ENVIRONMENTAL MANAGEMENT PLAN FOR CLUSTERMINES

For

SREE MINING & MINERALS MEDIPENTLA BARYTES MINE

Production : BARYTES-7881TPA Land Details : Govt. Land Extent : 8.00 Ha. Sy.No. : 972/2 (Old Sy.No 721/4) Village : Medipentla Mandal : Vemula District : State

& ADJOINING QUARRY LEASE AREAS

Lea se Name Extent- Ha Sta tus Det ai ls of lea se ar eas Pro duc tion [TPA] Sy.No.721/2,1/P, and 692 of of Medipentla Village, Sri Y.S Venkat Reddy 28.037 Existing 1512 –Barytes Vemula Mandal, Y.S.R District. Sy.No. 1/12 of T.V.Palli Non Sri.Azmthulah 9.413 Village, Vempalli Mandal, Non working working Y.S.R. District Sy.No. 275 of Gondipalli Non M/s K.A.B (P) Ltd 285.48 Village, Vemula Mandal, Non Working Working Y.S.R. District

PREPARED FOR

M/S SREE MINING & MINERALS, MG. PARTNER: SRI D.VIJAYA KUMAR REDDY H.NO.1/17A, BOGUDUPALLI VILLAGE & POST MANDAL Y.S.R. TELEPHONE : 08985899998

INDEX

S. NO Contents 1 INTRODUCTION 2 DETAILSABOUT THEPROPOSED QUARRY SITE 3 MINING ACTIVITY ENVIRONMENTAL 4 MANAGEMENTPLAN[CLUSTER] FIGURE-1 LOCATION MAP FIGURE-2 GOOGLE IMAGE SHOWING LEASE SKETCH FIGURE-3 TOPOGRAPHICAL MAP-10 KM RADIUS FIGURE-4 CLUSTER MAP SHOWING ADJOINING LEASES

1.0 INTRODUCTION 1.1 Introduction M/s Sree Mining & Minerals, Mg. Partner: Sri. D. Vijaya Kumar Reddy, has filed an application for QL for Barytes in Sy.No.972/2 (Old Sy.No.721/4) of Meedipentla Village, Vemula Mandal, Y.S.R. Kadapa District, Andhra Pradesh State over an extent of 8.00 Hect to the Assistant Director of Mines & Geology, on 07-06-2016. The Assistant Director of Mines & Geology, Yerraguntla submitted proposals recommending for grant of Quarry lease for Barytes over an extent of 8.00 Hect in Sy.No.972/2 (Old Sy.No.721/4) of Meedipentla Village, Vemula Mandal, Y.S.R. Kadapa District, Andhra Pradesh State in favour of M/s Sree Mining & Minerals, Mg. Partner: Sri. D. Vijaya Kumar Reddy. After careful examination of the proposals of the Assistant Director of Mines & Geology, Yerraguntla it is decided in principle to grant a Quarry lease for Barytes over an extent of 8.00 Hect in Sy.No.972/2 (Old Sy.No.721/4) of Meedipentla Village, Vemula Mandal, Y.S.R. Kadapa District, Andhra Pradesh State in favour of M/s Sree Mining & Minerals, Mg. Partner: Sri. D. Vijaya Kumar Reddy The salient features of the project are given below Salient features of the project

Project Name Medipentla Barytes mine of M/s. Sree Mining and Minerals Mining Lease Area 8.000 Ha. Location of mine Sy.Nos.972/2 of Medipentla Village, Vemula Mandal, Kadapa Dist, AndhraPradesh. Minerals of mine Barytes Mining Proposed Barytes- 7881 Tonns/annum production of mine Method of mining Under ground manual method Drilling/Blasting Line Drilling and Blasting is proposed but will be done in a controlled manner. No of working days 300days Water demand 10.0KLD Sources of water Water will be supplied from water tankers Man power 42 Solid Waste 11502Tonns of waste will be generated during planned five years Nearest railway station , Yerraguntla and Kadapa Railway stations of Chennai - Guntakal section. The distances of the mine from these Railway stations are 50 km, 65 km and 60km respectively Nearest airport BengaluruInternationalairportis250kmdueSouth from the mine lease area Project Cost Rs.40Lakhs

1

DETAILSOF THE MINES ARE GIVENBELOW: Lea se Name Extent- Ha Sta tus Det ai ls of lea se ar eas Pro duc tion [ TPA] Sy.No.721/2,1/ P, and 692 of of Medipentla Village, Sri Y.S Venkat Reddy 28.037 Existing 1512 –Barytes Vemula Mandal, Y.S.R District. Sy.No. 1/12 of T.V.Palli Non Sri.Azmthulah 9.413 Village, Vempalli Mandal, Non working working Y.S.R. District Sy.No. 275 of Gondipalli Non M/s K.A.B (P) Ltd 285.48 Village, Vemula Mandal, Non Working Working Y.S.R. District

As a part of fulfilling the conditions laid down in the Notice of Director, Mines & Geology, Ibrahimpatnam, Proponent was submitted a mining plan to carry on the quarrying operations systematically and more meticulously. Subsequently, the mining plan was approved by the Dy. Director, Mines & Geology, Kadapa through the letter no. 204 / MP-YGL / 2017 DT 12-02- 2018.

PROFILE OF THE PROJECT PROPONENT The Applicant of this QL area is having experience to undertake the mining. However the quarrying operations will be undertaken under the supervision of well experienced Mining Engineer.

BRIEF DESCRIPTION OF THE PROPOSEDMININGACTIVITY SIZE OF THE PROJECT The mining lease area of8.00Ha.is located in Govt. land. Under ground mining is followed and it has been proposed to produce approximately Barytes-7881Tonns/annum. The nearest habitation is Medipentla located at a distance of 1.5km due South from lease area. M/s Sree Mining & Minerals, Mg. Partner: Sri. D. Vijaya Kumar Reddy, has filed an application for QL for Barytes in Sy.No.972/2 (Old Sy.No.721/4) of Meedipentla Village, Vemula Mandal, Y.S.R. Kadapa District, Andhra Pradesh State over an extent of 8.00 Hect to the Assistant Director of Mines & Geology, Yerraguntla on 07-06-2016. The Assistant Director of Mines & Geology, Yerraguntla submitted proposals recommending for grant of Quarry lease for Barytes over an extent of 8.00 Hect in Sy.No.972/2 (Old Sy.No.721/4) of Meedipentla Village, Vemula Mandal, Y.S.R. Kadapa District, Andhra Pradesh State in favour of M/s Sree Mining & Minerals, Mg. Partner: Sri. D. Vijaya Kumar Reddy.

2

After careful examination of the proposals of the Assistant Director of Mines & Geology, Yerraguntla it is decided in principle to grant a Quarry lease for Barytes over an extent of 8.00 Hect in Sy.No.972/2 (Old Sy.No.721/4) of Meedipentla Village, Vemula Mandal, Y.S.R. Kadapa District, Andhra Pradesh State in favour of M/s Sree Mining & Minerals, Mg. Partner: Sri. D. Vijaya Kumar Reddy for a period of 20 years subject to submission of Approved Mining Plan within a period of 6 months from the date of issue of the notice under Rule 12 (5) (c) of APMMC Rules, 1966 along with consent for Establishment from A.P. Pollutions Control Board and Environmental Clearance from Ministry of Environment & Forests as per Environmental Impact Assessment Notification through S.O.1553, dated 14-09-2006 by Director of Mines & Geology, Ibrahimpatnam, vide Notice No 17275/R5-2/2017, dated 30-10-2017. Mining Plan approval was approved by Deputy Director of Mines & Geology, Kadapa. Employment Generation Proposed mining is Underground manual method and this project operation will provide livelihood to the 42 workers. It will provide employment to the people residing in vicinity.

3

2.0 DETAILSABOUT THE PROPOSEDQUARRY SITE

Type of Project Including Interlinked and Interdependent Projects, If Any. The Barytes mine is of 8.000 Ha. No interlinked projects were associated with this project.

Location The mining lease area is located in Sy.Nos.972/2 of Medipentla Village, Vemula Mandal, Kadapa Dist, Andhra Pradesh. The mining lease area falls in Survey of . Topo sheet No57J/7. Location of the mining lease in Kadapa District is shown as Figure-1.Google Image is shown as Figure – 2 and Topographical map is shown as Figure – 3 and the cluster map is enclosed as Figure-4.

Co-ordinates of the Quarry area GPSREADINGS OF QUARRY LEASEBOUNDARY PILLARS

GPS READINGS OF QUARRY APPLIED BOUNDARY PILLAR S CORNER LATITUDE LONGITUDE PILLARS (NORTHING) (EASTING) 1 N14⁰ 20’ 12.2″ E78⁰ 20’ 07.9″ 2 N14⁰ 20’ 08.9″ E78⁰ 20’ 08.2″ 3 N14⁰ 20’ 11.6″ E78⁰ 20’ 34.9″ 4 N14⁰ 20’ 14.9″ E78⁰ 20’ 34.5″ Map Datum -WGS -84

SITESERVICES The applicant has proposed to build an Office, Rest Rooms, First Aid Room, Shelters, Lavatory, Bore Well for drinking water will be provided in the North of the quarry lease applied area. Sanitary conditions are maintained as per rules.

Topography: The subject area is hillock. It is elevated on North side and sloping towards south side. There is 85m relief from N to S of the area. The applied area is located on South eastern flank of hill range trending northwest-southeast. The general gradient observed in the area is towards SE. The highest & lowest elevation in the applied area is 505m & 420m from the Assumed benchmark of 505m & the Assumed bench mark is shown in Plate No.3. The Surface cum Geological plan & Geological Cross Sections, Longitudinal section have been prepared on Scale of 1:1000 R.F..

4

FIGURE– 1 LOCATIONMAP

MINE SITE

5

FIGURE -2 GOOGLE IMAGE

6

FIGURE -3 TOPOGRAPHICAL MAP

7

FIGURE -4 CLUSTER MAP MINES IN 500 MTS PHERIPHERY

8

ADJOINING MINE DETAIL POSITION Extent- Production Lease Name Status Details of lease areas Year of Grant/ Ha [TPA] Sy. No 275 of Gondipalle M/s. Krishnappa Non Village, Vemula Mandal, Non 07-12-1974 Non Asbestons Barytes & 285.48 working Y.S.R. Kadapa District, Working Working NO AMP Private Limited Andhra Pradesh State Sy. No 1/12 of T.V Palle Non Village, Vempalli Mandal, Non 15-11-1978 Non Md. Azamathullah 9.43 working Y.S.R. Kadapa District, Working Working No AMP Andhra Pradesh State Sy. No 721/2 of 1512 28-03-2001 LR No Meedipentla Village, Existing Barytes 4644/MS/YGL/2016 Y.S.Venkata Reddy 28.037 Vemula Mandal, Y.S.R. working tonnes/ dated 20-01-2018 Kadapa District, Andhra annum Scheme of Mining Pradesh State Sy.No.972/2 (Old M/s Sree Mining & Sy.No.721/4) of Minerals, Mg. Meedipentla Village, Barytes Amp approved Partner: Sri. D. Vijaya 8.00 New Vemula Mandal, Y.S.R. 7881 TPA Fresh Grant Kumar Reddy - Kadapa District, Andhra Lessee Pradesh State

9

Details of Alternate Sites No alternate site was considered as the project is mineral specific and site specific.

Size or magnitude of operation The mine has lease over an area of 8 0 Ha. and the production rate is Barytes 7881 Tons per annum. The lessee follows Under ground manual mining. Production parameters The Mineral production target for five years is given in Table 2.1

Year wise Barytes Production Programme Total tentative ROM (Cum) Pit Top Soil OB/SB/IB Mineral ROM/Waste Year Excavation Ore Mineral reject No. (Cum) (Cum) reject Ratio (Cum) (Cum) (Cum) 1 2 3 4 5 6 7 8 9 I 1 1606 Nil 643 867 96 Nil 1 : 0.85 II 1 2642 Nil 840 1621 180 Nil 1 : 0.63 III 1 2319 Nil 928 1252 139 Nil 1 : 0.85 IV 1 2461 Nil 1201 1134 126 Nil 1 : 1.17 V 1 3475 Nil 1390 1877 209 Nil 1 : 0.85

YEAR PRODUCTION in tonnes DEVELOPMENT in tonnes I 3643 1478 II 6810 2040 III 5259 2133 IV 4763 2654 V 7881 3197

10

3.0 MININGACTIVITY Geology and Reserves Regional Geological setup The formations in which Barytes mineralization occurs belong to the lower Kadapa system constituting the following sub divisions and sequence. Lower Kadapa system : Cheyair series : (Younger) Traps Tadipatri shales Pulivendla quartzites Papagni series : Shales Vempali lime stones Gulcheru quartzite’s The basal Gulcheru quartzite’s rest unconformable over the older crystalline of Archaen age. The Papagni series stretches along the western margin of the characteristic crescent shaped Kadapa basin for a distance of 250km starting from near Kurnool in the north traversing the districts of Kurnool, Anantapur & Kadapa. The rocks have southern dips in the northern portion becoming easterly in the mid section & gradually changing to north easterly in the south with some local variations. The dips of Papagni series of beds are gentle ranging from 8º to 30º. The Pulivendula quartzite’s occur as comparatively narrow bands separating the Vempalli lime stone & shales from the overlying Tadipatri shale’s. These rock formations have been intruded by a suite of basic igneous rocks, viz. traps. The Barytes veins of importance are confined to the Vempalli (dolomitic) limestone’s & their associated traps. The regional structural features of importance are the number of prominent faults both along strike and dip of the formations through to be related to shearing effects due to which the associated complimentary fractures either as tension or shear have localized the Barytes deposit as fissure filling.

Local Geology The rock formations in and around the applied area are dolomitic rocks belong to Vempalli stage Papaghni series. Though the topsoil is occurring here and there about 0.3m to 0.5m thickness, the entire area is covered by dolomite. Veins of the Barytes are confined to the fissures with steep dips of 80º to 85° towards North. The typical pinching & swelling characteristics of the vein and inclusion of lenses are observed around the applied area. The applied area is located in the Barytes belt which is about 15 km length trending almost east west i.e is roughly from Talapalli Village up to Velpula village. Barytes centre extracted by Underground method. It is prepared to follow Underground of mining in the applied area. The based Gulcheruvu Quartzite’s are separated from older Achaeans by Eparcheans unconformity. The unique feature of Kadapa system is that every series has based Quartzite’s which are fallows by shales & lime stones.

11

The Barytes deposits occur either as filling or as veins in all the dolomitic limestone’s and shales. They are also associates as traps from the south end (Gulcheruvu) the North (Bollaram). All the largest vein deposits occur in the traps and adjacent to traps. In the areas with suffered faulting. Solicitation and mineralization had occurred resulting in the formation of Quartz and Barytes respectively. The applied area is confined to Lower Kadapa system, especially the Vempalli formations. The formation comprises purple & Buff shale in to needed layers or Dolomite. The Dolomite Exhibits features of shallow marine environment. The formation has intrusive trap sills with Barytes faults all along the strike and dip formations have localized the Barytes deposit as fissure fillings in the area. To the east and west side of the applied area Barytes mining is being carried out to depth ranging from 20m to 200m. In this area the Barytes vein is occurring as vein type with width ranging from 1m to 2 m. The trend of the Barytes vein is almost east west and dip is 85° towards North. The strike length of 802m towards east west direction with highest and lowest elevations as 490m and 290m. As seen from the adjacent mine working the strike direction was marked and the adjacent mine working are gone upto 200m depth where as the occurrence of Barytes was based from 9m to 200m. from surface.. Exploration 1) Production proposed for the next five years: YEAR PRODUCTION in tonnes DEVELOPMENT in tonnes I 3643 1478 II 6810 2040 III 5259 2133 IV 4763 2654 V 7881 3197 TOTAL 28356 11502

12

MINERAL RESERVES : Mineable reserves = Geological reserves (UNFC:111) -Blocked reserves (UNFC : 211& 221) BLOCKED RESERVES ESTIMATION : The reserves will be blocked under 7.5 m barrier on two sides of the area. i.e on North & South sides i.e Depth x width x thickness x T.F x RF = 80 x 15 x 1.5 x 4.2 x 0.6=4,536 tonnes Total Geological reserves are 1,56,492 tonees The total Blocked reserves are = 4,536 tonnes Total Mineable Reserves are : 1,51,956 tonnes Barytes mineable reserves 1,56,492 - 4,536 1,51,956 tonnes

TOTAL MINERAL RESERVES : RECOVERBLE MINERAL RESERVES BARYTES UNFC Geological Axis Estimated Reserves Classification Code UNFC code of Barytes in tonnes Total Mineral Resources (A+B) 111 G1 1,56,492 tonnes A. Mineral Reserves 1.UNFC 111

BLOCKED RESERVES BARYTES UNFC Geological Axis Estimated Reserves of Classification Code UNFC code Barytes in Tons. 1. Reserves blocked 7.5 211 & G1 4,536 tonnes m barrier zone in 221

Note : No resources are estimated in blocked in 7.5 m barrier zone MINERAL RESERVES : Total Estimated Reserves (UNFC-111) 1,56,492 tonnes Total Estimated Blocked Reserves (UNFC-211, 221) 4,536 tonnes

Total Mineable Reserves = Estimated Reserves - Estimated Blocked Reserves =1,56,492 tonnes - 4,536 tonnes = 1,51,956 tonnes Total Mineable Reserves are: 1,51,956 tonnes Geological Blocked Reserves in Mineable Reserves Mineral Reserves in tonnes tonnes in tonnes Barytes 1,56,492 4,536 1,51,956

LIFE OF THE MINE : Initially the total quantity of mineable reserves is considered as marketable reserves. In this way a total mineable reserves of 1,51,956 tonnes of Barytes available in the ML area. As the mine is proposed to produce 7881 tonnes Barytes shall be produced /annum, so the life of the mine is as follows: BARYTES Total Mineable Reserves of Barytes 1,51,956 19.21 Years Actual anticipated annual production 7881

13

PROJECT DESCRIPTION WITH PROCESSDETAILS Method of Mining a) TYPE OF MINING : The method of mining will be underground method of mining operation are proposed in the plan period. This method and mode of operation is taken into account mainly for the interest of safe and scientific mining, conservation of mineral and protection of environment by consideration of all the parameters and the geological attitudes of the ore body. Considering the geology and nature of the mineral occurrence and also due to stable strata condition, the proposed mining will be carried out by underground method. It is proposed to open 6 shafts staring from eastern side to western side namely Shaft No 1 to 6 in the applied area and in that shaft no 2, 4 & 6 will be used as 'man-way'. For every 10m horizontal distance one cross (level) cut will be made to connect the shafts, interconnection & man way in systematic manner as described (i) MODE OF ENTRY :The mode of entry is by shafts. Total 6 number of shafts are proposed. The surface RL of the shaft opening is 492m RL (Shaft 1 & 2), 475m RL (Shaft 3 & 4) and 465m RL (Shaft 5 & 6). The size of the shafts are 2.5 mts x 2.5 mts. The dimensions of the level 2mx2m. Shaft no.2, 4 & 6 will be treated as man way for the workers to enter into the mine by providing ladder way. Total 6 shafts, 4 levels and suitable interconnection at interval of 10 m x 10m will be formed during the plan period. (ii) UNDER GROUND LAY OUT : Total 6 number of shafts are proposed. The surface RL of the shaft opening is 492m RL (Shaft 1 & 2), 475m RL (Shaft 3 & 4) and 465m RL (Shaft 5 & 6). The size of the shafts are 2.5 mts x 2.5 mts. The dimensions of the level 2m x 2m. 6 levels will be formed connecting all the shafts at 414 m RL, keeping surface to first level at 10m and level to level at 10m interval respectively. Shaft no. 2, 4 & 6 will be provided ladder ways and shaft no 1, 3, & 5 will be utilized to transport of material from below ground to the surface. Near Shaft No 3 & 5 mechanical ventilator will be provided to keep sufficient air for the persons working in the underground. Regarding underground electrification, initially cap lamps will be provided later on after obtaining permission from DGMS, the underground electrification will be done with electricity. (iii) SYSTEM OF DRILLING & BLASTING : For drilling purpose a stopper or air legs mounted jackhammer machine shall be used with the required motive power of compressed air (140cfm) supplied through a pipe line from surface. A wedge cut holes shall be practiced in development of levels and shafts using hand held pneumatic drill machine namely silver 30 holmanco with chisel type bit. The blasting operations will be done manually and the general pattern of holes is shown in Annexure – IV. The frequency of blasting with the number of holes blasted at a time being restricted to 10 holes will be so regulated that as for as possible vein matter and country rock are blasted separately. Blasting will be done two to three rounds and once a day (shift).

14

The explosives used in the blast holes is formadyne in cartridges of 20cm length and 25mm dia initiated by detonator through waterproof plastic coated safety fuse. A total of 5 to 6kg of explosives will be consumed for each advance of face, the normal pull being 0.8m to 0.9m. All the regulations as per the MMR1961 & Indian Explosives act regarding storage & handling of explosives will be strictly followed. For each blasting around 0.8m of advancement will be achieved and the required explosives will be 5kgs. So for one blasting (2mx2mx0.8m) 3.2 cum of development will be achieved. During 5 years plan period a total production & development in both shafts and levels will be 39858 tonnes as explained in year wise production & development. So the required number of blasting will be 39858/3.2 = 12456 and explosives required will be 12456 x 5kg = 62280kgs. For one year the required explosives will be 62280/5 = 12456kgs & for one month 12456/12 = 1038kgs & for 1 day 1038/26 = 40 kgs.. (iv) METHOD AND SEQUENCE OF STOPPING : No stopping is proposed during the plan period, however in future it is proposed to extract the mineral by overhead of cut and fill method of stopping and filling the voids with the waste rock material, which will be brought down through a set of winzes. By the way all the waste rock generated during the development, will be completely utilized for the filling up the voids. (v) SYSTEM OF UNDERGROUND TRANSPORTATION : The system of hoist will be by skips operating on an inclined haulage so that from pit top to pit bottom an inclined track line will be made & extended with progress of depth. In the below ground tram line with tubs will be provided in the levels and loaded tubs will be trammed from the working points manually to the haulage shaft bottom similarly pit top also surface track line & tipping tubs arrangements will be provided for handling of Barytes as well as waste. Pit bottom lay out consist of loading arrangement at inclined haulage bottom connected with underground levels developed in the Barytes for transport of Barytes/waste rock to the surface (please see Plate No. 8).. (vi) SYSTEM OF WINDING/HOISTING : Hoisting will be provided at Shaft no.1, 3, & 5 to transport the waste rock and mineral from the underground to the surface with 12 HP engine coupled with winch and rope 5/8´´ diameter. In the haulage roadway 15kg /m of rails will be laid down in order to haul the waste & mineral. The gauge of the haulage track will be 2 feet wide. The capacity of the skip will be 0.75 T. A track line with tub will be laid down in the levels to transport the ROM to the hoisting point. This will be sufficient for handling the waste & mineral of the mine. (vii) SUBSIDENCE MANAGEMENT : No subsidence is proposed to be carried out in first five years period. During the first five years the subsidence management not yet proposed, due the lower level depth of mineral excavation proposed up to level-4 only.

15

The subsidence shall be taking place repeatedly and therefore subsidence management measures shall have to be planned accordingly. A methodology for such a subsidence management will suggest in first scheme of mining. (viii) MINE VENTILATION : The aim of mine ventilation is to provide for work persons in the underground air with permissible standards as stipulated below. Oxygen Not less than 19 % Carbondioxide Not more than 0.5 % After blasting within 5 minutes dilution of CO and NOx should be less than 50 ppm and 5 ppm respectively. Quantity of air /person Not less than 6 cum Velocity Not more than 4m/second in working face. Not more than 8m/second in shafts/inclines with man winding. Not more than 15m/second in ventilation shaft without man winding Up to 10m depth of working without much lateral extension of working, natural ventilation shall suffice supplemented by compressed air for clearing of noxious fumes. The proposed mine depth is about 120m. A mechanical ventilator of exhaust type will be installed at near Proposed Shaft no 2 & 6 producing 20,000 cft/m capacity of 7.5 HP. Necessary devices will be provided where & when necessity arises during development & subsequent stages. b) EXTENT OF MECHANIZATION Forconductingoftheproposedundergroundoperationsthefollowingequipmentwill be required. Item No. Description No. of Units 01 Diesel/electrically operated compressor (400 cfm/mt) 02 02 Jack hammers 04 03 Hoist/Winder (12 HP) with skip 02 04 Mechanical Ventilator (5 Kw/25mm wg Exhaust fan) 02 05 Pumps (10 HP) 04 06 Tipping tubs (0.5 tonnes capacity) 06 07 Track line 500 m 08 Cap lamps 50 nos 09 G.I. Pipe line 75mm 200m 25mm 100m

Raw Material Required Along With Estimated Quantity, Likely Source, Marketing Area of Final Product/S, Mode of Transport of Raw Material and Finished Product No raw material will be required in the project. The operation involves the extraction of Dolomite & Steatite and dumping in stock yard. The Dolomite & Steatite mineral will be transported through hired trucks to the industries.

16

USE OF MINERAL Barytes will be used in domestic market. It’s a very suitable material for most Paint Industries. It is used in different ways. PROCESSING Processing of Barytes is not involved. Resource Optimization/Recycling and Reuse Not envisaged. Availability of Water Its Source, Energy/ Power Requirement and Source WATER REQUIREMENT Water is required only for drinking purposes, green belt, wire saw cutting and dust suppression. The number of working people is around 30 so the total water requirement will be around 6.0 KLD. This water will be supplied from tankers/bore wells of nearby area. WATER REQUIREMENT Water Requirement Total Requirement (KLD) Dust suppression 2.5 Greenbelt Development 2.0 Domestic Usage 1.5 Total Water Requirement (KLD) 6.0

QUANTITY OF WASTES TO BE GENERATED (LIQUID AND SOLID) AND SCHEME FOR THEIR MANAGEMENT/ DISPOSAL Solid Waste Generation& its Disposal The waste material that will be generated due to mining is doloritic rock. During the five-year plan period about 11502tonnes of waste material will be generated and a little topsoil about 10 to 20cum quantity will also be generated. This topsoil will be used in plantation of the applied area. A non mineralized area of about 10000 sqm (580m x 17m) located north side will be utilized for stacking of about 11502tonnes waste material (Please see Plate No. 8 for location of dumping site.) It is proposed to keep the height of the dump upto 15m only. The coarse lumps of dolorite shall be arranged as a pack wall like structure at dumps slopes bottom in order to avoid rolling down of waste material. For stabilization of this dump grass will be grown over the dumps slope periodically. Liquid Effluent No liquid effluent will be generated at the mine site. The domestic waste water generated will be sent to septic tanks followed by soak pits. Size or magnitude of operation Theminehasleaseoveranareaof8.000Ha.andtheproductionrateisBarytes- 7881Tonns/annum, The lessee follows Under ground mining.

17

Production parameters The Mineral production target for five years is given in Table 3.1 YEAR PRODUCTION in tonnes DEVELOPMENT in tonnes I 3643 1478 II 6810 2040 III 5259 2133 IV 4763 2654 V 7881 3197 TOTAL 28356 11502

Connectivity The following are the environmental settings within 10 km radius

Nearest village Medipentla- 1.5 KMS Road State road connecting Plivendula–Kadapa11 Kms [NNE] Railway Line Nil [within 10 km] Railway station Nil [within 10 km] Port facility Nil [within 10 km] Airport Nil [within 10 km] Defence Installations Nil [within 10 km] Reserved forest Gorivinkanuma R.F. 4.3 KM[S] Water body Gattu Vanka 0.2 KM[W] Pulivendla Branch Canal 3.2 KM[N] Pendluru Vanka 9.5KM[N] Pendluru Cheruvu 8.7KM[NE] Pamluru Vanka 9.8KM[NE] National Park/ Wildlife sanctuary / Nil [within 10 km] Biosphere reserve / Tiger Reserve / Elephant Corridor Interstate border Andhra Pradesh-Karnataka boarder-150kms[S] National Highway Hyderabad-Banglore-180[S] District Head Quarters Kadapa-60.00km[NE] Nearest Town Vemula-8.00km[N]

LANDFORM, LANDUSEAND LANDOWNERSHIP The mining lease is located in Govt. Revenue land.

18

4.0.ENVIRONMENTAL MANAGEMENT PLAN FOR CLUSTER EnvironmentalManagementMeasuresspecifictotheabovesubjectminearedetailed under the following heads 1. Air Environment 2. Noise Environment 3. Water Environment 4. Land Environment 5. Socio Welfare Measures 6. Occupation Safety and Health Measures 7. Budget for Environmental Protection/management Measures

1. AIRENVIRONMENT a) Sources of Air Pollution There will be no impact on the air environment due to underground mining. However, during blasting compressed air flushing will be done. The surface air environment will have impact due to the trucks that ply on road to carry the material mined & dumping the waste. The excavated material will be transported through 10 tonnes trucks capacity. The daily production on average is 26 tonnes and tis needs 2 trucks for hauling. The air pollution will be limited only to this extent. The major sources of sir pollution in underground mining are, drilling, blasting, extraction, loading & unloading.  The proposed operations will cause air pollution on surface due to truck movement. This will be controlled by water sprinkling. The water will be sourced through tankers from nearby villages.  Dust masks will be provided to drilling workers Noise Pollution Control Measures In the quarry, the machinery operations like jackhammer drilling, compressor and excavators will generate noise pollution. The noise pollution will be limited underground atmosphere. He surface noise will be only due to vehicular movement. The noise pollution control measures are given below: . Drilling Workers will be provided with earmuffs, earplugs. . Regular maintenance of vehicles and machinery . Limiting the speed of vehicles entering and leaving the quarry to 25 kmph. Control of ground vibrations Blasting activity in underground mining will produce ground vibrations. As the mine will be operated with less machinery and the blasting is also minimum These vibrations will be transmitted to surface also. The nature of strata is doleritic which will not allow the vibrations more than 10% as the layering of the formation is prominent.

19

IMPACT DUE TOVEHICULAR TRAFFIC Max. No. of Trucks required to transport the Barytes will be  From proposed Quarry-2 nos.  From adjoining quarry of –1 nos.  The existing road is capable of absorbing this additional traffic.  Dust suppression will be taken up along the haulage roads & approach roads. Hence there will not be much impact on traffic due to this proposed mine activity. 2. Water Environment Impact on surface water bodies : There are no streams and other surface water bodies in and around applied area. The applied area is small hill. Only rain water drains through the slopes during rainy season. There are no activities in the surface except dumping of mining waste over waste dump and manual sorting of Barytes into various grades and sizes. Control Measures : It is gently sloping terrain with maximum relief of 95m. The rain water drains as sheet flow without erosive power. Hence there is no erosion, sedimentation and no changes in physical and chemical quality of surface water. A water garland (1mx1m) shall be formed to see that no rainwater comes to the shafts from higher reaches. The waste dump will be afforested and stabilized. Garland drains with silt traps will be provided all along the waste dump and silt free water will be let into the nearby seasonal stream. Impact on Ground water table : The proposed mining depth will be 100m, and the water table is at 30m below ground level. Ground water has to be pumped during heavy rains for about 15 days in a year. During remaining part of the year, pumping is required to pump minor quantity of water. The pumped water can be used for dust suppression and drinking. The quality of groundwater will not be affected as there is no chemical discharge from the mine. Following measures shall be taken:  It shall be ensured that good quality potable water is provided for drinking purposes. Good sanitation facilities (toilets with septic tank followed by soak pits) shall be provided and maintained for good hygienic conditions.  Garland drains with silt traps will be provided at the foot hill side of dump.  The spillages from fuelling of machinery shall be avoided and in case of any spillage the same shall be handled properly. Likewise the spent lubricating oils etc., shall be safely collected and properly disposed off.

20

4.LANDENVIRONMENT Areas of Considered The Identified aspects which can cause impact due to mining operations are Listed below  Land Use  Solid waste generation  Transportation  Green belt Land Use: The category of the mining lease area is Govt. Revenue land which is covered with shrubs. Solid Waste generation: Transportation activity within the mining lease area is mainly for transportation of Mineral by tippers from the mine pit to Industry units. I) Land management Measures A) Solid waste management The waste material that will be generated due to mining is doloritic rock. During the five-year plan period about 11502 tonnes of waste material will be generated and a little topsoil about 10 to 20cum quantity will also be generated. This topsoil will be used in plantation of the applied area. A non mineralized area of about 10000 sqm (580m x 17m) located north side will be utilized for stacking of about 11502 tonnes waste material (Please see Plate No. 8 for location of dumping site.) It is proposed to keep the height of the dump upto 15m only. The coarse lumps of dolorite shall be arranged as a pack wall like structure at dumps slopes bottom in order to avoid rolling down of waste material. For stabilization of this dump grass will be grown over the dumps slope periodically. SOLID WASTE GENERATIONS FROM OTHER QUARRY LEASE ARAE AS Lease Name Extent- Status Solid Waste Average Ha [Max]-TPA [TPA] Y.S. Venkat Reddy 28.03Ha Existing 2268 1502 Total Waste 2268 1502

Green belt Development AspertheconservationofMineralandMinesAct,itisrequiredtoleaveabarrierof 7.5m width all along the mining lease area and all along haulage roads SOCIALWELFARE MEASURES The mine will provideemploymentto42persons and equal number of persons will be employed indirectly for transportation and other activities. Local persons will be given preference.

21

5. OCCUPATIONAL HEALTH MEASURES and BUDGET Fugitive dust, noise and fines may affect the health of workers. Safety of employee during operation will be taken care as per mine regulations act 1961. To avoid any adverse effects on the health of workers due to dust & noise, the following measures will be implemented: Provision of rest shelters for mine workers with amenities like drinking water, fans, toilets etc.  Dust suppression of haul road.  First - Aid facilities within lease area  Height, slope and width of dump development as per the approved Mining plan.  Regular medical examination for the employees.  Dust masks will be provided for control of dust[All Quarries].  Ear plugs will be provided to employees to reduce the Noise impact.  Health check-up will be carried out for all employees in an external hospital yearly once and medical records will be maintained  Rs. 1500/- per person/year will be allocated employee occupation health. Periodicity of health checkups done for yearly for workers working in Quarry. Blood test (once in a year) Urine test (once in a year) Complete Physical examination (once in a year) X-ray of chest (once in a year) Lung/Pulmonary function test (once in a year) Sputum Examination (once in a year)

22

6. BUDGET FOR ENVIRONMENT MANAGEMENT PLAN Total cost for the project is 38 lakhs. Budget allocated for EMP is 3.40 Lakhs (Capital Cost), 2.55 Lakhs (Recurring Cost).

Ma intenance/ rec urr ing co st Sl no Work name Total fixed cost with periodicity 1 Saf ety shoe - 15,000 2 Helmet - 6,000 3 Hand g lo ves - 2000 4 Ear plugs - 1000 5 Clo th for pro tection from d ust 10,000 5,500 6 Dust Ma sks - 4,50 0 7 Wat er sprin kl in g 2,00,000 25,000 8 Gre en belt establish ment 60,000 20,000 9 Medical exa min ation - 45,000 10 Environme nta l Monitoring - 40,000 11 Social welfare measures - 60,000 12 Ga rl and dr ain s 70,000 30,000 To tal 3,40,000 2,55,000

Total budget from all the surrounding mines will be of Rs 6.8 lakhs towards capital cost and about Rs 5.10 lakhs towards the recurring cost to protect the Environment of the surrounding areas under the Environmental Protection Measures

POST PROJECT MONITORING PROGRAMME Monitoring of all the environmental parameters viz, air, water, noise and soil as per the formulated program based on CPCB and MOEF guidelines every year in order to detect any changes from the baseline status. Monitoring program will be followed till the quarrying operations continue. For implementation of Environment management Plan a small unit will be formed under control of the Mines manager. The job of this unit will be regular environmental monitoring, preparation and submission of environmental report, green belt development, etc.

23