Nelson Mandela Multi-Purpose Stadium

INTRODUCTION disciplines to take the concept design into design office. Notwithstanding the above, The Nelson Mandela Multi-Purpose the detailed design stage, as well as the the exercise was considered successful in Stadium is located about 50 m from Port construction monitoring stage. A Project the transfer of specialist design skills related Elizabeth’s North End Lake, and within Management Plan was developed whereby to a major sporting facility / industrial fast- 1 km from the sea, on a site that presented each discipline had to be presented by a track project. a number of challenging features, such discipline leader reporting to the Principal as expansive soil, a high water table, and Agent (BKS BTKM/PMSA Joint Venture). LIMITED TIME a pitch level 1 m below the overflow weir Design offices were made available on site The exceptionally short time period, from level of the lake. Various other challenges to facilitate a closer working relationship the date when the project budget was ap- encountered during the execution of this between the various disciplines. This proved proved (October 2006) to the anticipated project included late financial budget to be a challenge, as not all the disciplines inclusion as a Confederations Cup venue in approval, a short project implementation were represented by the key designers in the June 2009, theoretically allowed a period of period, an over-heated tender climate, a large number of consultants, and poor 1 weather conditions. Despite these challenges, and thanks to quality engineering and management, the 46 000 capacity, spectator-friendly stadium was completed on time and within budget, boasting a roof that is con- sidered an engineering masterpiece, and excellent sight lines and limited distances from the pitch for all spectators.

PROJECT BACKGROUND The initial design for estimating purposes was based on a 27 000 permanent seat facility and 18 000 temporary seats (FIFA required a capacity of 45 000 seats), and a single roof only for the western main stand. The Client, however, decided that it was imperative to design a facility which would be seen as an ‘icon’ – a unique design for the Nelson Mandela Bay (NMB) Metro. This resulted in a stadium designed with a NELSON MANDELA MULTI-PURPOSE STADIUM full roof structure covering all the stands. MANY CONSULTING FIRMS Technical Excellence category The Client believed that it was important to broaden the knowledge base of the consultants within the NMB Metro by KEY PLAYERS appointing 52 consulting firms of various Client Nelson Mandela Bay Municipality Professional Team BKS BTKM-PMSA Joint Venture 1 The Nelson Mandela Multi-Purpose Stadium Main contractor GLTAI (Grinaker-LTA Interbeton JV) is located about 50 m from ’s Major Subcontractors and Suppliers TMC (roof structure and membrane) North End Lake, and within 1 km from the sea George Roofing (aluminium cladding)

Civil Engineering | December 2010 55 2 3

30 months, excluding the three Christmas and its covering was a complex structure, loads carried by the roof, both as dead periods. Within this time the consultants difficult to erect in Port Elizabeth’s noto- and live loads during high winds, were had to be formally appointed and briefed riously strong winds. effectively transferred into the structure on the scope of work, detailed designs The main critical path ran through and into the foundations. had to be carried out and procurement the west stand, which had two additional The roof structure and coverings completed. The project was therefore split levels housing the changing and hosting were designed by specialist roof design into preparatory work which consisted of facilities. Whilst this area was started engineers based in Germany who ensured the relocation of existing services, provi- first, the volume and complexity of work that the weight of the roof structure was sion of bulk services, bulk earthworks was such that it was finished last. minimised by designing a space frame and piling. The main contract included The roof erection process started on tubular truss which kept the mass of each all works related to the stadium construc- the north stand, progressing clockwise of the 36 trusses at 55 tonnes each. tion as a single project. The main contract until the west stand concrete works had Monitoring the production of the commenced in March 2007 with practical been sufficiently completed to allow the structural steel roof and its delivery and completion close to the first week of erection of the roof there. Once the roof, erection, proved to be a considerable June 2009 to allow the hosting of the first including its coverings, had been erected challenge due to the distant location of official match, albeit not a Confederations on the west stand, the finishings in that the manufacturing facility. Each truss Cup match (explained later on in this area became the critical element, together type had to be pre-assembled in Kuwait article) on 16 June 2009 between the with the external works which could not to check the geometric correctness of the Southern Spears and British Lions teams. be started until the roof erection crane curves and any deflection at the front tip had been relocated to another area. The of the truss. Once the pre-assembly had SITE CONDITIONS initial programming sequence required been verified, the trusses had to be de- As mentioned above, the high water table, the roof to be erected in a clockwise di- assembled prior to shipping. The manu- plus the close proximity of the North End rection only, but it became necessary to facturing process took eight months, Lake, posed specific challenges. change this sequencing to 30% clockwise three months longer than had been pro- A specially designed crane pathway and 70% anti-clockwise, resulting in a grammed. Much of the delay was caused had to be constructed all around the sta- time-saving of several months. by the non-availability of certain sections dium at very specific gradients and engi- The concrete structure was con- of steel, together with the complexity of neered levels. This entailed the excavation structed in eight segments by different the roof geometry impacting on the pro- of expansive material and the importation construction teams, all segments top- duction of the roof purlins. This, together of quality material to provide a stable base ping out at a highly reinforced ring slab/ with delays experienced in shipping the for the crane to lift the 55 t girder struc- beam containing the precisely positioned trusses, resulted in substantial delays. tures into position. securing bolts for the structural steel The roof trusses were shipped in three Due to the poor soil conditions the roof. The positioning of these bolts and major consignments from Kuwait to Port entire structure had to be founded on a the casting in of these into the columns Elizabeth, then transported to site for as- set of 2 300 piles with pile lengths varying was critical, as the roof trusses were of sembly. Massive steel frame jigs were set from 7,5 m to 12,5 m. a predetermined size that could not be up on site for the assembly of each of the altered. In addition, it was imperative 46 m long trusses. The first truss com- ASPECTS OF CONSTRUCTION that not only were they dimensionally ponents arrived on 27 August 2008, and The concrete structure supporting the accurately positioned, but they needed to were assembled over a two-month period roof had high accuracy tolerances al- have the necessary cast in-situ bond to before being erected. The last truss was lowing minimal deviation, and the roof the concrete structure to ensure that the erected on 12 March 2009.

56 Civil Engineering | December 2010 4

2 3 4 and and The roof girders were 5 installed entirely from the outside of the stadium. The window of operation for the 500 t caterpillar crane was limited by the notorious Port Elizabeth winds, resulting in the erection of the girders occurring mostly in the morning 5 The initial programming sequence required the roof to be erected in a clockwise direction only, but it became necessary to change this sequencing to 30% clockwise and 70% anti-clockwise, resulting in a time-saving of several months 6 The roof acquires its remarkable form from the alternating arrangement of the girders and the membrane surfaces spanned in-between

The girder ring connecting the cantilevered end of all 36 trusses was sequentially erected with the trusses some 40 m above the playing surface. A restrictive requirement of the structural engineers was that at least five completed trusses had to be erected before any roof sheeting or cladding could be installed, and that this requirement be maintained 6 until the whole of the girder ring had been completed. Despite these challenges it is worth re- cording that the sequencing and program- ming of the work was sufficiently precise to require only minimal adjustment to the last truss to complete the installation. The fabric roof cladding spanning between the trusses was erected by spe- cialised erectors. The roof sheeting also required specialist installation teams who had received training in erection and abseiling techniques. These teams had been recruited from locally-based labour and, through this project, they acquired specialist abseiling and other skills which they could use elsewhere in the industry.

Civil Engineering | December 2010 57 7

Due to the many complexities, prac- (b) the demolishing or relocation of ex- be constructed below the level of the tical completion was achieved some six isting structures, and (c) the diversion and lake, and therefore certain mitigation months later than had originally been relocation of the existing box storm water measures, such as determining flood planned. The stadium lost its right to culvert that drained the North End Lake. paths and overland storm water routing, host the Confederation Cup in 2009, not The earthworks related to the ex- had to be taken to ensure that the ex- because the stadium was incomplete, but cavation of the stadium bowl and the cavations were not flooded during an rather because of the risk of being late and construction of the stand platforms. A extreme storm event. the need to consolidate all the matches to total of 122 203 m³ of cut material was The lake had to be lowered by ap- be within a reasonable commuting dis- taken away to spoil, with 103 210 m³ of proximately 1,2 m to enable critical tance. However, the British Lions tour of imported fill material placed and com- storm water components to be removed in June/July 2009 included a pacted to form the north, east and south and new storm water infrastructure to match played against the stands. Of note is the fact that the spoil be constructed. All stakeholders and at the NMB Stadium. site was located at the quarry where organisations that use the lake for re- the quartzitic fill material was sourced, creational purposes had to be consulted BULK EARTHWORKS resulting in trucks travelling fully laden before the water level could be lowered. In May 2006 the joint venture between in both directions. The process of lowering the lake and consulting engineering firms Goba, returning it to its normal operating level Izizwe and Iliso was appointed to com- NORTH END LAKE was done in a shorter period of time plete the design and implementation of The influence of the North End Lake than had been anticipated. Work Package 5. Work Package 5 entailed on the construction was significant. A full drainage analysis of the planning of (a) the bulk earthworks, The pitch level of the stadium would the stadium was undertaken by a

58 Civil Engineering | December 2010 7 The backlit membrane surfaces of the roof position on the work-shop geometry make the stadium widely visible at night and then connected with the rest of the girder. Connection plates with slightly piles were cast in-situ concrete piles with varied hole patterns were implemented reinforcement of up to 8 Y32 per cage. to accomplish this. After the calibration The majority of the piles were designed to of the girder and the pre-stressing of the resist vertical compressive forces ranging bolted connections the support of the from 3 500 kN to 10 500 kN. Other piles girder tip was lowered and the deforma- were also designed to resist tensile forces tion at the girder tip was checked. At of up to 10 500 kN. the same time the secondary structure of curved tubes was assembled and cali- ROOF brated for the aluminium cladding. With The silhouette of the stadium is marked the help of taut lines the relative height by the structure of the girders, which are between the purlins was measured to arranged to point towards the center of limit the unevenness of the cladding. The the stadium. The girders taper towards Y-columns were also bolted before being the bottom where they ‘grow onto’ the lifted into place. columns of the multi-storied colonnade The window of operation for the that wraps around the entire stadium. 500 t caterpillar crane was limited by the The structural roof elements (girders) maximum wind speed of 10 m/s. As such were all pre-assembled in a jig at ground wind speeds occur daily in Port Elizabeth, level, surveyed for tolerance compliance often already before noon, the erection of and then installed. The 55 t mass ele- the girders occurred mostly in the early ments were manufactured to very high hours of the morning. The installation of tolerances to enable the structure to be the aluminum cladding proved equally erected in this manner. challenging in these windy conditions. The roof cladding terminates be- Calm weather conditions were also fore the façade to provide a wind-tight required for the unrolling of the mem- connection of the roof to the façade, brane to the preliminary anchorages. The without requiring additional provisions. membrane bales were rolled out on a tem- The roof acquires its remarkable form porary net of tension straps and secured from the alternating arrangement of with over-laying straps to prevent lift-off the girders and the membrane surfaces until it had been sufficiently anchored. spanned in-between. Port Elizabeth is known as the ENVIRONMENTAL CONDITIONS ‘Windy City’. Therefore, besides rain pro- Situated on the coast of the Indian tection, much value was placed on per- Ocean, Port Elizabeth belongs to a group fect wind protection. A high roof edge, as of places that has some of the highest well as the reduced roof depth, mirrors recorded normative exposure to corro- specialist geotechnical engineer on behalf these requirements. The effectiveness of sion in the world. High temperatures, of BKS (the Principal Agent). PD Naidoo the derived geometry was tested using a in combination with humidity and & Associates were then called upon to wind tunnel and evaluated according to a prevalent coastal parallel winds, which design a subsurface drainage system comfort study. carry salt from the coast-line ocean spray below the entire west stand of the stadium In order to not interfere with the across long distances, result in steel cor- to relieve the area of surplus water. work on and around the playing field, the rosion rates of 100 to 300 μm/a. These pre-fabricated girders had to be installed conditions set the highest requirements PILING entirely from the outside of the stadium. for corrosion protection. A Joint Venture comprising Iliso The pre-fabrication of the girders was For corrosion protection, high grade Consulting, ARQ and Arcus Gibb was ap- performed on scaffolding, which was and very UV-resistant Polysyloxane were pointed by the NMB Metro to undertake equipped with individually adjustable employed. Movable parts were dual-layer the design and construction monitoring clamping saddles to accommodate the coated. In construction all gaps and areas of the foundation phase for the stadium. different girder geometries. After the difficult to reach were minimised and The geotechnical experts recom- calibration of the scaffolding, mobile single shear-plane bolted connections mended that cast in-situ augured piles cranes lifted the pre-fabricated units into were favoured. with enlarged bases be founded on very place, where they were bolted. The tip of stiff clay / very soft mud rock of the the girder was set in place as a single unit CONCLUSION Kirkwood formation. A total of 2 300 piles at the end. To compensate for the toler- The succsssful completion of the Nelson were installed in pile groups of up to 48 ances from fabrication and the bolt-hole Mandela Stadium, despite considerable piles per pile cap. The pile sizes ranged clearance of the connections, the girder challenges, represents a significant contri- from 355 mm to 610 mm in diameter. The tips were initially set in the specified bution to modern stadium architecture.

Civil Engineering | December 2010 59