3 DRAFT Package 1 – Preload & Demolition

S-473 Preload Mound Looking West

S-471 S-474 S-473 S-470

Embankment S-472 S-475

Constructed earthen Preload Mounds at 7 locations. ~285,000 CY each (2M CY Total) Demolition of all agricultural facilities including small irrigation pump stations $11 M NTP – Nov 2015

COMPLETED - June 2018 4 DRAFT Package 2 – Irrigation PS S-476

LPDD Header Canal LPDD PS#1 PS#2 S-476 Looking East

(3) 65 CFS Vertical Electric Pumps (195 CFS Total) S-476 Replaces the need for Header Canal to provide Perimeter Canal irrigation water to the east. $13M NTP - June 2016 Final Completion – April 2019 ~ 94% Complete 5 DRAFT Package 3 – Inflow Pump Station S-470

S-470

S-470 Looking Southeast

(4) 375 CFS Vertical Electric Pumps (1,500 CFS Total) 300’ Microwave Tower & Control Bldg SR-80 Bridge Armoring Townsend Canal Improvements $58.5 M NTP – March 2018 Final Completion – May 2022

~11% Complete 6 Site Preparation Package 1 DRAFT Tree Clearing Progress

10,000 acres $3.7M NTP – November 2017 Final Completion – June 2019 ~99% complete

7 Site Preparation Package 2 DRAFT Access Roads

Construction of approximately 16 Miles of Shell Rock Rd. Installation of approximately 2,500 LF of culverts Design and installation of road crossing over the Roberts/Banana Branch Canal Removal of existing culverts and temporary canal plugs $3.0 M NTP – April 2018 Final Completion – March 2019 ~99% complete

8 DRAFT Package 4 – Civil Works

. 2-Cell Reservoir • 10,500 Acres • 170,000 ac-ft of storage • Depth ranging from 15’ – 25’ . 19 Miles of Dam Embankment . 15 Miles of Perimeter Canal . 14 Major Water Control Structures . Recreation Features . Townsend Canal Improvements . Local & Site Access Bridges

9 DRAFT Solicitation Summary

Solicitation Part 1 Advertised: June 25, 2018 Prequalification Shortlist Approved: October 11, 2018 Solicitation Part 2 Issued: November 16, 2018 Bid Opening: January 30, 2019 Number of Bids Received: 4 Bid Range: $523,871,000 – $879,900,657 Engineer’s Estimate: $660,262,174

10 DRAFT Bid Summary

C-43 Water Management Builders JV $523,871,000 P&J Morgan JV $691,559,143 RJB Constructors JV $820,519,000 Barnard Construction Company, Inc. $879,900,657

11 DRAFT C43 Water Management Builders JV

Lane Construction Corporation - Salini Impregilompregilo, S.p.A. () Project Location Period Value Mazar Hydroelectric Power Project Ecuador 2005 - 2010 $ 285,805,700 Angostura Hydroelectric Chile 2010 - 2014 $ 304,515,838 Gilgel Give III Hydroelectric Power Ethiopia 2006 - 2016 $ 1,507,328,877 Project Gurara Water Transfer Nigeria 2001 - 2016 $ 580,962,920 Grand Ethiopian Renaissance Dam Ethopia 2005 - 2010 $ 4,508,928,539 Panama Canal – 3rd Set of Locks Panama 2009 - 2016 $ 1,413,504,000 Total $ 8,601,045,874

12 DRAFT Resolution

A Resolution of the Governing Board of the South Florida Water Management District to enter into a contract with C-43 Water Management Builders Joint Venture for the C-43 West Basin Storage Reservoir Bid Package 4 Civil Works in the amount of $523,871,000 of which non-ad valorem funds (Save Our Everglades Trust Fund and Land Acquisition Trust Fund) and ad valorem funds are budgeted in the Fiscal Year 2018- 2019 budget and the remainder is subject to Governing Board approval of future year budgets; providing an effective date. (Contract No. 4600003973)