Initial Environmental Examination

Document stage: Draft Project Number: 42486-016 August 2018

IND: Urban Services Improvement Program – Subproject of Water Supply Improvement in , Depalpur and Gautampura Towns

Package No: MPUSIP-2A

Prepared by Madhya Pradesh Urban Development Company, Government of Madhya Pradesh for the Asian Development Bank.

This draft initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, management, or staff, and may be preliminary in nature. Your attention is directed to the ‘terms of use’ section on ADB’s website.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

CURRENCY EQUIVALENTS (as on 1 May 2018) Currency Unit - Conversion INR 1.00 = $ 0.015 $ 1.00 = INR 66.00 ABBREVIATIONS

ADB – Asian Development Bank ASO – Assistant Safeguard Officer CFE – Consent for Establishment CFO – Consent for Operation CPCB – Central Pollution Control Board CWRM – Clear Water Rising Main CWS – Clear Water Sump EA – Executing Agency EE – Executive Engineer EHS – Environmental Health &Safety EIA – Environmental Impact Assessment EMP – Environmental Management Plan; GOI – Government of GOMP – Government of Madhya Pradesh HDPE – High Density Poly-ethylene HFL – Highest Flood Level IA – Implementing Agency IEE – Initial Environmental Examination; LPCD – Liters per Capita per Day MFF – Multi-tranche Financing Facility MLD – Million Liters per Day MOEF – Ministry of Environment and Forest MPPCB – Madhya Pradesh Pollution Control Board MPUDC – Madhya Pradesh Urban Development Company NOC – No Objection Certificate OHT – Over Head Tank PMC – Project Management Consultant PHED – Public Health Engineering Department PIU – Project Implementation Unit; PMU – Project Management Unit PO – Project Officer PWD – Public Works Department REA – Rapid Environmental Assessment Checklist RoW – Ri ght of Way RWRM – Raw Water Rising Main SE IAA – State Environmental Impact Assessment Authority SEP Site Environmental Plan SPS – Safeguard Policy Statement,2009 UDHD – Urban Development and Housing Department UDDLB – UrbanDepartment Local Body WTP – Water Treatment Plant WRD – Water Resources Department WSS – Water Supply Scheme

2 Initial Environmental Examination- Package 2A

WEIGHTS AND MEASURES

˚C Degree Celsius km kilometer LPCD Liter per capita per day mm millimeter m meter MLD million liter per day MCM million Cubic Meter Nos number sq.km Square Kilometer

3 Initial Environmental Examination- Package 2A

TABLE OF CONTENTS

I. EXECUTIVE SUMMARY ...... 7 II. INTRODUCTION ...... 13 A. Background ...... 13 B. Purpose of this IEE Report ...... 14 C. Report Structure ...... 15 III. DESCRIPTION OF THE PROJECT ...... 16 A. Project Area ...... 16 B. Existing Water Supply Situation ...... 16 C. Proposed Project ...... 20 IV. POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK ...... 30 A. ADB Policy ...... 30 B. National Environmental Laws ...... 30 V. DESCRIPTION OF THE ENVIRONMENT ...... 34 A. Methodology Used for Baseline Study ...... 34 B. Baseline Environmental Profile ...... 34 C. Subproject Site Environmental Features ...... 46 VI. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES ...... 52 A. Pre-Construction Impacts – Design & Location ...... 52 B. Construction Impacts ...... 70 C. Operation and Maintenance Impacts ...... 71 D. Project benefits ...... 72 VII. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE...... 73 A. Overview ...... 73 B. Public Consultation ...... 73 C. Information Disclosure ...... 84 VIII. GRIEVANCE REDRESS MECHANISM ...... 85 A. Project Specific Grievance Redress Mechanism ...... 85 IX. ENVIRONMENTAL MANAGEMENT PLAN ...... 88 A. Implementation Arrangements ...... 88 B. Environmental Management Plan ...... 88 C. EMP Compliance Responsibilities ...... 107 D. Training Needs ...... 109 E. Monitoring and Reporting ...... 110 F. EMP Implementation Cost ...... 111 X. CONCLUSION AND RECOMMENDATIONS ...... 113

4 Initial Environmental Examination- Package 2A

List of Tables

Table 1: Details of Rising main and Distribution network ...... 16 Table 2: Details of Rising main and Distribution network ...... 18 Table 3: Proposed Water Supply Subproject Components ...... 21 Table 4: Applicable Environmental Regulations ...... 31 Table 5: WHO Ambient Air& Noise Quality Guidelines ...... 33 Table 6: Baseline Environmental Features of the Subproject Towns ...... 35 Table 7: Site Environmental Features – Betma Town ...... 46 Table 8: Site Environmental Features – Gautampura ...... 48 Table 9: Site Environmental Features: Depalpur ...... 50 Table 10:Details of volume with contour height- Anicut Betma ...... 63 Table 11:Details of volume with contour height- Gautampura Anicut ...... 55 Table 12:Source Water Quality ...... 69 Table 13: Summary of Consultations with Stakeolders- Depalpur Nagar Parishad ...... 74 Table 14:Summary of Consultations with Stakeholders- Gautampura Nagar Parishad . 77 Table 15: Summary of Consultations with Stakeholders- Betma Nagar Parishad ...... 80 Table 12: Design Stage Environmental Management Plan ...... 90 Table 13: Pre-Construction State Environmental Management Plan ...... 92 Table 14: Construction Stage Environmental Management Plan ...... 94 Table 15: Operation Stage Environmental Management Plan...... 103 Table 16: Construction Stage Environmental Monitoring Plan ...... 105 Table 17: Operation Stage Environmental Monitoring Plan ...... 106 Table 18: Outline Capacity Building Program on EMP Implementation ...... 109 Table 19: Cost Estimates to Implement the EMP ...... 111

List of Figures

Figure 1: Subproject location ...... 19 Figure 2: Key Plan of Betma Water Supply Scheme ...... 24 Figure 3: Key Plan of Gautampura Water Supply Scheme ...... 25 Figure 4: Schematic drawing of proposed weir on ...... 26 Figure 5: Cross Section of Proposed Intake well of Gautampura WSS ...... 27 Figure 6: Key plan of Depalpur Water Supply Scheme ...... 28 Figure 7: Layout plan and cross section of proposed weir for Depalpur WSS ...... 29 Figure 8: Area & Environs-Betma ...... 43 Figure 9: Subproject area Environs – Depalpur ...... 44 Figure 10: Subproject Environs- Gautampura ...... 45 Figure 11: Google map showing Upstream and Downstream stretch of Gambhir River 64 Figure 12: Map showing Chambal River Sanctuary and Proposed Weir on Chambal Rive ...... 56 Figure 13: Map showing Location of Existing Dams on Chambal River & Chambal Sanctuary ...... 58 Figure 14: Map showing Location of Chambal Sanctuary & Existing / Proposed Dam on Chambal River ...... 58 Figure 15: Map showing Upstream and downstream stretch of Chambal riverError! Bookmark not defi

5 Initial Environmental Examination- Package 2A

Appendix

Appendix 1: REA Checklist ...... 116 Appendix 2: National Ambient Air Quality Standards ...... 131 Appendix 3: Vehicle Exhaust Emission Norms ...... 132 Appendix 4: National Ambient Air Quality Standards in Respect of Noise ...... 133 Appendix 5: Extract From Construction & Demolition Management Rules, 2016 ...... 134 Appendix 6: Salient Features of Major Labor Laws Applicable to Establishments Engaged in Construction of Civil Works ...... 140 Appendix 7: Stakeholder Consultation at Depalpur, Betma and Gautampura Town .... 142 Appendix 7A: Summary of Consultation with Stakeholders-Depalpur ...... 142 Appendix 7A1: Depalpur Stakeholder Consultation Photographs and List of Participant ...... 146 Appendix 7B: Summary of Consultation with Stakeholders-Gautampura ...... 155 Appendix 7B1: Gautampura Stakeholder Consultation Photographs & List of Participants ...... 160 Appendix 7C: Summary of Consultation with Stakeholders-Betma Nagar Parishad .... 172 Appendix 7C1: Betma Stakeholder Consultation Photographs & List of Participants . 176 Appendix 7C2: Press Release about meeting with Ward Parshads on proposed subproject WSS - Betma in the leading newspaper namely Nai Duniya ...... 193 Appendix 8: Data related to Betma WSS ...... 194 Appendix 9: Data related to Gautampura WSS ...... 196 Appendix 10: Sample Grievance Registration Form ...... 198 Appendix 11: Sample Outline Spoils (construction waste) Management Plan ...... 199 Appendix 12: Sample Outline Traffic Management Plan ...... 200 Appendix 13: Drinking Water Standards ...... 207 Appendix 14: SAMPLE ENVIRONMENTAL SITE INSPECTION REPORT ...... 210 Appendix 15: Quarterly Reporting Format for Assistant Safeguards Officer ...... 212

6 Initial Environmental Examination- Package 2A

I. EXECUTIVE SUMMARY

1. Government of Madhya Pradesh with loan funding from Asian Development Bank (ADB) has proposed to implement Madhya Pradesh Urban Services Improvement Project (MPUSIP), herein after referred as ‘the Project’. Madhya Pradesh Urban Development Company Limited (MPUDC) shall be the Implementing Agency and the State Urban Development and Housing Department (UDHD) shall be the executing agency for the Project.

2. The Project components are as follows:

(i) Component 1: Improvements to water supply and sewerage services in identified towns ➢ Continuous, pressurized, safe and sustainable drinking water through private household metered connections to 350,000 households with about 1.7million population resident in sixty-four towns in the State of Madhya Pradesh in Central India; and ➢ Sewage and storm water collection and treatment services proposed initially in two (2) identified towns (Khajuraho and Rajnagar) servicing about 42,000 population resident in 8000 households;

(ii) Component 2: Institutional Strengthening ➢ Capacity Building of implementing agencies (IAs), participating Urban Local Bodies (ULBs) and service utilities in contract management and service delivery for ensuring long term sustainability of services; ➢ Setting up of geographic information system (GIS) based water and sanitation asset management and service delivery monitoring; and ➢ Structured behavioral change campaigns to ensure the improvement in public health and cost recovery of service delivery.

(iii) Component 3: Project Management and Administration Support. This component will support the smooth and effective implementation and operation of the Project which includes expert support in Project design and implementation (design, procurement and Contract and Project Management, safeguards etc.), and project administration through Executing and Implementing Agencies.

3. The key outcome envisaged from the project is “effective urban water service delivery model rolled out in selective urban clusters of the State with the objective of achieving the following performance indicators by the year 2022.

2. The Subproject. Betma, Depalpur and Gautampura are located in the district in the western part of Madhya Pradesh state. These are small towns having the status of Municipal Council (Nagar Parishad) and population as per 2011 census was: Betma- 15,999, Depalpur- 17,474 and Gautampura- 14,585. Improvement of water supply in these towns will be implemented under a single Design-Build-Operate (DBO) contract package. The objective of the subproject is to achieve safe and sustainable water services both in terms of services to customers, cost recovery, providing 100% coverage with continuous, pressurized and safe drinking water services and achieving progressively increasing cost recovery by expanding the coverage and increasing operating efficiency. The subproject includes the following civil works.

a) Betma: (i) Weir of 6.5 m height and 60 m long and Intake well of 6 m dia and 9 m height on Gambhir River, (ii) Raw water rising main (RWRM) of 14,739 m long

7 Initial Environmental Examination- Package 2A

and 200 mm dia DI K9 pipe; (iii) Raw water pumps: 2 nos vertical turbine type pumps; (iv) Water Treatment Plant (WTP) of 2.16 MLD and clear water sump (CWS) of 65 KL capacity ; (v) Clear water feeder main (CWFM) of 4586 m long and 150- 250 mm dia DI- K9 pipes; (v) Distribution network of 35,142 m length and 110 to 280 mm dia HDPE Pipes; and (vi) consumer connections, and flow meters.

b) Depalpur: (i) Construction of weir having length of 100 m and 3.0 m height, and intake well of 5 m dia and 12 m height on Chambal River; (ii) RWRM of 175 m long and 200 mm dia DI K9 pipe; (iii) Raw water pumps: 2 nos vertical turbine type pumps; (iv) Water Treatment Plant (WTP) of 2.40 MLD and clear water sump (CWS) of 55 KL capacity ; (v) Clear water feeder main (CWFM) of 9,156 m long and 150- 200 mm dia DI- K9 pipes; (vi) 3 nos Overhead tank of 100 KL capacity each; (vii) Distribution network of 28,672 m length and 110 to 200 mm dia HDPE Pipes; and (vi) consumer connections, and flow meters.

c) Gautampura: (i) Weir of 5 m height and 100 m long and Intake well of 6 m dia and 11 m height is proposed on Chambal River, (ii) RWRM of 1,002 m long and 200 mm dia DI K9 pipe; (iii) Raw water pumps: 2 nos vertical turbine type pumps; (iv) Water Treatment Plant (WTP) of 2.10 MLD and clear water sump (CWS) of 55 KL capacity ; (v) Clear water feeder main (CWFM) of 3302 m long and 150- 200 mm dia DI- K9 pipes; (vi) Over head tank of 150 KL capacity; (vii) Distribution network of 26605 m length and 110 to 250 mm dia HDPE Pipes; and (vi) consumer connections, and flow meters.

3. Screening and assessment of potential impacts. ADB requires the consideration of environmental issues in all aspects of the Bank’s operations, and the requirements for environmental assessment are described in ADB’s Safeguard Policy Statement (SPS), 2009. As per the GoI EIA Notification, 2006, these subprojects do not require EIA study or environmental clearance. The potential environmental impacts of the subproject have been assessed using ADB Rapid Environmental Assessment Checklist for Water Supply. Then potential negative impacts were identified in relation to pre-construction, construction and operation of the improved infrastructure.

4. Categorization. Based on results of the assessment and ADB SPS, the subproject is classified as environmental Category B, i.e., the subproject is judged to be unlikely to have significant adverse environmental impacts. An initial environmental examination (IEE) is required to determine whether significant environmental impacts warranting an environmental impact assessment are likely.

5. Aim of this IEE is to (i) provide critical facts, significant findings, and recommended actions; (ii) present the national and local legal and institutional framework within which the environmental assessment has been carried out; (iii) provide information on existing geographic, ecological, social and temporal context including associated facilities within the subproject’s area of influence; (iv) assess the subproject’s likely positive and negative direct and indirect impacts to physical, biological, socioeconomic and physical cultural resources in the subproject’s area of influence; (v) identify mitigation measures and any residual negative impacts that cannot be mitigated; (vi) describe the process undertaken during project design to engage stakeholders and the planned information disclosure measures and the process for carrying out consultation with affected people and facilitating their participation during project implementation; (vii) describe the subproject’s grievance redress mechanism for

8 Initial Environmental Examination- Package 2A resolving complaints about environmental performance; (viii) present the set of mitigation measures to be undertaken to avoid, reduce, mitigate, or compensate for adverse environmental impacts; (ix) to describe the monitoring measures and reporting procedures to ensure early detection of conditions that necessitate particular mitigation measures; and (x) identify indicative costs and who is responsible for carrying out the mitigation and monitoring measures.

6. Description of the Environment. The subproject components are located in Betma, Depalpur and Gautampura towns and their surroundings. Weirs proposed in the all the three towns will be constructed across the rivers (Betma- Gambhir river and Depalpur and Gautampura- Chambal river), intake wells will be constructed on river banks. WTPs including clear water sumps are proposed close to the intake wells with sufficient government land. These components of the schemes are proposed away from the town and are mostly surrounded by agricultural lands and rivers. None of the components however proposed on any forest land. Other components like – OHTs, distribution pipeline network, domestic connections etc., are proposed within the limit of municipal boundary of the respective towns. The raw water transmission mains which are connecting intake well to WTP will be laid outside the town and clear water transmission mains from WTP to OHTs will be partly outside and partly within the municipality limit. Project area experience a subtropical climate, typical to north India, hot summers, cold and dry winters and monsoon rains. While there is no natural habitat left within the town areas, the areas near river intake wells are comparatively intact though most of the lands there too converted into agricultural use. There are no protected areas, like wildlife sanctuaries, national parks, nor there did any historically, archeologically protect areas in the vicinity. Towns are densely populated in the core/old town areas with narrow lanes mostly covering the residential areas with small and closely built houses, while other expanding areas of the towns are having broad lanes and sufficient spaces. Commercial areas are along the main roads with broad lanes having running traffic for most of the time.

7. Potential environmental impacts. The subproject area will not arise any significant adverse impacts due to: (i) small size population and their water demand, (ii) components proposed in the schemes are of comparatively is of small quantities & their effect will be locally which is manageable and controllable and (iii) predicted impacts are site-specific and likely to be associated with the construction process and are produced because the process is invasive, involving excavation and earth movements.

8. Environmental impacts arise due to the project design or because of the locations chosen for the project components are not significant. The proposed water supply schemes include creation of new water sources with the nearest /feasible surface water body. Schemes include construction of weirs (for all the three towns). Weirs across rivers are proposed for the storage of water to meet the water demand of 6 months during no flow period. Following are the details of sources selected for each of the towns:

a) The source of the Betma water supply scheme (WSS) is River Gambhir . This river is not a perennial river. As per information gathered from the local authority, the flows for about 5-6 months, mostly during monsoon, from late June / early July to November / December. Flow is considerable during the months of July to August; flow reduces significantly in November and December, and river gets completely dry in January and up to the onset of next monsoon in June. No flow data is available as

9 Initial Environmental Examination- Package 2A

there is river no gauging station on the river. Catchment area and rainfall based analysis indicated availability 58 MCM of water annually. The capacity of the weir is just about 1.4% of this water availability.

b) Chambal River is most suitable, dependable /sustainable surface source of water supply for Depalpur WSS. However for supplying water from Chambal River all the year around, a weir is to be constructed in the river. Reconnaissance survey was carried out in June 2015 along the river (from June 7th to 11th), and considering river banks and approachability, location near Tamalpur Village is selected for construction of weir. The maximum capacity of weir at FTL 498 m above MSL is coming as 1.94 MCM. c) The source of the Goutampura WSS is based on the river Chambal . The river Chambal is not the perennial river.. As per information gathered from the local authority The flow in the river reduced in the month of the Dec. to Jan. and gets dry after January. The site selected for the proposed weir have deep valley as well as have sufficient cross section to store the required demand of the year 2048. The flow data is not available as there is no flow gauge has been installed. Catchment area and rainfall based analysis indicated availability 338 MCM of water annually. The capacity of the both the weirs on Chambal for Depalpur and Gautampur is just about 0.5% of this water availability.

9. The height of weirs proposed to meet the water storage requirement, and also considering the height of river banks so as to limit the water storage / submergence to river course. Therefore there are no impacts due to submergence. Given the small storage compared to the total volume of water available in the river, no significant impacts envisaged on downstream. Given intermittent nature of rivers, there are no notable sensitive environmental features. There is no notable, protected or unique aquatic life in the river, and the fish is limited to local common species. National Chambal Gharial Sanctuary, established in River Chambal in its mid and lower reaches, is far away (about 300 km downstream) from proposed weir locations, and this distance is intercepted further by four major dams. Therefore the proposed weirs have no relevance to the sanctuary area. It is also proposed that weirs will be constructed as a vented structure, with open rectangular vents and gates; sill level of weir will be just above the river bed. On the sill there will be vertical slots to insert removable gates; gates will be closed prior to end of monsoon flows and opened prior to onset of heavy monsoon flows; this arrangement avoids silt accumulation and also prevents obstruction of heavy monsoon flows. As the package is implemented under DBO mode, the detailed design of weir will be conducted by the contractor after award of the contract. Water quality is good and there are no potential pollution sources in the vicinity that could affect the water quality. Necessary precautionary measures are suggested to avoid any impacts.

10. During the project construction phase, potential negative impacts may arise from disturbance of residents, businesses, increase in traffic, increase in noise level and dusts and the need to dispose moderate quantities of waste soil during construction phase and generation of sludge from the WTP during operation and maintenance phase. However, there are well-developed methods for mitigation, minimization to acceptable levels are proposed here.

10 Initial Environmental Examination- Package 2A

11. Environmental Management Plan As a part of mitigate measures in order to achieve acceptable levels in the negative impacts, an environmental management plan (EMP) has been proposed. All the locations are selected considering the minimum adverse environmental effects. These include (i) locating facilities on government-owned land to avoid the need for land acquisition and relocation of people; and (ii) laying of pipes in RoW alongside main/access roads, to reduce acquisition of land and impacts on livelihoods specifically in densely populated areas of the town. The EMP given here includes the design measures for (i) Weir and Intake well; (ii) safe disposal of sludge coming out of wash water tanks from WTP to reduce effluent (iii) energy efficient pumping equipment and (iv) quick leak detection and rectification to save the resources, etc. During execution phase, the EMP includes mitigation measures such as (i) implementation of traffic management plan in coordination with local traffic police to minimize traffic impacts (ii) awareness campaigns and consultations to inform residents and businesses of potential disturbances; (iii) provision of walkways and planks over trenches to ensure access will not be impeded; (iv) use of noise- dampening measures in areas with sensitive receptors such as hospitals, schools, places of worships and other silence-zones; (v) use of dust-suppression methods such as watering and/or covering of stockpiles; and (vi) finding beneficial use of excavated materials to extent possible to reduce the quantity that will be disposed off. As for the O&M phase, facilities will need to be repaired from time to time, but environmental impacts will be much less than those of the construction period as the work will be infrequent, affecting small areas only. The design of the WTP includes dewatering and drying areas as part of sludge management. The EMP includes mitigation measures and monitoring plan to ensure compliance to environmental standards during O&M phase.

12. The EMP will guide the environmentally-sound construction of the subproject and ensure efficient lines of communication between Madhya Pradesh Urban Development Company (MPUDC), project management unit (PMU), project implementing unit (PIU), consultants and contractors. The EMP will (i) ensure that the activities are undertaken in a responsible non-detrimental manner; (i) provide a pro-active, feasible and practical working tool to enable the measurement and monitoring of environmental performance on site; (ii) guide and control the implementation of findings and recommendations of the environmental assessment conducted for the subproject; (iii) detail specific actions deemed necessary to assist in mitigating the environmental impact of the subproject; and (iv) ensure that safety recommendations are complied with. The EMP includes a monitoring program to measure the environmental condition and effectiveness of implementation of the mitigation measures. It will include observations on- and off-site, document checks, and interviews with workers and beneficiaries.

13. The contractor will be required to submit to PMU, for review and approval, a site environmental plan (SEP) including (i) proposed sites/locations for construction work camps, storage areas, hauling roads, lay down areas, disposal areas for solid and hazardous wastes; (ii) specific mitigation measures following the approved EMP; (iii) monitoring program as per SEP; and (iv) budget for SEP implementation. No works are allowed to commence prior to approval of SEP. A copy of the EMP/approved SEP will be kept on site during the construction period at all times. The EMP included in the bid and contract documents. Non-compliance with, or any deviation from, the conditions set out in this document constitutes a failure in compliance.

14. Consultation, disclosure and grievance redress mechanism. The stakeholders were involved in developing the IEE through discussions on-site and public consultation at

11 Initial Environmental Examination- Package 2A several places in the town, after which views expressed were incorporated into the IEE and in the planning and development of the project. The IEE will be made available at public locations and will be disclosed to a wider audience via the ADB,MPUDC and PMU websites. The consultation process will be continued and expanded during project implementation to ensure that stakeholders are fully engaged in the project and have the opportunity to participate in its development and implementation. A grievance redress mechanism is described within the IEE to ensure any public grievances are addressed quickly.

15. Implementation Arrangements. Urban Development and Housing Department (UDHD) of Government of Madhya Pradesh is the Executing Agency and Madhya Pradesh Urban Development Company (MPUDC) is the Implementing Agency. Project Management Unit (PMU) attached to MPUDC is responsible for implementation, and will be supported by Program Implementation Units (PIUs). Several teams of Design Consultants, and a Program Management Consultant (PMC),will support PMU & PIUs. Infrastructure will be designed, built, and operated by DBO contractor for 10 years, after which it will be transferred to ULBs. Project Officer (Environment) at PMU and Assistant Safeguard Officer (ASO) at each of the PIU will be responsible for environment safeguards tasks, and will be supported by PMC. Contractor personnel will include an Environment, Health and Safety (EHS) supervisor.

16. Monitoring and Reporting. The PMU and PMC will be responsible for monitoring. The PMDC will submit quarterly and semi-annual monitoring reports to PMU, and the PMU will review and send the semi-annual monitoring reports to ADB. ADB will post the environmental monitoring reports on its website.

17. Conclusions and Recommendations. The subproject is therefore unlikely to cause significant adverse impacts. The potential impacts that are associated with design, construction and operation can be mitigated to standard levels without difficulty through proper engineering design and the incorporation or application of recommended mitigation measures and procedures. Based on the findings of the IEE, there are no significant impacts and the classification of the project as Category “B” is confirmed. No further special study or detailed environmental impact assessment (EIA) needs to be undertaken to comply with ADB SPS (2009) or GoI EIA Notification (2006). Project will require permission of Water Resources Department (WRD) for water abstraction, Weir and intake well construction for all the three towns, and consent of Madhya Pradesh Pollution Control Board (MPPCB) for WTPs. These permissions/approvals shall be obtained prior to award of contracts.

18. This IEE will be updated during the detailed design stage by the DBO contractor to reflect any changes, amendments and will be reviewed and approved by PMU.

12 Initial Environmental Examination- Package 2A

II. INTRODUCTION

Background 1. Government of Madhya Pradesh with loan funding from Asian Development Bank (ADB) has proposed to implement Madhya Pradesh Urban Services Improvement Project (MPUSIP), herein after referred as ‘the Project’. Madhya Pradesh Urban Development Company Limited (MPUDC) shall be the Implementing Agency and the State Urban Development and Housing Department (UDHD) shall be the executing agency for the Project.

2. The Project components are as follows:

(i) Component 1: Improvements to water supply and sewerage services in identified towns ➢ Continuous, pressurized, safe and sustainable drinking water through private household metered connections to 350,000 households with about 1.7million population resident in sixty-four towns in the State of Madhya Pradesh in Central India; and ➢ Sewage and storm water collection and treatment services proposed initially in two (2) identified towns (Khajuraho and Rajnagar) servicing about 42,000 population resident in 8000 households;

(ii) Component 2: Institutional Strengthening ➢ Capacity Building of implementing agencies (IAs), participating Urban Local Bodies (ULBs) and service utilities in contract management and service delivery for ensuring long term sustainability of services; ➢ Setting up of geographic information system (GIS) based water and sanitation asset management and service delivery monitoring; and ➢ Structured behavioral change campaigns to ensure the improvement in public health and cost recovery of service delivery.

(iii) Component 3: Project Management and Administration Support. This component will support the smooth and effective implementation and operation of the Project which includes expert support in Project design and implementation (design, procurement and Contract and Project Management, safeguards etc.), and project administration through Executing and Implementing Agencies.

3. The key outcome envisaged from the project is “effective urban water service delivery model rolled out in selective urban clusters of the State with the objective of achieving the following performance indicators by the year 2022.

(i) Access to piped water supply coverage increased to 95% of the households from 33% in 2015 in 64 towns; (ii) Women's drudgery for fetching water reduced by 80% (from spending an average of 55 minutes in 2015 to 10 minutes); (iii) Coverage of households with access to improved sanitation systems increased to 80% from 30% in 2015; (iv) Wastewater collection and/or safe sanitation service coverage increased to at least 80% of the households from 0% in 2015 in two towns; (v) Incidence of water logging/flooding reduced to two incidents per annum in four towns; and (vi) Women access to functioning sanitation systems increased to 95% from 25% in 2015 (in poor settlements) in four towns

13 Initial Environmental Examination- Package 2A

4. The key outputs envisaged from the project are:

(i) Output 1: Water supply infrastructure improved in 64 project towns and flood and sanitation infrastructure improved in two project towns with the following measurable indicators: ➢ Improved water supply capacity of 186ml/day installed in 64 towns; ➢ 4,000 km water supply networks installed in 64 towns; ➢ 350,000 households provided with metered house connections including 100 government schools; ➢ 8 MLD sewage or septage treatment plants constructed; and ➢ Installation of 120 km sewer and drainage mains and networks.

(ii) Output 2: Sustained urban infrastructure operation and management

➢ 23 performance-based contract (PBC) operation and maintenance (O&M) water supply contracts for 64 ULBs signed and operated; ➢ ULBs institute volumetric water charges for recovery of water service O&M costs ➢ ULBs’ water tariff collection ratio improved to 90% from 50% in 2014 based on the water meters’ readings ➢ 100% operating cost recovery (excluding debt service) achieved; ➢ GIS system established for effective O&M of water services

Purpose of this IEE Report

5. ADB requires the consideration of environmental issues in all aspects of the Bank’s operations, and the requirements for environmental assessment are described in ADB’s Safeguard Policy Statement (SPS), 2009. The potential environmental impacts of the subproject have been assessed using ADB Rapid Environmental Assessment Checklist for Water Supply (Appendix 1). Then potential negative impacts were identified in relation to pre-construction, construction and operation of the improved infrastructure, and results of the assessment show that the subproject is unlikely to cause significant adverse impacts. Thus, this initial environmental examination (IEE) has been prepared in accordance with ADB SPS’s requirements for environment category B projects

6. To understand the environment-related aspects of the project, a detailed Environmental Analysis and Assessment study is required. The study will involve collection and analysis of information regarding the environmental issues related to the project and preparation of an Initial Environmental Examination (IEE) and Environmental Management Plan (EMP), to be duly integrated in the overall design of the project. The IEE study is expected to focus on the positive health and environmental benefits, through supply of safe drinking water and creation of integrated sanitary conditions in the project area/region. The proposed assessment study will suggest several environmental mitigation measures to be included in the project design, due to which the project is expected to have a net positive benefit for the people in the project area.

7. Betma, Depalpur and Gautampura are located in the in the central western part of Madhya Pradesh state. These are small towns having the status of Municipal Council (Nagar Parishad) and population as per 2011 census was: Betma- 15,999, Depalpur- 17,474 and Gautampura- 14,585. Improvement of water supply in these towns will be implemented under a single Design-Build-Operate (DBO) contract package. The objective of the subproject is to achieve safe and sustainable water services both in terms of services to customers, cost recovery, providing 100% coverage with continuous, pressurized and safe

14 Initial Environmental Examination- Package 2A drinking water services and achieving progressively increasing cost recovery by expanding the coverage and increasing operating efficiency.

Report Structure 8. This Report contains the following nine (9) sections: (i) Executive summary; (ii) Introduction (iii) Description of the project (iv) Policy, legal and administrative framework (v) Description of the environment; (vi) Anticipated environmental impacts and mitigation measures; (vii) Public consultation and information disclosure; (viii) Grievance redress mechanism; (ix) Environmental management plan, and (x) Conclusion and recommendation

15 Initial Environmental Examination- Package 2A

III. DESCRIPTION OF THE PROJECT

A. Project Area 9. Project area comprises the urban areas and surroundings of Betma, Depalpur and Gautampura situated in Indore district in central western part of Madhya Pradesh state. Towns are located in same district, and in a distance range of about 80-100 km from each other. As per the census 2011, Betma had a population of 15,999, Depalpur had a population of 17,474 and Gautampura had a population of 14,585.

10. Subproject components are located within the urban and surroundings. While weir, intake well and WTPs are located outside the towns, all other components are located within the towns.

B. Existing Water Supply Situation 1. Betma

11. Water supply system in Betma is entirely dependent on ground water source in the form of tube wells. There is absence of dedicated water supply scheme as on today. Water supply to town is served by 17 tube wells located at different parts of city such as Chhota Betma, Dusshera Maidan, Shiv Ghat and Balaji. Out of 17 tube wells only 13 are in running condition. There is no Water Treatment plant. There is an existing clear water pipe line of 150 mm dia. Galvanized iron (GI) pipe. Pipe line has damaged at many spots and has leakage problem. Hence this pipeline is not taken into account for new system because it is undersized and by using of this pipe it will give high head, high head losses and negative pressure. The water is being supplied to the town, after preliminary treatment of chlorination. There are two sump wells and four overhead tanks (OHTs) in Betma. Conditions of all four OHTs are structurally good. Out of four overhead tanks two nos. are in use, remaining two OHTs could not be filled due to not getting the sufficient yield from the tube well. Total capacity of two OHTs in Betma is 600 KL through which water is supplied to all 15 wards in Betma. Water is stored in OHTs through pumping from two nos. of sump well.

12. Betma Nagar Parishad supplies approximately 0.6 milllion litre per day (MLD) of water. The duration and frequency of water supply is twenty minute on every day. Betma Nagar Parishad has divided 15 municipal wards into 4 zones for distribution of water supply. The per capita supply of water is 40 liters per capita per day ( lpcd). Table 1: Details of Rising main and Distribution network Rising main details Distribution network details Percentage of coverage Distribution network

At Indore road 150 mm 300 mm to 150 mm 30% GI Pipe from sump to GI, CI, PVC Pipe OHT

At Nagar Parishad 150 mm 30% 100 mm- 75 mm GI Pipe GI, CI, PVC Pipe from sump to OHT

Source: Nagar Parishad Betma

16 Initial Environmental Examination- Package 2A

2. Depalpur 13. The present water supply in Depalpur is mainly from tube wells. There are 12 nos. tube wells fitted with 10 horse power (HP)-12 HP motor pumps. The maximum water availability from tube wells is 0.60 MLD. The water from tube wells is being directly pumped on OHTs by adding bleaching power. There is a water treatment plant (WTP) and intake well on Chambal River in Depalpur, the same has been constructed in the year 1980. The water treatment plant is not in a good condition and is not been used presently by the Nagar Parishad. The intake well-constructed in the year 1980 is also in a bad condition and is not been used by the Nagar Parishad.

14. The maximum availability at present from groundwater sources is up to 0.60 MLD from which the average water supply is only 35 liters per capita per day in comparison to the standard norm of 70 lpcd as per standards set out in CPHEEO Manual of Ministry of Urban Development GOI for town. Ground water is not assured and educes after rainy season and moreover, in the years to come, the population will increase and the present rate of water supply from underground sources shall further reduce thereby creating water scarcity to the citizens of the Depalpur.

15. At present the water is supplied from the underground sources after disinfection by adding bleaching powder. The quality of water supplied is not monitored on regular basis. Thus the present Water supply system in the town is falling to deliver the demands due to limited source capacity, seasonal variations in availability, inadequate storage, poor network efficiency and low management capacity.

3. Gautampura

16. Water supply system in Gautampura is dependent on surface source. A Culvert of river Chambal (2.5 km away from the town) was converted to make shift stop dam structure by covering the circular closures (pipes) under the culvert. The water from this arrangement was brought and stored in the artificial lake which was created at a location called Kharcha. In order to conserve water and provide filtered water to the citizens, two dug wells were created near the lake. The water from these dug wells was then provided to the town. Eventually due to the creation of lake, the other water bodies in the town have also been recharged and the rise in water table in the surrounding areas has been tremendous. As a result of this now water approximately 0.62 MLD is being supplied to the town at the rate of 32 lpcd after 20% transmission losses at alternate day.

17. Another artificial lake is being created in the Runji area called Runji Talab. The natural rain water and ground water is stored here. One dug well is created near this lake from where conserved and filtered water is supplied to the Runji area citizens.

18. There is an existing clear water pipe line of 200 mm dia. ACP pipe. Pipe line has damaged at many spots and has leakage problem. Hence this pipeline is not taken into account for new system. The water is being supplied to the town after preliminary treatment of chlorination. There are two sump wells of total capacity 2.5 Lac liter and two OHTs of total capacity 700 KL in Gautampura. The condition of two overhead tanks is good. Total capacity of two OHT’s in Gautampura is 700 KL through which water is supplied to all 13 wards in

17 Initial Environmental Examination- Package 2A

Gautampura except ward no.1 & 2. Water is stored in OHTs through pumping from two nos. of sump well. Water is also supplied for the Gautampura town by 3 dug wells located near the artificial lake at Kharcha, approximately 1.5 km from the town and one dug well created near Runji Talab. 19. Gautampura Nagar Parishad supplies approximately 0.62 ML of water at alternate day. The duration and frequency of water supply is forty minute on alternate day. Gautampura Nagar Parishad is divided into 15 wards. The per capita supply of water is 32 lpcd.

Table 2: Details of Rising main and Distribution network Rising main details Distribution network details Percentage of coverage Distribution network

200 mm ACP Pipe 75 mm to 100 mm 70% GI, CI, PVC Pipe

Source: Nagar Parishad Gautampura

18 Initial Environmental Examination- Package 2A

Figure 1: Subproject location MP STATE MAP WITH SUBPROJECT DISTRICT

LOCATION OF TOWNS IN INDORE DISTRICT

19 Initial Environmental Examination- Package 2A

C. Proposed Project 20. As the water table is depleting all over, therefore, now it is not a reliable source for a permanent scheme in towns. As part of this project, it is proposed to develop comprehensive water supply schemes in each of the project towns. Proposals include new reliable water sources, water treatment plants, OHTs, energy efficient pumping machinery, raw and clear water transmission mains and distribution network covering the entire population of towns. Project will also provide consumer connections with flow meters. Bulk flow meters are proposed at strategic locations to monitor the system performance efficiency.

21. Following Table 3 shows the proposed water supply systems along with nature and size of components in three subproject towns. Figure 2 to Figure 7 show the proposed water systems, component layouts etc.

20 Initial Environmental Examination- Package 2A

Table 3: Proposed Water Supply Subproject Components Particulars Betma Depalpur Gautampura I. Water demand 1 Base year 1.53 MLD 1.70 MLD 1.35 MLD (2018) 2 Design year 1.98 MLD 2.00 MLD 1.62 MLD (2033) 3 Ultimate year 2.16 MLD 2.40 MLD 1.90 MLD (2048) II. Source 1 Alternatives 1. Kishanpura Talab 1. Chambal River 1. Chambal River 2. Gambhir River 2. Dam 2. Ground water 3. Chambal Water 3. 4. Banedia River 2 Selected Gambhir River Chambal River Chambal river source Weir and Intake well on river. Weir and Intake well on river. Weir and Intake well on river. III. Proposed system 1 From source Raw water abstraction from Gambhir Raw water abstraction from Chambal Raw water abstraction from Chambal to consumer river → raw water transmission river → raw water transmission river → raw water transmission supply (pumping) → treatment → clear water (pumping) → treatment → clear water (pumping) → treatment → clear water transmission (pumping) → storage → transmission (pumping) → storage → transmission (pumping) → storage → distribution → house connections with distribution → house connections with distribution → house connections with meters meters meters 2 Weir Dimensions: 6.5 m high, 60 m long Dimensions: 3 m height and 100 m long Dimensions: 5 m height and 100 m long weir across Gambhir River weir across Chambal River. weir across Chambal River

Gross storage capacity: 0.72 million Gross storage capacity: 1.27 MCM Gross storage capacity: 0.55 MCM cubic meter (MCM) Location: Near Tamalpur village Location: Near Chambal bridge Location: Kalariya village and land is (Latitude -22º 52' 18.53'' N & Longitude - (towards ward no . 6 ) under possession of WRD. 75º 29' 13.78'' E) on Chambal River.

Type of weir: a vented concrete structure, with solid concrete foundation up to sill level, i.e. slightly (~0.1 m) above the river bed level, and above which it will have rectangular open vents with slots to place removable gates up to the required design height; gates will be placed prior to end of high monsoon flows, and will be removed after the onset next monsoon flows. This type of 21

Particulars Betma Depalpur Gautampura structure allows heavy monsoon flow freely without any obstruction, and also avoids dam silting. This structure impounds water during low or no flow period, and during heavy river flow, gates will be removed. 3 Intake Well Reinforced cement concrete (RCC) RCC Intake well of 5 m diameter and 12 RCC Intake well of 6 m diameter and 11 intake well of 6 m diameter and 9 m ,m height m height and a approach bridge of 160 m height to collect and lift raw water. length Location: On the bank of Gambhir Location: On the bank of Chambal River River, upstream of proposed weir near upstream of proposed weir near Tamalpur Location: On the bank of Chambal River Kalariya village. village upstream of proposed weir near Chambal bridge (towards ward no. 6). 4 Pumping Two nos. vertical turbine type pump Two nos. Raw water Vertical Turbine Two nos. vertical turbine type pump with stations with 100% as standby is proposed. The pump sets (one working and one stand 100% as standby is proposed. The discharge of each pump is 25.00 LPS by) of 7.00 KW having motors of 10 HP discharge of each pump is 20.45 LPS and and head is 120.93 meter at each having discharge of 25 lps & having head is 24.36 meter at intermediate stage intermediate stage Year 2033. The 20.00 m of pumping head, 13.00 KVA Year 2033. The rating of each pump is rating of each pump is 37.59 KW (say transformer with all other necessary 6.20 KW (say 6.5 KW). One no. working 38.0 KW). One no. working and one electrical and mechanical installations for and one pump will be as a standby. uninterrupted power supply to pumps and pump will be as a standby. Provision of 2 numbers Centrifugal type motors. pump having discharge 1.54 ML or 19.44 LPS and head of 34 m with suitable motor 2 nos. Clear water Centrifugal pump-sets is proposed with 100 percent standby (1 (one working and one stand by) 25.00 no. working and one stand bye) KW having motors of 34.00 HP each arrangement at TP including suction pipe, having discharge of 25 lps & 85.00 m of control panel, cable and all accessories is pumping head, 45.00 KVA transformer made. with all other necessary electrical and mechanical installations. The pumps are being provided for the design period of 15 years i.e., up to 2033 (1.88 MLD)

5 Raw water 14,739 m long and 200 mm diameter 175 m long 200 mm diameter DI pipe 1,002 m long 200 mm diameter DI pipe transmission ductile iron (DI) pipe from Intake well to from Intake well at Tamalpur village to from Intake well to WTP. WTP WTP. Pipeline will be mostly laid along the main Pipelines will be mostly laid along the roads. Pipes will be laid underground. Transmission pipelines will be mostly laid 22 Initial Environmental Examination- Package 2A

Particulars Betma Depalpur Gautampura main roads. Pipes will be laid along the road. Pipes will be laid underground. underground. 6 WTP Capacity: 2.16 MLD Capacity: 2.40 MLD Capacity: 2.10 MLD Process/components (same for all towns): Coagulation &flocculation, sedimentation, rapid gravity filtration, chlorination, wash water recovery, sludge drying beds, tube settlers & miscellaneous infra (compound wall, landscaping, lighting, rest rooms etc)

Location: Near Salampur village; Location: On Government land in Location: Proposed site located in 10.48 ha of land available at the Tamalpur village Khasra No. 418, and is under government proposed site. The land is in the posession government’s possession. 7 Reservoirs / - 3 nos. overhead tanks (OHTs) of 100 KL 1 OHT of 150 KL capacity, within the tanks each at Resham Kendra, at Old Nagar proposed WTP campus Parishad and at Pashu Bazar in the town. 8 Clear water 4,586 m length, 150- 250 mm diameter 6,113 m length, 200 mm diameter DI pipe 3,302 m length, 150- 250 mm diameter DI transmission DI pipe from the clear water sump to from WTP to junction 1 near pipes from the clear water sump to the the OHT, along the main roads. Dharamshala along the roads proposed OHT, along the main roads.

9 Distribution Total length - 35,142 m, HDPE pipes Total length – 28,672 m, HDPE pipes of Total length – 26,605 m, HDPE pipes network 4,107 m in Zone 1 – pipe diameter diameter 110 - 250 mm 10,813 m in Zone 1 – pipe diameter 110- 110-180 mm, 180 mm, 22,217 m in Zone 2 – pipe diameter 10,738 m in Zone 2 – pipe diameter 110- 110-280 mm 280 mm 8,819 m in Zone 3 - pipe diameter 5,054 m in Zone 3 - pipe diameter 110- 110-250 mm 250 mm 10 Consumer Domestic - 3,035 no,s Domestic - 3,334 no,s Domestic - 2672 nos, connects with Non- domestic - 50 no,s non- domestic - 50 no,s Non- domestic - 50 nos meters

23 Initial Environmental Examination- Package 2A

Figure 2: Key Plan of Betma Water Supply Scheme

24

Figure 3: Key Plan of Gautampura Water Supply Scheme

25 Initial Environmental Examination- Package 2A

Figure 4: Schematic drawing of proposed weir on Chambal River

26 Initial Environmental Examination- Package 2A

Figure 5: Cross Section of Proposed Intake well of Gautampura WSS

27 Initial Environmental Examination- Package 2A

Figure 6: Key plan of Depalpur Water Supply Scheme

28 Initial Environmental Examination- Package 2A

Figure 7: Layout plan and cross section of proposed weir for Depalpur WSS

29 Initial Environmental Examination- Package 2A

IV. POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK

A. ADB Policy

22. ADB requires the consideration of environmental issues in all aspects of ADB’s operations, and the requirements for environmental assessment are described in ADB SPS, 2009. This states that ADB requires environmental assessment of all ADB investments.

23. Screening and categorization. The nature of the environmental assessment required for a project depends on the significance of its environmental impacts, which are related to the type and location of the project; the sensitivity, scale, nature, and magnitude of its potential impacts; and the availability of cost-effective mitigation measures. Projects are screened for their expected environmental impacts, and are assigned to one of the following four categories:

(i) Category A. Projects could have significant adverse environmental impacts. An EIA is required to address significant impacts. (ii) Category B. Projects could have some adverse environmental impacts, but of lesser degree or significance than those in category A. An IEE is required to determine whether significant environmental impacts warranting an EIA are likely. If an EIA is not needed, the IEE is regarded as the final environmental assessment report. (iii) Category C. Projects are unlikely to have adverse environmental impacts. No EIA or IEE is required, although environmental implications are reviewed. (iv) Category FI. Projects involve a credit line through a financial intermediary or an equity investment in a financial intermediary. The financial intermediary must apply an environmental management system, unless all projects will result in insignificant impacts.

24. Environmental management plan. An EMP, which addresses the potential impacts and risks identified by the environmental assessment, shall be prepared. The level of detail and complexity of the EMP and the priority of the identified measures and actions will be commensurate with the project’s impact and risks.

25. Public disclosure. ADB will post the safeguard documents on its website as well as disclose relevant information in accessible manner in local communities:

(i) for environmental category A projects, draft EIA report at least 120 days before Board consideration; (ii) final or updated EIA and/or IEE upon receipt; and (iii) Environmental monitoring reports submitted by the implementing agency during project implementation upon receipt.

B. National Environmental Laws

26. Environmental Assessment. The GoI EIA Notification of 2006 (replacing the EIA Notification of 1994), sets out the requirement for Environmental Assessment in India. This states that Environmental Clearance (EC) is required for specified activities/projects, and EC must be obtained before any construction work or land preparation (except land acquisition) may commence. Projects are categorized as A or B1 or B2 depending on the scale of the project and the nature of its impacts. None of the components of this water supply subproject falls under the ambit of the EIA Notification 2006, and, therefore no category assigned, and thus no EIA study and EC required for the subproject.

27. Applicable environmental regulations. Besides EIA Notification 2006, there are various 30 other acts, rules, policies and regulations currently in force in India that deal with environmental issues that could apply to infrastructure development. The specific regulatory compliance requirements of the subproject are shown in Table 4.

Table 4: Applicable Environmental Regulations Law Description Requirement Madhya Pradesh Prepared in accordance with the National Permission of WRD, State Water Water Policy, it states that “for environmental GoMP has been Policy, 2003 balance, skillful and planned management of obtained all types of developmental activities, forConstruction of economic use on equitable basis and in view Weirs and Intakes for of the prime importance of water for all all the three towns human and other living beings, an effective (River Chambal and and sound water policy is necessary”. Gambhir ) Policy is detailed in 17 sections dealing with different aspects of water resources. No. 7 deals with Water Allocation Priorities, and according to which drinking water supply shall have the highest priority followed by irrigation, power, tourism, etc. Water Resource Department is nodal department for permitting different uses of water resources. Policy also states that “clear provision for reservation of drinking water shall be made in irrigation projects” Water Act was enacted to provide for the prevention WTPs require CTE (Prevention and and control of water pollution and the (prior to start of Control of maintaining or restoring of wholesomeness of constriction) and CFO Pollution) Act of water, by Central and State Pollution Control (prior to start of 1974, Rules of Boards and for conferring and assigning to operation) from 1975, and CPCB/SPCBs powers &functions relating to MPPCB. amendments water pollution control. Application has to be Control of water pollution is achieved through submitted online at administering conditions imposed in consent http://www.mppcb.nic.in issued under to this Act. These conditions /xgn.html regulate the quantity and quantity of effluent, the location of discharge and the frequency of monitoring of effluents. Any component of the subproject having the potential to generate sewage or trade effluent will come under its purview. Such projects have to obtain Consent to Establish (CTE) & Consent to Operate (CTO) under Section 25 from Madhya Pradesh Pollution Control Board (MPPCB) Environment Emissions and discharges from the facilities Appendix 2 provides (Protection) Act, to be created or refurbished or augmented applicable standards for 1986 and CPCB shall comply with the notified standards ambient air quality. Environmental Appendix 3 provides Standards. vehicular emission norms

Noise Pollution Rule 3 of the Act specifies ambient air quality Appendix4 provides (Regulation and standards in respect of noise for different applicable noise

31 Initial Environmental Examination- Package 2A

Law Description Requirement Control) Rules, areas/zones. standards. 2000 amended up to 2010. Indian Drinking Gives details of the permissible and desirable Appendix 13 provides Water Standards limits of various parameters in drinking water drinking water as per the Burea of Indian Standards standards

Municipal Solid Rules to manage municipal solid waste Solid waste generated Wastes generated; provides rules for segregation, at proposed facilities Management storage, collection, processing and disposal. shall be managed and Rules, 2016 disposed in accordance with the MSWM Rules Construction & Rules to manage construction & to waste Construction & Demolition resulting from construction, remodeling, demolition waste Waste repair and demolition of any civil structure. generated from the Management Rules define C&D waste as waste comprising project construction Rules, 2016 of building materials, debris resulting from shall be managed and construction, re-modeling, repair and disposed as per the demolition of any civil structure. rules (Appendix 5) Labor Laws The contractor shall not make employment Appendix 6 provides decisions based upon personal applicable labor laws characteristics unrelated to job requirements. including amendments The contractor shall base the employment issued from time to time relationship upon equal opportunity and fair applicable to treatment, and shall not discriminate with establishments respect to aspects of the employment engaged in construction relationship, including recruitment and hiring, of civil works. compensation (including wages and benefits), working conditions and terms of employment or retirement, and discipline. The contractor shall provide equal wages and benefits to men and women for work of equal value or type.

28. ADB SPS Requirements. During the design, construction, and operation of the project the PMU and PIUs are required to apply pollution prevention and control technologies and practices consistent with international good practice, as reflected in internationally recognized standards such as the World Bank Group’s Environment, Health and Safety Guidelines (IFC’s General EHS Guidelines1 and Sector Specific (Water and Sanitation) Guidelines2). These standards contain performance levels and measures that are normally acceptable and applicable to projects. When Government of India regulations differ from these levels and measures, the PMU and PIUs will achieve whichever is more stringent. If less stringent levels or measures are appropriate in view of specific project circumstances, the PMU and PIUs will provide full and detailed justification for any proposed alternatives that are consistent with the requirements presented in ADB SPS. International acceptable air and noise quality guidelines are provided below:

1https://www.ifc.org/wps/wcm/connect/554e8d80488658e4b76af76a6515bb18/Final%2B- %2BGeneral%2BEHS%2BGuidelines.pdf?MOD=AJPERES 2 https://www.ifc.org/wps/wcm/connect/e22c050048855ae0875cd76a6515bb18/Final%2B- %2BWater%2Band%2BSanitation.pdf?MOD=AJPERES

32 Initial Environmental Examination- Package 2A

Table 5: WHO Ambient Air& Noise Quality Guidelines

33 Initial Environmental Examination- Package 2A

V. DESCRIPTION OF THE ENVIRONMENT

Methodology Used for Baseline Study

29. Data collection and stakeholder consultations. Focused Group Discussion, field visits, site surveys and social surveys were conducted through the different wards covering every section of society was conducted and data collected and analyzed accordingly with respect to the proposed subproject sites and the with respect to the need of water supply in all the three towns here.

30. The social survey broadly covered the following:

(i) Project details, reports, maps, and other documents prepared by technical experts of design consultant team. (ii) Discussions with technical experts, municipal authorities and relevant government agencies like WRD, Revenue Department, Forest Department, MPPCB, etc. (iii) Secondary data from previous project reports & published articles, if any, and (iv) Literature on land use, soil, geology, hydrology, climate, socioeconomic, and planning documents collected from Government agencies and websites.

31. Ocular inspection. Several visits to the project sites were made during IEE preparation period in 2016 to assess the existing environment (physical, biological, and socioeconomic) and gather information with regard to the proposed sites and scale of the proposed project. A separate socioeconomic study was conducted to determine the demographic information, existing service levels, stakeholder needs and priorities.

Baseline Environmental Profile

32. Following Table 6 presents the baseline environmental profile of subproject towns of Betma, Depalpur and Gautampura. It is organized in terms of physical, ecological, economical, and socio cultural resources

34 Initial Environmental Examination- Package 2A

Table 6: Baseline Environmental Features of the Subproject Towns Baseline Betma Depalpur Gautampura characteristics Location Betma is a Nagar Parishad in Indore Depalpur is a Nagar Parishad in Gautampura is Nagar Parishad in District of Madhya Pradesh State, Indore district in the state of Madhya region of Indore district in the state of India. Pradesh. Depalpur is located in the Madhya Pradesh. The geographical Location of Town western region of Madhya Pradesh, The geographical Location of Town Betma is given below. on the southern edge of Malwa Gautampura is given below: • Latitude- 220 40’48’’ N plateau. It was established in 1914 • Latitude- 22o59’11’’ N • Longitude- 750 37’12’’ E and Parishad was formed in the year • Longitude- 75031’23’’ E of 1984. Depalpur geographically lies Town is situated at an average at 230 51’N Latitude and 750-32’E elevation of 541m above mean sea Longitude, at an altitude of 533 m level (msl). above msl.

Connectivity Betma is located at approximately 28 The town is situated 40 Km from the Gautampura is located on the major district km from Indore towards west on District headquarter of Indore. road (MDR) connecting Indore to Depalpur National Highway 59 (NH 59). Betma via Gautampura is approximately 15 is located at a strategic location, km away from Depalpur. The MDR from which provides connectivity to three Depalpur to Gautampura further goes on to major towns of Indore, Depalpur and join state highway (SH 18), which connects . Ujjain to .

Betma is situated on NH-59 which Gautampura has rail connectivity and connects to Ahmedabad on its west nearest railway station is Gautampura Road and Indore (27 km) to its east. Indore railway station, which is about 3-4 km away railway station is the nearest railway from town station from the Betma. It is 29 km from Betma.

Area & The town is spread over an area of The town is spread over an area of The town is spread over an area of 2.93 sq. Population 8.8 sq. km and houses population of 3.55 sq. km and houses population km and houses population of 190,50 as per 15,999 as per 2011 census. of 14,474 as per 2011 census. 2011 census. Topography Betma is situated on an uneven tract Depalpur is located in the western Gautampura is situated on an uneven tract of land and the general ground slope region of Madhya Pradesh, on the of land and the general ground slope is 35

Baseline Betma Depalpur Gautampura characteristics is towards eastern side. A major southern edge of the Malwa plateau. towards eastern side. nallah flowing through the centre of It is located on an elevated plain, Betma forms the main drainage with the Vindhyas range to the south. system.

Soils & The lands of Betma primarily hold The soil profile found here is typically The lands of Gautampura primarily hold geology mixed red and black type soils, black clay soil having depth of 5 medium black soils. falling under the world soil meter. . classification of Brown earths. Climate Climate is sub tropical which is typical Climate is sub-tropical which is Gautampura is situated at an altitude of in this part of the country. Summer typical in this part of the country. about 502 meters above msl. Gautampura daytime temperature reaches up to Summers are hot and dry followed by has a typical sub-tropical climate. Three 450 C with 20-25 percentage monsoon months, with approximate distinct seasons are observed, summer, humidity. Winter night temperature 32-35 inches of rainfall followed by monsoon and winter. Summers start in mid- falls to 5-60C with 20-25 percentage mild winters in the months of Dec- March and can be extremely hot in April and humidity. Jan. Summer day time temperature May. Daytime temperature reaches up to 43 can reach 42-45 °C with 25-30% °C and night temperature can fall to 6 °C. Rainfall: The annual average rainfall humidity. Winter night temperature Winters are moderate and usually dry. in Betma is approx. 800 mm. The can fall to 6-7 °C with 20-25% rains usually break in the month of humidity. Rainfall: The average rainfall in Gautampura June, with the maximum number of is approx. 812 mm. Rains are due to rainy days experienced during the May is generally the hottest month southwest monsoons. The typical monsoon months of July and August. with the mean daily maximum season goes from mid-June to mid- temperature at about 40˚C. On September individual days, the maximum temperature may go above 44˚C or 45˚C. With the onset of monsoon in the district by the middle of June, there is an appreciable drop in temperature. After November there is

36 Initial Environmental Examination- Package 2A

Baseline Betma Depalpur Gautampura characteristics a rapid decrease in both day and night temperatures. January is the coldest month with the mean daily maximum temperature of about 26˚C and the mean daily minimum of 10˚C.

Surface water Kishanpura Pond: It is an earthen Chambal River is flowing in south River Chambal flows from the western side pond approximately 5 km away from east direction of the town at a of the town Gautampura. It is approximately Betma town. The total capacity of the distance of approximately 7 km from 1 km from the town. River is not perennial. pond is 2.845 mcm. Out of which the town. It is not a perennial river. Flow of the river ceases in the month of 2.493 mcm is used for irrigation. Dead November. storage capacity is 0.355 mcm. Pond Banedia Lake is second largest lake is also used for fisheries. There is no of Madhya Pradesh. It is situated provision for drinking water from this inside the Depalpur town limit. It is pond. having capacity of 6.43 MCM water. Gambhir River: River flows But the water has been authorized to approximately 15 km from Betma use for the irrigation purpose only town. Banks of river are deeper and and it is not good enough for the wider than Chambal River. Gambhir is drinking purpose. But it is the main not a perennial river. River flows ground water recharger to the mostly during monsoon, and flow surrounding aquifers. ceases in the months of December/January. Groundwater Private tube wells are extra deep As per the information provided Presently Gautampura water supply is ranging from 150 m to 300 m and under Central Ground Water Board based on ground water. There are 14 tube even more. The drawl from these report, the depth to water level map wells in the town. Water is drawn from these tubes well is very high. Hence ground tube wells. Most of the tube wells are in the (pre-monsoon 2006) reveals that the water source is not sustainable. As bank of Runi talab and artificial lake created per hydro geomorphologic map of the water levels in the range of 10-20 m near Chambal Bridge. Total 0.62 ML water is area prepared by National Remote bgl (meters below ground level) supplied at an average rate of 32 lpcd. But Sensing Agency, Department of occupy almost the entire Depalpur during the summer yield of these tube wells Space, Govt. of India, Hyderabad, the reduces considerably. Private tube wells are 37 Initial Environmental Examination- Package 2A

Baseline Betma Depalpur Gautampura characteristics recharge conditions in the area is Block. Observation of the depth to extra deep ranging from 150 m to 300 m and moderate. Rocks are plateau water level map (post monsoon even more. The drawl from these tubes well weathered type. 2006) reveals that a major part of the is very high. Hence ground water source is not sustainable. As per hydro district has water levels in the range geomorphologic map of the area prepared of 2-5 m bgl by National Remote Sensing Agency, Department of Space, Govt. of India,

Hyderabad, the recharge conditions in the area is good to moderate. Air quality No air quality data available, however, No air quality data available, No air quality data available, however, there there are no air pollution sources, however, there are no air pollution are no air pollution sources, except the dust, except the dust, which is mainly due sources, except the dust, which is which is mainly due to dry weather, activities to dry weather, activities like traffic mainly due to dry weather, activities like traffic movement. movement. like traffic movement. Ecological The project area –municipal area of The project area – municipal area of The project area –municipal area of Betma Nagar Parishad, comprises the Depalpur Nagar Parishad, comprises Gautampura Nagar Parishad, comprises the habitat areas of the town. There are the habitat areas of Depalpur town. habitat areas of Depalpur town. There are no ecologically sensitive features in There are no ecologically sensitive no ecologically sensitive features like forest the project area. Streams are features like forest in the project in the project area. Streams are seasonal, seasonal, so there is no noticeable area. Streams are seasonal, so there so there is no noticeable aquatic life. Flora aquatic life. Betma reserve forest is no noticeable aquatic life. Flora and fauna found in the area is of local located in southeast direction, about and fauna found in the area is of species 6-7 km from the town. None of the local species project components are located in or near the forest area. Flora and fauna found in the area is of local species

38 Initial Environmental Examination- Package 2A

Baseline Betma Depalpur Gautampura characteristics Economic The total municipal area is 8.8 sq km The total municipal area is 3.55 sq The total municipal area is 2.93 sq km out development and there are total 15 Wards in the km and there are total 15 Wards in of which developed land is approximately Land use municipal area. Out of which the municipal area. Out of which 27.1% and rest is undeveloped land which developed land is approximately 36%. developed land is approximately includes agriculture land (72.5%) and water Rest is undeveloped land which 39%. Rest is undeveloped land bodies (0.2%). includes agricultural land (54%). which includes agricultural land Among the developed land, residential (58%) and waterbodies (0.98 %). area occupies the major land share Among the developed land, which is 28% of the total area followed Residential area occupies the major by roads which is 5.48%. land share which is 25.8% of the total area followed by roads which is 5.48%. Slums occupy around 2.5% of area in Depalpur. There are 7 major slums in existence in Depalpur as per the information given by municipal officials. Nearly 65% percent of the total population lives in slums. Agriculture & The major economic activities in The primary economic activities in There is absence of major industries in industry the town are agriculture and the town are mainly agriculture Gautampura as per the information trade/commerce. Betma being an and trade / commerce. Depalpur provided by Gautampura Municipal important centre for agriculture being an important centre for Officials. Potato is the major crop harvested produce has enabled the agricultural produce has enabled in Gautampura and as a result some cold emergence of agri-industry related the emergence of Agri-industry storages have come up. However, many of activities. Apart from the people related activities. Majority of them are closed down. who are into administration, people are involved in agricultural The major economic activity in the town is majority of people are involved in produce, business, commerce and agriculture. Major agricultural production in agriculture produce, business, small scale industries. Depalpur Gautampura town is potatoes, wheat and commerce and small scale city comes under the Indore Agro soyabean. These products are exported to industry. Region for agriculture trade and Indore and Ujjain. market.

Wholesale business of agricultural products is one of the most 39 Initial Environmental Examination- Package 2A

Baseline Betma Depalpur Gautampura characteristics important activities of Depalpur town. Grains, pulses, sugarcane, wheat, rice, Groundnut, etc are major agricultural products of Depalpur. There is one agricultural market in Depalpur Infrastructure Roads are quite broad in most of the The old town areas of Depalpur town Roads are quite broad in most of the areas - transport areas of the Betma town. The main is characterized by very narrow of the Gautampura town. The main roads, roads, where there are commercial roads that are frequently congested where there are commercial and transport and transport activities, are congested with traffic and pedestrians. In activities, are congested with pedestrians, with pedestrians, traffic and activities. contrast the remainder of the town traffic and activities. The major modes of The major modes of transportation in has a relatively good road system, transportation in the city are cycle, the city are cycle, motorcycle and auto particularly in the outer areas, where motorcycle and auto rickshaws. Public rickshaws. Public modes of transport streets are wide and not heavily used modes of transport such as city bus, mini such as city bus, mini buses etc are by traffic. Roads are surface either buses etc are not prevalent in the city. There not prevalent in the city. There is with bitumen or concrete, and roads is no proper infrastructure for bus stand but no proper infrastructure for bus stand in the outer areas are mostly the connectivity of the town with other cities but the connectivity of the town with unpaved. Most of the roads are is good. other cities is good. maintained by respective municipal councils except the main roads connecting other towns and villages, which are maintained by the Public Works Department (PWD). Sewerage, Betma town does not have an Depalpur town have decentralized Betma town does not have an underground sanitation and underground sewage system. There is treatment provisions through sewage system. There is no sewage drainage no sewage treatment facility in the individual septic tanks and soak pits treatment facility in the town. The prevalent town. The prevalent sewerage at respective households. In sewerage systems generally practiced by systems generally practiced by the congested areas the road side drains the people in town is individual septic tanks people in town is individual septic are acting like open sewer drains and privately maintained by the respective tanks privately maintained by the most of the kitchen waste is directly households. Road side open drains cater to respective households. Road side disposed of in closed drains. These the runoff during rains, and due to lack of open drains cater to the runoff during drains are connected to the primary sewerage system, wastewater also disposed rains, and due to lack of sewerage drains (nallah) which ultimately into open drains. system, wastewater also disposed disposes the wastewater at Banedia 40 Initial Environmental Examination- Package 2A

Baseline Betma Depalpur Gautampura characteristics into open drains. Lake and open fields thereby contaminating the lake water and surrounding environment. Currently, nallah carries wastewater from the area of Sardar patel marg, Lala lajpat marg, Aza marg and flows through ganesh marg, ultimately merged into the Banedia Lake. Existing drainage supply network system is shown in Map enclosed with the report. Solid waste Town has an efficient system of waste Town has an efficient system of Town has an efficient system of waste management collection. Door to door collection is waste collection. Door to door collection. Door to door collection is done in done in all the wards between 8 am in collection is done in all the wards all the wards between 8 am in morning to 2 morning to 2 pm in afternoon. between 7 am in morning to 2 pm in pm in afternoon. Sweeping of roads and Sweeping of roads and cleaning of afternoon. Sweeping of roads and cleaning of drains is done in morning drains is done in morning and waste cleaning of drains is done in and waste is collected along road side. After is collected along road side. After morning and waste is collected along collecting the waste from different areas and road side. After collecting the waste different sources it is being transported with collecting the waste from different from different areas and different tractors/dumpers to the dumping site. Waste areas and different sources it is being sources it is being transported with is dumped by open dumping method; there transported with tractors/dumpers to tractors/dumpers to the dumping site. is no sanitary landfill facility. the dumping site. Waste is dumped by Waste is dumped by open dumping open dumping method; there is no method; there is no sanitary landfill sanitary landfill facility. facility. Demographic Population of the town as per 2011 Population of the town as per 2011 Population of the town as per 2011 census characteristics census is 15,999. census is 17,474 is 19,050.

Sex ratio – 951 (2011), Sex ratio – 947 (2011), Sex ratio – 962 (2011), literacy rate – 72 % (2011) literacy rate – 76.63 % (2011) literacy rate – 66.58 % (2011)

History, There is no heritage & archaeological Historically Depalpur is a Fort town Gautampura “place of meditation of Gautam culture & site in the town. (old Depalpur), where whole city Rishi” is famous for a unique age- old tourism reside inside the fort surrounded by tradition- Hingot festival. The festival is 41 Initial Environmental Examination- Package 2A

Baseline Betma Depalpur Gautampura characteristics guarding wall. One can find traces of associated with the religious belief and wall; it is believed that this fort was observed on ‘ Dhok Padwa’ – a day after part of Sindhiya Empire forming the in which warriors are categorized in border of state. New Depalpur area two groups, who attack each other with extended outside wall. There are burning hingots (a hollow fruit stuffed with however no notified/protected gun powder) that resembles flying missiles. monuments / archeological / There are however no notified/protected historical places in the town. monuments / archeological / historical places in the town.

42 Initial Environmental Examination- Package 2A

Figure 8: Area & Environs-Betma (a) Subproject area Environs- Betma

Proposed weir location

43

(b) Subproject area Environs- Betma

Figure 9: Subproject area Environs – Depalpur

44 Initial Environmental Examination- Package 2A

Figure 10: Subproject Environs- Gautampura

Proposed weir

Proposed WTP site

45 Initial Environmental Examination- Package 2A

C. Subproject Site Environmental Features

33. Features of the selected subproject sites are presented in the following table.

Table 7: Site Environmental Features – Betma Town S. Infrastructure Location & Environmental Site Photograph N Features o 1 Water Intake To enhance source reliability arrangements and sustainability, one Weir is proposed of about 6.5 m height and 60 m long at D/S side of Intake well. There will be no submergence or involvement of private land and asset due to construction of this work. Aquatic life of water pool to be taken care during construction activities in the river.

Proposed site for weir and intake well is approx. 14 km from the town in the north-east direction. Land is outside the town, surrounded by agriculture land. Land belongs to water resources department. Aquatic life in the location is limited to local species of fishes, and aquatic plants No notable sensitive features are found. 2 WTP with sump No trees are found. Open field, well (2.16 MLD at present no utilization. Land is and 1.65 KL outside the town, surrounded sump well) by agriculture land. The land belongs to Government of MP.

3 Transmission From proposed intake to WTP Network 14739 m long RWRM will be laid along the National highway and some part along the kuchha road. From WTP to the proposed OHTs, CWRM (4586 m) will be laid within the RoW. Transmission pipelines will be mostly laid along the main

46 Initial Environmental Examination- Package 2A

roads. Pipes will be laid underground.

4 Distribution Pipes will be laid within the road network (35142 right of way (ROW) - in road’s m) earthen shoulder in wider roads, and within the carriageway in narrow roads, where there is no space. Roads in the town are quite broad everywhere and pipelines can be laid easily by the side of road on the earthen shoulder. There are no trees along the road.

47 Initial Environmental Examination- Package 2A

Table 8: Site Environmental Features – Gautampura S. Infrastructure Location & Environmental Site Photograph N Features o 1 Weir, Intake To enhance source well cum pump reliability and sustainability, house one Weir is also proposed of about 5 m height from Bed level at D/S side of Intake well. There will be no submergence or involvement of private land and asset due to construction of this work.

In the bank Chambal River, there is proposed R.C.C. intake well of 6 m diameter and 11 m height H.F.L. and River bed level is 152.00 m and 134.00 m respectively. River bed is at 134.00 m keeping the invert level of intake well 4.5 m below the bed level of the river at 129.50 m.

3 Raw water It is proposed raw water Rising Main rising main of Dia. 250 mm DI K9 from intake to WTP along RoW of kuchha road and PWD road. Some part of RWRM comes under private land and third party negotiation has been conducted and a separate RP had been prepared for the same.

4 WTP with sump Prosed WTP site, sump well well and OHT and OHT constructed at vacant government land and there is no tree or scrub comes under proposed site.

48 Initial Environmental Examination- Package 2A

5 Clear water From WTP to three OHTs in transmission the Town by the side of road on its earthen bund covering total distance of 3302 meters.

6 Distribution Pipes will be laid within the network road right of way (ROW) - in road’s earthen shoulder in wider roads, and within the carriageway in narrow roads, where there is no space. Roads in the Gautampura are quite broad everywhere and pipelines can be laid easily by the side of road on the earthen shoulder. There are no trees along the road.

49 Initial Environmental Examination- Package 2A

Table 9: Site Environmental Features: Depalpur

S. Infrastructur Location & Environmental Site Photograph N e Features o 1 Weir To enhance source reliability and sustainability, one Weir is proposed of about 3 m height at D/S side of Intake well. There will be no submergence or involvement of private land and asset due to construction of this work. Aquatic life of water pool to be taken care during construction activities in the river.

2 Intake well Intake well will be built in Chambal River at right bank, under the control of Water Resources Department, GoMP.

3 Raw/Clear From proposed intake to WTP only water 175 m long RWRM will be laid along transmission the kuchha road. line CWRM of 6110 m has been proposed along PWD road. Transmission pipelines will be mostly laid along the main roads, the land owned by Govt; this land is vacant, and pipeline will be laid with the permission of ULB. Water from this pipeline will also be provided to ULB premises. There is no forest land within the prescribed limit of the town.

50 Initial Environmental Examination- Package 2A

7 WTP WTP of 2.40 MLD is proposed near the intake well site with CWS There is no involvement of Private/Forest land and tree cutting is not involved during construction.

7 Distribution Pipes will be laid within the road right network of way (ROW) - in road’s earthen (28672 m) shoulder in wider roads, and within the carriageway in narrow roads, where there is no space. Roads in the old part of the town are quite narrow and pipes will be laid mostly in the centre of the road. There is no forest land within the prescribed limit of the town. Hence there is no involvement of Forest land or required any permission for implementing this project. There is no tree cutting involved during construction period.

51 Initial Environmental Examination- Package 2A

VI. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

34. Potential environmental impacts of the proposed infrastructure components are presented in this section. Measures to minimize/mitigate negative impacts, if any, are recommended along with the agency responsible for implementation. Monitoring actions to be conducted during the implementation phase is also recommended.

35. Screening of potential environmental impacts are categorized into four categories considering subproject phases: location impacts and design impacts (pre-construction phase), construction phase impacts and operations and maintenance phase impacts.

a. Location impacts include impacts associated with site selection and include loss of on-site biophysical array and encroachment either directly or indirectly on adjacent environments. It also includes impacts on people who will lose their livelihood or any other structures by the development of that site. b. Design impacts include impacts arising from Investment Program design, including technology used, scale of operation/throughput, waste production, discharge specifications, pollution sources and ancillary services. c. Construction impacts include impacts caused by site clearing, earthworks, machinery, vehicles and workers. Construction site impacts include erosion, dust, noise, traffic congestion and waste production. d. O&M impacts include impacts arising from the operation and maintenance activities of the infrastructure facility. These include routine management of operational waste streams, and occupational health and safety issues.

36. Screening of environmental impacts has been based on the impact magnitude (negligible/moderate/severe – in the order of increasing degree) and impact duration (temporary/permanent).

37. This section of the IEE reviews possible project-related impacts, in order to identify issues requiring further attention and screen out issues of no relevance. ADB SPS (2009) require that impacts and risks will be analyzed during pre-construction, construction, and operational stages in the context of the project’s area of influence.

38. The ADB Rapid Environmental Assessment Checklist in http://www.adb.org/documents/guidelines/environmental_assessment/eaguidelines002.aspis used to screen project for environmental impacts and to determine the scope of the IEE.

39. In the case of this project (i) most of the individual elements are relatively small and involve straightforward construction and operation, so impacts will be mainly localized and not greatly significant;(ii) proposed water abstraction from the sources is very small compared to overall water availability since it is going to use the existing water source as well, and the proposed Weir designed for the balance requirement on at the rate of 70 lpcd as per norms, so there is no area coming in the submergence due to the construction of this Weir & is confined to river course itself; (iii) most of the predicted impacts are associated with the construction process, and are produced because that process is invasive, involving excavation and earth movements; and some works are located in the reservoir and (iv) being mostly located in an urban area, will not cause direct impact on biodiversity values. The proposed project components locations are belongs to the government property and existing roads, hence land acquisition and encroachment on private property will not happen in this case.

A. Pre-Construction Impacts – Design & Location

40. Design of the Proposed Components. Technical design of the (i) intake well, including Weir, (ii) water treatment plant; (iii) raw water and clear water transmissions mains (iv) over head tanks, and (v) distribution network, connections, flow meters, etc., follows the

52 Initial Environmental Examination- Package 2A

relevant national planning and design guidelines, focusing on providing a robust system which is easy to operate, sustainable, efficient and economically viable. Besides, the project also included the following environmental considerations:

(i) Weirs to be constructed as vented structures, with open rectangular vents and gates with sill level of weir just above the river bed; in this arrangement, on the sill there will be vertical slots to insert removable gates; gates will be closed prior to end of monsoon flows and opened prior to onset of heavy monsoon flows; this arrangement avoid silt accumulation and also prevents obstruction of heavy monsoon flows (ii) For weirs across perennial rivers, a sluice gate will be provided in weir structure to discharge minimum water to downstream needs during no weir overflow period - this is not applicable to this project as no perennial rivers are proposed for construction weirs (iii) Recovering backwash water from treatment process. (iv) Treatment and disposal management of sludge from treatment process. (v) Minimizing water losses from pipelines by perfect jointing and alignments using appropriate techniques (vi) Designing the entire system to maintain optimal flow and terminal pressure, and optimising the overall energy usage (vii) Reducing the incidence of water borne diseases by providing 100% population including urban poor with potable water supplies (viii) Improve water use efficiency and reduce water wastage at household level by recording and monitoring the water usage, and charging the consumers as per usage; due consideration to urban poor (ix) Minimize unaccounted for water (UFW) losses using district metered area approach with flow meter and pressure logging arrangements to identify and rectify the leaks, and unauthorized connections (x) Using low-noise and energy efficient pumping systems

41. Water Source & Sustainability. As the subproject towns are located far from each other (25-30 km) there was no possibility of a combined source/ bulk water scheme. Therefore, independent water supply schemes are proposed for 3 towns separately based on the most feasible water source considering techno-economic and environmental considerations. Source – (a) Depalpur Town 42. Sources available in the vicinity of the project area

(a) Chambal River: - Flowing in south east direction of the town. The river is flowing approximately 7 km from the town. River is not perennial. Due to small water catchment area, flow ceases immediately after the monsoon is over. For drawing of 2.40 MLD from the river a storage structure shall be required having sufficient capacity for storing water for the period of 6 months in a year. Thus the storage capacity required shall be 1.27 MCM.

(b) Yashwant Sagar Dam: -Situated at south east direction of the town. The Dam is the approximately 15 km away from the town. It has catchment area of 485 Sq. km. and having gross capacity of 15.96 MCM. The irrigation area attached to the Yashwant Sagar Dam is 1500 ha and the water required for irrigation purpose is 8 MCM. But it cannot spare any amount of water to Depalpur as it is already used as a major source for Indore and Hatod town water supply schemes.

53 Initial Environmental Examination- Package 2A

(c) Narmada River :-The perennial River Narmada is approximately 90 km away from Depalpur. Looking to the large distance and high pumping, bringing water from Narmada will be not only very high in terms of Capex but also in Opex.

(d) Banedia lake:- It is situated inside the Depalpur town limit. It is having capacity of 6.43 MCM water. But the water has been authorized to use for the irrigation purpose only and it is not good enough for the drinking purpose.

43. Most Suitable Source of Water Supply: Looking to above, Chambal River is most suitable dependable /sustainable surface source of water supply because of the less distance and pumping cost. However for supplying water from Chambal River all the year round, a weir is to be constructed in the river. For the reconnaissance survey is being carried out from 07/06/2015 to 11/06/2015 in the river. Looking to the banks and approachability, the most appropriate location for construction of weir is near Tamalpur Village. The maximum capacity of weir at full tank level (FTL), 498 m above msl, is coming as 1.94 MCM.

44. Out of the available gross capacity of proposed weir on Chambal River, 50% shall be the losses on account of evaporation, pilferage and seepage. Thus the net useful capacity shall be 0.85MCM available for water supply to Depalpur for during non-rainy season of 6 months every year for next 30 years. The net available useful capacity will be sufficient to supply water @ 70lpcd to the design population of Depalpur. Taking 70lpcd for design population the clear water requirement is 2.00 MLD. Taking 15% treatment and transmission losses, the gross water requirement is 2.40 MLD. Thus 2.40 MLD water is required for the proposed project. Figure 11: Location of Proposed Weir

54 Initial Environmental Examination- Package 2A

(b) Source- Gautampura Town

45. Sources available in the vicinity of the project area

(i) Ground Water Source:- Presently Gautampura water supply is based on ground water. There are 14 tube wells in the town. Water is drawn from these tube wells. Most of the tube wells are in the bank of Runi talab and artificial lake created near Chambal Bridge. Total 0.62 ML water is supplied at an average rate of 32 lpcd. But during the summer yield of these tube wells reduces considerably. Private tube wells are extra deep ranging from 150 m to 300 m and even more. The drawl from these tubes well is very high. Hence ground water source is not sustainable. As per hydro geomorphologic map of the area prepared by National Remote Sensing Agency, Department of Space, Govt. of India, Hyderabad, the recharge conditions in the area is good to moderate.

(ii) Surface Source:-River Chambal flows from the western side of the town Gautampura. It is approximately 1002 m from the town. Near Gautampura river is not perennial. Flow of the river ceases in the month of November. Total Water demand of the town is 0.69 MCM in Yr.2048 and storage required in during non rainy period is 0.55 MCM (water demand in Yr.2048 is 1.90 MLD, required storage capacity for 240 days with 20% losses is 0.55 mcm) in Yr.2048. Hence after survey and investigation near Chambal bridge (towards ward no . 6 ) an weir 5 m high, 100 m long is proposed. At 5 m height of weir required storage of water 0.55 MCM is found. Hence it is justified that Chambal river is suitable source. Contour of 484 m is within valley of river. Details of volume with contour height are given below.

Table 10:Details of volume with contour height- Gautampura Anicut

Volume in Cumulative Volume in Contour Area in sq m Volume in cum MCM MCM

479 4261.6

480 31582.0 17921.79 0.0179 0.01792

481 92898.7 62240.32 0.0622 0.08016

482 143364.3 118131.5 0.1181 0.19829

483 171528.8 157446.6 0.1574 0.35574

484 191443.0 181485.9 0.1815 0.55000

485 210163.3 200803.2 0.2008 0.75080

486 230095.9 220129.6 0.2201 0.97093

55 Initial Environmental Examination- Package 2A

(c) Source Sustainability and Downstream Impacts due to construction weirs across Chambal River for Depalpur and Gautampura Towns 46. River Chambal is identified as source of water for Depalpur and Gautampura towns, and it is proposed to construct one weir each for the towns across the rivers. Proposed Depalpur weir location across Chambal is about 7 km from Depalpur town. Gautampura weir location is about 18- 20 km downstream (length of river course) of Depalpur weir location. Total length of Chambal River is 960 km and the proposed weir at Depalpur is situated at about 65 km (river length) from its origin, and Gauthampura weir location is further downstream, about 18-20 km from Depalpur weir. Both these weirs are located in initial reaches of river. There is an existing weir / dam across Chambal River, about 20 km upstream of proposed weir at Depalpur

Figure 12: Location of Depalpur and Gautampura Weirs on Chambal

47. Chambal River. Chambal River is one of the major rivers of Northern India, and is a tributary of Yamuna River, forming part of Gangetic basin. River originates in Singal chouri peak, near town, on the northern slopes of Vindhya Range, in the state of Madhya Pradesh. River flows mostly south to north / north east in its course of 960 km – from its origin, for about 345 km, it flows in south north direction in the state of Madhya Pradesh and then in mostly northeastern direction for about 225 km in the State of Rajasthan. The river course after flowing through Rajasthan forms border between Rajasthan and Madhya Pradesh (for about 217 km), and then forms the boundary between Madhya Pradesh and Uttar Pradesh (for about 145 km). After this, the river flows through Uttar Pradesh for about 32 km before joining Yamuna River.

48. Chambal River is rain-fed, and known for pollution free fresh water, flowing through rugged terrain with a drop of 732 m from its origin to its confluence with Yamuna River over a length of 960 km. Of this about 300 m drop is within first 16 km of its course. With its

56 Initial Environmental Examination- Package 2A

catchment area of 143,219 sq. km, River Chambal is non-perennial in its initial courses, and as the catchment area contribution grows downstream, the river becomes perennial. Chambal, in its course of 960 km jointed by several of tributary rivers such as Shipra, Choti Kalisindh, Sivanna, Retam, Ansar, Kalisindh, Banas, Parbati, Seep, Kuwari, Kuno, Alnia, Mej, Chakan, Parwati, Chamla, Gambhir, Lakhunder, Khan, Bangeri, Kedel and Teelar. River flow varies considerably throughout the year with very high flows during monsoon to lowest flow in summer season. Average discharge of the river is about 450 m3 per second, maximum is around 2000 m3 per second, while minimum is in the range of 50-60 m3 per second.

49. The National Chambal Gharial Wildlife Sanctuary was established in 1970’s covering nearly 610 km of Chambal River from the downstream of Kota Barrage and up to its joining river Yamuna in Uttar Pradesh, across the three states to protect and conserve of critically endangered Gharial (Figure 1). The Chambal River sanctuary has good faunal biodiversity including 2 species of crocodilians – the mugger and gharial, several species of freshwater turtles, smooth-coated otters, gangetic river dolphins, skimmers, black-bellied terns, sarus cranes and black-necked storks. About 435 km section of Sanctuary, which includes about 60 km section of its tributary Parvati River, is under the jurisdiction of Madhya Pradesh. As stated above, proposed weirs at Depalpur and Gautampura are located in the initial course of river within 80 km from its course, and thus this location is almost 300 km upstream of sanctuary. Further, there are several major dams in this section of 300 m including , Rana Pratap Sagar Dam, Jawahar Sagar Dam, and Kota Barrage. Therefore the proposed weir location has no real significance with respect to Chambal Sanctuary. Figure 13: Location of National Chambal Sanctuary

57 Initial Environmental Examination- Package 2A

Figure 14: Location of Existing Dams on Chambal River and Chambal Sanctuary

Proposed Weir location

Figure 15: Chambal Sanctuary & Existing / Proposed Dams on Chambal River

50. River flow, source sustainability and downstream impacts. There are no flow- gauging stations located in or close to this stretch. River in this stretch, as per the

58 Initial Environmental Examination- Package 2A

information from local people and water resource department officials, given its limited catchment and rain-fed nature, is not perennial. The river is perennial in the medium and lower reaches. In the initial section, the river flows for about six to seven months in a year; flow usually starts with the southwest monsoon rains in late June / July and continues throughout post monsoon, northeast monsoon season (October-November) and up to January. Flow completely recedes from late January/February to onset of monsoon in late June/July. Flow also fluctuates considerably, with very high flows in the months of July and August, high flows in the months of September and October, medium flows in November to December, to a very low flow in January before complete dries out by end of January or February.

51. In the absence of flow records, the engineer’s estimate of volume of water availability is based on catchment area and rainfall analysis. As per the estimate presented below (see Table below), total water availability at the weir site is 338.7 MCM. Following Figure shows the catchment area of the river, up to the proposed weir site at Gautampura. Total catchment area is 1,243 sq. km, which is just about just 0.87% of the total river catchment area.

Figure 16: Catchment area of weir at Gautampura

52. There is an existing stop dam / check dam on 20 km upstream, and other than this there are no water holding structures or major water abstraction points in the river upstream. The proposed yearly water abstraction for both Depalpur and Gautampura is 1.82 MCM (1.27 + 0.55 MCM), which is just a fraction (about 0.53%) of total yearly water availability in the catchment, i.e. 338.7 MCM. This abstraction is negligible and not likely to

59 Initial Environmental Examination- Package 2A

have any impacts downstream. There are also no notable water abstraction points or users in the immediate downstream of the proposed weirs. There is one small village named Jalodiya located at about 2 km. River is not perennial, and flows for about 6 to 7 months a year, and the remaining 5 to 6 months it goes completely dry. With the construction of proposed weir with a small storage capacity with a fraction of total water availability in the river as stated above, there will be any notable changes in the flow regime is not going to change this flow regime post construction. Table 11: Catchment Area – Rainfall based Water Yield Estimate in Chambal River at Proposed Gautampura Weir Site Gautampura weir site 1 Catchment area (A) = 1243 Sq Km 2 Average rain fall (Maximum) (I) = 750 Mm 3 Average rain fall (Minimum)(I) = 450 Mm 4 Run off coefficient = 0.61 Assuming 50% covered and 50% uncovered = 5 Formula = AIR I Maximum rainfall = (1234X1000X1000X0.75X0.61) cum = 568672500 cum = 568.67 MCM Minimum rainfall = 338733000 cum Total Available water = 338.733 MCM

53. Ecological impacts. Although Chambal River, which is 960 km long and perennial in its mid and lower reaches with considerable ecological value and rich river aquatic fauna species as described above, in the upper reaches close to the source where the weirs are proposed is not the same. It flows intermittently and goes completely dry for about 5-6 months a year. There is no notable, protected or unique aquatic life in the river, and the fish is limited to local varieties. There is no commercial fishing taking place in this stretch of the river. As it is unlikely to have any notable changes in the river flow regime no impacts envisaged on downstream users or river ecosystem, due to construction of proposed weir. The proposed impoundment, in fact, is likely to benefit the environment through groundwater recharge and propagating aquatic life. Also, there is an already an existing check dam/weir, about 20 km upstream side of the proposed weir, and several minor and major dams in the downstream course, therefore no further impacts envisaged on river ecosystem such as maintaining physical processes and habitats downstream (include movement of fishes and sediment trapping etc., due to creation of new structure).

54. Moreover, it is proposed that weir will be constructed as vented structures, with open rectangular vents and gates; sill level of weir will be just above the river bed. On the

60 Initial Environmental Examination- Package 2A

sill there will be vertical slots to insert removable gates; gates will be closed prior to end of monsoon flows and opened prior to onset of heavy monsoon flows; this arrangement avoids silt accumulation and also prevents obstruction of heavy monsoon flows. Typical cross section of proposed weir is given below. As the package is implemented under DBO mode, the detailed design of weir will be conducted by the contractor after award of the contract.

55. Weir storage /submergence area: Following Figures shows the weir storage / submergence area of Depalpur and Gautampura weirs. The height of weir in both the cases is less than the height of the river banks, and therefore the water storage is confined to river course / flood plain, and there is no submergence of lands outside the river. Total water storage / submergence area at weir height is calculated as 19 ha in Gautampura and 61.3 ha in Depalpur., which is fully in the river. No negative impacts or acquisition of government of private or government lands anticipated.

Figure 17: Gautampura Weir Submergence Area

61 Initial Environmental Examination- Package 2A

Figure 18: Depalpur Weir Submergence Area

62 Initial Environmental Examination- Package 2A

(d) Betma Town 56. Source Identification : There are three surface sources near Betma town:-

(i). Kishanpura Pond:- It is earthen pond approximately 5 km away from the Betma town. The total capacity of the pond is 2.845 mcm. Out of which 2.493 mcm is used for irrigation. Dead storage capacity is 0.355 mcm. Fisheries are also done in this pond. There is no provision for drinking water from this pond. Also it is difficult to curtail agriculture for drinking purpose. This may arise farmer agitation. Hence it can’t be taken as water source for Betma town. (ii). Chambal River: There is Chambal River near Betma. Ghata Bilod in Betma road is nearest point from Betma town where Chambal river flows. It originates from Janapav mountain. (iii). Gambir River: - The another side of Betma town nearly 15 km in Betma Indore road there is a Gambhir River. The bank of river is deeper and wider than Chambal River. Gambhir River is not perennial. Flow of the river ceases in the month of November December. But there is possibility of getting sufficient storage of water by constructing weir on this river. Details of water demand at different stage during non rainy period are given below- Total water demand at intermediate stage (Yr.2033) -1.98 MLD (0.57 mcm for 240 days with 20% losses). Total water demand at ultimate stage (Yr.2048)- 2.47 MLD ( 0.71 mcm 240 days with 20% losses). Total water demand for Yr.2068- 3.20 MLD (0.92 mcm 240 days with 20% losses). After survey and investigation at Gambhir river an anicut 6.5 m high, 60 m long is proposed. At 5.5 m height of weir storage of water 0.55 mcm is found. It will fulfill water requirement till year 2030. The source of the Betma WSS is based on the river Gambhir . The river Gambhir is not the perennial river.. The flow data is not available as there is no flow gauge has been installed. As per information gathered from the local authority The flow in the river reduced in the month of the Nov. to December and gets dry after January. .

Table 12:Details of volume with contour height- Anicut Betma

Volume in Cumulative Contour Area in sq m Volume in cum MCM Volume in MCM

524 5099.799

525 25627.88 1536 3.84 0.015 364 0.0153 6384

526 50417.62 38022.75 0.038023 0.05338659

527 77568.47 63993.04 0.063993 0.11737963

528 106888 92228.22 0.092228 0.20960785

63 Initial Environmental Examination- Package 2A

529 131338.4 119113.2 0.119113 0.32872103

530 154445.2 142891.8 0.142892 0.47161281

Figure 19: Google map showing Upstream and Downstream stretch of Gambhir River

64 Initial Environmental Examination- Package 2A

(e) Source Sustainability and Downstream Impacts due to construction weir across Gambir River for Betma Town

57. Gambhir River originates from Janapav near Mhow town in Vindyan mountain range. It is a tributary of which in turn is a tributary of River Chambal. Gambhir River mostly flows south to north, and join Shipra River in Ujjain City. Shipra River joins Chambal River at Madhya Pradesh Rajasthan border in Mandasaur District. Total length of Gambir River from its origin to its joining Shipra River in Ujjain is 288 km, and its course is completely in the state of Madhya Pradesh. Proposed weir is located across Gambhir River near Kalariya village, about 12 km from Betma town. This location is about 33 km from the origin. There is a small weir about 5 km of upstream of proposed weir location. There are also small dams/weirs in its downstream course before it joins Shipra River near Ujjain.

58. River flow, source sustainability and downstream impacts. There are no flow- gauging stations on this river. River is rain-fed and is not perennial. The river flows for about five to six months in a year; flow usually starts with the southwest monsoon rains in late June / July and continues throughout post monsoon, northeast monsoon season (October-November) and up to December. Flow completely recedes from late December / January to the onset of monsoon in late June/July. Flow also fluctuates considerably, with high flows in the months of July and August, medium flows in the months of September and October and low flows in November to December, before complete dries out by mid or end of December.

59. In the absence of flow records, the engineer’s estimate of volume of water availability is based on catchment area and rainfall analysis. As per the estimate presented

65 Initial Environmental Examination- Package 2A

below, total water availability at the weir site is 51.8 MCM. Figure 1 shows the catchment area of the river, up to the proposed weir site at Betma. Total catchment area at weir site is calculated as 189 sq. km.

Figure 20: Catchment area of weir at Betma

60. The proposed yearly water abstraction is 0.72 MCM, which is just a fraction (about 1.4%) of total yearly water availability in the catchment (i.e.51.8 MCM). This abstraction is negligible and not likely to have any impacts downstream. There are also no notable water abstraction points or users in the immediate downstream of the proposed weirs. There is one small village named Jalodiya located at about 2 km. River is not perennial, and flows for about 6 to 7 months a year, and the remaining 5 to 6 months it goes completely dry. With the construction of proposed weir with a small storage capacity with a fraction of total water availability in the river as stated above, there will be any notable changes in the flow regime is not going to change this flow regime post construction. Table 13: Catchment Area – Rainfall based Water Yield Estimate in Gambir River at Proposed Betma Weir Site S. No Parameters Vaue Units 1 Catchment area (A) = 189 Sq Km 2 Average rain fall (Maximum) (I) = 750 Mm 3 Average rain fall (Minimum)(I) = 450 Mm 4 Run off coefficient = 0.61

66 Initial Environmental Examination- Package 2A

Assuming 50% covered and 50% uncovered = 5 Formula = AIR i Maximum rainfall = (189X1000X1000X0.75X0.61) cum = 86467500 cum = 86.4675 MCM Minimum rainfall = 51880500 cum Total Available water = 51.8805 MCM

61. Ecological impacts. Gambir River is not a perennial river, and runs completely dry for 6-7 months in year. There are no notable sensitive environmental features in the river. There is no notable, protected or unique aquatic life in the river, and the fish is limited to local common species. There is no commercial fishing taking place. As there are unlikely to be any notable changes in the river flow regime, no impacts envisaged on downstream users or river ecosystem. The proposed impoundment, in fact, is likely to benefit the environment through groundwater recharge and propagating aquatic life. Also, there are already existing dams/weirs, on the upstream and downstream course of the river, therefore no further impacts envisaged due to proposed weir. It is proposed that weir will be constructed as a vented structure, with open rectangular vents and gates; sill level of weir will be just above the river bed. On the sill there will be vertical slots to insert removable gates; gates will be closed prior to end of monsoon flows and opened prior to onset of heavy monsoon flows; this arrangement avoids silt accumulation and also prevents obstruction of heavy monsoon flows. Typical cross section of proposed weir is given below. As the package is implemented under DBO mode, the detailed design of weir will be conducted by the contractor after award of the contract.

62. Weir storage /submergence area: The following Figure shows the weir storage / submergence area of proposed Betma weir. The height of weir is less than the height of the river banks, and therefore the water storage is confined to river course / flood plain, and there is no submergence of lands outside the river. Total water storage / submergence area at weir height is calculated as 13.1 ha, which is fully in the river. No negative impacts or acquisition of government of private or government lands anticipated.

67 Initial Environmental Examination- Package 2A

Figure 21: Betma Weir Submergence area

68 Initial Environmental Examination- Package 2A

63. Source water quality & pollution sources. Current water quality is suitable for drinking water after conventional treatment and disinfection, and as there are no notable pollution sources in the upstream near the intake, there is no likely risk of source contamination. However, there is a need to check on future development to avoid contamination of source.

64. Water Quality of Source: The catchment areas of all the three towns are mostly characterized by agricultural and barren lands. There are no polluting sources like industries or mining in the catchment areas. Habitations are limited to small villages, there is no major town located in the catchment. All the parameters of water quality in comparison with drinking water standards are well within the limits, hence Convention water treatment and disinfection, which is proposed in the project, is adequate to make the water usable for drinking purposes.

Table 14: Source Water Quality Parameters Gambhir River Chambal River Permissible (proposed weir (proposed weir Limit location) location) pH 7.25 8.34 6.5-8.5 Turbidity, NTU 28 48 1-5 Appearance Clear Turbid - Odour Odourless Odourless Agreeable Chlorides (mg/l) 37 29 25 Nitrate mg/l 2.53 4.40 45 Total hardness (mg/l) 156 188 200-600 Ca Hardness as 92 24 75-200 CaCO3 Sulphate mg/l 3.50 63.84 200-400 Fluoride (mg/l) 1.28 0.947 1.0-1.5 Iron (as Fe), mg/l ND ND 0.3 Manganese (as Mn), ND 0.132 0.1-0.3 mg/l Source: Sampling Survey 2016 by DPR consultant

65. Use of Chlorine as disinfectant. Treatment of water is one of the important functions executed in all water works. In this different operations are carried out for making the raw water obtained from various sources fit for uses to which it is to be put up i.e. domestic, industrial or for fire fighting. The actual operation to be carried out, their sequence and the results to be accomplished depend upon the quality of raw water to be treated and the standards of purification to be obtained. Analysis of raw water of river Chambal and Gambhir river reveals that no special treatment is required except nominal flocculation and filtration followed by chlorination. This is to be constructed for the requirement of intermediate stage. According to the anticipated population in the year 2033, the capacity of water treatment plant required is given above. Hydraulic design, line diagram and layout plan is attached. The sludge created in washing of different

69 Initial Environmental Examination- Package 2A

components of the treatment plant units will be treated in the campus by constructing a small aeration tank. The cost of this unit is included in the estimate.

66. Sensitive project locations. None of the subprojects are surrounded by forest areas, which are of open mixed or dense mixed type jungles that are under reserved, protected or unclassified categories. None of the subproject components are located in the forest areas, nor is any pipeline aligned through the forests. This will be further verified and ensured during the detailed design phase.

67. Similarly proposed works in the river bed (for dam and intake) may damage the river bed, lead to degradation of water quality due to increase in turbidity and contamination from fuels and lubricant used in construction work. Increase in silt content and water turbidity, chemical quality can affect the aquatic life. Measures are included in the EMP to avoid, minimize these impacts.

68. Removal of trees and vegetation will be minimize by best alignment and layout planning of facilities, however, this cannot be avoided fully. Appropriate measures in terms of compensatory tree plantation is included in the EMP.

69. Utilities. Telephone lines, electric poles and wires, water lines within the proposed project locations may require to be shifted in few cases. To mitigate the adverse impacts due to relocation of the utilities, the contractor, in collaboration with ULB will be required to implement appropriate measures. These are given in the EMP.

70. Site selection of construction work camps, stockpile areas, storage areas, and disposal areas. Priority is to locate these near the project location. However, if it is deemed necessary to locate elsewhere, sites to be considered will not promote instability and result in destruction of property, vegetation, irrigation, and drinking water supply systems. Residential areas will not be considered for setting up construction camps to protect the human environment (i.e., to curb accident risks, health risks due to air and water pollution and dust, and noise, and to prevent social conflicts, shortages of amenities, and crime). Extreme care will be taken to avoid disposals near forest areas, water bodies, or in areas which will

71. Site selection of sources of materials. Significant quantities of coarse aggregate and fine aggregate will be required for construction works. Requirement of gravel is limited. Contractor should procure these materials only from the quarries permitted/licensed by Mines and Geology Department. Contractor should, to the maximum extent possible, procure material from existing quarries, and creation of new quarry areas should be avoid as far as possible. It will be the construction contractor’s responsibility to verify the suitability of all material sources and to obtain the approval of Department of Mines & Geology and local revenue administration.

B. Construction Impacts 72. Construction works. Civil works in the project include linear excavation for laying pipes along the roads, placing pipes in the trench and refilling with the excavated soil. The trenches will be of 0.4 m – 0.7 m wide and 0.8 to 1 m depth. Subsequent to completion of works, road reinstatement will be undertaken by the contractor as part of the civil works. The roads in the core city area of all the towns are very narrow and congested with pedestrians and vehicles (mainly 2-wheelers), while the roads in outer areas are wide.

73. Earth work excavation will be undertaken by machine (backhoe excavator) or manually and include danger lighting and using barricades at every 100 m.. Sufficient care will be taken while laying so that existing utilities and cables are not damaged and pipes are not thrown into the trenches or dragged, but carefully laid in the trenches. As trenches are a maximum of 1.2 m, there is no risk of collapse of trenches or risk to surrounding buildings. Once they are laid, pipes will be joined as per specification and then tested for any cracks of leakages. The

70 Initial Environmental Examination- Package 2A

minimum working hours will be 8 hours daily, the total duration of each stage depends on the soil condition and other local features. About 95% of the excavated soil will be used for refilling the refilling the trench after placing the pipe and therefore residual soil after pipe laying and refilling is not significant. This excel soil shall be used for construction.

74. Other civil works in the subprojects include construction of Weir across river Chambal in Depalpur and Gautampura and Gambhir in Betma, intake cum pump house on the river bank, raw water pumping station including laying of water intake pipe, water treatment plants, overhead tanks identified sites. These works will be confined to sites, and construction will include general activities like excavation for foundation, construction of foundations, columns, walls and roof in cement concrete and masonry, and fixing of mechanical and electrical fixtures, etc.

75. Although construction of these project components involves quite simple techniques of civil work, the invasive nature of excavation and the project locations in the built-up areas of the town where there are a variety of human activities, will result in impacts to the environment and sensitive receptors such as residents, businesses, and the community in general. The following are anticipated impacts, which are temporary and for short duration:

(i) Dust and air emissions from construction activities and equipment / vehicles affecting the ambient air quality (ii) Impacts on natural drainage, surface water bodies due to disposal of construction waste and silt / chemical laden run off from work areas (iii) Impacts on river eco-system due to river bed construction (iv) Impacts due to disposal of surplus soil, construction waste, debris etc., (v) Impacts due to noise and vibration from consultation activities (vi) Impacts due to collection of groundwater in trenches & disposal of the same (vii) Impact/public inconvenience/ accessibility issues due to excavation on public roads (narrow old town roads), movement of trucks carrying construction material (viii) Impacts on business, activities, people due to loss/restricted access to public/private/business/sensitive areas (schools, hospitals), etc., (ix) Occupation health and safety impacts on workers (x) Health Impacts due to removal of existing AC (asbestos cement) pipes (xi) Community health and safety impacts due to construction in an urban area (xii) Impacts due to establishment/operation of temporary construction camps

76. The above impacts are typical for construction in urban areas, and therefore are common to all the three subproject towns. These are negative but short-term and reversible by mitigation measures. There are well-developed and proven measures and construction practices to avoid, mitigate and/or minimize these impacts to acceptable levels. These measures are given in the construction phase EMP applicable to all three towns.

D. Operation and Maintenance Impacts

77. Operation and Maintenance of the water supply system will be carried out by the DBO Contractor for 10 years, and after which the respective municipalities will operate and maintain the infrastructure. During the system design life (15/30 years for mechanical/civil components),it shall not require major repairs or refurbishments and should operate with little maintenance beyond routine actions required to keep the equipment in working order. The stability and integrity of the system will be monitored periodically to detect any problems and allow remedial action if required. Any repairs will be small-scale involving manual, temporary, and short-term works involving regular checking and recording of performance for signs of deterioration, servicing and replacement of parts.

71 Initial Environmental Examination- Package 2A

78. Recurrence of pipe bursting and leakage problems can be managed by the leak detection and water auditing surveys. The ULBs will be required to ensure that the leak detection and rectification time is minimized.

79. Provision for recirculation system for filter backwash – backwash water from filter beds will be sent to a storage tank, and after allowing adequate time for settlement of solids, clarified water will be pumped to WTP inlet. This arrangement will avoid pollution and also minimize wastage of water. Water treatment process will generate sludge from sedimentation of particulate matter in raw water, flocculated and precipitated material resulting from chemical coagulation, residuals of excess chemical dosage, plankton etc; and waste from rinsing and back washing of filter media containing debris, chemical precipitates, straining of organic debris and plankton. Accumulated sludge from Tube Settler, filter backwash etc., will be disposed-off at sludge drying beds for natural drying. Dried sludge will be disposed off in a land fill or used as soil conditioner if it is suitable

E. Project benefits

80. During the construction phase, there are likely to be positive impacts through employment generation, increase in local revenue from the project activities. During the operation phase also, there is potential for employment generation, though limited, as the improved and expanded water infrastructure requires additional workforce.

81. The citizens of Betma, Depalpur and Gautampura will be the major beneficiaries of the improved water supply system, as they will be provided with a constant supply of better quality water, piped into their homes at an appropriate pressure. The project will improve the over-all health condition of the towns as water borne diseases will be reduced, so people should spend less on healthcare and lose fewer working days due to illness, so their economic status should also improve, as well as their overall health. This should also improve the environment of these areas, should deliver major improvements in individual and community health and well-being.

72 Initial Environmental Examination- Package 2A

VII. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE

A. Overview

82. The active participation of stakeholders including local community, NGOs/CBOs, and the media in all stages of project preparation and implementation is essential for successful implementation of the project. It will ensure that the subprojects are designed, constructed, and operated with utmost consideration to local needs, ensures community acceptance, and will bring maximum benefits to the people. Public consultation and information disclosure is a must as per the ADB policy.

83. Most of the main stakeholders have already been identified and consulted during preparation of this IEE, and any others that are identified during project implementation will be brought into the process in the future. Primary stakeholders of the subproject are: residents, shopkeepers and businesspeople who live and work alongside the roads in which network improvements will be provided and near sites where facilities will be built (WTP and water tanks), and government and utility agencies responsible for provision of services in all the three towns, and Madhya Pradesh Pollution Control Board. Secondary stakeholder are: NGOs and CBOs working in the area, community representatives, beneficiary community in general, government agencies, the executing and implementing agencies (MPUDC, PMU and PIUs), Government of India and the ADB.

B. Public Consultation

84. The public consultation and disclosure program is a continuous process throughout the project implementation, including project planning, design and construction.

1. Consultation during Project Preparation

85. Institutional consultations were conducted with the Governmental Departments such as PMU, Pollution Control Board, Public Health Engineering Department, Water Resourced Department, ASI and Forest Department etc. The subproject proposal is formulated in consultation with all the three Nagar Parishads and suit the requirements of the ULBs.

86. Focus-group discussions with affected persons and other stakeholders were conducted to learn their views and concerns. A socio economic household survey has been conducted in the town, covering sample households, to understand the household characteristics, health status, and the infrastructure service levels, and also the demand for infrastructure services. General public and the people residing along the project activity areas were also consulted during visits to the project sites. A consultation meeting was conducted in December 2015 with NGOs actively working in Indore district. Details of the public consultations are provided in following Tables and Appendix 7.

87. It was observed that people are willing to extend their cooperation as the proposed activities are proposed to enhance the infrastructure service levels and the living standard of the public. The public expressed their concern regarding the nuisance and disturbance (dust, road closure and traffic management activities), which may affect the health and their livelihood.

73 Initial Environmental Examination- Package 2A

Table 15: Summary of Consultations with Stakeolders- Depalpur Nagar Parishad Date Location No. of Participant Topic Discussed Issue raised Participants 11th May At Total=26 UlB Chairman & • The Water Supply Project Background, • The Chairman of the ULB 2018 Community y M=21, F=4 Vice Chairman, Environmental, Social, traffic safety issue expressed willingness to accept hall, Nagar ULB Sub Engineer, and benefit from the project were explained the project; Parishad Asstt. Sub to the Stakeholders. • Willingness to connect to piped • Present drinking water supply source and drinking water supply; engineer, ULB its condition • Depalpur Nagar Parishad is Staff, • Need of improvement of the present operating water supply system for Representative of situation the town but capacity to be build. Member of • Briefing on project objectives probable Parliament (MP), implementation procedures • The existing water supply system Ward Parshads & • Potential positive and negative impacts due is in dilapidated condition and needs refurbishment along with local peoples to project implementation • Land use and area to be covered under the water supply coverage (100 project percent). • Drinking water user charge • Land required for the water supply • Grievance Redress procedures project will be dealt by the ULB and they will handle this with the • Improvement in environment, health and concerned government hygiene etc. departments. • Prior information is required before start of • community participation in project the civil works in the respective ward implementation; • Operation and maintenance is covered • Implementing agency; and better under the subproject and ensure community /improved service. participation • Operation and maintenance of the • Assured full support during execution. facilities developed under the • During excavation for dust and traffic project and community management assurance given to the participation; business community • Probability of keeping the poor and

the vulnerable out of the user charge. • Public notice to be circulated,

74

construction should be completed in the given time, debris • For Safety of Local traffic and pedestrian in Built-up Zone, fencing should be provided.

11th Ward No. 8, Total=19 Slum area • Briefing on project objectives probable • None of the people knew about the May.2018 Nehru Marg M=5, F=14 implementation procedures proposed project. • Potential positive and negative impacts due • On learning about the project, they to project implementation expressed that they were happy • Experiences sharing on - livelihood that the entire community would be activities, Resettlement and Rehabilitation, benefited from the upgraded water women empowerment tribal development, supply. health, education, convergence with • Assured full support during existing government social security implementation. schemes etc. • Agreed on taking water • Grievance Redress procedures connections but user charges to be reduced for slum people.

11th May Ward No. 10, Total=40 Community People • Status of existing drinking water supply • The area has insufficient and 2018 Ayodhya M=10, F=30 system; inadequate drinking water Basti • Need for improvements to present system; resource. Water supply to the area • Relevant information of the upcoming is done through tube wells that project and benefits of the project. supplies water to the community • Potential positive and negative impacts due people. The area faces severe to project implementation water crisis during the summer • Ensuring no income loss season when the ground water • Grievance Redress procedures level drops. • Experiences sharing on - livelihood • The community willingly accepted activities, Resettlement and Rehabilitation, the project. The community women empowerment tribal development, members expressed that their health, education, convergence with economic situation would prevent existing government social security them from paying water user schemes etc. charges. (The men work as daily laborers and the women

75 Initial Environmental Examination- Package 2A

Housewives). In 216 - Total =10 Community People • Status of existing drinking water supply • The area has insufficient and M=10, F=0 system; inadequate drinking water • Need for improvements to present system; resource. Water supply to the area • Relevant information of the upcoming is done through two tube wells that project and benefits of the project. supplies water to the community • Potential positive and negative impacts due people. The area faces severe to project implementation water crisis during the summer • Ensuring no income loss season when the ground water level drops. • The community willingly accepted the project. The community members expressed that their economic situation would prevent them from paying water user charges. (The men work as daily laborers and the women Housewives).

76 Initial Environmental Examination- Package 2A

Table 16:Summary of Consultations with Stakeholders- Gautampura Nagar Parishad

Date Location No. of Participant Topic Discussed Issue raised Participant 11nd At ULB Office Total = 13 CMO, ULB official, Sub The Water Supply Project • CMO has concern that the project financial May Engineer, Ward Background, Environmental, Social, burden Nagar Palika able to handle or not M= 8, F= 5 2018 Parshads/ Elected GRM, traffic safety issue and benefit • The Chairman of the ULB expressed representatives & local from the project were explained to the willingness to accept the project; peoples Stakeholders. • Willingness to connect to piped drinking water supply; • Present drinking water supply • Gautampura Nagar Parishad is operating source and its condition water supply system for the town but • Need of improvement of the present capacity to be build. situation • community participation in project • Briefing on project objectives implementation; probable implementation • Implementing agency; and better /improved procedures service. • Potential positive and negative • Operation and maintenance of the facilities impacts due to project developed under the project and implementation community participation; • Land use and area to be covered • Probability of keeping the poor and the under the project vulnerable out of the user charge. • Drinking water user charge

77 Initial Environmental Examination- Package 2A

11th Ward No. 06 Community People The Water Supply Project • The area has insufficient and inadequate May Bhoi Mohalla Total = 12 Background, Environmental, Social, drinking water resource. Water supply to 2018 GRM, traffic safety issue and benefit the area is done through two tube wells M= 8, F= 4 from the project were explained to the that supplies water to the community Stakeholders. people. The area faces severe water crisis during the summer season when the • Status of existing drinking water ground water level drops. supply system; • The community willingly accepted the • Need for improvements to present project. The community members system; expressed that their economic situation • Relevant information of the would prevent them from paying water user upcoming project and benefits of charges. (The men work as daily laborers and the women Housewives). the project. • Potential positive and negative impacts due to project implementation Ensuring no income loss 11th Ward No. 10 Total = 13 Community people • Briefing on project objectives • None of the people knew about the May Bagh Mohalla probable implementation proposed project 2018 M= 5, F= 8 procedures • On learning about the project, they • Potential positive and negative expressed that they were happy that the impacts due to project entire community would be benefited from implementation the upgraded water supply. • Experiences sharing on - livelihood • Assured full support during activities, Resettlement and implementation. Rehabilitation, women empowerment tribal development, health, education, convergence with existing government social security schemes etc. • Grievance Redress procedures

78 Initial Environmental Examination- Package 2A

11th Ward No. 05 Total = 14 Community People The Water Supply Project • The area has insufficient and inadequate May Background, Environmental, Social, drinking water resource. Water supply to 2018 Sarvi Mohalla M= 6, F= 8 traffic safety issue and benefit from the area is done through two tube wells the project were explained to the that supplies water to the community Stakeholders. people. The area faces severe water crisis during the summer season when the • Status of existing drinking water ground water level drops. supply system; • The community willingly accepted the • Need for improvements to present project. The community members system; expressed that their economic situation • Relevant information of the would prevent them from paying water upcoming project and benefits of user charges. (The men work as daily the project. laborers and the women Housewives). • Potential positive and negative • As excavation not been able to done at impacts due to project night because labour will not get agree to implementation work in night shift so shifting will be done • Ensuring no income loss at a vacant place near or next lane such • Community participation in project that no income loss takes place due the implementation civil work. Vendors get agreed on proposal

• Completion of project on time. • shifting of Street vendors. • Shifting or adjusting extended potion of shopkeepers. 2016 At Parishad Chairperson of ULB, The Water Supply Project • ULB Chairman has concern that the project Hall, Ward Parshads/ Background, Environmental, Social, financial burden Nagar Palika able to Gautampura Elected representatives traffic safety issue and benefit from handle or not the project were explained to the & local peoples • The Chairman of the ULB expressed Stakeholders. willingness to accept the project; • Present drinking water supply • Willingness to connect to piped drinking source and its condition water supply; • Need of improvement of the present • Gautampura Nagar Parishad is operating situation water supply system for the town but • Briefing on project objectives

79 Initial Environmental Examination- Package 2A

probable implementation capacity to be build. procedures • community participation in project • Potential positive and negative implementation; impacts due to project • Implementing agency; and better /improved implementation service. • Land use and area to be covered • Operation and maintenance of the facilities under the project developed under the project and Drinking water user charge community participation; • Probability of keeping the poor and the vulnerable out of the user charge.

Table 17: Summary of Consultations with Stakeholders- Betma Nagar Parishad Date Location Participant Topic Discussed Issue raised 8th At Nagar Total Chairperson of ULB, The Water Supply Project Background, • ULB Chairman has concern that the project May. Parishad = 20 CMO, Ward Parshads Environmental, Social, traffic safety issue financial burden Nagar Palika able to handle or 2018 Office , DBO Contractor, PIU and benefit from the project were not M = PMC Indore explained to the Stakeholders. • The Chairman of the ULB expressed willingness 15, to accept the project;

F = • Willingness to connect to piped drinking water 05 • Present drinking water supply source supply; and its condition • Betma Nagar Parishad is operating water supply • Need of improvement of the present system for the town but capacity to be build. situation • community participation in project • Briefing on project objectives probable implementation; implementation procedures • Implementing agency; and better /improved • Potential positive and negative impacts service. due to project implementation • Operation and maintenance of the facilities • Land use and area to be covered under developed under the project and community the project participation; • Drinking water user charge • Probability of keeping the poor and the

80 Initial Environmental Examination- Package 2A

vulnerable out of the user charge.

8th Ward No. 01 Total Community People • Briefing on project objectives probable • None of the people knew about the proposed May = 21 implementation procedures project. On learning about the project, they 2018 • Potential positive and negative impacts expressed that they were happy that the entire M = due to project implementation community would be benefited from the 4, F = • Experiences sharing on - livelihood upgraded water supply. 17 activities, Resettlement and • Assured full support during implementation. Rehabilitation, women empowerment tribal development, health, education, convergence with existing government social security schemes etc. • Grievance Redress procedures 8th Ward No. 03 Total Community People The Water Supply Project Background, • The area has insufficient and inadequate May = 15 Environmental, Social, traffic safety issue drinking water resource. Water supply to the 2018 and benefit from the project were area is done through tube wells that supplies M = explained to the Stakeholders water to the community people. The area faces 4, • Status of existing drinking water supply severe water crisis during the summer season F = system; when the ground water level drops. 11 • Need for improvements to present • The community willingly accepted the project. system; The community members expressed that their • Relevant information of the upcoming economic situation would prevent them from project and benefits of the project. paying water user charges. (The men work as • Potential positive and negative impacts daily laborers and the women Housewives). due to project implementation • Ensuring no income loss 8th Ward No. 02 Total Community People The Water Supply Project Background, • The area has insufficient and inadequate May = 16 Environmental, Social, traffic safety issue drinking water resource. Water supply to the 2018 and benefit from the project were area is done through tube wells that supplies M = explained to the Stakeholders water to the community people. The area faces 8, F = • Status of existing drinking water supply severe water crisis during the summer season 8 system; when the ground water level drops. • Need for improvements to present • The community willingly accepted the project. system; The community members expressed that their • Relevant information of the upcoming economic situation would prevent them from

81 Initial Environmental Examination- Package 2A

project and benefits of the project. paying water user charges. (The men work as • Potential positive and negative impacts daily laborers and the women Housewives). due to project implementation Ensuring no income loss

8th Ward No. 07 Total Community People The Water Supply Project Background, • The area has insufficient and inadequate May & 08 = 17 Environmental, Social, traffic safety issue drinking water resource. Water supply to the 2018 and benefit from the project were area is done through tube wells that supplies M = explained to the Stakeholders water to the community people. The area faces 7, • Status of existing drinking water supply severe water crisis during the summer season F = system; when the ground water level drops. 10 • Need for improvements to present • The community willingly accepted the project. system; The community members expressed that their • Relevant information of the upcoming economic situation would prevent them from project and benefits of the project. paying water user charges. (The men work as • Potential positive and negative impacts daily laborers and the women Housewives). due to project implementation Ensuring no income loss 8th Ward No. 10, Total Community People • Briefing on project objectives probable • None of the people knew about the proposed May Malviya = 16 implementation procedures project. On learning about the project, they 2018 Mohalla • Potential positive and negative impacts expressed that they were happy that the entire M = due to project implementation community would be benefited from the 5, • Experiences sharing on - livelihood upgraded water supply. activities, Resettlement and • Assured full support during implementation. F = Rehabilitation, women empowerment 11 tribal development, health, education, convergence with existing government social security schemes etc. Grievance Redress procedures 8th Ward No. 11, Total Shopkeepers, The Water Supply Project Background, • As excavation not been able to done at night May Ambedkar =38 Environmental, Social, traffic safety issue because labour will not get agree to work in 2018 Mohalla and benefit from the project were night shift so shifting will be done at a vacant M =6, explained to the Stakeholders place near or next lane such that no income F = • Project effective for Shadora community loss takes place due the civil work. Vendors get people agreed on proposal

82 Initial Environmental Examination- Package 2A

32 • Community participation in project • implementation • Completion of project on time. • Vyapari Sangh will cooperate when laying done in congested whole sale market temporarily shifting of weekly vegetable market during excavation. • shifting of Street vendors. • Shifting or adjusting extended potion of shopkeepers.

83 Initial Environmental Examination- Package 2A

2. Consultation during construction

88. Prior to start of construction, ULB and PIU with the assistance of PMC will conduct information dissemination sessions at various places and solicit the help of the local community, leaders/prominent for the project work. At each ward/neighborhood level, focus group meetings will be conducted to discuss and plan construction work with local communities to reduce disturbance and other impacts.

89. A constant communication will be established with the affected communities to redress the environmental issues likely to surface during construction phases and also regarding the grievance redress mechanism. ULB/PIU and PMC will organize public meetings and will appraise the communities about the progress on the implementation of EMP. Meeting will also be organized at the potential hotspots/sensitive locations before and during the construction.

C. Information Disclosure

90. Executive summary of the IEE will be translated in Hindi and made available at the offices of PMU, PIU, Nagar Parishad offices, and also displayed on their notice boards. Hard copies of the IEE will be accessible to citizens as a means to disclose the document and at the same time creating wider public awareness. Electronic version of the IEE in English and Executive Summary in Hindi will be placed in the official website of the MPUDC, PMU after approval of the IEE by Government and ADB. Stakeholders will also be made aware of grievance register and redress mechanism.

91. Public information campaigns to explain the project details to a wider population will be conducted. Public disclosure meetings will be conducted at key project stages to inform the public of progress and future plans. Prior to start of construction, the PMU/PIU will issue Notification on the start date of implementation in local newspapers A board showing the details of the project will be displayed at the construction site for the information of general public.

92. Local communities will be continuously consulted regarding location of construction camps, access and hauling routes and other likely disturbances during construction. The road closure together with the proposed detours will be communicated via advertising, pamphlets, radio broadcasts, road signage, etc.

84

VIII. GRIEVANCE REDRESS MECHANISM

A. Project Specific Grievance Redress Mechanism

93. A program-specific grievance redress mechanism (GRM) shall be established to receive, evaluate, and facilitate the resolution of AP’s concerns, complaints, and grievances about the social and environmental performance at the level of the project. The following GRM provides a time-bound and transparent mechanism to voice and resolve social and environmental concerns linked to the project.

94. A common GRM will be in place for social, environmental, or any other grievances related to the project. The GRM will provide an accessible and trusted platform for receiving and facilitating resolution of affected persons’ grievances related to the program. The multi-tier GRM for the project is outlined below, each tier having time-bound schedules and with responsible persons identified to address grievances and seek appropriate persons’ advice at each stage, as required. ULB-wide public awareness campaigns will ensure that awareness on grievance redress procedures is generated through the campaign.

95. Who can complain: A complaint may be brought by persons who are, or could be, “directly, indirectly, materially, and adversely” affected by the project. A complaint can be submitted on behalf of the affected person/people by a representative, provided that he or she identifies the affected person/people and includes evidence of the authority to act on their behalf.

96. What the Grievance/Complain should contain: Any concerns pertaining to safeguard compliance - environment, involuntary resettlement, indigenous people, design related issues, compensation, service delivery or any other issues or concerns related to the project. The complaint must contain name, date, address/contact details of the complainant, location of the problem area, along with the problem. In addition, online filing using the state’s existing grievance redress mechanism or telephone helpline will also be open to use by affected persons3.

97. Where to file a Complaint: Complainants will have the flexibility of conveying grievances/suggestions by dropping or reporting grievance redress/suggestion forms in complaints/suggestion boxes to be installed by project at all the three Nagar Parishad offices, PIU offices, CM (Chief Minister) Helpline or by e-mail or by writing in a complaints register in the PIU offices or at construction site offices.

98. How to file a Complaint: The application should be precise and specific. The application can be sent either by post or through electronic means or deliver personally. A sample grievance form is at Appendix 10.

(i) Offline System - The application can be made on the application form available at all accessible places (NPs/ Office of PIUs/ construction site offices). The application should have the name and complete postal address of the applicant. (ii) Online System - Grievances pertaining to the implementation of the project can also be filed online at the website of MPUDC/PMU or by e-mails.

99. Documentation: Documentation of the complaints is important and must contain

3 Government of Madhya Pradesh has a special program called Chief Minister’s Monitoring Programme, which monitors development programs in the state and provides for online registration of complaints. The Public Grievance Redressal Department of GoMP clearly displays the Chief Minister’s Helpline Number, through which persons may lodge complaints directly to the highest authority in the state. The website of the Public Grievance Redressal Department also provides a kiosk locator for district level grievance redress kiosks. http://www.mp.gov.in/web/guest/home.

85 Initial Environmental Examination- Package 2A

name of the complainant, date of receipt of the complaint, address/contact details of the person, location of the problem area, and how the problem was resolved. PMU with the support of PIU will have the overall responsibility for timely grievance redress, and for registration of grievances, related disclosure, and communication with the aggrieved party. All the documents made available to the public at the community level (at ward offices) and will include information on the contact number, address and contact person for registering grievances, and will be disseminated throughout the project area by the PIU.

100. Grievance/Problem Redress through Participatory Process: Efforts must be made by the PIU with the support of safeguard consultants to resolve problems amicably, conflicts through participatory process with the community and the Nagar Parishads. In case of grievances that are immediate and urgent in the perception of the complainant, the Contractor, and supervision personnel from the PIU will provide the most easily accessible or first level of contact for the quick resolution of grievances. Contact phone numbers and names of the concerned staff and contractors, will be posted at all construction sites at visible locations.

101. Following process will be followed:

(i) 1st level grievance. In case of grievances that are immediate and urgent in the perception of the complainant, PMC supervising staff will direct the contractor to and ensures that it is resolved. If the grievance is not under the contractor scope, but under the program, PMC (field office) will resolve this issue. All the grievances should be resolved within 3 days of receipt of a complaint/grievance. The complaints/grievances received in the CM helpline that are related to MPUSIP will be referred to project GRM at this first level. CM helpline staff will be included in the GRM training so that they can identify the related grievances and forward to this project GRM.

(ii) 2nd level grievance. All grievances that cannot be redressed at first level within 3 days will be brought to the notice of PIU and PMC Assistant Environmental Specialist. PIU will review the grievance and act appropriately to resolve it within 10 days of receipt.

(iii) 3rd level grievance. All the grievances that are not addressed at 2nd level by PIU within in 10 days of receipt will be brought to the notice of notice of the Grievance Redressal Committee (GRC)4. GRC will meet twice a month and determine the merit of each grievance brought to the committee. The GRC will resolve the grievance within 1 month of receiving the complaint. All decisions taken by the GRC will be communicated to complainant by the Nodal Officer.

102. In case of any inter-departmental or inter-jurisdictional coordination required for resolution of specific grievances, the PIU will refer the matter directly to the PMU for state- level or inter-departmental coordination and resolution, instead of the town-level GRC. The project GRM notwithstanding, an aggrieved person shall have access to the country's legal system at any stage, and accessing the country's legal system can run parallel to accessing the GRM and is not dependent on the negative outcome of the GRM. Alternatively, if the grievance is related to land acquisition, resettlement & rehabilitation5, the APs can approach the Land Acquisition, Rehabilitation and Resettlement Authority (LARRA) of Madhya Pradesh, established under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation, and Resettlement Act, 2013.

4 Grievance redress committee (GRC) will be formed at town-level with members composed of: ULB Chairperson, ULB CMO, Environmental Specialist of PMC, PIU Dy.PM and PIU Community Development Officer. In case of any complaints by IP or members of scheduled tribes, the PIU will include as special member, a representative of an independent local NGO involved in tribal welfare. Special invitees to hearing of IP complaints will include two representatives from affected IP community and the project IP NGO, if appointed for IPP implementation. 5 the Authority admits grievance only with reference to the LA and R&R issues under the new Act

86 Initial Environmental Examination- Package 2A

103. Record-keeping. PIU will keep records of grievances received, corrective actions taken and the final outcome. The number of grievances recorded and resolved and the outcomes will be displayed/disclosed in the PIU office, ULB offices, and on the web.

Figure 1: MPUSIP Grievance Redress Mechanism

Affected person

Yes Field level within 3 days Grievance 1st Level Responsible: Contractor, PMC, and redressed and Grievance PIU field staff record keeping

No Yes PIU Grievance Redress Unit within 10 days Grievance 2nd Level PIU ASO, PMC RS in consultation redressed and Grievance with Project Engineer record keeping

No Yes Grievance Redress Committee rd within 30 days 3 Level GRC at town level. In case of IP Grievance Grievance complaints, independent IP NGO, IP redressed and community representatives to be record keeping involved. No

Court of Law

Note: ASO=Assistant Safeguard Officer, GRC = Grievance Redressal Committee; PMC = Project Management Consultants, PMU = Project Management Unit

87 Initial Environmental Examination- Package 2A

IX. ENVIRONMENTAL MANAGEMENT PLAN

A. Implementation Arrangements

104. Urban Development and Housing Department (UDHD) of Government of Madhya Pradesh will be the Executing Agency for the Program, responsible for management, coordination and execution of all activities funded under the loan. Implementing Agency will be the recently established Madhya Pradesh Urban Development Company (MPUDC), a wholly owned subsidiary of GoMP. A central Project Management Unit (PMU) attached to MPUDC will be responsible for implementing the MPUSIP. The PMU will be supported by Program Implementation Units (PIUs) with flexibility to redeployment depending upon the implementation requirements.

105. The PMU and PIUs will be supported by several teams of Design Consultants in preparation of preliminary engineering designs.

106. Water Resource Review Committee (WRRC) is constituted to undertake a thorough review of the source when recommended by the Design Consultant in regard to techno- economic feasibility and sustainability especially ensuring climate change resilience, and Technical Review Committee (TRC) to review and approve the preliminary designs developed by the Design Consultants.

107. Program Management Consultant (PMC) centrally located in PMU and with field teams located in PIUs shall be responsible for implementation of the Program. All infrastructure contracts will be procured through performance-based contracts (PBCs) and include build- operate (BO) framework. Based on the preliminary designs prepared by Design Consultants, the DBO (design-build-operate) Contractor will design, construct, commission and operate for 10 years, after which it will be transferred to the respective ULB.

108. Two Committees - an Empowered Committee cum Executive Committee and a Technical Clearance and Tender Committee have been constituted by the Government to be responsible for effective and timely implementation of the Program.

109. Safeguards. At PMU, there will be two safeguard specialists: (i) Project Officer (Environment) and (ii) Social & Gender Offer, who will responsible for compliance with the environmental and social safeguards in program implementation. PO (Environment) will have overall responsibility in implementation of the investment program as per the Environmental Assessment & Review Framework (EARF) agreed between ADB and the government. At individual subproject level, PO will ensure that environmental assessment is conducted, and a project-specific is prepared and implemented, and the compliance, and corrective actions, if any are reported as required.

B. Environmental Management Plan

110. An environmental management plan (EMP) has been developed to provide mitigation measures to reduce all negative impacts to acceptable levels.

111. The EMP will guide the environmentally-sound construction of the subproject and ensure efficient lines of communication between MPUDC, project management unit (PMU), project implementing unit (PIU), consultants and contractors. The EMP will (i) ensure that the activities are undertaken in a responsible non-detrimental manner; (i) provide a pro-active, feasible and practical working tool to enable the measurement and monitoring of environmental performance on site; (ii) guide and control the implementation of findings and recommendations of the environmental assessment conducted for the subproject; (iii) detail specific actions deemed necessary to assist in mitigating the environmental impact of the subproject; and (iv) ensure that safety recommendations are complied with. The EMP includes

88 Initial Environmental Examination- Package 2A

a monitoring program to measure the environmental condition and effectiveness of implementation of the mitigation measures. It will include observations on- and off-site, document checks, and interviews with workers and beneficiaries.

112. The contractor will be required to submit to PIU, for review and approval, a site environmental plan (SEP) including (i) proposed sites/locations for construction work camps, storage areas, hauling roads, lay down areas, disposal areas for solid and hazardous wastes; (ii) specific mitigation measures following the approved EMP; (iii) monitoring program as per SEP; and (iv) budget for SEP implementation. No works are allowed to commence prior to approval of SEP.

113. A copy of the EMP/approved SEP will be kept on site during the construction period at all times. The EMP included in the bid and contract documents. Non-compliance with, or any deviation from, the conditions set out in this document constitutes a failure in compliance.

114. For civil works, the contractor will be required to (i) carry out all of the mitigation and monitoring measures set forth in the approved SEP; and (ii) implement any corrective or preventative actions set out in safeguards monitoring reports that the employer will prepare from time to time to monitor implementation of this IEE and SEP. The contractor shall allocate budget for compliance with these SEP measures, requirements and actions.

115. The following tables show the potential environmental impacts, proposed mitigation measures and responsible agencies for implementation and monitoring.

89 Initial Environmental Examination- Package 2A

Table 18: Design Stage Environmental Management Plan Field Anticipated Mitigation Measures Responsible for Cost and Impact Implementation Source of Funds Design of water Unsustainable • Weirs to be constructed as vented structures, with open These measures Part of project supply system source; resource & rectangular vents and gates with sill level of weir just above are already costs energy use the river bed; in this arrangement, on the sill there will be included in the vertical slots to insert removable gates; gates will be closed preliminary prior to end of monsoon flows and opened prior to onset of designs. heavy monsoon flows; this arrangement avoid silt accumulation and also prevents obstruction of heavy DBO Contractor monsoon flows (DBOC)to follow, • Recovering wash water from treatment process enhance where • Treatment and reuse of sludge from treatment process possible. • Minimizing water losses from pipelines by perfect jointing and alignments using appropriate techniques PMU to ensure • Designing the entire system to maintain optimal flow and compliance. terminal pressure, and optimizing the overall energy usage • Reducing the incidence of water borne diseases by providing 100% population including urban poor with potable water supplies • Improve water use efficiency and reduce water wastage at household level by recording and monitoring the water usage, and charging the consumers as per usage; due consideration to urban poor • Minimize unaccounted for water (UFW) losses using district metered area approach with flow meter and pressure logging arrangements to identify and rectify the leaks, and unauthorized connections • Using low-noise and energy efficient pumping systems • During the design, construction, and operation of the project, apply pollution prevention and control technologies and practices consistent with international good practice, as reflected in internationally recognized standards such as the World Bank Group’s Environment, Health and Safety

90

Field Anticipated Mitigation Measures Responsible for Cost and Impact Implementation Source of Funds Guidelines (IFC’s General EHS Guidelines6 and Sector Specific (Water and Sanitation) Guidelines7). Water Project • Obtain permission from Water resources department, GoMP PMU & respective No costs; scope abstraction from sustainability & • Betma, Depalpur and Gautampura- permission / water Nagar Parishads of IA Chambal and water use conflicts allocation for water abstraction from River and construction (process already Gambhir of intake and Weir initiated)

Waste Environmental • Obtain consent from MPPCB for WTPs at Betma, Depalpur PMU / Nagar No costs; scope generation from pollution and Gautampura prior to start of construction Parishad; DBOC of IA & DBO WTP operations to prepare application, and assist as required Chlorine usage Chlorine handling & • Provide the following measure at the chlorine application These measures Project Costs as disinfectant at application risk – unit: are already WTPs health &safety risk o Chlorine neutralization pit with a lime slurry feeder included in the to workers and o Proper ventilation, lighting, entry and exit facilities preliminary general public o Facility for isolation in the event of major chlorine designs. leakage (if needed) o Personal protection and safety equipment for the DBOC to follow, operators in the chlorine plant enhance where o Provide training to the staff in safe handling and possible. application of chlorine; this shall be included in the contract of Chlorinator supplier PMU to ensure o Supplier of Chlorinator equipment shall provide standard compliance. operating manual for safe operation and as well as maintenance and repairs; preferably these shall be provided both in English and Hindi Languages

6https://www.ifc.org/wps/wcm/connect/554e8d80488658e4b76af76a6515bb18/Final%2B-%2BGeneral%2BEHS%2BGuidelines.pdf?MOD=AJPERES 7 https://www.ifc.org/wps/wcm/connect/e22c050048855ae0875cd76a6515bb18/Final%2B-%2BWater%2Band%2BSanitation.pdf?MOD=AJPERES

91

Table 19: Pre-Construction State Environmental Management Plan Field Anticipated Mitigation Measures Responsible for Cost and Impact Implementation Source of Funds Utilities Damage/ • Identify and include locations of utilities in the detailed DBOC with PIU Project costs – disturbance to designs/drawings to prevent unnecessary disruption of collaboration. general telephone lines, services PMU to ensure construction electric lines, water • Prepare a contingency plan to include actions to be taken in compliance practice lines in project area case of unintentional interruption of services. EMP Unsatisfactory • Appoint EHS supervisor and designate 1 EHS coordinator DBO contractor Cost for Implementation compliance to EMP (among the technical staff) in each town implementation & reporting • Ensure that all pre-construction activities are complete prior of mitigation to start of construction work measures • Ensure timely submission of monitoring reports responsibility of contractor. Construction Degradation of river • Schedule the works on river bed during summer no-flow DBOC to follow Project costs – works on river course and period general bed (stop dam) pollution • Do not disturb river bed except the actual work area; no PIU/ PMU to construction equipment, machinery shall be operated outside the work ensure practice area compliance • Avoid use of fuels, chemicals & lubricants; ensure no spillage • Clean up the area after the completion & prior to the onset of monsoon flow Construction Conflicts with local • Prioritize barren, waste, infertile, vacant lands within the DBOC to identify Part of project work camps, community; area, locations costs stockpile areas, disruption to traffic • Shall not be located in productive agricultural lands, water following the storage areas flow and sensitive bodies, natural drainage channels, flood plains & criteria and waste receptors groundwater recharge areas, forests, vegetative lands, etc. disposal areas • Locate at sites that will not promote instability, flooding and PIU to ensure result in destruction of natural drainage, vegetation, irrigation, compliance and & drinking water supply; approve • For private lands, obtain land owner’s (not lessees) written consent; indicate the requirement for reinstatement to original • Site should have a minimum buffer of 0.5 – 1 km from all

92

Field Anticipated Mitigation Measures Responsible for Cost and Impact Implementation Source of Funds socially, Sources of Extraction of • Obtain material only existing borrow sites/quarries already DBOC to identify Part of project Materials materials can permitted by the Department of Mines and Geology; sources that costs disrupt natural land • If new quarries sites/quarries are necessary, contractor shall have all permits, contours and be obtain all necessary permissions as per the law in force. if required, vegetation resulting • Contractor to obtain construction materials only after written obtain permits, in accelerated permission / approval of PIU for respective sources and submit to erosion, • Maintain a construction material register at the site PIU disturbance in natural drainage PIU to check patterns, ponding and approve and water logging, and water pollution.

Consents, Failure to obtain • Obtain all necessary consents, permits, clearance, NOCs, PMU / PIU to Part of project permits, necessary etc required for the project prior to award of contact or start obtain project costs clearances, consents, permits, of civil works, as necessary. clearances; NOCs, etc. NOCs, etc. can DBOC to provide result to design • Include in detailed designs, drawings and documents all necessary revisions and/or regulatory conditions and provisions, where required assistance stoppage of works • Contractor to identify & obtain all necessary approvals, including in compliance with labour laws, before start of construction; DBOC to obtain construction • Contractor to acknowledge in writing to PIU and provide permits & copies of all obtained permits, clearance, NOCs, etc. PIU to ensure

Health risk due to • Obtain details from PHED/NPs on location of underground DBOC in Part of project Asbestos exposure to AC pipes coordination with costs Cement Pipes asbestos materials • Locate the new piper carefully to avoid encountering AC PIU and ULB pipes

93

Field Anticipated Mitigation Measures Responsible for Cost and Impact Implementation Source of Funds • Leave the AC pipes undisturbed in the ground.

Table 20: Construction Stage Environmental Management Plan Field Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation EMP Implementation Irreversible impact to • Project manager and all key workers will be DBOC Cost of EMP Implementation Training the environment, required to undergo training on EMP Orientation Training to workers, and implementation including spoils/waste PMC Construction contractor is responsibility of community management, Standard operating and Environmental PMU. procedures (SOP) for construction works; Specialists to occupational health and safety (OH&S), conduct the training Other costs responsibility of core labor laws, applicable environmental contractor. laws, etc. Air Quality Emissions from • Control dust by water sprinkling on DBO Contractor Cost for implementation of construction vehicles, exposed soil, stock stockpiled material on mitigation measures equipment, and site responsibility of contractor. machinery used for • Barricade area, provide wind sheets installation of • Use tarpaulins to cover sand and other Air quality monitoring costs pipelines resulting to loose material when transported by trucks; are included in the EMP dusts and increase in • Clean wheels and undercarriage of haul costs of project concentration of trucks prior to leaving construction site vehicle-related • Prevent entry of traffic, public in pollutants such as construction area carbon monoxide, • Fit all heavy equipment, and machinery sulfur oxides, with air pollution control devices which are particulate matter, operating correctly; all the vehicle shall nitrous oxides, and meet the emission norms and shall have hydrocarbons. valid pollution under control (PUC)

94

Field Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation certificate. • Conduct air quality monitoring as per the monitoring plan. Surface water quality Mobilization of settled • Avoid earthworks during the rainy season DBO Contractor Cost for implementation of silt materials, and • Avoid stockpiling of earth fill especially mitigation measures chemical during the monsoon season unless responsibility of contractor. contamination from covered by tarpaulins or plastic sheets; fuels and lubricants • Reuse excess spoils & materials in the Water quality monitoring during installation of construction as far a possible costs are included in the pipelines can • Identify disposal sites prior to construction EMP costs of project contaminate nearby & dispose construction waste only at surface water quality. designated areas • Install temporary silt traps basins along the drainage leading to the water bodies; • Place storage areas for fuels and lubricants away from any drainage leading to water bodies; • Conduct surface quality inspection according to the Environmental Management Plan (EMP). Noise Levels Increase in noise • Conduct noise generating activities (eg, cc DBO Contractor Cost for implementation of level due to earth- road cutting) during day time mitigation measures moving and • Minimize noise from construction responsibility of contractor. excavation equipment (by using vehicle silencers, equipment, and the fitting jackhammers with noise-reducing transportation of mufflers, and use portable street barriers to equipment, materials, minimize sound impact to surrounding and people sensitive receptor; • Maintain maximum sound level not exceeding 80 decibels (DBA) when measured at a distance of 10 m or more from the vehicle/s. • Identify any buildings at risk from vibration

95

Field Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation damage and avoiding any use of pneumatic drills or heavy vehicles in the vicinity; • Consult local communities in advance to avoid working at sensitive times, such as religious and cultural festivals. Landscape and Impacts due to • Stockpiles, lubricants, fuels, and other DBO Contractor Cost for implementation of aesthetics excess excavated materials should be located away from mitigation measures earth, excess steep slopes and water bodies; responsibility of contractor. construction • Avoid stockpiling any excess spoils; materials, and solid dispose immediately to designated areas waste such as • Domestic solid waste generated at removed concrete, construction camps and work sites shall be wood, packaging properly managed (collected, segregated, materials, empty disposed properly); waste should not containers, spoils, burned oils, lubricants, and • Residual and hazardous wastes such as other similar items. oils, fuels, and lubricants shall be disposed through approved recyclers • Environmentally restore the work sites to at least pre-project conditions; PIU to approve in writing that site is restored Ecological Resources – Loss of vegetation • Avoid removal of vegetation / tree cutting DBO Contractor Cost for implementation of Terrestrial and tree cover • If unavoidable, minimize as far as possible, mitigation measures and obtain tree-cutting permit responsibility of contractor. • Plant 10 trees for every one cut Land use Environmental Issues • The impact due to change in land use will Not applicable Not applicable due to land use be negligible due to this project. change Accessibility Traffic problems and • Confine work areas along the roads to the DBO Contractor Cost for implementation of conflicts near project minimum possible extent; all the activities, mitigation measures locations and haul including material & waste/surplus soil responsibility of contractor. road stocking should be confined to this area.

96

Field Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation Proper barricading should be provided; avoid material/surplus soil stocking in congested areas – immediately remove from site/ or brought to the as and when required • Leave spaces for access between mounds of soil; • Provide walkways and metal sheets where required to maintain access across for people and vehicles; • Plan transportation routes so that heavy vehicles do not use narrow local roads, except in the immediate vicinity of delivery sites; • Schedule transport and hauling activities during non-peak hours; • Keep the site free from all unnecessary obstructions; • Drive vehicles in a considerate manner; • Coordinate with Traffic Police for temporary road diversions, where necessary, and for provision of traffic aids • Notify affected area by public information notices, providing sign boards informing nature and duration of construction works and contact numbers for concerns/complaints. • For works in very narrow roads o Inform the affected local population 1- week in advance about the work schedule o Plan and execute the work in such a way that the period of disturbance/ loss

97

Field Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation of access is minimum. o Provide pedestrian access in all the locations until normalcy is restored. Provide wooden/metal planks over the open trenches at each house to maintain the access. Socio-Economic – Impede the access of • Do not obstruct access; provide temporary DBO Contractor Cost for implementation of Income. residents and access, by leaving spaces in excavation, mitigation measures customers to nearby provide walkways and metal sheets for responsibility of contractor. shops people and vehicles where necessary to continue business • Increase workforce in the areas with predominantly institutions, place of worship, business establishment, hospitals, and schools; • Consult businesses and institutions regarding operating hours and factoring this in work schedules Socio-Economic – Generate temporary • Employ local persons in construction work DBO Contractor Cost for implementation of Employment employment and if manpower is available mitigation measures increase in local responsibility of contractor. revenue Occupational Health Occupational hazards • Comply with all national, state and local DBO Contractor Cost for implementation of and Safety which can arise core labor laws (see Appendix 6of this IEE) mitigation measures during work • Following internationally recognized health responsibility of contractor. and safety standards such as the World Bank Group’s Environment, Health and Safety Guidelines (IFC’s General EHS Guidelines8 and Sector Specific (Water and Sanitation) Guidelines9).

8https://www.ifc.org/wps/wcm/connect/554e8d80488658e4b76af76a6515bb18/Final%2B-%2BGeneral%2BEHS%2BGuidelines.pdf?MOD=AJPERES 9 https://www.ifc.org/wps/wcm/connect/e22c050048855ae0875cd76a6515bb18/Final%2B-%2BWater%2Band%2BSanitation.pdf?MOD=AJPERES

98

Field Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation • • Implement site-specific occupational health and safety (OH&S) measures, such as the following • Provided personal protective equipment (PPE) to workers(like helmet, gumboot, safety belt, gloves, nose musk and ear plugs), and ensure that they are used • Conduct OH&S training workers/staff • Do no employ ad-hoc work procedures, follow best & acceptable work practices • Document work-related accidents • Provide qualified & easily accessible first- aid facilities all times at all sites • Secure all installations from unauthorized intrusion and accident risks; • Provide potable drinking water; • Provide clean eating areas where workers are not exposed to hazardous or noxious substances; • Provide H&S orientation training to all workers to ensure that they are apprised of the basic site rules of work at the site, PPEs, and preventing injuring to fellow workers; • Ensure that visitor/s do not enter hazard areas unescorted • Ensure the visibility of workers through their use of high visibility vests when working in or walking through heavy equipment operating areas; • Ensure moving equipment is outfitted with audible back-up alarms;

99

Field Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation • Mark and provide sign boards for hazardous areas such as energized electrical devices and lines, service rooms housing high voltage equipment, and areas for storage and disposal. Signage shall be in accordance with international standards and be well known to, and easily understood by workers, visitors, and the general public as appropriate; and • Disallow worker exposure to noise level greater than 85 dBA for a duration of more than 8 hours per day without hearing protection. The use of hearing protection shall be enforced actively. Community Health and Traffic accidents and • Plan routes to avoid times of peak- DBO Contractor Cost for implementation of Safety. vehicle collision with pedestrian activities and high risk areas. mitigation measures pedestrians during • Prevent public entry in to work areas responsibility of contractor. material and waste through barricading and security guards transportation • Maintain regularly the vehicles and minimize potentially serious accidents caused by equipment malfunction or premature failure. • Provide road signs and flag persons to warn of on-going trenching activities. • In very narrow streets, conduct work section-wise (~100 m), and complete excavation, pipe laying and backfilling in minimum possible time (1 day preferably) Work Camps and Temporary air and • Establish camps only after site approval DBO Contractor Cost for implementation of worksites noise pollution from • Avoid cutting of trees/ clearing bushes mitigation measures machine operation, • Provide adequate drinking water, water for responsibility of contractor. water pollution from other uses, and sanitation facilities storage and use of • Ensure conditions of livability at work

100

Field Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation fuels, oils, solvents, camps are maintained at the highest and lubricants standards possible at all times; • Prohibit employees from poaching wildlife Unsanitary and poor and cutting of trees for firewood; living conditions for • Train employees in the storage and workers handling of materials which can potentially cause soil contamination; • Recover used oil and lubricants and reuse or remove from the site; • Manage solid waste according to the preference hierarchy: reuse, recycling and disposal to designated areas; • Ensure unauthorized persons specially children are not allowed in any worksite Post-construction Damage due to • Remove all spoils wreckage, rubbish, or DBO Contractor Cost for implementation of clean-up debris, spoils, excess temporary structures (such as buildings, mitigation measures construction materials shelters, and latrines) which are no longer responsibility of contractor. required • All excavated roads shall be reinstated to original condition. • All disrupted utilities restored • All affected structures rehabilitated/compensated • The area that previously housed the construction camp is to be checked for spills of substances such as oil, paint, etc. and these shall be cleaned up. • All hardened surfaces within the construction camp area shall be ripped, all imported materials removed, and the area shall be top soiled and regressed • The contractor must arrange the cancellation of all temporary services.

101

Field Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation • Restore the work sites to pre-project conditions; PIU to approve in writing that site is restored

102

Table 21: Operation Stage Environmental Management Plan Field Anticipated Mitigation Measures Responsible for Monitoring of Cost and Impact Mitigation Mitigation Source of Funds Check for Loss of water, • Effective leak detection and water DBO Contractor PIU and Operating blockage and increased demand auditing to reduce the water losses respective costs leakage and inconvenience Nagar problems to consumers & Parishads reducing the general public water losses Water Impacts on public • Ensure protection of water source Respective PMU in Operating contamination – health quality (Chambal and Gambhir rivers), Nagar Parishads coordination costs raw water any entry of wastewater into the river with WRD contamination upstream of Weir sites should be DBO Contractor at source and prevented. PIU and treated water • Contamination of treated water during respective during transmission and distribution should Nagar transmission be prevented by quickly identifying, Parishads isolating and repairing the leak section. Develop a system of leak detection and rectification. • Conduct regular monitoring of raw & treated water and ensure that water supplied at all times meets the drinking water standards (Appendix 13) Discharge the Pollution of • Backwash water will be recirculated DBO Contractor PIU and Operating impurities and streams /drains so no wastewater generated from respective costs other solids WTPs Nagar collected due to • Maintain the mechanical parts as per Parishads filtration and the maintenance plan to avoid any back wash hazards Sludge Land and water • Collect the sludge from WTP units, DBO Contractor PIU and Operating generation pollution, impacts dry in sludge drying beds, and reuse / respective costs on health & dispose safely as per the design Nagar

103

Field Anticipated Mitigation Measures Responsible for Monitoring of Cost and Impact Mitigation Mitigation Source of Funds environment Parishads Increased in Water pollution, • Sanitation facilities needs to be Respective PMU To be sewage and impacts on improved at community level and at Nagar Parishads identified generation public health and the town level to meet the increased - environment sewage demand respective NPs Generation of Impacts on public • Collect solid wastes and dispose to DBO Contractor PIU and Operating waste materials health and approved disposal yards respective costs environment Nagar Parishads Occupational Health, social and • Provide appropriate PPE to workers & DBO Contractor PIU and Operating health and economic impacts training on its proper use respective costs safety on the workers • Use fall protection equipment when Nagar working at heights. Parishads • Maintain work areas to minimize slipping and tripping hazards. • Implement a training program for operators who work with chlorine regarding safe handling practices and emergency response procedures. • Prepare escape plans from areas where there might be a chlorine emission. • Install safety showers and eye wash stations near the chlorine equipment and other areas where hazardous chemicals are stored or used. • Prohibit eating, smoking, and drinking except in designated areas.

104

Table 22: Construction Stage Environmental Monitoring Plan Monitoring field Monitoring Monitoring parameters Frequency Responsibility Cost & Source of Funds location Construction All work sites Implementation of dust Regularly as required Supervising Part of TOR of PIU, PMC and disturbances, nuisances, control, noise control, during construction; staff and PMU public & worker safety, traffic management, & checklist to be filled safeguards safety measures. monthly once specialists Site inspection checklist to review implementation is appended at Appendix 14 Ambient air quality 6 locations • PM10, PM2.5 NO2, Once before start of DBO Cost for implementation of (2 locations in SO2, CO construction Contractor monitoring measures each town: (i) at Quarterly (yearly 4- responsibility of contractor WTP site, (ii) times) during (54 samples x 5000 per distribution work construction (2 year sample = 270,000) site) period considered)

Ambient noise 6 locations • Day time and night Once before start of DBO Cost for implementation of (2 locations in time noise levels (24 construction Contractor monitoring measures each town: (i) at hours) Quarterly (yearly 4- responsibility of contractor WTP site, (ii) times) during (54 samples x 1500 per distribution work construction (2 year sample = 81,000) site) period considered) Surface water quality 1 locations (down • pH, Oil & grease, Cl, Once before start of DBO Cost for implementation of Stream of work F, NO3, TC, FC, construction& Contractor monitoring measures sites in Chambal Hardness, Turbidity monthly during responsibility of contractor and Gambhir river) BOD, COD, DO, construction (3 months (12 samples x 4000 per Total Alkalnity period considered) in sample = 48,000) river (27 samples x 4000 per Once before start of sample = 108,000) construction&

105

Quarterly during construction (24)

Table 23: Operation Stage Environmental Monitoring Plan Monitoring Monitoring Monitoring parameters Frequency Responsibility Cost & field location Source of Funds Source water Near intake point pH, Cl, F, NO3, TC, FC, Hardness, Turbidity BOD, COD, DO, Yearly DBO O&M costs quality in Chambal and Total Alkalnity twice (pre & Contractor Gambhir river heavy metals & pesticides post monsoon) Monitoring of Consumer end- pH, Nitrite, Nitrate, Turbidity, Total Alkalnity, Total coliform and Monthly DBO O&M costs quality of random sampling Feacal coliform once Contractor water supplied in all zones to consumers Sludge quality WTP Analysis for concentration of heavy metals and confirm that value Yearly once DBO O&M costs and suitability are within the following limits (all units are in mg/kg dry, except Contractor as manure pH) • Arsenic - 10.00, • Cadmium - 5.00 • Chromium - 50.00 • Copper - 300.00 • Lead - 100.00 • Mercury - 0.15 • Nickel - 50.00 • Zinc - 1000.00 • PH - 5.5-8.5

106

C. EMP Compliance Responsibilities

116. PMU Responsibilities. PO (Environment) will be supported by PMC, which will be staffed with an Environmental Specialist, and Environmental Coordinators. Key tasks and responsibilities of the PO (Environment) for this sub project include the following:

Bidding stage:

(i) Prior to invitation of bids for civil works contract, ensure that

a. Water Resources Department (WRD) permission is obtained for sourcing water from Chambal and Gambhir River River and to construct Weir & intake well cum pump house on it. b. Consent for establishment (CFE) is obtained from MPPCB for WTP construction.

(ii) Ensure that EMP is included in bidding documents and civil works contracts. (iii) Ensure that the bid/contract documents include specific provisions requiring contractors to comply with all applicable labour laws and core labour standards including:

a. Labour welfare measures and provision of amenities b. prohibition of child labour as defined in national legislation for construction and maintenance activities; c. equal pay for equal work of equal value regardless of gender, ethnicity, or caste; d. elimination of forced labour; e. The requirement to disseminate information on sexually transmitted diseases, including HIV/AIDS, to employees and local communities surrounding the project sites. (iv) Ensure that staff required for implementation of EMP is included in the bid requirements (v) Ensure that EMP cost is included in the project cost (vi) In the pre-bid meeting, provide insight into the EARF requirements, IEE update, EMP measures, and overall compliance requirements to the bidders

Construction stage:

(i) Facilitate and ensure that all necessary environmental clearances/permissions, including that of contractor’s are in place prior to start of construction (ii) Organize an induction course for the training of contractors, preparing them on EMP implementation, environmental monitoring, and on taking immediate action to remedy unexpected adverse impacts or ineffective mitigation measures found during the course of implementation. (iii) provide oversight on environmental management aspects of subprojects and ensure EMPs are implemented by PIU and contractors (iv) Supervise and provide guidance to the PIUs to properly carry out the environmental monitoring as per the EMP (v) Oversee grievance redress mechanism to address any grievances brought about in a timely manner; ensure that records are properly maintained (vi) Consolidate monthly environmental monitoring reports from PIU and submit semi-annual monitoring reports to ADB (vii) Oversee site closures to ensure that all work / facility sites are restored properly prior to issuing work completion certificate to the contractor

107

Operation stage:

(i) Ensure and consent for operation (CFO) is obtained from MPPCB for WTP prior to start of operation

117. PIU Responsibilities. PIU will be headed by a Project Manager and supported by PMC. An Assistant Project Manager of PIU will be given additional responsibilities of safeguard tasks and will be designated as Assistant Environmental Officer (ASO). ASO will be supported by PDMC Environmental Specialist and Environmental Coordinator. Key tasks and responsibilities of the ASO for this subproject include the following:

(i) Provide necessary support to PIU and Nagar Parishads in obtaining permission from WRD and MPPCB; liaison with PMU and regulatory agencies (ii) Oversee day-to-day implementation of EMPs by contractors, including compliance with all government rules and regulations, take necessary action for obtaining rights of way (iii) Oversee environmental monitoring by contractors (iv) Take corrective actions when necessary to ensure no environmental impacts (v) Submit monthly environmental monitoring reports to PMU (vi) Conduct continuous public consultation and awareness (vii) Address any grievances brought about through the grievance redress mechanism in a timely manner as per the EMP

118. Contractor’s responsibilities.

Bidding stage:

(i) Understand the EMP requirements and allocate necessary resources (budget, staff, etc.,) (ii) Understand the regulatory compliance requirements related to labour welfare, safety, environment etc.,

Design stage:

(i) Review the IEE Report including the REA checklist, category and the EMP, and conduct site visits to understand the environmental sensitivity of the project sites. (ii) Update the REA checklist, confirm the category, and update/revise the IEE Report of the project reflecting the changes /amendments /additions that are effected in the project during the detailed design (iii) Update / revise and finalize the EMP (iv) Provide all necessary technical assistance to PIU / ULB in obtaining regulatory clearances/approvals. (v) Ensure that all design-related measures of the EMP, and conditions, if any, of government regulatory agencies (like MPPCB consent conditions) are duly included in the final designs.

Construction stage:

(i) Ensure that all regulatory clearances (both project related and contractor related) are in place before start of the construction work. (ii) Mobilize EHS officer and Archaeological supervisor prior to start of work

108

(iii) Confirm with PIU availability of rights of way at all project sites prior to start of work. (iv) Prepare and submit: a. Construction waste management (CWM) plan b. Traffic management (TM) plan (v) Implement the mitigation measures as per the EMP including CWM & TM Plans (vi) Follow the EMP measures/guidelines for establishment of temporary construction camps, construction waste disposal sites, and material borrow areas, etc., (vii) Implement EMP and ensure compliance with all the mitigation and enhancement measures (viii) Conduct environmental monitoring (air, noise, water etc.,) as per the EMP (ix) Undertake immediate action as suggested by PIU / PMU / PMC to remedy unexpected adverse impacts or ineffective mitigation measures found during the course of implementation (x) Submit monthly compliance reports on EMP implementation (xi) Act promptly on public complaints and grievances related to construction work and redress in a timely manner in coordination with PIU (xii) Comply with applicable government rules and regulations

Operation stage:

(i) Obtain CFO from MPPCB in coordination with the ULB, and comply with MPPCB conditions, if any, during the operation phase (ii) Implement the operation phase EMP including the monitoring plan (iii) Submit quarterly EMP implementation report

D. Training Needs

119. The following Table 18 presents the outline of capacity building program to ensure EMP implementation. The estimated cost is Rs.275,000 (excluding trainings of contractors which will be part of EMP implementation cost during construction) to be covered by the project’s capacity building program. The detailed cost and specific modules will be customized for the available skill set after assessing the capabilities of the target participants and the requirements of the project by the ES of PMC.

Table 24: Outline Capacity Building Program on EMP Implementation Description Target Estimate Cost and Participants& (INR) Source of Venue Funds 1. Introduction and Sensitization to All staff and - Included in the Environmental Issues (1 day) consultants involved overall program - ADB Safeguards Policy Statement in the project cost - Government of India and Madhya Pradesh applicable safeguard laws, At PMU, Bhopal regulations and policies including but (combined program not limited to core labor standards, for all subprojects) OH&S, etc. - Incorporation of EMP into the project

109

Description Target Estimate Cost and Participants& (INR) Source of Venue Funds design and contracts - Monitoring, reporting and corrective action planning 2. EMP implementation (1/2 day) All PIU staff, - Part of overall - EMP mitigation & monitoring measures contractor staff and program costs – -Roles and responsibilities consultants involved PMC will conduct - Public relations, - Consultations in the Betma and at PIU office - Grievance redress Gautampura - Monitoring and corrective action subproject Part of scope of planning work of PMU, - Reporting and disclosure At PIU PIU, PMC & - Construction site standard operating DBOC procedures (SOP) - AC pipe protocol - Traffic management plan - Waste management plan - Site clean-up & restoration 3. Contractors Orientation to Workers Once before start of - Contractors cost (1/2 day) work, and thereafter - Environment, health and safety in regular briefing project construction every month once. Daily briefing on safety prior to start of work

All workers (including unskilled laborers)

F. Monitoring and Reporting

120. During the detailed design stage, DBO Contractor should confirm PMU the mobilization of Environmental Expert for IEE update and integrating design stage EMP into designs.

121. Prior to commencement of the works, the contractor will submit a compliance report to PIU that all identified pre-construction mitigation measures as detailed in the EMP are undertaken. Contractor should confirm EHS supervisor is mobilized and EHS coordinators are designated for each town for effective implementation of the EMU. PMU with the assistance of the PMC will review the report and permit commencement of works.

122. During construction, results from internal monitoring by the contractor will be reflected in their monthly EMP implementation reports to the PIU. PMU will review and advise contractors

110

for corrective actions if necessary. Quarterly report summarizing compliance and corrective measures taken will be prepared by PMC field team at PIU and submitted to PMU (Appendix 15). During operation, the contractor will conduct management and monitoring actions as per the operation stage EMP, and submit to PMU and ULB a quarterly report on EMP implementation and compliance.

123. Based on monthly & quarterly reports and measurements, PMU will submit to ADB, semi-annual (6-monthly) Environmental Monitoring Reports (EMR).Once concurrence from the ADB is received the report will be disclosed on the MPUDC and PMU websites.

124. ADB will review project performance against the MPUSIP commitments as agreed in the legal documents. The extent of ADB’s monitoring and supervision activities will be commensurate with the project’s risks and impacts. Monitoring and supervising of social and environmental safeguards will be integrated into the project performance management system

G. EMP Implementation Cost

125. Most of the mitigation measures require the contractors to adopt good site practice, which should be part of their normal procedures already, so there are unlikely to be major costs associated with compliance. The costs which are specific to EMP implementation and are not covered elsewhere in the projects are given below. The total costs are estimated at INR 2.43 million, which are to be covered by contractor costs.

Table 25: Cost Estimates to Implement the EMP Particulars Stages Unit Total Rate Cost Costs Numb (INR) (INR) Covere er d By A Implementation . staff 1 Environmental Design & pre Per 0.5 150,00 75,000 DBO Specialist construction month 0 Contract 1 EHS Supervisor Construction per 24 50,000 1,200,00 DBO month 0 contract Subtotal (A) 1,275,00 0 B Mitigation . Measures 1 Consent for Pre Lump 150,000 Project establishments & construction sum costs consent for operation from MPPCB

111

Particulars Stages Unit Total Rate Cost Costs Numb (INR) (INR) Covere er d By 2 Provision for tree Construction Per tree 100 1,000 100,000 DBO cutting & contract compensatory plantation measures 3 Traffic management Construction Lump - - 300,000 DBO at work sites sum – 3 contract (Pavement Markings, towns Channelizing Devices, Arrow Panels and Warning Lights) Subtotal (B) 550,000 C Monitoring . Measures 1 Air quality monitoring Construction / sample 54 5,000 270,000 DBOC 2 Noise levels Construction / sample 54 1,500 81,500 DBOC monitoring 3 Surface water Construction / sample 39 4,000 156,000 DBOC monitoring 4 Water and sludge Operation LS / yr - - 100,000 DBO Subtotal (C) 607,500 Subtotal (D) - Total (A+B+C) INR 2,432,50 0

112

113

X. CONCLUSION AND RECOMMENDATIONS

126. The process described in this document has assessed the environmental impacts of all elements of the Betma, Depalpur and Gautampura water supply improvement subproject. All potential impacts were identified in relation to pre-construction, construction, and operation phases. Planning principles and design considerations have been reviewed and incorporated into the site planning and design process wherever possible; thus, environmental impacts as being due to the project design or location were not significant.

127. No flow data available for these rivers as they are not gauged by WRD. Considering the low water requirement of towns (2.16 MLD for Betma, 2.40 MLD for Depalpur and 2.10 MLD for Gautampura), and very high flows during monsoon, (as gathered from local information), it is assessed to be unlikely to have any issue of source sustainability. To cater to the no-flow period (5-6 months), weirs are proposed. These are small weirs, with a height of 4-6 m above the river bed level (same as depth of river banks), thus confining the submergence to river course itself. Both the rivers – Chambal (source for Depalpur and Gautampura) and Gambir (source for Betma) are not perennial. Chambal flows for about 6-7 months while Gambir flows for about 5-6 months a year, mostly during monsoon and post monsoon. Chambal is a large (988 km length) and interstate river and although it is perennial in the mid and lower courses, in the upper reaches, in which both the weirs are proposed for project towns, river is not perennial. There are existing weirs / dams on both the river upstream and downstream of proposed weir locations, and considering this there are no notable changes envisaged in the flow regime. Overall water abstraction against the water availability is between 0.5 to 1.4 %, which is negligible and unlikely to have any impacts.

128. Given intermittent nature of rivers, there are no notable sensitive environmental features. There is no notable, protected or unique aquatic life in the river, and the fish is limited to local common species. National Chambal Gharial Sanctuary, established in River Chambal in its mid and lower reaches, is far away (about 300 km downstream) from proposed weir locations, and this distance is intercepted further by four major dams. Therefore the proposed weirs have no relevance to the sanctuary area. It is also proposed that weirs will be constructed as a vented structure, with open rectangular vents and gates; sill level of weir will be just above the river bed. On the sill there will be vertical slots to insert removable gates; gates will be closed prior to end of monsoon flows and opened prior to onset of heavy monsoon flows; this arrangement avoids silt accumulation and also prevents obstruction of heavy monsoon flows. As the package is implemented under DBO mode, the detailed design of weir will be conducted by the contractor after award of the contract.

The water impoundment / submergence due to proposed weirs is confined to river courses as the proposed height of the weirs is less than the height of river banks at respective weir locations. Therefore there is no submergence of government or private lands or forest areas. The proposed impoundment in fact is likely to benefit the environment through groundwater recharge and propagation of aquatic life. Water quality is suitable for drinking water after conventional treatment and disinfection, and there are no notable pollution sources. No negative

impacts thus envisaged.

129. During the construction phase, impacts mainly arise from the construction dust and noise, the need to dispose of large quantities of waste soil and import of construction material, and from the disturbance of residents, businesses, traffic and important buildings by the construction work. The social impacts (access disruptions) due to construction activities are unavoidable, as the residential and commercial establishments exist along the roads where pipes will be laid. As some of the works are conducted in rive, there is a risk of water contamination, river bed damage, etc. Appropriate measures are suggested.

130. Anticipated impacts of water supply during operation and maintenance will be related to detection and repair of leaks, pipe bursts. These are, however, likely to be minimal, as proper design and selection of good quality pipe material shall mean that leaks are minimal. Leak repair work will be similar to the pipe-laying work. Appropriate measures to deal with backwash water and sludge from WTP is included in the project design. Application and handling of chlorine gas will involve certain risks, and appropriate measures are suggested for safe application. The DBO Contractor will implement the operation stage EMP during contract period.

131. The public participation processes undertaken during project design ensured stakeholders are engaged during the preparation of the IEE. The planned information disclosure measures and process for carrying out consultation with affected people will facilitate their participation during project implementation.

132. The project’s grievance redress mechanism will provide the citizens with a platform to redress of their grievances, and describes the informal and formal channels, time frame, and mechanisms for resolving complaints about environmental performance.

133. The EMP will assist the PMU, PIU, PMC and DBO contractor in mitigating the environmental impacts, and guide them in the environmentally sound execution of the proposed project.

134. A copy of the EMP/approved SEP shall be kept on-site during the construction period at all times. The EMP shall be made binding on all contractors operating on the site, and will be included in the contractual clauses. Non-compliance with, or any deviation from, the conditions set out in this document shall constitute a failure in compliance.

135. The project will benefit the general public by contributing to the long-term improvement of water supply systems and community livability in Betma and Gautampura.

136. Therefore, as per ADB SPS, the project is classified as environmental category B and does not require further environmental impact assessment. However, to conform to government guidelines, the project requires (i) permission of WRD, GoMP for water abstraction from Chambal and Gambhir River River, and for construction of Weir and intakes on it and (ii) Consent for Establishment (CFE) and Consent for Operation (CFO) for WTPs from MPPCB. These permissions/approvals shall be obtained.

114

137. This IEE shall be updated during the detailed design stage by the DBO contractor to reflect any changes, amendments and will be reviewed and approved by PMU.

115

Appendix 1: REA Checklist

I. Country/Project: India/Madhya Pradesh Urban Services Improvement program- Betma Water Supply Subproject Sector/Division: Urban Development & Environment Department/MPUDC Screening Questions Yes No Remarks A.PROJECT SITING IS THE PROJECT AREA • Densely populated?  The project covers entire town including the densely populated areas. There are no major negative impacts envisaged because Distribution lines will be located in unused Government lands along side the existing roads and can be constructed without causing disturbance to houses and commercial establishments. In narrow streets disruption to road users is likely and measures like best activity scheduling, alternative routes, prior information to road users, houses and shops will minimize the impact to acceptable levels. The site of WTP is located in less dense area so no negative impact envisaged. • Heavy with development  No activities? • Adjacent to or within any  No environmentally sensitive areas? No • Cultural heritage site/Historical  importance • Protected area  No • Wetland  No • Mangrove  No • Estuarine  No • Buffer zone of protected  No Area • Special area for  No protecting biodiversity • Bay  No B.POTENTIAL ENVIRONMENTAL IMPACTS Will the project cause…

• Pollution of raw water supply  There are no significant water pollution from upstream wastewater sources in the catchment. Raw water quality is discharge from communities, tested and found that it is suitable for industries, agriculture, and Domestic use. soil erosion runoff?

116

• Impairment of historical  /cultural monuments/areas, and loss/damage to these sites?

• Hazard of land subsidence  Not applicable, subproject does not involve caused by excessive ground groundwater abstraction water pumping? • Social conflicts arising from  Project does not involve land acquisition displacement of communities /displacement .No social conflicts envisaged. • Conflicts in abstraction of raw  No, the water will be abstracted with due water for water supply with permission of Water Resource Department other beneficial water uses for surface and ground waters? • Unsatisfactory raw water supply  Raw water Quality is tested and found that it is (e.g. excessive pathogens or suitable for Domestic use. mineral constituents)?

 Water will be treated and disinfected prior to • Delivery of unsafe water to supply. distribution system?  Water is abstracted from Gambhir river there • Inadequate protection of intake are no major polluting sources in the works or wells, leading to catchment. pollution of water supply? • Over-pumping of ground water,  No Ground water pumping is required as leading to salinization and Surface water source is selected for the ground subsidence? project • Excessive algal growth in  Regular cleaning of storage tanks will be storage reservoir? conducted during operation. • Increase in production of  As per CPHEEO manual the rate of water sewage beyond capabilities of supply is 70lpcd for the town where sewerage community facilities? scheme is not anticipated. • Inadequate disposal of sludge  Appropriate provision for sludge drying and from water treatment plants? disposal is included in the project

• Inadequate buffer zone around  No pumping and treatment plants to alleviate noise and other possible nuisances and protect facilities?

117

• Impairments associated with  No transmission lines and access roads? • Health hazards arising from  Measures for safe handling of Chlorine are inadequate design of facilities for included. receiving, storing, and handling of chlorine and other hazardous chemicals? • Health and safety hazards to  Measures for safe handling of Chlorine are workers from the management included. of chlorine used for disinfection and

• Dislocation or involuntary  There is no resettlement of people for project resettlement of people implementation. • Social conflicts between  The contractor will be utilizing the local labour construction workers from other forces as far as possible; in case if it is areas & community workers unavoidable, labour camps and facilities will be provided appropriately. No conflicts envisaged. • Noise and dust from  Dust suppression measures such as water construction activities sprinkling will be employed • Increased road traffic due to  Excavation & Laying pipelines along public interference of construction road will interfere with the traffic. activities? Construction material transport will increase traffic within city and dumping construction material on road cause traffic congestion. Proper traffic & Construction planning will be ensured to minimize the interference. • Continuing soil erosion, silt  Construction work during monsoon shall be runoff from construction carried out with due care so that silt run off due operation to construction operation is prevented. • Delivery of unsafe water due to  No, appropriate O&M will be conducted. poor O&M treatment processes (especially mud accumulations

in filters) and inadequate chlorination due to lack of adequate monitoring of chlorine residuals in distribution systems? • Delivery of water to distribution  Not envisaged. system, which is corrosive due to inadequate attention to feeding of corrective chemicals? • Accidental leakage of Chlorine  Measures for safe handling of chlorine are gas included.

118

• Excessive abstraction of water  Water abstraction will be limited to allocate affecting downstream water quantity for Athana. users? • Competing uses of water?  -

• Increased sewage flow due to  As per CPHEEO manual the rate of water increased water supply? supply is 70lpcd for the town where sewerage scheme is not anticipated • Increased volume of sullage  No (wastewater from cooking and washing) and sludge from waste water treatment plant?

• Large population influx during  minimum influx of population during the project construction and construction and operation period. operation that causes increased

burden on social infrastructure

and services (such as water supply and sanitation systems)? • Social conflicts if workers from  The contractor will be advised to absorb local other regions or countries are labour forces as far as possible; in case if it is hired? unavoidable, labour would be hired for temporary phase. No conflicts envisaged.

• Risks to community health and  No such materials are used in project so no safety due to the transport, risk to community health & safety storage, and use and/or disposal of materials such as explosives, fuel, and other chemicals during operation and construction ?

• Community safety risks due  Proper safety measures would be ensured to both accidental and natural during the construction & operation and hazards, especially where the decommissioning. structural elements or components of the project are accessible to members of the affected community or where their failure could result in injury to the community throughout project construction, operation, and decommissioning ?

119

Climate Change and Disaster Risk Yes No Remarks Questions The following questions are not for environmental categorization.They are included in this checklist to help identify potential climate and disaster risks. Is the Project are a subject to hazards √ Semi-arid zone, unreliable such as earthquakes, floods, landslides, rainfall, less vegetation cover. tropicalcy clone winds, storm surges, Promote more efficient use of tsunami or volcanic eruptions and water by reducing losses and climate changes? wastage to counter increased demands due to higher temperatures.

Could changes in temperature, √ Reduction in rainfall may affect precipitation, or extreme events patterns the water availability from dam. over the Project lifespan affect technical or Given financial the priority for drinking water sustainability(e.g., changes in rainfall supply, dead storage will be patterns disrupt reliability utilized in case of low rain fall of water supply; sea level rise creates years salinity intrusion into proposed water supply source)?

Are there any demographic or socio- √ No economic aspects of the Project area that are already vulnerable(e.g., high in cadence of marginalized populations, rural-urban migrants, illegal Settlements, ethnic minorities, women or children)?

Could the Project potentially increase the √ No climate or disaster vulnerability of the surrounding area(e.g. ,by using water from A vulnerable source that is relied upon by many user groups, or encouraging settlement in earthquake zones)?

120

II. Country/Project: India/Madhya Pradesh Urban Services Improvement program- Gautampura- Water Supply Subproject Sector/Division: Urban Development & Environment Department/MPUDC Screening Questions Yes No Remarks

A.PROJECT SITING IS THE PROJECT AREA • Densely populated?  The project covers entire town including the densely populated areas. There are no major negative impacts envisaged because Distribution lines will be located in unused Government lands along side the existing roads and can be constructed without causing disturbance to houses and commercial establishments. In narrow streets disruption to road users is likely and measures like best activity scheduling, alternative routes, prior information to road users, houses and shops will minimize the impact to acceptable levels. The site of WTP is located in less dense area so no negative impact envisaged.

• Heavy with development  No activities? • Adjacent to or within any  No environmentally sensitive areas? No • Cultural heritage site/Historical  importance • Protected area  No • Wetland  No • Mangrove  No • Estuarine  No • Buffer zone of protected  No Area • Special area for  No protecting biodiversity • Bay  No B.POTENTIAL ENVIRONMENTAL IMPACTS Will the project cause… There are no significant water pollution • Pollution of raw water supply sources in the catchment. Raw water quality is From upstream wastewater tested and found that it is suitable for Discharge from communities, Domestic use. industries, agriculture, and soil erosion runoff? 

121

• Impairment of historical /cultural monuments/areas, and  loss/damage to these sites?

• Hazard of land subsidence Not applicable, subproject does not involve caused by excessive ground  groundwater abstraction water pumping?

• Social conflicts arising from Project does not involve land acquisition displacement of communities  /displacement .No social conflicts envisaged.

• Conflicts in abstraction of raw water for water supply with other beneficial water uses for surface and ground waters?

No, the water will be abstracted with due  permission of Water Resource Department from Chambal River • Unsatisfactory raw water supply (e.g. excessive pathogens or Raw water Quality is tested and found that it is mineral constituents)?  suitable for Domestic use.

Water will be treated and disinfected prior to • Delivery of unsafe water to supply. distribution system? 

Water is abstracted from Chambal river there • Inadequate protection of intake are no major polluting sources in the works or wells, leading to  catchment. pollution of water supply? • Over-pumping of ground water, No Ground water pumping is required as leading to salinization and Surface water source is selected for the ground subsidence?  project • Excessive algal growth in Regular cleaning of storage tanks will be storage reservoir?  conducted during operation. • Increase in production of As per CPHEEO manual the rate of water sewage beyond capabilities of supply is 70lpcd for the town where sewerage community facilities?  scheme is not anticipated. • Inadequate disposal of sludge from water treatment plants? Appropriate provision for sludge drying and  disposal is included in the project • Inadequate buffer zone around pumping and treatment plants to alleviate noise and other possible nuisances and protect facilities?  No 122

• Impairments associated with transmission lines and access roads?  No • Health hazards arising from Measures for safe handling of Chlorine are inadequate design of facilities for included. receiving, storing, and handling  of chlorine and other hazardous chemicals? • Health and safety hazards to workers from the management of chlorine used for disinfection  Measures for safe handling of Chlorine are and included.

• Dislocation or involuntary There is no resettlement of people for project resettlement of people  implementation.

The contractor will be utilizing the local labour • Social conflicts between forces as far as possible; in case if it is construction workers from other unavoidable, labour camps and facilities will be areas & community workers  provided appropriately. No conflicts envisaged.

• Noise and dust from Dust suppression measures such as water construction activities  sprinkling will be employed

Excavation & Laying pipelines along public road will interfere with the traffic. • Increased road traffic due to Construction material transport will increase interference of construction traffic within city and dumping construction activities?  material on road cause traffic congestion. Proper traffic & Construction planning will be ensured to minimize the interference. • Continuing soil erosion, silt Construction work during monsoon shall be runoff from construction carried out with due care so that silt run off due operation  to construction operation is prevented. • Delivery of unsafe water due to poor O&M treatment processes (especially mud accumulations in filters) and inadequate chlorination due to lack of  No, appropriate O&M will be conducted. adequate monitoring of chlorine

residuals in distribution systems? • Delivery of water to distribution  Not envisaged. system, which is corrosive due to inadequate attention to

123

feeding of corrective chemicals?

• Accidental leakage of Chlorine Measures for safe handling of chlorine are gas  included. • Excessive abstraction of water Water abstraction will be limited to allocate affecting downstream water  quantity for Gautmapura. users? • Competing uses of water? Water abstraction will be limited to allocate  quantity for Athana As per CPHEEO manual the rate of water • Increased sewage flow due to supply is 70lpcd for the town where sewerage increased water supply?  scheme is not anticipated • Increased volume of sullage (wastewater from cooking and washing)and sludge from waste  No water treatment plant? • Large population influx during project construction and operation that causes increased minimum influx of population during the  construction and operation period. burden on social infrastructure

and services (such as water supply and sanitation systems)? The contractor will be advised to absorb local • Social conflicts if workers from labour forces as far as possible; in case if it is other regions or countries are unavoidable, labour would be hired for hired?  temporary phase. No conflicts envisaged.

• Risks to community health and safety due to the transport, storage, and use and/or disposal of materials such as explosives, fuel, and other chemicals during operation and No such materials are used in project so no construction ?  risk to community health & safety • Community safety risks due to both accidental and natural Proper safety measures would be ensured hazards, especially where the during the construction & operation and structural elements or  decommissioning. components of the project are accessible to members of the affected community or where their failure could result in injury to the community throughout project construction, operation, and decommissioning ?

124

Climate Change and Disaster Risk Questions Ye No Remarks The following questions are not for s environmental categorization.They are included in this checklist to help identify potential climate and disaster risks.

Is the Project are a subject to hazards such √ Semi-arid zone, unreliable as earthquakes, floods, landslides, tropicalcy rainfall, less vegetation cover. clone winds, storm surges, tsunami or Promote more efficient use of volcanic eruptions and climate changes? water by reducing losses and wastage to counter increased demands due to higher Could changes in temperature, precipitation, or √ Reduction in rainfall may affect extreme events patterns over the Project the water availability from dam. lifespan affect technical or financial Given sustainability(e.g., changes in rainfall patterns the priority for drinking water disrupt reliability supply, dead storage will be of water supply; sea level rise creates utilized in case of low rain fall salinity intrusion into proposed water supply years source)?

Are there any demographic or socio-economic √ No aspects of the Project area that are already vulnerable(e.g., high in cadence of marginalized populations, rural-urban migrants, illegal Settlements, ethnic minorities, women or children)?

Could the Project potentially increase the √ No climate or disaster vulnerability of the surrounding area(e.g. ,by using water from A vulnerable source that is relied upon by many user groups, or encouraging settlement in earthquake zones)?

125

III. Country/Project: India/Madhya Pradesh Urban Services Improvement program-Depalpur- Water Supply subproject Sector/Division: Urban Development & Environment Department/MPUDC

Screening Questions Yes No Remarks A. PROJECT SITING IS THE PROJECT AREA Depalpur town is having average density 17406 / Sqkm Project covers entire town including the density population areas. There are no major negative impacts envisaged because pipeline will be located in unused Government lands along side the existing roads and can be constructed without causing disturbance to houses and  commercial establishments. In narrow • Densely populated? streets disruption to road users is likely and

measures like best activity scheduling, alternative routes, prior information to road users, houses and shops will minimize the impact to acceptable levels. • Heavy with development activities?  No • Adjacent to or within any environmentally sensitive areas?  No

• Cultural heritage site

 No.

• Protected area  No • Wetland  No • Mangrove  No • Estuarine  No • Buffer zone of protected Area  No • Special area for protecting biodiversity  No • Bay  No B.POTENTIAL ENVIRONMENTAL IMPACTS Will the project cause… • Pollution of raw water supply There are no significant water pollution from upstream wastewater discharge from  sources in the catchment. Raw water quality communities, is tested and found that it is suitable for industries, agriculture, and Domestic use. soil erosion runoff?

126

• Impairment of historical / In Depalpur only traces of fort wall found ,it cultural monuments/areas, and loss/damage to these is not a Heritage town. Project works do not sites?  impair any part of wall or sites.

• Hazard of land subsidence caused by excessive ground Not applicable, subproject does not involve water pumping?  groundwater abstraction

Project does not involve land acquisition • Social conflicts arising from /displacement .No social conflicts displacement of communities envisaged.  No, the water will be abstracted with due of Water Resource Department .Keetkhedi • Conflicts in abstraction of raw water for water supply dam having gross storage capacity of with other beneficial water 21.06MCM and it is presently used for uses for surface and ground  irrigation purpose & net capacity required for waters? Depalpur Water Supply scheme is

1.23MCM.Moreover water abstraction is just 5% of gross storage. • Unsatisfactory raw water supply (e.g. excessive pathogens or mineral  Raw water Quality is tested and found that it constituents)? is suitable for Domestic use. Water will be treated and disinfected prior to • Delivery of unsafe water to supply. distribution system?  • Inadequate protection of Water is abstracted from Keetkhedi Dam intake works or wells, leading to pollution of water there are no major polluting sources in the supply?  catchment No Ground water pumping is required as • Over-pumping of ground water, leading to salinization Surface water source is selected for the and ground subsidence?  project

• Excessive algal growth in Regular cleaning of storage tanks will be storage reservoir?  conducted during operation. As per CPHEEO manual the rate of water • Increase in production of sewage beyond capabilities supply is 70lpcd for the town where of community facilities?  sewerage scheme is not anticipated. • Inadequate disposal of sludge from water treatment Appropriate provision for sludge drying and plants? disposal is included in the project  • Inadequate buffer zone around pumping and treatment plants to alleviate noise and other possible No nuisances and protect facilities?  • Impairments associated with transmission lines and No access roads? 

127

• Health hazards arising from inadequate design of Measures for safe handling of Chlorine are facilities for receiving, included. storing, and handling of  chlorine and other hazardous chemicals? • Health and safety hazards to workers from the Measures for safe handling of Chlorine are management of chlorine  included. used for disinfection and

• Dislocation or involuntary There is no resettlement of people for resettlement of people  project implementation. The contractor will be utilizing the local • Social conflicts between labour forces as far as possible; in case if it construction workers from is unavoidable, labour camps and facilities other areas & community  will be provided appropriately. No conflicts workers envisaged. • Noise and dust from Dust suppression measures such as water construction activities  sprinkling will be employed Excavation & Laying pipelines along public • Increased road traffic due to  road will interfere with the traffic. interference of construction Construction material transport will increase activities? traffic within city and dumping construction material on road cause traffic congestion. Proper traffic & Construction planning will be ensured to minimize the interference. • Continuing soil erosion, silt Construction work during monsoon shall be runoff from construction carried out with due care so that silt run off operation  due to construction operation is prevented. • Delivery of unsafe water due to poor O&M treatment processes (especially mud Appropriate O&M will be conducted accumulations in filters) and inadequate chlorination due to lack of adequate monitoring of chlorine residuals in distribution systems?  • Delivery of water to distribution system, which is Not envisaged corrosive due to inadequate  attention to feeding of corrective chemicals? Measures for safe handling of chlorine are • Accidental leakage of included. Chlorine gas 

• Excessive abstraction of  Water abstraction will be limited to allocate 128

water affecting downstream quantity for Depalpur. water users? • competing uses of water? Water abstraction will be limited to allocate  quantity for Depalpur. As per CPHEEO manual the rate of water • Increased sewage flow due supply is 70lpcd for the town where to increased water supply?  sewerage scheme is not anticipated • increased volume of sullage (wastewater from cooking and washing)and sludge No from waste water treatment plant?  • large population influx during project construction and minimum influx of population during the operation that causes construction and operation period. increased burden on social infrastructure and services (such as water supply and sanitation systems)?  The contractor will be advised to absorb • Social conflicts if workers local labour forces as far as possible; in from other regions or case if it is unavoidable, labour would be countries are hired? hired for temporary phase. No conflicts  envisaged.

• Risks to community health and safety due to the No such materials are used in project so no transport, storage, and use risk to community health & safety. and/or disposal of materials such as explosives, fuel, and other chemicals during operation and construction ? 

• Community safety risks due to both accidental and Proper safety measures would be ensured natural hazards, especially during the construction & operation and where the structural decommissioning. elements or components of the project are accessible to members of the affected community or where their failure could result in injury to the community throughout project construction, operation, and decommissioning ? 

129

Climate Change and Disaster Risk Yes No Remarks Questions The following questions are not for environmental categorization. They are included in this checklist to help identify potential climate and disaster risks.

Is the Project area subject to hazards such √ Semi-arid zone, unreliable as earthquakes, floods, landslides, tropical rainfall, less vegetation cover. cyclone winds, storm surges, tsunami or Promote more efficient use of volcanic eruptions and climate changes? water by reducing losses and wastage to counter increased demands due to higher temperatures.

Could changes in temperature, precipitation, √ Reduction in rainfall may affect or extreme events patterns over the Project the water availability from dam. lifespan affect technical or financial Given sustainability (e.g., changes in rainfall patterns the priority for drinking water disrupt reliability supply, dead storage will be of water supply; sea level rise creates utilized in case of low rain fall salinity intrusion into proposed water years supply source)?

Are there any demographic or socio- √ No economic aspects of the Project area that are already vulnerable (e.g.,high incidence of marginalized populations, rural-urban migrants, illegal Settlements, ethnic minorities, women or children)?

Could the Project potentially increase the √ No climate or disaster vulnerability of the surrounding area (e.g., by using water from a vulnerable source that is relied upon by many user groups, or encouraging settlement in earthquake zones)?

130

Appendix 2: National Ambient Air Quality Standards

Sl Pollutants Time Concentration in ambient air Method of No: weighted Industrial, Ecologically measurement average Residential, Sensitive Rural & Other Areas Areas 1 Sulphur Dioxide Annual 50 20 Improved West and

(SO2) 24 hours 80 80 Geake-Ultraviolet µg/m3 fluorescence 2 Nitrogen Dioxide Annual 40 30 Modified Jacob

3 (NO2) µg/m 24 hours 80 80 &Hochheiser (Na- Arsenite) Chemiluminescence 3 Particulate Annual 60 60 Gravimetric Matter (Size 24 hours 100 100 -TOEM less than 10 µm) -Beta attenuation or PM10 µg/m3 4 Particulate Annual 40 40 Gravimetric Matter (Size 24 hours 60 60 -TOEM less than 2.5 -Beta attenuation µm) or PM2.5 µg/m3 5 Carbon 8 hours 02 02 Non Dispersive Infra Monoxide (CO) 1 hours 04 04 Red (NDIR) mg/m3 Spectroscopy

131

Appendix 3: Vehicle Exhaust Emission Norms 1. Passenger Cars Norms CO( g/km) HC+ NOx(g/km) 1991Norms 14.3-27.1 2.0(Only HC) 1996 Norms 8.68-12.40 3.00-4.36 1998Norms 4.34-6.20 1.50-2.18 India stage 2000 norms 2.72 0.97 Bharat stage-II 2.2 0.5 Bharat Stage-III 2.3 0.35 (combined) Bharat Stage-IV 1.0 0.18 (combined)

2. Heavy Diesel Vehicles Norms CO( g/kmhr) HC (g/kmhr) NOx (g/kmhr) PM(g/kmhr) 1991Norms 14 3.5 18 - 1996 Norms 11.2 2.4 14.4 - India stage 2000 norms 4.5 1.1 8.0 0.36 Bharat stage-II 4.0 1.1 7.0 0.15 Bharat Stage-III 2.1 1.6 5.0 0.10 Bharat Stage-IV 1.5 0.96 3.5 0.02 Source: Central Pollution Control Board CO = Carbon Monixide; g/kmhr = grams per kilometer-hour; HC = Hydrocarbons; NOx = oxides of nitrogen; PM = Particulates Matter

132

Appendix 4: National Ambient Air Quality Standards in Respect of Noise

Area code Category of area/zone Limit in dB (A) Day time Night time A Industrial area 75 70 B Commercial area 65 55 C Residential area 55 45 D Silence zone 50 40

133

Appendix 5: Extract From Construction & Demolition Management Rules, 2016

134

135

136

137

138

139

Appendix 6: Salient Features of Major Labor Laws Applicable to Establishments Engaged in Construction of Civil Works

(i) Workmen Compensation Act, 1923 - The Act provides for compensation in case of injury by accident arising out of and during the course of employment.

(ii) Payment of Gratuity Act, 1972 - Gratuity is payable to an employee under the Act on satisfaction of certain conditions on separation if an employee has completed 5 years’ service or more or on death at the rate of 15 days wages for every completed year of service. The Act is applicable to all establishments employing 10 or more employees.

(iii) Employees’ PF and Miscellaneous Provisions Act, 1952 - The Act provides for monthly contributions by the employer plus workers @10 % or 8.33 %. The benefits payable under the Act are: (a) Pension or family pension on retirement or death as the case may be; (b) deposit linked insurance on the death in harness of the worker; (c) payment of PF accumulation on retirement/death etc.

(iv) Maternity Benefit Act, 1951 - The Act provides for leave and some other benefits to women employees in case of confinement or miscarriage etc.

(v) Contract Labour (Regulation and Abolition) Act, 1970 - The Act provides for certain welfare measures to be provided by the Contractor to contract labor and in case the Contractor fails to provide, the same are required to be provided by the Principal Employer by Law. The principal employer is required to take Certificate of Registration and the Contractor is required to take a License from the designated Officer. The Act is applicable to the establishments or Contractor of principal employer if they employ 20 or more contract labor.

(vi) Minimum Wages Act, 1948 - The employer is supposed to pay not less than the Minimum Wages fixed by appropriate Government as per provisions of the Act if the employment is a scheduled employment. Construction of Buildings, Roads, Runways are scheduled employment.

(vii) Payment of Wages Act, 1936 - It lays down as to by what date the wages are to be paid, when it will be paid and what deductions can be made from the wages of the workers.

(viii) Equal Remuneration Act, 1979 - The Act provides for payment of equal wages for work of equal nature to Male and Female workers and not for making discrimination against Female employees in the matters of transfers, training and promotions etc.

(ix) Payment of Bonus Act, 1965 - The Act is applicable to all establishments employing 20 or more workmen. The Act provides for payments of annual bonus subject to a minimum of 8.33 % of wages and maximum of 20 % of wages to employees drawing Rs. 3,500/- per month or less. The bonus to be paid to employees getting Rs. 2,500/- per month or above up to Rs.3,500/- per month shall be worked out by taking wages as Rs.2,500/- per month only. The Act does not apply to certain establishments. The newly set up establishments are exempted for five years in certain circumstances. Some of the State Governments have reduced the employment size from 20 to 10 for the purpose of applicability of the Act.

(x) Industrial Disputes Act, 1947 - The Act lays down the machinery and procedure for resolution of industrial disputes, in what situations a strike or lock-out becomes illegal and what

140

are the requirements for laying off or retrenching the employees or closing down the establishment.

(xi) Industrial Employment (Standing Orders) Act, 1946 - It is applicable to all establishments employing 100 or more workmen (employment size reduced by some of the States and Central Government to 50). The Act provides for laying down rules governing the conditions of employment by the employer on matters provided in the Act and get the same certified by the designated Authority.

(xii) Trade Unions Act, 1926 - The Act lays down the procedure for registration of trade unions of workmen and employees. The trade unions registered under the Act have been given certain immunities from civil and criminal liabilities.

(xiii) Child Labor (Prohibition and Regulation) Act, 1986 - The Act prohibits employment of children below 14 years of age in certain occupations and processes and provides for regulation of employment of children in all other occupations and processes. Employment of child labor is prohibited in Building and Construction Industry.

(xiv) Inter-State Migrant Workmen's (Regulation of Employment and Conditions of Service) Act, 1979 - The Act is applicable to an establishment which employs 5 or more inter-state migrant workmen through an intermediary (who has recruited workmen in one state for employment in the establishment situated in another state). The inter-state migrant workmen, in an establishment to which this Act becomes applicable, are required to be provided certain facilities such as housing, medical aid, traveling expenses from home up to the establishment and back, etc

(xv) The Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996 and the Cess Act of 1996 - All the establishments who carry on any building or other construction work and employ 10 or more workers are covered under this Act. All such establishments are required to pay Cess at rate not exceeding 2% of the cost of construction as may be notified by the Government. The employer of the establishment is required to provide safety measures at the building or construction work and other welfare measures, such as canteens, first-aid facilities, ambulance, housing accommodation for workers near the workplace etc. The employer to whom the Act applies has to obtain a registration certificate from the Registering Officer appointed by the Government.

141

Appendix 7: Stakeholder Consultation at Depalpur, Betma and Gautampura Town Appendix 8: Summary of Consultation with Stakeholders-Depalpur

Date Location No. of Participant Topic Issue raised Participants Discussed 11th May At Total=26 UlB Chairman The Water • The Chairman 2018 Community M=21, F=4 & Vice Supply Project of the ULB y hall, Chairman, ULB Background, expressed Nagar Sub Engineer, Environmental, willingness to accept the Parishad Asstt. Sub Social, traffic project; engineer, ULB safety issue and • Willingness to Staff, benefit from the connect to Representative project were piped drinking of Member of explained to the water supply; Parliament Stakeholders. • Depalpur (MP), Ward Nagar Parishad is Parshads & • Present drinking water operating local peoples water supply supply source system for the and its town but condition capacity to be • Need of build. improvement of the present • The existing water supply situation system is in • Briefing on dilapidated project condition and objectives needs probable refurbishment implementatio along with water supply n procedures coverage (100 • Potential percent). positive and • Land required negative for the water impacts due supply project to project will be dealt by the ULB and implementatio they will handle n this with the • Land use and concerned area to be government covered under departments. the project • community • Drinking water participation in user charge project implementation • Grievance

142

Redress ; procedures • Implementing agency; and better /improved service. • Operation and maintenance of the facilities developed under the project and community participation; • Probability of keeping the poor and the vulnerable out of the user charge.

11th Ward No. Total=19 Slum area • Briefing on • None of the May.2018 8, Nehru M=5, F=14 project people knew Marg objectives about the probable proposed implementatio project. n procedures • On learning • Potential about the positive and project, they negative expressed that impacts due they were to project happy that the implementatio entire n community • Experiences would be sharing on - benefited from livelihood the upgraded activities, water supply. Resettlement • Assured full and support during Rehabilitation, implementation women . empowerment • Agreed on tribal taking water development, connections health, but user education, charges to be convergence reduced for

143

with existing slum people. government social security schemes etc. • Grievance Redress procedures

11th May Ward No. Total=40 Community • Status of • The area has 2018 10, M=10, F=30 People existing insufficient and Ayodhya drinking water inadequate Basti supply drinking water system; resource. • Need for Water supply improvements to the area is to present done through system; tube wells that • Relevant supplies water information of to the the upcoming community project and people. The benefits of the area faces project. severe water • Potential crisis during positive and the summer negative season when impacts due the ground to project water level implementatio drops. n • The community • Ensuring no willingly income loss accepted the • Grievance project. The Redress community procedures members • Experiences expressed that sharing on - their economic livelihood situation would activities, prevent them Resettlement from paying and water user Rehabilitation, charges. (The women men work as empowerment daily laborers tribal and the women development, Housewives). health, education, convergence with existing

144

government social security schemes etc.

In 216 - Total =10 Community • Status of • The area has M=10, F=0 People existing insufficient and drinking water inadequate supply drinking water system; resource. • Need for Water supply improvements to the area is to present done through system; two tube wells • Relevant that supplies information of water to the the upcoming community project and people. The benefits of the area faces project. severe water • Potential crisis during positive and the summer negative season when impacts due the ground to project water level implementatio drops. n • The community • Ensuring no willingly income loss accepted the project. The community members expressed that their economic situation would prevent them from paying water user charges. (The men work as daily laborers and the women Housewives).

145

Appendix 9: Depalpur Stakeholder Consultation Photographs and List of Participant

Photogrphs of Consultation with ULB Chairman, Ward Parshads, other Officials of Nagar Parishad in May 2018

146

147

Consultation Photograps at Ward No 8, Nehru Marg with Local Peoples & List of Participant

148

149

Consultation Photograps at Ward No 10, Ayodhya Nagar with Local Peoples & List of Participant

150

151

152

Consultation Photograps with Local Peoples & Local representatives alongwith List of Participant in 2016

153

154

Appendix 10: Summary of Consultation with Stakeholders-Gautampura Date Location No. of Participant Topic Issue raised Participant Discussed 11nd At ULB Total = 13 CMO, ULB The Water • CMO has May Office official, Sub Supply Project concern that the 2018 M= 8, F= 5 Engineer, Ward Background, project financial Parshads/ Environmental, burden Nagar Elected Social, GRM, Palika able to representatives traffic safety handle or not & local peoples issue and benefit • The Chairman of from the project the ULB were explained to expressed the Stakeholders. willingness to accept the • Present project; drinking water • Willingness to supply source connect to piped and its drinking water condition supply; • Need of • Gautampura improvement of Nagar Parishad the present is operating situation water supply • Briefing on system for the project town but capacity objectives to be build. probable • community implementation participation in procedures project • Potential implementation; positive and • Implementing negative agency; and impacts due to better /improved project service. implementation • Operation and • Land use and maintenance of area to be the facilities covered under developed under the project the project and • Drinking water community user charge participation; • Probability of keeping the poor and the

155

vulnerable out of the user charge.

11th Ward No. Community The Water • The area has May 06 Total = 12 People Supply Project insufficient and 2018 Bhoi Background, inadequate Mohalla M= 8, F= 4 Environmental, drinking water Social, GRM, resource. Water traffic safety supply to the issue and benefit area is done from the project through two tube were explained to wells that the Stakeholders. supplies water to the community • Status of people. The area existing faces severe drinking water water crisis supply system; during the • Need for summer season improvements when the ground to present water level system; drops. • Relevant • The community information of willingly accepted the upcoming the project. The project and community benefits of the members expressed that project. their economic • Potential situation would positive and prevent them negative from paying impacts due to water user project charges. (The implementation men work as daily laborers Ensuring no and the women income loss Housewives).

156

11th Ward No. Total = 13 Community • Briefing on • None of the May 10 people project people knew 2018 Bagh M= 5, F= 8 objectives about the Mohalla probable proposed project implementation • On learning procedures about the • Potential project, they positive and expressed that negative they were happy impacts due to that the entire project community implementation would be • Experiences benefited from sharing on - the upgraded livelihood water supply. activities, • Assured full Resettlement support during and implementation. Rehabilitation, women empowerment tribal development, health, education, convergence with existing government social security schemes etc. • Grievance Redress procedures 11th Ward No. Total = 14 Community The Water • The area has May 05 People Supply Project insufficient and 2018 M= 6, F= 8 Background, inadequate Sarvi Environmental, drinking water Mohalla Social, traffic resource. Water safety issue and supply to the benefit from the area is done project were through two tube explained to the wells that Stakeholders. supplies water to the community • Status of people. The area existing faces severe drinking water water crisis supply system; during the

157

• Need for summer season improvements when the ground to present water level system; drops. • Relevant • The community information of willingly the upcoming accepted the project and project. The benefits of the community project. members • Potential expressed that positive and their economic negative situation would impacts due to prevent them project from paying implementation water user • Ensuring no charges. (The income loss men work as • Community daily laborers participation in and the women project Housewives). implementation • As excavation • Completion of not been able to project on time. done at night • shifting of because labour Street vendors. will not get agree • Shifting or to work in night adjusting shift so shifting extended will be done at a potion of vacant place near or next lane shopkeepers. such that no income loss takes place due the civil work. Vendors get agreed on proposal

2016 At Parishad Chairperson of The Water • ULB Chairman Hall, ULB, Ward Supply Project has concern that Gautampura Parshads/ Background, the project Environmental, Elected financial burden Social, traffic Nagar Palika representatives safety issue and able to handle or & local peoples benefit from the not

158

project were • The Chairman of explained to the the ULB Stakeholders. expressed • Present willingness to drinking water accept the supply source project; and its • Willingness to condition connect to piped • Need of drinking water improvement of supply; the present • Gautampura situation Nagar Parishad • Briefing on is operating project water supply objectives system for the probable town but capacity implementation to be build. procedures • community • Potential participation in positive and project negative implementation; impacts due to • Implementing project agency; and implementation better /improved • Land use and service. area to be • Operation and covered under maintenance of the project the facilities Drinking water developed under user charge the project and community participation; • Probability of keeping the poor and the vulnerable out of the user charge.

159

Appendix 11: Gautampura Stakeholder Consultation Photographs & List of Participants

Photogrphs of Consultation with CMO of Nagar Parishad Gautampur in May 2018

Photogrphs of Consultation with CMO and Ward Parshads, other Officials of Nagar Parishad in May 2018

160

161

162

Consultation Photograps at Ward No 06, Bhoi Mohalla with Local Peoples & List of Participant

163

164

Consultation Photograps at Ward No 10, Bhag Mohalla with Local Peoples & List of Participant

165

166

Consultation Photograps at Ward No 05, Sarvi Mohalla with Local Peoples & List of Participant

167

168

Photogrphs of Consultation with ULB Official, Ward Parshads, other Officials of Nagar Parishad & Local people in May 2016

169

170

171

Appendix 12: Summary of Consultation with Stakeholders-Betma Nagar Parishad

Date Location Participant Topic Discussed Issue raised 8th At Nagar Total = Chairperson of The Water Supply • ULB Chairman has May. Parishad 20 ULB, CMO, Project Background, concern that the project 2018 Office Ward Parshads , Environmental, Social, financial burden Nagar M = 15, ULB Official, traffic safety issue and Palika able to handle or F = 05 DBO Contractor, benefit from the project not PIU PMC Indore were explained to the • The Chairman of the Stakeholders. ULB expressed willingness to accept the • Present drinking project; water supply source • Willingness to connect and its condition to piped drinking water • Need of improvement supply; of the present • Betma Nagar Parishad situation is operating water • Briefing on project supply system for the objectives probable town but capacity to be implementation build. procedures • community participation • Potential positive and in project negative impacts due implementation; to project • Implementing agency; implementation and better /improved • Land use and area to service. be covered under the • Operation and project maintenance of the • Drinking water user facilities developed charge under the project and community participation; • Probability of keeping the poor and the vulnerable out of the user charge.

172

8th Ward No. Total = Community • Briefing on project • None of the people May 01 21 People objectives probable knew about the 2018 implementation proposed project. On M = 4, F procedures learning about the = 17 • Potential positive and project, they expressed negative impacts due that they were happy to project that the entire implementation community would be • Experiences sharing benefited from the on - livelihood upgraded water supply. activities, • Assured full support Resettlement and during implementation. Rehabilitation, women empowerment tribal development, health, education, convergence with existing government social security schemes etc. • Grievance Redress procedures 8th Ward No. Total = Community The Water Supply • The area has May 03 15 People Project Background, insufficient and 2018 Environmental, Social, inadequate drinking M = 4, traffic safety issue and water resource. Water F = 11 benefit from the project supply to the area is were explained to the done through tube wells Stakeholders that supplies water to • Status of existing the community people. drinking water supply The area faces severe system; water crisis during the • Need for summer season when improvements to the ground water level present system; drops. • Relevant information • The community willingly of the upcoming accepted the project. project and benefits The community of the project. members expressed • Potential positive and that their economic negative impacts due situation would prevent to project them from paying water implementation user charges. (The men • Ensuring no income work as daily laborers loss and the women Housewives).

173

8th Ward No. Total = Community The Water Supply • The area has May 02 16 People Project Background, insufficient and 2018 Environmental, Social, inadequate drinking M = 8, F traffic safety issue and water resource. Water = 8 benefit from the project supply to the area is were explained to the done through tube wells Stakeholders that supplies water to • Status of existing the community people. drinking water supply The area faces severe system; water crisis during the • Need for summer season when improvements to the ground water level present system; drops. • Relevant information • The community willingly of the upcoming accepted the project. project and benefits The community of the project. members expressed • Potential positive and that their economic negative impacts due situation would prevent to project them from paying water implementation user charges. (The men Ensuring no income work as daily laborers loss and the women Housewives). 8th Ward No. Total = Community The Water Supply • The area has May 07 & 08 17 People Project Background, insufficient and 2018 Environmental, Social, inadequate drinking M = 7, traffic safety issue and water resource. Water F = 10 benefit from the project supply to the area is were explained to the done through tube wells Stakeholders that supplies water to • Status of existing the community people. drinking water supply The area faces severe system; water crisis during the • Need for summer season when improvements to the ground water level present system; drops. • Relevant information • The community willingly of the upcoming accepted the project. project and benefits The community of the project. members expressed • Potential positive and that their economic negative impacts due situation would prevent to project them from paying water implementation user charges. (The men Ensuring no income work as daily laborers loss and the women Housewives).

174

8th Ward No. Total = Community • Briefing on project • None of the people May 10, 16 People objectives probable knew about the 2018 Malviya implementation proposed project. On Mohalla M = 5, procedures learning about the • Potential positive and project, they expressed F = 11 negative impacts due that they were happy to project that the entire implementation community would be • Experiences sharing benefited from the on - livelihood upgraded water supply. activities, • Assured full support Resettlement and during implementation. Rehabilitation, women empowerment tribal development, health, education, convergence with existing government social security schemes etc. Grievance Redress procedures 8th Ward No. Total =38 Shopkeepers, The Water Supply • As excavation not been May 11, Project Background, able to done at night 2018 Ambedkar M =6, F = Environmental, Social, because labour will not Mohalla 32 traffic safety issue and get agree to work in benefit from the project night shift so shifting will were explained to the be done at a vacant Stakeholders place near or next lane • Project effective for such that no income Shadora community loss takes place due the people civil work. Vendors get • Community agreed on proposal participation in • project implementation • Completion of project on time. • Vyapari Sangh will cooperate when laying done in congested whole sale market temporarily shifting of weekly vegetable market during excavation. • shifting of Street vendors. • Shifting or adjusting

175

extended potion of shopkeepers. Appendix 13: Betma Stakeholder Consultation Photographs & List of Participants

Photogrphs of Consultation with ULB Chairman, CMO and Ward Parshads, other Officials of Nagar Parishadin May 2018

176

177

178

Consultation Photograps at Ward No 01, Tehsil Tappa with Local Peoples & List of Participant

179

180

Consultation Photograps at Ward No 03, Shikshak Nagar with Local Peoples & List of Participant

181

182

Consultation Photograps at Ward No 02, with Local Peoples & List of Participant

183

184

Consultation Photograps at Ward No 07-8, with Local Peoples & List of Participant

185

186

Consultation Photograps at Ward No. 10, Malviya Mohalla with Local Peoples & List of Participant

187

188

Consultation Photograps at Ward No. 11, Ambedkar Mohalla with Local Peoples & List of Participant

189

190

191

192

Appendix 14: Press Release about meeting with Ward Parshads on proposed subproject WSS - Betma in the leading newspaper namely Nai Duniya

193

Appendix 15: Data related to Betma WSS

Census Population of the Town 2011 Sr. No. Year Population 1 1981 6580 2 1991 9587 3 2001 12530 4 2011 15999

Ward Wise Population 2011 Ward Ward Name Population no. 1 Jawahar ward 1062 2 Mahatma Gandhi ward 952 3 Subhash ward 906 4 Shastri ward 1186 5 Dr. Ambedkar ward 1057 6 Devi Ahilya ward 1066 7 Indra ward 1045 8 Dr. Jakir Hussain ward 981 9 Azad ward 1044 10 Walmiki ward 1079 11 Shivaji ward 1059 12 Maharana Pratap ward 1036 13 Samrat Ashok ward 1087 14 Mahaveer ward 1235 15 Annpurna ward 1204 Total 15999

194

Details of water source & system S.No. Ground Source Particulars Details

1. No. of Intake well - 2. No. of Tube wells 17 nos. , 13nos. working Chhota Betma 10nos., 6 nos. working

Dusshera Maidan 4 nos.

Shiv Ghat 1 no.

Balaji 2 nos.

3. No. of Hand pumps 70 nos., 55 nos. working

4. No. of tankers 04 nos.

5. No. of ELSRs 04 nos., 3 nos. working

6. No. of Sump 02 nos. , 100 KL & 65 KL 7. No. of Dug well 01 no., not in use 7. No. of pump 17 nos. , 13 nos. working Chhota Betma 10 nos., 6 nos. 10 HP working

Dusshera 4 nos., 4 nos. 10 HP Maidan working

Shiv Ghat 1 no. 10 HP Balaji 2 nos. 10 HP

8. Per Capita Supply 40 LPCD

Source: Nagar Parishad Betma

195

Appendix 16: Data related to Gautampura WSS

Census Population of the Town Sr. No. Year Population 1 1991 10150 2 2001 13225 3 2011 14584 Ward wise Population of the Town Ward No. Ward name Population 1 1084 Maulana Azad ward 2 1363 Jawahar Ward 3 1214 Shaheed Bhagat singh ward 4 758 Rani Durgavati ward 5 673 Indira ward 6 706 Mahatma Gandhi ward 7 761 Pandit Dindayal ward 8 781 Dr. Zakir Hussain ward 9 1063 Swami vivekanand ward 10 952 Subhash Ward 11 1208 Shashtri ward 12 966 Dr Ambedkar 13 853 Rajiv ward 14 1072 Raidas Ward 15 1131 Valmiki ward 14584 Total

Details of water source & system S.No. Ground Source Particulars Details

1. No. of Intake well NO

2. No. of Tube wells 14nos.

3. No. of Hand pumps 68 nos.

4. No. of tankers 05 nos. working

5. No. of ELSRs 2 nos. working , structurally good.

196

6. No. of Sump 2 nos. 150 KL,100 KL 7. No. of pump 17 nos. (15 nos. 10 HP ,2 nos. 12 HP)

8. Per Capita supply 32 LPCD

197

Appendix 17: Sample Grievance Registration Form

(To be available in Hindi and English) The ______Project welcomes complaints, suggestions, queries, and comments regarding project implementation. We encourage persons with grievance to provide their name and contact information to enable us to get in touch with you for clarification and feedback. Should you choose to include your personal details but want that information to remain confidential, please inform us by writing/typing *(CONFIDENTIAL)* above your name. Thank you.

Date Place of registration Project Town

Project: Contact information/personal details Name Gender * Male Age * Female Home address Place Phone no. E-mail Complaint/suggestion/comment/question Please provide the details (who, what, where, and how) of your grievance below:

If included as attachment/note/letter, please tick here: How do you want us to reach you for feedback or update on your comment/grievance?

FOR OFFICIAL USE ONLY Registered by: (Name of official registering grievance)

Mode of communication: Note/letter E-mail Verbal/telephonic Reviewed by: (Names/positions of officials reviewing grievance)

Action taken:

Whether action taken disclosed: Yes No Means of disclosure:

198

Appendix 18: Sample Outline Spoils (construction waste) Management Plan

• The Spoil Management Plan should be site specific and be part of the monthly Construction Management Plan. • The contractor, in consultation with the PIU, has to find out appropriate location/s for the disposal of the excess soil generated. The spoils should be deposited only at these sites. • Further precautions need to be taken in case of the contaminated spoils • The vehicle carrying the spoil should be covered properly. • The spoils generating from each site should be removed on the same day or immediately after the work is complete. The site / road should be restored to the original condition.

I. Spoils information The spoil information contains the details like a) The type / material, b) Potential contamination by that type, c) Expected volume (site / component specific), d) Spoil Classification etc.

II. Spoils management The Spoil Management section gives the details of a) Transportation of spoil b) disposal site details c) Precautions taken d) Volume of contaminated spoil, if present, d) Suggested reuse of disposal of the spoil

III. Documentation The volume of spoil generated (site specific, date wise), site disposed, reuse / disposal details should be documented properly.

199

200

Appendix 19: Sample Outline Traffic Management Plan

A. Principles for TMP around the Water Pipes Construction Sites

1. One of the prime objectives of this TMP is to ensure the safety of all the road users along the work zone, and to address the following issues: (i) the safety of pedestrians, bicyclists, and motorists travelling through the construction zone; (ii) protection of work crews from hazards associated with moving traffic; (iii) mitigation of the adverse impact on road capacity and delays to the road users; (iv) maintenance of access to adjoining properties; and (v) addressing issues that may delay the project.

B. Operating Policies for TMP

2. The following principles will help promote safe and efficient movement for all road users (motorists, bicyclists, and pedestrians, including persons with disabilities) through and around work zones while reasonably protecting workers and equipment. (i) Make traffic safety and temporary traffic control an integral and high-priority element of project from planning through design, construction, and maintenance. (ii) Inhibit traffic movement as little as possible. (iii) Provide clear and positive guidance to drivers, bicyclists, and pedestrians as they approach and travel through the temporary traffic control zone. (iv) Inspect traffic control elements routinely, both day and night, and make modifications when necessary. (v) Pay increased attention to roadside safety in the vicinity of temporary traffic control zones. (vi) Train all persons that select, place, and maintain temporary traffic control devices. (vii) Keep the public well informed. (viii) Make appropriate accommodation for abutting property owners, residents, businesses, emergency services, railroads, commercial vehicles, and transit operations.

3. Figure A2 to Figure A12illustrates the operating policy for TMP for the construction of water pipes and the sewers along various types of roads.

C. Analyze the impact due to street closure

4. Apart from the capacity analysis, a final decision to close a particular street and divert the traffic should involve the following steps:

(i) approval from the ULB/Public Works Department (PWD) to use the local streets as detours; (ii) consultation with businesses, community members, traffic police, PWD, etc, regarding the mitigation measures necessary at the detours where the road is diverted during the construction; (iii) determining of the maximum number of days allowed for road closure, and incorporation of such provisions into the contract documents;

(iv) determining if additional traffic control or temporary improvements are needed along the detour route; (v) considering how access will be provided to the worksite; (vi) contacting emergency service, school officials, and transit authorities to determine if there are impacts to their operations; and (vii) developing a notification program to the public so that the closure is not a surprise. As part of this program, the public should be advised of alternate routes that commuters can take or will have to take as result of the traffic diversion.

5. If full road-closure of certain streets within the area is not feasible due to inadequate capacity of the detour street or public opposition, the full closure can be restricted to weekends with the construction commencing on Saturday night and ending on Monday morning prior to the morning peak period.

Figure A1: Policy Steps for the TMP

• Review construction schedule and methods Review

Traffic Re- • Identify initial traffic recirculation and control policy Circulation

• Identify routes for traffic diversions Traffic • Analyse adverse impact & mitigation at the detours Diversions

• Begin community consultation for consensus Full Road • Finalise or determine alternate detours Colsures

• Identify temporary parking (on and off -street ) Temporary • Discuss with CMC, owner, community for use parking

• Coordinate with theTraffic Police to enforce traffic and diversions Police Coordination

• Install traffic control devices (traffic cones, sgns, lightings, etc) Install control devices

• Conduct campaigns, publicity, and notify public about street closure Awareness

Develop a mechanism to address public grievances regarding disruptons (traffic, utilities, and diversions) Public • Redress

D. Public awareness and notifications

6. As per discussions in the previous sections, there will be travel delays during the constructions, as is the case with most construction projects, albeit on a reduced scale if utilities and traffic management are properly coordinated. There are additional grounds for travel delays in the area, as most of the streets lack sufficient capacity to accommodate additional traffic from diverted traffic as a result of street closures to accommodate the works.

201

6. The awareness campaign and the prior notification for the public will be a continuous activity which the project will carry out to compensate for the above delays and minimize public claims as result of these problems. These activities will take place sufficiently in advance of the time when the roadblocks or traffic diversions take place at the particular streets. The reason for this is to allow sufficient time for the public and residents to understand the changes to their travel plans. The project will notify the public about the roadblocks and traffic diversion through public notices, ward level meetings and city level meeting with the elected representatives.

7. The PIU will also conduct an awareness campaign to educate the public about the following issues:

(i) traffic control devices in place at the work zones (signs, traffic cones, barriers, etc.); (ii) defensive driving behaviour along the work zones; and (iii) reduced speeds enforced at the work zones and traffic diversions.

8. It may be necessary to conduct the awareness programs/campaigns on road safety during construction.

9. The campaign will cater to all types of target groups i.e. children, adults, and drivers. Therefore, these campaigns will be conducted in schools and community centres. In addition, the project will publish a brochure for public information. These brochures will be widely circulated around the area and will also be available at the PIU, and the contractor's site office. The text of the brochure should be concise to be effective, with a lot of graphics. It will serve the following purpose:

(i) explain why the brochure was prepared, along with a brief description of the project; (ii) advise the public to expect the unexpected; (iii) educate the public about the various traffic control devices and safety measures adopted at the work zones; (iv) educate the public about the safe road user behaviour to emulate at the work zones; (v) tell the public how to stay informed or where to inquire about road safety issues at the work zones (name, telephone, mobile number of the contact person; and (vi) indicate the office hours of relevant offices.

E. Install traffic control devices at the work zones and traffic diversion routes

10. The purpose of installing traffic control devices at the work zones is to delineate these areas to warn, inform, and direct the road users about a hazard ahead, and to protect them as well as the workers. As proper delineation is a key to achieve the above objective, it is important to install good traffic signs at the work zones. The following traffic control devices are used in work zones:

• Signs • Pavement Markings • Channelizing Devices • Arrow Panels • Warning Lights

202

11. Procedures for installing traffic control devices at any work zone vary, depending on road configuration, location of the work, construction activity, duration, traffic speed and volume, and pedestrian traffic. Work will take place along major roads, and the minor internal roads. As such, the traffic volume and road geometry vary. The main roads carry considerable traffic; internal roads in the new city areas are wide but in old city roads very narrow and carry considerable traffic. However, regardless of where the construction takes place, all the work zones should be cordoned off, and traffic shifted away at least with traffic cones, barricades, and temporary signs (temporary “STOP” and “GO”).

12. Figure A2 to Figure A6 illustrates a typical set-up for installing traffic control devices at the work zone of the area, depending on the location of work on the road way, and road geometrics: • Work on shoulder or parking lane • Shoulder or parking lane closed on divided road • Work in Travel lane • Lane closure on road with low volume • Street closure with detour

13. The work zone should take into consideration the space required for a buffer zone between the workers and the traffic (lateral and longitudinal) and the transition space required for delineation, as applicable. For the works, a 30 cm clearance between the traffic and the temporary STOP and GO signs should be provided. In addition, at least 60 cm is necessary to install the temporary traffic signs and cones.

14. Traffic police should regulate traffic away from the work zone and enforce the traffic diversion result from full street closure in certain areas during construction. Flagggers/ personnel should be equipped with reflective jackets at all times and have traffic control batons (preferably the LED type) for regulating the traffic during night time.

16. In addition to the delineation devices, all the construction workers should wear fluorescent safety vests and helmets in order to be visible to the motorists at all times. There should be provision for lighting beacons and illumination for night constructions.

203

Figure A2 & A3: Work on shoulder or parking lane & Shoulder or parking lane closed on divided road

204

Figure A4 & A5: Work in Travel lane & Lane closure on road with low volume

205

Figure A6: Street closure with detour

206

Appendix 207

Appendix 20: Drinking Water Standards

No Substance or Requireme Undesirable effect Permissible Remarks . characteristic nt outside the desirable limit in the Desirable absence of limit alternate Source Essential Characteristic 1. Colour Hazen 5 Above 5, consumer 25 Extended to 25 Units, Max acceptance decreases only if toxic Substance are not suspect in absence of alternate sources 2. Odour Unobjectio - - a) test cold and nable when heated b) test are several dilutions 3. Taste Agreeable - - Test to be conducted only after safely has been established 4. Turbidity (NTU) 5 Above 5, consumer 10 - Max acceptance decreases 5. pH value 6.5 to 8.5 Beyond this range the No - water will after the relaxation mucous membrane and/or water supply system 6. Total 300 Encrustation in water 600 - Hardness supply structure and (mg/L) adverse effects on CaCO3 domestic use 7. Iron (mg/L, Fe) 0.3 Beyond this limit 1.0 - Max taste/appearance are affected; has adverse effects on domestic uses and water supply structure and promotes iron bacteria 8. Chlorides 250 250 Beyond effects 1000 - (mg/L, Cl) Max outside the desirable limit 9. Residual free 0.2 - - To be applicable Chlorine only when water is (mg/L), Max chlorinated. Tested at customer end. When protection against viral

207

Appendix 208

infection is required, it should be min. 0.5 mg/L. Desirable Characteristics 10 Dissolved 500 Beyond this, 2000 - . solids mg/L. palatability decreases Max and may cause gastrointestinal irritation. 11 Calcium (mg/L, 75 Encrustation in water 200 - . Ca) Max. supply structure and adverse effects on domestic use. 12 Magnesium 30 Encrustation in water 100 - . (mg/L, Mg) supply structure and Max adverse effects on domestic use. 13 Copper (mg/L, 0.05 Astringent taste dis 1.5 - . Cu) Max coloration and corrosion of pipes fittings and utensils will be caused beyond this. 14 Manganese 0.1 Beyond this limit 0.3 - . (mg/L, Mn) taste/appearance are Max affected, has advers effect on domestic use and water supply structure 15 Sulphate 200 Beyond this causes 400 May be extended . (mg/L, SO4) gastro intestinal upto 400 provided Max. irritation when magnesium (as magnesium or sodium Mg) does not are present exceed 30 16 Nitrate (mg/L, 45 Beyond this 100 - . NO3) Max. methaemoglobinemia takes place. 17 Fluoride (mg/L, 1.0 Fluoride may be kept 1.5 - . F) Max. as low as possible. High fluoride may cause fluorosis. 18 Phenolic 0.001 Beyond this, it may 0.002 - . Compounds cause objectionable (mg/L taste and odour C6H5OH) Max. 19 Mercury (mg/L 0.001 Beyond this the water No To be tested when . Hg) Max becomes toxic Relaxation. pollution is suspected 20 Cadmium 0.01 Beyond this the water No To be tested when (mg/L, Cd) becomes toxic Relaxation. pollution is

208

Appendix 209

Max suspected 21 Selenium 0.01 Beyond this the water No To be tested when . (mg/L, Se) Max becomes toxic. Relaxation. pollution is suspected 22 Arsenic 0.05 Beyond this the water No To be tested when . (mg/L, As) becomes toxic Relaxation pollution is Max. suspected 23 Cyanide 0.05 Beyond this the water No To be tested when . becomes toxic Relaxation pollution is suspected 24 Lead (mg/L 0.05 Beyond this the water No To be tested when . Pb) Max. becomes toxic Relaxation pollution is suspected 25 Zinc (mg/L, Zn) 5 Beyond this limit it can 15 To be tested when . Max. cause astringent taste pollution is and an opalescence in suspected water 26 Anionic 0.2 Beyond this limit it can 1.0 To be tested when . detergents cause a light froth in pollution is (mg/L, MBAS) water suspected Max 27 Chromium 0.05 May be carcinogenic - - . (mg/L, Cr6+ above this limit 28 Polynuclear - May be carcinogenic - - . Aromatic Hydrocarbons (mg/l, PAH) Max 29 Mineral oil 0.01 Beyond this limit, 0.03 To be tested when . (mg/L) undesirable taste and pollution is odour after suspected chlorination takes place 30 Pesticides Absent Toxic 0.001 - . (mg/L) max Radioactive materials 31 Alpha emitters - - 0.1 - . Bq/L Max 32 Beta emitters - - 1.0 - . Pci/L Max 33 Alkalinity 200 Beyond this limit, taste 600 - . (mg/L,) Max becomes unpleasant 34 Aluminum 0.03 Cumulative effect is 0.2 . (mg/L, Al) Max reported to cause dementia 35 Boron (mg/L) 1.0 - 5.0 - . Max

209

Appendix 210

Appendix 21: SAMPLE ENVIRONMENTAL SITE INSPECTION REPORT

Project Name Contract Number

NAME: ______DATE: ______TITLE: ______DMA: ______LOCATION: ______GROUP: ______

WEATHER: Project Survey Activity Design Stage Implementation Pre-Commissioning Guarantee Period

Monitoring Items Complianc e Compliance marked as Yes / No / Not applicable (NA) / Partially Implemented (PI) EHS supervisor appointed by contractor and available on site Archaeological Supervisor appointed by contractor and available on site Construction site management plan (spoils, safety, schedule, equipment etc.,) prepared Traffic management plan prepared Dust is under control Excavated soil properly placed within minimum space Construction area is confined; no traffic/pedestrian entry observed Surplus soil/debris/waste is disposed without delay Construction material (sand/gravel/aggregate) brought to site as & when required only Tarpaulins used to cover sand & other loose material when transported by vehicles After unloading , wheels & undercarriage of vehicles cleaned prior to leaving the site No AC pipes disturbed/removed during excavation No chance finds encountered during excavation Work is planned in consultation with traffic police Work is not being conducted during heavy traffic Work at a stretch is completed within a day (excavation, pipe laying & backfilling) Pipe trenches are not kept open unduly Road is not completely closed; work is conducted on edge; at least one line is kept open Road is closed; alternative route provided & public informed, information board provided Pedestrian access to houses is not blocked due to pipe laying Spaces left in between trenches for access Wooden planks/metal sheets provided across trench for pedestrian No public/unauthorized entry observed in work site

210

Appendix 211

Children safety measures (barricades, security) in place at works in residential areas Prior public information provided about the work, schedule and disturbances Caution/warning board provided on site Guards with red flag provided during work at busy roads Workers using appropriate PPE (boots, gloves, helmets, ear muffs etc) Workers conducting or near heavy noise work is provided with ear muffs Contractor is following standard & safe construction practices Deep excavation is conducted with land slip/protection measures First aid facilities are available on site and workers informed Drinking water provided at the site Toilet facility provided at the site Separate toilet facility is provided for women workers Workers camps are maintained cleanly Adequate toilet & bath facilities provided Contractor employed local workers as far as possible Workers camp set up with the permission of PIU Adequate housing provided Sufficient water provided for drinking/washing/bath No noisy work is conducted in the nights Local people informed of noisy work No blasting activity conducted Pneumatic drills or other equipment creating vibration is not used near old/risky buildings

Signature ______

Sign off

______Name Name Position Position

211

Appendix 212

Appendix 22: Quarterly Reporting Format for Assistant Safeguards Officer

1. Introduction • Overall project description and objectives • Description of sub-projects • Environmental category of the sub-projects • Details of site personnel and/or consultants responsible for environmental monitoring • Overall project and sub-project progress and status

Status of Sub-Project Progres No Sub-Project Desig Pre- Constructio Operation List of s of . Name n Constructio n al Phase Works Works n            

2. Compliance status with National/ State/ Local statutory environmental requirements No. Sub-Project Name Statutory Environmental Status of Action Requirements Compliance Required

3. Compliance status with environmental loan covenants No. (List schedule Covenant Status of Action Required and paragraph Compliance number of Loan Agreement)

4. Compliance status with the environmental management and monitoring plan • Provide the monitoring results as per the parameters outlined in the EMP. Append supporting documents where applicable, including Environmental Site Inspection Reports. • There should be reporting on the following items which can be incorporated in the checklist of routine Environmental Site Inspection Report followed with a summary in the semi-annual report send to ADB. Visual assessment and review of relevant site documentation during routine site inspection needs to note and record the following: o What are the dust suppression techniques followed for site and if any dust was noted to escape the site boundaries; o If muddy water was escaping site boundaries or muddy tracks were seen on adjacent roads; o adequacy of type of erosion and sediment control measures installed on site, condition of erosion and sediment control measures including if these were intact following heavy rain; o Are their designated areas for concrete works, and refuelling;

212

Appendix 213

o Are their spill kits on site and if there are site procedure for handling emergencies; o Is there any chemical stored on site and what is the storage condition? o Is there any dewatering activities if yes, where is the water being discharged; o How are the stockpiles being managed; o How is solid and liquid waste being handled on site; o Review of the complaint management system; o Checking if there are any activities being under taken out of working hours and how that is being managed.

213

214 Summary Monitoring Table Impacts Mitigation Parameters Method of Location Date of Name of (List Measures Monitored Monitoring of Monitoring Person from (List from (As a Monitoring Conducted Who IEE) IEE) minimum Conducted those the identified in Monitoring the IEE should be monitored) Design Phase

Pre-Construction Phase

Construction Phase

Operational Phase

Overall Compliance with CEMP/ EMP No. Sub- EMP/ CEMP CEMP/ EMP Status of Action Project Part of Being Implementation Proposed and Name Contract Implemented (Excellent/ Additional Documents (Y/N) Satisfactory/ Partially Measures (Y/N) Satisfactory/ Below Required Satisfactory)

5. Approach and methodology for environmental monitoring of the project • Brief description on the approach and methodology used for environmental monitoring of each sub-project

6. Monitoring of environmental impacts on project surroundings (ambient air, water quality and noise levels) • Brief discussion on the basis for monitoring • Indicate type and location of environmental parameters to be monitored • Indicate the method of monitoring and equipment to be used • Provide monitoring results and an analysis of results in relation to baseline data and statutory requirements

As a minimum the results should be presented as per the tables below.

Appendix 215

Air Quality Results Parameters (Government Standards) Site No. Date of Testing Site Location PM10 SO2 NO2 µg/m3 µg/m3 µg/m3

Parameters (Monitoring Results) Site No. Date of Testing Site Location PM10 SO2 NO2 µg/m3 µg/m3 µg/m3

Water Quality Results Parameters (Government Standards) Site Date of Site Location pH Conductivity BOD TSS TN TP No. Sampling µS/cm mg/L mg/L mg/L mg/L

Parameters (Monitoring Results) Site Date of Site Location pH Conductivity BOD TSS TN TP No. Sampling µS/cm mg/L mg/L mg/L mg/L

Noise Quality Results LAeq (dBA) (Government Site No. Date of Testing Site Location Standard) Day Time Night Time

LA (dBA) (Monitoring Results) Site No. Date of Testing Site Location eq Day Time Night Time

7. Summary of key issues and remedial actions • Summary of follow up time-bound actions to be taken within a set timeframe.

8. Appendixes • Photos • Summary of consultations • Copies of environmental clearances and permits • Sample of environmental site inspection report • Other 215

Appendix 216

Appendix 23: Calculation for Water Availability in Rivers at Wier Sites

Calculation for Water availability

Rainfall data of Indore Area – 1930 to 2013

Total Maximum No. of Annual intensity Sr. Max. Annual Rainy Rainfall Probability (P) = Return Period I No. one Day MAX days in a (mm) in m/(N(=84)+1) T=1/P (years) =[ { K Ta } / { D (m) rainfall (mm) year Decreasin + b }n ] (cm / g Order ↓ hr)

1 134.874 69 1901.34 0.011764706 85 8.356301039 2 104.394 88 1590.6 0.023529412 42.5 7.586657807 3 111.252 62 1527.048 0.035294118 28.3333 7.169739462 4 143.764 72 1459.103 0.047058824 21.25 6.887901287 5 113.03 82 1458.214 0.058823529 17 6.676942844 6 86.36 88 1453.896 0.070588235 14.1667 6.509382514 7 101.854 71 1445.4 0.082352941 12.1429 6.370997145 8 108.712 75 1439.164 0.094117647 10.625 6.253502576 9 167.132 80 1405.382 0.105882353 9.44444 6.151664919 10 156.972 64 1369.3394 0.117647059 8.5 6.06197411 11 123.952 88 1331.62 0.129411765 7.72727 5.981965954 12 213.36 59 1320 0.141176471 7.08333 5.909846646 13 166.116 79 1319.23 0.152941176 6.53846 5.844271375 14 116.332 84 1316.736 0.164705882 6.07143 5.784207031 15 178.054 85 1289.4 0.176470588 5.66667 5.728843465 16 133.858 80 1278.128 0.188235294 5.3125 5.677534104 17 250.444 97 1187.2 0.2 5 5.62975503 18 92.202 79 1175.4 0.211764706 4.72222 5.585076036 19 79.248 104 1161.54 0.223529412 4.47368 5.543139717 20 99.06 82 1157.73 0.235294118 4.25 5.50364605 21 224.028 62 1152.398 0.247058824 4.04762 5.46634084 22 119.38 62 1149.096 0.258823529 3.86364 5.431006912 23 70.866 61 1110.742 0.270588235 3.69565 5.39745732 24 73.152 84 1102.36 0.282352941 3.54167 5.365530033

216

Appendix 217

25 124.206 82 1095.3 0.294117647 3.4 5.335083734 26 93.98 80 1092.7 0.305882353 3.26923 5.305994464 27 59.69 91 1085.596 0.317647059 3.14815 5.278152919 28 110.998 68 1073.89 0.329411765 3.03571 5.251462247 29 90.932 90 1066.8 0.341176471 2.93103 5.22583624 30 191.008 94 1062.5 0.352941176 2.83333 5.20119785 31 231.14 78 1059.18 0.364705882 2.74194 5.17747794 32 125.222 98 1054.0365 0.376470588 2.65625 5.154614253 33 195.58 75 1038.79 0.388235294 2.57576 5.132550534 34 81.28 90 1034.7706 0.4 2.5 5.11123579 35 87.63 72 1033.272 0.411764706 2.42857 5.090623662 36 220.726 63 1022.096 0.423529412 2.36111 5.070671881 37 73.914 51 1018.794 0.435294118 2.2973 5.051341809 38 95.25 83 1012.19 0.447058824 2.23684 5.032598037 39 64.77 68 1003.554 0.458823529 2.17949 5.014408039 40 72.644 68 1001.53 0.470588235 2.125 4.996741869 41 102.87 81 987.298 0.482352941 2.07317 4.979571901 42 143.5 76 974.7 0.494117647 2.02381 4.962872593 43 151.3 51 973.8 0.505882353 1.97674 4.94662029 44 189.2 91 969.5 0.517647059 1.93182 4.930793038 45 146.8 64 959.62 0.529411765 1.88889 4.915370433 46 66.5 86 957.8 0.541176471 1.84783 4.900333476 47 90 68 955.04 0.552941176 1.80851 4.885664447 48 153.8 84 951.88 0.564705882 1.77083 4.871346798 49 153.8 81 951.23 0.576470588 1.73469 4.857365051 50 207.9 75 949.93 0.588235294 1.7 4.843704705 51 95.52 78 945.58 0.6 1.66667 4.830352163 52 146.34 78 943.61 0.611764706 1.63462 4.817294654 53 52.57 67 931.418 0.623529412 1.60377 4.804520171 54 96.5 80 922.2 0.635294118 1.57407 4.792017409 55 109.72 50 917.194 0.647058824 1.54545 4.779775714 56 76.94 44 902.716 0.658823529 1.51786 4.767785036 57 118 64 902 0.670588235 1.49123 4.75603588 58 106.17 50 873.51 0.682352941 1.46552 4.744519271 59 106.17 71 872.49 0.694117647 1.44068 4.733226712 60 101.2 61 868.6 0.705882353 1.41667 4.722150158 217

Appendix 218

61 128.5 92 867.918 0.717647059 1.39344 4.711281978 62 96 55 866.902 0.729411765 1.37097 4.700614931 63 63 50 846.8 0.741176471 1.34921 4.690142139 64 97.6 77 837.692 0.752941176 1.32813 4.679857066 65 149 81 818.4642 0.764705882 1.30769 4.66975349 66 128.7 76 795.29 0.776470588 1.28788 4.659825489 67 206.7 69 786.3 0.788235294 1.26866 4.650067421 68 241 75 779.96 0.8 1.25 4.640473905 69 105 77 760.476 0.811764706 1.23188 4.631039806 70 98 71 744.6 0.823529412 1.21429 4.621760222 71 53 49 740.4 0.835294118 1.19718 4.612630469 72 130 50 710.692 0.847058824 1.18056 4.603646067 73 63.8 57 680.974 0.858823529 1.16438 4.594802731 74 98 75 679 0.870588235 1.14865 4.586096359 75 99.4 68 664.3 0.882352941 1.13333 4.577523021 76 181 60 654.07 0.894117647 1.11842 4.569078951 77 84.2 78 646.6 0.905882353 1.1039 4.560760537 78 110.8 59 627.888 0.917647059 1.08974 4.552564312 79 82.4 54 623.824 0.929411765 1.07595 4.544486951 80 108 62 597.8 0.941176471 1.0625 4.536525256 81 109.4 71 555 0.952941176 1.04938 4.528676157 82 222.6 70 554.228 0.964705882 1.03659 4.520936699 83 228.6 81 487.7 0.976470588 1.0241 4.513304043 84 246.7 88 322.05 0.988235294 1.0119 4.505775454

Calculation for total runoff Goutampura and Depalpur weir at Chambal River Sr No Sq 1 Catchment area (A) = 1243 Km Average rain fall 2 (Maximum) (I) = 750 Mm Average rain fall 3 (Minimum)(I) = 450 Mm 4 Run off coefficient = 0.61 Assuming 50% covered and 50% uncovered = 5 Formula = AIR (1234X1000X1000X0.75X0.6 i Maximum rainfall = 1) cum

218

Appendix 219

= 568672500 cum MC = 568.67 M Minimum rainfall = 338733000 cum MC Total Available water = 338.733 M

Calculation for total runoff Betma weir at Gambhir River Sr No Sq 1 Catchment area (A) = 189 Km Average rain fall 2 (Maximum) (I) = 750 Mm Average rain fall 3 (Minimum)(I) = 450 Mm 4 Run off coefficient = 0.61 Assuming 50% covered and 50% uncovered = 5 Formula = AIR (189X1000X1000X0.75X0.61 i Maximum rainfall = ) cum = 86467500 cum MC = 86.4675 M Minimum rainfall = 51880500 cum MC Total Available water = 51.8805 M

219

SOUTH ASIA REGIONAL DEPARTMENT SAFEGUARDS INFORMATION LOG FOR SAUW PROJECTS

Project: IND: Madhya Pradesh Urban Services Improvement Program Loan No.: Package No.: MPUSIP – 2A Water supply system improvement in Depalpur, Gautampura and Betma Towns Components: Depalpur Town: (i) Weir (3 m height and 100 m long) across Chambal River (capacity 1.27 million cubic meter, MCM), and intake (ii) Raw water transmission - 175 m length, 200 mm diameter (iii) Water Treatment Plant (WTP) of 2.40 MLD (iv) 3 overhead tank (OHT, 100 KL each) (v) Clear water transmission – 6,113 m length, 200 mm diameter (vi) Distribution network – 28,672 m length, 110 – 250 mm diameter (vii) Consumer connections: 3,334 numbers

Gautapura Town: (i) Weir (5 m height and 100 m long) across Chambal River (capacity 0.55 MCM), and intake (ii) Raw Water Transmission – 1,002 m length, 200 mm diameter (iii) WTP of 2.10 MLD; (iv) 1 OHT (150 KL) (v) Clear water Transmission –3,308 m length, 150-250 mm diameter (vi) Distribution network – 26,605 m length, 110 – 250 mm diameter (vii) Consumer connections: 2,672 numbers

Betma Town: (i) Weir (6.5 m height and 60 m long) across Gambir River (capacity 0.72 MCM), and intake (ii) Raw water transmission – 14,739 m length, 200 mm diameter (iii) WTP of 2.16 MLD; (iv) Clear water Transmission –4,586 m length, 150-250 mm diameter (v) Distribution network – 35,142 km, 110 – 250 mm diameter (vi) Consumer connections: 3,035 numbers Contract Type: NCB - Date of IEE: Updated August 2018 Draft IEE Updated/Revised IEE Others This package was awarded without - This package is under implementation, approval of the IEE. Draft IEE was and therefore this IEE needs prepared based on preliminary design immediate finalization based on the study in November 2016, but no detailed design. revised IEE submitted addressing ADB comments until July 2018 If design and construction is being taken up component-wise, phase-wise approach to be adopted for final IEE, which should include detailed implementation schedule showing timeline (completion of each component/chainage-wise detailed design and corresponding IEE submission) .

Section Status Comments/Remarks 1. Environmental assessment Yes No MPUSIP Cat B project. IEE is report (EIA/IEE/envi due √ required. Draft IEE was prepared diligence) has been during project preparation. prepared? No river flow data is available, and analysis on water availability and source sustainability is provided based on catchment area and rainfall Section Status Comments/Remarks analysis. No data on river ecology or aquatic life available. Rivers are not perennial and remain completely dry for 5- 7 months in year. Based on local consultations, report indicated that there are no notable sensitive areas, and aquatic life is limited to local common species of fishes.

2. EIA/IEE/envi due diligence Yes No IEE is based on preliminary design. based on project √ Detailed design being carried out by components and detailed the Contractor (DBO Contract) and engineering design? IEE need to be updated with detailed design.

This package is under implementation, and therefore this IEE need immediate Uupdate / finalization based on the detailed design. 3. Statutory Requirements - Forest Clearance Not applicable. No components are located in forest areas. - No Objection Certificate Not applicable. - Site Location Clearance Not applicable. - Environmental Compliance Not applicable, the components are Certificate not listed in the Schedule 1 of the EIA Notification Act and its rules and regulations. √ Permit to Construct (or Consent to establish (CTE) and equivalent) consent to operate (CTO) for WTP from MPPCB √ Permit to Operate (or Consent to establish (CTE) and equivalent) consent to operate (CTO) for WTP from MPPCB √ Permit for weir and intake Water Resources Department (WRD), Government of Madhya Pradesh, permission for water abstraction and construction of intakes - Others – Tree Cutting Permit Exact number of trees to be cut is not determined at this stage

Action Required: Include in the IEE: In the Final IEE, the following information will be included: (i) Exact number of tress to be cut should be reported in the Final IEE (ii) Contractor to obtain Tree Cutting Permit from the Forest Department Contractor allocate budget (amount XXX) for the tree compensation/ replantation 5. Policy, legal, and Adequate Not Adequate administrative framework √ EIA/IEE/envi due diligence included discussion on: √ National regulation/law on EIA Not applicable, the components are not listed in the Schedule 1 of the EIA Notification Act and its rules and Section Status Comments/Remarks regulations. √ Environmental agency National, state, local laws, Action Required: The Final IEE and rules and regulations related to SEMP should provide specific environmental pollution, OHS, information on how the above laws, core labor standards, etc. rules and regulations will be followed by the contractor. - Relevant international Action Required. Include in the final environmental agreements IEE, the relevant international environmental agreements where India is a signatory √ Environmental standards Applicable. though equivalent (IFC’s EHS Guidelines) environmental legislations (national and local) are adopted in this subproject, it is clearly mentioned in the Draft IEE, that the PMU and PIU should adopt stringent measures as specified in the World Bank Group’s Environment, Health and Safety Guidelines.

Action Required: The Final IEE and SEMP should provide specific information on how DBO contractor (i) applies pollution prevention and control technologies and practices consistent with international good practices as reflected in internationally recognized standards such as the World Bank Group’s Environmental, Health and Safety Guidelines and (ii) adopts cleaner production processes and good energy efficiency practices. If less stringent levels or measures are appropriate in view of specific project circumstances, the DBO contractor will provide full and detailed justification for any proposed alternatives that are consistent with the requirements presented in ADB SPS. 6. Anticipated environmental EIA/IEE/envi due Mitigation impacts and mitigation diligence satisfactorily measures measures discussed impacts and provided? risks on: Yes No √ Biodiversity n/a Not applicable. Endangered species conservation and habitats not present in subproject area. √ Pollution √ WTP generates sludge from prevention and sedimentation, chemical flocculation, abatement residuals of excess chemical dosage, plankton etc; and wastewater from rinsing and back washing of filter. IEE includes design measures for proper management of sludge and wastewater. Wastewater will be collected and recirculated, resulting in zero waste discharge, and settled sludge will be dewatered, dried, and disposed by land filling / reused in Section Status Comments/Remarks beneficial purposes. Various pollution prevention measures included in IEE for construction phase to control dust,noise, emissions from construction vehicles, silt-laden surface runoff during rains etc., Action required: The Final IEE and SEMP should show how (i) design provides for pollution prevention from WTP, and (ii) how dust noise, air emissions, and water pollution will be controlled during the construction. √ Health and √ The Draft IEE and EMP includes safety mitigation measures and requirements to be followed by DBO contractor.

Action Required: The Final IEE and SEMP should provide specific information on (i) how DBO contractor will implement occupational health and safety; (ii) DBO contractor to confirm appointment/delegation of Site Health and Safety Officer; and (iii) include DBO contractor’s Healthy and Safety Plan. Physical cultural n/a Not applicable. There are no places resources (PCR) of archeological / historical importance or protected monuments X Cumulative Not applicable. The subproject will impacts not add any incremental impacts to the environment. X Transboundary Not applicable. The subproject is impacts small-scale, site-specific and short in duration to have potential transboundary impacts. √ Construction √ Differently written; it does not reflect impacts what is in the EMP

Action required. In the in final IEE, detailed description of construction impacts, and ensure consistency with EMP tables 7. Impacts from Associated Addressed Not Not Not applicable, there are no Facilities Addressed applicable associated facilities under this √ subproject/package. 8. Analysis of Alternatives Yes No Not required for Cat B and no need to √ include in IEE.

9. EMP budget included Yes No Included in provisional sums of the √ contract

Action Required: The Final IEE and SEMP should provide specific information on actual budget of DBO contractor on SEMP implementation and environmental monitoring. 10. EMP implementation Yes No (i) MPUSIP Phase 1 Project integrated in PAM, and in √ Administration Manual (PAM) Section Status Comments/Remarks bid and contract includes sections on documents environmental safeguards. Information in the PAM has been referred in the preparation of the Draft IEE. (ii) MPUSIP Phase 1 EARF also provides detailed requirements on EMP implementation and necessary formats. These are included in the Draft IEE. (iii) Bid document mentions that IEE and EMP forms part of the bid document.

Action Required: Confirm that IEE and EMP provided to contractor after contract award. This will be confirmed by PMU in the environmental monitoring report to be submitted to ADB on a semi-annual basis. 11. Consultation and Yes No Included in IEE. As per the details Participation √ furnished in the Draft IEE, Stakeholder Consultation/s was held in respective municipal offices and at various locations in the project towns in May 2018..

In all 315 stakeholders participated in the consultations (male =136, female = 179)

During the consultation/s the following queries were raised by the local communities and it was responded by the PIU and Consultants.

• All stakeholders were very supporting of the project, and extended full cooperation during the works • Expressed concern regarding construction nuisance and disturbance; suggested that public notice to be circulated and, construction should be completed in the given time, • For safety of local traffic and pedestrian in built-up zone, barricading / fencing should be provided

Attention of stakeholders drawn to the EMP, and explained to them how the construction issues will be managed by implementing mitigation measures. All necessary measures as per EMP will be taken by contractor to avoid/minimize construction disturbances. Action Required: The PIU and DBO Contractor will continue meaningful Section Status Comments/Remarks consultations and information disclosure during detailed design, construction and O&M stages. DBO Contractor will include records of consultations, issues/concerns, attendance sheets, and resolutions to the progress report to be submitted to PIU. This will be included by PMU in the environmental monitoring report to be submitted to ADB on a semi- annual basis. 12. Grievance Redress Yes No GRM established in MPUSIP 1. Mechanism √ Action Required: PIUs will establish GRM and with the help of DBO Contractor, will disseminate information on GRM during implementation. GRM Notification will be included by PMU in the environmental monitoring report to be submitted to ADB on a semi-annual basis. Description of GRM GRM established in MPUSIP Phase 1 will be followed therefore applicable to this subproject/package. GRM description Included in IEE. Identification of GRC members Included in IEE.

Action Required: GRC composition will be included by PMU in the environmental monitoring report to be submitted to ADB on a semi-annual basis. 13. Disclosure Endorsement to disclose on ADB Pending. This will be requested when website the IEE has been cleared by ADB. Disclosed on project website Pending. This will be requested when the IEE has been cleared by ADB. Relevant information available to Pending. This will be requested when stakeholders and affected people in the IEE has been cleared by ADB. language and form they understand 14. Mobilized PMU Yes No Mobilized Environment Specialist √ 15. Mobilized PIU Environment Yes No An Assistant Project Manager (APM) Specialist √ in PIU is designated for coordinating on safeguards at PIU level 16. Mobilized PMC Yes No Mobilized Environment Specialist at √ PMU level 17 Mobilized PMC √ Not yet appointed. Environment Engineer at PIU level Action Required: PIU level environmental consultant to be mobilized by ??? (date) 17. Confirm bid and contract Yes No The Draft IEE includes EHS documents and/or EMP √ supervisor requirement. Bid include requirement for the specifically does not include EHS contractor to appoint EHS supervisor requirement, but EMP is supervisor and/or nodal part of the bid, which clearly specified person for environmental EHS supervisor requirement. safeguards Section Status Comments/Remarks Action Required: PIU to confirm qualifications of EHS supervisor to implement health and safety requirements in the SEMP. This will be included by PMU in the environmental monitoring report to be submitted to ADB on a semi-annual basis. 18. If contract awarded Yes No EHS supervisor mobilized by the already, confirm √ Contractor contractor’s appointment of EHS supervisor and/or nodal person for environmental safeguards 19. Awareness training on Yes No Conducted by PMU. The DBO compliance to safeguard √ Contractor is provided with requirements Safeguards Induction to discuss applicable environmental safeguards requirements. The environmental safeguards training/ workshop was conducted by the environmental officers of PMU/PIU and their consultants.

Action required. GRC members will be provided with workshops and training so they will be able to address project-related complaints/grievances. This will be included by PMU in the environmental monitoring report to be submitted to ADB on a semi-annual basis. 20. Monitoring and Reporting Yes No √ Sample monitoring checklists are included in the Draft IEE.

Action Required: The Final IEE and SEMP will include more detailed checklists such (i) contractors daily EHS Checklist; (ii) contractors monthly SEMP Implementation Report; and (iii) PIU environmental safeguards compliance report. 21. Others/Remarks This IEE report is under review, not yet approved by ADB

Specific comments for further follow up: - This IEE needs immediate update / finalization based on the detailed design; - - PIU level environmental specialist to be appointed by PMC - - CTE to be obtained prior to start of WTP construction - Permission for water abstraction and intake construction to be obtained from WRD - The draft IEE for Package 2A is recommended for ADB Clearance for inclusion in bid and contract documents. - Cleared draft IEE to be disclosed on project website (PMU and PIU). If project website is not available, the summary of the draft IEE should be posted in public notice boards. - The relevant information in the draft IEE should also be disclosed to stakeholders and affected people in a timely manner in language/form they understand. - Continuous meaningful consultations including information dissemination on project-GRM should be conducted during detailed engineering design, construction and if required, until O&M. Section Status Comments/Remarks - PMU to submit to ADB the final IEE together with DBO contractor’s SEMP/s for review and disclosure. The final IEE should include detailed information on how the abovementioned further actions are conducted/met. - DBO contractor should submit to PMU and PIU the SEMP/s upon completion of the detailed engineering design. NO works should be allowed until the SEMP/s is/are cleared and confirmed to satisfactorily meet the requirements of Government of India laws, rules and regulations and ADB SPS. - Reporting of SEMP/s implementation and environmental safeguards should be: (i) DBO contractor to PIU to be done on the monthly basis; (ii) PIU to PMU to be done every three months; and (iii) PMU to ADB every six months

Prepared by: Achyutha Rao Aleti (Consultant)

Noted and Checked By: t

Documents/References: 1. Draft IEE for Package 2A - Sent by Tina Sisodia to ADB (16 August 2018)