Initial Environment Examination

Project Number: 44427-013 May 2018 (Addendum)

IND: State Road Sector Project Subproject : Balod – (MDR) - Upgradation of 2 Lane to 4 Lane at Two Stretches under “Balod – Dhamtari” of Package-13

Submitted by

Public Works Department, Government of Chattisgarh,

This report has been submitted to ADB by the Public Works Department, Government of Chattisgarh, Raipur and is made publicly available in accordance with ADB’s Public Communications Policy (2011). It does not necessarily reflect the views of ADB. This report is an addendum to the IEE report posted in January 2013 available on https://www.adb.org/projects/documents/chhattisgarh-state-road-sector-project-balod-dhamtari- road-subproject-iee. This addendum to initial environment examination report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Addendum Initial Environmental Examination

Balod – Dhamtari (MDR) Subproject (Upgradation of 2 Lane to 4 Lane at Two Stretches under “Balod – Dhamtari” of Package-13)

Loan Number: 2981-IND May 2018

IND: Chhattisgarh State Road Sector Project

Prepared by: Public Works Department, Government of Chhattisgarh for the Asian Development Bank.

The addendum initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature

1 | P a g e

Contents

A. INTRODUCTION ...... 1 B. APPLICABLE ENVIRONMENTAL POLICIES AND OTHER LEGISLATIONS ...... 5 C. SUB-PROJECT DESCRIPTION ...... 5 D. APPROACH FOR ADDENDUM PREPRATION ...... 8 E. DESCRIPTION OF ENVIRONMENT ...... 8 F. POTENTIAL ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES ...... 9 G. ENVIRONMENTAL MANAGEMENT ...... 10 H. INSTITUTIONAL REQUIREMENTS AND ENVIRONMENTAL MONITORING PLAN ...... 10 I. GRIEVANCE REDRESS MECHANISM ...... 11 J. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE ...... 11 K. FIELD-BASED ENVIRONMENTAL DUE DILIGENCE ...... 12 L. CONCLUSION ………………………………………………………………………………………13

2 | P a g e

List of Tables

Table 1 - Details of Packages Under Group A Group B and Group C ...... 1 Table 2 - Package Wise Details of ADB Approved IEE Reports ...... 3 Table 3 - Details of Packages under Balod- Dhamtari (MDR)………… ...... 4 Table 4 - Change of scope from two to four lane in Package-13 ...... 5 Table 5 - Environmental Features Along the Sections ...... 8 Table 6 - Details of Tree Cutting ...... 9 Table 7 - Details of Payment to Forest Department ...... 9

List of Figures

Figure 1 - Project Location Map ...... 4 Figure 2 – Location map on google map from Km 17+080 to Km 17+640 at Gurur ………...... 6 Figure 3 - Location map on google map from Km 38+000 to Km 38+991 at Jhalmala….. …...... 6 Figure 4 - Approved Typical Cross section for 4 Lane ...... 7 Figure 5- Public Consultation at Gurur………...... 11 Figure 6 - Public Consultation at Jhalmala ...... 12

List of Annexures

Annexure I Rapid Environmental Assessment (REA) Checklist Annexure II Attendance Sheet of Public Consultation Annexure III Environmental Management Plan Annexure IV Environmental Monitoring Plan Annexure V Grevienece Readdressal Mechanishm Annexure VI Tree Cutting Permission (Package 13) Annexure VII Photographs of Field Visit

3 | P a g e

List of Acronyms

ADB Asian Development Bank CGPWD Chhattisgarh Public Works Department Ch. Chainage CSC Construction Supervision Consultant CSRSDP Chhattisgarh State Roads Sector Development Project CSRSP Chhattisgarh State Road Sector Project CTE Consent to Establish Cum Cubic meter DFO Divisional Forest Officer DPR Detailed Project Report EA Executing Agency EARF Environmental Assessment and Review Framework EHS Environment Health Safety EMP Environmental Management Plan GoCG Government of Chhattisgarh GPS Global Positioning System GRC Grievance Redressal Cell GRM Grievance Redress Mechanism HIV/AIDS Human Immunodeficiency Virus/ Acquired Immune Deficiency Syndrome HMP Hot Mix Plant IEE Initial Environmental Examination IRC Indian Road Congress JV Joint Venture Km Kilometre LHS Left Hand Side M.T. Metric Tonne MDR Major District Road MoEF&CC Ministry of Environment Forest & Climate Change MoRTH Ministry of Road Transport Highways PIU Project Implementation Unit PM10 Particulate Matter < 10 micron PM2.5 Particulate Matter < 2.5 micron PUC Pollution Under Control PWD Public Works Department RF Resettlement Framework RHS Right Hand Side ROW Right of Way RMC Ready Mix Concrete SH State Highway SPCB State Pollution Control Board SPS ADB Safeguard Policy Statement, 2009

4 | P a g e

A INTRODUCTION

1. Roads are the main mode of transportation in Chhattisgarh. National highways (NH6, NH16 and NH78) provide good east-west connections with neighbouring states, and NH43 and NH200 provide the main north-south connection between Raipur, Bilaspur and . However, the remaining roads in Chhattisgarh are mostly in poor conditions, and not passable in the monsoon season. This is especially true for roads in southern and northern Chhattisgarh, where most of the tribal people live. The total road length in Chhattisgarh is about 36,000 km with the road density less than 30 km per 100 km 2 against the national average of 100 km per 100 km2. To improve state roads, Chhattisgarh Public Works Department (CGPWD) in 2002–2003, prepared a 10-Year Master Plan for Road Sector Development (MPRSD) for the years 2003 to 2012. MPRSD aims to (i) promote development of six main road corridors, (ii) remove capacity bottlenecks from the network to better connect rural areas, and (iii) support socioeconomic development by improving road access and connectivity among growth centres. Based on MPRSD, Government of Chhattisgarh prepared and approved a priority investment program for improvement (rehabilitation, strengthening and widening) of about 5,000 km of state roads at an estimated cost of about Rs 105 billion ($2 billion). CGPWD has improved many roads through Government funds and support from funding agencies including 1249 Km roads with the help of ADB.

2. The Government of Chhattisgarh (GoCG) plans to improve the state road network under Chhattisgarh State Roads Sector Development Project (CSRSDP) with the assistance of Asian Development Bank and for that has applied a loan through Government of from the Asian Development Bank (ADB) for the improvement of about 916 kms state roads in Chhattisgarh. This road up-gradation and rehabilitation project will improve transport efficiency of the State road network which will contribute to expansion of economic opportunities and poverty reduction.

3. The Chhattisgarh Public Works Department (CGPWD), Government of Chhattisgarh is the Executing Agency (EA) for the project. The nineteen project roads have been divided into three Groups (Group A, B &C). The Consultancy services have been engaged for advisory and construction supervision, institutional strengthening, social rehabilitation and resettlement, environmental mitigation and road safety measures. The construction supervision consultancy works have been awarded to following agencies 4. This project comprises of widening and strengthening of state highways and major district roads. Under Group B roads, there are 8 packages (Package-1 to 6) of about 273.30 km, under Group B roads, there are 8 packages (Package-7 & 8, Package-10 to 15) about 390.36 km and under Group-C roads, there are 4 packages (Packages -16 to 19) comprising of 191.944 km road network. The details of road package, name of the road and length under each package are given in table 1.

Table 1 - Details of Packages Under Group A Group B and Group C Length S. No. Package Name of the Road District (km) Group –A 1. Package 1 Raipur – Bhaisa (SH-9) 36.50 Raipur Raipur & Baloda 2. Package 2 Bhaisa – Baloda Bazar (SH-9) 35.58 Bazar 3. Package 3 Nandghat – Baloda Bazar (SH-10) 42.19 Baloda Bazar 4. Package 4 Baloda Bazar - Gidhori (SH- 9) 49.04 Baloda Bazar 5. Package 5 Simga – Arang(Gullu) (SH- 20) 57.15 Raipur

1 | P a g e

Raipur & 6. Package 6 Arang (Gullu) – (SH-20 / MDR) 52.84 Dhamtari Total Length of Project Road in Group –A (in KM) 273.30 Group –B 7. Package 7 Raipur-Urla-Patharidih-Berla-Kodwa (MDR) 48.03 Raipur and Package 8 Balod and 8. - Kachche (SH-5) 77.13 Rajnandgaon 9. Package 10 Chandukuri Maro Umariya (MDR) 68.27 Bemetra Package 11 Rohanda-Foratari-Atariya-Khairagarh 10. 39.25 Rajandgaon (MDR) 11. Package 12 Khairagarh - Donagargarh - Tumadlbod (MDR) 53.31 Kabirdham 12. Package 13 Balod -Dhamtari (MDR) 30.67 Kabirdham 13. Package 14 Anda-Funda (MDR) 32.73 Durg and Balod 14. Package 15 Bodla-Traegaon-Daldali (MDR) 40.97 Balod Total Length of Project Road in Group –B (in KM) 390.36 Group –C 15. Package 16 Sheorinarayan – Birra – Champa (SH-9) 51.798 Janjgir-Champa Package 17 Bilaspur & 16. Ratanpur - Kota-Lormi (SH-10) 50.200 Mungeli Package 18 Lormi – Pandariya & Mungeli– Lormi with Mungeli & 17. 37.007 Mungeli bypass (SH-10/MDR) Kabirdham Package 19 Jairamnagar – Masturi – Malhar – Jondhara - Bilaspur & Baloda 18. 52.939 Lawan (MDR) Bazar Total Length of Project Road in Group –C (in KM) 191.944 Project Road Under Implementation in Group-A,B &C (in KM) 855.604

5. As required by ADB’s Safeguard Policy Statement 2009 (SPS 2009), an environmental assessment and review framework (EARF) was prepared and approved in 2012 to provide guidance on environmental screening, assessment, institutional arrangements, and procedures to be followed, where components were not yet been fully defined and locations not identified. The EARF ensures that succeeding tranches comply with SPS 2009 and the applicable national laws and regulations 6. The initial environmental examination was carried out for all the subprojects falling under group A, group B and group C and the details of ADB approved IEE reports against each package are provided in Table 2 below :

2 | P a g e

Table 2 - Package Wise Details of ADB Approved IEE Reports (Chhattisgarh State Road Sector Project)

ADB Approved IEE Report S. No. Package Name of the Road

1. Package 1 Raipur – Bhaisa (SH-9) Raipur to Balodabazar (SH-9); January 2013 2. Package 2 Bhaisa – Baloda Bazar (SH-9) 3. Package 3 Nandghat – Baloda Bazar (SH-10) Nandghat-Gidhoury (SH-10) July 2012 4. Package 4 Baloda Bazar - Gidhori (SH- 9) 5. Package 5 Simga – Arang(Gullu) (SH- 20) Simga-Kurud (SH-20); July 2012 6. Package 6 Arang (Gullu) – Kurud (SH-20 / MDR)

7. Package 7 Raipur-Urla-Patharidih-Berla-Kodwa (MDR) Raipur-Urla-Belra-Kodwa Road; January 2013 Package 8 Rajnandgaon 8. Rajnandgaon- Kachche (SH-5) Kachche(Antagarh) Road; January 2013 9. Package 10 Chandukuri Maro Umariya (MDR) Chandkhuri-Maro-Umariya Road; January 2013 Package 11 Rohanda-Foratari-Atariya-Khairagarh Dhamda -Khairagarh Road; 10. (MDR) January 2013 Package 12 Khairagarh - Donagargarh - Khairagarh-Tumdibod Road; 11. Tumadlbod (MDR) January 2013 Package 13 Balod – Dhamtari Road; January 12. Balod -Dhamtari (MDR) 2013 Package 14 Anda-Funda Road; January 13. Anda-Funda (MDR) 2013 Package 15 Badola-Daldali Road; January 14. Bodla-Traegaon-Daldali (MDR) 2013 Package 16 Shivrinarayan-Birra-Champa 15. Sheorinarayan – Birra – Champa (SH-9) Road; January 2013 16. Package 17 Ratanpur - Kota-Lormi (SH-10) Ratanpur-Kota-Lormi-Pandaria- Mungeli Road; January 2013 Package 18 Lormi – Pandariya & Mungeli– Lormi with 17. Mungeli bypass (SH-10/MDR) Package 19 Jairamnagar – Masturi – Malhar – Jondhara Jairamnagar – Masturi-Lawan 18. Road; January 2013 - Lawan (MDR) 7. The ADB approved IEE report “Balod -Dhamtari (MDR)” approved in January 2013 cover one package i.e. package 13. During implementation stage change in scope of work was undertaken in package 13 from the original provided scope of work as per ADB approved IEE report. The detail of in this package ‘‘Balod -Dhamtari (MDR))” is provided in table 3 while project location Map is given in figure 1.

3 | P a g e

Table 3 - Details of Package under Balod -Dhamtari (MDR)

S. No Package Name of Package Length Location 1 13 Balod -Dhamtari (MDR) 30.67 Balod -

Figure 1 - Project Location Map

8. This report is addendum to the ADB-approved IEE report prepared for ‘Balod -Dhamtari (MDR)”. The addendum to IEE report has been prepared due to change of scope from two lanes to four lanes at two different sections of under this contract package -13. 9. This addendum to IEE report would capture information on the environmental consequences associated with change of scope. This report will also cover the field based environmental due diligence studies to

4 | P a g e

ascertain presence of any residual environmental impacts since the sub-projects were implemented without undertaking environmental assessments and suggest specific remedial measures, if any to address such residual impacts. B. APPLICABLE ENVIRONMENTAL POLICIES AND OTHER LEGISLATIONS

10. As per the Ministry of Environment, Forest and Climate Change, GoI, vide its Notification No.S.O. 1533 dated 14-09- 2006 and its subsequent amendment, the environmental clearance is not applicable under the sub-project. Aside from SPS 2009, the project needs to comply with the requirements provided by the GoI acts, rules, notifications, standards, and policies and other state level guidelines that apply to the project. The relevant regulations and other legislations are given in chapter 2 of ADB approved IEE report, January 2013 are applicable for this subproject. C. SUB-PROJECT DESCRIPTION 11. The project activities involve widening of existing roads to 2 – lane carriageway, within available ROW. The Balod -Dhamtari Road is 30.67 Km long, where widening and up-gradation have been proposed. The road widening activities primarily will comprise of raising the embankment at certain locations and its stabilisation including construction of retaining wall if required especially near wate r bodies, overlay on the existing carriageway, junction improvement, and construction of minor bridges, culvert and RCC drain in built-up section. 12. The project road starts on SH-7 at Km 53.900 and ends on NH – 43 at Km 85.300. The total length of the project road is 31.67 km. It starts from Balod and passes through Purur, Kamharkham, Kaneri, Kulia, Bohardi, Gurur, Tari, Barda, Kannewada, Sakre, Jamruva, Jagtara and Jamala terminates on NH- 43. The project road at two different sections such as from (i) Km 17+080 to Km 17+640 at Gurur; and (ii) Km 38+000 to Km 38+991 at Jhalmala will be four lane within available RoW. There is very little congestion along the junctions. Improvement of this road section will connect the interior rural areas with the National Highway 43 and thereby bring people nearer to district headquarters at Balod and Dhamtari districts. 13. During the implementation stage the widening of road was undertaken for 4 lane carriageways instead of 2-lane (as provided in ADB approved IEE report) at two chainages. The 4-lane carriageway included 14.0 m wide road (with 7 m width of each lane), 0.400meter median and 1.3 m of drainage on both sides. The hard shoulder varies from 1.6 m to 2.5 m depending on the available RoW and the works have been completed within the existing RoW. 14. This addendum to ADB approved IEE report is being prepared due to widening of road to four lanes instead of two lane (provided in scope of work as per approved IEE) at two stretches of “Balod - Dhamtari (MDR)” Road. The details are given in table 4: Table 4 - Change of scope from two to four lane in Package-13 Location Name Chainage (KM) Length (Km) S.No

1 Gurur Km 17+080 to Km 17+640 0 .560 2 Jhalmala Km 38+000 to Km 38+991 0.991 Total Length of 4-lane Stretches 1.551

5 | P a g e

15. The location maps prepared in google map Gurur from Km 17.080 to Km 17.640, and Jhamala from Km 38.000 to Km 38.991 are given in figure 2 and figure 3 respectively. The typical cross-section for four lane is given in figure 4. 16. The works have been completed at all two sections of four lane alignments.

Figure 2 – Location map on Google from Km 17+ 080 to Km 17 +640 at Gurur

Figure 3 - Location map on Google from Km 38+000 to Km 38+991 at Jhalmala

6 | P a g e

Figure 4 - Approved Typical Cross section for 4 Lane 2

7 | P a g e

D. APPROACH FOR ADDENDUM PREPRATION

17. The Addendum to ADB-approved IEE report (January 2013) has been prepared based on field visits, carrying out discussion with field staffs and the officials of executing agency (EA) conducted during project implementation stage. The information gathered during site visit has been used to update the Rapid Environmental Assessment (REA) Checklist (Annexure I), which assisted in screening, categorization of sub-project and anticipating potential impacts on environment due to construction of sub-project.

E. DESCRIPTION OF ENVIRONMENT

18. The sub-project is located in district Balod and Dhamtari. The descriptions of environment for this district have been captured in Chapter 3.0 (Description of Environment) of ADB approved IEE report prepared in January 2013, which adequately capture the environmental setting in the district and may be referred. The testing of environmental parameters such as ambient air quality, ambient noise levels and water quality have been conducted package wise under the project covered in different environmental monitoring reports. The environmental features along the sections from Km 17.080 to Km 17.640 and from Km 38.000 to Km 38.991 has been collected from site and given in the table 5. Table 5 - Environmental Features Along the Sections S. No Environmental Features Status Remarks, if any 1 Forest section Not involved No impact anticipated 2 Number of trees available No tree is present at location where No impact anticipated the scope of work is changed. The work is being carried out under existing Row. No additional tree cutting is involved due to change of scope. 3 Tree to be cut due to No additional tree cutting is involved No impact anticipated change of scope 4 Water bodies such as No water bodies are present along the No impact anticipated pond, river sections where the scope of work is changed. However, small village ponds are present alongside the overall stretch of road. No impact is anticipated on village ponds due to change in scope of work. 5 Environmental sensitive No school, college and hospital are No impact anticipated features such as school, present nearby the sections where the college, hospitals scope of work is changed. However educational institutions and hospitals are present alongside the overall stretch of road. Safety measures are being taken to avoid any hinderance to educational institutions and hospitals as given in EMP 6 Archaeological site, Not involved No impact anticipated monument, cultural heritage and temple

8 | P a g e

F. POTENTIAL ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

19. The preparation of this addendum is accordance to specified criteria provided in the Environmental Assessment Review Framework (EARF). These criteria were used for identify in the potential environmental impacts due to the sub-project in ADB-approved IEE report under the Chapter 5. The REA checklist prepared for the sub-project forms the basis for assessment of potential environmental impacts and suggesting mitigation measures

20. No additional environmental impacts are anticipated due to widening of road from 2 lane (as per scope provided in ADB approved IEE report) to 4 lane (Changed scope of work). The change in scope of work does not involve any additional tree cutting, structure damage, impact on water bodies and environmental sensitive area. The upgradation of road is being undertaken within the existing RoW thus no land acquisition is required. Thus, the no additional mitigation measures are suggested

21. The roads under package-13 “Balod-Dhamtari (MDR)” not pass through any forest land. However, to up-grades the roads tree cutting is inevitable. During implementation stage, a total of 456 trees of which total 465 trees may need to be cut in actual within ROW in this Package. The number of trees impacted for upgradation to 4 lane remains same as for 2 lane, as there are no additional tree s cutting involved due to change in scope of work. The details of trees required to be cut under package 13 is provided in table 6 and permission obtained from competent authority for package 13 is provided in Annexure VI .

22. The tree cutting required for widening of road to 2 lane road and 4 lane road remained same as no additional tree cutting was required for widening of road to 4 lane. This to clarify that the widening of road to 4 lane is done within the existing RoW and no land acquisition is involved

Table 6 - Details of Tree Cutting Package Permission Obtained from Actual No. of No. of Trees Cut Balance No. of No. Collector for cutting of Trees Trees to be Cut As on 31th March 2018 Trees to be cut 8 456 456 456 0

23. For each tree to be cut for the road widening, the concerned authority in their permission letters have imposed condition that 10 times the trees should be planted preferable near to the existing roads as compensatory plantation. The details of payment made to State Forest Department under each package for tree cutting and compensatory plantations are provided in table No.7

Table 7 - Details of Payment to Forest Department Package Payments Done to Forest Department Forest Division No. As on 30TH March 2018 (Rs. in Lacs) For Cutting of Trees Compensatory Plantation

13 8.65 45.60 DFO Balod Sub Total 8.65 45.60

24. The change in scope of work will not change the environmental category of the project i.e. Category - B as no additional environmental impact is anticipated. Moreover, the widening of road from 2 to 4 lane is within the RoW of existing road. The potential environmental impacts anticipated remains same and are specifically capture in Section 4.0 of ADB-approved IEE report, which is also valid during widening of road to 4 lane.

9 | P a g e

G. ENVIRONMENTAL MANAGEMENT

25. The ADB-approved IEE report has suggested appropriate measures to mitigate impacts associated with construction activities. An Environmental Management Plan (Annexure III) has been prepared for the project that discusses the anticipated impacts, monitoring requirements, and development of mitigation measures with respect to the following stages: (i) Pre-Construction, (ii) Construction, and (iii) Operation and Maintenance. The environmental management plan was made part of contract agreement for contractor’s mandatory compliance to EMP.

26. The impacts associated with the sub-project are mainly due to activities during construction stage. As no additional environmental impacts are anticipated due to the change in scope of work. Thus, the Environmental Management Plan prepared for the project is adequate to mitigate the impacts due to sub-project

H. INSTITUTIONAL REQUIREMENTS AND ENVIRONMENTAL MONITORING PLAN

27. Chhattisgarh State Roads Sector Development Project (CSRSDP) has taken up civil works for road up-gradation and rehabilitation, Consultancy services have been engaged for advisory and construction supervision, institutional strengthening, social rehabilitation and resettlement, environmental mitigation and road safety measures.

28. The Government of Chhattisgarh (GoCG) plans to improve the state road network under Chhattisgarh State Roads Sector Development Project (CSRSDP) with the assistance of Asian Development Bank. The Chhattisgarh Public Works Department (CGPWD), Government of Chhattisgarh is the Executing Agency (EA) for the project

29. The Consultancy services for Construction Supervision for the project roads to be developed are divided into three Groups (Group A, Group B and Group C). The Chhattisgarh Public Works Department has employed Egis International in JV with Egis India Consulting Engineering Pvt. Ltd.to undertake Consultancy services for Construction Supervision of Rehabilitation and Upgrading of Group “B” Road (Contract Package 7 to 15) Contract Agreement No.10 of 2014-2015, Durg Dated 28.02.2015. The objectives of the Consultancy services are to ensure that high quality construction is achieved and to ensure that all work is carried out in full compliance with the Environmental Safeguard, Social Safeguard, Engineering design, technical specifications and other documents as well as promoting technology transfer by employment of local/PWD staff and on the job training

30. The Road Specific Environment Management Plan has been formulated which consists of a set of mitigation measures; monitoring and institutional measures applicable to design, construction and operation stages of the project and roles and responsibilities of various parties. The upgradation of environmental management plan is not required due to change of scope and no additional environmental implications are anticipated. Thus, the EMP present in the ADB-approved IEE report has been implemented by the civil contractors

31. In order to comply to requirements of Environmental Monitoring Plan (EMoP) as provided in Contract Agreement an external environmental monitoring agency M/s Anacon Laboratories Pvt. Ltd. (NABET Accredited & MoEF&CC approved Laboratory) has been hired by the Civil Contractors for their respective packages to carry out the environmental monitoring with regards to ambient air quality, water quality, soil quality and noise levels during the construction period.

10 | P a g e

32. The environmental monitoring for ambient air quality, water quality, soil quality and noise levels have been conducted during construction phase and test results along with analysis are covered in subsequent semi-annual environmental monitoring report.

I. GRIEVANCE REDRESS MECHANISM

33. Balod-Dhamtari (MDR) Subproject falls under Balod & Dhamtari Districts. Grievance Redressal Committee (GRC) has been formed this project district. The details are provided in Annexure V.

34. Grievance Redress Committee (GRC) set up at district level monitors grievances arising during implementation for each package under area of its jurisdictions. The GRC determines the merit of each grievance, and resolve grievances within an outer time limit of three months of receiving the complaint. The Affected Persons has the right to refer the grievances to appropriate courts of law if not satisfied with the redress at any stage of the process. The set up GRC has the system of records keeping, contact details of complainant date of the complaint received, nature of grievance etc. if any for the ongoing project and taking the necessary action against the complaint

35. Till date no grievance has been reported with respect to environmental issues in this package 13 (Balod-Dhamtari (MDR). Any grievance from any person will be addressed in set time frame and will be properly documented.

J. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE

36. Public Consultation (PC) meetings with local people residing along the road have been conducted at all two locations such as Gurur and Jhalmala. The photographs collected during PC at Gurur and Jhalmala are given in Figure 5, and 6 respectively.

37. The meeting aims to address associated environmental implications due to proposed project. The sample attendance sheet of public consultation at Jhalmala Chowk is provided in Annexure II. The discussions during the consultation are as follows:  General issues related to safety, accident and traffic control and dust emission has raised by the local community which contractor has proposed in their action plan to follow during construction.

Figure-5 Public Consultation at Gurur

11 | P a g e

Figure-6 Public Consultation at Jhalmala 38. The addendum to IEE report shall be disclosed and made available to the public.

K. FIELD-BASED ENVIRONMENTAL DUE DILIGENCE 39. This chapter ascertains presence of any residual environmental impacts due to implementation of works at two locations i.e. Balod-Dhamtari (MDR) 1.551 km {Gurur 00.560 km (Km 17.080 to Km 17.640) and Jhalmala 0.991 km (38.000 to Km 38.991)} where scope of work is changed from the original provided scope and suggests appropriate, time-bound corrective measures to address those residual environmental impacts, if any. The photographs of field visit are provided in Annexure VII. 40. The various aspects that would be considered for such field-based environmental due diligence are elaborated below: (a) Confirmation of EMP in contractor’s contract agreement: EMP is made part of contractor’s contractor agreement and the contractor’s compliance to EMP is being monitored by carrying out field visits from time to time during the project implementation. The change of scope in package-13 has not resulted in any addition environmental implication. No environmental sensitive area, structures, water bodies and trees are present in the area where the road is being upgraded from 2 lane to 4 lane. Moreover, the upgradation of road is being undertaken in the existing RoW. Thus, the upgradation of EMP is not required due to change of scope. (b) Compliance status during pre-construction and construction stage of the sub-project(s): Environmental Management Plan is made part of contractor’s contract agreement and contractor is mandate to comply with the environmental implications provided in the EMP. (c) Status of statutory permission applicable for the sub-project(s), if any: No additional statutory permission is required due to change of scope in package-13 The applicable statutory permissions such as (i) consent to establish and operate of construction plants; (ii) , permission to withdrawal of construction water from surface and ground water sources; (iii) quarry lease deed and quarry license from state department of mines and geology; (iv) labor licenses and associated insurance policy/workmen compensation; and (v) permission of storage handling and transport of hazardous material have been obtained by the respective civil contractors. The civil contractors have also renewed the required statutory permissions for the sub-project. (d) Status on implementation of environmental mitigation measures, if any and testing of environmental parameters of ambient air quality and ambient noise levels along the sub- projects as per agreed monitoring plan, if any: environmental monitoring for ambient air quality,

12 | P a g e

water quality and ambient noise level have been carried out as per given ADB-approved environmental monitoring plan (Refer Annexure IV). All the test results are within permissible limits and no impacts on air quality, water quality and ambient noise levels are anticipated due to change of scope under package-13. (e) Residual environmental impacts, if any with appropriate, time-bound corrective measures: The civil contactors are reminded from time to time, to follow the environmental management plan and the mitigation measures as per EMP. No environmental impact has be en noticed. Thus, no added corrective measure is required/suggested. (f) Public consultations during project implementation stages: Public consultation is being carried out as a part of continuous participation of public in the proposed project during the implementation stage. The details of public consultations carried out for the changed scope of subp roject are provided in Chapter J of this addendum to IEE report. The public consultations being carried out during project implementation stage are also being updated in the subsequent semi-annual environmental monitoring reports. (g) Status of grievances, if any, received due to implementation of the sub-projects: The grievance redressal committee are setup in all the concern districts (Annexure V). The details of GRC are provided in Chapter I of this addendum to IEE report. No grievance related to environmental issue for any subproject is recorded. (h) Conclusions: No major environmental impact is predicted due to the change in scope of subproject.

L. CONCLUSION 41. This addendum to IEE report is based upon the environmental assessment and review framework (EARF) which is consistent with the ADB’s Safeguard Policy Statement (SPS) 2009. The subproject is classified as category “B” for environmental and does not require further environmental impact assessment. The ADB-approved EMP prepared for the project is valid and the same is recommended for adoption during implementation stage.

13 | P a g e

Annexure – I Rapid Environmental Assessment Checklist

ROADS AND HIGHWAYS Instructions (i) The project team completes this checklist to support the environmental classification of a project. It is to be attached to the environmental categorization form and submitted to the Environment and Safeguards Division (RSES), for endorsement by Director, RSES and for approval by the Chief Compliance Officer.

(ii) This checklist focuses on environmental issues and concerns. To ensure that social dimensions are adequately considered, refer also to ADB's (a) checklists on involuntary resettlement and Indigenous Peoples; (b) poverty reduction handbook; (c) staff guide to consultation and participation; and (d) gender checklists.

(iii) Answer the questions assuming the “without mitigation” case. The purpose is to identify potential imp acts. Use the “remarks” section to discuss any anticipated mitigation measures.

Country / Project Title: India : Chhattisgarh State Road Sector Project: Subproject –Balod- Dhamtari (MDR ) Subproject (Chhattisgarh) Sector Division: Transport Sector Screening questions Yes No Remarks A. Project Siting Is the project area adjacent to or within any of the following environmentally sensitive areas? Cultural heritage site X No archaeologically protected monument or cultural heritage site in located within the road ROW or even within 5 Km distance from the road. Though, few religious structures like temple are located close to the roads. Protected Area X No protected area is located close to roads and nearby (assessment made upto 10 Km ) area. Wetland X No protected or classified wet land is located close to the roads. Few village ponds though are located close to the project road. Mangrove X Project road is not located in coastal areas. Estuarine X No Estuarine is located in the project area. Buffer zone of protected area X No such area is located in the project vicinity. Special area for protecting biodiversity X No such area is located in the project vicinity. B. Potential Environmental Impacts Encroachment on historical/cultural areas; X The topography of proposed project road is disfiguration of landscape by road mainly plain. There is no encroachment of embankments, cuts, fills, and quarries? historical places in this stretch. Since road

14 | P a g e

Screening questions Yes No Remarks widening being confined to available ROW, no change in landscape is expected. Earth material will be sourced from pre identified areas (located within 25 to 30 Km from the road) and with the consent of landowner. All borrow areas being suitably rehabilitated.

No such impact is envisaged because of changed scope of subproject. Encroachment on precious ecology (e.g. X There is no National Parks, Wild Life Sensitive or protected areas)? Sanctuaries or any other similar eco- sensitive areas in and around the project area. Alteration of surface water hydrology of X The proposed change in scope of work waterways crossed by roads, resulting in (construction of four lane divided increased sediment in streams affected by carriageway in 1.551 km length) are not increased soil erosion at construction site? crossing through any Rivers and small drains. No addition impact is anticipated due to changed scope of subproject. Deterioration of surface water quality due to X Adequate sanitary facilities including silt runoff and sanitary wastes from worker- sewage treatment facilities being provided based camps and chemicals used in at construction camp, which being set-up construction? away from habitat and water bodies. No harmful ingredients are likely being used in the construction activities. As such, no impact on surface water quality is anticipated due to construction. No such additional impact is envisaged because of changed scope of subproject. Increased local air pollution due to rock X Localised air pollution level is likely being crushing, cutting and filling works, and increased for short duration during chemicals from asphalt processing? construction period due to construction vehicle movement and asphalt processing. The asphalt mixing plant (hot mix plant) has been located away from habituated areas with adequately high stack for effective dispersion of likely emissions. Dust separation measures like spraying of water on unpaved vehicle movement areas being proposed to minimise the dust generation.

The changed scope of subproject does not result in any additional impact Risks and vulnerabilities related to X Workers may get exposed to dust and occupational health and safety due to noise during construction activities. physical, chemical, biological, and However the exposure levels being for

15 | P a g e

Screening questions Yes No Remarks radiological hazards during project short and insignificant. Workers have been construction and operation? provided PPEs to minimise such exposure and associated harmful occupational health

effects.

Traffic on the road is expected little high and as such, no occupational health hazard is anticipated during operation phase. The impact due to changed scope of work will remain same as earlier. Noise and vibration due to blasting and X No Blasting is involved. No significant noise other civil works? generation is expected during construction activities except normal construction equipment operational noise.

All stationary noise making sources equipment like DG set, compressors being installed with acoustic enclosures.

No such additional impact is envisaged because of changed scope of subproject. Dislocation or involuntary resettlement of X The project road being widened within people existing RoW to two lane to four lane at two locations . No such additional impact is envisaged because of changed scope of subproject Dislocation and compulsory resettlement of X No displacement of people is involved. people living in right-of-way? Disproportionate impacts on the poor, X No such impact is being anticipated. women and children, Indigenous Peoples or other vulnerable groups? Other social concerns relating to X No such social concern is being expected. inconveniences in living conditions in the Concern may arise during construction project areas that may trigger cases of stage due to increase in ambient air upper respiratory problems and stress? pollution levels, which is expected being localised and temporary in nature. This aspect being effectively controlled with the proposed dust suppression and other mitigation measures. As such people at large are supportive of project.

No such additional impact is envisaged because of changed scope of subproject Hazardous driving conditions where X Hazardous driving condition may arise construction interferes with existing roads? around bridge construction areas and at locations of road interface with non-project roads. To minimized the impact suitable traffic management plan being designed and implemented by the contractor to

16 | P a g e

Screening questions Yes No Remarks prevent any hazardous driving condition in above situations.

No such additional impact is envisaged because of changed scope of subproject

Poor sanitation and solid waste disposal in X Proper provisions for sanitation (sewage construction camps and work sites, and treatment), health care (drinking water possible transmission of communicable supply and periodic health check-ups) and diseases from workers to local populations? solid waste disposal (through composting) facilities being made at each construction camp.

Awareness being created amongst the workers about hygiene and health protection. Creation of temporary breeding habitats for X No such condition is being anticipated. mosquito vectors of disease? Further each borrow area will be rehabilitated as per pre-agreed used and rehabilitation plan.

No such additional impact is envisaged because of changed scope of subproject Accident risks associated with increased X Adequate safety measures being adopted vehicular traffic, leading to accidental spills to avoid accidents during construction and of toxic materials and loss of life? will be operation stages. Measures, like signage, speed control, crash barriers will be taken close to sensitive locations if required Increased noise and air pollution resulting X Increase in noise and air pollution is little from traffic volume? being expected during construction phase but it has been confined within few meters of either side of the road. Adequate mitigation measures being adopted to minimise the same. During operation phase, vehicular traffic will be the main source of air and noise pollution. Improved road conditions, extensive plantation including multi-layered plantation along the road will reduce the noise and air pollution impact.

No such additional impact is envisaged because of changed scope of subproject Increased risk of water pollution from oil, X This possibility is minimal but cannot be grease and fuel spills, and other materials ruled out. Controlled construction activities from vehicles using the road? and proper drainage system being reduced this possibility.

17 | P a g e

Screening questions Yes No Remarks Provision is made for adequate signage and crash barriers near water bodies, which will minimise the possibilities of accidental water pollution.

No such additional impact is envisaged because of changed scope of subproject Social conflicts if workers from other X Most of the workers being hired locally. regions or countries are hired? Large population influx during project X Most of the workers being hired locally. construction and operation that causes One construction camp has been increased burden on social infrastructure established in this package with expected and services (such as water supply and workers population of only 50-60. This is sanitation systems)? unlikely to cause any significant burden on social infrastructure and services. Risks to community health and safety due X The construction material (aggregate from to the transport, storage, and use and/or approved quarries, borrow earth, bitumen) disposal of materials such as explosives, being sourced from nearby and approved fuel and other chemicals during sources. No explosive or chemicals is construction and operation? being used. Bitumen waste if any generated during construction being either recycled or disposed-off in controlled manner. Community safety risks due to both X No such impacts are anticipated. accidental and natural causes, especially Adequate awareness being created where the structural elements or amongst people and workers through components of the project are accessible to information disclosure, safety signage and members of the affected community or public consultation about safety aspects. where their failure could result in injury to the community throughout project construction, operation and decommissioning. Based on above assessment no additional environmental impact is anticipated and the project is categorized as ‘B’

18 | P a g e

Annexure II Attendance Sheet of Public Consultation

19 | P a g e

Annexure III

Environmental Management Plan for Balod – Dhamtari Road

(The requirement related to ‘Precautions for Safeguarding Environment” detailed at Section 111 of Technical Specifications and Sub-clause 4.18 of PCCB (pre-conditions for contract bidding) shall be read in conjunction with the measures given below. All the requirement detailed at section 111 and sub clause 4.18 and as given below are to be implemented.)

Environmental Remedial Measures Reference to Laws Approximate Mitigation Cost Institutional Responsibility Aspect/Impact /Guidelines Location Implementation Supervision A. Design and Pre - Construction Stage 1. Design Considerations Legislative approvals Considering the proposed project Legislative As identified in DPR Part of Activity 1 to 3 PIU PWD activities the following legislative requirements for the location of construction concerned approvals shall be required in respective activity. costs Nodal officer of advance: PWD and activity 4 & 5 1. Obtain permission from forest or contractor district authorities as applicable for cutting of trees

2. Obtain concurrence from Gram Panchyats for shifting or demolition of community structure 3. Obtain permission from concerned authorities for shifting of utilities ( like electric pole, telephone lines, hand pumps) 4. Obtain connect to establish Hot Mix plant, batching plant(if required), quarry operation if new quarry to be opened, and setting up construction 5. Obtain permission for withdrawal of ground water as applicable Utility Relocation Utilities relocation will be Design requirement As per widening plan Included in Design PIU PWD reasonably completed before construction cost Consultant construction starts and without affecting any essential supplies to habitat like water supply..

20 | P a g e

Environmental Remedial Measures Reference to Laws Approximate Mitigation Cost Institutional Responsibility Aspect/Impact /Guidelines Location Implementation Supervision Shifting of Community Community structures, like, Design requirement As per widening plan Included in Design PIU PWD Structure religious structures will be shifted construction cost Consultant appropriately, if required. Climate Change and No climate Change induced Local Forest Rule Within RoW or on Covered in EMP Through Forest PIU PWD Removal of trees vulnerability anticipated. Govt. Land Department

Approximately 456 trees may need to be cut within 16m ROW for up-gradation of the project road before the commencement of construction with prior Clarence from the Forest Department/District Authorities as applicable.

Compensatory afforestation: Ten trees will be planted for each tree felled as per regulatory compliance. Geometric adjustment to reduce tree cutting.

Removal of Structures The project road does not require Design requirement Within RoW Included in Construction PIU PWD and acquisition of land land acquisition Only few non title construction cost Agencies, PIU/ holders are affected. They will be PWD removed as per the project’s Rehabilitation and Resettlement plan prepared separately Widening Option and Selection of widening option (left Design requirement All habitat areas Included in Design PIU PWD Pavement design and aligned, right aligned or centric throughout the construction cost Consultant inadequate drainage widening) to be decided based on alignment provisions in habitat the least cutting of tree, minimum areas loss of structure and embankment design considerations.

Selection of suitable pavement design in settlement areas considering alignment level and drainage requirements.

Raise road level as feasible, above the nearby areas with provision of adequate side drains to evacuate the rain water and

21 | P a g e

Environmental Remedial Measures Reference to Laws Approximate Mitigation Cost Institutional Responsibility Aspect/Impact /Guidelines Location Implementation Supervision domestic discharges (drained by settlement occasionally) to prevent damage to road and rain water entry to habitats’ houses.

Provision of adequate no of cross drainage structures based on drainage pattern shall be made to maintain natural flow of rain water across the road. Safety along the Adequate safety provisions like Design requirement Crash barriers are Included in Design PIU PWD proposed alignment crash barriers at accident prone proposed at sensitive construction cost Consultant areas, rumble strips in habitat locations like school, areas to regulate speed, retro- medical centers, reflective warning sign boards along the project nears school, hospital, religious corridor places (Preferably PCC boards with retro- reflective paints to Rumble strips are avoid its theft) shall be made. proposed at the all the settlements and crossing points

2. Natural Hazards Protection from Adoption of relevant IS codes for IRC:34 Throughout the Project Design PIU PWD damage from design embankment/ structures Recommendations stretch especially preparation and Consultant Earthquake suitable to withstand earthquake for road construction bridge structures construction of highest magnitude in moderate in waterlogged area costs Cost earthquake intensity Zone ( and IRC: 75 and Seismic Zone II level as per Indian MoRT&H guidelines classification). for Design of High Embankments B. Construction Stage 3. Climate and Air Quality Local Weather Additional Plantation on river Kyoto Protocol, Road Side Design CSC / PIU Throughout project conditions banks, borrow areas and sensitive Environmental Plantations in Consultant and PWD corridor, mainly at locations to increase the green Protection Act, 1986; the ratio of 1:10 Contractor cover and improve the aesthetics The Air (Prevention haulage roads, ( costs highlight earthwork, and Control of in the following Pollution) Act, 1981 construction sites, table) loading areas, + Included in Design CSC / PIU storage areas, IRC and construction Consultant and PWD transport route. Dust Generation due Transport, of loose and fine MORT&H costs Contractor CSC / PIU to construction materials through covered vehicles Specifications for PWD

22 | P a g e

Environmental Remedial Measures Reference to Laws Approximate Mitigation Cost Institutional Responsibility Aspect/Impact /Guidelines Location Implementation Supervision activities and and paved roads to the extent Road and Bridge transport, storage and feasible . works handling of Air (P and CP) construction materials Loading and unloading of Act 1974 and Central construction materials shall be Motor and Vehicle made at designated locations in Act 1988 project area with provisions of water fogging around these locations

Storage areas to be located downwind of the habitation area.

Water spraying on earthworks, unpaved haulage roads and other dust prone areas.

Provision of PPEs to workers. Emission from vehicle, Regular maintenance of machinery Asphalt mixing Included in Contractor CSC/ CSC / equipment and and equipment. plants, crushers, DG construction PIU PWD machinery sets locations costs Hot Mix Plant shall have a bag filter and be located at least 1 km downwind of the human settlement. Included in monitoring cost Batching, plant (if required) and crushers at downwind (0.5km) direction from the nearest settlement. Hot mix plant to be fitted with adequate stack height. Obtain consent to establish (NOC) from PCB before setting up these plants.

Only crushers licensed by the PCB shall be used

DG sets with stacks of adequate height and use of low sulphur diesel as fuel.

Use LPG as fuel at construction camps

23 | P a g e

Environmental Remedial Measures Reference to Laws Approximate Mitigation Cost Institutional Responsibility Aspect/Impact /Guidelines Location Implementation Supervision

Undertake periodic ambient air quality monitoring as per EMOP 4 . Noise Noise from Provision is made for installing Legal requirement The school, hospitals Cost for Contractor CSC / PIU construction vehicle, need base noise barrier near Noise Pollution are away from the Plantation PWD equipment and sensitive locations like hospitals, (Regulation and road, therefore, at already machinery. schools. Control) Rules, 2000 the time of indicated above. and amendments construction of road Rest part of All equipment shall be fitted with thereof supervision construction silencers and will be properly + consultant will costs maintained to minimize its Clause No 501.8.6. evaluate the need to operational noise. MoRT&H noise barriers. Specifications for Stationary noise making Road and Bridge equipment shall be placed along works uninhabited stretches. Monitoring Cost The timing for construction as indicated In activities shall be regulated such EMoP. that all noise generating construction activities happen after school hours.

Construction must not take place at night to avoid disturbance to community.

The provision of temporary noise barrier (Barricading) shall be made near identified sensitive locations or near the noise source during construction.

Plantation along the boundary wall using appropriate species shall be made at start of construction itself.

Protection devices (ear plugs or ear muffs) shall be provided to the workers operating near high noise generating machines

24 | P a g e

Environmental Remedial Measures Reference to Laws Approximate Mitigation Cost Institutional Responsibility Aspect/Impact /Guidelines Location Implementation Supervision

Noise measurements as per EMoP should be carried out to ensure the effectiveness of mitigation measures and develop a mechanism to record and respond to complaints on noise

Noise monitoring as per EMoP. 5. Land and Soil Land use Change and The top soil from the productive Project requirement Throughout the Included in Contractor CSC / PIU Loss of productive/top land shall be preserved and project section and construction cost PWD soil reused for plantation purposes as borrow areas top cover of embankment slope for growing vegetation to protect soil erosion.

The land taken on lease for access road and construction camp shall be is restored back to its original land use before handing it over back to land owner. Slope protection and Bank protection measures shall be IRC: 56 -1974 At high embankment Construction Design CSC / PIU Soil erosion due to taken at erosion prone areas. The recommended area cost consultant and PWD construction activities, protection measures may include practice for treatment Contractor, earthwork, and cut and use of geo-textiles matting, bio ( of embankment fill vegetative) - turfing slopes for erosion control Side slopes of the embankment Clause No. 306 and shall not be steeper than 2H:1V. 305.2.2 Provision of side drain to guide the MoRT&H water to natural outfalls. In rural Specifications for stretches, longitudinal side drains Road and Bridge shall be intercepted by drains works Guidelines IX serving as outlet channels to for Soil erosion reduce the erosion.

Soil spread on slopes for permanent disposal shall be buttressed at the toe by retaining walls.

25 | P a g e

Environmental Remedial Measures Reference to Laws Approximate Mitigation Cost Institutional Responsibility Aspect/Impact /Guidelines Location Implementation Supervision Turfing of embankment slopes shall be done along the stretch. Stone pitching wherever necessary.

Shrubs and grasses shall be planted in loose soil area.

Soil erosion shall be visually checked on slopes and high embankment areas. In case soil erosion is found, suitable measures shall be taken to control the soil erosion further including bio-turfing

While planning or executing excavations the Contractor will take all adequate precautions against soil erosion as per MoRT&H 306.

Soil erosion at earth The earth stockpiles to be At earth stockpiles Construction Contractor CSC / PIU stockpiles provided with gentle slopes to cost PWD prevent soil erosion and stock piles to be located downwind.. Borrow areas Non-productive, barren lands, IRC Guidelines (No. Borrow sites location. Construction Contractor CSC / PIU wasteland shall be used for IRC:10-1961) on cost PWD borrowing earth with the borrow areas necessary permissions/ consents. selection and amount to be extracted Borrow areas should not be located on cultivable lands except For quarries in the situations where land (Environmental owners desires to level the land. Protection Act and The top soil shall be preserved Rules, 1986; Water and depth shall be restricted to the Act, Air Act) desired level and the slop shall not + Clause No. 305.2.2 be steeper than 25%. MoRT&H Specifications for Borrow areas shall be sited away Road and Bridge from inhabited areas. To the works extent possible, Guidelines V for Borrow Areas

26 | P a g e

Environmental Remedial Measures Reference to Laws Approximate Mitigation Cost Institutional Responsibility Aspect/Impact /Guidelines Location Implementation Supervision To the extent borrow areas shall Management be sited away from inhabited areas.

Borrow areas shall be leveled with salvaged material or other filling materials which do not pose contamination of soil. Else, it shall be converted into fishpond in consultation with fishery department and land owner/community. Rehabilitation of the borrow areas as per Guidelines for redevelopment of Borrow Areas. Quarry Operations Aggregates will be sourced from Clause No. 111.3 existing licensed quarries. MoRT&H Copies of consent/ approval / Specifications for rehabilitation plan for a new quarry Road and Bridge or use of existing source will be works Guidelines VI submitted to EO, PIU. for Quarry Areas Management The contractor will develop a Quarry Redevelopment plan, as per the Mining Rules of the state and submit a copy of the approval to EA if new quarries are to be opened. Compaction of soil and Construction vehicles, machinery, Design Parking areas, Included in Contractor CSC / PIU impact on quarry haul and equipment to be stationed in requirement Haulage roads and construction cost PWD roads due to the designated ROW to avoid construction yards. movement of vehicles compaction. and equipment Approach roads/haulage roads shall be designed along the barren and hard soil area to reduce the compaction.

Transportation of quarry material to the dumping site through heavy vehicles shall be done through existing major roads to the extent possible to restrict wear and tear to the village/minor roads.

27 | P a g e

Environmental Remedial Measures Reference to Laws Approximate Mitigation Cost Institutional Responsibility Aspect/Impact /Guidelines Location Implementation Supervision Land taken for construction camp and other temporary facility shall be restored to its original conditions. Contamination Fuel and lubricants shall be stored Design Fuelling station, Monitoring Cost Contractor CSC / PIU of soil and construction at the predefined storage location requirement construction sites, Included in PWD waste management away from drainage channels. The and construction EMoP storage area shall be paved with camps and disposal gentle slope to a corner and location. connected with a chamber to collect any spills of the oils

Construction vehicles and equipment will be maintained and refueled in such a fashion that oil/diesel spillage does not contaminate the soil.

All efforts shall be made to minimize the waste generation. Unavoidable waste shall be stored at the designated place prior to disposal. To avoid soil contamination at the wash-down and re-fuelling areas, “oil interceptors” shall be provided. Oil and grease spill and oil soaked materials are to be collected and stored in labeled containers (Labelled: WASTE OIL; and hazardous sign be displayed) and sold off to SPCB/ MoEF authorized Waste Oil Recycler

Septic tank or mobile toilets fitted with anaerobic treatment facility shall be provided at construction camp.

Domestic solid waste at construction camp shall be segregated into biodegradable and non-biodegradable waste. The non-biodegradable and

28 | P a g e

Environmental Remedial Measures Reference to Laws Approximate Mitigation Cost Institutional Responsibility Aspect/Impact /Guidelines Location Implementation Supervision recyclable waste shall be sold off.

Efforts shall be made that biodegradable waste shall be composted in the mechanized and movable composter by the contractor. Non bio-degradable and non saleable waste shall be disposed off to authorized land fill site.

All excavated materials from roadway, shoulders, drains, cross drainage should be used for backfilling embankments, filling pits, and landscaping.

Unusable debris material should be suitably disposed off at pre designated disposal locations, with approval of the concerned authority.

Unproductive/wastelands shall be selected for dumping sites. Away from residential areas and located at least 1KM downwind side of these locations, Dumping sites shall not be close to water body and contaminate any water sources, rivers. Dumping sites should have adequate capacity equal to the amount of debris generated. Public perception and consent from the village Panchayats about the location of debris disposal site shall be obtained before finalizing the location.

The bituminous wastes shall be disposed in secure landfill sites only in environmentally accepted manner. For removal of debris,

29 | P a g e

Environmental Remedial Measures Reference to Laws Approximate Mitigation Cost Institutional Responsibility Aspect/Impact /Guidelines Location Implementation Supervision wastes and its disposal MoRT&H guidelines should be followed.

Soil quality monitoring shall be carried out as per EMoP.

6. Water Resources Construction water Requisite permission as applicable Clause No. 1010 EP Throughout the Included in Contractor CSC / PIU shall be obtained for abstraction of Act 1986 MoRT&H Project section construction cost PWD groundwater. Specifications for Road and Bridge The contractor shall make works arrangements for water required for construction without affecting the water availability and supply to nearby communities.

Water intensive activities shall not be undertaken during summer season.

Provisions shall be made to connect road side drains with exiting nearby ponds.

30 | P a g e

Environmental Remedial Measures Reference to Laws Approximate Mitigation Cost Institutional Responsibility Aspect/Impact /Guidelines Location Implementation Supervision Alteration in surface Existing drainage system to be Design requirement, Near all drainage Included in Contractor CSC / PIU water hydrology due to maintained and further enhanced. Clause No 501.8.6. channels, river construction cost PWD embankment MoRT&H crossings etc. Adequate cross drainage Specifications for structures shall be provided. Road and Bridge. Additional balancing culverts shall IRC SP 42 and 50 for be provided in flood prone areas. design of surface and subsurface The embankment height shall be designed consistent with the existing topography of the region and shall be higher than the HFL.

Elaborate drainage system shall be provided to drain the storm water from the roadway and embankment and to ensure minimum disturbance to natural drainage of surface and subsurface water of the area.

Surface runoff from the main road and embankment slopes shall be discharged through longitudinal drains, designed for adequate cross section, and the outfalls.

No construction material will be stored or disposed near any water body except for reusing it for enhancement measures such as embankment raising.

Siltation in water Embankment slopes to be Design requirement , Near Natural drains, Included in Contractor CSC / PIU bodies due to modified suitably to restrict the soil Clause No 501.8.6. embankment slopes. construction cost PWD construction activities/ debris entering water bodies. MoRT&H earthwork Provision of Silt fencing shall be Specifications for made at water bodies. Road and Bridge works Silt/sediment should be collected (CP and CP) and stockpiled for possible reuse and worldwide best as surfacing of slopes where they practices have to be re-vegetated.

31 | P a g e

Environmental Remedial Measures Reference to Laws Approximate Mitigation Cost Institutional Responsibility Aspect/Impact /Guidelines Location Implementation Supervision Earthworks and stone works to be prevented from impeding natural flow of rivers, streams and existing drainage system.

Provision of retaining wall is made along the road for the ponds located next to the road to prevent soil erosion and siltation of pond

Deterioration in No vehicles or equipment should The Water Water bodies, Construction Contractor CSC / PIU Surface water quality be parked or refueled near water- (Prevention and refueling stations, cost PWD due to leakage from bodies, so as to avoid Control of Pollution) construction camps. vehicles and contamination from fuel and Act, 1974 and Monitoring cost equipment. lubricants. amendments thereof. as indicated in EMoP Oil and grease traps and fuelling platforms to be provided at re- fuelling locations.

All chemicals and oil shall be stored away from water and on concreted platform with catchment pit for spills collection.

All equipment operators, drivers, and warehouse personnel will be trained in immediate response for spill containment and eventual cleanup. Readily available, simple to understand and preferably written in the local language emergency response procedure, including reporting, will be provided by the contractors

Construction camp to be sited away from water bodies.

Wastes must be collected, stored and taken to approve disposal site only.

Water quality shall be monitored

32 | P a g e

Environmental Remedial Measures Reference to Laws Approximate Mitigation Cost Institutional Responsibility Aspect/Impact /Guidelines Location Implementation Supervision periodically. 7. Flora and Fauna Vegetation loss due to Suitable modifications in design to Forest Conservation Throughout project Indicated above Forest CSC / PIU site preparation and minimize tree cutting. Act 1980 corridor Department for PWD construction activities + tree cutting and and Roadside trees to be removed with IRC SP: 21 and IRC compensatory Plantation Strategy prior approval of competent SP:66 tree plantation. authority. Rest contractor

Compensatory plantation at 1:10 basis with local forest department.

Provision of LPG in construction camp as fuel source to avoid tree cutting, if possible.

Additional plantation near river banks to check erosion (not possible during construction stage).

In the event of design changes during the construction stages additional assessments including the possibility to save trees shall be made by the EA . Road side Plantation Strategy as per IRC specifications including manuring.

Control use of pesticides/manure 8. Construction Camps Impact associated with All camps should maintain Design Requirement Both construction Included in Contractor CSC / PIU location minimum distance from following: camps construction cost PWD # 1000 m from habitation # 500 m from water bodies

33 | P a g e

Environmental Remedial Measures Reference to Laws Approximate Mitigation Cost Institutional Responsibility Aspect/Impact /Guidelines Location Implementation Supervision worker’s Health in The location, layout and basic The Building and All construction Part of the Contractor CSC / PIU construction camp facility provision of each labor Other Construction camps Contract PWD camp will be submitted to CSC workers (Regulation prior to their construction. The of Employment and construction shall commence only Conditions of after approval of CSC concurrence Service) Act 1996 and The contractor will maintain The Water necessary living accommodation (Prevention and and ancillary facilities in functional Control of Pollution) and hygienic manner as approved Act, 1974 and by the EA. amendments thereof

Preventive medical care to be provided to workers.

Disposal of solid waste on regular basis at identified locations.

The Contractor will take all precautions to protect the workers from insect and pest to reduce the risk to health. This includes the use of insecticides which should comply with local regulations.

No alcoholic liquor or prohibited drugs will be imported to, sell, give, barter to the workers of host community.

Provision of day crèche for children

Limited recreation and sporting facilities for the staff and workers.

Immunization to immigrant workers/local community against communicable and sexually transmitted diseases.

34 | P a g e

Environmental Remedial Measures Reference to Laws Approximate Mitigation Cost Institutional Responsibility Aspect/Impact /Guidelines Location Implementation Supervision 9. Management of Construction Waste/Dismantled Debris Selection of Dumping Unproductive/wastelands shall be Design Requirement At all Dumping Sites Part of the Contractor. CSC / PIU Sites selected for dumping sites. and MoRT&H contract PWD Away from residential areas and guidelines water bodies

Dumping sites have adequate capacity equal to the amount of debris generated.

Public perception and consent from the village Panchayats has to be obtained before finalizing the location. Reuse and disposal of The existing bitumen surface shall construction and be utilized for paving of cross dismantled waste roads, access roads, and paving works in construction sites and camps, temporary traffic diversions, and haulage routes.

All excavated materials from roadway, shoulders, verges, drains, cross drainage will be used for backfilling embankments, filling pits, and landscaping.

Unusable debris material should be suitably disposed off at pre- designated disposal locations, with approval of the concerned authority. The bituminous wastes shall be disposed in secure landfill sites only in environmentally accepted manner. For removal of debris, wastes and its disposal MORT&H guidelines should be followed.

Unusable and surplus materials, as determined by the Project Engineer, will be removed and disposed off-site.

35 | P a g e

Environmental Remedial Measures Reference to Laws Approximate Mitigation Cost Institutional Responsibility Aspect/Impact /Guidelines Location Implementation Supervision 10. Accessibility, Traffic Management, Accident and Safety Risks Design requirement Temporary traffic diversion shall Design requirement Throughout the Project Contractor CSC / PIU and Traffic Planning be planned by the contractor and and project corridor preparation and PWD During Construction approved by the CSC IRC SP:55 especially at construction cost Stage intersections. The traffic control plans shall contain details of diversions; traffic safety arrangements during construction; safety measures for nighttime traffic and precautions for transportation of hazardous materials. Traffic control plans shall be prepared in line with requirements of IRC’s SP 55 document’.

The Contractor will ensure that the diversion/detour is always maintained in running condition, particularly during the monsoon to avoid disruption to traffic flow. On stretches where it is not possible to pass the traffic on the part width of existing carriageway, temporary paved diversions will be constructed.

The contractor shall inform local community of changes to traffic routes, and pedestrian access arrangements with assistance from CSC and Nodal officer concerned

Use of adequate signage to ensure traffic management and safety. Conduct of regular safety audit on safety measures. Pedestrians, animal All measures for the safety of Design requirement Near habitation on Included in Contractor in CSC / PIU and Vehicular traffic during construction viz. and both sides of construction consultation with PWD movement, signs, markings, flags, lights and IRC: SP: 27 -1984 schools, temples, cost. Forest flagmen as proposed in the Traffic Report Containing hospitals, department and Control Plan/Drawings shall be Recommendations construction sites, PIU taken. of IRC Regional haulage roads,

36 | P a g e

Environmental Remedial Measures Reference to Laws Approximate Mitigation Cost Institutional Responsibility Aspect/Impact /Guidelines Location Implementation Supervision Temporary access and diversion, Workshops on diversion sites. with proper drainage facilities. Highw ay Safety Access facility to the schools IRC:SP: 32 -1988 Road located adjacent to the highway. Safety for Children (5-12 Years Old)

IRC:SP: 44 -1994 Accident risk from Contractors to adopt and maintain Highw ay Safety Construction sites Included in Obligation of CSC / PIU construction safe working practices. Code construction cost Contractor PWD activities Usage of fluorescent and retro- IRC: SP: 55 -2001 reflective signage, in local Guidelines for language at the construction sites Safety in Construction Zones Training to workers on safety The Building and other procedures and precautions. Construction w orkers Act 1996 Provision of PPEs to workers. and Cess Act of 1996 Provision of a readily available first Factories Act 1948 aid unit including an adequate supply of dressing materials. Ensure ready access to ambulance, nursing staff, and doctor when needed. The contractor will not employ any person below the age of 14 years for any work and no woman will be employed on the work of painting with products containing lead in any form.

Clear demarcation of areas for restricted accesses to avoid accidents. 11. Common Property Resources and other Utilities Damage to Common Ensure that no construction Environment Throughout the Construction Contractor CSC / PIU Property Resources material dumped close to the such Protection corridor cost PWD and Utilities facilities and all precautions are Requirement taken such that no damage happen to any of common property resources and utilities.

37 | P a g e

Environmental Remedial Measures Reference to Laws Approximate Mitigation Cost Institutional Responsibility Aspect/Impact /Guidelines Location Implementation Supervision Access to common The area shall be barricaded for Environment Throughout the Construction Contractor CSC / PIU property resources safety prospective. It shall be Protection corridor cost PWD ensured that access to these area Requirement ensure for people to visit such places. 12. Enhancement Measures Environmental Enhancement of tree plantations Environmental Throughout the Construction Contractor CSC / PIU enhancement along near likely to be relocated Enhancement as part corridor cost PWD the corridor community structures/ landscaping of project etc. requirement

Enhancement/rehabilitation of borrow areas etc. 13. Contractor Demobilization Clean-up Operations, Contractor will prepare site Project requirement Throughout the ---- Contractor CSC / PIU Restoration and restoration plans, which will be Corridor and borrow PWD Rehabilitation approved by the CSC. The areas cleanup and restoration operations are to be implemented by the contractor prior to demobilization.

All construction zones including river-beds, culverts, road-side areas, camps, hot mix plant sites, crushers, batching plant sites and any other area used/affected by the project will be left clean and tidy, at the contractor's expense, to the satisfaction of the Environmental officer. All the opened borrow areas will be rehabilitated and CSC will certify in this regard. B. Operation Stage 1. Climate and Air quality Air pollution due to due Roadside tree plantations shall be Environmental Throughout the Indicated In CSC / PIU PWD to vehicular movement maintained. Protection Act, 1986; Corridor EMoP Regular maintenance of the road The Air (Prevention will be done to ensure good and Control of surface condition Pollution) Act, 1981

Ambient air quality monitoring shall

38 | P a g e

Environmental Remedial Measures Reference to Laws Approximate Mitigation Cost Institutional Responsibility Aspect/Impact /Guidelines Location Implementation Supervision be carried out as per EMoP. If monitored parameters are above the prescribed limit, suitable control measures must be taken.

Road signs shall be provided reminding the motorist to properly maintain their vehicles to economize on fuel consumption and protect the environment. 2 Noise Environment Noise due to Effective traffic management and Noise Pollution In all settlement Included in CSC / PIU PWD movement of traffic good riding conditions shall be (Regulation and areas additional maintained to reduce the noise Control) Rules, 2000 plantation cost. level throughout the stretch and and amendments speed limitation and honking thereof restrictions may be enforced near sensitive locations.

The effectiveness of the multilayered plantation should be monitored.

3. Land and Soil Soil erosion at Periodic checking to be carried to Project requirement At bridge locations Included in CSC / PIU PWD embankment during assess the effectiveness of the and embankment Operation/ heavy rain fall. stabilization measures viz. turfing, slopes and other Maintenance stone pitching, river training probable soil erosion cost structures etc. areas. Soil erosion at borrow Visual monitoring and inspection of Project requirement At bridge locations Included in CSC / PIU PWD areas soil erosion at borrow areas, and embankment Operation/ quarries (if closed and slopes and other Maintenance rehabilitated), embankments and probable soil erosion cost other places expected to be areas. affected, will be carried out once in every six months as suggested in monitoring plan. 4. Water Resources Contamination of Monitoring of surface water bodies Near Baher Nadi, Indicated in CSC / PIU PWD surface water quality Ama Nadi and drains EMoP due to leakage of oil /natural streams

39 | P a g e

Environmental Remedial Measures Reference to Laws Approximate Mitigation Cost Institutional Responsibility Aspect/Impact /Guidelines Location Implementation Supervision Siltation Regular visual checks shall be made to observe any incidence of blockade of drains/culverts. Regular checks shall be made for soil erosion and turfing conditions of river training structures for its effective maintenance. 5. Flora and Fauna Vegetation Planted trees, shrubs, and grasses Forest Conservation Throughout the Indicated in CSC / PIU PWD to be properly maintained. Act 1980 corridor Monitoring cost in EMoP The tree survivalist audit to be conducted at least once in a year to assess the effectiveness

6. Flooding/ inundation Road inundation due Field Unit will ensure that all drains Project operation In settlement area Overall CSC/PIU CSC / PIU PWD to choking of drainage (side drains and all cross requirement Operation cost channels drainages) are periodically cleared especially before monsoon season to facilitate the quick passage of rainwater and avoid flooding. 7. Right-of-Way Maintenance Accident Risk due to The construction site shall be kept Project requirement Throughout the Included in CSC / PIU PWD uncontrolled growth of completely clear of vegetation. Project route operation/ vegetation Maintenance Regular maintenance of plantation cost

Invasive plant not to be planted near the road.

Controlled use of herbicide/pesticide

The designated ROW shall be maintained free of any encroachment. 8. Accidents and Safety Accident risks Traffic control measures, including IRC:SP:55 Throughout the Included in CSC / PIU PWD associated with traffic speed limits, will be enforced Project route operation/ movement. strictly. Maintenance cost

40 | P a g e

Environmental Remedial Measures Reference to Laws Approximate Mitigation Cost Institutional Responsibility Aspect/Impact /Guidelines Location Implementation Supervision Further encroachment and squatting within the ROW will be prevented.

Monitor/ensure that all safety provisions included in design and construction phase are properly maintained

Transport of Preparation of spill prevention and Throughout the Included in CSC / PIU PWD Dangerous Goods control and emergency project stretch operation/ preparedness and responsive Maintenance plans based on an analysis of cost. hazards, implementation of presentation and control measures. 9. Monitoring Operation Performance Monitoring Operation Monitor the operational Throughout the Included in CSC / PIU PWD Performance performance of the mitigation/ corridor EMoP enhancement measures carried out as a part of the project

The indicators selected for monitoring include the survival rate of trees; utility of enhancement provision, status of rehabilitation of borrow areas, Air quality, water quality, noise levels, soil quality, drainage pattern. The monitoring and reporting to be carried out as per EMoP

Source: ADB approved IEE report, Balod-Dhamtari (MDR) subproject Note: The changed scope of project has not resulted in any additional environmental implications thus the earlier proposed environmental management plan can be utilized and upgradation of EMP is not required.

41 | P a g e

Annexure -IV

Environmental Monitoring Plan for the Project Road

Package- 13 Balod-Dhamtari (MDR) Subproject

Environmental Duration / Project stage Parameter Standards Locations Implementation Supervision Frequency Component

Air Construction SPM, SO2, Minimal Wherever the Stack Emission Contractor through a PIU, Supervision Phase NOx, CO, HC National contractor decides to Monitoring approved monitoring Consultant, PWD Standards locate the Hot Mix agency Plant

PM2.5, PM10, National Stretch of the road Continuous 24- Contractor through a PIU, Supervision

SO2, NOx and Ambient where construction hourly, twice a approved monitoring Consultant, PWD CO Quality in progress site week once agency preferably at Kulia Standards during and Jamruva Construction Phase

Operation PM2.5, PM10, National At Kulia and Jamruva Continuous 24- PIU, PWD PWD

Phase SO2, NOx and Ambient hourly, twice a CO Quality week once in Standards year for 2 years

Water Quality Construction pH, TDS, TSS, As Water At Kulia and Jamruva Once during the Contractor through a PIU, Supervision Stage Oil & Grease quality Construction approved monitoring Consultant, PWD standards Phase agency

(IS 10500)

42 | P a g e

Environmental Duration / Project stage Parameter Standards Locations Implementation Supervision Frequency Component Operation pH, TDS, TSS, As Water At Kulia and Jamruva End of summer PIU, PWD PWD Phase Oil & Grease quality before the onset standards on monsoon every year for 2 (IS 10500) years

Noise and Construction Noise Level in As per Kulia and Jamruva One day hourly Contractor through a PIU, Supervision Vibration Phase dB (A) National measurement, approved monitoring Consultant, PWD Noise once in six agency standards months once during the Construction Phase

Operation Noise Level in As per At Kulia and One day hourly PIU, PWD PIU, Supervision Phase dB (A) National Jamruva measurement, Consultant, PWD Noise standards.

Soil Erosion Construction Soil erosion -- On slops and After PIU, PWD PIU, Supervision Phase embankment precipitation Consultant, PWD

Operation Soil erosion -- On slops and After PIU, PWD PIU, Supervision Phase embankment precipitation Consultant, PWD

Road Side Construction Monitoring of As laid out in Entire stretch of During felling of Forest Dept. PIU, PWD Plantation Phase trees felling the detailed project road trees design for project

43 | P a g e

Environmental Duration / Project stage Parameter Standards Locations Implementation Supervision Frequency Component Operation Survival rate The survival Entire stretch of Every year for 3 PWD, Forest Dept. PWD Phase of trees rate should project road years success of re- be at least plantation 70% below which re- plantation shall be done.

Source: ADB approved IEE report, Balod-Dhamtari (MDR) Subproject

44 | P a g e

Cost of Environmental Monitoring Plan

Component Stage Item Parameters Unit Cost Quantity Total Cost  Monitoring at hot mix plant locations Stack emission 6000/- Two time during construction 12000 approved by the Supervision monitoring of SPM, phase Consultant SO2, NOx, CO, HC Construction and VOC  Monitoring at construction site in PM , PM , SO , 4000/- Continuous 24 - hourly, twice a 96000 Air 2.5 10 2 tandem with construction work NOx and CO week twice in each season preferably at Kulia and Jamruva during construction Operation  Ambient Air Quality monitoring at PM2.5, PM10, SO2, 4000/- 2 locations, 24, hourly 96000 preferably at Kulia and Jamruva NOx and CO monitoring twice a week every season for 2 years Pre-monsoon and post 40000 Construction At Kulia and Jamruva As per IS 10500 5,000/- monsoon season for two years Water Pre-monsoon and post 40000 Operation At Kulia and Jamruva As per IS 10500 5,000/- monsoon season for two years At equipment yards Day and Night Leq 2,000/- As and when necessary 12000 Construction Noise Monitoring at 2 Construction Site Day and Night Leq 2,000/- As and when necessary 12000 Noise Operation Noise Monitoring at 2 Construction Site Day and Night Leq 2,000/- Once in every year for two 20000 including Kulia and Jamruva years Soil Construction At productive land abutting traffic detours No. of Samples 6,000/- Max. of 2 locations for each of 2 20000 and traffic diversions, to be identified by years the Supervision Consultant Operation Supervision of expert to check the soil LS 15000 2 visits during rains 30000 erosion Green Belt Construction Along the stretch Lump sum 35000 35000 Operation At locations of compensatory plantation Lump sum 35000 35000 Total 448000

Source: ADB approved IEE report, Balod-Dhamtari (MDR) Subproject Note: The changed scope of project has not resulted in any additional environmental implications thus the earlier proposed environmental monitoring plan can be utilized and upgradation of EMP is not required

45 | P a g e

. Annexure-V

Grievance Redress Committee – District Balod -Dhamtari ( MDR) Subproject

46 | P a g e

Annexure VI

Permission for Tree Cutting (Package -13)

47 | P a g e

Annexure VII

Photographs of Field Visit

Photo-1 field photograph Jhalmala Photo-1 field photograph Jhalmala

48 | P a g e