Certificate of Acceptance for Maintenance
Total Page:16
File Type:pdf, Size:1020Kb
Certificate of acceptance for practical completion
Name of project : Address :
Project manager:
Part 1 (please tick boxes)
I accept the works for practical completion and handover
I accept the works for practical completion and handover subject to the outstanding work being rectified by the contractor, or as shown in the completion certificate form (item 1 below – copy attached) under the terms of the contract. The person who will be responsible for ensuring that the contractor carries out the above work is:
The additional items in the attached schedule are to be completed before the work can be accepted for practical completion and handover (note: the schedule should show how these items will be executed and the responsibilities for action and supervision).
Part 2 Schedule of documents for practical completion (please tick boxes)
Completion certificate
Enclosed To follow Not applicable
1) Building control inspection for occupation
2) Certificate of occupation
3) Building log book
Building and structural information
4) Contractors and sub contractors drawing details
5) Health and safety file, including the date that drawings will be available
Mechanical and electrical information
6) O&M manual – electrical services (including as fitted drawings)
7) O&M manual – mechanical services (including as fitted drawings)
Test certificates
Enclosed To follow Not applicable
8) Electrical test certificate covering all circuits to BS 7671
9) Fire alarm test and certification to BS 5389
10) Emergency lighting test and certification to BS 5266 & BS 5499
11) Intruder alarm certification
12) Lightning conductor and earthing test results
13) Details of power operated doors
14) Window controls
15) CCTV systems
16) Disabled alarm systems to part M of the building regulations
17) Telecommunication and data installations to EN50173, BS 6701 and ‘Standards for wiring telecommunication networks in Cornwall Council buildings’
18) Lift test certificates as: a) Platform Lift BS 6440 b) Hydraulic or electric passenger/goods lifts BS 5655
19) Gas installation - internal
20) Gas installation - external
21) Boiler commissioning certificate
22) Internal heating installation
23) External heating mains
24) Mechanical ventilation/air conditioning plants and installations
25) Pressure test certificates
26) Certificate of chlorination 27) Certificate of dosing for heating systems
28) Cranes, hoists, lifting beams
29) Safety ring bolts – window cleaning equipment
30) Other plant and installations
Fire precaution documents
Enclosed To follow Not applicable
31) Schedule of fire appliances
Other miscellaneous requirements
32) Defect and failure reports already issued (with details of action taken)
33) Snagging list for building works
34) Snagging list for mechanical installation
35) Snagging list for electrical installation
36) Schedule of keys and security devices
37) Copies of any guarantees on materials and workmanship
38) Contractors evaluation form
Sections for any additional items
39)
40)
41)
42)
Part 33 Further documents The following documents are required and will be provided by the project manager within three months
Part 4
I acknowledge receipt of the information noted in part 2 above and await the information listed in part 3.
Signature: Date: Distribution (tick boxes) Contractor (three copies)
Area maintenance engineers (two copies)
Project manager (two copies)