<<

SWG Telecon August 7, 2020 Project Status Helene Winters Project Science Nour Raouafi Payload Status SB,JK,DM,RH Solar Orbiter H. Gilbert/T. Nieves SOC Activities Martha Kusterer Payload SE Telecon Sarah Hamilton Theory Group M. Velli/A. Higginson Upcoming Meetings Nour Raouafi Science Presentation: Bill Matthaeus: Shear-Driven Transition to Isotropically Turbulent Outside the Alfvén Critical Zone Parker Solar Probe Project Status SWG Telecon August 7, 2020 Project Manager: Helene Winters Deputy PM: Susan Ensor Project Scientist: Nour Raouafi Mission System Eng: Jim Kinnison System Assurance Manager: Linda Burke Parker Solar Probe Project Status Summary

May Jun Jul COMMENTS

All spacecraft subsystems performing nominally. The 3rd Venus gravity assist was conducted 11 July and TCM-15 was executed 19 July – both highly accurate. Orbit 5 concluded on 2 August. On 9 April, following a detection of stale telemetry from Electronics Control Unit A (ECU-A), the spacecraft’s fault protection autonomously Technical G G G transitioned to ECU-B and is functioning nominally. ECU-A appears be fully functional. The issue appears to be the same as seen during a pre-flight test, and was found to be a problem in the firmware. Put the vendor under contract to support the investigation. Collected data to compare operations of ECUs-A and –B. Low-rate data is indicative of a healthy ECU-A, but the team will analyze the high-rate data after downlink in the next Ka-band period (starting 14 August). Orbit 6: Spacecraft began orbit 6 on 2 August; will continue until 2 November The next Ka-band period will be 14-17 August Encounter 6 is 21 September-2 October, with closest perihelion to date, 20 RS, on 27 September Pre-encounter 6 Review: 18 August. Schedule G G G Orbit 7: TCM-16: 28 December 2020; TCM-17: 31 January 2021; TCM-18: 15 February 2021 Perihelion: 17 January 2021 Venus gravity assist 4: 20 February 2021 Next data release: 15 September Parker One Science Conference scheduled for March 23rd – 27th at APL: postponed in accordance with NASA recommendation based on the Coronavirus Disease (COVID-19) global outbreak; date TBD 2021. Awaiting results of PPBE. The project has resumed fee charging (had been held up during Phase C/D->E transition), but has not yet Resources G/Y G/Y G/Y charged for prior months in Phase E; still lagging – held up awaiting instrument confirmation of last Phase C/D invoice. The status will be changed from G/Y to G once we have also invoiced for the catch-up fee. Analyzing Phase E cost projections in light of instrument team funding requests. Beginning effort to expand instrument science reporting in monthly status reports to the program office. Programmatic G G G PSP Project below GSFC cost reserve guidelines and has limited funds available to deal with unexpected anomalies throughout Phase E. Continue to follow plans to avoid and mitigate the effects of the COVID-19 pandemic, and to monitor the situation. G Good Shape Y Minor Problem R Major Problem Spacecraft Status Solar Distance: Solar Distance: 0.810 to 0.817 AU↓

Spacecraft/ Status On-Going Issues Weekly Highlights Subsystem

All subsystems performing nominally at end of period; spacecraft at aphelion orientation, 45 Spacecraft degrees off +Z to , heading inbound in orbit 6

Fault Management & Autonomy

Avionics

Various issues w/ file handling, most notably playback of SSR files Flight Software at high rates via Ka-band (Monitoring SP-A-817 and SP-A-821) Star tracker 2 reset observed approximately 2 days prior to encounter 5 exit. Observables are similar to Guidance and Control SP-A-883 (closed) where a dust impact created false star tracks. No impact to pointing as star tracker 1 maintained lock. Confirmation analysis underway. PDU (Power Distribution Unit) Kick-off meeting held July 27th with vendor. On-orbit high-rate telemetry collection from ECU- Stale telemetry was detected from ECU-A (SP-A-889, 2020/100), EPS (Electrical Power A performed 2020-211 (July 29th). Initial analysis of coarsely sampled real-time telemetry resulting in an autonomous transition to ECU-B, with operations System) indicates a healthy ECU-A. High-rate data files to be downlinked during next Ka window in nominal. mid August Propulsion

SACS (Solar Array Cooling System)

Exterior component temperatures not matching thermal model Thermal predictions at aphelion variable orientations (SP-A-844) Radio A reset prior to REM side switch (SP-A-877, closed) Radio B Telecom (RF) Nominal performance during X-band tracks during this period. reset (SP-A-880, monitor) Science Instrument Status

Operational Commissioning Recorder Issues/ New Instrument Weekly Highlights Status Status Usage Constraints Anomalies Instrument is powered on and collecting data. SSR No Calibration of EPI-Lo None None Allocation reset for data collection period 5C on Heavy Ions 0% July 29th. Instrument is powered on and collecting data. SSR No Calibration of EPI-Hi None None Allocation reset for data collection period 5C on Heavy Ions 0% July 29th. Instrument is powered on and collecting data. SSR FIELDS 0.39% None None Allocation reset for data collection period 5C on July 29th.

Instrument is powered on and collecting data. SSR SWEAP 0.78% None None Allocation reset for data collection period 5C on July 29th.

Instrument is powered off. SSR Allocation reset for WISPR 0 % None None data collection period 5C on July 29th. Top 10 Risk Matrix Last Risk Board: 07/09/2020

Top Code Trend Title Ten

5- Very High 1 354 Unchanged Dust Penetration (Risk ID PSP-13)

4- High 2 352 Unchanged Phase E Project Reserve Levels

3 360 Unchanged Orbit 5 DSN Risk 3-Moderate Solar Array Degradation Prediction 4 345 Unchanged PSP-R-345 PSP-R-352 PSP-R-354 Uncertainty 2- Low PSP-R-349 PSP-R-360 PSP-R-350 5 349 Unchanged PSP Momentum Build Up PSP-R-353 PSP-R-351 G&C Model Functionality into PSP-R-357 1- Very Low 6 350 Unchanged Command Load Constraint Checker = PSP-R-361 (CLCC)

1 - Very 3 - 5 - Very 2 - Low 4 - High 7 353 Unchanged File System Corruption Low Moderate High

Spacecraft / Instrument Thermal 8 351 Unchanged Exceedances

9 357 Unchanged SV Access via CRC Memory Dump

10 361 Unchanged ECU Risk for Orbit 5 Update to Instruments’ Monthly Status § Program office has asked for more insight into science progress. § Need simple status of science tasks to be included in monthly report. § Special focus on efforts not a part of the original Extended Phase D / Phase E contract, e.g., augmentation, any requests made during PPBE (annual budget review, last held April 2020) § We’ll provide a basic list of science tasks, § e.g., from original SOW § Trace the flow of energy that heats and accelerates the solar corona and solar wind. § Determine the structure and dynamics of the plasma and magnetic at the sources of the solar wind. § Explore mechanisms that accelerate and transport energetic particles. § e.g., from (ISOIS) augmentation § routinely analyze (using sw) & calibrate the EPI-Hi response to neutral-particle data and produce data products § do calibration & modeling needed to take advantage of x-ray signals § develop analysis tools for anti-coincidence measurements in EPI-Lo § analysis of anti-coincidence measurements in EPI-Lo § Additional in-flight cal & cros-cal with other instruments on PSP, as well as other space-based and ground-based observatories § in-flight analysis and validation of EPI-Lo extended energy measurement via deeloped sw/tools § quick-look each orbit for prioritizing downlink § Feel free to iterate on list, and to supplement

§ We also plan to pass on the data archive table, as already8/7/20 provided. 7 COVID-19 Pandemic Mitigations Steps Remain in place

§ All staff are working from home unless there is a specific need to be physically present in a facility § Contingency planning information has been provided to the program office § Emergency personnel who may need to come on site were identified § APL is at stage 3 (and NASA centers have returned to stage 4), allowing APL staff to come to the campus, if needed § All non-essential travel is presently on hold § APL has an enhanced disinfecting process § APL has added significantly to the number of simultaneous WebEx users allowed, telephone bandwidth, and internet bandwidth, and has procured a government version of Zoom which is now in use § APL does have a few cases of COVID-19; contract tracing process executed rigorously § MOPS is extending the command-loss timer and the period covered by spacecraft command loads as proactive measures in case of any unexpected DSN outages during the pandemic § MOPS is leveraging automated and remote support for DSN contacts as appropriate; when in-MOC support is needed, precautions are being taken to enhance the safety of team members § Masks are mandatory in any common areas 8/7/20 8 Parker Solar Probe Project Science SWG Telecon August 7, 2020 Orbit 5

• Ready for Venus Gravity Assist #3, July 11, 2020: big success for science o Now working with Engineering, MOPs, DSN on VGA-4 • DCP 5c: data transfer & new data gathering ongoing • New priority table – will uploaded on August 14 • Working with A&A on the PSP Special Issue – Submission deadline August 30, 2020 • Working with the science teams on publications for the first two Venus flybys • Working on coordination with SolO and DKIST • Orbit 4 Data Release: September 15, 2020

8/6/20 10 A&A Special Issue Submission deadline: August 30, 2020 8/7/20 12 8/7/20 13 8/7/20 14 8/7/20 15 8/7/20 16 Project Science (1/2) June 29 – July 5, 2020

Weekly Status: June 29th – July 5th § Working with Science Operations Center (SOC) team on planning orbits 6-10 § Working on coordination with the Solar Orbiter mission and Daniel K. Inouye Solar Telescope (DKIST): PS had a telecon with the Solar Orbiter Project Scientist on June 10th to start discussion on close coordination, collaboration, data sharing, etc. several actions items resulted from this meeting; the PSs will meet again in a month to continue these discussions § Working with Astronomy & Astrophysics to negotiate Parker Special Issue on science discoveries, primarily from orbits 4 & 5 § Supporting COVID-19 risk assessment and contingency planning for PSP § Worked with the instrument Principal Investigators (PIs) to make sure that all critical personnel for the instrument suite operations are identified and that they have all the resources they need to work remotely § Worked on the Project DSN risk § Working with the science teams to assess risks for science § Working with the science teams on publications for the first two Venus flybys § Science Highlight #2 “Long Memory in Switchbacks” from Thierry Dudok de Wit (University of Orléans) will be posted on PSP Gateway July 6th § Updates to PSP Encounter 5 Predictions at link: https://sppgway.jhuapl.edu/encounters

PSP Weekly Status Update 06/29/2020-07/05/2020 Project Science (2/2) June 29 – July 5, 2020

Meetings & Telecons Supported: June 29th – July 5th § FIELDS Team Meeting, June 29th § PSP Loss of DSS-55 Impacts, June 29th § PS Tag-up with Program (HQ), June 29th § PSP Project Weekly Status Meeting, June 30th § WISPR SOC Telecon, June 30th § PSP Mission Operations Orbit Planning, July 1st § Telecon with Sofiane Bourouaine (new PSP/PS staff member), July 2nd § SWEAP Data Exploration Meeting, July 2nd § Weekly Tag up with the Program (HQ) and Mission (GSFC) Scientists, July 2nd § Weekly Project Science PS/DPS Tag-up, July 2nd Planned Activities: § PSP SWG Telecon, Science Speaker and Topic TBD, 1:00-2:30 PM, July 10th § Parker Solar Probe Theory Group Telecon: Speaker, Anna Tenerani (UT Austin); Topic, TBD; 12:00 PM-1:30 PM EST, July 23rd § Postponed PSP Science Conference #1 (Parker One: parkersolarprobe.jhuapl.edu/News-Center/Events/Parker-Series/) due to the pandemic ; will be rescheduled – considering timeframe, also in light of the pandemic § Due to Parker One being postponed to 2021, a virtual SWG meeting is being planned for this coming fall; the dates of October 14-15 are being retained for this SWG meeting § Orbit 4 data release: August 4th (90 days from May 6th)

PSP Weekly Status Update 06/29/2020-07/05/2020 Project Science (1/3) July 6-12, 2020

Weekly Status: July 6th – July 12th § Working with Science Operations Center (SOC) team on planning orbits 6-10 § Working on coordination with the Solar Orbiter mission and Daniel K. Inouye Solar Telescope (DKIST): PS had a telecon with the Solar Orbiter Project Scientist on June 10th to start discussion on close coordination, collaboration, data sharing, etc. several action items resulted from this meeting; the PSs will meet again in a month to continue these discussions § Working with Astronomy & Astrophysics to negotiate Parker Special Issue on science discoveries, primarily from orbits 4 & 5 § Supporting COVID-19 risk assessment and contingency planning for PSP § Worked with the instrument Principal Investigators (PIs) to make sure that all critical personnel for the instrument suite operations are identified and that they have all the resources they need to work remotely § Worked on the Project DSN risk § Working with the science teams to assess risks for science § Worked with the science teams on publications for the first two Venus flybys § Science Highlight #2 “Long Memory in Switchbacks” from Thierry Dudok de Wit (University of Orléans) posted on PSP Gateway website [ https://sppgway.jhuapl.edu/psp_sciencehighlights ] July 2nd ; Hightlight #3 “Observations of the 4 April 2019 SEP Event at PSP” from Rick Leske (Caltech) posted July 10th ; Highlight #4 “Why was the solar wind measured during PSP’s second perihelion suddenly tenuous and less variable?” from Alexis Rouillard (IRAP) posted July 11th § Updates to PSP encounter 5 predictions at link: https://sppgway.jhuapl.edu/encounters

PSP Weekly Status Update 07/06/2020-07/12/2020 Project Science (2/3) July 6-12, 2020

Meetings & Telecons Supported: July 6th – July 12th § PSP Project Leadership Team Tag-Up, July 6th § SWEAP Science Team Telecon, July 6th § FIELDS Team Meeting, July 6th § Discussion with Dr. R. Ghosh Regarding PSP PS Team, July 6th § Tag-up with SWEAP SOC Leads, July 6th § PSP FIELDS/SWEAP Working Group Telecon: Turbulence, July 7th § PSP FIELDS/SWEAP Working Group Telecon: Spacecraft Charging, July 7th § PSP Project Weekly Status Meeting, July 7th § WISPR SOC Telecon, July 7th § Switchbacks vs Instabilities Telecon, July 8th § PSP Dust Team Telecon, July 8th § PSP APFR Meeting, July 8th § WISPR Enc 5 Missing Images and SSR Allocation AR, July 8th § PSP Mission Operations Orbit Planning, July 8th § Multi-spacecraft Turbulence Analysis Discussion with Dr. S. Bourouaine, July 8th § PSP CCB/Risk Board Meeting, July 9th PSP Weekly Status Update 07/06/2020-07/12/2020 Project Science (3/3) July 6-12, 2020

§ Parker Solar Probe Science Working Group Telecon, 1:00-3:00 PM, July 10th § Presentations of data from PSP Orbit 5: FIELDS (Stuart Bale, UCB); SWEAP (Michael Stevens, SAO); ISϴIS (Christina Cohen, Caltech); WISPR (Russ Howard, NRL); § Presentations of recent Solar Orbiter data: MAG (Tim Horbury); Radio and Plasma Waves (M. Maksimovic); SoloHI (R. Howard) § Weekly Tag up with the Program (HQ) and Mission (GSFC) Scientists, July 10th § Weekly PSP/DPS tag-up, July 10th Planned Activities: § PSP SWG Telecon, Science Speaker and Topic TBD, 1:00-2:30 PM, August 7th § Parker Solar Probe Theory Group Telecon: Presentation “Magnetic Kinks” to be given by Anna Tenerani (UT rd Austin) [ website of presentations: https://sppgway.jhuapl.edu/theorygroup ], 12:00 PM-1:30 PM EST, July 23 § Postponed PSP Science Conference #1 (Parker One: parkersolarprobe.jhuapl.edu/News- Center/Events/Parker-Series/) due to the pandemic; will be rescheduled – considering timeframe, also in light of the pandemic § Due to Parker One being postponed to 2021, a virtual SWG meeting is being planned for this coming fall; the dates of October 14-15 are being held for this SWG meeting § Orbit 4 data release: August 4th – rescheduling to mid-September, consistent with data availability on the

ground PSP Weekly Status Update 07/06/2020-07/12/2020 Project Science (1/3) July 13-19, 2020

Weekly Status: July 13th – July 19th § Working with Science Operations Center (SOC) team on planning orbits 6-10 § Working on coordination with the Solar Orbiter mission and Daniel K. Inouye Solar Telescope (DKIST): PS had a telecon with the Solar Orbiter Project Scientist on June 10th to start discussion on close coordination, collaboration, data sharing, etc. several action items resulted from this meeting; the PSs will meet again in a month to continue these discussions § Working with Astronomy & Astrophysics to negotiate Parker Special Issue on science discoveries, primarily from orbits 4 & 5 § Supporting COVID-19 risk assessment and contingency planning for PSP § Worked with the instrument Principal Investigators (PIs) to make sure that all critical personnel for the instrument suite operations are identified and that they have all the resources they need to work remotely § Worked on the Project DSN risk § Working with the science teams to assess risks for science § Worked with the science teams on publications for the first two Venus flybys § Two authors of separate ApJS papers published in early 2020 were contacted, and agreed to deliver PSP Science Highlight slides and ancillary material (videos) by July 31st July and August 14th

PSP Weekly Status Update 07/13/2020-07/19/2020 Project Science (2/3) July 13-19, 2020

Meetings & Telecons Supported: July 13th – July 19th § SWEAP Science Team Telecon, July 13th § FIELDS Team Meeting, July 13th § PSP FIELDS/SWEAP Working Group Telecon: Solar Wind Sources, July 14th § PSP FIELDS/SWEAP Working Group Telecon: Switchbacks, July 14th § PSP Project Weekly Status Meeting, July 14th § WISPR List of Software Tasks Telecon, July 14th § WISPR SOC Telecon, July 14th § PSP Mission Operations Orbit Planning Meeting, July 15th § PSP Off-cycle AR Meeting - SP-A-880 (Redundant Radio Reset Detected on 2020-002), July 15th § SWEAP Transfer Issue, July 16th § PSP Project Science Bi-weekly Tag-up Meeting, July 17th § PSP PIs Telecon with PS, July 17th § Weekly Tag-up with the Program (HQ) and Mission (GSFC) Scientists, July 17th § PSP PS/DPS Weekly Tag-up, July 17th PSP Weekly Status Update 07/13/2020-07/19/2020 Project Science (3/3) July 13-19, 2020 Planned Activities: § PSP SWG Telecon, Science Speakers and Topics TBD, 1:00-3:00 PM, August 7th § Parker Solar Probe Theory Group Telecon: Presentation “Magnetic Kinks” to be given by Anna Tenerani (UT Austin) [ website of presentations: rd https://sppgway.jhuapl.edu/theorygroup ], 12:00 PM-1:30 PM EST, July 23 § Postponed PSP Science Conference #1 (Parker One: parkersolarprobe.jhuapl.edu/News-Center/Events/Parker-Series/) due to the pandemic; will be rescheduled – considering timeframe, also in light of the pandemic § Due to Parker One being postponed to 2021, a virtual SWG meeting is being planned for this coming fall; the dates of October 14-15 are being held for this SWG meeting § Orbit 4 data release: September 15th

PSP Weekly Status Update 07/13/2020-07/19/2020 Project Science (1/3) July 20-26, 2020

PSP Weekly Status Update 07/13/2020-07/19/2020 Project Science (2/3) July 20-26, 2020

PSP Weekly Status Update 07/13/2020-07/19/2020 Project Science (3/3) July 20-26, 2020

PSP Weekly Status Update 07/13/2020-07/19/2020 Project Science: Overview July 27 – August 2, 2020 Weekly Status: July 27th – August 2nd § Working with Science Operations Center (SOC) team on planning orbits 6-10 § Working on coordination with the Solar Orbiter mission and Daniel K. Inouye Solar Telescope (DKIST): PS had a telecon with the Solar Orbiter Project Scientist on June 10th to start discussion on close coordination, collaboration, data sharing, etc.; several action items resulted from this meeting; the PSs will meet again in a month to continue these discussions § Working with Astronomy & Astrophysics to negotiate Parker Special Issue on science discoveries, primarily from orbits 4 & 5. Currently, list from science team includes 25 papers in preparation [ https://sppgway.jhuapl.edu/special_issue_list ] § Supporting COVID-19 risk assessment and contingency planning for PSP § Worked with the instrument Principal Investigators (PIs) to make sure that all critical personnel for the instrument suite operations are identified and that they have all the resources they need to work remotely § Worked on the Project DSN risk § Working with the science teams to assess risks for science § Working with the science teams on publications for the first two Venus flybys § Two authors of separate ApJS papers published in early 2020 were contacted, and agreed to deliver PSP Science Highlight slides and ancillary material (videos) by August 7th and August 21st PSP Weekly Status Update 07/27/2020-08/02/2020 Project Science: Upcoming (1 of 2) July 27 – August 2, 2020

Meetings & Telecons Supported: July 27th – August 2nd § PSP Public Affairs Tag-up, July 27th § SWEAP Science Team Telecon, July 27th § PSP Science Data Animation: Discussion with the Program Scientist (HQ), July 27th § PSP FIELDS/SWEAP Working Group Telecon: Quasi-thermal Noise & Electrons, July 28th § PSP FIELDS/SWEAP Working Group Telecon: Large-scale Structures & Ions, July 28th § PSP Project Weekly Status Meeting, July 28th § WISPR SOC Telecon, July 28th § PSP Mission Operations Orbit Planning Meeting, July 29th § PSP Contract Discussion, July 30th § Solar Orbiter ISWG Telecon, July 30th § PSP PS-PM Tag-up, July 30th § Special PSP Theory Telecon: Presentation “Effect of Minimum Variance Criteria on Foreshock Wave Properties for 150,000+ Venus Express Intervals,” Alexandra Brosius (Penn State University), 12:00 -1:30 PM EST, July 30th § PSP Project Science Tag-up, July 30th § Weekly Tag-up with the Program (HQ) and Mission (GSFC) Scientists, July 30th

PSP Weekly Status Update 07/27/2020-08/02/2020 Project Science: Upcoming (2 of 2) July 27 – August 2, 2020

Planned Activities: § PSP SWG Telecon, Science Speakers and Topics TBD, 1:00-3:00 PM, August 7th § Parker Solar Probe Theory Group Telecon: Presentation and Speaker TBD [ website of past th presentations: https://sppgway.jhuapl.edu/theorygroup ], 12:00 PM-1:30 PM EST, August 27 § Postponed PSP Science Conference #1 (Parker One: parkersolarprobe.jhuapl.edu/News- Center/Events/Parker-Series/ ) due to the pandemic; will be rescheduled – considering timeframe, also in light of the pandemic § Due to Parker One being postponed to 2021, a virtual SWG meeting is being planned for this coming fall; the dates of October 14th -15th are being held for this SWG meeting § Orbit 4 data release: September 15th § AGU Fall Meeting, 7-11 Dec. 2020: Special Sessions Pertinent to Measurements from Parker Solar Probe • SH006 - Fundamental Physics of the Solar Corona and Inner Heliosphere • SH007 - Fundamental Plasma Physics in the Modern Space Physics Era: MMS, PSP and Beyond • SH015 - Parker Solar Probe: One Step Closer to the Sun • SH028 - Turbulence and magnetic reconnection: What new science do we learn from Parker Solar Probe? PSP Weekly Status Update 07/27/2020-08/02/2020 Science Operations Center Status

• Supported Meetings • Science Planning Tools § Missions Operations, Operations Planning, Payload System Engineering, § Delivered builds 2020.07.21.001 for SPADER and ActivityCalendar CCB/Risk, APFR and MOPs/GS § Delivered build 2020.7.29.001 for SPADER to correct an issue th th • SOC Telecons on July 24 and upcoming August 14 § Science Planning Analysis and Data Estimation Resource (SPADER) New Features • Data Releases § September 1st 2020: Details on new or changed instrument data products § Updated RF & DSN products due to SPDF & SDAC § Added PSP multi-mission radial alignment, Parker alignment, and th quadrature calculations to Orbit Plot. They ignore the Heliographic § September 15 2020: Orbit 4 data (for data not released earlier) (HG) latitude when calculating the angular differences; that is, only the • GSEOS HG longitude is used; this is used by default now § GSE Software worked with the EPI-Hi team to track down an anomaly with § Added Parker Spirals and variable solar wind to Orbit Plot the spacecraft emulator. It was due to a very large log file which caused the § PASF Merger New Features communication between the emulator and GSEOS to be interrupted. § Fixed activity duplication bug in staggering algorithm when illegal • Science Gateway activity durations are used § Managing routine gateway operations § ActivityCalendar New Features § The automated PSP telemetry reports are being sent to identified team § Automated download of input products members, please inform us if you want to be on the list. § Coming Features • Frame Kernels § SPADER: Automated download of input products; this feature will § EPI-Lo, EPI-Hi, WISPR, SWEAP kernels complete eliminate the need to issue new builds just to include updated input files § FIELDS frames near completion, next, FIELDS evaluation § Enhancements to reflect the multiple data collection periods per orbit • Science Operations and the extended campaigns § 7/21/20 – 7/31/20: Delivered merged Orbit 6 Segment 2 Payload Activity § Stagger of instrument time tag activities with spacecraft time tag Sequence File (PASF) activities in time § 8/3/20: Start of orbit 6 • Science Downlink Planning § 8/14/20 & 8/17/20 – Prime SSR Directory Listings § Supported Project Science for Venus 3 Flyby, Encounter 5 Reviews and post- § 8/11/20 – 8/21/20: Upcoming merge of Orbit 6 Segment 3 PASF Encounter 5 and data collection periods 6A and 6B. § 8/23/20: Start of Data Collection Period 6A § Supported Project Science and Mission Ops for Orbit 7 and Orbit 8 planning PSP Payload Systems Engineering

o Purpose : To Provide Instrument Insight to Spacecraft Systems and Operations o Bi-Weekly Meetings o Last meeting held 5/28 o SSR Q & A with FSW and MOPs o Next Scheduled Meeting 7/23 o TBD o Will schedule off-cycle meeting if needed

o Ad-Hoc Meetings to Address Specific Concerns, as necessary

o Venus 3 Flyby Closest Approach July 11th

o Encounter 6 Review to be scheduled Mid-August

PSP Science Working Group 7/10/20 PSP Payload Systems Engineering o Purpose : To Provide Instrument Insight to Spacecraft Systems and Operations o Bi-Weekly Meetings o Last meeting held 8/6 o Venus 4 Flyby Planning o Next Scheduled Meeting 820 o TBD o Will schedule off-cycle meeting if needed o Informal Science Operations Lessons Learned Review o Tentative Date September 17th during PSE Meeting o Instrument teams to present lessons learned o Useful to all teams as lessons can be applicable to all teams o Prepare for Upcoming Orbit 8 Special Requests o Encounter 6 Review August 18th Zoom o Slides due to Sarah August 14th o Please include SSR percentage usage predictions for the Encounter 6 Data collection periods PSP Science Working Group 7/10/20 PSP Theory Group

Hosts: Aleida Higginson & Marco Velli Cadence: monthly – every 4th Thursday, 12:00 − 13:30 (EST) Webpage: http://sppgway.jhuapl.edu/TG_Telecons (Presentation + Zoom recording)

Last Telecons: July 23, 2020 Speaker: Anna Tenerani (UT Austin) Topic: On the stability of Alfvénic fluctuations and switchbacks in the solar wind

July 30, 2020 Speaker: Alexandra Brosius (Penn State) Topic: Effect of Minimum Variance Criteria on Foreshock Wave Properties for 150,000+ Venus Express Intervals

Next Telecons: August 27, 2020 Speaker: Olga Panasenco

September 24, 2020 Speaker: Bhinsen Shivamoggi (UT Austin)

8/7/20 34 H. Gilbert, T. Nieves-Chinchilla NASA SOC Project Scientists [email protected]

- First light press conference on July 16.

- MAGDAWG (07/22) held the first post-launch meeting. Alexis Rouillard chaired the working group meeting.

- 1st Science In-Situ working group kick-off meeting (07/30) with ~150 participants on the zoom call. Daniel Verscharen is the chair of the WG and coordinator of the different sub-WGs with more specific topics. The kick-off meetings for the sub-wgs are scheduled in September.

- Solar Orbiter Venus first gravity assistance maneuver on December 27th.

- Nominal Phase, with Remote Sensing instruments, starts Nov 2021.

Upcoming Activities: EUI observation on May 30, 2020 @0.51 AU SWT#28 online meeting is scheduled for September 9-10, 2020. These images reveal a multitude of small flaring MAGDAWG meeting TBD, October 2020. loops, erupting bright spots and dark, moving fibrils AGU Fall (hybrid) meeting, December 1-17, 2020. that have been called ‘campfires’. First In-situ data release to the public in September. Credit: Solar Orbiter/EUI Team (ESA & NASA); CSL, IAS, MPS, PMOD/WRC, ROB, UCL/MSSL Payload Status & Science Data Overviews

VGA-3 data • FIELDS Stuart Bale • SWEAP Justin Kasper • IS�IS Dave McComas • WISPR Russ Howard SWG Telecon August 7, 2020 Science Highlights

Bill Matthaeus Univ. Delaware ([email protected]) Shear-Driven Transition to Isotropically Turbulent Solar Wind Outside the Alfvén Critical Zone (submitted to ApJ)