Volume 1722 Price Rs. 30/- Date 27/07/2021
Sealed tenders in duplicate superscribing the name of the work on the envelop are invited from the reputed and resourceful contractor for the following jobs.
Tender papers etc. will be available free of cost in KMC website (www.kmcgov.in)
The Tenderers have to enclose current GST/PAN/CE/ credential certificate in similar kinds of jobs as per tender documents available in KMC website and necessary Earnest Money in Bank Draft / Pay Order drawn in favour of The Kolkata Municipal Corporation along with the tender paper at least 1 (one) working day before the date of opening, failing which the tenders will be liable for rejection.
If the last date of receipt of tender or the day of opening of tender happens to be a holiday or otherwise, the next working day will be the last date of receiving or opening. The tenderer may remain present at the time of opening of tenders at respective offices.
Additional S. D. money, if any, must be deposited within a week from the date of intimation of acceptance of the tender.
Agreement for work value exceeding Rs. 50,000/- will have to be executed by the selected tenderer.
The Corporation reserves the right to accept/reject in full or in part of any tender without assigning any reason whatsoever.
1 DETAILS OF P.I/NOTICE INVITING TENDER/QUOTATION 1. (i) Name of The Department :- LIGHTING, BR. I, CMO (ii) Tender invited and to be received by :- EXECUTIVE ENGINEER/LIGHTING/BOROUGH-1
(iii) Time & last date of receipt/opening of tender :- 06.08.2021 ON 01:30 PM / 06.08.2021 ON 02:00 PM (iv) S.D. money, if any :- 2% of the total value of the accepted tender.
1 Sl. Name Of The Work Estimated Amount Earnest Money Time Of Price Of Tender No. Rs. Rs. Completion Rs. 1 REPAIRING AND LIFTING OF RS 1,69,337.41 RS 3,500.00 25 Days 0 Each FEEDER PILLAR BOXES AT 48 B.T. ROAD, 48V B.T. ROAD,KALICHARAN GHOSH ROAD AND OTHER PLACES IN WARD NO-2 UNDER BOROUGH- 1
2 DETAILS OF P.I/NOTICE INVITING TENDER/QUOTATION 1. (i) Name of The Department :- LIGHTING, BR. VI, CMO (ii) Tender invited and to be received by :- EE(E) Lighting Zone:II
(iii) Time & last date of receipt/opening of tender :- 09.08.2021 ON 12:00 PM / 09.08.2021 ON 02:00 PM (iv) S.D. money, if any :- % of the total value of the accepted tender.
Sl. Name Of The Work Estimated Amount Earnest Money Time Of Price Of Tender No. Rs. Rs. Completion Rs. 1 REPAIRING OF PARK LIGHTING 194673.86 4000 10 Days --- Each SYSTEM AT RSM SQURE PARK AND VIVEKANANDA UDDAN AND OTHER VARIOUS PARKS IN WARD NO: 51 2 SUPPLY AND DELIVARY OF LED 198181.72 4000 10 Days --- Each FITTINGS FOR THE HIGH MAST AT LENIN PARK IN WARD NO: 46
3 DETAILS OF P.I/NOTICE INVITING TENDER/QUOTATION 1. (i) Name of The Department :- LIGHTING, BR. VI, CMO (ii) Tender invited and to be received by :- EE(E) Lighting Zone:II
(iii) Time & last date of receipt/opening of tender :- 06.08.2021 ON 12:00 PM / 06.08.2021 ON 02:00 PM (iv) S.D. money, if any :- % of the total value of the accepted tender.
Sl. Name Of The Work Estimated Amount Earnest Money Time Of Price Of Tender No. Rs. Rs. Completion Rs. 1 RENOVATION OF STREET LIGHTING 495869.44 10000 10 Days --- Each SYSTEM AT CHARLIE CHAPLIN SQUARE IN WARD NO: 46
4 DETAILS OF P.I/NOTICE INVITING TENDER/QUOTATION 1. (i) Name of The Department :- LIGHTING, BR. IV, CMO (ii) Tender invited and to be received by :- EX. ENGR.(ELEC)/LTG/Z-II/BR-IV
(iii) Time & last date of receipt/opening of tender :- 04.08.2021 ON 12:00 PM / 04.08.2021 ON 02:00 PM (iv) S.D. money, if any :- % of the total value of the accepted tender.
2 Sl. Name Of The Work Estimated Amount Earnest Money Time Of Price Of Tender No. Rs. Rs. Completion Rs. 1 REPAIR AND RENOVATION OF 98680.84 2000.00 15 Days --- Each ELECTRICAL DISTRIBUTION SYSTEM WITH NECESSARY ELECTRICAL WIRING AT KMCP SCHOOL ,59, RAJA RAM MOHAN SARANI WD-38, UNDER BR-IV.
5 DETAILS OF P.I/NOTICE INVITING TENDER/QUOTATION 1. (i) Name of The Department :- WATER SUPPLY, BR. X, CMO (ii) Tender invited and to be received by :- EX. ENGR. W/S(SOUTH)
(iii) Time & last date of receipt/opening of tender :- 03.08.2021 ON 11:00 AM / 03.08.2021 ON 11:30 AM (iv) S.D. money, if any :- 2% of the total value of the accepted tender.
Sl. Name Of The Work Estimated Amount Earnest Money Time Of Price Of Tender No. Rs. Rs. Completion Rs. 1 REPAIR & MAINTENANCE OF 98210.43 2000 60 Days 0 Each WATER SUPPLY SYSTEM BY CUT & FLUSH METHOD & ITS ALLIED WORK NEAR PREM NO. 39A P.G.M SHAH ROAD ( C.M.D.A COMPLEX ) , KATJUNAGAR D -BLOCK ETC IN WARD NO.93,BR.X.
6 DETAILS OF P.I/NOTICE INVITING TENDER/QUOTATION 1. (i) Name of The Department :- ELECTRICITY, , HQ (ii) Tender invited and to be received by :- Executive Engineer(E)/Electricity-II
(iii) Time & last date of receipt/opening of tender :- 05.08.2021 ON 02:00 PM / 05.08.2021 ON 02:30 PM (iv) S.D. money, if any :- % of the total value of the accepted tender.
Sl. Name Of The Work Estimated Amount Earnest Money Time Of Price Of Tender No. Rs. Rs. Completion Rs. 1 Wiring of lift shaft & lift machine room at 181240.46 3700 15 Days --- Kankurgachi VIP market & PD lift under KMC
7 DETAILS OF P.I/NOTICE INVITING TENDER/QUOTATION 1. (i) Name of The Department :- PARKS AND SQUARES, BR. IX, CMO (ii) Tender invited and to be received by :- OSD & Ex-Officio DY.C.E(C)/P&S
(iii) Time & last date of receipt/opening of tender :- 03.08.2021 ON 12:00 PM / 03.08.2021 ON 12:30 PM (iv) S.D. money, if any :- 2% of the total value of the accepted tender.
3 Sl. Name Of The Work Estimated Amount Earnest Money Time Of Price Of Tender No. Rs. Rs. Completion Rs. 1 REPAIRING OF FOUNTAIN AT SOLO Quotation Invited 2 percent of the 30 Days --- Each ANA BURIAL GROUND 70/1A total quoted EKBALPORE ROAD, IN WARD NO.- amount 78, BR-IX.
8 DETAILS OF P.I/NOTICE INVITING TENDER/QUOTATION 1. (i) Name of The Department :- WATER SUPPLY, BR. VII, CMO (ii) Tender invited and to be received by :- EXECUTIVE ENGINEER (CENTRAL) W. S. AT CMO BUILDIN
(iii) Time & last date of receipt/opening of tender :- 05.08.2021 ON 11:30 AM / 05.08.2021 ON 12:00 PM (iv) S.D. money, if any :- 2% of the total value of the accepted tender.
Sl. Name Of The Work Estimated Amount Earnest Money Time Of Price Of Tender No. Rs. Rs. Completion Rs. 1 REPLACEMENT OF 150 MM DIA 3,38,394.32 7,000.00 25 Days --- Each MAIN FROM 6B, TILJALA SHIBTALA LANE TO 57A/1, TILJALA MASJID BARI LANE IN WARD-65.
9 DETAILS OF P.I/NOTICE INVITING TENDER/QUOTATION 1. (i) Name of The Department :- LIGHTING, BR. V, CMO (ii) Tender invited and to be received by :- EX. ENGR.(LTG.)/Z-II
(iii) Time & last date of receipt/opening of tender :- 04.08.2021 ON 12:00 PM / 04.08.2021 ON 02:00 PM (iv) S.D. money, if any :- 2% of the total value of the accepted tender.
Sl. Name Of The Work Estimated Amount Earnest Money Time Of Price Of Tender No. Rs. Rs. Completion Rs. 1 Repairing & maintenance of street 97416.12 2000.00 30 Days 0 Each lighting system at Mahendra Sarkar street & other sites in ward no-50
10 DETAILS OF P.I/NOTICE INVITING TENDER/QUOTATION 1. (i) Name of The Department :- WATER SUPPLY, , CMO (ii) Tender invited and to be received by :- EXECUTIVE ENGINEER(O&M-III) ,GRWW
(iii) Time & last date of receipt/opening of tender :- 10.08.2021 ON 01:00 PM / 10.08.2021 ON 02:00 PM (iv) S.D. money, if any :- 2% of the total value of the accepted tender.
Sl. Name Of The Work Estimated Amount Earnest Money Time Of Price Of Tender No. Rs. Rs. Completion Rs. 1 MODIFICATION AND DEVELOPMENT 2,81,995.00 5,700.00 21 Days --- Each OF SUPPORTING FRAME STRUCTURE ARRANGEMENT WITH ALLIED WORKS FOR COAGULATION TANK NO-7 UNDER TP-I, GRWW.
4 Sl. Name Of The Work Estimated Amount Earnest Money Time Of Price Of Tender No. Rs. Rs. Completion Rs. 2 REPAIRING AND ROOF TREATMENT 2,97,249.00 6,000.00 21 Days --- Each OF ALUM GODOWN WITH OTHER ALLIED WORKS AT WTP-I UNDER GRWW. 3 REPAIRING AND DESILTING OF 98,641.00 2,000.00 10 Days --- Each ORIFICE CHANNEL AND CONNECTING LAUNDER CHANNEL OF CLARIFLOCCULATOR NO-3 WITH ALLIED WORKS AT WTP-I UNDER GRWW. 4 LEVELLING, DRESSING AND 2,29,540.00 4,600.00 21 Days --- Each REPAIRING OF IP CONSTRUCTION SURROUNDING OF CLARIFLOCCULATOR NO-3 AND 4 WITH ANCILLARY WORKS UNDER TP-I, GRWW. 5 REPAIRING AND RENOVATION OF 4,56,036.00 9,200.00 21 Days --- Each ROOF ABOVE FILTER BED NO 14 AND 16 WITH ALLIED WORKS AT TP-I, GRWW. 6 REPAIRING AND DESILTING OF 97,659.00 2,000.00 10 Days --- Each ORIFICE CHANNEL AND CONNECTING LAUNDER CHANNEL OF CLARIFLOCCULATOR NO-4 WITH ALLIED WORKS AT WTP-I UNDER GRWW. 7 REPAIRING, SERVICING, 2,99,478.00 6,000.00 14 Days --- Each OVERHAULING, TESTING AND COMMISSIONING OF AIR COMPRESSOR NO.-2 AT SLUDGE PUMP HOUSE WITH ALLIED WORKS UNDER WTP-I, GRWW. 8 CHEMICAL TREATMENT OF INSIDE 4,99,251.00 10,000.00 21 Days --- Each WALLS OF THE SEMI UNDERGROUND RESERVOIR FOR LIQUID PAC WITH ALLIED WORKS AT TP-I, GRWW.
11 DETAILS OF P.I/NOTICE INVITING TENDER/QUOTATION 1. (i) Name of The Department :- PARKS AND SQUARES, , CMO (ii) Tender invited and to be received by :- Dy.C.E.(C)
(iii) Time & last date of receipt/opening of tender :- 04.08.2021 ON 12:00 PM / 04.08.2021 ON 12:30 PM (iv) S.D. money, if any :- 2% of the total value of the accepted tender.
5 Sl. Name Of The Work Estimated Amount Earnest Money Time Of Price Of Tender No. Rs. Rs. Completion Rs. 1 REPAIRING AND RENOVATION OF 435801.22 9000 45 Days --- Each SITTING ARRENGEMENTS AND ALLIED WORKS AT CITIZENS PARK (MOHOR KUNJA) IN WARD NO. 63 BOROUGH - VII.
12 DETAILS OF P.I/NOTICE INVITING TENDER/QUOTATION 1. (i) Name of The Department :- LIGHTING, BR. IX, CMO (ii) Tender invited and to be received by :- EX.ENGR(E)/LTG/Z-III
(iii) Time & last date of receipt/opening of tender :- 07.08.2021 ON 12:30 PM / 07.08.2021 ON 02:00 PM (iv) S.D. money, if any :- 2% of the total value of the accepted tender.
Sl. Name Of The Work Estimated Amount Earnest Money Time Of Price Of Tender No. Rs. Rs. Completion Rs. 1 TEMPORARY LIGHTING 180048.00 3800.00 3 Days --- Each ARRANGEMENT FOR MUHARRAM FESTIVAL AT EKBALPUR ROAD,IBRAHIM ROAD,MAYURBHANJ ROAD & OTHER PLACES IN WARD NO-78 2 TEMPORARY LIGHTING 148830.00 3000.00 3 Days --- Each ARRANGEMENT FOR MUHARRAM FESTIVAL AT DENT MISSION ROAD,M.M.ALI ROAD,DR. SUDHIR BOSE ROAD & OTHER PLACES IN WARD NO-77 3 TEMPORARY LIGHTING 137940.00 2800.00 3 Days --- Each ARRANGEMENT FOR MUHARRAM FESTIVAL AT DIFFERENT PLACES OF DIAMOND HARBOUR ROAD UNDER BR-IX 4 TEMPORARY LIGHTING 413820.00 8500.00 3 Days --- Each ARRANGEMENT FOR MUHARRAM FESTIVAL AT SURROUNDING AREAS OF KARBALA PARK,WATTGAUNGE STREET,GARDEN REACH ROAD,MUNSIGAUNGE ROAD,KARL MARX SARANI,CANAL ROAD,ACHAMBIT SHAH ROAD & IN HASTINGS AREAS ETC. IN WARD NO-75 5 TEMPORARY LIGHTING 174240.00 3500.00 3 Days --- Each ARRANGEMENT FOR MUHARRAM FESTIVAL AT DIFFERENT PLACES OF KARL MARX SARANI(C.G.R ROAD) UNDER BR-IX
6 Sl. Name Of The Work Estimated Amount Earnest Money Time Of Price Of Tender No. Rs. Rs. Completion Rs. 6 TEMPORARY LIGHTING 94380.00 2000.00 3 Days --- Each ARRANGEMENT FOR MUHARRAM FESTIVAL AT RAMANATH PAUL ROAD,SATYA DOCTOR ROAD & OTHER PLACES IN WARD NO-76
13 DETAILS OF P.I/NOTICE INVITING TENDER/QUOTATION 1. (i) Name of The Department :- WATER SUPPLY, , CMO (ii) Tender invited and to be received by :- EE/E/M/PH-I/GRWW
(iii) Time & last date of receipt/opening of tender :- 05.08.2021 ON 12:00 PM / 05.08.2021 ON 01:00 PM (iv) S.D. money, if any :- 2% of the total value of the accepted tender.
Sl. Name Of The Work Estimated Amount Earnest Money Time Of Price Of Tender No. Rs. Rs. Completion Rs. 1 REPAIRING & OVERHAULING OF 2,98,367.00 6,000.00 12 Days --- Each MAIN L.T DISTRIBUTION PANEL BOARD AT WTP-II INCLUDING REPLACEMENT OF NECESSARY SPARE PARTS WITH OTHER ELECTRICAL WORKS AT OFFICE BUILDING WITHIN GRWW CAMPUS.
2 DRESSING, LEVELLING & EARTH 2,90,718.00 5,900.00 15 Days --- Each FILLING ALONG THE EDGE OF 18 MGD UGR AFTER CUTTING AND CLEANING THE JUNGLE FROM JUSCO CORNER TO CENTRAL STORE FOR THE BETTERMENT OF THE PLANT WITHIN GRWW CAMPUS.
3 POWER SUPPLY ARRANGEMENT 2,92,634.00 5,900.00 5 Days --- Each BY SILENT DG SET FOR DEWATERING PURPOSE FROM THE BACKWASH CHANNEL FOR REPLACEMENT OF 700MM & 600MM BFV VALVE OF FILTER BED NO A-8 INCL. PROVISION OF SUFFICIENT LIGHTING ARRANGEMENT ALSO IN AT WTP-IV OF GRWW.
7 Sl. Name Of The Work Estimated Amount Earnest Money Time Of Price Of Tender No. Rs. Rs. Completion Rs. 4 REPLACEMENT OF EXISTING 2,78,287.00 5,600.00 7 Days --- Each DAMAGED 600 MM DIA. BFV VALVE BY NEW ONE IN THE OUTLET VALVE FOR FILTER BED OF A7 INCLUDING LIFTING & LOWERING ARRANGEMENT BY CHAIN PULLEY BLOCK AND CHANGE OF BOLTS & NUTS AT WTP IV IN GRWW. WITH OTHER ALLIED WORKS.
5 CONSTRUCTION OF IP OF 2,78,269.00 5,600.00 15 Days --- Each SURFACE AREA FROM VALVE MNTNC ROOM TO SAJNETALA INTERCONNECTION VALVE CHAMBER AFTER CLEANING & DRESSING OF THE AREA WITHIN CLEAR WATER CAMPUS OF GRWW.
6 CONSTRUCTION OF RCC SLAB 90,400.00 1,900.00 10 Days --- Each OVER THE SURFACE DRAIN NEAR SAJNETALA INTERCONNECTION VALVE CHAMBERS TO AVOID ANY ACCIDENT AND SAFE MOVEMENT OF O & M STAFFS FOR OPERATION OF VALVES ON ROUND THE CLOCK BASIS WITHIN GRWW CAMPUS.
7 REPAIRING & RENOVATION OF 2,82,838.00 5,700.00 10 Days --- Each EXISTING DAMAGED SURFACE DRAIN DUE TO LAYING OF 900 MM DIA MS PIPE FOR 10 MGD PUMP HOUSE FROM ZERO GATE TO L&T OLD TIME OFFICE INCLUDING OTHER ALLIED WORKS WITHIN CLEAR WATER CAMPUS OF GRWW.
8 REPLACEMENT OF DAMAGED 2,33,522.00 4,700.00 12 Days --- Each CHEQUERED PLATES OVER THE CABLE TRENCHES BY NEW ONE INCLUDING REPAIRING THE EXISTING MS FRAME TO AVOID ANY SERIOUS ACCIDENT AGAINST MOVEMENT OF STAFFS WITHIN PUMP HOUSE FLOOR AT CWPS PH- I OF GRWW.
8 Sl. Name Of The Work Estimated Amount Earnest Money Time Of Price Of Tender No. Rs. Rs. Completion Rs. 9 RAISING THE SUMP LEVEL BY 2,22,201.00 4,500.00 15 Days --- Each PROVIDING BRICK SOLING & CONCRETE ON THE BACK SIDE OF LLPS TO AVOID STAGNANT WATER ON THE SUMP AFTER CLEANING, DRESSING & LEVELLING THE ENTIRE SUMP AREA WITHIN GRWW COMPLEX.
10 REPAIRING & PAINTING THE WHEEL 2,19,050.00 4,400.00 10 Days --- Each GUARD & EDGING OF ROAD (BOTH SIDES) FROM ZERO GATE NO-1 TO ZERO GATE NO-2 INCLUDING PAINTING THE SAME & WEIGHT BRIDGE & SECURITY ROOM NEAR ZERO GATE NO 2 WITHIN GRWW CAMPUS.
11 CONSTRUCTION OF MS PLATFORM 1,09,394.00 2,200.00 07 Days --- Each FOR 450MM DIA S/V & 300 MM DIA S/V ON BOTH SIDES TO OPERATE THESE VALVES SMOOTHLY DURING CHECKING &