LIST OF EXECUTED WORKS: ROADS & MOTORWAYS INTEGRAL INŽENJERING PLC

Contracted Value of commence- Ordinal Internal Value of Contractor (C) Project name and location Contract in ment and Name and address of the Employer Type and description of the works No. No. Contract in KM Subcontractor (S) EUR completion date

Heavy maintenance (upgrading) of the state The project included upgrading (rehabilitation) of complete section of state road IA3 (motorway) in total JP Putevi Srbije, road IA3, section: Border CRO/SER length of 21.65 km. Bulevar kralja Aleksandra 282 (Batrovci) – Kuzmin 1, from km 0+554.86 to Works included preliminary works, works on road base and superstructure, rehabilitation works on bridges, 15.08.2018.- 11050 Beograd 136 277 km 22+196.11 (left carriageway) and from km 38727850,31 19801235,44 works on improvement of drainage system, works on road belt and traffic signalization, and public lightning. C 31.05.2020. tel: +381 11 30 37 433 0+564.64 to km 22+229.16 (right Works on section with the biggest traffic load in Republic of as successfully completed under the gordana.suboticki-djordjevic@putevi- carriageway), Contract No. RRSP/RRW- traffic, i.e. without total stoppage. srbije.rs IA3BK/2017-07

Koridori Srbije, d.o.o. (Serbia Corridors) Construction of highway section in total length l= 6,75 km, with all structures, Construction of 7 bridges on Corridor X Highway Project, Construction of Beograd, highway section, one bridge on local road, one railway bridge, 3 RC grille structures with prestressed Highway E 75, Section: CaričinaDolina – September 2013 JV Integral-Inter- Kralja Petra 21 11000 Beograd anchors for permanent protection of slopes, 28 culverts, relocation of 1 km of railway, relocation of 1,3 km of 135 273 Vladičin Han, LOT 5: Road and bridges at 224.407.629,56 114.737.799,07 - kop-Prijedorputevi phone 11 33 44 174 local roads, works on regulation of Južna Morava river, Sokolica river and Koznička river. sub-section CaričinaDolina – Tunnel Manajle, June 2018 (60-20-20) fax: +381 11 32 48 682 project involve relocation of HV, MV and LV lines, construction of TC chanellization, PS, drainage works, ICB br. CORRX.E75.EIB.PACK2-LOT5.ICB supply and installation of traffic signalization and equipment, noise protection walls and landscaping.

Construction of the Main Road M-17.3 Neum –Stolac LOT 1 JP Ceste Federacije BiH d.o.o. Sarajevo Pavement of road section Stari Neum – Babin Terazije 54 01.02.2018. - Project included construction of main road in total lenght of 7,00 km. Works includes construction of tunnel 134 272 Do L=5,3km 6.027.207,03 3.081.662,02 tel: +387 33 250 370 C 24/04/2019 Oštrovac, in total lenght of 190 m1 and construction of underpass Oskrusnica. Construction of road section Babin Do – Oštrovac L=1,7km and Construction of the tunnel Oštrovac L=190m1.

Works on design and construction of full profile motorways section (l=35,300.00 m) with all belonging elements, two motorway intersections with toll plazas, traffic control and maintenance centre, rest and service area, structures at the motorway, of which the most important are viaducts with length l=449 m, and l=400 m, bridge with length l=340.00 m, and artificial tunnel. Project includes construction of total of 21,529.24 m local roads, geomechanical works, relocation of power Design and construction of Luka - installation, power supply installations of the toll plazas, rest and service area and artificial tunnel, works on Public Company Doboj Motorway, Section Banja Luka - 01 Sept 2014 - illumination of interchanges, works on setting up traffic signalization and equipment, and noise protection. JV Integral-Granit 133 268 445.558.204,83 227.810.292,73 "Republic of Srpska Motorways" Prnjavor (km 0+000 to km 35+300) Contract 30 Sept 2018 Project includes design and implementation of intelligent traffic systems, video surveillance and traffic (60-40) +387 51 233 670 no. RS/EIB-2012/W management; works on dewatering of pavement, regulation of watercourses, installations of optical cables and emergency call system, and toll collection system. Pavement structure: driving and overtaking lane: SMA 4cm, binding bituminous course 6 cm, bituminous road base BNS 7 cm, cement stabilisation 20 cm, road base 25 cm stopping lane: asphalt concrete 7 cm, bituminous bearing course BNS 7 cm, road base 52 cm

1272 calendar Design and construction of motorway section in total length l=36.609.72 m, with all structures, two days after motorway intersections with toll plazas, traffic control and maintenance centre, rest and service area, Commencement structures at the motorway, of which the most important are the Bosna bridge L=425.40 m, Ukrina bridge Date L=103.06 m, Slatinci artificial tunnel l=80.50m. 09 November Project includes construction of total of 21.422,48 m local roads, geomechanical works, relocation of power 2012 -10 Design and construction of Banja Luka - installation, power supply installations of the toll plazas, rest and service area and artificial tunnel, works on September 2016 Public Company Doboj Motorway, Section Prnjavor - Doboj illumination of interchanges, works on setting up traffic signalization and equipment. JV Integral-Granit 132 265 452.807.085,58 231.516.586,61 (Taking-over) "Republic of Srpska Motorways" (km 35+300 to km 71+909.72) Contract no. Project shall include design and implementation of intelligent traffic systems, video surveillance and traffic (60-40) DNP in duration +387 51 233 670 RS/EBRD-2012/W of 24 August 2012 management; works on dewatering of pavement, installations of optical cables and emergency call system, of 730 days and noise protection. starts as from 11 Pavement structure: September driving and overtaking lane: SMA 4cm, binding bituminous course 6 cm, bituminous road base BNS 7 cm, 2016, ends on cement stabilisation 20 cm, road base 25 cm; 10 September stopping lane: asphalt-concrete 7 cm, bituminous bearing course BNS 7 cm, road base 52 cm 2018

Project included construction of main road in total length of 8.9 km. Two tunnels constructed were: tunnel Čemerno and tunnel Surdup, in total length of l=2.305.00m. Tunnel Čemerno is 2,109.00 m long, and tunnel Surdup is 196.00m long. Both tunnels were constructed by applying the New Austrian construction method (NATM), including all electrical and mechanical installation. Clearance of each tunnel is 55sq.m, and excavation profile of both tunnels is 97.54sq.m each. Tunnel works included underground and open cut excavations. Rocky mass was secured by installation of SN anchors and reinforcing mesh at tunnel portals, and installation of SN and IBO Public Company Permanent solution for the landslide Čemerno September 2008 anchors, steel reinforcing mesh and centerings in the other parts of the tunnel. Following installation of JV Integral, CPM 131 260 71.846.761,91 36.734.666,05 "Republic of Srpska Roads" at the trunk road M-20 Gacko-Foča - 06 August 2013 anchors, mesh and centerings, the tunnel surface was protected by sprayed concrete MB 30, waterproofing BH, REWEUS +387 51 334 500 coat, and construction of the secondary tunnel lining. The project further included the structures: viaduct ''Trnova Luka'', length: L=408.00 (steel composite structure with columns of over 50m high), one viaduct length l=88.00m, the "Hrštica" Bridge l=37.36m and the bridge over the Ždralov potok l=12m. In order to secure stability of the road structure, total of 1,605.00m of reinforced-concrete walls were constructed. In addition, slope stabilisation in this geologically very complex terrain was obtained by installation of steel anchors and applying up-to-date geotehnical methods.

Construction of an intersection at the trunk road M4 Tuzla - Šićki Brod. The work encompasses construction Federation of B&H of 5 bridges (l1=9,80m/P1= 88 m2; l2=13,80m/P2=136,6 m2; l3=18,40m/P3=184m2; l4=42,50m/P4=415 m2; March 2010 - 31- JV Integral, CPM 130 254 Construction of intesection Šićki Brod (Lot 2) 6.466.914,00 3.306.480,62 Road Directorate of FB&H l5=26,50m/P5=258 m2), reconstruction of 4 bridges (P=185,4+187,41+184,00+388m2), alignment works Dec-2011 BH, REWEUS Tel. +387 33 563 468 (reconstruction of existing and construction of a new pavement) works on intersection branches, drainage, lighting, traffic signalization and equipment.

Rehabilitation of the pavement structure in total length of l=8.13 km. Works include scraping and destroying of asphalt surfacing in total surface of approx. 53.000 m2, replacing of road base, pot holes patching, Public Company cracks sealing, construction of new bearing course BNS 22 in the sutface of approx. 4.450 m2, and Rehabilitation of Kopači - Ustiprača (M20) April - December 129 253 2.799.091,30 1.431.152,66 "Republic of Srpska Roads" wearing course AB 11ks in the surface of approx. 53.000m2. Besides the a/m, the works include: C BA-RISP-40381BA/RS-ICB-W-10-03 2011 +387 51 334 500 reconstruction and upgrade of existing retaining wall, cleaning of drainage system, construction of new drainage system, cleaning and reconstruction of gutters, cleaning and filling of shoulders and as well as works related to traffic signalization and equipment.

Rehabilitation of the pavement structure in total length of l=29.40 km. Works include scraping and Rehabilitation of road direction R15 Šipovo - Public Company destroying of asphalt surfacing in total surface of approx. 145.000 m2, replacing of road base, pot holes April - December 128 252 Kupres in the length of 29,40 km 2.525.513,69 1.291.274,65 "Republic of Srpska Roads" patching, cracks sealing, construction of a wearing course AB 11ks in the surface of approx. 157.000m2. C 2011 EBRD/RS-10-03W +387 51 334 500 Besides the a/m, the works include: cleaning of drainage system, cleaning and reconstruction of gutters, cleaning and filling of shoulders and as well as works related to traffic signalization and equipment.

Rehabilitation of the pavement structure in total length of l=11.77 km. Works include scraping and destroying of asphalt surfacing in total surface of approx.87.000 m2, replacing of road base, pot holes Rehabilitation of road direction R14 Han Kola Public Company April - December patching, cracks sealing, construction of a new bearing layer BNS 22 in the surface of approx. 31.000 m2 127 251 - Srpske Toplice 2.122.422,94 1.085.177,62 "Republic of Srpska Roads c 2011 and construction of wearing course AB 11ks in total surface of 82.000m2. Besides the a/m, the works EBRD/RS-10-02W +387 51 334 500 include: cleaning of drainage system, construction of a new drainage, cleaning and reconstruction of gutters and cleaning and filling of shoulders and as well as works related to traffic signalization and equipment.

Rehabilitation of the pavement structure in total length of l=36.39 km. The works include scraping and Rehabilitation of road directions M5/M19.3 destroying of asphalt surfacing in total surface of approx. 90.000 m2, replacing of road base, pot holes Public Company Rogatica - Sastavci - Ustiprača and M5/M19.3 April - December patching, cracks sealing, construction of a new bearing layer BNS 22 in the surface of approx.2.000 m2 126 250 2.968.241,75 1.517.637,91 "Republic of Srpska Roads" Višegrad - Vardište 2011 and construction of wearing course AB 11ks in total surface of 175.000m2. Besides the a/m, the works +387 51 334 500 EBRD/RS-10-01W include: cleaning of drainage system and gutters, cleaning and filling of shoulders as well as works related to traffic signalization and equipment.

Public Company "Republic of Srpska Roads" Execution of works at construction of motorway section (l=6.736 m) with all additional elements, Construction of the highway Gradiška - Banja Director: Nedeljko Knežević, B.Sc.Oec. earthmoving works, concrete and insulation works on two bridges of spans 28,80 m and 19,60m and three 27-April-2011 - 125 249 Luka (Mahovljani): 46.927.945,37 23.993.877,47 +387 51 334 500 overbridges. C 24-Nov-2011 Lot 3: km 30+000 to km 36+736 /Public Company "Republic of Srpska Bridges are prefabricated monolith structure, prestressed concrete prefabricated girders MB45, M150, V8, Motorways" structure funded on bored HW piles Ø1000, length 14,0m. +387 51 233 670

Execution of works at construction of entire motorway (l=9,500 m) with all additional elements, four overbridges, three double bridges (spans 30m each) on the motorway and two bridges on local roads, and one underbridge Jazovac bridge - two bridges length 2x37.60 m, prefabricated monolith structure, prestressed concrete prefabricated girders MB45, M150, V8, structure funded on bored HW piles Ø800, length 14,0m Jurkovica II bridge - two bridges length 2x37.51 m, prefabricated monolith structure, prestressed concrete prefabricated girders MB45, M150, V8, structure funded on bored HW piles Ø800, length 14,0m Borna bridge - two bridges length 2x37.64 m, prefabricated monolith structure, prestressed concrete Public Company prefabricated girders MB45, M150, V8, structure funded on bored HW piles Ø800, length 12,0m "Republic of Srpska Roads" Bridge at VL 27A - bridge length 53,84 m, bridge structure (2x20=40m), prefabricated monolith structure, Construction of the highway Gradiška - Banja Director: Nedeljko Knežević, B.Sc.Oec. 11-Dec-2007 - prestressed concrete prefabricated girders MB45, M150, V8, structure funded on bored HW piles Ø800, JV Konstruktor Luka (Mahovljani): +387 51 334 500 124 248 82.586.511,74 42.225.812,95 24-Nov-2011 length 12,0m Inženjering - Lot 2: km 20+500 to km 30+000 including /Public Company "Republic of Srpska Bridge on RAMP A- bridge length 53,84 m, bridge structure (2x20=40m), prefabricated monolith structure, Integral Inženjering local roads Motorways" prestressed concrete prefabricated girders MB45, M150, V8, structure funded on bored HW piles Ø800, Dušan Topić length 13,0m +387 51 233 670 Overbridges in length 54.04m each, overbridge structure (2x20=40m), prefabricated monolith structure, prestressed concrete prefabricated girders MB45, M150, V8, structure funded on bored HW piles Ø1000 Underbridge at km 29+515.000 - monolith RC structure, underbridge clear span 9.50 x 5.30m Pavement structure: driving lane: SMA 5cm, binding bituminous course 7 cm, bituminous road base BNS 10 cm, cement stabilisation 20 cm, road base 30 cm overtaking lane: SMA 5cm, binding bituminous course 7 cm, bituminous road base 10 cm, road base 35 cm stopping lane: bituminous bearing course BNS 5 cm, binding bituminous course 7 cm, road base 35 cm

Execution of works at construction of entire motorway (l=10.755 m) with all additional elements, six

1 Execution of works at construction of entire motorway (l=10.755 m) with all additional elements, six overbridges and one double carriageway bridge (span 40m) Jurkovica Bridge - two bridges in the length 2x53.29m, bridge structure (2x20=40m) prefabricated monolith structure, prestressed prefabricated concrete girders MB45, M150, V8, structure funded on bored HW piles Ø1000, length 14.0m. Overbridge at km 13+688.902 - length 113.84m, Overbridge structure (4x25=100m), prefabricated monolith structure, prestressed concrete prefabricated girders MB45, M150, V8, structure funded on bored HW piles Ø1000 for middle piers Ø800. Abutments funded on 5 piles each, length 18m, that is 22m. Foundation of the middle pier is funded on 6 piles. Overbridge at km 11+662.045 - length 54.04m, Overbridge structure (2x20=40m), prefabricated monolith structure, prestressed concrete prefabricated girders MB45, M150, V8, structure funded on bored HW piles Ø1000 Public Company Overbridge at km 12+348.955 - length 54.04m, Overbridge structure (2x20=40m), prefabricated monolith "Republic of Srpska Roads" Construction of the highway Gradiška - Banja structure, prestressed concrete prefabricated girders MB45, M150, V8, structure funded on bored HW piles JV Konstruktor 11-Dec-2007 - +387 51 334 500 123 247 Luka (Mahovljani): 97.663.418,74 49.934.513,09 Ø1000 Inženjering - 24-Nov-2011 /Public Company "Republic of Srpska Lot 1: km 10+254,59 to km 20+500 Overbridge at km 14+910.00 - length 54.04m, Overbridge structure (2x20=40m), prefabricated monolith Integral Inženjering Motorways structure, prestressed concrete prefabricated girders MB45, M150, V8, structure fundd on bored HW piles +387 51 233 670 Ø1000 Overbridge at km 17+550.00 - length 54.04m, Overbridge structure (2x20=40m), prefabricated monolith structure, prestressed concrete prefabricated girders MB45, M150, V8, structure funded on bored HW piles Ø1000 Overbridge at km 20+252.50 - length 54.04m, Overbridge structure (2x20=40m), prefabricated monolith structure, prestressed concrete prefabricated girders MB45, M150, V8, structure funded on bored HW piles Ø1000 Pavement structure: driving lane: SMA 5cm, binding bito course 7 cm, Bituminous road base BNS 10 cm, cement stabilisation 20 cm, road base 30 cm overtaking lane: SMA 5cm, binding bito course 7 cm, Bituminous road base BNS 10 cm, road base 35 cm stopping lane: Bituminous road base BNS 5 cm, binding bituminous course 7 cm, road base 35 cm

Works on asphalting of local road network in December 2010 Municipality Kupres Works on construction and asphalting of local road network in Municipality Kupres: construction and 122 245 72.421,24 37.028,39 c Municipality Kupres - July 2011 + 387 50 480 077 asphalting of the road to Milišići and construction and asphalting of the road to Matići

Works on asphalting and furnishing of football December 2010 Municipality Kupres Works on subgrade, construction of stabilized roadabse, construction of wearing course AB 11, illumination 121 244 48.385,35 24.739,04 C ground in Municipality Kupres - July 2011 + 387 50 480 077 of the playground and furnishing of the football ground.

Execution of works and interventions at Agency for Construction and Earth works (earth traffic lanes planning, rolling and compacting of a new road alignment), concrete works streets and local road directions within regular May - Development of Berane (construction of asphalt-concrete wearing course, equilizing bed, upper bearing layer, mechanical milling of 120 243 391.166,00 200.000,00 C maintenance in December 2010 Ul. IV Crnogorske br. 4; Berane asphalt wearing course, mechanical cutting of asphalt) transport of debris, mechanical and manual removal 2010 at the territory of Berane Municipality Tel: + 382 51 230 574 of existing asphalt layer, delivery of asphalt mixture AB-11 andBNS-22).

Traffic Directorate Reconstruction-investment maintenance of May - 19 IV proleterske Street, Podgorica, Crna 119 242 trunk and pincipal roads in 233.351,37 119.310,66 Construction of wearing course AB 11s, levelling of existing asphalt layer, construction of equilizing bed C June 2010 Gora Lot 16: R-8 Rožaje - Kula Tel: +382 20 655 052

Traffic Directorate Reconstruction-investment maintenance of May - 19 IV proleterske Street, Podgorica, Crna 118 241 trunk and pincipal roads in Montenegro 60.811,57 31.092,46 Construction of wearing course AB 11s, levelling of existing asphalt layer, construction of equilizing bed C June 2010 Gora Lot 15: R-9 Murino-Plav-Gusinje Tel: +382 20 655 052

Reconstruction-investment maintenance of Traffic Directorate trunk and pincipal roads in Montenegro May - 19 IV proleterske Street, Podgorica, Crna 117 240 185.467,66 94.828,11 Construction of wearing course AB 11s, levelling of existing asphalt layer, construction of equilizing bed C Lot 14: M-9 Kolašin-Mateševo-Andrijevica- June 2010 Gora Bjeluha Tel: +382 20 655 052

Traffic Directorate Reconstruction-investment maintenance of May - 19 IV proleterske Street, Podgorica, Crna 116 239 trunk and pincipal roads in Montenegro 325.418,86 166.384,02 Construction of wearing course AB 11s, levelling of existing asphalt layer, construction of equilizing bed C June 2010 Gora Lot 13: M-21 Barski Most-Ribarevina Tel: +382 20 655 052

Traffic Directorate Reconstruction-investment maintenance of May - 19 IV proleterske Street, Podgorica, Crna 115 238 trunk and pincipal roads in Montenegro, Lot 610.049,88 311.913,55 Construction of wearing course AB 11s, levelling of existing asphalt layer, construction of equilizing bed C June 2010 Gora 12: M-2 Ribarevine-Špiljani Tel: +382 20 655 052

Public Works Directorate Improvement of local roads in the length of May - 18 Novaka Miloševa Street, Podgorica, Levelling of existing road, scraping of asphalt pavement, construction of mechanically stabilized road bed, 114 237 256.545,22 131.169,49 C 3km in the Berane Municipality June 2010 Crna Gora construction of shoulders Tel: +382 20 230 207

Public Works Directorate 18 Novaka Miloševa Street, Podgorica, Improvement of local roads in the length of May - Levelling of existing road, scraping of asphalt pavement, construction of mechanically stabilized road bed, 113 236 244.146,42 124.830,08 Crna Gora C 3km in the Andrijevica Municipality June 2010 construction of shoulders Tel: +382 20 230 207

Earth works (planning earth lanes, rolling and compaction, excavation and spreading on the new road Execution of works and interventions at local Agency for Investments and Construction section), concrete works (material purchase, construction of wearing coarse made of asphalt concrete, roads, as well as maintenance of roads and April - December Berana construction of levelling coarse, construction of upper bering layer, mechanict removal of wearing asphalt 112 230 2.967.084,06 1.517.045,99 C streets at the territory of Berane Municipality 2009 IV Crnogorske 4; Berane coarse, mechanic asphalt cutting) in 2009 (regular maintenance) Tel: + 382 51 230 574 transport of debris, mechanical and manual removal of existing asphalt, delivery of asphalt mixture AB-11 and BNS-22.

Execution of street asphalt works works in Plav Municipality Plav and Gusinje and reconstruction of May - Directorate for Space Designing and Execution of street asphalt works works in Plav and Gusinje and reconstruction of damaged asphalt 111 227 171.360,89 87.615,43 C damaged asphalt pavement at streets and September 2009 investments pavement at streets and local roads (patching of damaged pavement) local roads (patching of damaged pavement) Čaršijska bb

Andrijevica Municipality Improvement (asphalt works) of local road July - August B. Deletića bb Mechanical excavation, construction of culverts, construction of bearing road base, construction of BNS. 110 225 449.192,85 229.668,66 C Trešnjevik-Štavna, in the length of 4.433,98m 2009 84 320 Andrijevica Total lenght of the section is 4.4 km Tel. 087/243-161

Government of Montenegro Reconstruction works - capital maintenance of Traffic Directorate The works include asphalt scraping to the level of blanket course, rehabliatation of asphalt paving, repair trunk and principal roads in Montenegro – Lot May 2009 - June 4. Proleterske 19 109 224 97.253,64 49.725,00 and cleaning of dewatering system, procurement and installation of traffic signalization. Works on this C 18.R-20 Berane-Trpezi-Kalače, in total length 2009 Podgorica project are performed without complete road closure. of 950 m Tel: + 382 20 655 052

Government of Montenegro Reconstruction works - capital maintenance of Traffic Directorate Removal of asphalt till the road base level, works on rehabliatation of asphalt paving, repair and cleaning of trunk and principal roads in Montenegro – Lot May 2009 - June 4. Proleterske 19 108 223 181.578,28 92.839,50 dewatering system, procurement and installation of traffic signalization. Works on this project are performed C 17.R-9 Murino-Plav-Gusinje, in total length of 2009 Podgorica without complete road closure. 1400 m Tel: + 382 20 655 052

Earth works (planning of earth carriageway, rolling and compacting, excavation and spreading in new road Execution of works and interventions at route), concrete works, (purchase of material, construction of asphalt-concrete wearing course, construction April - December Agency for Construction and 107 218 streets and road directions within regular 3.932.830,31 2.010.824,21 of equalizing bed, construction of upper bearing base, mechanical removing of wearing asphalt course, C 2008 Development of Berane maintenance in 2008 mechanical cutting of asphalt), transport of debris, mechanical and manual removing of existing asphalt, delivery of asphalt mixture AB-11 and BNS-22.

Municipality Gacko Street pavement in the settlement Burak- July - September Construction of roadbase, placement of curbstones and pavement on street, with construction of drainage 106 217 813.274,54 415.820,67 Tel: 059/464-430 C Voćnjak in Gacko 2008 system and concrete manholes. Total lenght of the section is 1.2 km

Construction of the Obalska Street in Berane, length 3117,36m: construction of 3 sections and main road in Government of Montenegro; Traffic the widening zone, construction of sidewalks and pedestrian passes, construction of vertical and horizontal Construction of Obalska Street in Berane and Directorate, Novaka Miloševa St, 18, April - December signallization, and precipitation sewerage. 105 216 construction of Bridge over the Bistrica River 6.586.161,24 3.367.450,77 Podgorica C 2008 Construction of prestressed RC bridge over the Bistrica river and preparation of design documentation; Contract no. 07/08 from 03 April 2008 Tel: +381 81 230 133 including the construction of access road to the new bridge, mechanical excavation and contact concreting of drilled piles Ø 880 mm that the bridge is based upon. Piers have been casted at situ in metal formwork

Rehabilitation of the road M4 Banja Luka The Project includes reconstruction of the trunk road M-4 in the length of 32,2 km. The works include Public Company (Rebrovac)-Čelinac and October 2008 - asphalt scraping to the level of blanket course, excavation and replacement of the poor-quality blanket 104 215 6.641.323,02 3.395.654,54 "Republic of Srpska Roads" C M4 Čelinac-Kotor Varoš, tender no. EIB/ December 2008 course, works on rehabilitation of the asphalt overlay, repair and cleaning of the drainage system, supply +387 51 309 129 RS-08-01W and installation of traffic signalization. Works on this project are executed without total stoppage of traffic

Reconstruction of roads in Trešnjevo, September 2008 Fondation CARITAS Luxembourg, Reconstruction of roads in Trešnjevo local community, in the lenght of 2 km. The works include (pavement) JV Konstruktor - 103 214 114.508,56 58.547,30 Andrijevica Municipality - October 2008 Berane Office asphalt scraping and construction of new BNS layer. Integral

Reconstruction of 6km long road including construction of 1 km long additional lane for slow traffic; Road Directorate Republic of Reconstruction of the road M2 Sept 2007/ reconstruction of the tunnel, underground excavation, protection of rocks by SN anchors, protection by 102 213 21.453.471,88 10.968.986,72 Montenegro C Mioska-Kolašin Oct 2008 grouting with CC 30, new linings, new impregnation, new portal of total length of approximately 1.000,00 m; +38281244662 stabilization of 5 slopes - 30 and 50 m high

Construction of section of Gradiška – Banja Luka motorway in the toatl length of 5700 m with four traffic lanes, 3.75 m wide, two stopping lanes, 2.50 m wide, two marginal strips along verge 0.50 m wide, two marginal strips along central reserve, 0.20 m wide, two shoulders, 1.50 m wide, central reserve of app. width of 4.00 m between lanes. Beside the construction of the whole highway profile, the project included: Bridge veza 5: the structure constructivelly, rigid RC carcass with three spans and surfacing, two bridges of the total length of L=9+12+9m= 30 m; Bridge veza 4: constructivelly, rigid RC carcass with three spans and surfacing, two bridges of the total length of L=9+12+9m= 30 m; Bridge veza 3: overpass L=2x25=50 m, continuous plate with T-section; Viaduct veza 2: two viaducts of the total length of L=7x35=245 m m, precast prestressed main girders; Execution of works on highway E661, section September 2004 Public Company Bridge veza 1: two bridges of the total length of L=10 m, constructive solution is precast plate made of two 101 209 Gradiška - Banja Luka, section Banja Luka 109.995.198,57 56.239.652,00 - September "Republic of Srpska Roads" types of prestressed elements and elements of which work in-situ. C Airport - Glamočani 2009 +387 51 334 500 Construction of 4 tunnels of the total length of 1673 m (391+389+477+416) with complete lightning and ventilation installation. The tunnels are constructed with the new Austrian method of constructing (NATM). The area of the tunnel profile is 55 m2. The works on construction of tunnels meant the underground and wide excavation (open cut). Protection of slopes is done by placing of SN anchors and reinforcement on the outlets and inlets from the tunnel and placing of SN and IBO anchors, reinforcement and centres in the other part of the tunnel. After the placing of anchors, mesh and centres, the protection of sprayed concrete MB 30, the waterproofing layer and construction of secondary concrete tunnel lining. Construction of service communications of the total length of 2700 m. Construction of motorway drainage system with PP pipes, DN 250-500, the total length of 7330 m, installation of system for atmpsheric water treatment - 15 pieces of separators.

Construction of rotary intersection at the west transit road in Banja Luka. Besides works on construction of the communication, the project also includes works on cable sewage, street-lights and rainfall sewage. The Public Company Construction of the rotary intersection near July - September works on construction of pavement structure included the removal of the existing layers of pavement 100 207 892.030,08 456.087,33 "Republic of Srpska Roads" C "Energomont" building 2008 structure, excavation of material, construction of embankment till the designed level, construction of upper +387 51 334 500 bearing layer of crushed stones, construction of BNS bearing layer and wearing asphalt concrete layer. The project has been completed without complete road closure.

2 The project included: construction of complete section of urban road in total length of 1,4 km. The works included: works on excavations and embankments construction, protection of embankment slopes, November 2007 Public Company construction of roadbase and bitumenous layer BNS and asphalt concrete layer; installation of traffic Construction of south bypass around Trebinje 99 206 819.923,36 419.220,16 - September "Republic of Srpska Roads" signalization. Beside these works, the project included: excavation of bridge foundations, concrete works on C Trebinje 2008 +387 51 334 500 abutment and middle bridge piers, coupling beams of bridge structure, span and road structure and placing of bridge lighting. The span structure of bridge is constructed in the matal formwork in-situ.

The Project includes reconstruction of the main road M-14, section Otoka - Novi Grad in total length app. Public Company 17,7 km. The works include asphalt scraping to the level of blanket course, excavation and replacement of Rehabilitation of the road M-14, section Otoka 98 205 2.002.724,79 1.023.976,93 April - June 2008 "Republic of Srpska Roads" the poor-quality blanket course, works on rehabilitation of the asphalt overlay, repair and cleaning of the C - Novi Grad +387 51 334 500 drainage system, supply and installation of traffic signalization. Works on this project are executed without total stoppage of traffic.

Asphalting of local macadam road in the Municipality of Lopare, Local community October 2007- 97 204 settlement Vukosavci - Ćatinovača, 130.000,00 66.468,00 Vukosavci, Execution of earthworks, civil engineering works, installation of enbankment, roadbase, asphalting C November 2007. Municipality of Lopare 065 658 135

Asphalting of local macadam road in the Municipality of Lopare, Local community October 2007- 96 203 settlement Kozjak, 96.996,00 49.593,26 Vukosavci, Execution of earthworks, civil engineering works, installation of enbankment, roadbase, asphalting C November 2007 Municipality of Lopare 065 658 135

Municipality of Lopare, Local community October 2007- 95 202 Asphalting of streets in Lopare 48.558,40 24.827,40 Lopare Execution of earthworks, civil engineering works, installation of enbankment, roadbase, asphalting C November 2007 065 658 135

BiH Federation, Rehabilitation and reconstruction of roads in October 2007- Ministry of Traffic, Communications, Construction of sidewalks, access roads, roadbase, asphalting of roads, installation of shoulders, drainage, 94 201 Županija Posavska 1.579.268,89 807.467,36 C November 2007 Trade and Entrepreneurship of Županija installation of traffic signalization Municipalities Odžak, Domaljevac and Orašje Posavska

Reconstruction of city communication Bulevar Banja Luka City via Reconstruction of city communication with total length of approx. 550 m with reconstruction of vertical and Cara Dušana with complete infrastructure in Construction Establishment October 2007 horizontal traffic signalization . 93 200 the section between streets Krajiških brigada 1.023.471,18 523.292,50 Banja Luka C December 2007 Infrastructural reconstruction: reconstruction of water system network in total length of 470 m (PEHD DN and Kralja Petra I Karađorđevića in Banja tel: 051 225 900 225); reconstruction of street lights; construction of energy and PTT pipelines (PVC DN 110). Luka 051 225 904

"Fondation CARITAS Luxembourg", Construction and other works, mechanical asphalt cutting, manual removal of existing asphalt, edge Rehabilitation of the existing streets in the September- 92 199 111.437,36 56.977,02 office in Berane Office of CARITAS in preparation and transport of debris to the disposal site, provision of materials and asphalt creation, kerbs C Local Community Pešca, Municipality Berane November 2007 Berane and channels creation

Government of Montenegro Directorate Construction of pipe culverts and of Public Works Construction of embankment out of material from local borrow pit, August 2007- 91 198 embankments at local road for Lake Hrid in 58.947,15 30.139,20 Podgorica thickness 20 cm. C September 2007 the length of 2.5 km, Plav Municipality Novaka Miloševa 18 Construction of prefabricated or semi-prefabricated culverts with ends, total construction, DN 600 mm + 382 20 230 207

Rehabilitation of asphalt road surface damages (pot holes) on streets; mechanical asphalt cutting, manual Rehabilitation of asphalt road surface Municipality Plav; Directorate for space July- removal of existing asphalt, edge preparation and transport of debris to the disposal site, provision of 90 197 damages (pot holes) on streets in Plav and 56.141,38 28.704,63 designing and investments, Čaršijska C August 2007 materials and asphalt Asphalt-concrete-11 creation for levelling holes 5 cm average depth, with emulsion Gusinje b.b., Plav spraying and compaction by rolling. Total lenght of the rehabilitated road is 12 km.

Earthworks (planning earth lanes, rolling and compaction, excavation and spreading on the existing road Works on rehabilitation and asphalt laying on May 2007 - Agency for Construction and section), concrete works, works on pavement structure (mechanical removal of wearing coarse, mechanic 89 196 the existing town streets and local roads in 988.831,62 505.581,58 C December 2007 Development of Berane asphalt cutting, construction of upper bering layer out of crushed stones, construction of BNS levelling the territory of Municipality Berane coarse and wearing coarse out of asphalt concrete 11. Total lenght of the road section is 15 km.

The project encompassed preliminary and earth works, as well as works on pavement construction (roadbase, BNS and asphalt-concrete layer), installation of horizontal and vertical signalisation on the JV GP Put following sections of traffic network) Sarajevo, Modernization (aphalt work) of road June 2007 - 1. Andrijevica -Seoce, 4.50km long; Asfaltgradnja 88 195 infrastructure on the territory of Municipality 999.676,19 511.126,32 Municipality Andrijevica September 2007 2. Trepča 2.00km long; Visoko, Integral Andrijevica 3. Trešnjevo 1.00 km long; inženjering, BBM 4. Kralje - Oblo Brdo 1.00 km long; Amfibolit 5.Konjuhe - Jošanica 3.20 km long, according to adopted offer No. 1858 dated June 4, 2007.

Construction of new motorway lane, reconstruction and expansion of the existing motorway lane to solid profile. Section is 7.6 km long. Profile of one lane of the motorway is two traffic lanes (driving and overtaking lanes 3.75 m wide), stopping lane 2.5 m wide, marginal strip 0.50 m wide. Verge is 4.00 m wide. Within the Construction of motorway Zenica - Sarajevo, Federation of Bosnia and Herzegovina, project, there are three concrete retaining “L” walls, 350 m long, and three concrete gravity retaining walls section Kakanj - Visoko, subsection II: February - FBiH Road Directorate, 87 194 30.983.704,13 15.841.716,37 280 m long. Construction of atmospheric sewage with PEHD corrugated pipes SN 8, DN 315-630, 7000 m C - Visoko, in length 7.6 km, November 2007 Tel: +387 33 563 468 long in total, construction of drainage system of the road with PEHD perforated corrugated pipes SN8, DN LOT A1 section works 315-500, 6150 m long in total. Pavement structure consist of BNS22A layer (6-7cm thick) wearing coarse; SMA 16 (5cm) and asphalt- concrete 16s layer (5cm)

The project included: execution of preliminary and earth works, works on construction of new and Government of Montenegro; Traffic rehabilitation of existing culverts, construction of new retaining walls, works on construction of road base Reconstruction of regional road R-10, Slijepač May - Directorate, Novaka Miloševa St, 18, 86 189 3.047.357,60 1.558.089,20 (roadbase made of crushed stone aggregate, bitumenous layer BNS and asphalt concrete layer), placing of C Most - Tomaševo December 2007 Podgorica vertical and horizontal signalization and installation of guard-rails.The total length of reconstructed road is 5 Tel: +381 81 230 133 km.

Construction of streets in Rožaje - "Jaha Municipality of Rožaje The project included: execution of earth works, civil engineering and craftsman works, works on Kurtagića" Street, "Novopazarska" Street and April - Address: M. Tita bb construction of road base (roadbase made of crushed stone aggregate, bitumenous layer BNS and asphalt 85 188 1.886.571,09 964.588,48 C reconstruction of "Hivzije Ćatovića" Street in October 2007 Phone: +381 69 620 186 concrete layer), placing of vertical and horizontal signalization, public lighting (electriacal installations). The Rožaje total length of constructed and reconstructed street is 3 km.

The proiject of Rehabilitation of Dobrinja - Bogatići Road included: route cleaning, removing of topsoil, road September 2006 Public Company bed-bulk excavation, excavation, construction of embankment, road darinage. Works on superstructure Rehabilitation of Dobrinja - Bogatići Road (M 84 186 1.711.453,32 875.052,19 - November "Republic of Srpska Roads" included: filling of alligator cracks by liquid bitumen mass and mixture of bitumen and filler, milling of asphalt C 18) 2006 +387 51 334 500 and placement of bitumenous layer and layer of asphalt concrete, placing of horizontal and vertical signalization, installation of guard-rail on the section of app. 20 km.

Construction of the access road to the new bridge in Modriča. The project included the works on construction of complete section of the main road in the toatl length of 1,8 Construction of the access road to new km with the construction of junction on the existing crossroads and the construction of new junction. The bridges and belonging structures, and Public Company works included the earth works: excavation, construction of embankment and drainage; works on January 2005 - 83 183 crossroads (connection) to the existing roads 1.556.310,42 795.728,88 "Republic of Srpska Roads" construction of superstructure: construction of roadbase made of crushed stone aggregate, construction of C December 2006 in Modriča and Vukosavlje over the Bosna +387 51 334 500 bearing layer BNS d=8cm and asphalt-concrete d=5cm; construction of vertical and horizontal signalization River, on the new route M17-1 and illumination of the access to the underpass and placing of guard-rail. On the crossing on the new road acrosss the stream Jakešnica is constructed the RC bridge, span l=11m, which is executed monolithly in-situ.

Construction of the access road to the new bridge in Doboj. The project included the works on construction of complete section of the main road in the total length of 2,4 Construction of the access road to new km with the construction of junction on the existing crossroads and the construction of new junction. The bridges and belonging structures, and Public Company works included the earth works: excavation, construction of embankment and drainage; works on October 2004 - 82 182 crossroads (connection) to the existing roads 1.925.296,66 984.388,55 "Republic of Srpska Roads" construction of superstructure: construction of roadbase made of crushed stone aggregate, construction of S December 2006 in Doboj over the Bosna River, on the new +387 51 334 500 bearing layer BNS d=8cm and asphalt-concrete d=5cm; construction of vertical and horizontal signalization route M4-3 and illumination of the access to the underpass and placing of guard-rail. The project also included the construction of undrepass below the railway, span l=14m, made of pre- stressed RC girders, funded on piles.

December 2003 Route cleaning, removing of topsoil, road bed-bulk excavation, construction of embankment, embankment Improvement of local roads in the area of City of Banja Luka 81 176 2.783.450,50 1.423.155,64 - facing and shoulders, road structures and superstructure out of asphalt mass, horizontal and vertical C Banja Luka 051/216 688 July 2006 signalization, installation of guard-rail.

Rehabilitation of Novi Grad - Prijedor Road September 2004 Asfaltgradnja d.d. Visoko Earth works, construction of the carriageway, patching, overlaying, construction of gullies, traffic marking 80 171 Contract: RS-WB/04-6W, Subcontractor's 1.545.139,41 790.017,24 - November C Tel: +387.32.740.126 and road equipment Contract: 1251/04 dtd 14/09/2004 2005

Reconstruction, modernization and construction of the primary route M-8 Foča/ September 2004 Public Company Reconstruction and widening in the length of 2,15km, including excavation, construction of embankments, 79 170 Srbinje - Pljevlja, section Foča/Srbinje - 1.812.473,11 926.702,78 - November "Republic of Srpska Roads" C road drainage, retainment walls, carriageway and road signallization Duhovna Akademija from km 22+576,64 - 2005 +387 51 334 500 24+726,64 in the length l=2,15km

Road reconstruction works, construction of second traffic lane with pedestrian pathway and service Reconstruction of Banja Luka West Transit Public Company August 2005 - facilities. The Works include: regulation of Postranac creek, construction of water and sewerage pipeline, 78 169 Road (EIB/RS-15) 2.680.315,72 1.370.423,67 "Republic of Srpska Roads" S November 2005 as well as main sewer, electro-energetic and telecommunication sewage, vertical, horizontal and traffic RS, B&H +387 51 334 500 signalization, public lighting and landscaping.

Public Company Rehabilitation of Trnovo - Dobro Polje Road, April - August Construction of road bed and superstructure of AB 16, upgrading of the wearing course, filling cracks, 77 166 2.820.837,35 1.442.271,24 "Republic of Srpska Roads" C Contract EIB/RS-09 2005 eliminating ruts and patching potholes; placement of new kerbs; traffic signalization and equipment +387 51 334 500

Rehabilitation of Doboj - Petrovo Road September 2004 Asfaltgradnja d.d. Visoko Earth works, construction of the carriageway, patching, overlaying, construction of gutters, traffic marking 76 163 Contract: RS-WB/04-7W, Subcontractor's 1.748.269,35 893.875,92 C - July 2005 Tel: +387.32.740.126 and road equipment Contract: 1250/04 dtd 14/09/2004

Main road M2, Podgorica - Kolašin Government of Montenegro Section Bogutovski potok: reconstruction of September 2003 Earth works, structures, road superstructure, traffic signalization and road equipment, reinforcing works, 75 161 2.210.767,86 1.130.347,66 Ministry of Maritime Affairs and Transport C road and tunnel No:13 with galleries - May 2005 reconstruction of the tunnel No:13, galleries Tel: +381 81 230 133 Section Subadanj: reconstruction of road

Installation of the rock fall prevention structure August - Asfaltgradnja dd Visoko Reconstruction of slopes on the road by containment net, anchors and sprayed concrete. Slope decreasing 74 153 707.546,50 361.762,78 C on the road M-16, Jajce -B.Luka; September 2004 032.740.126 with slope digging and wedging. Construction of protective gabions.

Ministry of Transport and Communications of RS, Section Construction of East Trunk Road, August - 73 152 413.810,22 211.577,81 Road directorate of RS Construction of city communication of four lane (2+2) cariage drive, total length 177.60m. C Section on km 0+000 to 0+177.60, Annex September 2004 Banja Luka Tel. 051 309 128

Improvement of Road Conditions on Main Public Company Excavation and construction of embankments out of natural gravel, construction of mechanically stabilized June - August 72 150 Road M-14.1 S. Brod-Derventa (MSR New 927.383,07 474.163,43 "Republic of Srpska Roads" bearing structure, construction of upper bearing structure (BNS), as well as asphalt wearing course. Soiling C 2004 Jersey) Sijekovac - SFOR/46A-2002 +387 51 334 500 and vegetative protection of the slopes.

Ministry of Transport and Communications of RS Reconstruction works on ditches, gutters, berms, cleaning of culverts and drainages, reconstruction of Rehabilitation of the road section Lapišnica - October 2003- PID Transport 71 149 7.199.933,31 3.681.267,45 potholes, ruts, longitudinal and transversal cracks, gabions, pavement reconstruction, reconstruction of C Podromanija - Vardište September 2004 Public Company shoulders, placing of new guard rail, guard posts, containment nets, and traffic signalization "Republic of Srpska Roads" +387 51 334 500

TACO Installation of rock fall prevention structures Sarajevo Reconstruction of slopes on the road by containment net, anchors and sprayed concrete. Slope decreasing 70 145 on the road Gornji Vakuf-Prozor-Jablanica 206.648,23 105.657,56 April-June 2004 C SFOR with slope digging and wedging. Construction of protective gabions. (Gračanica) +387 33 495 723

3 TACO Installation of rock fall prevention structures Sarajevo Reconstruction of slopes on the road by containment net, anchors and sprayed concrete. Slope decreasing 69 144 127.632,87 65.257,65 April-June 2004 C on the road Gornji Vakuf-Makljen-Prozor SFOR with slope digging and wedging. Construction of protective gabions. +387 33 495 723

Ministry of Transport and Communications of RS Reconstruction works on ditches, gutters, berms, cleaning of culverts and drainages, reconstruction of Rehabilitation of the road section Šešlije - October 2003- PID Transport 68 143 3.100.000,33 1.585.005,00 potholes, ruts, longitudinal and transversal cracks, pavement reconstruction, reconstruction of shoulders, C Doboj Contract No. EIB/RS/07 May 2004 Public Company placing of new guard rail, guard posts, and traffic signalization "Republic of Srpska Roads" +387 51 334 500

Installation of Road Safety Structures March -April SFOR / TACO JV "Tuzlaputevi - 67 142 (Guardrails) SA-03-C-1069, NJ 03 09 B, 119.967,10 61.338,20 Replacement of old and installing of new guardrails, as well as metal supports 2004 + 387 35 254 170 Integral" Doboj - Šićki Brod

Ministry of Transport and Reconstruction, construction and Communications of RS, modernization of the road R-476 A Šnjegotina Road Directorate of RS Cleaning of the route, removal of topsoil, road bed – wide excavation, excavation for stairs and ditches, – Klupe, road section from km 2+979,98 to km May 2002 - 66 140 725.724,90 371.057,25 Banja Luka construction of embankment, embankment facing and shoulder, structures and superstructure are made of S 4+578,61, in length l =1.598,63 m, Contract September 2003 Public Company asphalt, traffic signalization and placing of guard rail No. 03-345-1742/02 "Republic of Srpska Roads" RS, Bosnia and Herzegovina +387 51 334 500

Rehabilitation of M-18 Šićki Brod - Krivajevići, September 2003 FBH Road Directorate Cleaning and routine maintenance of drainage; patching of asphalt constructions; overlaying of asphalt- 65 139 Contract No. BA/RMSP/FBHRD/ICB/13/W/03/ 2.794.256,96 1.428.680,90 - December 2 Put života, krilo A/III C concrete course; reconstruction of existing road; horizontal road markings; supported signs. IN 2003 71000 Sarajevo

Road reconstruction, in length 5400 m. Removal of old asphalt layer, culvert construction and construction Road reconstruction Kozarac - Trnopolje, April 2003- PARSONS DELAWARE INC. 64 132 886.228,80 453.121,59 of access roads. Channel cleaning, construction of base layer, asphalt placing. Placing of vertical and C Contract No. 739387-30281 August 2003 035/253 161 horizontal road signalization.

Construction of reinforced concrete wall km Republic of Srpska Railways 119+200 to 119+230 in order to secure earth April 2003 - Watercourse regulation, mechanical excavations, making of drainage layer behind retaining wall, concreting 63 128 68.900,00 35.228,01 Doboj C roadway Dobrinj-Banja Luka-Doboj-Zvornik June 2003 of reinforced concrete retaining wall, preparation of design documentation 053 / 223 - 012 from undercutting

Construction of Marija Dimić Street Reconstruction of communication, execution of earth works, RC works, works on construction of new October 2002 - 62 127 (Petrićevački put) in Banja Luka, Contract No. 852.955,75 436.109,35 City of Banja Luka atmospheric sewage system with appropriate infrastructure, execution of works on establishing of C 2003 05-370-2822/02 Tel. 051 216 688 communication and placing traffic equipment

Europen Agency for Reconstruction, Access communications to Primary school " February 2003 - Construction of communications with accompanying infrastructure.Primarily electrical cables are to be laid 61 125 243.650,53 124.576,54 Podgorica C Zlatica " Podgorica Maj 2003 illumination, horizontal and vertical signalization Tel. 081 231 741

Construction of communication with related Staking of route, cleaning of terrain, construction of whole communication, construction of water supply, January - May City of Banja Luka 60 123 infrastructure - Stevana Markovića Street, 101.793,60 52.046,24 precipitation and foul drainage, installation of street lighting and distribution of power supply network for C 2003 Dragoljub Davidović Banja Luka street lighting Tel. 051 216 688

Reconstruction and construction of the part of Route cleaning, removal of the humus layer, road bed-wide excavation, excavations for stairs and Njegoševa Street, as well as construction of August 2002 - excavation of ditches, construction of embankment, embankment facing and shoulder, structure and 59 122 960.449,91 491.070,24 City of Banja Luka C atmospheric and foul water sewage in Banja December 2002 superstructure will be made of asphalt, traffic signalisation and placing of guard rails, construction of Tel. 051 216 688 Luka, Contract No. 05-370-2447/02 atmospheric and foul water sewage

SFOR Earth excavation and terrain drainage by concrete walls, making of shoulder drainage channels, making a Rehabilitation of landslide Stupari (near Tuzla) Octobar 2002 - 58 120 124.321,36 63.564,50 Sarajevo Office roadbase, asphalt road surface and structures, concreting of foundations and walls, construction of stone C by retaining wall construction January 2003 Tel. 033 495 000 lining, replacement of surfacing and guard rail

Construction of the forest truck road Šipašno- Forestry Project Implementation Unit Cleaning of the route, removal of topsoil, road bed-wide excavation for stairs and ditches, construction of May 2002 - 57 117 Zlatac (Forest reserve "Botin",Nevesinje),RS, 401.289,06 205.175,84 (PIU) embankment, embankment facing and shoulder, structures and superstructure are made of broken stone, C November 2002 Bosnia & Herzegovina Tel. 055 220 940 traffic signalisation

Construction of the forest truck road Livade- Forestry Project Implementation Unit Cleaning of the route, removal of topsoil, road bed-wide excavation for stairs and ditches, construction of May 2002 - 56 116 Bač (Forest reserve "Maglić",Srbinje),RS, 350.120,44 179.013,74 (PIU) embankment, embankment facing and shoulder, structures and superstructure are made of broken stone, S November 2002 Bosnia & Herzegovina Tel. 055 220 940 traffic signalisation

JV Integral, Put Upgrading of Road Safety Equipment in April 2002 - European Agency for Reconstruction Repair of asphalt layer on four sections of the road, placing of the horizontal and vertical signalization, 55 115 3.207.123,33 1.639.776,12 E.Sarajevo and Southern Montenegro May 2003 Tel. + 381 81 406 600 construction of new guardrail on seven sections of the road Primorje

PARSONS DELAWARE INC. May 2002 - Making of the Main/construction Design, cleaning of the route, machine removal of topsoil, construction of 54 113 Bratunac - Hrnčići Road Reconstruction 187.923,10 96.083,56 Sarajevo Office C October 2002 sub-base of the road with necessary compacting, construction of the road base and road fittings Tel. 033 220 948

Project of Reconstruction Pavement Government of Montenegro, rehabilitation of the road KULA - ROŽAJE RK August 2001 - Removal of the existing bituminous layers, construction of new roadway, drainage works and placing of 53 111 2.943.804,91 1.505.143,55 Ministry of Maritame Trade and Transport C 1 and RK2 October 2002 traffic sign work Tel. + 381 81 230 133 Montenegro

Reconstruction and rehabilitation of the part of Reconstruction of the communication, execution of earth works, RC works, works on construction of new August City of Banja Luka 52 110 Milana Radmana Street and extension of the 260.848,45 133.369,69 atmospheric water intellation, with appropriate infrastructure, execution of works on communication C 2002-May 2003 Tel. 051 216 688 Drage Vasića Street in Banja Luka construction and placing of traffic equipment

Ministry of Transport and Communications of RS, Reconstruction, rehabilitation and September 2001 Road Directorate of RS modernization of the road R-429 Trebinje - 51 106 2.956.510,83 1.511.639,98 - Banja Luka Reconstruction, rehabilitation and modernization of the regional road section, lenght 7.120,31 m C Herceg Novi, section Tuli - Grab September 2002 Public Company RS, Bosnia & Herzegovina "Republic of Srpska Roads". +387 51 334 500

Ministry of Transport and Communications of RS, December 2001 Road Directorate of RS Temporary roads for the Western main road in Preparatory works, machine excavation of the soil, panning of road bed, construction of road base, new 50 103 213.254,20 109.035,14 - Banja Luka C Banja Luka (P-12 to P-18 i P-20 to P-34) layers of the roadway, drainage works and construction of vertical and horizontal signalisation July 2002 Public Company "Republic of Srpska Roads" +387 51 334 500

Ministry of Transport and Communications of RS, December 2001 Road Directorate of RS Temporary roads for the Western main road in 49 102 197.002,01 100.725,53 - Banja Luka Works on the construction of the temporary roads, rain-water drainage and retaining wall C Banja Luka (P-12 to P-18 i P-20 to P-34) July 2002 Public Company "Republic of Srpska Roads" +387 51 334 500

Supply and installation of guardrails on the SFOR May - June Supply and installation of traffic safety equipment that consists of guardrail sements-panels normal, long, 48 92 main road M 17,section Doboj - Bos.Brod 43.336,24 22.157,47 Sarajevo Office C 2002 short, steel poles made of I profiles and catadiopters Bosnia & Herzegovina Tel. 033 495 000

Landscaping of bussines premises at crossroads of Njegoševa Street - Kupreška March - June " Maxmara " Banja Luka Works on landscaping consist of excavation and construction of road bed for the new roadway surfaces, 47 91 33.047,39 16.896,86 C Street in Banja Luka 2002 Tel. 051 358 940 construction of roadbase, placing of asphalt, construction of precipitation and atmospheric drainage Bosnia & Herzegovina

Construction of the retaining wall on the road SFOR March - May Chase cutting of the damages on the existing retaining wall, cleaning of the weakened parts of the wall, 46 90 M-15, Baraći 51.969,75 26.571,71 Sarajevo Office C 2002 construction of the concrete counterforts, placing of the safety fence of the new RC slab Bosnia & Herzegovina Tel. 033 495 000

City of Banja Luka via October - Reconstruction of the section of Kralja Alfonsa Construction Establishment 45 83 66.118,10 33.805,65 December Stripping of the existing pavement and the construction of the new one, in the lenght of 120 m C XIII Street Banja Luka. 2001 Tel. 051 216 662

Ministry of Transport and Communications of RS, Road Rehabilitation and Reparation Banja Road Directorate of RS Luka - Teslić January 2001 - 44 76 1.443.980,97 738.295,75 Banja Luka Ground levelling, horizontal and vertical signalisation, channel making C Section Maslovare - Hrastova Kosa September 2001 Public Company Bosnia & Herzegovina "Republic of Srpska Roads" +387 51 334 500

PID Transport of RS Banja Luka Road Construction Banja Luka - Teslić October 2000 - Public Company Construction of new road, soil repair, system of drainage of surface and riparian water and slope 43 75 Section Hrastova Kosa - village Bebe, 9.849.670,80 5.036.056,71 C September 2001 "Republic of Srpska Roads" landscaping. Bosnia & Herzegovina +387 51 334 500

Ministry of Transport and Construction, econstruction and November 2000 Communications of RS, Construction of another road surface lane with associate junctions, bicycle and pedestrian paths, lighting 42 74 modernization of the Eastern Motorway, Banja 2.071.361,77 1.059.070,46 - Road directorate of RS C and horizontal and vertical signalisation Luka September 2001 Banja Luka Tel. 051 309 128

March SFOR 41 67 Derventa - Klašnice Road 35.214,00 18.004,63 Installation of the containment nets, road barriers and road marking C 2001 Tel. 033 495 000 Bosnia & Herzegovina

Reconstruction of local road ODP "PRIJEDORPUTEVI" December 40 66 Omarska - Marićka 310.620,00 158.817,48 Prijedor Construction of base layer, cleaning of structures, development of opened channels C 2000 Bosnia & Herzegovina Tel. 052 233 117

Reconstruction of local road Bistrica - June - ODP "PRIJEDORPUTEVI" 39 65 Lamovita Vrijesak 333.420,00 170.474,94 September Prijedor Construction of base layer, cleaning of structures, development of opened channels C Bosnia & Herzegovina 2000 Tel. 052 233 117

Reconstruction of local road M-4 September - ODP "PRIJEDORPUTEVI" 38 64 Srednja Lamovita 383.980,00 196.325,86 December Prijedor Construction of base layer, cleaning of structures, development of opened channels C Bosnia & Herzegovina 2000 Tel. 052 233 117

Reconstruction of local road October - ODP "PRIJEDORPUTEVI" 37 63 Dubovik - Novi Grad 225.063,00 115.072,88 November Prijedor Construction of base layer, cleaning of structures, development of opened channels C Bosnia & Herzegovina 2000 Tel. 052 233 117

Road reconstruction September - ODP "PRIJEDORPUTEVI" Cutting of pot holes,hole patching,scraping of delevelled surfaces, construction of new asphalt 36 62 K.Dubica - Prijedor 636.300,00 325.335,02 December Prijedor surface,horizontal and vertical signalisation, cleaning of structures, installation of steel nets to the asphalt C Bosnia & Herzegovina 2000 Tel. 052 233 117 structure

4 Road Directorate of RS Rehabilitation of road surface on road B.Luka September - Banja Luka Cutting of pot holes,hole patching,scraping of delevelled surfaces, construction of new asphalt 35 61 - Klašnice 408.211,00 208.714,97 November Public Company surface,horizontal and vertical signalisation, cleaning of structures, installation of steel nets to the asphalt C Bosnia & Herzegovina 2000 "Republic of Srpska Roads" structure +387 51 334 500

Road Directorate of RS November - Banja Luka Construction of road Kotor Varoš - Teslić New route cutting, construction of bed, carrying layer and asphalt structure with road structures (culverts, 34 60 143.196,67 73.215,29 December Public Company C Bosnia & Herzegovina opened channels, etc) 2000 "Republic of Srpska Roads" +387 51 334 500

Road Directorate of RS Rehabilitation of road surface on road M 16 October - Banja Luka 33 59 Banja Luka - Jajce 150.016,68 76.702,31 December Public Company Scraping of delevelled surfaces, cutting and patching of pot holes, construction of asphalt structure C Bosnia & Herzegovina 2000 "Republic of Srpska Roads". +387 51 334 500

Road Directorate of RS Rehabilitation of road surface on road M 19 November - Banja Luka 32 58 Šepak - Vlasenica 101.043,72 51.662,83 December Public Company Scraping of delevelled surfaces, cutting and patching of pot holes, construction of asphalt structure C Bosnia & Herzegovina 2000 "Republic of Srpska Roads" +387 51 334 500

Road Directorate of RS Lighting and traffic lighting works on the road September - Banja Luka Installation of galvanized chandeillier, height of 10 m, installation of lighting signalisation at portals and 31 56 M16 1.733.647,40 886.399,84 December Public Company C consoles Bosnia & Herzegovina 2000 "Republic of Srpska Roads" +387 51 334 500

PID Transport of RS Banja Luka September - Reconstruction of the road Tjentište - Gacko Public Company Cutting of pot holes,hole patching,scraping of delevelled surfaces, construction of new asphalt 30 53 3.620.152,00 1.850.954,33 November C Bosnia & Herzegovina "Republic of Srpska Roads" surface,horizontal and vertical signalisation, cleaning of structures 2000 +387 51 334 500

Road Directorate of RS Rehabilitation of road surface on road Banja October - Banja Luka Cutting of pot holes,hole patching,scraping of delevelled surfaces, construction of new asphalt 29 52 Luka - Klašnice and Sratinska 933.670,52 477.378,16 November Public Company surface,horizontal and vertical signalisation, cleaning of structures, installation of steel nets to the asphalt C Bosnia & Herzegovina 2000 "Republic of Srpska Roads" structure. Construction of base layer, cleaning of structures, development of opened channels +387 51 334 500

Ministry of Transport and Rehabilitation of the pavement on the road M September - Communications of RS, Cutting of pot holes,hole patching,scraping of delevelled surfaces, construction of new asphalt 16 Banja Luka - Klašnice, section 28 51 408.211,00 208.714,97 October Road Directorate of RS surface,horizontal and vertical signalisation, cleaning of structures, installation of steel nets to the asphalt C 380+450-40+080 2000 Banja Luka structure Bosnia & Herzegovina Tel. 051 309 128

Rehabilitation of the road M16, Banja Luka - October - Republička Direkcija za puteve Repair of landslide, construction of pavement structure and culverts, installation of drainage and their 27 50 Jajce, km 26-27 649.935,90 332.306,95 November Banja Luka C dewatering, horizontal and vertical signalisation Bosnia & Herzegovina 2000 Tel. 051 309 128

Rehabilitation of the landslide at the road September - Road directorate of RS Repair of landslide by counterforts, with cushion beams and retaining wall from the both sides of the 26 49 M19, Šepak - Vlasenica km 43 - 44 466.641,92 238.590,23 November Banja Luka C landslide,construction of pavement structure and culverts Bosnia & Herzegovina 2000 Tel. 051 309 128

Rehabilitation of the Motor Way, Cutting of pot holes,hole patching,scraping of delevelled surfaces, construction of new asphalt PID Transport of RS Banja Luka 25 47 Banja Luka - Klašnice 1.017.465,03 520.221,61 2000 surface,horizontal and vertical signalisation, cleaning of structures, installation of steel nets to the asphalt C Tel. 051 308 172 Bosnia & Herzegovina structure

PID Transport of RS Banja Luka Rehabilitation of the Motor Way Cutting of pot holes,hole patching,scraping of delevelled surfaces, construction of new asphalt May - October Public Company 24 45 Brod na Drini - Tjentište 506.563,00 259.001,55 surface,horizontal and vertical signalisation, cleaning of structures and shoulders and development of road C 2000 "Republic of Srpska Roads" Bosnia & Herzegovina area +387 51 334 500

Improvement of traffic safety, SA-00- SFOR 23 44 C-202,TCR PELICAN 60.627,50 30.998,35 2000 Installation of safety fences, road barriers and road marking C Tel. 033 495 000 Bosnia & Herzegovina

Improvement of traffic safety, SA-00- March - August SFOR 22 43 C-202,TCR PELICAN 67.582,70 34.554,49 Installation of safety fences, road barriers and road marking C 2000 Tel. 033 495 000 Bosnia & Herzegovina

Improvement of traffic safety, SA-00- March - August SFOR 21 42 C-0204,TCR GULL 123.572,00 63.181,36 Installation of safety fences, road barriers and road marking C 2000 Tel. 033 495 000 Bosnia & Herzegovina

Improvement of traffic safety, SA-00- SFOR 20 41 C-1617,TCR BLUEBIRD 17.372,00 8.882,16 July 2000 Installation of safety fences, road barriers and road marking C Tel. 033 495 000 Bosnia & Herzegovina

Installing of safety fences and containing nets, March - August SFOR 19 40 SA-00-C-203,TCR HORNBLOWER 53.112,00 27.155,73 Installation of safety fences, road barriers and road marking C 2000 Tel. 033 495 00 Bosnia & Herzegovina

Installing of safety fences and improvement of traffic safety, SA-00-C-1648,TCR July - August SFOR 18 39 70.370,00 35.979,61 Installation of safety fences, road barriers and road marking C HORNBLOWER 2000 Tel. 011 650 522 Bosnia & Herzegovina

PID Transport of RS Banja Luka Rehabilitation of the Motor Way,Banja Luka- Cutting of pot holes,hole patching,scraping of delevelled surfaces, construction of new asphalt Public Company 17 36 Klašnice 2.193.924,18 1.121.735,62 June 2000 surface,horizontal and vertical signalisation, cleaning of structures, installation of steel nets to the asphalt C "Republic of Srpska Roads" Bosnia & Herzegovina structure +387 51 334 500

Reparation of the access road and left river June - ELEKTROPRIVREDA RS dyke, downstream Hydro Power Plant - Cutting of pot holes,hole patching,scraping of delevelled surfaces, construction of new asphalt 16 33 1.247.663,02 637.919,97 December H.E. BOČAC C BOČAC surface,horizontal and vertical signalisation, cleaning of structures, bank protection 2000 Tel. 051 215 915 Bosnia & Herzegovina

Rehabilitation of the local road at km 26 Road Directorate of April - May 15 32 Goleši, local community Borkovići 17.614,33 9.006,06 Banja Luka City Construction of base layer, cleaning of structures, development of opened channels C 2000 Bosnia & Herzegovina Tel. 051 309 128

Installing of the containment nets on the road directions Banja Luka - Jajce - Mrkonjić Grad March - May SFOR - RACO, Sarajevo 14 29 250.000,00 127.822,97 Installation of the containment nets, road barriers and road marking C - Glamoč 2000 Tel. 033 495 000 Bosnia & Herzegovina

Rehabilitation of the langslide at the road M15 December 1999 Republička Direkcija za puteve 13 28 Banja Luka - Jajce (GULL) 506.629,00 259.035,29 - RS / SFOR - RACO Sarajevo Construction of concrete foundations of retaining wall, replacement of pavement structure C Bosnia & Herzegovina April 2000 Tel. 051 309 128

Boulevard Cara Dušana, Construction new September - Banja Luka City, Fund for construction roadways/extension including construction of Concrete works at bridges, construction of new pavement structure, construction of new asphalt surface, December land planning and Road Directorate of new square,arches over the river and four horizontal and vertical signalization, cleaning of structures, reconstruction of water supply network - pipeline 12 24 3.734.662,75 1.909.502,74 1999/ RS Banja Luka C smaller bridges and dislocation of water PHDE 100 DN 400, PN 10, L=460 m, construction of sewage system Ø 350 - Ø 1000, concrete and PVC September - supply network pipes - total length 620 m. December 2006 Tel. 051 308 172 Bosnia & Herzegovina

June - Road Reconstruction / Bijeljina - Banj Brdo Parsons Delaware / Tuzla Cutting of pot holes,hole patching,scraping of delevelled surfaces, construction of new asphalt 11 21 4.395.194,00 2.247.227,01 December C Bosnia & Herzegovina Tel. 035 282 200 surface,horizontal and vertical signalisation, cleaning of structures 1999

PID Transport of RS Banja Luka Road Reconstruction / Novi Grad - K.Dubica April - October Public Company Cutting of pot holes,hole patching,scraping of delevelled surfaces, construction of new asphalt 10 20 1.190.271,25 608.576,03 C Bosnia & Herzegovina 1999 "Republic of Srpska Roads" surface,horizontal and vertical signalisation, cleaning of structures +387 51 334 500

PID Transport of RS Banja Luka Road Reconstruction / Brod on/D - Tjentiste March - July Public Company Cutting of pot holes,hole patching,scraping of delevelled surfaces, construction of new asphalt 9 19 2.482.247,98 1.269.153,24 C Bosnia & Herzegovina 1999 "Republic of Srpska Roads". surface,horizontal and vertical signalisation, cleaning of structures +387 51 334 500

Reconstruction of the bridge/road Modriča - April - June Parsons Delaware / Tuzla 8 14 Gradačac 196.000,00 100.213,21 Scraping of delevelled surfaces, construction of new asphalt surface, horizontal and vertical signalisation C 1999 Tel. 035 282 200 Bosnia & Herzegovina

PID Transport of RS Banja Luka Road Reconstruction / Johova - K.Dubica Oktober 1998 - Public Company Concrete works on bridges,cutting of pot holes,hole patching,scraping of delevelled surfaces,construction of 7 13 400.000,00 204.516,75 C Bosnia & Herzegovina March 1999 "Republic of Srpska Roads" new asphalt surface,horizontal and vertical signalisation,cleaning of structure +387 51 334 500

Bridges and road reparations/ road Derventa - September 1998 Parsons Delaware / Tuzla Concrete works on bridges,cutting of pot holes,hole patching,scraping of delevelled surfaces,construction of 6 12 Brod 815.823,00 417.123,68 - C Tel. 035 282 200 new asphalt surface,horizontal and vertical signalisation,cleaning of structure Bosnia & Herzegovina April 1999

PID Transport of RS Banja Luka Road reparation / Doboj-Crkvine-Šamac July - October Public Company Ctting of pot holes,hole patching,scraping of delevelled surfaces,construction of new asphalt 5 11 750.000,00 383.468,91 C Bosnia & Herzegovina 1998 "Republic of Srpska Roads" surface,horizontal and vertical signalisation +387 51 334 500

PID Transport of RS Banja Luka Construction of the road,bridge and River July 1998 - Public Company Embankment construction, pavement structure construction, paving of access places, construction of 4 10 Dike/Road Kostajnica-K.Dubica 337.626,00 172.625,43 C May 1999 "Republic of Srpska Roads" asphalt structure, concrete works at bridges and road structures Bosnia & Herzegovina +387 51 334 500

Construction of the road,bridge and River July 1998 - Parsons Delaware / Banja Luka Concrete works on bridges,cutting of pot holes,hole patching,scraping of delevelled surfaces,construction of 3 9 Dike/Road Kostajnica-K.Dubica 318.594,00 162.894,53 C May 1999 Tel. 035 282 200 new asphalt surface,horizontal and vertical signalisation,cleaning of structure,river bank protection Bosnia & Herzegovina

Rehabilitation of the Motor Way,Banja Luka- Cutting of pot holes,hole patching,scraping of delevelled surfaces, construction of new asphalt May - October JEDINSTVO - Gradiška 2 6 Klašnice 2.709.050,00 1.385.115,27 surface,horizontal and vertical signalisation, cleaning of structures, installation of steel nets to the asphalt 1998 Tel. 051 813 297 Bosnia & Herzegovina structure

Construction of the roads and River Ferry World Vision - Banja Luka April - October Embankment construction, pavement structure construction, paving of access places, construction of 1 4 Dock on the Sava river Municipality Srbac 560.000,00 286.323,45 Tel. 051 464 490 1998 asphalt structure, concrete works at bridges and road structures Bosnia & Herzegovina

5