Belene NPP Configuration Presented by Alexey Matveev Varna, May 27-29 2009 1 Belene NPP Project Configuration Management

JSC Atomstroyexport is developing the configuration management to implement Benele construction Project and meet the terms of Terms of Reference. The principal tasks of the configuration management system are:

 NPP structures, and components comply with the established requirements;

 The physical and functional performances of the plant are accurately described in NPP documentation. Definitions

ISO 10007 “The Guidelines for Configuration Management”

Configuration Management: technical and organizational activities incorporating:

−identification of configuration;

−configuration control;

−submittal of reports on configuration status;

−verification of configuration of united information space. Definitions

Project Management Book of Knowledge (PMBok)

Configuration Management is a set of formal procedures applied to exercise the technical and administrative management aimed at proper review and registration of the requested changes in the Project content, before they are processed within the overall process. Belene NPP Project Configuration Management

Configuration management comprises:

 change identification;  change assessment;  change coordination;  change approval or rejection;  Change introduction. One of the main tasks while implementing the above processes is the analysis of the effect of one change upon all the related elements. Contractor’s Configuration Management Plan Work

The Contractor develops Belene NPP Configuration Plan to define the work organization and describe the system.

Requirements of CM Plan will be mandatory for meeting by all the Contractor’s Subcontractors.

To ensure compatibility of the system with CM system of the Employer this document is developed based upon the “Belene NPP Configuration Management Procedure” BNPP02003, which has been agreed upon with the Employer. Elements of Configuration Management Configuration Identification

Belene NPP construction Project configuration elements are:

 NPP design documentation (as NPP itself);

 EPC /Agreement dated 29.11.2006.

All the physical and functional performances required to define a configuration element within its whole lifecycle shall be documented. Contractor’s Configuration Management Plan Basic Provisions During Belene NPP Project implementation the following configuration management elements are singled out to be combined into a system:

 Identification system;  Project Cost;  Design documents (including  Equipment; commissioning and operation documents);  Project Schedule;  Asbuilt documents (buildings  Project data base. and structures);  EPC Contract;  with Subcontractors; Contractor’s Configuration Management Plan

Configuration Management Elements

Schedule

Equipment Unit Case

Coding Cost DatabaseМонтаж WD Com.Doc. Contract Oper.Doc ТР Subcontracts Contractor’s Configuration Management Plan

Element: “Identification System”

Б ВО 466 .02.01.01. Dates of equipment and documents submittal Contractor’s Configuration Management Plan

Element: “Identification System” The main tasks of the Identification System are:

 Unambiguous identification of the subject of control;  Assurance of links between the configuration management elements. The Manual (PMM) procedures are used to set forth the coding rules (for equipment, documents, correspondence etc.), among them:

BNPP01018 “Document Identification System”; BNPP07002 “Identification and Numbering of the Equipment”; BNPP07005 “Application of KKS coding system for “Belene NPP” Project” etc. Contractor’s Configuration Management Plan

Element: “Design Documents”

The main task of the said documents is the description of the subject of configuration (Belene NPP), comprising:

Design drawings and specifications; Equipment specifications; Work implementation designs; Technical solutions; Commissioning documents; Operation documents etc. Contractor’s Configuration Management Plan “Buildings and Structures. Unit Case” The basic element “Buildings and Structures. Unit Case” incorporates the following subjects of management: Buildings, rooms; Civil structures (documents (drawings) “asbuilt”); Work takeover certificates; Concealed work takeover certificates; Inspection finding report; Element and system test reports; Welded joint control reports etc.

Asbuilt documents for civil and erection and commissioning activities combined into a united system make up the Unit Case . Contractor’s Configuration Management Plan

Element: “Project Time Schedule”

Project time schedules are the basic CM element to control the dates.

Multilevel hierarchical system of time schedules is adopted in the Project. Contractor’s Configuration Management Plan

Element: “Project Time Schedule”

Primavera Project Management v.6.0 is selected to be the software for network time scheduling in the Project.

The effects of Configuration System elements upon Project implementation dates are analyzed using Summary Integrated Overall Time Schedule of the Project and Detail Time Schedules of implementation of individual types of activities. Contractor’s Configuration Management Plan

Element: “Equipment” The basic element of CM “Equipment” incorporates the following subjects of management: Composition of process systems; Equipment, items and materials – aggregates; Aggregate part; Shop drawings (manufacturer’s drawings); Equipment design documents; Shipment documents. Contractor’s Configuration Management Plan

Element: “EPC Contract, Subcontracts”

Basic element of the CM “Contract, subcontracts” incorporates the following management subjects: Contractor’s Bid; Agreement between the Contractor and the Employer dated November 29, 2006; Text of the EPC Contract, including Appendices and Addenda thereto; Texts of Subcontracts for implementation of individual types of activities; Contractor’s Configuration Management Plan

Element: “Cost” Basic component of the CM “Cost” incorporates the following subjects of management: The Bid price; The price of Agreement between the Contractor and the Employer of November 29, 2006; Overall Contract price; Price of individual Articles of EPC Contract; Price of Addenda to the Contract; Price of Subcontracts for implementation of individual types of activities. Contractor’s Configuration Management Plan

“Project Database”|

EPC Contract, WD, Commissioning Documents Addenda, Operating Documents Subcontracts Nonconformity reports Equipment design documents

Project Database Other documents Procurement specificaitons

Design changes

Database of NPP Project used in configuration management includes about 40 local databases and is designed to arrange full internal . Contractor’s Configuration Management Plan

An Example of Change Introduction

Change Release of Change Introduction of introduction into Affects Introduction of Notification change into the Working Technical Design? changes into TD (new type of valve) initial technical data Documents

Release of WD Is the valve Delivered? revision ordered? Keeping inventory of Analysis of effect upon Analysis of effect upon reserve at the warehouse dates and cost. Order. dates and cost. Modification of Modification of Making supply Addendum to EPC supply subcontract subcontract Contract

Development of Manufacture and supply Design Inputs/ Specs Manufacture and supply Signing Addendum to HANDOVER FOR EPC Contract INSTALLATION