MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (3.50 Mty)

1.0 INTRODUCTION

1.1 BACKGROUND OF PROJECT REPORT

The Amalgamated Gondegaon-Ghatrohan OC project had been envisaged in Gondegaon-Ghatrohan block in Kamptee Coalfield. The project consists of two sub quarries i.e. Gondegaon sub quarry & Ghatrohan sub quarry. Presently, both the sub-quarries are in operation by departmental HEMM (in Gondegaon sub-quarry) as well as Out-sourced HEMM (in Ghatrohan sub- quarry).

PR for Gondegaon OC was prepared in November, 1989 for a capital investment of Rs.6796.25 lakhs and target production of 0.75 Mty and was approved in the year 1992 in Departmental Option.

Excavation work of Gondegaon OC was started in 1994-95 and coal extraction commenced in 1995-96. Due to increase in the expenses by 40.67%, a Revised Cost Estimate was prepared for 0.75 Mty in June, 1998 for a total capital investment of Rs.9560.24 lakhs (existing capital of Rs.6151.95 lakhs + balance expenditure of Rs.3408.29 lakhs). The RCE was approved by CIL Board on 25.8.1998 for a capital investment of Rs.9560.24 lakhs.

A Completion Report for Gondegaon OC mine was prepared by WCL in 1999 for a total capital expenditure of Rs.9535.31 lakhs.

Subsequently, PR for Gondegaon Extension OC including Ghatrohan OC was prepared in June, 2004 for a capital investment of Rs.12415.67 lakhs (Gross Block) for a capacity of 1.50 Mty. However, it was sanctioned for incremental capacity of 0.75 Mty with an incremental capital of Rs.2753.71 lakhs.

Thereafter RPR for Amalgamated Gondegaon-Ghatrohan OC (December- 2010) was prepared to enhance the production capacity from 1.50 Mty to 2.00 Page - 1 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019) Mty. The balance coal reserves and volume of OB calculated as on 01.4.2010 were 29.07 Mt and 153.91 Mm3 respectively at a stripping ratio of 5.29 m3/t. This RPR was accorded 2nd Stage approval by WCL Board on 07/01/2011 with an additional capital investment of Rs 73.8846 crores in Partial Hiring option.

As desired by WCL, updation of the approved RPR (Dec. 2010) was done at August 2015 prices and discussed in the TSC meeting at WCL HQ on 11/09/2015 wherein it was directed to review report for a higher capacity on the basis of joint technical meeting between CMPDI, WCL HQ, WCL Area & mine officials. Subsequently, a meeting was held on 12/9/2015 at CMPDI, Nagpur and it was decided to prepare Revised Project Report of Amalgamated Gondegaon - Ghatrohan OC for a target capacity of 2.50 Mty.

Based on the decisions taken in various meetings with WCL (HQ), Nagpur Area and mine officials, Revised Project Report of Amalgamated Gondegaon Ghatrohan OC for 2.50 Mty capacity was prepared in November, 2015 considering the latest scenario of land acquisition and further project requirements communicated by Mine/Area.

The Revised Project Report of Amalgamated Gondegaon Ghatrohan OC (2.50 Mty) was approved by WCL Board in its 273rd meeting held on 3rd February, 2016.

GM (P&P), WCL vide his letter no. WCL/GM (P&P) / MR / 18/484 dated 09.02.2018 requested CMPDI, RI-IV, Nagpur to update the RPR of Amalgamated Gondegaon Ghatrohan OC for 3.50 Mty capacity.

Based on the decisions taken in various meetings with WCL (HQ), Nagpur Area and mine officials, following changes were incorporated in the RPR of Amalgamated Gondegaon Ghatrohan OC updated in the month of February- 2018 :

a) Target capacity of the mine was increased from 2.50 Mty to 3.50 Mty and accordingly life of mine reduced to 7 years as on 01.04.2018.

Page - 2 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

b) Additional Provision was made for 1 no. of Mobile Crusher on hiring and Electronic Weighbridge to cater the increased capacity of the mine.

c) Provision of Manpower was increased to 921 considering an increase of 201 manpower over & above the present day manpower of 720 .

d) Provisions for P&M revised considering correspondence with WCL.

e) Provisions for HEMM was revised considering existing HEMM at Gondegaon Ghatrohan OC.

After incorporating the above, the RPR of Gondegaon Ghatrohan OC mine was updated for the month of February-2018. The above RPR was discussed in the meeting of Technical Sub-Committee of WCL Board held on 07.03.2018 at WCL (HQ), Nagpur. In the meeting, it was discussed that there is wide difference in the quality of upper set of coal seams (Seam-V and IV) and lower set of coal seams (Seam-III & II) in Amalgamated Gondegaon Ghatrohan OC mine. Finally, it was decided that separate coal stocks and dispatch arrangement for inferior quality coal of upper seams (V and IV) and better quality coal of lower seams (Seam-III & II) will be maintained in the mine and accordingly, sale price of both type of coal will be considered separately as per their corresponding year-wise quantity in economic evaluation.

Based on the above decision, RPR of Amalgamated Gondegaon Ghatrohan OC mine was prepared in the month of March, 2018.

Chronology of the previous approved reports are as follows:-

Production Approved Sl. Year of Technology Year of Preparation Capacity Capital No. Approval Adopted (Mty) (Rs. Lakh)

PR for Gondegaon Shovel-dumper 1 1992 0.75 6796.25 Opencast mine Departmental Option

RCE for Gondegaon Shovel-dumper 2 1998 0.75 9560.24 Opencast mine Departmental Option

Page - 3 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

Production Approved Sl. Year of Technology Year of Preparation Capacity Capital No. Approval Adopted (Mty) (Rs. Lakh) 3 Completion Report 1999 0.75 9535.31

PR for Gondegaon Shovel-dumper 0.75 2753.71

4 Extension Opencast 2004 Partial Hiring (incre- (incre-

mine Option mental) mental) RPR Amalgamated Shovel-dumper 5 Gondegaon- 7.1.2011 Partial Hiring 2.00 7388.46 Ghatrohan OC Option RPR Amalgamated Shovel-dumper 6 Gondegaon- 3.2.2016 Partial Hiring 2.50 23848.18 Ghatrohan OC Option RPR Amalgamated Shovel-dumper T 7 Gondegaon- 10.4.2018 Partial Hiring 3.50 32518.02 h Ghatrohan OC Option

The Ministry of Environment, Forest and Climate Change vide letter dated 14th March, 2018 granted Environmental Clearance to the expansion of Gondegaon Extension Opencast Mining Project from 2.50 MTPA to 3.50 MTPA in area of 917 ha (mine leasehold area 845.74 ha) for a period of one year subject to compliance of certain terms & conditions and environmental safeguards. Lateron, the Ministry of Environment, Forest and Climate Change vide letter no. J-11015/106/2009-IA.II(M) dated 28.03.2019 accorded approval for continuance of Gondegaon Extension Opencast Mining Project from 2.50 MTPA to 3.50 MTPA in area of 917 ha (mine leasehold area 845.74 ha) for a further period of one year.

The RPR for Amalgamated Inder-Kamptee Deep OC was approved by WCL Board in September,2018 in which 54.34 ha land was proposed to be transferred from neighbouring Gondegaon-Ghatrohan OC. Accordingly, EC application for amendment in EC of Expansion of Kamptee Deep OC ‘for a capacity of 3.20 MTPA within a mine lease area of 857.60 ha was discussed in EAC in its 46th meeting held on 25.06.2019. The EAC, after deliberation observed that the proposed amalgamation involves carving out some area of

Page - 4 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019) adjoining Gondegaon Opencast coal mining project and thus requiring amendment in its environmental clearance also. There being no proposal in this regard, the committee was not inclined to take the proposal forward.

Hence, for applying for amendment in the existing EC of Expansion of Gondegaon Extension OC, a Mining Plan with mine lease area of 791.40 ha (845.74-54.34) for a capacity of 3.50 MTPA has been prepared.

1.2 EXISTING STATUS

Five coal seams which are characteristic of Kamptee Coalfield, are present in the Gondegaon-Ghatrohan block also. All these seams occur in the Middle Barakar horizon of about 100 m thickness. The seams in Kamptee Coalfield are numbered from bottom to top, the bottom-most Seam-I is the oldest, while the top most Seam-V is the youngest. The oldest Seam-I is found to be deposited around 100 m above the Talchir-Barakar contact. Of the five seams, Seams-II, III & IV occur in 2 to 3 split sections, while Seam-V is present as a single horizon. Seam-I is impersistent and also thin, mostly below 0.90 m thickness, hence not considered in this report.

Due to the steep gradient & multi-seam characteristics, shovel-dumper system of mining is in vogue.

Seam - II to V occur in Gondegaon-Ghatrohan Block in nine sections, viz. Seam-I (Bottom), I (Top), II (Bottom), II (Top), III (Bottom), III (Top), IV (Bottom) {Seam-IV Bottom and IV Middle may be considered as Seam-IV Bottom due to very thin parting between them}, IV (Top) & V.

The various performance parameters of the mine from 2012-13 to 2016-17 as per cost sheet are as follows:-

Sl. Description 2014-15 2015-16 2016-17 2017-18 2018-19 No. 1 Manpower (nos) 655 643 720 750 782 2 Coal Prodtn (Mt) 1.86 2.13 2.15 3.16 3.50 3 Deptt OBR (Mm3) 3.23 3.84 4.35 4.06 4.43 4 HOE OB (Mm3) 2.65 0.42 0.76 7.61 7.79

Page - 5 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

Sl. Description 2014-15 2015-16 2016-17 2017-18 2018-19 No. 5 Overall Profit 46.9430 (-)2.5042 (-)24.00 113.13 190.36 (Rs crores) 6 Overall Profit (Rs per t) 252.50 (-)11.76 (-)111.45 357.57 543.91

The coal and OB removal from Gondegaon/Gondegaon Ghatrohan OC mine since inception is as follows :

ACTUAL COAL EXTRACTION AND OB REMOVAL SINCE INCEPTION

Overburden (Mm3) Stripping Year Coal (Mt) By Deptt Ratio By HOE Total HEMM (m3 /t ) 1994-95 - 0.007 - 0.007 - 1995-96 0.002 0.842 - 0.842 - 1996-97 0.175 1.190 0.887 2.077 11.87 1997-98 0.378 2.149 0.515 2.664 7.05 1998-99 0.619 2.598 0.946 3.544 5.73 1999-00 0.701 2.729 0.845 3.574 5.10 2000-01 0.801 2.667 0.258 2.925 3.65 2001-02 0.985 2.953 0.465 3.418 3.47 2002-03 1.148 3.059 0.536 3.595 3.13 2003-04 1.175 3.159 0.980 4.139 3.52 2004-05 1.100 2.821 1.389 4.210 3.83 2005-06 1.196 2.854 0.720 3.574 2.99 2006-07 1.230 3.177 - 3.177 2.58 2007-08 1.399 3.091 - 3.091 2.21 2008-09 1.500 3.439 - 3.439 2.29 2009-10 1.418 3.846 1.380 5.226 3.69 2010-11 1.404 3.460 1.558 5.018 3.57 2011-12 1.521 3.356 0.153 3.509 2.31 2012-13 1.708 3.480 1.022 4.502 2.64 2013-14 1.820 3.200 2.211 5.411 2.97 2014-15 1.860 3.230 2.650 5.880 3.16 2015-16 2.129 3.837 0.417 4.254 2.00 2016-17 2.153 4.346 0.760 5.106 2.37 2017-18 3.164 4.057 7.615 11.672 3.69 2018-19 3.500 4.426 7.792 12.218 3.49 Total 33.086 73.973 33.099 107.072

Page - 6 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

1.3 JUSTIFICATION OF PREPARATION OF MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE

The RPR for Amalgamated Inder-Kamptee Deep OC which was approved by WCL Board in September,2018 in which 54.34 ha land was proposed to be transferred from neighbouring Gondegaon-Ghatrohan OC. Accordingly, EC application for amendment in EC of Expansion of Kamptee Deep OC for a capacity of 3.20 MTPA within a mine lease area of 857.60 ha was discussed in EAC in its 46th meeting held on 25.06.2019. The EAC, after deliberation observed that the proposed amalgamation involves carving out some area of adjoining Gondegaon Opencast coal mining project and thus requiring amendment in its environmental clearance also. There being no proposal in this regard, the committee was not inclined to take the proposal forward.

Hence, for applying for amendment in the existing EC of Expansion of Gondegaon Extension OC, proposed mining plan with mine lease area of 791.40 (845.74-54.34) ha for a capacity of 3.50 MTPA has been prepared.

1.4 SALIENT FEATURES OF LAST APPROVED RPR AND EARLIER APPROVED RPR

The Salient Feature of Updated RPR (March-2018) and earlier approved RPR, November, 2015 (approved on 03.02.2016) are summarized below:

Updated RPR Updated RPR of Amalgamated of Amalgamated Sl. Gondegaon- Gondegaon- Particulars No. Ghatrohan OC Ghatrohan OC (Nov., 2015) (March-2018) (Partial Hiring) (Partial Hiring) A General Parameters 01 Balance Mineable Reserves (Mt) 29.23 22.19 (as on 1.4.2015) (as on 1.4.2018) GCV of coal (0.10m dilution at Gr-G-9 G-10 (Seam-V&IV) 02 each contact point) (4828 kCal/kg) G-8 (Seam-III & II)

Page - 7 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

Updated RPR Updated RPR of Amalgamated of Amalgamated Sl. Gondegaon- Gondegaon- Particulars No. Ghatrohan OC Ghatrohan OC (Nov., 2015) (March-2018) (Partial Hiring) (Partial Hiring) 03 Target Production (Mty) 2.50 3.50 04 Volume of Overburden 121.31 98.20 05 Average S/R (m3/t) 4.15 4.43 06 Manpower requirement (nos.) 450 921 07 Overall OMS (t) 21.044 14.395 B Financial parameters Power Sector Power Sector 08 Capital Requirement (Rs. In crores) Additional Capital 198.6824 191.7835 WDV of Existing Assets 39.7994 133.3967 Total 238.4818 325.1802 09 Cost of Production (Rs/t) a) At 100% of target capacity 959.36 1196.00 b) At 85% of target capacity 1062.90 1322.46 10 Average Notified Selling Price 1190.50 1537.67 (Rs/t) 11 Profit (+)/ Loss (-) (Rs/t) a) At 100% of target capacity 231.14 341.67 b) At 85% of target capacity 127.60 215.21 12 Financial IRR a) At 100% of target capacity 57.74 % 82.45 % b) At 85% of target capacity 37.14 % 42.09 %

1.5 CONSTRAINTS / RISK IN MINING

Following difficulties and constraints are apprehended in mining:

Sl. No. Constraint Associated Risk 1 Gondegaon village Delay shall affect the dumping Rehabilitation & shifting. schedule of the mine. 2 Land acquisition for Delay shall affect the dumping dumping schedule of the mine.

Page - 8 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

2.0 MARKETABILITY

The mines of WCL are under constant pressure to meet the increasing demand of non-coking coal for power houses and other bulk consumers from Western as well as Southern part of country. The justification of this mine has been studied in the light of estimated demand for non-coking coal from power sector in and production forecast from existing, completed, ongoing and future projects of WCL.

2.1 DEMAND OF COAL

The year wise FSA/LOA commitment of WCL upto 2021-22 is detailed below:

FSA / LOA COMMITMENT AS ON 01.03.2019 (Mt) SL. PARTICULARS Applic- 2019-20 2020-21 2021-22 NO. able Qty. at Qty. at Qty. at Trigger FSA FSA FSA Trigger Trigger Trigger Level Qty. Qty. Qty. Level Level Level A) EXISTING COMMITMENTS THROUGH FSAs & MOUs and LINKAGE AUCTIONS Old power producers existing as on 31.3.09 1 90% 30.628 27.566 30.628 27.56630.628 27.566 with whom FSAs have been signed Past commitment of non-power sector except Cokeries with whom FSAs are 2 60% 1.168 0.701 1.168 0.701 0.231 0.139 signed prior to 31.12.2011 & Commitment of Bhilai Steel Plant from Nandan Washery 3 New Non-power FSA executed 50% 0.566 0.283 0.566 0.283 0.000 0.000 4 Cost plus FSAs with Wardha Power Co.Ltd. 90% 1.625 1.463 1.625 1.463 1.625 1.463 New Power FSA executed with MPPGCL on 02.01.2013, NTPC on 04.09.2013, VIPL on 5 75% 9.271 6.953 9.271 6.953 9.271 6.953 10.03.2014 and Mahagenco (as per IMTF's recommendations) on 27.04.2015 6 Bridge Linkage with Mahagenco 0.000 0.000 0.000 0.000 0.000 0.000 7 GSECL MOU 1.200 1.080 1.200 1.080 1.200 1.080 8 TANGEDCO Commitment 90% 0.500 0.450 0.500 0.450 0.500 0.450 9 Linkage Auction Commitments Tranche I 75% 1.643 1.232 1.643 1.232 1.643 1.232 10 Linkage Auction Commitments Tranche II 75% 1.312 0.984 1.312 0.984 1.312 0.984 11 Linkage Auction Commitments Tranche III 75% 0.408 0.306 0.408 0.306 0.408 0.306 Linkage Auction Tranche IV & Future 12 75% 9.450 7.088 9.450 7.088 9.450 7.088 Expected Commitment# Sub Total :Existing Commitments through 57.772 48.105 57.771 48.10556.268 47.260 FSAs, MOUs and Linkage Auction

Page - 9 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

FSA / LOA COMMITMENT AS ON 01.03.2019 (Mt) SL. PARTICULARS Applic- 2019-20 2020-21 2021-22 NO. able Qty. at Qty. at Qty. at Trigger FSA FSA FSA Trigger Trigger Trigger Level Qty. Qty. Qty. Level Level Level

B) SHAKTI SCHEME & VALID LOA COMMITMENTS

SHAKTI A1 (LoA commitments for post 2009 TPPs of and beyond 78000 MW 1 capacity listed in MOC PD, which have 75% 7.916 5.937 7.916 5.937 7.916 5.937 completed milestones as 100% PPA level. 2 Normative requirement of Shakti B-I 75% 1.403 1.052 1.403 1.052 1.403 1.052 3 Normative requirement of Shakti B-II 75% 2.750 2.063 2.750 2.063 2.750 2.063 4 Normative requirement of Shakti B-III 75% 0.700 0.525 0.700 0.525 0.700 0.525 Commitment of Shree Singhaji, 5 75% 1.543 1.157 1.543 1.157 1.543 1.157 MPPGCL NTPC Cost Plus Tapering LoA Tapering Period: 6 90% 5.688 5.1192 4.266 3.839 1.422 0.000 First year –2019-2020 (75%) Second year –2020-2021 (50%) Third year – 2021-2022 (25%) Sub-Total : FSAs to be executed 20.000 15.853 18.578 14.573 15.734 10.734 with Power sector

TOTAL (A+B) 77.772 63.958 76.349 62.678 72.002 57.994 C Spot e-Auction 6.000 6.000 6.000 6.000 6.000 6.000 Other Auctions ( Exclusive/ Special D 5.500 5.500 5.500 5.500 5.500 5.500 Forward/ Special Spot etc)# TOTAL COMMITMENT (A+B+C+D) 89.272 75.458 87.849 74.178 83.502 69.494

# Tentative Provisional

The above table indicates that WCL has a FSA/LOA commitment of 77.772 Mt, 76.349 Mt and 72.002 Mt at 100% supply for the year 2019-20, 2020-21 & 2021-22 respectively. The FSA/LOA commitment at trigger level are 63.958 Mt, 62.678 Mt and 57.994 Mt for the year 2019-20, 2020-21 and 2021-22 respectively. In addition to this, the coal supply through Spot e-Auction and Other Auctions (Exclusive/ Special Forward / special Spot etc.) is envisaged as 11.50 Mt in 2019-20, 2020-21 and 2021-22.

Page - 10 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

2.2 AVAILABILITY OF COAL

CIL is planning for 1 Billion Tonnes Coal production and the share of WCL is 60 Mt in this 1 BT planned production. The following table shows the availability of coal from the existing, completed, on-going and future mines of WCL: Coal Production Projectection from WCL Mines

Projections of Availability of Coal (Mt) Sl. No. Sector 2019-20 2020-21 2021-22 1 Existing mines 0.15 0.15 0.15 2 Completed projects 16.29 13.05 9.37 3 On-going projects 38.56 42.35 44.71 4 Future projects 0.00 4.45 5.77 Total 55.00 60.00 60.00

2.3 DEFICIT IN AVAILABILITY OF COAL FROM WCL

Following table shows the deficit in availability of coal, including middling, from the various Existing, Completed, On-going, and Future Projects of WCL:

Demand, Supply and Deficit in Availability of Coal

Sl. Projections of Surplus / Deficit of Coal (Mt) Sector No. 2019-20 2020-21 2021-22 Total FSA/LOA 1 Commitment + proposed 89.272 87.849 83.502 E-Auction 2 Availability of coal 55.00 60.00 60.00

3 Surplus / Deficit (+/-) (-) 34.272 (-) 27.849 (-) 23.502

From the above table, it is clear that the deficit in supply of coal from WCL is 34.272 Mt in 2019-20 which will be narrowed down to 27.849 Mt in 2020-21 and 23.502 in 2021-22, if WCL achieves the target capacity of 60 Mt in 2020- 21.

2.4 UTILITY OR MARKET FOR THE COAL FROM MINE / PROJECT

The mines of WCL are under constant pressure to meet the increasing demand of non-coking coal for power houses and other bulk consumers

Page - 11 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019) from Western as well as Southern part of country. The justification of this mine has been studied in the light of estimated demand for non-coking coal from power sector in Maharashtra and production forecast from existing, completed, ongoing and future projects of WCL.

2.5 AVAILABLE LINKAGE OR FIRM FUEL SUPPLY AGREEMENT (FSA)

At present there is no firm fuel supply linkage specific for this mine. However, as detailed in para 2.1 above, existing commitments through FSAs and MOUs is available for WCL as a whole.

2.6 JUSTIFICATION AND MARKETABILITY

From the tables given in para no. 2.1 to 2.3, it is clear that the deficit in supply of coal from WCL is 34.272 Mt in 2019-20 which will be narrowed down to 27.849 Mt in 2020-21 and 23.502 in 2021-22, if WCL achieves the target capacity of 60 Mt in 2020-21. To further reduce the gap between demand and supply of coal, it is very essential to either open new mines or increase the production from existing mines of WCL. Thus, Mining Plan of Expansion of Gondegaon Extension Opencast Project having target capacity of 3.50 Mty will help to reduce the gap between demand and supply of coal from WCL mines.

3.0 PROJECT SITE INFORMATION

3.1 LOCATION & COMMUNICATION

The area under consideration lies between latitudes E22o6' – E22 o 16' and longitudes N79o11' - N79o 12'. The area is covered by Survey of Topo sheet No. 55 O/3. Ghatrohan block is located North - West of exising Gondegaon Opencast mine. Expansion of Gondegaon Extension Opencast Mine which is amalgamation of Gondegaon and Ghatrohan block is in of Maharashtra and is under administrative control of Nagpur Area of Limited. This Mining Plan envisages extension of Gondegaon OC by amalgamation of the existing Gondegaon OC mine with adjoining Ghatrohan OC block.

The proposed quarriable area is bounded by State high way No.233 in North, in West and South and incrop of Seam-I in East. The quarriable area is separated by the barrier from Inder UG to OC project. Page - 12 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

3.2 TOPOGRAPHY AND DRAINAGE

The surface area is generally undulating with elevations ranging from 278 m to 288 m above MSL. The main drainage is controlled by Southerly flowing Kanhan river along the Western and Southern boundaries of the block. Minor seasonal streams originating within the block drain into Kanhan river. In general the area is sloping towards South West and South.

3.3 LAND USE PATTERN

The entire area of the block is covered by fertile black cotton agricultural land and is presently being used for growing crops like cotton, lentils, chilli, sunflower etc.

4.0 GEOLOGY

4.1 INTRODUCTION

CMPDIL prepared a comprehensive report incorporating the data of 76 boreholes drilled by IBM & 7 boreholes drilled by CMPDIL. The report entitled "Revised Geological Report on Ghatrohan-Gondegaon Block, Kamptee Coalfield" was submitted in March, 1985 by CMPDIL wherein the entire data was re-interpreted with the purpose of evolving a simplified structure and estimation of reserves upto 150 m depth for Seams-V & IV. This was done so as to facilitate opencast mine proposition in the block.

In March 1986, CMPDIL vide their letter no.RIN:GD:MECL:6851 dated 6th March, 1986, requested Mineral exploration Corporation Limited (MECL) to take up ten points for drilling in Gondegaon-Ghatrohan block. The boreholes were proposed upto Seam-IV Bottom only.

The exploration in the block commenced in April'86. While the exploration was in progress, on reviewing the data of the six boreholes completed by MECL, further programme to take up additional boreholes was finalized in different stages. Thus, in this block, a total of 44 boreholes were released out of which only 33 boreholes could be completed by MECL.

Page - 13 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

Though the boreholes were initially proposed to be drilled upto Seam-IV Bottom so as to assess, in particular, the quarriable potential, some of the boreholes were advised to be drilled upto the bottom-most of Seam-I in the Kamptee Coalfield. This was done in order to confirm the thicknesses and quality of the seams – III, II and I.

MECL submitted the report entitled "Geological Report on Exploration for Coal Gondegaon-Ghatrohan Block, Kamptee Coalfield, April' 1988".

To increase the coal production from Nagpur Area of WCL, opencast patch deposits in Gondegaon-Ghatrohan block were identified and CMPDIL, RI-IV, Nagpur published a project report entitled "Opencast patch deposits in Ghatrohan block", March 1996. In the above report, drilling for confirmation of Incrop, Structure and workable thickness of lower seams were suggested. CMPDIL, RI-IV took the exploration work during May,1996 to June,1996 and February, 1997 to June,1997 in two phases and drilled total 31 no. of boreholes (CMKG Series) with 2973.00 meters of drilling. CMPDIL prepared a report entitled "Geological Note on Part of Gondegaon-Ghatrohan Block, Kamptee Coalfield, Dist. Nagpur, (M.S.), March,1998".

4.1.1 Different Geological Reports Prepared for the Block

Following Geological Reports were prepared for the proposed Gondegaon Ghatrohan Block:-

Sl.No. Agency Geological Report 1 Report on Detailed Exploration of Coal in Ghatrohan IBM Sector, Kamptee Coalfield, August,1964 2 Revised Geological Report on Ghatrohan-Gondegaon CMPDIL Block, Kamptee Coalfield, March,1985 3 Geological Report on Exploration for Coal Gondegaon- MECL Ghatrohan Block, Kamptee Coalfield, April,1988 4 Geological Note on Part of Gondegaon-Ghatrohan CMPDIL Block, Kamptee Coalfield, March,1998

Page - 14 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

4.1.2 Block Boundaries

The geological block boundaries of Gondegaon Ghatrohan block are as follows:

North : Subcrop of Seam-II (B)

South : Fault F9- F9

East : 200 m influence distance from borehole MKG-1.

West : Eastern bank of Kanhan river and .

4.2 EXPLORATION STATUS

4.2.1 The details of boreholes drilled in the quarry and surrounding area are tabulated below :

Agency Series of No. of Metreage Geological Report Boreholes boreholes drilled Report on Detailed Exploration of IBM KG 76 9684 Coal in Ghatrohan Sector, Kamptee coalfield, August,1964 Revised Geological Report on CMPDIL CMKMK 7 1066 Ghatrohan-Gondegaon Block, Kamptee Coalfield, March,1985 Geological Report on Exploration for Coal Gondegaon - Ghatrohan MECL MKG 33 3657.35 Block, Kamptee Coalfield, April,1988 Geological Note on Part of CMPDIL CMKG 31 2973 Gondegaon-Ghatrohan Block, Kamptee Coalfield, March,1998

TOTAL 147 17380.35

4.2.2 Borehole Density

The density of boreholes for quarriable block is 33 boreholes per square km.

4.3 GEOLOGY AND STRUCTURE OF THE BLOCK

4.3.1 Geological Formations

The formation-wise description is as follows :-

Page - 15 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

Talchirs

There are no outcrops of Talchirs in the block. Borehole MKG-29, drilled in the north-eastern part of the block, has intersected Talchirs at 119.53 m. Its thickness, as intersected in the borehole, is only 1.47 m and could be identified because of its distinct greenish coloured shale.

Barakars

Barakars are of Lower Permian age. Barakars in the block could be divided into three parts, based on the presence or absence of seams. The three parts of Barakars are Upper Barakars, Middle Barakars and Lower Barakars.

Upper Barakars

The Upper Barakars is that part which lies above the youngest Seam-V. It consists of medium to coarse grained grey sandstones.

Middle Barakars

The horizon from roof of Seam-V to the floor of Seam-I is termed as Middle Barakars. The Middle Barakars comprises of grey feldspathic sandstones, shales, carbonaceous shales and 5 seams with their individual thickness of 1 m to 10 m.

Lower Barakars

The part of Barakars lying below floor of Seam-I upto the Talchir contact is termed as Lower Barakars. It comprises mainly fine grained sandstone, shales and intercalations. It is characterized by the presence of fine garnets in dissiminated form.

Kamthis

Kamthis have been deposited on the eroded surface of Barakars and thus, there is a distinct erosional unconformity between them. Kamthis, in general, comprises friable ferruginous sandstone which is medium to coarse grained and pink in colour. It also consists of shales and variegated clays.

Page - 16 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019) Soil

The area in its major central and western parts is covered with black cotton soil. In the west and in south, along the banks of Kanhan river, the alluvium in the form of sand and gravel has been noticed.

4.3.2 Faults

The block is traversed by eleven faults serially numbered as F1 to F11. The faults have been interpreted based on the difference in FRL on both sides, omission and reduction in seam thickness, etc. The description of individual faults is furnished in the following table:-

Fault Strike Amount Location & Nature of evidences No. & Extent direction of throw F1-F1 NW-SE 100 m Lies across the 1. Strike fault. due N.E. central part of 2. Difference in FRL value on the block and both sides of fault further extends 3. Direct evidence beyond the block BH No. Seam Faulted in the East & CMKG-22 All seams except Seam-V West. CMKG- All seams except Seam-V & 27 IV (T) KG-8 All seams except Seam-II(B) KG -57 All seams except Seam-II(T) & (B) KG -50 All seams except Seam-III (T) & (B) & II (T) & (B) KG -13 All seams except Seam- III(T), IV(T) & (B) F2-F2 Curvilinear 5-15 m Lies in Sector-I. 1. Difference in FRL value on NW-SE to southerly Extends beyond either side of the fault. almost the block in the 2. Direct evidence of faulting E-W west, dies out in BH No. Seam Faulted the east near KG-54 Seam-III(T) & (B) borehole Nos. KG-60 Seam-III(T) & (B),II(T) &(B) KG-54 & KG-29. F3-F3 NE-SW 20 m due Extends beyond 1. Difference in FRL value on S.E. Subcrop in N.E. either side of the fault. Abuts against F5 2. Direct evidence of faulting in S.W. BH No. Seam Faulted KG-14 Seam-III(T) & (B) F4-F4 NE-SW 20 m due Extends beyond 1. Difference in FRL value on S.E. incrop in N.E. either side of the fault. Abuts against F5 2. Direct evidence : Seam II(B) Part faulted in borehole KG-3.

Page - 17 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

Fault Strike Amount & Location & Nature of evidences No. direction Extent of throw F5-F5 WNW- 30-40 m Abuts against F1 1. Difference in FRL value on ESE due south in the west. either side of the fault. Extends beyond 2. Direct evidence of faulting the block in the BH No. Seam Faulted east. KG-35 Seam-II(T) & (B) KG-34 Seam-III(T) & (B),II(T) &(B) KG-20 Seam-IV(T) & (B), III(T) F6-F6 E-W 35 m due Abuts against F1 1. Difference in FRL value on north in the west and F3 either side of the fault. in the east. 2. Direct evidence of faulting BH No. Seam Faulted KG-70 Seam-II(T) & (B) KG-4, Seam-V KG-67 F7-F7 NE- 50-60 m Abuts against F1 1. Difference in FRL value on SW due S.E. in the NE. either side of the fault. Extends beyond 2. Direct evidence of faulting the block in the BH No. Seam Faulted SW. MKG-26 Seam-II(T) & (B), III(T) & (B) 1. Oblique fault Abuts against NNE- 20.m.due fault F6 – F6 in FRL difference in BHs.KG-4 F8-F8 SSW SE the North & F1 – 2. on up thrown side & KG-2 in F1 in the South down thrown side.

1. Oblique fault Joins fault F7 – F7 in the West & Omission of Seam-II in KG- 20 to 60 m 2. F -F E – W continuous to 75. 9 9 due S. Inder block in the Based on sub surface data East 3. of BHs. On either side of the fault 1. Oblique fault Joins F9 – F9 in Level difference on either F -F 20 to 40 m the West and 10 10 E – W side of the fault in BH MKG- due S extends to Inder 2. 7, MKG-8 on upthrown side block in the East. and CMKMK-57 & MKG- 3on downthrown side. 1. Oblique fault Based on sub surface data NW – Joins fault F1-F1 of BHs. On either side in BH F -F 5 – 10 m 11 11 and abuts against 2. MKG-6, KG-74, MKG-8 up due NE SE F10-F10. thrown side and CMKMK-59 on down thrown side. Omission of Seam-IV (T) in 3. KG-74.

Page - 18 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

4.3.3 Strike and Dip

The strike and dip of the coal seam in the proposed area is entirely based on the sub-surface data obtained from the boreholes. The floor contours of the composite seam has been drawn at 10 m interval from which it would be seen that the amount of dip and strike direction are quite variable.

The Gondegaon-Ghatrohan Block is a part of the Kamptee - Silewara- Patansaongi Sub-basin. The general strike of beds is ESE-WNW to NW-SE. The gradient of the coal seams varies from 1 in 3.5 to 1 in 5 due SW to SSW.

4.4 COAL SEAM

Five coal seams which are characteristic of Kamptee Coalfield, are present in the Gondegaon-Ghatrohan block also. All these seams occur in the Middle Barakar horizon of about 100 m thickness. The seams in Kamptee Coalfield are numbered from bottom to top, the bottom-most Seam-I is the oldest, while the Seam-V, the youngest. The oldest Seam-I is found to be deposited around 100 m above the Talchir-Barakar contact. Of the five seams, Seams-II, III & IV occur in 2 to 3 split sections, while Seam-V is present as a single horizon. Seam-I is impersistent and also thin, mostly below 0.90 m thickness.

Seam-I to V occur in Gondegaon-Ghatrohan Block in nine sections, viz. Seam-I (Bottom), I (Top), II (Bottom), II (Top), III (Bottom), III (Top), IV (Bottom) {Seam-IV Bottom and IV Middle may be considered as Seam-IV Bottom due to very thin parting between them}, IV (Top) & V.

Details of Coal seam for Gondegaon OC & Ghatrohan OC are as shown in the following tables :-

Coal Seam details : Gondegaon OC

Seam with Floor depth (m) Thickness (m) Average Remarks parting Minimum Maximum Minimum Maximum V 26.20 137.41 3.80 11.32 8.5 Persistent (KG-73) (CMKMK-57) Parting 22.36 40.69 - Sandstone variates IV (Top) 35.80 165.58 1.13 7.25 3.3 Persistent (MKG-13) (CMKMK-57)

Page - 19 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

Seam with Floor depth (m) Thickness (m) Average Remarks parting Minimum Maximum Minimum Maximum Parting 0.54 11.93 Sandstone variates IV (Bottom) 31.90 175.91 4.68 13.02 7.4 Persistent (CMKMK-60) (CMKMK-57) Parting 8.69 25.01 Sandstone variates III (Bottom) 36.43 205.07 0.55 5.71 3.7 Persistent (KG-40) (CMKMK-57) Parting 1.11 17.17 Shale, shaly sst. II (Top) 31.60 219.60 0.44 3.83 2.3 Persistent (KG-23) (CMKMK-57) Parting 0.50 10.07 Shale, shaly sst. II (Bottom) 36.60 224.50 0.39 4.40 2.5 Persistent (KG-23) (CMKMK-57)

Coal Seam details : Ghatrohan OC

Seam with Floor depth (m) Thickness (m) Average Remarks parting Minimum Maximum Minimum Maximum V 23.25 121.65 5.75 10.51 9.00 Persistent (CMKG-7) (MKG-30) Parting 25.16 34.45 Sandstone variates IV (Top) 25.56 160.80 1.44 6.52 2.00 Persistent (KG-62) (MKG-30) Parting 1.12 15.79 Shaly sandstone, shale, interc-alation of sst. and shale IV 31.70 173.51 1.90 10.64 6.00 Persistent (Bottom) (KG-51) (MKG-30) Parting 23.47 31.55 Sandstone variates III 28.11 159.45 0.65 7.10 4.00 Persistent (Bottom) (CMKG-30) (CMKG-19) Parting 3.08 9.34 Shale, shaly sst. II (Top) 31.60 168.10 0.48 3.90 2.00 Persistent (KG-23) (CMKG-19) Parting 0.27 6.29 Shale, shaly sst. II 34.00 173.62 0.41 5.00 2.00 Persistent (Bottom) (CMKG-28) (CMKG-19)

4.5 QUALITY PARAMETERS

Seam-wise quality details of Gondegaon-Ghatrohan OC are as shown in the following table:-

Page - 20 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

SEAMWISE COAL QUALITY WITHOUT DILUTION Gondegaon OC Ghatrohan OC Seam Combined Seam Combined Section- Effective Seam-wise Effective Section-wise Seam-wise Seams wise thickness Weighted thickness Weighted Weighted Weighted (m) Av. GCV (m) Av. GCV Av. GCV Av. GCV (kCal/kg) (kCal/kg) (kCal/kg) (kCal/kg) V 8.02 4305 4305 7.21 4528 4528 IV-TOP 3.37 4567 3.10 4314 4790 4709 IV BOTTOM 6.77 4894 5.09 4902 III-TOP 1.58 5033 5659 5713 III BOTTOM 3.43 5761 3.07 5713 II-TOP 2.36 5598 1.85 5598 5596 5661 II BOTTOM 2.28 5592 2.63 5707

4.6 GEOLOGICAL RESERVES

The proposed boundaries of Gondegaon Ghatrohan geological block are as follows :

North : Subcrop of Seam-II (B)

South : Fault F9- F9

East : 200 m influence distance from borehole MKG-1.

West : Eastern bank of Kanhan river and Pench river.

The sectors for reserves estimation in Gondegaon-Ghatrohan Block have been demarcated mainly on the basis of faults. The boundaries of these sectors are described below :

Sectors Sector Boundaries

I Subcrop of Seam-II (Bottom), Pench River, Faults F1,F3

II Subcrop of Seam-II (Bottom), Kanhan River, Faults F1,F7

Page - 21 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

Sectors Sector Boundaries

III Subcrop of Seam-II (Bottom), Faults F3,F5 F4

IV Subcrop of Seam-II (Bottom), to Faults F4,F5

V Faults F5,F6 A5 Fault F1-F1, F6-F6 and the limit of the Subcrop of seam A6 Fault F1-F1, F11-F11, F10-F10 and the limit of the Subcrop of seam A7 Fault F9-F9, F10-F10 and the limit of the area explored in the East (200 m from borehole MKG-1) A8 Fault F1-f1, F7-F7, F10-F10, F11-F11 and upto the 150 m depth line B1 Fault F7-F7, F9-F9, F10-F10 and more than 150 m depth line B2 Fault F9-F9, F10-F10 and more than 150 m depth line

The seam-wise & sector-wise net Geological reserves are tabulated below :

Sector Seam-wise Net Geological Reserves (Mt) V IVT IVB III T IIIB IIT IIB Total I 2.192 0.998 2.844 1.894 1.907 1.777 11.612 II 1.790 1.090 2.776 2.185 1.709 2.049 11.599 III 0.036 0.130 0.404 0.413 0.300 0.439 1.722 IV - - - 0.204 0.152 0.204 0.560 V 0.643 0.298 0.607 0.161 0.129 0.093 1.931 A5 2.47 1.69 3.10 0.23 1.39 1.24 1.16 11.280 A6 0.51 0.77 1.78 0.38 1.12 0.70 1.24 6.500 A7 2.845 1.088 2.491 6.424 A8 3.38 1.22 2.60 0.35 1.36 1.05 0.93 10.890 B1 3.146 1.317 2.102 6.565 B2 1.169 0.418 0.895 2.482 Total 18.181 9.019 19.599 0.96 8.727 7.187 7.892 71.565

Thus, the net in situ proved geological reserves in proposed Gondegaon- Ghatrohan block are 71.565 million tonnes. Page - 22 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

5.0 MINE BOUNDARY, RESERVES, TARGET & MINE LIFE

5.1 MINE BOUNDARY DELINEATION

Mine Boundary of the proposed Amalgamated Gondegaon Ghatrohan OC mine is as follows:

MINE BOUNDARY

Rise Dip East West (North) (South)

On the floor of At about 150 m 60 m barrier from Inder 100 m barrier from Seam-II (Bottom) depth or 140 m Colliery in Gondegaon Kanhan river on at full thickness FRL on upthrow block and along Fault the surface and

of fault F1-F1 F7-F7 on Ghatrohan Fault F7-F7 on block. Gondegaon block.

5.2 MINEABLE RESERVES

Out of total 71.565 Mt geological reserves of Gondegaon-Ghatrohan block, the geological reserves considered in Gondegaon-Ghatrohan OC mine upto 150m depth is 59.965 Mt. Rest 11.600 Mt lies in the dip side beyond 150m depth. Considering 10% geological losses due to geological disturbance e.g. Faults etc. and 5% mining losses due to losses during mining activity as per present practice, the mineable reserves upto 150m depth worked out to 51.27 Mt.

To arrive at the balance coal and OB as on 01.04.2019 for the proposed Mining Plan of Expansion of Gondegaon Extension Opencast Project, actual coal and OB extracted upto 31.03.2019 have been deducted from the total coal and OB (29.23 Mt coal and 121.31 Mm3 OB) of the approved RPR of November, 2015.

Calculations of projected balance reserves as on 31/03/2019 adopted for this report has been arrived at as shown in the following table :

Page - 23 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

Gondegaon Ghatrohan Total Sl. OC OC Description No. COAL OB COAL OB COAL OB Mt Mm3 Mt Mm3 Mt Mm3 Balance As Per RPR- 1 10.47 42.73 18.76 78.58 29.23 121.31 2015 2 Actual 2015-16 2.13 4.30 0.00 0.00 2.13 4.30 3 Actual 2016-17 2.15 5.10 0.00 0.00 2.15 5.10 4 Actual 2017-18 2.41 5.01 0.75 6.66 3.16 11.67 5 Actual 2018-19 2.22 11.10 1.28 1.12 3.50 12.22 Balance As On 6 31/03/19 = (1) - 1.56 17.22 16.73 70.80 18.29 88.02 (2+3+4+5) =

In this Mining Plan, 2019-20 is considered as Year-I and total coal and OB considered as on 01.04.2019 are 18.29 Mt and 88.02 Mm3 respectively.

5.3 TARGET PRODUCTION

Based on the Geo-mining parameters such as strike length, gradient, thickness of seam, average rate of deepening of opencast quarries in WCL and production performance in existing mine, the target production in the proposed Mining Plan for Expansion of Gondegaon Extension Opencast Project has been envisaged as 3.50 Mty.

5.4 MINE LIFE

The total mineable reserves in the proposed mine as on 1.4.2019 is 18.29 Mt and with a target production of 3.50 mty, the balance life of mine has been envisaged as 6 years starting from 01.04.2019.

6.0 METHOD OF MINING

6.1 GEO-MINING CHARACTERSTICS

Page - 24 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

The geo-mining parameters of the Expansion of Gondegaon Extension OC are detailed in the following table :

Sl. Particulars Gondegaon Ghatrohan Total No. Sub Quarry Sub Quarry 1. Area of the Quarry (including existing OC) a) On floor (ha) 95.43 87.35 182.78 b) On surface (ha) 156.93 120.20 277.13 2. Depth (m) (Balance Quarry) a) Initial 120 37 b) Final 176 145 1 in 3.5 to 1 in 3.8 to 3. Average Gradient of Seam 1 in 5 1 in 5 4. Average thickness of seam (m) 27.43 28.34 27.72 5. Average Strike length on floor of 1600 1400 3000 Quarry (m) 6. Width on surface (m) [dip rise] 860 1010 7. Width on floor (m) [dip rise] 620 750 8. GCV band (0.10m dilution at each G-10 (Seam – V & IV) contact point) kCal/kg G-8 (Seam – III & II) 9. Mineable Reserves (Mt) 1.56 16.73 18.29 10. Total OB (Mm3) 17.22 70.80 88.02 11. Average stripping ratio (m3/t) 11.04 4.23 4.81

6.2 SELECTION OF MINING METHOD

Expansion of Gondegaon Extension Opencast Project which is Amalgamation of Gondegaon – Ghatrohan OC is already in operation with Shovel Dumper system of mining and hence same technology has been envisaged in this proposed Mining Plan. Deployment of dragline is ruled out due to multi-seam working and varying thickness of partings between the coal seams. Due to steep gradient (1 in 3.5 to 1 in 5), Surface Miner deployment is also not

Page - 25 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019) feasible. Shovel-Dumper Technology is most flexible system and moreover, well adopted in coal mines of WCL. Considering the average gradient of mine inclined slicing method is envisaged in proposed mine.

6.3 EQUIPMENT SELECTION

In this Mining Plan, it is envisaged to excavate partially coal and OB by departmental HEMM keeping in view available capacity of Departmental HEMM as on 01.04.2019. Balance workload of coal & OB will be removed by hiring/outsourcing agency.

6.4 MINING SYSTEM AND SYSTEM PARAMETERS

6.4.1 Width & Height of Benches

For overburden, keeping the bench height of 10 m, the width of working and non-working benches are kept as 30 m and 20 m respectively. Haul road would be constructed on the floor of the quarry at a gradient of 1 in 16 with a width sufficient for dumper movement, dozer path, drainage and electrification etc.

6.4.2 Slope of Benches & Quarry

i) During Mining Operation

The slope of individual benches depends on the type of strata. In this report, the slope of individual bench is proposed as 45o in soil, alluvium and clay whereas, it is 70o in hard strata. The overall slope of the quarry in dip side during mining operation varies around 22o (from horizontal plane) depending on the nature of strata in the entire depth of quarry.

ii) At the end of quarry

The slope of individual benches in the batter at the end of quarry remains same as that during mining operation i.e. 45o in soil, alluvium and clay and 70o in hard strata. Overall angle considered during planning is about 400 in dip side & about 370 in rise side. However, it is proposed to do scientific study for slope stability in quarry benches and OB dumps by any scientific agency.

Page - 26 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

7.0 MINING AND DUMPING STRATEGY

7.1 CONSTRAINTS ON MINE DEVELOPMENT

Following constraints are apprehended in mining :

Sl. Constraint Associated Risk No. 1 Gondegaon village Delay shall affect dumping schedule. Rehabilitation 2 Land acquisition Delay shall affect dumping schedule.

7.2 MINING STRATEGY

7.2.1 Presently, Expansion of Gondegaon Extension Opencast Project which is Amalgamation of Gondegaon and Ghatrohan OC is being worked in Partial Hiring option.

The target capacity of Gondegaon Extension Opencast Project is 3.50 Mty. Both Gondegaon and Ghatrohan sub-quarry will be worked simultaneously by deploying existing departmental HEMM as well as out-sourced HEMM. The capacity of departmental HEMM varies from 5.51 Mm3/year to 6.23 Mm3/year depending on the lead and lift of coal and OB. Initially, entire departmental HEMM will be deployed in Gondegaon sub-quarry and the entire balance coal and OB of this sub-quarry as on 31.03.2019 will be extracted. In addition to departmental HEMM, part OB of Gondegaon sub-quarry will have to be excavated through out-sourcing agency.

The balance coal and OB from Ghatrohan sub-quarry as on 31.03.2019 will be worked by out-sourcing agency till exhaustion of reserves in Gondegaon sub quarry and thereafter departmental HEMM from Gondegaon sub-quarry will be shifted to Ghatrohan sub-quarry. The entire coal and OB of Ghatrohan sub-quarry will be worked in 6 years which is the total balance life of mine. The OB excavated from Gondegaon Sub-quarry will be partly accommodated in simultaneous internal dumping in Gondegaon sub-quarry and partly in external OB dumps. The balance OB from Ghatrohan sub-quarry will be

Page - 27 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019) initially dumped in External OB dump and internal dumping will start from 2nd year in decoaled void of Gondegaon sub-quarry as well as Ghatrohan sub- quarry.

7.2.2 VOLUME REGIME

The entire Gondegaon Extension Opencast Project has been divided into four cuts namely; Cut (A+B) in Gondegaon sub-quarry and Cut-C, D & E in Ghatrohan sub-quarry. The mineable reserves, OB and stripping ratio in these cuts are given in the following table:-

Sl. Cut No. Quarry Description of Cut Coal OB S.R. No. (Mt) (Mm3) (m3/t) 1 A+B Gondegaon Up to dip-side limit 1.56 17.22 11.04 of quarry 2 C Ghatrohan Up to 210 FRL 5.76 33.16 4.90 3 D Ghatrohan Up to up-thrown 7.44 26.25 3.53 fault F1-F1’ 4 E Ghatrohan Up to dip-side limit 3.53 11.39 3.23 of quarry 5 Sub Total (2+3+4) 16.73 70.80 4.23 Total (1+5) 18.29 88.02 4.81

7.3 DUMPING STRATEGY

The total balance OB in Gondegaon Extension Opencast Project as on 01.04.2019 has been assessed as 88.02 Mm3, out of which 51.96 Mm3 OB is proposed to be dumped in External OB Dump - A3 & D4 (1.87 Mm3) and Dump - A2 (50.09 Mm3). The balance 36.06 Mm3 OB (88.02 Mm3 – 51.96 Mm3) will be accommodated in internal dumps in the decoaled void of Gondegaon sub-quarry and Ghatrohan sub-quarry.

Both Gondegaon and Ghatrohan sub-quarries will be worked simultaneously to achieve the target production of 3.50 Mty. The OB excavated from Gondegaon Sub-quarry will be partly accommodated in simultaneous internal dumping in Gondegaon sub-quarry and partly in external OB dumps. The OB from Ghatrohan sub-quarry will be initially dumped in External OB dump and

Page - 28 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019) internal dumping will start from 2nd year in decoaled void of Gondegaon sub- quarry as well as Ghatrohan sub-quarry.

7.3.1 Dump Capacity

The balance dump capacity of different existing OB Dumps in Gondegaon Extension Opencast Project has been assessed as on 01.04.2019 considering the quantity of OB already dumped upto 31.03.2019. The details of OB Dumps with balance capacity as on 01.04.2019 are tabulated below :

DUMP CAPACITY

Sl. OB Dump Capacity (Mm3) Dump Height No. (As On 01.04.2019) 1 Top Soil Dump - A-3 & D-4 20m 1.87 2 External Dump A-2 90m 50.09 Internal Backfilling in decoaled Below and 3 void of Gondegaon and Above 36.06 Ghatrohan sub-quarries Ground Grand Total 88.02

8.0 MINING SCHEDULE AND EQUIPMENT PHASING

8.1 DESIGN CRITERIA

The Mining Plan of Gondegaon Extension Opencast Project which is Amalgamated Gondegaon Ghatrohan OC has envisaged 330 days of working in a year based on 7 days schedule of mine working. As per the prevalent practice in WCL, there will be 3 working shifts in a day and each shift will be of 8 hours duration. The excavation category of OB material has been assumed as 50% Category– III + 50% Category-IV, whereas, for coal it is assumed as Category-IV. The in-situ volume weight of OB material has been considered as 2.1 t/m3 whereas for coal it is taken as 1.60 t/m3.

8.2 CALENDAR PROGRAMME OF EXCAVATION

Calendar Programme has been prepared on the basis of separate estimation of coal and overburden in various cuts of Gondegaon and Ghatrohan sub-

Page - 29 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019) quarries. Based on quarry-wise and cut-wise coal, OB and stripping ratio, year-wise natural OB has been assessed for planned production of coal. Thereafter, year-wise programmed OB has been planned to minimize the peak OB.

The Cut-wise coal, OB and stripping ratio is tabulated below : -

Cut-wise Coal, Natural OB (top OB & Parting) & Stripping Ratio as on 01.04.2019

Quarry CUT Coal OB (Mm3) S.R. No. (Mt) (m3/t) Top OB Parting Total

Gondegaon A+B 1.56 0.00 17.22 17.22 11.04 C 5.76 2.16 31.00 33.16 4.90 Ghatrohan D 7.44 2.63 23.62 26.25 3.53 E 3.53 4.34 7.05 11.39 3.23 Total 18.29 9.13 78.89 88.02 4.81

The Calendar Programme in the proposed Mining Plan of Gondegaon Extension Opencast Project which is Amalgamated Gondegaon Ghatrohan OC has been prepared for target production of 3.50 Mty and the annual peak OB of 22.85 Mm3. The balance coal reserves and overburden have been estimated as on 01.04.2019 and the first year of the Mining Plan has been considered as 2019-20. Calendar Programme has been drawn up separately for Gondegaon OC and Ghatrohan OC. The sequence of mining shall be as per the Balance of Cut-A+B in Gondegaon OC and Cuts-C, D, E of Ghatrohan OC.

The end limit floor contours of these cuts are shown in Quarry and Surface Layout Plan. It is imperative that this sequence of mining be strictly adhered to in order to obtain void for backfilling so that the dumping programme can be achieved. The basic mining strategy at Ghatrohan OC is to work the quarry in full strike keeping downthrown side advance up to the major up thrown strike

Fault F1-F1 so that the void thus created can be subsequently utilized for backfilling while working at up throw side.

Page - 30 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

CALENDAR PROGRAMME OF EXCAVATION

Coal (Mt) Natural O.B (Mm3) Programmed O.B (Mm3)

Yr Quarry Cut Top Top Yearly Cumm. Parting Total Cumm. Parting Total Cumm. OB OB

Gondegaon A+B 0.50 0.50 0.00 5.52 5.52 5.52 0.00 5.52 5.52 5.52

1 Ghatrohan C 3.00 3.50 1.12 16.15 17.27 22.79 1.18 16.15 17.33 22.85 Sub-Total 3.50 3.50 1.12 21.67 22.79 22.79 1.18 21.67 22.85 22.85

Gondegaon A+B 0.50 4.00 0.00 5.52 5.52 28.31 0.00 5.52 5.52 28.37

C 2.76 6.76 1.04 14.85 15.89 44.20 0.98 14.85 15.83 44.20 2 Ghatrohan D 0.24 7.00 0.09 0.76 0.85 45.05 0.74 0.76 1.50 45.70 Sub-Total 3.50 7.00 1.13 21.13 22.26 45.05 1.72 21.13 22.85 45.70

Gondegaon 0.56 7.56 0.00 6.18 6.18 51.23 0.00 6.18 6.18 51.88 A+B

3 Ghatrohan D 2.94 10.50 1.04 9.33 10.37 61.60 0.74 9.33 10.07 61.95 Sub-Total 3.50 10.50 1.04 15.51 16.55 61.60 0.74 15.51 16.25 61.95

4 Ghatrohan D 3.50 14.00 1.24 11.11 12.35 73.95 1.15 11.11 12.26 74.21 D 0.76 14.76 0.26 2.42 2.68 76.63 0 2.42 2.42 76.63 Ghatrohan 5 E 2.74 17.50 3.37 5.47 8.84 85.47 4.34 5.47 9.81 86.44 Sub-Total 3.50 17.50 3.63 7.89 11.52 85.47 4.34 7.89 12.23 86.44

6 Ghatrohan E 0.79 18.29 0.97 1.58 2.55 88.02 0 1.58 1.58 88.02 TOTAL 18.29 9.13 78.89 88.02 9.13 78.89 88.02

8.3 DUMPING SCHEDULE

The total balance OB in proposed Mining Plan of Gondegaon Extension Opencast Project as on 01.04.2019 has been assessed as 88.02 Mm3, out of which 51.96 Mm3 OB is proposed to be dumped in External OB Dump - A3 & D4 (1.87 Mm3) and Dump - A2 (50.09 Mm3). The balance 36.06 Mm3 OB (88.02 Mm3 – 51.96 Mm3) will be accommodated in internal dumps in the decoaled void of Gondegaon sub-quarry and Ghatrohan sub-quarry.

Page - 31 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

The year-wise and quarry-wise OB quantity and the dumping schedule is tabulated below :

DUMPING SCHEDULE

Total OB Dumping (Mm3)

3 Internal OB (Mm ) Top Soil Dump External Year Quarry Back- A-3,D-4 Dump A-2 filling

Gondegaon 5.52 5.52 1 Ghatrohan 17.33 0.24 17.09 Sub-Total 22.85 0.24 22.61 Gondegaon 5.52 4.02 1.50 2 Ghatrohan 17.33 0.35 13.00 3.98 Sub-Total 22.85 0.35 17.02 5.48 Gondegaon 6.18 2.18 4.00 3 Ghatrohan 10.07 0.15 3.92 6.00 Sub-Total 16.25 0.15 6.1 10.00 4 Ghatroha 12.26 0.24 0.91 11.11 5 Ghatrohan 12.23 0.89 3.45 7.89 6 Ghatrohan 1.58 0 1.58 TOTAL 88.02 1.87 50.09 36.06

8.4 WORKLOAD FOR HIRING AGENCY

The year-wise workload for hiring/ out-sourcing agency in proposed Mining Plan of Gondegaon Extension Opencast Project will be as per proposed Calender Programme of Excavation. The existing system capacity will be maintained for departmental workload. The yearwise balance capacity in addition to departmental workload is proposed to be catered by outsourcing HEMM

8.5 EQUIPMENT SCHEDULE

8.5.1 EXISTING, REPLACEMENT AND ADDITIONAL HEMM

List of existing HEMM as on 01/02/2019 have been made available by mine . As per the date of commissioning & CIL Survey-Off Norms (approved in CMD's meet dated 10.7.2007), availability of the said equipment has been

Page - 32 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019) assessed. The break-up of existing HEMM, Replacement HEMM & additional HEMM considered in this Mining Plan is as follows :

EXISTING, REPLACEMENT AND ADDITIONAL HEMM

As per Mining Plan (August,2019) Existing as on Sl. HEMM Requirement (Nos) Particulars 01/04/2019 No. Yr of Yr of Addl. Nos Repl. Total Comm. Repl. Prov. FOR COAL & PARTING 1 6.1 m3(die) Hyd Shovel 2014 1 2021 1 0 1 2009 1 2019 1 0 1 2 5.0 m3(die) Hyd B/H 2013 1 2020 1 0 1 2013 2 2020 2 0 2 3 4.3 m3(die) Hyd B/H 2015 1 2022 1 0 1 2018 1 2025 1 0 1 2008 3 2019 3 0 3 2009 4 2019 4 0 4 2011 2 2019 2 0 2 2012 4 2019 4 0 4 4 60 T RD DUMPERS 2013 5 2020 5 0 5 2015 7 2022 7 0 7 2016 4 2023 4 0 4 2018 1 2025 1 0 1 5 460 HP DOZER 2001 1 2018 1 0 1 2008 2 No Repl. 0 0 0 2009 1 2019 1 0 1 6 320 HP DOZER 2010 2 2019 2 0 2 2015 2 2022 2 0 2 2018 1 2025 1 0 1 2001 1 2019 1 0 1 2005 1 2019 1 0 1 7 160mm RBH Drill(Diesel) 2014 1 2023 1 0 1 2015 2 2024 2 0 2 2017 1 2026 1 0 1 FOR COMMON 1 1.5 m3(die) Hyd B/H 2012 1 2019 1 0 1 2012 1 2021 1 0 1 2 294 HP Motor Grader 2013 1 2022 1 0 1 2001 1 No Repl. 0 0 0 3 Mobile Crane 30 t 2016 1 2025 1 0 1 4 Mobile Crane11 t 2017 1 2026 1 0 1 5 Mobile Crane 9.5 t 2012 1 2021 1 0 1 6 Mobile Crane 8 t 2000 1 2019 1 0 1 7 Tyre Handler 2014 1 2021 1 0 1

Page - 33 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

As per Mining Plan (August,2019) Existing as on Sl. HEMM Requirement (Nos) Particulars 01/04/2019 No. Yr of Yr of Addl. Nos Repl. Total Comm. Repl. Prov. 2015 1 2022 1 0 1 8 Water sprinkler 28 kl 2017 2 2024 2 0 2 5.74 m3 Front End 9 0 0 1 1 Loader 10 Diesel Bowser 3kl 0 0 1 1 11 Mobile maintanence van 0 0 1 1 12 Fire fighting truck 0 0 1 1

8.6 HIRING / OUT-SOURCING OF HEMM

8.6.1 SCOPE OF WORK FOR HIRING / OUT-SOURCING AGENCY

The scope of work by hiring/outsourcing of HEMM shall include blast hole drilling, earth work excavation, loading, transportation, dumping, dozing, construction of haul road, leveling at dumping sites, water spraying and land reclamation etc. as per guidelines of the project authorities highlighted in this project report or otherwise to suit the local conditions. All statutory rules, regulations and applicable laws are to be followed including those related to government licenses, workmen compensation, insurances etc.

Excavated materials shall have to be dumped at sites, which will be shown by project authorities from time to time in accordance with dump plan of this report. Haul road has to be maintained with the requisite gradient as per regulation and in accordance with the conditions imposed by DGMS in its permission under regulation 98(1) and (3) and other relevant provisions of Coal Mines Regulations, 2017.

8.7 DRILLING & BLASTING

The degree of fragmentation in opencast mine has to be optimised so that total cost of drilling, blasting, excavating, transport and crushing as a total system is minimised. In OB, powder factor of 1.70 m3/kg has been considered. Powder factor of 7 t/kg has been considered in coal. It is recommended that blasting parameters shall be optimised from time to time depending upon local site conditions at the time of actual operations.

Page - 34 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

9.0 COAL QUALITY

Seam-wise coal quality has been calculated considering GCV of boreholes within the quarry separately for Gondegaon & Ghatrohan quarry and the weighted average GCV without any dilution are tabulated below :-

SEAMWISE COAL QUALITY WITHOUT DILUTION Gondegaon OC Ghatrohan OC Seam Combined Seam Combined Section- Effective Seam-wise Effective Section-wise Seam-wise Seams wise thickness Weighted thickness Weighted Weighted Weighted (m) Av. GCV (m) Av. GCV Av. GCV Av. GCV (kCal/kg) (kCal/kg) (kCal/kg) (kCal/kg) V 8.02 4305 4305 7.21 4528 4528 IV-TOP 3.37 4567 3.10 4314 4790 4709 IV BOTTOM 6.77 4894 5.09 4902 III-TOP 1.58 5033 5659 5713 III BOTTOM 3.43 5761 3.07 5713 II-TOP 2.36 5598 1.85 5598 5596 5661 II BOTTOM 2.28 5592 2.63 5707

Due to multi seam sections and partings, there is possibility of quality deterioration during mining and therefore 10% dilution of coal has been considered in this Mining Plan to arrive at the quality of extracted coal. Seam- wise and quarry wise coal quality considering 10% dilution in proposed Mining Plan of Gondegaon Extension Opencast Project are tabulated below :

SEAMWISE COAL QUALITY WITH 10% DILUTION Gondegaon OC Ghatrohan OC Seam-wise Seam-wise Seams Weighted GCV Weighted GCV Average GCV Band Average GCV Band (kCal/kg) (kCal/kg) V 4200 G-11 4406 G-10 IV-TOP 4540 G-10 4406 G-10 IV BOTTOM III-TOP 4989 G-8 5364 G-7 III BOTTOM II-TOP 5150 G-8 5179 G-8 II BOTTOM

Page - 35 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

9.1 PROJECTED COAL QUALITY

The RPR of Amalgamated Gondegaon Ghatrohan OC mine was discussed in the meeting of Technical Sub-Committee of WCL Board held on 07.03.2018 at WCL (HQ), Nagpur. In the meeting, it was discussed that there is wide difference in the quality of upper set of coal seams (Seam-V and IV) and lower set of coal seams (Seam-III & II) in Gondegaon Extension Opencast Project which is Amalgamated Gondegaon Ghatrohan OC mine. Finally, it was decided that separate coal stocks and dispatch arrangement for inferior quality coal of Seam-V and IV and better quality coal of Seam-III & II will be maintained in the mine and accordingly, sale price of both type of coal will be considered separately as per their corresponding year-wise quantity .

Based on the above decision, year-wise quantity of coal of upper set of seams (V & IV) and lower set of seams (III & II) alonwith corresponding quality of coal have been estimated separately. GCV of coal extracted from Seam-V and IV will fall in G-10 band while coal extracted from Seam-III and II will be border line of G-7 & G-8.

10.0 PROVISION OF PUMPS, PIPES AND PIPE FITTINGS

Pumping system has been designed for the volume of water accumulated in the mine at the target plus five year production considering maximum rainfall in a day as 190mm.

Peak pumping capacity worked out as 327389 m3. Above volume of water will be dewatered in 5 days at the rate of 20 hrs pumping per day. Pumping capacity per day thus worked out as 65478 m3.

10.1 COAL HANDLING ARRANGEMENT

Presently, there are two streams (CHP – I & CHP –II ) in existing Gondegaon Ghatrohan OC mine, wherein coal is crushed by feeder breakers and discharged on to 1200 mm wide conveyors and thereafter to a fixed grizzly which in turn discharges coal on to 60t capacity overhead hoppers. One additional mobile crusher was proposed to be operated departmentally. This mobile crusher has not been procured till date. Extra manpower has been Page - 36 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019) provided for this departmental mobile crusher. One (1 no.) additional mobile crusher on hiring basis has been considered in this Mining Plan to cater the crushing requirement. One number of 100te electronic weigh bridge has also been provided for handling extra work load.

12.0 WORKSHOP

HEMM deployed by hiring of equipment shall be maintained by contractor. For Departmental equipment, an independent full fledge unit excavation workshop has been envisaged for the project. Proposed workshop will consist of two types of maintenance and repair shops. These maintenance and repair shops will be as follows :

(a) Excavation Workshop

This workshop would extend basic engineering support in respect of maintenance and repair of various departmental HEMM Deployed in the mine. Capital repair of HEMM and other equipment would be carried out at central workshop, Tadali.

(b) E & M Workshop

Separate E & M workshop facilities have also been provided to carry out maintenance and repair of the CHP, equipment , pumps, Light Vehicles, electricals etc.,

13.0 POWER SUPPLY

13.1 SOURCE OF POWER

Gondegaon OC project is at present receiving power at 33 kV by means of an overhead feeder from Khaparkera substation of MSEDCL. An alternate 33 kV feeder has also been drawn to the project substation from Mansar substation of MSEDCL, which act as a standby feeder in case of failure of Khaparkhera feeder. The projected maximum demand for the Expansion of Gondegaon Extension OC mine (including residential colony) is 5962 kVA.

No additional quarters have been proposed in the proposed Mining Plan. Power to township shall continue to be drawn from the project main substation. At present project main substation is having two 33 kV / 3.3 kV

Page - 37 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019) main transformers having capacity of 2.5 MVA each. In view of the increase in projected maximum demand, it is proposed to install an additional 33 kV /3.3 kV transformer of capacity 5 MVA. This enhanced capacity of substation will cater the load of pumping and CHP of proposed mine

The Salient features of the Electrical Parameters in proposed Mining Plan of Expansion of Gondegaon Extension Opencast Project are detailed below :

13.2 SALIENT FEATURES OF THE ELECTRICAL PARAMETERS

Sl. No. Item Head Particulars 1 Projected Maximum Demand A) Only Mine 5412 kVA B) Only Township 550 kVA C) Total 5962 kVA 2 Specific Energy Consumption A) With Respect To OB Production nil B) With Respect To Coal Production 0.86 kWh/t C) With Respect To Common Load 3.41 kWh/t D) With Respect To Total Load 4.28 kWh/t 3 Specific Power Cost 40.08 Rs./t 4 Fixed Percentage Of Power Cost 61.43 % 5 Variable Percentage Of Power Cost 38.57 % 6 Average Cost Of Purchased Power 9.37 Rs./kWh

14.0 CIVIL CONSTRUCTION

14.1 The estimated balance life of Gondegaon Extension Opencast Project is 6 years as on 01.04.2019 and there is scope of future expansion in dip side, as such all civil works have been envisaged on permanent specifications. It should be ensured that all the service & residential buildings are constructed on non-coal bearing area. The topsoil in this region is predominantly black cotton. Hence provision in the estimate has been made for poor/black cotton soil, safeguarding against the settlement of foundations. Therefore, it is suggested that before undertaking detailed engineering and construction work, geo-engineering investigations of soil should be done.

Page - 38 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

14.2 SERVICE BUILDINGS

Keeping in view the needs and requirements of this mine, provision for service buildings such as office & stores, first aid centre and other buildings have been provided. As per requirement of project authorities, provision for Managers Office, renovation of excavation office & Sub-area Manager Office, Hard Stand for dumpers etc. have been provided.

It should be ensured that all the Service buildings are constructed on non-coal bearing area.

14.3 RESIDENTIAL BUILDING

Total manpower proposed for this project is 921 However, considering the availability of 340 nos. of existing houses in the neighborhood, no provision for Residential buildings has been envisaged except for 1.80 km boundary wall for existing colony.

14.4 ROADS AND CULVERTS

Colony Roads and Culverts

As there is no new colony, hence no colony roads are provided.

Haul Roads & Culverts

Transportation of part of total OB is proposed to be done by Hiring of HEMM & provision of 4.00 km haul road has been kept as per 60T Dumper specification.

Service Roads & Culverts

For approaching different Service Buildings, 0.50 km additional road is needed & provisions have been made .

Diversion and Strengthening of Road

Diversion of 2.50 km of existing village cart roads have been envisaged in this Mining Plan.

Page - 39 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019) Further provision of 2.50 km of surface road has been kept in order to take care of diversions in the existing surface roads because of re-alignment of surface dumps.

As per requirement of project authorities, further provision for Public Road fly- over for dumper crossing have been provided near Ghatrohan village .

14.5 WATER SUPPLY AND SEWERAGE

No additional residential quarters have been provided in this Mining Plan and therefore there is no provision for colony water supply and sewerage.

15.0 SAFETY & CONSERVATION

The project report has been drawn in conformity with the prevailing statutory provisions applicable for safety in Opencast Mines. However following matters related to safety during opencast operations have to be given special considerations.

15.1 PRECAUTIONS AGAINST SURFACE WATER

Ghatrohan Sub-quarry is at 100 m distance from Kanhan river and a part of quarry falls below HFL. The HFL of Gondegaon & Ghatrohan Opencast block is 279.035 m recorded on 7th Sept.1994 by Inder Colliery Survey Office. Since there is a danger of flood water from Kanhan river to proposed quarry, a flood protection embankment has been proposed. The proposed embankment is 30m wide at the top and of height 6m above HFL. As per prevailing practice, proposed embankment has to be constructed by spreading the suitable soil i.e. fine grained soil for Hearting zone and coarse grained soil for casing zone in continuous layers and compacted by mechanical means i.e. by rollers to standard optimum dry density at optimum moisture content. Also it has been proposed to provide 300 mm thick boulders pitching on water side of embankment upto HFL. However for portion of embankment where the surface level is higher than the HFL, no pitching has been envisaged.

Page - 40 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019) However before adoption of this section it is suggested that the proposed embankment section may be got approved by competent authority like Maharashtra Irrigation department of Govt. of Maharashtra and DGMS for its structural safety and stability. The alignment of the proposed embankment is shown in Quarry Layout Plan. It is also suggested to determine withdrawal level/Danger mark, so that as water level crosses the limit, workings shall be stopped.

Suitable alarms connected to float in Kanhan river would be provided at strategic places like Time Keeper Office, Security Office, Safety Office, Manager Residence, Pit Office etc. The floats in the river would activate the alarms as soon as the water level in the river crosses the danger mark. Suitable action can then be taken to investigate the alarm and take other suitable precautions. In addition, river side patrolling would also be carried out during monsoon to caution the project authority in case of any sudden rise in the river. Adequate wireless communication sets have been provided for the above purpose. The rain water falling within the project area would be diverted from the quarry area by providing garland drains and shall be collected towards low lying area.

15.2 DUST SUPPRESSION

For suppression of dust water sprinkler has been provided. Suppression of mine dust may be done by using package bond & dust bond, for methodology of application DGMS Circular No.8 of 1997 may be referred.

15.3 FIRE & SPONTANEOUS HEATING

Wild or herbaceous plants shall be removed from the mine. No person shall deposit heated material or ashes on any opencast working. Also no person shall light a fire or permit a fire to be lighted in any OC working except by the permission in writing of the Manager and only for a special purpose specified therein. No coal shall be left exposed in coal benches more than its incubation period to avoid fire in seam due to spontaneous heating. Proper type of the extinguisher to be kept in each HEMM ready for use in case of emergency. One Fire Fighting Truck has been provided in this report. Page - 41 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

In coal stock, coal shall be despatched on the basis of first in first out.

15.4 SLOPE STABILITY

It is suggested that following action may be taken to deal with slope stability problem.

i) Vulnerable area may be identified and marked on quarry plan.

ii) Observation of actual alignment of fault, its throw, joints, etc. may be recorded during the process of exploitation.

iii) Water drainage system may be properly implemented to prevent accumulation of water in cracks. Also dumps shall be leveled to prevent accumulation of water over it. Proper drainage in dumps shall be also provided to prevent erosion of toe of dump.

iv) Regular monitoring of tension cracks, horizontal and vertical movement of strata in critical area may be done.

v) Rise side slope to be reinforced if required because it has to stand throughout quarry life. No dumps/surface structures to be located within 15m of quarry edge as it will act as surcharge there by destabilizing the slope.

vi) No undercutting of slopes to be done.

vii) Proper hydrogeological studies to be done if water table is at level of slope it should be brought down by using submersible pumps to prevent hydrostatic pressure.

viii) Proper selection of site for dumping to be done and place shall be made free from loose material. Dumping shall not be done at an angle more than angle of repose of material being dumped.

ix) After completion of dumping operations, dumps to be stabilized by growing vegetation.

x) Every person deployed by leaser of HEMM must be trained & briefed about aspects related to slope stability.

Page - 42 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

15.5 HAUL ROAD MAINTENANCE

Adequate care must be taken for proper construction and maintenance of haul road as per the existing guidelines. The gradient of haul road should not be steeper than 1 in 16.

15.6 BLASTING OPERATIONS

As explosives are required in bulk for blasting in OC mines, provision of regulation should be ensured. All blasting operations shall be carried out in day light. Suitable precautions shall be taken as per statute before and after blasting operations. Controlled blasting technique has to be practised to minimise fly off rocks and ground vibrations and keep them within safe limits . In order to keep the ground vibrations within the permissible limit, to avoid flying of rock fragments and also to achieve satisfactory blasting results, optimized drilling / blasting parameters depending upon rock formation using combination of relays / delays will have to be evolved. It is further recommended that at the time of actual execution, proper study for controlled blasting and ground vibration is done with scientific body in order to evolve site specific charge distance relationship.

15.7 SCIENTIFIC STUDIES

Following areas have been identified in the proposed mine for detailed scientific studies:

a) Slope Stability

It is proposed to carry out scientific study on slope stability of external and internal OB dumps as well as for final slope of quarry batter. Based on the findings of scientific research the proposed slope of dumps and batter in the report may change.

b) Drilling & Blasting

For optimum fragmentation of rock and coal to minimize the overall cost of excavation, it is proposed in this report to engage some scientific body to carry out research for optimum drilling and blasting. Accordingly, the powder factor suggested after this study will be followed in the proposed mine. Page - 43 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

c) Hydrogeology

Proper provision has been made in this report for scientific study to assess the hydrogeological parameters of the proposed area.

In addition to this, various other parameters like, soil testing, etc. need scientific study.

15.8 SAFETY ASPECTS FOR OUTSOURCING/HIRING OF HEMM

Special precaution should be taken while deploying workers in the mine. Before employing any labour to the mine, proper vocational training should be imparted and recommendations of Safety Conference should be strictly followed. Terms and conditions shall be fixed by management for deployment of labours by leaser of HEMM as well as machineries. Some of the major aspects are as follows:

A) For persons :

i) No persons shall be deployed unless he is trained at VTC ii) Records in Form-B & Form-D shall be maintained.

iii) Records of Vocational Training Certificate and driving licence of operators shall be kept by HEMM outsourcing agency and shall be made readily available for inspection by management.

iv) Salaries shall be distributed in front of management representative.

v) No person shall be employed unless person holds VTC certificate and Management is informed. A record of it shall be maintained.

vi) Adequate supervision shall be maintained by qualified competent persons.

B) For Machineries :

i) All the machineries to be deployed in mines should be checked before deployment. Regular checking of m/c deployed by leaser of HEMM shall be done. No unfit m/c shall be deployed before the defect is rectified.

Page - 44 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019) ii) A proper record of repair and maintenance alongwith inspection done by management and defect pointed out shall be maintained and signed by authorised person.

iii) The trucks deployed by leaser of HEMM shall be provided with Audio visual alarms, proper light for use at night and period when natural light is not sufficient. Also audio visual alarms for reversing on trucks shall be provided.

Other precautions for machines

i) RTO certificate photo copies of all vehicles shall be submitted to management.

ii) Daily welding, monitoring, inspection shall be done by the HEMM outsourcing agencies mechanic as directed by management.

iii) Machine manufacturers should be asked to give risk analysis.

iv) Suitable type of the fire extinguishers shall be provided in every machines.

C) General :

i) No person/vehicle shall be deployed at any place other than authorised place.

ii) All workers should obey lawful instruction of mine management.

iii) Risk Management Plan of tipper/pay loader shall be made and implemented.

iv) All drivers shall obey systematic traffic rules prepared by management.

v) Before deploying workers they must be trained and briefed about safety aspects in opencast mine. .

16.0 ENVIRONMENTAL MANAGEMENT

The Ministry of Environment, Forest and Climate Change vide letter dated 14th March, 2018 granted Environmental Clearance to the expansion of Gondegaon Extension Opencast Mining Project from 2.50 MTPA to 3.50 MTPA in area of 917 ha (mine leasehold area 845.74 ha) for a period of one

Page - 45 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019) year subject to compliance of certain terms & conditions and environmental safeguards. Later on, the Ministry of Environment, Forest and Climate Change vide letter no. J-11015/106/2009-IA.II(M) dated 28.03.2019 accorded approval for continuance of Gondegaon Extension Opencast Mining Project from 2.50 MTPA to 3.50 MTPA in area of 917 ha (mine leasehold area 845.74 ha) for a further period of one year.

The RPR for Amalgamated Inder-Kamptee Deep OC was approved by WCL Board in September, 2018 in which 54.34 ha land was proposed to be transferred from neighbouring Gondegaon-Ghatrohan OC. Accordingly, EC application for amendment in EC of Expansion of Kamptee Deep OC for a capacity of 3.20 MTPA within a mine lease area of 857.60 ha was discussed in EAC in its 46th meeting held on 25.06.2019. The EAC, after deliberation observed that the proposed amalgamation involves carving out some area of adjoining Gondegaon Opencast coal mining project and thus requiring amendment in its environmental clearance also. There being no proposal in this regard, the committee was not inclined to take the proposal forward.

The likely impact of Expansion of Gondegaon Extension Opencast project on the environment and various mitigation measures are detailed below :

16.1 AIR QUALITY MANAGEMENT

Air pollution is likely to be generated due to dust, exhaust from vehicles, blasting fumes etc. In opencast mines, dust is likely to be produced during blasting, crushing of coal, handling of overburden and coal, drilling and operation of HEMM. The following measures have been proposed to control air pollution :

i) Water spraying is to be carried out on haul road at regular interval during each shift.

ii) Water spraying arrangement at dust generating points in CHP, feeder breaker, conveyor transfer points etc.

iii) Proper maintenance of all internal combustion engines to reduce smoke and exhaust fumes.

Page - 46 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

iv) Dust extractors in working condition in all the drills.

v) Tree plantation in rows and blocks along the approach road of the mine and also along the coal transportation road on both sides.

vi) Perimeter tipping of external overburden dumps. Tree plantation on the slope of the perimeter dump.

vii) Water spraying mixed with safe and non-toxic dust suppression chemicals on haul roads during dry months.

viii) Coal transportation in trucks covered with tarpaulin.

ix) Avoiding overloading of trucks.

x) Frequent cleaning of coal transportation road.

xi) In order to replace, transportation of coal by road, construction of pipe conveyor system is in progress for carrying coal from the mine head to Koradi TPS.

16.2 WATER QUALITY MANAGEMENT

The quantity of mine water pumped out would vary according to the season. The mine water may contain various impurities like coal dust, traces of grease, oil etc. in various proportions. The mine water would be allowed to collect in the quarry sump where primary settling would take place. The mine water would then be pumped into secondary settling tanks on the surface.

Here the water would be allowed to settle and thereafter part of treated water will be utilized for meeting in -house water requirement (like dust suppression, watering of plants, washing of HEMM, potable use etc). Peripheral trenching is recommended near external OB dumps for coursing the run-off and leached water from the dumps. If required, the water may be sent to surface settling tanks before discharging it into the drainage channels.

The used water from the industrial area comprising CHP, Workshop, Garage etc. may be contaminated with grease, oil, coal dust, dirt etc. This water will

Page - 47 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019) be allowed to settle and suitable treatment will be carried out in oil and grease trap. Thereafter the treated water will be mostly recycled.

16.3 GROUND WATER MANAGEMENT

Due to proposed project, it is anticipated that the effect on ground water regime will be pronounced upto around 500 m from mine edge and effect will be pronounced in the down-dip side and milder in the up-dip side. But this effect will be temporary in nature and once the project is over, after 2 – 3 rains, the regime will regain its almost original status. Any shortage of water in the affected villages during the temporary period will be supplemented through supply of treated water pumped out from the mine.

16.4 NOISE AND GROUND VIBRATION MANAGEMENT

Existing noise level at the mine site (wrt pre-mining level) is likely to increase and following measures are being suggested to reduce noise and ground vibration effects:

i) With judicious use of explosives and correct blasting techniques, ground vibration and noise pollution would be reduced.

ii) Structures prone to vibration or those with moving parts are suggested to be inspected periodically and source of vibration should be damped to minimize noise and vibration.

iii) Proper maintenance of HEMM and exhaust silencers.

iv) Vegetation barrier around the service buildings will act as effective acoustic barrier.

v) Ground vibration and fly rock can be controlled by proper use of delay detonators. This will help to reduce the noise pollution.

16.5 FLORA AND FAUNA MANAGEMENT

No Changes in the diversity of species or number of any species of animal and no reduction in the number of any unique, rare or endangered species of animals are anticipated. Any deterioration to existing fish or wild life habitat

Page - 48 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019) due to mining is ruled out. Similarly, no changes in the diversity of species or number of any species of plants and also no reduction of the number of unique, rare or endangered species of plants are anticipated.

Adequate plantation has been proposed with native species to maintain the diversity and also to attract the fauna.

16.6 LAND RESOURCE MANAGEMENT

Break-up of total 791.40 ha land during mining for various land use in proposed Expansion of Gondegaon Extension Opencast mine is tabulated below :

Sl. No. Land Use Area (Ha) 1. Quarry Area 277.13 2. Embankment Area 13.05 3. External OB dump 252.25 4. Infrastructure 57.26 5. Roads 5.74 6. Project Township 13.00 7. Rehabilitation Site 21.66 8. Area needed for rationalization and blasting zone 151.31 Total Land 791.40

Note:- 21.66 ha land for rehabilitation of Gondegaon Village is outside ML area.

Regarding land use during mining, in addition to excavation of quarry for coal, overburden dump will be created along with development of other mine related infrastructures. Overburden dump is proposed to be technically and biologically reclaimed and sufficient greenery will be developed. Table : Stage Wise Land Use Plan

Present 3 years after 4th S.N. Land use category (1st 6th year end of mine year year) life Backfilled Area (Reclaimed 0 20 79 79 1 with plantation) 0 0 0 40

Page - 49 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

Present 3 years after 4th S.N. Land use category (1st 6th year end of mine year year) life Excavated Area (Not 2 146.98 166.98 198.13 198.13 reclaimed)/void External OB dump 163.07 232.03 232.03 252.25 3 (Reclaimed with plantation) 28 30 40 40

Top soil dump ((Reclaimed 20.22 20.22 20.22 0 4 with plantation) 0 0 0 0

Undisturbed area (brought 367.67 254.46 164.31 164.31 5 under plantation) 96 100 120 130

5.74 5.74 5.74 5.74 6 Roads (avenue plantation) 1.00 1.00 1.00 1.00 Area around buildings and 57.26 57.26 57.26 57.26 7 Infrastructures 24.20 24.20 24.20 24.20 8.80 13.05 13.05 13.05 8 Embankment 8.00 8.00 8.00 8.00 Rehabilitation (Land 21.66 21.66 21.66 21.66 9 Outside ML Boundary) 12.44 12.44 12.44 12.44 Total 791.40 791.40 791.40 791.40 (Plantation) 169.64 175.64 205.64 255.64

Table : Post Mining Land Use Plan

Land use (ha) Sl. Land use during No. mining Water Public Plantation Undisturbed Total Body use External OB 1 40.00 0.00 0.00 0.00 252.25 Dump 2 Excavation 40.00 237.13 0.00 0.00 277.13

3 Roads 1.00 0.00 4.74 0.00 5.74 4 Built up area 44.64 0.00 47.33 0.00 91.97 5 Undisturbed Area 130.00 0 0 16.92 164.31

Total 255.64 237.13 52.07 16.92 791.40

16.7 ENVIRONMENT MANAGEMENT SYSTEM

To have a close watch on the environmental condition and implementation of various measures suggested, a multi- disciplinary approach is essential. At

Page - 50 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019) present WCL headquarter acts as apex body which supervises the activities relating to environment at project level through the General Manager. General Manager of the area coordinates the activities of various disciplines in the area to render all necessary assistance at the implementing level i.e. the project. Area Nodal Officer (Environment) monitors all aspects of environment on behalf of the General Manager. He also takes suitable steps for generation of environment data along-with its analysis and interpretations. As far as plantation is concerned horticulturist with suitable backup staff is provided in the area for undertaking the plantation jobs including raising of a nursery. Sub-Area Manager is responsible for mechanical reclamation of the area. He is also responsible for biological reclamation with assistance of GM’s office. Others External Backfilled (undisturbed Total Dump area year area/etc.) No. No. Area Area Area No. of Area No. of of of (ha) (ha) (ha) trees (ha) trees trees trees 1st 28 70 0 0 141.64 354.1 169.64 424.1 year 4th 30 75 0 0 145.64 364.1 175.64 439.1 year 6th 40 100 0 0 165.64 414.1 205.64 514.1 year 3 years after 40 100 40 100 175.64 439.1 255.64 639.1 end of mining

17.0 LAND AND REHABILITATION

17.1 LAND REQUIREMENT

There is no forest land involved in this project. In the approved RPR for Gondegaon-Ghatrohan OC mine (March,2018) 845.74 ha land was proposed including 21.66 ha land for rehabilitation site for Gondegaon village. Out of 845.74 ha land, 54.34 ha land is proposed to be transferred to neighbouring Amalgamated Inder- Kamptee Deep OC mine. Hence, the total land for the project purpose (mine lease Area) as envisaged in this Mining Plan for Expansion of Gondegaon Extension Opencast mine works out to 791.40 ha. Out of 791.40 ha land, 760.09 ha land has already been acquired and balance

Page - 51 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019) 31.31 ha land has to be acquired. The above details have been outlined on the basis of information available from the mine.

The details of land in possession & balance requirement of land for proposed Mining Plan for Expansion of Gondegaon Extension Opencast Project is as follows:

Sl. Mode of Type Land (Ha) Balance Total No. Acquisition of under Land to be land (ha) land physical acquired possession (Ha) 1 2 3 4 5 6 (4+5) A) LA Act 1 Tenancy Land 366.54 366.54

2 Govt. Land 18.05 18.05

Sub Total (A) 384.59 384.59

B) LA Act Lapsed (Direct purchase) 1 Tenancy Land 119.87 119.87

2 Govt. Land 19.42 19.42

Sub Total (B) 139.29 139.29 C) CBA Act 1 Tenancy Land 370.53 17.05 387.58

2 Govt. Land 16.12 16.12

Sub Total (C) 386.65 403.70

D) Direct Tenancy Land 46.76 2.42+5.71 54.89 Purchase =8.13 E) Gondegaon Tenancy Land 6.13 6.13 Gaothan F) Sub Total (A+B+C+D+E) 957.29 988.60

G) Transfer Land to Inder OCM 142.86 142.86

H) Land to be transferred to 54.34 54.34 Amalgamated Inder Kamptee Deep OC I Balance land in proposed Mining 760.09 31.31 791.40 Plan (F-G-H)

Page - 52 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019) From above table, it is clear that there is no forest land involved in this project. In the approved RPR for Gondegaon-Ghatrohan OC mine (March,2018) 845.74 ha land was proposed including 21.66 ha land for rehabilitation site for Gondegaon village. Out of 845.74 ha land, 54.34 ha land is proposed to be transferred to neighbouring Amalgamated Inder- Kamptee Deep OC mine. Hence, the total land for the proposed Mining Plan for Expansion of Gondegaon Extension Opencast mine works out to 791.40 ha. Out of 791.40 ha land, 760.09 ha land has already been acquired and balance 31.31 ha land has to be acquired. The above details have been outlined on the basis of information available from the mine.

Thus, the amendment in EC in respect of Expansion of Gondegaon Extension OC Project will be solicited for change in mine lease area from 845.74 ha (existing EC dated 28.03.2019) to 791.40 ha as detailed out above. There will not be any change in the production capacity as well as change in mine configuration.

17.1 LAND USE

Break-up of total 791.40 ha land during mining for various land use in proposed Expansion of Gondegaon Extension Opencast mine is tabulated below : Sl. No. Land Use Area (Ha) 1. Quarry Area 277.13 2. Embankment Area 13.05 3. External OB dump 252.25 4. Infrastructure 57.26 5. Roads 5.74 6. Project Township 13.00 7. Rehabilitation Site 21.66 8. Area needed for rationalization and blasting zone 151.31 Total Land 791.40

Note:- 21.66 ha land for rehabilitation of Gondegaon Village is outside ML area.

Page - 53 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

18.0 MINE CLOSURE PLANNING

18.1 Mine closure planning has to be carried out at the starting of the mine and needs periodic reviewing and revision during its life cycle to cope with the geo-technical constraints, safety and economic risks, social & environmental challenges. For the Mine Closure activities, a corpus fund is created by opening an escrow account with the coal controller organization in nationalised bank. For opencast mine, an amount @ Rs 6.00 lakhs per Ha of the project area and for underground mine, an amount @ Rs 1.00 lakhs per Ha of the project area is required to be deposited in this account for final mine closure. Progressive mine closure is done with the fund provided in approved report. The above rate has been adopted as per Circular No. 55011-01- 2009-CPAM, GOI, Ministry of Coal, dated 27 August 2009.

In the approved RPR for Gondegaon-Ghatrohan OC mine (March, 2018) 845.74 ha land was proposed including 21.66 ha land for rehabilitation site for Gondegaon village. Out of 845.74 ha land, 54.34 ha land is proposed to be transferred to neighbouring Amalgamated Inder- Kamptee Deep OC mine. Hence, the total land involved as project area envisaged in this Mining Plan for Expansion of Gondegaon Extension Opencast mine works out to 791.40 ha. In the proposed Mining Plan, including 21.66 ha land for rehabilitation of Gondegaon village. As per recent practice, land for rehabilitation of village is not considered for calculation of mine closure cost. Hence, in this Mining Plan, the total corpus of closure cost has been worked out for 769.74 ha land and balance life of 6 years as on 01.04.2019 after making adjustment for the corpus fund already deposited in the Escrow account of existing Gondegaon OC/ Gondegaon-Ghatrohan OC mine during the period from 2013-14 to 2018- 19.

The total amount deposited in the Escrow A/c against Mine Closure for existing Gondegaon OC/ Gondegaon-Ghatrohan OC mine upto 2018-19 is tabulated below :-

Page - 54 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

Year Amount Deposited in Escrow A/c upto 2018-19 (Rs. In Lakhs) 2013-14 1482.84 2014-15 595.28 2015-16 255.02 2016-17 437.33 2017-18 504.58 2018-19 529.81 Total 3804.86

The detailed calculation of the corpus fund as well as annual corpus amount for the proposed mining plan for Expansion of Gondegaon Extension OC mine has been worked out and the details are tabulated below. The corpus amount already deposited in the Escrow A/c upto 2018-19 has been deducted to arrive the mine closure cost for this mining plan for Expansion of Gondegaon Extension OC mine. The annual corpus is to be deposited in the escrow account in 2019-20 (1st year of the Mining Plan) and in subsequent years with 5% escalation.

Sl. Details No. 1 WPI for All Commodities for Aug 2009 (New Series) 83.02 2 WPI for All Commodities for June, 2019 (New Series) 121.50 3 Ratio of WPI =(2) / (1) 1.46350277 4 Total land area requirement for the project (ha) = 769.74 5 Mine closure cost @ Rs 6 lacs/ha (Rs in Lakhs) = 4618.44 Mine closure cost after indexing from Aug'09 to 6 6759.10 June`2019 (Rs. In Lakhs) = (5) x (3) = Amount already deposited by existing Gondegaon 7 /Gondegaon –Ghatrohan OC mine up to 31.03.2019 3804.86 (Rs in Lakhs) Net Mine closure cost as on 2019-20 after adjusting 8 the closure amount deposited upto 2018-19 2954.24 (Rs in Lakhs) (6 - 7)

Page - 55 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

Sl. Details No. Life of Expansion of Gondegaon Extension OC mine in 9 6 years starting from 1st year (2019-20) Annual Contribution to Escrow fund as on 2019-20 (Rs. 10 492.37 In Lakhs) = (8)/(9)

The annual Mine Closure Cost with 5% escalation and schedule of deposit from FY 2019-20 in subsequent years is tabulated below:

Amounts Schedule of Deposit Sl.No. Financial Year (Rs. Lakhs) (Rs. Lakhs) 1 2019-20 492.37 492.37

2 2020-21 516.99 516.99 3 2021-22 542.84 542.84 4 2022-23 569.98 569.98 5 2023-24 598.48 598.48

6 2024-25 628.40 628.40

3349.06 3349.06

18.5 BREAK-UP OF CLOSURE FUND FOR VARIOUS CLOSURE ACTIVITIES

Total Corpus Fund= Rs. 3804.86 lakhs + Rs. 3349.06 Lakhs = Rs. 7153.92 Lakhs

Activity wise Break-up of Closure Cost

% of Total Amount Sl. Mine Remarks Activity (Rs in No. Closure Lakhs) Cost A Dismantling of structures Service Building 0.2 14.31 To be included in final Residential Building 2.67 191.01 mine closure plan. Industrial Structures like, Workshop, Field 0.3 21.46 substation, etc. B Permanent Fencing of mine void and To be included in final other dangerous area mine closure plan. Random rubble masonry of height 1.2 1.5 107.31 meter including leveling up in cement concrete 1:6:12 in mud mortar C Grading of highwall slopes To be included in final Levelling and grading of highwall slopes 1.77 126.62 mine closure plan. D OB Dump Reclamation Handling/Dozing of OB Dump into mine 88.66 6342.67 71% for progressive void and preparation of Internal dump for and 17.66% for final reclamation. mine closure.

Page - 56 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

% of Total Amount Sl. Mine Activity (Rs in Remarks No. Closure Lakhs) Cost Technical and Bio-reclamation including 0.4 28.62 Equal Weightage plantation and post care. through-out the life of the mine. E Landscaping Landscaping of the open space in 0.3 21.46 Equal Weightage leasehold area for improving its aesthetic through-out the life of and eco value. the mine. F Plantation Plantation over cleared area obtained after 35.77 To be included in final dismantling. 0.5 mine closure plan. Plantation around the quarry area and in 0.2 14.31 Equal Weightage safety zone. through-out the life of the mine. Plantation over the external OB Dump 0.02 1.431 Equal Weightage through-out the life of the mine. G Post Closure Env Monitoring/Testing of For three years after

Parameters for three years. mine closure Air Quality 0.22 15.74 Water Quality 0.2 14.31 H Entrepreneurship development 0.26 18.60 Equal Weightage (vocational/ skill development) Training through-out the life of for sustainable income of affected the mine. people. I Miscellaneous and other mitigative 143.08 Equal Weightage measures. 2 through-out the life of the mine. J Post Closure Man power cost for 0.8 57.23 To be included in final supervision mine closure plan. TOTAL 100% 7153.92

1. Mining is to be carried out in a phased manner initiating afforestation / reclamation work in the mined out area of first phase while commencing mining in the 2nd phase.

2. Upto 80% of the total deposited amount including interest accrued in the ECSROW account may be released after every 5 years. The amount released should be equal to expenditure incurred on Progressive Mine closure in past 5 years or 80% whichever is less.

3. The above cost / expenditure will be met from the corpus fund deposited in the escrow account by the mine operator. However, the additional amount beyond the escrow account will be provided by the mine

Page - 57 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019) operator after estimating the final mine closure cost (as per the mine closure guideline). 4. The amount indicated separately under each head in the above table is indicative only and based on actual expenditure the amount may change.

19.0 MANPOWER & PRODUCTIVITY

19.1 Manpower

The manpower requirement for proposed Mining Plan for Expansion of Gondegaon Extension Opencast project has been summarised as follows:

Sl. No. Particulars Nos. 1. Executives 40 2. Non-executives: i) Monthly rated staff 183 ii) Daily rated staff 698 3. Total 921

The manpower on the basis of group operation has been indicated in the following table.

Sl. No. Particulars No. i) Coal 184 ii) Overburden 157 iii) Common 577 iv) Reclamation 3 Total 921

19.2 Productivity

The annual capacity of this mine has been rated as 3.50 Mty of coal and 22.85 Mm3 Peak OB. The manpower employed would be 921 and the overall OMS works out to 14.395 t including welfare manpower and 16.655 t excluding welfare manpower.

Page - 58 MINING PLAN

MINING PLAN FOR EXPANSION OF GONDEGAON EXTENSION OC MINE (AUG., 2019)

19.2 CONCLUSION

The Ministry of Environment, Forest and Climate Change vide letter dated 14th March, 2018 granted Environmental Clearance to the expansion of Gondegaon Extension Opencast Mining Project from 2.50 MTPA to 3.50 MTPA in area of 917 ha (mine leasehold area 845.74 ha) for a period of one year subject to compliance of certain terms & conditions and environmental safeguards. Later on, the Ministry of Environment, Forest and Climate Change vide letter no. J-11015/106/2009-IA.II(M) dated 28.03.2019 accorded approval for continuance of Gondegaon Extension Opencast Mining Project from 2.50 MTPA to 3.50 MTPA in area of 917 ha (mine leasehold area 845.74 ha) for a further period of one year.

The RPR for Amalgamated Inder-Kamptee Deep OC was approved by WCL Board in September,2018 in which 54.34 ha land was proposed to be transferred from neioghbouring Gondegaon-Ghatrohan OC. Accordingly, EC application for amendment in EC of Expansion of Kamptee Deep OC (which is neighbouring mine of Gondegaon-Ghatrohan OC) for a capacity of 3.20 MTPA within a mine lease area of 857.60 ha was discussed in EAC in its 46th meeting held on 25.06.2019. The EAC, after deliberation observed that the proposed amalgamation involves carving out some area of adjoining Gondegaon Opencast coal mining project and thus requiring amendment in its environmental clearance also. There being no proposal in this regard, the committee was not inclined to take the proposal forward.

Hence, for applying for amendment in the existing EC of Expansion of Gondegaon Extension OC, Mining plan for a capacity of 3.50 MTPA for mine lease area of 791.40 ha has been prepared for approval from Competent Authority.

****************

Page - 59 MINING PLAN