EIA for the Proposed Mixed Housing and Commercial Development on Lot 66166, Tanjung Dua Belas, Daerah Kuala Langat, Darul Ehsan for Setara Hati Sdn. Bhd.

Summary of Environmental Impacts and Mitigating Measures All the impacts that are likely to be generated by the proposed Project is summarized in Table E. Mitigating measures specifically proposed for each of the impacts are also presented in a systematic manner in accordance to pre-construction, construction and operational phase. Hence, such data enable convenient identification of impacts along with their respective temporal (i.e., acute or residual) and spatial (i.e., magnitude) considerations.

Table E: Summary of Environmental Impacts and Mitigating Measures for the Proposed Project

PHASE OF DEVELOPMENT ACTIVITIES POTENTIAL IMPACTS MITIGATING MEASURES SIGNIFICANCE REMARKS A. Pre-Construction Phase Reconnaissance study of • Preparation of • The activity is rather None. Short-term. The pre-construction the Project Site. documentation and plans localized and not expected stage basically involves of the proposed to generate any the documentation, development. disturbances to the legal approval from the existing environment. relevant authorities, Detail study of the existing • Field survey and site • Some form of beneficial building construction condition. investigation by impacts such as job design and engineering and opportunities (i.e., development planning, environmental surveying works, field survey as well as consultants. associated labourers and site investigation. analytical laboratories) may be possible.

d-i EIA for the Proposed Mixed Housing and Commercial Development on Lot 66166, Mukim Tanjung Dua Belas, Daerah Kuala Langat, Selangor Darul Ehsan for Setara Hati Sdn. Bhd.

Cont…. PHASE OF DEVELOPMENT ACTIVITIES POTENTIAL IMPACTS MITIGATING MEASURES SIGNIFICANCE REMARKS B. Construction Phase Construction of the access • The provision of proper • Main impact is in terms of • Constant wetting of the road Short-term within The contractor should road transportational routes is noise and dust and covering the transported the duration of the ensure that the given foremost disturbances. raw or fill material with proposed Project. transportation of heavy consideration in any • Increment of traffic risks canvas sheets to control machineries, developmental project. especially by heavy fugitive dust during times of equipments and This is to ensure vehicles plying Jalan low precipitation. construction material convenience to the Kampong Lombong, and • Flagmen must be stationed adhere to specific workers as well as Jalan Lombong Emas 3. at the access road junctions guidelines from enabling smooth • Spillage of raw to control and direct traffic. relevant authorities. transportation of construction material • The vehicles will have to construction materials onto public roads. observe speed limits and any and heavy machinery. damage done to the Main Access route to • Transportation of transportation routes should Project Site machineries, equipment be repaired. and construction material • Proper warning signs, signals to the site is from Jalan or warning light and Kampong Lombong, barricades are recommended  Jalan Lombong Emas 3. to ensure safety and smooth flow of traffic.

Access Route within • Existing earthen routes • A wash trough will be project site within the site. • As the access route has constructed to avoid dirtying been established within the public road. the Project area, the • Establishment of tarred road magnitude of disturbance or at least compacted unto the physical crusher run roads and environment may be constant wetting of work considered as nominal. tracks to minimize dust dispersion.

d-ii EIA for the Proposed Mixed Housing and Commercial Development on Lot 66166, Mukim Tanjung Dua Belas, Daerah Kuala Langat, Selangor Darul Ehsan for Setara Hati Sdn. Bhd.

Cont…. PHASE OF ACTIVITIES POTENTIAL IMPACTS MITIGATING MEASURES SIGNIFICANCE REMARKS DEVELOPMENT Mobilization on site • Construction of workers • The benefits to the local • Adequate facilities to prevent an Short-term within camp. community would be unhealthy environment. the duration of the • The sewage to be source of employment • Providing safety devices which proposed Project. generated during the and small-scale business are recommended in the construction stage is at investment. Occupational Safety and Health 22,500 l/day 1 • It is estimated that an Act 1994 (OSHA) for construction (~estimated-100 approximate of 100 workers to ensure their safety. workers). workers shall be needed • All foreign workers shall be • Provision of maintenance to complete the stage. screened against the presence of yard/ workshop. • In terms of adverse contagious diseases. impact, presence of • A total of 3 numbers of septic foreign labour might tanks with a capacity of 35 PE poses antisocial behaviour each are required to contain the and risk of introduction of sewage discharge of 100PE at the contagious diseases that site to the compliance limits. needs to be addressed. • No open-burning of rubbish • Organic pollution in terms should be carried out. of sewage waste. • Proper skid tank storage to curtail • Heavy machinery and the possibility of oil and grease equipment can generate contamination. oily waste. • The generated spent oil and • Oil/ grease and hydraulic grease from the maintenance spill onto soil causing the works have to be stored and soil and groundwater handled as per the Environmental contamination. Quality (Scheduled Wastes) Regulations 2005

1 Assumption during construction stage based on per worker with per capita discharge rate of 225l/day. Adapted from MS1228 Sewage Guidelines.

d-iii EIA for the Proposed Mixed Housing and Commercial Development on Lot 66166, Mukim Tanjung Dua Belas, Daerah Kuala Langat, Selangor Darul Ehsan for Setara Hati Sdn. Bhd.

Cont…. PHASE OF DEVELOPMENT ACTIVITIES POTENTIAL IMPACTS MITIGATING MEASURES SIGNIFICANCE REMARKS Site Clearing and Biomass • Site clearing will involve the • The loss of current • Biomass stockpile area should Short term Close compliance to the Disposal. removal of mainly of oil vegetation and the related be earmarked within the proposals in the ESCP palm trees and shrubs and habitats. Project area prior being plan, biomass disposal small woody plants as well • May lead to soil erosion disposed off site to an plan proper as involve hacking of the and increase in surface approved dumpsite. management practices existing buildings. runoff. • Open burning is strictly on-site will help • Biomass generation is • If not disposed off prohibited , as it would lead to prevent excessive approximately 10,230.44 properly, can lead to air pollution problems. water quality tons for estimated palm water quality • The undergrowth and small deterioration. trees area at the Project Site deterioration and attract woody plants such as area. unwanted pests and high branches of secondary organic loading in the vegetations as well as river shredded oil palm fronds and • Demolishing activities trunks can be mulched on would generate higher site. sound and dust levels, • Implementation of best which might pose a management practice on-site nuisance towards nearby (i.e., turfing, temporary earth population. drains and sediment basins) • Open burning of biomass • The Contractor should place or solid waste shall heavy emphasis in soil generate soot and dust. conservation by adopting • Earthwork and environmentally integrated construction activities measures to counter against limited nesting and soil erosion. habitat of faunas within • Demolished material will be the Project Site area. disposed off site to an approved dumpsite and any reusable material from the demolished waste is sold to an external party by the contractor.

d-iv EIA for the Proposed Mixed Housing and Commercial Development on Lot 66166, Mukim Tanjung Dua Belas, Daerah Kuala Langat, Selangor Darul Ehsan for Setara Hati Sdn. Bhd.

Cont…. PHASE OF DEVELOPMENT ACTIVITIES POTENTIAL IMPACTS MITIGATING MEASURES SIGNIFICANCE REMARKS Impact of earthworks. • The cut and fill quantities • The main impact • Site clearing, earthworks and Short term are approximated to generated from construction works of the 1,561m3 and 1,871,847m3 earthworks activities is proposed development will be • The cut and fill respectively. probably in the form of conducted in 2 stages and five activity are • The shortage of soil washout into the river (5) sediment basins to spread out up to 1,870,286m 3 shall be especially during heavy minimize the extent of the 18 month for imported from a borrow pit rain. bare soil exposure and each stages. source from , • Settlement of the subsequently, soil erosion • Earthworks are located 40km away from underlying subsoil by the problems. carried out in the project site. load imposed after filling. • Any sediment generated from stages according • Excavation of higher • If not properly compacted, the site shall be retained in to its stages. grounds to form platforms, fill areas is susceptible to the silt structure before being roads and other area as erosion, slipping and discharged into Sg. . shown in design drawings subsidence. • Covering of platform should • Filling to lower area to form • If the cuttings are too be carried out immediately at embankments and platform steep and are not properly all exposed areas. Measures to design levels protected, stability such as mulching, problems may arise hydroseeding, installation of • The leveling of ground and turf mats or other suitable the use of heavy geotextiles are suggested to machinery for the promote vegetation growth. compaction of the fill • The heavy vehicles will have material during land to observe speed limits and development and any damage done to the construction activities will transportation routes should give rise to dust and noise be repaired. pollution.

d-v EIA for the Proposed Mixed Housing and Commercial Development on Lot 66166, Mukim Tanjung Dua Belas, Daerah Kuala Langat, Selangor Darul Ehsan for Setara Hati Sdn. Bhd.

Cont…. PHASE OF DEVELOPMENT ACTIVITIES POTENTIAL IMPACTS MITIGATING MEASURES SIGNIFICANCE REMARKS Impact of earthworks. • Erosion control proposed is by programme schedule, mulching, soil roughening or generally refer to track walking or imprinting a slope and cover crops / grass. • Sediment Control proposed is sediment basins, check dam, silt fence and street sweeping. • Runoff Management BMPs is earth bank / diversion channel, drainage outlet protection and temporary waterway crossing • Tracking control proposed is the use of hoarding, stabilized construction access, interlocking paver block, wash trough, and keeping area moist. • Maintenance of the completed and temporary works

d-vi EIA for the Proposed Mixed Housing and Commercial Development on Lot 66166, Mukim Tanjung Dua Belas, Daerah Kuala Langat, Selangor Darul Ehsan for Setara Hati Sdn. Bhd.

Cont…. PHASE OF DEVELOPMENT ACTIVITIES POTENTIAL IMPACTS MITIGATING MEASURES SIGNIFICANCE REMARKS Hydrology • Site clearing and • The clearing of the existing • All together there is five (5) Short term The temporary earthwork activities will vegetation will increase in sediment basins proposed for the drainage system have a significant impact discharge into Sg. Kelang. entire development area in order will be designed on the hydrological to trap all surface runoff. to comply with regime. • The surface drainage needs to be the procedures as constructed in order to reduce the outlined in the infiltration and erosion caused by MASMA manual. surface runoff especially during heavy rainstorms. Soil Erosion • Site clearing and • During this earthworks and • The earthworks and construction Short term earthworks in the form of construction stage, works will be carried out in 2 cut and fill activities. This Soil erosion rates under the worst stages. activity will be only case scenario: • Provision of five (5) sediment basins carried out at proposed Stage 1- 53.2 tons/ha/year for the Site. built up area. Stage 2- 55.0 tons/ha/year • Maintenance of the drainage The entire Project Site – 54.0 network and sediment basins. tons/ha/year. • Biotechnical protection and Sediment yield under the worst mechanical practices to attend to case scenario: the exposed soil. Stage 1- 1,294 tons • Implementation of ESCP. Stage 2- 1,035 tons The entire Project Site – 2,329 tons per storm event which is approximately thirteen (12) times higher than the existing condition of 185 tons per storm event.

d-vii EIA for the Proposed Mixed Housing and Commercial Development on Lot 66166, Mukim Tanjung Dua Belas, Daerah Kuala Langat, Selangor Darul Ehsan for Setara Hati Sdn. Bhd.

Cont…. PHASE OF DEVELOPMENT ACTIVITIES POTENTIAL IMPACTS MITIGATING MEASURES SIGNIFICANCE REMARKS Air Pollution • Improper storage of raw • Increased level of TSP due to • All storage and transported Short-term within The air pollution construction materials spillage or wind-blown dust from material especially bulk the duration of problem is such as cement, sand, uncovered material which may material, should be properly the proposed considered to be gravels. have some effects on aesthetic covered and secured with Project. short-term problem value and health aspects. ropes to prevent spillage and and localised within • The leveling of ground and the wind-blown dust. the working areas. use of heavy machinery for the • Provision of wash trough. compaction of the fill material • Constant wetting and cleaning during earthwork and of roads connecting the Site construction activities will give to external public roads. rise to dust pollution. Regular maintenance of • Traffic movement on dirt road will vehicles and machinery, and churn up the surface and may observation of speed limits incite hazy condition especially shall reduce the level of during dry and windy periods. exhaust gases, dust as well as • Based on prevailing wind vehicular noise and vibration. occurrence from north-south • To erect hoarding along the direction, there isn’t any boundary of the Project Site. immediate sensitive receptors on the southern portion of the Project Site. However, Bandar Rimbayu and Orang Asli Resettlement Area is located 1.2KM and 2KM towards southern region respectively.

d-viii EIA for the Proposed Mixed Housing and Commercial Development on Lot 66166, Mukim Tanjung Dua Belas, Daerah Kuala Langat, Selangor Darul Ehsan for Setara Hati Sdn. Bhd.

Cont…. PHASE OF DEVELOPMENT ACTIVITIES POTENTIAL IMPACTS MITIGATING MEASURES SIGNIFICANCE REMARKS Noise Pollution Earthwork Nearest receptor, i.e., residents of • Noisy construction activities Similarly with air Kampong Lombong which is located should be done only during pollution, noise approximately 90m to the northern of day-time to preserve pollution is also the Project Site, shall experience tranquility of night-time and localized and excessive noise level emitted from reduce level of nuisance to short term. tractors, scrappers, trucks and, surrounding population. jackhammer/rock drills.

Building and • Piling Activities • As the whole site is using pilling • Method of piling Short-term Infrastructural Works • Construction Debris method, the distance from the recommended is by using within the • Traffic and nearest house will be Kampong enclosed hydraulic pile to duration of the Transportation Impact Lombong located at the northern reduce the impact on the proposed part of the Project Site which is noise at the nearest Project. approximately 90m away. proposed building to the existing buildings. • All domestic and building waste will be disposed off site to an approved dumpsite. • Traffic management is necessary to control traffic movements especially during peak hours.

d-ix EIA for the Proposed Mixed Housing and Commercial Development on Lot 66166, Mukim Tanjung Dua Belas, Daerah Kuala Langat, Selangor Darul Ehsan for Setara Hati Sdn. Bhd.

Cont…. PHASE OF DEVELOPMENT ACTIVITIES POTENTIAL IMPACTS MITIGATING MEASURES SIGNIFICANCE REMARKS • Given a distance of 90m from the nearest receptors (i.e., Kampong Lombong) the noise emission at 10 percentile of the time is below than

the limit of L10 =75, if the enclosed hydraulic drop hammer is used (the simulated reading shows of 70.90dB (A) with limited working time). • Sedimentation is likely to occur, higher rainfall runoff on land surfaces; as a result the scour problems occur and increase sedimentation into stream. • Improper disposal of construction debris may eventually clog drains, affecting the appearance of the Project Site. • During construction stage, lorries and trucks delivering building materials, aggregate, etc will increase traffic flow of the area.

d-x EIA for the Proposed Mixed Housing and Commercial Development on Lot 66166, Mukim Tanjung Dua Belas, Daerah Kuala Langat, Selangor Darul Ehsan for Setara Hati Sdn. Bhd.

Cont…. PHASE OF DEVELOPMENT ACTIVITIES POTENTIAL IMPACTS MITIGATING MEASURES SIGNIFICANCE REMARKS C. Operational Phase Stormwater Management • Implementation of the • Without a proper drainage planning • The project area divided into 2 It is anticipated Project requires the and stormwater management, catchments area. that there will be installation of various water quality and surface runoff • The total area provided for no localized stormwater will be disturbed as the landuse detention pond/lakes are 12.41 flooding upon management practices constituent of the Project Site will acre or 4.82% of the project site construction of an to retard the abrupt have gone through a major and drainage reserve of 6.81 efficient drainage flow of the runoff as alteration. acres or 2.65% of the Project system. enunciated by Jabatan site Pengairan dan Saliran • There are altogether two (2) (JPS) “storm numbers of detention ponds discharge” concept. which form a permanent lake in the center of the development. • All discharges will be flowing to Sg. Klang which is located at the northeast of the Project Site.

d-xi EIA for the Proposed Mixed Housing and Commercial Development on Lot 66166, Mukim Tanjung Dua Belas, Daerah Kuala Langat, Selangor Darul Ehsan for Setara Hati Sdn. Bhd.

Cont…. PHASE OF DEVELOPMENT ACTIVITIES POTENTIAL IMPACTS MITIGATING MEASURES SIGNIFICANCE REMARKS Water Pollution • The wastewater from the • Any discharge that fails to • There is a Sewage Treatment Short-term. The design of sewage human population (P.E of comply with Standard A levels Plant proposed to be treatment plant shall 24,596) at full will pollute the receiving river. established at the Project Site comply to “Malaysian operational stage is • Indiscriminate dumping of waste located at the north eastern Sewerage Industry approximately 5,534,100 into the drainage system would part. The sewage from the Guidelines –Volume IV – l/day. degrade the water quality. residential area and the public Sewage Treatment amenities will be conveyed by Plants (Third Edition gravity flow into the Sewage SPAN 2009)” Treatment Plant. The Sewage Treatment Plant proposed would be able to treat for 25,000 PE (5,625,000 l/day) • Increment in BOD loading and ammoniacal nitrogen will be able to be treated with a proper sewage pollution control and prevent its loading accumulation into Sg. Klang.

d-xii EIA for the Proposed Mixed Housing and Commercial Development on Lot 66166, Mukim Tanjung Dua Belas, Daerah Kuala Langat, Selangor Darul Ehsan for Setara Hati Sdn. Bhd.

Cont…. PHASE OF ACTIVITIES POTENTIAL IMPACTS MITIGATING MEASURES SIGNIFICANCE REMARKS DEVELOPMENT Waste Management Solid waste expected to be • Improper disposal of solid • Implementation of a proper generated from the community waste may affect and adequate waste collection -Solid Waste on-site is 24,596 kg/day. aesthetic quality, a source system by the Local Authority. of water contamination • The solid wastes will be and proliferation of disposed to Tanjung 12 disease vectors. Landfill, located approximately 28km from the Project site

-Sullage and Kitchen • All drainage systems and • Grease traps must to be Waste Management piping will be clogged if prepared for all kitchens in the from Food and the sullage and kitchen cafeteria and food court to Beverages Outlets. wastes are discharged trap the Fat, Oil and Grease without a proper trap. (FOG).

d-xiii EIA for the Proposed Mixed Housing and Commercial Development on Lot 66166, Mukim Tanjung Dua Belas, Daerah Kuala Langat, Selangor Darul Ehsan for Setara Hati Sdn. Bhd.

Cont…. PHASE OF ACTIVITIES POTENTIAL IMPACTS MITIGATING MEASURES SIGNIFICANCE REMARKS DEVELOPMENT Air, Noise and Vibration • The increase in traffic • The traffic emissions are • Provision of sufficiently sized Residual impacts activities would be a source expected to be the major junctions, traffic signages and of impact on both the air source of air pollution in proper maintenance of road and noise quality. the area. Air pollutants network system. • Quarries activities adjacent such as dust, smoke and • Regulatory procedures or to the Project Site would be exhaust gases are mainly control of traffic emissions to the main source of Noise and traced to vehicular comply with the legislative Vibration pollution. combustion. limits. • The increasing traffic • Provision of adequate and activities and human efficient road systems to activities are the main reduce traffic congestion. contributing factors to • Landscaping to enhance the noise pollution which aesthetics of the development would primarily come area. from heavy vehicles • Provision of 500m non- movement and other residential area. transport related • Mitigation at source, activities. transmission path and • Blasting activities from receiver are highlighted on the quarries would cause the conclusion of the Noise noise and vibration and Vibration Modelling pollution to the Report which is appended as development. Volume II of the EIA report.

d-xiv EIA for the Proposed Mixed Housing and Commercial Development on Lot 66166, Mukim Tanjung Dua Belas, Daerah Kuala Langat, Selangor Darul Ehsan for Setara Hati Sdn. Bhd.

Cont…. PHASE OF DEVELOPMENT ACTIVITIES POTENTIAL IMPACTS MITIGATING MEASURES SIGNIFICANCE REMARKS Biological Environment • Enhance the aesthetic • Biological impacts are • Re-establish and diversify Long-term. value of the Project Site basically upon re-planting of the flora and fauna species, with landscape greeneries by establishment albeit nominal in the Site. programme. of buffer zones and • Implementation of landscaping. aesthetically pleasing, • This activity could further visually enhancing and attract some fauna species to extensive landscaping will the Project Site. attract a community of small • The loss of the existing animals and provide a terrestrial biological wholesome environment. environment during the establishment of a built development. Socio-economic • The potential positive • Increase current status of None Long-term. Environment impacts on the socio- living of the local population economic environment residing nearby in terms of are evident with the public utilities, amenities, implementation of the infrastructures and increase proposed Project. employment opportunities. Residual impacts • Potential residual • Discharges from the sewage impacts are from water, treatment plant which noise and air. eventually flow into Sg. Klang. • The proposed Project does not warrant serious environmental concern in terms of anticipating any excessive noise nor gaseous pollutants being emitted to such an extent that it affects the living ambience of adjacent developments