<<

RP989

World Bank Financed Shaying River Channel Improvement Project Public Disclosure Authorized

Anhui Shaying River Channel Improvement Project Resettlement Action Plan

(Final Version)

Public Disclosure Authorized Public Disclosure Authorized

Anhui Provincial Port & Shipping Construction Investment Public Disclosure Authorized Group July 2010

Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Foreword

I. Purpose of preparing this resettlement action plan

1 The resettlement action plan (RAP) is prepared in accordance with the applicable laws of the People’s Republic of and local regulations and a series of provisions in the Bank Operational Policy OP4.12 Involuntary Resettlement for the purpose of “developing an action plan for resettlement and restoration for the people affected by the project, so that they benefit from the project, their standard of living is improved or at least restored after the completion of the project”. II. Definitions of terms Displaced persons

2 Based on the criteria for eligibility for compensation, “Displaced Persons” may be classified in one of the following three groups: a) those who have formal legal rights to land (including customary and traditional rights recognized under the laws of the country); b) those who do not have formal legal rights to land at the time the census begins but have a claim to such land or assets—provided that such claims are recognized under the laws of the country or become recognized through a process identified in the Resettlement Plan; and c) those who have no recognizable legal right or claim to the land they are occupying. 3 Persons covered under paragraphs 2(a) and (b) are provided compensation for the land they lose, and other assistance. Persons covered under paragraph 2(c) are provided resettlement assistance in lieu of compensation for the land they occupy, and other assistance, as necessary, to achieve the objective set out in this policy, if they occupy the project area prior to a cut-off date established by the borrower and acceptable to the World Bank. Persons who encroach on the area after the cut-off date are not entitled to compensation or any other form of resettlement assistance. All persons included in paragraph 2(a), (b), or (c) are provided compensation for loss of assets other than land. Compensation and resettlement measures

4 To address the following impacts of the involuntary taking of land: (i) relocation or loss of shelter; (ii) lost of assets or access to assets; or (iii) loss of income sources or means of livelihood, whether or not the affected persons must move to another location, a Resettlement Plan or a resettlement policy framework shall be prepared to cover the following: (a) The Resettlement Plan or resettlement policy framework includes measures to ensure that the displaced persons are: (i) informed about their options and rights pertaining to resettlement; (ii) consulted on, offered choices among, and provided with technically and economically feasible resettlement alternatives; and (iii) provided prompt and effective compensation at full replacement cost1, for losses of assets attributable directly to the project.

1 "Replacement cost" is the method of valuation of assets that helps determine the amount sufficient to replace lost assets and cover transaction costs. In applying this method of valuation, depreciation of structures and assets should not be taken into account. 1 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

(b) If the impacts include physical relocation, the Resettlement Plan or resettlement policy framework includes measures to ensure that the displaced persons are: (i) provided assistance (such as moving allowances) during relocation; and (ii) provided with residential housing, or housing sites, or, as required, agricultural sites for which a combination of productive potential, locational advantages, and other factors is at least equivalent to the advantages of the old site. (c) Where necessary to achieve the objective of the policy, the Resettlement Plan or resettlement policy framework also includes measures to ensure that displaced persons are: (i) offered support after displacement, for a transition period, based on a reasonable estimate of the time likely to be needed to restore their livelihood and standards of living; (ii) provided with development assistance in addition to compensation measures described in paragraph 4(a)(iii), such as land preparation, credit facilities, training, or job opportunities. 5 Cut-off date: means the date of publication of the bulletin of land acquisition and relocation in this project. After this date, the displaced persons shall not build, rebuild or expand their houses; shall not change the uses of their houses and land; shall not lease their land, lease, sell or purchase their houses; and any person that moves in after this date shall not qualify as a displaced person.

2 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Contents

1 OVERVIEW OF THE PROJECT 1

1.1 BRIEF INTRODUCTION...... 1 1.2 PROJECT BENEFIT ESTIMATES...... 3 1.3 PROJECT PREPARATION AND PROGRESS...... 3 1.4 KEY RESETTLEMENT IMPACTS...... 4 1.5 MEASURES TO REDUCE RESETTLEMENT...... 5 1.6 IDENTIFICATION OF RELATED PROJECTS...... 9 2 PROJECT IMPACTS 10

2.1 PROJECT IMPACT SURVEY ...... 10 2.2 AFFECTED AREAS...... 10 2.3 PROJECT IMPACTS ...... 11 2.3.1 Affected population ...... 11 2.3.2 Acquisition of collective land...... 12 2.3.3 Temporary occupation of collective land...... 13 2.3.4 Permanent acquisition and temporary occupation of state-owned land...... 14 2.3.5 Demolition of residential houses...... 14 2.3.6 Demolition of attachments ...... 15 2.3.7 Vulnerable groups...... 16 3 SOCIOECONOMIC OVERVIEW OF THE AFFECTED AREAS 17

3.1 SOCIOECONOMIC PROFILE OF AFFECTED CITIES AND COUNTIES/DISTRICTS ...... 17 3.2 SOCIOECONOMIC PROFILE OF AFFECTED TOWNSHIPS...... 19 3.3 SOCIOECONOMIC PROFILE OF AFFECTED VILLAGES...... 20 3.4 SOCIOECONOMIC PROFILE OF AFFECTED ETHNIC MINORITIES ...... 20 3.5 SOCIOECONOMIC PROFILE OF AFFECTED HOUSEHOLDS...... 22 3.5.1 Age distribution...... 22 3.5.2 Educational level...... 22 3.5.3 Productive resources...... 22 3.5.4 Household annual income and expenditure ...... 22 4 LEGAL FRAMEWORK AND POLICY OBJECTIVES 24

4.1 POLICY FRAMEWORK ...... 24 4.2 LEGAL AND POLICY PROVISIONS APPLICABLE TO RESETTLEMENT ...... 25 4.3 MAIN DIFFERENCES BETWEEN WORLD BANK POLICIES AND LAWS OF THE PRC ...... 35 4.4 RESETTLEMENT POLICIES OF THE PROJECT ...... 36 4.4.1 Compensation for acquisition of collective land and labor resettlement...... 36 4.4.2 Policy for permanent acquisition of state-owned land...... 36 4.4.3 Compensation and resettlement policies for houses on collective land ...... 36 4.4.4 Compensation and resettlement policies for houses on state-owned land ...... 37 4.4.5 Compensation and restoration policies for temporary land occupation...... 37 4.4.6 Compensation policy for vulnerable groups ...... 38 4.4.7 Compensation policy for affected infrastructure and ground attachments ...... 38 5 COMPENSATION RATES 39

5.1 COMPENSATION RATES FOR ACQUISITION OF RURAL COLLECTIVE LAND...... 39 5.2 COMPENSATION RATES FOR PERMANENT OCCUPATION OF STATE-OWNED LAND...... 42 5.3 COMPENSATION RATES FOR TEMPORARY LAND OCCUPATION ...... 42 5.4 COMPENSATION RATES FOR DEMOLITION OF HOUSES ON COLLECTIVE LAND...... 42 5.5 COMPENSATION RATES FOR DEMOLITION OF HOUSES ON STATE-OWNED LAND...... 43 5.6 COMPENSATION RATES FOR GROUND ATTACHMENTS...... 43 5.7 OTHER COSTS...... 44

1 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

6 PRODUCTION AND LIVELIHOOD RESTORATION PROGRAMS FOR DISPLACED PERSONS 45

6.1 RESETTLEMENT OBJECTIVE...... 45 6.2 RESETTLEMENT PRINCIPLES ...... 45 6.3 PERMANENT ACQUISITION OF COLLECTIVE LAND...... 45 6.3.1 Impact analysis of permanent land acquisition...... 45 6.3.2 Resettlement program for permanent land acquisition...... 48 6.4 DEMOLITION OF RESIDENTIAL HOUSES ...... 50 6.4.1 Resettlement for demolition of rural residential houses...... 50 6.4.2 Resettlement for demolition of urban residential houses ...... 51 6.5 GRATUITOUS ALLOCATION OF STATE-OWNED LAND...... 51 6.6 RESTORATION PROGRAM FOR TEMPORARILY OCCUPIED LAND ...... 51 6.7 RESTORATION PROGRAM FOR AFFECTED VULNERABLE GROUPS...... 52 6.8 PROTECTION OF WOMEN’S RIGHTS...... 52 6.9 RESTORATION PROGRAM FOR GROUND ATTACHMENTS ...... 53 7 ORGANIZATION 54

7.1 ORGANIZATION...... 54 7.2 ORGANIZATIONAL CHART ...... 57 7.3 STAFFING ...... 57 7.4 MEASURES TO DEVELOP INSTITUTIONAL CAPACITY ...... 57 8 RESETTLEMENT COSTS AND SOURCES OF FUNDS 59

8.1 BUDGET ...... 59 8.2 YEAR-BY-YEAR INVESTMENT PLAN...... 64 8.3 SOURCES OF RESETTLEMENT FUNDS...... 64 8.4 MANAGEMENT AND DISBURSEMENT PLAN OF RESETTLEMENT FUNDS ...... 64 8.4.1 Fund flow ...... 64 8.4.2 Disbursement and management ...... 65 9 PUBLIC PARTICIPATION, CONSULTATION AND APPEAL CHANNEL 66

9.1 PUBLIC PARTICIPATION STRATEGY...... 66 9.2 PUBLIC PARTICIPATION PROCESS AND POLICY DISCLOSURE PLAN...... 66 9.3 APPEAL CHANNEL ...... 67 10 IMPLEMENTATION SCHEDULE 69

10.1 PRINCIPLES FOR LINKUP BETWEEN RESETTLEMENT AND PROJECT CONSTRUCTION...... 69 10.2 SCHEDULE OF RESETTLEMENT MILESTONES ...... 69 10.2.1 Principles for preparing the working schedule...... 69 10.2.2 General resettlement schedule ...... 69 11 MONITORING AND EVALUATION ARRANGEMENTS 71

11.1 INTERNAL MONITORING ...... 71 11.1.1 Implementation procedures...... 71 11.1.2 Scope of monitoring ...... 71 11.1.3 Internal monitoring reporting ...... 71 11.2 EXTERNAL INDEPENDENT MONITORING ...... 71 11.2.1 Independent monitoring agency...... 71 11.2.2 Monitoring procedure and scope ...... 71 11.2.3 Monitoring indicators ...... 72 11.2.4 Post-evaluation ...... 73 12 ENTITLEMENT MATRIX 74

APPENDIX 1 SCHEMATIC MAP OF THE PROJECT...... 76 APPENDIX 2 RESETTLEMENT OF THE RELATED PROJECT SHIP LOCK RECONSTRUCTION ...... 77 APPENDIX 3 ETHNIC MINORITIES INVOLVED IN THE AFFECTED AREAS...... 79

2 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

APPENDIX 4 LAND RECLAMATION AND MEDIUM AND LOW YIELD LAND IMPROVEMENT PROJECT FOR SLUDGE DISPOSAL SITES ...... 82 APPENDIX 5 PLAN FOR IMPLEMENTING THE ENDOWMENT INSURANCE FOR LAND-EXPROPRIATED FARMERS IN THE AFFECTED AREAS ...... 89 APPENDIX 6 SCHEDULE OF TEMPORARILY OCCUPIED COLLECTIVE LAND FOR SPOIL GROUNDS...93 APPENDIX 7 LIST OF AFFECTED ATTACHMENTS ...... 94 APPENDIX 8 RESETTLEMENT MONITORING AND EVALUATION OUTLINE...... 96 APPENDIX 9 RESETTLEMENT INFORMATION BOOKLET...... 99 APPENDIX 10 POLICY FRAMEWORK FOR RESETTLEMENT ...... 113 APPENDIX 11 PHOTOS OF INTERVIEW...... 124 APPENDIX 12 FRAMEWORK AGREEMENT OF THE ANHUI PROVINCIAL COMMUNICATIONS DEPARTMENT AND THE FUYANG MUNICIPAL PEOPLE’S GOVERNMENT ON THE PROJECT...... 125 APPENDIX 13 THE LIST OF PERSON OF ALL CITIES AND COUNTIES IN RESETTLEMENT IMPLEMENTATION AGENCIES AND THEIR CONNECTION ...... 126

3 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

List of Tables

TABLE 1-1 SUMMARY OF COURSE LINES AND ENGINEERING MEASURES ...... 1 TABLE 1-2 BRIDGE RECONSTRUCTION WORKS...... 2 TABLE 1-3 SCHEDULE OF SUPPORTING WORKS ...... 3 TABLE 1-4 SCHEDULE OF KEY RESETTLEMENT IMPACTS ...... 4 TABLE 1-5 MEASURES TO REDUCE RESETTLEMENT...... 6 TABLE 2-1 SCOPE OF PERMANENT LAND USE AFFECTED AREAS ...... 10 TABLE 2-2 SCOPE OF TEMPORARY LAND USE AFFECTED AREAS ...... 10 TABLE 2-3 SUMMARY OF AFFECTED POPULATION...... 12 TABLE 2-4 SUMMARY OF PERMANENTLY ACQUIRED COLLECTIVE LAND...... 12 TABLE 2-5 SUMMARY OF TEMPORARILY OCCUPIED COLLECTIVE LAND...... 13 TABLE 2-6 STATE-OWNED LAND OCCUPIED PERMANENTLY (TEMPORARILY) BY THE PROJECT...... 14 TABLE 2-7 RURAL RESIDENTIAL HOUSES DEMOLISHED FOR THE PROJECT...... 14 TABLE 2-8 URBAN RESIDENTIAL HOUSES DEMOLISHED FOR THE PROJECT ...... 15 TABLE 2-9 SCHEDULE OF AFFECTED ATTACHMENTS...... 16 TABLE 2-10 SCHEDULE OF AFFECTED VULNERABLE GROUPS...... 16 TABLE 3-1 KEY ECONOMIC INDICATORS OF AFFECTED CITIES/COUNTIES...... 18 TABLE 3-2 KEY ECONOMIC INDICATORS OF AFFECTED TOWNSHIPS/SUB-DISTRICTS...... 19 TABLE 3-3 SOCIOECONOMIC PROFILE OF AFFECTED VILLAGES ...... 21 TABLE 3-4 STATISTICS OF AFFECTED POPULATION...... 22 TABLE 3-5 INCOME AND EXPENDITURE STRUCTURE OF AFFECTED RURAL HOUSEHOLDS...... 23 TABLE 4-1 LIST OF POLICIES APPLICABLE TO THE PROJECT...... 24 TABLE 5-1 UNIFORM ANNUAL OUTPUT VALUES AND COMPENSATION RATES FOR LAND ACQUISITION .40 TABLE 5-2 COMPENSATION RATES FOR TEMPORARY LAND OCCUPATION ...... 42 TABLE 5-3 COMPENSATION RATES FOR DEMOLITION OF RURAL RESIDENTIAL HOUSES ...... 42 TABLE 5-4 COMPENSATION RATES FOR DEMOLITION OF URBAN RESIDENTIAL HOUSES...... 43 TABLE 5-5 COMPENSATION RATES FOR GROUND ATTACHMENTS...... 43 TABLE 5-6 COMPENSATION RATES FOR OTHER COSTS...... 44 TABLE 6-1 IMPACT ANALYSIS OF ACQUISITION OF COLLECTIVE LAND ...... 47 TABLE 6-2 RESETTLEMENT PROGRAM FOR ACQUISITION OF COLLECTIVE LAND ...... 48 TABLE 6-3 PAYMENT AND BENEFIT RATES OF ENDOWMENT INSURANCE FOR LAND-EXPROPRIATED FARMERS ...... 49 TABLE 6-4 SCHEDULE OF MEDIUM AND LOW YIELD LAND IMPROVEMENT OF AFFECTED VILLAGES ...... 50 TABLE 7-1 FULL-TIME STAFFING OF RESETTLEMENT AGENCIES ...... 57 TABLE 7-2 GENERAL RESETTLEMENT TRAINING PROGRAM...... 58 TABLE 8-1 COMPENSATION BUDGET FOR RESETTLEMENT...... 61 TABLE 8-2 FUND USE PLAN BY YEAR ...... 64 TABLE 9-1 EARLY-STAGE RECORDS AND SUBSEQUENT PLAN FOR PUBLIC PARTICIPATION PROCESS OF AFFECTED PEOPLE ...... 66 TABLE 9-2 POLICY DISCLOSURE PROCESS...... 67 TABLE 10-1 RESETTLEMENT SCHEDULE...... 70

List of Figures FIGURE 2-1 COLLECTIVE LAND TO BE ACQUIRED ...... 13 FIGURE 2-2 LAND TO BE OCCUPIED TEMPORARILY IN SPOIL GROUND ...... 14 FIGURE 2-3 RURAL RESIDENTIAL HOUSES TO BE DEMOLISHED ...... 15 FIGURE 7-1 RESETTLEMENT ORGANIZATION ...... 57 FIGURE 8-1 FUND FLOWCHART...... 65 FIGURE 9-1 GRIEVANCE REDRESS ...... 68

4 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

ABBREVIATIONS

Anhui Provincial Port & Shipping APSCIG - Construction Investment Group M&E - Monitoring and evaluation MLR - Ministry of Land and Resources MSA Maritime Safety Administration NRCR - National Research Center for Resettlement PMO - Project Management Office PRC - People’s Republic of China RAP - Resettlement Action Plan

Units

Currency unit = Yuan (RMB) 1.00 yuan = $0.15 1 hectare = 15 mu 1 jin = 0.5 kg

i Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Overview of the Project

Brief introduction The Shaying River, located on the left side of the , is the largest branch of the Huai River. It is originated in the Funiu Mountain Range in Province, formed by the convergence of the Sha and Ying Rivers in City, running through central Henan from northwest to southeast, entering Anhui Province at the Changsheng Stream in City, and running from Jieshou City, Taihe County, Fuyang Municipality into the Huai River at Mohekou in , with a full length of 620km and a watershed area of 36,651 km2, in which its length is 206km and its watershed area 4,112 km2 in Anhui Province. According to the Layout Plan of Inland Navigation Channels and Ports (2005—2020), the Shaying River channel runs from Luohe, Henan to Mohekou, Anhui, with a full length of 378km, planned as a Class IV channel. The Yingshang ship lock and the Taihe Genglou hydraulic complex in Anhui have been completed, and the Fuyang ship lock is under construction. By now, the problem of navigation obstruction from lock and dam on the Shaying River channel has been largely solved. If the channel is further dredged, the stretch below Zhoukou, Henan will be open for navigation. The purpose of the Project is to restore the navigation of the Shaying River fully through channel dredging, obstructive bridge reconstruction, bank seepage control, the setup of revetments and anchorage service zones, and the deployment of navigation aids and signs. See Appendix 1 for the schematic map of the Project. The scope of the Project is as follows: A. Channel and dredging works The Anhui Shaying River channel from Changshenggou to Mohekou (Huai River inlet) has a full length of about 206km, and the mileage of the regulated channel will be about 205.6km. The Genglou, Fuyang (under construction) and Yingshang ship locks on this channel divides the regulated channel into four segments. According to the project design, the center of channel will be the thalweg of the existing channel where possible to maintain the existing plane form of the channel; where the width or bending radius of the channel is insufficient, engineering measures such as avulsion, dredging and regulation shall be taken, and highly bent river segments will be cut off locally to the standard for Class IV channels. The layout of course lines and the engineering measures are shown in Table 0-1. Table 0-1 Summary of course lines and engineering measures Key Channel segment and Direction of course line and engineering measures resettlement pile No. impact 1) The Changshenggou-Xiaogang segment is relatively 682.8 mu of straight; the center of channel is arranged along the thalweg, land will be with 7 intersection points, a minimum bending radius of 330m acquired, Jieshou-upper and a maximum bending radius of 1,000m; the channel affecting 192 Genglou lock mileage after setting-out is 7km; 2) the Xiaowan-Genglou ship households (K0+000-K26+000) lock segment is bent, narrow and varying, with flood land with 714 developed; this segment has 23 intersection points, with a people. minimum bending radius of 330m and a maximum bending Houses of radius of 1,300m; local avulsion is required at one location. 1,156.5 m2 In the Xuzhuang, Wangyao, Tianzhai, Lianghekou, will be Xiazhangwan, Chendian and Donggou segments, the channel demolished, is visibly bent, with a small bending radius, where convex affecting 12 Lower Genglou lock- bank avulsion and mouth cutting measures will be taken to households upper Fuyang lock regulate the channel; the center of channel of this segment has with 56 (K28+000-K80+000) 47 intersection points, with a minimum bending radius of people. 330m and a maximum bending radius of 1,500m; local avulsion is required at Xuzhuang, Xiazhangwan, Chendian and the Ciweixin River mouth, etc.

1 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Key Channel segment and Direction of course line and engineering measures resettlement pile No. impact 1) The Fuyang ship lock-Zhangdianweizi segment is slightly bent; the center of channel is largely arranged along the thalweg; this segment has 26 intersection points, with a Lower Fuyang lock- minimum bending radius of 330m and a maximum bending upper Yingshang radius of 2,500m; there are two cut-offs in this segment; 2) lock (K83+000- The Zhangdianweizi-Yingshang ship lock segment is bent, K159+000) with large bends at Kouzi, Xinji, Jiangkou and Xinmiao, etc.; this segment has 47 intersection points, with a minimum bending radius of 330m and a maximum bending radius of 3000m; there are two cut-offs in this segment. LowerYingshang This segment is bent, has many consecutive bends and 32 lock -Mohekou intersection points, with a minimum bending radius of 330m (K162+000- and a maximum bending radius of 1,200m; there are two cut- K205+600) offs in this segment. B. Bridge reconstruction The Anhui Shaying River channel is constructed up to the Class IV standard, and its navigation clearance shall be as follows for straight segments: 90×7.0m for single-opening navigation (clear width × clear height) and 45×7.0m (clear width × clear height) for double- opening navigation. There are 13 bridges along the Anhui Shaying River channel. In particular, the Liuzhuang Express Passage Bridge in Yingshang County, --Fuyang Expressway Bridge and S102 Yingshang Ship Lock Highway Bridge already meet the standard for Class IV channels, and the remaining 10 bridges are obstructive to varying degrees and are to be rebuilt. Among the 10 bridges to be rebuilt, the Fuyang Ship Lock Highway Bridge will be rebuilt together with the Fuyang ship lock and not included in the Project. In addition, in order to utilize channel construction funds rationally, since it will take time for the number of vessels to grow and vessels to become larger based on freight volume forecast, the obstructive bridges will rebuilt in stages. According to the survey, the Linjiedan Highway Bridge in Jieshou, North Bridge in Fuyang, Ying River South Bridge in Fuyang and - Railway Ying River Bridge and Fuyang-Zhoukou Expressway Bridge meet the standard for Class V channels, and will be rebuilt in the future. Therefore, 4 cross-river bridges will be rebuilt under the Project, which are the Jieshou Yumin Bridge, Jieshou (old S204) Shaying River Bridge, Taihe County Ying River 2nd Bridge and Taihe County Ying River 4th Bridge. See Table 0-2 for the bridge reconstruction works. Table 0-2 Bridge reconstruction works Present Rebuilt/newly built Key Main No. Bridge Length Width Main structural Length Width resettlement structural (m) (m) form (m) (m) impact form V-shaped (75+120+75)m Urban houses Jieshou continuous variable height of 27,884 m2 1 183.5 9.5 906.5 20.0 Yumin Bridge steel continuous will be structure box girder demolished, Jieshou (old Reinforced affecting 346 S204) concrete households 2 204.0 11.0 100m tied arch 327.5 20.0 Shaying River trussed with 1,406 Bridge arch people Reinforced (60+100+60)m Taihe County th concrete variable height 3 Ying River 4 230.0 10.6 977.5 32.0 double continuous Bridge arch box girder

2 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

(60+100+60)m suspension 251.6 7.0 cable steel truss bridge Reinforced Taihe County concrete 4 Ying River 2nd 345.0 17.6 100m tied arch 617.5 27.5 trussed Bridge arch C. Supporting works To meet the service requirements in navigational safety, harboring, lock delay and environmental protection for cargo vessels, it is necessary to arrange anchorages and service zones during channel improvement, including 2 anchorage service zones and 6 anchorages. The anchorage and service zone works of the Project are shown in Table 0-3. In addition, channel communication and video monitoring systems will be built around Fuyang Municipality in the Project, and navigation aids and signs will be arranged along the channel. All navigational marks will be illuminated at night.

Table 0-3 Schedule of supporting works

Key resettlement impact No. Pile No. Work Acquired Demolished rural land (mu) houses (m2) 1 Left bank K75+500 Fuyang service zone 83.5 0 2 Right bank K92 Sanshilipu service zone 263.9 445.9 3 Left bank K7 Xuzhai anchorage, Jieshou 167.9 0 4 Right bank K25+500 Upper Genglou lock anchorage 81.1 199.8 5 Left bank K29 Lower Genglou lock anchorage 70.5 0 6 Left bank K37+700 Taihe city gate anchorage 22.1 0 7 Right bank K159 Upper Yingshang lock anchorage 91.5 0 8 Left bank K162 Lower Yingshang lock anchorage 194.7 0

Project benefit estimates The Project will generate significant economic benefits after completion, with an economic internal rate of return of 11.7%; in addition, the Project is a not-for-profit traffic infrastructure project with excellent social benefits. It will improve the navigational capacity of the Shaying River, promote rapid economic growth, remove most of internal pollution sources of the Shaying River and improve water quality. In addition, the Project will reduce the permanent occupation of land resources arising from highway construction and the consumption of energy for highway construction, thereby facilitating environmental improvement and promoting sustainable growth.

Project preparation and progress To promote the construction of the Project and demonstrate the necessity and feasibility of its implementation, Anhui Provincial Port & Shipping Construction Investment Group (APSCIG) entrusted the Anhui Provincial Communications Planning, Survey and Design Institute to prepare the Preliminary Feasibility Study Report of the Anhui Shaying River Channel Improvement Project in February 2007, which was completed in October 2008. In November 2009, APSCIG entrusted the Anhui Provincial Communications Planning, Survey and Design Institute to prepare the Preliminary Design Report of the Anhui Shaying

3 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

River Channel Improvement Project, which was completed in July 2010.

Key resettlement impacts The Project involves 49 villages/communities in 27 townships/sub-districts of one city (Jieshou), three districts (Yingquan, Yingdong and Yingzhou) and two counties (Taihe and Yingshang), affecting 788 households with 3,140 people permanently (directly) and 2,891 households with 10,316 people temporarily. The Project occupies 1,658 mu of collective land and 98.83 mu of state-owned land permanently; rural residential houses of 1,802.2 m2 and urban residential houses of 27,884 m2 will be demolished, and 9,843.3 mu of land will be occupied temporarily (including 9,831.3 mu of collective land and 31 mu of state-owned land). The key resettlement impacts are shown in Table 0-4. Table 0-4 Schedule of key resettlement impacts

Project Type Unit Channel Bridge Supporting Subtotal works works works Total mu 682.8 0 975.2 1658 Farmland mu 192.1 0 86 278.1 Acquisition of Flood land mu 292.26 0 532.44 824.7 collective land Unused land mu 194.84 0 354.96 549.8 Housing site mu 3.6 0 1.8 5.4 Permanent occupation of state-owned mu mu 98.83 0 98.83 land Demolition of rural residential houses m2 1,156.5 0 645.7 1,802.2 Demolition of urban residential houses m2 0 27,884 0 27,884 Temporary Total mu 9,849.3 5 20 9,874.3 land Collective land mu 9,831.3 3 9 9,843.3 occupation State-owned land mu 18 2 11 31 Households affected by land acquisition / 192 0 232 424 only Population affected by land acquisition / 714 0 937 1,651 only Households affected by house demolition / 0 346 0 346 only Population affected by house demolition / 0 1,406 0 1,406 Directly only affected Households affected population by both land / 12 0 6 18 acquisition and house demolition Population affected by both land / 56 0 27 83 acquisition and house demolition Subtotal of directly / 204 346 238 788 affected households Subtotal of directly / 770 1,406 964 3,140 affected population 4 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Project Type Unit Channel Bridge Supporting Subtotal works works works Temporarily Households / 2,887 1 3 2,891 affected population Population / 10,302 4 10 10,316

Measures to reduce resettlement The design agency and the Employer of the Project attach great importance to measures to reduce resettlement impacts. At the planning and design stages, in order to reduce the Project’s impact on the local society and economy, the design agency and the Employer took some effective measures to optimize the design and avoid land acquisition and house demolition. ¾ Channel works 1) Arrange the channel line by fully utilizing the existing watercourse, and connect it organically with other watercourses to form a smooth channel network, shorten transport mileage and ensure safe and comfortable shipping. 2) Select technical indicators rationally for the channel, and ensure that bend elements meet the design ship form; improve shipping conditions to ensure safe shipping; strengthen the channel design for special segments with poor geologic conditions, local difficulties and bridges. 3) Improve the project design through option comparison and optimization to reduce land acquisition, house demolition and other resettlement impacts. The measures to reduce resettlement of the Project are shown in Table 0-5. ¾ Spoil grounds The channel improvement and dredging works involve a large amount of earthwork; to reduce the adverse impact from earth piling, the Employer and the design agency have taken the following measures: 1) The Shaying River dyke was reinforced recently, and there are a number of borrow pits beside the dyke. Earth arising from channel dredging consists mainly of sandy silt, silty clay and silty sand, and may be used as backfill for borrow pits or disposed of nearby. After disposal, land will be reclaimed for farming or improved for higher yield where possible to increase local farmers’ income. 2) Select lowland, flood land and borrow pits nearby to reduce farmland occupation. 3) Fill ponds and reinforce foundations to meet water conservancy and flood protection requirements, and reduce flood protection pressure. 4) Keep away from towns as much as possible to prevent mud pollution. At the resettlement action plan (RAP) and implementation stages, when land acquisition and house demolition is unavoidable, the Employer and the design agency will take a series of measures to reduce the Project’s negative impacts, such as further improving the project design, encouraging public participation, strengthening internal and external supervision mechanisms, and establishing a sound information feedback mechanism, etc. in order to reduce the Project’s impact on the locality.

5 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Table 0-5 Measures to reduce resettlement Comparison of options Reduced Item Basic description resettlement Advantages Disadvantages impacts 1) Lower investment; 2) Small The center of channel has a minimum disturbance to existing river Reducing 617 Recommended bending radius of 330m, and the channel; 3) Small amount of 1) Bent channel; 2) Long traveling mu of land option protruding left-side cusp is cut off excavation, easy construction; distance for vessels acquisition, 6500 Avulsion of Fuyang ship lock locally, with a channel mileage of 3km. 4) Reduced resettlement m2 of house –Zhangdianweizi segment impacts demolition and A new 1km channel will be excavated at 1) Channel mileage shortened 1) Higher investment; 2) High relocation of 212 Alternative the root of the protruding marginal bank, greatly; 2) Navigation amount of excavation, difficult households with option with a channel mileage of 1.3km. A new conditions are improved construction; 3) A new bridge is to 1058 people. bridge will be built. significantly. be built 1) Lower investment; 2) Small disturbance to existing river channel; 3) Small amount of The center of channel is arranged along 1) Bent channel; 2) Longer traveling Recommended excavation, easy construction; the existing channel, with a channel distance for vessels than the cut-off Reducing 526 option 4) Not affecting existing mileage of 5km. option mu of land communication and power acquisition, 4700 Avulsion of Zhangdianweizi facilities; 5) Reduced m2 of house -Yingshang ship lock resettlement impacts demolition and segment A new 1,100m channel will be relocation of 204 excavated on flood land, with a channel 1) Channel mileage shortened 1) Higher investment; 2) High households with mileage of 1.1km. The new and old by 3.9km; 2) The channel is Alternative amount of excavation; 3) Affecting 1001 people. channels will form a river islet straightened, and navigation option 3,000m of power and surrounded by water on four sides. To conditions are improved communication lines each provide traffic for villagers, a new significantly. bridge will be built.

6 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Comparison of options Reduced Item Basic description resettlement Advantages Disadvantages impacts The center of channel is arranged largely along the existing channel; the bending 1) Lower investment; 2) Small radius of the channel is small in Sanwan disturbance to existing river 1) Bent channel; 2) Longer traveling Recommended Village, where avulsion measures will channel; 3) Small amount of distance for vessels than the cut-off option be taken to attain the minimum bending excavation, easy construction; Reducing 478 option radius specified in the standard for Class 4) Reduced resettlement mu of land Avulsion of Wenying, - IV channels, with a channel mileage of impacts acquisition, 3600 Bianmei Village segment, 6km. m2 of house Jianying Xiang, Yingshang The existing channel cut off, and a new demolition and County 1,200m channel is excavated on flood relocation of 224 land. The new and old channels will 1) The channel mileage is households with 1) Large amount of work, difficult Alternative form a river islet surrounded by water on shortened by 4.8km; 2) 1108 people. construction; 2) A bridge will be option four sides. To provide traffic for Navigation conditions are built, high construction costs villagers, a new bridge will be built to improved significantly. connect the river islet with the right bank. 1) Lower investment; 2) Small The center of channel is arranged largely disturbance to existing river along the existing channel; the bending channel; 3) Low flood Recommended 1) Bent channel; 2) Long traveling radius of this segment is 300m. The protection level of dyke, Small option distance for vessels Reducing 334 bottom of the channel will be widened amount of excavation, easy mu of land locally. construction; 4) Reduced acquisition, 1400 resettlement impacts Avulsion of Yingshang ship m2 of house The existing channel cut off, and a new lock -Mohekou segment demolition and 1,000m channel is excavated on flood relocation of 112 land. The new and old channels will 1) The channel mileage is 1) Higher investment; 2) High households with Alternative form a river islet surrounded by water on shortened by 1.7km; 2) amount of excavation, difficult 567 people. option four sides. To provide traffic for Navigation conditions are construction; 3) A new bridge is to villagers, a new bridge will be built to improved significantly. be built connect the river islet with the right bank.

7 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Comparison of options Reduced Item Basic description resettlement Advantages Disadvantages impacts 1) Lower costs; 2) Small The center of channel is arranged largely disturbance to existing river along the existing channel. Cusp cutting Reducing 2900 Recommended channel; 3) Small amount of 1) Bent channel; 2) Long traveling measures will be taken locally to attain mu of land option excavation, easy construction; distance for vessels the specified minimum bending radius, acquisition, 6700 Avulsion in Zhengjiawan 4) Reduced resettlement with a channel mileage of about 5km. m2 of house Village, Wanggang Town, impacts demolition and Yingshang County The existing channel cut off, and a new 1) The channel mileage is 1) Higher investment; 2) High relocation of 800 1,000m channel is excavated on flood Alternative shortened by 4km; 2) amount of excavation, difficult households with land. To provide traffic for villagers, a option Navigation conditions are construction; 3) A new bridge is to 3500 people. new bridge will be built to connect the improved significantly. be built river islet with the right bank.

8 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Identification of related projects Related project refers to a project that is directly associated with the Project in function or benefit, and constructed concurrently with the Project during the preparation and implementation of the Project, namely an extended project constructed using funds other than World Bank lending within the range of the Project during the preparation and implementation of the Project. During project design, the Employer attached great importance to the identification of related projects, and the Project Management Office (PMO) and the design agency conducted a correlation analysis of all components. The old Fuyang ship lock is already expired, impeding the navigation of the Shaying River seriously. The Project aims to improve the navigational quality of the channel and improve the shipping capacity of the Shaying River. It has been confirmed by the design agency that the ongoing Fuyang ship lock reconstruction project is implemented together with the Project and is a related project of the Project. The survey results showed that only one project, named Fuyang Shiplock, links to the project, however, the resettlement review failed to find any land acquisition or resettlement. See Appendix 2.

9 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Project Impacts

Project impact survey From October to December 2009, the Anhui Provincial Communications Planning, Survey and Design Institute conducted a resettlement impact survey according to the project design. The Resettlement Planning Team, National Research Center for Resettlement (NRCR), Hohai University conducted a socioeconomic survey was the villages and sub- districts affected by land acquisition and house demolition, visited relevant government agencies to discuss the resettlement and compensation policies of the Project, and interviewed some affected villagers and village officials to discuss possible resettlement programs during December 4-7, 2009 and March 9-15, 2010 with the assistance of the design agency (Anhui Provincial Communications Planning, Survey and Design Institute).

Affected areas Land acquisition, house demolition and temporary land use activities of the World Bank Financed Anhui Shaying River Channel Improvement Project (hereinafter referred to as the “Project”) unavoidable affects one city (Jieshou), three districts (Yingquan, Yingzhou and Yingdong) and two counties (Yingshang and Taihe) of Fuyang Municipality. In particular, the project affects twenty-seven towns in total. Among these,, sixteen towns are affected by permanent occupancy nineteen towns are affected by temporary land use and eight towns are affected by both permanent and temporary land use. As for affected villages, there are forty- nine villages/communities are affected in total, among these, twenty villages/communities are affected by permanent occupancy, thirty-four villages/communities are affected by temporary land use and eight villages/communities affected by both respectively . See Table 0-1 and Table 0-2. Table 0-1 Scope of permanent land use affected areas Component City/ / county Township/ sub-district Village/ community Jieshou City Town Houwei Taihe County Zhaoji Xiang Xiazhangwan Wenji Town Dongxiaotao, Datao Xingliu Town Chenying Zhoupeng Sub-district Fengzhuang Channel works Ninglaozhuang Town Fanying Sanshilipu Town Gaolou Xinji Town Xiawan Huangqiao Town Sanwan Yingshang County Ying River Xiang Sanba Yanghu Town Jinyuzi Jieshou City Xuzhai Town Xiaowan Yingquan District Ninglaozhuang Town Chenying Yingzhou District Sanshilipu Town Wuzhai Supporting works Xingzhai Town Houzhuang Taihe County Jiuxian Town Xijie Chengguan Town Dongzou Garden, Xizou Garden Yingshang County Shencheng Town Shibei Area

Table 0-2 Scope of temporary land use affected areas

No. City/ district/ county Township/ sub-district Village/ community 1 Dongcheng Sub-district Renwan Jieshou city 2 Tianying Town Houwei

10 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

No. City/ district/ county Township/ sub-district Village/ community 3 Zhuzhuang Daxin Town 4 Taihe County Daliu 5 Wenji Town Datao 6 Sanliqiao 7 Fanying 8 Ninglaozhuang Town Chenying Yingquan District 9 Baimiao 10 Dukou 11 Zaozhuang Town Wangzhuang 12 Huayuan Yingzhou District Sanshilipu Town 13 Gaowan 14 Zhaozhuang 15 Yingdong Distirct Yuanzhai Town Yuanzhai 16 Wanghai 17 Wushipu Town Liuxiao 18 Ningda Liushipu Town 19 Zhouzhuang 20 Wangzhuang 21 Huangyin Xinji Town 22 Sugou 23 Fanzhuang 24 Jianying Xiang Xiwan 25 Gucheng Xiang Chentaizi Yingshang county 26 Xiaoji Huangqiao Town 27 Lianggang 28 Bianhai Shibalipu Town 29 Songgou 30 Sanba Balihe Town 31 32 Xinliuji Town Jiangliu 33 Yanghu Town Zhaolou 34 Saijian Town Baliduo

Project impacts According to the physical quantity survey, the types of impact of the Project include: (1) land loss due to permanent land acquisition/ temporary landoccupation; (2) demolition of residential houses; and (3) demolition of attachments. Affected population The Project involves 49 villages/communities in 27 townships/sub-districts of one city (Jieshou), three districts (Yingquan, Yingdong and Yingzhou) and two counties (Taihe and Yingshang), affecting 788 households with 3,140 people permanently (directly). In particular, 424 households with 1,651 people are affected by land acquisition only, 346 households with 1,406 people are affected by house demolition only, and 18 households with 83 people are affected by both land acquisition and house demolition. In addition, the Project affects 2,891 11 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

households with 10,316 people temporarily. See Table 0-3. Table 0-3 Summary of affected population

Project Type Unit Channel Bridge Supporting Subtotal works works works Households affected by / 192 0 232 424 land acquisition only Population affected by / 714 0 937 1,651 land acquisition only Households affected by / 0 346 0 346 house demolition only Directly Population affected by affected / 0 1,406 0 1,406 house demolition only population Households affected by both land acquisition and / 12 0 6 18 house demolition Population affected by both land acquisition and / 56 0 27 83 house demolition Temporarily Households / 2,887 1 3 2,891 affected population Population / 10,302 4 10 10,316

Acquisition of collective land Acquisition of collective land is caused by the channel improvement and supporting works. The Project will acquire 1,658 mu of collective land permanently, involving no basic farmland and affecting 442 households with 1,734 people. The acquired collective land includes 278.1 mu of dry land, accounting for 16.77%; 2824.7 mu of flood land, accounting for 49.74%, 3549.8 mu of unused land, accounting for 33.16%; and 5.4 mu of housing site, accounting for 0.33%. See Table 0-4.

Table 0-4 Summary of permanently acquired collective land

Acquired land (mu) Directly affected population No. Component Dry Flood Unused land Housing site Total Households Population land land Channel 1 192.1 292.26 194.84 3.6 682.8 204 770 works 2 Supporting 86 532.44 354.96 1.8 975.2 238 964

2 According to Some Provisions on the Determination Land Ownership and Use Rights (SLA [1995] No.26) promulgated by the State Land Administration on March 11, 1995, “Land within river embankments, riverside land out of embankments, and land below the historical highest or design flood level of unbanked rivers, except that whose ownership was assigned to farmers during the land reform, that has not been acquired by the state and is still used by farmer collectives, shall be owned by the state”. It was found that the flood land to be acquired for the Project is land whose ownership was assigned to village collectives with a certificate of land ownership, and such land is used for farming by farmers. 3 It has been defined by the Fuyang Municipal Land and Resources Bureau that the unused land of the Project is the land between the main and summer dykes of the Shaying River channel. When the channel encounters a flood, the land will be flooded; such unused land is owned by the collectives of the affected villages along the Shaying River.

12 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

works Total 278.1 824.7 549.8 5.4 1,658 442 1,734 Proportion 16.77% 49.74% 33.16% 0.33% 100.00% \ \

Figure 0-1 Collective land to be acquired

Temporary occupation of collective land The Project occupies 9,843.3 mu of collective land temporarily, which is caused mainly by the spoil grounds occupied for dredging in the channel works. The spoil grounds occupy 9,831.3 mu in total; the land occupied temporarily by the 34 spoil grounds is described in Appendix 6. The remaining temporarily occupied collective land is caused by the piling of construction tools and the erection of construction sheds during construction. The temporarily occupied collective land includes 6,778.8 mu of dry land (68.87%), 26.2 mu pond (0.27%), 1,457.4 mu of nursery (14.81%) and 1,580.9 mu of barren land (16.06%). See Table 0-5 Table 0-5 Summary of temporarily occupied collective land

Temporary occupation of collective land (mu) Affected population Component Dry land Pond Nursery Barren land Subtotal Households Population Channel works 6766.8 26.2 1,457.4 1,580.9 9,831.3 2,887 10,302 Bridge works 3 0 0 0 3 1 4 Supporting works 9 0 0 0 9 3 10 Total 6,778.8 26.2 1,457.4 1,580.9 9,843.3 2,891 10,316 Proportion 68.87% 0.27% 14.81% 16.06% 100.00% \ \

13 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Figure 0-2 Land to be occupied temporarily in spoil ground

Permanent acquisition and temporary occupation of state-owned land The Project will occupy 31 mu of state-owned land for road construction temporarily. The bridge works and the supporting works will occupy 98.83 mu of state-owned land permanently, which is state-owned land for road and watercourse construction, involving no affected population. The impacts of permanent acquisition and temporary occupation of state-owned land are shown in Table 0-6. Table 0-6 State-owned land occupied permanently (temporarily) by the Project Temporary Permanent occupation (mu) occupation (mu) No. Component State-owned land for road Allocation construction 1 Channel works 18 0 2 Bridge works 2 98.83 3 Supporting works 11 0 5 Total 31 98.83 Demolition of residential houses The Project involves demolition of residential houses of 29,686.2 m2 only, including urban residential houses of 27,884 m2, affecting 346 households with 1,406 people, and rural residential houses of 1,802.2 m2, affecting 18 households with 86 people. 1. Demolition of rural residential houses Demolition of rural residential houses affects 3 villages in 3 townships of Yingshang County, Yingzhou District and Taihe County, caused by avulsion in the channel works and the supporting works. Rural residential houses of 1,802.2 m2 will be demolished, including storied buildings of 1,288.5 m2 (71.5%) and single-storied buildings with brick wall and tile roof of 513.7 m2 (28.5%), affecting 18 households with 83 people. See Table 0-7.

Table 0-7 Rural residential houses demolished for the Project

Rural residential houses (m2) Single- City/ district/ Township/ Village/ storied Affected Affected No. Component Storied county sub-district community building with Subtotal households population building brick wall and tile roof Channel Yingshang Ying River 1 improvement Sanba 834.2 322.3 1,156.5 12 56 County Xiang works Management Yingzhou Sanshilipu 2 Wuzhai 356.8 89.1 445.9 4 19 service zone District Town Jiuxi 3 Anchorage Taihe County Xijie 97.5 102.3 199.8 2 8 Community

14 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Total 1,288.5 513.7 1,802.2 18 83 Proportion 71.50% 28.50% 100.00% \ \

Figure 0-3 Rural residential houses to be demolished 2. Demolition of urban residential houses Demolition of urban residential houses affects 6 villages and communities in Jieshou City and Taihe County, caused by the bridge works. Urban residential houses of 27,884 m2 will be demolished, including houses in masonry-concrete structure (Grade 1) of 20,771.35 m2, accounting for 74.49%, and houses in reinforced concrete structure (Grade 1) of 7,112.65 m2, accounting for 25.51%, affecting 346 households with 1,406 people. See Table 0-8. Table 0-8 Urban residential houses demolished for the Project

Demolition of urban houses Affected population City/ district/ Township/ Village/ Component Masonry Reinforced county sub-district community Subtotal concrete concrete Households Population Grade 1 Grade 1 Xicheng Shengli Sub- 2800 1251 1549 36 144 Jieshou Community district Yumin Jieshou City Chengdong Bridge Sub- Shangzhuang 2885 2308 577 29 103 district Jieshou Taihe 8545 7519.6 1025.4 115 506 (old Community Yingnan Bridge S204) Jieshou City Sub- works Shaying district Gangzhuang 8204 4924 3280 91 352 River Bridge Taihe Wenji Datao 2725 2452.5 272.5 36 147 County Town Ying Taihe River County Chengguan Taoqiao 2725 2316.25 408.75 39 154 Bridge Town IV Total 27,884 20,771.35 7,112.65 346 1,406 Proportion 100.00% 74.49% 25.51% \ \

Demolition of attachments Some attachments will be demolished during the construction of the Project, including trees (with diameter of less than 10cm, greater than 10cm and greater than 20cm), tombs and telegraph poles. The Project affects 86,005 trees, 2,213 tombs and 101 telegraph poles. The attachments affected by the Project are shown in Table 0-9, and the details thereof are described in Appendix 7. 15 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Table 0-9 Schedule of affected attachments Trees Tombs Telegraph poles <10cm >10 cm >20 cm Subtotal 17,757 14,207 54,041 86,005 2,213 101

Vulnerable groups In the affected population of the Project, 21 households with 80 people fall into vulnerable groups (0.6% of the affected population), in which 16 households with 74 people receive minimum living security (MLS); and there are 5 five-guarantee households with 6 people. The vulnerable groups affected by the Project are related to the bridge reconstruction work in Jieshou City and the channel works, as shown in Table 0-10. Table 0-10 Schedule of affected vulnerable groups Five-guarantee MLS households Component County Township Village households Households Population Households Population Yingzhou District Sanshilipu Town Gaolou 2 11 1 1 Yingdong District Kouzi Town Zhangdianweizi 1 4 0 0 Channel Xinji Town Xiawan 1 6 2 3 works Huangqiao Town Sanwan 0 0 1 1 Yingshang County Ying River Xiang Sanba 3 14 0 0 Yanghu Town Jinyuzi 4 19 0 0 Yingnan Sub- Taihe Community 1 3 1 1 Bridge works Jieshou City district Gangzhuang 4 17 0 0 Total 16 74 5 6

16 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Socioeconomic Overview of the Affected Areas The Project involves one municipality (Fuyang), three districts (Yingquan, Yingdong and Yingzhou) and three counties/cities (Jieshou City, Taihe County and Yingshang County).

Socioeconomic profile of affected cities and counties/districts Fuyang Municipality—Fuyang is located in northwestern Anhui, the south tip of the Huang-Huai-Hai Plain and the west of the Plain. It borders Zhoukou and Cities, Henan Province on the west, Xinyang City, Henan Province on the southwest, City on the north and northeast, and Huainan City on the east, and abuts on the Huai River across Liu’an City on the south. Presently, Fuyang Municipality governs Jieshou City, Taihe, Linquan, Yingshang and Funan Counties, and Yingzhou, Yingquan and Yingdong Districts, with an area of 9,775 km2 and a population of 9.743 million, being the largest population municipality of Anhui Province. Fuyang abounds with resources, and is an important production base of farm and sideline products of the state, and also a rising coal and energy base of Anhui Province and even the whole eastern China region. According to statistics, Fuyang’s regional GDP was 75.512 billion yuan in 2007, in which the added value of primary industries was 8.131 billion yuan, that of secondary industries 40.401 billion yuan and that of tertiary industries 25.272 billion yuan. Annual social investment in fixed assets attained 43.03 billion yuan, in which the investment in urban fixed assets was 38.821 billion yuan, ranking second in the province. Annual fiscal revenue was 14.013 billion yuan. In 2007, the average pay of in-service workers of Fuyang was 21,708 yuan, per capita disposable income of urban residents 12,866 yuan, per capita consumer expenditure 9,851.65 yuan and per capita net income of farmers 2,683.3 yuan. In 2007, Fuyang’s industrialization level was 50.63% and urbanization rate 47.13%. Yingquan District—Yingquan District enjoys an advantaged geographic location and convenient traffic, run through by the Beijing-Kowloon, Shang-Fu, Luo-Fu, Huai-Fu and Fu- Huai Railways. The largest marshalling yard of the Beijing-Kowloon Railway is located in this district, which is the most automated in Asia. The highway network is developed. This district is run through by National Highway 105, Provincial Highway 202 and the Jie-Fu- Beng Expressway, forming a developed traffic network with five railways. Rural roads provide access to every village, inland transport provides access to rivers and seas, and there are flights leading to major cities. Yingquan District is a county-level district set up when Fuyang became a municipality in 1996, governing 12 townships and sub-district offices, with an area of 648 km2 and a total population of 620,000. It is located in central Fuyang and the hinterland of the extensive Huaibei Plain; it is located in a humid climate zone, with a warm climate, moderate rainfall and sufficient sunshine, and an arable area of 37,000 ha (hectares). Population is 634,000, in which rural population is 538,000, agricultural labor force 206,000, industrial labor force 14,000, transport labor force 8,000, wholesale, retail, trade and catering labor force 15,000, and other labor force 63,000. The district governs 7 towns, 4 sub-district offices, one Xiang and 252 village (neighborhood) committees. The forest coverage rate in its jurisdiction is 27%. Yingdong District—Yingdong District is located in the east of Fuyang and the Huang- Huai-Hai Plain, featuring flat terrain, distinct seasons, moderate rainfall and sufficient sunshine, suitable for the growth of various crops, animals and plants. It borders Yingzhou District on the west, Yingshang County on the south, Yingquan District on the north and on the east. Yingdong District has an area of 684.9 km2 and governs 3 sub- district offices, 8 towns and one Xiang; its total population is 603,000, rural labor force 306,000 and arable area 38,800 ha. Yingzhou District—Yingzhou District is located in the south of Fuyang, being the political, economic, technological, cultural, traffic, financial and information center of Fuyang Municipality with a population of 9 million. With an area of 591 km2, it governs 5 sub-district

17 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

offices and 8 townships. The district has 30,000 ha of arable land and is an important production base of commodity grains, hybrid pigs and high-grade yellow cattle; the six major industrial sectors of textile, farm and sideline food processing, food manufacture, papermaking and paper products, plastic products, nonmetallic mineral products, and printing have taken form, with over 50 major products. Jieshou City—Jieshou City is the northwest gate of Anhui, located at the junction of Jingjiu economic zone and the Eurasia Bridge economic zone, facing the eastern China economic circle centering in , backed by the hinterland of the Central Plains, being an important gateway between the east and west parts of Mainland China, enjoying extensive room of development. The city has a total area of 667.3 km2, an arable area of 620,000 mu and a population of 730,000, and governs 18 Xiangs, towns and sub-district offices. Jieshou City is a national production base of high-grade wheat, cotton, goat and yellow cattle, and a main grain, cotton, oil and meat producing area of Anhui Province. Taihe County—Taihe County is located in the northwest of Anhui, the hinterland of the Huang-Huai Plain, between Fuyang and Bozhou Municipalities, with an area of 1,822 km2 and a population of 1.627 million. Taihe County boasts convenient traffic, sound infrastructure, fertile land and rich produce. Its agriculture is in a tripartite structure of grains, cash crops and feeds. Grain crops include wheat, soybean, corn, sorghum and sweet potato mainly, and cash crops include sesame, rape, cotton, tobacco leaf, mint and Chinese medicinal materials mainly, especially mint, whose annual cultivation area stabilizes at about 250,000 mu. The county’s mint oil output is over 1/3 of national output. Yingshang County—Yingshang County is located at the junction of the Huai and Ying Rivers and the south tip of the Huang-Huai Plain, with an area of 1,859 km2, an arable area of 107,000 ha and a population of 1.6 million. It governs 30 townships and 346 village (neighborhood) committees, being a national ecological exemplary zone, a plain tourist county and a coal-based power town. In 2004 and 2005, it was one of the top 10 most potential counties of Anhui. Yingshang abounds with grains, fruits, timbers, vegetables, livestock and aquatic products, with total output ranking top in Anhui. It is a top 10 livestock and aquatic product county of Anhui, a national base of coarse wool rabbit, a national top 100 grain producing county, a national top 100 landscaping county, a national leading county in water resources construction, a national eco-agriculture exemplary county and a national labor export exemplary county. The key economic indicators of the affected cities and counties are shown in Table 0-1. Table 0-1 Key economic indicators of affected cities/counties

Fuyang Yingquan Yingzhou Yingdong Jieshou Taihe Indicator Municipality District District District City County Total population (10,000) 988 67.9 64.13 62.42 77.2 167.5 Men (10,000) 468 35.2 34 29 36 87.5 Women (10,000) 520 32.7 30.13 33.42 41.2 80 Population Nonagricultural population 121.8 10.7 21.28 12.67 14.6 14.5 (10,000) Labor force (10,000) 689 44 36 41 47 119 Total arable area (1,000 ha) 574.8 3.69 3.18 4.12 39 114.8 Irrigated land (1,000 ha) 45 0.3 0.4 0.72 30 91 Arable Dry land (1,000 ha) 429 2.3 2.34 3.2 2 8 land Other (1,000 ha) 100.8 1.09 0.44 0.2 7 15.8 Grain output (10,000 tons) 502.9 29 22.92 31.8 36 96.2 Output GDP (100 million yuan) 541.27 35 40.03 32.08 50.81 81.5 value Output value (100 Primary 165.57 11.8 10.23 11.14 14.46 26.8 million yuan) industries Proportion (%) 30.59 33.71 25.6 34.73 28.46 32.88 Secondary Output value (100 180.71 5.4 7.45 7.52 19.66 26.3 industries million yuan) 18 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Fuyang Yingquan Yingzhou Yingdong Jieshou Taihe Indicator Municipality District District District City County Proportion (%) 33.39 15.43 18.6 23.44 38.69 32.27 Output value (100 Tertiary 194.99 17.8 22.34 13.41 16.69 28.4 million yuan) industries Proportion (%) 36.02 50.86 55.8 41.8 32.85 34.85 Per capita GDP (yuan) 5478 5155 6242 5139 6582 4866 Per capita disposable income of 3215 3898 4280 2013 4300 4121 urban residents (yuan) Income Per capita net income of rural 3187 3901 3943 2880 3967 3991 residents (yuan) Source: 2008 Fuyang Statistical Yearbook

Socioeconomic profile of affected townships Land requisition and house demolition involves 16 townships/sub-districts of Fuyang. Accoridng to the survey, in the 16 affected townships, there are 240,596 households in total, a total population of 1,082,416 people and a per family population of 4.49 people. Of these townships, per capita net income of farmers ranges from 2,980 yuan (Wenji Town) to 5,400 yuan (Zhoupeng Sub-district); the total arable area of the 16 townships is 709,419 mu, and per capita arable area 0.66 mu, in which Xingliu Town, Zhoupeng Sub-district and Shencheng Town have a smaller per capita arable area, mainly because Zhoupeng Sub-district, Xingliu Town and Shencheng Town are located in outskirts, with a relatively small amount of arable land. Villagers’ main source of income is employment. The key economic indicators of the affected townships are shown in Table 0-2. Table 0-2 Key economic indicators of affected townships/sub-districts Per capita Per capita net No. Township/ sub-district Households Population Arable area arable area income of farmers 1 Tianying Town 6800 31000 21230 0.685 3500 2 Xuzhai Town 14000 63000 39700 0.63 3123 3 Kouzi Town 18445 83000 69000 0.831 3240 4 Sanshilipu Town 9210 41432 38000 0.917 3560 5 Wenji Town 2850 12800 11800 0.922 2980 6 Ninglaozhuang Town 22090 99400 92112 0.927 3600 7 Xingliu Town 25100 113000 32000 0.283 3400 8 Zhoupeng Sub-district 16000 76000 9800 0.129 5400 9 Xiangyang Sub-district 12500 62000 53,000 0.855 5210 10 Shencheng Town 36000 163000 58000 0.356 3500 11 Xinji Town 10600 48050 42525 0.885 3100 12 Huangqiao Town 18961 66692 54150 0.812 3010 13 Ying River Xiang 13000 75784 71700 0.946 3200 14 Yanghu Town 9560 54498 35595 0.653 3400 15 Xingzhai Town 12480 40760 55440 1.36 2990 16 Chengguan Town 13000 52000 25367 0.488 4120

19 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Socioeconomic profile of affected villages The 20 permanent affected villages have 3,449 households in total, a total population of 13,944 people, and a per family population of 4.04. In these villages, per capita net income of farmers ranges from 1,800 yuan (Xiazhangwan Village) to 3,245 yuan (Fanying Village). The total arable area of the 20 villages is 9,533 mu, and per capita arable area 0.68 mu, mainly being dry land, used to grow wheat and other crops. It was learned from the in-depth interview with affected villagers and officials that most of these affected villagers do not rely on agricultural production as the main source of income, a small amount of farmland is left to elderly people for farming and young people mostly work outside. See Table 0-3.

Socioeconomic profile of affected ethnic minorities The Project involves 68 villages in 31 townships of one city (Jieshou City), three districts (Yingzhou, Yingquan and Yingdong) and two counties (Yingshang and Taihe). There are 40,252 households with 170,833 people in the affected areas, including a minority population of 9,212 people, accounting for 5.39% of total population. The Task Force from Hohai University investigated the distribution of ethnic minorities in the affected areas village by village with the assistance of the PMO. There are Hui people in 15 out of the 68 affected villages, in which 3 are villages inhabited centrally by Hui people, namely Saijian, Zhoutai and Baliduo Villages, Saijian Xiang, Yingshang County. Except dietary habits, the villagers of these villages lead the same life as the local Han people. Their children of school age receive the state’s uniform 9-year compulsory education, and their sources of income are the same as the local Han people, mainly being urban employment. In terms of crop cultivation, the local Hui people grow wheat and corn mainly, similar to the Han people. By comparing the features of the affected Hui people with the criteria in World Bank OP4.10, we find that these Hui villages do not meet all the 4 conditions for ethnic minority in World Bank OP4.10. Therefore, these 3 villages are not identified as minority villages for the purpose of World Bank OP4.10. See Appendix 3 for a detailed description of ethnic minorities.

20 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Table 0-3 Socioeconomic profile of affected villages Arable Per capita Per capita annual No. City/ district/ county Township/ sub-district Village/ community Households Population Where: men Labor force area (mu) arable area (mu) net income (yuan) 1 Tianying Town Houwei 224 760 380 530 675 0.89 2,452 Jieshou City 2 Xuzhai Town Xiaowan 150 640 359 420 500 0.78 2,589 3 Yingdong District Kouzi Town Zhangdianweizi 80 300 156 210 270 0.90 3,214 4 Wuzhai 218 699 345 480 512 0.73 2,,980 Yingzhou District Sanshilipu Town 5 Gaolou 121 539 356 420 449 0.83 2,874 6 Datao 117 400 233 250 209 0.52 2,453 Wenji Town 7 Chendian 240 1,060 890 780 700 0.66 3,100 8 Yingquan District Ninglaozhuang Town Fanying 340 1,700 1,001 1,157 1,700 1.00 3,245 9 Xingliu Town Chenying 200 712 356 464 255 0.36 2,579 10 Zhoupeng Sub-district Fengzhuang 60 270 145 189 189 0.70 3,210 11 Shencheng Town Shibei Area 31 121 63 74 130 1.07 3,100 12 Xinji Town Xiawan 152 700 345 546 627 0.90 2,300 13 Yingshang County Huangqiao Town Sanwan 400 1,720 890 1,345 747 0.43 2,250 14 Ying River Xiang Sanba 145 527 329 409 502 0.95 2,100 15 Yanghu Town Jinyuzi 340 1,200 714 817 454 0.38 2,200 16 Xingzhai Town Houzhuang 90 460 213 298 460 1.00 2,300 17 Jiuxi Community Xijie 189 737 352 489 321 0.44 3,150 18 Taihe County Dongzou Garden 89 321 169 197 113 0.35 3,200 Chengguan Town 19 Xizou Garden 110 378 199 245 120 0.32 3,200 20 Zhaoji Xiang Xiazhangwan 153 700 373 489 600 0.86 1,800

21 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Socioeconomic profile of affected households In March 2010, the Task Force from Hohai University conducted a socioeconomic survey of 52 households with 269 people affected by the Project. It was learned that their per capita agricultural income accounted for 31.87% of per capita income, and they also had income from nonagricultural jobs or sideline operations. The profile of the respondents is shown in Table 0-4. Table 0-4 Statistics of affected population

Men Women Total Item Number % Number % Number % Age 6 years 2 1.44% 5 3.85% 7 2.60% 6-16 years 15 10.79% 16 12.31% 31 11.52% 16-60 years 110 79.14% 99 76.15% 209 77.70% 60 years 12 8.63% 10 7.69% 22 8.18% Subtotal 139 100.00% 130 100.00% 269 100.00% Educational level Primary school or below 30 21.58% 35 26.92% 65 24.16% Junior high school 82 58.99% 72 55.38% 154 57.25% Senior high school or above 27 19.42% 23 17.69% 50 18.59% Subtotal 139 100.00% 130 100.00% 269 100.00% Labor force 99 52.66% 89 47.34% 188 100.00%

Age distribution In the 52 surveyed households with 269 people, 7 people are aged below 6 years, accounting for 2.60%; 31 people are aged 6-16 years, accounting for 11.52%; 209 people are aged 16-60 years, accounting for 77.70%; and 22 people are aged above 60 years, accounting for 8.18%. Educational level In the 52 surveyed households with 269 people, 65 people have received primary school or below education, accounting for 24.16%; 154 people have received junior high school education, accounting for 57.25%; and 50 people have received senior high school or above education, accounting for 18.59%. Productive resources In the 52 surveyed households with 269 people, arable area is 237 mu, per capita arable area 0.88 mu and per family arable area 4.56 mu, where the main crop is wheat. Household annual income and expenditure In the 52 surveyed households with 269 people, annual average family income is 3,405.9 yuan, in which wage income is 1,335.5 yuan, accounting for 39.21% and family operating income 1,715.4 yuan, accounting for 50.37% (in which agricultural income is 1,085.5 yuan, accounting for 31.87% of gross income); annual average family expenditure is 2,843.6 yuan, in which family operating expenditure is 545 yuan, accounting for 19.17%, expenditure on purchase of productive fixed assets 68 yuan, accounting for 2.39% and living expenses 1,987.5 yuan, accounting for 69.89%. The income and expenditure structure is shown in Table 0-5.

22 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Table 0-5 Income and expenditure structure of affected rural households Per capita Item Proportion (%) income (yuan) Wage income 1,335.50 39.21% Family operating income 1,715.40 50.37% Where: Income from primary 1,085.50 31.87% industries Income from Annual family 421.50 12.38% secondary industries income Income from tertiary 208.40 6.12% industries Property income 115.00 3.38% transfer income 240.00 7.05% Total 3,405.90 100.00% Family operating expenditure 545.00 19.17% Purchase of productive fixed 68.00 2.39% assets Annual family Tax payment 18.50 0.65% expenditure Living expenses 1,987.50 69.89% Property expenditure 9.10 0.32% Transfer expenditure 215.50 7.58% Total 2,843.60 100.00% Net income4 3,121.00 /

4 The net income = Income – Expenditure of production

23 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Legal Framework and Policy Objectives To drive the land acquisition, house demolition and resettlement work of the Project effectively, protect the lawful rights and interests of the affected people and entities, and enable the successful implementation of the Project, the policies of the Project have been enacted in accordance with the applicable regulations of the People’s Republic of China (RPC), Anhui Province and the Liuzhou Municipal Government on land acquisition and house demolition, as well as the World Bank Operational Policy OP4.12 Involuntary Resettlement. The resettlement work of the Project will be conducted in strict conformity with the policies in the RAP, and any change during implementation has to be approved by the World Bank.

Policy framework The policy framework of the Project is shown in Table 0-1. Table 0-1 List of policies applicable to the Project Policy document Effective date

S Land Administration Law of the PRC 2004-8-28 t a t

e Regulations on the Implementation of the Land Administration Law 1998-12-27 of the PRC (Decree No.256 of the State Council) Decision of the State Council on Deepening the Reform and Rigidly 2004-10-21 Enforcing Land Administration (Guo Fa [2004]28) Interim Regulation of the PRC on Farmland Occupation Tax 2008-1-1 Guidelines on Improving Compensation and Resettlement Systems 2004-11-3 for Land Acquisition (MLR Fa [2004] No.238) Circular of the State Council on Intensifying Land Control (Guo Fa 2006-8-31 [2006] No.31) Measures on Public Announcement of Land Acquisition 2002-1-1 Circular of the Ministry of Land and Resources on Carrying out 2004 MLR Fa No.58 Proper Compensation for Land Acquisition Practically Decision of the State Council on Amending the Regulation of the Regulation of the PRC on the Administration of Navigable 2009-1-1 Waterways

A Measures of Anhui Province for the Implementation of the Land n 2000-9-22 h Administration Law of the PRC u i

P Circular on Regulating Compensation and Resettlement for Land r o Acquisition and Arbitrating Disputes over Land Acquisition Properly 2007-2-15 v i n (ALRD [2007] No.54) c e Uniform Annual Output Value and Compensation Standard for Land 2010-1-1 Acquisition of Anhui Province (APG [2009] No.132) Circular on Issuing the Interim Rules for the Appraisal of Demolished 2004-7-1 urban Houses of Anhui Province (Jian Fang [2004] No.142)

F Measures of Fuyang Municipality for the Administration of Urban u

y 2002-9-21

a House Demolition (FMG Fa [2002] No.3) n

g Announcement on Benchmark Rates of Cash Compensation for M House Demolition on State-owned Land within the Urban Planning 2010-1-1 u n

i Area of Fuyang Municipality in 2009 (FMG Mi [2009] No.20) c i

p Announcement on Benchmark Rates of Cash Compensation for a l

i House Demolition on State-owned Land within the Planning Area of 2008-1-1 t y the Five Counties and Cities in 2008 (FMG Mi [2008] No.29) Circular on Issuing the Measures of Fuyang Municipality for the Implementation of Land Acquisition and House Demolition for Non- 2000-3-10 agricultural Construction (FMG Fa [2000] No.18) Measures of Fuyang Municipality for the Basic Endowment Insurance 2009-5-20 of Land-expropriated Farmers

24 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Policy document Effective date B d o

r Operational Policy OP4.12 Involuntary Resettlement and appendixes 2002-1-1 a l Bank Procedure BP4.12 Involuntary Resettlement and appendixes 2002-1-1

Legal and policy provisions applicable to resettlement ¾ Relevant provisions of the Land Administration Law of the PRC Article 8 Land in urban districts shall be owned by the State. Land in the rural areas and suburban areas, except otherwise provided for by the State, shall be collectively owned by peasants including land for building houses, land and hills allowed to be retained by peasants. Article 10 In lands collectively owned by peasants those have been allocated to villagers for collective ownership according to law shall be operated and managed by village collective economic organizations or villagers’ committee and those have allocated to two or more peasants collective economic organizations of a village, shall be operated and managed jointly by the collective economic organizations of the village or villagers’ groups; and those have allocated to township (town) peasant collectives shall be operated and managed by the rural collective economic organizations of the township (town). Article 45 The acquisition of the following land shall be approved by the State Council: (1) Basic farmland; (2) Land exceeding 35 hectares outside the basic farmland; (3) Other land exceeding 70 hectares. Article 47 In land acquisition, compensation should be made according to the original purposes of the land acquired. Compensation fees for land acquired include land compensation fees, resettlement fees and compensation for attachments to or green crops on the land. The land compensation fees shall be 6-10 times the annual average output value of the three years preceding the acquisition of the cultivated land. The resettlement fee shall be calculated according to the number of agricultural population to be resettled. The number of agricultural population to be resettled shall be calculated by dividing the amount of cultivated land acquired by the per capital land occupied of the unit whose land is acquired. The resettlement fees for each agricultural person to be resettled shall be 4-6 times the average annual output value of the three years preceding the acquisition of the cultivated land. But the maximum resettlement fee per hectare of land acquired shall not exceed 15 times of the average annual output value of the three years prior to the acquisition. In special circumstances, the State Council may raise the standards for land compensation and resettlement fees for land acquired according to the social and economic development level. Article 48 After the plan for land compensation and resettlement fees is finalized, related local people’s governments shall make an announcement and hear the opinions of the rural collective economic organizations and peasants whose land has been acquired. Article 49 Rural collective economic organizations shall make public to its members the receipts and expenditures of the land compensation fees for land acquired and accept their supervision. It is forbidden to embezzle or divert the land compensation fees and other related expenses. Article 50 Local people’s governments at all levels shall support rural collective economic organizations and peasants in their efforts toward development and operations or in 25 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project starting up enterprises. Article 54 A paid leasing should be go through in use of land owned by the State by a construction unit. But the following land may be obtained through government allocation with the approval of the people’s governments at and above the county level according to law: (1) Land for use by government organs and for military use; (2). Land for building urban infrastructure and for public welfare undertakings; (3) Land for building energy, communications and water conservancy and other infrastructure projects supported by the State. (4)Other land as provided for by the law and administrative decrees. Article 57 In the case of temporary using State-owned land or land owned by peasant collectives by construction projects or geological survey teams, approval should be obtained from the land administrative departments of local people’s governments at and above the county level. Whereas the land to be temporarily used is within the urban planned areas, the consent of the urban planning departments should be obtained before being submitted for approval. Land users should sign contracts for temporary use of land with related land administrative departments or rural collective organizations or villagers committees depending on the ownership of the land and pay land compensation fees for the temporary use of the land according to the standard specified in the contracts. Users who use the land temporarily should use the land according to the purposes agreed upon in the contract for the temporary use of land and should not build permanent structures. The term for the temporary use of land shall not usually exceed two years. Article 62 One rural household can own one piece of land for building house, with the area not exceeding the standards provided for by provinces, autonomous regions and municipalities. Construction of rural houses should conform to the general plans for the utilization of land of townships (towns) and the original land occupied by houses and open spaces of villages should be used as much as possible for building houses. The use of land for building houses should be examined by the township (town) people’s governments and approved by the county people’s governments. Whereas occupation of agricultural land is involved the examination and approval procedure provided for in Article 44 of this law is required. ¾ Relevant provisions of the Regulations on the Implementation of the Land Administration Law of the PRC Article 25 Municipal, county people’s government of the locality whose land has been acquired shall, upon approval of the land acquisition plan according to law, organize its implementation, and make an announcement in the village (township), hamlet whose land has been acquired on the approval organ of the land acquisition, number of the approval document, use, scope and area of the acquired land as well as the rates for compensation of land acquisition, measures for the resettlement of agricultural personnel and duration for processing land acquisition compensation. Persons of ownership and persons of use right of the acquired land should, within the duration prescribed in the announcement, go to the competent department of people’s government designated in the announcement to go through the registration for land acquisition compensation on the strength of land ownership certificates. The competent departments of municipal, county people’s governments shall, on the basis of the approved land acquisition plan and in conjunction with the departments concerned, draw up land acquisition compensation and resettlement plan, make an announcement thereof in the village (township), hamlet wherein the acquired land is located to solicit the views of the rural collective economic organizations and peasants on the 26 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project acquired land. The competent departments of land administration of municipal, county people’s governments shall, upon approval of the land acquisition compensation and resettlement plan submitted to the municipal, county people’s governments, organize its implementation. Where a dispute arises over the compensation rates, coordination shall be carried out by local people’s government above the county level; where coordination has failed, arbitration shall be resorted to by the people’s government that approved the land acquisition. Land acquisition compensation and resettlement dispute shall not affect the implementation of the land acquisition plan. Payment of various expenses for land acquisition should be effected in full within 3 months starting from the date of approval of the land acquisition and resettlement plan. Article 26 Land compensation fee goes to the rural collective economic organization; compensation fee for ground appendices and young crops shall be for the owner(s) of ground appendices and young crops. Funds earmarked for land acquisition resettlement subsidy must be used for the designated purpose and shall not be diverted to any other purpose. For persons required to be resettled by the rural collective economic organization, payment of the resettlement subsidy shall be made to the rural collective economic organization to be administered and used by the rural collective economic organization; where resettlement is to be arranged by other units, the resettlement subsidy shall be paid to the resettlement units; where no unified resettlement is required, the resettlement subsidy shall be given to the individuals to be resettled or used for the payment of insurance premium for the resettled persons on gaining the consent of the resettled persons. Municipal, county and village (township) people’s governments should strengthen supervision over the use of resettlement subsidy. ¾ Relevant provisions of the Decision of the State Council on Deepening the Reform and Rigidly Enforcing Land Administration 3. Improving the compensation and resettlement system for land acquisition (12) Improving measures of compensation for land acquisition. County-level and above local people’s governments shall take practical measures so that the standard of living of farmers affected by land acquisition is not reduced by land acquisition. Land compensation, resettlement subsidy and compensation for ground annexes and crops shall be paid in full and timely pursuant to law. If the land compensation and resettlement subsidy pursuant to the prevailing laws and regulations are insufficient to maintain the former standard of living of the farmers affected by land acquisition or to pay the social security expenses of farmers who lose all land due to land acquisition, the people’s governments of provinces, autonomous regions and municipalities directly under the Central Government shall approve an increased resettlement subsidy. If the sum of the land compensation and the resettlement subsidy attains the statutory upper limit and is still insufficient to maintain the former standard of living of the farmers affected by land acquisition, local people’s governments may pay a subsidy from the income from compensated use of state land. The people’s governments of provinces, autonomous regions and municipalities directly under the Central Government shall fix and publish the uniform annual output value standards or integrated land prices for land acquisition of all cities and counties, so that the same price applies to the same kind of land. For key construction projects of the state, land acquisition expenses must be listed in the budgetary estimate in full. Compensation rates and resettlement measures for large and medium-sized water resources and hydropower projects shall be otherwise stipulated by the State Council. (13) Resettling land-expropriated farmers properly. County-level and above local people’s governments shall take specific measures to guarantee long-term livelihoods of farmers affected by land acquisition. For projects with a stable income, farmers may become a shareholder using the right to use of land used for construction approved pursuant to law. 27 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Within the urban planning area, local people’s governments shall bring farmers who lose all land due to land acquisition into the urban employment system, and establish a social security system; out of the urban planning area, in acquiring land collectively owned by farmers, local people’s governments shall reserve necessary arable land or arrange appropriate jobs for farmers affected by land acquisition within the same administrative area; farmers without land who do not have the basic living and production conditions shall be subject to non-local resettlement. The labor and social security authorities shall propose guidelines for the employment training and social security systems for farmers affected by land acquisition as soon as possible. (14) Improving land acquisition procedures. During land acquisition, the ownership of collective land of farmers and the right to contracted management of farmers’ land shall be maintained. Before land acquisition is submitted for approval pursuant to law, the use, location, compensation standard and mode of resettlement of the land to be acquired shall be notified to farmers affected by land acquisition; the survey results of the present situation of the land to be acquired shall be confirmed by rural collective economic organizations and farmers to be affected by land acquisition; if necessary, the land and resources authorities shall organize a hearing in accordance with the applicable provisions. The materials for notification to and confirmation by the farmers affected by land acquisition shall be taken as requisite materials for approval for land acquisition. Accelerate the establishment and improvement of the coordination and judgment mechanism for disputes over compensation and resettlement for land acquisition to protect the lawful rights and interests of farmers affected by land acquisition and land users. Approved matters of land acquisition shall be disclosed unless in special cases. (15) Strengthening Supervision over the implementation of land acquisition. If the compensation and resettlement for land acquisition has not been implemented, the acquired land shall not be used forcibly. The People’s governments of provinces, autonomous regions and municipalities directly under the Central Government shall formulate the procedures for the distribution of the land compensation within rural collective economic organizations on the principle that the land compensation is used for rural households affected by land acquisition mainly. Rural collective economic organizations affected by land acquisition shall disclose the receipt, disbursement and allocation of land compensation fees to their members and accept supervision. The agricultural and civil affairs authorities shall strengthen the supervision over the allocation and use of land compensation fees within rural collective economic organizations. ¾ Relevant provisions of the Guidelines of the Ministry of Land and Resources on Improving Compensation and Resettlement Systems for Land Acquisition Article 1 Compensation rates for land acquisition (2) Fixation of uniform annual output value multiples. The uniform multiple of annual output value for land compensation fees and resettlement subsidy shall be fixed within the statutory range so that land-expropriated farmers’ standard of living is not reduced; if compensation fees for land acquisition calculated from the statutory uniform multiple of annual output value are insufficient for land-expropriated farmers to maintain their former standard of living or insufficient to cover their social security costs, the multiple shall be increased appropriately with the approval of the province-level people’s government; if an aggregate multiple of 30 for land compensation fees and resettlement subsidy is still insufficient for land-expropriated farmers to maintain their former standard of living, the local people’s government shall allocate a certain proportion from the income from the compensated use of state-owned land for subsidization. For basic farmland occupied with lawful approval, the highest compensation rate announced by the local people’s government shall apply. (3) Fixation of composite land prices for land acquisition areas. Where conditions permit, the province-level land and resources authority may fix composite land prices for land 28 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project acquisition for different counties and cities in the province together with other competent authorities, and report such prices to the province-level people’s government for approval, disclosure and implementation. Such prices shall be fixed in consideration of land type, output value, geographic location, farmland rating, per capita arable area, land supply-demand relationship, local economic level and minimum living security level of urban residents, etc. Article 2 Mode of resettlement of land-expropriated farmers: (5) Resettlement for agricultural production. In case of acquisition of farmers’ collective land out of the urban planning area, land-expropriated farmers shall be first provided with necessary farmland using rural collective mobile land, contracted land returned voluntarily by farmers, contracted land turnover and newly added farmland from land development and rearrangement so as to continue with agricultural production. (6) Resettlement by reemployment. Conditions shall be created positively to provide free labor skills training and jobs to land-expropriated farmers. Under equal conditions, the land user shall first employ land-expropriated farmers. In case of acquisition of farmers’ collective land within the urban planning area, land-expropriated farmers shall be included in the urban employment system, and a social security system established for them. (7) Resettlement by dividend distribution. For project construction land with long-term stable return, the affected rural collective economic organization may become a shareholder with compensation fees for land acquisition or the approved right to use the land for construction in consultation with the land user on a voluntary basis. The rural collective economic organization and farmers shall obtain proceeds in the form of priority shares under the contract. (8) Non-local resettlement. If basic production and living conditions are not available to land-expropriated farmers locally, the government may organize non-local resettlement in a unified manner in full consultation with the affected rural collective economic organization and farmers. Article 3 Working procedures of land acquisition: (9) Disclosure of information on land acquisition. Before land acquisition is approved, the local land and resources authority shall notify the purpose and location of the land to be acquired, compensation rates and resettlement mode to the affected rural collective economic organization and farmers in writing. After notification, any attachment or young crop built or cultivated by the affected rural collective economic organization and farmers on the land to be acquired temporarily shall not be compensated for upon land acquisition. (10) Confirmation of land acquisition survey results. The local land and resources authority shall survey the ownership, type and area of the land to be acquired, and the ownership, type and quantity of ground attachments thereon. The survey results shall be confirmed together with the affected rural collective economic organization, farmers and owners of ground attachments. (11) Organization of land acquisition hearing. Before land acquisition is approved, the local land and resources authority shall notify the affected rural collective economic organization and farmers the compensation rates and resettlement mode for the land to be acquired, which shall have the right to apply for a hearing. If the party concerned applies for a hearing, such hearing shall be organized in accordance with the Regulation on Public Hearings of Land and Resources. ¾ Relevant provisions of the Regulation on the Dismantlement of Urban Houses Article 6 Only if the agency about to demolish houses has obtained a permit for house demolition can demolition be implemented. Article 8 When issuing the permit for house demolition, the administrative department for house demolition shall disclose the demolisher, scope and period of demolition specified 29 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project in the permit for house demolition in the form of a house demolition announcement. The administrative department for house demolition and the demolisher shall make proper and timely publicity and explanation to displaced persons. Article 22 The demolisher shall compensate displaced persons hereunder. Article 23 Displaced persons may be compensated in cash or by property swap. Article 24 The amount of cash compensation shall be determined based on the demolished house’s geographic location, purpose and building area, and the appraised price on the real estate market. Specific measures shall be formulated by the people’s governments of provinces, autonomous regions and municipalities directly under the Central Government. Article 25 In case of property swap, the demolisher and the displaced person shall calculate the amount of compensation of the demolished house and the price of the replacement house pursuant to Article 24 above, and settle the price difference of property swap. In case of demolition of an attachment to a non-public-welfare institution’s premises, no property swap shall be made and the demolisher shall offer cash compensation. Article 26 In case of demolition of a public welfare institution’s premises, the demolisher shall rebuild such premises in accordance with the applicable laws, regulations and urban plan, or provide cash compensation. Article 27 In case of demolition of a leased house, and the displaced person and the lessee dissolves the leasehold relation or the displaced person resettles the lessee, the demolisher shall compensate the displaced person accordingly. If the displaced person and the lessee fail to agree on the dissolution of the leasehold relation, the demolisher shall grant property swap to the displaced person. If the replacement house is leased by the former lessee, the displaced person shall enter into a new house lease contract with the former lessee. Article 31 The demolisher shall pay a moving subsidy to the displaced person or the lessee. The rates of the moving subsidy and temporary resettlement subsidy shall be stipulated by the people’s governments of provinces, autonomous regions and municipalities directly under the Central Government. Article 33 If demolition of any non-residential house results in suspension of production or business, the demolisher shall offer appropriate compensation. ¾ Relevant provisions of the Measures of Anhui Province for the Implementation of the Land Administration Law of the PRC Article 25 If any organization or individual needs to use land for construction, it shall go through land use approval formalities according to law. Article 27 If any construction project is to occupy state-owned unused land identified in the master land utilization plan, except otherwise approved by the State Council, such project shall be reported to the provincial people’s government for approval if the occupied area exceeds 4 ha or the municipal or county people’s government for approval if the occupied area does not exceed 4 ha. Article 33 Land acquisition shall be handled as follows: (1) Drafting a land acquisition plan and submitting it for approval. The land administrative authorities of a municipal or county people’s government shall draft a plan for use of farmland for other purposes, a farmland replenishment plan, a land acquisition plan and a land supply plan to the municipal or county people’s government for approval, and escalate them to people’s governments with approval authority for approval. In case of acquisition of woodland, the consent of the woodland administrative authorities shall be obtained in

30 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project advance. (2) Announcement of land acquisition plan. After the land acquisition plan has been approved according to law, the municipal or county people’s government shall disclose the approval authority, approval document number, acquired land’s use, range and area, land compensation rates, resettlement measures of agricultural population and deadline of land compensation in the affected township and village. (3) Compensation registration. The owner and user of the acquired land shall go through the land compensation registration formalities carrying the certificate of land ownership or any other valid certificate with the competent authority for land administration of the municipal or county people’s government within 15 days of announcement. (4) Announcement of land compensation and resettlement program. The competent authority for land administration of the municipal or county people’s government shall draft a land compensation and resettlement program together with other competent authorities according to the approved land acquisition plan, and publish it in the affected township and village to collect comments from the affected rural collective economic organization and farmers for a period of 15 days; after the land compensation and resettlement program has been approved by the municipal or county people’s government, it shall be implemented by the competent authority for land administration of the municipal or county people’s government. If there is any dispute over the compensation rates, such dispute shall be mediated by the county level or above people’s government; failing this, such dispute shall be arbitrated by the people’s government approving land use. (5) Handover of the acquired land. All land acquisition costs shall be paid in full within 3 months of approval of the land compensation and resettlement program. The owner and user of the acquired land shall hand over the acquired land within 30 days of payment. In case of acquisition of farmer contracted land, the land contract change formalities shall be settled according to law…… Article 34 Land compensation standards for acquisition of land other than arable land: (1) For fishponds, etc., 6 times the annual average output value of the preceding 3 years; (2) For orchards, etc., 7 times the annual average output value of the preceding 3 years; in case of no harvest, 6 times the annual average output value of similar land of the preceding 3 years; (3) For reclaimed land which has been cultivated for less than 3 years, 3-4 times the annual average output value of the arable land of the same village (team) of the preceding 3 years; for reclaimed land which has been cultivated for 3 years or more, the same as arable land; (4) Land used for construction collectively owned by farmers, 4-5 times the annual average output value of the arable land of the same village (team) of the preceding 3 years; (5) For other land, 2-3 times the annual average output value of the arable land of the same village (team) of the preceding 3 years. The compensation standards for woodland shall be governed by the applicable laws and regulations. Article 35 Resettlement subsidy standard for every farmer to be resettled: (1) For acquisition of farmland, 3-4 times the annual average output value of the preceding 3 years; (2) For land used for construction collectively owned by farmers, 2-3 times the annual average output value of the arable land of the same village (team) of the preceding 3 years; For barren hills and slopes, no resettlement subsidy is paid.

31 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Article 36 If the farmers to be resettled are unable to maintain their former standard of living, with the approval of the provincial people’s government, the resettlement subsidy may be increased. However, the sum of the land compensation and the resettlement subsidy shall not exceed 30 times the annual average output value of the preceding 3 years of the acquired arable land. Depending on social and economic development, the provincial people’s government may increase land compensation and resettlement subsidy rates for land other than farmland in special circumstances. …… Article 37 Compensation rates for young crops and attachments on the acquired land: (1) Young crops on the acquired farmland shall be compensated for at the output value of the current season; perennial crops shall be compensated for at annual output value; no compensation shall be granted if there is no young crop. (2) No compensation shall be granted if fish fries have been bred for 2 years or more; the compensation shall be 3-4 times breeding costs if fish fries have been bred for less than 2 years. (3) Timber forests, shelter forests and special-purpose forests with an average trunk diameter of over 20cm shall be compensated for at 10%-20% of the value of the actual volume; those with an average trunk diameter of 5-20cm shall be compensated for at 60%- 80% of the value of the actual volume. (4) Nursery stocks, economic forests and firewood forests shall be compensated for at twice the annual average output value of the past 3 years; those without output value yet shall be compensated for at twice the actual investment in forestation. Sapling forests and new forests shall be compensated for at twice the actual investment. (5) The compensation rates for houses and other attachments shall be stipulated by the provincial people’s government. Article 38 Where state-owned farming, forestry, stockbreeding or fishery land is approved for nonagricultural construction, such land shall be compensated for by reference to Article 47 of the Land Administration Law and Articles 34 and 37 of these Measures. Article 42 After the farmland of a rural collective economic organization has been acquired and all its members have been turned into urban residents, the remaining land shall be owned by the state and used by the former rural collective economic organization; when such land is occupied by any construction project, the former rural collective economic organization shall be compensated according to the measures and criteria for land acquisition. Article 43 One rural household can have one housing site only. The housing site area for residential house construction by rural residents shall be as follows: (1) Not more than 160 m2 per household for suburbs, rural towns and markets; (2) Not more than 220 m2 per household for the Huaibei Plain; and (3) Not more than 160 m2 per household for mountain and hilly areas; not more than 300 m2 per household if barren mountain or land is used for residential house construction. Article 44 A rural resident who meets one of the following conditions may apply for the use of housing site: (4) Its former housing site has been acquired according to law;…… ¾ Relevant provisions of the Uniform Annual Output Value and Compensation Standard for Land Acquisition of Anhui Province 1. From January 1, 2010, land compensation fees and resettlement subsidy for

32 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project collective land acquired within the administrative region of the province shall be subject to the new land compensation rates. Compensation rates for large and medium-sized water resources and hydropower projects shall be otherwise stipulated by the State Council. Municipal and county people’s governments may increase their land compensation rates for special types of land based on local conditions. 2. The use of state-owned farm (tree farm, pasture or fishery) land shall be subject to the land compensation rates of the area of the relevant township or sub-district; if there are multiple areas around such farm (tree farm, pasture or fishery), the highest rates of the surrounding areas shall apply. ¾ Relevant provisions of the Measures of Fuyang Municipality for the Basic Endowment Insurance of Land-expropriated Farmers Article 3 People of the agricultural status in household registration who have lost all contracted land or have a per capita arable area of less than 0.3 mu after land acquisition pursuant to law, having attained 16 years of age upon land acquisition and having not effected the basic endowment insurance of urban workers may cover the basic endowment insurance of land-expropriated farmers voluntarily. Article 4 The basic endowment insurance of land-expropriated farmers shall be subject to the principles of insurance upon acquisition, insurance before acquisition and no approval of land acquisition without securing social security costs. Article 6 Endowment insurance funds for farmers land-expropriated farmers consist of unified funds and personal account funds, and shall be used specifically for the basic endowment insurance of land-expropriated farmers…… Article 12 ……When the insured attains the age of 60 years for men and 55 years for women, he/she can receive the basic endowment insurance benefit on a monthly basis from the following month. ¾ Relevant provisions of the Measures of Fuyang Municipality for the Implementation of Land Acquisition and House Demolition for Non- agricultural Construction Article 16 House demolition and resettlement shall be subject to local restoration, non- local resettlement or single compensation: …… Article 18 The resettlement subsidy for land acquisition must be used for the specified purpose and shall not be diverted to any other purpose. The land user shall recruit members of the affected villager team under equal conditions, and the resettlement subsidy shall be used by the land user; if those to be resettled are resettled by any other agency, the resettlement subsidy shall be paid to the resettler; if uniform resettlement is not required, the resettlement subsidy shall be granted to displaced persons or used for their insurance with their consent. Article 19 If all land of the affected collective economic organization or villager team is acquired, the township government (sub-district office) shall escalate relevant materials for household re-registration according to the provisions of the competent provincial authority. Article 25 The compensation rates for municipal roads, highways, railways, water resources projects and public facilities shall be subject to the applicable provisions. ¾ Relevant provisions of the Measures of Fuyang Municipality for the Administration of Urban House Demolition Article 2 These Measures shall apply where houses and attachments are to be demolished for construction on our city’s urban planning area, and displaced persons are to be compensated and resettled. Article 6 Only if the agency about to demolish houses has obtained a permit for house demolition can demolition be implemented. 33 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Article 10 The demolisher may demolish houses itself or through a qualified agency. Neither the administrative department for house demolition nor any other government agency shall act as the demolisher or accept any entrustment of demolition. Article 11 If the demolisher appoints an agency for demolition, it shall issue a power of attorney to the appointed agency and enter into a demolition agency contract therewith. The demolisher shall submit the demolition agency contract to the administrative department for house demolition for record within 15 days of execution of such contract. The appointed agency shall not transfer such appointment. Article 13 The demolisher shall implement house demolition within the scope and period of demolition specified in the permit for house demolition. If the scope or period of demolition is to be changed for any special reason, the relevant formalities shall be completed with the former approval authority. Article 24 Displaced persons may be compensated in cash or by property swap. Unless otherwise specified in laws and regulations, displaced persons shall have the right to select the mode of compensation. Article 25 The amount of cash compensation shall be determined based on the demolished house’s geographic location, purpose and building area, and the appraised price on the real estate market. Article 26 The house area and use for the purpose of cash compensation and property swap shall be as specified in the certificate of title to house property issued by the housing administrative department; if no certificate of title to house property has been obtained, the owner of the demolished house shall apply for the house ownership registration formalities with the house ownership administrative department with the planning permit for construction project within 5 days of issue of the demolition announcement…… Article 27 In case of property swap, if the demolisher and the owner of the demolished house fail to reach an agreement, the amount of compensation of the demolished house and the price of the replacement house shall be calculated hereunder, and the price difference of property swap settled. The price difference of property swap shall be negotiated by the parties concerned; failing this, the appraised price on the real estate market shall apply …… ¾ Relevant provisions of the Announcement on Benchmark Rates of Cash Compensation for House Demolition on State-owned Land within the Urban Planning Area of Fuyang Municipality in 2009 The benchmark rates of cash compensation for house demolition within the urban planning area of Jieshou City, Taihe County, , Funan County and Yingshang County in 2009 shall still be as specified in the Announcement on Benchmark Rates of Cash Compensation for House Demolition on State-owned Land within the Planning Area of the Five Counties and Cities in 2008 (FMG Mi [2008] No.29) issued by the municipal government. ¾ World Bank policy on involuntary resettlement 10. The implementation of resettlement activities is linked to the implementation of the investment component of the project to ensure that displacement or restriction of access does not occur before necessary measures for resettlement are in place. For impacts covered in para. 3(a) of this policy, these measures include provision of compensation and of other assistance required for relocation, prior to displacement, and preparation and provision of resettlement sites with adequate facilities, where required. In particular, taking of land and related assets may take place only after compensation has been paid and, where applicable, resettlement sites and moving allowances have been provided to the displaced persons. For impacts covered in para. 3(b) of this policy, the measures to assist the displaced persons are

34 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project implemented in accordance with the plan of action as part of the project (see para. 30). 11. Preference should be given to land-based resettlement strategies for displaced persons whose livelihoods are land-based. These strategies may include resettlement on public land, or on private land acquired or purchased for resettlement. Whenever replacement land is offered, resettlers are provided with land for which a combination of productive potential, locational advantages, and other factors is at least equivalent to the advantages of the land taken. If land is not the preferred option of the displaced persons, the provision of land would adversely affect the sustainability of a park or protected area, or sufficient land is not available at a reasonable price, non-land-based options built around opportunities for employment or self-employment should be provided in addition to cash compensation for land and other assets lost. The lack of adequate land must be demonstrated and documented to the satisfaction of the Bank. 15. Criteria for Eligibility. Displaced persons may be classified in one of the following three groups: (a) those who have formal legal rights to land (including customary and traditional rights recognized under the laws of the country); (b) those who do not have formal legal rights to land at the time the census begins but have a claim to such land or assets—provided that such claims are recognized under the laws of the country or become recognized through a process identified in the Resettlement Plan; and (c) those who have no recognizable legal right or claim to the land they are occupying.

Main differences between World Bank policies and laws of the PRC Compensation for resettlement of vulnerable groups ¾ Difference: World Bank policies require that special compensation is granted to all vulnerable groups, especially seriously affected households faced with pauperization. In Chinese compensation policies, compensation is based only on the quantity of loss. ¾ Solution: Special funds are available to assist the vulnerable groups, who will be identified during the detailed survey. Consultation and disclosure ¾ Difference: World Bank policies require the affected people are aware of all relevant information, and consulted with as soon as possible. Although there are measures on public announcement of land acquisition in China, the disclosure period is usually so short that the affected people cannot participate effectively. ¾ Solution: Consultation has begun at the early stage (before and during technical assistance). The PMO agrees to disclose the Resettlement Plan and provide the Resettlement Brochure to the affected people as required by World Bank. Lack of legal title ¾ Difference: World Bank policies require all demolished houses, whether lawful or unlawful, shall be compensated for at the same standards. According to Chinese laws, no compensation shall be provided for the acquisition of land and houses of unlawful owners. ¾ Solution: For World Bank financed projects, all affected people, whether lawful or unlawful, whether having ownership or right to use, will be protected before the cut-off date.

35 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Resettlement monitoring, evaluation and reporting ¾ Difference: World Bank requires internal and external resettlement monitoring. However, there is no such requirement in Chinese laws, expect for reservoir projects. ¾ Solution: Internal and external resettlement monitoring systems have been established for all World Bank financed projects, and have been included in the Resettlement Plan.

Resettlement policies of the Project The resettlement policies applicable to the Project have been formulated in accordance with the policies of the PRC, the Anhui Provincial Government, the Fuyang Municipal Government and the World Bank on resettlement. For the purpose of the Project, no alteration shall be made to the relevant policy provisions, criteria for eligibility for entitlement, property appraisal criteria and compensation rates without the approval of the World Bank. According to the existing project design, the main impacts of the Project are land acquisition/occupation and house demolition, etc. The following policies apply to the project impacts. Compensation for acquisition of collective land and labor resettlement (1) In case of land acquisition, the acquired land shall be compensated for based on its original use. Compensation fees for land acquisition include compensation fees for land, ground attachments young crops, and resettlement subsidy. (2) The use of land compensation fees and resettlement subsidy shall be decided by the village congress; the land compensation fees may be paid to the affected village or households; the resettlement subsidy must be used specifically for labor resettlement for the acquired land and shall not be diverted to any other purpose; the compensation fees for ground attachments and young crops shall be paid to their respective owners. After an affected household receives compensation, if it meets the criteria for the endowment insurance of land-expropriated farmers, it may participate in the endowment insurance of land-expropriated farmers. (3) The land compensation rates shall be as specified in the Uniform Annual Output Value and Compensation Standard for Land Acquisition of Anhui Province (APG [2009] No.132). Policy for permanent acquisition of state-owned land According to the applicable laws and regulations, the state-owned land occupied permanently by the Project is allocated gratuitously. Compensation and resettlement policies for houses on collective land

4.4.3.1 Compensation and resettlement for house demolition In the Project, residential houses to be demolished on collective land shall be subject to local restoration, non-local resettlement or single compensation; displaced persons will also receive a moving subsidy, a temporary resettlement subsidy and an incentive, etc. After receiving cash compensation, displaced persons may select different modes of resettlement based on their economic condition and family need. (1) Local restoration: If any commercial residential complex is built, the demolished house shall be restored at the former building area in principle and compensated for at replacement cost. The price of the restored house shall be calculated at the cost price

36 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

approved by the pricing authority. (2) Non-local resettlement: Where local restoration is infeasible, the relocated household shall enter a new countryside planning resettlement area according to the house demolition and resettlement plan of the land administrative department, and may purchase a house at the same price as the compensation rate for the demolished house. In addition, the village collective may also reallocate a housing site of the same area to the relocated household to rebuild a house. (3) Any relocated household to which neither local restoration nor non-local resettlement is feasible shall be compensated at a time at 150% of the amount of compensation for the demolished house. The additional 50% compensation is higher than that for the housing site.

4.4.3.2 Subsidies for relocation A moving subsidy and a lease subsidy for the transition period of house construction shall be granted to relocated households. (1) Moving subsidy: 200 yuan/household; (2) Lease subsidy for the transition period of house construction: 2 yuan/month·m2. Compensation and resettlement policies for houses on state-owned land The compensation for demolition of residential houses include house compensation fees and moving subsidy, etc, and displaced persons shall be resettled by cash compensation or property swap; displaced persons shall have the right to select the mode of compensation.

4.4.4.1 Compensation and resettlement for house demolition (1) In case of cash compensation, the compensation price of the demolished house shall be determined based on the demolished house’s geographic location, purpose and building area, and the appraised price on the real estate market, and paid to the displaced person, who shall secure a resettlement house itself. (2) In case of property swap, the amount compensation of the demolished house and the price of the replacement house shall be determined based on the demolished house’s geographic location, purpose and building area, and the appraised price on the real estate market; The price difference between the demolished house and the replacement house shall be negotiated by the parties concerned; failing this, the appraised price on the real estate market shall apply. The demolisher shall resettle the displaced person or lessee within the specified transition period (not more than 18 months). (3) If any displaced person selects cash compensation other than property swap, a subsidy of 20% shall be added to the appraised value of cash compensation for house demolition (including house and courtyard).

4.4.4.2 Subsidies for relocation (1) Moving subsidy: 4 yuan/m2 based on building area (2) Temporary resettlement subsidy: 5‰ of the benchmark rate (unit price) of demolished houses per month-m2 Compensation and restoration policies for temporary land occupation Temporary occupation of rural collective land shall be compensated for based on the purpose and loss of occupation. Compensation fees for temporary land occupation include young crop/ground attachment compensation fees, and land reclamation fees. Land occupied temporarily by the Project includes land occupied temporarily by construction sites and spoil grounds, mainly spoil grounds. These spoil grounds are mostly 37 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

hollow farmland and its level may be increased after disposal. In addition, fertile river bottomland can improve the fertility of the temporarily occupied land and eliminate the need for reclamation. Therefore, only young crop/ground attachment compensation fees are calculated for the farmland occupied by the spoil grounds without reclamation fees. For the land occupied temporarily by construction sites, compensation fees include young crop/ground attachment compensation fees and land reclamation fees. ¾ Temporarily occupied land shall be compensated for based on the period of occupation and the annual output value of land; non-arable land shall be compensated for by reference to arable land; the compensation rate is 1,500 yuan/mu/year; the period of temporary occupation shall not exceed 2 years. ¾ Land reclamation fees are 6 yuan/m2, and are not calculated for unused land. To reduce the impact of land acquisition on young crops, the Project will be constructed after harvesting or before sowing as the case may be, subject to a one month prior notice to affected farmers. No compensation fees shall be calculated for temporary occupation of state-owned land. Demolished ground attachments shall be compensated for at replacement cost or restored by the PMO according to the former standard and size under the project budget. Compensation policy for vulnerable groups In addition to the above policies, vulnerable groups affected by the Project are also entitled to some other preferential policies: ¾ If any displaced person is incapable of work, has no means of living or statutory supporter, the village committee shall assist him/her in building a house or send him/her to an old people’s home. ¾ Labor in households falling into vulnerable groups shall be provided with occupational training, job information and guidance to increase their job opportunities. ¾ During project construction, children of households falling into vulnerable groups shall be first recruited to do unskilled jobs. ¾ The agency responsible for relocation shall do its best to aid and support the relocation of households falling into vulnerable groups. Compensation policy for affected infrastructure and ground attachments Special facilities affected by the Project will be compensated for or rebuilt as required according t the former function, size and standard under the project budget. All ground attachments affected by the Project will be compensated for directly to their owners at replacement cost.

38 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Compensation rates The compensation rates for different impacts of the Project have been fixed according to the above legal framework, and by reference to the policies of the PRC, the Anhui Provincial Government, the Fuyang Municipal Government and the World Bank on resettlement.

Compensation rates for acquisition of rural collective land The compensation rates for acquisition of collective land have been fixed according to the Land Administration Law of the PRC, the Guidelines on Improving Compensation and Resettlement Systems for Land Acquisition, the Measures of Anhui Province for the Implementation of the Land Administration Law of the PRC and Uniform Annual Output Value and Compensation Standard for Land Acquisition of Anhui Province (APG [2009] No.132)5, etc., and the information and field survey findings provided by the municipal land and resources bureau concerned: (1) For farmland acquired for the Project, depending on per capita arable area, land compensation fees will be 6-10 times the uniform annual output value of the past 3 years (2007, 2008 and 2009) and resettlement subsidy 12-16 times the uniform annual output value of the past 3 years, totaling 28,000-53,000 yuan/mu, and young crop compensation fees 1/2 of the annual average output value of the past 3 years. (2) For unused land acquired for the Project, since such unused land is contracted to farmers by the collective for reclamation and planting, farmers can receive agricultural income except during the period of channel inundation. To ensure that farmers’ income is not reduced after land acquisition and their standard of living is not lower than the pre-acquisition level, the land compensation fee and resettlement subsidy rates of the Project are higher than those specified in the Uniform Annual Output Value and Compensation Standard for Land Acquisition of Anhui Province (APG [2009] No.132). The rates for both land compensation fees and resettlement subsidy are 6 times the uniform annual output value of the past 3 years (In the Uniform Annual Output Value and Compensation Standard for Land Acquisition of Anhui Province, the compensation rate for unused land is 5 times the uniform annual output value of the past 3 years and that for resettlement subsidy 5-6 times the uniform annual output value of the past 3 years), and the compensation rate for young crops is still 1/2 of the output value of the past 3 years. The uniform annual output values and compensation rates of the rural collective land acquired for the Project are shown in Table 0-1. The compensation rates for rural housing sites shall be based on those for farmland6.

5 The compensation rate is clarified as follows:1) uniform annual output value; 2) comprehensive plot land price. The compensation rate is mainly calculated on the basis of land output value and per capita land. For this project, the uniform annual output value is applicable. 6 Since housing sites are available only by acquiring farmland, the compensation rates for housing sites of the Project shall be based on those for farmland on the basis of “replacement”. 39 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Table 0-1 Uniform annual output values and compensation rates for land acquisition

Farmland7 Unused land

Output fees M compensation ulLand tisubsidy pleResettlement fees Co compensation mpLand ensat subsidy ionResettlement ratefees (y compensation uan crop Young /mu) Subtotal fees Mcompens ulLand tisubsidy pleResettlement fees Co compensation mpLand ensat subsidy ionResettlement ratefees (y compensation uan crop Young /mu) City/ district/ value of Subtotal Subtotal Subtotal No. Township/ sub-district Village/ community county P3Y

(yuan/mu) ation

1 Tianying Town Houwei 1480 7 14 21 10360 20720 740 31820 6 6 12 8880 8880 740 18500 Jieshou City 2 Xuzhai Town Xiaowan 1430 7 14 21 10010 20020 715 30745 6 6 12 8580 8580 715 17875 Yingdong 3 Kouzi Town Zhangdianweizi 1400 8 15 23 11200 21000 700 32900 6 6 12 8400 8400 700 17500 District 4 Yingzhou Wuzhai 1400 8 15 23 11200 21000 700 32900 6 6 12 8400 8400 700 17500 Sanshilipu Town 5 District Gaolou 1400 8 15 23 11200 21000 700 32900 6 6 12 8400 8400 700 17500 6 Datao 1400 8 15 23 11200 21000 700 32900 6 6 12 8400 8400 700 17500 Wenji Town 7 Chendian 1400 8 15 23 11200 21000 700 32900 6 6 12 8400 8400 700 17500 Yingquan 8 Ninglaozhuang Town Fanying 1400 8 15 23 11200 21000 700 32900 6 6 12 8400 8400 700 17500 District 9 Zhoupeng Sub-district Fengzhuang 1580 9 15 24 14220 23700 790 38710 6 6 12 9480 9480 790 19750 10 Xingliu Town Chenying 1580 9 15 24 14220 23700 790 38710 6 6 12 9480 9480 790 19750 11 Yingshang Shencheng Town Shibei Area 1500 7 15 22 10500 22500 750 33750 6 6 12 9000 9000 750 18750 County 12 Xinji Town Xiawan 1370 6 14 20 8220 19180 685 28085 6 6 12 8220 8220 685 17125 13 Huangqiao Town Sanwan 1460 7 14 21 10220 20440 730 31390 6 6 12 8760 8760 730 18250 14 Ying River Xiang Sanba 1370 6 14 20 8220 19180 685 28085 6 6 12 8220 8220 685 17125

7 According to APG [2009] No.132, the compensation rates were provided for two categories of collective land: farmland and unused land. The dry land, flood land and land for housing site will be treated as farmland and paid at the same compensation rate.

40 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

15 Yanghu Town Jinyuzi 1370 6 14 20 8220 19180 685 28085 6 6 12 8220 8220 685 17125 16 Xingzhai Town Houzhuang 1780 6 12 18 10680 21360 890 32930 6 6 12 10680 10680 890 22250 17 Jiuxian Town Xijie 1780 6 12 18 10680 21360 890 32930 6 6 12 10680 10680 890 22250 Taihe 18 Dongzou Garden 2000 10 16 26 20000 32000 1000 53,000 6 6 12 12000 12000 1000 25000 County Chengguan Town 19 Xizou Garden 2000 10 16 26 20000 32000 1000 53,000 6 6 12 12000 12000 1000 25000 20 Zhaoji Xiang Xiazhangwan 1780 6 12 18 10680 21360 890 32930 6 6 12 10680 10680 890 22250 Note Land compensation and resettlement subsidy rate is calculated based on AAOV and landholding per capital of the affected village, etc.

41 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Compensation rates for permanent occupation of state-owned land The land for construction of the Project is state-owned land for public infrastructure, which is obtained by allocation.

Compensation rates for temporary land occupation According to the provisions of the state, Anhui Province and Fuyang Municipality on temporary land occupation, compensation fees for temporary land occupation include young crop/ground attachment compensation fees and land reclamation fees. Land occupied temporarily by the Project is occupied mainly by the spoil grounds. These spoil grounds are mostly hollow farmland and its level may be increased after disposal. In addition, fertile river bottomland can improve the fertility of the temporarily occupied land and eliminate the need for reclamation. After consultation between the Employer and farmers, farmers have come to support the Project. Therefore, only young crop/ground attachment compensation fees are calculated for the farmland occupied by the spoil grounds without reclamation fees. Except the land occupied temporarily by the spoil grounds, compensation fees for land occupied temporarily by the Project include young crop/ground attachment compensation fees and land reclamation fees. Temporarily occupied land shall be compensated for based on the period of occupation and the annual output value of land; non-arable land shall be compensated for by reference to arable land To reduce the impact of land acquisition on young crops, the Project will be constructed after harvesting or before sowing as the case may be, subject to a one month prior notice to affected farmers. The compensation rates for temporary land occupation are shown in Table 0-2. Table 0-2 Compensation rates for temporary land occupation Young crop/ground Land reclamation fees Item attachment compensation (yuan/m2) fees (yuan/mu· year) Compensation rates for temporary land 1500 6 occupation Remarks Based on 2 years

Compensation rates for demolition of houses on collective land The replacement cost rates for different types of houses have been fixed according to the relevant provisions of Anhui Province and Fuyang Municipality, and by reference to the replacement cost analysis of the main types of affected houses and the compensation rates of similar past projects, as shown in Table 0-3. Table 0-3 Compensation rates for demolition of rural residential houses Type Unit Compensation rate Remarks (yuan/unit) 1) House compensation Storied buildings m2 410 Single-storied m2 260 building with brick wall and tile roof 2) Other costs Moving subsidy Household 200

42 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Temporary Month ·m2 2 Based on the actual period, estimated resettlement to be 6 months in this report subsidy

Compensation rates for demolition of houses on state-owned land Urban house demolition for the Project involves Jieshou City and Taihe County; the compensation rates have been fixed based on actual market appraised prices according to the benchmark rates of Fuyang Municipality and the affected districts and counties, and by reference to the geographic location and building area of each house, the compensation rate is possibly changed according to the evaluation prior to house demolition. The compensation rates for residential houses are shown in Table 0-4. Table 0-4 Compensation rates for demolition of urban residential houses Compensation rate (yuan/unit) Remarks Type Unit Jieshou Taihe City County 1) House compensation Reinforced concrete m2 1430 1480 Grade 1 Tier-1 areas Masonry concrete m2 1250 1300 Grade 1 2) Other costs Moving m2 4 4 subsidy 1) 5‰ of the benchmark rate (unit price) of demolished houses per month-m2 Temporary 2) Based on the actual period, estimated to be 6 Month resettlemen 5‰ 5‰ months in this report ·m2 t subsidy 3) The demolisher shall resettle the displaced person or lessee within the specified transition period (not more than 18 months).

Compensation rates for ground attachments Special facilities affected by the Project will be compensated for or rebuilt as required according t the former function, size and standard. All ground attachments affected by the Project will be compensated for directly to their owners at replacement cost. The compensation rates for affected ground attachments are shown in Table 0-5. Table 0-5 Compensation rates for ground attachments No. Type / feature Unit Compensation rate (yuan/unit) 1 Arbor tree less than 10cm in / 4 diameter 2 Arbor tree 10cm-20cm in / 12 diameter 3 Arbor tree over 20cm in diameter / 20 4 Tomb / 240 5 Telegraph pole / 30

43 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Other costs The rates for other land acquisition and house demolition costs of the Project are shown in Table 0-6. Table 0-6 Compensation rates for other costs No. Item Charging standard Basis Farmland occupation Tier-18: 37.5/m2 Cai Nong Cun [2008] 1 tax Other9: 18.75/m2 No.367 Endowment insurance FMG Ban [2009] 2 premium of land- 25 yuan/m2 No.45 expropriated farmers 3 Water resources fund 500 yuan/mu APG [2000] No.3 4 Land reclamation fees 8 yuan/m2 Land acquisition 5 4% of total basic resettlement costs management fees 6 Survey and design fees 3% of total basic resettlement costs 7 Administrative fees 5% of total basic resettlement costs 8 Technical training fees 1% of total basic resettlement costs 9 External M&E fees 0.5% of total basic resettlement costs 10% of the sum of basic land resettlement costs, design fees, 10 Contingencies implementation fees, training fees and monitoring fees

8 Hedong, Xiangyang and Xinqiao Sub-district Offices, Yingdong District, Fuyang; Wenfeng and Qinghe Sub-district Offices, seats of the Yingxi and Wangdian Governments, Yingzhou District, and the administrative villages to the north; Quanying, Quanbei and Zhoupeng Sub- district Offices, Yingquan District; 9 Areas except Tier-1areas 44 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Production and Livelihood Restoration Programs for Displaced Persons The resettlement objective of the Project is to ensure that the displaced persons can receive full compensation for their losses, reasonable resettlement and satisfactory restoration, enable them to share the benefits of the Project and assist them in temporary difficulties, so that their income level and standard of living, and the affected enterprises’ production capacity and profitability are improved or at least restored, in real terms, to pre-displacement levels or to levels prevailing prior to the beginning of project implementation, whichever is higher. According to the applicable policies and the consultation with the affected people, the municipal PMO has developed compensation and resettlement programs for the affected people.

Resettlement objective To ensure that the displaced persons can receive full compensation for their losses, reasonable resettlement and satisfactory restoration, enable them to share the benefits of the Project and assist them in temporary difficulties, so that their income level and standard of living, and the affected enterprises’ production capacity and profitability are improved or at least restored, in real terms, to pre-displacement levels or to levels prevailing prior to the beginning of project implementation, whichever is higher

Resettlement principles 1. Principle of minimizing resettlement Since the Project is in a belt form, the design route may be modified appropriately to minimize the resettlement impacts of the Project. 2. Principle of equivalent compensation To ensure that displaced persons’ standard of living is not reduced due to project implementation, the principle equivalent compensation will apply, which has two aspects: compensating for properties at replacement cost and for other losses on an equivalent basis. 3. Principle of key concern 1) The Project will pay attention to vulnerable groups (old people not living together with adult children, widows, single-parent families, the disabled, chronic patients and the poor). During relocation, they will be offered preferential policies in housing and employment, etc. After relocation, they will be visited regularly and assisted in special difficulties until handover to local civil affairs authorities. 2) Developmental relocation will be planned and local government forces utilized to give employment training to displaced persons and create job opportunities for them so that they can adapt to the environment of the resettlement site and become self-reliant economically, and the responsibility of resettlement is transferred from the resettlement agencies to displaced persons themselves. 3) The Project will pursue maximum resettlement cost-effectiveness, endeavor to improve the resettlement capacity of the resettlement agencies, regulate resettlement behavior and establish a sound internal control mechanism to prevent the waste and retention of funds, make good use of resettlement funds and attain the best resettlement effects.

Permanent acquisition of collective land Impact analysis of permanent land acquisition The Project acquires 1,658 mu of collective land permanently, involving 20 villages of Fuyang Municipality, affecting 442 households with 1,734 people, including dry land (278.1 mu), flood land (824.7 mu), unused land (549.8 mu) and housing base plot(5.4 mu).

45 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

In the socioeconomic survey, a comparative analysis was made of the farmland of the 20 affected villages before and after land acquisition. In terms of land loss rate, 7 villages have a land loss rate of less than 10%, 6 villages 10%-20%, 4 villages 20%-50% and 3 villages above 50%. The impacts of permanent land acquisition are shown in Table 0-1. In the 13 villages with a land loss rate of over 10%, except Xijie, Houzhuang and Sanba Villages, the other villages were acquired of land for dyke and dam works built in the 1970s. After that, the per capita arable area of these villages has been low, and the villagers here have no longer relied on agricultural production as their main source of income. Crops on their land are used mainly for own consumption, and the labor in the village earns a living by employment mainly, so land acquisition will not affect their income greatly. The Task Force has learned from interview that the villagers of these 7 villages generally think that they will have more opportunities of developing in town after receiving sufficient and reasonable cash compensation and training. For Xijie, Houzhuang and Sanba Villages, the Task Force has learned from interview that though the per capita arable area of these 3 villages is relatively high, the farmland is mainly flood land close to the channel and becomes non-arable in the flood season, agricultural income is restricted by season and natural environment, and still accounts for a small portion of their gross income. The main sources of family income are employment and doing business in town. Therefore, land acquisition will not affect the income the villagers of these 3 villages greatly. Farmers generally support land acquisition but ask for reasonable compensation, preferably cash compensation.

46 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Table 0-1 Impact analysis of acquisition of collective land

Affected City Acquired land area (mu) Land area after Per capita Per capita arable Township/ Village/ House Popu- Land area population Impact No. / district/ land acquisition arable area area after land sub-district community -holds lation (mu) Unused Dry House Popu- rate county Flood land Subtotal (mu) (mu) acquisition (mu) land land -holds lation 1 Jieshou Tianying Town Houwei 224 760 675 8.16 5.44 0 13.6 2 7 2.01% 661.4 0.89 0.87 2 Municipality Xuzhai Town Xiaowan 150 640 500 100.74 67.16 0 167.9 41 159 33.58% 332.1 0.78 0.52 Yingdong 3 Kouzi Town Zhangdianweizi 80 300 270 28.02 18.68 48.4 95.1 21 71 35.22% 174.9 0.90 0.58 District 4 Yingzhou Sanshilipu Wuzhai 218 699 512 124.02 82.68 56 262.7 81 347 51.31% 249.3 0.73 0.36 5 District Town Gaolou 121 539 449 36.24 24.16 20.7 81.1 8 34 18.06% 367.9 0.83 0.68 6 Datao 117 400 209 7.98 5.32 0 13.3 7 29 6.36% 195.7 0.52 0.49 Wenji Town 7 Chendian 240 1,060 700 15.12 10.08 0 25.2 6 27 3.60% 674.8 0.66 0.64 8 Yingquan Ninglaozhuang Fanying 340 1,700 1,700 37.62 25.08 0 62.7 9 35 3.69% 1,637.3 1.00 0.96 District 9 Xingliu Town Chenying 200 712 255 17.64 11.76 0 29.4 14 44 11.53% 225.6 0.36 0.32 Zhoupeng 10 Fengzhuang 60 270 189 32.1 21.4 30 83.5 21 90 44.18% 105.5 0.70 0.39 Sub-district Shencheng 11 Shibei Area 31 121 130 54.9 36.6 0 91.5 12 47 70.38% 38.5 1.07 0.32 Town 12 Xinji Town Xiawan 152 700 627 11.46 7.64 0 19.1 4 14 3.05% 607.9 0.90 0.87 Yingshang Huangqiao 13 Sanwan 400 1720 747 40.32 26.88 55.3 122.5 57 221 16.40% 624.5 0.43 0.36 County Town 14 Ying River Xiang Sanba 145 527 502 141.96 94.64 67.7 304.3 61 223 60.62% 197.7 0.95 0.38 15 Yanghu Town Jinyuzi 340 1200 454 29.46 19.64 0 49.1 24 89 10.81% 404.9 0.38 0.34 16 Xingzhai Town Houzhuang 90 460 460 48.3 32.2 0 80.5 13 55 17.50% 379.5 1.00 0.83 17 Jiuxi Community Xijie 189 737 321 42.3 28.2 0 70.5 38 141 21.96% 250.5 0.44 0.34 Taihe Dongzou 18 89 321 113 6 4 0 10 3 14 8.85% 103 0.35 0.32 County Chengguan Garden Town 19 Xizou Garden 110 378 120 7.26 4.84 0 12.1 6 21 10.08% 107.9 0.32 0.29 20 Zhaoji Xiang Xiazhangwan 153 700 600 35.1 23.4 0 58.5 14 66 9.75% 541.5 0.86 0.77 Total \ \ \ 3,449 13,944 9,533 824.7 549.8 278.1 1,652.6 442 1,734 \ 7,880.4 0.68 0.57

47 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Resettlement program for permanent land acquisition At the feasibility study and preliminary design stages, the design agency compared the project options to minimize resettlement impacts. In March 2010, the Task Force held a focus group discussion with every village affected by land acquisition and house demolition to discuss a resettlement program, and determined the general resettlement plan based on displaced persons’ opinions and the practical conditions of the affected areas, namely compensation and resettlement by direct cash compensation and social security. According to most focus group discussions and interviews with affected people, all affected households ask for cash compensation with or without land reallocation in the village. The affected households will use the remaining land to cultivate cash crops and obtain a secure source of income. The main livelihood restoration measures of the Project include: (1) The affected households use compensation fees received and the remaining land to cultivate cash crops, deal with sideline operations or do small commodity business; (2) Eligible land-expropriated farmers will be covered by the basic endowment insurance of land- expropriated farmers after receiving compensation; (3) The spoil grounds are used to improve medium and low yield land, increase agricultural income and reduce the impact of land acquisition; and (4) The affected labor receives free technical training and job information. The resettlement program for those affected by land acquisition is shown in Table 0-2. Table 0-2 Resettlement program for acquisition of collective land Resettlement program Affected Agricultural (with remaining land) or Endowment insurance of land- population nonagricultural resettlement (people) expropriated farmers (people) 1,734 1,684 50

a) Direct cash compensation and agricultural resettlement with remaining land The affected villages are located along the Shaying River channel. Before project implementation, except Xijie, Sanba and Houzhuang Villages, the other villages have been acquired of land for channel, dyke and dam construction projects. Therefore, the affected villager teams have established practices for allocation of land compensation fees, which will be followed in the allocation of land compensation fees of the Project. According to the practical situation of the affected villager teams, land compensation fees will be allocated as follows mainly: Resettlement subsidy, and land and young crop compensation fees will be paid directly to the affected households without land reallocation. The Task Force has learned from the survey that among the affected villages, the committee of Xiazhangwan Village will draw 1,000 yuan/mu from land compensation fees as collective funds for developing the collective economy or public welfare programs. This mode has been recognized by the local villagers. Except Xiazhangwan Village, the other 26 affected villages will pay resettlement subsidy, and land and young crop compensation fees to farmers in full without land reallocation. b) Basic endowment insurance of land-expropriated farmers According to the Measures of Fuyang Municipality for the Basic Endowment Insurance of Land-expropriated Farmers, within the urban planning area of Fuyang, land-expropriated farmers who lose all land or have a per capita arable area of less than 0.3 mu, have attained 16 years of age upon land acquisition and have not participated in the basic urban endowment insurance may join the endowment insurance of land-expropriated farmers shall be covered by endowment insurance of land-expropriated farmers. Based on an impact analysis of land acquisition (Table 6-1), the per capita arable area of Xizou Garden will be less than 0.3 mu after land acquisition.

48 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

According to the survey, security funds of land-expropriated farmers consist of funds of a unified account 10 and an individual account. Under different programs, land-expropriated farmers are entitled to different policies. Personal account funds for the endowment insurance of land-expropriated farmers include premiums paid voluntarily by land-expropriated farmers and interests thereon. There are 3 payment levels of endowment insurance premiums: Level 1 3,600 yuan, Level 2 7,200 yuan and Level 3 10,800 yuan. Land-expropriated farmers participating in endowment insurance will receive endowment insurance benefits monthly from the following month when attaining the age of 60 years for men or 55 years for women. Endowment insurance benefits received by land-expropriated farmers consist of a basic benefit and a supplementary benefit. The basic benefit will be paid from the unified account, while the supplementary benefit from the personal account. After the personal account is used out, the supplementary benefit will be paid from the unified account. Personal account funds of the basic endowment insurance of land-expropriated farmers include individual payment, collective payment and interests thereon. The village collective will pay 4,000 yuan for each insured from land compensation fees and the collective economic organization’s operating income, etc., or this sum will be paid by the village collective or each individual directly to the municipal special financial account of endowment insurance funds of land-expropriated farmers. Depending on the type of insurance, land-expropriated farmers participating in endowment insurance may be entitled to different benefits, as shown in Table 0-3. Table 0-3 Payment and benefit rates of endowment insurance for land-expropriated farmers Payment composition Benefit (yuan/month) No. Type and standard (yuan) Individual Collective Basic Supplementary Total Non-payment by both individual 1 0 0 80 0 80 and village collective Non-payment by individual, 2 0 4,000 80 50 130 payment by village collective 3,600 0 80 40 120 Payment by individual, 3 7,200 0 80 80 160 non-payment by village collective 10,800 0 80 120 200 3,600 4,000 80 90 170 Payment by both individual 4 7,200 4,000 80 130 210 and village collective 10,800 4,000 80 180 260 Those villagers affected by land acquisition can receive at least 28,000 yuan/mu for their acquired land, which is higher than the highest payment level of the endowment insurance of land-expropriated farmers of 10,800 yuan. In addition, even if affected households and villages make no payment, eligible land-expropriated farmers will also receive a monthly benefit of 80 yuan. Therefore, land-expropriated farmers will receive land compensation fees that are sufficient for endowment insurance payment and their livelihood will be ensured. In addition, According to the survey, most affected farmers, especially elderly ones, are willing to participate in endowment insurance. The implementation plan for the endowment insurance of land-expropriated farmers is described in Appendix 5. c) Medium and low yield land improvement To reduce the impact of land acquisition and temporary land occupation on the villages along the Shaying River, and in consideration of the utilization of river bottom fertile spoil11,

10 The government contribution shall be disbursed from the income from the compensated use of state-owned land, such as land transfer fees, or collected from the land user for administratively allocated land, both at the rate of 25 yuan/m2 49 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

the PMO plans to use spoil to build and improve some medium and low yield land, barren land and borrow pits occupied temporarily by the spoil grounds medium and low yield land, barren land and borrow pits, and allocate or lease it to the affected people to reduce their land acquisition losses. See Appendix 4. The 34 temporary spoil grounds of the Project will occupy 9,831.3 mu of rural collective land, in which the ponds, barren land and borrow pits that may be used for land reclamation have a total area of 1,607.1 mu (16.35%); hollow medium and low yield land that may be improved has a total area of 3,080.4 mu (31.33%). Among the 20 villages affected by land acquisition, Sanba and Datao Villages have 1,203.5 mu of medium and low yield land that can be turned into high-yield land. In these two villages, total land acquisition area is 317.6 mu, affecting 68 households with 252 people. See Table 0-4.

Table 0-4 Schedule of medium and low yield land improvement of affected villages

Impacts of land acquisition Population Per capita Improved No. Village Acquired per family arable area (mu) Households Population land area (mu) land area (mu) 1 Sanba 3.63 0.95 304.3 61 223 841.3 2 Datao 3.42 0.52 13.3 7 29 362.2 Total \ \ 317.6 68 252 1,203.5

Demolition of residential houses The Project involves demolition of residential houses only, with a total area of 29,686.2 m2, affecting 364 households with 1,489 people, including houses on collective land of 1,802.2 m2, affecting 18 households with 83 people, and houses on state-owned land of 27,884 m2, affecting 346 households with 1,406 people. Resettlement for demolition of rural residential houses The Project involves demolition of rural residential houses of 1,802.2 m2, affecting 18 households with 83 people and 3 villages (Sanba, Wuzhai and Xijie). In rural areas, demolished houses are poorly equipped, bad in quality or irrational in structure, the supporting facilities around the settlements are poor, and traffic is inconvenient. In the 3 affected villages, 4 households in Wuzhai Village and 2 in Xijie Village are affected. These households will be reallocated a housing site by the village collective for resettlement. The village committee is in charge of the activities of site formation (Electricity, water supply , roads are available, etc) , the cost is included in the plot land acquisition. In addition, the relocated households will receive replacement cost and a moving subsidy. The Task Force has learned from interview that the relocated households are willing to accept this mode of resettlement. In Sanba Village, 12 households with 56 people are affected. This village has been acquired of land for channel, dyke and dam works before project implementation. The demolition range includes old sites of dyke and dam works. These villagers have been compensated and resettled in dyke and dam works, and already have housing elsewhere, so they will not be resettled under the Project. However, to ensure the livelihood of these villagers and help them improve their standard of living, their houses will be compensated for at replacement cost. The Task Force has learned through interview that these villagers are satisfied with the mode of resettlement.

11 EIA has test the sludge of the river bottom, the results showed that the spoil can be reused as farmland.

50 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Resettlement for demolition of urban residential houses The Project involves demolition of urban residential houses of 27,884 m2, affecting 346 households with 1,406 people, involving Jieshou City and Taihe County respectively. The demolition area of Jieshou City is 22,434 m2, affecting 271 households with 1,105 people, and that of Taihe County 5,450 m2, affecting 75 households with 301 people. The mode of compensation for house demolition is cash compensation or property swap. According to the Task Force’s survey, the affected residential houses in Jieshou City and Taihe County are old, small, poorly equipped and have a bad environment, and it is inconvenient for residents to live and trip. For the purpose of compensation and resettlement, displaced persons will select a qualified appraisal agency to appraise their houses based on geographic location, structure, use, floor and orientation on the basis of replacement. Displaced persons may select a secondhand or commercial house of suitable location and area based on their needs to improve living conditions. The compensation rates for urban residential houses of Jieshou City are: reinforced concrete structure 1,430 yuan/m2 and masonry concrete structure 1,250 yuan/m2. Commercial housing prices of this city are 1,200- 1,600 yuan/m2, and secondhand housing prices 1,100-1,500 yuan/m2. The compensation rates for urban residential houses of Taihe County are: reinforced concrete structure 1,480 yuan/m2 and masonry concrete structure 1,300 yuan/m2. Commercial housing prices of this county are 1,350-1,700 yuan/m2 and secondhand housing prices 1,100-1,560 yuan/m2. It can be seen that cash compensation fees and moving subsidy are sufficient for the relocated households to buy firsthand or secondhand housing. In addition, it was learned by the Task Force that the affected areas of Taihe County and Jieshou City are old urban areas, where real estate development is strong, and the supply of new housing is sufficient. According to online information of Fuyang’s real estate transaction websites (http://fy.58.com/ and http://fuyang.baixing.com/), sufficient information on secondhand housing is available in Jieshou City and Taihe County, so that displaced persons can buy suitable commercial or secondhand housing.

Gratuitous allocation of state-owned land The Project involves permanent occupation of 98.83 mu of state-owned land, all being allocated and involving no resettlement.

Restoration program for temporarily occupied land The navigation works, bridge works and supporting works of the Project will occupy 31 mu of state-owned roads and channels temporarily. Such land is within the road and channel planning boundary lines, avoiding construction on densely populated streets and reducing the impact on pedestrian and road traffic. Therefore, no land occupation fees will be incurred. The Project will occupy 9,843.3 mu of collective land, to be occupied for the storage of construction machinery and by the spoil grounds. Collective land will be occupied by the spoil grounds mainly. Spoil produced by the dredging works will be carried to the spoil grounds, occupying 9,831.3 mu of collective land temporarily, including 6,778.8 mu of dry land (68.87%), 26.2 mu of pond (0.27%), 1,457.4 mu of nursery (14.81%) and 1,580.9 mu of barren land (16.06%). Farmland occupation should be avoided where possible. Land occupied temporarily by the spoil grounds is mostly hollow farmland, its level may be increased by spoil produced during dredging to prevent land inundation by floods. It has been confirmed by the EIA agency that fertile river bottomland can improve the fertility of the temporarily occupied land and can be used directly for farming after the temporary occupation period. In the land occupied temporarily by the Project, except the land occupied temporarily by the spoil grounds, the restorer shall be determined by representatives of affected households, the village collective and the implementing agencies together. 51 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

To minimize the impact of temporary land occupation, the key principles of restoration are as follows: ¾ The affected households will have priority. Thus, not only the affected people will receive job opportunities and increase their family income, but also the quality of land restoration will be ensured. If the affected households and the village collective are unwilling to restore the occupied land themselves, the land will be reclaimed by the implementing agencies. ¾ Strict measures will be taken to protect surface soil during construction to avoid irrecoverable impacts. During excavation, surface soil (recommended thickness 30- 50cm) will be gathered and piled separately, and water loss and soil erosion prevention measures taken. After construction, subsurface soil will be backfilled first, then surface soil laid evenly on the surface, and the site leveled to mitigate the impact on farmland quality. Land that hardens temporarily during construction will be plowed immediately after construction to restore its looseness. ¾ For some barren land and old borrow pits, the construction agency may fill fertile channel silt to turn them into arable land and increase land resources. To improve the economic, social and ecological benefits of the Project, and reduce the impact of temporary land occupation on farmers, the PMO has entrusted the Task Force to prepare a plan for land reclamation and medium and low yield land improvement of the spoil grounds, as described in Appendix 6.

Restoration program for affected vulnerable groups In the affected population of the Project, 21 households with 80 people fall into vulnerable groups, in which 16 households with 74 people receive MLS, accounting for 92.5%; and there are 5 five-guarantee households with 6 people, accounting for 7.5%. The vulnerable groups affected by the Project are related to the bridge reconstruction work in Jieshou City and the channel works. ¾ MLS households 1) Two laborers of every affected household will receive livelihood training and priority in employment (working outside, working in project construction, etc.); 2) They will receive a government subsidy. ¾ Five-guarantee households 1) The village collective will subsidize five-guarantee households every month; 2) The village committee may arrange five-guarantee households to enter an old people’s home on voluntary basis. Except the above measures, the PMO will grant a subsidy of 5,000 yuan to every household with difficulty in order to protect the interests of the affected vulnerable groups. Protection of women’s rights Women will participate fully in resettlement activities through information disclosure and meetings of the village collective; they will have the same rights as men in receiving compensation, being employed for the Project and attending training. In addition, the following measures will be taken to ensure women’s rights and interests: (1) During project construction, a certain number of women (at least 20% of unskilled labor) will obtain unskilled job opportunities. In addition, women will receive equal pay for equal work like men; (2) Technical training will be first provided to affected female laborers to ensure that their economic status will not be lowered; 52 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

(3) Affected women will receive relevant information during resettlement and participate in public consultation and resettlement. The compensation agreement must be signed by a coupled. Restoration program for ground attachments After owners of affected ground attachments have been compensated by the implementing agencies, they will be rebuilt by owners. In addition, restoration measures for demolished facilities must be planned and arranged in advance and suited to local conditions, so that such measures are safe, efficient, timely and accurate, and their adverse impact on nearby residents is minimized.

53 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Organization Organization To ensure successful resettlement as desired, implement the approved Resettlement Plan effectively, and carry out supervision and management, a top-down organization must be set up during project implementation. Since resettlement is a very extensive task that necessitates the assistance and collaboration of all departments, the land and resources, forestry and agriculture authorities, etc. will participate and assist in the implementation of resettlement. Each affected township and village has one or two leaders responsible mainly for resettlement. The agencies responsible for the land acquisition and house demolition work of the Project include: ¾ APCD Foreign-funded Project Management Office (Provincial PMO) ¾ APSCIG ¾ Headquarters of Fuyang Municipality and counties (including county-level cities) thereunder12 ¾ Town PMOs ¾ Village (neighborhood) committees ¾ Design agency ¾ External independent M&E agency — PMO

Responsible mainly for organizing the resettlement of the Project, formulating policies on resettlement activities of the Project, coordinating relations among all levels of the resettlement organization, and serving as a bridge between World Bank and the implementing agencies — APSCIG

APSCIG sets up the on-site PMO, consisting of the department of environment and resettlement with 2 or 3 full-time staffs. Meanwhile, a full-time deputy director of the on-site PMO will be appointed to take in charge the land acquisition, house demolition and resettlement activities . Responsible mainly for handling day-to-day affairs in resettlement planning and implementation, and exercising the management, planning, implementation, coordination, supervision and monitoring functions of resettlement as the project management agency: Formulating the land acquisition, house demolition and resettlement policies for the Project; Entrusting the design agency to define the affected areas, measure the data on physical objects affected by land acquisition and house demolition, and save such data; Applying for the license for planning of land use and the license for land used for construction; Giving operational training to the key resettlement officials of the land acquisition, house demolition and PMO; Organizing and coordinating the preparation and implementation of the Resettlement Plan;

12 The construction headquarters of the Project will be established based on the MSA in conjunction with the land and resources bureau, relocation office, water resources bureau, communications bureau and construction bureau to be responsible for resettlement. 54 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Responsible for the management and disbursement of the resettlement funds, and supervising the use thereof; Directing, coordinating and supervising resettlement activities and their progress; Directing and assisting in the disposition of complaints; Taking charge of and inspecting internal monitoring, and preparing land acquisition, house demolition and resettlement progress reports; Selecting the external monitoring agency and assisting in external monitoring activities — Headquarters of Fuyang Municipality and counties (including county-level cities) there under

Fuyang municipality sets up the project headquarters. The vice mayor of Fuyang municipality who is in charge of the communication, will coordinate the land acquisition, housing demolition and resettlement issues in his jurisdiction. The counties of Fuyang involved in the project will set up the county project headquarters six months prior to the project civil works commence. The vice county mayor in charge of the communication will coordinate the land acquisition, house demolition and resettlement issues. The on-site PMO of APSCIG will sign the agreement with the county project headquarters and entrust them to implement the resettlement activities within the county jurisdiction. The details are as follows: Assisting the design agency in defining the affected areas, measuring the data on physical objects affected by land acquisition and house demolition, and saving such data; Assisting in preparing the Resettlement Plan and responsible for the implementation of resettlement; Selecting key resettlement officials for operational training; Organizing public consultation, and propagandizing the resettlement policies; Directing, coordinating and supervising resettlement activities of the agencies related to land acquisition, house demolition and resettlement and their progress; Responsible for resettlement, paying resettlement costs pursuant to the agreement, and handling complaints from displaced persons; Implementing internal monitoring activities, preparing internal monitoring reports, and reporting to AHAB regularly; Assisting in external monitoring activities. — Town PMOs

The town PMOs are headed by the leader responsible of each town, and composed of key officials of the land and resources office, the police office, the civil affairs office and the villages. Their main responsibilities are: Participating in the survey of the Project, and assisting in the preparation of the Resettlement Plan; Organizing public participation, and propagandizing the resettlement policies; Implementing, inspecting, monitoring and recording all resettlement activities within the town; Responsible for the disbursement and management of land compensation fees; Supervising the acquisition, occupation and restoration of land; Reporting land acquisition and resettlement information to the county highway administration bureau; Coordinating and handling conflicts and issues arising from its work. — Village (neighborhood) committees 55 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

The resettlement working team of a village committee is composed of its key officials. Its main responsibilities are: Participating in the social and economic survey and the impact survey of the Project; Organizing public consultation, and propagandizing the policies on land acquisition and house demolition; Organizing the implementation of resettlement activities for agricultural and nonagricultural production; Reporting the displaced persons’ opinions and suggestions to the competent authorities; Providing assistance to displaced households with difficulties. — Design agency

At the planning and design stage, it will survey the physical indicators of land occupation and house demolition, the environmental capacity, the usable resources, etc. accurately, and assist the governments in the affected areas in formulating resettlement programs, preparing budgetary investment estimates for compensation for land occupation and house demolition, and drawing the relevant drawings. At the implementation stage, it will submit the design documents, technical specifications, drawings and notices to the employer timely, make design disclosure to the project management offices of all levels, assist in the implementation of the relocation and resettlement for production of the displaced persons, and improve the resettlement programs based on the practical situation. — External independent M&E agency

APSCIG will employ a qualified M&E agency as the external resettlement M&E agency. Its main responsibilities are: 1) Observing all aspects of resettlement planning and implementation as an independent M&E agency, monitor and evaluate the resettlement results and the social adaptability of the displaced persons, and submit resettlement M&E reports to World Bank through the PMO; and 2) Providing technical advice to the PMO in data collection and processing.

56 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Organizational chart

Project Leading Group

Fuyang Municipal Provincial PMO Internal Design Land & Resources agency Bureau, House itoring Demolition Management Office Extenral monitoring On-site PMO of APSCIG

Resettlement implementing i s I t n R a A a d U f t d c u e e r l r q e a l m r - b L o a m o u s a c l o t a w i n r o s a n l h u i i n t l d o h t t c i i i e i o t u o t o o i d u n s o u n n r e n l s o e a e f n d

Figure 0-1 Resettlement Organization Staffing To ensure the successful implementation of the Resettlement Plan, and strengthen the timely and effective communication with the Provincial PMO, the implementing agencies and the World Bank, the Provincial PMO, APSCIG and relevant agencies have assigned full-time staff to take charge of the coordination and organization of resettlement and implementation. The resettlement agencies are staffed as shown in Table 0-1. Table 0-1 Full-time staffing of resettlement agencies Agency Staff Composition remark Project Leading Group 2 Civil servants On-site PMO of APSCIG 2-3 Senior engineers Headquarters of Fuyang Municipality 2 Civil servants, senior engineers Each Headquarters of counties (cities) 3-5 Civil servants, technicians county Design research institute 2 Senior engineers, engineers External monitoring agency 4 Resettlement and social experts

Measures to develop institutional capacity

¾ Before the implementation of the Resettlement Plan, the land acquisition, house demolition and resettlement staff will be trained on the World Bank operational guidelines on resettlement, regulations on land acquisition and house demolition, resettlement implementation management, etc. in order to improve the professional proficiency and practical abilities. ¾ During the resettlement stage, the backbone resettlement staff will be organized to learn and investigate domestic World Bank financed projects, and attend resettlement policy training and other specialized training 57 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

courses. In addition, to increase the employment rate of the affected people, they will be organized to attend skills training irregularly depending on project progress. ¾ Sufficient funds and equipment will be provided to improve working efficiency. ¾ Reward and punishment measures for the land acquisition, house demolition and resettlement staff will be established and improved to motivate the staff. ¾ A land acquisition, house demolition and resettlement management information system will be established to realize computer-based land acquisition, house demolition and resettlement data management, strengthen information feedback, and ensure a smooth flow of information, while major decisions will be made by the Project Leading Group. ¾ Strengthen the reporting system and internal monitoring, and solve identified problems timely. ¾ Strengthen independent monitoring & evaluation (M&E); the independent M&E agency shall point out existing problems to the competent authorities timely and propose solutions. ¾ Resettlement officials and staff will be organized for training, and the affected people will be given skills training. The resettlement training program is shown in Table 0-2. Table 0-2 General resettlement training program Cost estimate No. Scope of training Subject Time Location (10,000 yuan) Investigation of resettlement Backbone staff of 1 of domestic World Bank One time Domestic 10 PMO financed projects Domestic resettlement Backbone staff of 2 Once a year Domestic 5 operational training PMO Domestic resettlement 3 Resettlement staff Once a year Domestic 5 operational training Skills training of affected 4 Affected people Irregular Fuyang 20 people * The international resettlement training plan and budget will be included in the whole project training.

58 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Resettlement costs and sources of funds Budget All costs incurred during land acquisition and resettlement will be included in the general budget of the Project. The Project’s resettlement costs include compensation fees for permanent and temporary land occupation, demolition of houses and ground attachments, and relevant taxes. The total investment in resettlement is 169.3350 million yuan, accounting for 9% of the total investment in the Project. Of the total resettlement costs, the costs for acquisition of rural collective land are 52.7795 million yuan (31.17%); costs for temporary land occupation 11.4899 million yuan (6.79%); costs for house demolition 38.2504 million yuan (22.59%); compensation costs for demolition of attachments 1.4053 million yuan (0.83%); and all taxes amount to 65.41 million yuan (38.63%). See for the detailed budget.

59 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Table 0-1 for the detailed budget.

60 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Table 0-1 Compensation budget for resettlement

Costs (10,000 yuan) No. Channel works Bridge works Supporting works Item Proportion Taihe Yingshang Yingzhou Yingdong Yingquan Taihe Yingshang Taihe Yingquan Yingzhou Total Jieshou Jieshou Jieshou (%) County County District District District County County County District District Acquisition of 36.92 158.83 1016.46 186.48 126.79 399.88 0.00 0.00 455.85 1435.44 471.05 243.50 746.75 5277.95 31.17% 1 rural collective land 1.1 Dry land 0.00 0.00 0.00 67.79 0.00 0.00 0.00 0.00 0.00 425.46 0.00 98.25 183.40 774.90 4.58% Land compensation fees 0.00 0.00 0.00 22.77 0.00 0.00 0.00 0.00 0.00 11.16 0.00 33.00 61.60 128.53 0.76% Resettlement subsidy 0.00 0.00 0.00 43.47 0.00 0.00 0.00 0.00 0.00 279.00 0.00 63.00 117.60 503.07 2.97% Young crop compensation fees 0.00 0.00 0.00 1.55 0.00 0.00 0.00 0.00 0.00 135.30 0.00 2.25 4.20 143.30 0.85% 1.2 Flood land 26.72 114.95 730.98 118.69 91.77 256.63 0.00 0.00 329.92 730.98 340.14 105.13 406.17 3252.08 19.20% Land compensation fees 8.98 38.61 245.52 39.86 30.82 86.20 0.00 0.00 110.81 245.52 114.25 35.31 136.42 1092.30 6.45% Resettlement subsidy 17.14 73.71 468.72 76.10 58.84 164.56 0.00 0.00 211.55 468.72 218.11 67.41 260.44 2085.30 12.31% Young crop compensation fees 0.61 2.63 16.74 2.72 2.10 5.88 0.00 0.00 7.56 16.74 7.79 2.41 9.30 74.48 0.44% 1.3 Unused land 10.20 43.88 279.00 0.00 35.03 143.25 0.00 0.00 125.93 279.00 129.83 40.13 155.03 1241.25 7.33% Land compensation fees 4.90 21.06 133.92 0.00 16.81 68.76 0.00 0.00 60.44 133.92 62.32 19.26 74.41 595.80 3.52% Resettlement subsidy 4.90 21.06 133.92 0.00 16.81 68.76 0.00 0.00 60.44 133.92 62.32 19.26 74.41 595.80 3.52% Young crop compensation fees 0.41 1.76 11.16 0.00 1.40 5.73 0.00 0.00 5.04 11.16 5.19 1.61 6.20 49.65 0.29% 1.4 Housing site 0.00 0.00 6.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.08 0.00 2.16 9.72 0.06% Land compensation fees 0.00 0.00 3.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.54 0.00 1.08 4.86 0.03% Resettlement subsidy 0.00 0.00 3.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.54 0.00 1.08 4.86 0.03% 2 Temporary land occupation 88.26 62.76 459.08 254.48 108.43 175.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1148.99 6.79% 3 House demolition 0.00 0.00 43.05 0.00 0.00 0.00 3016.59 741.54 0.00 0.00 6.74 0.00 17.11 3825.04 22.59% Demolition of rural 0.00 0.00 43.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.74 0.00 17.11 66.91 0.40% 3.1 residential houses Benchmark rate 0.00 0.00 34.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.00 0.00 14.63 52.83 0.31% of storied buildings

61 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Costs (10,000 yuan) No. Channel works Bridge works Supporting works Item Proportion Taihe Yingshang Yingzhou Yingdong Yingquan Taihe Yingshang Taihe Yingquan Yingzhou Total Jieshou Jieshou Jieshou (%) County County District District District County County County District District Benchmark rate of single-storied building with 0.00 0.00 8.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.66 0.00 2.32 13.36 0.08% brick wall and tile roof Moving costs 0.00 0.00 0.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.04 0.00 0.08 0.36 0.00% Temporary resettlement subsidy 0.00 0.00 0.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.04 0.00 0.09 0.36 0.00% Demolition of urban 0.00 0.00 0.00 0.00 0.00 0.00 3016.59 741.54 0.00 0.00 0.00 0.00 0.00 3758.13 22.19% 3.2 residential houses Benchmark rate of 0.00 0.00 0.00 0.00 0.00 0.00 919.69 100.83 0.00 0.00 0.00 0.00 0.00 1020.52 6.03% reinforced concrete Grade 1 Benchmark rate of 0.00 0.00 0.00 0.00 0.00 0.00 2000.33 619.94 0.00 0.00 0.00 0.00 0.00 2620.26 15.47% masonry concrete Grade 1 Moving subsidy 0.00 0.00 0.00 0.00 0.00 0.00 8.97 2.18 0.00 0.00 0.00 0.00 0.00 11.15 0.07% Temporary resettlement subsidy 0.00 0.00 0.00 0.00 0.00 0.00 87.60 18.60 0.00 0.00 0.00 0.00 0.00 106.20 0.63% 4 Ground attachments 5.46 0.00 67.76 12.79 35.68 18.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 140.53 0.83% Tomb 3.26 0.00 30.46 0.00 8.62 6.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 48.65 0.29% Scattered tree (<10cm) 1.04 0.00 3.58 0.00 0.00 5.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.26 0.06% Scattered tree (10cm-20cm) 0.00 0.00 30.94 0.00 0.00 6.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 37.24 0.22% Scattered tree (>20cm) 1.15 0.00 2.54 12.40 27.06 0.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 43.68 0.26% Telegraph pole 0.00 0.00 0.24 0.39 0.00 0.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.69 0.00% Subtotal of Items 1-4 130.64 221.59 1586.35 453.75 270.91 594.69 3016.59 741.54 455.85 1435.44 477.78 243.50 763.87 10392.51 61.37% 5 Survey and design fees 3.92 6.65 47.59 13.61 8.13 17.84 90.50 22.25 13.68 43.06 14.33 7.31 22.92 311.78 1.84% External M&E fees 0.65 1.11 7.93 2.27 1.35 2.97 15.08 3.71 2.28 7.18 2.39 1.22 3.82 51.96 0.31% Administrative fees 6.53 11.08 79.32 22.69 13.55 29.73 150.83 37.08 22.79 71.77 23.89 12.18 38.19 519.63 3.07% 6 Water resources fund 0.40 1.76 10.59 2.30 3.82 5.28 0.00 0.00 5.15 11.34 5.68 10.99 6.84 64.15 0.38% 7 Training fees 1.31 2.22 15.86 4.54 2.71 5.95 30.17 7.42 4.56 14.35 4.78 2.44 7.64 103.93 0.61% 8 Contingency costs 13.65 23.16 165.77 47.42 28.31 62.15 315.23 77.49 47.64 150.00 49.93 25.45 79.82 1086.02 6.41%

62 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Costs (10,000 yuan) No. Channel works Bridge works Supporting works Item Proportion Taihe Yingshang Yingzhou Yingdong Yingquan Taihe Yingshang Taihe Yingquan Yingzhou Total Jieshou Jieshou Jieshou (%) County County District District District County County County District District 9 Land reclamation fees 4.29 18.73 113.01 24.51 40.78 56.36 0.00 0.00 54.91 121.06 60.56 117.33 72.99 684.53 4.04% 10 Farmland occupation tax 10.06 43.90 264.86 57.45 95.57 188.24 0.00 0.00 128.69 283.74 141.95 275.00 171.06 1660.52 9.81% Land acquisition 1.42 6.71 29.63 7.74 11.36 17.78 0.00 0.00 12.65 39.51 19.05 30.35 21.77 197.97 1.17% 10 management fees Endowment insurance premiums 13.41 58.53 171.39 60.43 46.72 176.12 0.00 0.00 171.59 378.32 189.26 366.67 228.08 1860.52 10.99% 11 of land-expropriated farmers 12 Subtotal of Items 5-11 55.64 173.84 905.96 242.95 252.30 562.42 601.81 147.94 463.93 1120.34 511.82 848.92 653.13 6541.00 38.63% 13 Total 186.29 395.43 2492.31 696.71 523.20 1157.12 3618.40 889.48 919.78 2555.78 989.60 1092.42 1417.00 16933.50 100.00%

63 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Year-by-year investment plan A year-by-year investment plan has been prepared according to the progress of land acquisition and house demolition, as shown in Table 0-2. Table 0-2 Fund use plan by year Unit: 10,000 yuan Year 2011 2012 2013 2014 2015 Total Jieshou 472.45 944.89 1889.79 944.89 472.45 4724.46 City Taihe 227.45 454.90 909.80 454.90 227.45 2274.51 County Yingshang 504.81 1009.62 2019.23 1009.62 504.81 5048.09 County Yingzhou 211.37 422.74 845.48 422.74 211.37 2113.70 District Yingdong 52.32 104.64 209.28 104.64 52.32 523.20 District Yingquan 224.95 449.91 899.82 449.91 224.95 2249.54 District Total 1693.35 3386.70 6773.40 3386.70 1693.35 16933.50 Proportion 10.00% 20.00% 40.00% 20.00% 10.00% 100.00%

Sources of resettlement funds According to the project contents, the resettlement funds come from as below: For Bridge works and its linkage road: the resettlement funds will be shared by the local government and APSCIG. Other projects (excluding bridge works): The resettlement funds will be financed by APSCIG. Management and disbursement plan of resettlement funds Fund flow To ensure that resettlement and compensation funds are paid timely and fully to the affected people according to the compensation policy and rates specified in the Resettlement Plan, the disbursement procedure of the Project is as follows: APSCIG disburses resettlement fees to the resettlement implementing agencies— Headquarters of counties , which disburse relevant taxes and duties to the relocation offices and counties land and resources bureau directly, and deposit compensation fees for house demolition, land compensation fees, resettlement subsidy and young crop compensation fees into a bank or credit cooperative according to the land acquisition agreement; the bank or credit cooperative will pay such fees directly to the affected villages or individuals; compensation fees for residential house demolition will be paid to the affected people; compensation fees for infrastructure and attachments will be paid to relevant agencies or individuals. In particular, land compensation fees and resettlement subsidy will be used in full consultation with villagers. Fund use programs so determined will be submitted to APSCIG for approval and to the Provincial PMO for reference. The fund flow is shown in Figure 0-1 .

64 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Local counterpart funds

APSCIG

Headquarters of Fuyang Municipality and counties (cities) thereunder

Land and Bank or Township/ sub- resources bureau credit district office and house cooperative R V A e i A t l l t l o a a f c c g f a e h e t c m e c t d e o e d m n h t p o m o e u o w i s t e p t n e h l e e e o r / l s d

Figure 0-1 Fund flowchart Disbursement and management To ensure that the resettlement funds are in place timely and fully, and to ensure the restoration of the production, livelihoods and income level of the affected rural households, the following measures will be taken: ¾ All costs related to resettlement will be included in the general budget of the Project; ¾ The land compensation and the resettlement subsidy will be paid up before land acquisition so that all affected people can be resettled properly; ¾ To ensure the successful implementation of land acquisition and resettlement, and to ensure that all funds are disbursed on schedule, all levels financial and supervisory organization will be established; and ¾ The budget is an estimate of the resettlement costs. Due to practical variations in the affected areas, practical impacts of DMS (Detailed Measurement Survey), modifications to compensation, inflation and other factors, the actual costs may be increased, but APSCIG will ensure the disbursement of compensation fees. The budget has taken contingencies into account, and will be used and modified as necessary.

65 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Public Participation, Consultation and Appeal Channel Public participation strategy According to the policies and regulations of the state, Anhui Province, Fuyang Municipality and the affected districts and counties on land acquisition, house demolition and resettlement, the participation of and consultation with the displaced persons will be attached great importance to at the resettlement policy-making, planning and implementation stages in order to maintain the lawful rights and interests of the displaced persons and affected entities, reduce grievances and disputes, and realize the resettlement objective properly by developing sound policies and implementation rules on relocation and resettlement, preparing an effective resettlement plan, and organizing implementation properly. During the feasibility study stage, the Provincial PMO and APSCIG have consulted residents affected by land acquisition and house demolition, traffic authorities, other government agencies and nongovernmental organizations (NGOs) about advice and opinions on resettlement in Fuyang Municipality many times. Disclosure of the Resettlement Plan: The Resettlement Plan was disclosed at the Provincial PMO, APSCIG and the Fuyang Municipal MSA on August, 10th,2010; an announcement will be published on major local newspapers for disclosure to displaced persons and NGOs. Key information in the Resettlement Plan will be compiled into a resettlement brochure, which will be distributed to displaced persons after assessment and before relocation. Such brochure will cover project overview, project impacts, compensation policies, implementing agencies and appeal channel, etc.

Public participation process and policy disclosure plan

To handle issues and requirements proposed by affected households about house demolition and resettlement timely and properly, the affected people should be further consulted so that all issues can be solved before the Resettlement Plan is implemented. The resettlement implementing agencies will arrange public participation meetings rationally, so that every affected household has an opportunity to consult with the resettlement implementing agencies about the compensation agreement before signing it. The public participation process and plan are shown in Table 0-1; the policy disclosure process is shown in Table 0-2. Table 0-1 Early-stage records and subsequent plan for public participation process of affected people

Time Location Participants Topics Conclusion/plan Need for the Project, Sub-district Design agency, EIA consultation of schemes, Oct. 2009- offices within agency, APSCIG, environmental impact Jan. 2010 the affected Fuyang Municipal survey and public areas MSA, etc. participation Compensation and resettlement policies: as per state and local Socioeconomic survey, Design agency, affected policies; Resettlement affected area and physical Sub-district residents, heads of programs: Affected quantity survey, Dec. 2009- offices within implementing agencies, people expect to be consultation of Mar. 2010 the affected etc.; land and resources compensated at the latest resettlement policies, areas bureau and other provincial standard; investigation of government agencies Affected people resettlement programs support the Project on the basis of reasonable compensation. 66 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Time Location Participants Topics Conclusion/plan APSCIG, Fuyang Municipal MSA, Optimization of relocation offices, land compensation and May 2010 APSCIG and resources bureau resettlement policies and and other government resettlement programs agencies Supplementary Range of land Fuyang Municipal Individual issues of consultation on acquisition and MSA, land and Jul. 2010 resettlement policies and individual issues upon house resources bureau, plan finalization of the demolition affected people Resettlement Plan

Table 0-2 Policy disclosure process

Language and method Document Date of publication Place of publication of disclosure Introduction of related Chinese, municipal Community or village End of May 2010 projects government website committee General introduction to Chinese, municipal Community or village land acquisition and house End of May 2010 government website committee demolition information Municipal land acquisition Chinese, municipal Community or village and house demolition End of June 2010 government website committee policies Notice to disclose the Community or village Chinese, newspapers In early August 2010 Resettlement Plan committee After passing World Chinese, handed to Bank examination, before Community or village Resettlement Brochure displaced persons the project committee implementation After passing World Resettlement Report Chinese and English Library Bank examination

Appeal channel Since the resettlement work is conducted with the participation of the affected people, no substantial dispute will arise. However, to ensure that the affected people have a channel to file an appeal on any issue concerning land acquisition and resettlement, a 5-stage grievance redress mechanism has been established in the Resettlement Plan: ¾ Stage 1: If any displaced person is dissatisfied with the Resettlement Plan, he/she can report this to the village committee or sub-district resettlement office orally or in writing. In case of an oral appeal, the village committee or sub-district resettlement office shall handle such appeal and keep written records. Such appeal should be solved within 2 weeks; ¾ Stage 2: If the displaced person is dissatisfied with the disposition of Stage 1, he/she may file an appeal to the headquarters of Fuyang Municipality or any county (including county-level city) thereunder. After receiving such disposition, they shall make a disposition within 7 days. Contact information such as person name, telephone number of Headquarters of Fuyang Municipality and Counties see Appendix 13; ¾ Stage 3: If the displaced person is still dissatisfied with the disposition of Stage 2, he/she may file an appeal to the on-site PMO of APSCIG. After receiving such disposition, he shall make a disposition within 2 weeks; ¾ Stage 4: If the displaced person is still dissatisfied with the disposition of Stage 3, he/she may escalate the appeal to the competent administrative organs in accordance

67 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

with the Administrative Procedure Law of the PRC after receiving such disposition for arbitration. ¾ Stage 5: If the displaced person is still dissatisfied with the arbitration award, he/she may file a suit in a civil court in accordance with the Civil Procedure Law of the PRC after receiving the arbitration award.

Village Township/sub-district

headquarters of Fuyang Municipality and ties (including county l l ities)

On-site PMO Anhui Provincial Port & Shipping

Administrative ruling / local

Figure 0-1 Grievance redress Displaced persons may file an appeal about any aspect of resettlement, including compensation rates, etc. The above appeal channel will be notified to displaced persons at a meeting or otherwise, so that displaced persons are fully aware of their right of appeal. Mass media will be utilized for publicity, and opinions and advice about resettlement will be compiled into messages for study and disposition by the implementing agencies. All agencies will accept grievances and appeals from the affected people for free, and costs so reasonably incurred will be disbursed from contingency costs.

68 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Implementation schedule

Principles for linkup between resettlement and project construction

According to the project schedule, the Project will be completed from February 2011 to June 2016 in stages. The land acquisition, house demolition and resettlement schedule links up the construction schedules of the components. The main tasks of land acquisition, house demolition and resettlement will begin in October 2010 and end in June 2015. The basic principles of scheduling are as follows: ¾ Land acquisition and house demolition shall be completed one month before the beginning of land use; the beginning time shall be determined based on the need for land acquisition, house demolition and resettlement. ¾ Sufficient time must be allowed for land acquisition, house demolition and resettlement before commencement of construction.

Schedule of resettlement milestones

Principles for preparing the working schedule ¾ The range of land acquisition and house demolition shall be determined based on the design drawings of the individual works, which shall be completed before the physical quantity survey of land acquisition and house demolition. ¾ Physical quantities affected by land acquisition shall be surveyed by the Provincial PMO, APSCIG, MSAs (headquarters) of Fuyang Municipality and counties (including county-level cities) thereunder, other competent authorities and owners according to the boundary map of land acquisition and house demolition before the execution of the compensation and resettlement agreement. ¾ APSCIG and the MSAs (headquarters) of Fuyang Municipality and counties (including county-level cities) thereunder shall hold a mobilization meeting with relocated households and entities to disclose policies and resettlement measures on land acquisition, house demolition, compensation and resettlement before the execution of the compensation and resettlement agreement. The land acquisition and house demolition announcement will be published formally after the mobilization meeting. ¾ The demolisher and the affected people shall enter into the compensation and resettlement agreement after the physical quantity survey and the publication of the land acquisition and house demolition announcement. ¾ Infrastructure will be constructed in advance and then demolished. ¾ Resettlement costs shall be settled after the execution of the agreement and before relocation. ¾ The resettlement work shall be inspected so that it is satisfactory to the relocated households and entities. General resettlement schedule The general resettlement schedule of the Project has been drafted according to the progress of preparation and implementation activities of land acquisition, house demolition and resettlement. The specific period of implementation may be adjusted due to any deviation from the general schedule. See Table 0-1. 69 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Table 0-1 Resettlement schedule

Yingshang Stage Task Fuyang Municipality Jieshou City Taihe County

P County r e

p Determination of range of a

r land acquisition and house Sep.-Dec. 2009 Aug.-Dec. 2009 Aug.-Dec. 2009 Aug.-Dec. 2009 a t i

o demolition n

p Physical quantity survey of

e Dec. 2009-Mar. Dec. 2009-Mar. Dec. 2009-Mar.

r land acquisition and house Dec. 2009-Mar. 2010 i

o 2010 2010 2010

d demolition Preliminary socioeconomic Feb. 2010-Mar. Feb. 2010-Mar. Feb. 2010-Mar. Feb. 2010-Mar. 2010 survey 2010 2010 2010 Consultation of Mar.-Apr. 2010 Mar.-Apr. 2010 Mar.-Apr. 2010 Mar.-Apr. 2010 resettlement programs Preparation of the Mar.-Apr. 2010 Mar.-Apr. 2010 Mar.-Apr. 2010 Mar.-Apr. 2010 Resettlement Plan Disclosure of the Aug. 2010 Aug. 2010 Aug. 2010 Aug. 2010 Resettlement Plan Approval of the Sep. 2010 Sep. 2010 Sep. 2010 Sep. 2010

I Resettlement Plan m

p Approval of acquisition of Feb. 2011- Feb. 2011- Feb. 2011- l

e Feb. 2011-Feb.2013

m rural collective land Feb.2013 Feb.2013 Feb.2013 e

n Holding a land acquisition t a

t and house demolition Nov. 2011- Nov. 2011- Nov. 2011- i

o Nov. 2011-Jul.2013

n mobilization meeting to Jul.2013 Jul.2013 Jul.2013 p

e disclose policies r i

o Issuing the land acquisition d Dec. 2011- Dec. 2011- Dec. 2011- and house demolition Dec. 2011-Oct.2014 Oct.2014 Oct.2014 Oct.2014 announcement Negotiating and signing Feb. 2012- Feb. 2012- Feb. 2012- compensation and Feb. 2012-Dec.2014 Dec.2014 Dec.2014 Dec.2014 resettlement agreement House demolition and Mar. 2012- Mar. 2012- Mar. 2012- Mar. 2012-Feb.2015 relocation of facilities Feb.2015 Feb.2015 Feb.2015 Handover of land for Jun. 2012- Jun. 2012- Jun. 2012- Jun. 2012-Apr.2015 construction Apr.2015 Apr.2015 Apr.2015 Construction of Aug. 2012-Apr. Aug. 2012-Apr. Aug. 2012-Apr. Aug. 2012-Apr. 2015 resettlement houses 2015 2015 2015 Displaced persons moving Sep. 2012-Nov. Sep. 2012-Nov. Sep. 2012-Nov. Sep. 2012-Nov. 2015 into new houses 2015 2015 2015 Income restoration of Feb. 2011-Dec. Feb. 2011-Dec. Feb. 2011-Dec. Feb. 2011-Dec. 2015

M persons moving 2015 2015 2015 &

E May. 2011-Dec. May. 2011-Dec. May. 2011-Dec. May. 2011-Dec. M&E 2015 2015 2015 2015

70 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Monitoring and Evaluation Arrangements To ensure the successful implementation of the Resettlement Plan and resettle the displaced persons properly, periodic M&E of land acquisition, house demolition and resettlement activities will be conducted in accordance with the World Bank Operational Policy OP4.12 Involuntary Resettlement and the Operational Guide to the Monitoring and Evaluation of Resettlement of World Bank Financed Projects in China. Monitoring is divided into internal monitoring of resettlement agencies and external independent monitoring. Internal monitoring Internal monitoring shall be implemented by APSCIG with the assistance of the headquarters of Fuyang Municipality and counties (including county-level cities) thereunder, affected townships/sub-districts and village committees, etc. APSCIG will establish a database of land acquisition, house demolition and resettlement, and use it to prepare the Resettlement Plan, monitor all relocated households and entities, and conduct internal supervision and inspection of the whole process of resettlement. Implementation procedures During implementation, APSCIG will establish a corresponding resettlement database, collect and record information on the resettlement of displaced persons from the monitoring sample, and report update activity records and implementation progress to the superior levels of the resettlement organization timely to maintain continuous monitoring. Scope of monitoring ¾ Land approval ¾ Compensation fees and disbursement ¾ House rebuilding ¾ Construction and allocation of resettlement houses for property swap ¾ Production and livelihood restoration measures of displaced persons ¾ Restoration of special facilities ¾ Schedule of the above activities ¾ Staffing, training, working schedule and efficiency of the resettlement organization ¾ Registration and handling of grievances and appeals of displaced persons ¾ Implementation of land reclamation and medium and low yield land improvement plan for spoil grounds Internal monitoring reporting APSCIG will prepare a report on the progress of land acquisition, house demolition and resettlement of the Project every 6 months, and submit it to the Provincial PMO, which will in turn submit it to the World Bank. External independent monitoring Independent monitoring agency Before the beginning of land acquisition and house demolition, the Provincial PMO or APSCIG will entrust an independent and fair third party agency with over 5 years of experience in the M&E of World Bank financed projects to monitor and evaluate land acquisition, house demolition and resettlement activities of the Project. Monitoring procedure and scope 1. Preparing an M&E outline 2. Developing software for the resettlement M&E information system

71 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

3. Preparing a survey outline, survey form and record card of affected residents and typical affected entities 4. Design of sampling survey plan and sample size 5. Baseline survey A baseline survey required for the independent M&E of the households affected by land acquisition will be conducted to acquire baseline data on the standard of living (livelihood, production and income levels) of the monitored relocated households. 6. Establishing an M&E information system An M&E information system will be established, where a database will be established for different types of M&E data, in order to provide computer aid for analysis and follow-up monitoring. 7. M&E survey (1) Capacity evaluation of resettlement implementing agencies: to survey the working capacity and efficiency of the resettlement implementing agencies (2) Monitoring of resettlement progress, compensation rates and payment to typical relocated households: to monitor the disbursement of compensation fees, income restoration and resettlement quality of residents; and restoration measures for vulnerable groups (3) Public participation and consultation: to monitor public participation activities during the preparation and implementation of the Resettlement Plan, and the effectiveness of participation (4) Appeals: to monitor the registration and disposition of appeals of displaced persons 8. Compiling monitoring data, and establishing a database 9. Comparative analysis 10. Preparing M&E reports according to the monitoring plan

¾ May 2011, setting up the independent resettlement M&E team and preparing terms of reference ¾ July 2011, preparing for independent resettlement M&E, including preparing survey outline and questionnaire, establishing monitoring system, defining tasks and selecting monitoring sites; ¾ July 2011, submitting M&E Report No.1 (baseline survey report); ¾ January 2012, 2nd round of monitoring, submitting M&E Report No.2; ¾ July 2012, 3rd round of monitoring, submitting M&E Report No.3; ¾ January 2013, 4th round of monitoring, submitting M&E Report No.4; ¾ July 2013, 5th round of monitoring, submitting M&E Report No.5; ¾ January 2014, 6th round of monitoring, submitting M&E Report No.6; ¾ July 2014, 7th round of monitoring, submitting M&E Report No.7; ¾ Jannuary 2015, 8 th round of monitoring, submitting M&E Report No.8; ¾ December 2015, submitting post-evaluation report

Monitoring indicators

¾ Socioeconomic indicators: per capita income, GDP and employment rate; ¾ Institutional indicators: staffing, staff competencies, rules and regulations, equipment, completion rate of transactions; ¾ Displaced persons: availability of compensation fees, mode of production resettlement, rate of change of income, employment rate, satisfaction with resettlement;

72 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

¾ Residential houses: availability of compensation fees, location of new site, land acquisition progress of new site, satisfaction with resettlement; ¾ Infrastructure: availability of compensation fees and functional recovery ratio ¾ Temporary land occupation: availability of restoration fees, progress of land restoration

Post-evaluation After project implementation, the resettlement activities will be subject to post- evaluation using the theory and methodology for post-evaluation on the basis of M&E. Successful experience and lessons of land-expropriated farmers will be evaluated to provide experience that can be drawn on for future resettlement. Post-evaluation will be conducted by an external independent monitoring and evaluation agency appointed by the Provincial PMO or APSCIG. The post-evaluation agency will prepare terms of reference for post-evaluation to establish a system of evaluation indicators, conduct socioeconomic analysis and survey, and prepare the “Resettlement Post-evaluation Report” for submission to the Provincial PMO and the World Bank.

73 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Entitlement Matrix

Type of impact Degree of impact Affected people Compensation and resettlement policy Compensation rates (1) In case of land acquisition, the acquired land shall be compensated for based on its original use. Compensation fees for land acquisition include compensation fees for land, ground attachments young crops, and resettlement subsidy. (2) The use of land compensation fees and resettlement subsidy shall Acquiring 1,652.6 be decided by the village congress; the land compensation fees may Permanent mu of collective 442 households be paid to the affected village or households; the resettlement acquisition of Farmland: 32,200-37,920 yuan/mu land permanently, with 1,734 people subsidy must be used specifically for labor resettlement for the collective land affecting 20 villages acquired land and shall not be diverted to any other purpose; the compensation fees for ground attachments and young crops shall be paid to their respective owners. After an affected household receives compensation, if it meets the criteria for the endowment insurance of land-expropriated farmers, it may participate in the endowment insurance of land-expropriated farmers. Permanent Occupying 98.83 occupation of mu of state-owned None Gratuitous allocation state-owned land permanently land Affecting 2,891 Temporary occupation of rural collective land shall be compensated Temporary households with for based on the purpose and loss of occupation. Compensation fees occupation of 9,843.3 mu Young crop compensation rate: 1,500 yuan/mu 10,316 people for temporary land occupation include young crop/ground attachment collective land temporarily compensation fees, and land reclamation fees. House compensation (1) Receiving house compensation at replacement cost, and Storied building: 410 yuan/m2 compensation for relocation of attachments based on actual costs; Single-storied building with brick wall and tile Demolition of (2) Selecting local restoration, non-local resettlement or single roof: 260 yuan/m2 Demolition area 18 households rural residential compensation as one wishes after receiving the cash compensation 1,802.2 m2 with 83 people houses for the house Other compensation (3) Receiving a moving subsidy and a lease subsidy for the transition Moving subsidy: 200 yuan/household period of house construction Lease subsidy for the transition period of house construction: 2 yuan/month·m2 Demolition of (1) Receiving house compensation at replacement cost, and House compensation (Tier-1 areas) Demolition area 346 households urban compensation for relocation of attachments based on actual costs; Jieshou City: reinforced concrete Grade 1: 1,430 27,884 m2 with 1,406 people residential (2) Selecting cash compensation or property swap as one wishes after yuan/m2, masonry concrete Grade 1: 1,250 74 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Type of impact Degree of impact Affected people Compensation and resettlement policy Compensation rates houses receiving the cash compensation for the house yuan/m2 (3) Receiving a moving subsidy and a transition subsidy Taihe County: reinforced concrete Grade 1: 1480 yuan/m2, masonry concrete Grade 1: 1300 yuan/m2

Other compensation Moving subsidy: 4 yuan/m2, based on building area Temporary resettlement subsidy: 5‰ of the benchmark rate (unit price) of demolished houses per month-m2 Ground / Owner To be compensated by the PMO to the owner attachments Compensation rates, Affected people payment of dissatisfied with compensation fees, land acquisition, All costs and management fees involved in such appeal should be Appeals and house house demolition exempted. demolition and or resettlement resettlement and filing an measures appeal

75 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Appendix 1 Schematic map of the Project

76 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Appendix 2 Resettlement of the related project Fuyang Ship Lock Reconstruction

The old Fuyang ship lock is already expired, impeding the navigation of the Shaying River seriously. The Project aims to improve the navigational quality of the channel and improve the shipping capacity of the Shaying River. The Fuyang ship lock reconstruction project has been identified by the Task Force as a related project of the Project. The Fuyang ship lock reconstruction project occupies 74 ha of land in total, including 33.96 ha of land permanently and 40.04 ha of land temporarily. Such land includes the former site of the Fuyang ship lock and allocated state-owned land, in which the area of the allocated state-owned land is 20.065 ha, being state-owned land along the Shaying River channel and on the dyke, so no new land will be acquired for this project.

Attached Figure 1 Permit to use state-owned land of the Fuyang ship lock reconstruction project

The Ying River Fuyang ship lock administrative office obtained the right to use land for construction from the Xiangyang Sub-district Office, Yingdong District on October 30, 2008, namely the Permit to Use State-owned Land of the People’s Republic of China (FDGY [2009] No.A120228). See Attached Figure 1.

Attached Figure 2 Opinion on site selection for the Fuyang ship lock reconstruction project

The Anhui Provincial Department of Construction identified the site for the Fuyang ship lock reconstruction project on the Shaying River on May 13, 2009 in the Opinion on Site Selection for Construction Project of the People’s Republic of China (XZH No.340000200900023). See Attached 77 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Figure 2. The Fuyang ship lock reconstruction project is an important water traffic project between Henan and Anhui Provinces on the Shaying River, located on the west side of the Fuyang regulating lock on the Ying River in Yingdong District, Fuyang. This project includes demolition of the old ship lock, construction of new lock chamber, lock head, access channels and cross-lock access bridge, etc. This project consists of a main construction area (ship lock, upstream and downstream access channels, cross-lock access bridge and connecting highway), spoil grounds, construction roads and construction sites, etc. The volume of earth and rock excavation of this project is 1.9106 million m3, that of earth and rock filling 583,300 m3, and that of discarded earth and rock 1.3327 million m3. The total investment in this project is 182 million yuan, in which the investment in civil works is about 131 million yuan. This project involves no resettlement. This project broke ground in September 2009 and is to be completed in August 2011.

78 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Appendix 3 Ethnic minorities involved in the affected areas

1. Introduction to ethnic minorities in the affected areas

The Project involves 68 villages in 31 townships of one city (Jieshou City), three districts (Yingzhou, Yingquan and Yingdong) and two counties (Yingshang and Taihe). There are 40,252 households with 170,833 people in the affected areas, including a minority population of 9,212 people, accounting for 5.39% of total population.

The Task Force from Hohai University investigated the distribution of ethnic minorities in the affected areas village by village with the assistance of the PMO. There are Hui people in 15 out of the 68 affected villages, in which 3 are villages inhabited centrally by Hui people, namely Saijian, Zhoutai and Baliduo Villages, Saijian Xiang, Yingshang County. See Attached Table 1.

Attached Table 1 Identification of ethnic minorities affected by the Project

City/ Is it a Township/ Admin. village/ Househol Populat Arable Minority No. county/ minority Remarks sub-district community ds ion area (mu) population district village?

Dongcheng 1 Renwan 46 163 86 No \ \ Sub-district 2 Jieshou Tianying Weiyao 1029 4060 3195 No \ \ 3 City Town Houwei 224 760 675 No \ \ Xuzhai 4 Xiaowan 150 640 500 No \ \ Town Xingzhai 5 Houzhuang 90 460 460 No \ \ Town Jiuxi 6 Xijie 278 1056 260 No \ \ Community 7 Dongzou Garden 102 355 106.5 No \ \ Taihe Chengguan 8 County Town Xizou Garden 110 400 120 No \ \ Zhaoji 9 Xiazhangwan 153 1000 600 No \ \ Xiang 10 Zhuzhuang 1581 6130 6362 No \ \ Daxin Town 11 Daliu 880 3150 2400 No \ \ 12 Yingsh Wushipu Liuxiao 7818 30010 15000 No 300 Hui (scattered) ang 13 Ningda 1089 4900 6370 No 150 Hui (scattered) County Liushipu 14 Zhouzhuang 980 4300 4000 No \ \ 15 Sugou 830 4200 4000 No \ \ 16 Wangzhuang 270 1983 2100 No 8 Hui (scattered) Xinji Town 17 Huangying 480 2000 1800 No \ \ 18 Fanzhuang 617 3560 4272 No \ \ Jianying 19 Xiwan 1047 4400 4000 No \ \ Xiang Gucheng 20 Chentaizi 970 4800 6336 No \ \ Xiang 21 Huangqiao Xiaoji 450 2230 1500 No 50 Hui (scattered)

79 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

City/ Is it a Township/ Admin. village/ Househol Populat Arable Minority No. county/ minority Remarks sub-district community ds ion area (mu) population district village?

22 Town Lianggang 1480 6100 7869 No 460 Hui (scattered) 23 Bianmei 880 5300 3200 No 80 Hui (scattered) Shibalipu 24 Songgou 480 2200 1800 No \ \ 25 Sanba 145 527 527 No \ \ Balihe Town 26 Yantai 130 530 280 No 60 Hui (scattered) Xinliuji 27 Jiangliu 810 3410 2956 No \ \ Town 28 Jiangtai 754 3133 3940 No 210 Hui (scattered) 29 Zhanglou 1017 4092 4795 No 96 Hui (scattered) 30 Saijian Saijian 965 4206 4807 Yes 2300 Hui 31 Town Litai 1194 4374 4800 No 70 Hui (scattered) 32 Zhoutai 1220 4541 5128 Yes 2800 Hui 33 Baliduo 879 3690 4296 Yes 2600 Hui 34 Shibei Area 31 200 130 No \ \ Shencheng 35 Chentun 265 1320 89 No \ \ Town 36 Fantaizi 50 400 280 No \ \ 37 Xinji Town Xiawan 152 700 627 No \ \ Huangqiao 38 Sanwan 400 1720 747 No 4 Hui (scattered) Town Ying River 39 Sanba 145 527 527 No \ \ Xiang 40 Jinyuzi 340 1200 250 No \ \ 41 Yanghu Zhaolou 791 3320 3500 No \ \ 42 Town Wangzuizi 170 1020 714 No \ \ 43 Qilinsi 150 880 616 No \ \ 44 Huayuan 367 1500 1511 No \ \ 45 Yingzh Gaowan 540 2200 1230 No \ \ ou Sanshilipu 46 District Wuzhai 218 1400 301 No \ \ 47 Gaolou 121 670 603 No \ \ 48 Zhaozhuang 1035 4500 3500 No \ \ Yuanzhai 49 Yuanzhai 1200 6000 4000 No \ \ Yingdo Town 50 ng Wnaghai 130 800 210 No 24 Hui (scattered) 51 District Caogou 102 700 140 No \ \ Kouzi Town 52 Zhangdianweizi 80 300 270 No \ \ 53 Yingqu Datao 117 400 80 No \ \ an 54 Datao 117 400 80 No \ \ District Wenji Town 55 Dongxiaotao 80 340 95.2 No \ \ 56 Chendian 240 1060 700 No \ \ Xingliu 57 Chenying 200 1000 200 No \ \ Town Taoyuan 58 371 1500 1500 No \ \ Xiangyang Community Sub-district 59 Zhangzhuang 100 301 130 No \ \

80 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

City/ Is it a Township/ Admin. village/ Househol Populat Arable Minority No. county/ minority Remarks sub-district community ds ion area (mu) population district village?

60 Wangzhuang 1700 5568 4100 No \ \ Zhoupeng 61 Dukou 265 1320 89 No \ \ Sub-district 62 Xinjing 60 270 189 No \ \ 63 Sanliqiao 20 106 300 No \ \ 64 Fanying 340 1700 1700 No \ \ 65 Ninglaozhua Chenying 117 411 327 No \ \ 66 ng Town Baimiao 600 2100 1400 No \ \ 67 Fanying 340 1700 1700 No \ \ 68 Xiaoying 150 640 500 No \ \

2. Comparison of features of affected ethnic minorities with World Bank definition The Task Force investigated the 3 villages. Except dietary habits, the villagers of these villages lead the same life as the local Han people. Their children of school age receive the state’s uniform 9- year compulsory education, and their sources of income are the same as the local Han people, mainly being urban employment. In terms of crop cultivation, the local Hui people grow wheat and corn mainly, similar to the Han people. By comparing the features of the affected Hui people with the criteria in World Bank OP4.10, we find that these Hui villages do not meet all the 4 conditions for ethnic minority in World Bank OP4.10. Therefore, these 3 villages are not identified as minority villages for the purpose of World Bank OP4.10. See Attached Table 2.

Attached Table 2 Checklist of World Bank OP4.10 guidelines and features of affected ethnic minorities

Provisions of World Bank OP4.10 Features of affected Hui people self-identification as members of a distinct The Hui people are self-identified as members of an ethnic indigenous cultural group and recognition of cultural group, which is recognized and respected by others. this identity by others; Compliant

collective attachment to geographically The Hui people are attached collectively to natural resources distinct habitats or ancestral territories in the in the affected areas, but their per capita arable area and per project area and to the natural resources in capita income are largely equal to those of nearby Han people. these habitats and territories; Compliant customary cultural, economic, social, or The Hui culture is a combination of the Islamic and political institutions that are separate from Confucian cultures; in the meantime, their economic, social and those of the dominant society and culture; political institutions are not separate from those of the dominant society. Not compliant an indigenous language, often different The Hui people have no language of their own, and generally from the official language of the country or use Chinese; they use some Persian and Arabic words in region. religious and internal life only. Not compliant

81 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Appendix 4 Land reclamation and medium and low yield land improvement project for sludge disposal sites

Land occupied temporarily by the Project is occupied mainly by the spoil grounds, with a total occupied area of 9,831.3 mu, including 1,457.4 mu of nursery (14.82%), 6,766.8 mu of dry land (68.83%) (including 3,080.4 mu of bottomland), and 1,607.1 mu of ponds, barren land and borrow pits (16.35%). In consideration of the relatively small per capita arable area of the affected areas, and the economic, environmental and social benefits of the Project, the PMO plans to use fertile spoil from the bottom of the Shaying River to fill ponds, barren land and borrow pits temporarily occupied by the Project to reclaim land. In addition, bottomland out of the dyke will be raised with spoil to improve farming quality and prevent flooding. The experiments and tests of EIA agency (Shanghai Ship and Shipping Research Institute) reveal that bottom mud of the Shaying River contains nitrogen, phosphorus and other nutritive elements and minerals, as well as organics and a variety of microelements that are not rare in ordinary mineral fertilizers. As the base fertilizer and complementary fertilizer for farmland, bottom mud not only provides all nutrients required for the growth of crops and increases the output of crops, but also improves the fertility of soil fertilizers and soil moisture content. Therefore, it is feasible to use spoil from the Shaying River for land reclamation and medium and low yield land improvement. In 2007, the Anhui Provincial Government approved the Flood Drainage Plan of the Huai River Watershed of Anhui Province, which was to be implemented in stages. The priority in the near future is to improve bottomland along the Huai River with an area of 9,000 km2, including 8 million mu of farmland, involving a population of over 7 million. Spoil utilization under the Project can play a good exemplary role for the implementation of this plan.

1. Principles of land reclamation and medium and low yield land improvement 1.1 Principle of suiting local conditions This principle requires that claimed land should be used for forestry or farming as the case may be so that land utilization is optimized. In addition, the disposal of spoil should be noted during land reclamation and improvement based on the actual conditions of the spoil grounds to prevent under- disposal or over-disposal, otherwise land would not be optimum for utilization. 1.2 Principle of “whoever improves land will benefit” This principle aims to give full play to the role of the affected people/villagers as the subject; county, town and village officials should hold meetings, prepare publicity materials and posters, and utilize local news media to give extensive publicity, so that the affected people realize the benefits of land improvement, and participate in land improvement actively. Under equal conditions, newly claimed and improved land should be allocated or leased to the affected people. 1.3 Principle of conservation and intensivism This principle requires that land should be utilized to the greatest possible extent during land reclamation and medium and low yield land improvement to prevent waste, turn spoil “from waste to treasury”, maximize the amount of farmland and increase the output of medium and low yield land. 1.4 Principle of overall benefits This principle requires that economic, social and ecological benefits should be paid equal attention to during land reclamation and medium and low yield land improvement: Economically, the

82 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

cost of land reclamation and improvement should be considered, and rational engineering measures taken for land reclamation and improvement; socially, success experience in land reclamation and improvement should be publicized to provide a reference for other domestic water resources projects; ecologically, the environment should be protected during land reclamation and improvement.

2. Present land situation of sludge disposal sites The 34 temporary spoil grounds of the Project will occupy 9,831.3 mu of rural collective land, in which the ponds, barren land and borrow pits that may be used for land reclamation have a total area of 1,607.1 mu (16.35%); hollow medium and low yield land that may be improved has a total area of 3,080.4 mu (31.33%); the area of temporarily occupied arable dry land is 5,143.8 mu (52.32%). According to the survey, ponds, barren land and borrow pits in the affected villages are not used for farming or stockbreeding, and are seriously abandoned. The wheat yield per mu of medium and low yield land is about 600 jin per harvest. There are usually two harvests in the affected areas. 2.1 Present situation of ponds, barren land and borrow pits The barren land, ponds and borrow pits occupied temporarily by the spoil grounds, located at the 4#, 9#, 10#, 11# and 17# spoil grounds in Taihe County, Yingquan District and Yingshang County respectively, with a total area of 1,607.1 mu. See Attached Table 3. The Task Force has learned from the survey that such ponds, barren land and borrow pits are not used for farming and stockbreeding, and have been left unused for a long time. This is a great waste for the relatively small per capita arable area in the affected areas.

Attached Table 3 Schedule of barren land, ponds and borrow pits No. of Temporarily Piling Type of land disposal Location Soil source occupied height Real photo occupation sites land (mu) (mm)

Daliu Village, K36+000-K40+000 Pond, Barren 4 Daxin Town, and Taihe city gate 106.2 2.5 land Taihe County anchorage

Baimiao Village, Ninglaozhuang 9 K67+000-K72+000 243.7 2.5 Borrow pit Town, Yingquan District, Fuyang

Wanzhuang Village, 10 K72+000-K76+000 476.7 2.5 Borrow pit Yingquan District, Fuyang

83 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Dukou Village, K76+000-K80+000 11 Yingquan and Fuyang lock 296.5 2.5 Borrow pit District, Fuyang anchorage

Ningda Village, Liushipu, 17 K105+000-K108+000 483.9 2.5 Barren land Yingshang County

2.2 Present situation of medium and low yield land

The medium and low yield land occupied temporarily by the spoil grounds, located at the 2#, 3#, 5#, 7#, 15#, 29#, 30# and 34# spoil grounds in Jieshou City, Yingdong District, Yingzhou District, Yingquan District and Yingshang County, with a total area of 3,680.4 mu. See Attached Table 4. The Task Force has learned from the survey that the land occupied by these spoil grounds is depressed dry land. In bottomland areas, due to unsmooth drainage, groundwater level is relatively high all the year round. Therefore, once there is relatively more rainfall, flooding is very likely to occur even if water logging has been drained. In usual years, crops in bottomland areas have a significantly lower yield than high yield land due to potential flooding. It was learned from the interview of farmers in Yingshang County and Jieshou City that most of them expect to raise the level of land with spoil produced by the Project, thereby improving land quality.

Attached Table 4 Schedule of existing bottomland

Tempor Type of No. of arily Piling land disposal Location Soil source occupie height Real photo occupati sites d land (mm) on (mu)

K0+000-K10+000 and Weiyao Village, Tianying Dry land 2 upper Genglou lock 219.9 2.5 Town, Jieshou (hollow) anchorage

K28+000-K33+000 and Zhuzhuang Village, Daxin Dry land 3 lower Genglou lock 418.4 2.5 Town, Taihe County (hollow) anchorage

84 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Datao Village, Yingdong Dry land 5 K40+000-K48+000 362.2 2.5 District, Fuyang (hollow)

Fanying Village, K62+000-K67+000 and Dry land 7 Ninglaozhuang Town, Ciweixin River service 784.5 2.5 (hollow) Yingquan District zone

Gaowan Village, Yingzhou Dry land 15 K95+000-K102+000 607.6 2.5 District, Fuyang (hollow)

K157+000-K162+000 Songgou Village, Shibalipu, Dry land 29 and upper Yingshang 254.0 2.5 Yingshang County (hollow) lock anchorage

K162+000-K168+000, lower Yingshang lock Balihe Town, Yingshang Dry land 30 anchorage and 841.3 2.5 CountySanba Village (hollow) Longwangmiao anchorage

Baliduo Village, Saijian Hui Dry land 34 K196+000-K205+000 192.3 2.5 Town, Yingshang County (hollow)

1. Implementation plan of land reclamation and medium and low yield land improvement Three aspects should be planned properly before land reclamation and low yield land improvement: First, canal roads, structures and field roads: Since bottom mud of the Shaying River has relatively high moisture content, preparation should be made for the construction of drainage canals before disposal of spoil. In addition, in order to develop large-scale operation, extensive land improvement should be planned before disposal of spoil, and field roads should be designed rationally for easy access of machinery. Second, soil delivery plan: Before disposal of spoil, the number of slurry pumps for riverbed construction and relay pumps on the bank should be determined, and the earth capacity, dredging range and earth discharge range of each pump defined pursuant to the requirement that channel dredging should be combined closely with bottomland improvement. Third, power supply and consumption plan: Transformers and power lines should be arranged rationally based on the practical conditions of the power sources and facilities along the channel, so that the slurry and relay pumps are supplied with power properly and safely. 85 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

3.1 Land reclamation Water in ponds should be drained completely by the construction agency using pumping equipment before land reclamation to prevent excessively high moisture content of soil after spoil filling, otherwise the fertility of land might be affected. After drainage, the construction agency will dispose spoil to the ponds, flatten out the ponds mechanically timely thereafter, and excavate open drain ditches. The flattened land will be handed over to the appropriate village committee or individuals directly for reclamation. For water containing barren land and borrow pits, the construction agency will excavate open drain ditches before land reclamation to divert excess water. Then, the construction agency will dispose spoil to barren land and borrow pits, and flatten them out mechanically timely. The flattened land will be handed over to the appropriate village committee or individuals directly for reclamation. Since bottom mud of the Shaying River has relatively high moisture content, after spoil disposal and land leveling by the construction agency, the village committee or villagers of the affected village will excavate blind ditches themselves after land reclamation to reduce the moisture content of soil. In addition, farmers should select suitable crops as the case may be to prevent yield reduction due to excessively high moisture content. The construction agency should consider the future need for mechanized farming during land leveling and reserve rational field roads during spoil disposal and land leveling. Field roads should be arranged in “ ”, “ ” or “” forms, so that land is connected into pieces where possible and machinery has easy access. After the completion of the Project, the whole area should be fully covered by mechanized farming roads to ensure mechanized operation and the transport of agricultural means of production. 3.2 Medium and low yield land improvement Surface damming and silt burial and covering measures should be taken as the case may be in medium and low yield land improvement. Surface damming: Bottomland is a natural cofferdam. Mellow soil of the top layer of 20-30cm must be taken to build a 0.5m high and 0.8m wide cofferdam with a gradient of 1:1-1:1.5 to meet the required excess draft and safe freeboard, prevent slurry from overflowing into surrounding fertile land, and ensure that improved fields are largely level with the surrounding ground after silt deposition. For uneven or inclined bottomland, the cofferdam height should vary with ground level, so that the cofferdam top is largely on the same horizontal line with a height difference of less than 5cm. Filling should begin with the very bottom by filling, leveling, impurity removal and tamping layer by layer. At existing water outlets, loopholes and extremely low points, particular attention should be paid to tamping quality to eliminate any potential hazard. Silt burial and covering: During channel construction, a slurry pump will be used to feed riverbed earth into bottomland. Note that the silt deposit in the field should be largely level with the land out of the cofferdam. After the water logging in the cofferdam has been drained and a certain solidification period has elapsed, cofferdam soil will be laid on silt and leveled to reach the preliminary target of bottomland improvement. Some bottomland is like a narrow belt vertical to the river, where drainage is possible at the far end only. In order to improve soil structure and reduce the workload of leveling, the soil outlet should be moved from the near end to the far end as the case may be. An afflux groove should be preferably formed, and the slurry flow in the groove stirred often. After surface damming and silt burial and covering, the construction agency will hand over the land to the affected village collective or individual land contractors for reclamation.

86 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

2. Overall benefit analysis In the Project, spoil will be used to improve some land of the spoil grounds. 1,607.1 mu of land will be reclaimed and 3,080.4 mu of medium and low yield land improved in total. The total area of reclaimed and improved land accounts for 46.67% of the area of temporarily occupied land. The reclaimed and improved land can be used to grow wheat and corn, etc. Land reclamation and improvement will generate favorable economic, social and ecological benefits. Economic benefits: Medium and low yield land improvement can reduce the impact of land acquisition on some villages in the channel works and supporting works. Sanba and Datao Villages involved in this program are acquired of 317.6 mu land in the Project in total, affecting 68 households with 252 people; on the other hand, improved land area attains 1,203.5 mu and beneficiary population is 448 households with 1,583 people, producing significant economic benefits. According to the survey, the cost of reclamation of 1 mu of land is about 1,000 yuan. Since soil has relatively high moisture content after land reclamation and improvement, the land will be left unused for one year to remove excess moisture, during which the land will be non-arable. If it is assumed that medium and low yield land has two harvests a year and an average wheat output of 600 jin per mu, and the price is 0.8 yuan per jin in Fuyang, farmers’ loss in the first year of reclamation will be 1,960 yuan/mu for medium and low yield land or 1,000 yuan/mu for ponds, barren land and borrow pits. See Attached Table 5. Based on conservative estimates, for land reclamation, if it assumed that medium and low yield land has an average wheat output of 600 jin per mu and the price is 0.8 yuan per jin in Fuyang, the net return on the reclaimed land will be 960 yuan per mu one year after reclamation, and the reclaimed land will produce economic income of 1.5428 million yuan annually. For bottomland improvement, if high-yield land has an average wheat output of 1,000 jin per mu and the price is 0.8 yuan per jin, the improved land will produce a net added value of 640 yuan per mu-year or 1.972 million yuan in total. Since the compensation rate for temporary land occupation of the Project is 1,500 yuan/mu, which is sufficient for land reclamation, and the return on reclaimed and improved land will be long lasting, the Project will generate significant economic benefits.

Attached Table 5 Cost and return of land reclamation and improvement Annual return Investment (yuan/mu) (yuan/year) Item Cost of Cost of Net added output suspension secondary Total cost value of farming plowing Medium and low yield land 960 1,000 1,960 640 improvement Reclaimed land 0 1,000 1,000 960

Social benefits: After medium and low yield land improvement, the agricultural income of beneficiary farmers will increase significantly, promoting the improvement of their standard of living. In addition, since there is over 8 million mu of barren land and depressed medium and low yield land in the Huai River watershed, the Project will provide valuable experience for the improvement of such land and play an excellent exemplary role, generating significant social benefits.

87 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Ecological benefits: According to the survey of the EIA agency, after land reclamation and improvement, a 4-meter-high corridor-type green belt will be created through landscaping along the river banks to resist wind and conserve water and soil. Well filled bottom mud will not flow back into the river and will beautify the environment and regulate the microclimate, generating significant ecological benefits.

3. Implementation management Supervision and management: The county PMOs shall be responsible for the supervision and management of the Project, including fund use and disbursement management, construction progress supervision, construction quality supervision, staffing management and organizational coordination management, etc. The village committee of each affected village should urge farmers to use land timely after land improvement to avoid land waste. Implementing agency: The construction agency shall be responsible for spoil disposal and land leveling, and the village committee of the affected village or individual land contractors shall be responsible for subsequent land arrangement. Source of funds: The Employer will pay spoil disposal costs of 386.4787 million yuan to the construction agency from the project budget. After leveling by the construction agency, land arrangement costs will be disbursed by the village committee or land contractors from compensation fees for temporary land occupation. Land allocation: The village committee of the affected village or land contractors will allocate or lease leveled land to the affected people first.

88 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Appendix 5 Plan for implementing the endowment insurance for land- expropriated farmers in the affected areas

The Project acquires 1,658 mu of collective land permanently, involving 10 villages of Fuyang Municipality, affecting 442 households with 1,734 people, including dry land (278.1 mu), flood land (824.7 mu) and unused land (549.8 mu), totaling 1,652.6 mu. In terms of per capita arable area, the per capita arable area of one village (Xizou Garden) will be less than 0.3 mu after land acquisition; in terms of land loss rate, 7 villages have a land loss rate of less than 10%, 6 villages 10%-20%, 4 villages 20%-50% and 3 villages above 50%. Since land- expropriated farmers may be generated in villages with a higher land loss rate, this plan has been prepared to ensure the interests and income restoration of land-expropriated farmers. 1. Policy basis Land-expropriated farmers generated by the Project shall be secured in accordance with the Measures of Fuyang Municipality for the Basic Endowment Insurance of Land-expropriated Farmers (FMG Ban [2009] No.45), and all counties and districts of Fuyang Municipality shall comply with these Measures. The relevant provisions are as follows: Article 3 People of the agricultural status in household registration who have lost all contracted land or have a per capita arable area of less than 0.3 mu after land acquisition pursuant to law, having attained 16 years of age upon land acquisition and having not effected the basic endowment insurance of urban workers may cover the basic endowment insurance of land-expropriated farmers voluntarily. Article 4 The basic endowment insurance of land-expropriated farmers shall be subject to the principles of insurance upon acquisition, insurance before acquisition and no approval of land acquisition without securing social security costs. Article 5 The labor and social authorities of all localities shall be responsible for the management of the basic endowment insurance of land-expropriated farmers. The rural social endowment insurance agencies of the labor and social authorities of all localities (hereinafter referred to the handling agencies) shall be responsible for day-to-day work of the basic endowment insurance of land-expropriated farmers, and their labor costs and funds shall be included in the fiscal budget and disbursed from the finance of the same level. Article 6 Endowment insurance funds for farmers land-expropriated farmers consist of unified funds and personal account funds, and shall be used specifically for the basic endowment insurance of land-expropriated farmers. Article 7 Unified funds for the basic endowment insurance of land-expropriated farmers shall consist of government contribution. The government contribution shall be disbursed from the income from the compensated use of state-owned land, such as land transfer fees, or collected from the land user for administratively allocated land, both at the rate of 25 yuan/m2. The government contribution shall be included in land acquisition costs, and collected by the district and county land and resources authorities together with the financial authorities according to the above rate, and transferred to the municipal special financial account of endowment insurance funds of land-expropriated farmers. Article 8 Personal account funds for the endowment insurance of land-expropriated farmers shall individual payment, collective payment and interests thereon.

89 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

2. Implementation management The labor and social authorities of all localities shall be responsible for the management of the basic endowment insurance of land-expropriated farmers. The rural social endowment insurance agencies of the labor and social authorities of all localities shall be responsible for day-to-day work of the basic endowment insurance of land-expropriated farmers, and their labor costs and funds shall be included in the fiscal budget and disbursed from the finance of the same level. The labor and social authorities of Yingdong District, Fuyang Municipality, Yingquan District, Yingzhou District, Jieshou City, Taihe County and Yingshang County involved in the Project shall be responsible for the day-to-day management of the endowment insurance of land-expropriated farmers, set up a special account for land-expropriated farmers generated by the Project, and ensure that insurance funds are sufficient and disbursed timely. 3. Subject of insurance According to the Measures of Fuyang Municipality for the Basic Endowment Insurance of Land- expropriated Farmers, within the urban planning area of Fuyang, land-expropriated farmers who lose all land or have a per capita arable area of less than 0.3 mu, have attained 16 years of age upon land acquisition and have not participated in the basic urban endowment insurance may join the endowment insurance of land-expropriated farmers shall be covered by endowment insurance of land- expropriated farmers. 4. Insurance standard Security funds of land-expropriated farmers consist of funds of a unified account 13 and an individual account. Under different programs, land-expropriated farmers are entitled to different policies. Personal account funds for the endowment insurance of land-expropriated farmers include premiums paid voluntarily by land-expropriated farmers and interests thereon. There are 3 payment levels of endowment insurance premiums: Level 1 3,600 yuan, Level 2 7,200 yuan and Level 3 10,800 yuan. Land-expropriated farmers participating in endowment insurance will receive endowment insurance benefits monthly from the following month when attaining the age of 60 years for men or 55 years for women. Endowment insurance benefits received by land-expropriated farmers consist of a basic benefit and a supplementary benefit. The basic benefit will be paid from the unified account, while the supplementary benefit from the personal account. After the personal account is used out, the supplementary benefit will be paid from the unified account. Personal account funds of the basic endowment insurance of land-expropriated farmers include individual payment, collective payment and interests thereon. The village collective will pay 4,000 yuan for each insured from land compensation fees and the collective economic organization’s operating income, etc., or this sum will be paid by the village collective or each individual directly to the municipal special financial account of endowment insurance funds of land-expropriated farmers. Depending on the type of insurance, land-expropriated farmers participating in endowment insurance may be entitled to different benefits, as shown in Attached Table 6. Attached Table 6 Payment and benefit rates of endowment insurance for land-expropriated farmers

13 The government contribution shall be disbursed from the income from the compensated use of state-owned land, such as land transfer fees, or collected from the land user for administratively allocated land, both at the rate of 25 yuan/m2 90 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Payment composition Benefit (yuan/month) No. Type and standard (yuan) Individual Collective Basic Supplementary Total Non-payment by both individual 1 0 0 80 0 80 and village collective Non-payment by individual, 2 0 4,000 80 50 130 payment by village collective 3,600 0 80 40 120 Payment by individual, 3 7,200 0 80 80 160 non-payment by village collective 10,800 0 80 120 200 3,600 4,000 80 90 170 Payment by both individual 4 7,200 4,000 80 130 210 and village collective 10,800 4,000 80 180 260

5. Implementation plan The districts and counties of Fuyang Municipality shall implement the endowment insurance of land-expropriated farmers for eligible land-expropriated farmers generated by the Project as follows together with the townships/sub-districts and villages/communities: Fund raising: The Employer must pay social security premiums of land-expropriated farmers within 3 months after the date of approval of the land compensation and resettlement plan, and the land and resources authorities shall examine such funds according to the basis of payment. Endowment insurance premiums paid by individuals shall be collected by the district and county handling agencies, and transferred to the special financial account of social security funds of land- expropriated farmers monthly. Identification of subjects: After land acquisition, land-expropriated farmers shall apply for social security in the unit of family. Such application shall be discussed by the villager team and disclosed. After disclosure, a list shall be prepared and submitted to the township government, township land and resources authority and township police station for preliminary examination, and then submitted to the district land and resources authority, public security organ and handling agency for reexamination. The above authorities shall examine the list according to FMG Ban [2009] No.45. After examination, the list shall be submitted to the district government for determination, and the determined list will be returned to the villager team for 3 days of disclosure. Each villager team shall submit its list to the township labor and social security station for review, which shall submit the list to the district labor and social authority for registration. Insurance formalities: After a handling agency receives funds disbursed by the financial authority, the district or county labor and social authority shall issue the Certificate of Registration of Social Security of Land-expropriated Farmers, the Certificate of Registration of Subsidization for the Basic Endowment Insurance of Land-expropriated Farmers and other documentary evidence according to the list of land-expropriated farmers approved by the district or county government. Land-expropriated farmers shall go through the relevant formalities with the handling agency of the district or county labor and social security authority carrying the above certificates and a valid identification certificate. In case of 10 or more farmers, the villager team shall gather their certificates and go through the formalities in a unified manner. The villager team shall submit a list of receivers of endowment insurance benefits to the township social security station for review at a fixed time of each month. After review, the township social security station shall submit the list to the district handling agency by the 10th of each month to report additional or missing receivers of that month and ensure that benefits are paid timely.

91 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Fund disbursement: Insured farmers attaining 60 years of age for men or 55 years of age for women shall complete the Approval Form of Application for Receiving Basic Endowment Insurance Benefit at the district handling agency carrying the ID card, household register and Handbook of Basic Endowment Insurance of Land-expropriated Farmers of Fuyang Municipality. The district handling agency shall submit such approval forms to the municipal handling agency, and go through the endowment insurance benefit receiving formalities with the approval of the municipal labor and social authority. When the insured attains the age of 60 years for men and 55 years for women, he/she can receive the basic endowment insurance benefit on a monthly basis from the following month. Employment training: Labor of working age participating in the endowment insurance of land- expropriated farmers shall be included in the scope of urban employment management services. All district and county labor and social authorities shall organize pre-job vocational skills training for land-expropriated farmers in a planned manner to improve their vocational and job skills, and provide referral, vocational guidance and other employment services.

92 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Appendix 6 Schedule of temporarily occupied collective land for spoil grounds

Temporary Affected population No. of Quantity of land spoil City/ county/ district Source of mud Land type mud m3 occupation Households Population ground (mu) 1 Renwan Village, Dongcheng Sub-district, Jieshou Xuzhai anchorage 672336 368.4 Nursery 104 323 K0+000-K10+000 and 2 Weiyao Village, Tianying Town, Jieshou upper Genglou lock 424832 219.9 Dry land 91 298 anchorage K28+000-K33+000 3 Zhuzhuang Village, Daxin Town, Taihe County and lower Genglou 755657 418.4 Dry land 102 341 lock anchorage K36+000-K40+000 Barren 4 Daliu Village, Daxin Town, Taihe County and Taihe city gate 235260 106.2 0 0 land anchorage 5 Datao Village, Yingdong District, Fuyang K40+000-K48+000 662010 362.2 Dry land 98 356 6 Sanliqiao Village, Ninglaozhuang Town, Yingquan District, Fuyang K48+000-K62+000 352990 176.8 Dry land 65 231 K62+000-K67+000 7 Fanying Village, Ninglaozhuang Town, Yingquan District and Guozhuang service 1365865 784.5 Dry land 277 713 zone Ciweixin River 8 Chenying Village, Ninglaozhuang Town, Yingquan District, Fuyang 411235 211.8 Dry land 84 299 connection 9 Baimiao Village, Ninglaozhuang Town, Yingquan District, Fuyang K67+000-K72+000 464491 243.7 Pond 16 79 10 Wanzhuang Village, Yingquan District, Fuyang K72+000-K76+000 852843 476.7 Pond 18 82 K76+000-K80+000 11 Dukou Village, Yingquan District, Fuyang and 552414 296.5 Dry land 49 172 connection K83+000-K86+000 12 Huayuan Village, Yingzhou District, Fuyang and Sanshilipu service 1873302 1089.0 Dry land 189 545 zone 13 Zhaozhuang Village, Yingdong District, Fuyang K86+000-K92+000 626149 340.7 Dry land 210 625 14 Yuanzhai Village, Yingdong District, Fuyang K92+000-K95+000 371260 187.8 Dry land 41 178 15 Gaowan Village, Yingzhou District, Fuyang K95+000-K102+000 1070901 607.6 Dry land 166 628

93 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

16 Liuxiao Village, Wushipu, Yingshang County K102+000-K105+000 395000 202.0 Dry land 55 256 17 Ningda Village, Liushipu, Yingshang County K105+000-K108+000 864755 483.9 Dry land 142 506 18 Zhouzhuang Village, Liushipu, Yingshang County K108+000-K112+000 428986 222.4 Dry land 59 202 19 Wnaghai Village, Yingdong District, Fuyang K112+000-K115+000 382189 194.4 Dry land 134 402 20 Sugou Village, Xinji Town, Yingshang County K115+000-K118+000 309588 150.8 Dry land 41 159 21 Wangzhuang Village, Xinji Town, Yingshang County K118+000-K121+000 227842 101.8 Dry land 34 137 22 Huangying Village, Xinji Town, Yingshang County K121+000-K124+000 199069 84.5 Dry land 34 142 23 Fanzhuang Village, Xinji Town, Yingshang County K124+000-K130+000 331539 164.0 Dry land 62 275 24 Xiwan Village, Jianying Xiang, Yingshang County K130+000-K135+000 263726 123.3 Dry land 49 213 25 Chentaizi Village, Gucheng Xiang, Yingshang County K135+000-K140+000 192524 80.6 Woodland 31 131 26 Xiaoji Village, Huangqiao Town, Yingshang County K140+000-K143+000 187973 77.8 Dry land 32 121 27 Lianggang Village, Huangqiao Town, Yingshang County K143+000-K147+000 708041 389.9 Dry land 146 632 28 Bianmei Village, Shibalipu, Yingshang County K147+000-K157+000 196733 83.1 Dry land 34 121 K157+000-K162+000 29 Songgou Village, Shibalipu, Yingshang County and upper Yingshang 481627 254.0 Dry land 92 289 lock anchorage K162+000-K168+000 30 Sanba Village, Balihe Town, Yingshang County and Longwangmiao 1460553 841.3 Dry land 252 1023 anchorage 31 Yantai Village, Balihe Town, Yingshang County K168+000-K174+000 170704 67.5 Dry land 29 148 32 Jiangliu Village, Xinliuji Town, Yingshang County K174+000-K185+000 302030 146.3 Dry land 61 301 33 Zhaolou Village, Yanghu Town, Yingshang County K185+000-K196+000 193147 80.9 Dry land 31 126 34 Baliduo Village, Saijian Hui Town, Yingshang County K196+000-K205+000 378780 192.3 Dry land 59 248 Total 18366351 9,831.3 2,887 10,302

Appendix 7 List of affected attachments

Trees City/ county/ district Township/ sub-district Village Tombs Telegraph poles <10cm >10 cm >20 cm Dongcheng Sub-district Renwan 2600 105 Jieshou City Tianying Town Weiyao 576 31 Zhuzhuang 600 45 Taihe County Daxin Town Daliu 5800 10

94 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Trees City/ county/ district Township/ sub-district Village Tombs Telegraph poles <10cm >10 cm >20 cm Datao 1260 74 Yingdong District Zhaozhuang 11520 138 Yingdong District Yuanzhai 500 80 Yingdong District Wnaghai 250 67 Wushipu Liuxiao 2741 35 Liushipu Ningda 3150 95 30 Liushipu Zhouzhuang 2700 45 15 Sugou 460 35 Wangzhuang 938 40 Xinji Town Huangying 950 47 Fanzhuang 450 525 45 6 Jianying Xiang Xiwan 550 75 Gucheng Xiang Chentaizi 2500 65 Yingshang County Jianying Xiang Wanghaizi 1500 45 Huangqiao Town Lianggang 6750 90 26 Shibalipu Bianmei 150 35 Xiayuan 1250 96 Balihe Town Sanba 4362 336 Yantai 1250 35 Xinliuji Town Jiangliu 1746 75 Yanghu Town Zhaolou 1356 45 4 Saijian Town Baliduo 1864 30 Huayuan 2000 50 Yingzhou District Yingzhou District Gaowan 4200 81 Sanliqiao 2250 78 Fanying 3000 115 Ninglaozhuang Town Yingquan District Fanying 14107 Baimiao 1500 35 20 Yingquan District Wangzhuang 650 35 Total 17,757 14,207 54,041 2,213 101

95 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Appendix 8 Resettlement monitoring and evaluation outline

A Purpose of resettlement M&E According to the World Bank policy on resettlement, the resettlement work of the Project will be subject to external M&E by examining the progress, funding and management of land acquisition, house demolition and resettlement, and analyzing and comparing the production level and standard of living of displaced persons. While submitting reports to the World Bank, Provincial PMO and competent authorities regularly (twice a year during the resettlement period), the external monitoring agency will provide information and advice as a reference for decision-making. External M&E will enable the World Bank and competent authorities to well understand whether land acquisition and resettlement work is conducted on schedule and as expected, point out issues and provide advice for improvement. B Scope of resettlement M&E (1) M&E of land acquisition progress ‹ Including: land acquisition progress; restoration of infrastructure; restoration of temporarily occupied land (2) M&E of fund availability and use ‹ Including: fund availability; fund use (planned vs. actual) (3) M&E of standard of living of displaced persons ‹ Including: production level and standard of living before relocation; production level and standard of living after relocation; comparative analysis and evaluation of production levels and standards of living before and after relocation (4) Capacity evaluation of the implementing agencies, public participation and grievance redress C Technical route The technical route of external M&E is shown in Attached Figure 3.

96 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Project setup

Preparing M&E terms of f

Preparing survey outline, questionnaire and typical household record card

Design of sampling plan

Baseline survey

Establishing M&E management i f tion system

Monitoring & survey

Regional Monitoring Monitoring Spoil ground socioecono by of affected restoration mic survey implementi villages monitoring

Compiling monitoring data and blishing a database

Comparative analysis

Preparing M&E report

No Is resettlement monitoring l d? End

Attached Figure 3 Technical route of external monitoring D External monitoring agency The external resettlement M&E work of the Project will be undertaken by an external monitoring agency appointed by the Provincial PMO or APSCIG and accepted by the World Bank. E Organization and division of labor of resettlement M&E ‹ The Provincial PMO or APSCIG will appoint an external agency to conduct M&E survey, data collection, computational analysis and result examination. 97 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

‹ The external monitoring agency will organize a “resettlement M&E team”, whose takes include conducting resettlement M&E, preparing M&E terms of reference, setting up monitoring sites, conducting field survey and in-house analysis, and preparing resettlement M&E reports according to the World Bank policy on involuntary resettlement. ‹ The Provincial PMO or APSCIG will assist the resettlement M&E team in the field survey in terms of staff and traffic. F Mode of resettlement M&E ‹ M&E will be conducted through a combination of field survey, computational analysis and overall expert evaluation. ‹ The progress, funding, organization and management of resettlement will be surveyed comprehensively. ‹ The relocated households will be subject to a sampling survey using the classified random sampling method. Typical sample relocated households will be followed up. The sampling rate is 10% of households affected by land acquisition and 20% of households affected by house demolition. ‹ The comprehensive survey will be conducted by means of questionnaire survey, focus group discussion and literature review, etc. ‹ In addition to written materials, photos, audio and video records, and real objects will also be collected. G External resettlement M&E reporting The external monitoring agency will submit a resettlement monitoring to the Provincial PMO, APSCIG and the World Bank semiannually (as required by the World Bank).

98 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Appendix 9 Resettlement Information Booklet

Resettlement Information Booklet of the World Bank Financed Anhui Shaying River Channel Improvement Project

Unit: Anhui Provincial Port & Shipping Construction Investment Group

March 2010

99 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

A. Brief description of the Project The Anhui Shaying River Channel Improvement Project (hereinafter referred to as the “Project”) aims to restore the navigation of the Shaying River fully through channel dredging, obstructive bridge reconstruction, bank seepage control, the setup of revetments and anchorage service zones, and the deployment of navigation aids and signs. The Project consists of three components: channel and dredging works, bridge reconstruction and supporting works. In the channel and dredging works, the mileage of the regulated channel will be 205.6km. In the bridge reconstruction works, 10 obstructive bridges will be rebuilt. The supporting works include 2 anchorage service zones and 6 anchorages. In addition, channel communication and video monitoring systems will be built around Fuyang Municipality in the Project, and navigation aids and signs will be arranged along the channel. All navigational marks will be illuminated at night. The total investment in resettlement is 169.3350 million yuan, accounting for 9% of the total investment in the Project. Of the total resettlement costs, the costs for acquisition of rural collective land are 52.7795 million yuan (31.17%); costs for temporary land occupation 11.4899 million yuan (6.79%); costs for house demolition 38.2504 million yuan (22.59%); compensation costs for demolition of attachments 1.4053 million yuan (0.83%); and all taxes amount to 65.41 million yuan (38.63%). See for the detailed budget.

100 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Table 0-1 for the detailed budget. The planned implementation period of the Project is from 2011 to 2016. The main tasks of land acquisition, house demolition and resettlement will begin in October 2010 and end in June 2015. B. Resettlement impacts The types of impact of the Project include: (1) land loss due to acquisition/occupation; (2) demolition of residential houses; and (3) demolition of attachments. The land acquisition and house demolition work of the Project involves 20 villages/communities in 16 townships/sub-districts of one city (Jieshou), three districts (Yingquan, Yingdong and Yingzhou) and two counties (Taihe and Yingshang), affecting 788 households with 3,140 people permanently (directly). In particular, 424 households with 1,651 people are affected by land acquisition only, 346 households with 1,406 people are affected by house demolition only, and 18 households with 83 people are affected by both land acquisition and house demolition. In addition, the Project affects 2,891 households with 10,316 people temporarily. The key resettlement impacts are shown in Attached Table 7.

101 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Attached Table 7 Key resettlement impacts

Project Type Unit Channel Bridge Supporting Subtotal works works works Households affected by / 192 0 232 424 land acquisition only Population affected by / 714 0 937 1,651 land acquisition only Households affected by / 0 346 0 346 house demolition only Directly Population affected by affected / 0 1,406 0 1,406 house demolition only population Households affected by both land acquisition and / 12 0 6 18 house demolition Population affected by both land acquisition and / 56 0 27 83 house demolition Temporarily Households / 2,887 1 3 2,891 affected population Population / 10,302 4 10 10,316

C. Legal framework and policies C.1 Laws, regulations and policies applicable to resettlement The resettlement policies applicable to the Project have been formulated in accordance with the policies of the PRC, the Anhui Provincial Government, the Fuyang Municipal Government and the World Bank on resettlement. The legal framework and policies for resettlement of the Project is as follows: Policy document Effective date

S Land Administration Law of the PRC 2004-8-28 t a t

e Regulations on the Implementation of the Land Administration Law 1998-12-27 of the PRC (Decree No.256 of the State Council) Decision of the State Council on Deepening the Reform and Rigidly 2004-10-21 Enforcing Land Administration (Guo Fa [2004]28) Interim Regulation of the PRC on Farmland Occupation Tax 2008-1-1 Guidelines on Improving Compensation and Resettlement Systems for 2004-11-3 Land Acquisition (MLR Fa [2004] No.238) Circular of the State Council on Intensifying Land Control (Guo Fa 2006-8-31 [2006] No.31) Measures on Public Announcement of Land Acquisition 2002-1-1 Circular of the Ministry of Land and Resources on Carrying out 2004 MLR Fa No.58 Proper Compensation for Land Acquisition Practically Decision of the State Council on Amending the Regulation of the Regulation of the PRC on the Administration of Navigable 2009-1-1 Waterways

A Measures of Anhui Province for the Implementation of the Land n 2000-9-22 h Administration Law of the PRC u i

P Circular on Regulating Compensation and Resettlement for Land r o Acquisition and Arbitrating Disputes over Land Acquisition Properly 2007-2-15 v i n (ALRD [2007] No.54) c e Uniform Annual Output Value and Compensation Standard for Land 2010-1-1 Acquisition of Anhui Province (APG [2009] No.132)

102 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Policy document Effective date Circular on Issuing the Interim Rules for the Appraisal of Demolished 2004-7-1 urban Houses of Anhui Province (Jian Fang [2004] No.142)

F Measures of Fuyang Municipality for the Administration of Urban u

y 2002-9-21

a House Demolition (FMG Fa [2002] No.3) n

g Announcement on Benchmark Rates of Cash Compensation for M House Demolition on State-owned Land within the Urban Planning 2010-1-1 u n

i Area of Fuyang Municipality in 2009 (FMG Mi [2009] No.20) c i

p Announcement on Benchmark Rates of Cash Compensation for a l

i House Demolition on State-owned Land within the Planning Area of 2008-1-1 t y the Five Counties and Cities in 2008 (FMG Mi [2008] No.29) Circular on Issuing the Measures of Fuyang Municipality for the Implementation of Land Acquisition and House Demolition for Non- 2000-3-10 agricultural Construction (FMG Fa [2000] No.18) Measures of Fuyang Municipality for the Basic Endowment Insurance 2009-5-20 of Land-expropriated Farmers Interim Measures of Fuyang Municipality for the Training and Social 2009-6-1 Security of Land-expropriated Farmers (FMG Ban [2009] No.45) B d o

r Operational Policy OP4.12 Involuntary Resettlement and appendixes 2002-1-1 a l Bank Procedure BP4.12 Involuntary Resettlement and appendixes 2002-1-1

C.2 Main compensation rates ‹ Acquisition of collective land The compensation rates for acquisition of collective land have been fixed according to the Land Administration Law of the PRC, the Guidelines on Improving Compensation and Resettlement Systems for Land Acquisition, the Measures of Anhui Province for the Implementation of the Land Administration Law of the PRC and Uniform Annual Output Value and Compensation Standard for Land Acquisition of Anhui Province (APG [2009] No.132), etc., and the information and field survey findings provided by the municipal land and resources bureau concerned: For farmland acquired for the Project, land compensation fees will be 6-10 times the uniform annual output value of the past 3 years and resettlement subsidy 12-16 times the uniform annual output value of the past 3 years, totaling 28,000-53,000 yuan/mu, and young crop compensation fees 1/2 of the annual average output value of the past 3 years. The compensation rates for acquisition of collective land are shown in Attached Table 8 Schedule of compensation rates for acquisition of collective land.

103 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Attached Table 8 Schedule of compensation rates for acquisition of collective land

Farmland Unused land Compensation rate Multiple Compensation rate (yuan/mu) Multiple

fees compensation Land subsidy Resettlement Subtotal fees compensation Land subsidy Resettlement fees compensation crop Young Subtotal fees compensation Land subsidy Resettlement Subtotal fees (y ucompensation anLand /musubsidy ) Resettlement fees compensation crop Young Subtotal Output value of P3Y No. City/ district/ county Township/ sub-district Village/ community (yuan/mu)

1 Tianying Town Houwei 1480 7 14 21 10360 20720 740 31820 6 6 12 8880 8880 740 18500 Jieshou City 2 Xuzhai Town Xiaowan 1430 7 14 21 10010 20020 715 30745 6 6 12 8580 8580 715 17875 3 Yingdong District Kouzi Town Zhangdianweizi 1400 8 15 23 11200 21000 700 32900 6 6 12 8400 8400 700 17500 4 Wuzhai 1400 8 15 23 11200 21000 700 32900 6 6 12 8400 8400 700 17500 Yingzhou District Sanshilipu Town 5 Gaolou 1400 8 15 23 11200 21000 700 32900 6 6 12 8400 8400 700 17500 6 Datao 1400 8 15 23 11200 21000 700 32900 6 6 12 8400 8400 700 17500 Wenji Town 7 Chendian 1400 8 15 23 11200 21000 700 32900 6 6 12 8400 8400 700 17500 8 Yingquan District Ninglaozhuang Town Fanying 1400 8 15 23 11200 21000 700 32900 6 6 12 8400 8400 700 17500 9 Zhoupeng Sub-district Fengzhuang 1580 9 15 24 14220 23700 790 38710 6 6 12 9480 9480 790 19750 10 Xingliu Town Chenying 1580 9 15 24 14220 23700 790 38710 6 6 12 9480 9480 790 19750 11 Shencheng Town Shibei Area 1500 7 15 22 10500 22500 750 33750 6 6 12 9000 9000 750 18750 12 Xinji Town Xiawan 1370 6 14 20 8220 19180 685 28085 6 6 12 8220 8220 685 17125 13 Yingshang County Huangqiao Town Sanwan 1460 7 14 21 10220 20440 730 31390 6 6 12 8760 8760 730 18250 14 Ying River Xiang Sanba 1370 6 14 20 8220 19180 685 28085 6 6 12 8220 8220 685 17125 15 Yanghu Town Jinyuzi 1370 6 14 20 8220 19180 685 28085 6 6 12 8220 8220 685 17125 16 Taihe County Xingzhai Town Houzhuang 1780 6 12 18 10680 21360 890 32930 6 6 12 10680 10680 890 22250 17 Jiuxian Town Xijie 1780 6 12 18 10680 21360 890 32930 6 6 12 10680 10680 890 22250 18 Dongzou Garden 2000 10 16 26 20000 32000 1000 53,000 6 6 12 12000 12000 1000 25000 Chengguan Town 19 Xizou Garden 2000 10 16 26 20000 32000 1000 53,000 6 6 12 12000 12000 1000 25000

104 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

20 Zhaoji Xiang Xiazhangwan 1780 6 12 18 10680 21360 890 32930 6 6 12 10680 10680 890 22250

105 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

‹ Compensation rates for temporary occupation of collective land According to the provisions of the state, Anhui Province and Fuyang Municipality on temporary land occupation, compensation fees for temporary land occupation include young crop/ground attachment compensation fees and land reclamation fees. Land occupied temporarily by the Project is occupied mainly by the spoil grounds. These spoil grounds are mostly hollow farmland and its level may be increased after disposal. In addition, fertile river bottomland can improve the fertility of the temporarily occupied land and eliminate the need for reclamation. Except the land occupied temporarily by the spoil grounds, compensation fees for land occupied temporarily by the Project include young crop/ground attachment compensation fees and land reclamation fees. See Attached Table 8.

Attached Table 8 Compensation rates for temporary land occupation

Young crop/ground Land reclamation fees Item attachment compensation (yuan/m2) fees (yuan/mu· year) Compensation rates for temporary land 1,500 6 occupation Remarks Based on 2 years /

‹ House demolition rate for collective land The replacement cost rates for different types of houses have been fixed according to the relevant provisions of Anhui Province and Fuyang Municipality, and by reference to the replacement cost analysis of the main types of affected houses and the compensation rates of similar past projects, as shown in Attached Table 9.

Attached Table 9 Compensation rates for demolition of rural residential houses

Type Unit Compensation rate Remarks (yuan/unit) 1) House compensation / Storied building m2 410 / Single-storied building m2 260 / with brick wall and tile roof 2) Other costs / Moving subsidy Household 200 / Temporary resettlement Month ·m2 2 Based on the actual period, estimated subsidy to be 6 months in this report

‹ House demolition rate for state-owned land Urban house demolition for the Project involves Jieshou City and Taihe County; the compensation rates have been fixed based on actual market appraised prices according to the benchmark rates of Fuyang Municipality and the affected districts and counties, and by reference to the geographic location and building area of each house. The compensation rates for residential houses are shown in Attached Table 10.

Attached Table 10 Compensation rates for demolition of urban residential houses

Compensation rate (yuan/unit) Remarks Type Unit Jieshou Taihe City County 1) House

106 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Compensation rate (yuan/unit) Remarks Type Unit Jieshou Taihe City County compensation Reinforced concrete m2 1430 1480 Grade 1 Tier-1 areas Masonry concrete m2 1250 1300 Grade 1 2) Other costs Moving m2 4 4 subsidy 1) 5‰ of the benchmark rate (unit price) of demolished houses per month-m2 Temporary 2) Based on the actual period, estimated to be 6 Month resettlement 5‰ 5‰ months in this report ·m2 subsidy 3) The demolisher shall resettle the displaced person or lessee within the specified transition period (not more than 18 months).

‹ Compensation rates for ground attachments Special facilities affected by the Project will be compensated for or rebuilt as required according t the former function, size and standard. All ground attachments affected by the Project will be compensated for directly to their owners at replacement cost. The compensation rates for affected ground attachments are shown in Attached Table 11.

Attached Table 11 Compensation rates for ground attachments

No. Type / feature Unit Compensation rate (yuan/unit) 1 Arbor tree less than 10cm in / 4 diameter 2 Arbor tree 10cm-20cm in / 12 diameter 3 Arbor tree over 20cm in diameter / 20 4 Tomb / 240 5 Telegraph pole / 30

C.3 Entitlement matrix The entitlement matrix has been prepared according to the relevant policies in this appendix. See Attached Table 12.

107 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Attached Table 12 Entitlement Matrix

Type of impact Degree of impact Affected people Compensation and resettlement policy Compensation rates (1) In case of land acquisition, the acquired land shall be compensated for based on its original use. Compensation fees for land acquisition include compensation fees for land, ground attachments young crops, and resettlement subsidy. (2) The use of land compensation fees and resettlement subsidy shall Acquiring 1,652.6 be decided by the village congress; the land compensation fees may Permanent mu of collective 442 households be paid to the affected village or households; the resettlement acquisition of land permanently, Farmland: 32,200-37,920 yuan/mu with 1,734 people subsidy must be used specifically for labor resettlement for the collective land affecting 20 acquired land and shall not be diverted to any other purpose; the villages compensation fees for ground attachments and young crops shall be paid to their respective owners. After an affected household receives compensation, if it meets the criteria for the endowment insurance of land-expropriated farmers, it may participate in the endowment insurance of land-expropriated farmers. Permanent Occupying 98.83 occupation of mu of state- None Gratuitous allocation state-owned owned land land permanently Affecting 2,891 Temporary occupation of rural collective land shall be compensated Temporary households with for based on the purpose and loss of occupation. Compensation fees occupation of 9,843.3 mu Young crop compensation rate: 1,500 yuan/mu 10,316 people for temporary land occupation include young crop/ground collective land temporarily attachment compensation fees, and land reclamation fees. House compensation (1) Receiving house compensation at replacement cost, and Storied building: 410 yuan/m2 compensation for relocation of attachments based on actual costs; Single-storied building with brick wall and tile Demolition of (2) Selecting local restoration, non-local resettlement or single roof: 260 yuan/m2 Demolition area 18 households rural residential compensation as one wishes after receiving the cash compensation 1,802.2 m2 with 83 people houses for the house Other compensation (3) Receiving a moving subsidy and a lease subsidy for the Moving subsidy: 200 yuan/household transition period of house construction Lease subsidy for the transition period of house construction: 2 yuan/month·m2 Demolition of Demolition area 346 households (1) Receiving house compensation at replacement cost, and House compensation (Tier-1 areas)

108 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Type of impact Degree of impact Affected people Compensation and resettlement policy Compensation rates urban 27,884 m2 with 1,406 people compensation for relocation of attachments based on actual costs; Jieshou City: reinforced concrete Grade 1: residential (2) Selecting cash compensation or property swap as one wishes 1,430 yuan/m2, masonry concrete Grade 1: houses after receiving the cash compensation for the house 1,250 yuan/m2 (3) Receiving a moving subsidy and a transition subsidy Taihe County: reinforced concrete Grade 1: 1480 yuan/m2, masonry concrete Grade 1: 1300 yuan/m2

Other compensation Moving subsidy: 4 yuan/m2, based on building area Temporary resettlement subsidy: 5‰ of the benchmark rate (unit price) of demolished houses per month-m2 Ground / Owner To be compensated by the PMO to the owner attachments Compensation Affected people rates, payment of dissatisfied with compensation land acquisition, All costs and management fees involved in such appeal should be Appeals fees, and house house demolition exempted. demolition and or resettlement resettlement and filing an measures appeal

109 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

D Resettlement organization

To ensure successful resettlement as desired, a top-down organization must be set up during project implementation to plan, coordinate and monitor resettlement activities. Since resettlement is a very extensive task that necessitates the assistance and collaboration of all departments, the land and resources, forestry and agriculture authorities, etc. will participate and assist in the implementation of resettlement. Each affected township and village has one or two leaders responsible mainly for resettlement. The agencies responsible for the land acquisition and house demolition work of the Project include: ¾ APCD Foreign-funded Project Management Office (Provincial PMO) ¾ APSCIG ¾ Headquarters of Fuyang Municipality and counties (including county-level cities) thereunder14 ¾ Town PMOs ¾ Village (neighborhood) committees ¾ Design agency ¾ External independent M&E agency E Grievance redress Since public participation is encouraged during the preparation and implementation of the Resettlement Plan, no substantial dispute will arise. However, unexpected issues may arise during the whole process. In order to solve such issues effectively and ensure successful project completion and land acquisition, a 5-stage grievance redress mechanism has been established for the Project: ¾ Stage 1: If any displaced person is dissatisfied with the Resettlement Plan, he/she can report this to the village committee or sub-district resettlement office orally or in writing. In case of an oral appeal, the village committee or sub-district resettlement office shall handle such appeal and keep written records. Such appeal should be solved within 2 weeks; ¾ Stage 2: If the displaced person is dissatisfied with the disposition of Stage 1, he/she may file an appeal to the headquarters of Fuyang Municipality or any county (including county-level city) thereunder. After receiving such disposition, they shall make a disposition within 7 days; ¾ Stage 3: If the displaced person is still dissatisfied with the disposition of Stage 2, he/she may file an appeal to the on-site PMO of APSCIG. After receiving such disposition, he shall make a disposition within 2 weeks; ¾ Stage 4: If the displaced person is still dissatisfied with the disposition of Stage 3, he/she may escalate the appeal to the competent administrative organs in accordance with the Administrative Procedure Law of the PRC after receiving such disposition for arbitration. ¾ Stage 5: If the displaced person is still dissatisfied with the arbitration award, he/she may file a suit in a civil court in accordance with the Civil Procedure Law of the PRC after receiving the arbitration award. All agencies will accept grievances and appeals from the affected people for free, and costs so reasonably incurred will be disbursed from contingency costs. During the whole

14 The construction headquarters of the Project will be established based on the MSA in conjunction with the land and resources bureau, relocation office, water resources bureau, communications bureau and construction bureau to be responsible for resettlement. 110 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

construction period of the Project, these appeal procedures will remain effective, so that the affected people can use them to solve relevant issues. The above appeal channel will be notified to displaced persons through mass media, so that displaced persons are fully aware of their right of appeal. The grievance redress process will be disclosed to the affected people through mass media. F Resettlement implementation schedule The general resettlement schedule of the Project has been drafted according to the progress of preparation and implementation activities of land acquisition, house demolition and resettlement. The specific period of implementation may be adjusted due to any deviation from the general schedule. See

StageP Task Fuyang Municipality Jieshou City Taihe County Yingshang County r e

p Determination of range of land a

r acquisition and houseSep.-Dec. 2009 Aug.-Dec. 2009 Aug.-Dec. 2009 Aug.-Dec. 2009 a t i

o demolition n

p Physical quantity survey of land e

r acquisition and houseDec. 2009-Mar. 2010 Dec. 2009-Mar. 2010 Dec. 2009-Mar. 2010Dec. 2009-Mar. 2010 i o

d demolition Preliminary socioeconomic Feb. 2010-Mar. 2010 Feb. 2010-Mar. 2010 Feb. 2010-Mar. 2010 Feb. 2010-Mar. 2010 survey Consultation of resettlement Mar.-Apr. 2010 Mar.-Apr. 2010 Mar.-Apr. 2010 Mar.-Apr. 2010 programs Preparation of the Resettlement Mar.-Apr. 2010 Mar.-Apr. 2010 Mar.-Apr. 2010 Mar.-Apr. 2010 Plan Disclosure of the Resettlement Aug. 2010 Aug. 2010 Aug. 2010 Aug. 2010 Plan Approval of the Resettlement Sep. 2010 Sep. 2010 Sep. 2010 Sep. 2010

I Plan m

p Approval of acquisition of rural l

e Feb. 2011-Feb.2013 Feb. 2011-Feb.2013 Feb. 2011-Feb.2013 Feb. 2011-Feb.2013

m collective land e

n Holding a land acquisition and t a

t house demolition mobilizationNov. 2011-Jul.2013 Nov. 2011-Jul.2013 Nov. 2011-Jul.2013 Nov. 2011-Jul.2013 i o

n meeting to disclose policies p

e Issuing the land acquisition and r i o house demolitionDec. 2011-Oct.2014 Dec. 2011-Oct.2014 Dec. 2011-Oct.2014 Dec. 2011-Oct.2014 d announcement Negotiating and signing compensation and resettlementFeb. 2012-Dec.2014 Feb. 2012-Dec.2014 Feb. 2012-Dec.2014 Feb. 2012-Dec.2014 agreement House demolition and Mar. 2012-Feb.2015 Mar. 2012-Feb.2015 Mar. 2012-Feb.2015 Mar. 2012-Feb.2015 relocation of facilities Handover of land for Jun. 2012-Apr.2015 Jun. 2012-Apr.2015 Jun. 2012-Apr.2015 Jun. 2012-Apr.2015 construction Construction of resettlement Aug. 2012-Apr. 2015 Aug. 2012-Apr. 2015 Aug. 2012-Apr. 2015Aug. 2012-Apr. 2015 houses Displaced persons moving into Sep. 2012-Nov. 2015 Sep. 2012-Nov. 2015 Sep. 2012-Nov. 2015 Sep. 2012-Nov. 2015 new houses Income restoration of persons Feb. 2011-Dec. 2015 Feb. 2011-Dec. 2015 Feb. 2011-Dec. 2015 Feb. 2011-Dec. 2015

M moving & E M&E May. 2011-Dec. 2015 May. 2011-Dec. 2015May. 2011-Dec. 2015May. 2011-Dec. 2015

. Attached Table 13 Resettlement schedule

StageP Task Fuyang Municipality Jieshou City Taihe County Yingshang County r e

p Determination of range of a

r land acquisition and house Sep.-Dec. 2009 Aug.-Dec. 2009 Aug.-Dec. 2009 Aug.-Dec. 2009 a t i

o demolition n

p Physical quantity survey of

e Dec. 2009-Mar. Dec. 2009-Mar. Dec. 2009-Mar. r land acquisition and house Dec. 2009-Mar. 2010 i

o 2010 2010 2010 d demolition Preliminary socioeconomic Feb. 2010-Mar. Feb. 2010-Mar. Feb. 2010-Mar. Feb. 2010-Mar. 2010 survey 2010 2010 2010

111 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Consultation of resettlement Mar.-Apr. 2010 Mar.-Apr. 2010 Mar.-Apr. 2010 Mar.-Apr. 2010 programs Preparation of the Mar.-Apr. 2010 Mar.-Apr. 2010 Mar.-Apr. 2010 Mar.-Apr. 2010 Resettlement Plan Disclosure of the Resettlement Aug. 2010 Aug. 2010 Aug. 2010 Aug. 2010 Plan Approval of the Resettlement Sep. 2010 Sep. 2010 Sep. 2010 Sep. 2010

I Plan m p Approval of acquisition of l e Feb. 2011-Feb.2013 Feb. 2011-Feb.2013 Feb. 2011-Feb.2013 Feb. 2011-Feb.2013 m rural collective land e n Holding a land acquisition and t a t house demolition mobilization Nov. 2011-Jul.2013 Nov. 2011-Jul.2013 Nov. 2011-Jul.2013 Nov. 2011-Jul.2013 i o n meeting to disclose policies p e Issuing the land acquisition r i o and house demolition Dec. 2011-Oct.2014 Dec. 2011-Oct.2014 Dec. 2011-Oct.2014 Dec. 2011-Oct.2014 d announcement Negotiating and signing compensation and Feb. 2012-Dec.2014 Feb. 2012-Dec.2014 Feb. 2012-Dec.2014 Feb. 2012-Dec.2014 resettlement agreement House demolition and Mar. 2012-Feb.2015 Mar. 2012-Feb.2015 Mar. 2012-Feb.2015 Mar. 2012-Feb.2015 relocation of facilities Handover of land for Jun. 2012-Apr.2015 Jun. 2012-Apr.2015 Jun. 2012-Apr.2015 Jun. 2012-Apr.2015 construction Construction of resettlement Aug. 2012-Apr. Aug. 2012-Apr. Aug. 2012-Apr. Aug. 2012-Apr. 2015 houses 2015 2015 2015 Displaced persons moving Sep. 2012-Nov. Sep. 2012-Nov. Sep. 2012-Nov. Sep. 2012-Nov. 2015 into new houses 2015 2015 2015 Income restoration of persons Feb. 2011-Dec. Feb. 2011-Dec. Feb. 2011-Dec. Feb. 2011-Dec. 2015

M moving 2015 2015 2015 &

E May. 2011-Dec. May. 2011-Dec. May. 2011-Dec. M&E May. 2011-Dec. 2015 2015 2015 2015

112 Appendix 10 Policy framework for resettlement

World Bank Financed Anhui Shaying River Channel Improvement Project

Policy framework for resettlement

National Research Center for Resettlement, Hohai University

May 2010 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project CONTENTS I Background ...... 109 II OBJECTIVES, PRINCIPLES AND TERMS OF POLICY FRAMEWORK 115 III PREPARATION OF THE RAP 110 IV INSTITUTIONAL AND LEGAL FRAMEWORK 112 V IMPLEMENTATION PROCESS 115 VI FINANCIAL ARRANGEMENTS 115 VII PUBLIC PARTICIPATION AND INFORMATION DISCLOSURE 115 VIII APPEAL PROCEDURES 116 IX MONITORING AND EVALUATION 117 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project I. Background 1. Fuyang is located in northwestern Anhui, the south tip of the Huang-Huai-Hai Plain and the west of the Huaibei Plain. It borders Zhoukou and Zhumadian Cities, Henan Province on the west, Xinyang City, Henan Province on the southwest, Bozhou City on the north and northeast, and Huainan City on the east, and abuts on the Huai River across Liu’an City on the south. Presently, Fuyang Municipality governs Jieshou City, Taihe, Linquan, Yingshang and Funan Counties, and Yingzhou, Yingquan and Yingdong Districts, with an area of 9,775 km2 and a population of 9.743 million, being the largest population municipality of Anhui Province. 2. Fuyang abounds with resources, and is an important production base of farm and sideline products of the state, and also a rising coal and energy base of Anhui Province and even the whole eastern China region. According to statistics, Fuyang’s regional GDP was 75.512 billion yuan in 2007, in which the added value of primary industries was 8.131 billion yuan, that of secondary industries 40.401 billion yuan and that of tertiary industries 25.272 billion yuan. Annual social investment in fixed assets attained 43.03 billion yuan, in which the investment in urban fixed assets was 38.821 billion yuan, ranking second in the province. Annual fiscal revenue was 14.013 billion yuan. In 2007, the average pay of in-service workers of Fuyang was 21,708 yuan, per capita disposable income of urban residents 12,866 yuan, per capita consumer expenditure 9,851.65 yuan and per capita net income of farmers 2,683.3 yuan. 3. The Shaying River, located on the left side of the Huai River, is the largest branch of the Huai River. It is originated in the Funiu Mountain Range in Henan Province, formed by the convergence of the Sha and Ying Rivers in Zhoukou City, running through central Henan from northwest to southeast, entering Anhui Province at the Changsheng Stream in Jieshou City, and running from Jieshou City, Taihe County, Fuyang Municipality into the Huai River at Mohekou in Yingshang County, with a full length of 620km and a watershed area of 36,651 km2, in which its length is 206km and its watershed area 4,112 km2 in Anhui Province. 4. According to the Layout Plan of Inland Navigation Channels and Ports (2005— 2020), the Shaying River channel runs from Luohe, Henan to Mohekou, Anhui, with a full length of 378km, planned as a Class IV channel. The Yingshang ship lock and the Taihe Genglou hydraulic complex in Anhui have been completed, and the Fuyang ship lock is under construction. By now, the problem of navigation obstruction from lock and dam on the Shaying River channel has been largely solved. If the channel is further dredged, the stretch below Zhoukou, Henan will be open for navigation. 5. The land acquisition and house demolition work of the Project involves 20 villages/communities in 16 townships/sub-districts of one city (Jieshou), three districts (Yingquan, Yingdong and Yingzhou) and two counties (Taihe and Yingshang). Since impacts of the access roads and construction sites of the channel works, supporting works and bridge works have not been identified yet, villagers or residents of some villages and communities might be affected. This policy framework has been prepared to ensure the interests of these displaced persons.

II. Objectives, principles and terms of policy framework 1. This policy framework for resettlement is prepared in accordance with OP4.12 Involuntary Resettlement in the World Bank Operational Handbook issued in December 2001. The overall objectives are: ‹ Involuntary resettlement should be avoided where feasible, or minimized, exploring all viable alternative project designs ‹ Where it is not feasible to avoid resettlement, resettlement activities should be conceived and executed as sustainable development programs, providing sufficient investment resources to enable the persons displaced by the project to share in project benefits. Displaced persons3 should be meaningfully consulted and should have opportunities to participate in planning and implementing resettlement

115 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project programs; ‹ Displaced persons should be assisted in their efforts to improve their livelihoods and standards of living or at least to restore them, in real terms, to pre-displacement levels or to levels prevailing prior to the beginning of project implementation, whichever is higher. 2. This policy framework sets the principles and objectives of resettlement, appropriate guidelines, rights, legal and institutional framework, modes of compensation and restoration, participant profile and grievance redress procedures for resettlement, and is used to guide the compensation, resettlement and restoration of displaced persons, etc. 3. Every resettlement plan shall be based on identifiable basic information collected, and displaced persons shall include the following: ‹ Those whose farmland or rural house together with housing site is affected wholly or partly by the Project (permanent or temporary); ‹ Those whose urban residential house is affected wholly or partly by the Project (permanent or temporary); ‹ Those whose business (enterprise, public institution or store) is affected wholly or partly by the Project (permanent or temporary); ‹ Those whose young crops or ground attachments are affected wholly or partly by the Project (permanent or temporary). ‹ The transition period of resettlement shall be minimized, and restoration measures shall be made available to displaced persons before the expected start-up date; ‹ Acquisition programs for land and other assets, and restoration measures available shall be discussed repeated with displaced persons to ensure minimum disturbance; displaced persons will be empowered before the expected start-up date; ‹ The existing service and resource level of the community shall be maintained or improved; ‹ Whenever or wherever necessary, financial and material resources for resettlement and restoration must be available. The budget in the Resettlement Plan shall include contingencies; ‹ Institutional and organizational arrangements shall ensure that land acquisition and resettlement can be designed, planned, consulted about and implemented effectively and timely. ‹ The implementation of the Resettlement Plan shall be subject to effective and timely supervision and M&E.

III. Preparation of the RAP 4. The Resettlement Plan (including payment of all expenses related to resettlement) shall be prepared and implemented by APSCIG. 5. The Resettlement Plan shall cover the following (if relevant). Items irrelevant with the Project shall be specified in the Resettlement Plan: ¾ General description of the Project; ¾ Identification of potential impacts of the Project; ¾ Objectives (key objectives of the Resettlement Plan); ‹ Socioeconomic research: Such research shall be conducted at the early stage of project preparation, and include potential displaced persons, including survey findings and other descriptions; ‹ Legal framework: analysis findings of the legal framework, including the scope of acquisition power of resettlement agencies and associated nature of compensation, applicable legal and administrative procedures, relevant laws and social welfare legislation, laws and regulations, and necessary legal steps; ‹ Institutional framework: including identification of resettlement agencies and NGOs that may function, evaluation of their institutional capacity, and proposal of any step to strengthen institutional capacity; 116 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project ‹ Eligibility: identification of criteria of displaced persons, and determination of whether they are entitled to compensation and other resettlement assistances as displaced persons; ‹ Valuation and compensation of losses; ‹ Resettlement and restoration measures: description of cash compensation and other resettlement measures; ‹ Selection, preparation and rearrangement of resettlement sites; ‹ Supply of housing, infrastructure and social services; ‹ Environmental protection and management; ‹ Public participation and consultation, where displaced persons and relevant communities must be included; ‹ Integration with local population: measures to alleviate the impact of resettlement on any local community; ‹ Appeal procedures: available procedures for any third party to settle any dispute over resettlement; ‹ Organization and responsibilities; ‹ Implementation schedule; ‹ Cost and budget; ‹ M&E 6. A brief resettlement plan shall at least cover the following: ‹ Detailed survey of displaced persons and assets appraisal; ‹ Description of compensation to be provided and other resettlement assistances; ‹ Communication with displaced persons about acceptable alternatives; ‹ Institutional responsibilities implemented and appeal procedures; ‹ Monitoring and implementation arrangements; ‹ Schedule and budget. 7. The Resettlement Plan shall be completed no later than 6 month before the beginning date of resettlement, and implemented after approval by the executing agency and competent authorities. IV. Institutional and legal framework 8. The legal framework that directs the implementation of the Resettlement Plan is prepared in accordance with the regulations of the PRC, Anhui Province and the Fuyang Municipal Government on land acquisition and house demolition. 9. The main laws, regulations and ordinances of the PRC that are applied to this framework and ensure its legal validity are as follows: Attached Table 14 Policy framework

Policy document Effective date

S Land Administration Law of the PRC 2004-8-28 t a t

e Regulations on the Implementation of the Land Administration Law 1998-12-27 of the PRC (Decree No.256 of the State Council) Decision of the State Council on Deepening the Reform and Rigidly 2004-10-21 Enforcing Land Administration (Guo Fa [2004]28) Interim Regulation of the PRC on Farmland Occupation Tax 2008-1-1 Guidelines on Improving Compensation and Resettlement Systems 2004-11-3 for Land Acquisition (MLR Fa [2004] No.238) Circular of the State Council on Intensifying Land Control (Guo Fa 2006-8-31 [2006] No.31) Measures on Public Announcement of Land Acquisition 2002-1-1 Circular of the Ministry of Land and Resources on Carrying out 2004 MLR Fa No.58 Proper Compensation for Land Acquisition Practically

117 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project Policy document Effective date Decision of the State Council on Amending the Regulation of the Regulation of the PRC on the Administration of Navigable 2009-1-1 Waterways

A Measures of Anhui Province for the Implementation of the Land n 2000-9-22 h Administration Law of the PRC u i

P Circular on Regulating Compensation and Resettlement for Land r o Acquisition and Arbitrating Disputes over Land Acquisition Properly 2007-2-15 v i

n (ALRD [2007] No.54) c e Uniform Annual Output Value and Compensation Standard for Land 2010-1-1 Acquisition of Anhui Province (APG [2009] No.132) Circular on Issuing the Interim Rules for the Appraisal of Demolished 2004-7-1 urban Houses of Anhui Province (Jian Fang [2004] No.142)

F Measures of Fuyang Municipality for the Administration of Urban u

y 2002-9-21

a House Demolition (FMG Fa [2002] No.3) n

g Announcement on Benchmark Rates of Cash Compensation for M House Demolition on State-owned Land within the Urban Planning 2010-1-1 u n

i Area of Fuyang Municipality in 2009 (FMG Mi [2009] No.20) c i

p Announcement on Benchmark Rates of Cash Compensation for a l

i House Demolition on State-owned Land within the Planning Area of 2008-1-1 t y the Five Counties and Cities in 2008 (FMG Mi [2008] No.29) Circular on Issuing the Measures of Fuyang Municipality for the Implementation of Land Acquisition and House Demolition for Non- 2000-3-10 agricultural Construction (FMG Fa [2000] No.18) Measures of Fuyang Municipality for the Basic Endowment Insurance 2009-5-20 of Land-expropriated Farmers B d o

r Operational Policy OP4.12 Involuntary Resettlement and appendixes 2002-1-1 a l Bank Procedure BP4.12 Involuntary Resettlement and appendixes 2002-1-1

10. The Resettlement Plan is prepared to ensure that displaced persons have sufficient opportunities to replace their lost properties, and improve or at least restore their income level and standard of living. To realize these objectives, it should be ensured that all displaced persons are identified, and all displaced persons think the remedies set out in the Resettlement Plan are reasonable. In consideration of the main types of impact (e.g., land acquisition and occupation, residential house demolition (including rural and urban) and non-residential house demolition (including enterprise, public institution and store), etc.), the following measures shall usually be taken: 11. Land-expropriated farmers will be entitled to the following compensation and restoration measures: ‹ The remaining collective farmland after land acquisition will be reallocated by the village committee among all collective members. In this case, if partial acquisition of land renders houses or buildings unsafe or functionally lost, such land shall be fully acquired. All displaced persons shall be entitled to the reallocation of land, and benefit from any project invested with collective land compensation fees. ‹ According to the Land Administration Law and relevant laws, where land reallocation is impossible, displaced persons deprived of farmland must be identified. In some cases, paid job opportunities may be offered to them at wages at least equivalent to their lost income. In other cases, displaced persons will at least receive a resettlement subsidy equivalent to 4-6 times the annual average output value of their lost land in the past 3 years. If displaced persons are still unable to restore their former standard of living despite of this, the resettlement subsidy may be increased up to 15 times the annual average output value of the past 3 years; ‹ If land compensation fees and resettlement subsidy are still insufficient to restore displaced persons’ standard of living, the municipal and county governments 118 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project concerned may use income from the compensated use of state-owned land for subsidization; ‹ Land compensation fees and resettlement subsidy shall be paid to the village committee of each affected village or displaced persons, used to (1) increase arable area if land is usable; (2) increase agricultural output by providing irrigation and improving agricultural practices; or (3) develop nonagricultural income based on existing activities. Like fixed assets, lost young crops, fruits and economic forests of displaced persons will be compensated for at replacement cost. ‹ Lost income, young crops, land and infrastructure of displaced persons affected by temporary land occupation will also be compensated for. 12. Demolished houses and attachments will be compensated for and restored as follows: ‹ The village collective reallocates a housing site for resettlement; ‹ Property swap; ‹ Compensation at full replacement cost; ‹ Reconstruction or restoration of all facilities and services (e.g., road, water supply, power, telephone, cable TV and school); ‹ The transition subsidy shall ensure relocation of all properties or acquisition of temporary housing. 13. Proposed compensation rates: According to a preliminary field survey and the policy standard of Fuyang Municipality, possible compensation rates are as follows: ‹ Compensation rates for acquisition of rural collective land: 6-10 times the uniform annual output value of the past 3 years and resettlement subsidy 12-16 times the uniform annual output value of the past 3 years, totaling 28,000-53,000 yuan/mu, and young crop compensation fees 1/2 of the annual average output value of the past 3 years ‹ State-owned land is acquired by allocation. ‹ The compensation rates for temporary occupation of rural collective land are shown in Attached Table 15. Attached Table 15 Compensation rates for temporary land occupation

Young crop/ground Land reclamation fees Item attachment compensation (yuan/m2) fees (yuan/mu· year) Compensation rates for temporary land 1,500 6 occupation Remarks Based on 2 years

¾ Compensation for demolition of rural residential houses Attached Table 16 Cash compensation rates for demolition of rural residential houses Type Unit Compensation rate Remarks (yuan/unit) 1) House compensation Storied building m2 410 Single-storied m2 260 building with brick wall and tile roof 2) Other costs Moving subsidy Household 200 Temporary Month ·m2 2 Based on the actual period, estimated resettlement to be 6 months in this report subsidy 119 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

¾ Compensation for demolition of urban residential houses Attached Table 17 Cash compensation rates for demolition of urban residential houses

Unit: yuan/m2 Compensation rate (yuan/unit) Remarks Type Unit Taihe Jieshou City County 1) House compensation Reinforced concrete m2 1430 1480 Grade 1 Tier-1 areas masonry concrete m2 1250 1300 Grade 1 2) Other costs Moving m2 4 4 subsidy 1) 5‰ of the benchmark rate (unit price) of demolished houses per month-m2 Temporary 2) Based on the actual period, estimated to be Month resettlemen 5‰ 5‰ 6 months in this report ·m2 t subsidy 3) The demolisher shall resettle the displaced person or lessee within the specified transition period (not more than 18 months).

¾ Compensation rates for ground attachments Attached Table 18 Compensation rates for ground attachments No. Type / feature Unit Compensation rate (yuan/unit) 1 Arbor tree less than 10cm in / 4 diameter 2 Arbor tree 10cm-20cm in / 12 diameter 3 Arbor tree over 20cm in diameter / 20 4 Tomb / 240 5 Telegraph pole / 30

¾ Other costs Attached Table 19Compensation rates for other costs No. Item Charging standard Basis Farmland occupation Tier-115: 37.5/m2 Cai Nong Cun [2008] 1 tax Other16: 18.75/m2 No.367 Endowment insurance FMG Ban [2009] 2 premium of land- 25 yuan/m2 No.45 expropriated farmers

15 Hedong, Xiangyang and Xinqiao Sub-district Offices, Yingdong District, Fuyang; Wenfeng and Qinghe Sub-district Offices, seats of the Yingxi and Wangdian Governments, Yingzhou District, and the administrative villages to the north; Quanying, Quanbei and Zhoupeng Sub- district Offices, Yingquan District; 16 Areas except Tier-1areas 120 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project No. Item Charging standard Basis 3 Water resources fund 500 yuan/mu APG [2000] No.3 4 Land reclamation fees 8 yuan/m2 5 Land reclamation fees 6 yuan/m2 Land acquisition 6 4% of total land acquisition costs management fees 7 Survey and design fees 3% of total direct resettlement costs 8 Administrative fees 5% of total direct resettlement costs 9 Technical training fees 1% of total direct resettlement costs 0.5% of total direct land acquisition 10 External M&E fees costs 10% of the sum of basic land acquisition costs, design fees, 11 Contingencies implementation fees, training fees and monitoring fees

V. Implementation process 14. For all areas involved in the Project, lawful land acquisition approval formalities must be obtained before acquisition and house demolition. 15. Compensation, resettlement and restoration activities shall not begin until all implementing agencies (IAs) have confirmed the Resettlement Plan. 16. The Resettlement Plan shall include a specific implementation schedule for all required activities. If necessary, the payment of compensation fees, restoration measures (in cash or kind) for other rights and resettlement activities shall at least be completed one month before land acquisition. If it is impossible to pay all compensation fees before land acquisition or provide any other necessary form of assistance, an extra transition subsidy will be necessary.

VI. Financial arrangements 17. As described in para. 10, the provincial PMO will assume all land acquisition and resettlement costs. Any resettlement plan consistent with this policy framework must include cost estimates and budget. Whether anyone is identified as a displaced person at the resettlement planning stage, or whether sufficient relief funds are available, all people affected adversely by land acquisition and house demolition will be entitled to compensation or any other appropriate relief measure. For the above reason, the budget in the Resettlement Plan shall include contingencies, which are usually 10% or more of the general resettlement budget to cover unforeseeable resettlement costs. 18. The compensation rates identified in the Resettlement Plan provide a basis for the calculation of resettlement compensation fees. Resettlement compensation fees shall be fully paid to individuals or collectives that lose land or other properties, and shall not be deducted for any reason. The Resettlement Plan shall describe through what procedure compensation fees are paid to displaced persons. A basic principle is funds should flow as directly as possible with minimum intermediate links.

VII. Public participation and information disclosure 19. The Resettlement Plan must describe measures taken or to be taken. The affected people shall be allowed to participate in the proposed resettlement arrangements, and their sense of participation in livelihood improvement or restoration measures strengthened. To ensure that the affected people’s opinions and advice can be fully considered, public participation shall be implemented prior to project design and resettlement relief measures, and must run through the whole process of implementation of the Resettlement Plan and external monitoring. 121 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project 20. At the first and final draft stages of the Resettlement Plan, APSCIG and the implementing agencies shall also disclose the Resettlement Plan to the affected people and the public in certain languages at certain locations in the affected areas.

VIII. Appeal procedures 21. Since the resettlement work is conducted with the participation of the affected people, no substantial dispute will arise. However, to ensure that the affected people have a channel to file an appeal on any issue concerning land acquisition and resettlement, a 5-stage grievance redress mechanism has been established in the Resettlement Plan: ‹ Stage 1: If any displaced person is dissatisfied with the Resettlement Plan, he/she can report this to the village committee or sub-district resettlement office orally or in writing. In case of an oral appeal, the village committee or sub-district resettlement office shall handle such appeal and keep written records. Such appeal should be solved within 2 weeks; ‹ Stage 2: If the displaced person is dissatisfied with the disposition of Stage 1, he/she may file an appeal to the MSA (headquarters) of Fuyang Municipality or any county (including county-level city) thereunder after receiving such disposition, which shall make a disposition within 7 days; ‹ Stage 3: If the displaced person is still dissatisfied with the disposition of Stage 2, he/she may file an appeal to the APSCIG after receiving such disposition, which shall make a disposition within 2 weeks; ‹ Stage 4: If the displaced person is still dissatisfied with the disposition of Stage 3, he/she may escalate the appeal to the competent administrative organs in accordance with the Administrative Procedure Law of the PRC after receiving such disposition for arbitration. ‹ Stage 5: If the displaced person is still dissatisfied with the arbitration award, he/she may file a suit in a civil court in accordance with the Civil Procedure Law of the PRC after receiving the arbitration award.

IX. Monitoring and evaluation 22. APSCIG shall supervise and monitor the implementation of the Resettlement Plan. Supervision and monitoring results shall be recorded and put on file for reporting to the superior. 23. Internal monitoring and supervision: ‹ Inspecting performance, including checking baseline information, asset loss or lost appraised value, terms of compensation, and resettlement and restoration rights of all displaced persons according to this policy framework and the Resettlement Plan; ‹ Monitoring whether the Resettlement Plan has been implemented according to the designed and approved program; ‹ Checking whether funds for implementing the Resettlement Plan are disbursed timely and fully, and whether such funds are used in conformity with the Resettlement Plan; ‹ Recording all grievances and solutions, and ensuring that grievances are solved timely. 24. External independent monitoring: An independent agency or individual consultant will be employed to conduct periodic external M&E of the implementation of the Resettlement Plan. Such independent agency or consultant may be an academic or institutional agency, NGO or independent consulting firm that has competent and experienced staff. 122 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project 25. In adaptation to the examination of the submitted internal supervision information and monitoring reports, the external monitoring agency shall perform a sampling survey of 20% of the relocated households within 6 months of implementation of the Resettlement Plan for the purpose of: ¾ Evaluating the participation of displaced persons, disbursement procedure of compensation fees, and whether restoration rights are secured and consistent with the policy framework and the Resettlement Plan; ¾ Evaluating whether the objective of “improving or at least restoring their income level and standard of living” is realized; ¾ Gathering qualitative indicators of socioeconomic impact of the Project on displaced persons; ¾ Proposing advice for improving the implementation procedures of the Resettlement Plan so as to realize the principles and objectives of this policy framework.

123 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

Appendix 11 Photos of Interview

124 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project Appendix 12 Framework Agreement of the Anhui Provincial Communications Department and the Fuyang Municipal People’s Government on the Project

125 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project Appendix 13 The list of person of all cities and counties in resettlement implementation agencies and their connection

1. The MSA of Fuyang Municipality

Contact:Gao Yong

Tel: 0558-2293979

Add:No. 118, Yingshang North Street ,Fuyang

2. The MSA department of Fuyang

Contact:Li Jian

Tel: 0558-2322045

Add: No. 118, Yingshang East Street ,Fuyang

3. The MSA department of Jieshou Municipality

Contact:Guo yongqiang

Tel: 0558-4822884

Add:Gangkou Road, East Shunhe Street, Jieshou

4. The MSA department of Taihe county

Contact:Wang qing

Tel: 0558-8617189

Add:No.47,South Renmin Road Taihe

5. The MSA department of Yingshang county

Contact:Jiang hui

Tel: 0558-4565652

Add:South Industrial Park, S102 Provincial Road, Yingshang

126 Resettlement Plan of the World Bank Financed Anhui Shaying River Channel Improvement Project

127