<<

Research Report 301

EVALUATION OF CORED SPECIMENS FROM TIMBER CAISSON BENEATH PIER NO.2 OF THE US 25 BRIDGE OVER THE OHIO RIVER BETWEEN COVINGTON AND CINCINNATI Fl4l(l)

KVP-56; HPR-1(6), Part Ill

by

Jas. H. Havens, Director of Research Assaf Rahal, Research Engineer

Division of Research DEPARTMENT OF HIGHWAYS Commonwealth of Kentucky

December 1970 INTRODUCTION

from the Pier No. 2 of the tormer C&O Bridge at Covington is off-shore 1927, this pier Kentucky side of the Ohio River. It was built in 1887. In The other three was extended downstream to support a new railroad bridge. to high­ piers remained independent. The original structure was then converted 1937. In 1968, an way use and was purchased by the Commonwealth of Kentucky in deficiencies in engineering analysis of the superstructure indicated critical traffic. Subse­ terms of "safety factors", and the bridge was closed to all Of greatest quently, various plans for reconstruction came under consideration. No. 2 ·- jointly significance here is the consideration toward re-use of Pier Cost estimates with a new highway bridge and the existing railroad bridge. uoon the appeared persuasive; the structural feasibility remained dependent of the mason•j, con­ integrity of the pier -- more specifically, the worthiness crete, and the underlying timber caisson. vertical Prior to removal of the steel superstructure (fall of 1970), report concerns the cores were extracted from Pier No. 2 for evaluation. This evaluation of specimens of wood from the timber caisson. in the Trans­ The substructure construction was described by wm. H. Burr, 1890; a copy actions of the American Society of Civil Engineers, Vol. XXIII, is most per­ is appended hereto for convenient reference; Plate XIII, therein, tinent.

PERMANENCE OF BURIED TIMBER FOUNDATIONS

throughout Timber foundations under masonry structures have been employed history. Wood buried below the oxygen-diffusior. zone is preserved recorded for a short oxygen starvation of fungi and bacteria. Decay may proceed through and utili­ time. Anaerobic bacteria have an implied capability of regenerating cycle is likely to z.ing oxygen from host organic matter; however, the digestive buried woods do become unbalanced, poisoned, or at least arrested. Obviously, pilings suffice for not persist forever. Some commentaries indicate that wood the tenure of 80 to 100 years; others suggest hundreds of years. However, years. American structures in this country rarely exceeds a hundred or more limits engineers do not usually build to withstand the ages. Obsolescence main piers of the tenure. European engineers strive for greater tenure. The site, was begun Roebling suspension bridge immediately upstream from the C&O 10-12 feet in 1857; the piers are founded on hewed log mats set on gravel 1867. above bedrock. The bridge was opened to traffic January 1, EVALUATION OF WOOD SPECIMENS

Consideration of use of Pier No. 2 in the new structure afforded a rare condition opportunity for historical but purposeful inspection of the present immediate of the wood. Discovery of decay or rot would probably have led to and rejection of the alternative. Upon recovery, the cores appeared frayed appeared, severely damaged, Later, when sawed along the diameter, bright wood scent A slightly acrid odor was detectable; but there was also a distinctive of of newly-cut wood. Specimens of pine were dlstinctly odorous, A specimen only poplar was recovered but was examined by the Forest Products Laboratory Not all of (See Appendix 11). In the main, the cores consisted of white oak, gun-metal the specimens were bright (yellowish); some were dark-- approaching subjected blue or dark gray. Miniature specimens were cut from the cores and to compressive loading. Stress-strain curves are presented here, Comparative Copies stress-strain curves obtained from new white oak wood are also provided. of the core logs are appended. evalua­ Figure 1 is a composite photograph of ~he three cores received for iron pin tion. Attention is directed to the incidental recovery of a wrought in the upper portion of the NW core,

-2-

wrought wrought

of of

Recovery Recovery

Evaluation, Evaluation,

for for

Received Received

incidentals incidentals

was was

Cores Cores

of of

core core

NW NW

Photo Photo

in in

pin pin

iron iron

Composite Composite

1: 1:

Fig, Fig, w w SIMPLE COMPRESSION TESTS

Small cubical specimens, ranging from 0. 7 in. to 1.2 in. in size, were cut from the cylindrical cores. Except for slight surface drying during fine shap­ ing, the specimens were maintained in a wet condition until the compression tests were completed. A specimen of bright wood in test is shown in Fig. 2. All compression tests were made perpendicular to the grain. There was notice­ able weeping of water from the pores.

Fig. J shows a specimen of dark wood distorted (residual) by compression. None of the specimens ruptured, split, or tore; all specimens, including new wood, exhibited a yield point followed by strain hardening. The resulting stress-strain relationships are shown in Fig. 4. The minimum yield point occurred at about 350 psi; the yield stress of new wood was in the order of 2 to 2.5 times that of old wood. The handbook yield point for white oak, at 70% moisture (green and unseasoned), is 850 psi.

NOTE: New wood specimens were soaked in water for .five days before testing.

Differences (between ne"' and old wood) in the number of annual rings per inch are also shown in Fig. 5. Because of these differences, the woods are not directly comparable in terms of strength. The new wood specimens contain a significantly greater proportion of late wood growth and are thereby adjudged to be superior in strength. Due to an assumed improbability of finding new wood comparable in anatomical attributes to the old wood, it was decided to air dry specimens of old wood and to make strength tests in that condition and to compare those strengths with handbook values for new wood. The average hand­ book value for white oak in this condition is 1410 psi. The strengths of the 5. two specimens selected (one bright wood and one dark wood) are shown in Fig. By this comparison, the old wood would necessarily be adjudged equal to average new wood. This interpretation minimizes any effects otherwise attributable to decay. It does not suffice to explain the low, wet strength of the old wood. -­ It is suggested that moisture contents approaching a state of supersaturation possibly somewhat greater than that of green wood and of osmotic origin -- affects the wet strength. The effect of swelling, attending unloading (coring), on moisture content was not determined.. However, a small but significant s\.;rell pressure was measured upon re-immersion (discussed subsequently).

-4- Fig. 2: Specimen of Bright White Oak in Compression. Note weeping from pores near base of specimen.

Fig. 3: Dark White Oak Specimen Showing Residual Distortion Following Severe Compression,

-5- 1400

1300

9 rings per in. 1200 9rays per in. 9 rings per in. 9 rays per 1100

1000

900 20 rings per L ,~ 8 rays per in. 800

' 700 "0 0:: 23 rings per in. 6 ...9- 600 9 rays per in .

Ul Ul w 500 22 rings per in. a:: f- 8 rays per in. en 400 ..f­ ::::> 300

0,{______-J ______~------L------0 0.1 0.2 0.3 0.• UNIT STRAIN ( inch I inch )

Fig. 4: Stress-Strain Relationships Obtained frum Old Wood and New Wood (saturated).

6 NW 155.3-155.5 1800

Dark woad -- 1600 --151.0-152.5 ... - ~

1400

.: 0" 1200 ~ .,; .c

({) 1000 ({) LIJa:: f- ({) f- 800 z ::::>

600

400

200

2 3 4 5 6 7 STRAIN (percent)

Fig. 5: Stress-Strain Relationship Obtained from Air-Dry Specimens of Old Wood.

7 SWELL AND RELAXATION TESTS (TRIAXIAL)

A cylindrical specimen of dark wood; 2.72 in. x 1.30 in., was placed in a triaxial test chamber and surrounded by water under 20 psi pressure; the speci­ men was restrained in the axial direction by a nominal preload of 1 lb. and a load-cell. After 24 hrs., the swell pressure was 6.1 lbs. The load was increased to 50 lbs.; and, under constant strain, the specimen was allowed to relax for 1 to 6 hrs.; the residual load then was recorded. Then the load was removed and the residual strain recorded (usually 20 to 30 minutes after unloading). This procedure was repeated with five additional, 50-lb. increments of loads; the maximum load was 300 lbs. The resulting strain-hysteresis data were plotted as shown in Fig. 6. The relaxation loads after a time (1 to 6 hrs.) are shown plot­ ted against applied load, in Fig. 7. There, the deviations from the line of equality indicate the relative creep-relaxation of load with respect to the applied load and time. From these data, the relaxation modulus, G, was calcula­ ted from the equation given below.

G = P/3 A e1,

in which: P = Applied Load A = Area of Specimen (after straining) el = Strain (from original height of specimen)

The respective moduli for old and new wood are:

Old White Oak (From Cores)

50 lb. load: G 2398 psi (60 Min) 100 lb. load: G = 2856 psi ( 164 Hin) 150 lb. load: G = 3834 psi (110 Min) 200 lb. load: G = 4668 psi (75 Min) 250 lb. load: G = 5596 psi (360 Min) 300 lb. load: G = 6348 psi (70 Hin)

New White Oak

58 lb. load: G = 7145 psi (62 Min) 100 lb. load: G = 7903 psi (60 Min) 150 lb. load: G = 9371 psi (60 Nin) 200 lb. load: G = 10,501 psi (61 Nin) 250 lb. load: G = 11' 572 psi (68 Hin) 300 lb. load: G = 13,096 psi (65 Nin)

Finally, after a period of rest, the specimen \vas loaded at a constant rate of strain (1/1000 in. per min.) while monitoring the load. The resulting stress-strain graph is shown in Fig. 8. The effects of the previous strain history of the specimen is evident in the lotver portion of the curve; some collapse of internal fibers undoubtedly occurred during previous loadings;

-8- thereafter near-linearity is resumed. Also shmvn there is stress-strain curve obtained from successive, quick applications of 50-lb. increments of load (from Fig. 6 ).

Comparative compression graphs obtained from similar tests on a specimen of new white oak are provided for each of the test situations. Significant differences between the old wood and new wood are:

1. 'fhe old wood was kept wet except for slight drying while shaping the specimens; the new wood specimens were shaped and then soaked for five days.

2. The specimen of old wood contained 19 rings and 13 rays per inch; the new wood specimen contained 9 rings and 9 rays per inch.

-9- 240

220 OLD WHITE OAK

200

180

160 ... 140 £! 120 w w 100 LOACED POINTS w ~ f- w 80

60

40

20

0 0 .3 . 4 .5 .6 .7 .8 STRAIN(%)

NEW WHITE OAK 220

200

180

• 160 ....,~ ,.~ 140

120 w"' 0: 1- "' 100 eo

60

40

20

0.1 0·2 0.3 0.4 0·5 STRAIN(%)

Fig. 6: Strain-Hystere&iQ Tests: Old and New Wood. Arrows show cycling of loads; points show total strains with respect to original height of specimen. Residual strain points show the unrecovered strains from each load-rebound cycle. 10 020~ OLD WOOD

CCC 70 min. '""

"' 360mln. • " "'

~ ,00 7~mln.

e '" '"' '" ~ 110 min. "' 5 '"

w 164 min

Llno of Equality "' (~ookean Ela•tlolty)

60mln

•,!"-c,70-c,c,-,c,~c,70 -"c,,c,~,~.~c,''•~,c.,~c,,~,~,c,c0~,, RELAXED LOAD ( 11>5.)

'" NOW WHITE OJ\K 65mln. '"

6Smln '"

slmln . ~ 200

•," ~ ISO ~ 60mln c g 120

60mtn. Line ol Equality (Hookoan Elo•tloityl

62 min.

'" '" '" '" RELAXED LOAD ([bs.)

Fig, 7: Relaxation or Subsidence of Load - Due to Creep.

ll STRESS Vs STRAIN 240 OLD WOOD

220

QUICK STRAIN, 200 LOAD APPLIED INCREMENTALLY, ~ 180 (FIG. 6) 'vo/ I 160 I I l' IOOO IN PER MIN., CONTINUOUS 140 I I ...... 120 ·- ~ 100 I I w eo ""' w w

~ 60 "w 7 ·I 40 I

20 / / " 0 - .6 .7 .8 .9 1.0 I. I 1.2 1.3 1.4 1.5 1.6 .4 .5

STRAIN {%)

260

NEW WHITE OAK 240

220 f I I 200 I QUICK STRAIN, / LOAO APPLIED I leo INCREMENTALLY,/ ~= (FIG. 6) I ',; 160 !.-->I ¢ I " 140 I "' I "f IOOO IN PER MIN., CONTINUOUS w"' I 120 I "'t;; / I 100 /' / / / eo ;{ / 60 / /

40 /"/

20

0 0 0-2 0.3 05 0-6 07 o.e

Fig. 8: Stress-Strain Curves Obtained in Triaxial Test Apparatus (20 psi lateral pressure) Following Creep-Relaxation Tests.

12 ANATOMY OF VJOOD

The inner struc[ure of white oak >·IOOd is similar to that of red oak, but wrtite oak has perceptibly more abundant tyloses filling large spring-growth tracheid. Fig. 9 is a cross-sectional view of new wood (magnified 13.5 times). The parts are labeled. It is reportedly possible to blow air through the pores of a short length of red oak whereas the pores in ~1hite oak are plugged with tyloses. Tyloses are an intrusive growth of parenchyma cells into tracheid cells after sap flow subsides. Tracheid comprise the principal vertical (axial) piping system; they feed smaller, horizontal (radial) tracheid, These occur principally in the rays. The rays are discontinuous in the vertical direction and are an inch or more in height in white oak,

The porous springtime growth and the rays >

Fig. 10 is a companion to Fig. 9 and shows a side view of the same specimen.

Figs. 11 and 12 illustrate dark wood core specimens.

Fig. 13 is bright wood from Pier No. 2 and is comparative to Fig, 12.

Fig. 14 illustrates the pine in cross-section,

-13- Radial Rays (9 per inch)

Late< Wood Annual Ring (9 Tyloses per inch) (White -­ Plugging Material)

Fig. 9: Cross-Sectional View of New White Oak Magnified 13.5X.

1. Annual rings are large vertical pores (tracheid) produced by early spring growth; as growing season progresses additional pores form but become successively smaller and farther apart. The late wood growth is more dense and is stronger.

2. Radial rays are horizontal cells and lateral conductors of sap; they act as a lateral (radial) piping system. Rays are discontinuous in the vertical direction; each bundle is about one inch in height.

-14- Axial Direction

'-kay (Discon­ Tracheid ...... (Discon­ ~ tinuous) tinuous) Tracheids (Pores)

.....___Ray

Fig. 10: Side View of Ne''' Vlhite Oak, Magnified 13.5X.

1. Tracheids, (Pores) filled with tyloses.

2. Ray; radial pores are not visible at this magnification.

-15- l1agnified 17.5X. Fig, 11: Cross Sectional Vie" of Dark \,~ood from Pier No, 2, Note greater abundance of large pores; specimen contains 17.5 rings per inch and 10 rays per inch.

~~------Axial Direction------._

1'racheid (filled) Ray-

5X, Greater Fig, 12: Side View of Dark vlood from Pier No, 2, l1agnified 17. abundance of large pores are evident here also. -16- _,,_____ Axial 1)irPr1-inn -----~

~Ray

Tracheid ("ith >Tyloses)

----Ray

Fig. 13: Side Vie" of Bright \>Jood from Pier No. 2, Hagnified 17 .SX.

Early_ ~Armual Wood Ring (Late Wood)

Fig. 14: Cross-Sectional View of Pine from Pier No. 2, Hagnified 17 .SX. In contrast to hardwoods, strength of conifer woods increases as the number of rings per inch increases.,

-17- DISCUSSION

The wood specimens tested were necessarily selected from portions within the cores which were recovered intact -- that is, showing the least internal damage (fraying, etc,) from the cutting bit. It should be recognized that there was not complete recovery; the possibility remains that the recovered portion of the cores, and thereby the specimens tested, represent only the best wood, This situation seems unreconcilable unless, through insight or conjecture, the imper­ fect recovery is attributed altogether to the coring equipment,

The only specimen of pine available in cores as received (specimens submit­ ted to Forest Products Laboratory were selected from cores beforehand) contained a large knot and was not suitable for physical tests,

No specimens of yellow poplar was available. The tests were, therefore, limited to the white oak wood,

The simple compression tests and the relaxation moduli indicated an appar­ ent loss of strength in comparison to new wood, If it were assumed that the old wood was originally as strong as the new wood, the differences in strength might be attributed directly to age, deterioration, decay, etc, However, there are significant reasons, based on anatomical or structural comparisons, to suspect that the new wood is superior to the original quality of the old wood and that interpretation of strength differences as a loss in strength of the old wood is not altogether justifiable, The old wood contains about twice as many porous rings per lineal inch as the new wood, Strength varies in some inverse propor­ tion to the number of rings per inch -~ probably more discretely with the per­ centage of the area occupied by large pores, Visual comparison of Fig. 9 with Fig. 11 suffices to show that the new wood and old wood are not identical in these dimensional attributes. A cursory ratio of 2:1 would, indeed, minimize the strength loss attributable to deterioration of the old wood -- that is, if wet-strength loss is used as an estimate or measure of deterioration, Air-dry strengths further minimize the extent of deterioration,

NOTE 1: In weighing these observations, attention should be directed also to Forest Products Laboratory's report and the discussions there concerning losses in acetyl content and the implied relationship between these chemical changes and strength,

On the basis of these observations, the loss in wet strength with time might be i~ the order of 25 percent -- part of which may be accountable in terms of saturation (cf. acetyl loss, FPL reports) and an undefined portion to bacterial decay (cf. FPL reports).

NOTE 2: The design bearing pressure was less than 100 psi (cf, Burr),

NOTE 3: There seems to be a noticeable degree of uncertainty implied in the FPL reports in regard to strength loss, "Inadvisable" was the word used in the FPL report of September 1970, to summari.ze

-18- all uncertainties bearing on re-use of the pier. In the earlier report, the term "not be depended on11 was used.. These same un­ certainties appear in the FPL evaluation of pine piles under the 14th Street bridge in washington, D.C. (see Item 3, Appendix II). The judgments rendered there were doubtlessly precedential.

Tlv source of the white oak timbers is now unknown. Obviously, the new Hood :;recJ in an environment distinctly different from that where the old wood gre;;. It would be interesting to knoc1 if the old wood came from virgin forests in rr;ore northern climates or if the new wood specimen is merely typical of second-growth timbers.

-19- APPENDIX I

A. LOCATION OF CORES

B. THE H.C. NUTTING COMPANY'S TEST BORING REPORTS Cincinnati

N.W. N.E. 0 0 2nd. 3 rd.

s.w. Aborted Holes 0 ®® I st.

SCHEMATIC LOCATION OF CORE HOLES TI!ID'I'INIII I!NII!IINIIII!M N\11:1 111011. I:II:INIIIIUI.TAN11!1 • IIIINCII1H1 410110 Ai!O!i"'m" IO!CAfl:l • CINeiNNATI, CHIC - • Till.. 11111B-111!111-111111CI

"Ail A UU'I'UAL NO't'IICTION YO CL.tllltft'IB. TM8t PWUC. ANO CMBfll:IHH.VU. ALL ~ AU 8UBIIII'i"''Rt All 'flitft CONiriDIENnAL ~ 01' GUIINY'fl, AND AUTMORIZATION IFt2fi ~OA'ftOfll W MA~, ~~ Ga: U'l'1llAC'I'IJ PIKN4 0111 Rll:fiARDUIII OUR R!IPOft"fGl Ill ~ ~- l!,lUIIt ~ ~AL. •• 7-8-70 - kg Pa~~te 1 of 3

CUENT ______Haze let: & F.rdal MI:lm No. ____..;;;..;;_;;.;;;.;; 1021•, 25 __

PROJECT Inv.of S.Pier of C&O R.R.& Cov,to Cinti. Hwv, llridp:

OIIILLEII_w_._M_o_o_re______DIIILL No, __2_5 ___ Dii'I'E IITMTE0 ___;;6_-;;;.24-.;.._;7..;;0 __ _

ELEVATION REFERENCE ---..;~ro'it;,.>igc::i;;,v.::;;e1:.:.'------DATE OOMI'LETEI:l __;::.6-...;2::;6::.-...;7_,0'--- CASING: DIAI.IETEII 3.5ni.,D, HMIMER WT. I'ALL. ______IWIIPLEII:DIAMETEII&TYPE2"o.D, Split S"oon & Nli~ & 13XM HAMMEIIWT. FALL------DEPTH TO WATER: IMI\IIEDIAT£ ______... /_,C,.o:,or_,e,_,l!"-'a..,r.._r,.e_.l __UII'Ofl COI\IIPLETION-----==--~=--- DEPTH TO WATER DAYS AFTER COMPLETION WAT£11 UIIEO 11'1 MILLING Fr0111 8 •0 ' TYPI! REVATION DEI'TH DESCRIPTION OF MA-IAI.II t!A&IPIJ! t!A&IPIJ! 01' ..... DP'I'II t!A&IPIJ! :::: ...... O'

o. 2' Blacktop 0.2' o. 8' Cr.ncrete

1.0' 7. 0. Void

8.0' 8-14.5 NXM 100% 6.5' Layered san~stone and concrete

14.5' 14.5-24. NXM 92% 10,0' Layered sandstone and concrete

24,5' 24.5-34.J NXM 100% 10.0' Layered sandstone and conr.rete

34eJ' 34,5-44 • .5 NXM 78% 10.0' Layered sandstone and concrete

44.5' 44,5-54.5 NxM 97%

RE.IdARKS: Form 504A-10-58 Page 2 of 3

PROJECT Inv, of S, Pier of C&O R. R. & Cov. to Cinti. Hwy, Bridge HOLE No. __...: 8...:•'--CW..:.'------

TYPE BLOWS PER DESCRIPTION Of MATERIALS SAMPLE SAMPLE OF No. DEPTH SAMPLE . .::._gN•~ or o co_re Hec.

Layered limestone and concrete

54.5-64.5 NXM 100% Layered l.itues tone and COl.Hitete.

64.5-74,5 NXM 98%

~ayered limestone, ·sandstone and concrete

7 4. 5-84.1 NXM 98% Layered limestone, sandstone .and concrete

84,5-94.1 NXM 100% Layered limestone, sandstone and concrete

94; )-104 5 NXM 100%

L~;yered limestone, sandstone and concrete

104.5-114,5 NXM 100/~ Layered limes ,tone , sandstone an.d concrete

ll4. 5-121' 5 NXM 75% Con{;rete

124.5-134.5 NXM 92% Conc:re.te I 134.5-139,5 NXM 50% Concrete

139.5-11,9.5I NXM 100% Concrete I 149.5-151 NXM Wood

151-153 BXM

l,~h)Od

' 1 153-.~.55 ! BXH \ f, ~ I• I l I. i ! I' I ' ! I Fonn 504A-10-58 Page 3 of 3

PROJECTinv.of S,Pier of C&O R.R.& Cov,to Cinti.Hwy, Bridge HOLENo, _____s_. __ W~·------

TVP£ BLOWS PER ElEVATION DEPTH DESCRIPTION OF MA'f'DtiALS SAM PL.£ SAMPI.E OF .... DEPTH SAMPLE .~:.~tt. ... 1.53 .0 "'"' .. 2.0' Wood

155.0 155-158 l!XM 3.0' Wood

158.0 158-160 ss 90 H.B. 2.0' Gray fine sand, moist - medium dense

160.0 Refusal at 160.0' on concrete

No water return

Wood samples retained by Hazelet and Erdal

BORING COMPLETED

I I -1orm No. 504--1 {)-58

TESTING ENGINEERS AND SOIL CONSUL.T ANTS o SINCE 1921

4120 AIRPORT ROAD o CINCINNATI, OHIO 45226 • TEL.. 1.513-321-1591Ei

All THE "A$ A MUTUAL PROTI!CTION TO CLIENT&, THE PUBLIC, AND OURS!!LVI!S, ALL REPORTS ARE 8UISMITTED CONFIDENTIAL PROPERTY OJ' GLII!NTI!I, AND AUTHORIZATION FOR PUEILICATION OF STATEIIII!l:NTS. CONCLUSIONS, OR EXTRACTS FROM OR MOARDING OUR REPORTS IS RII!:SERVED PENDING OUIII WRITTEN APPROVAL." 7-8-70 - kg Page 1 of 3 TEST BORING IIEPOIIT

.....::;1;.:0.::2...:4..:.•::.25:::..._ ___ CliENT_ Il<1zelet & Erda! ORDER No. ___

PROJECr Tns:...':_f S,Pier of C&O R.R.& Cov,to Cinto.Hwy. Bridge HOLE No. _____N;.:.:_• W::..:.• ----- lOCATIOl'i ...... ~c;rthwest quarter section of hi.ghway bridge pier 2 DRil.LEfL_~:.:J':_::M:_: 0:.;0:.:r:.:e:..______DRILL No. __z_S __ ~ DATE STARTED, ___:6:...-..:2:.: :...-.:.7..:0___ _

2 _ ELEVATION FifFERENCE ____:;;N..:o_;t~g..:i.;,v..:e::::n ______DATE COMPLETEDo _ _:6:...-.::.:.:6:._-...:7..:0:.__ __ CASING: DIAMETER ___~,_,.::3~·.:::5_.:;Ic.:•.;Dc.:·_~---=~~==- HAMMER WT. ____ FALL _____ SAMPlf.ll;DIAMETER&TYPE2"0.D, Split Spoon & NXM & BXM HAMMERWT. FALL ______DEPTH TO WATER: IMMEDIATE ______,/c;C~o"-r"'e"-B~a.._r.._r_,e.=1 __ UPON COMPLETION:------Frotn 8 O' DEPTH TC WATER DAYS AFTER COMPLETION WATER USED IN DRILLING ___-=•••·~N'<•"" .. ,...... ,_~. TYPE BLOWS PER Recovery ElEVATION ij)(f"TH DESCRIPTION OF MATERIALS SAMPLE SAMPLE OF 6" ON I No. DEPTH SAMPLE SAMPLER I ()I ., o Core~ec . o. 4' Blacktop

o. 4' 0,6' Concrete 1.0' 7.0' Void

8.0' 8-14.5 NXM 100% 6.5' Layered sandstone and concrete

14.5' 14.5-24. NXM 96% 10.0' Layered sandstone and concrete

24.5' 24.5-34.5 NXM 100% 10.0' Layered sandstone and concrete

34.5' 34.5-44.5 NXM 98% 10.0' Layered sandstone and concrete ' /44,5 I 44.5-54.5 NXM 92% i I ' I

NG CO. :S.;.Mnph:r~.- :·:, :_·;yv-r;;,.~<, ~'rrr· Pw; ~-,zl 'G.:-;nng ers nf !Md be:~ in the horin~!. ~ Form 504A-10-58 Page 2 of 3

PROJECTinv,of S.Pier of C&O R.R.& Cov,to Cinti.Hwy, Bridge HOLE No. __..::N;..:•~W..::• ______

TYPE SLOWS PER DESCRIPTION OF MATERIALS SAMPLE SAMPLE OF ELEVATION DEPTH No. DEPTH SAMPLE .~:.~'t- or % Core----.rec. 4/,. ~·

10.0' Layered sandstone, limestone and concrete

54.5' NXM 92% 10.0' Layered sandstone and concrete r·'·"·, 64.5' 64.5-74.5 NXM 96% 10.0' Layered sandstone and concrete

74.5' 74.5-84.5 NXM 95% 10.0' Layered sandstone and concrete

84.5' 84.5-94.5 NXM 98% 10.0' Layered sandstone and concrete 100% 94.5' 4.5-104. r; NXM 10.0' Layered sandstone and concrete

104.5' 104.5-111 .5 NXM 75% 10.0' Layered sands tone and concrete

111>. 5' 114.5-12 .5 NXM 77% 10,0' Concrete

124.5' 124.5-12 ,5 NXM 90% 5.0' ConcretP. 47% 129.5' 129.5-13 .5 NXM 5.0' Concrete 75% 134.5' 134.5-14 ,5 NXM 10.0' Cont::cete 63% 144.5' 144.5-14 .5 NXM 5.0' Concrete Approx~ lv,g. s' 149.5-151 NXM 85 .I 1.5' Hood I I ' ' I 85 ! ., t;. ·1 r, ~~ 151-152.5 EXM I ~ J. ,, -~- rc •.! ~ ~ ' . i. ,. --) -·' ' Form 504A-10·58 l' age 3 of 3

PROJECTinv,of S.Pier of C&O R,R,& Cov.to Cinti,Hwy, Bridge HOU: No., __..:.N:.::•....:.:.~~'.::.• ------

TYPE III.OWS """ DEPTH DESCRIPTION OF MATERIALS SAMPLE SAMPI.E Of ~" ON ElEVATION .... SAMPLE 111 152.5. """" or ......

1.8' Wood Aptorox.

154.3. 154.3-155 .3 BXM 85 1.0' Wood

155. 3' 155.3-15€ , 8 BXM 85 1. 5. Wood

156.8' 156.8-15 ,2 BXM 85 o. 4' Wood

157.2' 157.2-15 .s ss 180 0.3' Concrete

157 .s Refusal at 157,5' on concrete

No Water Return

No Voids Noted

BORING COMPLETED

; '

l Tii!STINC!!J I!Nt!UNII!I!!A8 AND SOIL. CONSUL.TANTS e SIN.CI! 1921 4"120 AlftPOII'n" ROAD • CINCINNATI, OHIO 4622CS " TIIIU ... B13-321~881G!I

li!UIIIINIT"t'ED Alii YMII "All A MUTUAL IIIIIO'fltCTION TO CLIBN'fil, 'fMII PUI!I!LIC. AND OUIQO!ILYIUI. AU. ~ AM CONCLU&IONIII, CONIII'Iaawr&A&. PROPERTY Ofl' GUBNTtll, AND AUTHORIZATION FOfil PUIDUCA'YION Ofi' 8'1'AT'III:f41ENT8, AWRO\IA.L." 011 liUlTIIACft FitOM Ofil RIICIARDING OUR MPORTIII 18 liltii:URW:O "IIIDING OW WAI'I'1"KN 7-8-70 - kg Page 1 of 3

___ CLIENT __H_a_z_e_l_e_t_&_E_r_d...;a_l ______OI'IDER No. ____::1.:.02;:;.4...;':..:2:.:5:.__

PROJEC~nv,of S.Pier of C&O R.R. Cov,to Cinti,Hwy, Bridge HOLE No. ____..::;N:.;•_::E.:..• ----

__ LOCATION __N~o.:.r.:.t.:.h.:.e.:.a.:.s.:.t~q~u:.:a:.:r:.:t:.:e:.:r~s:.:e:.:c:.:t.:.i.:.o:.:n~o;:;.f_h.:.i.:.g~h.:.w.:.a.:.y~b:..:r:.:i:.:d~g~e~p:.:i.:.e.:.r ______

DRILLEII_...;C::.:•:.....;;C::u=e._y_&:::....;W.:.•:....:.M::o::::o::::r.::e______DIIIll No 28 II 25 DATE STAIITED __...;6~-"'1"-'7:..:-:..<7_,0:.__ __

ELEVATION REFERENCE ___;;Nro'"it~g:.::i.;;v.:;en~------DATE COMPLETED, ___,6_-;2;e.8-_7'-'0"---- _ CASING: DIAMETER J,S"I.D. HAMMERWT. FALL ______SAMPLER: DIAMETER & TYPE.=zc..".::;O,_,D:.:..• ...:S:aP:.::l:.:i:.::t'-"'S"-poo=n"-'&'-'iNXM!';:.::....::.&_.B,X..,M.:_..,-JHAMMER WT. FALL ______DEPTH TO WATER: IMMEDIATE /Core Barrel UPON COMPLETION-----::---:-...,.-;--- WATER USED IN DRILLING From 8 .0' DEPTH TO WATER DAYS AFTER COMPLETION TV I'£ BLOWS PER Recovery DESCRIPTION OF MATERIALS SAMPLE SAMPLE OF ELEVATION DEPTH No. DEPTH SAMPLE ..:~~L'lR O' Df'% ~re K.c.

1.0' Blacktop and concrete 1.0' 7. 0' Void

8.0' 8-17 NXM 94%

. 9.0' Layered limestone, sandstone and concrete

17 .0' 17-25. 5 NXM 59% 8,5 1 Layered limestone, sandstone and concrete

25,5' 25.5-30 NXM 100% 4.5' Layered sandstone and concrete

30.0' 30-35 NXM 100% 5.0' Layered sandstone and concrete

35,0' 35-40 NXM 80% 5.0' Layered sandstone and concrete 4o.o ' 40 -45 ' NXM 100%

II~MARKS: Reopectlully oubmit!ed, THE H. C. NUTTING CO. Samples recovered from this test bnring are available for inspection, which is strongly recommended, The company assumes no responsibility for interpreta­ tions made by others of load bearing, stability, excavating or other physical Bys?G~ characteristics of materials penetrated in the boring. 504A-10.58 l'orrn Page 2 of 3

PROJECTinv.of S.Pier of C&O R.R.& Cov.to Cinti.Hwy,Br1dge HOLENo'----~N~·~E~,~------

TYPE BLOWS PER 6'" ON ELEVATION DEPTH DOCRIPTION Of MATimALS SAMPLE SAMPLE OF .... DEPTH SAMPLE 40.0' ...... """' ROC.

5.0' Layered sandstone and concrete

45.0' 45-50 NXM 100% 5.0' Layered sandstone and concrete

50.0' 50-55 NXM 100% 5.0' Layered sandstone and concrete

55.0' 55-60 NXM 100% 5.0' Layered sandstone and concrete

60.0' 60-65 NXM 100% s.o• Layered sandstone and concrete

65 ,.()' 65-72 NXM 100% 7.0' Layered sandstone and concrete

72 .o• 72-82 NXM 97% 10.0' Layered sandstone and concrete

82,0' 82-92 NXM 87% 10.0' Layered sandstone and concrete

92.0' 92-100 NXM 93% 8.0' Layered sandstone and concrete

100.0 100-107 NXM 100% 7.0' Layered sandstone and concrete

107.0 107-117 NXM 94% 10.0' Layered sandstone and concrete

117 .o 117-127 NXM 35% 10. 0' Concrete u: .ni 127-134 N:01 36% 17. ()' (<)n-;.:ret:e 134-142 NXM 25% 134. ot I Form 504A-10-58

PROJECTinv.of S,Pier of C&O R.R.& Cov, to Cinti.Hwy. Bri~ge

'fVPI! IDLOW'S NA ELEVATION DEPTH DESCRIPTION OF MA1'UIAI..S ISAYPU SAY.._£ .,. ,. 01'1 DUTil !SAYPU 134,0 .... ~

8.0' Concrete

142.0 142-149 NXM 0 7.0' Concrete Approx.

149,0 149-150 BXM 611 1.0' Wood

150.0 lSD-152 IIXM 68 1.0' Wood

151.0 1.0' Wood

152,0 152-154 IIXM 68 2.0' Wood

154.0 154-1.56 !IXM b!l 2.0' Wood

156,0 156-157.3 BXM 68 1.3' Wood I ~57.3 157.3-157.5 ss 130 0.2' Concrete

157.5

Refusal at 157.5' on concrete

No water return

No vo1 ds noted

BORING COMPLETED

I i

I I' I I APPENDIX II

REPORTS OF FOREST PRODUCTS LABORATORY

1. September 1970

2. Rec'd May 21, 1970

3. 14th Street Bridge over Potomac River, V/ashington, D.C.; Wood Preserving, AWPI, January 1970. 9/1970

REPORT OF CONDITIONS FOUND Il'l ADDIT:::ONAL SAMPLES TAKEN IN JUNE 1970

FROh THE PIER-SUPPORTING GRILLAGE OI THE U,S, '25 HIGHWAY-RAILRo-AD :BRIDG!j;,

BETWEEN COVINGTON AND CINCINNATI

By

JOE W CLA.Rl{ 1 Forest Products Laboratory,- Forest Service U,S, Department of Agriculture

Introduction and Background

This supplemental report has been prepared to become a part of the earlier report submitted in May 1970. Xhat report ~as based on sample core$ taken in January 1970 and obtained from a single hole bored through on ~he grillage timbers. This supplemental appraisal has been made sample cores obtained in June 1970 from two additional borings through tne grillage members, The June samples were frozen ana held in cold storage, including refrigerated (dry ice) packaging, for shipment to the

Lab prior to examination in contrast to alcohol PLckling which was used with the January samples. As indicated in the May report, there was a question of sample adequacy using only the Januarv cores taken from a single hole through the grillage. The cores taken from the two additional i.oles in June have largely confirm<'d the earlier findings and have provided some additional information.

1 of ~intained at Madison. Wis •• in cooperation with the University Wisconsin. of Distribution Wood Species Present in the Grillage and the Pattern

holes, the pattern For th€ three sets of cores obtained from as many This includes an upper of wood species distribution nas Oeen ,~he same. member of southern (first) member of yellow-poplar, a lower (seventh) (of the materials examined) yellow p~ne, and the intervening five members has been white oak having been oak, Practically all of the oak examined samples were not heartwood. Some of the interior grillage timber at FPL. represented by the materials received for examination considerable Species distribution in the grillage mass is of very timber as the significance since the placement of the yellow-poplar environment adjacent uppermost member leaves it exposed to the alkaline but highly significant to the poured concrete,which results in a partial also in contact with loss of wet strength. The lower member being pine, species are less concrete, is not so severely affected since coniferous to hardwoods. affected by equivalent alkaline conditions in com?arison there is a single One must assume from the three samples examined that layer of the grillage. layer of yellow-poplar timbers making up the uppermost

Atypically Weakened Wood, Macroscopically Evident

(yellow-poplar) In the January sample, the uppermost grillage member could be was very noticeably weakened and, in the wet condition, to chemical characterized as "mushy" or "spongy." This was attributed hardwood in strongly degradation related to the members having been a a measure of the extent alkaline environment. Loss of acetyl was used as the two sets of cores of such weakening. Both yellow-?oplar samples from of acetyl and this taken in June showed a similar characteristic loss presumably was again attributable to the prolonged contacting exposure of the upper member to the poured-in-place concreue.

Tn the June-collected set of samples the secono grillage timber from the top in hole NE at elevation depth 150 feet was a distinctly softened oak member that was classified as punky in the wet condition,

The sample pieces of this timber in the wet condition offered little resistance to sawing or cutting with a knife. 1t is probably significant that this member was next to the top timber in the array of seven timbers and therefore in relatively close proximity to and below the poured concrete, The small samples of this member checked severely o~ drying• which is a further indication of severe deterioration,

Microscopic Appraisal of Samples

Microscopically, the array of June-collected core samples was very similar to the January cores previously examined, The commonly noted presence of bacteria in practically all of the tissues examined was characteristic of the samples including all three species of wood and unquestionably permeating the white oak heartwood,

Bacteria were unusually abundant in the oak sample cited above where they were literally impacted in all types of cells comprising both the longitudinal and horizontal tissues, It is probable that the severe weakening of this member was caused,at least in part. by the bacteria present.

In both pine samples received with the June cores, the same break• down of secondary tracheid walls in the cells representing terminal growth for the respective annual rings was observed as indicated in the earlier report and illustrated by figures 4 and 5 of that report, Again, no

fungi were detected microscopically in these areas and the wall failures

are thought to result from bacterial attack,

Culture Isolations

The June samples were received in a frozen condition, wrapped in

, and packaged in dry ice, This method of handling the cores

made successful cultural isolations possible and a much larger array of

organisms have been isolated than was obtained from the alcohol-pickled

samples taken in January. The cultured isolates represent vari0us forma

of micro-organisms, including several species of both coccus and rod

forms of bacteria, yeastlike organisms, and actinomycetes. None of

these organisms have been specifically identified,, but such identities are

not essential to the practical appraisal of the present problem, That

the organisms are living in the grillage wood, are present in all species

of the grillage timbers including the qak heartwood, and represent a

large variety of micro-organisms make this aspect of the grillage condition

questionable as regards its proionged future service,

Acetyl Loss in Re?resentative Samples

Acetyl loss, as determined by the Division of Wood Chemistry, was very similar for the last received (June) samples as for the former

samples (collected in January), Loss in the yellow-poplar samples was from one-third to three-quarters of the estimated acetyl formerly present,

It is also estimated that roughly one-half of the acetyl had been lost irom the oak samples. Acetyl losses in the pine samples were again quite

::inimal.

-4- Individual sample appraisals for acetyl loss are shown in the following table, along with other sample data,

Data for Grillage Samples Qollected in June 1970

Sample :Rings: Wood .: Specific: Acetyl : per : species .: gravityl: presend :inch .:

NE l49(A) 12 : Yellow-poplar : 0.426 0.81 NE 150(A) 17 White oak ".449 1.50 NE 156(D) 26 :e••••••do ...... : 2., 758 1.86 NE 156(E) 20 Ye lloH pine .453 ,85

NW 149.5(A): 26 Ye lloH-pop lar .320 1. 19 NW l49.5(B): 26 White oak ,583 1,43 NW l56,3(D): 16 : ...... do ...... : ,379 1,95 NW 156,8(B): 24 YelloH pine .440 1,06

1rhe specific gravity averages or ranges normally to be expected for the three species are as folloH: yelloH-poplRr -- 0,38; Hhite oak -- 0,55~0.64; and southern yelloH pine -- 0,45-0.64. -!illrdwoods2 normally have an acetyl content of from 3 to 5 percent; while coniferous species have much less, Jrhis sample showing an abnormally high specific gravity was ashed and found to contain an above-average content of 8eposited mineral matter',

These levels of acetyl loss ~noicate a very definite loss of wet stre~gth in the most severely affected piece of yellow-poplar examined

&nd could result in compression failures if a comparable degree of weakening becomes uniform across the bearing face of the grillage, Wet strength losses in the oak members have been definite but not hazardous usually; howeve~ they could possibly become critical if additional acetyl loss occurs or if strength loss develops generally as a result of the activity of the microMorganisms, which are abundantly present, Recommendations

In view of the present findings which are essentially similar to the findings reported in our earlier written report, it would appear inadvisable to rebuild the new bridge on the old grillage~supported pier with the expectation that 80 to 100 years of service life ~ ~ assured,

Alternatively, we cannot say with certainty that the grillage will not continue to support the pier adequately for that length of time; but because there has been a very considerable amount of chemical degrade, which may be continuing slowly,and because organisms are still present, which may biologically affect the service life of the structure, it would seem appropriate to rebuild the bridge using a design that would permit, if necessary, the addition of a supporting pier as outlined in our earlier conversations with Mr. Wood and again with Mr. Grayson. CONDITION OF THE PIER-SUPPORTING WOOD GRILLAGE

OF THE U.S. 25 HIGHWAY-RAILROAD BRIDGE

OVER THE OHIO RIVER BETWEEN COVINGTON AND CINCINNATI

By

JOE W. CLARK, Pathologist 1 . Forest Products Laboratory,- Forest Serv1ce U.S. Department of Agriculture

An earlier, verbal report was made to Mr. Robert H. Wood on March 12,

1970, covering the initial results obtained in an appraisal of cored wood samples of the timber grillage received from the Hazelet and Erdal

Company of Louisville, Ky. These samples were obtained from in-place coring of the grillage under the south river pier of the 11. S ..25 bridge over the Ohio River between C9vington and Clncinnati. This large concrete and masonry pier extends 142 feet above the grillage on which it rests, and the grillage occupies an area 79 by 34 feet and is composed in depth of seven layers of 12- by 12-inch timbers. The upper surface of this solid-piled mass of timber is at a point approximately 40 feet below the river surface (water) level and 30 feet below river bottom. The grillage material has been in place since 1890 when the bridge was built. Fol- lowing is the final report giving a full account of our completed apprais- al of the samples ana including results from additional tests not completed or reported at the time of our last verbal with Mr. Wood. lMaintained at Madison, Wis., in cooperation with the University of Wisconsine Physical Damage to the Samples by the Core-Boring Process

The core samples received at the Laboratory for appraisal had been subjected to variable degrees of twisting attributable to the core cutting or boring process. This twisting action. in some core segments, caused much fiber breakage or separation, particularly in the outer 1/4 to 3/8 inch of the core samples. In some cases, such damage extended completely through the core,while in other cases the damage was superficial, limited to the core surface, and considered negligible. The occurrence of such damage appears to have resulted during the boring process from the random packing of the kerf material between the in-place core and the inside sur- face of the core cutting tool as it revolved. "Most of the core samples were firmly encased in such wood fiber compactions when received at the

Laboratory. The subsequent sample appraisals were based exclusively on the interior parts of the core samples which were free from visually detectable twisting deformation.

Microscopic Examination of the Sample Material

Microscope slides were prepared from material taken at different

levels in the grillage. From these slides positive identifications of wood samples were made by Dr. Kukachka, the senior wood taxonomist at the

Laboratory. Of the 11 core fragments examined, nine were white oak, one was yellow-poplar, and only one was yellow oine, although the original

account of the construction indicated that the grillage was constructed of pine timbers.

Careful appraisal ot the material prepared for m~croscopic examination

showed bacteria commonly present in all samples (see fig. 1). Assigning

specific cell-wall deterioration in the wood to these organisms has not

-2- been possible, although some instances of biological degrade of the wood were noted in the pine sample (seefigs. 4 and 5). This type of damage was observed to be present in varying degrees in the latewood cells of most annual rings in the pine that was inspected. Such degrade could be particularly significant in strength loss if gentL~lly present in exten­ sive areas of the grillage members. No filamentous fungi were detectable in association with this degrade, but more sampling WLll be necessary before a reliable appraisal of the pine present in the grillage can be made.

All of the bacteria observed microscopically in the wood sample sections appeared to be coccus forms. All 32 cultured isolates obtained from the randomly sampled grillage cores are rod forms of bacteria (see fig. 2). This suggests that the alcohol solution used for protecting the cores may have killed the coccus forms, observed microscopically, and permitted the culture recovery of only a comparatively resistant or spore­ forming rod form.

Generally, bacteria are thought to cause little deterioration of the wood cell wall material but rather to utilize cell contents and certain pit membranes causing some increase in porosity but little strength loss.

The effects of many bacteria on wood are incompletely known.

In a few cases the hyphae of unidentified fungi were observed in oak members, but these were not profusely developed and may represent dead

fungus infections that were established in the freshly cut timber or during

construction and prior to the covering of the grillage with the resulting

exclusion of air from the material. No fungi were obtained in culture,

although they too may have been killed by the alcohol pickling solution if any were living. -3- Ruptures in the cell walls representing compression failures (fig. 3) were rather common, but it was impossible to establish the exact cause of such defects, Possibly, these failures could have resulted from the twisting action of the core-boring process referred to above. Also, longitudinal seoaration of the wood cells along the primary walls was observed at infrequent points, This, too, could have resulted from the same cause,although material was selected for slide preparation that was free of visibly apparent defects thought to have been induced by the fungi, coring process~ Alternatively, bacteria, actinomycetes, or ~oft-rot capable of preferentially attacking lignin, could possibly account for abnormal weakening of the primary wall and consequent failure under torque loading since the primary wall is predominantly lignin.

Chemical Depositions in the Wood

Portions of the yellow-poplar sample appeared to be crusty and micro­ scopic inspection of such parts showed a crystalline chemical deposition in the wood cells to a depth of 1/2 inch or slightly more measured from what appeared to be an upper or lower surface face of the timber. Two different forms of the deposition were noted; one, a yellowish crystal material, was represented by particles several times the diameter of the largest wood cells. Such crystal accretion in the wood disrupts the cel­ lular structure of the wood and causes very acute localized loss of strength.

Fortunately, such accretions were on1y observed in the single sample of yellow-poplar.

A second form of chemical deposition or accretion appeared as a white crystalline material filling cell lumens in the same general area as the yellowish crystal material noted above. This deposition was also present

-4- in the yellow-poplar only and since this timber represented the uppermost piece of the grillage, it would presumably have been in contact or approx- imately in contact with concrete which was poured over the grillage.

Tests indicated that at least one of the chemicals is likely to be cal- cium carbonate.

Specific Gravity Determinations

Specific gravity of the several samples was det<:>.rmined on the basis of green volume (water displacement) and ovendry weight. The samples tested were approximate cubes cut from the center of solid wood segments of the cores. The cubes were generally from 0.5 to 0.7 inch on a side,

The footage depths at which the core segments were taken served as iden- tifying numbers for the cubes used in the specific gravity determinations; and the results of these tests gave the followingvvalues:

Sample Sample Rings Sample Average or range No. wood per spec~fii of specific gravity species inch gravltx;: for the species --- 2 149.0 Yellow-poplar 32 -o.4s O.B8

151.5 White oak 13 .69 0.55-0.64

152.0 •...• do .•..• , . 16 .62 .55- .64

152.5 •.•.. do ..•.•.. 12 .61 .55- .64 .55- .64 155.5 0 • e •• do ...... 13 .60

156.0 ..•.. do ..•.•.. 14 .64 .55- .64

156.5 Southern pine 28 .43 .45- .64 lspecific gravity determin·ations were made with the help of Harold Wahlgren in the Division of Wood Quality Research, using the specialized equip­ ment in that Division developed for the purpose of gravity determinations, 2 ~his value is possibly high due to probable calcium carbonate deposition.

-5- Acetyl Content Determination

During a conference with Dr. Harold Tarkow, Chief of the Wood

Chemistry Division at the Laboratory, he suggested that the wood grillage, submerged as this material has been in an alkalineenvironment, resulting from the curing of the concrete, could possibly have been adversely and affected by chemical changes in this period of time. The occurrence acetyl extent of such a change is best estimated by measuring the loss of which can be used as an indicator of the change, Wood material varies in this reaction, depending on the species of the wood, the specific the character of the liquid environment as to the chemicals present and changes prevailing pH, and the length of time of exposure. These chemical are somewhat similar to those induced by the cold soda pulping process used in the conversion of hardwood species. Generally, the hardwoods are affected in a shorter period of time and more severely than soft- woods under comparable conditions, as shown in the following table:

Wood species and samEle No, Acet)!l content (Pc t,)

White oak No. 152.0 1.82

White oak No. 155.5 1.77

White oak No, 156.0 1.73

Yellow-poplar No, 1.49.0 • 38

Yellow pine No. 156.5 .89

Hardwoods commonly contain 3-5 percent acetyl while conifers nor- in mally contain much le.ss. Thu's, the results indicate a loss of acetyl been the oak samples of more than 50 percent of what is estimated to have having present originally. The pine sample showed little loss of acetyl,

-6- originally contained an estimated 0.6 to 1.0 percent. The yellow-poplar bad lost perhaps 2"0 mC!ch as 75 percent of the acetyl estimated to have

been present originally, and thus appears to have been seriously and critically weakened.

The significance of this loss is not t~~ obsence of the acetyl, but rather the resulting effect of the total chemical change, of which the acetyl loss is only a part. This effect can be demonstrated by treating wood with dilute alkali to cause elevated fiber saturation levels. Fiber saturation in hardwoods may be as high as 65 or 70 percent moisture con­ tent. This characteristic of wood has been demonstrated and reported by

Tarkow and Feist; a copy of the report is attached and attention is di­ rected to table V, page 82, and the section "Effect of Treatment with

Dilute Alkali," pages 82 and 83. Additional work by W, Klauditz (1957), has shown that wet strength losses as high as 50 percent may result from very short treatments of mild solutions of dilute alkali. Highly signi­ ficant reductions in all strength properties are known to be character­ istic of wood at such high fiber saturation levels.

The fact that dry wood strength is much less affected by these changes is of little consequence in this case since the grillage members undoubtedly remain water saturated in their present position. Inasmuch as these strengch losses are or s1gnificance prima~ily ~u the hardwoods, such as the white oak and yellow-poplar in contrast to the pine of the grillage sampleo, additional sampling of the grillage is highly desirable to determine what wood species are actually present and how the different species are distributed.

Additional corroborative evidence of strength loss in the yellow­ poplar core sample was its "mushy" character, evident in the saturated

-7·· condition by moderate fillger pressure in contrast to a near-normal wood firmness in the dry condition. Further, it may be noted that the yellow­ wet poplar sample had to oe frozen to obtain sufficient rigidity, in the of condition, to cut thin sections for examinatio~while none the other samples required similar support.

Summary of Findings

The several characteristics determined for the grillage samples can be summarized as follows:

(1) Severe twisting of the core samples attributable to the coring

process caused much physical damage in varying amounts to the core wood.

In our appraisal of the cores, we- attempted to avoid such damaged material. resulted There is a definite chance that some of the coring damage may have of from the weakened physical condition of the wood, representing a loss

strength due to chemical and/or biological deterioration. This is very

definitely true for the single sample of yellow-poplar. In the samples during of oak and in the one pine sample, some part of the physical damage

coring may have resulted from chemical or biological weakening, from

random compaction of kerfed fibers and particles, or from a combination

of these two factors.

(2) Identification of core samples showed the predominant wood spe­

cies to be white oak rather than pine as reported in the original account sam­ of the construct1on. One segment of yellow pine was included in the

ples~ 'as a segment of yellow-poplar.

(3) Bacteria of both coccus and rod forms were present in the core

samples as determined either microscopically or by cultural isolation. lignin It was not determined whether the culture isolat3s were capable of

-8- or cellulose degradation, but de~Ln1te degrade of the secondary cell walls of the pine sample was observP.d. Although no fungus hyphae were found

associated with this specific degrade, it is suggested that this is an

example of biological degradation. This type of biological attack was

repeatedly observed in the latewood cells of the pine sample annual rings.

Whether this degradation had occurred prior to, during, or after bridge

construction could not be determined, but it must be considered signifi­

cant evidence of strength loss.

(4) Fungi were observed microscopically in several instances in the

oak samples. No fungi were obtained in 30 culture isolation attempts and

it seems probable that the observed hyphae were the result of infections

having started prior to or during the construction period. Very little

deterioration ot wood cell-wall material was associated with these fungi

in the material exam1ned.

(5) Rupr:ure of a compression-failure type in the secondary wall

of some wood cells was moderately conn•

of oak fibers along the orimary wall was also observed in several samples

Whether these forms of damage were due to bioLogically or chemically de­

graded wood or to the mecnanical stresses imposed by core boring was not

determinable.

(6) Specific gravity determinations for seven samples, including

one pine, one yellow-poplar, and five oaK members, showed no abnormally

low-density ma~erial, although the pine sample was just below the minimum

spec1tic gravity tor the range of yellow pine. The wood samples were

Bpnroximat:elv normal for rates of growth: Oak showed lZ-16 rings p<>r inch

pine snowed 28 rings per inch (a reasonao!y slow growth for th1s species),

-9- and yellow-poplar showed 32 rings per i~~h c~ decidedly slower rate or growth than normal).

(7) A test for chemical changes indicated by acetyl loss in the samples was positive for the hardwoods, but only extensive enough in the yellow-poplar sample to be definitely considered hazardously weakening.

Appraising this factor is oarticularly difficult since there is no way of determining how much more weaken~ng will develop in the future, Nor­ mally, under stable conditions, acetyl loss occurs more rapidly in an initial period and becomes less rapid due to a reduced rate of loss after a prolonged period.

If the additional cores to be taken in the future prove to be largely pine, this Jpecific problem would be considered less sign1t1cant than it now appears to be,

Conclusions and Recommendations Suggested for Consideration

As a general summary, it should be noted that no single factor or combination of factors that have been appraised point to a definite and unequivocal condemnation of the grillage for continued support of the pier as proposed in the reconstruction of this bridge. However, the mar­ ginal character of some factors, the unpredictable degree by which some of these factors may change in the future, and the remaining unknown ent~­ ties due to sample limitations that fail to provide sufficient information on the species of wood presen~ and their distribution in the grillage assembly are ample justification for a recommendation that the grillage not be depended on for complete support of the pier through the service life of the anticipated bridge reconstruction.

-10- Principal considerations leading to this conclusion include "he following:

(1) The sample is inadequate for a broad and reliable conclusion, coming as it does from a single set of cores taken from a single hole in a very considerable expanse of timbers that we must now assume are com­ posed of at least three species and possibly more. Further, the core­ cutting process has introduced a degree of twisting and breakage in the samples that has been difficult to appraise.

(2) Substantial and critical strength loss has occurred in the upper yellow-poplar grillage member as a result of chemical changes, pre­ sumably induced by an alkaline environment associated with the overlyi.,g concrete. Without extensive additional sampling to identify wood species and their distribution, the significance of this factor cannot be accu­ rately appraised.

(3) Additional strength loss has also occurred in the oak samples from the same cause, but the extent of strength loss is con­ sidered marginal. We cannot predict with surety whether or not further significant chemical change in the oak will occur in the next 80 years,

(4) Biological degradation in some segments of the core samples now approach a marginal point in strength loss, Much depends on bow extensive or common such areas may be and whe~r living organisms are

still active. This can only be estimated with additional sampling and culturing.

(5) The probability of additional degradation by either chemical or biological agents with time cannot be predicted with a high degree of certainty. However, assuming no change in the environment surrounding the grill!tge, it is possible that little additional deterioration will occur.

-11- Recommendations

(l) We recommend that numerous additional cores be taken with an improved coring tool to better appraise the species of wood present, their distribution, and their physical and biological condition.

(2) Special attention should be given the uppermosttand lowest grillage members which contact concrete and particula~so if these rnem- bers are hardwoods.

(3) Special consideration should be given in appraising any yellow- poplar members present as to the amounts found and their location or distribution.

Suggestions for a Preservative Application and the Filling of Voids

If the engineers decide to continue the grillage in service and to pressure-fill holes bored on a grid pattern, as previously considered, to eliminate any voids that may now be present above or below the grillage, it would then be our recommendation that, after the holes are drilled and before the consolidating fill is applied, a water-soluble, toxic agent, such as the wood preservative FCAP, be forced under pressure into the grillage interfaces and any other available space. This material is a recognized wood preservative containing fluoride, chromium, arsenic, and dinitrophenol. Such material would presumably, by slow diffusion over an extended period of time, permeate much of the grillage wood and retard further biological deterioration in the treated portions.

This specific toxicant has been recommended by Lee Gjovik of the

Wood Preservation section. The material would be available from either the Koppers Company, Inc., or from the Osmose Wood Preserving Company.

-12- For further information about this product, we sugsest that you contact, respectively, either:

Mr. R. B. Putman, Manager Wolman Preservative Department Forest Products Division Koppers Company, Inc. Koppers Building Pittsburgh, Pennsylvania 15219

Mr. George B. Fahlstrom, Director Research Division Osmose Wood Preserving Co. of America, Inc, 980 Ellicott Street Buffalo, New York 14209 you, Either of these men may have specific advice that could be useful to

Also, you should be advised that chis preservative has been classified as a pesticide under current pesticide regulations. It 1s recommended, therefore, that the appropriate state agencies be consulted before the material is used.

Finally, we would recommend that a fill material having a slightly acid or netural pH be used to eliminate the grillage voids. The addition of more alkaline material could likely cause additional chemical changes indicated by 1oss of acetyl which may otherwise be stabilized at this point.

-13- Figure 1.--Bacteria supported on tylosal membranes in vessel cells of

white oak samples. This particular slide was prepared from oak core

sample taken at the 152.0-foot level, but such oacterial infections

were commnn throughout all the sample materials examined. Notice

the two sizes of bacteria present, both coccus forms but distinctly

different in size. Bacteria observed microscopically were consis­

tently of the coccus form (1200X).

Figure 2.--Bacteria from one of numerous cultures obtained by isolation

attempts from the grillage samples. Similar cultures were obtained

from all samples. These bacteria were consistently found to be

short rod forms occurring either singly or in short chains. No

coccus froms of bacteria were obtained in culture. The absence of

living coccus bacteria in the samples is tf1rought to be due to the

alcohol pickling of the wood samples.

Figure 3.--Radial section of oak from a depth of 155.5 feet showing cell·

wall compr~seion failures. This physical defect could not specifically

be attributed to any single tor combination of causes with certainty,

but such faults represent a s.ignificant decrease in strength. See

text for possible explanation of ~ause (1200X).

Figure 4.--Cross section of pine sample (156.5 ft.) showing cell-wall

deterioration in the last three to 10 tracheids of an annual ring.

This cond1c1on was observed repeatedl} 1n this sample and may be due

to biological (enzymatic) breakdown of the secondary cell wall.

Whether such action has been the result of fungal or bacterial action

was not determined, but from a practical point of view, tt makes

little or no difference--the end result is weakening of the wood.

Normal cells are designated by~ deteriorated cells by~ (380X).

Figure 5. --A second view ot the cell-wall deterioration

in the pine sample shown at a greater magnification

(1200X). Secondary cell-wall material deteriorated

in cells marked ..!2• cell walls normal in cells marked ~·

Purchased by the Forest Products Laboratory, U.S. Department Of Agriculture, for offici"al use

HAROLD TARKOW The Superswollen State of Wood and WILLIAM C. FEIST

THE colloid chemist uses the term Ihe suggestion is made that the changes of certain physical and chemical properties ((limited swelling gel" to describe a· of wood on mild pulping are caused by increased plasticization (fiber saturation material that has a limited but reversible point). A quantitative procedure is described for measuring the fiber saturation swelling capacity. The classical ex­ point of wood substance following such chemical tre-atments of wood. Conv~ntional ample of this is agar, in which swelling pulping procedures raise the flber saturation point of all species of wood. With is limited by restraints imposed at the dilute alkali (1-2% sodium hydrvxide) treatment, a marked difference is noted be­ time of gelation. In this sense, wood tween hardwoods and softwoods. Softwoods are essentially unaffected by the substance is a limited swelling gel. treatment. The fiber saturation point of the hardwoods doubled. Chemically, The restraints in wood substance that this is accompanied only by deacetylation and an appreCiable increase in free corm limit swelling are "cross-links" com­ boxyl content, which suggests cleavage of polyuronic ester bonds. The highly posed of crystalline regions, of hydrogen­ swollen condition can be recovered following air-drying~ Wood in this super· bonded regions too small or irregular swollen condition should have the potential for novel uses. to be detected by X-ray diffraction, and possibly of primary valence bonds Keywords: Fibers · Saturation · Swelling · Penetration · Cellulose • Hardwoods • between polymeric components. ThBse Softwoods· Wood pulps· Chemical pulping· Deacetylll.tion · Polyuronides· restraints were introduQed when the Chemical bonds · Carboxyl groups · Esters wood substance formed and ~'gelled" during secondary thickemng of the cell wall. The properties of whole the wet structurally intact holocellulose. Apparently the 11 normal" lignin that is wood Suggest similarity in swelling 1 capaci-ty -of wood substance. Volu­ His data are summarized in Table I. present does not necessarily preclude metrically, it is about 45%, The Delignification reduced the green additional hydration. fiber saturation point of most sfi,ecies, tensile strength of wood by about 85%. Confirmation and extension comes from work by Lagergren et al. (3). because of the constant density of wood Similar reductions were found for bending and compressive strengths. The wet tensil.e strengths of a hardwood substance, is 30-40%. Klauditz interpreted the results in terms and a softwood treated with 2.5% In this paper, q, brief review of the sodium hydroxide for 2 hr (room tem­ effect of certain chemical treatments of a "hydrophobic action of the lignin," perature, unwashed) were measured. on some properties of green wood is which means the removal of the lignin given, followed by a description of a allowed for an increased moisture The hardwood lost 75% of its wet procedure for quantitatively mee.suring adsorption. strength; the softwood lost only 17%. Thus, the hardwood is much more the fiber saturation point, and a dis­ Klauditz also 'studied the effect of cussion of the probable mechanism re­ dilute alkali (2). Sticks of green wood sensitive to alkali. It is recognized sponsible for the observed increase in were immersed in 0.2% sodium hy­ that satisfactory cold soda pulps can" fiber saturation point. This condition droxide, washed, and the wet tensile ·not be made with softwoods. of the swollen substance with the in­ strength was measured. creased fiber saturation point is referred After 10 hr, although the yields were Effect of Treatment on the Anisotropic to as the 11 superswollen state." about 94%, the wet strength had dropped at least 50%. About 60% of Diffusion Characteristics of Water~ the 6% loss. in yield was due to loss in So/ubi~ Electrolytes REVIEW OF LITERATURE acetyl content. Thus, with the loss of Effect of Certain Mild Treatments on the only 2-3% of basic substance, an The diffusion rate (D) of a water­ Strength of Green Wood appreciable loss in wet strength had soiuble material through water-logged The wet strength of green wood i;B occurred. Klauditz attributed this to wood is a highly anisotropic property. an increase in hydration capacity re­ Dlon itudinat/ about 70% of the dry strength. The According to Stamm (4), 11 sulting from a loss of acetyl groups. wet strength of paper is 1-5% of the Dtrnnaverae (Di/Dt) is _about 15. Be- dry strength. Klauditz (I) stated that an explanation in terms of simple de­ lignification would be inadequate, be­ Table I. Wet Tensile Strength of Structurally Intact Holocellulose --::::-:-- cause fiber-separation and reconstitution Reduc- are also , involved. He treated green tion in .$ticks (0.3 by 3 by 16 em) with acidified Wet wet ~odhun chlorite, washed out the chem­ tensile tensile ical, and measured the strength of Yield, Lignin, Pentosan, Acetyl strength,"" strength Species % % % % kg/cm2 % Beech 100 23.3 23.4 4.84 919 Beech holowood 77.8 3.1 28.4 6.32 116 87 HAROLD 'rARKOW, Chemist, and WILLIAM C. Aspen 100 23.3 20.9 4.53 442 FEIST, Chemist, Forest Products Laboratory, Aspen holowood 76.0 1.9 27.6 5.81 75 83 Forest Service, U. S. Dept. of Agriculture, Madi~ lon,-Wis. a Based on wood area. Concln"iQne were similar when based on e.rea of cell wall. Reprinted from Tappi, The Journal of the Technical Association of the Pulp and Paper Industry, Vol. 51, No.2, Feoruary 1968. Copyright, 1968 by TAPPI, and reprinted by permission of the copyright owner Table II. Diffusion Characteristics of Water~borne Solutes in Modified Wood Relative Yield, Increase in Liefer- 2 2 D, ence"' Wood Treatment % D 1, cm /sec Dt, cm /sec D, Dt,% 1 (5) Softwood None IOO 0.8Xl0 0.02 X 10 • I 0.033 ~sodium chloride)h 330 (6) Softwood Sulfite 9I (potassium chloride) I O.I4 Sulfite 85 (potassium chloride) I 0.20 500 (6) Softwood I300 (7) Softwood Kraft 60 o.84 x w-• o.36 x w-• I 0.43 (sodium hydroxide) (sodium chloride) I 0.046 40 (8) Softwood 6% NaOI! (9) None IOO (sodium ion) I O.I6 Hardwood 500 (9) Hardwood 20 hr at pH (buffer chemical) I 0.78 13.5, 25 9 C s Numbers refer to Literature Cited references. b Diffusing chemical shown in parentheses.

cause of the high ratio of length of 1.5 r------,------,----r------,-----, lumen to cell wall thickness (about to longitudinal HOLOCELLUI_OSE 500), the resistance u. diffusion resides mainly within the 0 lumen. The contribution to the overall "' resistance by the cell walls is very small. '"' Consequently, one would expect modi­ ,.: C£LL0PI'lANc ....o fications of the ce11 wall to have rela­ ffi

Tappi / February 1968 Vol. 51, No. 2 Ill MEASUREMENT OF THE SWELLING RH, or the fiber saturation point. At 90% RH and below, the equilib­ CAPACITY OF WOOD SUBSTANCE This is readily determined for unmodi­ rium moisture contents (EMC) of fied wood. In previous work (12-14) holocellulose and wood are similar. The swelling capacity of wood sub­ a procedure is described for measuring The considerably higher EMC of the stance, as a good approximation, is the fiber saturation point of modified holocellulose at 100% RH (Fig. 1) sug­ measured by the amount of moisture woods and of certain pulps. It is based gests that pockets of liquid water are associated with the substance at 100% on measuring the amollllt of solute-free present (perhaps hundreds of angstroms water in a waterlogged specimen equili­ in size), and are communicating with the brated with a dilute solution of a water­ environment through ch~ or "bot­ soluble polymer whose molecular f'lize tlenecks," the sizes of which are eqUiva­ Table IV. Fiber Saturation Point of precludes penetration into the wood lent to those of the critical molecular sizes Sitka Spruce Holocellulose with Varying substance. of the polyethylene glycoL Fiber satu­ lignin Content ration points of the cellulosic material described in this report were measured Fiber EXPERIMENTAL Lignin Lignin saturation with PEG-9000. Measurements were content, rerrwval, point, Wood made in triplicate with a reproducibility % % % ±2%. Transverse sections 20-~il-thick of of 'W.05 0 green Sitka spruce and sugar maple were 21.54 26 63 used. 16.98 42 70 RESULTS 10.66 63 94 5.53 81 130 to Holocellulose Holocellulose Effect of Conversion 3.27 89 140 Different Lignin Contents 1.11 96 180 with Cross sections 20-mil-thick of Sitka to holocellulose, the spruce were treated by the modified In converting the lignin from Sitka sodium chlorite method (15). The removal of 90% of resulted in a fiber washed holocellulose retained the geo­ spruce specimens of about 140% (Table Table V. Effect of Alkali Treatment metrical form of the wood very well. satUJ'ation point of the additional and Acid Wash on Fiber Saturation IV). '!'he ·•olume· wood sub­ Point water asRodated with the Alkali- Treated Wood stance was several times greater than Fiber the calculated volume of lignin removed. saturation 20-mil-thick of green maple Sections Consequently, the wood substance must point, were treated with dilute and Douglas-fir have undergone considerable swelling on Treatment % (1-4%) and washed sodium hydroxide conversion to holocellulose. acetic acid and water. Maple with water, dilute Examination under the microscope of None 40 green sections before and after delignifi­ 73 1%Na0j.?25°0,3hr revealed an appreciable increase 1%Na0 ,25°C,6hr 69 Liquid-Ammonia Treated Wood cation 1% NaOH, 25°C, 18 hr 66 in cell wall thickness. Stone and Scallan 1~ NaOH, 60°C, 3 hr 65 Sections 20-mil-tWck of air-dried made similar interpretations (16). Al­ 4o/o N9.0H, 25°C, 6 hr 68 maple were immersed in liquid ammonia though drying and rewetting of the halo­ Douglas-. fir at -33 and at +30°C (under pressure), cellulose resulted in some loss in fiber None 32 followed by air-drying and washing. saturation point, the loss became negli­ 1~ NaOH, 25°C, 3 hr 36 gible if the rewetting was made at 100°0, 4 0 NaOH, 25°C, 3 hr 32 Sulfite-Pulped Wood Sections 20-mil-thick of green Sitka Effect of Treatment with Dilute Alkali with 16% sodium spruce were heated The effect of alkali treatment on Table VI. Effect of Liquid Ammonia at 160°C for different times, bisulfite maple and Douglas-fir is shown in Treatment on the Fiber Saturation Point at 80% filtered, washed, and dried conclusions are drawn of Maple Table V. Three RH. from this table: Fiber saturation 1. Dilute alkali has little effect on Molecular Treating point, Determination of Critical the fiber saturation point of the Nonpenetration into Green condition % Weight for softwood 43 Wood Substance 2. Dilute alkali has a marked effect 51 nonsolvent water con­ on the fiber saturation point of the 70 In Fig. 1 the tent (13) for several water-logged cellu­ hardwood losic materials is shown as a function of 3. With the hardwooci, there seems the "llolecular weight of polyethylene to be an increase in fiber saturation glycol (PEG). The critical molecular point that is roughly independent concentration and tem­ Table VII. Fiber Saturation Points of weight is 3000-6000; in other words, of alkali The maximum fiber Sitka Spruce Sulfite Pulps depending on the cellulosic material, perature. the molecular size of the glycol above saturation point is 73% for the Fiber which penetration does not occur is alkali-treated, acid-washed wood. Lignin saturation is now available that content, point, 3000-6000. The nonsolvent water con­ Evidence Yield, maximum fiber satura­ % % % tent measured at and above this molecu~ this same lrtr size is identical with the fiber satu­ tion point is reached with treating 100 29.5 35 times considerably less tha.n 3 hr. 85 23 64 ration point and is a measure of the 75 17 76 swelling capacity of the material. Fig­ Preliminary chemical analysis 67 12 99 ure 1 shows a four-fold range in swelling shows that the only distinctive 52 3.8 104 capacity. changes are 1t reduction in a~P.tyl

/ fappi 82 llol. 51, No.? February 1968 content and a threefold increase woods result in a marked increase in rotting fungi circumvent this difuculty in carboxyl content, as measured the swelling capacity of the wood sub­ by sending out hyphae. This raises by calcium ion exchange. The stance. Stated differently, the sub­ some significant questions. How do formation of carboxyl groups fol­ stance becomes more highly plasticized. cellulolytic bacteria function? Why lowing alkali treatment and even Limited chemical data suggest that this does increased plasticization of cell wall following sodium chlorite treat­ effect is accompanied by considerable tissue increase the rate of attack by some ment has been demonstrated by increases in carboxyl content; this is of these bacteria? Does this increa~ed Sarkar in his extensive work with very likely a result of the breaking of plasticization explain the increase in jute (19). Sjostrom (20) has also polyuronic ester bonds, that is, the digestibility of straw when treated with reported marked increases in car­ breaking of cross-links. dilute alkali (24)? Is wood substance yl group· content following A hallmark of recent polymer theory in the superswollen state accessible to organisms within the lumen ~i.. tre~tment ..A v~luable clue is the prediction and confirmation of digesting JOstrom's findmgs 1s that the appreciable reductions in swelling ca­ despite the presence of lignin? This increase in carboxyl content fol- pacity of polymers following the intro­ last question is particularly significant lowing alkali treatment is con­ duction of relatively few cross-links. for this day of food shortage and popu­ siderably greater for hardwoods Stark and Rowland (21) have done re­ lation explosion. than for softwoods. lated work with formaldehyde-cross­ linked cellulose. Perhaps the increased swelling capacity discussed in this re­ LITERATURE CITED Eifect of Treatment with Liquid effect. We are sug­ Point port is the reverse Ammonia on the Fiber Saturation described gesting that the phenomena 1. Klauditz1 W., Holzforschung 6 (3): 70 The maximum fiber saturation point in the Review of Literature section of (19.\2). 11 (2): 47 with liquid ammonia this paper can be understood as being 2. Klauditz_. W., Holzforschung of maple treated (1957). VI) is the same as that obtained due to an increased plasticization of the (Table 3. Lagergren_. S. 1 Rydholm, S., and Stock­ by dilute alkali treatment (Table V). cell wall. The magnitude of this in­ man_. L., Svensk Papperstid. 60 : 632 If the increased swelling capacity is due creased plasticization is given by the in­ (1957). 4. Stamm1 A. J .1 uwood and Cellulose to the breaking of certain Swelling crease in swelling capacity. The sub­ 1 Science/ Ronald Press 1 New York, restraints, the same restraints must be stance within the cell wall at 100% RH N.Y., p. 410_. 1964. broken by both treatments. Although can be considered to be in a superswollen 5. Behr_. E. A., Briggs, D. R., and Kau­ liquid ammonia causes a partial trans­ condition. fert, F. H., J. Phys. Chem. 57: 476 cellulose III, Sjostrom (20) reported a slight in­ (1953). formation of cellulose I to 6. Yorston, F. H., Pulp and Paper Res. the alkali treatment described here is crease in carboxyl content in softwoods Inst. of Canada, Lab. Rep. No. 23, inadequate to produce any merceri­ following treatment with alkali. Yet 1943. zation effects (17). An explanation for we have observed no increase in swelling 7. McKibbins, Samuel W., Tappi 43 liquid cap·acity with softwoods. Perhaps sa­ (10): 801 (1960). the similarity of caustic and 8. Maass_. 0., Can. J. Res. 10: 180 ammonia treatments could involve ponification of polyuronic ester bonds is (1934). similar breaking of polyuronic ester necessary, but not sufficient to rJbtain 9. Stone, John E., 'l'appi 40 (7): 539, this effect. Other less nJkali-sensitive (1957). bonds. J. 9: 228 saponify bonds may exist in softwoods. Per­ 10. Stranks, D. W., Forest Prod. Alkali solutions very readily (1959). these bonds and form free carboxyl haps the effect is related to the con­ 11. Norberg, P. H. and Meier, H., Holz­ groups. Ammonolysis would also siderably higher lignin content or to its forschung. 20 (6): 174 (1966). cleave these bonds and form amides. different distribution in softwoods (22). 12. Feist, W. C. and Tarkow, H., Forest is Furthermore, the structures of the Prod. J. 17 (10): 65 (1967). The net result with both treatments 13. Tarkow, H., Feist, W. C., and Souther­ the elimination of primary valence glucurono-xylans in hardwoods and land, C. F., Forest Prod.. J. 16 (10): cross-links between certain polymeric softwoods are considerably different 61 (1966). components. The occurrence of am­ (23). 14. Stone, J. E. and Scallan, A. M., by The swelling capacities reported here Tappi 50 (10): 496 (1967). monolysis has been demonstrated 15. Thompson, N. S. and Kaustinen, 0. Wang (18). In fact, the kinetic im­ for alkali-treated wood are for the A., Tappi 47 (3): 157 (1964). plications suggested in Table VI agree acid-washed material. Higher swelling 16. Stone, J. E. and Scallan, A. M., with those reported by Wang. capacities are found for washed, but not J. Poly Sci. C11: 13 (1965). acid-washed material. The modified 17. Sisson, W. A. and Saner, W. R., J. Phys. Chem. 5:717 (1941). wood with its liberated carboxyl groups P. Y., Balker, H. I., and Effect of Sulfite Pulping on Fiber 18. Wang1 is behaving toward changes in pH much Purves, C. B., Can. J. Chem. 42: 2434 Saturation Point as any conventional ion exchange resin (1964). satu­ behaves. 19. Sarkar, P. B., Chatterjee, H., and A considerable increase in fiber Mazumdar, A. K., J. Text. Inst. Trans. ration point occurred with decreasing Previous work at our laboratory has 38: T318 (1947). adsorption yield of sulfite pulp from Sitka spruce shown that the moisture 20. SjOstrOm, E., Janson, J. 1 Haglund, P., (Table VII). The effect was· not as isotherms of pulps and of wood are and EnstrOm, B., J. Poly. Sci. Cll: halo­ similar below 90% RI-1; yet as this 221 (1965). pronounced as that noted with 21. Stark, S. M. and Rowland, S. P., cellulose (Table IV). Recent unpub­ investigation shows, the adsorption of J. Appl. Poly. Sci. 10: 1777 (1966). lished work at the Forest Productf pulps at 100% RH is considerably 22. Berlyn, G. P. and Mark, R. E., Forest that this may be higher. It is suggested that the func­ Prod. J. 15: 140 (1965). Laboratory has shown and Tech­ at tion of a wet··strengthening resin is 23. Timell, T. E., Wood Science due to the different temperatures nology 1 (1): 45 (1967). which the two pulping treatments were simply a partial restoring of the swelling 24. Wilson, R. K. and Pigden, W. J., made. capacity characteristic of the original Can. J. Anim. Sci. 44: 122 (1964). wood. Because the critical molecular size of RECEIVED FOR REVIEW July 25, 1967, ACCEPTED Sept. 30, 1967. DISCUSSION most modified cellulosic materials is The authors wish to acknowledge the coopera­ The resuThs of the literature survey equivalent. to or less than that of PEG- tion of the Tennessee Valley Authority iu. this work. now become understandable. Conven­ 6000_. it must be coneluded that. cellulo­ The Forest Products Laboratory is maintained tional pulping of hardwoods and soft­ lytic enzyme£ do not diffuse freely at Madison, Wis., in cooperation with the Univer­ woods and alkali treatment of hard- through water-swollen tissu-es.. Wood- sity of Wisconsin. 113 Tappi / February 1968 Vol. 51. No. 2 Condition Of Pine Piling Suomerged 62 Years In River Water

14th Street Bridge Over Potomac River, Washington, D.C.

THEO. C, SCHEFFER, Pathologist C. G. DUNCAN, Pathologist1 ""d THOMAS WilKINSON, Engineer Forest Products Laboratory,:! Fo1est Service U.S. Department of Agriculture Madison, Wisconsin

JN 1963, THE question was raised roborated with a third set of samples, Swain of the Washington office of the with by the bridge engineers as to and strength evaluations of the wood. Forest Service, in collaboration Bridge, whether the piling under the old 14th The conditions of the piling was of the engineer on the 14th Street Street Bridge in Washington, D.C., more than practical interest because Mr. H. Emekli, arranged to have four was sufficiently sound to warrant conw it gave us an opportunity to observe more sections of piling sent to the structing a new bridge on it. Our ex­ the condition of untreated wood with Laboratory. These were examined aminations in 1963 and 1967 of wood an authenticated history under fresh microscopically and specimens from The from representative piles indicated that water for a long period of time. them were tested for strength. from it probably was not, but it was de­ In response to our desire to analyze findings, and conclusions derived assays, cided in 1968 that this should be cor- more of the piling, Mr. George Me- both the present and the earlier are the subject of this report. According to Mr. Emekli, the four Table 1 - Results of compression parallel to grain test of 1 by 1 specimens sections had never been encased in cut from pile sections obtained from pier 9 of 14th Street Bridge, concrete, since the concrete encase­ '¥ashington, D.C. ment on these particular piles started several feet below mudline. The sec­ tions were all from pier 9. Two of ~sh~ng strength. them, which will be referred to here as pile L 1 and pile L2, came from just above the muclline; the other two, ).l.,so.i. _P.s.i. pile L3 and pile lA, came from just 0.430 1,380 below the· mudlinc, according to Mr. .394 1,200 1,29() Emekli. The species of pine could .395 1,!40 not be established, but it seems logical .402 1.420 l,ZSO · to assume that it was one of the four .420 1,320 major southern pines. .434 1,680 1,500 The sections were tested for 139 .421 1,550 strength in compression parallel to the 89 .465 1,310 grain. Specimens were 1 by 1 hy 4 154 .381 1,370 inches and they were tested in the 182 .• 380 1,250 green condition in accordance with .369 1,040 184 the procedure outlined in ASTM :'153 .399 1,280 0143. The location of the specimens .390 2,230 is shown in Figure 1. The results arc .367 2,180 shown in Tahle 1. .431 2,880 The residual strength of the piles .429 2,840 cannot be analyzed relative to known to ob­ ~;ap"'o.od initial values, but it is possible tain some estimate of strength change (Continued on page 24)

'Average values (Wood Handbook) for sound, green southern pine wood: 'Deceased. loblolly- 3,490 Longleaf- 4,300 ~Maintained at Madison, Wis., in coopera­ University of Wisconsin. Shortleaf- 3,430 Slash- 4,340 tion with the

January, 1969 22 >:->< __ :;~\;:_lfh-'cis--JJ~P!in'aUy -~e'en tissuri,ea that -tim}l'er- pilln~ -_~aetJ_>~;f __ -- --,P~ 'pt_eSs\.ll-1,14r~otei:l -for IJse in fresh wQter in$:tallettio_ll~,-:~hc.r"v:_~_ :'­ _>-"~-':':er;_-:tJ:i)_s -re.c!)ln_t· repq_rt ·on. piUngJ> _remov'e_d froryJ- _the, old_ !4th:.: --~- -~fX~-~t_-__'·~ri~~-e- across t!"u::i, Potoro£1t- River- _in. Washinston,- D.~_,: ''-::pr.~inpt_s,_a -1"ti!-eVaiiJC1tion -af _this e*:~blished thou_ght.- _ -- - -:;> .:-: .:'#h~n, ·!_he _q[~ ·hr-id£Je was dis_mcmtl_ed,- after :neor:l_y- _60.-y_~_(li --~e_tqil").d_ s~udy,_ This, examination_ revealed -tljat -even th~ugb__ __ -'fhefEb·pile.~:_had b_een- in _fresh _waterr· the timbers __ dbQY_e_.t_he- ~'-:-': mu,1:l_!jne :h9c;f :1_e$S than- Qne-ha[f ·their Original·_:stren,g_th,- Qll~-. ,.,, l?.!i!J'?w:- mu_dliQe_ they had n~ more thun about 80%- .Of t_~eir --­ ~r-igtl\al 'st[~ngth,_ Thi.( FPt -n~'port J$ -presented --to show' ,.the re$ults -of _the _~x": ~h:lJpa_ti<¥J __ by the _Forest Products t.ahotatory. The many casp_e~t~ ,::·:::(,f- -this _:-report- are_ worthy of furt~r- ctndlysis and.-e:on_sider$1 7 "·:_j~p~ J~_y_ 'speeifiers- -t~nd users of timber produds: It s_e~mi"' _,_Pi:v~ent Jq avoid possible materiQ\ d~te.tioratioo in fresh_ wq_te:r:' ::' .:JillltaJt~t,ij)ns b}r spec.1fying the use, of Pressure-treatec:J _timb@r_ - -pi)~s:--~. V'J,-001> P~ES.E!tVING

The pilings that are on the barge are a few that were pulled when the 14th Street Bridge was razed.

Pile l'l

Diagram for cutting 1" by 1" compression parallel to grain specimens from pile sections obtained from pier 9 of the 14th Street Bridge, Washington, D.C.

WOOD PRESERVING by referring to the average crushing­ summarized in Table 2. Bacteria were dence that the pine sapwood belo\\1 strength (parallel to grain) values for present in all portions of all Pile sec­ mudline in the river water for 62 southern pines. Using for reference tions. They were more prevalent in years had been substantially weakened the average strength of the weakest sections below mudline than in sec­ in crushing strength by bacteria. The of the southern pines, loblolly and tions above, and the wood below mud­ heartwood was affected Jess; judging shortleaf (Table 1), one could conclude line was correspondingly altered to .. a from the condition of wood recovered that the wood above mudlinc tended greater degree microscoPically. The from lakes and river bottoms after to have less than one-half its original greater residual strength in the wood much longer periods than 62 years, strength and that below mudline no below mudline cannot be accounted however, the heartwood also probably more than about 80 percent of its for on the basis of the microscopical would eventually have been seriously original strength. Thus, it seems that appearance of the wood, which was degraded. there was a definite and substantial not as good as that of the wood above The fungus infection probably was reduction in crushing strength of the mudline. It can only be suggested at incurred before the piles were driven, piles above mudline and a moderate this time that microscopically visible since fungi are not known to be capa~ reduction in strength below mudline. alterations of pine wood induced by ble of seriously invading wood under Although the apparent reduction in bacteria are not a reliable index of the water, and limited fungus infection strength below mudline may not be changes in wood strength of the mag­ of southern pine poles and piling on statistically significant, it probably is nitude found in this piling. the storage yard is common. The a real one in view of microscopical Fungus hyphae were present in the fungus infection however, did not ap~ evidence of bacterially caused changes sapwood and outer heartwood, but pear tO be extensive enough to have in the wood. not in the inner ·heartwood. been a sizable factor in the apparent The microscopical observations are We conclude from the total evi- reduced strength of the wood. !Ill

Table 2 - Summary of microscopical observations of thin sections from pine piling obtained from pier 9 of 14th Street Bridge, Washington, D.C.

24 January, 1969 APPENDIX III

\ULLIAM IL BURR 1 S REPORT TO ASCE (1890)

(Plates XV, XVI, and XVII have been o~itted) AMERICAN SOCIETY OF CIVIL ENGINEERS. INSTITUTED 1852.

TRANSACTIONS. in NoTE.-This Society is not responsible, as .a body, for the facts and opinions advanced any of its publications.

446. (Vol. XXIII.-August, 1890.)

THE RIVER SPANS OF THE CINCINNATI AND COVINGTON ELEVATED RAILWAY, TRANS­ FER AND BRIDGE COMPANY

By WILLIAM H. BURR, M. Am. Soc. C. E.

WITH DISCUSSION.

The structure which forms the subject of this paper crosses the Ohio River at Cincinnati, Ohio, and with its approaches forms a part of the Chesapeake and Ohio Railroad system. It acquires its interest as a piece of engineering chiefly from the magnitude of the individual spans of which it is composed. There were no special engineering difficulties to be overcome either in the substructure or superstructure, but the central span of the three, 550 feet long between centers of piers, and 84 feet deep between centers of chords, is the greatest simple non-continuous truss span yet constructed. The two spans which flank the center or main channel span are 490 feet each between pier centers, with center depths of 75 feet; and the fact that all the spans carry a double track raHway with two roadways and two sidewalks, renders them also the heaviest non-continuous trusses which have yet been built either in 48 BURR ON RIVER SPANS OF CINCINNATI BRIDGE. BURR ON RIVER SPANS OF CINCINNATI BRIDGE. 49 this country or in Europe. The detail drawings accompanying this :Much difficulty was experienced in obtaining metal for the heavy paper show all the main features of the trusses and fioor systems and plate links at the upper ends of the end posts which would fill the their connections which are of any special inte1·est. AB they indicate, requirements of the specifications, or sufficiently near thereto. Anum­ all the main parts of the trusses are of steel, while the lateral and tranf­ ber of steel plate makers felt confident of being able to produce such verse systems of bracing and the floor-beams and stringers are of thick and heavy plates as would meet the requirements of this case, wrought-iron. but repeated trials were failures. The metal would be very low in With the exception of the connection between the :floor-beams and dastic limit as well as in ultimate, and develop porous places in the posts, and the web system, there will be found few' features not ordi­ interior of the mass. The whole difficulty lay in the small amount of narily included in the best American practice for heavy spans. All work which was put upon the metal between the ingot and finished connections are central, and so designed as to eliminate essentially all plate. Messrs. Graff, Bennett & Co. finally produced a number of plates secondary stresses. The system of web members used, and whic.h has -of open hearth steel which met the requirements of the specifications. been developed by the Phrenix :Bridge Company for its long spans, is Their financial difficulties coming on at this time, however, prevented seen to be single, and it is of interest in passing to note that if a single their ~'.ompletionof more than a few only of the plates required. The system of bracing may be used for trusses of the dimensionJ and weight -remaining plates for these heavy links were made of :Bessemer steel and of these under consideration, there would seem to be no case where it produced at the Homestead Mills of Messrs. Carnegie, Phipps & Co. may not be advantageously employed. There is thus avoided all the The experience with these plates was very interesting in itself, although ambiguity and secondary stresses which are inevitable to a greater or less the difficulties encountered threatened at one time to result in a serious degree when any multiple system of web members is used. delay to the progress of the work. It demonstrated in a peculiarly The boring of individual truss members was done with such lengths -clear and effective manner the improvement in the quality of the as would eliminate. all secondary stresses whatever at a condition of metal produced by an increased amount of work. The most porous loading intermediate between no moving load and a full moving load. portions of several plates were a number of times wor"Sed down under As the latter condition of loading will very rarely occm·, these normal .a hammer to bars of most excellent steel, alike in respect to its elastic

lengths will reduce the secondary stresses to an absolute minimum; in limit 1 ultimate resistance and ductility. fact, -will reduce them to such small magnitude as to leave them with no The 7·inch steel eye·bars were forged from open hearth steel, while importance whatever. The connection between the floor-beams and the B·inch bars were forged from Bessemer steel. posts, which is made by means of close-fitting turned bolts in holes The steel pins were forged from open hearth metal. drilled with those members assembled, is of such a character as to secure :Before proceeding with the actual shop work on these spans, many all the advantages of a rigid connection and at the same time eliminate .careful tests on th.;; effect of the var:ous shop manipulations of the steel all tension upon the connecting bolts, leaving them to transfer shear material were made in order that the greatest confidence might be only; at the same time the weights of both railway and highway floor placed in the resulting work. Rivets both with counter-sunk and full systems are transferred centrally, so as to bring an equal distribution of beads on one and both sides of plates were driven, and the hammer­ weights upon all of the web members intersecting at any lower chord ing continued throughout the stage of blue heat as the metal cooled panel point. Under the requirements of the specifications all rivet holes down; heads were then knocked off, or the counter-sunk rivets in the plates and angles forming the upper chords and end posts, and driven out in such a way as to give their material as much abusf', ..as nearly all intermediate posts, were made with multiple drills of six drills possible. The results of these tests were in every way high'fy satisfac­ in a gang. The only exceptions to this statement were some light plates tory and showed that the material selected was admirably adapteci to and angl1'3s in a few of the intermediate posts, which were punched and its purpose. They also revealed the fact that with proper material in reamed. steel rivets, that is, with phosphorus not over about five hundredths of

a a

4 4

of of

of of

of of 53 53

on on

the the

the the

the the

9th 9th

and and

De­

The The

steel steel

then then

high high

piles piles

Ran­

turn turn

pier pier valu· valu·

each each

trains trains

with with

trans­

about about

last last

There There

on on

driven driven

shown shown

regular regular

notes notes

and and

its its

work work

work work

Mr. Mr.

in in

him him

continu­

bracing, bracing,

and and

any any

since since

timbers. timbers.

Covington Covington

placed placed

the the

was was

the the

of of

remaining remaining

and and

Cincinnati. Cincinnati.

of of

the the on on

of of

near near October, October,

first first

given given

are are steel steel

storm storm

ample ample

including including

false false

at at

iron iron

reconstructed reconstructed

sticks sticks

of of

the the

December December

stated, stated,

capped capped

span span

banks. banks.

schedule schedule

or or

which which

water water

words words

of of

of of

platform platform

the the

thick thick

also also

thereafter. thereafter.

12-inch 12-inch

as as

and and

the the

the the

BRIDGE. BRIDGE.

oak oak

On On

body body

During During

structure, structure,

and and

the the

piles piles

x x

at at

transverse transverse

driving driving

dimensions dimensions

for for

heavy heavy

carried carried

ha.s ha.s

piles piles

or or

the the

on on

time time

28th 28th

in in

a a

high high

12 12

Engineer Engineer

iron iron

entirely entirely

E., E.,

the the

on on

of of

delivered delivered

the the

The The

550-feet 550-feet

and and

white white

was was

which which

and and

main main

out out

C. C.

pounds pounds

inches inches

of of

completed, completed,

timbers, timbers,

the the

of of

the the

recede recede

effected, effected,

span. span.

floor floor

Chief Chief

after after

of of

sama-

which which

27 27

rest rest

Company, Company,

and and

been been

are are

the the

Soc. Soc.

on on

to to

run run

all all

the the

000 000

end end

oak oak

was was

continued continued

immediately immediately

(frequently (frequently

work work

gravel gravel

lateral lateral

of of

oak oak

completed. completed.

batter batter

the the

of of Am. Am.

just just

last last

CINCINNATI CINCINNATI

of of

period period

700 700

also also

was was

entirely entirely

from from

placed. placed.

each each

spans spans

They They

Bridge Bridge prevented prevented

all all

shops shops

of of

M. M.

490-feet 490-feet

work work

rise rise

and and

the the

Randolph, Randolph,

OF OF

is is

steel steel

the the

work work

work work

soon soon

white white

was was

bracing, bracing,

white white

time time

The The

and and

and and

floor floor and and

third third

1ine3 1ine3

coupling coupling

Epes Epes

on on

clay clay

erection erection

with with

and and

north north

Cincinnati Cincinnati

commenced commenced

bridge, bridge,

and and

flood flood

masonry masonry

false false

490-feet 490-feet

steel steel

were were

Mr. Mr.

the the

completed completed

same same

Sooysm.ith, Sooysm.ith,

SPANS SPANS

last last

masonry, masonry,

nine nine

floors floors

SUBSTRUCTURE.* SUBSTRUCTURE.*

the the

the the

and and

the the

to to

masonry masonry

weeks, weeks,

the the

Transfer Transfer

substructu-re substructu-re

12-inch 12-inch

days, days,

day, day,

iron iron

12-inch 12-inch

railway railway

the the

two two

directions. directions.

This This

Phamixville Phamixville

and and

water water the the

of of

the the The The

in in

x x

transverse transverse

at at

was was

courses courses

the the

work work

pier pier

the the

into into

over over

Charles Charles

the the

the the

and and

of of

the the

three three

the the

12 12

RIVER RIVER making making

both both

iron iron

solid solid

of of

from from

indebted indebted

railway railway and and

constructed. constructed.

until until

time time

Railway, Railway,

placing placing

particulars. particulars.

of of

Mr. Mr.

at at

span span

for for

a a

sixteen sixteen

span span

"\Vithin "\Vithin

feet feet

in in

false false

work. work.

of of

the the

ON ON

co:~rses co:~rses

night night

bottom bottom

which which

feet, feet,

remaining remaining

with with

some some

in in

inches. inches.

42 42

The The

run. run.

passed passed

account account

ever ever

clear clear

chiefly chiefly

night night

the the

of of

had had

piers piers

several several

this this

work work

lateral lateral

and and

27 27

carry carry

on on

to to

is is

for for

12 12

however, however,

Elevated Elevated

the the

although although

in in

of of

ce:tters ce:tters

pier pier

these these

of of

material material

any any

490-feet 490-feet

including including

of of

all all

and and

BURR BURR

length length

30 30

of of

iron iron

oft' oft'

floor floor

XII. XII.

bottom bottom

forward forward

traffic traffic

25th. 25th.

feet, feet,

shore shore

following following

writer writer

of of

swung swung

as as

latter latter

mark mark

b"sed, b"sed,

rise rise

day day

and and

new new

longitudinally longitudinally

erection erection

regularly regularly

driving driving

completed completed

36 36

is is

that that

span, span,

the the

north north

first first

apart, apart,

five five

The The

assistance assistance

Cincinnati Cincinnati

was was

Plate Plate

x x

*The *The

refusal refusal

The The

railw&y railw&y

large large

pushed pushed

floor floor

from from coupling coupling

it it

beginning beginning

flood flood

water water for for

November, November,

pile pile

the the erection erection

the the

this this

cember cember

ously ously railway railway

was was

were were

carry carry versly versly

72 72

These These

feet feet

are are to to

on on

surmounts surmounts

stepped stepped

and and

able able

which which dolph) dolph)

a a

of of

in in

as as

in in

in in or or

be be

by by

act act

the the

the the

the the

the the

two two

two­

the the

feet feet

feet feet

and and

and and

con­

false false

four­

trav­

faet, faet,

false false

work work

high high to to

about about

to to

5 5

either either

of of

of of

feet feet

of of

the the

in in

nel;l.l'ly nel;l.l'ly

part part

being being

550 550

Indiana Indiana

V V

for for from from

The The

the the

two two

its its

was was after after

not not

45 45

obliquely obliquely

intervals, intervals,

false false

maximum maximum

amounts amounts

subsequent subsequent

quantity quantity

it it

piles piles

and and

forming forming

within within

the the

on on the the

and and

ordered ordered

found found

completed completed the the

sted. sted.

early early

was was

run run

its its

Ohio, Ohio,

the the

night; night;

of of

weeks weeks erection erection

of of

by by

feet. feet.

water water

hours hours

and and

be be

but but

character character

iUuminated iUuminated

lumber lumber

in in

thus thus

operations operations

work work

to to

and and

of of the the

was was

sevqal sevqal

were were

BRIDGE. BRIDGE. completion completion

to to

40 40

six six

largest largest piles, piles,

were were driven driven

and and

five five

and and

placed placed

River River

started started

of of

work work

rise, rise,

about about

at at

maintained maintained

new new

angle angle

thus thus

and and

the the

false false

the the

a a

iron iron

had had

formed formed

day day

just just

considerable considerable

depth depth

at at

every every

been been

and and

work work

Ohio Ohio

the the

of of

was was

piling piling

to to

possible possible

false false

A A

within within

being being

the the

the the

river river

protection, protection,

also also

was was

such such

safeguard safeguard

as as

that that

very very

had had

both both

phenomenal phenomenal

the the

extremities, extremities,

protection protection

including including

in in

site site

cessation cessation

protection, protection,

false false

ordered ordered

of of

flood flood

periods, periods,

piles piles

new new

with with

of of

the the

26th, 26th,

in in

heavy heavy

CINCINNATI CINCINNATI

this this

its its

again again

the the

no no

recede recede

lines lines

founded founded

with with

pile pile

piles piles the the

the the

six six

September September

once once

This This

of of

points points

of of

work, work,

short short

to to

OF OF

bridge bridge placed placed

was was

of of

of of of of

at at

placing placing

water water

scantling. scantling.

from from

once once apparatus apparatus

was was

complete complete

950 950

continued continued

river river

give give

with with

August August

6 6 handling handling

these these

concentration concentration

for for

prosecuted prosecuted

lines lines

a a

and and

eaeh eaeh

false false

many many

x x

low low

feet feet

protection, protection,

to to

there there

experience experience

ent.ire ent.ire expectation expectation

the the

on on

of of

4 4

the the

SPANS SPANS

as as

floor floor

the the

over over

submerged submerged

group group

plant plant

two two

month month

in in

hours hours evident evident

a a

by by

work work

from from

the the

at at

the the

Company Company

hoisting hoisting

actively actively

for for

entire entire

25th, 25th,

commenced commenced

framed framed

lineal lineal

receded receded

of of

order order

usual usual

by by

just just

anticipation. anticipation.

formed formed

Each Each

steel steel

time time

autumn autumn

light light

wreck, wreck,

insure insure

pile-driving, pile-driving,

and and

rises rises

the the

feet feet

RIVER. RIVER. it it

was was

entire entire

in in

V-shaped V-shaped

New New

to to

piles piles

the the

to to

of of

of of

became became

a a

and and the the

the the

and and

1200 1200

600 600

this this

have have

water water

Bridge Bridge

neglect neglect

ON ON

as as

was was

sheathed sheathed

usual usual

protection, protection,

the the

lumber lumber

traveler traveler

It It and and

backed backed

of of

work work

number number

wreck, wreck,

so so

hence hence

to to

electric electric

feet. feet.

the the

D2cember D2cember

of of

time. time.

wreck wreck

the the

:U·on :U·on

a a

the the

then then

about about

the the

day day

about about

although although

17 17

number number

on on

would would

up-stream. up-stream.

Contrary Contrary

steel steel

BURR BURR

day. day.

feet feet

safe safe

During During

justified justified

a a

and and

Phcenix Phcenix

the the

actively actively

the the

to to

for for

during during that that

operations operations

centers, centers,

admirably admirably

traveler traveler

or or

the the

and and

intersection intersection

thorough thorough

were were

5 5

after after

and and

of of feet feet

Georgia, Georgia,

river river

~e, ~e,

shortest shortest

So So

extensive extensive

the the

The The

work. work.

pla pla

travelers; travelers;

million million

drift. drift.

against against most most

elers elers

day day

events events

the the

lines lines water water

span span

apart apart

550 550

sidered sidered

experienced, experienced,

night night

all all their their

season season

up-stream up-stream

from from an an

October, October, from from

iron iron

work, work, and and

structure structure

days days

the the firmly firmly

52 52

height, height, failure. failure.

in in

in in

the the

its its

the the

the the

the the

two two

57 57

was was

the the

the the

the the

was was

com­

were were

ejec­

the the

etc., etc.,

was was

shaft shaft

3 3 x 4

doors doors

con­

most most

of of

sacks. sacks.

sides. sides.

of of

except except

stirred stirred

by by

was was

pipes pipes

work­

at at

inches inches

It It

closely closely

give give

air air

with with

and and

the the

and and

in in

8 8

compres­

the the

working working

into into

worked worked

to to

chamber. chamber.

hole hole

when when

pipe pipe

the the

to to

sides sides

Valves Valves

the the

been been

shaft shaft

doors doors

compressed compressed

caisson caisson

the the

wer.ehoisted wer.ehoisted

feet feet

4-inch 4-inch

alongside alongside

and and

fitting fitting

the the

shaft shaft

a~r a~r

to to

removed removed

shaft.. shaft..

feet feet

boulders, boulders,

caisson, caisson,

2 2

Men Men

opposite opposite

the the

and and

square square

the the

excavating excavating

the the

gathered gathered

strainer, strainer,

from from

the the

order order

the the

opened opened

small small

7 7

the the

chamber chamber

4·inch 4·inch

air air

from from

on on

fill fill in in

the the

and and

the the

boat boat

a a

working working

be be

and and

BRIDGE. BRIDGE.

it. it.

a a

to to

in in

feet feet

by by

this this

having having

be be

or or

and and

bucket bucket

to to

the the

3 3

sand sand

above above

after after

of of

also also

finished. finished.

however, however,

happen happen

the the

the the

a a

6 6

equalized equalized

time time

>vith >vith

through through

concrete concrete

long long

with with

inches inches

which which

of of

work work

in in

river river

and and

on on

would would

leading leading

above above

and and

working working

hose hose

was was

grooves grooves

compressed compressed

6 6

etc., etc.,

used used

would would

about about

pump pump

the the

closure, closure,

been been

means means

the the

feet feet

down down

roof roof

should should

into into

the the

whole whole

materials materials

through through

the the

4 4

guided guided

just just

sand sand

concrete concrete

of of

foot foot

into into

pipes pipes

raised raised

only only

give give

by by

bad bad

gravel gravel

work work

shafts shafts

pipe pipe

1 1

the the

concave concave

near near

CINCINNATI CINCINNATI

projected projected

of of

work work

rocks, rocks,

the the

up up

derrick derrick

rubber rubber

corresponding corresponding

the the

into into

was was

to to

and and

was was

was was

a a

about about

OF OF

the the

and and

top top

bucket bucket

carried carried

was was

until until

crib crib

4-inch 4-inch

above above

fitting fitting

It It

ejector ejector

and and

automatic automatic

accidents accidents

bucket bucket

of of

etc., etc.,

in in

nearly nearly

which which

the the

4·inch 4·inch

beginning beginning

Worthington Worthington

located located

forming forming

the the

locked locked

foot foot

bucket bucket

concrete concrete

if if

supplying supplying

gravel gravel

dischar~e dischar~e

the the

the the

and and

were were

the the

a a

boulders, boulders,

1 1

top, top,

openings openings

of of

to to

from from

pipe pipe night night

material material

SPANS SPANS

chamber chamber

with with

the the

to to

of of

of of

in in

the the

of of

sand, sand,

to to

bottom bottom

cylindf'rS cylindf'rS

was was

out out

The The

valYe valYe

in in

means means

and and

at at

its its

shaft shaft

pipes, pipes,

to to

course course

air air

deck deck

the the

a a

and and

part part

in in

two two

pursued pursued

end end

The The

doors doors

larger larger

done done

get get

used used

by by

piles piles

air air

The The

downward. downward.

time time

bolted bolted

the the

the the

the the

RIVER RIVER

over over

boulders boulders

into into

to to

which which

day day

deck deck was was

it. it.

two two

remove remove

working working

was was

chamber chamber

The The

were were

purpose purpose

the the

of of

lower lower

it. it.

attached attached

upper upper

were were

which which

opened. opened.

up up

ON ON

was was

and and

Small Small

attached attached

to to

short short

after after

the the

air air

the the

time time

excavating excavating

the the

with with

passed passed

a a

the the

the the

jet jet

terminating terminating

cylinder cylinder

shifts shifts

shaft shaft

to to

above above

through through

Both Both

terminating terminating

pipes pipes

There There

method method

use use

after after

to to

a a

on on

the the

quantity quantity

used, used,

within within

for for

the the

forced forced

was was

For For

pump pump

BURR BURR

projecting projecting

with with

this this

up up

this this

just just

cylinder cylinder

openings openings

material. material.

end end

ample ample

to to

cylinder cylinder

thrown, thrown,

This This

not not

bolted bolted

in in

below, below,

with with

chamber. chamber.

sand sand

the the

diameter, diameter,

small small

the the

place place

men men

sors sors

was was

pressor. pressor.

a a

attached attached up up

eight-hour eight-hour

tor tor

frequent frequent A A

beams beams

shaft. shaft.

cylinder cylinder

were were

in in

caisson. caisson.

This This

inside inside

entirely entirely

in in

inches inches

lower lower

carried carried

through through

of of

material material

chamber, chamber,

air. air.

lower lower

ing ing

Four-inch Four-inch

were were

chamber. chamber.

in in

concrete concrete

nection nection

izing izing

a a

x x

at at

to to

20 20

96 96

on on

was was

2d, 2d,

was was

was was

one one

car­ the the

and and H H

up­

and and

con­ crib crib

nec­

iron iron

x x

wide wide

built built

Both Both used used

doors doors

a a

equal· equal·

plant. plant.

above above

A A

was was

luger­

parties parties

hckle. hckle.

door door

26 26

Worth­

bottom bottom

closed closed

shoving shoving

and and

air air

position position

required required

a a

door door

20th 20th

June June

30 30

angle angle

The The

located located

one-hal£ one-hal£

laid laid

found found

the the

boiler boiler

caisson caisson

boilers boilers

section section

x x

carried carried

and and

lo\ver lo\ver

inches inches

valve valve

and and

entire entire

false false

and and

a a

each. each.

deck deck

into into

of of

riveted riveted

time time

the the

when when

masonry masonry

with with

gradually gradually

18 18

barge, barge,

15 15

June June

was was

or or

the the

duplex duplex

completing completing

upper upper

deck deck

were were

and and

£rom £rom

the the

the the

the the

as as

three three

the the

barge barge

was was

in in

pressure. pressure.

~-inch ~-inch

As As

and and

one one

BRIDGE. BRIDGE.

was was

block block

made made launched launched

iron iron

pieces pieces

with with

lder lder

the the

When When

the the

two two

of of

door door

caisson. caisson.

ability ability

of of

larger larger

floated floated

and and

of of

making making

and and

by by

plant plant

of of

bottom bottom

and and

work work

upper upper

varied varied

lock

ala ala

other other

spent spent

the the

the the

which which

small small

The The

lock, lock,

When When

through through

was was

section section

Ea~h Ea~h

boiler boiler

24, 24,

latter. latter.

air air

of of

to to

The The

candle-power candle-power

increased increased

such such

to to river river

lock lock

water, water,

x x

-w-as -w-as

it it

light light

The The

pump pump

air air

by by

course course

changes changes

into into

gasket, gasket,

V-shaped, V-shaped,

cylinder cylinder

the the

the the

16 16

lowered lowered

carried carried

connections connections

for for

to to

200 200

air air

and and

crib. crib.

downward. downward.

low low

CINCINNATI CINCINNATI

of of

1 1

maintenance maintenance

t-inch t-inch

time time

the the

compressors, compressors,

one one

it, it,

plate, plate,

middle middle

one one

chamber chamber

piles piles

apart. apart. caisson. caisson.

which which

the the

and and

of of

of of

OF OF

and and

to to

electric electric

section section

air air

pressure pressure

top top

sawing sawing

4-foot 4-foot

the the

rubber rubber

and and

boilers. boilers.

increased. increased.

the the

only only

Knowles Knowles

in in

manner manner

settled settled

the the

below below

swung swung

edge. edge.

cylim1er cylim1er

pressure pressure

up up

air air

by by

the the

requisites requisites

after after

carried carried

the the

guide guide

and and

pump, pump,

20th 20th

inches inches

had had

raisecl raisecl

one one

this this

lights lights

near near

lashed lashed

was was

working working

wrought wrought

three three

repair repair

corresponding corresponding

the the

caisson caisson

SPANS SPANS

:float :float

1st 1st

the the

in in

feet feet

or or

duplex duplex

H-inch H-inch

and and

diameter diameter

both both

16 16

In In

shop shop

7 7

above above

to to

arc arc

masonry masonry

a a

to to

of of

the the

June June

was was

pressure pressure

and and

the the

the the

cutting cutting

the the

which which

were were

carried carried

of of

July July

caisson, caisson,

of of

of of

of of

~-inch ~-inch

lock lock

located located

feet feet

18, 18,

caisson caisson

chamber chamber

and and

RIVER RIVER

for for

four four

inches inches

the the

rungs rungs

located located

until until

machinery machinery

was was

x x

of of

barge barge

20 20

top top

Ingersol Ingersol

6 6

lo-,yer. lo-,yer.

inside inside

the the

air air

doors doors

machine

bottom bottom

was was

surface surface

compressor, compressor,

Worthington Worthington

protection protection

a a

2d 2d

ON ON

descended descended

10 10

sustain sustain

or or

height height

ring; ring;

acco:f.cling acco:f.cling

was was

Ohio Ohio

of of

done done

the the

cylinder, cylinder,

with with

of of

foot foot

the the

two two

under under

built built

The The

removed removed

to to

round round

18 18

line line

level level

working working alongside alongside

1 1

false false

the the

These These

be be

June June

of of

made made

a a

the the

cylinder cylinder

The The

lock lock

bottom bottom

row row

duplex duplex

from from

BURR BURR

as as

deck deck

it. it.

equalization equalization

pneumatic pneumatic

gasket gasket

caisson caisson

pumps, pumps,

to to

a a

the the

contained contained

to to

on on

minutes minutes

compressor compressor

18 18

fit. fit.

about about

shaft shaft

the the

;f-inch ;f-inch

air air

inches, inches,

carried carried

or or

up up

dynamo dynamo

and and

barges barges

entirely entirely

From From

the the

x x

portions portions

the the

caisson caisson

straight straight

valves valves

The The

aid aid

air air

27 27

for for

top top

crete crete

three three

descencling descencling }-inch }-inch

As As

tight tight

with with

or or

around around

ried ried

added added

x x work work

sunk sunk

generally generally

The The

barges barges

essary essary

10;-

one one

sol sol

running running

two two

the the

ington ington

feet, feet,

was was

rested rested

behind behind

stream. stream.

the the

to to

an an

roof roof

it. it. 56 56 a

of

or

or

be

61

for

the

the tho

and

(60)

end

and

feet,

spans,

of

during

with

part

caisson

are

hundred

feet,

hundred

{27)

shall

sectional

sixty

member

side

all

'' "

11

''

" ''

"

stresses.

timbers

Co.,

COMPANY.

between

five

(11)

one

and

piers,

center.

accessible

lowest

contraction

of

pounds.

&

two

of

railway,

than

each

of

tracks

be

to

to

BRIDGE.

dispJacement,

224 285

285

047

200 324 200

000

manner.

guard

and

and

for

river

eltven

BRIDGE

less

span

13

77

13

81

including

rail

track

stresses

sha.ll provided

twenty-seven 719

890 922

202

be

the

sidewalks.

diagram

feet.

CINCINNATI.---SPECIFICA­

center

two

of

pins;

railway

36

13

36

not 13

be

metal

be

of

Sooysmith

the

,. ..

the

(20)

shall

the

data.

of

of

AND

end

central

feet,

temperature

PH

expansion

base double

on

for

a

......

.••••.

shall

of

by

shall

structure

CINCINNATI

s,

in

......

maximum

effect

.

kind

and

weight

THE

of

.....•.

, ...... , •

free

Messrs.

(4.86)

substructure,

twenty

......

side.

the

from

OF

weighing

center

for

noted

the

high

the

structure.

weight

center

by

weight

foot

of foot......

the

preceding

total

trusses

to

wagon-way

the

excepting

COVINGTON

provided

than

feet.

to

each

the

sustained

feet

each

consist

buoyant

variation

for

tracks. efficient

weight

show

being

built

the

total

be of

steel,

total

SPANS

{5)

on a

pier,

parts of

less

each

in

SrJ.ua.re

square

eighty-six

......

or

(10)

8PANS.-BY

the

to

be

center

......

also

all

center

measuring

total

used

shall

Jhe

made

usual

pier,

Fahr.

shall

between

not

for

pier,

performed

per

per BETWEEN

railway

structure,

ten

weights,

be

pile pile.

and

iron

less

RIVER

given railings,

portion be

feet,

shall

MAIN

pier,

shall

from

foot

to

sidewalk

is their

of members

was

elear

the

abutment

River

load

per

load

per the

a

proper

ON

painting.

tota.l

in

be

degrees

in

headway,

(545)

shall

THE

distance

sidewalk

bracing,

of

BRIDGE

loads,

feet.

and

screens

practicable

River

lineal

abutment main

and

outside

and

which

hundred

Total

Total

Load Load

work,

corresponding

as

1888,

FOR

(150)

shall

BURR

diagram

(13)

all

distance

each

members

pneumatic structure clear

bridge

above

per

of

width

clear

rarts

total

Kentucky

Kentucky Ohio

Ohio

RIVER

fa.r

four of

of

and

crib

for

the

forty-five

fifty

overhead

Strong

The

The

The

The

The

The Wooden All

The

parts, Thi':l Provision

As

TIONS

1887 the

OHIO pins.

wagon-way

volume thirteen

pounds

wagon-ways

flooring, class and each

ancl that

and

areas

all and inspection actual

on

the

per

feet

men

were

struc­

pier.

owing

inches

contin­

foHows:'

pier.

and

nor

went

few

concrete,

upon

12

height.

maximum

0.451

as

this

a

!Jier.

"

delay

Shift

in

"

"

of

lost,

are

and

built

piers,

work

and

about

span:

Kentueky

Ohio

day

each

BRIDGE.

short

Kentucky

yard!:!.

were

yards.

average, piers

piers

The

same

a

pei-

feet

great,

yds.

j

yds.

"

140

"

"

of

masonry

substructure,

hours

lives

position

cubic

and

cubic

550 river

en.

cu.

abutment

river

1887. feet

very

and

no

in

the

inches

1888.

floor

42

the

first

I:S

two

the

eight

of

and

logs

1887.

but

17th,

success.

66.150

to

66.150

of

1888. Cl:SCINNATI

its

times

963.663

Ohio,

9th,

465.910

on

431.603

405.342

the

861.172

exp2rienced.

7i

1398.680

3

4

river,

.4

at

in

.1

lumber

.3

OF

timber

..

24th,

_

130

for

Portland.

ends

})ile

30th,

working

of

June

..

cutting

hends,"

perfect

____

____

was

·was

statement

.

abutment

CONTENTS,

CoNTE!I."'TS.

_. _.

"

a

cement.

the

_ . _

per

......

September

bed

spans,

pier

about ......

_

June

volume.

from SPANS di~p]acement.

at

concrete.

top,

__

.....•....

remained

was

weeks

to

German caissons

of

_____

-. . . . .

- timber.

......

including

pier

Septeml)er

pier

......

on

feet

__

caissons

of

days,

Yarions

succinct

-

yards

...

and

M.

two

c.1rried

yards

so-called

approximateJy,

a

·steel

RlVER

injured

..

.....•

Louisville

...... •....

pier

caissons

......

B.

the

is

Kentucky Ohio

caisson

Alsen's

......

the

hath

cubic

---

......

time

cubio

day,

bed-rock

ON

and

loads

weight

weights,

cubic

on

bottom

two

stone

feel

hy

stone

in

except

working

Kentucky Ohio

Total

Total

the

day.

harr.•ls per

at

tbe

the

barrels

033

383.73

iron

all

total

BURR

apparently

per

heat

loads,

155.735

569.73

550

following

Kentucky

foot

delay,

Rate

Oolitic

Oolitic

Began

Freestone

Completed Completed

Freestone

Limestone--.-

Began

Actual

Limestone

153

4 3 450

5

Distance

514 and

over

disabled

men

The The

No

The

insufficient

The

moving

masonry,

ture,

square

the uously.

cribs

were

smoothly

up-stream.

to

60 and

~~:S.

1

test

gira.era.

qh~racter

timsh.

S~andard

IHec<'"-

!1~1~~~~

Plate

ments.

~~d~i;!~~~s

if

as

at at

or

of

in

of

be

in

an

65

but

this

two andAuchoiage.

the

and

and

rolls

.

same

shall

be

mini-

shear

eta

of

thick-

of

square

of

and

ends

uniform

pressure

the

on

shall

a

in

;

(t)

designed

thousand

protected

rollers

the

centers

a-

Whenever

poe

shall

motion,

sliding

parallel;

required

of

resist

upward

size

manufacture

so

of

be

of

of

that

er

masonry,

t-

the

inch

meeting.

to

all

inch

d k

point

of

be

provision

be

t- wrought-iron

practicable,

.

and of

quarter

be

and

on

Adjacent

em

the

area.

ductility

lines

BRIDGE.

shall

maximum

a

turned

of

thus

thirty-six

than

sideway

not

requirements against

to

joint

lineal

with,

shall

than

shoulders

the

the

the

shall

rom

calculated.

and

I

and

the

max~um

and

than

less

the planed

per Will

provision

plate

plates

only.

number

fibrous,

less

diameter

that

and

web

with

exceed

at

Whenever

matters.

be

or

the

less

free

membzrs

bed

anchored

bed

anchored

truly

the

not

the tb.e

stiffened.

fulfills between

complied

members

be planed

not

finish

ilot

upward

of

CINCINNATI

correctly

the

of

be

elasticity

is

be

ductile,

bending

press11re

inch.

all

of

d

cracks.

foreign

coincide

be

OF

and

of

intersect

process

firmly

will

piece,

never

smooth,

shall

of

shall

securely

or

office

dimension,

the

tangent

common

material

be

out

properly

prevent

surface

proportioned

resist

;

can

t,

approaches

bar,

determine

tough,

shall

between

cannOt be

test

a

shall

the

where

to

square

limit

case

so

to

shall

the

to

the

MATEBIALS.-WROUGHT-IRON.

SPANS

be

'bar

d,

1

plates

keep -specific

as

steel

cases

is

be

size

masonry

and

perfection

blisters

shall

shall

OF

stra1g

motion.

web

stress

have

to

rolling

shortest

the

of

No

all

000

member

either

girders

flanges

full than

of

the

attachments

must

shall

trusE!

standard

of

the

in

be

its

RlVER ass,

in

reduced,

the

same

provided

str~ngth,

conditions connection

They

shall

bearing

holes

a

c

each

on

of

the

be

is

casing

anchored

v'540

the

and

buckles,

plate

and

ones.

lines

h

ON

of

each

QUALITY

a:p.d

more

the

shall

on

of

and

so

stiff

times

bridge.

from

these

eac

spans

foot

of

a

the

shall

longitudinal

tensile

cross-section~, not'

from

thickness_

flaws,.

end

it of

that

exceed

or

pounds.

for B'CHR

motion.

I I . h

stress

plates

rollers

rollers

surface

of

d~manded,

thinner

thickness

surfaces,

wrought-iron

the

cross-section

The

cut

designing

twelve

where

and

and

and

not

side

square·

.

be

the

1ty

cross-section

other

000)

All

As

3.

One.end

The

The

wrought-iron

Bed

the

The

Connections

In

made

a!

qu

(H6

ness, the permitting

will-produce, injurious will

by in inches.

specification. determined consecutive the mum each

rolling per

sideway

shall

least

inch

be

gravity cases

practicable,

bearing

rivets.

that inch,

only,

to

ori.

be­

be

the

the

the

the

less.

and

one-

that

least

(50).

r

to

not

as angl~s

or

by tension

(±)inch

its

working

from

sway-rod.

thousand

are

fifty

and

than

rivets

of

to

and

shall

intervals

well

pressure

right

ror

proportioned

combinations.

stress,

provided

for

clause_.

found

five-sixteenths

at

less

as

so

the

of

all

exceed

distance

points

be

thirtefm

BRIDGE.

be last

inches, be beads

lateral

one-quarter

than

posts,

for

for

suitable

painting.

line

intensities

not

to

intensities

in

the

pounds

the

not

The

No

at

span,

shall

in

supports less

bending

for

than

compression

end

and

of

in

stress

stress)

and

are

does

l'

or

of

000)

?"'"

as

l'

the

U-)

shall

less

rods

tensile

"'

the

column

supporting

__

of

min. max.

(15

specified

or

000

I formula:

1

CINCINNATI

2

of

and

pins.

the

all

stresses

between

inclined

ooo

supports

1

20

accessible

bending.

members.

shearing

stresses

gyration supported

resist

to

_(45).

01<'

14

painting,

for

intensities

is

+

bars

midd]R

of

(I-

and

be

the by

diameter.

1

for

to

between

one-eighth

wind

+20000

length

support,

of

signification

thousand

for

of

1

the in

the

face

compression

__

000

distance

following

of

between

all

them.

diagonals

the

SPANS

4

shall

radius

than

=

pounds

percent.

pounds.

strut

I

stress

l

bar.

forty-five

chords

parts inches. one

same

for

the

inch

the-

alternating

line

R

fifteen

specified

of

struts

in

upon

less

(50)

to

of

to

nearest

000)

the

(1)

by

000)

top

the

least

main-

R

strength

other·stresses.

)

only

metal_in

distance 0

or

accessible

RIVER

of

to

undue

on

exceed

(18

proportioned

{14

(:/

fifty

one

steel

of

members

full

allowed

st1·ess

threaded

have

are lengt:Q.

the

tension.

acting

with

intensity, 01'\

:flange

of

subject

be

r

when

not

surfaces,

gyration

and

body

of

of

the

be

of

of

stress,

than

and

diagonals

length

of

the

other

\)

faces

and

of

1

the

inch

formula:

shall

l

(

forces shall

of

BURR is

thousand

-tension

struts

thousand

proportioned

less

ratio

interpolated.

shall

pounds

stresses

intermediate

eyes

thickness

all plate

limits

to

an

addition

bearing

main

R

R,

rattling

line

compression

bOth

be

be

develop

one-thirtieth radius of

of

ratio

000)

Steel

Pins

The

On The Long An

T.he The

On

For

In For

the

to

wind

(-ftr)

shall

shearing

edge

64

where

avoid

to when

diameter

as shall

of than stresses where sixteenth

least

welded

(13

eighteen

directly

the

fourteen following

rivets.

and

stresses.

rods.

and

1Ubers.

upset Ere-bars

Wind ~pression Pins

Alternating

stresses.

of of

inspeo­

of of

steeL steeL

Inspection. Inspection.

weights. weights.

Variation Variation

tion. tion.

Time Time

Rivet Rivet

a a

so so

in in

to to

it it

bf bf

are are

on on

the the

its its

69 69

the the

000 000

on on

they they

com­

than than from from

have have

early early

be be

were were

num-

4 4

tough tough

on on

plates plates

means. means.

clause clause

single single

by by

of of

as as

_pattern _pattern

elonga-

rolling~ rolling~

pounds pounds

shearing shearing

a a

material material

tested tested

cast cast

the the

be be that that

in in

joints joints

may may

necessary necessary

to to

at at

more more

bars bars

proceed proceed

of of

shall shall

number number

fracture fracture

such such

000 000

position position

so so

the the

as as

of of

within within

tallow. tallow.

the the

such such

the the

of of

limit, limit,

and and

when when

sheared sheared

60 60

true true

shall shall

sustaining sustaining

by by

afforded afforded

stated stated

surfaces surfaces

bars bars

promptly promptly

of of

square square shall shall

1on. 1on.

into into

and and

requirements, requirements,

of of

t' t'

of of

transmit transmit

sample sample

be be

as as

BRIDGE. BRIDGE.

rolled rolled

sign sign

greater greater

leaves leaves

make make

and and

and and

. .

agreement, agreement,

wheie wheie

members members

bearings bearings

elastic elastic

the the

inch inch

it it

strength strength

made made

lead lead

to to

pounds pounds driven. driven.

materials materials

reJeC reJeC

the the

1 1

quality quality

castings castings

shall shall

obtained obtained

an an be be

being being

which which

abutting abutting

capable capable

brought brought

~ ~

are are

500 500

progresses, progresses,

even even

strength strength

blow-holes, blow-holes,

contractor contractor

be be

all all

special special

the the

fracture, fracture,

without without

weight, weight,

white white

grooves, grooves,

it it

below below

girders girders

be be

rolled rolled

to to

tensile tensile

will will

of of

before before

are are

and and All All

which which

present present

or or

then then

abutting abutting

as as

in in

a a

of of

the the

pieces pieces

bolts bolts

of of

by by

or or

any any

cause--;~_vr cause--;~_vr

and and

rivets rivets

may may

flat, flat,

CINCINNATI CINCINNATI

purpose purpose

e e

of of

shall shall

tensile tensile

load load

not not

plate plate

cent. cent.

of of

by by

from from

as as

proportionately proportionately

tons tons

19, 19,

steel steel

the the

is is

have have

permits. permits.

OF OF

then then

shUts shUts

made made

mill mill

turned turned

a a

of of

point point

specified, specified,

material material

this this

20 20

weight weight

lot lot

per per

members members

Sample Sample

specified, specified,

the the be be

may may

is is or or

and and

lot. lot.

plates plates

double, double,

CAST-IRON. CAST-IRON.

or or

4 4

moulds moulds

cold cold

determined determined

central central

the the

the the

first~class. first~class.

d d b

protected protected

him, him,

must must for for

work work

the the

the the

on on

absence absence

e e WORKMANSHIP. WORKMANSHIP.

before before

tests, tests,

a a

specified specified

16 16

at at

of of

SPANS SPANS

"fi "fi

that that

be be

be be

flanges flanges

a a

shall shall

exceed exceed

iron iron

the the

of of

inspector inspector

connected connected

sand sand

by, by,

than than

bend. bend.

the the

bars bars

universal universal

throughout throughout

splice splice

of of

finish. finish.

planed planed

given given

tests tests

when when

of of

in in

quality quality

speCl speCl

area area

not not

separate separate

tests tests

in in

bending bending

the the

-in -in

inches inches

must must

must must

the the

work work

I I

are are

have have

facilities facilities

a a

test test

clauses clauses

injurious injurious

there there

of of

be be

for for

a a

opposite opposite

6 6

RIVER RIVER

if if

of of

·except ·except

rejecting rejecting

more more

of of

or, or,

inch inch

of of

that that

chilled chilled the the

and and

lh lh

cross~section cross~section

the the

in in

shall shall

number number

metal metal

contact contact

and and

notice notice

nature nature

ON ON

feet feet

shall shall

from from

for for

rolled rolled

of of

but, but,

in in

of of

truly truly

holes holes

must must

and and

4 4

for for

rom rom

lots lots

surfaces surfaces

f f

upon; upon;

the the

nu~ber nu~ber

such such

due due

square square

where where

spaced spaced

be be

results results

. .

surface surface

members members

of of

necessary necessary free free

capable capable

bar. bar.

inch, inch,

I I

larger larger

constitute constitute

workmanlike workmanlike

steel steel

heat heat

members, members,

as as

reduction reduction

rivet rivet

in in

cause cause

BURR BURR

determined determined

plates plates

a a

a a

be be

inspection inspection

per per

Such Such

workmanship workmanship

cen cen

AU AU

rolled, rolled,

such such

shall shall

be be

after after

spliced, spliced,

span span

variation variation

show show

be be iron, iron, be be

agreed agreed

each each

of of

and and

finished finished

rough rough

same same

for for

provided provided

The The

When When

All All

convex convex Inspection Inspection

square square

and and

.Except .Except

A A

per per

The The

Rivet Rivet

period period

shall shall

accurately accurately

All All a a

pression pression

fully fully

holes holes

the the clear clear

-"]" -"]"

-the -the

-gray -gray ber ber

make make

:and :and

been been

~, ~,

manufacturer; manufacturer;

being being

·shall ·shall 17, 17,

tests, tests,

mill. mill.

per per

taken. taken.

the the

tion tion

pounds pounds

(or, (or,

shall shall

shall shall

-pattern, -pattern,

bars) bars)

a a

as as

in in

to to

In In

be be

are are

the the

the the

the the

the the

test test

bars bars

less less

and and

may may

such such

four four

tests tests

per­

from from

cent. cent.

indi~ indi~

limit limit

made made

taken taken

steel, steel,

if if

when when

inch. inch.

to to

at at

a a

of of

te-nsile te-nsile

break­

of of

than than

twelve twelve

have have

stretch stretch

be be

require~ require~

3 3

the the

avf'rage. avf'rage.

of of

not not

the the

two two

be be

per per

strength strength

and and

give give

and and

for for

contractor contractor

are are

stated stated

inch. inch.

was was

of of

purchaser, purchaser,

4 4

fracture fracture

considered. considered.

less less

plates plates

the the

all all

strength strength

bai-; bai-;

the the

after after

arranged arranged

elastic elastic

than than

it it

area area

squar~ squar~

must must

from from

will will

of of

the the tests, tests,

be be

area area

tests tests of of

correctly correctly

or or clause clause

the the

tests tests

quality quality

furnished furnished

tests tests

bars bars

not not

than than

of of

an an

therefrom therefrom

tensile tensile

pounds pounds

test test

resistance resistance

by by

per per

and and

of of

square square

of of

less less

below below

of of

charge, charge, and and

a a

ten ten

not not

BRIDGE. BRIDGE.

be be

tensile tensile

test test

the the

the the

point point

which which

cut cut

making making

bars bars

desire desire

bar, bar,

000 000

result result

the the

dimension dimension

more more

per per

not not

if if

measured measured

These These

heat, heat,

in in

the the

50 50 cent. cent.

of of

have have

than than

reduct.ion reduct.ion

shall shall

the the

tensile tensile

of of

the the

area area

: :

requirements requirements

shall shall

pounds pounds

additional additional

may may

be be

cracks cracks

additional additional

+ +

from from

alone alone

pieces pieces

at at

reduction reduction

of of

: :

furnished furnished

without without

per per

lot lot

specified; specified;

by by

of of

reduction reduction

sample sample

test test

he he

or or

4 4

provisions provisions

each each

results results

000 000

of of

must must

more more

be be

000 000

supervision supervision

length length

bar bar

shortest shortest

pounds pounds

such such

test test

shall shall

as as

for for

area area

the the

its its

clause clause

accepted accepted

that that

uniform uniform

68 68

included included

for for

a a

curve curve charge. charge.

desires desires

CINCINNATI CINCINNATI

the the ultimate ultimate

pieces pieces

in in

200 200 than than

strength strength

of of

the the

a a

not not

the the

round round

flaws flaws

mann~r mann~r

gives gives

bars bars

shall shall

be be

of of

be be

machine, machine,

be be

1 1

respective respective

and and

to to

a a

tests tests

flaw, flaw,

at at

OF OF

the the the the

of of

each each

square square

contractor contractor

reduction reduction

test test

rolling, rolling,

determined determined

more more

test test

bars bars

follows: follows:

of of

ductility ductility

times times

the the

having having inch inch

shall shall

or or

from from

under under

piece piece

than than

shall shall

cast cast

percentage percentage

particular particular

and and

tensile tensile

shall shall

following following

such such

without without

the the

elongation elongation

each, each,

the the

fracture. fracture.

be be

total total

as as

a a

and and

strength strength

occur occur

testing testing

ten ten

reduction reduction

contractor contractor

and and

SPANS SPANS

these these

a a

following following

test·· test··

free free

of of

to to

les~ les~

by by

the the

the the

and and

manifest manifest for for

the the finished finished

tests tests

a a

the the

each each

that that

results results

of of

inch, inch, four four

and and

round round

a a

of of

square square

be be

in in

in in

the the

of of

the the

conforming conforming

of of

be be any any

must must

not not

expense, expense,

strength, strength,

selected selected

if if

tensile tensile

additional additional

from from

additional additional

tests tests

such such

have have

if if

in in

heating heating

'point 'point

has has

if if

made made and and

per per

RIVER RIVER

jaws jaws

inch, inch,

giVing giVing

half half

forth forth

compression compression

must must

square square length length

material material

elasticity elasticity

the the

own own

shall shall

be be

the the

one one

the the

ingot ingot

two two

or, or,

the the

but but

determined, determined,

satisfied- and and

and and

ductility, ductility,

contract contract

but, but,

diameter, diameter,

were were

pieces pieces

length length

shall shall

manufacturer manufacturer in in

ON ON

of of

above-described above-described

-;-

made made

piece piece

set set

of of

of of

of of

tensile tensile

one~ one~

the the

per per

.his .his

thus thus

be be

finish, finish,

and and

bars bars

not not

one one

and and

in in

the the

pounds pounds

requirements, requirements,

from from

be be

of of

at at

square square

each each

each, each,

test test

elongation elongation

for for the the

000 000

the the

test test

is is

used used

between between

bar bar

original original

, ,

limit limit

to to

effect effect

charge, charge,

sides sides

than than

which which

000 000

BURR BURR

results, results,

shall shall

of of

on on

$5 $5

1·ejected, 1·ejected,

per per required, required,

samples samples

be be

said said

For For

asunder asunder inch inch

tests tests

by by

400 400

an an

manner manner All All

average average

4 4

From From

specified. specified.

pounds pounds

any any

in in

theffi theffi

the the

round, round,

2 2

be be if if

of of

uniformly, uniformly,

each each

to to

quality quality

tests tests

le13s le13s

an an

on on

bending, bending,

him him

If If

Except Except

an an

both both

Finished Finished 19. 19.

the the

17. 17.

16. 16.

without without

may may

below below

ments ments average average

For For

which which

in in the the

for for

above above

strength, strength, cates cates

make make

pulled pulled

purchaser purchaser

will, will,

rate rate

for for

for for

workmanlike workmanlike

on on

ing ing

diameters diameters

determining determining

piece, piece,

centage centage tested tested

than than of of

pounds pounds

not not

within within

material material

68 68

cool cool truly truly The The

steel steel

62:500 62:500

test test

area area

of of

of of

tests. tests.

andre-

finished finished

Number Number

pieces. pieces.

ductlOn ductlOn

{ln {ln

bars. bars.

Tensile Tensile Fini~h Fini~h

and and

tests. tests.

Inspections Inspections

Timber. Timber.

Railings. Railings.

Camber. Camber.

to to

in in

in in

the the

the the

73 73

and and

any any

and and

not not

ties ties

The The

time time

and and

than than

than than

than than

shall shall

oak, oak,

floor floor

floor floor

coats coats

of of

of of

not not

or or

partial partial

of of

placed placed

and and

timber. timber.

shakes, shakes,

pounds pounds

of of

suitable suitable

tonguedBcreens. tonguedBcreens.

less less

a a

strongly strongly

mutually mutually

the the

less less

less less

shall shall :firmly :firmly

otherwise otherwise

mills mills

specified. specified.

track track

of of

test test

white white

of of

three three

system. system.

in in

(30) (30)

if if

be be

timber timber

not not

wind wind

bolts bolts

brackets brackets

not not

holes, holes,

Intermediate Intermediate

not not

of of

the the

make make

length length

be be

beams beams

The The

wide, wide,

foot foot

them them

splitting splitting

bottom bottom

of of

lap-jointed lap-jointed

kinds kinds

provided. provided.

with with

of of

floor floor

chords chords

at at

and and

shall shall

between between

inch inch

from from

thirty thirty

and and

to to

or or

BRIDGE. BRIDGE.

be be

be be

shall shall

floor floor the the

temperature temperature

of of

worm worm

thorough thorough

the the

inch inch

of of

(i) (i)

cubic cubic

treatment. treatment.

inehes, inehes,

accepted accepted

a a

sides sides

span. span.

secure secure

free free

creosoted creosoted

a a

inches inches

of of

mil mil

thereto. thereto.

structure. structure.

of of

sufficient sufficient

also also

the the

piers piers

Fahrenheit, Fahrenheit,

shall shall

to to

at at

floor-beam floor-beam

placed placed

a a

pins pins

design, design,

be be

(4) (4)

(10) (10)

of of

the the

pressure pressure

each each

material material

The The

the the

to to

both both

railway railway

all all

paid paid

a a

before before

of of

be be

wood wood

cracking cracking

square square

of of

inspectors inspectors

the the

shall shall

to to

of of

is is

pressure pressure

ten ten

) )

on on

will will

riveted riveted

sap-wood, sap-wood,

They They

four four

base base

0

the the

wood wood

and and

-

stiffness stiffness

0

degrees degrees

over over

full-sized, full-sized,

by by

the the

per per

oil oil

line line

CINCINNATI CINCINNATI

by by

done done

or or

shall shall

under under

mercury, mercury,

These These

ends ends

approved approved

three-quarter three-quarter

wind wind

sound sound

(cl

the the

apart apart

stays stays

than than

fastened fastened

sufficiently sufficiently

be be

from from

a a

OF OF

ways ways

of of

of of

(230) (230)

of of

wind, wind,

by by

the the

painted painted

estimate estimate

avoid avoid

iilspect iilspect

durability. durability.

center center

floor floor

sidewalks. sidewalks.

wood wood

extend extend

feet feet

brash brash

inches inches

creosoted creosoted

requ~ite requ~ite

pounds pounds

of of

be be

at at

directly directly

must must

creosote creosote

more more

be be

t'ests. t'ests.

or or

to to

of of

resist resist

the the

outside outside

be be

(8) (8)

quality. quality.

the the

wagon~ wagon~

inches inches

height height

wagon-waJ. wagon-waJ.

final final

SPANS SPANS

the the

out out

(10) (10)

thirty thirty

shall shall

to to

first·dass first·dass

securely securely

shall shall

stringers stringers

not not

hundredth hundredth

on on

to to

shall shall

(150) (150)

flooring flooring

railway railway

floor floor

the the

as as shall shall

(24) (24)

of of

the the

the the

into into

best best

be be

heavy heavy

seasoning seasoning

decayed decayed

and and

ten ten

each each

and and

eight eight

the the

masonry masonry

strong strong

so so

paint. paint.

required required

be be

strength strength

the the

secure secure

trimming trimming

the the

of of

RIVER RIVER

the the

fifty fifty

operation operation

supported supported

plank plank

on on

They They

timbers timbers

above above

true true

the the

to to

timber timber

shall shall

its its

over over

for for

the the

than than

of of

to to

eighteen eighteen

with with

railings railings

Before Before

knots, knots,

and and

reduce reduce

be be

ON ON

inspectors inspectors

measured measured

shall shall

between between

as as

and and

guards guards

this this

in in

inject.ion inject.ion

be be

pine pine

thorough thorough

apart. apart.

floor floor

to to

high high

metallic metallic

with with

hundred hundred

one one

pounQ_s pounQ_s

in in

twenty-four twenty-four

foo~. foo~.

sawed sawed

to to

a a

make make

more more

minimum. minimum.

supported supported

the the

shall shall

loose loose

as as

bolted bolted

a a

provided provided

of of

is is

BURR BURR

and and

outside outside

notched notched

be be

feet feet

feet feet

upon. upon.

wheel wheel

timber timber

by by

(12) (12)

stringers stringers

two two

camber camber

sereens sereens

stringers stringers

laterally laterally

framing framing

by by

than than

impairing impairing

manner manner

so so

used used

and and

to to

or or

not not

and and

oil oil

be be

be be

hundred hundred

a a (4) (4)

(4) (4)

groove

square square

Competent Competent

All All

Sap-wood Sap-wood

1st, 1st,

The The

prepared: prepared:

They They

The The 2cl, 2cl,

The The

Two Two

The The

The The

The The

less less

shall shall

approved approved

one one timber. timber.

being being

be be

twelve twelve

This This

vacuum vacuum

exceed exceed

defect defect

large large

railings railings

connections connections

braced braced

:agreed :agreed

.-sound. .-sound.

-shops -shops

It It

and and

per per

built, built,

of of

securely securely

'stays 'stays

be be

four four

four four

beams beams

shall shall

shall shall

beams beams

_place. _place.

·such ·such

(3) (3)

(it) (it)

be be

be be

the the

No No (50) (50)

and and

and and

cen­

pine pine

shall shall

con­

their their

side. side.

holes holes

guard guard

on on

inches inches

nailing nailing

twenty­

the the

two two

wrought wrought

fastened fastened

fifty fifty

shall shall

must must

horizon­

to to

three three

quality. quality.

(4) (4)

wide. wide.

thickness. thickness.

that that

each each

the the

nuts, nuts,

of of

rivet rivet

by by

thicknesses thicknesses

yellow yellow

by by

adjustment adjustment

connections connections

in in

flooring flooring

to to

pine pine

so so

on on

nuts nuts

inch inch

best best

of of

both both

wid~, wid~,

or or

secured secured

four four

punching punching

wood wood

center. center.

screws screws

two two

;) ;)

planks planks

inches inches

three-quarter three-quarter

1

adjustment. adjustment.

check check

All All

the the

nuts. nuts.

rigid rigid

inches inches by by

oak oak

to to

BRIDGE. BRIDGE.

(l

outside outside

feet feet

plate plate

of of

lag lag

by by

edges edges

yellow yellow

of of

(8) (8)

of of

fastened fastened

placed placed

inches inches

all all

uniform uniform

(g) (g)

a a

Tequiring Tequiring

sidewalk sidewalk

and and

fastened fastened

and and

(3) (3)

or or

the the

through through

split split

be be

timber timber

(8) (8)

white white

for for

be be

creosoted, creosoted,

center center

the the

inch inch

nails nails

and and

inches inches

with with

eight eight

or or

eight eight

sway-braced, sway-braced,

section. section.

consist consist

oak oak

of of

and and

bearing. bearing.

heads heads

(t) (t)

sixteenth sixteenth

purpose purpose

three three

stringers stringers

bolts bolts

and and

shall shall

in in

by by

also also

bolts bolts

(13) (13)

shall shall

from from

threads threads

eight eight

be be

members members

than than

practica.lly practica.lly

penny penny

CINCINNATI CINCINNATI

to to

shall shall

crack crack

the the

All All

piece piece

the the

white white

spliced spliced

under under

creosoted creosoted

be be

seven seven

stringers. stringers.

about about

to to

than than

OF OF

(40) (40)

shall shall

uniform uniform

inches inches

inches inches

inches inches screw screw

of of

other other

pieces, pieces,

more more

not not

be be

the the

lap-jointed lap-jointed

of of

for for

of of

a a

thoroughly thoroughly

thirteen thirteen

rails. rails.

by by

(8) (8)

{8) {8)

of of

shall shall

all all

five-eighths five-eighths

(14) (14)

not not

be be

wagon-way wagon-way

-be -be

wagon-ways wagon-ways

wagon-way wagon-way

be be

will will

more more

be be

forty forty

top top

specified. specified.

shall shall

bolted bolted

Washers Washers

allowed. allowed.

spaced spaced

preference preference

SPANS SPANS

have have

by by

nailing nailing

consist consist

and and

outer outer

and and

edge edge

by by

on on

eight eight

the the

the the

the the

be be

wagon-ways wagon-ways

inch inch

eight eight

not not

wrench wrench

be be

shall shall

in in

sidewalks sidewalks

adjusting adjusting

be be

shall shall

·shall ·shall

shall shall

metal metal

of of

of of on on

timbers timbers

be be

a a

of of

the the the the

by by

shall shall

(7) (7)

the the

girders girders

fourteen fourteen

shaH shaH

and and

thick thick

shall shall

the the

will will

RIVER RIVER

of of

the the

used used

with with

thickness thickness

shall shall

fastened fastened

of of

secured secured

shall shall

of of

with with

tie tie

nuts nuts

guard guard

planes planes

timbers timbers

be be

sidewalks sidewalks

plate plate

ON ON

sway-rods sway-rods

center. center.

flooring flooring

thick thick

inches inches

flooring flooring

be be

flooring flooring

wrought-iron wrought-iron

seven seven

structure structure

bolts bolts

that that

fastened fastened

spaced spaced

between between

flooring flooring

inches inches

of of

to to

and and

planes planes

and and

(6) (6)

flOoring flOoring

the the

and and

stringers. stringers.

pieces pieces

access. access.

shall shall

uniform uniform

fourth fourth

guard guard

vertically. vertically.

shall shall with with

provided provided

(2~) (2~)

top top

such such

flooring flooring

BURR BURR

under under

flooring flooring feet, feet,

stringers stringers

under under

with with

under under

six six

shearing. shearing.

inches inches

top top

cross-ties cross-ties

ties ties

vertical vertical

whole whole

of of

and and

webs webs

space space

thick, thick,

the the

accessible accessible

the the

center center

be be

be be

bolts. bolts.

and and

(2) (2)

vertical vertical

(22) (22)

of of

The The

The The

The The

The The

of of

The The

The The

rrhe rrhe

The The

The The

These These

Every Every

They They

The The

plank. plank. Washers Washers

The The

nailing nailing

Lateral Lateral

The The

The The

Rivets Rivets

resist resist

penny penny

pieces pieces

be be spikes. spikes.

to to

two two

one-half one-half

of of

from from

top top

tral tral

inches inches

central central

inch inch

timbers timbers

two two

easily easily tally tally

provided provided

bo bo

venient venient

riveting. riveting.

round-headed round-headed shall shall

shall shall

72 72

t!.oor. t!.oor.

washers washers

bracing. bracing.

nuts. nuts.

Roadways. Roadways.

Railway Railway

Bolts, Bolts,

Sway Sway

Adjustment. Adjustment. :and :and

test test

bars. bars.

S~andard S~andard

pieces. pieces.

Test Test

to to

of of

he he

be be

77 77

be be

the the

the the

the the

ten ten

per per

not not

and and

that that

pins pins

bars bars

inch inch

shall shall

after after

must must

more more

when when

point point

head, head,

cross-

borne borne

under under

price, price,

piece. piece.

of of

of of

of of

to to

twelve twelve

of of

by by

sample sample

quality quality

all all

shall shall

shall shall

strength strength

finish finish

specified specified

be be

fuvER fuvER

the the

not not

unless unless

the the

heat, heat,

the the

bar, bar,

thickness, thickness,

test test

in in

the the

These These

tested tested

square square

pounds pounds least least

bars bars

if if

in in

inch inch

sides sides

the the

length length

in in

cross-section cross-section

of of

belonging belonging

the the

also also

borne borne length length

that that

at at

t t

and and

round round

contract contract

OHIO OHIO

a a

own own

per per

measured, measured,

are are

rejected. rejected.

test test

used used

500 500

resistance resistance

be be

to to

alone alone

at at

of' of'

but but

than than

inches. inches.

inch inch

dimension dimension

be be

ductility ductility

BRIDGE. BRIDGE.

machine, machine,

break break

bars bars

sides sides

its its

58 58

be be

uniform uniform

two two

be be

shall shall

t t

full-sized full-sized

which which

be be

FOR FOR

5 5

the" the"

inch, inch,

cha1·ge. cha1·ge.

for for

or or

parallel; parallel;

a a

opposite opposite

as as less less

in in

A A

shall shall

if if

to to

having having

and and

minimum minimum

test test

equal equal

shall shall

both both

mp,y mp,y

rolls, rolls,

pieces pieces

cast cast

than than

samples samples

manufacturer, manufacturer, tests tests

strength strength

than than

at at

at at

than than

shall shall

Prns Prns which which

paid paid

testing testing

a a

ultimate ultimate

two two

the the

on on

form form

multiple multiple

lot lot

used used

eye eye

ancl ancl

square square

steel steel

test test

the the

lots, lots,

eye eye

piece, piece,

less less

turned turned

the the

a a

of of

less less

be be

section. section.

each each

without without

of of

a a

bars bars

be be

the the

rejected rejected

of of the the

STEEL STEEL

at at

respect. respect.

length length

CINCINNATI CINCINNATI

shoulders shoulders

the the

the the

not not

of of

of of

and and

shows shows

elasticity elasticity

of of

test test

finished finished

follows: follows:

full-sized full-sized

these these

to to

be be

such such

from from

in in

i-

area area

stretch stretch

jaws jaws

full·sized full·sized

full-sized full-sized

may may

shall shall

average average

nearest nearest

of of

in in

of of

bar bar

OF OF

as as

elongation elongation

this this

FOR FOR

be be

rejected rejected

of of

inch. inch.

the the

tests tests

the the

diameter, diameter,

original original

tests tests

the the

an an

may may

piece, piece,

practicable, practicable,

in in

from from

than than

the the

ingots ingots

planed planed

shorter shorter

from from

BRIDGE. BRIDGE.

to to

the the

come come

brt,rs brt,rs of of

break break

expense expense

in in

in in

the the

between between

of of

other other

which which

a a

the the

limit limit

bars bars

the the

lot lot

break break

writing writing

and and

shall shall

test test

of of

manufacturer manufacturer

and and

less less

between between

SPANS SPANS

of of

the the

and and

show show

square square

the the

same same

of of

the the

on on

all all

in in

inch inch

inch inch

they they

resistance resistance

half half

and and

any any

eye-bars. eye-bars.

from from

length length

limitations, limitations,

which which

be be

and and

at at

the the

belong belong

determined determined

the the

per per

an an

bar, bar,

tangent tangent

and and

bo~1y bo~1y

to to

which which

as as

but but

case case

reduction reduction

Whenever Whenever

ductility ductility

the the

one· one·

by by

of of

be be

head, head,

be be

be be

bars bars

strength, strength,

not not dimension dimension

RIVER RIVER

bars bars

among among

SPECIFICATIONS SPECIFICATIONS

expense expense

standard standard

the the

no no

it it

square square

average average

if if those those

the the

above above

tensile tensile

left left

dimension, dimension,

a a

barf'! barf'!

diameters diameters

boJy boJy

round, round,

the the

uniformly, uniformly,

objection objection

the the

original original

which which

the the

in in

from from

ON ON

in in

in in

pounds pounds

the the

one one

shall shall

shall shall

per per

must must

the the

steel steel

the the

inch. inch.

tested tested

shaH shaH

be be

but but

in in

than than

an an

or or

of of

value. value.

full-sized full-sized

making making

the the

tensile tensile

but but

if if

from from

cool cool

belonging belonging

bar bar

of of

500 500

truly truly

shortest shortest

to to

made made

on on

curve curve

reduced, reduced,

17; 17;

and and

in in

twelve twelve

break break

case case

less less

the the

to to

sides sides

BURR BURR

shortest shortest

62 62

From From

ultimate ultimate

lot lot

The The

costs costs

is is

break break

inch, inch,

be be full-sized full-sized

manufacturer, manufacturer,

scrap scrap

square square

bars bars

pounds pounds

the the

are are

material material

the the

before before

its its

be be

have have

not not

1 1

specified specified

lot lot

than than

its its

to to

exceeding exceeding

from from

determining determining

(3.) (3.)

break break

All All

(16.) (16.)

The The

Any Any

The The All All

the the

clause clause

original original

fracture, fracture, accepted accepted

either either

500 500

8UPPLE~IENTARY 8UPPLE~IENTARY

which which

the the

determined determined

shall shall

section section

opposite opposite cut cut

occur occur than than times times

breaking, breaking,

in in times times

any any

not not In In

shall shall in in

of of

of of

or or

58 58

lot lot

less less

here here manufacturer; manufacturer;

be be

piece piece

square square

heads heads

by by

furnished furnished bars, bars,

less less

are are

of of

arranged arranged

is is

at at

of of

in in

in in

an an

be be

lot lot

by by

the the

the the

the the

one one

the the

the the

the the the­

and and

lot. lot.

any any

eyes eyes

time time

pile, pile,

than than

shall shall

more­

more more

with­

made· made·

of of

rolled rolled

to to

agree­

below­

subse­

as as

inches. inches.

to to

of of

a a

and and

process process

tons tons

each each

afforded afforded

of of

must must

Ti Ti

rolled rolled

whatever whatever

by by

make make

be be

3! 3!

quality quality

leaves leaves

in in

'vith 'vith

same same

below below

time time

which which

holes; holes;

more more

dimensions dimensions

strength strength

the the

in in

20 20

be be

part part

cent. cent.

of of

separate separate

be be

being being

it it

to to

fmnished fmnished

special special

angles angles

the the

the the

a a

holes holes

pins pins

pin pin

than than

bars. bars.

advance advance

bars bars

not not

full full

promptly promptly

per per

any any

proportionately proportionately

cent. cent.

same same

dimensions dimensions

must must

from from

bars bars

at at

same same

under under

be be cover cover

can can

bars bars

4 4

of of

shall shall

in in

material material

placed placed

drawings, drawings,

any any

BRIDGE. BRIDGE.

then then of of

rejection. rejection.

considered considered

a a

the the

be be

the the

and and

manufacturer manufacturer

the the

in in

of of

of of

the the

the the

exceed exceed

per per

lot lot

before before

right right

all all

more more

of of

and and

present present

Of Of

for for

of of

be be

the the

4 4

pins pins

19, 19,

bars bars

than than

piece piece

the the

shall shall

at at

will will

or or

at at

given given

total total

steel steel

of of

o£ o£

rolled rolled

when when

tests, tests,

full-size full-size

size size

the the

constitute constitute

not not

in in

not not

centers centers

or or

is is

material material

a a

annealed annealed

line line

boring; boring;

that that

purpose purpose

for for

of of

of of

which which

is is

shall shall

bars bars

cause cause

than than

allowed allowed

the the

then then

more more

and and

16 16

in in

absence absence

whole whole

the the

eyes, eyes,

bored bored

in in

each each

be be

panel, panel,

shall shall

on on

be be

this this

if if

consist consist

and and

material material

through through

determined determined

full-sized full-sized

CINCil;o\NATI CINCil;o\NATI

notice notice

shown shown

inch inch

the the

center center

him, him,

structure. structure.

before before

variation variation

the the

more more

the the

exceed exceed

weight weight

that that

rejecting rejecting

between between

for for

eye-bars eye-bars

manufacture manufacture

of of

number number

may may

in in

shall shall

results results

and and

lo lo

piece piece

OF OF

will will

the the

lots lots

cross-section cross-section

clauses clauses

same same

the the

tests tests

of of

pass pass

the the

or or

number number also also

so so

no no

inspector inspector

thereby. thereby.

of of

additional additional

mark, mark,

for for

of of

not not

or, or,

of of

given given

in in

of of

of of

to to

on on

tests tests

for for

quality quality

; ;

accurately accurately

the the

results results

the the

the the

lot lot

heated, heated,

steel steel

straight straight

provided provided

than than

length length

larger larger

Such Such

for for

two two

otherwise otherwise

shall shall

giving giving

pattern pattern

if if

facilities facilities

of of

end end

to to

SPANS SPANS

charge, charge,

a a

and and

be be

shall shall

tests tests

length length

specified specified

a a

be be

cause cause

mode mode

the the

any any

notice notice

special special

strength strength

whatever whatever

upon upon

purpose, purpose,

the the

show show

lot lot

be be

of of

number number

more more

as as

making making

a a

thus thus

for for

for for

and and

from from

but, but,

determined determined each each

that that

A A

in in

required required

unless unless

and and

single single

cross-section cross-section

due due

; ;

must must

the the must must

holes holes

this this

record record

of of

partially partially

heads, heads,

where where

dimensions dimensions

taken. taken.

by by

at at

by by

a a

RIVER RIVER

be be

bar bar

provided provided

(or, (or,

bars) bars)

in in

without without

bars bars

weJds weJds

agreed agreed

shall shall

such such

well well

tests tests

necessary necessary

destruction, destruction,

that that

for for

from from

of of

pin pin

belonging belonging

the the

after after

of of

pin pin

ON ON

nor nor

all all

it it

holes holes

as as to to

same same

cases cases

as as

been been

No No

All All

shall shall

each each

rolled, rolled,

were were

bars bars

of of

allowed allowed

size size

been been

the the

bars bars

inspection inspection

cent. cent.

the the

purpose purpose

adjustable adjustable

make make

Eye-bars Eye-bars

members, members,

complete complete

pin pin

all all

the the

determine determine

number number

tests, tests,

be be

has has

of of

preserved. preserved.

For For

time time

variation variation

inch, inch,

head; head;

two two

A A annealed. annealed.

designated designated

BURR BURR

and and

to to

bars bars

teste4 teste4

of of

per per

and and

the the

number number

the the eye-bars eye-bars

have have

In In

mill. mill.

being being not not

To To 2 2

A A

All All

manufacturer manufacturer

The The

center center

of of

l

the the

be be

3

allow allow

be be

material material

2-;-

be be

will will

forcing. forcing.

of of

same same

annealing annealing manufacturers manufacturers

tests tests

35. 35.

Hs Hs

For For

requirements, requirements,

33. 33.

the the

23. 23.

head. head. All All

82. 82.

22. 22.

the the

may may

"lot." "lot."

shall shall

shape shape

of of of of

required required

quently quently

shall shall

eye-bar. eye-bar.

the the out out

number number

may may

length, length, in in

than than diameter. diameter.

must must

pieces pieces

diameter diameter

axis axis

than than

by by

sample sample rolling rolling

inch inch ment, ment,

such such

on on

proceed proceed

weight, weight,

as as

necessary necessary

greater greater

requirements, requirements,

ten ten

76 76

the the

sidered. sidered. the the 00 0 TABLE No.1. RAILWAY, TEsTs oF STEEL BY THE PH

TRANSFER AND BR1DGE COMPANY. ··-·-======c=== PouNDS PER 8QUAl\l;: lNCI! AT PER 0EN1.'. OF FiNAL Section of Bending Accepted or Fracture. Test.. Rejected. Heat. Material, Test Specimen Elastic Li mit. ·----- 72.560 24.75 48.70 Hom. 6669 Comp'~ Steel. %.,','0 48.570 4.7.890 71.660 24.75 43.20 6669 21.50 .1,5.10 6667 " " 47.640 70.100 48.5tl0 72.250 ~5.00 49.30 6667 " " 26.50 59.90 666,!, " 45.750 68.400 " 46.140 68.700 25.00 1\7 50 6664 " " 21\,00 64..80 6662 " 47.370 72.250 " 47.370 7l. 770 27.50 56.60 6662 " " 24.25 5!.10 6652 " 43.000 70.0.'i0 " 43.540 68.540 2.'5. 75 57.60 6652 " " 26.25 50.90 Reje.~ted. 6996 .. ~9.390 73.220 " .. 48.560 71 800 26.25 54.50 6996 " 27.00 58.80 Accer,ted, 6982 .. " 46.000 6!1,250 45.820 71.360 26.25 57.80 698,1, .. .. 57.50 6994 .. .. 46.150 69,960 26.25 47.700 70.940 27.00 56.20 6985 .. " 25.00 60.40 6983 .. .. 47.250 70.170 .. 45.820 67.300 26.75 59.20 6981 .. 26.00 54.90 6992 .. " 45.850 6~L020 48.430 70.700 27.50 58.80 6986 " " 45.50 69117 .. " ,U.SOO 67,800 25.00 45.300 65.600 26.00 62.10 6990 " " 2

TABLE No.2. RAILWAY, TESTS OF STEEL BY THE PH

POUNDS PER 8QU.AEIE INCH .AT PER CEST, OF J1'JNAL Section of Bending Aceepterl Fracture. I Beat. Material. Test I Test. Rf'jectf'd," Specimen. Ultimate Stretch in 8 Reduction. Elastic I.'imit. Strength. inchf'B,

0 45.910 69.570 28.75 61.10 Hom. 1~? fl~.t. Accer.ted. 6850 ComP;, Steel. x:·.o 50.50 6846 45.100 68.460 2!1..50 " .. 4!1..800 69.000 26.25 52.80 " " " " .... " 68.340 27.00 57.50 " " 6845 " " 4!1.,!!60 " " 6847 " " 46.260 ti8.58fJ 26.75 66.80 " " " " 46.030 69.160 25.00 1\3.30 " " " " 6848 " " 58.60 6696 !1.7.UO 72.100 26.50 " " " " " " 45. 'tO I ...... 6!l98 !I.!L840 71.680 23.50 " " " " 42.50 ...... 6f9M " " 49.070 72-:160 23.50 " " 6663 48.MO 72.090 26.26 55.60 " ...... " " " 57.40 ...... 6663 " " 47. '(50 '71.870 26.50 " " 49.170 7:.!.450 24.50 4-1.60 " ...... " 6692 " " 38,40 6692 4-9.170 72.160 25.75 " ...... " " " 4-2.30 6688 47.030 69.000 22.50 " ...... " " " 24.00 42.00 ...... 61i88 " " 4-7.170 69.340 " " 6674 46.290 67.940 26.75 50.00 " ...... " " " 26.50 53.73 ...... 667!1, " " 4-5.500 67.850 " " ------

00,... TABLE No. If.

CoviNGTON ELEVATED RAILWAY, TEsTs oF STEEL BY THE PHCENrx BmDGE CoMPANY FOR THE CINCINNATI AND TRANSI!'ER AND BRIDGE CoMPANY • ......

PouNDS I'Eit SQUARE lNOH AT PER CENT. 01>' FINAL Seciion Of Accepted or Test Fracture. Benclin~ Heat. Material. Specimen. 'l'est. Rejected. Ultimate Strength in 8 Reduction. Inches. Elastic Lfmit. Strength. inches. ··--- -..-. ------Silky cup, lBOQ on self. Acc,~pled. 335 X 1.015 X .4.02 40.690 68.630 30.00 38.48 ~"pl. 55.26 Silky cup. .. 336 10 X 1.015 X . 760 37.850 62.740 26.97 ' 1"Pl. 35.36 Ang. silky• ...... 338 12 X !"pl. 1.020 X . 010 49,980 76.320 24.00 56.10 Aug. silky...... 331 12 X ~"pl. 1.018 X ,605 42.610 66.150 25.00 27.50 Ang, silky...... 350 16 X £''pl. 1.000 X . 753 43.750 66.060 .. 1.020 X . 791 37.180 63.710 28.12 50.05 Silky cup, .. .. 3'9!1. 17! X H" pl. "" Silky cup, ...... 1.023 :X: • 796 34o.270 62,640 23.75 37.84 398 17! X ji" pl. Silky cnv...... 332 1!l.f X 1" pl. 1.025 :X: .500 41.170 ii4.400 25.00 52.6-i 25.00 54.74 Silky cuv...... 3ll 20 X In" pl. 1.030 :X: .430 41.100 63.230 .. .. 1.02 X 0.56 43,830 67.140 25.00 51.2S Sllky cup. .. 593 20 X ..ftJ" pl. Part cup and silky. .. 1.01 X 0.57 45.140 67.270 25.00 53.S7 6ll 20 x -fn" pl. Part cup and silky. " .. .." 610 20 XU''pi. 1.01 X 0.68 46.430 (i8.580 25.62 52.29 " 0.99 X 0.68 46.210 62.600 25.62 53.66 Silky cug...... 612 20 xU" pl. silky. .. X 0.68 40.300 62.550 2;1,50 47.15 An g. an " " 578 20 X H" pl, 1.01 Silky cup, ...... 579 20 xH"pl. .99 X 0.69 43.870 70.100 27.50 50.00 23.12 37.37 Silky cup...... 343 21!- X f'll" pl. 1.055 X ,330 49.9\JO fi8.950 .. .. 1.025 X .501 41.680 68.370 2i. 75 47.50 Silky cup, .. 334 24 X f' pl. Silky cup, ...... 399 llO X !"pl. 1.03 xOAB 52.300 64.920 22.50 52.83 23.75 U,50 Silky cup. .. .. 398 '' l.OHi x ,M8 44.950 62.930 " 30 x 1°0 pl. Silky cup. .. .. 406 30 X r',-" pl. 1.02 X 0.50 44,790 62.980 25.00 55.21 " 1.00 X 0.56 39.980 63.120 <:lf\,25 52.28 SilkY cup, I .. .. " 407 30 x -fu" pl. Silky cup. .. 390 30 x for" pl. 1.02 X 0.1i7 42,510 66.550 •t::. 75 51.01 " " 49.86 Silky cup. .. .. 368 29 X ~"pl. 1.020 X .597 48.610 69,460 25.62 " ,1,2.50 Silky cup...... 396 30 x t"a" pl. .992 X ,557 45.070 70.590 :•6,87 I .. I

TABLE No.6.

OoVING'.roN ELEVATED RAILWAY, TEsTS oF STEEL BY THE PHCENIX BRIDGE CoMPANY FOR THE CINCINNATI AND TRANS1!'ER AND BRIDGE CoMPANY. . -~----

PER SQUARE INmi AT PER CENT. OF FINAL of POUNDS Section Bending Accepted or TeRt ---· Fracture. Test, Rejected. Heat. Material.· Specimen. Inches. Ultimate Stretch in 8 Reduction. Elastic Limit. Strength. inches.

and silky. 180° on self. Acc~pted. 1.01 X 0.61 39.900 68.41(, 2S.12 45.13 Ang. 411 30x -l'r" pl. Silky cup. .. 30 X J( pl. 1.05 X 0.86 41.750 68.280 24.37 42.01 " 24,S7 4.4.15 Silky cup...... 415 30 X f' pl, 1.04 X 0.£3 !1.5.390 69.230 "' 22.50 S9.90 ll'l'cg. silky cup...... :X: ~" pl. 1.01 X 0.61 43.260 69.110 410 30 Ang. and silky...... 30 X fin pl, 1.03 X 0.61 39 .no 66.700 24.S7 36.84 400 48.115 Silky cup...... 401 SOx ~ .. pi l.Of X 0.6[) 49.3\lO 6\J.S80 28.75 SOx ~"pl. 1.04 X 0.62 43.010 68.200 2S.12 55.27 Silky cup...... 402 Irreg., ang. and silky, ...... 30 X pl: 1.02 X 0.61 40.320 68.540 24.37 37.01 403 i" 48.70 Irreg., a.ng. and siTh:y, ...... 389 BOx ~"pl. 1.020 X .613 Sf/.190 117.020 27.50 .995 X . 613 42.6<10 68.050 24. 47.04 Irreg., ang. and silky...... 393 30x ~"pl. ang. and silky, .. 1. X .607 42.180 69.200 26.87 48.10 Irreg, .... 395 ~Ox ~"pl. Irreg_,a.ng. and silky. .. 30x i"pl. 1.007 X .610 3\).210 69.200 27.50 47.59 .... 397 50.2-1 Silky cup, .. 359 SOx ~"pl. 1.005 X .623 42.960 66.460 28.75 40.350 68.270 20.63 34.89 Silky iLng. 180° on self. .. 360 SOx ~" pl, l.002x .502 .. .. 1.03 X 0.62 44.380 67.840 25.6:! 38.31 Ang. and silky. " 404 SOx ~"pl. Aug. and silky, ...... pl. 1.020 X .6:.!6 43.700 65.780 26.87 41.86 372 sox~" (;'8.520 4li.1 Ang. and silky. .. .. 382 30 X ~" pl, l.OHx .016 44.831) 21.1!7 " 25. 40.57 Aug. and silky, ...... 372 SOx ~"pl. 1.003 X .624 41.550 63.280 41 330 66.620 26.25 46.50 Aug, aud silky...... 377 SOx ~"pl. 1.033 X .631 ...... 1.026 X . 61.)0 45.190 62.770 26.87 44.84 At g. and silky. 383 30 X jJ" pl. An g. and sill!y...... pl. 1.023 X . 751 38.010 70.670 '<13.12 32.29 370 30x f' 4,3,63 Silky cup...... 30x 11"pl 1.040 X . 727 42.720 69.840 25.62 3!8 40.93 Silky cup...... 367 30 X pl: 4l 920 65.620 25.62 !i" 1.035 X . 795 42.14 Silky cup...... 378 30 X j," pl. 1.0,!.0 X .85·~ I 42. no 69.300 21.87 68.2(0 27.50 !17 .04 Silky cup...... 408 sox~" pl. 1.03 x0.86 37.390 LOS X \l. 86 39.4:10 69.140 26.87 49.05 Silky cup...... 409 30 X *" pl. I .. 00 "' 00 00 TABLE No. 9.

TESTS OF STEEL BY THE PHCENIX BRIDGE COMPANY FOR THE CINOINNATI AND CoVINGTON ELEVATED RAILWAY, TRANSFER AND BRIDGE COMPANY. - .. - I POUNDS PER SQUARE lNOH AT PER 0J!.NT, OF FINAL Section of Bending Ot' Test Fracture. Accepted Heat, Material. Specimen. Test. Rejecttld. Ult.imate Strelch in 8 Reduction. Inches. Elaetio Limit. I Strength. inches. -- 257.149 7 X 1£" .49 X 1.63 40.690 64.060 26. {3.2 Silky...... " .. Accepted.., 257.14.9 7xlj" .49 X 1.65 40.720 6~.840 27.8 51.5 Silky, ...... 259.506 7xW' .50x1.6..1 36.250 62.500 27.9 MJ,S Silky...... " 259.526 7 X}~" .49xl.65 36.420 61.980 27.8 44.3 Silky pitt...... " I lam. 261.5~7 7 :X: li" .51 x1.6:J 42.280 60.240 28.6 56.1 Silky...... " 258.756 7x lU" .50 X 1.83 40.050 64-.980 26.6 46.5 Silky...... " 261.324 7 xlU" .51 X 1.84 39.280 63.060 30.7 60.8 Silky...... " 261.318 7x1H" .49xl.83 39.740 61.810 27.2 49.1 Silky...... " 261.114 7x1-}ft" .49xl.84 38.430 63.020 27. I 42.1 Silky...... " 261.3lli 7 X 1}~" .50 X 1.82 37.860 65.090 28. 37.8 Silky...... " 259.410 7 X ltjj" .57 X 1.84 3(>,690 64.040 26.90 37,5 Silky...... " 259.354 7 X 1}i" ,li6x1.85 3~.990 62.580 29.60 52.90 Silky...... " 56.6 Silky. 259.1~3 7 X lN/" ,51 x1.85 39,570 62.560 32.2 I ...... " 257.590 7 X lH" ,58xl.S2 39.170 64.6~0 27.4 39.15 Silky gran...... " 21i7 .41::1 7 X 2" .51x2.02 36.880 62.400 30.0 39.6 Silky gran...... " 2·i7 .554 7 x 2-l-s" .5lx1.96 4Ulli0 63.610 32.1 48.6 Silky...... " Silky. 259.654 7 X 2-f'-6" .51x1.96 39.300 60.980 30.0 4.3.5 ...... " 257.960 7 X 2ft" .51 X 1.95 40.530 62.0!0 30.5 50.3 Silky...... " 21.5U 8x1N'pl, Diameter.S23 40.230 65.04.0 22. 44.53 Silky...... " 21.661 t! X 1{\'!" pl, .. .825 39.280 64.630 25.75 47.12 Silky...... " 21.553 8x1*"pl. " .815 40.830 71.400 27. 53.63 Silky...... " 21.525 8 X 1 \'!"pl. " .812 40.750 71.260 27.5 54.12 Silky...... " 21.533 8 X 1"1~" pl, " . 832 40.000 66.220 25 . 51.41 Silky cup, ...... " 8 X 1{ " pl, ,825 40.400 64-.540 25,75 52.6 Silky, ...... 21.529 6 " " 21.54.9 8 :X 1-N' pl. " .820 41.380 65.330 25.75 48.23 Silky cup...... " -

TABLE No. 10.

TEST OF STEEL BY THE Pm:ENIX BRIDGE CoMPANY FOR THE CINCINNATI AND CoviNGTON ELEVATED RAILWAY, TRANSFER AND BRIDGE CoMPANY. - -- - ,. Seetion of POUNDS PER SQUARE INCH AT PER CENT, OF FINAL Teet Heat. Material. Specimen. Fraetm'e. Bending Accepted or Diameter. Test, Rejected, Elastic Limit, mtimate Stretch in 8 Inches. Strength. inches, Reduction.

21 557 sx1r pl. .825 42.280 69.4.00 22.5 43.16 Rllky...... 21 599 8 X lffi" pl. ,812 38.630 65.280 25; 45.41 Silky, ...... 21603 SxlH''pl. . 814. 41.600 65.34.0 27.5 48. Silky, ...... 21619 8xl-H"pl. .815 40.640 64.600 25.5 49.36 Silky...... 21 591 8 X lh}" pl. .812 42.290 67,600 24. 42.62 Silky...... 21598 8 X 1f!" pl. .825 40.590 63.600 25. 47.98 Silky...... 21 607 3 X 1-k" pl. . 830 41.210 69.300 I 26.25 47.76 Silky...... Rivet Steel. *" round. 37.44.0 64.610. 29. 47. Cup sllky. 180<> flat. " 41.990 61.800 28.75 50.9 Cup silky. " " " 40.130 65.590 28. 42.8 Irregular silky. " " " 39.170 64.510 so. 61.2 Cup silky, " " .. 37.840 64.670 29.25 51.3 Cup silky. " " " 38.400 64.330 30. 62.0 Irregular sill1y. " " " 37.620 63.110 31.75 63. Irregular silky. " " " 38.810 63.920 28.75 59.5 Irregular silky. " " " 36.750 66.400 27.25 46.8 Irregular silky. " " H" ro.~nd. 37.890 63.620 30.5 56.3 Cup silky. ... I " 38.090 62.500 31. 56.5 Cup silky, " - I

00 "' TABLE No. 13.

TESTS OF STEEL BY THE PH

TRANSFER AND BRIDGE COMPANY.

I POUNDS PER SQUARE !NOH AT PXR CENT. O:F li'rNAL I Test Piece; Fracture and Remarks, Link Plate. length= 8 inches. I Elaat1c Limit. Ultimate. Reduction. Elongati'on.

~, 1 inch round. 28.530 61.140 50.3 27.5 Cup silky, 1 " 28.020 60.440 39.8 25.5 Angular silky. -~~·- . 1 " 26.880 58.340 63.0 30.0 Cup silky. 1 " 28.020 57.450 62.1 31.25 Cup eUky, ~~~ 1 24..260 60.280 51.6 26,00 Irregular silky. ~""~ " 25.860 63.310 51.9 25.50 Angular silky. fi: H: 1 " 1 " 26.110 63.310 64.5 28.75 Cup silky. o!

TABLE No. 14.

TEsTs OF STEEL AND IRON ANGLES BY THE Pmmux BRIDGE CoMPANY FOR THE CINCINNATI AND CoviNGTON ELEVATED RAILWAY, TRANSFER AND BRIDGE 00llPANY. - I POUNDS !'Ell. SQUARE !NOH AT PER CENT. OF FINAL

Test Pteoe; Fracture and Remarks. Size of Angle. length= 81ncbes. Ela.stlo Limit, Ultjmate. Reduction, Elongation.

5 X 3" 25 pounds. 1 1 X 0.32" 39.430 71.290 52.9 '21.25 Angular silky, .. 41 " 1 X 0.55" 39.110 71.580 55.5 27.25 Cup sllky. .. " I X 0.625" 38.650 69.650 46.4 26.00 Cup silky. 6 X 4" .," " I X 0.4" 39.440 71.105 54.3 23.75 Irregular silky. " .. 1 X 0.43" 39.010 69.860 52.7 23.75 Ang!!lar sil.~y. " ••72 .. i 1 X 0.74" 35.6IO 73.970 51.9 28.25 " 72 .. 1x0.73" 36.930 72.910 53,4, 27.75 .. " .. .. 1 X 0.86" 33.290 65.870 41.0 26.25 .. " .. J 1 X 0.84." 34.I70 63.060 60.8 31.25 .. .. lix 6" 57" .." 1 X 0.49" 26.120 46.920 28.1 20.50 Fibrous . .. "57 " 1 X 0.50" 27.270 46.060 18,9 13.75 " " 86 .. 1 1 x0.7l" 29,/iOO 50.600 25.3 21.75 " .. 86 " 1x0.70" 27.190 47,910 21.7 19.25 " .. .. 1 X 0.86" 25.110 45.910 23.9 20.00 " .. "95 .. 1 X 0.86" 25.230 48.120 28.7 26.21i .. .. 100 .. 1 X 0,88" 24.420 47.220 25.5 22.5(, .. .. 100 .. l,x0,90" 24.309 46.180 30.9 25.50 .. .. 108 .. 1 X 0.98'' 2!.540 47.000 21.2 21.25 .. .. 108 .. ) il 1 x_0.97" 24.050 48.090 26,0 20.50 .. " 108 .. 1 X 0.98" 24.670 48.730 30,1 25.00 .. Vol. XXIII, p. ~4. TABLE No. 15.

TmTs oF FULT.o-SIZE STEEL E-rE-BARS BY THE PmENIX BmDGm CoMPANY I•'O:R •ruE CrNOINNATI AND Covnm-roN ELEVATED RAILROAD, TaANSFEU AND BRIDGE- CoMPANY.

All pin-holes 6tij-" diameter.

PEII SQUAJIE l!n. edges. 27' \),6" :!8.900 62..270 2~ ft. 25.8 46.8 Silky eupped, 10 Y. flue 16.1 p. c. grau. edges. ===~==~~~cc==="=~o-:c'===~o··=~o~- 0 No:rE.-'! B" illdlCfl.tes BoSBQIDCl' steel; all others are Qpeu he~rth metal.

l

.~ =oe ""!;:

I :II f ~

·" b,, ·"""'..... l " "' ' ~-.Hz "

g·,uz " .,:!. ~ff j ..; ·"!' ~ ~

S'l:€'11~ :o.siiiY :.LS: r

~ "S NOt>tiHOr ~ nt•g• :o.s.;:.9 'i't"+~f '"' "[It"· - 111';:::::-" ··--JE·····.····.··· ... '· '. '.· '...... ]] ...... "~. :1.: . m::~~OJL.:.~~-~ _ ·~.,_- . . r ~ :,.. s : /") :' ·' 1 ENG'RS.

446

ON

BRIDGE.

XHI.

XXIII

BURR

PLATE

AM.SOC.CIV.

VOL

CINCINNATI

TRANS.

1

11

I

,

~

I

__

1

I

1

I

I

--\

I

I

I

-"""

I

----

I

...

----~------

I

Ckn>Oer.

e

I

&.

I

I

~I

!I

~~

I

-l~c'~

I

I

__

I

I

.

I

I

I

-~'-§ffi'_

I

Through

______

I

11

--

:!F1'---~-

.,.

~------

r··-

I

~---

I

ffJ]utl"ttt'<-~

I

I

11

?-

I

==~--

I

I

~

I

______

__

I

'.w.;:-_,;¥~:

'

~~

;,t~---

_,..5~Fr

r--

tl

,F-

..

_

_

~------==~

.;r,.,=..r

B::_s.:.

=

_

"'"~a-

_

Crib

.

l"

I

'

!!

~

of

~=~----=

----

,.

.,_

..

Tap

:~

~=~

\,.o"

t~,~.;!

---

-_-_

~~~~~~~~~.

----~-

~

-

--

_

~·~-

IIHIIIIIIIHIIIIIIIIIII

=

I

'

,,

:5'--

:~ l

:

.

~----

"

,,

~

~'

"

'

'

\.

'fltt:.-;i-_-::::.

I

I

t-.9_.::9.::

_

111111

1"--

------

r

~

11

fJ[l"'ffiU!,

.. --R=l-+

__

' '

' .;:tJnlt::Eil4-

~

~

-~

_,

'

"

~

'tf

JYgk

~

__

J.

I

Low

~

'

----

'

---+-

------

J5~.:~C~.

-.

'

I

__!_

~

"~..

29t

-.

s=

______

.

~.}{)1"V

-~--

~-

~~i,'JU\;n;rvati-

,.

~,"