Humble Monthly Activity Report

Total Page:16

File Type:pdf, Size:1020Kb

Humble Monthly Activity Report

2013 PAVING IMPROVEMENTS PROJECT

HARRIS COUNTY, TEXAS

Weekly Progress Report HDR| Engineering Inc. Project No.13-047

Week Ending December 21, 2013

Submitted to

Piney Point City Council

4635 Southwest Freeway, Houston TX 77027-7169 (713) 622-9264. Fax (713) 622-9265. www.hdr.co Piney Point 2013 Paving Improvements Project Progress Report for Week ending December 21, 2013

December 15 to December 21, Activity/Status Activity/Status 2013 Paving IMPROVEMENTS PROJECT 2013 Paving IMPROVEMENTS PROJECT

MOBILIZATION:  This period no work was performed on t his aspect of the project.

PAVING ITEMS:

FARNHAM PARK

 This period no work was performed on t his aspect of the project.

MEADOWICK DRIVE

 Placed the concrete for this road repair 124 ft by Placed concrete for 11114 Meadowick driveway. View to the 14 ft. north.

 Placed steel reinforcement and concrete for the driveway at 11114 Meadowick.

Placed concrete for the road repair at 11114 Meadowick Drive. View to the east.

PINEY POINT ROAD (at Surry Oaks)

Placed forms and steel reinforcement on Meadowick Drive for the  Saw cut and removed the old concrete driveway and concrete road repair. View to the northeast. roadway on Piney Point at Surry Oaks Lane.

 Removed the driveway at 11334 Surrey Oaks N. COUNTRY SQUIRE DRIVE Lane.

 Completed repairs on this section.  Excavated out the old sub-base material and placed new stabilized sand. 111 ft by 14 ft.

 Placed steel reinforcement and concrete. December 15 to December 21, December 15 to December 21, Page 2 of 4 Piney Point 2013 Paving Improvements Project Progress Report for Week ending December 21, 2013

Activity/Status Activity/Status

2013 Paving IMPROVEMENTS PROJECT 2013 Paving IMPROVEMENTS PROJECT

WINDERMERE LANE

 Completed repairs on this section.

Placed stabilized sand, forms and steel reinforcement for Meadowick Drive. View to the west.

Removing the old concrete on Piney Point road for the roadway repair. View to the north.

Placing the concrete for the Piney Point Roadway repair and driveway at 11334 Surry Oaks Lane. View to the north.

Removing the concrete driveway at 11334 Surrey Oaks Ln. on the Piney Point roadway repair. View to the south.

December 15 to December 21, Page 3 of 4 Piney Point 2013 Paving Improvements Project Progress Report for Week ending December 21, 2013

Next Week’s Planned Activities Next Week’s Planned Activities December 22 to December 28, December 22 to December 28,

2013 Paving IMPROVEMENTS PROJECT 2013 Paving IMPROVEMENTS PROJECT

MOBILIZATION:  This period no work was performed on this aspect of the project.

PAVING ITEMS:

FARNHAM PARK

 This period no work will be performed on this aspect of the project till the week being December 30, 2013.

MEADOWICK DRIVE

 Place the 6-inch concrete curb. Placed concrete for the Piney Point road repair at Surry Oaks Lane. View to the north.

N. COUNTRY SQUIRE DRIVE Contractor will be off December 24 and 25 for  Completed Christmas and will return on the 26.

PINEY POINT ROAD

 Place the 6-inch concrete curb.

WINDERMERE LANE

 Completed.

Placing concrete for the Piney Point road repair. View to the north.