Minutes of the Wilge Forum Meeting held on 16 November 2010 at Reitz

Attendance Register

Name Company Telephone/Cell E-mail address Number Phillemon DWA 012 392 1352 [email protected] Shibambo N.P Cindi Phumelela 0768847324 Municipality L. Langa DWA 012 392 1379 [email protected]

S. Mporetji Rand Water 0822220987 [email protected]

E.J.V Rensburg Environmental 0825511204 [email protected] Health SM Van Schalkwyk Environmental 058 304 1247 Health TNC Sekhobo TMDM 058 718 1018 Tinghitsi D DWA:IE 0828969005 [email protected]

TJ Mofokeng EHS 0834109696 BB Buthelezi DOH 0747650551 [email protected] LB Sello DOH 0820904808 H.Maringa TMDM 0722335877 P.J De Jager Nketoana 0760182425 Municipality H.S Niemandt Phumelela 071 568 3568 Municipality

DISCUSSION ACTION/FOLLOW UP 1. Welcome Chairperson Mr. Cindi welcomed all the attendees and showed some concerns in terms of attendance as well as the venue and expressed that these issues need to be discussed.

2. Introduction of attendees ALL All attendees introduced themselves

3. Apologies: • T Mphuthi • E Matseba ALL • T Pather • D Mofokeng • P Heiley 4. Minutes of Previous Meeting ALL

Mr. S Mporetji was misspelled as S Mporetjie

5. Acceptance of the Minutes

The minutes were accepted as true reflection of what ALL was discussed during the previous meeting.

6. Matters Arising from the Previous Meeting ALL • None.

7. Additions to the Agenda and Approval of the Agenda

• None.

8. Items for Presentation

There were no items for presentation as there was no Projector. Rand Water will present on the next forum meeting.

9. Water Quality in the Wilge Catchment DWA DWA

• WF has been unacceptable for the past 3 months • Fecal Coliform has not been analyzed for the past 3 months. • Bethlehem WWTW was not complying for the past 6 months.

WWTW that is always complying • sewage works • Reitz sewage works.

Least compliant and of major concern • Bethlehem WWTW • WWTW

Rand Water

• Rand Water presented their water quality status Rand Water report; generally there have not been any changes

of Water Quality for this quarter.

• It was reported that there are four sewage works

that are currently monitored by Rand Water.

• There is good performance with respect to ammonia in Tshiame. • Data for E.coli is missing due to the fact that there have been problems with Rand Water data.

Pollution Incidents DWA • There was a blockage at Qwa Qwa, due to pump failure. The municipality took the pump for repair • There was a manhole blockage in Makwane and it was unblocked within three hours.

Feedback on waste disposal sites • T.Pather sent a feedback on solid waste disposal DWA site. • Ground water monitoring will be enforced next year for all sites (2011). • Warden to apply for a new waste disposal site. There is a site but they need a new one. T. Pather mentioned that they must motivate for a new site. There will be a meeting on Thursday for the proposal.

10 Report back from Stakeholders in the Wilge Catchment

10.1 Phumelela Municipality • It was reported that R890.00 funding was received Phumelela LM from DWA, contractors have been appointed and have started working on pump station no.4.

10.2 Nketoana Municipality • Two pumps have been repaired. Clarifiers cables and motors are working. Nketoana LM • In need of assistance in fat trappings.

10.3 Dihlabeng Municipality Dihlabeng LM No representative.

10.4 Mafube Municipality

• The official mentioned that everything is working Mafube LM very well. • The official mentioned that the Technical Manager will advise when they are going to submit the WULA in the next forum meeting.

10.5 Thabo Mofutsanyane District Municipality TMDM • Everything is working very well in their area, except

for Phumelela Local Municipality.

10.6 MAP Water Map Water No representative.

10.7 DETEA DETEA No representative

10.8 Environmental Health Environmental Health

• Everything is working very well. 11. Water Use License Application Status DWA R.P Shibambo from DWA distributed the Water Use License Status. It was mentioned that two municipalities still need to apply for a WUL (Mafube and Dihlabeng Municipality) 12. Catchment Management Agency (CMA) update/Waste Discharge System DWA

A workshop was held on the 4th and 5th November concerning the CMA’s process. 13. Discussion of Additions to the Agenda ALL

No additions to the Agenda. 14. General ALL

Chairperson raised a concern about poor attendance from stakeholders. 15. Date of the next meeting: Chairperson 15 February 2011 17 May 2011 16 August 2011 15 November 2011 16. Closure chairperson Chairperson thanked all for attending the meeting and closed the meeting at 12h30