This Is What We Have DONE!
Total Page:16
File Type:pdf, Size:1020Kb
October 25, 2009
Team 1,
This is what we have DONE!:
(Phase 1 of 3) due Wednesday, 8:00am CST of Week 10 : One printed report placed in a three holes binder. The report shall include but not be limited to the following: � Part 1 – Describe the mission of Habitat for Humanity � Part 2 – Project Information 2.1. Contact information of the person from a COMPANY that is not from Habitat for Humanity that will work with you to prepare the project SCHEDULE AND that you will INTERVIEW and VIDEO TAPE (Name of the Company, Name of the contact person, position, telephone, fax, e-mail, etc). 2.2. Description of your specific project (usage of the building, main characteristics, areas, location, etc). See Attachment 1. 2.3. ALL information relevant for scheduling the project (drawings, quantity take-off, specifications, etc). 2.4. Proof that ALL members visited at least once the site of your project (Ex: Picture on the site)
IMPORTANT: The team has to have access to one or more site of the ONE Project Type to TAKE PICTURES. (Example: access to multiple houses at different level of completion, if possible) � Part 3 – Project Questionnaire 3.1 Questions to be asked to a SCHEDULER that does NOT work with Hattiesburg Area Habitat for Humanity. THIS IS WHAT IS DUE THIS WEDNESDAY:
(Phase 2 of 3) due Wednesday, 8:00am CST of Week 11 :
INCLASS STUDENTS: � Part 4- Schedule (Using SureTrak) The schedule should have between 40 and 70 activities.
4.4. PERT (Diagram with activities on node)
4.5. TARGET or BASELINE Gantt (Bar) chart
4.7. TWO ANNOTATED Picture per activity LINKED to the Gantt chart (Either from the same project or a similar project). Annotated (with 2 to 5 line of text) in this context means describe the BEST CONSTRUCTION process so Volunteers can build the house PROPERLY.
Fountain, Thomas Clarke, James Maples, Jacob Ramey, Gary Smith, Matthew
YOUR INSTRUCTIONS:
Each of you will have to get 2 pictures per activity, and write 2-5 lines of text describing how someone who has never done construction can perform the activity.
You will have 8 activities/person. o 2 pictures/activity o Instructions on how to perform the activity (for someone who is not a construction person)
You will need to put your 2 pictures for each activity into a PowerPoint along with the instructions. o The PowerPoint template is attached and will be available on the wiki page under FINAL PROJECT TEAM 1 o You each will need to update and upload the most recent version of the PowerPoint to Wiki: . On the left menu (at the bottom on the WikiPage) . Click on upload file . Upload your file named as Team1_Phase2_Powerpoint_PUT YOUR VERSION # HERE.ppt DO NOT SAVE OVER SOMEONE ELSES YOU WILL ADD ON TO THE VERSION ABOVE YOURS AND SAVE IT AS A NEW VERSION . To get it on the WIKI: Copy the destination file name Go to finial project o Team 1 o Edit page (make sure you sign in!) o Use the same format as the template (put your file after image) . [[Image:Team1_Phase2_Powerpoint.ppt]] . save
Fountain, Thomas 1. 1000 Clear Site 2. 1010 Building Layout 3. 1020 Excavate Footers 4. 1030 Place Rebar 5. 1040 Pour Footings 6. 1070 Fill Dirt 7. 1080 Plumbing Roughin 8. 1090 Grade Dirt
Clarke, James
9. 1100 Place Wire Mesh 10. 1110 Set Forms 11. 1120 Pour Slab 12. 1125 Order Pre-Fabricated Wood Trusses 13. 1130 Pre-Fabricated Wood Framing 14. 1135 Tie Rough Wall Framing 15. 1140 Tie Trusses in to Framing 16. 1150 Install Exterior Sheathing
Maples, Jacob
17. 1160 Install Roof Decking 18. 1170 Install Roof Felt 19. 1180 Install Shingles 20. 1230 Install Doors & Windows 21. 1240 Install Roof Sheathing 22. 1250 Rough Plumbing 23. 1260 Rough HVAC 24. 1270 Rough Electrical
Ramey, Gary
25. 1280 Place Shingles 26. 1290 Install Vinyl Siding 27. 1295 Place Insulation 28. 1300 Hang Drywall 29. 1310 Finish Drywall 30. 1320 Install Cabinets & Trim 31. 1330 Painting 32. 1340 HVAC Trimout
Smith, Matthew 33. 1350 Electrical Trimout 34. 1360 Flooring 35. 1370 Finish Plumbing 36. 1380 Install appliances 37. 1390 Install Fixtures 38. 1400 Grading 39. 1410 Landscaping 40. 1420 Punch List