VOLUME XXIV NUMBER 1 FIRST OUARTB,3 .'),1../ - ( MODERN STEEL CONSTRUCTION

An Unending Symphony in Steel A Tale of Two Bridges New Engineering for Steel Construction Released Building with a Historical Flourish Creating Space Where There is None Steel Wins the Roof "Sweeps" DECK OATISHEET. NO. 4 c:=::::======~ COMPOSITE DECK/SLAB I VALUES

TOTAL r-______~ C~O~M~PO~S~ITE~~I ~(M~o~me~n~t~o~f rl ne~rI1=·~.)~:~i~~he~.·~/ft~.=o~f ~w~~~ili~------_1 SLAB 150 PCF, n-9 11 5 PCF, n- 14 DECK/SLAB COMBINATION DEPTH r------~~G~og~.~~------~------~~~G~og~.~~------1 V 22 n W 19 U U U n 21 W " U U U 4.00" 3. 5 3. 6 3.8 4.1 4. 4 4.7 5.0 2. 8 2. 9 3.1 3. 3 3. 6 3.8 4.0 4. 50" 4. 9 5.2 5. 4 S.B 6.2 6.6 7 . 0 3. 9 4. 1 4.3 4.7 5.0 5. 4 5. 7 ~ .,~ 4, 75" 5.a 6.1 6. 3 6.a 7. 3 7. a a. 2 4. 6 4.a 5.1 5.5 5.9 6. 2 6.6 ~~ . 1Yl rt15~ . 0~0~"j~t6j.a~=7t·j11j7~·f4tj7j. 9ttfa .~5~~9t·tOt~9~.t 5 tf5~. 4[jt5~·i6t~5~· t9tt6~. 4~=t6 . ~a~j7~.~2tj7~.6t1 ~5~. 520~"~7.9~.0~9~.~4~9~. ~af,1~0~. 5~1~1.~2~1~1~.~9+1~2~. ~5~7~.1~72.~4~7~.*a~a~. 4~~9.~0~9~. 7.5+1~0~.101 l ~" B-LOK 5. 75" 10 . 310. 811.212.012.813.6 14 . 3 8.1 8.5 B. B 9. 510.210.8 11.4 UNlTEDSTEELDECK, IN C. 6.00" 11.812.312. 713.614.515.416. 2 9.2 9.610. 010. 811.512.212.9 4. 00" 3.5 3. 7 3.9 4.2 4.5 4.8 5.1 2.a 3.0 3.1 3.4 3.6 3.9 4.1 4. 50" 5.0 5.2 5.5 5.9 6. 3 6. 7 7.1 4.0 4. 2 4.4 4. 7 5. 1 5.4 5.7 4.75" 5.8 6.1 6.4 6.9 7.3 7.B 8 . 2 4.6 4.9 5.1 5.5 5.9 6.3 6.6 ~lTo 5 . 00" 6 . 8 7 . 1 7.4 7.9 8. 5 9.0 9.5 5. 3 5.6 5.9 6. 4 6 . 8 7.2 7.6 1 '12 · I CW 5. 50" 9.0 9. 4 9.810.511. 111.812.4 7.0 7. 4 7. 7 a. 3 8.9 9.410.0 I y," LOK·FLOOR 5. 75" 10 . 210.711.111.9 12.6 13 . 4 14 . 1 8 . 0 8.4 8.8 9 . 4 10.0 10.711.3 UNITED STEEL DECK, INC. 6 . 00" 11.612.212.613 . 514.315.115.9 9.0 9 . 5 9 . 910.611.312.112. 7 4.50" 4.6 4. 9 5.1 5.5 5. 9 6.2 6.6 3.7 3.9 4.1 4.4 4.8 5 . 1 5.4 5.00" 6.2 6.5 6.a 7. 3 7. a a.3 a.a 4.9 5.2 5. 4 5.9 6.3 6.a 7.2 5.25" 7.1 7.5 7.8 8.4 9.0 9.5 10.1 5.6 6.0 6 . 2 6.8 7.2 7.7 8.2 D '" 'I ~ ' I· 5.50" 8.1 8.5 8.9 9.610.210.9 11. 5 6 . 4 6 . 8 7.1 7.7 8.2 8.8 9 . 3 ~~~ 2·· 6 . 00" 10.511.011.412. 313.113.914.7 8.3 8.7 9.1 9.810. 511.211. 8 2" LOK· FLOOR 6.25" 11.812.412.913.914.7 15.6 16.5 9 . 3 9.810.211. 011.812.613.3 UNITED STEEL DECK, INC. 6 . 50" 13. 3 13.9 14 . 5 15.5 16.5 17.5 18.4 10.4 11. 0 11.4 12 . 3 13.2 14.0 14.8 5 . 50" 7 . 8 8.2 8.6 9.2 9.8 10 . 5 11.1 6.2 6.6 6 . 9 7.4 8 . 0 8.5 9.0 6 . 00" 9 . 810.310. 711.512.313.113. 9 7.8 8.2 8.6 9 . 310.010.711.3 '.' 6 . 25" 10 . 9 11.5 11.9 12.9 13 . 7 14.6 15.5 8.6 9.1 9.610.411. 111.912.6 ~IIo.~ . ' : ~ 6.50" 12 . 112. 7 13.314.315.216.217. 2 9. 6 10 . 1 10 . 6 11.5 12.3 13.2 13 . 9 7.00" 14.9 15.6 16.3 17.5 18.6 19.9 21.0 11.8 12 . 4 13.0 14.1 15.0 16.1 17.0 3" LOK·FLOOR 7.25" 16.417.318. 019. 320. 621.923.113. 013.714.315.516.6 17 . 7 18.7 UNITED STEEL DECK, INC. 7 . 50" 18.119.019.8 21.3 22.6 24 . 1 25. 4 14.3 15.1 15.7 17.0 18.219.4 20.6

*The 'I' values shown in the table ha ve been calculated by usmg the transformed section method of analysis - concrete converted to eqUivalent steel. The averages of the cracked and the uncracked I values are shown, Use E= 29,500 ksi (and the I shown) for hve load deflechon calculallons. All values are based on UNITED STEEL DECK, INC. deck secllons.

. ~i;rL~ I - ~'( P ~ r - - t2 ~ '- - MEMBER p~ - - -- ~L~\~\-~ UJ,f-JL.~~::<::::L.It NICHOLAS J. BOURA S, INC. ~~ ~.~ • • ~ h PO BOX 66'2. 4 75 SPRI CIIEI 0 AVI '. ,~~ ,. SU \1\1IT, f\\ IIRSn 079011 20 11 '277 161 7 ~TEIoEM8E'" • When it comes to constructional plate steels, widths 12" to 48" and thicknesses:y." to 12." we wrote the book. This current edition features Lukens-Conshohocken. A rolling mill and ship­ Lukens' capabilities with regard to: ping complex designed to meet your needs for Sizes. Standard specification plates available in light-te-medium thickness carbon plate and our widths to 195," lengths to 1250" and thicknesses Sure-Foot safety floor plate. to 25." A size card shows details. Lukens Flneline." A family of low-sulfur con­ Specifications. Mechanical properties and structional steels particularly effective when chemistry of the various grades of steel most used in fracture critical applications. frequently found in bridges and buildings. Dis­ For your copy of this brochure, illustrated played in chart form. with photos of our facilities and our products in Heat Treating. Offered on plates up to 890" long. use, just fill out the coupon below. Stripped Plate. An alternative to universal mill plate in applications such as fabricated bridge girders. Produced in lengths from 120" to 1250," ~UKEN1S5TEE~

LUKENS STEEL COMPANY I Write Ir------~ 586 Services BUilding I CoatesvIlle. PA t9320 I I Please send me 8 copy of your brochure, LUKENS CONSTRUCTIONAL I right I PLATE STEELS I I NAME I I TITlE I now I COMPANY • AOOflESS I ~ IL CITY ______STATE liP I MODERN CONGTRUCTION VOLUME XXIV NUMBER 1 FIRST QUARTER t 984 Published by • American Institute of Steel Construction The CONTENTS 400 North Michigan Avenue , 60611 Beth Israel: Unending Symphony in Steel 5 A Tale of Two Bridges 10 OFFICERS New Engineering for Steel Construction Released 14 John H Busch. Chairman Werner H. OU8sebarth, 333 Wacker: Building with a Historical Flourish 17 First Vice Chairman Cedars-Sinai: Space Where There is None 22 Charles P LewIs, Prestonwood Baptist: Steel Wins the Roof "Sweeps" 26 Second Vice Chairman Welded Steel Duct Bridges Factory Buildings 28 Oscar W Stewart, Jr.. Treasurer Richard G. Altmann, President William W lanigan, Secretary & General Counsel Geerhard Hssljer 1984 PRIZE BRIDGE COMPETITION ANNOUNCED Vice President, Research & Englneermg Entfles for AISC's 52nd Prize Bndge Compelltlon-to select the most LewIs Brunner. beautiful bridges opened during the penod Jan . 1, 1982 through June 30, Vice President, Marketmg 1984-8re now being accepted. A distmgUlshed panel of professionals has been named as the Jury of Awards:

EOITORIAL STAFF Edward V, Hourigan, Dlfector-Structures Design and Construction, New • George E Harper, Editor of Publications York Dept. of Transportation, Albany, NY Amy Kragnes, Edltonal Assistant Richard W, Karn, President, 8/ssell & Karn, San Leandro, CA ; Presldent­ James Herman, Business elect of ASCE Thomas R, Kuesel, Chalfman, Parsons 8rmckerhoff Quade & Douglas, New York, NY Charles Selm, Prmclpal, T. Y. Un International, San FranCISco, CA Harry Weese, Chalfman, Harry Weese & AsSOCiates, Chicago, IL REGIONAL OFFICES

NORTHEAST REG ION Judgmg of entfles will take place on September 18, and the winners will New York. NY (Hdq ) 212'695-4291 be adVised shortly thereafter on the jury's decision, Wmners will be fea­ BeSl00. MA 6171329 7417 tured in the December Issue 01 Englneenng News-Record. Award pres­ Ph iladelphia, PA 609·858·· 9354 entations to the winners will be made at AISC's prestlgrous Fourth Annual PlIlsburgh. PA 4121443 8840 Awards Banquet in Chicago on December 4th. SOUTHERN RE GION All entnes must be postmarked not later than September I, 1984. Further Allanta GA (Hdq ) 404/458-7679 details and entry forms may be obtained from: AfSC, Awards Commlftee, Charlotte. NC 704/541 0960 400 N, Michigan Avenue, Chicago, IL 60611 -4185. Dallas. TX 2 141630.5236 Houstoo. TX 713/2706363 ENGINEERING FOR STEEL CONSTRUCTION NOW RELEASED I CENTRAL REGION The all-new Engineering lor Steel Construction IS now available. A brand­ Chicago. IL (Hdq ) 3121670-2400 new text for advanced detailers and design engineers, the book IS keyed DelrOit. MI 3131352·5558 to the 8th Edition Manual 01 Steel Construction. A musl for every deSigner's Minneapolis. MN 6121888-379t St Lo",s, MO 314721- t332 reference sheff, it eontams design and detailmg procedures for more complex eonneel/ons and structures. 370 pages, with over 315 drawmgs. WESTERN REGION Los Angeles, CA (Hdq ) 8181444-4519 See the summary on page 14, and the ad on page 25 for instruction on Denver CO 303183 1-4622 ordermg. Order today for early delivery! San FranCISCo. CA 4151932 -0009 AISC HEADOUARTERS Chicago IL 312/670-2400 GOVERNMENTAL AFFAIRS Washington, D C 2021466-5548 I •

MOOERN STEE L CONSTRUCTION Beth Israel Hospital: Unending Symphony of Flexibility

by Elliot Paul Rothman, Terry A. Louderback and Apostolos M. Antonopoulos

he Beth Israel Hospital In Boston. The scheme chosen utilizes 3 V. -In light­ lIanges of each cantilevered glfder. With TMass IS a tightly grouped complex of weight concrete topping on 2-ln. compos­ appropnate stiffener plates Interconnected structures bUilt at Intervals Ite steel deck supported by composne The Reisman BUilding IS similar to the that began In 1928. The most recent round structural steel beams and glfders The Dana Research BUilding In ItS vertical ex­ of construction. known as "The Prolect," scheme offered lightweight. shallow struc­ pansion upon the onglnal steel frame de­ Includes four major structures Reisman, tural depth and a relatively high degree of signed for future loads. Here, however, the Libby. Stoneman and Northeast Buildings. rigidity for the moment-resisting frames deSign problem was somewhat dillerent a total of $44 million of construction In By Introducing light gauge steel studs as The onglnal lateral force resisting system addition. Immediately p[lor to beginning backup for the extenor bnck as well as at (steel moment resisting frames) was design work on The ProJect . the team de· cnllcal Intenor partitions, the team was based on a maximum uitlmate bUilding signed the new $12·mlllion Dana Blomed· able to provide the owner With one more height of approximately 110 It above the Ical Research FacIlity also at the Beth Is· lloor (about 17.000 sq It) than was pos­ roof of the onglnal deSign IntrodUCing rael Hospital. Each new structure reqUIred Sible uSing the onglnal type of construc­ lightweight matenals. such as composite innovative solutions to varying sets of lion- and Without compromlsmg the steel glfders and beams supporting com­ problems sound lloor construcllon the owner and poSIte steel decks plus lightweight con­ team demanded As a resuit. live new crete lloor topping and light gauge steel Lightweight Construction Gains 35,000 lloors were provided Instead of four studs. the lloor·to-lloor height was kept to Sq Ft Not Otherwise Possible One of the interesting structural features absolute minimum (12 ft on upper lloors) For the Dana Biomedical Research BUild· of thiS bUilding was that the fabflcator Nine additional stones were bUlit upon the 109 the problem was to maXimIZe the total elected to fabncate columns With canll­ eXlsllng structure. Instead of the eight pos· 1I0or area above the eXisting four-story levered glfders as "trees' so the glfdel Sible If new construction was the same as Siosberg-Landay BUilding which was o[lg- section could be continuous through the the onglnal deSign That IS a net Increase . ,naIIYdeSigned for lIexlblllty and future ver­ column while the columns were spliced at IIcal expansion of lour new lloors Member mid-height This resulted In a shop-welded sizes were based on luture construction moment connection (the structure resists With the same configuration as the onglnal lateral Jorces by moment-resisting Irames) Boston 's Beth Israel Hospital Model photo deSign. Ie 4 V.-m. solid one-way slabs on between the ends of each column and the and legends show multiplicity 01 remodel · non-composite structural steel beams To Ing Campus plan al lett Photo by Peter maXimize the number of additional lloors. Vanderwarker yet maintain the quality of Ihe onglnal con­ struction. several alternative Jramlng schemes were Investigated

ElI,ot Paul Rothman, A I A IS a director 01 the arChItectural hrm of Martha L Rothman-ElhOl Paul Rothman Inc BoSlon . Massachusetts Terry A Louderback, PE,s a pnnClpalln the structural englneenng firm of Souza and True Inc Watertown . Massachusetts Aposlolos M Antonopoulos IS an engineer In the structural englneenng firm of Souza and True Inc Watertown . Massachusetts

~

• Hartt! ffi

151 Ouarter 1984 5 of 18,000 sq ft of floor area. These reduced from the fourth floor up. No new structure Steel Solves Complex Building floor-to-floor heights required very close could be permitted below. By using Requirements coordination among team members. Un­ trussed supports at each existing column , Perhaps the most challenging structural der the present building program, Ihe hos­ and interconnecting these supports from problem was Ihe Northeasl BUilding. ThiS. pital is constructing four new floors , plus floor to floor, Ihe new loads are Iransferred new structure is contiguous to three ex numerous rooftop penthouses, the roofs of through bearing at the ends of the istlng buildings-Rabb, Gryzmlsh and Ya­ wh ich can serve as future floors. compression diagonals into the eXlsllng mins- each of a different type and era of The Libby Building Computer Medicine columns. Cantilever moments, due to new construction. Among the important con­ Facility, partially below grade, is a one­ conslruction, are Iransferred Into the ex­ siderallons In the selection of a structural story re inforced concrete structure at ­ isting structure at each floor (and roof) by system were: 1) relatively shallow con­ tached to the libby BUilding and con ­ hOrizontal compression and lenslOn struclion was reqUIred to provide ample nected to the hospital complex by a tunnel. forces. The horizontal components of Ihe headroom while matching the floor-to-floor The structure was designed for future ver­ compression force on Ihe diagonal struts heights of the eXisting buildings; 2) certain tical expansion of three additional floors. tend to neg ale the tension force In Ihe hor­ portions of the eXisting buildings, which izontal members at all levels, except the were eventually to be demolished and re­ Innovative Upgrading of Existing roof and lowest floor, where special con­ placed with new construction, were to re­ Patient Rooms to Standards nections are provided to transfer unbal­ main in operation while construcllon of the The Stoneman BUilding will be expanded anced horizontal forces. Construcllon IS new bU ilding was underway; 3) the multi- laterally to provide more spacious pallent light weight to minimize the Increased load use nature of the new building required rooms consistent with rooms in the Reis­ on Ihe exisling structure Each column and different live loads at different floors, but man Building. The structural solution 10 en­ foot ing in Ihe existing struclure affected by for coord ination reasons the depth of larging the patient rooms in the Stoneman Ihe new construction was checked and structure was to remain constant. This Building evolved from the criteria that the found to have adequate reserve strength characteristic was critical in coordinating east rooms be expanded by 8 ft , but only to safely support the new loads. the work of Ihe mechanical, plumbing and electrical trades . •

- Steel framing of Northeast BUilding met most challenging structural problems In complex remode ling •

6 MODERN STEE L CONSTR UCTION Given the above criteria , several framing Ease of Super·Structure Construction The only way to accomplish thiS was to schemes. both In concrete and In steel. Next to Existing Buildings use lightweight structural steel Therelore, were designed and priced. The prel,m,· One 01 the earliest lactors which led to a It was deCided to change half 01 the first nary conclusion was that for the super· re·evaluatlon of the onglnal concrete de· bay adlacent to the Rabb and Gryzmlsh structure, the most economical design ap· • sign was that construction of a portion of bUildings from concrete to structural steel peared to be a u",depth, one·way, rein· the Northeast BUilding would extend over forced concrete, ribbed slab, supported the eXisting Rabb BUilding. The Rabb PhaSing by wide reinforced concrete girders. The Building had been deSigned lor futu re ex· The need to maintain access to the Ber· relative costs of the different systems were panslon, but not to the degree required for enson Emergency Unit had a tremendous based on costs of matenals at the time of the Northeast BUilding. The eXlsllng col· Impact on construcllon of the Northeast the preliminary designs umns of the Rabb BUilding were not ong· BUilding A COrridor had to be maintained Events that took place as the design of Inally deSigned to support a concrete from the temporary entrance at the Yam Ins the Northeast BUilding evolved clearly In· structure. The possibility of construcflng BUilding to the emergency unit In the d,cate the fleXibility and cooperalion a de· new Northeast BUilding columns down Gryzmlsh BUilding In two areas, the first sign team must display to achieve a suc· through the Rabb BUilding was ,nvest" floor 01 the Northeast BUlfdlng overlapped cessful prolect. FollOWing the preliminary gated. but rejected lor several reasons. the emergency COrridor With the concrete drawing stage, the design process contln· Amongst the reasons was that foundalions scheme, these areas would have been ued to assess more factors upon which for new columns would have to be bUilt 10 omitted and placed later InSide a complete the chOice between structural steel and to 15 It below the lowest floor levet at Rabb bUilding Two columns adlacent to the concrete would depend These factors and adlacent to targe air handling equip, Gryzmlsh BUilding one on either Side of were grouped Into three broad categories: ment which had to remain In operation the emergency COrridor were changed super·structure, phaSing and foundations. The Simplest and most pracllcal solution from concrete to steel so they could be seemed to be to bUild on the eXlsling steel dropped IntO place The space available columns. uSing their additional capacity for construction did not allow enough room even for formwork.

DeSign cnterla for Northeast BUilding •

DESIGN CRITER." Future Conttructloft """'. ,.... ,.... l.=." _l...,dlon g._ • 1 o."iIn ~. lhown ,n poonds per lCI~re ,"" I!:::'"' (30) I - I t:1.. o.~ l __ Z For .1Iow.bIot 11,1"'" eoiumn Ioads_ aotOf " column ~ule ~...... l_ 1 1 -/301M'I1 3 0..0 load .'lOWance lor lulu.1I 1l00f - eontlllJ(:toon bUed on pr_"y tJ\OWn ,. ," eon'IPQl'hon "ab tystem ,- . .. . FI_1 ,. ,. " DoNo load .1I0wIU'IC. lor lulllfe roof .. c:onsltlJctlOn based on "fI4'! 6eck' IlUITI PNMftI CoMtrucUon .ystem anown lor root 01 .mI"'on 10 RAB8 BUILOING ...... U>AOS .s SUp.nmpONd Orl over ."uC'lur.' addItion -- 10 RABH hal not 1M«! Oro'<'~ IOf _. .. ,. .. 7 Tote! """0'" ot e.a:ttriof cum·" WI. FI_ 3 ,. IVSttm. Includlrog 'l't1IflQf CIIIOd"'O ,nd ...... "-c.', .. b.ck"'l>p ,hall not ••CMd SO P • , , - ,. NorttMel' &.1(1,"9 "- , .. $I'ucl..... A

15t Quarterl1 984 7 The construction manager, aller study­ Site excavation would have required gen­ of the bay. The same size W14 was used Ing the conflicts between new and existing eral dewatering of the site and the dnving throughout the building. Resultant floor construcllon, and the phasing difficulties, of sheet piling to maintain an access road depth was 20 in" the same as for the con - suggested that, for ease of construction , from the street along the Northeast Build­ crete scheme. The key to the success Of . the rest of the bay adfacent to the Ing to the rear of the Beth Israel site. To the structural steel scheme still was ItS Gryzmish Building be converted to struc­ reduce the required excavation and elim­ compatibility with both the architecture tural ste el. The columns, girders and Inate the sheeting and dewatering, engi­ and the mechanical work. beams could be erected under, over and neers considered caissons. With the con­ around the emergency corridor and the crete building, a low allowable bearing Creative Detailing In Structural Steef slab and deck placed later when the cor­ value of 3.5 tons per sq fl. and the depth Architectural requlremenls dictated that ndor was no longer needed of clay available for construction of the moment-resisting frames should be used A major element of the Northeast Build­ bells, caissons would not work. for lateral braCing . The number of frames Ing and the Emergency Unit IS the en­ reqUired was determined, and the frames trance cancpy, which provides for cov­ Steef Accommodates Multi-use were located so there was a path for me­ ered ambulance parking and mechanical Buildings chanical ducts 10 travel under the 20-ln. areas. As the canopy design developed, All factors Indicated a re-evaluallon from deep structure. At pOints where ducts the consensus of structure, given the long concrete was required. A more complete crossed under heavy girders of the mo­ spans required and the limestone facade, design was completed. which was spe­ ment frame , close scrutiny of mechanical was structural steel cific for two of the tYPical floors. As men­ deSign and the architecture permitted 21 - lioned earlier, different live loads were re­ In . deep girders. By raising the moment Effect on Foundations qUired at vanous floors. The second and frame girders 3 In. abcve the soffit of the The last factor which probably had the flllh floors reqUired live loads of 150 psf. deck, 24-1n. deep girders could be used , greatest Impact on the chOice of structure The remaining floors needed only 60 psf. greatly redUCing the reqUired weight of was the building foundations. With a cast­ The lightly loaded floors were designed steel. The deeper raised girders, besides In-place concrete structure. very large With composite beams generally at Ihlrd haVing smaller flanges which made the spread footings, or possibly even a mat­ pOints of the bay, W14 With 2-1n. deck and moment connections more economical, or a combination of the two-would have 4 V. -in. lightweight concrete. On heavily also made the frames stiffer and reduced been reqUIred for foundations. Construc­ loaded floors. the same slab and deck fabncatlon costs of the beams Because lion of the footings would have reqUIred were used as well as the same beam de­ the top of the girder was 3 In. above the general site excavation about 15 II below sign, but the beam spacing was de­ top of the beam , coping at the top beam the lowest level of the Northeast BUilding. creased from third pOints to quarter points flanges was not required (Fig . 1). ~------'. BUYor RENr - NEW or USED YOU'LL SAVE TWO WAYS WITH MI·JACK

• MI-Jack Droit Traveliff crones handle long loads sofely and efficiently .. . operate like on overhead traveling crone without fhe installation cost .

• MI-Jack offers single SOU rce soles, rental. service, technical assistance, yard layouts ... soves you time and money. 15 TO 350 TON CAPACITY • MANY MODElS IMMEDIATELY AVAILABLE • Colu"", Provkle ""1 I. 's " reefd For ".nt<:at ahg"'F'/Ief'II of we weld II I 10 Mam Weld R. _ 12" to R. • • Deck ClQwr.

Wl0 .

Slllt III J .a SIde ""41

Raised Girder

_ 18 a· TIp 01 Angl • • ~t • ..eh.!eM I 01 Column Web '." ml" ..,.m I .~C. ~~k-it~ t:=::J:~~H r '4 ~ Typ. , .,..... 1 R.. 'h' It 5" ,,0' 10" WlO _ .:.. Hom ahgn~t 01 angle "" ~ Steff R.. .. side t-- -­ 10 M accomplllhe(! b)' W24 __ ...n alignment 01 we Wl0 _15 __ Pro~loe ~er1 tk)t ,,., It.. ~ .. 1, W6 tor...., IllQnlMf'll LS II S galv.n'le

Figure 1 Northeast BUilding raised girder and girder connection details

In Ihe Northeast, as well as In the Reis­ L4 11 ·h3!81 man BUilding brick relief al each floor IS elt ... KI~ lm.... ;"e 01 L 5 15 -l'11). continuous and was achieved without the

need for diagonal "kickers" which often In­ Floor 3 $El &6 '-0" + • lerfere wllh services In Ihe ceiling space Vertical channels supporting Ihe hOrizon­ lal angles are supported from perimeter w.o . beams and girders by cantilevered Wide­ WS_lO ' - lIange stubs which are. In turn. backed up by beams framing perpendicular to the perimeter beams or girders (Fig 2). For FIgure 2 E)(tenor wall section shows re hevlng angle suspended from cantilevered Wide-flange stubs

Architect perimeter beams which span parallel With was slruclural steel The change Irom con­ Martha L Rothman·Elhot Paul Rothman Inc 1I00r beams. supplementary backup crete to sleel became even more favorable Boston, Massachusetts beams were added to align With each relief when sleel prices dropped dUring Ihe lime Structural Engineer angle support between preliminaries and re-evaluatlon Souza and True Inc When Ihe slructural portions of the Watertown, Massachusetts Advantages of Steel Construction Northeast BUilding were completed, Ihe Construction Manager By changing Ihe Slructure from concrete CM had saved nearly Ihree monlhs of con Jackson Consuuctlon Company to steel, caissons became a Viable foun~ SlrUCtlOn time by uSing sleel ralher Ihan Dedham Massachusetts dation scheme. Con5equenJly general concrele And In addition to Ihe time Geotechnical Consultant site excavation was reduced and Ihe re~ saved prelimInary estimates tndlcated Geotechnical Engineers Inc qUirements for sl1e dewatering and sheet that from $500.000 10 $750.000 was saved Winchester, Massachusetts piling were eliminated Deep cantilevered In Ihe cost of the lolal slruclure grade beams reqUired to sUPPOr! new col Steel Fabricators The Norlheasl BUilding and the se­ Montague-Bens Company Inc (The Prolectl umn5 Immedlalely adiacent 10 Ihe eXisting quence of evenls which led to liS comple­ Lynchburg Virginia structures were reduced sIgnIfIcantly In tion, affords a good example of the :lexI­ depth billty and Ihe creativity pOSSible In Haarmaan Steel Corporation (Dana BUildIng) After the deSign leam Identified a struc­ construction wllh Slruclural steel All of the Chicopee Massachusetts tural system compatible wllh architectural new bUildings al Beth Israel Hospllal each Steel Erector and mechanical syslems. the conslructlon wllh liS unique sel of SlruClural deSign • Daniel Marr & Son Company manager could develop a total structural problems offered a challenging assign· Boston, Massachusetts estimate whIch accounted for the cost of menl 10 the deSign leam Siructural steel Owner struclure. both superstruclure and foun­ has been used effectively to prOVide Ihe Beth Israel Hospital dallons. and ti me of completion The CM's owner wllh well~englneered economical Boston Massachusells analYSIS Indlcaled clearly the best malerlal and funCllonal spaces 0

151Ouarter 1984 9 Bridge Rehab with Speed and Low Cost . .. A Tale of Two Bridges •

1. Railroad Bridge modify details of the Similar HNTB deSign in Missouri . . . to comply with the railroad's. The prevIous HNTB deSign was based on a 250-ft span. whereas the damaged bndge was only n May 3, 1982. a middle span of the 246 ft-3 In. ONorfolk & Western RR bridge at Han­ Shop del all draWings and calculations nibal, Mo was struck by out-of-control were completed by In-house Bnslol En ­ barges One span wenl Into the MIssIs­ glneenng and submitted on schedule 10 sippI River and the end post of a second Ihe engineer within three weeks. The fab­ span was damaged. The steel structure, rication schedule to commence delivery In In service Since 1887. IS a part of the Nor­ early July could only be accomplished by folk & Western line linking Kansas C,ly and fasl-Iracklng the production process The the Chicago/Detroit area. Rail Iraff,c was erection sequence, established early In. significantly Impacted. and It was neces­ the conlract. allowed producllon to assign sary to divert traffic south Ihrough SI. a priority number to each shipping piece. LOUIS , with added expense and eXlended Both trusses of the structure were pre­ schedules assembled and knocked down In the shop Norfolk & Western faced the lask of re­ to Insure field fit-up pairing or replacing the damaged slruc­ Fabncated matenal started shipping to ture In the shortest time and at a reason­ Ihe site on July t 6. Crews were already able cost They explored these mobilized and Immediately starled assem­ pcssibllities: Runaway barges badly damaged Norfolk blyof Ihe bndge slruclure on three barges. & Western RR bridge at Hannibal, MO 1. Repair the damaged section of the ex ­ When the assembly was completed, the Isting bridge. barges were floated near Ihe removed 2. Replace only Ihe damaged part of the span. and the bridge was hOisted as a bridge while uSing the undamaged complete unll The ereclor used a barge­ Howard Needles Tammen & Bergendoff structure mounled Manitowoc 4000 10 assemble Ihe was selecled because Ihey had recently 3. Construct an entirely new bridge. truss structure on barges. A derrick barge designed a Similar Iruss bndge thai could 4. Search for a completed structure that lifted Ihe 465-ton structure Into place on eaSily adapt 10 Ihe rallroad 's needs. August 2 was no longer In use, or In limited use While the engineer was being selected. ThiS struclure would be purchased and A speCial problem Ihat had to be solved railroad personnel concurrently negoll­ altered to meet the railroad's needs. was Ihe need to deSign different bndge aled with several sleel fabncalors. Fabn­ beanngs for the new struclure The new Alternate one was eliminated due to Ihe cators were asked to quole a pnce and truss span was sllghlly deeper than Ihe extensive damage and the associated construction schedule based on a very eXlsllng one, thus the difference In depth costs of salvaging materiaL Alternate three open scope of work and without benefit of had to be laken up by the beanngs so the was not feaSible for schedule reasons. AI­ bid drawings. Requlremenls were de­ Iracks would align. Also, additional lime ternale four was explored. but such a scnbed verbally by Ihe owner and engi­ was gained In the field by Ihe deCISion 10 structure could not be found . neer. and Ihe fabricalors had 10 depend 11ft the assembled unll With a crane rather Replacing the damaged span with a on past experience to develop a proposal than Jack the unit Into place ThiS reqUIred steel structure proved Ihe only feaSible al ­ Norfolk & Western awarded Ihe con­ less speCialized equipment and conse-. ternative within the time constraints. struction conlracl lusl Ihree days after the quently less time for field mobilization. Immediately after the aCCident. Norfolk aCCident based on bOlh price and sched­ And the railroad was complelely oper­ & Western Interviewed several engineer­ ule. That same evening. the fabricator's allonal exactly Ihree months after the Ing firms for designing a new Iruss span. represenlatlves mel with the engineer to aCCident'

t o MOOE RN STEEL CONSTRUCTI ON TfUSS span was held-erected 00 barges Field bolting 01 panel point IS completed A BN-deslgned bfldge was mocMled by one mile north of brtdge Tolal erection Over 32.000 7/8-ln A325 high-strength removing 6 in between each panel point time was eight working days bolts were used on brtdge

New Iruss IS lifted to clear piers (above), Structural Engineer swung Into place and lowered onlo bear­ Howard Needles Tammen & Bergendoff Ings (I) Totalltft lime 45 mInutes Within Kansas City Missouri SIX hours 'Irst train passed over new span Steel Fabricator Bristol Steel CorporatlOl1 SI LoUIS. MISSOUri Steel Erector Bristol Steel Corporation enstol, VIrgInIa Owner Norfolk & Western Railroad • Roanoke, Virginia

1s t Quarter 1984 11 2. Century-Old Truss Bridge in Pennsylvania ... A century·otd steel truss bridge In Coud­ ...;~!~::"'] New hfe for rehablhtated 100·year old truss ersport, Pa. has been rehabilitated to six bridge al Coudersport. Pa (below) Bridge can carry SIX limes prevIous load limit times Its previously permllled load-carry­ Closeup of new steel reinforcing arch (I.) Ing capacity And the Job was done at a that made It possible • cost of only one thlfd that of a new bridge replacement to meet all modern stand­ ards The Coudersport span IS the flfst appll­ calion of the unique truss bridge reinforc­ Ing system Introduced last year by two Civil engineering professors at Bucknell Uni­ versity. Lewisburg, Pa under a research grant from the Structural Steel and Steel Plate Producers of AISI Already, a second application IS the re­ habilitalion of the Roaring Creek Bridge, bUilt In 1890. near Elysburg, Pa In addl­ lion, consideration of the plan IS underway by counties, consulting engineering firms and state highway departments from Maryland to California With thousands of old truss bridges. erected In the late t800's and early 1900's. now In seriously deteriorated condition. the plan's low cost appeals to many localities which do not have funds for new bridge construction. BUild ,n 1883, the single-lane Seventh Street Bridge was one of two that prOVide stall the bridge components Actual erec­ usual repalfi rehabilitalion schemes. the local access across the headwaters of the tion lime. by a crew of four , was only three weakest links are strenglhened to restore . Allegheny River In Coudersport The sec­ weeks The maximum traffiC Interruption the carrying capacity of the Original struc- ond bridge, too deteriorated for repalf, has was seven minutes! ture . often less than warranted by current been closed II was judged possible to Reinforcing steels were high-strength traffiC needs In thiS arch-dependent re­ save the aging Seventh Street Bridge, de­ A572 Gr 50 for arch sections and floor habilitalion. the carrying capacity of the spite buckled floor beams (restrained by beams and A36 steel for hangers and entlfe structure was upgraded, thus allow- cables) and a load limit lowered to only stringers Steels were generally fabricated Ing live loads to be Increased three tons. ThiS low capacity meant that as structural channels. I-beams. Wide­ The U S Department of Transportallon no fife trucks. garbage vehicles, ambul­ flange beams and I -In . square bars claSSifies 45% of all bridges as defiCient ances or school buses could enter that The bridge, which most recenlly had a or obsolete ThiS plan IS said to be prac­ part of the city three-ton load limit. IS now legally posted tical for all through-truss bridges In thiS Since there was no available funding for for a 20-ton capacity Developers of the condition a new bridge the Coudersport counCi l plan anticipate that. With reasonable main­ The system does not make new bridges chose another remedy- a truss bridge re­ tenance and traffic kept at or under the out of old ones . The Seventh Street Bridge Inforcement plan created by Dr Robert J new load limit. the bridge could well have remains the same In Its vertical clearance Brungraber. preSidential professor of ciVil a new service life expectancy of another deck Width. waterway openrng and ap engineering at Bucknell, Dr Jal B Kim . century proach roadway alignment chalfman of ItS Department of C,v,l Engi­ Rehabilitation began With replumblng But the big Improvement IS In structural neering, and an undergraduate student and stralghtenrng of the bridge With chain adequacy for modern loads Structural assistant. John Yadlosky . The underlying hOists. Improved connections were pro­ steel combined With englneenng Innova concept of the technique IS that the com­ Vided for the end portal bracing that pulled tlon made It all possible I 0 bination of a reinforcing arch With an ex· the span back Into shape Installallon then ISling truss system can carry a Significant entailed erecllon of a new structural arch extra load If It IS well-supported laterally on each Side of the bridge and reinforce­ Total cost of the complete rehabilita­ ment of a few critical members With pre­ tion funded by fuel tax money was fabricated parts. Then , new hangers. Structuraf Engineers $62.400 A new bridge at the site. a two­ stringers and floor beams. as well as re­ Robert Brungraber and Jal B Kim and-a-half-Iane facility to meet today's re­ placements for the Original buckled floor Buckne ll University LeWisburg Pennsylvania qUifed speCIfications would have cost beams, were Installed Finally. a slight up­ nearly $200.000. Besides the cost advan­ ward camber of the roadway was Intro­ Steel Fabricator/Erector tage of thiS plan. a primary benefit IS ItS duced for appearance Wlillamsport Fabricators. Inc erection speed and a minimal Interruption The prinCiple of the system IS not merely Wilhamsport, Pennsylvania • of traffiC The steel bUllderlerector met a reinforcement of the old bridge, but Virtual Owner GO-day time limit to both fabricate and in- replacement With a new arch bridge In the Borough of Coudersport Pennsylvania

12 MODERN STEEL CONSTRUCTI ON •

------"The Caoam Hambro® D-5oo composite floor system saved us "We cast this Hambro® lime, material and money when we used it to build our corpor­ ate headquarters. Congress Park IV." says Robert Satter. "We cast a floor one day and stripped it just 24 hours later. By then. comrosite floor today. it was ready for the sub trades to use as a work platform. rhe plywood and roll bars are reusable. And the job required no We'l strip it tomorrow." bridging, or on-site welding." Robert Salter, President Hambro's unique .L. fire-rated floor uses high strength steel. The Satter Companies, Inc., W. Palm Beach, FL It is twice as rigid as conventional Structures. Speedy erection reduces financing costs. Ideal for high or low rise commercial and residential buildings. And its sound ratings are superior. Another concrete rea:,on to specify Hambro is that "'c can guar­ antee fabrication within three weeks of approval of final drawings. Call or write today for D-5oo Brochure. Canam Hambro. 140 Gould St., Needham Heights. MA 02194. (617) 444 -5504. Telex: 95-1509.

GreenSpGlnl 1. Houston, TX GTEfHlnes. Westboro. MA Arch S I Moms Arch Drummey, Rosane, Anderson Engr Anderson -NJC:lOls & Co hambro Enor Walt!!' P MoOl' " Co e Cont McGregor Construclton Co Cont: 'lapp! & Co , Inc , Ovlpr Flilmdswood OtvelopmerU Co (Euon) We put a ceiling on the cost of floor construction, Engineering for Steel Construction, just published by AISC , delineates the most recent advances in connec­ tions and detailing for structural engineers. Here's a detailed summary . . .. •

Engineering for Steel Construction Reprinted courtesy Civil Engineering Magazine, January 1984.

by Robert O. Disque

tructural engineers are Increasingly S aware of the Importance of delalls and conneClions ,n steel structures These are not only the key to economy but also may be the source of trouble. For thiS reason . AISC has lust released a new 370-pg lextbook- Engmeermg for Steel Construction- for the advanced de­ taller and design engineer The new book IS a companion to Detallmg for Steel Con­ struction, which was wntten for the begin- ning detallerwho might have a high SChOOl . education Since both books are self-con­ tained , some matenal may be common to both Together, the books, which replace the 2nd Edition of Structural Steel Detall- mg, are geared to the 8th Edition Manual of Steel Construction Chapter 1: "Structural Englneenng" pre­ sents the theory and methods of appll­ callan used In the book to model design procedures for details and connecllons The Instantaneous center method for ana­ lyzing certain types of eccentnc connec­ tions IS descnbed, and references cited for simple solutions not available when the Manual was published Brackets are analyzed and detailed In two ways. A very conservative approach assumes the neutral aXIs of the bracket cOincides With the center of gravity of the bolt group A second approach deter­ mines the center of rotation by an Iterallve process where the static moment of the tenSion area equals Ihat of the compres­ Sion area Both procedures, which result In a more realistiC design, are Included in the book. Prying action .s fully expla.ned and .ts. vanous applications descnbed The pro­ cedure In the text IS based on that In the Robert 0. Disque IS Assistant Director of En ­ 8th Edilion Manual Prying action, essen­ gineering Amencan Institute of Steel Con­ tially, IS a phenomenon where the force In struction , Chicago, IUlnols a bolt ,n a hanger-type connecllon IS In-

14 MODERN STEEL CONSTRU CTION creased by the development of a prying January 1983 Journal of the Structural D,­ The procedure for deSigning the detail­ force Q Several combinations of bolt ca­ vIsion of ASCE Ing end-ptate connections was developed pacity and plate thickness can satisfy Single-plate shear connections are a rel­ by Krlshnamurthy. as presented In the 8th equations and static reqUIrements atively new Type 2 Simple connection AI­ Edition Manual The procedure IS empiri­ A new philosophy of material tear-out of Ihough II was In use for years. It was only cal. and IS based on phYSical tests and a • tension splices IS also Included In the ex­ In 1980 Ihat Prof Ralph M Richard of Ihe finite element analYSIS The result IS a Isting Structural Steel Detailmg material University of Arizona prOVided an analyti­ methac to determine bolt size and end­ was checked by equaling the allowable cal procedure for deSign . which IS In­ plate thickness However, no methac to shear stress of the material to the weld cluded In Ihls book determine column stiffener reqUirements capacity Thus 0 4F. = 0 707 (0 3)F w For Figure t shows a typical shear tab con­ was Included Stiffener requirements for F = 36 kSI and F = 70 kSI . the minimum necllon It has some Inherenl stiffness and end-ptate connections IS the subfect at a plate thickness IS t - 1 03w where W IS Improper deSign might disqualify II as a major research project at the University of the length of the weld leg The new pro­ Type 2 connection. Also. the rigidity might Okfahoma under the direction of Thomas cedure recognizes that malenal tear-out IS Impose force on the top part of the weld Murray At publication lime of Engmeeflng more of a block shear model. and new that connects the plate to the abutment for Steel Construction. research was not rules for this are Included In the past many connecllons have been complele Bul suffiCient progress has Chapter 2: "Metallurgy and Welding" deSigned With a moment equal to the re­ been made to recommend these tentative. acllon limes the distance a contains practically all the Information re­ conservative rules qUIred by the structural engineer on this 1 In the region of the beam compression subfect. TopiCS Include weidability. weld­ flange sllffeners are nol reqUIred when the Ing processes types of welds. welded column web t .. exceeds beam-to-column connections. electrode and process nomenclature. nondestruc­ I + P", live testing (NDT) methods Including ultra­ I + t. soniC and radiographic . fracture control I F. lt, + 5k + 2t. + 2w] I + and lamellar tearing I I + The factors which affect weld ability where P factored beam flange force. chemical composition. geometric proper­ kips. F speCIfied Yield strength of Ihe ties and grain size are discussed The ad­ columns kSI t, - beam flange thickness vantages and disadvantages of various In .. k - distance from outer face of flange welding processes are outlined to help the to web toe of fillet of column sec lion, In . deSigner and fabricator with shrinkage t, end-plate thickness. In w - end and distortion control problems and the plate fillet weld leg dimenSion. In It IS an ­ • text suggests ways to minimize lamellar tiCipated that final research Will permit 51< tearing to Increase to 6k or even 7k However, until then . 5k IS recommended Chapter 3: -Simple (Type 2) Connec­ tions- treats the behaVior and deSign of all 2 In the tension region. a rule of thumb Figure 1 TYPical shear tab connection popular connections-framing angles. IS proposed until research IS completed shear tabs. end plates. Single angles and ThiS rule IS conservallve. and states thai If Richards research Indicates thaI. for tees The chapter examines each poSSible the column flange thickness IS as Ihlck as design purposes. the moment should be failure mace and presents rules to prevent the bolt diameter (determined by Ihe calculaled by muiliplying Ihe reacllon by Krlshnamurthy. or Manual. procedure). them a + e (e IS determined as a function of For bolted connections thiS Includes then sllffeners are not reqUIred Otherwise connectIon dImenSIons and beam prop­ they are bolt shear material net shear. web tear­ erties. USing an uilimate deSign proce­ out (block shear) and Ihe effect of edge A welded beam conneciion Into the dure. the plate thickness and weld size IS and end distance on bolt bearing capac­ weak aXIs of a column has to be deSigned determined Ity For welded conneClions. new material and detailed With speCial care ResearCh IS presented for block shear on coped Chapter 4: "Moment Connections" In­ IS presently underway at Lehigh Unlverslly beams cludes the deSign and detailing of welded 10 determine how thiS connecllon can besl The question of eccentrlcilies on bolted beam-to-column connections. end plates. be deSigned to Insure It Will behave In a connections often arises For one-Sided flange plates. cap and seat angles and ductile lashlon once Ihe plastiC momenl of connections. eccentriCities on the out­ fleXible Wind connections The text em· the beam IS allalned Preliminary tests In­ standing legs should be accounted for phaslzes thaI. With a welded beam-to-col­ dicate that ductility coutd be Impaired If The 8th Edilion Manual Tables (Part 4) ac­ umn connection. the web of the beam the flange connection ptates are terml­ count for them For a Single vertical row need not be welded directly A better naled al the toes of Ihe column flange on the beam web. eccentnCltles have methac IS to weld a shear tab to the col­ Although final results are not yet In. several been Ignored traditionally. and no distress umns and bolt the beam web to the shear recommendallons have been made to 1m· has ever been reported For two vertical tab. Flanges of the beam are then held­ prove the connections rows on the web. however. less was known welded ThiS connection has been tested at the lime both the 8th Edilion Manual and thoroughly at Lehigh Unlversily and the t Use connecllon plales slightly Ihlcker • thiS new lext were published. so no pro­ University of Cal, fornia/Berkeley Those than the beam flange thickness cedure IS Included In either book. The au- tests have del ermined the connection can 2. Use backup stiffener thor recommends Joseph A Yura 's sug­ eaSily achieve the plastiC moment of the 3. Exlend Ihe conneCllon plate beyond gested block shear macel published In the beam the lips of column flanges

151 Quarter 1984 t5 Flexible moment connections designed and promote a uniform stress distribution Sized base plates. However, Since the mao to carry only the wind moment are also to the column lIange. If a non-uniform terlallncluded In the book a third method, treated In this new AISC text Several types lIange distribution eXists, Ihe beam·te-col· developed by Thomas Murray of Okla­ discussed Include cap and seat angles umn lIange weld could be overstressed homa University, has been proposed ThiS and lIange plates The text notes that determination of col­ method was published In AISC 's Engl'. umn web stiffeners should be the respon­ neermg Journal, 4th Quarter 1983, Rela· Chapter 5: "Skewed , Sloped and Sibility of the deSigner, rather than of the tlvely Simple, It IS expected to be very pop. Canted Beam Connections' IS an update detaller The reason IS that, for economy ular of a similar chapter In the 2nd Edition the deSigner might prefer a column with a Structural Steel Detallmg It Will be of more Chapter 7: "Framing for Heavy Con­ larger web or lIange to aVOid adding stlf· Interest to the detaller than the deSigner struction" Includes braCing , crane girders feners However, the deSigner should be aware trusses and heavy braCing connections As In the 2nd Edition of Structural Steel of the various eccenlrlcltles sometimes as­ Except for the material on heavy braCing Detallmg, the new text Includes details of sociated with these connections. One connections, It IS primarily an update of recommended column splices, Several change from prevIous detailing practice IS that In Structural Steel Detailing A heavy are shown, but the one which may need that all working points Will be located on braCing connecllon IS defined as a can· special attention IS the direct field-welded the material Previously, they could be lo­ nect,on InvolVing a column, beam and di­ splice A clean detail with no extra pieces, cated In space agonal brace Usually, very heavy loads It IS economical to prepare In the shop, are Involved, such as those expected In and uses minimal field labor Chapter 6: "Columns" Includes detailing power plants, Industrial structures and procedures, stiffener requirements and ThiS chapter also discusses the deSign hlgh'rlse bUildings deSign, bUilt-up members, lifting lugs, of column base plates The procedure In DeSigners differ Widely In the models splices and base plates Column stiffeners the 8th Edition Manual IS recognIZed as they use to deSign these connections For ultra-conservative In the case of small are required because of a local defiCiency thiS reason , AISC has underway a malar In column web or column lIange thickness base plates-those large enough In plan research prolect at the University 01 ArI ' In the area of beam compreSSion, lIange to Include lust the section profile The pro· zona which should be completed In a year stiffeners might be reqUIred to prevent col­ cedure In Engmeermg for Steel Construc· or so In the meantime, William A Thornton tlon , based on a Yield line theory devel­ umn web Yielding or buckling In the ten­ of C,ves Corporation has developed a pro· oped by R S Fling, results In reasonably Sion area, stiffeners prevent web Yielding cedure that IS Included In thiS new text 0

- ...... QUALITY PROCEDURES

OUALITY PROCEDURES CERTIPICAIION

• •••U • • • detailing firm follows prescribed draftmg room procedures designed to reduce the possibility of error • AS.UR •• compliance with specification • .S.U• • • Impartial evaluation of operations

FABRICATORS " .. your job demands the best. You can In rease the quality of your shop drawings and guarantee profesSionalism by uSing a firm certified under Ihe National InSlilul. of Steel Delailing QUALITY PROCEDURES PROGRAM, Contact: Baresel Corp. Central Detailing Service Corp. Dallas Detailing Co. 13320 Mapledale 140 S, Flower St., #20 t 2636 Walnut Hill Lane, #301 Norwalk, CA 90650 Orange, CA 92668 Dallas, TX 75229 213/921·6758 714/937·1573 214/350-7986 Gunther Baresel Jamie Gardner Robert Steger Fritz Baresel Ron Germaine

'.A. Free, ,r. & Co. • Inc. Schreiber & McGhee, Inc. P,O, Box 21007 P.O. Box 270580 Columbia, SC 29221 Dallas, TX 75227 803/772·4150 214/388-0674 'oe A. Free, Jr. Tom McGhee ·The National Institute of Steel Detailing Quality Procedures Program is administered by Abslech. • t6 MODERN STEEL CONSTRUCTION Steel Construction Readership Survey Please check and mail. No postage necessary.

IS No 2 Is MSC circulated In your office? Yes No '. How many people read It? __

JS your 'Irm? Check 4 Appro)l'Imaleiv how many are In your I"m? Check Sleel Fabncator 6 Less than 10 Supplier to Industry 7. 10-20 Government Agency B. 20·30 DOT 9 30·60 Educator 10. 100·300 300 or more Modern Steel ~s your functIon? Check 6 Are you dIrectly responsible lor specifyIng the type of framIng used 1 for the proJects designed by your firm? 2. 1 Yes 2 No Construction 3 4. 5, 6, 8 Do you read (scan) Readership 1 every Issue 2. most issues 3. some Issues structlon. do you mostly: Survey 4 no Issues

~odern Steel ConstructIon of 10 Are the articles techOlcal enough? ~o 1 Yes Too technical? 1. Yes Please check and mail. 2. No 2 No

No postage necessary. lhons do you read regularly? In structural englneenng design area, how do you compare MSC With • others you read? Check Better than As good as Not as good as Can't compare 1. 2. 3. 4, 5 6. 7. 8

yould you like to read In MSC? 14 Of the bUIldings your firm designs, what percentage are steel-framed __' 0 concrete-framed __%

1000/0

15 Of the bndges your firm deSigns, what percentage are steel __O ~ concrete __% ~ur firm primarily engaged? 100% _ _ ~ o __% 16 Are you a member of A1SC? __0' 0 1. No Which type? Achve Member 1 __~o 2. Yes ASSOCiate Member 2. _ _ 0,,0 Prolesslonal Member 3 -_% _ _ 0,0 17 Do you have any other comments on Modern Steel Construction __ 0, or Amencan Institute at Steel Constructfon you'd like to give us? _ _ 00 - _ % o • _ - 0 100%

Fold & Slaple •

NO POSTAGE NECESSARY• 111111 IF MAILED IN THE UNITED STATES

BUSINESS REPLY M A I L FIRST CLASS PER MIT NO 11588 CHICAGO. IL

-POSTAGE WILL BE PAID BY- AMERICAN INSTITUTE OF STEEL CONSTRUCTION 400 North Michigan Ave. ChICago, illinois 60611 hree cenlunes ago. Ihe French ex­ 333 : Tplorer LaSalle sleered his canoe pasl Ihe Slle ollhe new 333 Wacker BUilding In Chlcagos near Loop area . Building with a On a momenlous day In March 1982, a pompously coslumed -LaSalle,· pori rayed by a local educalor-advenlurer landed hiS Historical Flourish 20-11 canoe al Ihe bUilding Slle His amval marked Ihe beginning 01 lopping out cer­ emonies with local dig Manes, owners and contractors thai ended with Ihe hOlsllng of a commemorallve plaque 10 Ihe bUilding 's highest point, signaling complellon of Ihe sleel framework by Robert L. Miller The ambilion of every partlclpanf In a bUilding development owner to lenant archltecl and engineer 10 contractor IS to Robert L Miller was vice president 01 GeE of be Involved In outstanding prolects The IlliflOls . consulting engineers , when the 333 deSign disciplines hunger for profects that Wacker BUilding was under construction presenl challenges to stir our Imaglnallon, but not Just as a mental exerCise The frUits of our Imaglnallve efforts should be vltaf to the success of the profect Chicago's new 36-story 333 West Wacker DrIVe BUilding IS an excellent example of Ihls type of prolect The triangular site presented Ihe archi­ tects with unique challenges and oppor­ tUnities Their labors culminated In a wlng­ shaped 36-story office tower that Incor­ porates a curved face along Wacker Drive The curved facade flows naturally With a bend In the that turns In front of the bUilding In contrast to thiS magnificently curved surface, the three re­ • maining Sides are straight but they have notches that break up the flat surfaces While the tnangular site presented an Interesting challenge to the architects to come up wllh a working footpnnt of Ihe bUilding, the constraints below the ground presented the struclural engineers With their first challenge. Invesllgatlon of the subsurface Indicated a caisson foundation system would be most applicable How ever, easements from two subway lines and the close proximity of the foundation to the property line loomed as formidable challenges Concessions by the Chicago Transit Au· thonty eliminated one easement Grade beams span to , and cantilever off the cais­ sons to support the structure along both the Lake Street subway easement and the Wacker Dnve foundations The shape of the bUilding limited the number of available Intenor columns. and spans for the gravity system vaned Widely Any structural system that rel ies on con­ tinuity or repetilion could not be Incorpo­ rated economically In thiS prolect In ad ­ dillon, the curved surface and notches presented addilional engineering chal­ • lenges Engineers analyzed five gravity and lat-

151 Quarter 1984 17 eral framing systems. These analyses In­ umns are within leasable areas. Addillon­ the floor framing systems were designed cluded four sleel schemes consisting of ally, thiS scheme offers fleXibility to accom­ uSing high strength (50,000 pSI) steel. ThiS short-span composite beams and girders: modate special requests for present and system resulted In a sleel weight of ap­ stub girders with composite beams; and future tenants. As tenants request m­ proximately 17 IbsJsq fI , including the lat- long span composite beams supported by creases In the live-load capacity of their eral system. TYPical office bUildings in Chi-. girders on the short span. The lone con­ floors , the capacity of floor members can cago usually range from 14 to 16 Ibs Jsq crete system analyzed was concrete pan be Increased by welding plates and struc­ ft Since 333 West Wacker Drive IS hardly 10lsts supported on haunched girders turaltees to the bottom flanges. The struc­ tYPical , the engineers were satisfied that Since concrete relies predominantly on ture was also modified to Include Interior the final steel weight was Ihe lowest limit continuity and repetitiveness for Its econ­ stairs for two tenants after bUilding erec­ for thiS bUilding . omy, and steel does not, the engineers tion had begun. The cost of these modi­ The elements discussed so far may be concentrated most of their efforts on steel. fications was a fraction of what it would interestmg, and certamly challengmg With a floor-to-floor height of 12 ft-2 In. , have been If a concrete structure had However, as the architectural deSign and a ceiling height of 8 ft-6 In., the pro­ been bUilt One Inherent potential problem evolved Into an outstanding architectural posed framing systems had to provide of dead-load deflecllon in the long-span addition to the commu­ shallow secondary framing members and beams was dealt With by cambering those nity, the eng meers' Imagmallon would limited penetration through primary mem­ members ShOring was conSidered, but have to become part 01 the deSign effort bers. With this In mind, along with cost and the general contractor found cambering to architectural analYSIS, the steel framing be about one half the cost. Extensive Analysis Required system-incorporating long-span beams, The floor framing system consists 01 3Y.­ The unique shape of the tower required With girders framing In the shorter direc­ In lightweight concrete slabs over 2-ln. extenSive analYSIS to determine the Impact tion- was selected. metal deck on 16-ln deep cambered com­ of Wind forces on the bU ilding A Wind tun­ posite beams, 10 ft a c., spanning pre­ nel test was essential to derive an effec­ Modification Cost Minfmat dominantly between 40 and 45 ft , 24 -in tive , economical Wind system Dr. Isyumov Architecturally, this structural scheme was and 30-ln deep composite girders span­ of the University of Weslern Ontario con­ attractive, Since It prOVided for a limited ning 30 to 45 ft With a limited number 01 ducted the Wind tunnel tests. Results pro­ number of Intenor columns In tenant these girders haVing reinforced penetra­ Vided the data reqUired to deCide on both spaces In the lOW-rise floors, only two col- tions for mechanical ducts Two thirds 01 the most applicable Wind system , and the

Last steel up for 333 WaCker Building at histone site (I). Above (and r) shows building 's structural steel frame as it curves to adapt to triangular site Renowned in background (r) •

18 MODERN STEEL CONSTRUCTION • Advancing Engineering Software W e are the developers of the most extenSIVe program library with on· gOing support services Engineering apphcatlon programs In analysis , design and business for Structural Civil Electrical Mechanical Sys Camp has analysIs and design History is reenacted as "La­ programs speCIfically for structural Salle's~ canoe heads for shore at steel bulldmgs fiver Juncture (above) "LaSaUe " These programs Include then exchanges greetings with SPSTRESS local dignttarles prior 10 lopping SPSTIIESS General Systems Analysis out ceremonies Sys Comp's revised and enhanced ver­ Sion of STRESS for Ihe analySis of regular two or three dlmenslonallrames. SGEN SPSTRESS Inpul File Generator ThiS mteractlve program operates In a conversational mode to generate Input reqUired by SPSTRESS STRCHK SPSTRESS Check , Steel Seam or Column Reduces the manual output of data for stress checking of steel beams or col· umns , User selects from a SPSTRESS frame analYSIS in accordance With AISC speCifications SPLOT SPSTRESS Geometry and Dellected Shape PloUlng Reads data output from program Pt6 t , SPSTRESS, to create on a ploner a graphIC representation of the structure bemg deSigned Also mcluded Sleel Beam Steel Column Column Base Plate Composite Steel Beam Welded Sleel Girder Sleel Column Base Plale With Boll TenSion Sleel Column Splice DeSign AU of these programs analyze and design the vanous structural steel members in accordance With AISC speCifications for various combined loadmg and moment conditions .

Packaoed With , Of licensed to OpMIte on oau Gen efll oomputef systems MS DOS and IBM PC """,,""" Write or cailloday. ~SysComp 2042 Broadway Sanla MonICa . CA 90404 (213)829-9707 (800) 421-7157

, 51 Quarter 1984 19 analysIs of that system aXial loads from one Iruss node to another. that time could be saved by reVising the The wind tunnel data Indicated signifi­ ZOning reqUIrements for the bUilding re­ normal sequence of construction. This cant lorsional loads would be applied 10 sulted in a plaza design that Interrupted presenled a unique and unexpecled chal­ the laleral structural system. The effective thiS system and prOVided us with another lenge. eccentricity of the wind load on the curved challenge. DeSign and documentation was based . surface was about 60 ft. To resist thiS tor­ on the concrele slructural system extend- sion, a moment-connected exterior frame Yet More Challenges! Ing up to the third floor at the core and to concealed behind the curlaln wall would By recessing the bUilding enclosure at the the ground floor for Ihe balance of the have been ideal. This lateral syslem would ground floor, the zoning ordinance pro­ building. From these points, the sleel have been attracllve, although highlight­ Vides for a five-story bonus The arcade structure would have orlglnaled. Due to Ing Ihe structure of the building was not Ihus created made it Impossible to extend Ihe contractor's concern that the compli­ an Initial architectural consideration. How­ the X-brace system to Ihe foundation. To cated lower level concrete work would not ever, since the sides of the bUilding are work around thiS , the engineers used the be completed In time for the scheduled not perpendicular to each other, Iransfer­ floor diaphragms, beginning at the third beginning of steel erection, erection was ring loads around Ihe corners efficiently floor, to transfer the load to the core started at the top of the caissons. ThiS ap­ would be Impossible using momenl con­ Analysis indicated the majority of the proach reqUired Incorporation of extensive nections. In addition, Ihe number of avail­ load transfer would take place at the third temporary support systems below the third able exterior columns was Ilmlled by ar­ floor. By Increasing the Ihlrd floor slab floor This temporary steel, encased In ch,teclural conSiderations. Without tightly thickness, emplOYing extensive reinforce­ concrete, remains embedded In the final spaced columns, the rigid frame lacked ment on that level, and by providng suf­ structure This temporary system permit- economical Stiffness. Finally, nolches In ficient shear studs on the remaining trans­ ted steel erection through the 13th level the Side and back walls would inlerrupt Ihe fer floors, the marriage of the exterior X­ With Ihe final concrete structure In place, continuity required for ngld frames. brace system and the concrete floor dia­ steel erection above Ihe 13th level pro­ To determine If the centrally loaded core phragms was complete. These floor dia­ ceeded unhindered. could be of assistance In resisting applied phragms were then anchored to the core With thiS unique approach to construc- torsional loads, core framing in both steel _primarily by uSing shear studs. The third tion , extensive modifications were re ­ and concrele was analyzed. The deler­ floor load transfer Incorporated, In addition quired In the concrete struclure so that mlnallon was It would be more effiCient to shear studs, drag beams and reinforc­ reinforCing steel would be placed In a and economical to Incorporate an extenor Ing bars anchored directly to the top of the manner consistent with the design. The re- sleel frame as typical and prOVide a stiff­ concrete core. DeSigning Ihe core walls In sult of the design and construction team ened concrete core only where the exterior concrete from Ihe caissons up to the third effort has already been recognized by an frame could not be used floor permitted stiffening of the Gore suf­ award from the Structural Engineers As­ An X-braced exlernal syslem With lim­ fiCiently to resist total torSional loads Once sociation of IllinOIS for its ·contrlbution to . Ited hOrizontal proJecllon on the curved these loads were In the core, Ihe concrete Ihe state of the art of the structural engi­ surface, running Ihe full Width on the re­ slab al the ground floor and the slab on neering profession.· maining Ihree sides, was proposed ThiS grade (as diaphragms) deliver tile forces When the 10lnt venture of Urban Invest­ syslem was found mosl effiCient In meellng to the foundation system. SpeCi al X-brac­ ment and Development Co. and EqUitable the torsional challenge. The bracing IS de­ ing was employed in the core above the life Assurance society of the U.S. deCided Signed on t 2-slory modules With this third floor to help control Ihe total hOrizon­ 10 develop this site they knew It would be a module, diagonals Interact column/beam tal bUilding drlfl unique building. The result of Ihe efforts of nodes al every second floor At the When the general contractor analyzed the entire bUilding team-a bUilding whose notches, links are Incorporated to transfer the construclion schedule, he deCided uniqueness Will never be duplicated! 0

Under-the-deck photo shows curved structural steel frame

Architects Kahn , Pedersen, Fox . New York City, and Perkins & win . Chicago, IIhnols Structural Engineer GeE of illinOIS, Inc Chicago illinOIS General Contractor Inland Construction Co Chicago illinOIS Steel Erector Amencan Bridge DIVISion , US Steel Corp Owners Urban Investment and Development Co., and Equitable Ufe Assurance SocIety • ChIcago 11hnOi S

20 MODERN STEEL CONSTRUCTION Make sure your bolts are . properly tensioned. Specify Coronet Load Indicators.

You don't calculate your building backs which lead to schedule disrup­ connections by guesswork. So tions and loss of productivity. why allow guesswork to determine So, know bolts have been tensioned how well bolts are tightened in the properly by eliminating the guesswork field? and save the after costs of loose That's exactly what happens when bolts, too. Speci fy Coronet Load high-strength structural bolts are Indicators. Wnte or call today for an Installed uSing the " turn-of-nut" up-to-date fact file. method. This method depends on guesswork because It depends on where nut rotation IS started and how it's measured. Different rotation reqUIrements are necessary for differ­ ent bolt lengths. And nut rotation can collect ply compression Instead of bolt tension. Compounding the unreliability of thiS method of bolt Installation, there is no proof that the Installed bolts have .. been tightened properly. Inspection is , performed With a calibrated torque • wrench which does not necessarily measure tension. With Coronet Load Indicators, how­ ever, you can be sure structural joints are properly assembled. As the bolt IS tensioned, the clamping force flattens the protrusions, reducing the gap. Coronet Load Indicators are accurate because the specified gap Indicates correct clamping force, or tension. They provide Immediate visual proof that 100 percent of the bolts have been correctly tensioned. They save costs because they are simple and easy to Install with standard socket wre nches, and Inspection is consider­ ably faster than With a calibra ted torque wrench. And Coronet Load Indicators can help avoid costly call-

The new ~ Cenl. WI SMm.. WaltWlgton WlI bI 76 ~ wf-..n ~«i 1N1ung .. the ~ buI6dIng 'N8SI of the MtswI/ClPI """'-& ~ AIMfIn.s.p SlnJctt#M E"fIII"'"' ~ Wwd. R~ , 8MUtwe, a.n..I Conn.:­ I« HeM. S WngtIf & eomp.ny StHI Faonc:.lor Samsung Cotpor./)Ott 5,.. Erector ~ 8ndge. tlYIston 01 U 5 "'HI c:b ~~n~~~~n~~rner Inc • 522 Parkway View Drive PIttsburgh. PA 15205 Telephone (412) 787·2253 . Telex 812381 mer:'b=e l Cedars-Sinai Medical Center: Creating Space • Where There is None

by Kenneth Liu he Cedars-Sinai Medical Center In Los The first problem the architect faced and TAngeles IS one of the most modern was to find a spot for the facllily In the Michael L. Bobrow hospitals In the nallon When It was con­ confined. bUilt-up property of the hospitaL structed In t 976. every effort was made to The answer was the east plaza level of the provide for future reqUIrements. as well as center. a landscaped area on the roof of the current needs of the faCility But to fore­ the parking structure of the eight-story see all future reqUIrements. particularly for center ThiS plaza while attractive. was not a medical faCility IS ImposSible fully ulilized. and It would provide a can· A few years later. the hospital needed venlent locallon for the addition The Pri­ additional space for a conference cen­ mary constraint as far as the structural en­ tera small auditOrium and severat rooms gineer was concerned was weight The In which to hold seminars The architect. plaza was not deSigned to support another

Kenneth UU , AlA IS prtnclpal architecture and together with the structural engineer. structure If It were necessary to Michael L Bobrow AlA. IS a partner In the came up with a ptan for a SOO-seat audi­ strengthen the eXlsllng structure betow the arctutectural !lrm 01 Bobrow Thomas and As­ tOrium. fleXible space for SIX seminar plaza leveL the new faCility would not be SOCiates, Los Angeles. California rooms. and even a small art gallery economically feasible .Part of the solullon. •

In addition to clearing the area was to re­ move some of the planters and benches from the surrounding area The rest of the solution was to prOVide a light efficient structural steel frame for the addition Within the constraints of the seismiC codes and also to carefully monllor the weight of other building matenals The architectural challenge was to cre­ ate a structure which would appear as a natural extension of the eXlsllng medical center yet maintain Its own IndiVidual Idenllty Continuity was achieved With the same solar· bronze glass as the eXisting bUilding IndiViduality was expressed by breaking down the scale of the bUilding

Cedars-Sinai Medical Cenler, Los Angeles, acqUired needed space lor conference. • aud,!onumtsemlnar rooms on plaza above parking deck (I) Below ample conler- ence area and large auditOrium accommo­ date hasp.lars vaned needs First is Arbed's new rolled 40" beam . .. available in 16 sections from 149 to 328 Ibs. It gives high section moduli, great lateral buckling resistance, and competes economically with both fabricated sections, as well as reinforced precast and prestressed concrete. Then there's Arbed's rolled ''tailor-made'' series (up to 42.45" x 18.13 " x 848Ibs.)... that lets you specify the beam weight you need, other than what is normally available. Result? Big savings: in fabrication costs and weight. Why not get all the facts? Send the coupon now for information including complete specifications. IDa;~~~m~~~~~~~~7.~n I (212) 486·9890. Domestic Telex: (W.U.) 125 159, Int'l Telex (ITT) 421180. I In Canada: TradeARBED Canada, Inc., 1176 Blair Road, Burlington, I I OntariO, Canada L7M 1K9. (416) 335-5710, Telex 0618258 I Please send complete Information on TradeARBED's 40 ' beams and I I "TAILOR-MADE" beams. I Name Tltie I Firm I I Address __ l...!;!!L ______s .!!!.e__ .2.I !!....~J

Ilr-v.lEAli!BEDlnc. INNOVATORS OF STEEL CONSTRUCTION PRODUCTS 151 Quaner 1984 23 by employing setbacks along Ihe roof manent art gallery In ItS more than tADO­ Archftect plane. The resultant crystalline structure. sq It of gallery and lobby space, changing 8obrowfThomas and Associates through the play of the same color and a exhibitions of the hosplta 's highly es­ Los Angeles . California radically different scale. permits the ad­ teemed contemporary art collect,on are Structural Engineer dition to visually bounce back and forth held Albert G Presky and ASSOCiates between Its own identity and that as an Technically, what IS partlcularty unusuat Los Angeles. California about the bUilding IS the use of the plaza extension of the main bUilding General Contractor • Internally. arrival in the conference cen­ level as ItS Site The design team , working Jones Brothers Construction Co ter is defined by a two-story lobby gallery. with the structural engineer, deve oped a Los Angeles. California which creates ItS own sense of special tight structure that would meet the seismiC Steel Fabricator place within the center This cenlral area. codes The $35-mlllion addition. named Riverside Steel ConslrucllOn the Harvey S Morse Conference Center and the one-story wings on each side, ac­ Santa Fe Springs, California commodate a 6,ODO-sq It audltoflum which for the Los Angeles phllanthrop st, pro­ IS divIsible Into SIX rooms designed fa! vides 12,000 sq ft of space for medical Owner seminars Advanced, state-of-the-art au­ professionals, hospital staff and commu- Cedars-Sinai Medical Center Los Angeles . California dio-visual equipment IS available In all nlly use o meellng areas In addition, there IS a per-

New Lightweight Version of AISC Manual Available

The complete, unabfldged Manual of Steel Construction, 8th Edition, is now available in a lightweight "field" volume - half the thickness and half the weight of the standard "library" version of the 8th Edition Manual published by AISC since mid-1980. Printed on fine, opaque "bible" paper, with a flexible, lightweight cover, this new light­ weight version of the Manual is ideal to use on a job site or to carry in a briefcase. It won 't quite fit in your pocket - but it's a great traveling companion . The new lightweight volume, and the standard "library ' volume, are each available for • the same price of $48.00. But now you have a choice : Library Volume : Standard 8th Edition Manual, 832 pages, based on the 1978 AISC Specification. Lightweight Field Identical contents and type size, same number of pages­ Volume: but only %" thick and weighs only 1 lb. 5 V. oz. Use the convenient coupon below to order either version (or both ).

AMERICAN INSTITUTE OF STEEL CONSTRUCTION, INC. P.O. BOX 4588, CHICAGO, IL 60680

Please ship immediately the following order for the 8th Edition AISC Manual of Steel Construction at $48 each (ArSC member pnce $36): __co pies of Field Volume __copie s of Library Volume; $ total payment enclosed.

NAME & TITLE

COMPANY

ADDRESS

CITY STATE ZIP

Please enclose remittance . No C.D.C orders In New Yorl<:. California and illinoiS add sales tal( ShiPPing charges prepaid In U.S. •

24 MODERN Sl EEL CONSTRUCTION • COMPLETELY REVISED ...

now available from AISC

Engineering for Steel Construction

Keyed to 8th Edition Manual of Steel Construction

• Brand new text geared to Features ... advanced detailer's and design engineer's needs. • All aspects of connection • Comprehensive guide to design and detailing • current detailing and design • Latest information on practice for steel-framed metallurgy and on welding structures. • Updated skewed, sloped and • Handsome, concise, with 370 canted beam connections pages of directions, problems/ solutions, 315 drawings. • Framing for heavy construction • A valuable reference for anyone • Heavy bracing connections involved in steel design and • Six appendices contain design construction. aids and tables

Order your copy today from . . .

American Institute 01 Steel Construction, Inc. NAME ______P.O. Box 4588, Chicago, IL 60680 TITLE, ______I enclose payment 01 $ 10'_---:-_ copies 01 Engineering for Steel Construction (M014) @ $52 each. COMPANY ______

ADDRESS, ______Please enclose remittance. No C.O.D. orders, please. In New York, Illinois and California. add • CITY ____ STATE ____ ZIP' ____ sales tax. AllOW 4 weeks for delivery. Shipping charges prepaid in Continental U.S. MSC641

1sl Ouarter 1984 25 ~------~------Prestonwood Baptist Church : Steel Wins the Roof "Sweeps"

he cong regatlon of Prestonwood Bap­ define the slope and serve as ridge At the top of thiS column it was neces•­ Ttist Church in Dallas reqUIred a 4,000- trusses. Deep long-span jOists of W12 sec­ sary to support several trusses- RT-1, RT- seat auditorium where the whole congre­ tions In top and bottom chords spanned 2, RT-3 etc - at different levels (Photo 2). gation could not only observe but also be the trusses. Web members were either To accommodate all these trusses Without a part of the proceedings. A large area W 12 sections or double angles. The top serious eccentricity and to provide for lat­ above the pulpit was desired to provide a chord was oriented with a W12 web ver­ eral rigidity for wind loads along the RT-1 sweeping view of the chOIr ; to house audiO tical. In the bottom chord, the W12 web direction, W33 rolled shapes, more eco­ equipment and speaker cluster In the ceil­ was oriented horizontally, so the bottom nomical than built-up shapes, were used ing and the organ pipes behind the choir chord bracing could be at large distances as columns. For the length where the weak platform. both for proper acoustics; and to (Photo 1). axis slenderness was large, this W33 sec­ provide uninterrupted sight lines to the pul­ These trusses were shipped in two sec­ tion was sliffened by two WT7 sec lions Pit from any part of the auditOrium so that tions and assembled on the ground before welded to the web so the column was In this large congregation could feel c l ose ~ being hoisted into position. The functional the shape of two intersecting wide-flange The roof sweeps up to focus on the requirement of unobstructed vISion In the shapes. As seen in Fig. 1, on the west and cross ~ A copper batten seam roof, a time­ auditorium dictated that the ends of these south sides of the roof the slopes were very honored element In church architecture, trusses be supported at different heights steep. In these faces, WB sections were was used on the sloping roof. The roof was (also Photo 1). The column height at the used as stringers in lieu of open web Joists shop-fabricated and delivered to the site high end of truss RT- 1 was 77 11-2 in ., of so that biaxial moments could be resisted without serious delay In erection time. Fig­ which 33 11-4 in . was un braced by any In­ satisfactorily (Photo 3). 0 ure 1 shows the roof framing plan and roof termediate level framing . Maximum truss slopes The roof trusses RT-1 and RT-2 spans are 131 11-6 in.

Exterior of Preslonwood Baptist Church, Oallas (I.) shows steel -framed rool sweeping upward to cross . Long truss spans in intenor (r ) provide uninter­ rupted sightlines for worshippers

26 MODERN STEEL CONSTRUCTION STRUCTURAL PRODUCTS • Architect JPJ Architects. Inc What % of your needs Dallas . Texas require ST. LOUIS Structural Engineer SCREW & BOLT HIGH Mullen & Powell. Inc Dallas. Texas STRENGTH Bolts? General Contractor Robert E McKee. Inc Consider this - Dallas, Texas Steel Fabricator • American Made Austin Steel Company, Inc • Tested & Certified Dallas , Texas • Full Range of Owner Type I & ill Products Preslonwood Baptist Church Dallas, Texas • Fast Delivery .95 Years of Figure 1 North half of roof Dependable Service plan shows structural steel framing Sloping roof IS Iden I.f.ed by h'gh p<>nl (H P ) and low po.nl (L P ) eleval.oos

Photo 1 (above) IS structural 51eel frame of rool Loog spans (up 10 131 11-6.n) pro· vide column-free areas for large audlto­ num Photo 3 (above, I) IS extenar 01 sleel Irame. shows steep roof slopes at south and west laces We wantto be involved. CALL US COLLECT! Today at 314·389-7 500

ST LOUISSCREW& BOLTCO

Photo 2 (I ) Tall column supports trusses RT I. RT·2. NOllce weak ax.s sllffenlng 10 bottom of trusses

151 Quarter/1984 27 Welded Steel Duct Designed to Bridge Factory Buildings by German Gurfinkel • ransfer of exhaust gases from the top BUilding layout at the mill permitted tachlng the duct only to the lower tower, Tof a smeller bUltdlng In the new Florida placement of three supporting towers for while suspending It, hammock-type fash ­ Steel Company mill In Jackson. Tenn Into the Inchned duct Thus, design of he duct Ion. from the other two towers Thus, the cleanup equipment on the ground was as a two-span continuous bridge Nlth two duct expands and contracts about the necessary to collect dust and filter the air end canillevers became possible (Fig 2) lower-tower support Total longitudinal diS ­ before releasing It Into the atmosphere The maximum span between towers , and placement of the duct end at the smeller Design of a 322-11 long 12 V.- 1I dla duct the longest cantilever, were 143-11 and 55- bUilding, about the lower-tower support, Inchned t 5' with the horizontal, was re­ ft long, respectively was calculated at 9 In Similar displace­ qUired Temperature effects governed design of ments at the two Intermediate tower sup­ Conventional structural designs re ­ the duct supports at the towers. Exhaust ports were calculated at 7V. In and 2'1'. qUired support for the duct all along ItS gases of 400' F keep the duct QUite hot In., respectively. Since these displace­ length In various ways These were not as dUring normal plant operallon. HO'Never, a ments can easity be realized by the long compelltlve In cost, and lime of fabrication potential shutdown of operations dUring suspension rods, temperature-Induced and erection, as one design which used the winter could possibly bring the tem­ stresses are hardly generated In the duct the duct Itself (In bridge-type fashion) to perature of the duct down to 0' F Thus, Thus freed from temperature-Induced support the loads (see Fig 1) expansion of the duct between a poSSible stresses, deSign of the duct was governed 70' F at erection lime and 400' F dUring by gravity loads and Wind Use of a sllff­ German Gurfmkel IS professor 01 cIvil eng i­ service, followed by contracllon to 0' F. ened-shell cross section reqUired only a neering Umver Slty of IllinOIs-C hampaign· had to be accommodated by the supports 3/ 16-ln thick plate reinforced by a set of Urbana IIhnols Th iS was accomplished by rig idly at - longitudinal and circumferential sllffeners •

Figure 1 Welded sleel duct (322 11 long x 12 5ft dla ) bridges three supporllng tow­ ers Duct permits removal of 400" F ex­ haust gases from lop of smelter building

Figure 2 Duct bndge spans open spaces and sc r a p ~ ha nd hng bUilding on way to top of smelter

SnHN£ItWT'.""'" ITVP}

[NO OF !>MEL T BUILDING SLIDES"I'" SCRAP HANOLING BUILDING 71'- e· IIt·o· •

SCHE MATIC ELEVATION 28 MODERN STEEL CONSTRUCTION • (see Fig 3) ASTM A36 steel was specified ered ,n deSign of the duct It was deter­ and the structure was welded together mined that the governing load was caused with E60 t8 electrodes by Ihe combined action of self weight piuS Weight of Ihe stiffened shell was cal­ snow and Ice DeSign of the cross section culated at 505 Ib ft ProvIsions were made 01 the duct called for prOViding strength to also for future placement of longitudinal reslstlhe slmullaneous effects of a t ,580- grating and ralflng at an additional 95 Ib klp·ft bending moment, a IS-kip longltu· ft to permit eaSier access and Inspection dlnallhrust and a 71-klp Iransverse shear of the duct Thus Ihe total gravity load was DeSign crltena called for a shell sllffened taken at 600 Ib ft externally by a set of 20 continuous lon­ The live load on the ducl. conslsllng of gitudinal angles The maximum compres­ snow and Ice was calculated at 330 Ib sive stress, due to combined action of ft Wind load was eSllmated at 30 psf (for bending moment and thrust, was 8 kSI on NATIONAL a lOQ·year mean recurrence Interval. a Ihe cntlcal angle sllffener, acllng compos­ basIc speed of 80 mph and exposure Type Itely With lOin of effecllve flange from the INSTITUTE OF C) thiS led to a Uniformly dlstnbuted wind shell Transverse clrcumferenllal stiffeners load of 375 Ib ft acting against the duct were deSigned to prevent buckling of Ihe STEEL DETAILINC In a plane inclined 15° 10 the hOrizontal and longitudinal stiffeners Their spacing was comalnlng Ihe longitudinal aXIs of the duct calculaled to allow as much as one per­ Vanous loading conditions were consld- cent devlalion In the longitudinal aXIs of r~p'~S~nI;ng : the independenl sleel detailer

d~dicar~d 10: increasing professionalism in the sleel detailing induSlry and improving relation among colleagues in the steel construction industry

conlact us for furthu information on: • assocl8!e membelllhip • membership roster • publications av atlable • quality procedures program • assoc iation goals and activities

EXECUTIVE OFFICE 2506 GROSS POINT ROAD EVANSTON, ILLINOIS 60201 Figure 3 Front vIew of duct as It hangs hammock-style from 2'h-ln dla (312) 475-7530 steel bars attached to top beam of supporting tower Duct IS welded cyf,ndncal snell :1 16-ln In,ck shffened Iongllud,nally by 20 3x3xlO-ln steel angles Transverse stiffening IS WT6x13 flngs 13 It apart At sup ­ •port towers WT8x33 flng supports are used

151 Ouarter 1984 29 the duct between them This hmltatlon IS be of speclallnleresl (see Fig 5) . Thus. In considered well within normal fabrication lhe same fashion as a sailboat IS stabilized tolerance and IS unlikely to be exceeded against the wind . the duct IS proVided at A cross section of the duct at one of two each tower with keel -type devices. one be­ suspended suppo~s IS shown In Fig 5 low and one above These devices are ac­ Note the 3116-ln thick sleel shell sllffened tivated In the wind by bearing against the by 20 longlludlnal 3V, x 3V, x 318-ln. steel transverse beams of the supporting angles In addition. there IS a WT8x33.5 frames Longitudinal displacements of the Architect (mill) • clrcumferenllal sllffener attached to lhe duct at these locations are faclhtated by TLM Engineers duct thai IS used 10 lransfer the bridge sandwiched neoprene plates Jackson. Tennessee reaClion lhrough two 2V2-ln dla hanger The duct was welded together In lhe rods to the supporting-tower frame shop and fabricated In longitudinal sec­ Structural Engineer (duetlng) Professor German Gurllnkel lions lor shipment. These were temporarily The duCI IS provided with reSISlance to UniverSIty of Ilhnols-Champaign-Urbana wind-Induced forces al each suppo~lng bolted together In the field Unlll welded tower The keel-lype devices used al lhe permanently In place. The fi nished dUCI­ Owner ,nlermed,ate and upper towers. where the bridge has been In conllnuous opera lion Flonda Sleel Company duct IS suspended by hanger rods. may since late 1981 0 Jackson. Tennessee

Figure 4 Cross-sechon of duct bridge al a Ii. DUCT 10'-0· suspended support

lOV/ER LEG

I II • 3,,.. t SHELL·

;,r. -..\, 1

CROSS-SECTION

Figure 5 Nole keel-type deVice on duct underbelly that prOVides laleral reSlralnt Without hlndenng longitudinal displace­ ments BUIlt In paIrs. these elements are effecllve In reSisting Wind IndUCed laleral forces that act against bridge •

30 MODERN STEEL CONSTRUCTION Pick the Profile that's right for you I Need Some Help? Manufacturing Plants : Epic Metals Corporation is involved daily • Pittsburgh. Po • Chicago. III. In engineering and manufacturing • Toledo. Ohio • Lakeland. Fla. Composite Decks, EPC Cellular Raceway Contact us today for Prompt Domestic System, Cellular Decks, Roof Decks, Form and Internot,onol Sh,pments Decks, Roofing and Siding. Our staff IS ready to serve your needs. EPIC,

~ rchltects, EnQlneers, Contractors ... Eleven Talbot Avenue. Rankin PA 15104 give us a call ... write ... telex ... or PHONE: 412/351·3913 TWX: 710-664·4424 come and Visit. EPICMETAL BOOK We olso manufacture some of the above profiles In aluminum

31 AMERICAN INSTITUTE OF STEEL CONSTRUCTION The Wrigley Building, 400 North Michigan Avenue USBULK POSTAGI' RATE J Chicago, Il 60611 PAID WHEATON , III Address CorrectIon Requested lPerm,' No .766 •

AMERICAN COMPUTERS & ENGINEERS •