<<

PROPOSED TERMS OF REFERENCE (TOR) FOR EIA & EMP STUDY

1.0 INTRODUCTION

National Highways Authority of (NHAI) is engaged in the development of National Highways. As a part of this endeavor, the Authority has decided to widen and strengthen – Bamnabore - Samakhiali & Bamanbore – sections into 6-lane divided carriageway configuration. The Joint Venture of M/s. Aarvee Associates Architects Engineers & Consultants Pvt. Ltd. and M/s. Nag Infrastructure Consulting Engineers Pvt. Ltd. has been awarded the work of preparation of detailed project report. The details of the project stretch are given in Table -1. Table -1: Details of the Project Stretch

Length Section Chainage NH – No State Km. Ahmedabad – Bamanbore Km. 12.000 to Km. NH-8A – Samakhiali section 306.000 338 (App.) Rajkot – Bamanbore Km. 185.558 to NH-8B section Km. 215.600

Based on the Revised NH No's and viability, the project Road is divided into two packages which are as given in Table -2. Table -2: Details of the Existing and Design Chainage of the NH Package Existing Chainage Ex. NH Design Chainage New NH Km 0.000 to Km I Km. 12.000 to Km. 182.500 NH 8A NH 47 170.700 Km 185.244 to Km 215.600 NH 8B & Km 184.700 to Km II & Km 182.500 to Km NH 27 NH 8A 341.477 306.000

2.0 PROJECT DESCRIPTION The Form -I and TOR now submitted pertain to Package -II which is reproduced here under:

Package -2: Six Laning of Rajkot (Km. 185.258) to Bamanbore (Km. 215.600) section of NH-8B and Bamanbore (Km. 182.500) – Samaikhiali (Km. 306.000) section of NH-8A in the State of Gujarat - (Km.184.700 to 341.477 of New NH 27) The project stretch falls in two districts of Gujarat State namely Rajkot and Kutch. The approximate project length is 156.78 Km The development of the existing project of 4-laning to 6-laning divided carriageway will result in safe and efficient traffic operation and will accommodate the future growth in traffic for the design period. NH -8A and NH-8B will pass through the Bamanbore, Jodhpar, , and Rajkot towns. The project also traverses through the Protected Social Forestry throughout the project stretch. The salient features of the project are given in the Table -3 & 4. Table -3: Salient Features of the Project S.No. Parameter(s) Description

1 Location of Project The proposed highway project stretch falls in two districts of Gujarat State namely Rajkot and Kachchh. (New NH-27 Chainage Km.184.700 to 341.477 in the State of Gujarat) The approximate project length is 156.78 Kms.

2 Terrain The existing project stretch is passing through Plain terrain, Rolling terrain and intermittently it passes through Hilly terrain.

Major Settlement The project stretch is having densely populated or 3 along the Project built up areas in Bamanbore, Wankaner, Morbi and Stretch Rajkot towns. Most of the built up areas are having bypasses and new bypasses are proposed wherever required. 4 Rivers/ Streams/ Canals The project stretch is crossing major rivers such as River Bhadar, River Machhu, and their tributaries. The some of the small rivers and streams are: Khari, Kaila, Niruna, Nara, Matiiweriwali, Rukmavati, Kankavati, Bhukhi etc. 5 Forest area and As per the , Gazette Sanctuaries Notification, 16th May 1974 / Vaisakha 26,1896, the Government of Gujarat declared the road side area or roads under PWD/ NHAI of the study districts such as Rajkot and Kutchh, as protected forests. Hence, in the entire stretch of 156.78 Km, part of the existing RoW is falling within the Protected Social Forestry.

6 Length of the Existing 153.8 Kms (Approx) Alignment 7 Existing Carriageway The existing carriageway is having 2 X 8.75m with Width 4.5m median with 4-lane configuration throughout the project stretch.

8 Proposed The proposed carriage way is having 2 X 12.75m Carriageway width with 4.5m Median in Six laning and 2 X 8.75m with 4.5m median in Wankaner and Morbi Bypasses.

9 Administrative Rajkot and Kachchh districts locations 10 State Gujarat State Table -4: Other Features of the Project Road S.No. Parameter(s) Existing Proposed 1 Right of Way (RoW) 45m 60m at few locations 2 Design Speed 100Kmph 100 Kmph 3 Major Bridges 9 9+8=17 4 Minor Bridges 34 34+13=47 5 No. of Railway Crossings 3 3 6 Railway Over Bridge (ROB) 2 3+3=6 7 Railway Under Bridge (RUB) 1 0 8 No. of Culverts 118 118+72=190 9 Pedestrian / Cattle Underpasses 2 2+10=12 10 Vehicular Underpasses / 6 6+10=16 Overpasses 11 Fly Overs 0 0 12 Foot Over Bridges 0 0 13 Bus Bayes 40 40 14 Truck Lay Byes 0 5 15 Rest Areas 0 1 16 Toll Plazas 2 3 17 Bypasses / Realignments 2 1.Wankaner: This alignment takes off at Km. 204.100 and traverses on the right hand side of the existing alignment and joins at Km. 212.000.

2. Morbi: This alignment alternative takes off at Km. 227.800 and traverses on the right hand side of the existing alignment and joins the existing at Km. 243.800. 18 Total Number of trees affected 3135 nos. -- 19 Tree Plantation Proposed -- 9500 nos. (1:3) 20 Land to be Acquired (Inc. land -- (236.45 + 53.76) 290.21 Ha under Social Forest) 21 Project Cost -- Rs. 1972.2 Crores 2.1 Site and its Environs The reconnaissance survey and subsequent field studies are carried in the months of February to May 2013 in the study area and various aspects pertaining to the geography, geology & soil, hydro-geology, river basins, forests & wildlife sanctuaries, transportation, socio-economic aspects, industries, and climatological conditions of the region are collected and analysed. The details of the findings are given below: a) Geographical features This section contains a detailed description on existing environment of the proposed project area including physical and biological environment in the study districts and more particularly in the area of study. The project area is located in Gujarat State covering two districts namely Rajkot and Kutchh.

Rajkot District: There are total 8 districts in region of Gujarat State. Among of them, constituted from the central region of Saurashtra. It is Located at 20.57 North Latitude to 23.07 East Latitude and between 70.20 East Longitude to 71.40 North Longitude. On the north of the Saurastra there is huge Rann of Kutchh, on the east side & Surendranagar districts located, on the south of the Saurastra & Amreli districts located and on the west of the region district is situated. River Machhu is one of the major river in the Rajkot District.

Kachchh District: Kachchh is an Ancient land with an Important Historical age. The name Kachchh was derived from its Geographical Characteristics and particularly resemblance of its earth surface with tortoise. Ancient literature mentioned this name Mallinath, in his treatise of Sanjivani defined Kachchh as during ancient time marsh land or fallow land. The foreign travelers who visited the region had mentioned in various records about the name Kachchh. It was also mentioned in rock inscriptions, copper plate inscriptions, ancient writings and manuscripts The physiography of the district is Marshy to saline desert of Rann of Kachchh and Little Rann of Kachchh extends into the saline tracts around the Gulf of Kachchh. This vast expanse of salts mixed with clay is devoid of any vegetation or habitation. The general elevation of this tract varies between 1 to 4 m above MSL.

There are numerous small rivers in the Kutch region. Those flowing north disappear in the Rann. While the remaining Join either the sea or the . Some of the main rivers are Khari, Kaila, Niruna, Nara, Matiiweriwali, Rukmavati, Kankavati, Bhukhi, etc. There are dams across Khari, Kaila, Niruna etc. and the other rivers are also prepared to be harnessed by having storage schemes to tide over scarcity conditions affecting this region quite frequently. b) Geology & Soil Characteristics Geology: The Gujarat State exposes rock belonging to the Precambrian, Mesozoic, Cenozoic, Eras. Stratigraphically, the record is incomplete as the rocks of Paleozoic era are totally absent in Gujarat. The hard rock covers about 49% of total area of Gujarat. The rest being occupied by sediments of Quaternary period. The hard rocks comprise Precambriam Metamorphites and associated Intrusives, sedimentary rocks of Mesozoic and Cenozoic eras and the trap I flows constituting Deccan Volcanics of Cretaceous, Eocene age. Soil: A major texture of the soil in the study region is 'Loamy'. However, in South-West part (in Ahmedabad and ) a soil texture in few area is found to be 'Clayey'. It is also 'Sandy' soil in some area of the Northern part () of the region.

The Costal area of the Saurashtra and Kachchh region are saline. Some parts of Kachchh near Rann are strong to very sever saline. North-Western part of Kachchh and costal part of are moderately strong saline. Some part of Rajkot district near little Rann of Kachchh, some coastal part of Jamnagar, Junagadh, , Amreli and Bhavnagar are slightly saline. c) Hydro-geology The diverse terrain conditions have given rise to different ground water situations in the study districts. The rock formations ranging in age from Archaean to recent include gneisses, schists, phyllites, intrusive, medium to coarse grained sandstones, basalts and recent alluvium. The high relief area in the eastern and north eastern part occupied by Archaean and Deccan Trap have steep gradient allowing high run-off and therefore have little groundwater potential. The yield of wells in these formations range from 5-10m3/hr. The yield in sandstones varies from 50 to 170 m3/hr. The yield of wells tapping Quaternary alluvium in Cambay basin ranges between 75-150m3/hr.

In Rajkot district, the shallow phreatic aquifer is a regionally extensive and extends down to 30 to 50 m depth with an average 42m BGL. It is also observed that seasonal fluctuation of water table, between pre-post monsoon periods, ranges from 0.50 to 4.0m in phreatic aquifer. In Kachchh district, the shallow phreatic aquifer is a regionally extensive and extends down to 75 to 125 m depth with an average 90m BGL. It is also observed that seasonal fluctuation of water table, between pre-post monsoon periods, ranges from -0.50 to 3.0m in phreatic aquifer. d) River basins, Flood and Cyclones The study districts area is drained by ephemeral rivers Sabarmati, Machhu, Khari, Kaila, Niruna, Nara, Matiiweriwali, Rukmavati, Kankavati, Bhukhi, etc. and their tributaries. River Machchu Basin: The total length of this North flowing river from its origin to its outfall into the little Rann of Katchch is 141.75 km. Machhu receives several tributaries on both the banks. There are 6 major tributaries having length more than 25 km out of which 4 tributaries namely Jamburi, Benia, Machhori and Maha feed from the right and the remaining 2 tributaries namely Beti and Asoi from the left. The drainage system on the right bank of Machhu is more extensive as compared to the left bank. The Beti, Asoi, Machhori and Maha, the 4 important tributaries together account for nearly 42.52% of the total catchment area of Machhu. Maha, the principal tributary, rises from Rampura in Chotila taluk of Surendranagar district and drains in North Western direction flowing through Surendranagar and Rajkot districts to join main stream Machhu about 1.6. km downstream of Panchaisa village. Machhori another important tributary also rises from Chotila taluka and drains towards North direction and meets the main stream about 8.5 km downstream of Wankaner in Rajkot district. Asoi tributory rises from the hilly region of village Vanjhara of Wankaner taluka and drains towards North direction and meets the main stream just upstream of village Derali.

Generally floods and cyclones are not occurred in the semi arid region of the study area and the same has been confirmed from the meteorological data collected from the study region. e) Forests, Biosphere and Sanctuary Forest Stretch: It is learnt from the site visit and subsequent discussions had with the concerned Forests officials that the entire project stretch passes through the Protected Social Forestry and apparently requires forest clearance as per the Forests (Conservation) Act, 1980 and subsequent amendments thereof. The photographs showing the protected social forest stretch in the RoW are given in Figure -1. Figure -1 : Photographs Showing the Protected Social Forestry along the RoW

Little Rann of Kachchh: Little Rann of Kachchh (LRK) is a unique place on earth with an unending possibility of exploration, numerous sites for unbelievable sights and unforgettable experiences. The Ministry of Environment and Forests (MoEF) has designated Little Rann of Kachchh as the potential Biosphere Reserve on 28th January, 2008. Little Rann of Kachchh landscape is situated between 22O55’ N to 24O35”N latitude and 70O30’ to 71O45’E longitude and tentatively extended over 6000 Km2 area. The Landscape broadly encompasses area from 10 talukas of Kachchh, Surendranagar, Rajkot, Patan and Banas kantha districts. Due to harsh environmental conditions, the LRK is free from human habitation. However, 108 villages of 10 talukas and 5 districts surrounded it. The landscape is the last home for the only surviving population of highly endangered Asiatic Wild Ass (Equus hemionus khur). The landscape covers about 4953 sq km of Wild Ass Sanctuary (WAS). Four territorial forest divisions and one wildlife sub-division is managing the area under forest department and WAS. The LRK landscape passes through the Tropic of Cancer. The area is also prone to disasters like droughts, cyclones and earthquakes. The 2001 earthquake severely damaged many villages of the landscape, especially of Surendranagar and Kachchh districts. The photographs showing the LRK and WAS in the RoW and interior part of the LRK in Figure -2 & 3.

Figure -2: The LRK and Wild Ass Sanctuary Area Passing the RoW (NH-8A) Figure -3: Interior Part of the Little Rann of Kachchh

Wild Asses Sanctuary:

Wild Asses Sanctuary (WAS) is in the centre of Little Rann of Kachchh (LRK) Landscape. The sanctuary was notified first in 1973 and included 4840.90 Km2 area of LRK. An area of 112.81 Km2 along the Greater Rann of Kachchh was further added through a second notification in 1978. These two notifications include mainly three types of areas: (i)the LRK (ii) the forest lands, and (iii) government wastelands of 108 surrounding villages of five districts. In total, the WAS extends in 4953.71 Km2 area. The wild ass falls in the family of ‘equide’ which includes Horses, Zebras and donkeys. Indian Wild Ass is one of the sturdiest animals in the world withstanding scorching mid-day temperature up to 48° C or more without any shelter in the midst of the desert facing long periods of drought surviving, where as other animals cannot survive. It has the strength and speed of a horse and can run at the speed of 60- 70 k.m./hr. The stature measures 120cm. in height, 210cms.in length and weighing about 240kgs. It possesses a shiny and a black brown hairy strip in the centre enhancing its beauty. They move either single or in herds of 10-30 in search of fodder and sweet water. They resign only in hot afternoon hours. They eat what they get, generally scrubby grass, suaeda nude flora and pods of prosopice. The breeding season is August to October and after a gestation period of 11months only young one is delivered which joins the herd in a very short time. The bray of a wild ass is shriller than that of a domestic donkey. The life span is 20 to 25 years. The photographs showing the Wild Ass in the Sanctuary are given in Figure -4.

Figure -4: Wild Asses in the Sanctuary

Salt Farming: Koli and Bhil community traditionally collected salt as a salt precipitate from saline oils of Kachchh after evaporation of ground water. Over a period of time, the process of collection of salt evolved into farming of salt through solar evaporation of seawater marine salt or sub terrain brine (Inland salt). Since 1953, India has become self sufficient in salt and ranks third in terms of annual salt production after USA and China. In recent years, the salt production has ranged from 14 to 17 million tonnes. Good availability of brine water along with plenty of sunshine and dry windy conditions are ideal settings for salt production in the state of Gujarat. The State produces between 10 to 13 million tones of salt and thus contributes around 70% of the total salt production of the country. Within Gujarat, while substantially large production of salt comes from unrecognized sector, more than 80% salts are produced from recognized sectors. It is estimated that 54,000 salt workers (commonly known as gariyas) are engaged in the salt making in the state. There are two major natural sources of salts- marine and inland (mainly the LRK). Importantly, while the marine salt work is directly relied on sea water, the inland salt works depends upon the exacting of exhaustible underground brine in LRK. Due to increase in industrial demands and engagement, more than 50% of the total salt demand is generated by the Soda ash and Caustic soda manufacturing units, which are intermediate products for soap, detergents and glass industry. The photographs showing the salt farming along the Right of Way of the NH-8A are given in Figure -5.

Figure -5: Salt Farming along the RoW (NH-8A) f) Socio-economic status As per the Census 2011, the Gujarat state has a Population of 60,383,628. Gujarat is the 10th largest state in terms of Population in India. Gujarat is one of the most industrialized states of India and thus attracts people from India both in terms of investment and jobs. The population increased from 50,671,017 in 2001 to 60,383,628 in 2011 representing a growth of 19.17% in one decade. Out of this figures, total male population stands at 31,482,282 and female at 28,901,346. In terms of Population, Ahmedabad is the largest city of Gujarat with 6.2 million people living here. and are other two major cities with population of 4.46 million and 1.67 million respectively. Rajkot is the fourth largest city of Gujarat with population of 1.50 million. Bhavnagar, , Junagadh and Jamnagar are the other major cities in Gujarat. Literacy Rate: The state of Gujarat has also shown an increase in its literacy rate by 10 percent in this decade. Currently it stands at 79.31 percent as compared to last census (2001) figures of 69.14 percent. Better education facilities by the state government have played a vital role in improving overall literacy rate of Gujarat. According to latest Census of 2011, Male Literacy rate in Gujarat stands at 87.23 percent while female literacy rate is 70.73 percent. Sex Ratio of Gujarat: Sex Ratio of Gujarat which is currently recorded as 918 females per 1000 males is lower than the national figures 940. Gujarat Sex Ratio has not shown any improvement from last census figures of 921 per 1000 females in 2001. According to latest census of 2011, there are 918 females available in Gujarat for every 1000 males. Religions: People following Hinduism constitute 89.1% of the population. The other religions include Muslims 9.1%, Jain and Sikhs 0.1% of Population. Gujarati is the official language of Gujarat while and English are also widely spoken. Kutchi, Bhili and Gamit are also spoken in the areas like Kutch region of Gujarat. Population Growth: Gujarat has witnessed a descent growth in its population in the last 60 years. From a small figure of 16 Lakh in 1950, it has gone passed 6.03 Crore in 2011. Rapid Industrialization and development of the Gujarat state has attracted people from all over India. Thus Population of Gujarat has increased considerably in the last 6 decades beginning from 1950. g) Industries There are many small, medium and large scale industries present in Surendrangar and Rajkot districts in the study area. The majority of the industries are located along NH-8A and NH-8B. Industries in study districts generating employment are automobile, marbles, ceramics, pharmaceutical, steel, rubber, plastics, minerals, metal, electrical, cotton, wooden, food & beverages etc. The forests in the region help the nation to earn foreign currency by exporting quality of wood. The other by-products of the forest are honey, tamarind and many ayurvedic plants, which earn revenues for the State. Study area is a major market center for ceramics and marbles. The photographs showing the industries located along the Right of Way of NH-8A are given in Figure -6. Figure -6: Industries Located Along the project road h) Transportation The study districts are having a good transport system in the State of Gujarat. These are connected to all the major cities across the country through various major and local highways, railways and air. There is a couple of major highways, State Highways and MDRs, Panchayat roads etc. Common modes of road transport within the cities /towns are city buses, cars and auto-rickshaws. i) Infrastructure The study region has well-developed and extensive infrastructural facilities in place. The power supply position is good and almost all the villages in study districts are electrified. The districts head quarter such as Rajkot and Bhuj have facilities like housing, hospital, drinking water facility, school and technical education, universities, medical college, etc. Emergency medical care and fire fighting facilities are also available at all Tehsils head quarters along the proposed project corridor. j) Seismic Details of the Area As per the seismic hazard map of India updated in 2000 by the Bureau of Indian Standards (BIS), the study district such as Rajkot & Suredernagar lies in Zone -IV and the Kachchh district lies in Zone -V. As classified in BIS map, Zone -V indicates the most seismically active region, while zone -II is the least seismically active region. However, the project influence area falls in ‘Moderate to high hazard’ region only. History of Earthquake: On January 26, 2001, while India celebrated its Republic Day, an earthquake of shattering intensity – 7.9 on the Richter scale – occurred at 20km northeast of Bhuj in the dry and arid district of Kutch in the western Indian state of Gujarat. The earthquake left 20,005 dead, 166,812 injured, 600,000 homeless and 212.6 billion Indian rupees in damage. The earthquake damaged the entire Kachchh district, partially damaged Suredranagar and Rajkot districts and limited impact on . k) Archeological Sites/Places of Tourist Interest No archeological sites were present within the Right of Way (ROW) of project highway. The archeological and places of tourist interest present within the study area are: Adalaj Step-well, Bhadra Fort, Sabarmati Ashramam, Sidi Sayad mosque, jumma mosque, Karba Gandhi No Delo / House, Watson Museum and Library, Lalpari Lake & Randarda Lake, Chamunda Mata Temple, Chotila, Naraya sarovar, Koteshwar temple, Wild ass sanctuary, LRK etc. l) Sources of Irrigation and Cropping Pattern The major sources of irrigation are wells and tube-wells in the study area. Besides this, very limited area is irrigated through small rivers & ponds. During Kharif, the groundnut crop is produced in irrigated areas. Maize also requires irrigation. Generally other crops are sown at the commencement of the rainy season. Bajra, Groundnut, Maize and Cotton are sown by broadcasting the seeds. Fertiliser is applied before sowing of groundnut and cotton. During Rabi, the mustard and gram is sown from September to October, in unirrigated land, while in the irrigated land, barley, gram and mustard are sown in October-November and wheat in November- December. The study area has little double cropped area with the crop cycle as moong-wheat, groundnut-wheat, moong-mustard, bajra-mustard, bajra-gram etc. The principal crop in the study area in Kharif is Bajra and the most important food grain crop in Rabi is wheat.

2.2 Meteorology of the Region Regional Meteorological and climatological data was compiled for IMD, Ahmedabad, which is be the nearest meteorological station located within the project study district. The meteorological data has been collected for a period of 30 years for Ahmedabad (1971 to 2000). 8.8.2.1 Climatic Conditions The study districts are falling under semi arid region of Gujarat State. The area has a distant place from Arabian Sea as well as Bay of Bengal gives rise of continental climate. During monsoon period from July to September and occasionally during rest period of the year in the wake of western disturbances humidity, cloudiness and rainfall activities increase. The year is broadly divided into four seasons namely: - the winter season starts from mid December to mid February, - summer or hot weather season from March to May, - monsoon season spread from end of June to mid September, and - October and November are known as transit period or post monsoon period. i) Temperature The mean minimum temperature of the area is ranging from 7.5ºC – 32.1ºC during winter season and mean maximum temperature is ranging from 23.3ºC – 44.4ºC in summer season. ii) Relative Humidity The mean humidity varies from minimum at 21.0% to maximum at 87.0% and the humidity figure shows that area belongs to hot semi-arid region. iii) Wind Speed The mean Wind speed normally is in the range of 4.8 to 11.8 Km/hr. The wind speed range is high during June to September due to entry of SW monsoons. iv) Wind Direction The predominant wind direction prevails from SW, W and NW. Following are the season wise predominant wind directions; during winter – Northwesterly, summer – Northwesterly, monsoon – westerly, northwesterly & southwesterly and in post monsoon season – Northwesterly. v) Rainfall The rainfall in this region, in general receives from the south-west towards the north-east. The maximum annual rainfall is received during the south-west monsoon which is about 95.00% and an amount of rainfall is received from non monsoon season (5.00%). The cold weather commences towards the end of November when the temperature begins to fall rapidly. The number of rainy days in the year is 33.3 and the average annual rainfall is 740.6mm.

As per Environmental Impact Assessment Notification, 2006 and its amendment 2009; the Project will fall under Category A and would require prior Environmental Clearance from MoEF, Govt. of India and hence an EIA study will be required to be carried out for the purpose. For carrying out the EIA study the Terms of Reference (TOR) has been proposed. 3.0 SCOPE OF THE STUDY The Scope of Surveys and studies for the project including all engineering aspects, environmental and socio-economic aspects of the projects are included in the ToR for feasibility studies. The salient features of the scope are given hereunder: i. The Consultant will also make suitable proposals for widening/improvement of the existing 4- lane road to 6- lane with provision of capacity augmentation etc. and strengthening of the carriageways, as required at the appropriate time to maintain the level of service over the design period. The consultant will also review the alignment based on the IRC codal provisions and propose realignments and bypasses as required. ii. The Consultant will study the possible locations and design of toll plaza. Wayside amenities required on tolled highway shall also be planned. The local and slow traffic may need segregation from the main traffic and provision of service roads and fencing may be considered, wherever necessary to improve efficiency and safety. iii. Consultant will prepare land acquisition proposals for the additional land required for widening the existing carriageway, forming bypasses etc. The Consultant will furnish land acquisition details as per revenue records / maps for further processing. iv. The Consultants will prepare documents for BOT/EPC contracts for the contract packages based on the mode of execution approved by client. v. Environmental Impact Assessment and Environmental Management Plan shall be carried out by the Consultant meeting the requirements of the Government of India or lending agencies like ADB/ World Bank/ JBIC etc. vi. Wherever required, consultant will liaise with all concerned Govt. agencies including but not limited to Electricity dept., Irrigation Dept., Water Resources Dept., District Development Authority, PWD, Municipality Department, Police Department, Revenue Department, Traffic Police, and secure all clearances and also incorporate the estimates for shifting of utilities of all types involved from concerned local authorities in the Feasibility Study. vii. Consultant will also obtain ‘NO Objection Certificate’ from Ministry of Environment and Forest. viii. Consultant is required to prepare all Land Acquisition Plans (i.e. all necessary schedules as per National Highway, 1956 Act) for acquisition of land required for the project under National Highways Act. 4.0 TERMS OF REFERENCE FOR EIA STUDY 4.1 Study Area A detailed study of all the environmental features falling within the immediate corridor of impact, which has been considered as 500 m on both sides from center line of road. The other sensitive environmental issues such as protected areas notified under wildlife (protection) Act 1972, critically polluted areas as notified by Central Pollution Control Board, notified eco-sensitive areas, interstate boundaries and international boundaries, water bodies of ecological significance, etc, were identified within 15 km from the alignment. The detailed information collected from the right of way as well as the area falling within 500 meters on the either side Road were collected from primary sources and the other environmental features within 15 kms aerial distance as explained above were collected from secondary data sources. Rapid EIA studies were carried out for the proposed project in accordance with the Environmental Impact Assessment Notification, 2006 and amendment thereof as well as MoEFs EIA Guidance Manual, 2010. The Environmental Baseline data was generated based on the EIA Guidance Manual, 2010 for the period of December 2013 to February 2014. Environmental Baseline monitoring report carriedout as per Standard TOR is given in EIA guidance manual by MoEF is enclosed as Appendix VI. The details of the EIA study was already carried out as follows:

4.2 Description of the Environment The Baseline data on various environmental features was collected both from Secondary and Primary sources from field surveys and investigations in order to describe the environmental settings of the project area. The data on different environmental components along the project corridor were collected followed by site reconnaissance in order to establish environmental condition of the project area. The study area will cover 15 km either side of the project stretch.

4.3 Baseline Data Generation (a) Secondary Data Collection: Secondary data was collected from secondary sources like publishes, literature from various government and private agencies, NGOs, or institutions on physical, biological and social components of environment. The data was reviewed for establishing existing environmental and ecological status within the project area.

(b) Field Survey: The desk work followed by field survey of the project site for identification of the environmental sensitive zones within the study area and physical verification of all the identified sensitive zones with respect to the location of the project Alignment and activities proposed. The field surveys are being included the measurement of environmental quality in terms of ambient air quality, water quality, soil quality, background noise level and ecology (Flora, fauna and roadside trees, etc.) along the existing alignment. The procedure for measurement of environmental quality surveys were carriedout as per guidelines of the Ministry of Environment and Forests, Government of India. Following details on different environmental features were collected either from the secondary sources or from field surveys:

I. Physical Environment i. Topography: Topography, ground conditions, altitude, slope, etc. ii. Soil and Geology: Soil type and it characteristics, soil erosion and land slide problem, geology of the area. iii. Water Environment: An inventory survey of all water bodies located within 500 m on either side of the project road sections will be carries out. Details of rivers, streams, springs, lakes, reservoirs within 500 meters of the proposed road right of way will be collected from the site along with their usage and importance for the local population. Study of hydrology of the project road. The natural drainage of the project region, the existing drainage pattern of the project road, runoff flow direction, possible flooding, erosion will be collected. The information on ground water table, the ground water availability in the project area, the exploitation of ground water studied was be collected from secondary sources. iv. Meteorological Data Meteorological data covering maximum and minimum wind speed, wind direction, rain fall, relative humidity and temperature for last 10 years period was collected from the nearest IMD, Ahmedabad and Rajkot Meteorological stations. History of special weather phenomenon like cyclones, cloud bursts, etc. were collected from the nearest meteorological station for a period of 50 years. The wind velocity, wind direction and wind rose, rainfall, temperature and relative humidity along the proposed alignment were also recorded during study period. v. Environmental Quality Baseline environmental quality data in terms of water, ambient air and Noise levels and soil quality would be generated as follows:

Ground & Surface Water Resources and Quality: The water samples from Ground water and surface water resources along the project road alignment were collected at fifteen (15) locations and analysed for the physico-chemical parameters. Surface water samples from different water bodies/rivers/streams along the project stretch were collected and analyzed for physico-chemical parameters. Ground water samples were also be collected from most commonly used ground water sources along the project road. The Ground water samples analysed for Temperature, pH, Turbidity, EC, Colour, TSS, TDS, Odour, DO, BOD, COD, TKN, Total Hardness, Sodium, Potassium, Calcium, Magnesium, Ammonia, Chloride, Sulphate, Phosphate, Nitrate, Fluoride, Surfactants, Dissolved Iron, Copper, Zinc, Manganese, Arsenic, lead, Mercury, Boron, Chromium, Phenols, Cadmium, Total Coliform, Faucal Coliform.

Surface water samples analysed for Temperature, pH, Turbidity, EC, Colour, TSS, TDS, Odour, DO, BOD, COD, TKN, Total Hardness, Sodium, Potassium, Calcium, Magnesium, Ammonia, Chloride, Sulphate, Phosphate, Nitrate, Fluoride, Surfactants, Dissolved Iron, Copper, Zinc, Manganese, Arsenic, Lead, Mercury, Boron, Chromium, Phenols, Cadmium, Total Coliform, Faucal Coliform.

Ambient Air Quality: Ambient air quality monitoring was carried out along the project stretch at five (5) locations covering different category of land use, viz. residential, commercial/industrial and sensitive zone like schools, college and hospital along the road with a frequency of twice a week for one month at different locations covering the sensitive locations. The ambient air quality monitoring will be carried out with respect to Particulate Matter (size less than 10μm) or PM10, Particulate Matter (size less than 2.5 μm) or PM2.5, Sulphur dioxide (SO2), Oxides of Nitrogen (NOX), Carbon Monoxide, and Hydrocarbons by following the MoEF guidelines.

Noise Environment: The noise monitoring will be carried out at fifteen (15) locations representative locations along the alignment of the project covering sensitive locations such as residential, hospitals, schools, sanctuaries etc. The noise monitoring will be done for 24 hrs at each location. During nigh time and day time, equivalent noise levels will be generated for each monitoring locations to have an idea of noise pollution levels in the study area.

Soil Quality: The soil samples of different area along the project stretch were collected at ten (10) locations for assessing the physico-chemical characteristics of the soil in the project area. The quality parameters analysed for pH, Electrical conductivity, sand, silt, clay, texture, moisture retention capacity, infiltration rate, bulk density, porosity, organic matter, Nitrogen, potassium, phosphorous, Pb, iron and organic carbon. vi. Existing Land Use Pattern: Land use pattern was established along the project road classifying, forest area, Agriculture land, cultural waste land and area not available for cultivation, urban and rural settlements, water bodies, hills, etc. along the project road.

II. Biological Environment i. Flora and Fauna: Information on vegetation within the study areas was collected from secondary source as well as through site investigation. The vegetation study includes Forest area and road side plantation within the proposed ROW and the list of flora and fauna were collected. ii. Ecological Sensitive Locations: Ecological sensitive locations, such as Wildlife Sanctuary, National parks, bio reserve, etc. were identified within 10 km on either side of project road and studied. iii. Ecological Studies: Terrestrial and aquatic ecological studies was conducted along & within the proposed ROW. Common trees, shrubs, other vegetation, common fauna, rare and endangered species are also identified, surveyed and studied. The roadside trees within the proposed ROW was surveyed including botanical & vernacular name of trees species, girth wise enumeration, etc.

III. Socio-Economic and Cultural Environment

(a) Socio-economic Details: Study of demographic details including population, schedule caste, schedule tribe, literacy, occupation pattern in the settlements along the project road, economic and social conditions, life styles, etc. along the project road and study of infrastructure facilities in the settlements along the project road. The social study comprising socio-economic survey along the project road and reflect the number and details of Project Affected Persons (PAPs) along the project road. Following data was collected: • Details of the properties, houses, businesses etc. • Activities likely to be effected by land acquisition and their financial loses annually. • Data covering the vulnerable groups or persons including women, children, elderly, • people below the poverty line, indigenous people and notified settlements • Data on diseases in the locality and existing health care facilities • Data on demography including traditional skills and sources of livelihood along the proposed site.

(b) Places of Tourist, Historic, Archaeological and Religious Interests: Places of tourist interest, historical, archaeological places and places of religious interests (if any) identified along the project road- in the immediate vicinity and also within study area (15km on either side of the project road).

(c) Common Resources: An inventory of common community resources such as educational institutions, health centres, recreation centres, Courts, libraries, community centres, Public toilets, religious and cultural features etc. situated along the project corridor are prepared.

4.4 Analysis of Alternatives to the Project Road In-depth study of related maps, topographic sheets, physical inspection and environmental and social screening was carried out in order to find out the technically and environmentally sound, most feasible and environmental friendly alignment. Alternatives are considered for the analysis of “without” and “with” project situations and components. The selected Alternatives were compared in terms of their potential social & environmental impacts, capital & recurrent costs, suitability under local conditions, institutional training and monitoring requirements. For each alternative, the environmental costs and benefits will be quantified to the extent possible and the basis for the selected alternative was stated. Analysis of alternative includes alignment selection, finalization of bypasses, road widening to reduce the cutting of tree and minimizing the demolition of structures, grade separators, services roads, vehicular, pedestrian and cattle underpass, quarry materials, road safety, etc. 4.5 Anticipated Environmental Impacts and Mitigation Measures The environmental impact assessment was conducted in accordance with the requirement of the Ministry of Environment & Forests (MoEF) norms and guidelines. The collected primary and secondary data was compiled and analyzed to establish a comprehensive database and assess the existing baseline environmental condition. After establishing the baseline status of the study corridor and analysis of the project proposals and activities, the potential impacts on environmental components would be identified for pre-construction, construction and operational stages of the project. On the basis of the existing baseline environmental condition within the project area and the nature and extent of activities envisaged in construction/operation phase, the impacts would be identified and assessed for “Without and With Project Scenario” during construction and operation phases of the project. Wherever practicable, a quantitative analysis was performed for the impacts by using appropriate modeling method. All potential direct and indirect influence due to the proposed project was also addressed. The scope of work not confined only to alignment but the impacts due to the associated construction activities assessed. The following aspects are given due importance during assessment of impacts and recommending remedial measures: • Alignment of the project road and topographical changes • Roadside drainage to avoid water logging, erosion & environmental degradation • Impact on soil along the project road. • Impact of solid waste generated and solid waste management plan • Impact on borrow area and quarries • Impact of road safety • Impact on ambient air quality due to air pollution during construction activities and vehicle movement. • Prediction of ambient air quality due to projected vehicular traffic on the project road was carried out using computer based California Line Source Emission (CALINE - 4) software. • Impact on noise level during construction activities and vehicle movement. Prediction of noise levels was carried out using computer based Prediction of Noise level during Operation phase in future years to be determined using Federal Highways Noise Administration (FHWA) Model. • Assessment of impacts of road construction on ground and surface water sources in the study area • Impact of solid waste generated during construction phase of the project. • Nature, quantity and disposal of construction spoils, wastes and waste water. • Impacts of flora and fauna and ecological resources due to construction and operation of the project • Public health & sanitation, and occupational health & safety of construction workers. • Impact on safety of local people during construction and operation phases. • Road safety features to avoid accidents need of underpass, service road, etc. • Population affected and socio-economic impacts.

4.6 Public Consultation and Information Disclosure Public consultations are already carried out in the affected areas along the project road. The issues discussed during consultation are also incorporated in the design framework and environmental management and mitigation plan. A public Hearing is yet to be conducted.

4.7 Environmental Monitoring Programme Environmental monitoring plan for construction and post construction phases of the project road was formulated to ensure effectiveness of implemented environmental mitigation measures. Cost of Environmental Monitoring Plan for construction and post construction phase of the project was worked out. 4.8 Environment Management Plan After detail analysis of all the environmental impacts and issues, a proper and adequate Environmental management plan was prepared with the aim to avoid, mitigate or eliminate the adverse impacts due to the project. This was cover all the aspects of construction including roles and responsibilities for mitigation operations, emergency response procedures, and supervision, financing, monitoring and reporting. The Environmental Management Plan further include the prospects of environmental enhancement within the project area wherever possible. The EMP was envisaged the plans for the proper implementation of mitigation measures to reduce the adverse environmental impacts arising out of the project activities during construction and operation phase. The following issues are addressed in the EMP:

i. Preventive, mitigation, compensatory & enhancement measures for minimization & abatement of the undesirable impacts caused during the construction and operation stage. ii. Details of management plans (compensatory plantation, solid waste management plan, borrow area management plan, occupational safety and health plan etc.) including their implementation schedule and supervision programme. iii. Identified/recommended institutional set up for implementation of the EMP including institutional requirements, staffing and training. iv. Environmental monitoring programme during construction and operation phase including performance indicators, monitoring mechanisms, implementation programme and cost. v. Resettlement action plan for affected families as per NHAI Policy and NRRP 2007. vi. Environmental Management Budget: The preliminary environmental budget considering the environmental aspects for the project.

4.9 Structure of EIA Report The EIA report was followed the structure as per EIA Notification, 2006 and consists of the following Chapters: • Introduction • Project Description • Analysis of Alternatives (Technology and Site) • Description of the Environment • Anticipated Environmental Impact & Mitigation Measures • Public Consultation • Resettlement and Rehabilitation Plan • Project Benefits • Environmental Monitoring Program and Environmental Management Plan • Summary & Conclusion Appendix -I: Location Map Showing the Project Road Stretch Appendix -II: List of Villages and Towns in the Project Road

Chainage Village Name Taluk From To NH 8B Rajkot city map 185.300 186.230 Anandpar Rajkot 186.230 189.040 Maliyasan Rajkot 189.040 190.900 Maliyasan Rajkot 190.900 194.030 Thargadiyta Rajkot 194.030 195.320 Kuvada Rajkot 195.320 197.800 Kuvada Rajkot 197.800 200.715 Mota Kuchiyadad Rajkot 200.715 203.910 Kuchiyadad Rajkot 203.800 205.400 Hirasar Rajkot 205.400 207.930 Bamanbore Chotila 207.910 210.200 Bamanbore Chotila 210.200 213.500 Gundala Chotila 209.950 210.130 NH 8A Bhalgam Wankaner 180.945 185.435 Thikariyali Wankaner 182.205 183.155 Rangpar_W Wankaner 185.435 190.160 Jalida Wankaner 186.950 190.250 Garida Wankaner 190.250 193.450 Mahika Wankaner 193.450 196.975 Kothi Wankaner 196.975 197.850 Jodhapar Wankaner 197.850 201.745 Limbala Wankaner 201.985 202.120 Lalpar Wankaner 201.745 204.400 Kerala Wankaner Dhamalpar Wankaner Bypass Hasanpar Wankaner Chainage Village Name Taluk Bojpar Wankaner 211.910 211.985 Panchasar Wankaner 211.985 212.830 Vagasia Wankaner 212.830 218.805 Jambudiya bhayati Wankaner 218.805 220.195 Ranekpar Wankaner 220.195 222.975 Dhuva Wankaner 222.975 223.000 Makansar Morbi 223.000 227.595 Jambudiya Morbi Lakhdpur Morbi Ghunta Morbi Bypass Bela Morbi Pipli Morbi Nava-Sadulka Morbi Juna-Sadulka Morbi 248.520 251.500 Haripar Morbi 251.500 251.960 Gala Morbi 251.960 254.745 Junanagdavas Morbi 254.745 257.575 NavaNagdavas Morbi 257.575 258.950 Bahadurgadh Morbi 258.950 260.580 Vaghpar Morbi 260.580 262.300 Vadharva Maliya 262.300 263.750 Virvadraka Maliya 263.750 265.360 Khirai Maliya 266.160 267.740 Maliya Maliya 265.360 271.230 Haripar_Maliya Maliya 271.230 273.400 Shikarpur Bachau 283.730 292.350 Vandhiya Bachau 292.350 298.420 Nava Katariya Bachau 298.690 299.050 Junakatariya Bachau 297.140 300.710 Samakhiali Bachau 300.710 306.210 Appendix -III: Assessment of Alternatives for Bypasses

1. Wankaner Bypass:

Existing Road: The road passes through Wankaner village from Km. 205.800 to Km. 208.600. Wankener is located in Rajkot district. Either side of the Right of Way thickly covered with the habitations and the industrial area. The predominant industries located in the area are ceramics, marble, cement etc. Lot of traffic congestion is observed due to presence of industries on either side of the town. The town is developed on both sides with a higher concentration on the LHS. The upgradation of the existing road may require huge Resettlement & Rehabilitation issues and social acceptance of the people will also be a difficult task. It is anticipated that the proposal may also invite unnecessary court cases.

Alternative 1: This alignment takes off at Km. 204.100 and traverses on the right hand side of the existing alignment and joins at Km. 212.000. This alignment traverses partly through cultivated fields and partly through barren lands and has good geometrics. The total length would be around 7.9 Km. No major environmental issues are involved in the alternative except, cutting of the bushes in the area. It is envisaged that the R&R issues are very minimal in the alignment.

Alternative 2: The alignment takes off at Km. 203.800 and is to be taken on left hand side of the existing alignment and joins the existing alignment at Km. 212.200. The length of bypass will be about 8.4 Km. Since, concentration of industries is predominantly on the left side of the highway, the length of the this alternative is more compared to the alternative 1. Due to the presence of tributary of River Manchhu on the LHS of the existing road, CD works in alternative -2 are also more compared to the alternative -1. This alternative will also require crossing of existing railway line twice and requires two ROBs.

Map Showing the Alternative Assessment of Bypasses – Wankaner Bypass

2. Morbi Bypass: Existing Road: The road passes through Morbi town from Km. 235.300 to Km. 238.800. Morbi is situated in the Rajkot district. Industries are scattered all along the corridor from Km 225.000 to Km 243.000. There are more than 600 small, medium and large scale industries present in the town. The predominant industries present in the area are ceramics, marble, sanitary ware and Compact Fluorescent Lamp (CFL) etc. The presence of industries on either side of the RoW and thickly populated areas with industrial establishments causing the frequent traffic congestion in the town. Upgradation of the existing road may require to go for huge Resettlement & Rehabilitation (R&R) issues and the social acceptance of the proposal is poor. It is anticipated that the proposal may also invite unnecessary court cases.

Alternative 1: This alignment alternative takes off at Km. 227.800 and traverses on the right hand side of the existing alignment and joins the existing at Km. 243.800. It traverse mostly through cultivated and barren fields and has good geometrics. The total length would be around 19.6 Km. No major environmental issues are involved in the alternative except, cutting of trees and bushes in the area. It is envisaged that the R&R issues are very minimal in the alignment.

Alternative 2: The proposed alignment takes off at Km. 214.300 and after traversing on the LHS of the existing alignment joins the existing at Km. 247.800. The length of bypass will be about 33.5 Km since it has to be taken to the left of Manchhu reservoir. There are considerable number of trees and bushes to be removed in this alternative when compared with Alternative -1.

Alternative Assessment of Bypasses – Morbi Bypass Consultancy Services for Preparation of Feasibility for 6 laning of Ahmedabad – Bamanbore – Samakhiali & Bamanbore – FORM -1 & Rajkot section of NH-8A & 8B in the State of Gujarat Terms of Reference (TOR)

Appendix – IV: Details of Borrow Areas, Sand stone and Quarries Along the Project Stretch

Project Name: Ahmedabad – Bamanbore - Samakhiali Section II, Bamanbore – Samaikhiali

Location of Quarry Identification & Approx. type of Quarry Govt. Availability of Sample total For Soil / Metal / Land(G.L) S.No Dis- extent of Depth Contact Details Chainage tance Side Village State Quantity Sand / GSB/Fly- /Private Quarry (Acres) (m) 3 (KM) (ft ) ash Land(P.L)

Road Lakabhai , Ph:9879874619, 29 184+200 LHS Valgav Gujarat 10 2 80940 BA – 31 GL Side 9586522715, Wankoner Thaluk

Road 30 190+200 LHS Valgav Gujarat 5 5 101175 BA – 32 GL - Side

Road Asok Bhai , Ph: 9427563047, 31 193+100 LHS Gharidda Gujarat 10 5 202350 BA – 33 GL Side Wankaner Thaluk

Road Shankar, Ph:7600898186, 32 202+400 LHS Limbada Gujarat 10 4 161880 BA – 41 GL Side Wankoner Thaluk

Kaushar Stone Crushing, Yusuf< 33 202+400 1 RHS Lalpur Gujarat 5 10 202350 M – 14 PL Ph: 9979019992, 9879525486, Wankoner

Bharath Constructions,Sajeed, 34 202+500 1 RHS Lalpur Gujarat 4 10 161880 M – 13 PL Ph:9825031486, Wankaner

Wankane 15 35 208+400 6 LHS r Village Gujarat 3 182115 BA – 38 PL Navgan Bhai, Ph:9825222860 & Thaluk

Page 27 Consultancy Services for Preparation of Feasibility for 6 laning of Ahmedabad – Bamanbore – Samakhiali & Bamanbore – FORM -1 & Rajkot section of NH-8A & 8B in the State of Gujarat Terms of Reference (TOR)

Project Name: Ahmedabad – Bamanbore - Samakhiali Section II, Bamanbore – Samaikhiali

Identification & Location of Quarry Approx. Govt. Availability of Sample type of Quarry total Land(G.L) S.No Dis- extent of Depth For Soil / Metal / Contact Details Quantity /Private Chainage tance Side Village State Quarry (Acres) (m) Sand / GSB/Fly- (ft3) Land(P.L) (KM) ash Althaf (Sarpanch), Ramak- 36 219+200 2 LHS Gujarat 3.5 2.5 35411 BA – 39 GL Ph:9825931387, Wankaner pur Thaluk Makansa Anvar Bhai, Ph:9825755156, 37 226+200 5 LHS Gujarat 10 2.5 101175 BA – 37 GL r Morbi Thaluk

Madia Dharti Stone Products, 38 242+600 17 LHS Gujarat 12 20 971280 M – 6 PL Charasta Gigneswar, Ph:9879911385, Morbi

Rajkot Kishore, Morbi, Ph:987948121, 39 242+600 18 LHS Gujarat 7.5 10 303525 M – 7 PL Bypass 9825797973

Rajkot Rade Bhai & Khengar, 40 242+600 18 LHS Gujarat 50 10 2023500 M – 8 PL Bypass Ph:9909900100, 9925243000

Dhanara Bhanu Bhai, Ph:90989791957, 41 237+600 50 RHS Gujarat Lumpsum Lumpsum Lumpsum S – 5 GL m River 9978984555

Navasad Nandalal (Sarpanch), 42 245+900 1.5 LHS Gujarat 5 5 10101175 BA – 35 GL ulka Ph:9909595542, 9978984555

Navasad Nandalal (Sarpanch), 43 245+900 1.7 LHS Gujarat 5 2 40470 BA – 36 GL ulka Ph:9909595542, 9978984555

Page 28 Consultancy Services for Preparation of Feasibility for 6 laning of Ahmedabad – Bamanbore – Samakhiali & Bamanbore – FORM -1 & Rajkot section of NH-8A & 8B in the State of Gujarat Terms of Reference (TOR)

Project Name: Ahmedabad – Bamanbore - Samakhiali Section II, Bamanbore – Samaikhiali

Identification & Location of Quarry Approx. Govt. Availability of Sample type of Quarry total Land(G.L) S.No Dis- extent of Depth For Soil / Metal / Contact Details Quantity /Private Chainage tance Side Village State Quarry (Acres) (m) Sand / GSB/Fly- (ft3) Land(P.L) (KM) ash Prabath Singh (Sarpanch), Ph: Road Umarnag 44 251+500 LHS Gujarat 3 3 36423 BA – 34 GL 9978857903, Ramesh Bhai, Ph: Side ar 9099704295, Morbi Thaluk Mavji Bhai (Sarpanch), Ph: 45 260+700 2 LHS Sokhada Gujarat 7 3 84987 BA – 24 GL 9687522127, Deva Bhai, Ph:9979045745, Morbi Thaluk Malia Vil- Bhulan Bhai, Ph:9825360149, 46 268+400 3.5 RHS lage & Gujarat 20 3 242820 BA – 23 PL 9833208235 Thaluk Shi- 47 286+800 0.8 RHS Gujarat 50 10 2023500 BA – 22 PL Bheem Bhyai, Ph:992515855 karipura Mumayya, Ph:9925661669, Sa- 48 294+300 3 RHS Katariya Gujarat 10 3 121410 BA – 20 PL makhiali Katariya LHS 49 299+900 0.4 Hanu- Gujarat 3 2 24282 BA – 21 PL Bhanu Maharal, Ph:9825525496 0 mandam Banas River, Mumayya, 50 294+300 3 RHS Katariya Gujarat Lumpsum Lumpsum Lumpsum S – 4 GL Ph:9925661669, 9925316854

Note: B.A=BORROW AREA , MQ- METAL QUARRY , S- SAND , FA = FLYASH , GSB= GRANULAR SUBBASE

Page 29 Consultancy Services for Preparation of Feasibility for 6 laning of Ahmedabad – Bamanbore – Samakhiali & Bamanbore – FORM -1 & Rajkot section of NH-8A & 8B in the State of Gujarat Terms of Reference (TOR)

DETAILS OF BORROW AREA , METAL QUARRY AND SAND

Project Name: Ahmedabad – Bamanbore -Samakhiali Section III, Bamanbore – Rajkot

Location of Quarry Identification Availability & type of Govt. Sample Approx. of extent Quarry For Land(G.L) S.No Depth total Quant- Contact Details of Quarry 3 Soil / Metal / /Private Distance (m) ity (ft ) Chainage Side Village State (Acres) Sand / Land(P.L) (KM) GSB/Flyash

Sanjeev Bhai, Ph:9904802966, 51 188+200 2.2 LHS Sokhada Gujarat 7 2.5 70822 BA – 28 GL Rajkot

Savji Bhai, Ph:9979105462, 52 194+100 0.2 RHS Thargadiya Gujarat 6 5 121410 BA – 29 PL 9979018228

Road Raju Bhai (Sarpanch), 53 199+300 RHS Thargadiya Gujarat 25 4 404700 BA – 27 GL Side Ph:9723364050

Bhumi Metals, Dinesh Bhai, Rampar – 54 204+500 2 RHS Gujarat 20 10 809400 M – 9 PL Ph:9825231531, Navaneeth beti Bhai, Ph:9824248520, Rajkot

Page 30 Consultancy Services for Preparation of Feasibility for 6 laning of Ahmedabad – Bamanbore – Samakhiali & Bamanbore – FORM -1 & Rajkot section of NH-8A & 8B in the State of Gujarat Terms of Reference (TOR)

DETAILS OF BORROW AREA , METAL QUARRY AND SAND

Project Name: Ahmedabad – Bamanbore -Samakhiali Section III, Bamanbore – Rajkot

Location of Quarry Identification Availability & type of Govt. Sample Approx. of extent Quarry For Land(G.L) S.No Depth total Quant- Contact Details of Quarry 3 Soil / Metal / /Private Distance (m) ity (ft ) Chainage Side Village State (Acres) Sand / Land(P.L) (KM) GSB/Flyash

Gurukrupa Metals, Rana Bhai, Rampar – 55 203+900 2.2 LHS Gujarat 10 10 404700 M – 12 PL Ph:9879878749, 995037375, beti Rajkot

Pramukrupa Crushers, Nayan Rampar – 56 204+000 2.2 LHS Gujarat 2 10 80940 M – 11 PL Bhai, Ph:9825070279, beti 9925042435

Rampar – Road Bheem Bhai, Ph:9978546181, 57 202+300 RHS beti Kuchy- Gujarat 2 3 24282 BA – 30 PL Side 9586813911 adad

Road 58 21+600 RHS Rajkot Gujarat 50 3 607050 BA – 26 GL - Side

Page 31 Consultancy Services for Preparation of Feasibility for 6 laning of Ahmedabad – Bamanbore – Samakhiali & Bamanbore – FORM -1 & Rajkot section of NH-8A & 8B in the State of Gujarat Terms of Reference (TOR)

DETAILS OF BORROW AREA , METAL QUARRY AND SAND

Project Name: Ahmedabad – Bamanbore -Samakhiali Section III, Bamanbore – Rajkot

Location of Quarry Identification Availability & type of Govt. Sample Approx. of extent Quarry For Land(G.L) S.No Depth total Quant- Contact Details of Quarry 3 Soil / Metal / /Private Distance (m) ity (ft ) Chainage Side Village State (Acres) Sand / Land(P.L) (KM) GSB/Flyash

Road 59 210+200 LHS Rajkot Gujarat 50 5 1011750 BA – 40 GL - Side

Shiv Stone Crusher, Ramesh 60 201+000 1.5 LHS Rajkot Gujarat 6 10 242820 M – 10 PL Bhai, Ph:9909922042/3, Sath- ada patio,rajkot

Note: B.A=BORROW AREA , MQ- METAL QUARRY , S- SAND , FA = FLYASH , GSB= GRANULAR SUBBASE

Page 32 Consultancy Services for Preparation of Feasibility for 6 laning of Ahmedabad – Bamanbore – Samakhiali & Bamanbore – FORM -1 & Rajkot section of NH-8A & 8B in the State of Gujarat Terms of Reference (TOR)

Mass-Haul Diagram Showing the Borrow Areas, Quarries and Sand stone in the Project Road (Bamanbore to Samaikhiali)

Mass Haul Diagram of Bamanbore – Samakhiali Section – II

Samakhiali

BA – 21 0.4 km 299+900 RHS S – 4 1 km 2 km 294+300 1 km BA – 20 LHS BA – 22

286+800 0.8 km

BA – 23

268+400 3.5 km BA – 24 2 km 260+700

BA – 34

Road Side 251+500 BA – 36

0.2 km

BA – 35 1.5 km 245+900 M – 8 1 km 17 km 242+600 M – 7 M – 6 Dhanaran River

237+600 50 km S – 5 BA – 37 5 km 226+200

BA - 39 2 km 219+100

BA - 38 6 km 208+400 M – 13 BA – 41(GSB) 202+500 1 km 202+400 1 km 202+000 M – 14

BA – 33 Road Side 193+100

BA – 32(GSB) Road Side 190+200

BA – 31

Road Side 184+200

- Borrow area Bamanbore - Metal quarry

__ Sand Quarry

Page 33 Consultancy Services for Preparation of Feasibility for 6 laning of Ahmedabad – Bamanbore – Samakhiali & Bamanbore – FORM -1 & Rajkot section of NH-8A & 8B in the State of Gujarat Terms of Reference (TOR)

Mass-Haul Diagram Showing the Borrow Areas, Quarries and

MASS HAUL DIAGRAM FOR RAJKOT – BAMANBORE Section – III

BAMANBORE

BA – 26(GSB)

212+600 Road Side BA – 40(GSB)

Road Side 210+200 M – 9 204+500 2 km M – 11 2.2 km 204+000 M – 12 2.2 km 203+900

202+300 Road Side BA – 30

M-10 201+000

1.5km 199+300 Road Side BA - 27

BA – 29 194+100 0.2 km

BA – 28 2.2 km 188+200

__ Borrow Area RAJKOT

__ Metal Quarry

Sand stone in the Project Road (Rajkote to Bamanbore )

Page 34 Consultancy Services for Preparation of Feasibility for 6 laning of Ahmedabad – Bamanbore – Samakhiali & Bamanbore – FORM -1 & Rajkot section of NH-8A & 8B in the State of Gujarat Terms of Reference (TOR)

Appendix -V: Location Map Showing the Wild Ass Sanctuary

Page 35 Consultancy Services for Preparation of Feasibility for 6 laning of Ahmedabad – Bamanbore – Samakhiali & Bamanbore – FORM -1 & Rajkot section of NH-8A & 8B in the State of Gujarat Terms of Reference (TOR)

Appendix -VI: Environmental Baseline Monitoring Results

Page 36