Environmental Monitoring Report

Project Number: 38411-043 March 2018 Period: July – December 2016

IND: Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)- Project 2

Subproject: Ramial

Submitted by:

Project Management Unit (OIIAWMIP),

This report has been submitted to ADB by the Project Management Unit (OIIAWMIP), Bhubaneswar and is made publicly available in accordance with ADB’s Public Communications Policy (2011). It does not necessarily reflect the views of ADB. This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Orissa Integrated Irrigated Agriculture and Water Management Investment Program Consulting Services for “Institutional Strengthening and Project Management”

Department of Water Resources (DoWR) Project Management Unit (PMU) Orissa Integrated Irrigated Agriculture and Water Management Investment Programme (OIIAWMIP) – Project - 2 (ADB Loan No. 3265-IND) Draft SEMI- ANNUAL ENVIRONMENTAL MONITORING REPORT (Environmental Mitigation Measures Compliance Status & Monitoring of Select Parameters of Civil Works Packages in Project -2 under) Ramial Subproject

(July 2016 to December 2016)

July 2017 assisted by Institutional Strengthening and Project Management Consultants (ISPMC)

Hydrosult, Division of SNC- Lavalin Inc Environmental Monitoring Report December 2015 1

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

CONTENTS

No CONTENT Pg.No

List of Abbreviations

EXECUTIVE SUMMARY i to iv

1.0 INTRODUCTION 1 1.1 Project Background 1 1.2 Objective 1 1.3 Project Profile 1 2.0 IMPLEMENTATION STATUS AND EVALUATION 4 3.0 ENVIRONMENTAL MONITORING PROCEDURE REVIEW 4 4.0 ENVIRONMENTAL COMPLIANCES 4 4.1. Compliance Status with National / State / Local statutory 4 Authorities 4.2. Compliances Status on EMP Implementation – Ramial 8 Subproject 4.2.1 Ramial Subproject 8 4.2.1.1 Environmental Monitoring 9 4.2.1.2 Plantation 11 4.2.1.3 Consultation / Focus Group Discussions 11 4.2.1.4 Grievance Mechanism 12 5.0 INSTITUTIONAL ARRANGEMENTS 12 6.0 COMPLIANCES STATUS OF PREVIOUS EMR– RAMIAL 14 SUBPROJECT 7.0 COMPLIANCES WITH LOAN COVENANTS 16 8.0 CONCLUSIONS 17 List of Tables List of Annexure Photographs

Environmental Monitoring Report – Ramial Sub Project July 2016 2

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

List of Tables

Table 1 Showing Sub Project Status as on 31 December 2016 – Contract Package wise Table 2 Details of working permission in forest area Table 3 Details of Tree cutting for Ramial subproject – contract package wise Table 4 Quarry material vendor details for Ramial subproject – contract package wise Table 5 Details of Borrow Earth Approvals for Ramial Subproject - Contract package wise Table 6 Details of Labour Licences for Ramial subproject – contract package wise Table 7 Details of Insurances for Ramial Subproject – contract package wise Table 8 Compliance Status with EMP for Ramial Subproject - Contract Package wise Table 9 Details of Environmental Monitoring Table 10 Showing the status of plantation in Ramial subproject Table 11 Compliance Status from the Previous EMR Contract wise – Ramial Subproject Table 12 Compliances on Loan Covenants

Environmental Monitoring Report – Ramial Sub Project July 2016 3

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

List of Annexes

Environmental Mitigation Measures Compliances Status & Monitoring of Select Parameters at Subproject Level and By Civil Work Package wise)

Annex. No Details Ramial Subproject Annexure 1 Letter from DFO for Working Permission in Forest Areas

Annexure 2 Letter from DEIAA for exemption of Environmental Clearance for borrow earth – District Annexure 3 Compliance Status of Environmental Mitigation Measures adopted by Civil Works Contractors for CW-NCB – RML-01 Annexure 4 Compliance Status of Environmental Mitigation Measures adopted by Civil Works Contractors for CW-NCB –RML-03 Annexure 5 Compliance Status of Environmental Mitigation Measures adopted by Civil Works Contractors for CW-NCB –RML-04

Annexure 6 Compliance Status of Environmental Mitigation Measures adopted by Civil Works Contractors for CW-NCB –RML-05

Environmental Monitoring Report – Ramial Sub Project July 2016 4

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

List of Abbreviations

$ US. Dollar % Percentage ADB Asian Development Bank A.E Assistant Engineer BOQ’s Bill of Quantities C Centigrade CAD Command Area Development CFE Consent for Establishment CFO Consent for Operation CO Community Organisers CTA Component Technical Assistance CW Civil Works DDR Due Diligence Report DEIAA District Environment Impact Assessment Authority D.S.L Dead Storage Level DG Diesel Generator DoWR Department of Water Resources Dy.SIO Deputy Sub project Implementation Officer EARF Environmental Assessment and Review Framework E.E Executive Engineer EMP Environmental Management Plan EMR Environmental Monitoring Report ERM Extension, Renovation and Modernization FB Foot Bridge ha / Ha Hectares HMP Hot Mix plant HR Head Regulator HSD High Speed Diesel IA Implementing Agency IEE Initial Environmental Examination IS Indian Standard ISPM Institutional Strengthening and Project Management ISPMC Institutional Strengthening and Project Management Consultants IWRM Integrated Water Resources Management J.E Junior Engineer KM/ km/ Km Kilo meters Km2 Square Kilometers l Litres LHR Left Head Regulator m Meters M3 Cubic Metre MFF Multi-tranche Financing Facility Mg Milli grams MCM Million cubic meters mm Millimetres NCB National Competitive Bidding NGO Non Governmental Organisation NR Not Required NTU Nephelometric Turbidity Unit NWP National Water Policy OIIAWMIP Orissa Integrated Irrigated Agriculture and Water Management Investment Program PD Project Director PIM Participatory Irrigation Management PMU Project Management Unit PP Pani Panchayat PPME Project Planning and Monitoring Evaluation PPSU Pani Panchayat Support Unit PPTA Project Planning and Technical Assistance RD Reduced Distance ROW Right of Way Sec Seconds SIO’s Sub- Project Implementation Officers SST Support Service Team VRB Village Road Bridge WALMI Water and Land Management Institute WMM Wet Mix Macadam WUAs Water Users Association

Environmental Monitoring Report – Ramial Sub Project July 2016 5

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

PREFACE

This Environmental Monitoring Report (EMR) for the Ramial Subproject presents the salient features demonstrating the compliance status of environmental mitigation measures, environmental monitoring of selected parameters for the civil work contractors. It is in compliance with Loan Covenants of Project -2 of the OIIAWMIP for the period of July 2016 to end of December 2016. The report has been prepared for the PMU with guidance , support and assistance of CAD PIM Directorate (O & M) and Institutional Strengthening and Project Management Consultants (ISPMC).

This report represents Compliance with Environmental Safeguard Policy of ADB which includes preparation of Initial Environmental Examinations (IEE) reports -prepared for Project -2, Environmental Monitoring Plans (EMP) preparations and implementation monitoring with periodic monitoring reports. The report preparation, field activities for data acquisition was planned and undertaken with PMU/SIOs supported by ISPMC.

This document has been prepared using all available subproject chronological and current data / information, with necessary compilations for presentation; and analysis as deemed practicable to comply with Loan Agreement Schedule 5, Paras 5, 10, 11 and 14 item for the OIIAWMIP project – which requires PMU to submit progress report on the EMP implementation as part of ADB’s Safeguards Policy Statement (2009).

July 2017

ISPMC

Environmental Monitoring Report – Ramial Sub Project July 2016

6

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

EXECUTIVE SUMMARY i. “Orissa Integrated Irrigated Agriculture and Water Management Investment Program” (OIIAWMIP) is a multitranche financing facility (MFF) project with Asian Development Bank (ADB) assistance. Department of Water Resources (DoWR) had completed Project-1 implementation and Project -2 is under progress. Project 2 of the MFF implementation has commenced and will be closed in September 2018. It will modernize irrigation infrastructure of 4 major( Machhagaon, Pattamundai, HLC Range -1 and MCII) and 3 medium( Ramial, Kanjhari and Kansbahal) subprojects and 750 minor lift irrigation (MLI) schemes in selected river basin of . It will also strengthen 169 WUAs in improved land and water management for increase agricultural production, and restore saline embankments in 12 segments covering about 57 kilometres.

ii. The Executing Agency (EA) is the Department of Water Resources and the Implementing Agency (IA) is Project Management Unit (PMU). PMU / Subproject Implementation Officers (SIOs) undertake civil works through Contractors selected through National Competitive Bidding (NCB).

iii. The “Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP) under Project- 2 includes Irrigation sub-projects and Saline Embankments which are classified as “Category B” according to the Environment Policy (2009) of the Asian Development Bank (ADB). An environmental assessment and review framework (EARF) was also prepared to guide the environmental assessment of the subprojects. An Initial Environmental Examination (IEE) reports were prepared for the proposed sub-projects. Environmental Management Plan (EMP) is part of the IEE. EMP implementation responsibility mostly lies with the Contractors.

iv. Under Project -2, 6 sub-projects out of 7 subprojects civil works commenced {three major subprojects (Machhagaon, Pattamundai and HLC Range-1); three medium (Ramial, Kanjhari and Kansbahal)} and 10 saline embankments out of 12 have commenced civil works, the implementation of EMP was Contractors responsibility. EMP is part of civil work contract packages executed by Contractors, but not with the civil works carried out by Pani Panchayat (for irrigation subprojects only). The semi – annual Environmental Monitoring Report (EMR) is prepared for each subproject, the present EMR report pertains to the Ramial subproject.

v. The Ramial sub project was divided into 5 contract packages and one sub-minor package implemented by Pani Panchayat. Out of the 6 contract packages (including sub- minors) by this period 5 contract packages (CW- NCB- RML-01 and CW- NCB- RML-02 both clubbed to one package CW- NCB- RML-01, CW- NCB- RML-03, CW- NCB- RML-04 & CW- NCB- RML-05) have signed the agreement. While Contract package CW- NCB- RML-01 & CW- NCB- RML-02 was clubbed into one contract package and agreement signed on 22 February 2016; CW- NCB- RML-03 contract signed on 4 January 2016 ; CW- NCB- RML-04 contract package agreement done on 12 April 2016 and & CW- NCB- RML-05 agreement signed on 24 December 2016,while the rest of sub-minors are yet to be awarded.

vi. The objective of this report is to assess:(i) compliances of the project with the requirements of ADB’s environmental safeguards contained in ADB’s Environment Policy, (ii) Environmental Monitoring Report – Ramial subproject July 2017 i

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

the status of obtaining statutory clearances by the Contractors as per the national environmental laws, Govt. of and (iii) status of implementation of mitigating measures suggested in the EMP and difficulties encountered during the stages of implementation. The report findings also assist in formulation of corrective actions by PMU that may improve EMP implementation adjustments and in suggesting mechanism for effective supervision during Project-2 implementation

vii. Monitoring and reporting on EMP issues was going well there was no change in the scope of work from the approved contract package.

viii. During the early stages of the project, the SIO staff and contractor representatives at site were explained by ISPMC, Environment Specialist on the environmental safeguard requirements and the required measures that are needed at site along with necessary on job – training / sub project level trainings (on national environmental law requirements, environmental safeguards requirements of ADB, contractual clauses for EMP implementation. PMU also monitoring overall project progress and evaluating project benefits, social and environmental impacts.

ix. As part of capacity building program few persons (SIO staff and Contractors) were trained in the EMP implementation, environmental safeguards and an environmental Check list was introduced to the Contractors through PMU for effective monitoring.

x. The environmental monitoring report preparation for the implementation period i.e. from July 2016 to end of December 2016 is based on the monthly EMP checklist submitted by Contractors through SIO staff, feedback obtained from SIO staff especially Junior engineers inputs during day to day field activities, random field checking of work sites and verification and validation of information submitted by the Contractors and feedback from villagers through consultations by ISPMC Environment specialist form the basis for preparation of the report.

xi. The Ramial sub project doesn’t require any environmental clearances from the State Pollution Control Board or Ministry of Environment & Forests since this subproject is an existing one, no new canals were formed and only strengthening of existing systems were taken up. The canals are not located in the Coastal Regulation Zone, no clearance were needed. The subproject is a pre 1980 project where some of the existing canals existing right of way located in the forest areas, no additional area is needed, hence SIO has written for Working Permission to Forest Department and it is in progress, however since the existing canals are old and restoration of canals are undertaken with in the existing ROW, there is no objection from the Forest Department as per SIO staff.

xii. The Contractors have not established any plants under the sub project. Materials are purchased from the vendors only.

xiii. Overall the EMP implementation was partially satisfactory in all the contract packages due to initial delays in documentation / environmental monitoring and testing.

xiv. As per the environmental assessment and review framework prepared for the project, it states that DoWR wants the surface and ground water quality monitoring to assess

Environmental Monitoring Report – Ramial sub project July 2017 ii

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

the source of impacts of upstream urbanization and industrialization and to check the level of deterioration due to increased application of fertilizers and pesticides. The suggested monitoring parameters to the contractor have a dual objective to generate the data base for water quality of WRD and to assess the impacts of construction by the Contractors by monitoring turbidity. Silt analysis was also incorporated to ensure quality of silt before disposal. The generated environmental data will be utilised for Integrated Water Resource Management Planning. The SIO & Contractors are responsible for the environmental monitoring and the analysis would be carried out by the accredited laboratories.

xv. The environmental monitoring i.e. testing of surface water and silt was carried out during the month of June 2016, during July to December 2016 there was limited physical activity due to release of water into the canal system for cultivation. Hence SIO and Contractors were requested to adhere to the suggested frequency and undertake environmental monitoring immediately.

xvi. In the subproject, SIO has not received any grievances and no grievances were noted during consultations also.

xvii. A compliance review indicates full compliance with Loan Covenants. Table 12 shows the environmental safeguards assurances and the status of compliances. Conclusions xviii. Overall, EMP implementation is rated “Partially Satisfactory” in all the contract packages Consultations reveal beneficiaries (local communities) are generally happy with the construction program. During this period i.e. between July to December 2016 there was no physical activity due to release of water in the canal for cultivation. No adverse environmental impacts were observed and no grievances noted. The subprojects, after restoration of the canals shall increase economic benefits in the sub project area. xix. Awareness and Capacity development at PMU/SIOs commenced early in the project and included training on ADB environment policy and its implementation. Orientation programs on Environmental safeguards implementation was conducted during January and February 2016 which involves staff and Contractors of Kanjhari subproject also. Topics included ADB safeguards, environmental laws, contract clauses, and reporting needs xx. Subsequently subproject level orientation program was conducted on 24 June 2016 at to overcome the short comings; around 14 persons including the Environment Specialist was present. The key participants were SIO & Contractors staff. xxi. SIO has initiated for obtaining working permission from State Forest Department, however he shall ensure that the clearance shall be available before the coming working season. xxii. EMP implementation timelines have been met in general. However, EMP implementation by Contractors is rated partially satisfactory in all the contract packages with only minor initial delays noted by contractors, mainly due to understanding of the guidelines, contractual constraints and experience of contractor’s staff.

Environmental Monitoring Report – Ramial sub project July 2017 iii

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

xxiii. Contractor’s responsiveness is increasing and aided in EMP successful implementation as a Monthly Environmental Check was introduced to monitor all subprojects. xxiv. The Contractors shall ensure necessary pending insurances at the earliest as per provisions of the contract, however SIO has written to the contractors for early compliances. xxv. During the period July 2016 to December 2016 there was no physical activity due to release of water into the canal water system for rabi cultivation, the SIO / Contractors had undertaken environmental monitoring i.e surface water and silt during June 2016. The SIO had requested contractors to undertake environmental testing i.e ., testing of surface water, ground water, silt, soil and noise as per the suggested frequency. xxvi. SIO had requested Contractors to provide safety gear/equipment regularly which was not utilized adequately by labour because of discomfort, as observed and informed during monitoring visits, hence there is scope for improvement on the Contractors side to ensure and encourage the labour for a regular use. xxvii. Integrated Borrow area management approach by SIO’s (borrow area test for soil classification, OMC and MDD tests along with agreement with the landowners, obtaining Environmental Clearance from DEIAA/ DEAC) will ensure easy Contractors compliances, as a result this will improve the borrow area management. xxviii. SIO had requested Contractor to conduct AIDS awareness program periodically and the contractor shall ensure that they conduct in the next working season. xxix. The EMR data acquisitions may be archived as information and baseline for use in future DOWR environmental program management options and as anticipated policy enforcement changes evolve over time.

Environmental Monitoring Report – Ramial sub project July 2017 iv

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

1.0 INTRODUCTION 1.1 Project Background 1. “Orissa Integrated Irrigated Agriculture and Water Management Investment Program” (OIIAWMIP) is a multitranche financing facility (MFF) project with Asian Development Bank (ADB) assistance. It aims to enhance the productivity and sustainability of the existing irrigation schemes in the four northern river basins and a part of Mahanadi delta. This will involve renovating irrigation infrastructure, installing participatory irrigation management (PIM) systems with Pani Panchayats (PP) / water users associations (WUAs), and empowering WUAs as a cohesive platform for irrigation operation and maintenance (O & M) and agriculture development. The OIIAWMIP will also strengthen the institutional basis for PIM and integrated water resource management (IWRM) with management reforms and capacity strengthening of the relevant institutions.

2. Department of Water Resources (DoWR) had completed Project-1 implementation and Project -2 are under progress. Project 2 of the MFF implementation has commenced and will be closed in September 2018. It will modernize irrigation infrastructure of 4 major( Machhagaon, Pattamundai, HLC Range -1 and MCII) and 3 medium( Ramial, Kanjhari and Kansbahal) subprojects and 750 minor lift irrigation (MLI) schemes in selected river basin of Odisha. It will also strengthen 169 WUAs in improved land and water management for increase agricultural production, and restore saline embankments in 12 segments covering about 57 kilometers.

3. The Executing Agency (EA) is the Department of Water Resources and the Implementing Agency (IA) is Project Management Unit (PMU). PMU / SIOs undertake civil works through Contractors selected through National Competitive Bidding (NCB).

4. The “Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP) under Project- 2 includes Irrigation sub-projects and Saline Embankments which are classified as “Category B” according to the Environment Policy (2009) of the Asian Development Bank (ADB). An environmental assessment and review framework (EARF) was also prepared to guide the environmental assessment of the subprojects. An Initial Environmental Examination (IEE) reports were prepared for the proposed sub-projects. Environmental Management Plan (EMP) is part of the IEE. EMP implementation responsibility mostly lies with the Contractors.

1.2 Objective 5. The objective of this report is to assess: (i) compliances of the project with the requirements of ADB’s environmental safeguards contained in ADB’s Environment Policy, (ii) the status of obtaining statutory clearances by the contractor as per the national environmental laws, Govt. of India and (iii) status of implementation of mitigating measures suggested in the EMP and difficulties encountered during the stages of implementation. The report findings also assist in formulation of corrective actions by PMU that may improve EMP implementation adjustments and in suggesting mechanism for effective supervision during Project -2 implementation.

1.3 Project Profile 6. Under Project -2, 6 sub-projects out of 7 subprojects civil works have commenced (three major subprojects Machhagaon, Pattamundai and HLC Range-1); three medium (Ramial, Kanjhari Environmental Monitoring Report – Ramial subproject July 2017 1

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

and Kansbahal) and 10 saline embankments out of 12 have commenced civil works, the implementation of EMP was Contractors responsibility. EMP is part of civil work contract packages executed by Contractors, but not with the civil works carried out by Pani Panchayat.

7. In the present report, EMP implementation status of Ramial subproject is presented since July 2016 to end of December 2016. The Table 1 Shows the project components contract package wise, starting date of implementation, Scheduled date of completion etc., along with physical progress for each contract package in Ramial sub project under Tranche -1.

8. The Ramial sub project was divided into 5 contract packages and one sub-minor package to be implemented by Pani Panchayat. Out of the 6 contract packages (including sub-minors) by this period 5 contract packages (CW- NCB- RML-01 and CW- NCB- RML-02 both clubbed to one package CW- NCB- RML-01, CW- NCB- RML-03, and CW- NCB- RML-04 & CW- NCB- RML-05 ) have signed the agreement. While Contract package CW- NCB- RML-01 & CW- NCB- RML-02 was clubbed into one contract package and agreement signed on 22 February 2016; CW- NCB- RML- 03 contract signed on 4 January 2016; CW- NCB- RML-04 contract package agreement done on 12 April 2016, & for contract package CW- NCB- RML-05 agreement signed on 24 December 2016 while the rest of sub-minors are yet to be awarded.

Environmental Monitoring Report – Ramial sub project July 2017 2

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

Table 1 Showing Ramial Sub Project Status as on 31st December 2016 – Contractor Package wise Contract Sub –Project Title/ Components/ Date of Contract Date of Duratio Earth work Concrete Slope Financial Package Contractor Agreement Commence Completio n as per progress in work Protection progress ment date n Contrac % progress Works in % t in % progress in % CW-NCB-RML REM of left main canal, selective -01 (CW-NCB- lining including improvement/ 24 RML-02 modernisation of structures. 22-02-2016 22-02-2016 21-02-2018 45.862 62.938 Nil 56 Months clubbed with Contractor: GVV Construction –RML-01) Rehabilitation, Extension & Modernisation of Right Main 24 CW-NCB-RML Canal selective Lining and 04.01.2016 04.01.2016 03.01.2018 48.41 69.53 Nil 59 -03 Kandhara Distributary canal Months Lining including all structures Contractor: Munna Pani Rehabilitation, Extension & 12.04.2016 12.04.2016 11.04.2018 24 55 70 Nil 44 Modernisation of Distributary Months CW-NCB-RML- canal and selective Lining 04 including all structures Contractor: Munna Pani REM of minor canals of Ramial 24.12.2016 24.12.2016 23.03.2018 15 - - - Contracto irrigation sub-project including Months r under CW-NCB-RML improvement/ modernisation of mobilizati -05 structures. on Contractor: Munna Pani Various (98) Construction of Sub-minor canals Agreement ------(construction and associated structures of not done of Sub-minors Ramial irrigation system. of Ramial

Environmental Monitoring Report – Ramial sub project July 2017 3

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

2.0 IMPLEMENTATION STATUS AND EVALUATION 9. In the In Ramial Subproject civil works award of contract for 4 contract packages took place, out of which 3 contract packages was awarded during January & April 2016 and one contract package was awarded during December 2016. While sub minors works implemented by Pani Panchayat are yet to commence. Implementation of Environmental Management Plans is part of Contractors agreement for Contract packages but not for works implemented by Pani Panchayat. Monitoring and reporting on EMP issues was going well there was no change in the scope of work from the approved contract package.

3.0 ENVIRONMENTAL MONITORING PROCEDURE REVIEW 10. To comply with the Environmental Management Plan (EMP) recommendations and Environmental Statutory requirements as per the Initial Environment Examination (IEE) report of the project and loan covenants. Environment Specialist was assisting and advising the PMU, had reviewed the situation of the EMP implementation along with SIO staff of the ongoing contract packages in the subproject and environmental monitoring reports are being prepared as part of Environmental monitoring for the sub–projects under Projects -2 which were under implementation (construction stage) after award of contracts.

11. During the early stages of the project, the SIO staff and contractor representatives at site were explained on the environmental safeguard requirements and the required measures that are needed at site along with necessary on job – training / sub project level trainings (on national environmental law requirements, environmental safeguards requirements of ADB, contractual clauses for EMP implementation. PMU also monitoring overall project progress and evaluating project benefits, social and environmental impacts. As part of capacity building program few persons (SIO staff and Contractors) were trained in the EMP implementation, environmental safeguards and an environmental Check list was introduced to the Contractors through PMU.

12. The environmental monitoring report preparation for the implementation period i.e. from July 2016 to end of December 2016 is based on the monthly EMP checklist submitted by Contractors through SIO staff, feedback obtained from SIO staff especially Junior engineers inputs during day to day field activities, random field checking of work sites and verification and validation of information submitted by the Contractors and PP consultations by ISPMC Environment specialist form the basis for preparation of the report.

4.0 ENVIRONMENTAL COMPLIANCES 13. The environmental compliances are in accordance with the statutory requirements of National, State level authorities, as per ADB safeguard requirements and EMP requirements which were made part of Contractors agreements. The Status of compliances is described below:

4.1. Compliance Status with National / State / Local statutory Authorities 14. The Initial Environmental Examination (IEE) documents have identified the Environmental Regulations and Legislations applicable to the project and the clearances/NOCs to be obtained at various stages of construction. The EMPs detail out the mitigation measures for potential negative impacts. However, the Ramial sub project doesn’t require any environmental

Environmental Monitoring Report – Ramial sub project July 2017 4

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

clearances from the State Pollution Control Board or Ministry of Environment & Forests since all the subprojects were existing one, no new canals were formed and only strengthening of existing systems were taken up. The canals are not located in the Coastal Regulation Zone, no clearance were needed.

A. Working Permission from State Forest Department

15. The subproject is a pre 1980 project where some of the existing canals existing right of way located in the forest areas, no additional area is needed, hence SIO has written for Working Permission to Forest Department.

Table 2 Details of Working Permission for Forest Areas Name of the Subproject Details of Working Permission for Areas

Ramial E.E has written letter to DFO Dhenkanal on 09/05/2016 and in reply DFO has written letter to Asst. Conservator of Forest, Dhenkanal Division on Dt.24/05/2016. Working permission is under progress and Since these are old canal systems physically there is no objection from Forest Department also. Letter enclosed as Annexure -1

B. Tree Cutting Permission

16. In the IEE document identified there are trees that are present within the existing ROW of embankments out of which some trees might require felling, to the possible extent tree cutting shall be avoided but if any tree needs to be removed shall be done with State Forest Department Permission. The details of tree cutting are provided in Table 3 below:

Table 3 Details of Tree cutting for Ramial subproject – Contract Package wise Contract Contractor No. of trees No. of No of trees Details & Package identified as Per Trees felled or cut Status of IEE identified Forest Dept. to be Cut Permission as per site conditions CW-NCB- GVV No. not identified NR Nil NR RML -01 Construction (CW-NCB- RML-02 clubbed with RML- 01) CW-NCB- Munna Pani No. not identified NR Nil NR RML-03 CW-NCB- Munna Pani No. not identified NR Nil NR RML-04

Environmental Monitoring Report – Ramial sub project July 2017 5

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

Contract Contractor No. of trees No. of No of trees Details & Package identified as Per Trees felled or cut Status of IEE identified Forest Dept. to be Cut Permission as per site conditions CW-NCB- Munna Pani No. not identified NR Nil NR RML-05 (Note: NR – Not required)

C. Consent From State Pollution Control Boards:

17. The Contractor doesn’t require any specific environmental clearances from the Odisha State Pollution Control Board since they have not established any crusher/ HMP/ WMM plant etc. The contractors are purchasing the materials (aggregates) from the vendors only details provided in Table 4; they haven’t taken any quarry on lease nor were undertaking any blasting operations.

Table 4 Quarry material details for Ramial subproject – Contract package wise Contract Contractor Stone products Sand Morrum / other Package products

CW-NCB-RML - GVV Construction Purchased from Purchased Purchased from 01 (CW-NCB- Vendor* from Vendor* Vendor** RML-02 clubbed with RML-01) Munna Pani Purchased from Purchased Purchased from CW-NCB-RML- 03 Vendor* from Vendor* Vendor** Munna Pani Purchased from Purchased Purchased from CW-NCB-RML- 04 Vendor* from Vendor* Vendor** CW-NCB-RML- Munna Pani Contractor is under mobilization 05 (Note: *- Vendor Details submitted by Contractor to SIO; ** - SIO requested Contractors for vendor details)

18. No HSD was stored at the camp in a bulk only limited quantity stored by the Contractors; the contractor was purchasing HSD from the vendor only. Vehicle fitness and Pollution under Control certificates were requested for effective implementation of works and vehicles were sent to nearby garages for repair work if required.

D. Environmental Clearance for Borrow Earth

19. The details of borrow earth approvals subproject wise are provided under Table 5 below.

Table 5 Details of Borrow Earth Approvals for Ramial Subproject – Contract package wise Contract Package Contractor No. of Borrow Details & Status of earth Patches Environmental Clearance approved by SIO from DEIAA CW-NCB-RML -01 GVV Cutting earth is DEIAA Dhenkanal has (CW-NCB-RML-02 Construction being used till

Environmental Monitoring Report – Ramial sub project July 2017 6

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

Contract Package Contractor No. of Borrow Details & Status of earth Patches Environmental Clearance approved by SIO from DEIAA clubbed with RML- now only 1 patch given exemption for 01) of land is used Environmental Clearance Munna Pani No Borrow earth CW-NCB-RML-03 vide letter no. 709/ dated used 27.06.2017 enclosed as Munna Pani 7 patches used CW-NCB-RML-04 Annexure-2 and follow up for Borrow earth Munna Pani Contractor yet to with Tahasildhar in CW-NCB-RML-05 commence work progress

E. Status of Labour Licence

20. The details of Labour licenses subproject wise are provided under Table 6 below.

Table 6 Details of Labour Licences for Ramial subproject – Contract package wise Contract Package Sub –Project Title/ Labour Licence Obtained Components/ (Yes / N0) Contractor CW-NCB-RML -01(CW- GVV Construction YES (Provided*) NCB-RML-02 clubbed with RML-01) CW-NCB-RML-03 Munna Pani YES (Provided*) CW-NCB-RML-04 Munna Pani YES (Provided*) CW-NCB-RML-05 Munna Pani Contractor Requested (Note: * Contractor provided, details available with SIO)

F. Details of Insurance

21. The details of insurances undertaken subproject wise is provided in Table 7 below.

Table 7 Details of Insurances for Ramial Subproject – Contract package wise Contract Package Contractor All Risk Employee Accident Remarks Insurance Compensation Insurance Obtained Obtained Obtained (Yes / N0) (Yes / N0) (Yes / N0) CW-NCB-RML - GVV Construction YES YES Contractor - 01(CW-NCB- (Provided*) (Provided*) requested RML-02 clubbed with RML-01) Munna Pani YES YES Contractor - CW-NCB-RML-03 (Provided*) (Provided*) requested

Munna Pani YES YES - Contractor CW-NCB-RML-04 (Provided*) (Provided*) requested Munna Pani Contractor Contractor Contractor CW-NCB-RML-05 requested requested

Environmental Monitoring Report – Ramial sub project July 2017 7

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

Contract Package Contractor All Risk Employee Accident Remarks Insurance Compensation Insurance Obtained Obtained Obtained (Yes / N0) (Yes / N0) (Yes / N0) requested

4.2. Compliances Status on EMP Implementation - Ramial Subproject

4.2.1 Ramial Subproject 22. The Ramial Subproject is covering 4 contract packages and sub minor packages are yet to be awarded. Out of the 4 contract packages all contract packages have been awarded by this period except sub-minor Packages. During July 2016 to December 2016 there was limited physical work in progress, as the canal water was released for kharif cultivation. The status of EMP implementation against different environmental components for each contract package is shown in Annexure 3 to 6.

23. Overall the EMP implementation is rated partially satisfactory in all the with only minor delays (testing of surface water, ground water and silt/ soil) noted by some contractors, mainly due to understanding of the guidelines, contractual constraints and experience of the contractors & SIO staff.

24. EMP implementation quality in each contract packages is rated on a 3-point scale (i.e. satisfactory, partially satisfactory and unsatisfactory). Ratings are assigned considering the degree of contractors compliance with EMP condition as determined by reports, periodic monitoring by SIO with ISPMC assistance. The definitions adopted for assessment of the EMP implementation quality ratings are: (i) “Satisfactory” (S) - when overall compliant with EMP; “Partially Satisfactory” (PS) mostly compliant with EMP; and “Un-Satisfactory” (NS)– when inadequately compliant with EMP”.

25. The EMP implementation rating is shown in Table 8. EMP implementation out of 3 contract packages, it is partially satisfactory in all the contract packages.

Table 8 Compliance Status with EMP for Ramial Subproject- Contract package wise

S.No Contract Package EMP Rating Observations / Remarks status (Satisfactory/ Partially (Yes/ Satisfactory/ No/ NR) Unsatisfactory) CW-NCB-RML -01(CW- • Mostly EMP complied. 1 Yes Partially Satisfactory NCB-RML-02 clubbed with RML-01) 2 Yes Partially Satisfactory • Mostly EMP complied. CW-NCB-RML -03

3 Yes Partially Satisfactory • CW-NCB-RML -04 Mostly EMP complied. Yes Contractor is under mobilization 4 CW-NCB-RML -05

Environmental Monitoring Report – Ramial sub project July 2017 8

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

4.2.1.1 Environmental Monitoring 26. During the design phase sub-project wise IEE’s were prepared incorporating EMP, to make EMP more effective WRD had incorporated Environmental testing and monitoring (Surface water, ground water and silt analysis) as part of environmental budget. As part of technical specification of Contractors BOQ Contractors shall adhere to the mitigation measures as stipulated in the IEE document. As per the environmental assessment and review framework prepared for the project, it states that DoWR wants the surface and ground water quality monitoring to assess the source of impacts of upstream urbanization and industrialization and to check the level of deterioration due to increased application of fertilizers and pesticides. The suggested monitoring parameters to the contractor have a dual objective to generate the data base for water quality of WRD and to assess the impacts of construction by the Contractors by monitoring turbidity. Silt analysis was also incorporated to ensure quality of silt before disposal. The generated environmental data will be utilised for Integrated Water Resource Management Planning. The SIO & contractors are responsible for the environmental monitoring and the analysis would be carried out by the approved laboratories.

27. The details of provisions under EMP as per IEE are detailed in Table 9 which also provides the number of locations against the proposed is also indicated. The analysis of the data is as follows:

Table 9 Details of Environmental Monitoring Environmental Suggeste Frequency No. of Locations Remarks Parameter d No. of and period of Env. Monitoring locations monitoring Carried out as per IEE as Per IEE Surface water 6 Twice in a NIL SIO / Contractor Ground water 6 year before Nil requested to undertake Soil 6 construction Nil immediately as per the Silt 6 and after Nil suggested frequency Noise Monitoring Nil construction Nil requested to undertake after release of water in the canal -

4.2.1.1.1 Ground Water Quality Monitoring 28. The project -2 do not have a provision of providing tube wells in the on the sides of the canals. However in the subproject contractors had not drilled any tube wells under three contract packages for providing drinking water to his labour. However since he is using existing tube wells located near the camps, hence he was requested by SIO to undertake water quality testing from a accredited laboratories immediately, the results shall be included in the next monitoring report.

4.2.1.1.2 Surface Water Quality Monitoring 29. As per the Initial Environment Examination Report prepared for the subproject there is a provision for testing the surface water in 6 locations. The environmental testing budget was not part of contractor’s responsibility; however SIO had carried out testing from reservoir and one sample from RD 100m of Right main canal during June 2016. Though agreements were conducted between January and April 2016, the canal water supply was closed. Hence SIO had

Environmental Monitoring Report – Ramial sub project July 2017 9

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

undertaken during June 2016. The reservoir water shall act a reference of baseline information. The results of the analysis was presented in the previous EMR, during this period i.e. between July to December 2016 limited activity was in progress due to release of water in the canal system between 1st July to end of November 2016, hence limited work was in progress. However SIO and Contractors were requested to undertake surface water testing immediately adhering to the suggested frequency.

4.2.1.1.3 Soil Quality Monitoring 30. In the study area, the command area is dominated by three classes of soils.

• Khateibereni Soil series (Oxic Quartzite) Soils are dark yellowish brown, light textured and well drained, acidic in reaction and low in organic content. The soil is low in available nitrogen, moderate in available potash and low in available phosphorus. The soil is shallow and found in upper topography. The soil is not suitable for crop agriculture and is recommended for pasture development.

• Palasdangi Soil series (Fine Loamy) This soil series is yellowish brown in colour and loamy sand to sandy loam in composition and is well drained. The soil is acidic in reaction, low in organic content, has low phosphorus content and medium in nitrogen and potash content.. This soil is suitable for irrigated agriculture.

• Saala Series (Fine clayey). The soils are moderately permeable, acidic in reaction and high in organic content. They have high nitrogen and potash content and medium to high phosphorus content. The soils are highly suitable for irrigated agriculture.

31. The texture of this soil is sandy loam, silty loam; clay loam and heavy loam and it is very fertile in nature while the laterite soil is generally hard, infertile and acidic in nature.

32. However the soil samples adjacent to the canal embankment were to be tested as per the EMP provisions of the IEE however the SIO was not aware hence he was requested to undertake immediately.

4.2.1.1.4 Silt Quality Monitoring 33. Desiltation of canals are proposed now out of 4 contract packages only 3 packages are in force (Contract Package 1 & 2 merged in to a single package). Though IEE reports suggested for testing of 6 silt samples in the subproject. However SIO has undertaken testing of silt in 3 locations during the period covering one sample from each contract package.

34. The silt sample from contract package RML -01 was collected from Sasoposi RD 6.00km (Approx) of left main canal; for RML-03 it was collected from RD 5.00 km of Right main canal and for RML-04 it was RD 4.416 km of Kanpura Distributary. All the samples were tested during 23 June 2016. The results of the silt analysis is presented in the previous EMR. Since there was no desiltation activity during this period i.e. due to release of canal water, hence SIO & Contractor was requested to undertake immediately.

Environmental Monitoring Report – Ramial sub project July 2017 10

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

4.2.1.1.5 Noise Quality Monitoring 35. The ambient air quality standards in respect of noise in the project area for each contract package under Ramial were to be monitored on an hourly basis for each contract package which is under implementation. The noise testing was neither part of IEE nor BOQ. However after the ADB mission reviews visit during May 2016 it suggested and accordingly SIO had requested Contractors for undertaking the noise monitoring at the earliest. To ascertain the need for mitigative measures to be adopted by Contractors during construction period i.e. Noise emanating from vehicular movements, blowing of horns, and operation of construction equipment like concrete mixer, movement of construction equipments and sound producing instruments etc., were measured for a day during day and night.

36. The noise monitoring reports for each contract package shall be enclosed in the next environmental monitoring report.

37. However, the present work locations are away from the residential areas where the noise levels get diluted hence no impact of noise anticipated, in addition contractors were also instructed to do maintenance of the vehicle and equipments which will also reduce the noise levels further. So Contractor was instructed to adhere to the ambient air quality standards specified under the rules and shall undertake measures for abatement of noise including use of silencer for the vehicle if necessary and sending equipments for maintenance regularly.

4.2.1.2 Plantation Details

38. The IEE has identified that there are some trees within the existing right of way of the embankments, which might get affected due to construction and also to enhance the aesthetics of the area a provision for plantation has been indicated for in the IEE report. The contractor BOQ doesn’t have a provision for Plantation (Table -10). However at present no trees were cut and no plantation was carried out in the subproject areas, however if required as part of compensatory plantation the DoWR shall request State Forest Department in undertaking plantation where ever surplus ROW is available after completion of civil works

Table 10 showing the Status of Plantation in the Ramial subproject Contract Package No. of Plants Plantation Remarks proposed in carried out till IEE date CW-NCB-RML -01(CW-NCB-RML- Nil Nil - 02 clubbed with RML-01) CW-NCB-RML-03 Nil Nil - CW-NCB-RML-04 Nil Nil - CW-NCB-RML-05 Nil Nil -

4.2.1.3 Consultation (Focus Group Discussion) with Villagers 39. The public consultations were conducted in three villages (Sasaposi, Patabeda and Kanpura villages) that are located in the Ramial subproject, during June 2016 and the details were submitted in the previous EMR report. Since there was not much physical activity the consultations will be undertaken during the next EMR report preparation.

Environmental Monitoring Report – Ramial sub project July 2017 11

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

4.2.1.4 Grievance Mechanism

40. The subproject is part of Project -2 of investment program (OIIAWMIP) which has established a Grievance Redress Mechanism (GRM). In addition, there is an arrangement at the district level which provides a grievance mechanism whereby a grievance cell was located at the Collector’s office. The subproject, SIO has not received any grievances and no grievances were noted during last consultation consultations (details of consultations provided in section 4.2.1.3). If any minor grievances noted during SIO visits are being addressed by SIO staff.

5.0 INSTITUTIONAL ARRANGEMENTS 41. The following are the key agencies involved in the implementation of the EMP:

42. DoWR is the Executing Agency for OIIAWMIP. A Project Management Unit (PMU) has been established within the CAD&PIM Directorate with a Project Director of the rank of Chief Engineer operating under the overall guidance of Special Secretary cum Director CAD - PIM with the overall responsibility of program implementation. Chief Engineer cum Project Director, PMU will exercise the powers vested by the OPWD code for execution of all civil works.

43. At the field level Sub-project Implementation Offices (SIO) have been formed to implement the program. For Major irrigation sub-projects the concerned Superintending Engineer is the Sub- project manager and the concerned Executive Engineer is the Sub-project manager for Medium irrigation Sub-projects. The Sub-Project Manager, who is a Superintending Engineer (SE) for major irrigation systems and an EE for medium schemes, will manage the Technical Cell as well as monitor and guide the CAD and PP Support Cells for effective integration and coordination of the sub-project activities, under the support and guidance of PMU, EIC (P&D), and ISPM Consultants provided through regular PMU-SIO meetings.

44. DoWR for effective implementation of Project-2 sub-projects under OIIAWMIP proposes to create one Circle, four Divisions, 12 Sub-Divisions under the Chief Engineer – cum – Project Director, PMU.

Circle: One Superintending Engineer S.E will be in charge of circle office. He will be responsible for the managing the Technical Cell as well as monitor and guide the CAD and PP Support Cells for effective integration and coordination of the sub-project activities.

Division: Under each division one Executive Engineer (E.E) will be in charge of the division for, processing tender and bid documents executing the works, check measurement etc. He will ensure the quality of the ongoing works etc.

Sub-Division: Under each sub-division Assistant Engineer / Asst. Executive Engineer shall be in charge of the sub-division office. He will be supported by field functionaries like Junior Engineer and other field for execution, check measurement, monitoring the works and ensuring the quality of the work.

45. The Junior Engineer at the field level will be responsible for day to day environmental monitoring and the overall supervision and responsibility of EMP implementation will be with the concerned SIO Manager ( S.E for Major sub project and E.E for medium sub project).

Environmental Monitoring Report – Ramial sub project July 2017 12

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

Institutional Strengthening and Project Management Consultants (ISPMC)

46. The ISPMC will have an Environment Specialist, Resettlement Specialist and Indigenous group Specialist who will support the PMU in advising and monitoring the EMP measures with help of SIO Staff and WUAs. The ISPMC will assist in reviewing all the contractors’ monthly environmental reports submitted by Contractors through SIO in consultation with PMU. They will assist the PMU in preparing environmental monitoring reports and other reports like preparation of IEEs, RP and social assessment reports.

Responsible for carrying out monitoring measures

47. As per the “ Environmental Assessment and Review Frame work (EARF) prepared for the project it states that “PMU will be responsible to undertake (i) environmental screening at subproject identification stage; (ii) preparation of IEEs/EIAs at subproject appraisal stage; and (iii) environmental management and mitigation during subproject implementation and operational stage. At appraisal, IEEs /EIAs will be done with the engagement of consulting firms who would be guided by the project environmental specialist.

48. Environmental management and mitigation will be undertaken by the construction contractors during construction phase under the supervision of the designated staff in the subproject management offices (SIOs) and monitored by PMU environmental cell. The consultants mobilized for institutional strengthening and project management will also be entrusted to provide necessary capacity development of the DOWR engineers and SIO (S.E for major sub project and E.E for medium subproject) in terms of environmental planning and management”.

49. . The PMU / SIO of DoWR assisted by the WUAs, and the Institutional Strengthening and Project Management Consultants (ISPMC) will be guiding the implementation of the EMP. The SIO (S.E for major sub project and E.E for medium subproject). The field level Junior Engineer shall be responsible for monitoring the EMP activities of the Contractors on a day to day basis. The SIO staff and WUAs with the help of ISPMC, Environment Specialist will monitor the EMP implementation of the Contractor.

50. While the implementation of sub-minors shall be on WUAs and monitored by SIO. Pani Panchayat Support Unit (PPSU) is the state level apex agency who is responsible for strengthening the PP activities. PPSU - Environmental Monitoring Specialist be made responsible for the monitoring of WUAs along with SIO staff and these will work under the overall guidance of ISPMC.

51. The Environmental Framework prepared for the Project -2 states “Environmental management and mitigation will be undertaken by the construction contractors during construction phase. The PMU and SIOs as well as contractors were guided by the ISPMC Environmental Specialist in implementation of the EMPs and associated monitoring and reporting activities.

Environmental Monitoring Report – Ramial sub project July 2017 13

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

52. Systematic monitoring of the EMP was facilitated by a check list developed specifically for SIO- J.Es and contractors. The format was part of the IEE report and subsequently during January & February 2016 orientation program the format was explained.

53. The SIO staff and contractors representatives at site were explained on the environmental aspects and the required safeguards measures that are needed at site along with necessary on job – training / sub project level trainings (on national environmental law requirements, environmental safeguards requirements of ADB, contractual clauses for EMP implementation).

Capacity Building

54. During January 2016 and February 2016 Capacity building on EMP implementation was carried out by PMU with the help of ISPMC Consultants. So far 88 persons (Senior DoWR staff, SIO staff and Contractors also) were trained (which includes staff and Contractors from Ramial Subproject also) SIO staff and Contractor representatives in the EMP implementation and as a result Contractor compliances had improved to a greater extent.

55. The orientation program on Environmental Safeguards for Kanjhari subproject was held on 24 June 2016 at Kamakyanagar, ( Covering the staff and contractors of Ramial and Kanjhari Subprojects) to bring awareness on EMP implementation to SIO field staff and contractor representatives. There were 14 numbers of participants including the speaker. One Junior Engineer for each contract package was identified who will act as an Environmental Co- ordinator for monitoring the field level EMP implementation. This mechanism had helped in timely EMP compliances but with some delays

6.0 COMPLIANCES STATUS OF PREVIOUS EMP REPORT - SUB PROJECT WISE 56. For the Ramial Subproject i.e. contract package wise status of compliances with reference to the previous Environmental Monitoring Report (EMR) is stated in Table 11. As this is the first Environmental Monitoring Report for the subprojects so there are no previous compliances reported pending.

Table 11 Compliance Status from the Previous EMR Contract wise – Ramial Subproject Sl. No Contract Package Issue from the Previous Environmental Actions Taken by SIO Monitoring Report staff 1 All Contract Packages • Working permission in forest area SIO pursuing with DFO, however there is no objection from the forest office as the works are confined to existing available ROW 2 All Contract Packages • Environmental Testing and SIO and Contractor Monitoring requested to undertake immediately, PMU pursuing with SIO staff CW-NCB-RML -01(CW- 2 NCB-RML-02 clubbed • Vendor – Morrum Details – requested SIO requested the

Environmental Monitoring Report – Ramial sub project July 2017 14

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

Sl. No Contract Package Issue from the Previous Environmental Actions Taken by SIO Monitoring Report staff with RML-01) Contractor for early compliance • Insurance -All risk to undertaken Complied

• Accident was requested SIO requested Contractor • Environmental Monitoring to be continued SIO Requested Contractor • Minor Rain cuts (RD 6.7 km) were Lining completed in observed this portion

• Motivating the labour in use of Safety SIO requesting gadgets regularly Contractor to motivate regularly

Vendor details of Morrum SIO requested Contractor Insurance -All risk and Accident was SIO requested requested contractor for early compliance 2 CW-NCB-RML-03 • Disposal of cutting material from the Clearly and used for right bank filling low lying areas

• Motivating the labour in use of Safety SIO requesting gadgets regularly contractor for motivating regularly • Environmental clearance of borrow SIO had written to DFO earth and SIO/ contractor submitted details to Tahsildhar and the process is in progress • Insurance -All risk and Accident was requeste SIO requested • contractor for early compliance 3 CW-NCB-RML-04 • Vendor – Morrum Details – requested SIO requested Contractor for early compliance • Minor raincuts ( RD 4 to 6km of Khajuria Disty) was observed Rectified

• Motivating the labour in use of Safety SIO requesting gadgets regularly Contractor for regular motivation

Environmental Monitoring Report – Ramial sub project July 2017 15

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

7.0 COMPLIANCES WITH LOAN COVENANTS 57. OIIAWMIP Project -2 loan agreement Schedules 5 stipulates certain condition for safeguarding “Environment” which includes safeguards related provisions in bidding documents and works contracts and Safeguards monitoring and reporting requirements. A compliance review indicates full compliance with Loan Covenants. Table 12 shows the environmental safeguards assurances and the status of compliances.

Table 12 Compliances on Loan Covenants S.No Loan Covenants Status Environment 5 The Borrower shall ensure or cause the State to ensure that the preparation , design, construction, implementation, operation, and decommissioning of the project, each subproject and all Project facilities comply with a) all applicable laws and regulations of the Borrower and Complied the State relating to environment, health and safety b) the Environmental Safeguards Complied c) the EARF Compiled d) all measures and requirements set forth in the Complied respective IEE and EMP and any corrective or preventive actions set forth in a Safeguards Monitoring Report. Safeguards – Related Provisions in Bidding Documents and Works Contracts 10 The Borrower shall ensure or cause the State to ensure, that all bidding documents and contracts for Works contain provisions that require Contractors to : a) comply with the measures and requirements relevant Complied to the contractor set forth in the IEE/ EIA, the EMP, the RP and the IPP( to the extent they concern impacts on affected people during construction), and any corrective or preventive actions set out in a Safeguards Monitoring Report; b) make available budget for all such environmental and Complied social measures; c) Provide the State with a written notice of any No Change in the situation as unanticipated environmental, resettlement or reported in IEE & EMP indigenous peoples risks or impacts that arise during construction, implementation or operation of the Project that were not considered in the IEE, the EMP, the RP or the IPP d) Adequately record the conditions of roads, agricultural Complied land and other infrastructure prior to starting to transport materials and construction; and e) Fully reinstate pathways, other local infrastructure , and Complied – SIO ensuring agricultural land to at least their pre –project Contractors do regular conditions upon the completion of construction maintenance of roads as required Environmental Monitoring Report – Ramial sub project July 2017 16

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

Safeguards Monitoring and Reporting 11. The Borrower shall, or cause the State to, do the following: a) submit semi-annual Safeguards Monitoring Reports to Complied ADB and disclose relevant information from such reports to affected persons promptly upon submission b) If any unanticipated environmental and / or social risks No unanticipated impacts and impacts arise during construction, implementation or operation of the Project that were not considered in the IEE, the EMP, the RP or the IPP, promptly inform ADB of the occurrence of such risks or impacts, with detailed description of the event and proposed corrective action plan; and c) report any actual or potential breach of compliance No breach with the measures and requirements set forth in the EMP, the RP or the IPP promptly after becoming aware of the breach Labour Standards 14 The Borrower and State shall ensure that Works Complied Contracts under the Project follow all applicable labour laws of the Borrower and the State and that these further include provisions to the effect that Contractors: a) carryout HIV/ AIDS awareness programs for labour and Complied – AIDS awareness at disseminate information at worksites on risks of PMU level conducted during 18 sexually transmitted diseases and HIV / AIDS as part of June 2016 and collaboration with health and safety measures for those employed during Odisha AIDS Control Society construction; and undertaken and subproject level AIDS campaign for labours undertaken at four places on 28 June 2016 b) follow and implement all statutory provisions on labour Complied ( including not employing or suing children as labour, equal pay for equal work), health, safety, welfare, sanitation, and working conditions. Such contracts shall also include clauses for termination in case of any breach of the state provisions by the Contractors

8.0 CONCLUSIONS 58. Overall, EMP implementation is rated “Partially Satisfactory” in all the contract packages Consultations reveal beneficiaries (local communities) are generally happy with the construction program. During this period i.e. between July to December 2016 there was no physical activity due to release of water in the canal for cultivation. No adverse environmental impacts were observed and no grievances noted. The subprojects, after restoration of the canals shall increase economic benefits in the sub project area. 59. Awareness and Capacity development at PMU/SIOs commenced early in the project and included training on ADB environment policy and its implementation. Orientation programs on Environmental safeguards implementation was conducted during January and February 2016

Environmental Monitoring Report – Ramial sub project July 2017 17

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

which involves staff and Contractors of Kanjhari subproject also. Topics included ADB safeguards, environmental laws, contract clauses, and reporting needs 60. Subsequently subproject level orientation program was conducted on 24 June 2016 at Kamakhyanagar to overcome the short comings; around 14 persons including the Environment Specialist was present. The key participants were SIO & Contractors staff. 61. SIO has initiated for obtaining working permission from State Forest Department, however he shall ensure that the clearance shall be available before the coming working season. 62. EMP implementation timelines have been met in general. However, EMP implementation by Contractors is rated partially satisfactory in all the contract packages with only minor initial delays noted by contractors, mainly due to understanding of the guidelines, contractual constraints and experience of contractor’s staff. 63. Contractor’s responsiveness is increasing and aided in EMP successful implementation as a Monthly Environmental Check was introduced to monitor all subprojects. 64. The Contractors shall ensure necessary pending insurances at the earliest as per provisions of the contract, however SIO has written to the contractors for early compliances. 65. During the period July 2016 to December 2016 there was no physical activity due to release of water into the canal water system for rabi cultivation, the SIO / Contractors had undertaken environmental monitoring i.e surface water and silt during June 2016. The SIO had requested contractors to undertake environmental testing i.e ., testing of surface water, ground water, silt, soil and noise as per the suggested frequency. 66. SIO had requested Contractors to provide safety gear/equipment regularly which was not utilized adequately by labour because of discomfort, as observed and informed during monitoring visits, hence there is scope for improvement on the Contractors side to ensure and encourage the labour for a regular use. 67. Integrated Borrow area management approach by SIO’s (borrow area test for soil classification, OMC and MDD tests along with agreement with the landowners, obtaining Environmental Clearance from DEIAA/ DEAC) will ensure easy Contractors compliances, as a result this will improve the borrow area management. 68. SIO had requested Contractor to conduct AIDS awareness program periodically and the contractor shall ensure that they conduct in the next working season. 69. The EMR data acquisitions may be archived as information and baseline for use in future DOWR environmental program management options and as anticipated policy enforcement changes evolve over time.

Environmental Monitoring Report – Ramial sub project July 2017 18

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

ANNEXURES

Environmental Monitoring Report – Ramial sub project July 2017 19

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

Annexure 1 Letter from DFO for Working Permission in forest Areas

Environmental Monitoring Report – Ramial sub project July 2017 20

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

Annexure 2 Letter from DEIAA for Exemption of Environmental Clearance for Borrow Earth (Dhenkanal District)

Environmental Monitoring Report – Ramial sub project July 2017 21

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

Annexure 3

Status of Environmental Mitigation Measures adopted by Contractor for CW-NCB-RML-01 Name of the Sub-project : REM of Left Main Canal (0.0 km to 22.00 km), selective lining including improvement /modernisation of structures Name of the Contract Package : CW-NCB- RML-01 (RML-02 merged with RML-01) Implementation Period : July 2016 to end of December 2016 Physical Works Progress : Earth Work: 48.86% Concrete work: 62 % Financial Progress: 56%

Compliances S. Environmental by the Status on Mitigation measures by the Contractor No. Components / Issues Contractor No / Yes NR 1 Camp Yes • Temporary Transit Labour Camps established in rented accommodation at Kankadahada during July to December 2016. • The camp is used for supervisory staff and some labour. • During July to December 2016 limited work was in progress due to release of water in to the canal system • Local labour from Sasaposi, Khadei-bereni, Zerosai , Jhajiriberena, and Rahani villages were working during July and December 2016. Who doesn’t stay in the camp • No grievances observed as per SIO 2 Borrow Areas Yes • Earth procurement is the responsibility of Contractor. He has procured earth from private land and necessary royalty being deducted by the SIO staff ( Earth work : 1003.14cum total quantity) • Only 1 patch of borrow earth was used after obtaining written consent from the land owner, the SIO had requested contractor for obtaining necessary permissions. Though borrowing is as per land owners wish however J.E shall ensure that the contractor does proper levelling of borrow areas • As per SIO there are no grievance noticed however contractor was requested to adopt integrated borrow area management 3 Transporting Yes • The contractor has avoided the agricultural land for Construction Materials transportation of materials the contractor used and Haul Road existing village kachha roads and there are no Management damages as per SIO staff 4 Quarries Yes • The contractor has not operated any quarry of his own under the project. He has obtained aggregates (Sand and stone metal from the vendors. from quarry) • SIO had deducted necessary royalty from the Contractors (Sand- 6157. 04 cum and Stone Environmental Monitoring Report – Ramial sub project July 2017 22

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

Compliances S. Environmental by the Status on Mitigation measures by the Contractor No. Components / Issues Contractor No / Yes NR products – 6693.77 cum and morrum 5641.90 cum so far. 5 Soil Erosion & Siltation Yes • The Construction activity was restricted to non- monsoon period only. • Minor rain cuts ( RD 6.7km; ) were observed which would be taken up during next season and lining work has commenced • Provision for slope protection works like turfing is also proposed 6 Disposal of Silt, Yes • Dismantled material /the debris is used in filling the dismantle materials, low lying areas within the ROW. However the SIO debris and equipment had requested contractor to clear all the debris before on set of monsoon or release of water in the canal. • Cutting earth was disposed in the low lying areas. However Silt was tested during June 2016 7 Impact on land use Yes • Most of the material was stored along the sides of pattern of the area the canal not in any nearby agricultural lands hence there is no change in land use as per SIO staff. 8 Blockage of natural Yes • Most of the material was stored along the sides of drainage patterns the canals not in any nearby agricultural lands hence there is no change in land use as per SIO staff. 9 Temporary closure of Yes • No natural drainage was blocked; Contractor was irrigation schemes requested to clear excess construction materials present near the sluice sites. 10 Work Sites & protection Yes • The villagers were informed construction works and of public and workers the consultation carried out is presented in the below health and safety and sections. appointment of Safety • The Contractor had provided necessary protective Officer gears like helmets, hand gloves and boots to the labourers during construction period, however limited labour work in progress as most of the work carried out by machines, even there was resistance to wear continuously as per SIO. However the contractor had to motivate the labour in using the gadgets regularly. 11 Environmental Testing Yes • SIO and Contractor shall continue environmental and Monitoring ( testing as per IEE. Ground/ Surface Water, Silt and Soil)

12 Dust generation Yes • The canals are away from the habitations. However the Contractor had made dust suppression measures such as sprinkling of water wherever necessary. 13 Noise from Vehicles, Yes • The camp site and equipment sites were located Plants and Equipments away from the habitations. • The contractor had maintained the vehicles properly by sending it to regular maintenance.

Environmental Monitoring Report – Ramial sub project July 2017 23

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

Compliances S. Environmental by the Status on Mitigation measures by the Contractor No. Components / Issues Contractor No / Yes NR 14 Water Pollution from Yes • At Present water sample from reservoir testing Fuel and Lubricants undertaken during work period however after release of canal water surface water testing as per the suggested frequency shall be done by SIO to assess impact of the work. • The contractor had taken adequate care. He was sending vehicles for the repair to the nearby mechanics. If any minor repairs he has to do, he has ensured the area doesn’t contaminate. 15 Contamination of soil by Yes • The contractor had taken adequate care. He was fuel and lubricants sending vehicles for the repair to the nearby mechanics. If any minor repairs he has to do, he has ensured the area doesn’t contaminate. 16 Interference with Yes • The contractor had made proper safety arrangements existing road network with the local available materials etc., and as well as and traffic, blockage of informing the community, time to time, wherever access ways. Restriction necessary. on movements of communities 17 Emission from Yes • Necessary regular and routine maintenance practices Construction Vehicles, were undertaken for equipments as per the vendor’s Equipment and manuals. Machineries • The contractor had maintained the vehicles properly by sending it to regular maintenance. 18 Flora and Fauna Yes • Construction workers were not damaging any flora Protection, tree cutting if or fauna during their work and most of the labour any, including were not staying near the work site. They are from impairment of fisheries/ the adjoining villages who work and go. aquatic ecology & other • The Contractor had installed signed boards like no beneficial uses bird hunting etc. 19 Impact from other NR • The environmental pollution like dust emissions, Projects in the area damage to some sub-minors and improper borrowing of the earth are also noticed in the environs of the project because of other ongoing project woks like construction of road works and pipeline works; these are also contributing to the change in environmental conditions of the environs of this project.

Environmental Monitoring Report – Ramial sub project July 2017 24

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

Annexure 4

Status of Environmental Mitigation Measures adopted by Contractor for CW-NCB-RML -03 Name of the Sub-project : REM of Right Main Canal selective lining and Kandhara Distributary Canal lining including all structures Name of the Contract Package : CW-NCB- RML-03 Implementation Period : July 2016 to end of December 2016 Physical Works Progress : Earth work:-48.41 Concrete work: 69.53 % Financial Progress 59%

Compliances S. Environmental by the Status on Mitigation measures by the Contractor No. Components / Issues Contractor No / Yes NR 1 Camp Yes • Temporary Transit Labour Camps established in rented accommodation at Patabeda during July to December 2016 • The camp is used for supervisory staff and some labour. • Limited work was in progress during this period as canal water was released • Local labour from Patabeda, kankadahada, GopaPura villages were working during this period. Who doesn’t stay in the camp • No grievances observed as per SIO 2 Borrow Areas Yes • Earth procurement is the responsibility of Contractor. • During this period no borrow earth was used however cutting of earth was undertaken • As per SIO there are no grievance noticed however contractor was requested to adopt integrated borrow area management 3 Transporting Yes • The contractor has avoided the agricultural land for Construction Materials transportation of materials the contractor used and Haul Road existing village kachha roads and there are no Management damages as per SIO staff 4 Quarries Yes • The contractor has not operated any quarry of his own under the project. He has obtained aggregates (Sand and stone metal from the vendors. from quarry) • SIO had deducted necessary royalty from the Contractors (Sand-6666.47 cum and Stone products: 6428.82 cum and morrum: 5243.9 cum so far. 5 Soil Erosion & Siltation Yes • The Construction activity was restricted to non- monsoon period only. • Right bank cutting material deposited over the bank shall be disposed off properly, selected patches lining work was initiated • SIO requested Contractor to undertaken minor

Environmental Monitoring Report – Ramial sub project July 2017 25

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

Compliances S. Environmental by the Status on Mitigation measures by the Contractor No. Components / Issues Contractor No / Yes NR raincuts for rectification and turfing and lining shall be undertaken • Lining work in progress and Provision for slope protection works like turfing is also proposed. 6 Disposal of Silt, Yes • Dismantled material /the debris is used in filling the dismantle materials, low lying areas within the ROW. However the SIO debris and equipment had requested contractor to clear all the debris before on set of monsoon or release of water in the canal • Cutting earth was disposed in the low lying areas. However Silt was tested during June 2016 7 Impact on land use Yes • Most of the material was stored along the sides of pattern of the area the canal not in any nearby agricultural lands hence there is no change in land use as per SIO staff. 8 Blockage of natural Yes • Most of the material was stored along the sides of drainage patterns the canals not in any nearby agricultural lands hence there is no change in land use as per SIO staff. 9 Temporary closure of Yes • No natural drainage was blocked; Contractor was irrigation schemes requested to clear excess construction materials present near the sluice sites. 10 Work Sites & protection Yes • The villagers were informed construction works and of public and workers the consultation carried out is presented in the below health and safety and sections. appointment of Safety • The Contractor had provided necessary protective Officer gears like helmets, hand gloves and boots to the labourers during construction period, however limited labour work in progress as most of the work carried out by machines, even there was resistance to wear continuously as per SIO. However the contractor had to motivate the labour in using the gadgets regularly. 11 Environmental Testing Yes • SIO and Contractor shall continue environmental and Monitoring ( testing as per IEE. Ground/ Surface Water, Silt and Soil)

12 Dust generation Yes • The canals are away from the habitations. However the Contractor had made dust suppression measures such as sprinkling of water wherever necessary. 13 Noise from Vehicles, Yes • The camp site and equipment sites were located Plants and Equipments away from the habitations. • The contractor had maintained the vehicles properly by sending it to regular maintenance. 14 Water Pollution from Yes • SIO and Contractor were requested to undertaken Fuel and Lubricants environmental testing of surface water immediately • The contractor had taken adequate care. He was sending vehicles for the repair to the nearby mechanics. If any minor repairs he has to do, he has

Environmental Monitoring Report – Ramial sub project July 2017 26

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

Compliances S. Environmental by the Status on Mitigation measures by the Contractor No. Components / Issues Contractor No / Yes NR ensured the area doesn’t contaminate. 15 Contamination of soil by Yes • The contractor had taken adequate care. He was fuel and lubricants sending vehicles for the repair to the nearby mechanics. If any minor repairs he has to do, he has ensured the area doesn’t contaminate. 16 Interference with Yes • The contractor had made proper safety arrangements existing road network with the local available materials etc., and as well as and traffic, blockage of informing the community, time to time, wherever access ways. Restriction necessary. on movements of communities 17 Emission from Yes • Necessary regular and routine maintenance practices Construction Vehicles, were undertaken for equipments as per the vendor’s Equipment and manuals. Machineries • The contractor had maintained the vehicles properly by sending it to regular maintenance. 18 Flora and Fauna Yes • Construction workers were not damaging any flora Protection, tree cutting if or fauna during their work and most of the labour any, including were not staying near the work site. They are from impairment of fisheries/ the adjoining villages who work and go. aquatic ecology & other • The Contractor had installed signed boards like no beneficial uses bird hunting etc. 19 Impact from other NR • The environmental pollution like dust emissions, Projects in the area damage to some sub-minors and improper borrowing of the earth are also noticed in the environs of the project because of other ongoing project woks like construction of road works and pipeline works; these are also contributing to the change in environmental conditions of the environs of this project.

Environmental Monitoring Report – Ramial sub project July 2017 27

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

Annexure 5

Status of Environmental Mitigation Measures adopted by Contractor for CW-NCB-RML -04 Name of the Sub-project : REM of Batagoan, Khajuria and Kanpura Distributary canal and selective lining including all structures Name of the Contract Package : CW-NCB- RML-04 Implementation Period : July 2016 to end of December 2016 Physical Works Progress : Earth work: 55 % Concrete work: 70 % Financial progress: 44%

Compliances S. Environmental by the Status on Mitigation measures by the Contractor No. Components / Issues Contractor No / Yes NR 1 Camp Yes • Temporary Transit Labour Camps established in rented accommodation at main camp at Batagaon, Kanpura and Khajurai villages during July to December 2016. • The camp is used for supervisory staff and some labour. • During this period limited work was in progress i.e. due to release of canal water. • Local labour from Kanpura, Mundiatangar, Rahoni and Patharakata villages were working during this period. Who doesn’t stay in the camp • No grievances observed as per SIO 2 Borrow Areas Yes • Earth procurement is the responsibility of Contractor. He has procuring earth from private land and necessary royalty being deducted by the SIO staff. ( Earth work : 2696.4 cum total quantity) • Borrowing earth was as per the land owner’s convenience. Though borrowing is as per land owners wish however J.E shall ensure that the contractor does proper levelling of borrow areas • The SIO had approved 7 patches of borrow area but No-objection letters from land owners ( Tandimunda village -1no, Rahani village -7 no, Kajuria – 3 nos, Tangerposi- 2no, Kanpura -1no) were collected and SIO had requested contractor to undertake necessary permissions at the earliest • As per SIO there are no grievance noticed however contractor had to adopt integrated borrow area management 3 Transporting Yes • The contractor has avoided the agricultural land for Construction Materials transportation of materials the contractor used and Haul Road existing village kachha roads and there are no Management damages as per SIO staff

Environmental Monitoring Report – Ramial sub project July 2017 28

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

Compliances S. Environmental by the Status on Mitigation measures by the Contractor No. Components / Issues Contractor No / Yes NR 4 Quarries Yes • The contractor has not operated any quarry of his own under the project. He has obtained aggregates (Sand and stone metal from the vendors. from quarry) • SIO had deducted necessary royalty from the Contractors (Sand 1814.29 cum and Stone products: 3088.56 cum and morrum: 12.8 cum so far. 5 Soil Erosion & Siltation Yes • The Construction activity was restricted to non- monsoon period only. • Minor rain cuts were observed which would be taken up during next season however SIO had requested to rectify at the earliest • Provision for slope protection works like turfing is also proposed 6 Disposal of Silt, Yes • Dismantled material /the debris is used in filling the dismantle materials, low lying areas within the ROW. However the SIO debris and equipment had requested contractor to clear all the debris before on set of monsoon or release of water in the canal • Cutting earth was disposed in the low lying areas. However Silt was tested during June 2016 7 Impact on land use Yes • Most of the material was stored along the sides of pattern of the area the canal not in any nearby agricultural lands hence there is no change in land use as per SIO staff. 8 Blockage of natural Yes • Most of the material was stored along the sides of drainage patterns the canals not in any nearby agricultural lands hence there is no change in land use as per SIO staff. 9 Temporary closure of Yes • No natural drainage was blocked; Contractor was irrigation schemes requested to clear excess construction materials present near the sluice sites. 10 Work Sites & protection Yes • The villagers were informed construction works and of public and workers the consultation carried out is presented in the below health and safety and sections. appointment of Safety • The Contractor had provided necessary protective Officer gears like helmets, hand gloves and boots to the labourers during construction period, however limited labour work in progress as most of the work carried out by machines, even there was resistance to wear continuously as per SIO. However the contractor had to motivate the labour in using the gadgets regularly. 11 Environmental Testing Yes • SIO and Contractor requested to undertake and Monitoring ( environmental testing immediately as per the Ground/ Surface Water, suggested frequency Silt and Soil) • SIO and Contractor shall continue environmental testing as per IEE. 12 Dust generation Yes • The canals are away from the habitations. However the Contractor had made dust suppression measures such as sprinkling of water wherever necessary.

Environmental Monitoring Report – Ramial sub project July 2017 29

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

Compliances S. Environmental by the Status on Mitigation measures by the Contractor No. Components / Issues Contractor No / Yes NR 13 Noise from Vehicles, Yes • The camp site and equipment sites were located Plants and Equipments away from the habitations. • The contractor had maintained the vehicles properly by sending it to regular maintenance. 14 Water Pollution from Yes • SIO and Contractor shall undertake water testing Fuel and Lubricants immediately as per the suggested frequency • The contractor had taken adequate care. He was sending vehicles for the repair to the nearby mechanics. If any minor repairs he has to do, he has ensured the area doesn’t contaminate. 15 Contamination of soil by Yes • The contractor had taken adequate care. He was fuel and lubricants sending vehicles for the repair to the nearby mechanics. If any minor repairs he has to do, he has ensured the area doesn’t contaminate. 16 Interference with Yes • The contractor had made proper safety arrangements existing road network with the local available materials etc., and as well as and traffic, blockage of informing the community, time to time, wherever access ways. Restriction necessary. on movements of communities 17 Emission from Yes • Necessary regular and routine maintenance practices Construction Vehicles, were undertaken for equipments as per the vendor’s Equipment and manuals. Machineries • The contractor had maintained the vehicles properly by sending it to regular maintenance. 18 Flora and Fauna Yes • Construction workers were not damaging any flora Protection, tree cutting if or fauna during their work and most of the labour any, including were not staying near the work site. They are from impairment of fisheries/ the adjoining villages who work and go. aquatic ecology & other • The Contractor had installed signed boards like no beneficial uses bird hunting etc. 19 Impact from other NR • The environmental pollution like dust emissions, Projects in the area damage to some sub-minors and improper borrowing of the earth are also noticed in the environs of the project because of other ongoing project woks like construction of road works and pipeline works; these are also contributing to the change in environmental conditions of the environs of this project.

Environmental Monitoring Report – Ramial sub project July 2017 30

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

Annexure 6

Status of Environmental Mitigation Measures adopted by Contractor for CW-NCB-RML -05 Name of the Sub-project : REM of minor canlas of Ramial irrigation sub project including improvement / moderinisation of structures Name of the Contract Package : CW-NCB- RML-04 Implementation Period : July 2016 to end of December 2016 Physical Works Progress : Earth work: 0 % Concrete work: 0 % Financial progress: 0% agreement executed on 24 December 2016

Compliances S. Environmental by the Status on Mitigation measures by the Contractor No. Components / Issues Contractor No / Yes NR 1 Camp Yes • Contractor under mobilization, physical work yet to commence 2 Borrow Areas Yes Contractor under mobilization

3 Transporting Yes Contractor under mobilization Construction Materials and Haul Road Management 4 Quarries Yes Contractor under mobilization (Sand and stone metal from quarry) 5 Soil Erosion & Siltation Yes Contractor under mobilization

6 Disposal of Silt, Yes Contractor under mobilization dismantle materials, debris and equipment 7 Impact on land use Yes Contractor under mobilization pattern of the area 8 Blockage of natural Yes Contractor under mobilization drainage patterns 9 Temporary closure of Yes Contractor under mobilization irrigation schemes 10 Work Sites & protection Yes Contractor under mobilization of public and workers health and safety and appointment of Safety Officer

Environmental Monitoring Report – Ramial sub project July 2017 31

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

Compliances S. Environmental by the Status on Mitigation measures by the Contractor No. Components / Issues Contractor No / Yes NR 11 Environmental Testing Yes Contractor under mobilization and Monitoring ( Ground/ Surface Water, Silt and Soil) 12 Dust generation Yes Contractor under mobilization

13 Noise from Vehicles, Yes Contractor under mobilization Plants and Equipments 14 Water Pollution from Yes Contractor under mobilization Fuel and Lubricants

15 Contamination of soil by Yes Contractor under mobilization fuel and lubricants 16 Interference with Yes Contractor under mobilization existing road network and traffic, blockage of access ways. Restriction on movements of communities 17 Emission from Yes Contractor under mobilization Construction Vehicles, Equipment and Machineries 18 Flora and Fauna Yes Contractor under mobilization Protection, tree cutting if any, including impairment of fisheries/ aquatic ecology & other beneficial uses 19 Impact from other NR Contractor under mobilization Projects in the area

Environmental Monitoring Report – Ramial sub project July 2017 32

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

PHOTOGRAPHS

Environmental Monitoring Report – Ramial sub project July 2017 33

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

Photo Plate: - Ramial Sub Project

RML-01 Borrow Area of Batagaon village RML-01 Borrow Area of Batagaon Village

RML-01 Bridge RML-01 Guard wall

RML-04 Borrow Area RML-04 Borrow Area

Environmental Monitoring Report – Ramial sub project July 2017 34

Orissa Integrated Irrigated Agriculture and Water Management Investment Program

RML-04 Kanpura Traugh Wall RML-04 HR with Packing

RML-03 of lining area RML-01 of Lining Area

Focus Group Discussion with Villagers at Sasaposi AIDS awareness programme at Patabeda on dated 06.05.2016

Environmental Monitoring Report – Ramial sub project July 2017 35