Main Tab Name: CEL – Designations HAUĂURU MĂ RAKI WIND FARM PROJECT Conditions for Electricity Transmission Purposes Designations May 2011

TE AKAU SUBSTATION: WDC DES0013/08

MATIRA SUBSTATION: WDC DES0012/08

LIMESTONE DOWNS SUBSTATION: FDC L08058

INTERNAL TRANSMISSION LINE (220kV Single Circuit Line): WDC DES0014/08 and FDC L08059

MAIN TRANSMISSION LINE (220kV Double Circuit Line): FDC L08060

ORTON SWITCHYARD: FDC L08055

GRID CONNECTION: FDC L08056

A. PURPOSE OF DESIGNATIONS

These designations by Contact Energy Limited apply to the land comprised in Schedule One of these conditions, and are for the following purposes:

(i) The construction, operation, maintenance, replacement, renewal, and upgrading of a substation at Te Akau (“the Te Akau Substation”) and ancillary facilities.

(ii) The construction, operation, maintenance, replacement, renewal, and upgrading of a substation at Matira (“the Matira Substation”) and ancillary facilities.

(iii) The construction, operation, maintenance, replacement, renewal, and upgrading of a substation at Limestone Downs (“the Limestone Downs Substation”) and ancillary facilities.

(iv) The construction, operation, maintenance, replacement, renewal, and upgrading of a single circuit 220kV Internal Transmission line (“the Single Circuit Line”) on monopoles (except in some locations where lattice towers may be required) linking the Matira and Te Akau Substations in the south with the Limestone Downs Substation in the north, and ancillary facilities.

(v) The construction, operation, maintenance, replacement, renewal, and upgrading of a double circuit 220kV External Transmission line (“the Double Circuit Line”) on lattice towers (except in some locations where steel monopole towers are required) between the Limestone Downs Substation and the Orton Switchyard, and ancillary facilities.

(vi) The construction, operation, maintenance, replacement, renewal, and upgrading of a 220kV switchyard, transmission lines and ancillary facilities at Orton (“the Orton Switchyard”).

1 HAUĂURU MĂ RAKI WIND FARM PROJECT Conditions for Electricity Transmission Purposes Designations May 2011

(vii) The construction, operation, maintenance, replacement, renewal, and upgrading of double circuit 220kV transmission lines on lattice towers (“the Grid Connection”). The work will enable the connection of the existing Huntly – Otahuhu A 220kV transmission line to the Orton Switchyard. The works include any necessary modification to the existing Huntly – Otahuhu A line within the area shown in NOR Plan 9 as subject to this designation to enable the connection.

The works associated with each of these designations is required as part of the electricity transmission infrastructure necessary to connect the output from the Hauăuru mă raki wind farm project with the National Grid, and associated ancillary activities.

B. DESCRIPTION OF DESIGNATIONS IN DISTRICT PLAN

These designations shall be described in the applicable District Plan as “Electricity Transmission Purposes”.

CONDITIONS

1.0 Description of Works 1.1 The works to give effect to the designations of the Te Akau Substation, Matira Substation, Limestone Downs Substation (together “the Substations”), Single Circuit Line, Double Circuit Line, Grid Connection and Switchyard, shall be generally in accordance with the plans and information submitted by the requiring authority, including at the hearing, and the following plans of the works (located in Schedule Two of these conditions), and subject to any amendments required by the conditions of these designations that follow:

Te Akau Substation: a) NOR Plan 1 - Te Akau Substation: Drawing 1429-R050 – Rev 24.03.11 b) Te Akau Substation Layout: Drawing 2311429-SKE08 – Rev 24.03.11 c) Te Akau Substation Layout Section 1: Drawing 2311429-SKE08a – Rev 24.03.11 d) Te Akau Substation Layout Section 2: Drawing 2311429-SKE08b – Rev 24.03.11 e) Layout Plan Refined Design: Drawing 1429-R572 – Rev 24.03.11

Matira Substation: a) NOR Plan 2 - Matira Substation: Drawing 1429-R051 – Rev 24.03.11 b) Matira Substation Layout: Drawing 2311429-SKE09 – Rev 24.03.11 c) Matira Substation Layout Section 1: Drawing 2311429-SKE092 – Rev 24.03.11 d) Matira Substation Layout Section 2: Drawing 2311429-SKE093 – Rev 24.03.11 e) Layout Plan Refined Design: Drawing 1429-R550 – Rev 24.03.11

Limestone Downs Substation: a) NOR Plan 3 - Limestone Downs Substation: Drawing 1429-R052 – Rev 24.03.11

2 HAUĂURU MĂ RAKI WIND FARM PROJECT Conditions for Electricity Transmission Purposes Designations May 2011 b) Limestone Downs Substation Layout: Drawing 2311429-SKE10 – Rev 24.03.11 c) Limestone Downs Substation Layout Section 1: Drawing 2311429- SKE101 – Rev 24.03.11 d) Limestone Downs Substation Layout Section 6: Drawing 2311429- SKE106 – Rev 24.03.11 e) Layout Plan Refined Design: Drawings 1429-R520 and R521 (both Rev 24.03.11)

Single Circuit Line: a) NOR Plan 4 - Internal Transmission Line Te Akau to Matira Plan: Drawing 1429-R055 – Rev 24.03.11 b) NOR Plan 5 - Internal Transmission Line Matira to Limestone Downs: Drawing 1429-R054 – Rev 24.03.11 c) 220kV Transmission Line Single Circuit Monopole General Arrangement: Drawing 2311429-SKE-018 – Rev 24.03.11 d) 220kV Single Circuit Typical Arrangement Suspension and Strain Towers: Drawing 2311429-SKE025 – Rev 24.03.11 e) Generic Foundation Options: Poles: Drawing 2311429-SKE-019 – Rev 24.03.11 f) Generic Foundation Options: Towers: Drawing 2311232-SKE-020 – Rev 24.03.11 g) Layout Plan Refined Design: Drawings 1429-R520, R521, R523, R525, R527, R529, R530, R531, R533, R536, R539, R542, R546, R547, R550, R552, R553, R556, R559, R562, R563, R567, R569, R570, R571, and R572 (all Rev 24.03.11)

Double Circuit Line: a) NOR Plan 6 - External Transmission Line Limestone to Orton (1 of 7): Drawing 1429-R056 – Rev 24.03.11 b) NOR Plan 7 - External Transmission Line Limestone to Orton (2 of 7): Drawing 1429-R057 – Rev 24.03.11 c) NOR Plan 10 - External Transmission Line Tower Locations (3 of 7): Drawing 1429-R404 – Rev 24.03.11 d) NOR Plan 11 - External Transmission Line Tower Locations (4 of 7): Drawing 1429-R405 – Rev 24.03.11 e) NOR Plan 12/1 - External Transmission Line Tower Locations (5 of 7): Drawing 1429-R406 – Rev 24.03.11 f) NOR Plan 12/2 - External Transmission Line Tower Locations (6 of 7): Drawing 1429-R406a – Rev 24.03.11 g) NOR Plan 13 - External Transmission Line Tower Locations (7 of 7): Drawing 1429-R407 – Rev 24.03.11 h) 220kV Double Circuit Transmission Suspension and Strain Type Towers: Drawing 2311429-E301 and E302 – Rev 24.03.11 i) 220kV Double Circuit Typical Arrangement Suspension and Strain Monopoles: Drawing 2311429-SKE026 – Rev 24.03.11 j) Generic Foundation Options: Towers: Drawing 2311232-SKE-020 – Rev 24.03.11 k) Layout Plan Refined Design: Drawing 1429-R520, R521, R519, R585, R586, R587, R588, R589, R590, R591, R592, R593, R594, R595, R596, R597, R598, R599, and R601 (all Rev 24.03.11)

3 HAUĂURU MĂ RAKI WIND FARM PROJECT Conditions for Electricity Transmission Purposes Designations May 2011

Orton Switchyard: a) NOR Plan 8 - Orton Switchyard: Drawing 1429-R053 – Rev 24.03.11 b) Orton Switching Station Breaker and a Half Option Plan View Stage 1&2: Drawing 2311429-SKE13 – Rev 24.03.11 c) Orton Switching Station Breaker and a Half Option Isometric Stage 1&2: Drawing 2311429-SKE13a – Rev 24.03.11 d) Orton Switching Station Breaker and a Half Option Elevation Stage 1&2: Drawing 2311429-SKE13b – Rev 24.03.11 e) Layout Plan Refined Design: Drawing 1429-R601 – Rev 24.03.11

Grid Connection: a) NOR Plan 9 - Grid Connection: Drawing 1429-R058 – Rev 24.03.11 b) b) 220kV Double Circuit Transmission Suspension and Strain Type Towers: Drawing 2311429-E301 and E302 – Rev 24.03.11 c) Layout Plan Refined Design: Drawing 1429-R600 and R601 (both Rev 24.03.11)

1.2 In respect of the Double Circuit Line structure numbers L-064 – L-070 shall be monopoles.

2.0 Outline Plan

2.1 The requiring authority shall submit an outline plan or plans to the District Council pursuant to Section 176A of the Resource Management Act 1991 prior to commencing construction of any aspect of the designated works. In addition to any other matters that the Council can require to be included in the Outline Plan or plans in accordance with Section 176A(3)(f), the plan(s) shall incorporate the following documents (for the relevant aspects of the designations), as identified in subsequent conditions:

Substations: a) Design Details for Substation Lighting; b) Transformer Bund Design Plans; c) Oil Spill Management and Contingency Plans; d) Landscape Mitigation Plan (in respect of Matira substation only); e) Traffic Management Plans for Substation Entrances and Accesses; f) Design Plans for the Substation Entrances, Access Roads and Parking;

Orton Switchyard: a) Landscape Mitigation Plan; b) Lighting Management Plan; c) Traffic Management Plan; d) Design Plans for the Switchyard Entranceway, Access Road and Parking;

Single Circuit Line, Double Circuit Line and Grid Connection: a) Traffic Management Plans.

3.0 Height 3.1 Substation Sites and Orton Switchyard:

4 HAUĂURU MĂ RAKI WIND FARM PROJECT Conditions for Electricity Transmission Purposes Designations May 2011

The height of equipment and buildings within each of the Substation sites and the Orton Switchyard shall be as follows: a) Lighting and lightning poles - no higher than 30 metres; b) Telecommunication tower/pole - no higher than 30 metres; c) Line termination structure(s) - up to 40 metres for poles and 48 metres for towers, with maximum heights allowing for 5% tolerance above those heights as an outcome of detailed engineering design; d) Gantry – no higher than 30 metres; e) Except as otherwise provided above, no building or equipment shall be higher than 12 metres. 3.2 Single Circuit Line and Grid Connection: The height of transmission towers and monopoles shall be up to 48 metres with maximum heights allowing for 5% tolerance above that height as an outcome of detailed engineering design. 3.3 Double Circuit Line: The height of transmission towers and monopoles shall be: a) up to 48 metres; and b) a minimum of 55 metres for transmission towers L-O12, L-O13 and L-O14; with maximum heights allowing for 5% tolerance above that height as an outcome of detailed engineering design.

4.0 Resource Consents 4.1 Prior to commencement of construction works, the requiring authority shall hold all necessary resource consents from the Waikato Regional Council, and in particular earthworks consent WRC 117927.

5.0 Lighting for Substations and Orton Switchyard Substations: 5.1 The illuminance of substation site lighting installations shall not exceed 10 lux (lumens per square metre) spill (horizontal or vertical) of light at any window of an existing dwelling located on the balance of the relevant property and adjacent properties.

5.2 Prior to commencement of construction works for each substation, Design Details for Substation Lighting shall be submitted for certification by the Council Group Manager Regulatory in accordance with Condition 2.1.

Orton Switchyard: 5.3 The illuminance of the switchyard site lighting installations shall not exceed 10 lux (lumens per square metre) spill (horizontal or vertical) of light at any window of any existing dwellings located on adjacent properties.

5.4 Prior to commencement of construction works, a Lighting Management Plan shall be submitted to certification by the Waikato District Council Group Manager Regulatory in accordance with Condition 2.1. It shall include, but not

5 HAUĂURU MĂ RAKI WIND FARM PROJECT Conditions for Electricity Transmission Purposes Designations May 2011

be limited to, the design details for the switchyard lighting and any other lighting on the site.

6.0 Noise 6.1 All noise levels shall be measured in accordance with the requirements of „NZS6801:2008 „Acoustics - Measurement of Environmental Sound‟ and assessed in accordance with the requirements of „NZS6802:2008 „Acoustics – Environmental Noise‟.

6.2 Noise from construction activities shall not exceed the limits recommended in, and shall be measured and assessed in accordance with, „NZS6803:1999 Acoustics – Construction Noise‟.

Noise level for Substation sites and Orton Switchyard site: 6.3 The noise level from activities within any of the Substation sites and Orton Switchyard shall not exceed the following limits when measured within the notional boundary of any rural dwelling:

a) 50dBA (LAeq) Monday to Friday 7:00am to 7:00pm

b) 50dBA (LAeq) Saturday 7:00am to 6.00pm

c) 40dBA (LAeq) At all other times including Public Holidays

Noise levels for Single Circuit Line, Double Circuit Line and Grid Connection: 6.4 Noise from the operation of the transmission lines shall not exceed a limit of 40dBA LAeq when measured within the notional boundary of any rural dwelling.

7.0 Health & Safety EMF (Electric and Magnetic Fields) 7.1 In those areas of any Substation site, the Orton Switchyard, Single Circuit Line, Double Circuit Line or Grid Connection to which the public has access, electric and magnetic fields‟ strengths shall comply with the guidelines for public exposure to electric and magnetic fields as published in 1998 by the International Commission on Non-Ionizing Radiation Protection (ICNIRP).

7.2 Within 3 months of any Substation site, the Orton Switchyard, Single Circuit Line, Double Circuit Line or Grid Connection becoming operational, EMF levels in those areas of the site to which the public has access shall be measured to determine compliance with the guidelines for public exposure as detailed in Condition 7.1 and the results shall be forwarded to the Waikato District Council Group Manager Regulatory within 1 month of the measurements being completed.

Single Circuit Line, Double Circuit Line and Grid Connection: 7.3 Prior to commissioning the line for the Single Circuit Line, Double Circuit Line or Grid Connection the requiring authority shall ensure that an appropriately qualified person assesses all conductive structures in the vicinity of the line. As part of that assessment, a risk assessment of any hazards shall be

6 HAUĂURU MĂ RAKI WIND FARM PROJECT Conditions for Electricity Transmission Purposes Designations May 2011

undertaken and mitigation measures identified to address any significant risks relating to induction effects associated with the line. Any costs associated with implementing any necessary mitigation measures shall be borne by the requiring authority.

Electromagnetic Interference (Radio Disturbance) 7.4 All works shall be designed to comply with NZS 6869:2004 Limits & Measurement Methods of Electromagnetic Noise from High Voltage A.C. Power Systems, 015 to 1000 MHZ.

Security Fences (Substation sites and Orton Switchyard) 7.5 Security fences are to be erected around each of the Substation sites and around the Orton Switchyard platform.

Hazardous Substances (Substation sites) 7.6 The Substations shall be operated in accordance with Transpower Limited TP:GS.54.01 for Oil Spill Management. In addition, the requirements of the Hazardous Substances and New Organisms Act 1996 and Regulations shall apply to any classified hazardous substances stored or used on site.

7.7 Prior to construction of a Substation, and in accordance with TP:GS.54.01 for Oil Spill Management, a Transformer Bund Design Plan and an Oil Spill Management and Contingency Plan shall be submitted for certification by the Waikato District Council Group Manager Regulatory in accordance with Condition 2.1. The Transformer Bund Design Plan shall include, but not be limited to, the following: a) Selection of spill containment volumes based on the quantity of oil in the transformers; b) Methods of containment; c) Methods of separation; and d) Methods of stormwater and oil disposal.

8.0 Roading Traffic Management Plans 8.1 Prior to the construction activities associated with a Substation site, the Orton Switchyard, Single Circuit Line, Double Circuit Line or Grid Connection, a Traffic Management Plan relating to relevant construction works (for each aspect of the various designations) and the use of roads that will be used by construction traffic shall be prepared and submitted for certification by the Waikato District Council Group Manager Regulatory in accordance with Condition 2.1. The relevant Traffic Management Plan shall include the following matters: a) Measures to advise road users when heavy vehicle movements will occur along the road for construction purposes; b) Notification to WDC Roading Staff of the commencement and completion dates of construction works;

7 HAUĂURU MĂ RAKI WIND FARM PROJECT Conditions for Electricity Transmission Purposes Designations May 2011

c) The traffic safety measures to be put in place along the route to minimise the traffic safety risks and time delays for other motorists; d) The routing of construction traffic to the Substation site or construction site.

In respect of the Substations only:

e) in consultation with Waikato District Council, the requiring authority shall undertake inspections of relevant Council Roads before and after the transformers are delivered to a Substation. If any damage is identified in the inspection after the transformers have been delivered to a Substation, the requiring authority shall pay for the repair of road infrastructure.

Final Construction Drawings for access and parking areas for the Substations and Orton Switchyard site:

8.2 Prior to construction works at a Substation site or the Orton Switchyard, all final construction drawings of the accesses and parking areas (including drainage details), and identifying the location of any structures within Council Road reserve (being the Churchill Road reserve in the case of the Orton Switchyard), shall be prepared and submitted for certification by the Waikato District Council Group Manager Regulatory in accordance with Condition 2.1.

8.3 Prior to construction work commencing on a Substation or the Orton Switchyard, the requiring authority will construct an entranceway at the junction of: a) the substation access road and Te Akau Road (in respect of the Te Akau substation); b) the substation access road and Matira Road (in respect of the Matira substation); c) the substation access road and Road (in respect of the Limestone Downs substation); and d) the Switchyard and Churchill Road (in respect of the Orton Switchyard).

All final construction drawings of each of the entranceways shall be prepared and submitted for certification by the Waikato District Council Group Manager Regulatory in accordance with Condition 2.1.

9.0 Archaeology Sites 9.1 Earthworks and construction activities shall avoid the mapped archaeological features, buffer and cautionary zones associated with:

a) For the Te Akau Substation: archaeology site PJ:R14/192:B on Layout Plan Refined Design Drawing 1429-R572, Rev 24.03.11

b) For the Single Circuit Line: archaeology site WV:R13/60:A on Layout Plan Refined Design Drawing 1429-R536, Rev 24.03.11; archaeology site PJ:R14/177:A on Layout Plan Refined Design Drawing 1429-R570, Rev 24.03.11; and

8 HAUĂURU MĂ RAKI WIND FARM PROJECT Conditions for Electricity Transmission Purposes Designations May 2011

archaeology site and PJ:R14/184:B on Layout Plan Refined Design Drawing 1429-R571, Rev 24.03.11.

c) For the Double Circuit Line: archaeology site FR:R13/130:A on Layout Plan Refined Design Drawing 1429-R598, Rev 24.03.11.

10.0 Landscape Mitigation Matira Substation site and Orton Switchyard site 10.1 Landscape Mitigation Plans shall be prepared for the Matira Substation and the Orton Switchyard sites and submitted to the Waikato District Council within three months prior to construction of the Matira Substation or Orton Switchyard (as applicable) in accordance with Condition 2.1.

10.2 The Landscape Mitigation Plans (for each of the Matira Substation site and the Orton Switchyard site) shall include, but not be limited to, the following: a) The identification of the botanical name, common name, size at time of planting, mature height, quantities and location of all mitigation planting; b) An implementation strategy identifying when the mitigation works will be undertaken including areas that can be planted prior to construction where they will not be affected by construction activities; c) An establishment and maintenance schedule to include strategies for fertilisation, irrigation, weed and pest control; and d) All landscape areas are to be appropriately stock fenced (e.g. 7 wire post and batten fence) to prevent undergrazing.

10.3 All landscape mitigation planting for the Matira Substation and the Orton Switchyard sites shall be maintained in a satisfactory manner for the duration of the designation, provided always that the landscape planting shall not be a hazard to any structures on or connections to the substation or switchyard assets. Once a continuous row and/or canopy has been established, this maintenance shall include replanting of any gaps created by death or damage of trees, in order to allow a continuous row and/or canopy to re-establish.

Double Circuit Line and Grid Connection – Landscape Mitigation on Private Land 10.4 Three months prior to construction commencing on the Double Circuit Line or Grid Connection (as applicable) the requiring authority shall write to the owners of the following properties informing them of their entitlement to landscape mitigation:

Double Circuit Line: House # Rapid # Owner

N055 213 Nolan Road Walter N714 93 Fleming Road Lochiel Farmlands Ltd N504 1526 SH 22 Singh-Prada N721 122 Sharpe Road Lines, Care

9 HAUĂURU MĂ RAKI WIND FARM PROJECT Conditions for Electricity Transmission Purposes Designations May 2011

House # Rapid # Owner

N507 1405 SH 22 Nichol N719 1441 SH 22 Allan, Wright N720 1603 SH 22 Middleton, Macky N545 1619 SH 22 Jackson

Grid Connection: House # Rapid # Owner

N732 1173 Churchill Road Henry Farms Ltd N525 465 Otuiti Road Chapman, Hull N534 509 Otuiti Road Fitness, Glasgow N559 1113 Churchill Road Vanhoovels N560 1107 Churchill Road Kiernan N733 1127 Churchill Road Partridge

Conditions 10.6 to 10.11 of these designations shall not apply if alternative arrangements are agreed by contractual obligation between the requiring authority and property owner.

10.5 The written offer required by Condition 10.4 above shall inform landowners that they may request the requiring authority to undertake landscape mitigation prior to, or after, construction of the transmission line;

10.6 Within 2 months of construction commencing on the Double Circuit Line or the Grid Connection (as relevant), the requiring authority shall repeat the offer required by Condition 10.4 above for all landowners who have not accepted the offer. The requiring authority shall expressly state that the offer shall remain valid for 12 months following commissioning of the Double Circuit Line or Grid Connection (as relevant).

10.7 Subject to the prior written consent of the landowner/s being given, the requiring authority shall undertake landscape mitigation by means of on-site planting on those properties to mitigate the effects of the Double Circuit Line or Grid Connection (as relevant) on views from houses. The mitigation techniques shall be set out in a property specific concept plan (concept plan). The concept plan shall, where practicable, be amended in response to landowners‟ preference.

10.8 Following approval of the concept plan by the landowner, the requiring authority shall implement the concept plan at a practicable time agreed between the requiring authority and the landowner, but preferably within the first planting season following approval of the concept plan. A copy of the concept plan shall be forwarded to the Waikato District Council Group Manager Regulatory prior to the works being undertaken. Following completion of the works the requiring authority shall provide written confirmation to the Waikato District Council Group Manager Regulatory as to the timing and nature of the works.

10 HAUĂURU MĂ RAKI WIND FARM PROJECT Conditions for Electricity Transmission Purposes Designations May 2011

10.9 Subject to Condition 10.10, the requiring authority shall maintain the planting for 12 months after completion of planting.

10.10 In the event that landowners advise the requiring authority that they wish to maintain the planting themselves, the requiring authority shall pay the landowner the sum of money allocated in the cost estimate for maintenance set out in the approved concept plan.

10.11 In the event that landowners advise the requiring authority that they wish to implement the concept plan themselves, the requiring authority shall pay the landowner the sum of money allocated in the approved concept plan on the agreement that the landowner shall carry out the planting themselves. The requiring authority shall provide written notification to the Waikato District Council Group Manager Regulatory within 20 working days of advice from any landowners that wish to implement the concept plan on their own accord.

11.0 Ecology Management Double Circuit Line: 11.1 As part of the construction, operation, maintenance, renewal, replacement and upgrading of the Double Circuit Line:

a) no trees shall be trimmed or felled within the mapped areas of significant indigenous vegetation as shown on the plans in Schedule Two; and b) no earthworks shall encroach within the mapped areas of significant indigenous vegetation or associated buffer zones as shown on the plans in Schedule Two;

with the following exceptions:

Earthworks relating to construction of transmission assets for the Double Circuit Line:

- L-O 09 – tower to encroach within buffer; - L-O 12 – tower to encroach within buffer; - L-O 13 – tower to be constructed within vegetation; - L-O 14 – tower to be constructed partly within vegetation and partly within buffer; - L-O 40 – tower may encroach within buffer; - L-O 80 – tower to encroach within buffer

Trimming/felling for electrical conductor clearance – construction:

- Span L-O 13 to L-O 14 – notwithstanding the transmission tower height specified in condition 3.3b) some trimming of vegetation may be necessary in order to ensure compliance with electrical safety clearance requirements; - Spans L-O 39 to L-O 41 – some trimming/felling may be necessary in order to ensure compliance with electrical safety clearance requirements; - Any trimming shall be undertaken by a suitably trained and qualified arborist and the trees shall be individually trimmed to ensure that the integrity of the tree structure is not compromised.

11 HAUĂURU MĂ RAKI WIND FARM PROJECT Conditions for Electricity Transmission Purposes Designations May 2011

Trimming/felling for electrical conductor clearance – may be necessary in future for maintenance:

- Spans L-O 08 to L-O 15; - Spans L-O 39 to L-O 41.

11.2 In respect of spans L-O 08 to L-O 15 and L-O 39 to L-O 41, the indigenous vegetation shall be visually assessed by an appropriately qualified ecologist every 30 months (at the longest) to determine its health and the risk of trees falling so as to not compromise the transmission line. No indigenous vegetation shall be felled or trimmed in those spans unless it has been so identified as presenting a risk to the transmission line and/or compliance with electrical safety clearance requirements. A representative sample of individuals of the main indigenous tree species in those spans shall be tagged by GPS and their height re-measured every 5 years (at the longest) to ascertain growth rates. Any trimming shall be undertaken by a suitably trained and qualified arborist and the trees shall be individually trimmed to ensure that the integrity of the tree structure is not compromised.

11.3 No tree trimming or felling, with the exception of trimming or felling where there is a risk of trees falling so as to compromise the safe operation of the transmission line (addressed above), shall occur between the months of November and January inclusive so as to avoid the maternity period for long- tailed bats.

11.4 No potential bat roost trees shall be trimmed or felled during the long – tailed bat hibernation period of May to September inclusive with the exception of trimming or felling where there is a risk of trees falling so as to compromise the safe operation of the transmission line.

11.5 The overall construction footprint for the structures in or adjacent to Te Umukaraka Bush shall be limited to the following areas:

- L-O 09 – 13.3m by 13.3m; - L-O 12 – 13.3m by 13.3m; - L-O 13 – 15m by 15m; and - L-O 14 – 15m by 15m.

11.6 Earthworks, concrete, and fill volumes for the construction of structures in or adjacent to Te Umukaraka Bush shall be limited as follows:

Structure Excavation Spoil Volume Concrete Hardfill Volume Volume L-O 09 75m³ 75m³ 75m³ - L-O 12 75m³ 75m³ 75m³ - L-O 13 150m³ 125m³ 25m³ 40m³ L-O 14 110m³ 85m³ 25m³ 40m³

11.7 Access to structures within or adjacent to Te Umukaraka Bush, including L-O 13 or L-O 14, for construction and maintenance shall be limited to helicopter or by foot using existing tracks.

12 HAUĂURU MĂ RAKI WIND FARM PROJECT Conditions for Electricity Transmission Purposes Designations May 2011

11.8 In order to avoid disturbance on long-tailed bats using the maternity roost tree identified close to the site of transmission tower L-O 12, no activities shall occur in association with the construction of transmission tower L-O 12 within 50m of the bat roost tree between the calendar months of November to January inclusive.

11.9 No construction activities associated with the Double Circuit Line within 100 metres of the edge of the Punga Punga Wetland shall be undertaken in the period 1 September to 31 January so as to avoid disturbance to nesting Australasian Bitterns. Fencing proposed for Te Umukaraka Bush shall be undertaken at cost to the consent holder.

Advice Note: The Biodiversity and Remediation Enhancement Scheme contained in Schedule One, conditions 6.34 to 6.41 to the district council conditions for the associated Hauāuru mā Raki wind farm (resource consent numbers L08052, L08053, L08054, L08055, L08056 LUC0005/08, LUC0005/08.01, and LUC0005/08.02) provides a comprehensive scheme that covers biodiversity mitigation and offsets for both the wind farm, as well as the designated works for the Double Circuit transmission line. Upon commencing construction of works for the Double Circuit Line (the Main Transmission Line) the district council conditions for the wind farm (in particular Schedule One Condition 6.34A) require that the consent holder commence implementation and funding of the measures specified within the Te Umukaraka Bush and Punga Punga Wetland Protection and Enhancement projects within the Biodiversity Remediation and Enhancement Scheme (Figures 2 and 8) attached to the district council conditions as part of Schedule Six, these both being projects that are designed to offset effects of the designated works.

Grid Connection:

11.10 As part of the construction, operation, maintenance, renewal, replacement and upgrading of the transmission line associated with the Grid Connection:

a) no trees shall be trimmed or felled within the mapped areas of significant indigenous vegetation as shown on the plans in Schedule Two; and b) no earthworks shall encroach within the mapped areas of significant indigenous vegetation or associated buffer zones as shown on the plans in Schedule Two;

with the following exceptions:

Earthworks relating to construction of transmission assets:

- DEV-B 1 – tower may encroach within vegetation or buffer; - DEV-B 2 – tower may encroach within vegetation or buffer; - DEV-B 3 – tower to be constructed within vegetation;

Bird Diverters for Single Circuit Line, Double Circuit Line and Grid Connection: 11.11 At locations where the transmission line associated with the Single Circuit Line, Double Circuit Line or Grid Connection, crosses areas or is within 200

13 HAUĂURU MĂ RAKI WIND FARM PROJECT Conditions for Electricity Transmission Purposes Designations May 2011

metres of stands of native bush / forest, and the Kaawa, Waimarama, Opuatia, Waikaretu, Matira, Waikorea and Waimai Streams and Punga Punga Wetland, it shall be marked with bird diverter devices as recommended by an appropriately qualified ecologist.

12.0 Aviation Single Circuit Line, Double Circuit Line and Grid Connection:

12.1 The requiring authority shall, on a monthly basis during the construction of the transmission line (associated with the Single Circuit Line, Double Circuit Line or Grid Connection), inform the New Zealand Agricultural Aviation Association and the Civil Aviation Authority of the construction activities completed in the previous month, and intended to be undertaken in the following month including:

(a) erection of specific towers or poles (with locations and heights); (b) stringing of conductor and earthwires between specified towers or poles; and (c) whether helicopters will be being used during construction.

For the avoidance of doubt, the requirement applies to each tower or pole and stringing of each tower or pole, not merely the commencement of tower or pole erection or stringing.

12.2 The requiring authority shall be responsible for any actual and reasonable additional costs borne by any landowners and their successors in title whose existing (at the date on which the designation is included in the District Plan pursuant to section 184 (1)) normal aerial agricultural operations are adversely affected by the transmission lines associated with the Single Circuit Line, Double Circuit Line or Grid Connection, in terms of increased aircraft time, fuel costs and/or the need for alternative application. Actual and reasonable additional costs will be determined by an independent expert assessment, appointed and paid for by the requiring authority.

Double Circuit Line: 12.3 The requiring authority shall provide, administer and maintain an all weather hard surface airstrip in the Orton area for the use of those landowners and successors in title whose properties are located east of State Highway 22 and whose existing (as at the date on which it is included in the District Plan pursuant to section 184 (1)) normal aerial agricultural operations are affected by the Double Circuit Line. This will include providing, at the requiring authority's cost, weathertight fertiliser storage areas and equipment storage areas, and working areas for the number of landowners who use the airstrip, of a similar nature, similar or better standard, and similar scale to the landowners‟ existing facilities. The requiring authority shall ensure that a nominated employee or contractor is responsible for scheduling the use of the airstrip and fertiliser storage areas in an efficient and equitable manner and keeping it maintained to a standard appropriate for use for aerial topdressing aircraft.

14 HAUĂURU MĂ RAKI WIND FARM PROJECT Conditions for Electricity Transmission Purposes Designations May 2011

13.0 Waikaretu Limestone Quarry Single Circuit Line: 13. 1 The requiring authority shall install non-ceramic insulators to the transmission structures L-M 27 to L-M 31 or such replacement structures which run adjacent to Ravensdown's operating quarry at Waikaretu (“Ravensdown Quarry”).

13.2 When selecting the final location of the transmission structures indicatively marked L-M 27 to L-M 31, the requiring authority shall consult with Ravensdown and shall, as far as reasonably practicable, subject to engineering constraints, select a route (and associated easement) for the Single Circuit Line that passes (within the designated corridor):

(a) to the east of the current Ravensdown Quarry face (as marked A-B in the plan annexed as Schedule Three), if the Ravensdown Quarry is in operation at the time the Single Circuit Line is constructed; and (b) to the west of the limestone outcrop to the north of the Ravensdown Quarry (as marked X-Y in the plan annexed as Schedule Three).

In the event that reasonable practicability and engineering constraints preclude pole placement and easement along the lines X-Y and A-B, as the case may be, then Contact shall in consultation with Ravensdown select an alternative route within the Corridor so as to maximise, as far as practical, the separation distances between the existing and proposed Ravensdown Quarry and the transmission line placement.

14.0 Lapsing and Milestone Obligations Substations, Orton Switchyard, Single Circuit Line, Double Circuit Line and Grid Connection: 14.1 The designations for the Substations, Orton Switchyard, Single Circuit Line, Double Circuit Line and Grid Connection shall lapse 10 years after the date on which this consent commences and the designation is confirmed.

Milestone Obligations for the Single Circuit Line, Double Circuit Line and Grid Connection:

14.2 The requiring authority shall, within 3 months after the date on which the designations are included in the District Plan pursuant to Section 184(1), advise transmission line landowners (excluding those who have provided written approval) of their ability to request within a 3 month period, refinement of the transmission corridor across their land (if they have not already done so).

14.3 If the requiring authority receives such a request in writing from any transmission line landowner and subject to their granting reasonable access, it shall undertake detailed design investigations in consultation with the landowner within 12 months of reasonable access being permitted. The design shall be sufficient to narrow the transmission line corridor width across the property or properties concerned to 60 metres, and provide specific tower locations to within a radius of 20 metres.

15 HAUĂURU MĂ RAKI WIND FARM PROJECT Conditions for Electricity Transmission Purposes Designations May 2011

14.4 In the event that a transmission line landowner does not request refinement of the transmission corridor under condition 14.3 and/or grant reasonable access, then the requiring authority shall within 12 months either: a) apply to the District Court for an order granting access; or b) complete its investigation utilising geo-spatial and/or other techniques;

to narrow the applicable designation to 60 metres.

14.5 Within 6 months of completing refinement of the transmission corridor, the requiring authority shall uplift the designation outside the 60 metre corridor in accordance with section 182.

Lapse of designation 14.6 Notwithstanding Section 184 of the Act, or any other term or condition of this designation, the designation shall lapse on the subject property, on the expiry of 5 years after the date it is included in the Plan, unless in respect of any particular land the subject of the designation:

a) Contact has obtained an interest in that land, subject to the designation, sufficient for undertaking the work; or

b) The Minister of Lands has agreed to acquire or take that land (or acquire or take an interest in the land sufficient for undertaking the work) the subject of the designation under Part 2 of the Public Works Act.

14.7 The designations for the Substations, Orton Switchyard, Single Circuit Line, Double Circuit Line and Grid Connection shall lapse 10 years after the date on which this consent commences and the designation is confirmed.

14.8 Within 6 months of completion of construction the requiring authority shall uplift a designation over any land beyond any final easement area in accordance with Section 182.

Advice Note:

The easement width required for 90% of the spans will be approximately 37 metres.

15.0 Decommissioning 15.1 If a Substation, the Orton Switchyard, Single Circuit Line, Double Circuit Line or Grid Connection ceases operation for a continuous period of more than 24 months, or for any other reason determined by the requiring authority, the Substation, the Orton Switchyard, Single Circuit Line, Double Circuit Line or Grid Connection shall be decommissioned. This condition does not require the removal of sub-surface components, or the removal of roads. The requiring authority shall provide written notice to the Waikato District Council Group Manager Regulatory within 3 months of completion that all decommissioning works have been completed for a particular aspect of the designations.

16 HAUĂURU MĂ RAKI WIND FARM PROJECT Conditions for Electricity Transmission Purposes Designations May 2011

16.0 Recovery of Costs 16.1 Pursuant to Section 36 of the Resource Management Act 1991, the actual and reasonable costs incurred by Waikato District Council in monitoring conditions of these designations shall be paid by the requiring authority.

17

HAUĂURU MĂ RAKI WIND FARM PROJECT Conditions for Electricity Transmission Purposes Designations May 2011

Schedule One Landowner Schedule

18 HMR WWF Notices of Requirement Landowner Schedule

Waikato District Notices of Requirement v0.6 12/6/08

Ref Legal Description Title References Landowners Property Address Postal Address

Te Akau Substation - E2674100, N6390900 Mackrell; Bruce Wylie Te Akau South Road Peter & Pru Jackson Rishworth; David Hugh Te Akau 1215 Te Akau Road 1 Part Section 28 Block VI Whaingaroa SD SA1033/12 Jackson; Peter Alexander Hughlings RD1 RD1 Jackson; Prudence Mary Sladden Ngaruawahia Ngaruawahia

220kV SINGLE CIRCUIT LINE

Part Section 28 Block VI Whaingaroa SD SA1033/12 Mackrell; Bruce Wylie Lot 2 DP 304868, Part Section 8 and Section 25 Block VI Te Akau Road Peter and Pru Jackson 19310 Rishworth; David Hugh Whaingaroa SD Te Akau 1215 Te Akau Road 1 Jackson; Peter Alexander Hughlings RD1 RD1 Part Section 2 Block II Whaingaroa SD SA47D/437 Jackson; Prudence Mary Sladden Part Section 11 and Section 12 Block II Whaingaroa SD, Lot 4 DP Ngaruawahia Ngaruawahia 189865 346210

Lots 1 - 2 DPS 3808 SA27A/1144 C/- John Glenn Lot 1 DPS 52647 SA47D/435 1245 Waimai Valley Road RD2 Te Akau B2B Block, Lots 2 - 3 DPS 52647 SA47D/436 Glenn; Andrew McKinley Waimai Valley Road Ngaruawahia Glenn; John James 2 RD2 Glenn; Virginia Jill Ngaruawahia Andrew & Virginia Glenn Crawford; Michael Wayne Te Akau B7A Block SA1798/59 1057 Waimai Valley Road RD2 Ngaruawahia

Private Bag 544 3 Legal Road Waikato District Council Waimai Valley Road Ngaruawahia

C/- John Glenn 1245 Waimai Valley Road RD2 Waimai Valley Road Ngaruawahia 2 Section 3 Block II Whaingaroa SD SA935/40 Rukuhia Holdings Limited RD2 Ngaruawahia Andrew & Virginia Glenn 1057 Waimai Valley Road RD2 Ngaruawahia

Lot 1 DPS 8417 SA2B/213 Horsley; Campbell Robert Woodward C/- Robert Horsley Waikorea Valley Road Horsley; Rosemary Ann 462 Waikorea Valley Road 4 RD2 Jackson; Peter Alexander Hughling RD2 Lot 1 DPS 27901 SA26A/1074 Ngaruawahia Norris Ward Trustee Company Ltd Ngaruawahia

Part Te Akau B7B Block SA26A/1075 C/- Robert Horsley Horsley; Campbell Robert Woodward Waikorea Valley Road 462 Waikorea Valley Road 4 Horsley; Rosemary Ann RD2 RD2 Section 8 Block II Whaingaroa SD SA1709/49 Ellice Tanner Trustees No. 2 Ltd Ngaruawahia Ngaruawahia

Private Bag 544 5 Legal Road Waikato District Council Waikorea Valley Road Ngaruawahia

Te Akau B12J Block SA272/26 Matira Road C/- Steve Parrott Parrott; Steven John Matira Matira Extension Road 6 Lot 2 DP 33978 SA900/85 Parrott; Alexander Bruce RD2 RD2 Ngaruawahia Ngaruawahia

Sections 15 - 16 Block XIII Awaroa SD SA29A/46 C/- Richard & Joanne Matira Road Kuegler Matira 7 Matira Limited 369 Matira Road RD2 Part Te Akau B15B1 Block SA293/258 RD2 Ngaruawahia Ngaruawahia

Part Lot 1 DP 33978, Part Section 1 Block XIII Awaroa SD SA900/84 274 Matira Road 8 Eastside Farming Limited Matira Road RD2 Sections 4 - 14 Block XIII Awaroa SD SA8C/216 Ngaruawahia

Private Bag 544 9 Legal Road Waikato District Council Matira Road Ngaruawahia

Matira Substation - E2670240, N6399740 C/- Richard & Joanne Matira Road Kuegler Matira 7 Part Te Akau B15B1 Block SA293/258 Matira Limited 369 Matira Road RD2 RD2 Ngaruawahia Ngaruawahia HMR WWF Notices of Requirement Landowner Schedule

Franklin District Notices of Requirement v0.15 17/6/08

Ref Legal Description Title References Landowners Property Address Postal Address

220kV SINGLE CIRCUIT LINE

Matira Road C/- Richard Kuegler Matira 369 Matira Road 1 Te Akau B15B2A2A Block SA1495/2 Matira Limited RD2 RD2 Ngaruawahia Ngaruawahia

C/- Edwin Marshall Maori Owners - Pukerewa A Block - 195 69 Norrie Street owners listed on MLOL. Vested in a Melville Trust SA27D/1311 Pukerewa Road Hamilton (Marshall; Edwin 2 Pukerewa A Block and Maori Land Court RD5 Whare; Ken Title C/-Matthew Preston Simon; Matthew Lester C/- District Court Whare; Minarapa Rihaere Private Bag 2 Whare; Tokotakahi shown on CFR) Papakura

C/- Mina Whare Pukerewa Road RD2 Whare; Eruera Hara Te Waikaretu Valley Road Tuakau 3 Te Akau B15B2C1C Block SA6D/442 Whare; Hariata Kahuti Toko RD5 Whare; Mina (alias) Tuakau C/- Eru Whare 8 Old Taupiri Road Ngaruawahia

C/- Mina Whare 706 Pukerewa Road Whare; Minarapa Toko Pukerewa Road 4 Part Te Akau B15B2C1A Block 167705 RD5 Franklin Law Trustee Limited RD2 Tuakau Tuakau

Private Bag 5 5 Legal Road Council Waikorea Valley Road

Lot 2 DP 370414 285416 C/- David Whitford Waikaretu Valley Road 2483 Port Waikato - 6 D J Whitford Limited RD5 Waikaretu Road Lot 2 DP 310365 40710 Tuakau RD5 Tuakau

Lot 2 DP 384874, Lot 1 DPS 5551 340723 C/- Bruce Robinson Kokonga East Road Part Section 6 Block 1X Awaroa SD SA10D/164 P O Box 28444 7 Kokonga Farms Limited RD5 Remuera Tuakau Section 4 Block IX Awaroa SD SA5B/1402

Private Bag 5 8 Legal Road Franklin District Council Kokonga East Road Pukekohe

Port Waikato - Waikaretu Quarry Reserve Road Private Bag 5 9 Section 10 Blk IX Awaroa SD NZ Gazette 1955 page Franklin District Council RD5 Pukekohe 1041 Tuakau

Port Waikato - Waikaretu Lot 2 DPS 29367 SA26D/1159 Deane; Kerry Anthony C/- P O Box 28800 Road 10 Deane; Mark Peter Remuera RD5 Part Lot 1 DPS 29366 SA26D/1158 Deane; Christopher Gary Auckland Tuakau

Private Bag 5 11 Legal Road Franklin District Council Baker Road Pukekohe

Private Bag 5 12 Legal Road (unformed) Franklin District Council Pukekohe

Lot 5 DPS 11657 387049 C/- Chris Horton ABN AMRO P O Box 1196 Port Waikato - Waikaretu Auckland Road 13 Part Sections 11 and 12 and Section 16 Block II Coast Survey The C. Alma Baker Trust RD5 District, Part Sections 11 and 12 and Sections 4, 13, 15, 19 and SA46C/98 C/- Kevin Lowe Tuakau 20 Block V Awaroa SD, Part Te Akau B24 Block Dresden Securities Private Bag 92142 Auckland

Limestone Downs Substation - E2668160, N6412220 C/- Chris Horton ABN AMRO P O Box 1196 Port Waikato - Waikaretu Auckland Road 13 Section 4 Block V Awaroa SD, Part Te Akau B24 Block SA46C/98 The C. Alma Baker Trust RD5 C/- Kevin Lowe Tuakau Dresden Securities Private Bag 92142 Auckland 220 kV DOUBLE CIRCUIT LINE

Part Sections 11 and 12 and Section 16 Block II Coast Survey District, Part Sections 11 and 12 and Sections 4, 13, 15, 19 and SA46C/98 20 Block V Awaroa SD, Part Te Akau B24 Block C/- Chris Horton ABN AMRO Lot 5 DPS 11657 SA408/77 P O Box 1196 Port Waikato - Waikaretu Auckland Part Te Akau A13B Block SA215/184 Road 13 The C. Alma Baker Trust RD5 C/- Kevin Lowe Tuakau Dresden Securities Private Bag 92142 Part Te Akau A11 Block SA469/294 Auckland

Baker Road Grey; Eric Joseph 2/40 Cook Street 14 Section 114 Whangape Parish SA704/171 RD5 Grey; Valerie Winifred Howick 1705 Tuakau

Walter; David Millias 241 Nolan Road 241 Nolan Road 15 Section 4 Block II Awaroa SD SA49A/264 Walter; Pamela Stewart RD2 RD2 Ferguson; Peter Jock Tuakau Tuakau

Sections 5, 6 Block II Awaroa SD SA49C/269 Wairamarama Road C/- Graham Harford 16 Part Allotment 98B Whangape Parish SA374/257 Bramwell Farms Limited RD2 P O Box 106347 Part Allotment 110 Whangape Parish SA285/99 Tuakau Auckland

Waimarama Private Bag 5 17 Legal Road Franklin District Council Road Pukekohe

C/- Gary Rasmussen Wairamarama Road 250 Ness Valley Road 18 Part Allotment 101 and Allotment 102 Whangape Parish SA1B/605 Matairoa Limited RD2 RD5 Tuakau Papakura 1750

C/- Gavin & Jan Ball 1047 Wairamarama Road 1047 Wairamarama Road 19 Allotments 197, 198 Whangape Parish SA17B/1432 Gavin Ball Farms Limited RD2 RD2 Tuakau Tuakau

Opuatia 5C2A Block SA294/55 C/- Stuart & Thomas Orton Wairamarama Road Opuatia 5C2B Block SA294/54 Wairamarama Road 20 H D Orton Limited RD2 RD2 Tuakau Part Opuatia 4 No. 48 Block SA319/291 Tuakau

Private Bag 5 21 Legal Road (unformed) Franklin District Council Pukekohe

C/- Peter Mandeno Mandeno; Peter Woodward Allen and Eyre Road 252 Clevedon Kawakawa 22 Part Opuatia 4 Block SA2D/262 Mandeno; Thomas Graham RD2 Road Munn; Dennis James Tuakau Clevedon Papakura

Allen and Eyre Road Private Bag 3072 23 Marginal Strip under Part IVA Conservation Act 1987 N/A Department of Conservation RD2 Hamilton Tuakau

Assuming stream is non-navigable, the Allen and Eyre Road 24 Stream bed N/A adjacent owners will have a prescriptive RD2 right of ownership to the centreline Tuakau

C/- Michael Friedlander State Highway 22 3/203 Remuera Road 25 Section 23 Block XVI Onewhero SD SA50D/661 Lochiel Farmlands Limited Remuera Pukekohe Auckland

201 Brewster Road 201 Brewster Road Yearbury; Maurice Keith Pukekawa 26 Section 11 Block XVI Onewhero SD SA1103/125 Pukekawa Yearbury; Barbara Anne RD1 Pukekohe Pukekohe

Part Sections 5, 6 Block XVI Onewhero SD SA47A/118 1380A State Highway 22 1380A State Highway 22 27 Hickey; William Norman Pukekawa Pukekawa Section 16 Block XVI Onewhero SD SA5A/119 Pukekohe Pukekohe

P O Box 1459 28 Legal Road Transit New Zealand State Highway 22 Auckland Lot 3 DPS 40364 SA35D/346 1441 State Highway 2 C/- 9B Aldred Road Allan; Eric Bernard 29 Pukekawa Remuera Wright; Elizabeth Ann Lot 4 DPS 40364 SA35D/347 Pukekohe Auckland

1603 State Highway 22 1603 State Highway 22 Middleton; Bruce 30 Lot 5 DPS 40364 SA35D/348 Pukekawa Pukekawa Macky Trustee Company Limited Pukekohe Pukekohe

Markham; Stephen Richard State Highway 22 1319 State Highway 22 31 Lot 2 DPS 40362 SA35D/345 Markham; Janet Elizabeth Pukekawa RD1 Rumball; Robert Edgar Pukekohe Pukekohe

122 Sharpe Road 122 Sharpe Road Lines; Judith Anne 32 Lot 1 DP 13393 SA28C/856 Pukekawa Pukekawa Care; Andrew Alan Pukekohe Pukekohe

Sharpe Road 59A Lucerne Road 33 Lot 3 DPS 40447 SA35D/34 Cameron; Donald George Pukekawa Remuera Pukekohe Auckland 1005

McConnell; Nancy Anne 161 Otuiti Road 161 Otuiti Road 34 Lot 3 DP 315829 and Section 5 Block XIII Maramarua SD 62142 Hansen; Martin Frode Pukekawa Pukekawa Wadams; Allan John Manu Pukekohe Pukekohe

Section 6 Block XIII Maramarua SD SA650/80 401 Otuiti Road 401 Otuiti Road Hewitt; Matthew Arnold Pukekawa Pukekawa 35 Part Lot 7 DP 24536 SA46C/897 Hewitt; Ethne Anne RD1 RD1 Tuakau Tuakau

Orton Switchyard Otuiti Road 401 Otuiti Road Hewitt; Matthew Arnold Pukekawa Pukekawa 35 Part Lot 7 DP 24536 SA46C/897 Hewitt; Ethne Anne RD1 RD1 Tuakau Tuakau

Grid Connection Point Otuiti Road 401 Otuiti Road Hewitt; Matthew Arnold Pukekawa Pukekawa 35 Part Lot 7 DP 24536 SA46C/897 Hewitt; Ethne Anne RD1 RD1 Tuakau Tuakau

Partridge; Joseph Christopher 1127 Churchill Road 36 Part Lot 7 DP 24536 SA1766/50 Partridge; Linda Myrtle Orton

1173 Churchill Road 1173 Churchill Road 37 Part Lot 6 DP 24536 SA24D/635 Henry Farms Limited R D 5 Orton Tuakau

Churchill Road Private Bag 5 38 Legal Road Franklin District Council Orton Pukekohe

1162 Churchill Road McLanachan; Robert John 1162 Churchill Road 39 Lot 1 DP 377068 309741 Pukekawa McLanachan; Riki James Orton Pukekohe

525 Otuiti Road 525 Otuiti Road 40 Lot 4 DPS 51711 SA44A/474 Coussons; Michelle Wendy R D 1 Orton Tuakau

509 Otuiti Road Glasgow; Neville Thomas 509 Otuiti Road 41 Lot 1 DPS 51711 SA44A/471 R D 1 Fitness; Judith Ann Orton Tuakau

Otuiti Road Private Bag 5 42 Legal Road Franklin District Council Orton Pukekohe

211 Logan Road Wootton; Bryce Keith Otuiti Road 43 Lot 9 DP 24536 SA56B/441 R D 1 Wootton; Michell Ann Orton Tuakau HAUĂURU MĂ RAKI WIND FARM PROJECT Conditions for Electricity Transmission Purposes Designations May 2011

Schedule Two Plans

19 HAUĂURU MĂ RAKI WIND FARM PROJECT Conditions for Electricity Transmission Purposes Designations May 2011

Te Akau Substation: a) NOR Plan 1 - Te Akau Substation Site: Drawing 1429-R050 – Rev 24.03.11 b) Te Akau Substation Layout: Drawing 2311429-SKE08 – Rev 24.03.11 c) Te Akau Substation Layout Section 1: Drawing 2311429-SKE08a – Rev 24.03.11 d) Te Akau Substation Layout Section 2: Drawing 2311429-SKE08b – Rev 24.03.11 e) Layout Plan Refined Design: Drawing 1429-R572 – Rev 24.03.11

Matira Substation: a) NOR Plan 2 - Matira Substation: Drawing 1429-R051 – Rev 24.03.11 b) Matira Substation Layout: Drawing 2311429-SKE09 – Rev 24.03.11 c) Matira Substation Layout Section 1: Drawing 2311429-SKE092 – Rev 24.03.11 d) Matira Substation Layout Section 2: Drawing 2311429-SKE093 – Rev 24.03.11 e) Layout Plan Refined Design: Drawing 1429-R550 – Rev 24.03.11

Limestone Downs Substation: a) NOR Plan 3 - Limestone Downs Substation: Drawing 1429-R052 – Rev 24.03.11 b) Limestone Downs Substation Layout: Drawing 2311429-SKE10 – Rev 24.03.11 c) Limestone Downs Substation Layout Section 1: Drawing 2311429- SKE101 – Rev 24.03.11 d) Limestone Downs Substation Layout Section 6: Drawing 2311429- SKE106 – Rev 24.03.11 e) Layout Plan Refined Design: Drawings 1429-R520 and R521 (both Rev 24.03.11)

Single Circuit Line: a) NOR Plan 4 - Internal Transmission Line Te Akau to Matira Drawing 1429-R055 – Rev 24.03.11 b) NOR Plan 5 - Internal Transmission Line Matira to Limestone Downs Drawing 1429-R054 – Rev 24.03.11 d) 220kV Transmission Line Single Circuit Monopole General Arrangement: Drawing 2311429-SKE-018 – Rev 24.03.11 e) 220kV Single Circuit Typical Arrangement Suspension and Strain Towers: Drawing 2311429-SKE025 – Rev 24.03.11 f) Generic Foundation Options: Poles: Drawing 2311429-SKE-019 – Rev 24.03.11 g) Generic Foundation Options: Towers: Drawing 2311232-SKE-020 – Rev 24.03.11 h) Layout Plan Refined Design: Drawings 1429-R520, R521, R523, R525, R527, R529, R530, R531, R533, R536, R539, R542, R546, R547, R550, R552, R553, R556, R559, R562, R563, R567, R569, R570, R571, and R572 (all Rev 24.03.11)

20 HAUĂURU MĂ RAKI WIND FARM PROJECT Conditions for Electricity Transmission Purposes Designations May 2011

Double Circuit Line: a) NOR Plan 6 - External Transmission Line Limestone to Orton (1 of 7): Drawing 1429-R056 – Rev 24.03.11 b) NOR Plan 7 - External Transmission Line Limestone to Orton (2 of 7): Drawing 1429-R057 – Rev 24.03.11 c) NOR Plan 10 - External Transmission Line Tower Locations (3 of 7): Drawing 1429-R404 – Rev 24.03.11 d) NOR Plan 11 - External Transmission Line Tower Locations (4 of 7): Drawing 1429-R405 – Rev 24.03.11 e) NOR Plan 12/1 - External Transmission Line Tower Locations (5 of 7): Drawing 1429-R406 – Rev 24.03.11 f) NOR Plan 12/2 - External Transmission Line Tower Locations (6 of 7): Drawing 1429-R406a – Rev 24.03.11 g) NOR Plan 13 - External Transmission Line Tower Locations (7 of 7): Drawing 1429-R407 – Rev 24.03.11 h) 220kV Transmission Line Single Circuit Monopole General Arrangement: Drawing 2311429-SKE-018 – Rev 24.03.11 i) 220kV Double Circuit Transmission Suspension and Strain Type Towers: Drawing 2311429-E301 and E302 (both Rev 24.03.11) j) 220kV Double Circuit Typical Arrangement Suspension and Strain Monopoles: Drawing 2311429-SKE026 – Rev 24.03.11 k) Generic Foundation Options: Towers: Drawing 2311232-SKE-020 – Rev 24.03.11 l) Layout Plan Refined Design: Drawing 1429-R520, R521, R519, R585, R586, R587, R588, R589, R590, R591, R592, R593, R594, R595, R596, R597, R598, R599, and R601 (all Rev 24.03.11)

Orton Switchyard: a) NOR Plan 8 - Orton Switchyard Site: Drawing 1429-R053 – Rev 24.03.11 b) Orton Switching Station Breaker and a Half Option Plan View Stage 1&2: Drawing 2311429-SKE13 – Rev 24.03.11 c) Orton Switching Station Breaker and a Half Option Isometric Stage 1&2: Drawing 2311429-SKE13a – Rev 24.03.11 d) Orton Switching Station Breaker and a Half Option Elevation Stage 1&2: Drawing 2311429-SKE13b – Rev 24.03.11 e) Layout Plan Refined Design: Drawing 1429-R601 – Rev 24.03.11

Grid Connection: a) NOR Plan 9 - Grid Connection: Drawing 1429-R058 – Rev 24.03.11 b) 220kV Double Circuit Transmission Suspension and Strain Type Towers: Drawing 2311429-E301 and E302 – Rev 24.03.11 c) Layout Plan Refined Design: Drawing 1429-R600 and R601 (both Rev 24.03.11)

21 HAUĂURU MĂ RAKI WIND FARM PROJECT Conditions for Electricity Transmission Purposes Designations May 2011

Schedule Three Waikaretu Limestone Quarry Plans

22