ExpressLanes 11-0745cmc © 2011 lacmta METRO LA CRD (ExpressLanes) PROGRAM

MONTHLY PROJECT STATUS REPORT

THE PREPARATION OF THIS DOCUMENT HAS BEEN FINANCED IN PART THROUGH A GRANT FROM THE U. S. DEPARTMENT OF TRANSPORTATION, FEDERAL TRANSIT ADMINISTRATION (FTA).

JANUARY 2013 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

TABLE OF CONTENTS Page No.

Program Overview & Status……………………………………..……. 1-9

Management Issues…………………………………………….…….... 10

Program Status

 Program Scope……………………………………………...…. 11-14  Schedule o Key Milestones Six-Month Lookahead .……………..…. 15 o Program Summary Schedule ……………….………….. 16 o Critical Path Narrative…………………………………….. 17-23  Program Cost Status/Financial Grant Status…………...…... 24-29  Staffing…………………………………………………………… 30  Real Estate………………………………………………………. 31  Environmental…………………………………………………… 32  Community/Media Relations…………………………………… 33  Quality Assurance………………………………………………. 34  Safety…………………………………………………………….. 34  Third Party……………………………………………………….. 35-40

Contract Status/Construction Photographs………………………….. 41-47 Chronology of Events…….…………………………………………….. 48-50 “Go Live” Deployment Schedule….…………………………………… 51 LA CRD Pre-Deployment Data Collection.……………….……...... 52-90

Appendices……………………………………………………………… 91-94 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

PROGRAM OVERVIEW & STATUS Metro, Caltrans, and other mobility partners are working together to develop a package of solutions that will increase traffic flow and provide better travel options on I-10 and I-110 in County. ExpressLanes is a one-year demonstration program that will test innovations to improve existing transportation systems in three sub-regions: the San Gabriel Valley, Central Los Angeles and the South Bay Cities. These three sub-regions represent nearly 50 percent of both population and employment in LA County.

The Program Goal is to improve mobility and provide congestion relief on I-10 and I-110 corridors through the introduction of congestion pricing by converting High Occupancy Vehicle (HOV) lanes to High Occupancy Toll (HOT) lanes, improvement of transit service and other alternatives to driving, improvements to transit facilities, and the implementation of an intelligent parking management system in downtown Los Angeles.

This program offers improved transportation options and a choice for drivers of single occupant vehicles (SOV) to pay to travel in a high occupancy lane. The minimum toll per mile is $0.25 and the maximum toll per mile is $1.40. The general purpose lanes will not be tolled. An additional aim of the program is to foster incentives for sustainable change that creates travel time savings, increased trip reliability, cost savings, improves air quality and effectively manages our current roadway network.

The federal grant name for this Program is the Los Angeles County Congestion Reduction Demonstration (LA CRD). It is estimated that more than 2,400 construction-related jobs will be generated by this program.

PROGRAM MANAGEMENT Staff continues to work with Caltrans to address potential issues of conflict which may arise as a result of work they are currently performing related to the I-10 Rehab Project and other contractors working for Caltrans on the I-110 and I-10 Freeways. Staff is reviewing existing contracts and their status in order to manage any risk to our ExpressLanes program. Based upon percent expended, the Program is 77.2 % complete.

TOLL INFRASTRUCTURE AND FREEWAY/ROADWAY IMPROVEMENTS This element has completed the Environmental and Preliminary Design phases. Caltrans is the lead agency for the NEPA and CEQA Environmental Documents. On April 28, 2010, the Final EIR/FONSI for the I-10 and I-110 HOT Lanes was approved. On May 14, 2010 the Environmental Assessment was approved. Upon concurrence from FHWA, the Design-Build- Operate-Maintain (DBOM) RFP was released on June 7, 2010. Five addenda were issued to the RFP. Three proposals were received on August 31, 2010. The DBOM Contract was awarded to Atkinson Contractors, LP on December 16, 2010. The Notice to Proceed (NTP) was given to the contractor on January 11, 2011. During June 2011 the DBOM contractor submitted the Final Design Documents for the I-110 ExpressLanes. The groundbreaking ceremony for the start of construction of the ExpressLanes was held July 6, 2011 at the Harbor Gateway Transit Center. Construction for the sign foundations started in early August on the I- 110 freeway and started in late September on the I-10 freeway.

1 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

PROGRAM OVERVIEW & STATUS (Contd)

Staff worked with FTA/FHWA partners regarding the need for a schedule extension to ensure all roadway and tolling installations are completed prior to opening the HOT Lanes. Due to the high risk posed by the ongoing work being performed by the Caltrans I-10 Rehab Contractor on the I-10 corridor, Metro discussed with FHWA the need to have the I-110 tolling operation open before the I-10 tolling operation. A joint letter of concurrence from FHWA and FTA for the schedule extension was received February 2012.

The start of revenue operations on the I-110 HOT Lanes took place on November 10, 2012 and the projected date for the start of revenue operations on the I-10 HOT Lanes is February 2013.

Caltrans has issued a Change Order (CCO) to the I-10 Rehab Contractor for striping of the general purpose lanes and the I-10 Rehab Contractor performed the final striping work. This work was critical to allow ExpressLanes Project Contractor to progress its electrical and communication work on the outside shoulder required for DMS and toll signs. Caltrans has provided the I-10 Rehab Contractor survey controls so the final striping of GP lanes was able to move forward. Metro has accelerated the installation of the communication network on the I- 10 Freeway to meet the revenue operations date due to delays encountered. Metro continues to meet with these other contract REs in an effort to eliminate as many potential impacts as possible. Metro has diligently worked to take the lead role in advising other projects as to where and when our projects will be working at the various locations.

Access to the I-10 Freeway fiber optic cable installed by the I-10 Rehab Contractor has been granted to the DBOM Contractor by Caltrans for use on the ExpressLanes. This delay has created a schedule impact to the ExpressLanes Project.

Construction of the pedestrian bridge overcrossing on the I-110 Freeway at Adams Blvd. was completed in November. Construction work was also completed on the widening of the vehicular bridge at Adams. The work in and around the POC was accelerated in order to support the I-110 ExpressLanes Revenue Operations.

The DBOM Contractor began displaying messages on the Dynamic Message Signs in concert with Metro’s needs to inform the public on the I-10 future opening date. Example: ExpressLanes Coming Visit FasTrakLa.net for Info. Metro coordinated the messages on the DMS signs with the actual opening date of the 110 ExpressLanes and similar coordinated messages on the DMS signs is occurring with the actual opening of the 10 ExpressLanes which is projected to be February 23, 2013.

Work is continuing on I-10 Freeway on various toll sites, DMS signs, etc; in January. All power drop installations along the I-10 were completed in December by DWP and SCE. All drainage, median barrier reconstruction was completed in January on the I-10 Freeway.

2 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

PROGRAM OVERVIEW & STATUS (Contd)

Design for the earthcam cameras has been completed and the installation of the additional earthcam cameras continued in January along the I-110 and I-10 Freeways. A total of 13 earthcam cameras are being installed along the I-10 and I-110 Freeway corridors. The earthcam cameras will allow real time traffic monitoring when the ExpressLanes go into operation. This is an important aspect of project implementation and was issued to the DBOM Contractor as change order work. Metro is using a portion of the schedule contingency and some acceleration to implement this work into the project.

The DBOM Contractor has been impacted by Caltrans Contractor Flatiron/Lincoln Pacific working on the north end of the 110 Freeway. This contractor should have completed the fiber optic cable installation in the I-10/110 node in May 2012. This fiber optic cable installation by Flatiron was completed in October. The DBOM Contractor was able to complete the redundant loop between I-10 and I-110 Freeway a critical component of the fiber optic loop. Metro is analyzing this delay and will accelerate sections of the communication network to meet the project milestones. In September Metro issued a Contract Modification to the DBOM Contractor to acquire a leased line from ATT. This is still being installed and is due to be completed after the opening of the I-10 Freeway. This will provide additional Redundancy capacity if there are other future problems with the Caltrans fiber loop.

On I-10 Freeway the existing shoulder between Fremont and the I-605 Freeway will be restriped to create an additional Express Lane in each direction. A recent investigation of the existing shoulder condition revealed 6 areas that require pavement repairs before the shoulder is restriped to become the additional ExpressLane. This work needs to be completed prior to opening the I-10 ExpressLane to the traveling public in order to ensure it does not create a safety hazard. This work is being added to the scope of work to DBOM Contract and project schedule contingency will be used with selective acceleration to avoid impacts to the projected revenue operations date. During the month of December this work has been completed.

All of the DMS’s have now been powered up and trial messages are now being displayed on all the I-10 DMS signs. One example is Do not Cross the Double White Lines. Metro has issued a Change Order to the DBOM Contractor to install additional static signs on the I-10 and I-110 Freeways stating that all HOVs require a Fastrack to use the ExpressLanes. This is being done in consultation with CHP and Caltrans. Also additional static signs are being installed to advise drivers not to cross the Double White Lines.

Commissioning Testing of all systems, Toll Site and DMS Signs was taking place in January to ensure everything will be ready on the I-10 Freeway for Revenue Operations projected for February 23, 2013.

3 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

PROGRAM OVERVIEW & STATUS (Contd)

Tenant improvements were completed for the Customer Service Center in Gardena and hiring and training of customer service staff was done. Since the first shipment of transponders were delivered in April to the CSC, inventory control measures have been implemented. The official ribbon-cutting ceremony was held July 25, 2012 at the CSC in Gardena announcing to the public that the transponders are now available.

Metro has nearly completed the analysis of the various schedule delays that have been experienced on the ExpressLanes Project and has issued a Contract Extension Change Notice to the DBOM Contractor using a portion of the Project Schedule Contingency. Based on this analysis, there will not be any impact to the Revenue Operations Dates for the I-110 Freeway being November 10, 2012 and for the I-10 Freeway being February 2013.

Project Study Report (PSR): Adams Blvd. Figueroa St. HOV/HOT Lane Flyover – Metro and Caltrans executed a funding agreement on April 27, 2011 for Caltrans to perform a PSR and complete the environmental work for an extension of the I-110 HOV/HOT lanes from their current terminus at Adams Blvd. Caltrans held a kickoff meeting June 7th where the PSR was scheduled to be completed in April 2012 and the environmental work was to be completed in September 2013. However, in July Caltrans was informed by the Governor’s office that it cannot perform any reimbursable work until November. Work started again in October and is back on schedule for a PSR/PID completion date of June 2012. To maintain the original schedule, the Scope of Work was revised to move some of the PSR/PID work to the PAED Phase. The final PSR/PD was approved in June. In July Caltrans started work on the PAED Phase of the project. A Value Analysis Pre-Study Meeting was held in December. The Value Analysis is being performed to determine if there are any cost savings or refinements that can be done to the existing Alternatives. A Value Analysis Presentation was held in January with the Final Report to be provided in February.

TRANSIT SERVICE IMPROVEMENTS 59 new clean-fuel buses will be operated to support the demonstration program. Metro continues to operate its new Silver Line service connecting passengers to the El Monte and Artesia Transit Centers. Phase I of the enhanced Silver Line service (increased frequencies for AM peak) began on the Harbor Transitway portion of the Silver Line June 26, 2011. For the month of January the Silver Line Harbor Transitway (Phase I) weekday boardings total was 5,158 which represents a 86.68% increase in ridership since the Phase I service changes in June 2011. For the month of January the combined Harbor Transitway and El Monte Busway Silver Line weekday boardings total was 12,422 which represents a 87.87% increase in ridership since the Silver Line started service in December 2009. For weekday service in January, the Silver Line had an On-Time performance of 77.1%.

4 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

PROGRAM OVERVIEW & STATUS (Contd)

All of our municipal transit partners – Gardena, Foothill and Torrance have placed the order for their buses. Gardena has received its 2 buses and has completed the Post Delivery inspection (PDI) process. In June, all bike racks for the buses were procured and in August all bike racks were installed on the two buses (and all bus fleet) and were in service August 22, 2011. All 12 NABI 42 ft. CNG buses for Foothill Transit have been procured and accepted into their fleet. Torrance Transit met with New Flyer and decided to cancel its order for hybrid buses, due to the propulsion company declaring Chapter 11 bankruptcy. New CNG buses have been ordered and arrived in October 2011. Foothill, Gardena and Torrance are in the process of preparing their grant applications for their operating subsidies. Torrance Transit has submitted their FTA grant for operating funds and it is currently under review.

The FTA grant (CA-95-X203-00) was awarded on August 3, 2012 and executed on August 7, 2012. The service commenced on November 19, 2012. Foothill Transit’s grant application CA-95-X138 for the Operating subsidy CMAQ $3,200,000 was approved by the Federal Transit Administration (FTA) on July 9, 2012. The CMAQ funds have been switched over to the FTA and are now available to finance the added cost associated with the CRD project for Foothill Transit.

Municipal operators will deploy their buses upon opening day of the ExpressLanes. For Gardena and Torrance this took place November 2012 and for Foothill Transit this will be February 2013. LADOT completed the signal design plans of 19 intersections in February 2010. Due to changes in the ARRA project construction scope, the project was redesigned to continue the interconnect link to the ATSAC Center. As a result, all bids were cancelled April 20, 2011. Preliminary conduit path investigation into ATSAC Control Center completed in May 2011. Project re-design was completed November 2011. The bid package was completed December 6, 2011 and bids were received on January 18, 2012. The Board of Public Works awarded the contract in March and issued a Notice to Proceed. Barring any other unforeseen conditions, construction is anticipated to be completed by July 2012. Construction commenced on April 9, 2012. The project is progressing per the schedule even with some delays for special events at LA Live. The contractor is trying to work Saturdays to compensate for any lost work days. Full system integration was complete in September 2012. During June, the field construction part of the project was completed. Work continued on the integration and database part of the project. Metro submitted the transponder information to LADOT. Project was completed in September 2012. Part of the TPS project also includes the extension of the existing AM peak-period northbound bus-only lane on Figueroa St. between 23rd Street and 4th Street to cover the PM peak-period. A Traffic Control Report (TCR) was approved by the General Manager of LADOT to extend the PM peak-period bus only lane. The Figueroa Street PM Peak Bus-Only Lane was completed in October. All the signs and pavement markings were installed by LADOT field crews. LADOT obtained funding approval from Metro for the camera installation work at Alameda. Completion is scheduled for February 2013.

5 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

PROGRAM OVERVIEW & STATUS (Contd)

TRANSIT FACILITY IMPROVEMENTS El Monte Transit Center – Completed construction for Contract C0934R for Demo, Repave and Lighting Installation over the former Old Transportation Bldg. Completed construction at Power Chevrolet; Completed demolition of the Metro Transportation Building and completed paving at the site. Contract C0959 for the temporary terminal was awarded to S.H.E. for $657K with NTP issued April 20, 2010; construction was completed on September 3rd and the transition to the temporary terminal took place in early September. Contract for $39 million was awarded on June 18, 2010 to KPRS Construction Services, Inc. Notice to Proceed was issued 8/13/2010. A formal groundbreaking ceremony for the new El Monte Transit Center was held on September 22, 2010. Demolition of existing bus facility commenced on October 8, 2010 and was completed in November 2010. In November during initial excavation of the north roadway and former station area, contaminated soil impacted with lead and total petroleum hydrocarbons (TPH) was discovered. Additional soil investigation has identified significant contamination which increased the project budget by more than $6 million. (The $6 million overrun was funded by a reallocation of funding from the Patsaouras Plaza Project). Metro issued a change order for a 99 calendar day time extension to KPRS to address the soils handling delay impacts. North Access Road construction was completed in February 2011 which will allow for the smoother flow of bus operations into the Temporary Terminal. The excavation and contaminated soils handling is complete with final cost impacts under evaluation. In August 2011, utility stubouts were completed. In October activities continued for station walls, column construction and foundation pours. Station construction completion is projected to be August 2012 with the Temporary Terminal restoration projected to be October 2012. The LOP budget for the El Monte Station increased to $60.1 million. During July, KPRS completed the installation of the bus bay canopies on the concourse level, poured most of the curb and gutter around the perimeter of the station, and energized the Station after Southern Edison pulled their conduit. With electrical power turned on, the site is now in log out-tag out. KPRS began installation of the photovoltaic cells on the concourse level and the ceiling tiles on the lower level of the station, and continued work on the two escalators and the three elevators. The last week in July, the pre-fabricated toilet arrived on site, and KPSR submitted an initial punchlist of items for closeout. KPRS made great strides on both the transit and retail buildings, completing most of the mechanical, electrical, and plumbing (MEP) work, HVAC ducting, interior dry walling, ceiling tile installation, and bathroom tile installation. KPRS also made the initial concrete pours on the plaza in front of the transit retail buildings.

With all construction complete since December, all activities in January were administrative in nature. Metro negotiated change orders related to the work completed earlier. Metro also began unencumbering unused funds on purchase orders that supported construction and the station opening.

6 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

PROGRAM OVERVIEW & STATUS (Contd)

Patsaouras Plaza – Received Caltrans approval of PR/PSR in May. 100% Advanced Conceptual Engineering was completed in September 2010. The Board approved additional funding as well as a new State of Good Repair federal grant to complete the Patsaouras Plaza Project for a Life of Project Budget of $16.8 million and separated the LOP budget of Patsaouras Plaza from the LOP budget for the El Monte Station project as approved at the October 2011 Metro Board Meeting. In November staff re-engaged all consultant staff including traffic, geotechnical, and design engineers and started the process of revising the preliminary engineering package and preparing the project for advertisement. Staff will work to refine and revise the preliminary engineering package to mitigate risk item such as traffic plans, foundation plans, geotechnical conditions and coordination with the ExpressLanes Project. On July 20th, Metro issued a third amendment to the IFB. This third amendment was primarily to give the contractor responsibility of the artwork; and it extended the bid period for an additional two weeks in order to give prospective bidders sufficient time to address the new requirement. Amendment 3 also extended the bids due date from August 7th to August 14th. In December, the project team worked on a statement of work for a Task Order to STV Incorporated--the team that developed the Advanced Conceptual Engineering (ACE) design document – to incorporate the value engineering options and lessons learned from the debriefing with prior bidders. However, the task order takes the STV contract above the current contract limit and so a contract modification is being prepared. No other update to provide. The project will be Design-Build. NEPA approval was received February 2012.

Harbor Transitway – This project will have at least 5 procurements. The low bid at $547K was awarded to Minco Construction for the Harbor Gateway Law Enforcement substation & CCTVs with NTP issued March 2010 and construction was completed in October 2010. The low bid at $443K was awarded to Lime Inc. for the Station lighting & UPS with NTP issued June 2010. Construction was completed in December 2010. Contract of $912,500 for the sound enclosure was awarded to low bidder, Peterson Chase, on August 18, 2010. NTP was issued in October 2010. Project completion has been delayed because the sound enclosure design was rejected by Caltrans and the Contractor had to re-design the project. Design concepts for mounting sound panels in stairwells has been approved by Caltrans. Panels will be issued in October 2010. Project completion has been delayed because the sound enclosure design was rejected by Caltrans and the Contractor had to re-design the project.

Design concepts for mounting sound panels in stairwells has been approved by Caltrans. Panels will be ordered as soon as formal approval from Caltrans is received. Work was completed in January.

For the bus stop cutouts, the low bid of $235,000 was awarded to RC Becker in March 2011 and NTP was provided on April 15, 2011. Construction for bus stop cutouts was completed in August 2011. CCTV Contract C0986 price bids have been received and the contract was awarded in February 2012. In January, no work has been conducted since Metro conducted final inspection of the work in December. First Fire’s completion of punchlist work is still on hold pending Metro’s ITS Department’s completion of work

7 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

PROGRAM OVERVIEW & STATUS (Contd) that includes the installation of wireless antennas and programming of the servers. To date, project expenditures and encumbrances to date are well within the Project LOP.

Pomona Metrolink Station – In May 2010, 143 new parking spaces were opened for use east of the existing parking spaces. Construction of the temporary platform to board passengers on Main Track 2 (MT-2) traveling toward San Bernardino was completed and put into Service on June 20, 2010. In December 2010 the contractor completed widening of the platform and construction of the new east entrance. The platform was accepted for beneficial occupancy and put into service on December 15, 2010, along with the new east entrance with new pedestrian crossings. The MOU milestone of completion (beneficial occupancy) by December 30, 2010 was achieved. The last progress payment has been processed and paid by SCRRA. The closeout book has been completed and submitted to SCRRA’s Contracts Dept. The contractor has requested release of the remaining retention. Project close out completed in July 2011.

DEMAND–BASED PARKING PRICING (EXPRESSPARK) On August 31, 2010, Caltrans approved the E-76 for the PE 2 Phase of LA ExpressPark. Two qualified proposals were received on December 17, 2010. Because both proposals received exceeded the project budget, LADOT prepared additional guidance and a revised scope to be sent to the proposers. LADOT’s Evaluation Panel completed its work on April 6, 2011, and recommended that ACS State & Local Solutions be selected as the prime contractor for LA ExpressPark. The second proposer filed a protest. The formal protest of the contractor selection process was withdrawn on May 20, 2011.

LADOT Board of Transportation Commissioners approved the LA ExpressPark contractor selection and forwarded their report to the Mayor and the CAO on June 9, 2011. The CAO’s report was submitted for review on July 29th to the City Council. On August 12, 2011, the L.A. City Council unanimously approved the CAO report, authorizing LADOT to execute the contract with ACS for the implementation of the LA ExpressPark Intelligent Parking Management Project. Also, the City Council provided LADOT the authority to adjust on-street parking meter rates in the LA ExpressPark project area. On September 29, 2011, the City of Los Angeles executed the contract with ACS State and Local Solutions, Inc. for the implementation of the LA ExpressPark Intelligent Parking Management Program. It should be noted that the project has been separated into three phases. The date for LA ExpressPark to be fully operational (October 2012) will not impact the start of the Demo Evaluation Period. LA ExpressPark will support Phase I of the demand-based pricing no later than May 2012. It will be expanded to support Phase II no later than July 2012 and Phase III no later than November 2012, which is consistent with RFP requirements. Phase I will use the baseline data to refine base hourly rates to influence demand. Phase II will build on the demand balance from Phase I and will identify peak periods and establish hourly rates by the time of day. Phase III will adjust rates per block in select areas in real-time based on current demand.

8 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

PROGRAM OVERVIEW & STATUS (Contd)

Phase I of the IPM (MERGE System) was completed Sept. 24th. Phase 2 and 3 are underway. The MERGE System is currently scheduled to be fully operational in the first quarter 2013. The elements necessary for demand-based pricing are operational; remaining work includes further automation, integration of the parking guidance systems and workforce management. There are no rate changes planned for February; the next rate change will be March 4, 2013. Before making anymore rate changes, LADOT has asked its contractor to evaluate the effectiveness of the rate changes to date. In March, we will be testing the effectiveness of new labels on four block faces. For each of these block faces, the rate has reached the upper limit set by ordinance and there are adjacent block faces with lower rates. The goal of the test is to guide parkers to the available spaces on the lower priced block faces. The occupancy systems for El Pueblo, Pershing Square and LA Mall are now sending occupancy directly to MERGE for redistribution to the elements of the parking guidance system. The software is now in place and has been tested for sending messages through MERGE to the large DMS in South Park.

9 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

MANAGEMENT ISSUES

Concern No. 1: Caltrans Has Various Construction Contracts on the I-10 Freeway That May Impact the ExpressLanes Project

Status/Action Caltrans has contractors working on I-10 Freeway that have potential to impact revenue operations for the DBOM Contract. Due to some cancellations of lane closures by Caltrans, some delays to ExpressLanes schedule have been experienced.

Concern No. 2: Timing and Construction Coordination between ExpressLanes Operations and Patsaouras Plaza

Status/Action Metro has engaged traffic consultants and performed a Constructability Study to determine the mitigation measures. The results of these studies were analyzed for project impact by the Management Team responsible for preparing the RFP and advertisement. The construction effort required in order to complete the Patsaouras scope of work once awarded will make it necessary to coordinate completely with the ExpressLanes, even once open to the public. The one year demonstration period has a high potential of being impacted negatively if not recognized by the successful bidder with the performance of the work.

Concern No. 3: Patsaouras Plaza Cultural Resource Recovery Plan

Status/Action The Cultural Resources Monitoring and Discovery Plan was completed and submitted to FTA on March 9th. We submitted the document to SHPO for their concurrence on March 14th. SHPO concurred with the Cultural Resources Monitoring and Discovery Plan, that it was incorporated into the specifications for the project, and once construction begins, we will have monitoring by Native Americans and Archeologists as per the Plan.

Concern No. 4: Plan Forward for Patsaouras Plaza

Status/Action Bids cancelled, project team to review value engineering options to reduce project costs. Evaluate between re-bidding the project or moving forward with another course of action such as furthering the design.

Concern No. 5: HTW CCTV

Status/Action ITS needs to install phone lines to program the servers, place an antenna on a Metro tower, and to obtain the FCC licenses. ITS lack of progress has impacted completion of the work since late November. Metro met with ITS in November.

10 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

PROGRAM SCOPE

Los Angeles County Metropolitan Transportation Authority and Caltrans have partnered with Foothill Transit, Gardena Municipal Bus Lines, Los Angeles Department of Transportation, Southern California Regional Rail Authority (Metrolink) and Torrance Transit, to develop a package of solutions to increase traffic flow and provide travel options on the I-10 and I-110 freeways in Los Angeles County. These solutions will be incorporated into a one-year demonstration that will test new technologies to improve the existing transportation system called ExpressLanes.

The program goal is to improve mobility and provide congestion relief on the I-10 and I-110 freeways through the introduction of congestion pricing by converting High Occupancy Vehicle (HOV) Lanes to High Occupancy Toll (HOT) Lanes, improvements to the transit service along the freeways, transit facility improvements, increased funding for vanpools and the introduction of an intelligent parking management program, called ExpressPark, in downtown Los Angeles.

This program offers improved transportation options and a choice for drivers of single occupant vehicles (SOV) to pay to travel in a high occupancy lane. The general purpose lanes will not be tolled. The aim of the program is to foster incentives for sustainable change that creates travel time savings, increased trip reliability, cost savings, improved air quality and effectively manages our current roadway network.

11 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

PROGRAM SCOPE (Contd)

The features of the ExpressLanes program include:

1) TOLL INFRASTRUCTURE AND FREEWAY/ROADWAY IMPROVEMENTS

 I-10 HOV Conversion to HOT Lanes (I-605 to Alameda St./Union Station) and I- 110 HOV Conversion to HOT Lanes (Harbor Gateway Transit Center to Adams Blvd.) – an electronic toll collection system will be constructed that includes toll infrastructure, changeable message and static signage, transponders, cameras, back-office administration and management, CHP enforcement, and incident management response. nd nd  Add 2 HOT Lane on I-10 (between I-605 and I-1710) – a 2 HOT lane will be added on the I-10 between I-605 and I-710 in both the eastbound and westbound directions. This will be accomplished by re-striping the existing enforcement zone buffer and minor roadway widening.  Widen Adams Blvd. and Lane Modifications to Adams Blvd Off-Ramp – modifications at Adams Blvd. include re-configuration to include two dedicated left turn lanes and one dedicated right turn lane. Widening of Adams Blvd. will require the sidewalk to be taken to add an additional dedicated right turn in the westbound direction. To replace the sidewalk, a pedestrian over-crossing will be constructed over the I-110 freeway on the north side of Adams Blvd.  Project Study Report (PSR): Adams Blvd.-Figueroa St. HOT Lane Flyover – funding will be provided to Caltrans to perform a PSR to identify alternatives to connect from the northbound I-110 HOT Lanes to Figueroa St. The PSR will be coordinated with the Harbor Freeway Cap Park Feasibility Study lead by the City of Los Angeles.

2) TRANSIT SERVICE IMPROVEMENTS

 Enhanced Silver Line BRT and Feeder Services – Funding will be provided to Metro for 41 new CNG buses to enhance service on the I-10 and I-110 and create a new dual-hub BRT. In addition, Foothill Transit will deploy 12 new buses, Gardena Transit will deploy 2 new gas-hybrid buses and Torrance Transit will deploy 4 new buses to improve additional commuter bus service on both the I-10 and I-110. During the 1-year Demonstration period, Foothill, Torrance and Gardena will also receive an operating subsidy for their expanded service. Metro enhanced Silver Line service will be implemented in two phases – Phase I in FY12 and Phase II in FY13. All enhanced Metro Silver Line service will be in place prior to the opening of the ExpressLanes. Municipal operators will deploy their buses upon opening day of the ExpressLanes. For Gardena and Torrance this will be October 2012 and for Foothill Transit this will be February 2013.

12 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

PROGRAM SCOPE (Contd)

 Transit Signal Priority in Downtown Los Angeles – The LADOT will install bus signal priority technology on Figueroa St. between Wilshire Blvd. and Adams Blvd. (15 signals) and Flower St. between Wilshire Blvd. and Olympic Blvd. (5 signals) to enhance transit operations. This project will also extend the existing AM peak- period northbound bus-only lane on Figueroa St. to cover the PM peak-period.

 Vanpools – Activities to support the formation of 100 new vanpools include marketing and vanpool start-up costs such as training community groups to form commuter vanpools and ensure that vanpools are created and retained, ride- matching software, driver (or other empty seat subsidies), back-up driver training exams and parking lot leases.

3) TRANSIT FACILITY IMPROVEMENTS

 El Monte Transit Center Improvements – a new 30-bay bus terminal will be constructed at the current El Monte Transit Center location to accommodate service improvements and expansion. This will add capacity for Metro’s dual-hub BRT service and Foothill’s Silver Streak service and will be LEED Gold Certified.  Patsaouras Plaza Connector to the El Monte Busway – the existing passenger boarding/alighting areas located at the corner of Alameda St. and the Busway entrance will be relocated to the south side of Patsouras Plaza to allow direct pedestrian access to the Plaza and Union Station.  Harbor Transitway Park and Ride Improvements – improvements will include enhanced signage, lighting and security at 8 Park and Ride lots. A Sherriff’s Substation will be constructed at Harbor Gateway Transit Center. New bike lockers will be installed and bus stops will be re-located for lines 108 and 115 so that they are under the Slauson and Manchester Transitway stations. And at the 37th Street Station translucent and architectural sound attenuation panels will be installed to reduce noise levels for waiting customers on the Harbor Transitway. Design of the panels is based on noise testing and analyses conducted by noise experts, the architecture of the station and Caltrans requirements. Before and after noise data will be collected to evaluate whether or not additional sound attenuation projects are implemented in the future at other freeway adjacent stations.  Pomona Metrolink Station Expansion – this project consists of new pedestrian access improvements, 143 new parking spaces and the extension of the platform to accommodate additional rail cars at the Pomona (North) Metrolink Station that serves the San Bernardino Line. Operation of extended trains is projected to begin sometime in early 2011 on the San Bernardino Line.

13 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

PROGRAM SCOPE (Contd)

4) DEMAND–BASED PARKING PRICING

 LA ExpressPark – the LADOT will deploy new parking meter technology to 5,500 on-street metered parking spaces in the Central Business District, Chinatown, Civic Center, East Downtown, Little Tokyo and Washington/Broadway. These new meters will charge demand-based parking rates depending on the time of day and length of stay. They will also provide alternative payment options (i.e. credit card, cell phone). In addition to the on-street meters, occupancy reporting systems will also be implemented for the major City-owned off-street parking facilities (approx 7,500). Real-time parking information for 13,000 public on- and off-street parking spaces will be provided through various media including: websites, mobile phones, and on-street dynamic message signs. The project will be implemented in three successive phases of demand-based pricing development. Phase I: Base Hourly Rate – using baseline data, the system will iteratively refine base hourly rate to influence demand. Phase II: Time of Day – Building upon the demand balance achieved in Phase I, the system will identify peak periods and establish hourly rates by time of day. Phase III: Adaptive – In select areas, the system will adjust rates per block in real-time based on current demand.

14 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

KEY MILESTONE SCHEDULE SIX-MONTH LOOKAHEAD

Milestone Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Date HOT Lane Project I-10CommisioningTest 02/22/13 I-10 System Acceptance Test 04/22/13 Transit Facilities Improvement Harbor Transit Way Improvement El Monte Transit Center Pastouras Plaza

Metro Milestone Design/Build Constructors Third Parties Approval FHWA FederalHighway Administration /FTA CT Caltrans Milestone * New Date

15 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

PROGRAM SUMMARY SCHEDULE

16 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

CRITICAL PATH NARRATIVE

ExpressLanes Project The Critical Path of the HOT Lanes DBOM contract runs through the Toll Implementation design/procurement/test related activities. The schedule assumes a one month end-to- end testing period for each of the corridors, following installation of the Toll Operation Service Center and two months of integrated test period for the entire system following the corridor-wide testing. Our design consultants have confirmed that those durations are adequate for the testing activities. The opening of the I-110 HOT Lanes took place November 10, 2012 and the I-10 HOT Lanes is projected in February 2013.

Caltrans has issued a Change Order (CCO) to the I-10 Rehab Contractor for striping of the general purpose lanes and the I-10 Rehab Contractor performed most of the final striping work. This work was critical to allow ExpressLanes Project Contractor to progress its electrical and communication work on the outside shoulder required for DMS and toll signs. Caltrans has provided the I-10 Rehab Contractor survey controls so the final striping of GP lanes was able to move forward. Metro has accelerated the installation of the communication network on the I-10 Freeway to meet the revenue operations date due to delays encountered. Metro continues to meet with these other contract REs in an effort to eliminate as many potential impacts as possible. Metro has diligently worked to take the lead role in advising other projects as to where and when our projects will be working at the various locations.

Access to the I-10 Freeway fiber optic cable installed by the I-10 Rehab Contractor has now been granted to the DBOM Contractor by Caltrans for use on the ExpressLanes. This delay has created a schedule impact to the ExpressLanes Project.

Construction of the pedestrian bridge overcrossing on the I-110 Freeway at Adams Blvd. was completed in November. Construction work was also completed on the widening of the vehicular bridge at Adams. The work in and around the POC was accelerated in order to support the I-110 ExpressLanes Revenue Operations.

The DBOM Contractor began displaying messages on the Dynamic Message Signs in concert with Metro’s needs to inform the public on the I-10 future opening date. Example: ExpressLanes Coming Visit FasTrakLa.net for Info. Metro coordinated the messages on the DMS signs with the actual opening date of the 110 ExpressLanes, and similar coordinated messages on the DMS signs will occur with the actual opening of the 10 ExpressLanes which is projected to be February 23, 2013.

Work continued on I-10 Freeway on various toll sites, DMS signs, etc; in January. All power drop installations along the I-10 were completed in December by DWP and SCE. All drainage, median barrier reconstruction was completed in January on the I-10 Freeway.

17 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

CRITICAL PATH NARRATIVE (Contd)

Design for the earthcam cameras has been completed and the installation of the additional earthcam cameras continued in January along the I-110 and I-10 Freeways. A total of 13 earthcam cameras are being installed along the I-10 and I-110 Freeway corridors. The earthcam cameras will allow real time traffic monitoring when the ExpressLanes go into operation. This is an important aspect of project implementation and was issued to the DBOM Contractor as change order work. Metro is using a portion of the schedule contingency and some acceleration to implement this work into the project.

The DBOM Contractor has been impacted by Caltrans Contractor Flatiron/Lincoln Pacific working on the north end of the 110 Freeway. This contractor should have completed the fiber optic cable installation in the I-10/110 node in May 2012. This fiber optic cable installation by Flatiron was completed in October. The DBOM Contractor was able to complete the redundant loop between I-10 and I-110 Freeways as it is a critical component of the fiber optic loop. Metro is analyzing this delay and will accelerate sections of the communication network to meet the project milestones. In September Metro issued a Contract Modification to the DBOM Contractor to acquire a leased line from ATT. This is still being installed and is due to be completed after the opening of the 10 Freeway. This will provide additional Redundancy capacity if there are other future problems with the Caltrans fiber loop.

On I-10 Freeway the existing shoulder between Fremont and the 605 Freeway will be restriped to create an additional Express Lane in each direction. A recent investigation of the existing shoulder condition revealed 6 areas that require pavement repairs before the shoulder is restriped to become the additional ExpressLane. This work needs to be completed prior to opening the I-10 ExpressLane to the traveling public in order to ensure it does not create a safety hazard. This work is being added to the scope of work to DBOM Contract and project schedule contingency will be used with selective acceleration to avoid impacts to the projected revenue operations date. During the month of December this work has been completed.

All of the DMS’s have now been powered up and trial messages are now being displayed on all the I-10 DMS signs. One example is Do not Cross the Double White Lines. Metro has issued a Change Order to the DBOM Contractor to install additional static signs on the I-10 and I-110 Freeways stating that all HOVs require a Fastrack to use the ExpressLanes. This is being done in consultation with CHP and Caltrans. Also additional static signs are being installed to advise drivers not to cross the Double White Lines.

The I-110 ExpressLanes is in operation and continued to gain ridership/usage everyday. During the month of January the sale and issuance of transponders showed significant distribution level.

18 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

CRITICAL PATH NARRATIVE (Contd)

Tenant improvements were completed for the Customer Service Center in Gardena and hiring and training of customer service staff was done. Since the first shipment of transponders were delivered in April to the CSC, inventory control measures have been implemented. The CSC in Gardena and the El Monte location was opened to the public in July and is fully operational. This was a major successful accomplishment leading to the I- 110 Freeway future revenue operations.

Operational changes were made at the CSC in anticipation of the opening date of February 23, 2013 of the ExpressLanes on the I-10 Freeway.

Metro has nearly completed the analysis of the various schedule delays that have been experienced on the ExpressLanes Project and has issued a Contract Extension Change Notice to the DBOM Contractor using a portion of the Project Schedule Contingency and implementing acceleration on the project. Based on this analysis, there will not be any impact to the Revenue Operations Dates for the I-110 Freeway being November 10, 2012 and the projected opening of the ExpressLanes on the I-10 Freeway on February 23, 2013.

I-10 Rehab Construction Caltrans I-10 Rehab contractor (Atkinson) previously provided Metro a schedule update, which showed the project completing April of 2012. The Rehab Contractor completed work, however, after completing their work the Rehab Contractor had to come back to perform corrective work. The Caltrans I-10 Rehab Contractor is now over one year behind schedule and this seriously impacted the DBOM’s Contract Schedule. The Caltrans Rehab Contractor on the I-10 Freeway has now completed all work.

Transit Service Improvement Foothill and Gardena Transit – No changes to the critical path.

Transit Facility Improvements El Monte Transit Center – Current contractor schedule shows the substantial completion date is September 2012. The sustained delays to critical activities on construction schedule was caused by the contaminated soil found during excavation and excessive rain days in December over the (5) rain delay days in the Baseline schedule. The Patsaouras Plaza Project was separated from the El Monte Station LOP at the October Metro Board Meeting. The LOP budget will be $16.8 million for Patsaouras Plaza and the LOP budget for El Monte Station is increased to $60.1 million. During July, KPRS completed the installation of the bus bay canopies on the concourse level, poured most of the curb and gutter around the perimeter of the station, and energized the Station after Southern California Edison pulled their conduit. With electrical power turned on, the site in now in log out-tag out. KPRS began installation of the photovoltaic cells on the concourse level and the ceiling tiles on the lower level of the station, and continued work on the two escalators and the three elevators. The last week in July, the pre-fabricated toilet arrived

19 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

CRITICAL PATH NARRATIVE (Contd) on site, and KPSR submitted an initial punchlist of items for closeout. KPRS made great strides on both the transit and retail buildings, completing most of the mechanical, electrical, and plumbing (MEP) work, HVAC ducting, interior dry walling, ceiling tile installation, and bathroom tile installation. KPRS also made the initial concrete pours on the plaza in front of the transit retail buildings.

With all construction complete since December, all activities in January were administrative in nature. Metro negotiated change orders related to the work completed earlier. Metro also began unencumbering unused funds on purchase orders that supported construction and the station opening.

Pastaouras Plaza – Due to several factors: funding shortfall and potential construction schedule impacts to the ExpressLanes. Staff presented a Recovery Plan to the Board with a formal action in October 2011. Staff obtained additional Federal funding to complete the Patsaouras Plaza Project for a Life of Project Budget of $16.8 million and will separate Patsaouras Plaza from the El Monte Station Project as approved at the October 2011 Metro Board Meeting. On July 20th, Metro issued a third amendment to the IFB. This third amendment was primarily to give the contractor responsibility of the artwork; and it extended the bid period for an additional two weeks in order to give prospective bidders sufficient time to address the new requirement. Amendment 3 also extended the bids due date from August 7th to August 14th. In December, the project team worked on a statement of work for a Task Order to STV Incorporated--the team that developed the Advanced Conceptual Engineering (ACE) design document – to incorporate the value engineering options and lessons learned from the debriefing with prior bidders. However, the task order takes the STV contract above the current contract limit and so a contract modification is being prepared. No other update to provide. The project will be a Design-Build. Construction is scheduled for completion Summer 2014.

Harbor Transitway – Project completion has been delayed because the sound enclosure design was rejected by Caltrans and the Contractor must re-design the project. Caltrans has indicated it will take 4-6 weeks to review the re-design. To mitigate the delay, staff has requested additional support from the Metro Third Party Administration to work with Caltrans to accelerate their review and Metro procurement staff is working with the Contractor to accelerate their re-design. Design issues have been resolved on the sound barrier. Contractor (Peterson Chase) spent the month of July working on the construction work plan (CWP), and met with Metro to review the railing modifications during installation of the sound panels. Contractor is still scheduled to initiate post installation and base framing on August 22. Contractor schedule shows panels will be delivered by September 3rd and installed by September 24th. For the bus stop cutouts, the low bid of $235,000 was awarded to RC Becker in March 2011 and NTP was provided on April 15, 2011.

20 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

CRITICAL PATH NARRATIVE (Contd)

Construction for bus stop cutouts was completed in August 2011. CCTV Contract C0986 price bids have been received and the contract was awarded in February 2012. By the end of July, the contractor (First Fire Systems) had installed most of the cameras, but cameras are not yet live because wiring to power and provide signal has not yet been completed. Digital Message Signs arrived in July, and contractor has begun installing them at Harbor Gateway. A modification was issued to contractor for additional servers (and associated electrical components) required for the message boards. To date, project expenditures and encumbrances are well within the Project LOP. Contractor to accelerate their re-design. Design issues have been resolved on the sound barrier. Work was completed in January.

For the bus stop cutouts, the low bid of $235,000 was awarded to RC Becker in March 2011 and NTP was provided on April 15, 2011. Construction for bus stop cutouts was completed in August 2011. CCTV Contract C0986 price bids have been received and the contract was awarded in February 2012. In January, no work has been conducted since Metro conducted final inspection of the work in December. First Fire’s completion of punchlist work is still on hold pending Metro’s ITS Department’s completion of work that includes the installation of wireless antennas and programming of the servers. To date, project expenditures and encumbrances are well within the Project LOP.

Metrolink Pomona Station The project is complete.

Transit Signal Priority in Downtown The original completion date of December 31, 2010 was moved to August 31, 2011 due to a prolonged review process for the E-76 Authorization to Proceed with Construction and due to LADOT internal reorganization which resulted in Project Management being transferred to another group. Project assumed completion of ARRA TPS-ATSAC Communications System Rehabilitation, which was supposed to provide interconnect capacity for transit signal priority. Due to changes in the ARRA project construction scope, the project must be redesigned to continue the interconnect link to the ATSAC Center. The bids have been cancelled and the project was redesigned November 2011. The bid package was completed December 6, 2011 and 18 bids were opened January 18, 2012. The Board of Public Works awarded the contract in March and issued a Notice to Proceed. Construction commenced on April 9, 2012, and is anticipated to be completed by July 2012. The project is progressing per the schedule even with some delays for special events at LA Live. The contractor is trying to work Saturdays to compensate for any lost work days. Full system integration was completed in September 2012.

21 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

CRITICAL PATH NARRATIVE (Contd)

Metro submitted the transponder information to LADOT. Project was completed in September 2012. Part of the TPS project also includes the extension of the existing AM peak-period northbound bus-only lane on Figueroa St. between 23rd Street and 4th Street to cover the PM peak-period. A Traffic Control Report (TCR) was approved by the General Manager of LADOT to extend the PM peak-period bus only lane. The Figueroa Street PM Peak Bus-Only Lane was completed in October. All the signs and pavement markings were installed by LADOT field crews. LADOT obtained funding approval from Metro for the camera installation work at Alameda. Completion is scheduled for end of February 2013.

LA ExpressPark Project LADOT’s Evaluation Panel completed its work on April 6, 2011, and recommended that ACS State & Local Solutions be selected as the prime contractor for LA ExpressPark. The second proposer filed a protest. The formal protest of the contractor selection process was withdrawn on May 20, 2011. LADOT Board of Transportation Commissioners approved the LA ExpressPark contractor selection and forwarded their report to the Mayor and the CAO on June 9, 2011. On August 12, 2011, the L.A. City Council unanimously approved the CAO report, authorizing LADOT to execute the contract with ACS for the implementation of the LA ExpressPark Intelligent Parking Management Project. Also, the City Council provided LADOT the authority to adjust on- street parking meter rates in the LA ExpressPark project area. It should be noted that the project has been separated into three phases. The date for the LA ExpressPark to be fully operational (October 2012) will not impact the start of the Demo Evaluation Period. LA ExpressPark will support Phase I of the demand-based pricing no later than May 2012.

It will be expanded to support Phase II no later than July 2012 and Phase III no later than November 2012, which is consistent with RFP requirements. Phase I will use the baseline data to refine base hourly rates to influence demand. Phase II will build on the demand balance from Phase I and will identify peak periods and establish hourly rates by the time of day. Phase III will adjust rates per block in select areas in real-time based on current demand.

Phase I of the IPM (MERGE System) was completed Sept. 24th. Phase 2 and 3 are underway. The MERGE System is currently scheduled to be fully operational in the first quarter 2013. The new DMS signs in South Park were installed in December. The neighborhood DMS signs are now scheduled for installation in early 2013. It has taken longer than anticipated to get the necessary approvals for the DMS installations. The projected completion date for the MERGE system has been extended to 2/15/13. This extension will not affect the functions critical for demand-based pricing and guided enforcement.

22 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

CRITICAL PATH NARRATIVE (Contd)

The elements necessary for demand-based pricing are operational; remaining work includes further automation, integration of the parking guidance systems and workforce management. There were no rate changes planned for February; the next rate change will be March 4, 2013. Before making anymore rate changes, LADOT has asked its contractor to evaluate the effectiveness of the rate changes to date. In March, we will be testing the effectiveness of new labels on four block faces. For each of these block faces the rate has reached the upper limit set by ordinance and there are adjacent block faces with lower rates. The goal of the test is to guide parkers to the available spaces on the lower priced block faces. The occupancy systems for El Pueblo, Pershing Square and LA Mall are now sending occupancy directly to MERGE for redistribution to the elements of the parking guidance system. The software is now in place and has been tested for sending messages through MERGE to the large DMS in South Park.

23 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

PROGRAM COST STATUS

CONGESTION REDUCTION DEMONSTRATION PROGRAM COMBINED COST REPORT BY PROJECT METRO CONSTRUCTION MANAGEMENT DIVISION

PERIOD ENDING: JAN 2013 DOLLARS N

O CURRENT FORECAST COMMITMENTS* EXPENDITURES* BUDGET / T

E ADOPTED BUDGETPROJECT FORECAST S PERIOD TO DATE PERIOD TO DATE PERIOD TO DATE VARIANCE

CP 201059 - PROCURE 41 BUSES 27,214,617 - 27,214,617 - 27,214,617 - 27,214,617 -

CP 202286 - EL MONTE TRANSIT CENTER 4 60,106,000 60,106,000 83,598 57,155,415 190,131 55,473,517 -

CP 202287 - HARBOR TRANSITWAY IMPROVEMENTS 3,850,000 - 3,850,000 22,369 3,546,353 870,672 3,456,904 -

CP 202317 - PATSOURAS PLAZA CONNECTOR 4 16,803,000 - 16,803,000 13,471 2,510,454 58,288 2,271,988 -

CP 210115 - BIKE LOCKERS 101,012 - 101,012 - 101,012 - 101,012 -

CP 210120 - TOLLTECHNOLOGY & ROADWAY IMPROVEMENTS 1 120,635,000 - 120,635,000 187,957 105,553,183 2,104,436 102,302,466 -

METRO & CALTRANS TOTAL 228,709,629 - 228,709,629 307,394 196,081,034 3,223,528 190,820,504 -

OTHER AGENCIES OR OTHER METRO COSTS:

METROLINK POMONA METROLINK STATION - INC. PARKING 5 10,815,476 10,815,476 10,815,476 10,815,476 -

METRO OPERATING SUBSIDY FOR DEMO 6,716,462 6,716,462 376,500 773,706 363,588 678,787 -

METRO I-110 Adams Flyover PSR - METRO 3 7,840,790 7,840,790 1,362,265 - 740,398 -

FOOTHILL TRANSIT PROCURE 12 BUSES 7,500,000 - 7,500,000 7,305,825 - 7,305,825 -

FOOTHILL TRANSIT OPERATING SUBSIDY FOR DEMO 3,200,000 - 3,200,000 - - - -

TORRANCE TRANSIT PROCURE 4 BUSES 2,800,000 - 2,800,000 2,800,000 - 2,286,900 -

TORRANCE TRANSIT OPERATING SUBSIDY FOR DEMO 1,200,000 - 1,200,000 - - - -

GARDENA TRANSIT PROCURE 2 BUSES 1,200,000 - 1,200,000 1,200,000 - 1,129,584 -

GARDENA TRANSIT OPERATING SUBSIDY FOR DEMO 677,736 - 677,736 - - - -

LADOT TRANSIT SIGNAL PRIORITY 856,796 - 856,796 580,426 - 580,426 -

METRO FACILITYO&M ------

METRO VANPOOLS 400,000 - 400,000 58,929 144,208 20,412 57,780 -

LADOT EXPRESSPARK 18,500,000 - 18,500,000 18,477,803 665,889 10,117,095 -

OTHER AGENCIES OR OTHER METRO COSTS: 61,707,260 - 61,707,260 435,429 43,459,709 1,049,889 33,712,271 -

TOTAL CRD PROGRAM: 2 290,416,889 - 290,416,889 742,823 239,540,743 4,273,417 224,532,775 - NOTE 1: $120.6M ADOPTED BUDGET DOES NOT INCLUDE O&M COSTS FOR FIRST YEAR DEMONSTRATION. NOTE 2: ADOPTED BUDGET OF APPROXIMATELY $369.2M IS THE $331.8M BUDGET BOARD APPROVED IN DEC-10 PLUS PARTNER LOCAL MATCH AND OTHER NON-CRD FUNDS TO BE USED IN CRD PROGRAM LESS THE UNION DIVISION WHICH HAS BEEN REMOVED FROM CRD PROGRAM, BRINGING THE ADOPTED BUDGET TO APPROXIMATELY $291M. NOTE 3: FUNDED BY ISTEA EARMARK AND LOCAL MATCH NOTE 4: METRO BOARD REPORT AUTHORIZED TO SPLIT EL MONTE TRANSIT CENTER AND PATSOURAS PLAZA CONNECTOR INTO TWO SEPERATE PROJECTS IN OCTOBER, 2011. NOTE: EXPENDITURES ARE CUMULATIVE THROUGH DECEMBER 31, 2012. CP 202001 - UNION DIVISION, HAS BEEN REMOVED FROM THE CRD PROGRAM.

24 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

CONGESTION REDUCTION DEMONSTRATION PROGRAM STATUS OF FUNDS BY SOURCE AS OF DECEMBER 31, 2012

(A) (B) (C) (D) (E) (E/B+C) (F) (F/B+C) (G) (G/B+C)

Original Total Funds Add'l Funds Total Funds Funding Sources Commitments Expenditures BilledtoFundingSource Budget Anticipated Anticipated Available

$ % $ % $ % Federal - Section 5309 (1) 210,600,000$ -$ -$ -$ -$ -$ -$ Federal - Section 5307 (2) $ - $ 83,516,000 $ - $ 83,335,999 $ 82,926,348 99.3% $ 82,618,456 98.9% $ 82,505,321 98.8% Cities' match to Section 5307 (2) $ - $ 2,256,000 $ 1,793 $ 2,257,793 $ 2,257,793 100% $ 1,910,610 84.6% $ 1,910,610 84.6% Federal - CMAQ (transferred from 5307) $ - $ 57,500,000 $ 18,900,000 $ 76,400,000 $ 68,825,162 90.1% $ 59,987,613 78.5% $ 51,259,945 67.1% Federal - CMAQ $ - $ - $ 18,300,000 $ 17,900,001 $ 917,914 5.0% $ 736,566 4.0% $ 381,301 2.1% Federal - Section 5309 State of Good Repair $ - $ - $ - $ - $ - $ - $ - Federal - Section 5308 Clean Fuel $ - $ - $ - $ - $ - $ - $ - Federal - Section 5309 Livability Initiative $ - $ - $ 9,679,000 $ 9,679,000 $ 637,610 6.6% $ 399,144 4.1% $ 389,793 4.0% Other agencies' Federal Funds $ - $ - $ 9,732,591 $ 9,732,591 $ 4,395,175 45.2% $ 3,897,681 40.0% $ 3,897,681 40.0% State - Prop 1B SLPP (3) (5) (6) $ - $ 20,000,000 $ - $ 20,000,000 $ 20,000,000 100.0% $ 20,000,000 100.0% $ 20,000,000 100.0% State - Prop 1B Transit $ - $ - $ - $ - $ - $ - $ - Local - Measure R 35% (5) $ - $ 3,586,931 $ - $ 3,586,931 $ 3,586,931 100% $ 3,586,931 100.0% $ 3,586,931 100% Local - Prop C 40% (5) $ - $ 13,025,069 $ - $ 13,025,069 $ 12,926,649 99.2% $ 12,908,759 99.1% $ 12,880,475 98.9% Local - Prop C 25% (5) -$ 28,355,000$ 3,123,158$ 31,478,158$ 32,428,668$ 103.0% 31,835,638$ 101.1% 30,524,498$ 97.0% Local - Prop C 10% (5) -$ 1,120,000$ -$ 1,120,001$ 1,120,001$ 100.0% 1,120,001$ 100.0% 1,120,001$ 100.0% Local- Capital Projects Repayment (5) -$ 1,241,000$ -$ 1,241,000$ -$ 0.0% -$ 0.0% -$ 0.0% Local - SAFE (4) -$ -$ 4,000,000$ -$ -$ 0.0% -$ 0.0% -$ 0.0% Othe Local funds(7) -$ -$ 6,815,629$ 3,417,043$ 3,417,043$ 50.1% 1,735,145$ 25.5% 1,563,704$ 22.9% Other agencies' contribution $ - $ - $ 9,266,510 $ 9,038,246 $ 6,101,450 65.8% $ 3,796,230 41.0% $ 3,803,485 41.0% TOTALS $ 210,600,000 $ 210,600,000 $ 79,818,680 $ 282,211,832 $ 239,540,743 82.5% $ 224,532,775 77.3% $ 213,823,746 73.6% Notes: (1) Section 5309 original award of $210.6m was obligated in full for Metro's Preventive Maintenance activities. A combination of Section 5307 and local funds were allocated to the CRD Program to replace the Section 5309 funds. (2) Metro allocated 100% 5307 federal funds to the cities. In return, the cities provided match by reducing their allocated funds and exchanging with their own local funds. Balance of unallocated federal funds are available to the cities for other purposes. (3) SLPP = State and Local Partnership Program (4) SAFE = Service Authority for Freeway Emergencies (5) Represent a series of Metro' internal funds exchanges between projects to swap Section 5307 funds for local funds. (6) We are working with Caltrans to develop a process to bill the SLPP grant . Therefore, the reimbursement of our expenditures has been slowed. We expect to catch up in the next few months. (7) Other Local Funds will be identified in the Metro Adopted Fiscal Year Budget of the year the expense is budgeted. Division 13 was removed from the LA CRD program.

25 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

CONGESTION REDUCTION DEMONSTRATION PROGRAM STATUS OF FUNDS BY PROJECT AS OF DECEMBER 31, 2012

FUNDING SOURCES (Funds Anticipated)

Federal - PROJECT Federal - CMAQ Local - Local- Capital Section Federal - Section Cities' Match to (Transferred State - Prop 1B Measure R Local - Prop C Local - Prop C Local - Prop C Projects Total Local 5309 5307 Section 5307 from 5307) SLPP 35% 40% 25% 10% Repayment Funds Non CRD Funds Total Metro A B C D E F PROCUREMENT 41 BUSES $ - $ 22,588,132 $ - $ - $ - $ 3,586,931 $ 1,039,553 $ - $ - $ - $ 4,626,485 $ - $ 27,214,617 DIVISION 13 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - EL MONTE TRANSIT CENTER $ - $ 42,886,636 $ - $ - $ - $ - $ 10,851,736 $ - $ - $ - $ 10,851,736 $ 6,367,629 $ 60,106,000 PATSAOURAS PLAZA IMPROVEMENTS $ - $ 1,200,000 $ - $ - $ - $ - $ 300,000 $ - $ - $ - $ 300,000 $ 15,303,000 $ 16,803,000 HARBOR TRANSITWAY IMPROVEMENTS $ - $ 3,080,000 $ - $ - $ - $ - $ 770,000 $ - $ - $ - $ 770,000 $ - $ 3,850,000 BIKE LOCKERS (El Monte, Artesia) $ - $ 37,232 $ - $ - $ - $ - $ 63,780 $ - $ - $ - $ 63,780 $ - $ 101,012 TOLL TECHNOLOGY & ROADWAY IMPROVEMENTS (Express Lanes) -$ -$ -$ 41,500,000$ 20,000,000$ -$ -$ 28,355,000$ -$ 1,241,000$ 29,596,000$ 29,539,000$ 120,635,000$ Metro Total -$ 69,792,000$ -$ 41,500,000$ 20,000,000$ 3,586,931$ 13,025,069$ 28,355,000$ -$ 1,241,000$ 46,208,000$ 51,209,628$ 228,709,628$ Other Agencies/Other Metro Costs METORLINK - Pomona Station (Including Parking) $ - $ 4,480,000 $ - $ - $ - $ - $ - $ - $ 1,120,000 $ - $ 1,120,000 $ 5,215,476 $ 10,815,476 METRO - Operating Subsidy for Demo (Highway) $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 2,915,338 $ 2,915,338 METRO - Operating Subsidy for Demo (Transit) $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 3,801,124 $ 3,801,124 METRO - I-110 Adams Flyover (PSR) $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 7,840,790 $ 7,840,790 FOOTHILL TRANSIT - Procure 12 Buses $ - $ 6,008,000 $ 1,492,000 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 7,500,000 FOOTHILL TRANSIT - Operating Subsidy For Demo $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 3,200,000 $ 3,200,000 TORRANCE Transit - Procure 4 Buses $ - $ 2,276,000 $ 524,000 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 2,800,000 TORRANCE Transit - Operating Subsidy For Demo $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 1,200,000 $ 1,200,000 GARDENA Transit - Procure 4 Buses $ - $ 960,000 $ 240,000 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 1,200,000 GARDENA Transit - Operating Subsidy For Demo $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 677,736 $ 677,736 LADOT - Transit Signal Priority $ - $ - $ - $ 1,000,000 $ - $ - $ - $ - $ - $ - $ - $ (143,204) $ 856,796 METRO - Vanpools $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 400,000 $ 400,000 LADOT - Express Park $ - $ - $ - $ 15,000,000 $ - $ - $ - $ - $ - $ - $ - $ 3,500,000 $ 18,500,000 Other Agencies/Other Metro Costs Total -$ 13,724,000$ 2,256,000$ 16,000,000$ -$ -$ -$ -$ 1,120,000$ -$ 1,120,000$ 28,607,260$ 61,707,260$ TOTAL FUNDS ANTICIPATED $ - $ 83,516,000 $ 2,256,000 $ 57,500,000 $ 20,000,000 $ 3,586,931 $ 13,025,069 $ 28,355,000 $ 1,120,000 $ 1,241,000 $ 47,328,000 $ 79,816,888 $ 290,416,888 Note: columns A+B+C+D+E sum up to $210,600,000. The Non-CRD funds are beyond the $210.6 million. Division 13 was removed from the LA CRD program.

FUNDING SOURCES (Expenditures)

Federal - PROJECT Federal - CMAQ Local - Local- Capital Section Federal - Section Cities' Match to (Transferred State - Prop 1B Measure R Local - Prop C Local - Prop C Local - Prop C Projects Total Local 5309 5307 Section 5307 from 5307) SLPP 35% 40% 25% 10% Repayment Funds Non CRD Funds Total Available Sources $ - $83,516,000 $2,256,000 $57,500,000 $20,000,000 $3,586,931 $13,025,069 $28,355,000 $1,120,000 $1,241,000 $47,328,000 $79,816,888 $290,416,888 Metro PROCUREMENT 41 BUSES $ - $ 22,588,132 $ - $ - $ - $ 3,586,931 $ 1,039,553 $ - $ - $ - $ 4,626,485 $ - $ 27,214,617 DIVISION 13 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - EL MONTE TRANSIT CENTER $ - $ 42,886,636 $ - $ - $ - $ - $ 10,851,736 $ - $ - $ - $ 10,851,736 $ 1,545,014 $ 55,283,386 PATSAOURAS PLAZA IMPROVEMENTS $ - $ 1,049,234 $ - $ - $ - $ - $ 262,309 $ - $ - $ - $ 262,309 $ 940,980 $ 2,252,523 HARBOR TRANSITWAY IMPROVEMENTS $ - $ 2,068,985 $ - $ - $ - $ - $ 517,246 $ - $ - $ - $ 517,246 $ - $ 2,586,231 BIKE LOCKERS (El Monte, Artesia) $ - $ 37,232 $ - $ - $ - $ - $ 63,780 $ - $ - $ - $ 63,780 $ - $ 101,012 TOLL TECHNOLOGY & ROADWAY IMPROVEMENTS (Express Lanes) -$ -$ -$ 48,677,087$ 20,000,000$ -$ -$ 31,745,000$ -$ -$ 31,745,000$ -$ 100,422,087$ Metro Total -$ 68,630,220$ -$ 48,677,087$ 20,000,000$ 3,586,931$ 12,734,624$ 31,745,000$ -$ -$ 48,066,556$ 2,485,994$ 187,859,856$ Other Agencies/Other Metro Costs METROLINK - Pomona Station (Including Parking) $ - $ 4,479,999 $ - $ - $ - $ - $ - $ - $ 1,120,001 $ - $ 1,120,001 $ 5,215,476 $ 10,815,476 METRO - Operating Subsidy for Demo (Highway) $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - METRO - Operating Subsidy for Demo (Transit) $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 315,199 $ 315,199 METRO - I-110 Adams Flyover (PSR) $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 740,398 $ 740,398 FOOTHILL TRANSIT - Procure 12 Buses $ - $ 5,812,032 $ 1,493,793 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 7,305,825 FOOTHILL TRANSIT - Operating Subsidy For Demo $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - TORRANCE Transit - Procure 4 Buses $ - $ 2,096,000 $ 190,900 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 2,286,900 TORRANCE Transit - Operating Subsidy For Demo $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - GARDENA Transit - Procure 4 Buses $ - $ 903,667 $ 225,917 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 1,129,584 GARDENA Transit - Operating Subsidy For Demo $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - LADOT - Transit Signal Priority $ - $ - $ - $ 554,514 $ - $ - $ - $ - $ - $ - $ - $ 25,912 $ 580,426 METRO - Vanpools $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 37,368 $ 37,368 LADOT - Express Park $ - $ - $ - $ 8,209,744 $ - $ - $ - $ - $ - $ - $ - $ 1,241,462 $ 9,451,206 Other Agencies/Other Metro Costs Total -$ 13,291,698$ 1,910,610$ 8,764,258$ -$ -$ -$ -$ 1,120,001$ -$ 1,120,001$ 7,575,815$ 32,662,381$ TOTAL EXPENDITURES $ - $ 81,921,918 $ 1,910,610 $ 57,441,345 $ 20,000,000 $ 3,586,931 $ 12,734,624 $ 31,745,000 $ 1,120,001 $ - $ 49,186,557 $ 10,061,809 $ 220,522,237 Underbudget(overbudget) -$ 1,594,082$ 345,390$ 58,655$ -$ -$ 290,445$ (3,390,000)$ (1)$ 1,241,000$ (1,858,556)$ 69,755,079$ 69,894,651$

Note: The Express Lanes exceeded the PC25% funds available by $3.4 million. Items need to be reconciled.

26 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

PROGRAM COST ANALYSIS

Adopted Budget The Adopted Budget reflects removal of Division 13 budget resulting in an adjusted CRD Program Budget of $291 million.

Current Forecast The Current Forecast of approximately $291 million remains the same as the Adopted Budget.

Commitments The Commitments increased by $743K this period primarily for Metro staff charges, and purchase orders for materials and services for ExpressLanes, El Monte, Harbor Transitway, Patsaouras Plaza, Metro Vanpools and Metro Operating Subsidy.

Expenditures Expenditures increased by $4.0M this period primarily for expenditures for El Monte, Harbor Transitway, Patsaouras, ExpressLanes and LADOT’s ExpressPark Project, design and construction management consulting, and Metro and Caltrans staff labor charges. The $224.5M in Project Expenditures to date represents 77.2% of the program budget of $291 million.

27 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

STATUS OF FUNDS ANTICIPATED

FEDERAL CMAQ: Transit Signal Priority (LADOT): $856,796 of CMAQ funds are available for drawdown. Express Park (LADOT): $15,000,000 of CMAQ funds are available for drawdown. ExpressLanes (Metro): $25.762M of CMAQ funds are available for drawdown. A second request for $41.238M in CMAQ funding was approved April 25, 2011. A total of $67 million in CMAQ is available for drawdown. A third request of $2.498 million for the operating funds was approved in May 2012.

FEDERAL FTA 5307: Metro Bus Procurement: An FTA grant application of $23.572M (CA-90-Y716) was awarded on July 2, 2009. Funds are available for drawdown. Metro Bus Operations – In June a request was submitted to FHWA to transfer $3,801,124 in CMAQ funds to FTA (CA-95-X099). El Monte Transit Center: An FTA grant application of $2.160M (CA-90-Y716) was awarded on July 2, 2009. Funds are available for drawdown. Patsaouras Connector: An FTA grant application of $1.2M (CA-90-Y716) was awarded on July 2, 2009. Funds are available for drawdown. Harbor Transitway Improvements: An FTA grant application of $2.0M (CA-90-Y716) was awarded on July 2, 2009. Funds are available for drawdown. Bus Procurement and Operations (Other Agencies): Foothill Transit: A grant application for $7.5M (CA-90-Y797) has been approved and funds are available for drawdown. Torrance Transit: A grant application for $2.6M (CA-90-Y715) has been approved and funds are available for drawdown. Gardena Transit: A grant application for $960K (CA-90-Y707) has been approved and funds are available for drawdown. Metrolink: A grant application for $5.26M (CA-90-Y777) was approved in September 2010 and funds are available for drawdown. A separate grant for $339K (CA-90-Y840) has been approved and funds are available for drawdown. Metro Bus Operations: An FTA grant application of $3.8M (CA-95-X099) for Metro Silver Line operations was submitted to FTA in October 2011.

FEDERAL FTA 5309: Patsaouras Connector: An FTA grant award was announced in the amount of $9.7 million on October 17, 2011.

STATE SLPP: ExpressLanes (Metro): The CTC rather than approving a $20M allocation in SLPP Funds approved a $20M Letter of No Prejudice (LONP) at the September 2010 CTC Meeting. Per the Metro Board approval in August 2010, the use of Local Funds (PC25)

28 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

STATUS OF FUNDS ANTICIPATED (Contd) will be the fund source for the LONP. At its January 2011 Meeting, the CTC approved the $20 million in SLPP funds so there is no further need for the LONP. The State will reimburse Metro for any funds that were expended prior to the allocation of the funds in January 2011.

ADAMS FLYOVER PSR ISTEA FUNDS: $4,104,000 of ISTEA funds was approved in December 2010. A second request for $2,127,000 was approved by FHWA in February 2011. A third request for $41,632 was approved by FHWA in March 2011. The full amount of $6,272,632 in ISTEA funds have been approved and are available for drawdown.

29 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

STAFFING STATUS Total Program Staffing - FTEs

35

Plan 30 Actual

) 25 E T F (

s t n

e 20 l a v i u q E

e 15 m i T

l l u F 10

5

0 0 0 1 1 2 2 3 3 9 9 9 9 9 9 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 3 3 3 3 3 1 1 1 1 1 1 1 1 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 ------J J J J J J J J J J J J J F F F F A S A A S A A S A A S A N D N D N D N D O O O O M M M M M M M M

30 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

REAL ESTATE STATUS

 The HOT Lanes Project will be built entirely within existing Caltrans ROW, no additional project ROW will be required.

 No additional ROW is required for any of the remaining projects.

REAL ESTATE STATUS TO DATE

Appraisal Number of In Appraisal Process Turned Over to Parcels Required Process Complete Offer Made Closing Acquired Contractor

This Period 0 0 0 0 0 0 0

Last Period 0 0 0 0 0 0 0

31 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

ENVIRONMENTAL STATUS

There are seven (7) projects that require environmental approval. NEPA/CEQA approval has been received for all projects.

 I-10 and I-110 HOV Conversion to HOT Lanes – EIR/EA. NEPA approved May 2010. CEQA approved June 2010.

 Harbor Transitway Improvements – Listed Categorical Exclusion/Exemption, no approval required.

 El Monte Transit Center Improvements – Categorical Exclusion (NEPA)/Categorical Exemption (CEQA). Submitted September 2009. NEPA approved November 2009. CEQA approved December 2009.

 Patsaouras Plaza Connector – Categorical Exclusion (NEPA)/Categorical Exemption (CEQA). NEPA and CEQA approvals are pending. NEPA and CEQA approvals were received February 2012.

 Transit Signal Priority – Categorical Exclusion (NEPA)/Categorical Exemption (CEQA). NEPA and CEQA approved September 2009.

 LA ExpressPark – Categorical Exclusion (NEPA)/Categorical Exemption (CEQA). NEPA and CEQA approved October 2009.

 Pomona Metrolink Station Improvements – Categorical Exclusion (NEPA)/Statutory Exemption (CEQA). NEPA and CEQA submitted November 2007. CE approved July 2010.

32 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

COMMUNITY/MEDIA RELATIONS STATUS

During the month of January 2013 outreach briefings were provided to staff of federal, state and local elected officials at the Metro Quarterly Legislative Briefing, to council members and attendees at the Lawndale and Inglewood City Council Meetings, and to stakeholders at Metro Technical Advisory Committee, Transportation Research Board Annual Conference, Metro San Gabriel Valley Service Council, Institute of Transportation Engineers, and SEIU USWW. The total of 469 program briefings/events were held between April 25, 2008 and January31, 2013 as follows:

 Program stakeholder briefings, technical advisory group meetings, and live web chats: 269  Construction mitigation briefings: 4  Legislative briefings: 78  Corridor Advisory Group meetings: 16  Public hearings: 8  Community workshops: 7  Information tables: 25  Metro ExpressLanes Mobile Van (MEL) events: 62

A total of 34 construction notices were distributed to the public between June 7, 2011 and January 31, 2013. As of January 31, 2013, the Metro ExpressLanes stakeholder database included 2,766 contacts.

During the month of January 2013, 34 media stories mentioned Metro ExpressLanes Program.

33 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

QUALITY ASSURANCE STATUS

ExpressLanes Program

 Attended coordination and ITS Detection Systems Meetings.

SAFETY STATUS ExpressLanes  Participated in planning sessions with Contractor Management to discuss safety/security related issues.  Monitored construction activities to ensure compliance with contract specifications.  Reviewed contractor submittals and work plans to ensure compliance.  Atkinson and their subcontractors reported 2,401 work hours and zero incidents for the month of February 2013 and three recordable incidents. The Recordable Incident Rate is 2.4 and the National Average is 3.8.

El Monte Transit Center  Monitored punchlist activities to ensure compliance with contract specifications.  Total project to date work hours are 271,299 and zero incidents.

34 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

THIRD PARTY AGREEMENT STATUS THIRD PARTY ADMINISTRATION AGREEMENTS

Agency Agreement Purpose Special Funding Type of Completion Type Provisions Amount Funds Status

Caltrans Cooperative/ Outline roles; Includes $6.9M Capital Executed Funding funding for Caltrans Agreement environmental Review/ document and Approval roadway Deadlines improvements; Funding for Design/Construction Oversight and balance of Environmental Document Caltrans Encroachment Capital Completed Permit Expo MOU Overcrossing at Capital Completed Adams to Exposition LADWP Electrical Drops by PB/IBI Capital Completed Service Application Only Agreement So Cal Edison Electrical Drops by PB/IBI Capital Completed Service Application Only Agreement City of Los Maintenance Adams Blvd. Draft Angeles Agreement Pedestrian Bridge agreement pending. City of Los Amendment Design Review for TBD Capital City signed Angeles to Master Adams Blvd. and the letter. Cooperative POC Working with Agreement the City in preparing SPP’s. County of Los Amendment Design Review TBD Capital Executed. Angeles to Master Cooperative Agreement SCRRA MOU Design Review and TBD Capital Executed. Support Services Agreement PUC Crossing Adams Blvd. Capital Executed. Application Crossing Approval Modifications Across the Expo Line

35 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

AGENCY NOISE AGREEMENTS

Agency Agreement Purpose Special Funding Type of Completion Type Provisions Amount Funds Status

City of Nighttime and Includes POC Capital Noise Los Angeles Weekend Bridge at Adams variance was Variance Blvd. granted by the Police Commission. City of Freeway Median City Variance N/A Monterey Park Area Not Required

City of Freeway Median City Variance N/A Rosemead Area Not Required

City of Freeway Median City Variance N/A El Monte Area Not Required

City of N/A No Work in N/A Baldwin Park this Jurisdiction

INTEROPERABILITY AGREEMENTS

Agency Agreement Purpose Special Funding Type of Completion Type Provisions Amount Funds Status

Bay Area Toll User Fee User Fee (Title 21 $0 Operating Executed Authority Agreement Interoperability)

Orange User Fee User Fee (Title 21 $0 Operating Executed County Agreement Interoperability) Transportation Authority San Diego User Fee User Fee (Title 21 $0 Operating With Association of Agreement Interoperability) SANDAG for Governments Signature TCA User Fee User Fee (Title 21 $0 Operating Executed Agreement Interoperability) 6/8/10

36 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

OPERATIONS AND MAINTENANCE AGREEMENTS

Agency Agreement Purpose Special Funding Type of Completion Type Provisions Amount Funds Status

Caltrans Cooperative Outline roles for $0 Operating Executed Agreement operations and maintenance of HOT Lanes Caltrans Joint Use Advisory Committee Operating In Process Agreement & Sec. 166 Definitions CHP MOU Dedicated Data $1,994,284 Operating Executed Enforcement: Collection CMAQ or Toll 3 officers and 2 Requirement Revenues officers DMV Requestor Allows access to None $250 Operating Executed Account DMV records 2/9/12 USDOT Tolling Comply w/USC 166 $0 Operating N/A Agreement TCA License FasTrak Logo None $1 Operating Executed Agreement License 6/8/10 MTA FSP Amend FSP Operating In Process Agreement Agreement for dedicated trucks MTA Collection Operating Not Started Agency Agreement MTA Transit Transit Court to None Actual Operating Executed Court provide Hearing Costs Toll Hearing Officers for Revenues Officers Administrative Review Hearings Foothill Transit MOU Non Revenue $0 Operating In Process Usage Agreement Torrance MOU Non Revenue $0 Operating Executed Transit Usage Agreement Gardena MOU Non Revenue $0 Operating Executed Municipal Bus Usage Agreement Lines Metro Bus MOU Non Revenue $0 Operating Executed Operations Usage Agreement OCTA MOU Non Revenue $0 Operating Executed Usage Agreement LADOT MOU Non Revenue $0 Operating Executed Commuter Usage Agreement Express USC MOU Non Revenue $0 Operating Executed Usage Agreement LAX Flyaway MOU Non Revenue $0 Operating Executed Usage Agreement LA County MOU Non Revenue $0 Operating Executed Sheriffs Usage Agreement (Buses Only) CHP MOU Non Revenue $0 Operating Executed Usage Agreement

37 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

OPERATIONS AND MAINTENANCE AGREEMENTS

Agency Agreement Purpose Special Funding Type of Completion Type Provisions Amount Funds Status

MTA Welcome Materials needed for Operating Completed Package new Customer Welcome Package MTA Retail Materials needed for Operating Completed Welcome Kit Retail Transponder Packaging

TRANSIT IMPROVEMENT AGREEMENTS

Agency Agreement Purpose Special Funding Type of Completion Type Provisions Amount Funds Status

Caltrans Cooperative Patsaouras Plaza TBD Capital Executed Agreement Caltrans MOU El Monte Transit N/A Capital Executed Center Caltrans MOU Harbor Transitway N/A Capital Executed April 2010 LADWP Electrical Drops by Application Capital Completed Service Only Agreement So Cal Edison Electrical Drops by Application Capital Completed Service Only Agreement

38 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

FUNDING AGREEMENTS

Agency Agreement Purpose Special Funding Type of Completion Type Provisions Amount Funds Status

Caltrans Cooperative Initial Study for $200,000 Capital Executed Agreement Environmental Prop C June 2009 Document Caltrans Funding I-110 Flyover PSR $7,395,790 Capital Executed Agreement and PA/ED 4/27/11 Foothill Transit LOA Purchase 10 42’ Data $7,461,000 Capital and Executed Agency buses and funding Collection FTA 5307 Operating August 2009 for 1 year operating Requirement $3,200,000 subsidy CMAQ Foothill Transit LOA – Purchase of 2 No Additional $7,461,000 Capital and Executed Agency Amendment additional buses Operating FTA 5307 Operating November #1 Subsidy $3,200,000 2009 CMAQ Foothill Transit LOA – Revise to include $7,461,000 Capital and Executed Agency Amendment specifics about Data FTA 5307 Operating November #2 Collection $3,200,000 2011 CMAQ Gardena LOA Purchase 2 Data $1,200,000 Capital and Executed Municipal Bus gas/hybrid buses Collection FTA 5307 Operating September Lines and funding for 1 Requirement $580,187 2009 year operating CMAQ subsidy Gardena LOA – Revise to include $1,200,000 Capital and Executed Municipal Bus Amendment specifics about Data FTA 5307 Operating January Lines #1 Collection $580,187 2012 CMAQ Torrance LOA Purchase 4 buses Data $2,800,000 Capital and Executed Transit and funding for 1 Collection FTA 5307 Operating July 2009 year operating Requirement $1,160,373 subsidy CMAQ Torrance LOA – Revise to include $2,800,000 Capital and Executed Transit Amendment specifics about Data FTA 5307 Operating January #1 Collection $1,160,373 2012 CMAQ Los Angeles LOA Intelligent Parking Data $15,000,000 Capital Executed Department of Management Collection CMAQ August 2009 Transportation Program Requirement Los Angeles LOA Install Transit Signal Data $1,000,000 Capital Executed Department of Priority in Downtown Collection CMAQ August 2009 Transportation Los Angeles Requirement Los Angeles LOA – Revise to include $15,000,000 Capital Executed Department of Amendment specifics about Data CMAQ 7/17/12 Transportation #1 Collection Los Angeles LOA – Revise to include $900,884 Capital Executed Department of Amendment specifics about Data 7/17/12 Transportation #1 Collection and add a camera at Alameda Southern LOA Construct 100 Data $4,480,000 Capital Executed California parking spaces and Collection FTA 5307 August 2009 Regional Rail expand platform at Requirement $1,120,000 Authority the Metrolink Prop C 10% Pomona Station Southern LOA – Revise to include $4,480,000 Capital Executed California Amendment specifics about Data FTA 5307 November Regional Rail #1 Collection $1,120,000 2011 Authority Prop C 10%

39 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

FUNDING AGREEMENTS

Agency Agreement Purpose Special Funding Type of Completion Type Provisions Amount Funds Status

USDOT MOU Award CRD funding Tolling $213.6 Capital Executed for I-10 and SR-210 Authority Million FTA April 2008 Demonstration Required by 5309 Project 10/15/08; Revenue Operations by 12/31/10 USDOT MOU – Shift from SR-210 to Tolling $210.6 Capital Executed Amendment I-110 and I-10 Authority Million FTA July 2008 #1 Demonstration Required by 5309 Project 10/15/08; Revenue Operations by 12/31/10 USDOT MOU – Administrative Capacity $210.6 Capital Executed Amendment Amendment/ Improvements Million FTA November #2 Reconcile MOU with by 12/31/08; 5309 2008 Tolling Authority Revenue Legislation Operations by 12/31/10 USDOT Letter Concurrence for Capital Concurred Agreement Schedule Extension February 2012

DBOM CONTRACTOR RESPONSIBILITY

Agency Agreement Purpose Special Completion Type Provisions Status

FCC License Needed for DBOM COMPLETE Agreement Operation of Fastrak Contractor to Transponders? secure TBD Maintenance Toll Electrical and DBOM Agreement Equipment Contractor to Maintenance secure TBD Facility Lease Needed for DBOM COMPLETE Customer Service Contractor to Center secure TBD Credit Needed for DBOM COMPLETE Card/Bank Customer Service Contractor to Processing Center secure Agreements TBD Website Needed for DBOM COMPLETE Hosting Customer Service Contractor to Agreement Center secure TBD Phone/ Needed for DBOM COMPLETE Internet Customer Service Contractor to Service Center secure Agreement TBD Mail Needed for DBOM COMPLETE Processing Customer Service Contractor to Agreement Center secure TBD Armored Car Needed for DBOM COMPLETE Service Customer Service Contractor to Agreement Center secure

40 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

CONTRACT STATUS

ExpressLanes Project Contract No.: PS0922102333 Atkinson Construction Status as of: January 31, 2013 Progress/Work Completed: Major Activities (In Progress): · All Dynamic Message Signs along I-10 corridor are operational. ∙ Added Sign panel replacement along I-10 continues. · These are being used for early announcements that we will open I-10 ∙ Continue with setting up Customer Service Center to support all systems and ExpressLanes on February 23rd and do not cross double white lines, operation functions in Gardena and El Monte Centers for I-10 opening. and price control during testing of the system. ∙ DBOM will continue to complete AS BUILT drawings for entire project. · I-110 ExpressLanes continues to build momentum ∙ Systems work along I-10 continues. · Working w/Caltrans and CHP to track incidents occurring on the ∙ Striping along I-10 is nearly complete. Freeway and how they are being handled. ∙ Continue installation of Earthcam Cameras on I-10 and I-110 corridors. · Testing and trip construction on the I-10 continued thru January. ∙ Testing of all toll sites, DMS and systems on I-10 continues. · Bios wale work along I-10 EB and Rosemead completed.. · Completed sign lighting for all sign structures along I-10 corridor. Major Activities Next Period: · Continue placing systems, loops, sensors, and earthcam cameras associated Areas of Concern: with 10 corridor. ∙ Complete striping along I-10 corridor. · Coordination of the DBOM contractor proposed construction with ∙ Continue installation of Earthcam Cameras. other Caltrans contractors on I-10 & I-605. . Testing of all toll sites,and DMS Systems continues on I-10 Freeway. · Any equipment failures.

Original Time Current Forecast Variance Baseline Extension Contract Completion Cur-Fcast Commencement 01/11/11 0 01/11/11 01/11/11 0

Completion 09/26/12 148 02/21/13 02/21/13 0

Final Acceptance 11/26/12 148 04/22/13 04/22/13 0

Schedule Summary: Cost Summary: $ In 000's Notice of Award 12/15/10 1. Award Value: 72,364 Notice to Proceed 01/11/11 2. Executed Modifications: 13,618 Original Contract Duration (CD) 685 3. Pending Change Orders: 4,647 Approved Time Extensions (CD) 148 4. Current Contract Value (1 + 2 + 3): 90,629 Current Contract Duration (CD) 833 5. Incurred Cost: 79,932 Data Collection/Demostration (CD) 365 6. Percent Incurred Cost: 88.2% Elapsed Time from NTP (CD) 751 Contract Elapsed Time Percent 90.2%

41 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

CONSTRUCTION PHOTOGRAPHS

42 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

CONSTRUCTION PHOTOGRAPHS

43 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

CONSTRUCTION PHOTOGRAPHS

44 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

CONSTRUCTION PHOTOGRAPHS

45 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report CONTRACTSTATUS

El Monte Transit Center Project Contract No.: C0958 Contractor: KPRS Construction Svcs Inc. Status as: December 28, 2012

Progress/Work Completed: Major Activities (In Progress): Terminal Terminal - All major work has been completed, punch list work, final clean-up, - Contract close out. landscaping. - Replace sewage pump/replacement w/larger trash pumps. - DB Contractor to use retail building for close-out. - The parking lot replacement work was completed and opened to the Retail/Transit Building public. - Close out.

Retail/Transit Building - Complete punch-list ongoing. Major Activities Next Period: - Work on close-out activities.

Areas of Concern: - Any major equipment failures would be disruptive at this point. - Gas detection system is still not 100%. - Supplier vendor Honeywell performing lab analysis of filters.

Original Time Current Forecast Variance Baseline Extension Contract Completion Cur-Fcast

Commencement 08/13/10 0 08/13/10 N/A

Completion 06/05/12 190 12/12/12 12/12/12 0

Schedule Summary: Cost Summary: $ In 000's Notice of Award 06/18/10 1. Award Value: 39,001 Notice to Proceed 08/13/10 2. Executed Modifications: 0 Original Contract Duration (CD) 660 3. Approved Change Orders: 9,421 Approved Time Extensions (CD) 165 4. Current Contract Value (1 + 2 + 3): 48,422 Current Contract Duration (CD) 825 5. Incurred Cost: 48,306 Elapsed Time from NTP (CD) 810 6. Percent Incurred Cost: 99.8% Contract Elapsed Time Percent 98.2%

46 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

CONSTRUCTION PHOTOGRAPHS

El Monte Lot B.

El Monte Lot B Temporary Terminal converted to parking lot..

47 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

CHRONOLOGY OF EVENTS

April 24, 2008 MOU w/USDOT for $210 million Grant Award (I-210/I-10).

July 23, 2008 CTC Eligibility Finding.

July 24, 2008 1st Amendment to MOU w/USDOT (Changes Demo Project from I-210/1-10 to I-110/I-10).

August 24, 2008 Preliminary Concept of Operations for I-10 and I-110.

September 28, 2008 State Tolling Authority Legislation Approved (Expires 1/15/13).

September 29, 2008 Metro/Caltrans certify funding available for ExpressLanes.

November 24, 2008 2nd Amendment to MOU w/USDOT (administrative changes).

December 4, 2008 ExpressLanes Project Inclusion in RTP approved.

December 22, 2008 Key Physical Capacity Improvements identified to USDOT.

January 14, 2009 FTIP approved: Amend #1 to the RTP and Amend 08-01 to 2008 RIP.

January 22, 2009 Public Outreach & Communications Plan approved by Metro Board.

February 17, 2009 RFIQ for Toll Systems Integrator released.

April 15, 2009 Preliminary Engineering begins for Electronic Toll Collection.

May 4, 2009 Short List of Toll Systems Integrator Firms completed.

June 22, 2009 Public Hearings for Toll Rates (6).

July 23, 2009 Toll Rates and Toll Policy adopted.

January 20, 2010 Metro Board Approved USDOT National Evaluation Plan.

February 12, 2010 Circulation of the Draft EIR/EA for the the I-10 and I-110.

March 9 & 10, 2010 Public hearings held for the draft EIR/EA for I-10 and I-110.

March 25, 2010 Metro Board Approved Low Income Commuter Assessment.

48 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

CHRONOLOGY OF EVENTS

April 7, 2010 CTC Authorizes Design-Build Authority for I-10 and I-110 HOT Lanes.

April 22, 2010 Metro Board Approved Administrative Account Fee Schedule.

April 28, 2010 EIR/FONSI for the I-10 and I-110 HOT Lanes is approved. FHWA Project Oversight Agreement Executed.

May 14, 2010 Environmental Assessment for the I-10 and I-110 HOT Lanes is approved.

June 7, 2010 DBOM RFP released.

June 16, 2010 Issued DBOM RFP Addendum #1.

June 30, 2010 CEQA Documents Approved for I-10 and I-110 HOT Lanes.

August 31, 2010 DBOM RFP Proposals Received.

Sept. 20, 2010 Received E-76 from FHWA for CMAQ Funds.

Sept. 22, 2010 CTC Approval of LONP for SLPP Funds. El Monte Transit Center Groundbreaking.

Sept. 29, 2010 State Tolling Authority extended until 1/15/15 (AB1244 Eng).

October 4, 2010 USDOT announced award of $47.75 million in Federal Discretionary Grant Funds for Division 13 Facility.

November 30, 2010 Notice of Intent to Award DBOM Contract Circulated to LACMTA Board of Directors.

December 9, 2010 LACMTA Board Approval Life of Project (LOP) Budget Increase.

December 16, 2010 DBOM Contract Award to Atkinson Contractors, LP.

January 11, 2011 Notice to Proceed (NTP) given to DBOM Contractor.

February 15, 2011 Formal Partnering Session held with Atkinson Contractors, Caltrans, FHWA, Metrolink and Metro.

July 6, 2011 Groundbreaking Ceremony for the Start of Construction of the ExpressLanes.

49 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

CHRONOLOGY OF EVENTS

July 25, 2012 Ribbon-Cutting Ceremony for the Opening of the Customer Service Center.

October 10, 2012 Ribbon-Cutting Ceremony for the Opening of the El Monte Transit Station.

November 10, 2012 Start of Revenue Operations for 110 ExpressLanes.

50 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

”GO LIVE” DEPLOYMENT SCHEDULE

Timeline: Scheduled Start of Operation ExpressLanes Program 2009 8/2009 (Actual) Bicycle Lockers @ Harbor Gateway Transit Center 2010 12/2010 (Actual) Sheriff’s substation @ Harbor Gateway Transit Center 12/2010 (Actual) Metrolink Pomona (North) Station Improvements 2011 6/2011 (Actual) Phase I Silver Line enhanced service starts – AM peak every 10 minutes 7/2010 (Actual) Lighting at Harbor Transitway Stations 8/2011 (Actual) Bus Stop Cutouts @ Slauson & Manchester Transitway Stations 10/2011 Community-basedVanpoolFormation Late 2011 – (Actual) New Buses received for I-10 El Monte Busway Late 2011 – (Actual) New Buses received for I-110 Harbor Transitway 2012 5/2012 LA ExpressPark-Phase I Begins 6/2012 (Actual) I-110 Adams Blvd. Flyover – Project Initiation Document/Project Study Report (PID/PSR)* 7/2012 LA ExpressPark-Phase II Begins 10/2012 LA ExpressPark-Phase III Begins, IPM Fully Operational 10/2012 (Actual) ElMonte Station Expansion 9/2012(Actual) AdamsBlvd.StreetWidening 11/2012 (Actual) Noise Pilot @ 37” Street Harbor Transitway Station 11/2012 (Actual) CCTV Installation @ Harbor Transitway Stations 11/2012 (Actual) I-110 ExpressLanes 2013 2/2013 I-10 ExpressLanes 2014 Summer Patsaouras Plaza Connector 3/2014 I-110AdamsBlvd.Flyover–EnvironmentalDocument (PAED)* * The dates reflected are completion dates. The Project is not fully funded for actual construction.

51 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

LA CRD PRE-DEPLOYMENT DATA COLLECTION Exogenous Factors

Silver Line Non-UPA Transportation System Changes Log

December 2009 Service begins, bus assignments split between D9 & D18

December 2009 Service begins on Long Term Detour via 39th St. to Figueroa due to Expo Line construction

June 2010 Travel time added for schedule adherence

September 2010 Service begins operating at adjacent El Monte Temporary Station during new station construction

December 2010 Long Term Detour cancelled, buses begin operating via 37th St. Station & Adams Blvd; buses begin running out of D9 only

December 2009 to Present – Selected Late El Monte Busway closed which resulted in Night Closures detouring via local streets to serve Cal State LA; LAC + USC not served during this time

February 2011 – Selected Late Night Harbor Transitway closed which resulted in Closures detouring via Figueroa between Harbor Gateway Transit Center & downtown LA

March 2011-Selected Late Night Closures Harbor Transitway Closed which resulted in detouring via Figueroa between Harbor Gateway Transit Center & Downtown LA. Weekend night closures occurred for the El Monte Busway.

May 31, 2011 Harbor Transitway closed which resulted in detouring via Figueroa between Harbor Gateway Transit Center & downtown LA

June 2011 From June 1-10, 2011, the Harbor Transitway had night closures which resulted in detouring via Figueroa between Harbor Gateway Transit Center & downtown LA and bus stations were not served on freeway platform.

52 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Silver Line Non-UPA Transportation System Changes Log

August 2011 Beginning August 7, 2011 through September 2012 all stations along the Harbor Transitway are closed from 10:00 pm – 6:00 am every night due to Metro ExpressLanes construction. An alternate shuttle runs along Figueroa St. from 4:00 am – 6:00 am every day. No freeway platforms are served during the closure period.

September 2011 Beginning September 26, 2011 through September 2012, the El Monte Busway will be closed every night from 10:00 pm – 5 am (westbound) and 10:00 pm – 6:00 am (eastbound) due to Metro ExpressLanes construction. During this time, LAC+USC Medical Center Station and Cal State LA Station will not be served. Passengers are suggested to take Line 70 or Metrolink.

June 2012 Weekday rush hour service increased resulting in entire line operating a peak hour frequency of 4 1/2 min between El Monte and Downtown LA and frequency of 81/2 min (from 5 min and 10 min, respectively).

September – December 2012 – USC Saturday USC football gamedays at the Football Coliseum will feature additional service for pre and post game movement, serving 37th St/USC Transitway Station.

Traffic related delays expected during these occurrences.

53 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Silver Line Non-UPA Transportation System Changes Log

October 2012 New El Monte Station grand opening. Temporary bus terminal closed.

Silver to Silver promotional fare program begins (pass reciprocity and lower cash fare on Foothill may shift some riders from Silver Line to Silver Streak).

Restroom construction at Artesia TC.

December 2012 Temporary bus terminal converted back to public parking lot. (437 parking spaces)

54 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Metrolink San Bernardino Line Transportation System Changes Log  Beginning on April 1st, after the April 1, 2011 Dodger’s first home game, Antelope Valley and San Bernardino line trains will depart Union Station at 11 p.m. Ticket Packages for a Dodger ticket and Metrolink roundtrip ticket will start at $20.

 Beginning on May 1st, San May 2011 Bernardino Line train schedules will change to connect with a train at Union Station arriving at the Burbank Airport in time for 7 a.m. airport departures.  Effective May 9th, San Bernardino Line will add four new trains and two new peak hour express trains that have a trip time of sixty minutes from San Bernardino to Union Station.

 Effective July 1st, Southern July 2011 Californians can buy a weekend pass to ride unlimited Metrolink trains for only $10. Unlimited weekend riding was added for monthly pass holders at no additional cost.  New 10 percent student discount added to one-way and roundtrip ticket.  New 7-Day Pass will be good seven consecutive days from purchase between a set origination and destination.  The 10-trip Ticket will be discontinued sometime in the fall of 2011. A significant amount of lost revenue is attributed to this type of ticket due to a failure to validate, resulting in fare evasion.

55 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Metrolink San Bernardino Line Transportation System Changes Log  San Bernardino Line closed in the November 2011 evening Wednesday, November 2nd between Fontana and Rancho Cucamonga due to a freight train derailment.  Due to an annual track maintenance project, Metrolink train service will be limited on the San Bernardino Line on November 5-6, 12-13 and 19-20.

 The 60 Freeway was closed in both December 2011 directions due to a tanker explosion, resulting in traffic being diverted to the I-10 and public transportation.

Schedule changes went into effect January January 2012 9 to coordinate with Amtrak’s schedule changes and improve reliability. San Bernardino Line – Monday thru Friday Service.  Train 319 and 331 will arrive later into Los Angeles  Train 333, 337 and 387 times have changed out of San Bernardino  Train 330, 32, 334 times have changed out of Los Angeles

Take the San Bernardino Line to the special August 31 – September 30, 2012 – LA Fairplex Station that drops you off right at County Fair Special Service the fair. A free shuttle will take you to the Yellow Gate to begin your fair adventure.

October 2012  New train schedules effective Oct. 1, 2012  Oct. 17, 2012 – reconstructed platform and three new tracks completed at Union Station

56 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Silver Line Ridership % HTW HTW % Month Average Change Average Average Average Change Weekday from Jan. Saturday Sunday Weekday from June Boardings 2010 Boardings Boardings Boardings2 2011

Dec. 20091 4,208 -- 969 1,335

Jan. 2010 6,612 -- 2,231 1,411

Feb.2010 6,974 5.47% 2,489 1,768

Mar.2010 7,170 8.44% 2,566 1,805

Apr.2010 7,173 8.48% 2,860 1,744

May2010 7,422 12.25% 2,758 1,895

Jun. 2010 7,227 9.30% 2,880 1,929

Jul. 2010 7,488 13.24% 2,815 2,045

Aug.2010 7,487 -- 2,811 1,919

Sept.2010 7,741 17.07% 2,788 2,018

Oct. 2010 8,118 22.78% 2,892 2,044

Nov.2010 7,522 13.76% 2,304 1,474

Dec. 2010 7,889 19.31% 2,430 1,788

Jan. 2011 8,049 21.73% 2,800 1,701

Feb.2011 8,304 25.59% 2,595 1,918

Mar.2011 8,540 29.15% 2,836 1,804

Apr.2011 9,086 29.16% 2,900 1,804

May2011 9,329 41.09% 3,004 1,952

Jun. 2011 8,892 34.48% 2,919 1,973 2,763 --

Jul. 2011 9,480 43.38% 3,746 2,294 3,372 22.04% 1Silver Line started operation on 12/13/09 so ridership estimate represents partial month. 2 Phase I Service changes began June 26, 2011 on the Harbor Transitway (HTW) portion of the Silver Line.

57 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Silver Line Ridership % HTW HTW % Month Average Change Average Average Average Change Weekday from Jan. Saturday Sunday Weekday from June Boardings 2010 Boardings Boardings Boardings2 2011

Aug. 2011 9,730 47.16% 3,825 2,517 3,429 24.10%

Sep.2011 10,414 57.50% 3,852 2,454 3,710 34.27%

Oct. 2011 11,234 69.90% 4,095 2,433 3,833 38.73%

Nov.2011 10,648 61.04% 3,615 2,243 3,706 34.13%

Dec. 2011 9,386 41.95% 3,473 2,443 3,410 23.42%

Jan. 2012 10,601 60.32% 3,815 2,512 3,796 37.39%

Feb.2012 11,089 67.71% 4,122 2,555 3,969 43.65%

Mar.2012 11,157 68.73% 3,752 2,285 4,164 50.71%

Apr.2012 11,241 70.00% 4,099 2,642 4,134 49.62%

May2012 11,419 72.70% 4,218 2,679 4,202 52.08%

June 2012 10,941 65.47% 4,064 2,806 4,110 48.75%

July 2012 11,206 69% 4,529 3,093 4,504 63.01%

Aug.2012 11,449 72.70% 4,441 3,168 4,633 67.68%

Sep.2012 12,197 84.47% 4,757 3,109 4,899 77.31%

Oct. 2012 13,765 108.18% 5,235 3,782 5,259 90.34%

Nov.2012 13,515 104.40% 4,832 3,437 5,641 104.16%

Dec. 20123 11,237 69.95% 4,570 3,104 5,025 81.87%

Jan.2013 12,422 87.87% 4,847 3,159 5,158 86.68% 1Silver Line started operation on 12/13/09 so ridership estimate represents partial month. 2 Phase I Service changes began June 26, 2011 on the Harbor Transitway (HTW) portion of the Silver Line. Ridership levels for the Harbor Transitway/I-110 corridor are distinguished as the amount of boardings between Artesia Transit Center and Downtown Los Angeles. For Northbound traffic, the last stop is Olympic & Figueroa. For Southbound, the first stop is 5th & Flower. Also, all ridership numbers are estimates and 3 For December 2012, ridership numbers are presented as weighted averages reflecting both the ½ month proceeding the shakeup and the ½ month after the shakeup when ridership typically declines due to school and work holidays. are, therefore, subject to minor discrepancies. 3 For December 2012, ridership numbers are presented as weighted averages reflecting both the ½ month proceeding the shakeup and the ½ month after the shakeup when ridership typically declines due to school and work holidays. 58 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

El Monte Transit Center Parking Data % Date of Count Time of Count Total Capacity Utilization Count Jan.12,2010 10:30AM 1,486 1,761 84.38% June10,2010 11:45AM 1,492 2,069 72.11% July8,2010 12:15PM 1,457 2,069 70.42% August12,2010 12:45PM 1,449 2,053 69.85% Sept.9,2010 10:45AM 1,449 2,053 70.58% October14,2010 12:30PM 1,187 1,196 99.25% Nov10,2010 4:15PM 1,138 1,196 95.15% Dec.9,2010 12:00PM 1,162 1,196 97.16% Jan.13,2011 1:15PM 1,188 1,196 99.33% Feb.10,2011 2:00PM 1,088 1,105 98.46% March10,2011 1:15PM 1,099 1,105 99.46% April27,2011 2:30PM 1,115 1,134 98.32% May12,2011 3:00PM 1,109 1,134 97.80% June9,2011 3:15PM 1,058 1,134 93.30% July28,2011 3:05PM 1,106 1,134 97.53% August11,2011 3:30PM 1,080 1,134 95.24% Sept.15,2011 2:30PM 1,092 1,134 96.30% Oct.26,2011 2:15PM 1,115 1,134 98.32% Nov.17,2011 1:10PM 1,121 1,134 98.85% Dec.15,2011 3:30PM 1,055 1,134 93.03% Jan.19,2012 3:15PM 1,012 1,134 89.24% Feb.9,2012 3:00PM 1,094 1,134 96.47% March8,2012 12:30PM 1,120 1,134 98.76% April12,2012 12:30PM 1,134 1,134 100% May22,2012 11:00AM 1,115 1,115 100% June21,2012 1:30PM 1,097 1,115 98% July19,2012 2:00PM 1,097 1,115 98.38% August9,2012 2:00PM 1,067 1,115 95.69% Sept. 2012 Data Unavailable Oct. 2012 Data Unavailable Nov. 7, 2012 11:30 AM 1,098 1,115 98.48% Dec. 6, 2012 11:30 AM 1,089 1,115 97.66% Jan. 22, 2013 11:30 AM 1,233 1,525 80.85% *Prior to the April 27, 2011 counts. Parking Lot C at El Monte was restriped, creating an additional 29 Parking spots. The new capacity at the El Monte Transit center Parking Lot is 1,134 spots. ** On May 22, 2012 the total parking capacity for El Monte Transit Center was recounted. The capacity changed due to El Monte Station construction activity.

59 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Harbor Transitway Center Parking Data % Date of Count Time of Count Total Capacity Utilization Count June10,2010 10:00AM 607 1,862 32.55% July8,2010 10:30AM 606 1,862 32.54% August12,2010 10:45AM 609 1,862 32.71% Sept.9,2010 2:15PM 607 1,862 32.60% Oct.14,2010 11:00AM 637 1,862 34.21% Nov.10,2010 1:30PM 636 1,862 34.16% Dec.9,2010 11:00AM 590 1,862 31.68% Jan.13,2011 11:00AM 655 1,862 35.18% Feb.10,2011 12:00PM 685 1,862 36.79% March10,2011 10:45AM 681 1,862 36.57% April27,2011 11:15AM 683 1,862 36.68% May12,2011 10:45AM 759 1,862 40.76% June9,2011 10:50AM 640 1,862 34.37% July28,2011 12:00PM 644 1,862 34.59% August11,2011 12:30PM 653 1,862 35.07% Sept.15,2011 11:30PM 713 1,862 38.29% Oct.26,2011 11:30AM 789 1,862 42.37% Nov.17,2011 11:30AM 719 1,862 38.61% Dec.15,2011 12:15PM 682 1,862 36.62% Jan.19,2012* 11:30AM 784 1,728 45.37% Feb.9,2012 11:30AM 830 1,728 48.03% March8,2012** 11:30AM 810 1,551 52.22% Apr.12,2012 10:30AM 760 1,551 49.00% May16,2012*** 2:30PM 850 1,633 52.05% June21,2012 11:15AM 810 1,633 49.60% July19,2012 11:45PM 780 1,633 47.76% August9,2012 11:30AM 774 1,633 47.39% Sept. 2012 Data Unavailable Oct. 2012 Data Unavailable Nov. 7, 2012 11:30 AM 917 1,862 49.25% Dec. 6, 2012 11:00 AM 866 1,613 53.69% Jan, 17, 2013 11:00 AM 851 1,513 52.75%

*During the January 19, 2012, a decrease in parking capacity was observed at Rosecrans. The Capacity was recalculated and found to be reduced from 342 to 207, decreasing the Harbor Transitway total parking capacity from 1,863 to 1,728. ** During the March 8, 2012, a decrease in parking capacity was observed at Artesia Transit Center due to construction materials. The capacity decreased by 177 parking spots, leaving Artesia Transit Center with 803 spots and the Harbor Transitway Total Parking Capacity with 1,551 spots. ***On May 16, 2012 the total parking capacity for the Harbor Transitway was recounted. The capacity changed due to construction activity for the metro ExpressLanes.

60 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

El Monte Transit Center Bike Parking Data % Date of Count Time of Count Total Capacity Utilization Count Nov.10,2010 4:15PM 25 56 44.64% Dec.9,2010 12:00AM 34 56 60.71% Jan.13,2011 1:15PM 21 56 37.50% Feb.10,2011 2:00PM 35 56 62.5% March10,2011 1:15PM 35 56 62.5% April27,2011 2:30PM 33 56 58.93% May12,2011 3:00PM 35 56 62.5% June9,2011 3:15PM 35 56 62.5% July28,2011 3:05PM 37 56 66.07% Aug.11,2011 3:30PM 35 56 62.5% Sept.15,2011 2:30PM 43 56 76.79% Oct.26,2011 2:15PM 41 56 73.21% Nov.17,2011 1:10PM 42 56 75% Dec.15,2011 3:30PM 36 56 64.28% Jan.19,2012 3:20PM 42 56 75% Feb.9,2012 3:15PM 30 56 53.57% March8,2012 3:00PM 30 56 53.57% April12,2012 12:30PM 44 56 78.57% May22,2012* 11:00AM 43 44 97% June21,2012 1:30PM 44 44 100% July 19, 2012 ** 2:00 PM 45 56 80.35% August9,2012 2:00PM 39 56 69.64% Sept. 2012 Data Unavailable Oct. 2012 *** Data Unavailable Nov. 7, 2012 11:00 AM 36 56 62.07% Dec. 6, 2012 11:30 AM 38 56 62.55% Jan. 22, 2013 12:15 PM 39 56 59.54% *On May 22, 2012 the bike parking capacity for the El Monte Transit Center was recounted. ** 6 Additional U-Racks were placed at El Monte Station prior to the July 19, 2012 counts, *** Due to staffing changes parking data is unavailable.

61 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Harbor Gateway Transit Center Bike Data % Date of Count Time of Count Total Capacity Utilization Count Oct.14,2010 11:00AM 1 16 6.25% Nov.10,2010 2:15PM 0 22 0% Dec.9,2010 11:15AM 1 22 4.54% Jan.13,2011 11:20AM 4 22 18.18% Feb.10,2011 12:00PM 4 22 18.18% March10,2011 11:00AM 2 22 9.09% April27,2011 11:15AM 7 22 31.82% May12,2011 10:45AM 1 22 4.54% June9,2011 11:30AM 2 22 9.09% July28,2011 12:30PM 3 22 13.64% Aug.11,2011 12:45PM 2 22 9.09% Sept.15,2011 11:35PM 2 22 9.09% Oct.26,2011 11:30AM 0 22 0% Nov.17,2011 11:30AM 0 22 0% Dec.15,2011 12:30PM 1 22 4.54% Jan.19,2012 11:30AM 3 22 13.64% Feb.9,2012 11:10AM 7 22 31.82% March8,2012 11:30AM 3 22 13.64% April12,2012 10:45AM 3 22 13.64% May16,2012 3:00PM 5 22 22.72% June21,2012 11:15AM 5 22 22.72% July19,2012 10:45PM 4 22 18.18% Aug.9,2012 11:30AM 5 22 22.72% Sept. 2012 Data Unavailable Oct. 2012 * Data Unavailable Nov. 7, 2012 11:30 AM 5 30 16.67% Dec. 6, 2012 11:00 AM 7 30 23.33% Jan. 17, 2013 11:00 AM 5 30 15.67% * Due to staffing changes parking data is unavailable.

62 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Pomona Metrolink Station Parking Data % Date of Count Time of Count Total Capacity Utilization Count Sept.16,2009 10:45AM 230 230 100% Oct.21,2009 10:30AM 230 230 100% Nov.18,2009 10:15AM 230 230 100% Dec.16,2009 10:45AM 230 230 100% Jan.20,2010 10:00AM 230 230 100% Mar.17,2010 10:15AM 230 230 100% Apr.21,2010 10:30AM 230 230 100% May19,2010 10:15AM 230 230 100% June9,2010 1:00PM 307 373 82.53% July15,2010 10:15AM 310 373 83.33% August12,2010 1:30PM 310 372 83.33% Sept.9,2010 11:45AM 310 372 83.33% Oct.14,2010 1:25PM 344 372 92.47% Nov.10,2010 3:40PM 271 372 72.85% Dec.9,2010 1:00PM 232 372 62.36% Jan.13,2011 12:20PM 291 372 78.23% Feb.10,2011 1:00PM 309 372 83.06% March10,2011 12:15PM 351 372 94.35% April27,2011 12:35PM 308 372 82.80% May12,2011 12:45PM 298 372 80.11% June9,2011 12:45PM 276 372 74.19% July28,2011 1:30PM 284 372 76.34% August11,2011 1:45PM 294 372 79.03% Sept.15,2011 12:30PM 309 372 83.06% Oct.26,2011 1:40PM 321 372 86.29% Nov.17,2011 12:35PM 315 372 84.67% Dec.15,2011 1:20PM 298 372 80.11% Jan.19,2012 12:30PM 323 372 86.82% Feb.9,2012 12:30PM 317 372 85.21% March8,2012 12:45PM 347 372 93.27% April12,2012 11:45AM 322 372 86.55% May22,2012 12:00PM 358 372 96.23% June21,2012 2:05PM 302 372 81.18% July19,2012 11:45PM 291 372 78.22% August9,2012 12:45PM 305 372 81.98% Sept. 2012 Data Unavailable Oct. 2012* Data Unavailable Nov. 8, 2012 1:00 PM 334 372 89.78% Dec. 6, 2012 11:30 AM 336 372 90.32% Jan. 22, 2013 11:15 AM 342 372 91.93% * Due to staffing changes parking data is unavailable. 63 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Metrolink San Bernardino Line Ave. Weekday Inbound Ridership % Change from Date Boardings Previous Month June 2009 6,264 -- July 2009 6,185 -1.26% August2009 5,969 -3.49% September2009 6,028 0.99% October2009 6,122 1.56% November2009 5,915 -3.38% December2009 5,501 -7.00% January2010 5,750 4.53% February2010 5,762 0.21% March 2010 5,959 3.42% April2010 5,911 -0.81% May2010 5,854 -0.97% June 2010 5,797 -0.98% July 2010 5,510 -4.95% August2010 5,381 -2.40% September2010 5,595 3.98% October2010 5,720 2.23% November2010 5,635 -1.48% December2010 5,069 -11.16% January2011 5,646 11.38% February2011 5,730 1.49% March 2011 5,962 4.04% April2011 6,220 4.33% May2011 6,288 1.09% June 2011 6,060 -3.63% July 2011 6,134 1.22% August2011 6,069 -1.06% September2011 5,984 -1.04% October2011 5,886 -1.64% November2011 5,663 -3.79% December2011 5,660 -0.001% January2012 6,107 7.90% February2012 6,256 2.44% March 2012 6,173 -1.33% April2012 6,134 -0.63% May2012 6,293 2.59% June 2012 6,087 -3.27% July 2012 5,899 -3.09% August 2012 5,986 1.47% September2012 6,165 2.99% October2012 6,441 4.48% November2012 6,191 -3.88% December2012 5,484 -11.41%

64 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Metrolink San Bernardino Line Ave. Weekday Inbound Ridership % Change from Date Boardings Previous Month January2013 5,926 8.06%

65 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Cumulative Media Articles Date Article Publication or Blog How to Make Sure Your January/February Carpooling Employees Ride Toll- CommuteSmart News 2013 Issue Free on ExpressLanes January/February Carpool Loyalty Program to CommuteSmart News 2013 Issue award gift cards monthly Los Angeles is on the Express Inside Seven (Caltrans, District 7 Monthly January, 2013 Lane to Congestion Newsletter) Management South Bay Environmental Services Center - January, 2013 L.A. Metro ExpressLanes South Bay Cities Council of Governments Newsletter ExpressLanes Debuts in Los Parsons Brinckerhoff Bulletin - Volume 45, January, 2013 Angeles January 2013 ExpressLanes Will Open on the 1/30/2013 FAST Newsletter I-10 Freeway on February 23rd! Weekly Transit Coalition 1/29/2013 The Transit Coalition Newsletter eNewsletter, Volume 9, Issue 5 FasTrak Express Lanes on I-10 1/29/2013 Pasadena Patch Freeway to Debut Feb. 23 FasTrak Express Lanes on I-10 1/28/2013 Glendora Patch Freeway to Debut Feb. 23 Metro: Toll Lanes to Begin on 10 San Gabriel Valley Tribune, Pasadena Star 1/28/2013 Freeway on Feb. 23 News, and Whittier Daily News Vehicles With a Transponder Can Use the ExpressLanes, 1/26/2013 The World Journal Otherwise a $341 Ticket Could Be Issued The Metro ExpressLanes on the 1/26/2013 I-10 Freeway Will be Opened on Sing Tao Daily the 23rd Next Month ExpressLanes on I-10 Freeway 1/25/2013 The China Press to Open Soon Low-Income Families Can Get 1/25/2013 Discount on Metro The China Press ExpressLanes ExpressLanes to Open on I-10 1/25/2013 Freeway; Travel Without FasTrak LA Chinese Daily News Transponder Will Be Cited Monthly Fee For Metro FasTrak 1/24/2013 Transponders on Chopping Block

66 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Cumulative Media Articles Date Article Publication or Blog Metro ExpressLanes to Debut Along 14-miles of the I-10 San 1/24/2013 Metro Media Release Bernardino Freeway on Saturday, February 23 ExpressLanes to Open on 10 1/24/2013 The Source Blog Freeway on Feb. 23 Here's the Agenda for First Full Metro Board of Directors 1/24/2013 The Source Blog Meeting of 2013; Buenas Manana and Bon Appetit! Early Notes from Metro Board Meeting: Update on 1/24/2013 ExpressLanes Speed, Metrolink The Source Blog TAP-Enabled Tickets, Airport Metro Connector Metro Board Takes No Action on 1/24/2013 Motion to Eliminate Maintenance The Source Blog Fee For ExpressLane Accounts El Programa ExpressLanes de Metro se Inaugura el 23 de 1/24/2013 El Pasajero Blog Febrero en la Autopista San Bernardino I-10 More Toll Lanes Are Coming to 1/24/2013 LAist Los Angeles County Next Month Weekly Transit Coalition 1/22/2013 The Transit Coalition Newsletter eNewsletter, Volume 9, Issue 4 Metro Responds to FasTrak Criticism: Removing Monthly Fee Opens Budget Hole, 1/17/2013 Streetsblog LA Encourages People Outside L.A. County to Purchase, Not Use, Transponders Here's the Metro Staff Report Explaining the FasTrak Account 1/16/2013 The Source Blog Maintenance Fee for the ExpressLanes 1/16/2013 Priced Managed Lane Guide FHWA Reporte de Metro Que Explica La Cuota De Mantenimiento De La 1/16/2013 El Pasajero Blog Cuenta FasTrak De Los Carriles ExpressLanes (Un)Freeways: TEDx Tackles 1/13/2013 Curbed LA Congestion Pricing 1/5/2013 Gold Line May Open Next Year Arcadia's Best

67 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Cumulative Media Articles Date Article Publication or Blog El Museo de Caltrans Presentara 1/4/2013 el Programa ExpressLanes de El Pasajero Blog Metro Roadshow: Can I Get One of 1/4/2013 Those Los Angeles-Style Santa Cruz Sentinel FasTrak Transponders? SGV Commuters Encouraged to 1/3/2013 Baldwin Park Patch Get their FasTrak Transponders Caltrans Museum to Feature 1/2/2013 Caltrans News Release Metro ExpressLanes Display January Service Council 12/30/2012 The Source Blog Meetings December, 2012 Metro ExpressLanes Now Open CommuteSmart News Reader Poll Results: Expo Line 12/28/2012 Opening Was the Big Story of The Source Blog 2012! Viaje Con Metro Motion a Hollywood, A Los Carriles 12/28/2012 El Pasajero ExpressLanes y a Los Angeles del Futuro Roadshow: New FasTrak 12/28/2012 transponders in Southern San Jose Mercury News California Are Fancier Than Ours Ride Along with Metro Motion: 12/27/2012 Winter Edition Takes In Hollywood, The Source Blog ExpressLanes, and Future L.A. Bicycle People Make the 12/22/2012 Pasadena Star News Connection ExpressLanes Are Open on the I- 12/21/2012 110 Freeway and Will Open on the FAST Enewsletter I-10 Freeway in 2013! 12/20/2012 Toll Road Irony is Not Funny PublicCEO.com What was the Biggest 12/20/2012 Transportation Story of 2012? The Source Blog Take Our Poll! FasTrak on New 110 12/18/2012 The Toll Roads Website ExpressLanes Money-Making, Congestion- 12/18/2012 Reducing Express Lanes Spread Neon Tommy on California Freeways 12/17/2012 Urban Scrawl Los Angeles Downtown News

68 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Cumulative Media Articles Date Article Publication or Blog Yaroslavsky Submits Motion to 12/13/2012 Eliminate Maintenance Fee on The Source Blog ExpressLanes Supervisor Yaroslavsky Presenta Mocion Para Eliminar Cuota de 12/13/2012 El Pasajero Mantenimiento del Proyecto ExpressLanes Smartphone App Helps Drivers Find 12/12/2012 Blogdowntown Available Parking Spaces in DTLA Weekly Transit Coalition eNewsletter, 12/11/2012 The Transit Coalition Newsletter Volume 8, Issue 49 As Connecticut's Transit Funds 12/11/2012 Shrink, the Call for Tolls Grows Transportation Nation Louder Editorial: See Whether Toll Lanes 12/11/2012 The Sun, San Bernardino and the Inland Empire Work Before Planning More ParkMe Launches Real-Time Solution for Los Angeles County 12/11/2012 Business Wire Drivers Who No Longer Need Luck to Find a Parking Spot Opinion: Stop New Freeway Toll 12/10/2012 San Bernardino Sun Lanes Transportation Headlines, Friday, 12/7/2012 The Source Blog Dec. 7 Our View: Give Toll Road Drivers a 12/6/2012 Pasadena Star News Break Carriles De Cuota ExpressLanes: 12/6/2012 El Pasajero Testimonios de los Usuarios Transportation Headlines, 12/5/2012 The Source Blog Wednesday, Dec. 5 San Bernardino County: Toll Lanes 12/5/2012 Press Enterprise Considered for I-10 Controversial HOT Lanes Spread 12/5/2012 First Coast News Nationally Encuentre Regalos Navidenos 12/4/2012 El Pasajero Unicos Con La Ayuda De Metro Toll Lanes Create 'Another Option' to 12/4/2012 USA Today Avoid Traffic Controversial HOT Lanes Spread 12/4/2012 USA Today Nationally Weekly Transit Coalition eNewsletter, 12/4/2012 The Transit Coalition Newsletter Volume 8, Issue 48

69 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Cumulative Media Articles Date Article Publication or Blog Editorial: Drivers Were Confused By 12/2/2012 County's First Toll Road; Metro Daily News Needs to Give Them a Break November/ December MailBox: Not So Fast… Westways 2012 Issue November/ Events: Metro ExpressLanes Open December CommuteSmart News Nov. 10 2012 November No Free Rides Los Angeles Magazine 2012 Issue 12,000 Drivers Find After New L.A. 11/29/2012 The Orange County Register Toll Lanes Open Metro ExpressLanes Program Gears 11/29/2012 Mobility 21 - Forward Motion Up for Debut on I-10 in Early 2013 12,297 Tickets Already For Improper 11/28/2012 Curbed LA Use of the 110 Toll Lanes I-110 Metro ExpressLanes Open in 11/27/2012 HubDOT Los Angeles Thousands Hit With Toll Lane 11/27/2012 Supervisor Zev Yaroslavsky's Web Page Citations 11/27/2012 El Monte Bus Station Grand Opening Youtube (http://www.youtube.com/wat Half CA/I-110 Express Lane Users 11/26/2012 Are Solo Driver Buy-Ins, Tolls Toll Roads News Average 54 Cents/Mile Transportation Headlines, Tuesday, 11/20/2012 The Source Blog Nov. 20 Metro Introduces Toll Lane to 110 11/20/2012 The Daily Bruin Freeway Here's What Metro Will Do With Its 11/20/2012 Curbed LA New Toll Lane Money First Electronic Metro ExpressLanes Display Message Boards Go Live 11/19/2012 Along 14-Miles of the I-10 San Metro Media Release Bernardino Freeway Set to Debut in Early 2013 50K Transponders Issued So Far; Preparations Underway to Launch 11/19/2012 The Source Blog ExpressLanes on 10 Freeway in Early 2013 Transportation Headlines, Monday, 11/19/2012 The Source Blog Nov. 19

70 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Cumulative Media Articles El Primer Cartel Electronico de Metro ExpressLanes Se Predera En La 11/19/2012 El Pasajero Blog Autopista San Bernardino Esta Semana 2nd Set of L.A. Toll Lanes May Open 11/19/2012 LA Times Blog - L.A. Now On 10 Freeway By Late January How L.A.'s New Freeway Toll Lanes 11/19/2012 LA Times Works 11/17/2012 Doing the Math on 'Lexus Lanes' LA Times Toll Unsettles Los Angeles Motorists 11/16/2012 Used to 'Free' in Freeways The 110 Bumps the 91 for Highest 11/15/2012 The Orange County Register Peak Toll Rate Weekly Transit eNewsletter, Volume 11/14/2012 The Transit Coalition Newsletter 8, Issue 45 Transportation Headlines, 11/14/2012 The Source Blog Wednesday, Nov. 14 L.A.'s First Freeway Toll Lanes Off to 11/13/2012 LA Times Blog - L.A. Now Smooth Start, Officials Say ExpressLanes Quietly Open on I-110, 11/13/2012 Media Finds "Grumbling"…But Not Streetsblog LA Hysteria Transportation Headlines, Tuesday, 11/13/2012 The Source Blog Nov. 13 Metro ExpressLanes Flowed Well on 11/13/2012 The Source Blog 110 on Tuesday Morning Se Inicia El Cobro De Una Cuota En 11/13/2012 Carriles Del Proyecto ExpressLane The Source Blog De La Autopista 110 11/12/2012 Los Angeles Adopts Congestion Toll USC ATUN Annenberg TV News CHP to Begin Enforcing New Toll 11/12/2012 KTLA.com Lanes on 110 Freeway How L.A.'s First Toll Road Could 11/12/2012 KCET.com Help Reduce Traffic The Toll Lanes on the 110 Freeway 11/11/2012 Open, But Residents Have Polarized Sing Tao Daily Opinions Our View: Are Toll Lanes a Slippery San Gabriel Valley Tribune; Long Beach Press- 11/11/2012 Slope? Telegram

71 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Cumulative Media Articles L.A.'s First Toll Lanes Open; Trips 11/11/2012 LA Times Blog - L.A. Now Cost Up to $15.40 L.A. County Toll Lanes Get Smooth 11/11/2012 LA Times Blog - L.A. Now Start, Despite Some Grumbling Single Drivers May Use HOV Lane 11/11/2012 89.3 KPCC For Fee The Toll Lanes on the 110 Freeway 11/10/2012 Sing Tao Daily Opened Today The Toll Lanes on the 110 Freeway 11/10/2012 The World Journal Open, and Residents Can Apply Now That's HOT! High Occupancy Toll 11/10/2012 CBS Los Angeles Lanes Open On 110 Freeway Associated Press; San Luis Obispo Tribune; LA Charges Into New Territory with Seattle Post-Intelligencer; San Francisco 11/10/2012 Express Lanes Chronicle; San Jose Mercury; Tulsa World; KRLA 870; Erie Times-News New 110 Freeway ExpressLanes Set Pasadena Star News; San Bernardino Sun; Daily 11/10/2012 to Open at 10 p.m. Saturday Bulletin; Los Angeles Daily News Los Angeles Prepares City's First Toll 11/10/2012 Woodland Hills Patch Road Toll Lanes Now Open on 11-mile 11/10/2012 LA Times Blog - L.A. Now Stretch of 110 Freeway 11/10/2012 110 Freeway Toll Lanes Open Redondo Beach Patch And So it Begins: ExpressLanes - Los Angeles County's First Foray Into 11/10/2012 The Source Blog Congestion Pricing - Open Saturday Night on 110 Freeway! ExpressLanes Set to Debut on 110 11/10/2012 Freeway on Saturday Night, Weather The Source Blog Permitting Metro ExpressLanes Set to Open Saturday, Nov. 10; Congestion 11/9/2012 Reduction Demonstration Project to Metro Media Release Ease Commutes on 110 Harbor Freeway The First Express Toll Lanes Will 11/9/2012 The World Journal Open on This Saturday Opening of Toll Lanes on 110 Harbor 11/9/2012 Freeway Delayed Until Saturday San Gabriel Valley Tribune Night, Possibly Sunday Morning L.A. County Enters Era of Freeway 11/9/2012 Toll Lanes

72 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Cumulative Media Articles High Occupancy Toll Lanes Expected 11/9/2012 CBS Los Angeles to Open on 110 Freeway New Toll Lanes Open This Weekend 11/9/2012 Fox Los Angeles on The 110 Los Angeles Metro Express Lanes - 11/9/2012 Victor Caballero Blog Will it Work? Los Angeles Gets Its First Express 11/9/2012 Active Rain Blog Toll Lanes What You Need to Know About L.A.'s 11/9/2012 First Toll Lanes Opening This LAist Weekend 110 Freeway Toll Lanes Opening 11/9/2012 Redondo Beach Patch Delayed Metro ExpressLanes to Relieve 11/9/2012 Congestion By Allowing Single Riders Bikes and Hikes LA Blog on Toll Lanes Lexus Lanes Coming to Los Angeles' 11/9/2012 Blogging Los Angeles Harbor Freeway 1st Toll Carpool Lanes to Open in 11/9/2012 ABC7.com Los Angeles County Weather Blamed for Delay in 11/9/2012 Opening Harbor (110) Freeway Daily Breeze ExpressLanes Weather Blamed for Delay in 11/9/2012 Opening Harbor (110) Freeway Contra Costa Times ExpressLanes 110 Freeway Toll Lanes to Debut 11/9/2012 KTLA.com This Weekend Metro ExpressLanes se Inaugura el 11/9/2012 El Pasajero Blog 10 De Noviembre Puntos Importantes Para Recordar 11/9/2012 El Pasajero Blog Sobre Los ExpressLanes Video of Friday's ExpressLanes 11/9/2012 The Source Blog Media Event MAP: 110 Freeway "FasTrak" 11/9/2012 ExpressLanes Take a Toll on Drivers 89.3 KPCC Starting Nov. 10 ]-[11/9/2012 Metro Express Lanes KFI AM 640 - The Jon and Ken Show Youtube 11/9/2012 Metro ExpressLanes Begin Nov. 10! (http://www.youtube.com/watch?v=9Xc7MAjXX9Y) 11/8/2012 ExpressLanes Basics Reviewed The Source Blog

73 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Cumulative Media Articles Opening of Toll Lanes on 110 Harbor 11/8/2012 Freeway Delayed Until Saturday Pasadena Star News Night, Possibly Sunday Morning Express Lanes on 110 Freeway to 11/8/2012 Los Angeles Times - L.A. Now Open Saturday ExpressLanes to Bring "Congestion 11/8/2012 NBC Los Angeles.com Pricing" to Harbor Freeway 11/8/2012 Metro ExpressLanes Central City Association Newsletter Weekly Transit eNewsletter, Volume 11/7/2012 The Transit Coalition Newsletter 8, Issue 44 Metro Debuts New ExpressLanes on 11/6/2012 KCAL-TV Channel 9 110 Freeway Transportation Headlines, Tuesday, 11/6/2012 The Source Blog November 6 Preview of November Service 11/6/2012 The Source Blog Council Meetings ExpressLanes on the I-110 Open on 11/6/2012 UCLA Transportation Website Saturday Pay Lanes: A First in L.A. County Will 11/6/2012 Daily Breeze Start Saturday Everything You Need to Know About 11/6/2012 Curbed LA New 110 and 10 Toll Lanes : How to Drive in LA: 11/6/2012 Zerox Eases Traffic, Parking with Equities.com Innovative Data Management System Reuniones de los Concejos de 11/6/2012 El Pasajero Blog Servicios de Metro para Noviembre The First Express Toll Lanes Will 11/5/2012 The World Journal Open on This Saturday Congestion Pricing - Toll Lanes - 11/5/2012 LA Observed Come to LA Freeways High Occupancy Toll (HOT) ExpressLanes to Open on 110 11/5/2012 Los Angeles County Sheriff's Department Website Freeway on Sat, Nov. 10 - Metro Los Angeles Metro ExpressLanes Arrive on I-110 11/5/2012 Supervisor Don Knabe Weekly E-Newsletter Freeway This Week Transportation Headlines, Monday, 11/5/2012 The Source Blog Nov. 5 How Do They Do That? 11/5/2012 The Source Blog ExpressLanes Transponders

74 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Cumulative Media Articles ExpressLanes to Open November 11/5/2012 FAST Newsletter 10th - Get Your Transponder Now! Ready to Pay $1.40 A Mile For Faster 11/5/2012 LA Weekly Lanes on the 110 Freeway? 110 Freeway Toll Lanes to Debut 11/5/2012 KTLA.com Next Saturday Como Determinan Los 11/5/2012 Transpondedores Quienes Viajan En El Pasajero Blog Los ExpressLanes? Los Angeles To Open I-110 Metro 11/5/2012 ExpressLanes Saturday Nov 10, Toll Roads News Dynamic Pricing Tested Monday Metro Debuts New Express Lanes on 11/5/2012 CBS Los Angeles 110 Freeway ExpressLanes on 110 Freeway to 11/4/2012 ABC7.com Open Soon for Solo Drivers Pay Lanes: A First in L.A. County Will 11/3/2012 Daily News Start Saturday 11/3/2012 Pay Lanes: How It Works San Gabriel Valley Tribune 11/3/2012 Pay Lanes: How It Works Daily News Chat Live Today on ExpressLanes 11/2/2012 The Source Blog From Noon to 1 p.m. Live Chat Transcripts On 11/2/2012 The Source Blog ExpressLanes is Posted! How to Enter and Exit From 11/2/2012 The Source Blog ExpressLanes HOT Lanes Are Heating Up in Los 11/2/2012 CityWatch Angeles Como Entrar y Salir De Los 11/2/2012 El Pasajero Blog ExpressLanes Nine Days and Counting Until 11/1/2012 The Source Blog ExpressLanes Open on 110 Freeway 11/1/2012 Life in the ExpressLanes Supervisor Zev Yaroslavsky's Web Page ch?v=OsmfoKYCVf0&feature=youtu.be)

75 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Cumulative Media Articles Date Article Publication or Blog Fall 2012 Metro ExpressLanes Feature Metro Motion October 2012 ExpressLanes to Open on I-110 CommuteSmart News Toll Lanes Coming Soon to 110 Freeway; First in 10/1/2012 LA County Blogdowntown.com Metro ExpressLanes and Carpooling: The Facts, 10/2/2012 the Benefits and More LA Streetblog Weekly Transit Coalition eNewsletter, Volume 8, The Transit Coalition 10/2/2012 Issue 39 Newsletter Students Say They Will Not Use New Toll Lanes 10/7/2012 on I-110 Weekly Transit Coalition eNewsletter, Volume 9, The Transit Coalition 10/9/2012 Issue 40 Newsletter 10/9/2012 New El Monte Station Open Sunday Baldwin Park Patch Metro and Elected Officials Dedicate New State-of- the-Art El Monte Station Marking Completion of 10/10/2012 Construction and Start of Passenger Service Metro Media Release Metro and Elected Officials Dedicate New State-of- 10/10/2012 the-Art El Monte Station The Source Blog 10/10/2012 Dedication of New El Monte Station Metro Media Alert New $60 million El Monte Bus Station Unveiled, 10/10/2012 Opens to the Public Sunday Whittier Daily News ExpressLanes Van Out and About and Perhaps 10/11/2012 Coming to a Neighborhood Near You The Source Blog Mel, the Metro ExpressLanes Van, Brings FasTrak Accounts to Commuters with Appearances at College Campuses, Government Offices and 10/15/2012 Events Metro Media Release Metro ExpressLanes Live Internet Chat at Noon, 10/18/2012 Friday, Nov. 2 The Source Blog 10/24/2012 Special Guest Appearance by MEL Tomorrow! The Source Blog Today’s Special Appearance by MEL Cancelled 10/25/2012 But Human Reps will be Assisting Instead The Source Blog Toll Lanes Arrive in Los Angeles County Supervisor Don Knabe 10/29/2012 November 10 Weekly E-Newsletter 10/29/2012 110 Freeway Toll Lanes to Open Nov. 10 Redondo Beach Patch 10/29/2012 HOT Lanes Are Heating Up in Los Angeles The Frying Pan

76 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Cumulative Media Articles Date Article Publication or Blog Harbor (110) Freeway ExpressLanes Opening 10/30/12 Date Nears Daily Breeze Metro Reaches Milestone of Issuing 20,000 FasTrak Transponders Before the Nov. 10 ExpressLanes Opening on the 110 Harbor 10/30/12 Freeway Metro Media Release 10/31/12 Reminder: ExpressLanes Live Chat this Friday The Source Blog Do You Have Transponder Yet? Metro 10/31/12 ExpressLanes Live Internet Chat this Friday Metro Media Release 10/31/12 110 Freeway Toll Lanes Open Nov. 10 Beverly Hill Patch More Than 20,000 Transponders Pre-Issued for LA Times Blog – L.A. 10/31/12 110 Freeway Now November 10 the ExpressLanes Open and a New 10/31/12 Way of Looking at Getting Around Starts Examiner.com 10/31/12 110 Freeway Toll Lanes Open Nov. 10 Beverly Hill Patch Governor Oks Free Toll Lane Access for Clean 9/28/2012 Cars The Sacramento Bee Will Metro Rue the Day It Decided to Require 9/27/2012 Transponders for ExpressLanes Access LA Streetsblog 9/26/2012 Share the Ride and Get the Chance to Win Prizes The Source Blog Congestion Pricing Could Be a Solution to the Gas The Transit Coalition 9/26/2012 Tax Problem… Newsletter Metro to Open New El Monte Station to the Public 9/26/2012 on Sunday, Oct. 14 The Source Blog South Bay Environmental Services Center – South Bay Cities Council of Los Angeles County’s First ExpressLanes Project Governments 9/20/2012 to Debut on Saturday, Nov. 10 Newsletter 9/19/2012 Rideshare News The Source Blog Golden Pylon Awards: Traffic Reporters Get USC Football 9/19/2012 Some Love from Southland Transit Agencies Newsletter 9/19/2012 Freeway ExpressLanes Daily Breeze ExpressLanes to Open November 10th –You’re 9/18/2012 Your Transponder Now! FAST Newsletter 9/18/2012 The 110 Harbor Freeway Gets a HOT Makeover LAist L.A.’s First Toll Lanes to Open Nov. 10 on 110 Los Angeles Times- 9/18/2012 Freeway L.A. Now

77 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Cumulative Media Articles Date Article Publication or Blog Harbor (110) Freeway ExpressLanes to Open on 9/18/2012 Nov. 10 Daily Breeze Harbor (110) Freeway ExpressLanes to Open on San Jose Mercury 9/18/2012 Nov. 10 News ExpressLanes to Open on 110 Freeway on Nov. 9/18/2012 10 The Source Blog Los Angeles County’s First ExpressLanes Project 9/18/2012 to Debut on Saturday, Nov. 10 Metro Media Release 9/12/2012 5,000 Motorists Sign Up for Freeway Transponder Daily Breeze 9/12/2012 5,000th Account Opened for Metro ExpressLanes The Source Blog Metro ExpressLanes Reaches Significant Milestone with the Opening of the 5,000th FasTrak 9/12/2012 Account for the Congestion Reduction Project Metro Media Release Eat, Shop and Play Locally During Carmageddon II 9/11/2012 Weekend Sept. 29-30 The Source Blog L.A. Business This Week – A Weekly Automobile Club of Southern California Now Update from the L.A. 9/6/2012 Providing Transponders Area Chamber September/October 2012 Before You Sign Up for FasTrak, Read This… CommuteSmart News 9/1/2012 More on ExpressLanes Daily Breeze September, 2012 ExpressLanes Transponders Westways 8/27/2012 ExpressLanes Transponders Daily Breeze Metro ExpressLanes Transponders Now Available at Auto Club Branches Throughout Southern Los Angeles City and 8/21/2012 California Press AAA Now Offering ExpressLanes Transponders with 20 Percent Discount on Initial Tolls for Auto 8/20/2012 Club Members The Source Metro ExpressLanes Transponders Now Available at Auto Club Branches Throughout Southern 8/20/2012 California Metro media release Los Angeles ExpressLane Transponders Now 8/17/2012 Available at Auto Club Branches AAA Media Release City of LA Personnel Department Commute August, 2012 Metro ExpressLanes Info Bus At City Hall Options Newsletter USC Football 8/15/2012 Metro ExpressLanes Newsletter 8/2/2012 Freeway ExpressLanes Daily Breeze

78 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Cumulative Media Articles Date Article Publication or Blog Metro and Caltrans Announce Availability of Metro ExpressLanes FasTrak® Transponders for Fall Mobility 21 - Forward 7/31/2012 Debut Motion Metro Announces ExpressLanes Customer Walk- 7/27/2012 In Center in Gardena LA Sentinel Neon Tommy - USC Metro Unveils FasTrak Devices for Freeway Toll Annenberg Digital 7/26/2012 Lanes News Get in the ExpressLane: This ExpressLanes 7/26/2012 Congestion Pricing Thing Is… Curbed LA LA Commuters to Need Transponders for 7/26/2012 ExpressLanes ABC7.com Device Unveiled to Allow Motorists to Use Freeway 7/26/2012 Toll Lanes LA Times, L.A. Now ExpressLanes Equipment for Access to Harbor, 7/25/2012 San Bernardino Freeway Toll Lanes Goes on Sale Socalnews.com Metro and Caltrans Announce Availability of FasTrak Transponders for ExpressLanes Project 7/25/2012 on 10 and 110 Freeways The Source Blog Ribbon-Cutting Opens the Metro ExpressLanes 7/25/2012 Walk-In Customer Center The Source Blog 7/25/2012 Ribbon-Cutting Ceremony in Gardena The Source Blog Metro ExpressLanes FasTrak Customer Service 7/25/2012 Center Ribbon Cutting Ceremony Program The Source Blog Ya están disponibles los transpondedores para los 7/25/2012 nuevos Carriles Exprés en las autopistas 110 y 10 El Pasajero Blog Metro and Caltrans Announce Availability of Metro ExpressLane FasTrak® Transponders for Fall debut of I-110 Harbor Freeway ExpressLanes; San Bernardino Freeway Metro ExpressLanes Debut 7/25/2012 Early 2013 Metro Media Release Avisos de construcción en autopista I-10 por 7/24/2012 trabajos del proyecto ExpressLanes El Pasajero Blog Anuncian Mañana La Apertura del Centro de 7/24/2012 Usuarios Para Los Carriles Exprés de Metro El Pasajero Blog Metro, Caltrans & Elected Officials Announce Availability of Metro ExpressLanes FasTrak® Transponders for Debut of 110 Harbor Freeway 7/24/2012 ExpressLanes this Fall Metro Media Advisory HOT Lanes are Coming to L.A. Area to Burn Up Los Angeles Daily 7/22/2012 Congestion News Op Ed

79 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Cumulative Media Articles Date Article Publication or Blog Daily Breeze, Contra Transponders Hold Key to New Harbor (110) Costa Times, and San 7/19/2012 Freeway ExpressLanes Jose Mercury News 7/18/2012 110 Freeway Express Lanes Coming in November CBS Los Angeles L.A. Business This Week - A Weekly Update from the L.A. 7/12/2012 ExpressLanes Program to Launch in the Fall Area Chamber July 2012 Los Angeles News for Edition Metro to Add ExpressLanes in Los Angeles Travel Professionals Los Angeles Daily 7/11/2012 Clearing Up Toll -Lane Confusion (or Trying To) News Construction of El Monte Bus Station on Track to San Gabriel Valley 7/10/2012 Finish in Late August Tribune Editorial: Transportation Officials Must Do A Better Los Angeles Daily 7/7/2012 Job Preparing for Metro ExpressLanes News 7/5/2012 More Details on LA HOT Lanes Project Road Pricing Whittier Daily News, San Gabriel Valley Roadway Improvements Underway Throughout Tribune, and Pasadena 7/3/2012 San Gabriel Valley Star News Express Yourself: How New Express Lanes Are July/August Changing Our Commutes Westways Get Your Employees Prepared to Use Metro July, 2012 ExpressLanes CommuteSmart News San Gabriel Valley 6/26/2012 Our View: When Freeway is Not Free Tribune Whittier Daily News, San Gabriel Valley Drivers on the 10 Get Ready to Pay for Carpool Tribune, and Pasadena 6/25/2012 Lane Star News ExpressLanes Construction Notice for City of 6/15/2012 Rosemead The Source Blog 6/12/2012 Santa Monica Resets Its Parking Meter System The New York Times The Orange County 6/7/2012 Carpool Lanes on 110 to Go FasTrak Register Caltrans y Metro Muestran Como Funcionaran Los 6/6/2012 Carriles de Cuota En Las Autopista 110 y 10 El Pasajero Blog Motorists to Begin Seeing First Electronic ExpressLanes Message Boards Along Harbor 5/31/2012 Freeway The Source Blog Park This Way: Get ready to Pay Up to $6 at Hour Los Angeles Downtown 5/25/2012 at Downtown meters News

80 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Cumulative Media Articles Date Article Publication or Blog 5/22/2012 Transportation Headlines, Tuesday, May 22 The Source Blog In Los Angeles Demand-Based Pricing for 5/21/2012 Curbside Parking Goes Live Smart Planet Los Angeles Downtown 5/21/2012 New Parking Meter System Goes Into Effect News Downtown Parking Experiment Will Use GPS and 5/21/2012 Adjustable Pricing Blogdwntown.com City of Los Angeles Department of LA Express Park Will Make Parking and Getting Transportation media 5/21/2012 Around Downtown Los Angeles Easier Release Parking: What if Meters Reset Based on 5/19/2012 Demand? Hollywood Patch Downtown L.A. parking Fees to Rise, Fall with 5/18/2012 Demand LA Times, L.A. Now May/June 2012 Short Videos Explain ExpressLanes CommuteSmart News 5/1/2012 How Do They Do That ? Make Roads Smarter The Source Blog 4/26/2012 I-10 and I-110 ExpressLanes Rideshare Connection 4/10/2012 ExpressLanes Signs Keep Going Up The Source Blog Video en español: ¿cuáles son los reglamentos en 3/29/2012 los carriles de cuota? El Pasajero Blog Video en español: ¿cómo funcionarán los carriles 3/27/2012 de cuota? El Pasajero Blog Video en español: !Ya era Hora! Carriles 3/26/2012 ExpressLanes El Pasajero Blog 3/22/2012 The Future of Intelligent Parking The Atlantic Cities 3/13/2012 Video: The Greening of LA The Source Blog 3/8/2012 More Progress on New El Monte Station The Source Blog March/April 2012 Issue Metro ExpressLanes Update CommuteSmart News Unblocking the Box – Congestion Relief May Be 3/6/2012 Coming Soon to a City Near You The Source Blog 3/2/2012 ExpressLanes Video: carpool Loyalty Program The Source Blog 3/2/2012 Work Continues on New El Monte Station The Source Blog ExpressLanes Video: Rules of the Road and 3/2/2012 Enforcement The Source Blog 3/1/2012 ExpressLanes Signs are Gathering! The Source Blog Expresslanes Video: Explaining Congestion 3/1/2012 Pricing The Source Blog

81 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Cumulative Media Articles Date Article Publication or Blog Access to the Car Pool Lane Can Be Yours, For a 2/29/2012 Price The New York Times 2/29/2012 ExpressLanes Video: How it Works The Source Blog 2/28/2012 ExpressLanes Video: It’s About Time The Source Blog 2/24/2012 110 Freeway Gets its First ExpressLanes Sign The Source Blog Buried Car, Other Debris Delay New El Monte Bus San Gabriel Valley 2/22/2012 Station Tribune 1/30/2012 Transportation Headlines, Monday, Jan. 30 The Source Blog 40 Years Ago This Week: Groundbreaking for El Primary Resources, Monte Busway – California’s First Multi-Modal Metro Dorothy Peyton System & The World’s First Bus Rapid Transit Gray Transportation 1/23/2012 Stations Library and Archive 1/9/2012 Construction Notices for ExpressLanes Project The Source Blog 12/22/11 ExpressLanes Signs for 110 Freeway on the Way The Source Blog Five Things I’m Thinking About Transportation, 12/21/11 Dec. 21 Edition The Source Blog Behold: Metro ExpressLanes Congestion Pricing 12/14/11 Transponder! Curbed LA Fist Look: Transponders for Metro’s 12/14/11 ExpressLanes Project The Source Blog The Orange County 12/6/11 Are Toll Lanes the Answer to Traffic Congestion? Register 12/6/11 Transportation Headlines, Tuesday, Dec. 6 The Source Blog 12/5/11 New Timelines for Wilshire Bus Lanes Project The Source Blog Wilshire BRT and El Monte Busway Improvements 11/28/11 Coming…in 2015 LA Streetsblog Nov/Dec 11 Take the Metro Expresslanes ETC Carpool Issue Challenge to Win an iPad 2 CommuteSmart News 10/28/11 FTA Officially Announces Two Big Grants to Metro The Source Blog U.S. Department of Transportation Announces U.S. Department of $34.7 Million for Improvements to Transit in Los Transportation News 10/28/11 Angeles Release ACS to Work with Los Angeles to Implement New 10/27/11 Parking Program ExecutiveBiz Blog Bay Area Pushes for Huge ExpressLanes 10/25/11 Expansion The Source Blog 18 Active Risk Items for Metro’s ExpressLanes Metro – Sync Life with 10/11/11 Project Public Transit Blog OJO: Cierres En Autopista I-10 Por Trabajos de 10/1/11 Proyecto Expresslanes El Pasajero Blog

82 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Cumulative Media Articles Date Article Publication or Blog Transit Agencies Give Frontline Traffic Reporters 9/29/11 A Little Love The Source Blog 9/23/11 L.A.’s Commuter Dream LA Times Op Ed Cierres Nocturnos de Carriles en Autopista San 9/23/11 Bernardino a Partir del Domingo 25 El Pasajero Blog Solo Drivers of Low-Emission Autos Fume Over 9/14/11 Fees to Use Carpool Lanes La Times Metro ExpressLanes Construction to Close San Bernardino Freeway I-10 Transitway carpool Lanes During late Night/Early Morning Hours Effective 9/9/11 Sunday, Sept. 11 Metro Media Release 9/7/11 Dynamic Pricing: Flutuating Parking Meter Prices Smart Planet Lane Markings Works Beginning on 110 Freeway 8/30/11 Park of ExpressLanes Project The Source Blog Work on Harbor (110) Freeway Lanes to Cause 8/30/11 Some Overnight Closures Daily Breeze Interview with Donald Shoup: Los Angeles Making 8/24/11 Strides with ExpressPark LA Streetsblog Downtown LA Parking Meter Rate Hike Based on 8/16/11 Demand ABC7.com Most Popular Downtown Parking Spots Could Get 8/15/11 Very Pricey Soon Curbed LA 8/13/11 New L.A. Parking Meter Plan Gets Ticking LA Times ExpressPark Contract Heads to Council with 8/11/11 Questions about Technology Blogdowntown.com 8/3/11 Toll Lanes Daily Breeze Redondo Beach 8/2/11 110 Freeway to Gain Toll Lanes Patch.com Metro ExpressLanes Construction to Close Harbor Freeway Transitway Carpool Lanes During Late Night/Early Morning Hours Effective Sunday 8/2/11 August 7 Metro Media Release Express Park Set to Stack the Deck in Favor of 7/13/11 Parking Enforcement Blogdowntown.com 7/11/11 Escaping the 405 Mess on Flights of Fancy LA Times Op Ed Hearts and Minds: Comments Sections Shows 7/8/11 Confusion, Anger for I-10 and I-110 HOT Lanes LA Streetsblog What? Toll Lanes for the 10 and 110? Where? 7/7/11 How? Huh? The Source Blog Steve Lopez: Stop Whining About Toll Lanes on 7/7/11 L.A. Freeways LA Times Op Ed

83 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Cumulative Media Articles Date Article Publication or Blog Traffic Relief for $1.40 a mile: Toll Lane Construction Begins on 10 and 110 Where Aim is to Unclog Roads at Rush Hours; Toll Lanes Coming to 10 and 110 Freeways in Los Angeles 7/7/11 County LA Times City News Service: Metro Experiments with Toll Lanes on Harbor, San Southern California 7/6/11 Bernardino Freeways Local News Whittier Daily News, San Gabriel Valley Construction on New Toll Lanes on 10, 110 Tribune, and Pasadena 7/6/11 Freeways Getting Started Star News Metro Experiments with Toll Lanes on Harbor, San The Los Angeles 7/6/11 Bernardino Freeway Independent Groundbreaking Held for ExpressLanes 7/6/11 Congestion Pricing Project The Source Blog 7/6/11 Solo Drivers to Get HOV Lane Invite MSNBC.com Crews Begin HOV to HOT Project on 110, 10 7/6/11 Freeways NBC Los Angeles.com Metro and Caltrans Officially Break Ground on 7/6/11 ExpressLanes Project Metro Media Release Government Technology Solutions for State & Local Government 7/1/11 Parking Tech Helping Big Cities Ease Congestion (Govtech.com) About Those Transponder Fees for the 5/13/11 The Source Blog ExpressLanes Project Update: Regular Carpoolers Will Not Have to Pay 5/13/11 LA Streetsblog to Use ExpressLanes ExpressLanes Transponders, Coming to a Store 5/11/11 LA Streetsblog Near You…and to the AAA! May 2011 Roads and Bridges Moving in the City Issue Magazine 4/10/11 HOT Lanes Are Not a Solution to Traffic Woes Daily Trojan Reminder: ExpressLanes Meeting Tonight to 4/4/11 The Source Blog Discuss Adams Blvd. Improvements

3/24/11 Metro’s Freeway Projects Mean Better Everything Long Transportation For Everyone Beach.com 3/21/11 Metro’s Highway Program Ramps Up for Big Year The Source Blog 3/17/11 Streetfilms v. Local News on Congestion Pricing LA Streetsblog 3/15/11 Dueling Answers to Freeway Congestion CityWatch

84 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Cumulative Media Articles Date Article Publication or Blog Media, Congress Members, Running Another 3/15/11 Streetsblog LA ExpressLanes Mis-Information Campaign Both Sides of Congressional Aisle Hate Metro 3/14/11 Curbed LA Congestion Pricing Plan Toll-Lane Project Faces Renewed Opposition in 3/13/11 LA Times Congress Plan to Let Solo Drivers Pay Tolls to Use 10, 110 3/12/11 LA Times Blog Freeway Carpool Lanes Opposed LA Carpool Lanes to Open for Solo Drivers - In 3/3/11 2012, Drivers Can Choose to Pay More to Save NBC Los Angeles.com Time on the Freeway

3/3/11 Car-Pool Lanes for Solo Drivers? Fee System The Orange County Coming to L.A. Register Highs and Lows for Electric Vehicle Companies, 2/25/11 Technology Review and How to Buy Into the Carpool Lane LA To Charge a Toll For Driving Solo In HOV 2/25/11 Autoblog Green Lanes With New ExpressLanes Solo Drivers in Los Angeles Will Soon Be Allowed 2/25/11 TechCrunch To Drive In Carpool Lanes For a Fee

2/25/11 ACS to Operate New Los Angeles HOT Traffic Technology “ExpressLanes” System Today.com To Curb Congestion, Los Angeles Rolls Out 2/23/11 Smart Planet Dynamic Electric Toll Booths

2/23/11 Xerox Unit Setting up Calif. Tollway Hartford Business.com ACS, A Xerox Company, to Keep Los Angeles ACS, A Xerox 2/23/11 Drivers Moving with Electric Toll Collection for New Company, Media ExpressLanes Release Metro Plans to Remove Adams Blvd. Sidewalks 2/22/11 LA Streetsblog New My Figueroa ExpressPark Hits Bump When Bids Come In Over 2/15/11 Blogdowntown.com Budget O.C. Toll Roads His By Recession; Would you Pay 2/1/11 LA Times Blog for a Faster Commute? Recession Slows Use of Orange County’s Toll 2/1/11 LA Times Roads

1/12/11 ExpressLanes Project Picks Contractor The Source Blog

12/16/10 The Truth About HOT Lanes The Infrastructurist ExpressPark Aims to Give Smarts to Downtown’s 12/1/10 Blogdowntown.com Parking Spots

85 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Cumulative Media Articles Date Article Publication or Blog What a Difference Two Years Makes. Warm 11/22/10 Reception for Congestion Pricing in the San LA Streetsblog Gabriel Valley MTA Considers More Freeway Toll Lanes to 11/16/10 LA Times Reduce Congestion Long Beach Press- 11/16/10 Paying to Use Those Carpool Lanes Telegram San Gabriel Valley 11/16/10 Our View: Taking the Free From Our Freeways Tribune San Gabriel Valley 11/16/10 57, 10 Freeways List As Candidates for Toll Lanes Tribune Some Like it HOT: Metro Studying More Roads for 11/15/10 LA Streetsblog Congestion Pricing MTA Considering More Freeway Toll Lanes To 11/15/10 LA Times Reduce Congestion Will HOV Lanes Be Converted to Congestion 11/15/10 The Source Blog Pricing Toll Lanes? Read the Study Metro Breaks Ground on New State-of-the-Art 9/22/10 Metro Media Release Transit Facility at the El Monte Station Construction Begins on $45 Million El Monte Bus 9/22/10 Pasadena Star-News Station

9/21/10 Busiest Transit Center West of Chicago Expands Metro Media Advisory New Temporary El Monte Bus Terminal Begin 9/15/10 Mid Valley News Online Operations New Temporary El Monte Bus Terminal to Being 9/9/10 Metro Media Release Operations on Sunday, September 12

9/9/10 New Temporary El Monte Bus Terminal Begins The Source, Metro’s Operations on Sunday Blog

8/22/10 LA Program Aims to Make Parking Easier LA Times HOT Lanes Project Draft EIR/EA Available for 2/8/10 Caltrans News Release Public Review Silver Line Launches Sunday, Ready to Take You 12/9/09 Curbed LA to the HOT Lane MTA Changes Course, Opening Carpool Lanes to 7/24/09 LA Times Solo Drivers – For a Fee LA Transportation Officials Approve Letting Solo 7/23/09 LA Times Drivers Pay a Toll to Use Carpool Lanes 10 & 100 Freeways to Get Express Toll Lanes in 7/23/09 Laist 2010

86 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Cumulative Media Articles Date Article Publication or Blog Metro Board Approves Toll Rates for Freeway 7/23/09 ExpressLanes as Part of Congestion Reduction Metro Media Release Demonstration Project MTA Board Approves Toll Rates for 10, 110 7/23/09 Pasadena Star News Freeways 7/19/09 Coming Soon: Fast Lanes for the Rich Daily Breeze Op Ed Sign On To Metro’s Next Chat and Ask Questions 7/2/09 About ExpressLanes, Toll and Other Congestion Metro Media Release Reduction Strategies 6/28/09 Harbor Area Neighborhood Councils Form Alliance Daily Breeze 6/26/09 Express Lanes Coming To Our County LBPost.com 6/22/09 Congestion Pricing: More Heat Than Light CityWatchLA.com 6/15/09 Congestion Pricing – The Only Thing That Works LA Times Op Ed 6/14/09 Letters to the Editor: Divisions on Toll Lanes LA Times 6/13/09 For Whom The Toll Benefits LA Times Op Ed Metro Response to LA Times’ Tim Rutten Column 6/12/09 Metro Media Release on Congestion Reduction Demonstration Project Congestion Pricing – A Slippery Slope to Toll 6/10/09 LA Times Op Ed Roads 6/9/09 Fashioning Faster Freeways Daily Breeze 6/9/09 A Pagar En Las Vìas La Opinion 6/9/09 Congestion Pricing Considered LA Times

6/9/09 Solo Drivers Would Pay to Use Carpool Lanes Orange County Under Plan Register MTA Mulling Solo Harbor Freeway Carpool Lane 6/8/09 Daily Breeze Use – For a Fee LA County Considers Toll Charges on Two 6/8/09 LA Times Freeways Would You Pay $1.40/Mile to Use the Carpool 6/8/09 LAist Lane Solo? Metro to Hold Series of Community Public Hearings on Proposed Tolling Prices for Freeway 6/8/09 Metro Media Release ExpressLanes as Part of Congestion Reduction Demonstration Project 6/8/09 Toll Roads Socalnews.com Whittier Daily News, 6/8/09 MTA Details Toll Lane Plans for 10 and 110 San Gabriel Valley Freeways Tribune, and Pasadena Star News

87 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Cumulative Media Articles Date Article Publication or Blog Metro and Caltrans Officials to Hold Media Briefing 6/5/09 on Status of I-10 and I-110 Freeway ExpressLanes Metro Media Advisory Congestion Reduction Demonstration Project LA Times 8/26/08 Road Sage; Pricing May Not Hurt the Poor

Road Sage; Congestion Pricing Plan May Switch 7/9/08 LA Times Routes 6/10/08 Road Sage; Leaders Try to Stall Toll Lanes LA Times The Way To Go; Freeway Toll Lanes Aren’t an 5/3/08 LA Times Op Ed Experiment – They’re Proven Congestion Busters Not-So-Free ways; Toll Lanes Are One Answer to 4/29/08 Our Traffic Problems. But the MTA Might Have LA Times Op Ed Taken a Better Route 4/26/08 Diamond Lanes for the Rich LA Times Op Ed U.S. Offers Funds for Toll Lanes; MTA Will Weigh 4/24/08 Congestion Pricing on Parts of 10 and 210, But LA Times Fees to use Freeways Remain Controversial 4/14/08 Road Sage; Tolls on Freeways a Tough Sell LA Times

88 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Cumulative Media Broadcasts Date Broadcast Media Outlet 9/13/2012 Vicky Moore/Dick Helton KNX-AM 9/13/2012 Today in LA KNBC Eyewitness News at 4:30 am, 5:00 am, 6:00 am, 7/25/2012 11:00 am, 11:30 am, 4:30 pm, 5:00 pm, & 5:30 pm KABC Channel 7 7/25/2012 Today in LA KNBC Channel 4 7/25/2012 News – Air Talk KPCC 89.3 6/8/2012 Morning Broadcast Univision Reporter’s Notebook: Downtown LA Tests KCRW – Which Way, 6/7/2012 Adjustable Rate Parking LA? WSBT (CBS) – South 6/5/2012 WSBT News at 5:30 Bend, IN Story on Metro ExpressLanes Caltrans Museum KTTV-TV (FOX) 6/5/2012 Exhibit Channel 11 Tolls to Let Drivers Buy Their Way Into the Carpool 6/4/2012 Lanes NBCLA Caltrans to Offer Solo Drivers Premium Access to 6/4/2012 Carpool Lanes CBS Los Angeles 6/4/2012 5:11:46 AM KABC-AM Radio 6/4/2012 12:05:19 KNX-AM 10.70 6/4/2012 8:08:09 KNX-AM 10.70 Pat Morrison: Life is a Highway, I Wanna Ride it All KPCC-FM, 89.3 Los 7/7/11 Night Long Angeles The California Report: Los Angeles Congestion 7/7/11 Pricing KQED KTTV-TV (FOX) 7/6/11 Fox 11 Morning News at 6:00 am Channel 11 KPCC-FM, 89.3 Los 7/6/11 Larry Mantle's Air Talk Angeles 7/6/11 Today in LA at 5:00 am and 6:00 am KNBC-TV Channel 4 CBS 2 News at 11:00 am, Local Cut-In, and 6:00 7/6/11 pm KCBS-TV Channel 2 7/6/11 KCAL 9 News at Noon, 3:00 pm, and 10:00 pm KCAL-TV Channel 9 7/6/11 Eyewitness News at 11 am KABC-TV Channel 7 Plan Would Let Solo Drivers Pay to Use 10, 110 3/14/11 KTLA News Carpool Lanes

2/24/11 ExpressLanes-A “HOT” Topic! ACS Discusses Blogtalkradio/Xerox “High Occupancy Toll” Lanes Real Business Radio 6/8/09 The John and Ken Show KFI-AM 640

89 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

Cumulative Media Broadcasts Date Broadcast Media Outlet KNX-AM 1070 6/8/09 Tom Haule/Linda Nunez and KNX 1070 Newsradio Newsradio 6/8/09 CBS 2 News KCBS-TV Channel 2 6/8/09 Today in LA and Channel 4 News Nightside KNBC-TV Channel 4 Eyewitness News at 5:30 am, 6:00 am, and 6:00 6/8/09 KABC-TV Channel 7 pm KCAL 9 News at 12:00 noon, 3:00 pm and 4:00 6/8/09 KCAL-TV Channel 9 pm 6/8/09 Fox News at 11:00 am KCOP-TV Channel 13 6/9/09 Today in LA at 5:30 am and 6:00 am KNBC-TV Channel 4 KTLA News at 6:00 am, 9:00 am, Morning News, 6/9/09 KTLA-TV Channel 5 1:00 pm, and Prime News at 10:00 pm 6/9/09 Fox 11 Morning News at 5:00 am and 6:00 am KTTV-TV Channel 11 KTTV-TV Fox Channel 6/9/09 Fox 11 Morning News at 6:00 am 11 6/10/09 Today in LA KNBC-TV Channel 4

90 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

APPENDICES COST AND BUDGET TERMINOLOGY

ADOPTED BUDGET: The Approved Project Budget as established by Metro Board of Directors at the time it authorizes Construction Project Management Division to commence full design and construction of the project (Project Adoption).

CURRENT FORECAST: Evaluation of costs to go combined with actual expenditures.

COMMITMENTS: The total of actual contract awards, executed change orders or amendments, approved work orders of Master Cooperative Agreements, offers accepted for purchase of real estate, and other Metro actions which have been spent or result in the obligation of specific expenditures at a future time. Also includes commitments reported by other agencies.

EXPENDITURES: The total dollar amount of funds expended by Metro for contractor or consultant invoices, third party invoices, staff salaries, real estate and other expenses that is reported in Metro’s Financial Information System (FIS and expenditures reported by other agencies.

91 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

APPENDIX LIST OF ACRONYMS

ARRA American Recovery & Reinvestment Act AWIS Automated Work Zone Information Systems BRT Bus Rapid Transit CADD ComputerAidedDraftingandDesign CALTRANS California Department of Transportation CCTV Closed Circuit Television CD Calendar Day CDFG California Department of Fish and Game CM Construction Manager CMAC Congestion Mitigation Air Quality CMIA CashManagementImprovementAct CMS Changeable Message Signs CN Change Notice CNG Natural Gas CO Change Order COE Corps of Engineers COLA CityOfLosAngeles CONOPS Concept of Operations CPM CriticalPathMethod CPUC California Public Utilities Commission CR Camera Ready CRD Congestion Reduction Demonstration CTC California Transportation Commission D-B Design-Build D-B-B Design-Bid-Build DBOM Design, Build, Operate and Maintain DD Design Development DEIR DraftEnvironmentalImpactReport DWP DepartmentofWaterandPower EA Environmental Assessment EIR EnvironmentalImpactReport EIS EnvironmentalImpactStatement FD Final Design FEIR FinalEnvironmentalImpactReport FHWA Federal Highway Administration FIS Financial Information System FOCT Fiber Optics Cable Transmission System FTE Full Time Equivalent GDSR Geotechnical Design Summary Report GSA GeneralServicesAdministration GSRD Gross Solids Removal Devices HAR Highway Advisory Radio

92 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

APPENDIX LIST OF ACRONYMS (Continued)

HOT High Occupancy Toll HOV High Occupancy Vehicle IFB InvitationforBid IPO Integrated Project Office ITS IntelligentTransportationSystems LA LosAngeles LABOE Los Angeles Bureau of Engineering LACFCD Los Angeles County Flood Control District LADOT Los Angeles Department of Transportation LADPW Los Angeles Department of Public Works LADWP Los Angeles Department of Water and Power LARTMC Los Angeles Regional Transportation Management Center LFAT Local Field Acceptance Test LNTP Limited Notice To Proceed LONP LetterOfNoPrejudice LOP Life of Project MCA Master Cooperative Agreement METRO Los Angeles County Metropolitan Transportation Authority MIS MajorInvestmentStudy MOT MaintenanceofTraffic MOU MemorandumofUnderstanding MPSR MonthlyProjectStatusReport MVDS Microwave Vehicle Detection System MVP Maintenance Vehicle Pullouts MWD Metropolitan Water District N/A Not Applicable NEPA National Environmental Protection Act NHS National Highway System NOA Notice of Award NTE Not to Exceed NTP Notice To Proceed NTSC National Television System Committee P6 Primavera Project Planner® (scheduling software) PC Project Control PE Preliminary Engineering PIP ProjectImplementationPlan PM Project Manager PMA Project Management Assistance PMP ProjectManagementPlan P&P Policies & Procedures PR Project Report PS&E Plans, Specs & Engineering

93 Metro LA CRD (ExpressLanes) Program January 2013 Monthly Project Status Report

APPENDIX LIST OF ACRONYMS (Continued)

PSR ProjectStudyReport QA Quality Assurance QAR Quality Assurance Report QC QualityControl QPSR QuarterlyProjectStatusReport RFC Request For Change or Released for Construction (based on context) RFP Request For Proposal RMS Ramp Metering Systems ROM RoughOrderofMagnitude ROW Right-Of-Way SIT System Integration Testing RSTP Regional Surface Transportation Program RWQCB Regional Water Quality Control Board SAFETEA- Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for LU- Users SCE SouthernCaliforniaEdison SEMP Systems EngineeringManagement Plan SONET Synchronous Optical Network SOV Single Occupant Vehicle SOW StatementOfWork SP Special Provision TBD ToBeDetermined TCRP Traffic Congestion Relief Program TMS/CS Traffic Monitoring Stations/Count Stations TPM TransportationManagementPlan UPS UninterruptedPowerSupply USDOT United States Department of Transportation VE Value Engineering WBS Work Breakdown Structure WP Work Package

94