.5-7 Alternative 1 Unsignalized LOS Summary Comparison ...... 5-49 5.5-8 Alternative 2 Peak Hour Trip Summary by Station ...... 5-52 5.5-9 Alternative 2A (with parking) Signalized LOS Summary Comparison ...... 5-54 5.5-10 Alternative 2A (with parking) Unsignalized Intersection Traffic Operations Results ...... 5-55 5.5-11 Alternative 3 Peak Hour Trip Summary by Station ...... 5-58 5.5-12 Alternative 3 Signalized Intersection Traffic Operations Results ...... 5-59 5.5-13 Alternative 4 Peak Hour Trip Summary by Station ...... 5-61 5.5-14 Alternative 4 Signalized Intersection Traffic Operations Results ...... 5-62 5.5-15 Alternative 5 Peak Hour Trip Summary by Station ...... 5-64 5.5-16 Alternative 5 Signalized Intersection Traffic Operations Results ...... 5-65 5.5-17 Alternative 6 Peak Hour Trip Summary by Station ...... 5-67 5.5-18 Alternative 6 Signalized Intersection Traffic Operations Results ...... 5-68 5.5-19 Proposed Pedestrian Mitigation Measures ...... 5-71 5.5-20 Summary of Traffic Impacts and Mitigation………………………………...... 5-78 5.6-1 National Ambient Air Quality Standards ...... 5-82 5.6-2 Predicted Maximum 1-Hour CO Concentrations (Parts Per Million) ...... 5-84 5.6-3 Predicted Maximum 8-Hour CO Concentrations (Parts Per Million) ...... 5-85 5.6-4 Predicted Maximum 24-Hour PM10 Concentrations (Parts Per Million) ...... 5-86 5.6-5 Predicted Maximum 24-Hour PM2.5 Concentrations (Parts Per Million) ...... 5-87 5.6-6 Predicted Maximum Annual PM2.5 Concentrations (Parts Per Million) ...... 5-88 5.6-7 Projected PM2.5 Emissions for Proposed Commuter Rail Track Relocation (ug/m3 ) ...... 5-90 5.6-8 Mesoscale 2030 Mobile Source Analysis Results (kilograms per day) ...... 5-91 5.6-9 Greenhouse Gas (CO2) Analysis Results (kilograms per day) ...... 5-94 5.6-10 EOT Air Quality Analysis Comparison of Project Packages Benefits in the Year 2025 ...... 5-101 5.6-11 Comparison of Air Quality Benefits ...... 5-103 5.7-1 Potential Noise Impacts Without Mitigation for Alternatives 1, 2, 3, and 4 ...... 5-109 5.7-2 Potential Noise Impacts Without Mitigation for Alternatives 5 and 6 ...... 5-111 5.7-3 Summary of Potential Noise Impacts ...... 5-114 5.7-4 Summary of Proposed Noise Barrier Mitigation ...... 5-117 5.8-1 FTA Ground-Borne Noise and Vibration Impact Criteria ...... 5-122 5.8-2 FTA Ground-Borne Noise and Vibration Impact Criteria for Special Buildings...... 5-122 5.8-3 Vibration Criteria for Detailed Analysis ...... 5-123 5.8-4 Potential Vibration Impacts at Sensitive Receptors Without Mitigation ..... 5-127 5.8-5 Summary of Potential Vibration Impact ...... 5-128 5.8-6 Summary of Proposed Vibration Mitigation ...... 5-130 5.8-7 Potential Vibration Mitigation Measures for Crossovers and Turnouts ..... 5-131 5.9-1 Impervious Surface Changes by Station ...... 5-135 5.9-2 Summary of Impervious Surface Changes by Alternative ...... 5-137
Table of Contents vi Prepared by Vanasse Hangen Brustlin, Inc. – 10/15/2009
Draft Environmental Impact Report/Environmental Green Line Extension Project Assessment and Draft Section 4(f) Evaluation
Table No. Description Page 5.10-1 Direct Vegetated Habitat Impacts by Alternative ...... 5-140 5.13-1 Potential Impacts to Archaeologically Sensitive Areas ...... 5-155 5.14-1 RECs and Potential Impacts for Alternatives 1 and 3 - Extension to Medford Hillside ...... 5-163 5.14-2 RECs and Potential Impacts for Alternatives 1, 2, and 6 - Extension to Union Square (via commuter rail right-of-way) ...... 5-163 5.14-3 RECs and Potential Impacts for Alternatives 2, 4, and 5 - Extension to Route 16/Mystic Valley Parkway ...... 5-164 5.14-4 RECs and Potential Impacts for Alternatives 3 and 4 – Extension to Union Square via McGrath Highway/Route 28 and Somerville Avenue ... 5-165 5.14-5 RECs and Potential Impacts for Alternative 6 – Yard 8 Maintenance Facility ...... 5-166 5.14-6 Summary of RECs and their Impacts by Alternative ...... 5-168 5.15-1 Cambridge, Somerville, Medford, and Station Area Populations (2000 and 2030) ...... 5-172 5.15-2 TOD Potential at Proposed Station Sites ...... 5-175 5.15-3 TOD Potential by Alternative ...... 5-175 5.15-4 Rail System Benefits on Real Estate Values ...... 5-176 5.15-5 Populations of Cambridge, Somerville and Medford (2000 and 2006) ..... 5-182 5.15-6 Projected Population and Employment Within ½- Mile of Proposed Station Sites (2010 and 2030)...... 5-183 5.15-7 Proposed and Reasonably Foreseeable Projects in the Project Corridor . 5-184 6-1 Project Mitigation Commitments ...... 6-2 6-2 Summary of Construction Mitigation Measures ...... 6-3 6-3 Possible Permits or Approvals ...... 6-6
Table of Contents vii Prepared by Vanasse Hangen Brustlin, Inc. – 10/15/2009
Draft Environmental Impact Report/Environmental Green Line Extension Project Assessment and Draft Section 4(f) Evaluation
List of Figures
All figures are provided in Volume 2 except as indicated otherwise below.
Figure Description Page 1-1 Study Area 3.3-1 Station Locus Map (Sheet 1 of 2) 3.3-2 Station Locus Map (Sheet 2 of 2) 3.3-3 Maintenance Facility Initial Site Alternatives 3.3-4 Preferred Maintenance Facility Site 3.5-1 Baseline Alternative 3.6-1 Alternative 1 3.6-2 Alternative 2 3.6-3 Alternative 3 3.6-4 Alternative 4 3.6-5 Alternative 5 3.6-6 Alternative 6 3.7-1 Proposed Project 3.7-2 Relocated Lechmere Station – Station Layout 3.7-3 Relocated Lechmere Station – Station Plan 3.7-4 Relocated Lechmere Station – Circulation 3.7-5 Relocated Lechmere Station – Elevation 3.7-6 Brickbottom Station – Station Layout 3.7-7 Brickbottom Station – Station Plan 3.7-8 Brickbottom Station – Circulation 3.7-9 Brickbottom Station – Elevation 3.7-10 Gilman Square Station – Station Layout 3.7-11 Gilman Square Station – Station Plan 3.7-12 Gilman Square Station – Circulation 3.7-13 Gilman Square Station – Elevation 3.7-14 Lowell Street Station – Station Layout 3.7-15 Lowell Street Station – Station Plan 3.7-16 Lowell Street Station – Circulation 3.7-17 Lowell Street Station – Elevation 3.7-18 Ball Square Station – Station Layout 3.7-19 Ball Square Station – Station Plan 3.7-20 Ball Square Station – Circulation 3.7-21 Ball Square Station – Elevation 3.7-22 College Avenue Station Medford Hillside Terminus (Alt 1, 3) – Station Layout 3.7-23 College Avenue Station (Alt 2, 4, 5) Station Layout 3.7-24 College Avenue Station – Station Plan 3.7-25 College Avenue Station – Circulation 3.7-26 College Avenue Station – Elevation
Table of Contents viii Prepared by Vanasse Hangen Brustlin, Inc. – 10/15/2009
Draft Environmental Impact Report/Environmental Green Line Extension Project Assessment and Draft Section 4(f) Evaluation
Figure Description Page 3.7-27 Mystic Valley Parkway/Route 16 Station – Station Layout 3.7-28 Mystic Valley Parkway/Route 16 Station – Station Plan 3.7-29 Mystic Valley Parkway/Route 16 Station – Circulation 3.7-30 Mystic Valley Parkway/Route 16 Station – Elevation 3.7-31 Union Square Station – Station Layout 3.7-32 Union Square Station – Station Plan 3.7-33 Union Square Station – Circulation 3.7-34 Union Square Station – Elevation 3.7-35 Existing Section Looking North (in text) 3-53 3.7-36 Proposed Section Looking North (in text) 3-53 3.7-37 Typical Construction Staging (Sheet 1 of 2) 3.7-38 Typical Construction Staging (Sheet 2 of 2) 3.8-1 Typical Section of Somerville Community Path (in text) 3-58 4.1-1 Existing Conditions (Sheet 1 of 10) 4.1-2 Existing Conditions (Sheet 2 of 10) 4.1-3 Existing Conditions (Sheet 3 of 10) 4.1-4 Existing Conditions (Sheet 4 of 10) 4.1-5 Existing Conditions (Sheet 5 of 10) 4.1-6 Existing Conditions (Sheet 6 of 10) 4.1-7 Existing Conditions (Sheet 7 of 10) 4.1-8 Existing Conditions (Sheet 8 of 10) 4.1-9 Existing Conditions (Sheet 9 of 10) 4.1-10 Existing Conditions (Sheet 10 of 10) 4.2-1 Existing Land Use Index 4.2-2 Existing Land Use – Existing Lechmere Station 4.2-3 Existing Land Use – Brickbottom Station 4.2-4 Existing Land Use – Gilman Square Station 4.2-5 Existing Land Use – Lowell Street Station 4.2-6 Existing Land Use – Ball Square Station 4.2-7 Existing Land Use – College Avenue Station 4.2-8 Existing Land Use – Mystic Valley Parkway/Route 16 Station 4.2-9 Existing Land Use – Union Square Station 4.2-10 Primary Use Zoning – Cities of Somerville, Medford, and Cambridge 4.4-1 State-Defined Environmental Justice Populations 4.5-1 Existing and Proposed MBTA Bus and Transit System 4.5-2 Existing MBTA Commuter Rail Routes 4.5-3 Existing Freight Rail Routes 4.6-1 Traffic Study Intersections 4.7-1 Microscale Air Quality Study Intersections 4.8-1 Typical A-Weighted Sound Levels (in text) 4-64 4.8-2 Examples of Typical Outdoor Noise Exposure (in text) 4-65 4.8-3 Noise and Vibration Measurement Sites 4.9-1 Typical Ground-Borne Vibration Levels and Criteria (in text) 4-71 4.9-2 Existing Vibration Measurement Results (in text) 4-73 4.15-1 Location of Historic Resources Identified within the Green Line Extension Project APE (Sheet 1 of 10)
Table of Contents ix Prepared by Vanasse Hangen Brustlin, Inc. – 10/15/2009
Draft Environmental Impact Report/Environmental Green Line Extension Project Assessment and Draft Section 4(f) Evaluation
Figure Description Page 4.15-2 Location of Historic Resources Identified within the Green Line Extension Project APE (Sheet 2 of 10) 4.15-3 Location of Historic Resources Identified within the Green Line Extension Project APE (Sheet 3 of 10) 4.15-4 Location of Historic Resources Identified within the Green Line Extension Project APE (Sheet 4 of 10) 4.15-5 Location of Historic Resources Identified within the Green Line Extension Project APE (Sheet 5 of 10) 4.15-6 Location of Historic Resources Identified within the Green Line Extension Project APE (Sheet 6 of 10) 4.15-7 Location of Historic Resources Identified within the Green Line Extension Project APE (Sheet 7 of 10) 4.15-8 Location of Historic Resources Identified within the Green Line Extension Project APE (Sheet 8 of 10) 4.15-9 Location of Historic Resources Identified within the Green Line Extension Project APE (Sheet 9 of 10) 4.15-10 Location of Historic Resources Identified within the Green Line Extension Project APE (Sheet 10 of 10) 5.2-1 Proposed Property Acquisitions – Lechmere Station 5.2-2 Proposed Property Acquisitions – Brickbottom Station 5.2-3 Proposed Property Acquisitions – Gilman Square Station 5.2-4 Proposed Property Acquisitions – Lowell Street Station 5.2-5 Proposed Property Acquisitions – Ball Square Station 5.2-6 Proposed Property Acquisitions – College Avenue Station 5.2-7 Proposed Property Acquisitions – Mystic Valley Parkway/ Route 16 Station 5.2-8 Proposed Property Acquisitions – Union Square Station (Fitchburg Corridor Alternative) 5.2-9 Proposed Property Acquisitions – Union Square Station (In-Street Running Alternative) 5.6-1 Mesoscale 2030 Mobile Source Analysis Results (kilograms per day) (in text) 5-92 5.6-2 Mobile Source Air Toxics Emissions (in text) 5-95 5.7-1 Increase in Cumulative Noise Allowed by FTA Criteria (in text) 5-106 5.7-2 Noise Impacts and Mitigation Measures (Sheet 1 of 5) 5.7-3 Noise Impacts and Mitigation Measures (Sheet 2 of 5) 5.7-4 Noise Impacts and Mitigation Measures (Sheet 3 of 5) 5.7-5 Noise Impacts and Mitigation Measures (Sheet 4 of 5) 5.7-6 Noise Impacts and Mitigation Measures (Sheet 5 of 5) 5.7-7 Examples of Noise Barrier Materials (in text) 5-116 5.8-1 Criteria for Detailed Vibration Analysis (in text) 5-125 5.8-2 Vibration Impacts and Mitigation Measures (Sheet 1 of 5) 5.8-3 Vibration Impacts and Mitigation Measures (Sheet 2 of 5) 5.8-4 Vibration Impacts and Mitigation Measures (Sheet 3 of 5) 5.8-5 Vibration Impacts and Mitigation Measures (Sheet 4 of 5) 5.8-6 Vibration Impacts and Mitigation Measures (Sheet 5 of 5) 5.9-1 Proposed Stormwater Drainage 5.15-1 Proposed and Reasonably Foreseeable Projects
Table of Contents x Prepared by Vanasse Hangen Brustlin, Inc. – 10/15/2009
Draft Environmental Impact Report/Environmental Green Line Extension Project Assessment and Draft Section 4(f) Evaluation
Acronyms and Abbreviations
AAB Architectural Access Board
AAI All Appropriate Inquiries
ABA Architectural Barriers Act
ACO Administrative Consent Order
ADA Americans with Disabilities Act
ADT Annual Daily Traffic
A&P The Great Atlantic & Pacific Tea Company
APC Automated Passenger Counters
APE Area of Potential Effect
APTA American Public Transportation Association
ASI Automatic Station Identification
ASME American Society of Mechanical Engineers
ASTM American Society for Testing Materials
ATR Automated Traffic Recorder
AVI Automated Vehicle Identification
AVL Automated Vehicle Location
BCIL Boston Center for Independent Living
BET Boston Engine Terminal
B&L Boston and Lowell Railroad
BLC Boston Landmarks Commission
B&M Boston and Maine Railroad
BRT Bus Rapid Transit
CAAA Clean Air Act Amendments
CAD Computer-Assisted Dispatching
Acronyms and Abbreviations A-1 Prepared by Vanasse Hangen Brustlin, Inc. – 10/15/2009
Draft Environmental Impact Report/Environmental Green Line Extension Project Assessment and Draft Section 4(f) Evaluation
CA/T Central Artery/Tunnel Project
CAT Community Access Television
CCD Commercial Corridor District
CCTV Closed Circuit Television
CDBG Community Development Block Grant
CEQ Council on Environmental Quality
CERCLIS Comprehensive Environmental Response, Compensation and Liability Information System
CFR Code of Federal Regulations
CMR Code of Massachusetts Regulations
CO Carbon monoxide
CO2 Carbon dioxide
CSO Combined sewer overflows
CTPS Central Transportation Planning Staff
DCR Massachusetts Department of Conservation and Recreation
DEIR Draft Environmental Impact Report
DEP Department of Environmental Protection
DIF District Improvement Financing
DNL Day-Night Sound Level
DOCs Diesel oxidation catalysts
DOT U.S. Department of Transportation
DPFs Diesel particulate filters
EA Environmental Assessment
EENF Expanded Environmental Notification Form
EIR Environmental Impact Report
EEA Executive Office of Energy and Environmental Affairs
EOT Executive Office of Transportation and Public Works
EPA Environmental Protection Agency
EPH Extractable petroleum hydrocarbons
ERNS Emergency Response Notification System
Acronyms and Abbreviations A-2 Prepared by Vanasse Hangen Brustlin, Inc. – 10/15/2009
Draft Environmental Impact Report/Environmental Green Line Extension Project Assessment and Draft Section 4(f) Evaluation
ESA Environmental Site Assessment
FAQ Frequently Asked Question
FAR Floor Area Ratio
FEIR Final Environmental Impact Report
FHWA Federal Highway Administration
FONSI Finding of No Significant Impact
FRA Federal Railroad Administration
FSC Forest Stewardship Council
FTA Federal Transit Administration
GHG Greenhouse Gas
GPS Global Positioning System
GRS Guilford Rail System
HDPE High-density polyurethane
HUD U.S. Department of Housing and Urban Development
HVAC Heating, Ventilation and Air Conditioning
Hz Hertz – noise cycles per second
I/M Inspection and Maintenance
IRA Immediate Response Action
IRIS Integrated Risk Information System
ITE Institute of Transportation Engineers
LI Local Industrial Subdistrict
LNAPL Light non-aqueous phase liquid
LOS Level of service
LSP Licensed Site Professional
MAAB Massachusetts Architectural Access Board
MAPC Metropolitan Area Planning Council
MassDEP Massachusetts Department of Environmental Protection
MassGIS Massachusetts Geographic Information System
MassHighway Massachusetts Highway Department
MBTA Massachusetts Bay Transportation Authority
Acronyms and Abbreviations A-3 Prepared by Vanasse Hangen Brustlin, Inc. – 10/15/2009
Draft Environmental Impact Report/Environmental Green Line Extension Project Assessment and Draft Section 4(f) Evaluation
MCP Massachusetts Contingency Plan
MGL Massachusetts General Law
MEPA Massachusetts Environmental Policy Act
MHC Massachusetts Historical Commission
MIS/AA Major Investment Study/Alternatives Analysis
MOA Memorandum of Agreement
MPO Metropolitan Planning Organization
MPS Multiple Property Submission
MSATs Mobile Source Air Toxics
MSPG Multi-Sector General Permit for Stormwater Discharges Associated with Industrial Activity
MS4 Small Municipal Separate Storm Sewer System
MUTCD Manual on Uniform Traffic Control Devices
MWRA Massachusetts Water Resource Authority
NAAQS National Ambient Air Quality Standards
NATA National Air Toxics Assessment
NCHRP National Cooperative Highway Research Program
NEPA National Environmental Policy Act
NFPA National Fire Protection Association
NHPA National Historic Preservation Act
NLEV National low emission vehicle
NO Nitric oxide
NOx Oxide of nitrogen
NO2 Nitrogen dioxide
NPDES National Pollutant Discharge Elimination System
NPL National Priorities List
NRSA Neighborhood Revitalization Strategy Area
OCC Operations Control Center
OCS Overhead catenary system
OHM Oil/Hazardous Materials
Acronyms and Abbreviations A-4 Prepared by Vanasse Hangen Brustlin, Inc. – 10/15/2009
Draft Environmental Impact Report/Environmental Green Line Extension Project Assessment and Draft Section 4(f) Evaluation
O&M Operating and Maintenance
OSHA Occupational Safety and Health Administration
PAH Polycyclic aromatic hydrocarbons
PAR Pan Am Railways
PCBs Polycyclic chlorinated biphenyls
PDS Priority Development Sites
PLOS Pedestrian Level of Service
PM Particulate matter
PMOC Project Management Oversight Consultant
PPM Parts per million
PUD Planned Unit Developments
RAO Response Action Outcome
RCRA Resource Conservation and Recovery Act
R&D Research and Development
REC Recognizable Environmental Condition
RFG Reformulated gasoline
RMS Root-mean-square
ROW Right-of-way
RTNs Release Tracking Numbers
SCADA Supervisory Control and Data Acquisition
SCAT Somerville Community Access Television
SEL Sound exposure level
SIP State Implementation Plan
Somerville City of Somerville National Register Multiple Resource Area MRA
SPCC Spill Prevention, Control, and Countermeasures
ST Springfield Terminal Railway
STIP State Transportation Implementation Plan
SVOCs Semi-volatile Organic Compounds
SWL Solid Waste Landfills
Acronyms and Abbreviations A-5 Prepared by Vanasse Hangen Brustlin, Inc. – 10/15/2009
Draft Environmental Impact Report/Environmental Green Line Extension Project Assessment and Draft Section 4(f) Evaluation
SWPPP Stormwater Pollution Prevention Plan
TAZ Transportation analysis zone
TCLP Toxicity characteristic leachate procedure
TCRB Transportation Cooperative Research Program
TIP Massachusetts Transportation Improvement Program
TOD Transit-oriented development
TPH Total petroleum hydrocarbons
TSD Transportation, Sewage and Disposal
TSS Total suspended solids
USC United States Codes
UST Underground Storage Tank
V/C Volume to capacity ratio
VOCs Volatile organic compounds
VMT Vehicle miles travelled
VPH Volatile petroleum hydrocarbons
WAN Wide Area Network
YOE Year-Of-Expenditure
Acronyms and Abbreviations A-6 Prepared by Vanasse Hangen Brustlin, Inc. – 10/15/2009
opportunities for further review and input. Section 11.06(8)of the MEPA regulations indicate that a Single EIR may be allowed provided that the EENF:
(a) describes and analyzes all aspects of the Project and all feasible alternatives, regardless of any jurisdictional or other limitation that may apply to the Scope; (b) provides a detailed baseline in relation to which potential environmental impacts and mitigation measures can be assessed; and (c) demonstrates that the planning and design for the Project use all feasible means to avoid potential environmental impacts. modified by this scope. The EIR should include a copy of this Certificate.
Project Description and Permitting costs and funding sources. If EOT will pursue federal funding, it should coordinate the and National Environmental Policy Act (NEPA) review process. The EIR should include an existing conditions plan illustrating resources and abutting land uses for the entire project area and a proposed conditions plan (or plans) illustrating proposed elevations, structures and stormwater management systems.
As noted previously, the extension of the Green Line to Medford Hillside remains a part of the Commonwealth's transit commitments developed through the CNT Project permitting. This commitment was codified in the DEP Transit System Improvement Regulations (310 CMR 7.36) in 1991 and is included as an element of the Commonwealth7s State Implementation Plan (SIP) for ozone. Revised Transit Regulations are being issued today and include a legal commitment for EOT to extend Green Line Service using light-rail vehicles from Lechrnere Station to Medford Hillside and a spur to Union Square before December 31,2014. I note that the regulations do not specify the terminus of the line within Medford Hillside and final project designs will be dependent upon the attainment of specific emissions reductions. A broad approach to the alternatives analysis is important so that additional MEPA review will not be required should policy, regulations and/or funding opportunities change.
Draft Environmental Impact Report/Environmental Green Line Extension Project Assessment and Draft Section 4(f) Evaluation
Executive Summary
About the Project
The Green Line Extension Project is an initiative of the Executive Office of Transportation and Public Works (EOT) and the Massachusetts Bay Transportation Authority (MBTA) to enhance transit services in order to improve mobility and regional access for residents in the communities of Cambridge, Somerville, and Medford. The Project is required by the State Implementation Plan (SIP) and fulfills a longstanding commitment of the Central Artery/Tunnel Project to increase public transit.
The Green Line Extension Project will finally provide light rail transit beyond Lechmere Station, serving the region’s most densely populated communities of Cambridge, Somerville and Medford that today are surrounded by, but are not directly served by, fixed-guideway transit. With approximately 18,870 people per square mile in Somerville, 15,760 in Cambridge, and 6,850 in Medford, the study area neighborhoods are among the densest in the Boston region1 and Somerville is recognized as one of the most densely populated municipalities in United States. In addition, approximately 60 percent of the residents of Cambridge, Somerville, and Medford live in state-defined environmental justice areas, which take up approximately 42.8 percent of the cities’ combined area.2 The Project Area is currently under-served by transit, and U.S. Census data (2000) indicate that approximately 21 percent of study area households do not own a vehicle, which can create a need for reliable and efficient transit service. Although MBTA commuter rail lines pass through the study area corridor, there are no rail transit stops within these communities. In addition, roadway congestion in the study area affects the reliability of current on-street transit services and results in long travel times (approximately 30 minutes) from Lechmere Station to the Mystic Valley Parkway/Route 16 area despite the relatively short distance (approximately four miles).
1 U.S. Census Bureau, Census 2000. 2 Environmental justice areas are defined by thresholds for income, minority populations, foreign-born populations, and English proficiency. Therefore, most environmental justice areas contain a mix of environmental justice and non- environmental justice residents.
Executive Summary ES-1 Prepared by Vanasse Hangen Brustlin, Inc. – 10/15/2009
Draft Environmental Impact Report/Environmental Green Line Extension Project Assessment and Draft Section 4(f) Evaluation
The purpose of the Green Line Extension Project is to improve corridor mobility, boost transit ridership, improve air quality, ensure equitable distribution of transit services, and support opportunities for smart growth initiatives and sustainable development in the Project area of Cambridge, Somerville, and Medford.
The proposed Green Line Extension Project evaluated in this Draft Environmental Impact Report/Environmental Assessment (DEIR/EA) includes: