EMGA MitchellMcLennan

PWCS Planning + Environment + Acous cs

The Terminal 4 Project Preliminary Environmental Assessment Report Prepared for Port Waratah Coal Services Limited - November 2010

www.emgamm.com

PreliminaryEnvironmentalAssessment

FinalReport

Terminal4Project|PreparedforPortWaratahCoalServicesLimited|26November2010

Approvedby PaulMitchell Approvedby BrettMcLennan

Position Director Position Director

Signature Signature

Date 26November2010 Date 26 November2010

ThisReporthasbeenpreparedinaccordancewiththebriefprovidedbytheClientandhasreliiedupontheinformation collected at or under the times and conditions specified in the Report. All findings, conclusions or recommendations containedwithintheReportarebasedonlyontheaforementionedcircumstances.Furthermore,theReportisfortheuse oftheClientonlyandnoresponsibilitywillbetakenforitsusebyotherparties.

DocumentControl

Version Date Preparedby Reviewedby

1 05October2010 BrettMcLennan,DuncanPeake,JodiKelehear PaulMitchell 2 03November2010 JodiKelehear BrettMcLennan 3 19November2010 BrettMcLennan PaulMitchell 4 22November2010 JodiKelehear BrettMcLennan 5 26November2010 JodiKelehear BrettMcLennan

Planning+Environment+Acoustics

T+61(0)294939500|F+61(0)294939599 GroundFloor|Suite01|20ChandosStreet| StLeonards|NewSouthWales|2065|Australia www.emgamm.com

i

“Thispagehasbeenintentionallyleftblank”

ii

TableofContents

Chapter1 Introduction 1 1.1 Projectoverview 1 1.2 Theproponent 1 1.3 Sitedescription 1 1.4 NeedfortheProject 2 1.5 PurposeandcontentofthisPreliminaryEnvironmentalAssessment 3

Chapter2 Background 7 2.1 HistoryofIsland 7 2.2 HistoryoftheT4ProjectArea 7 2.3 HistoryoftheKooragangCoalTerminal 8 2.4 Existingmaritimeapprovals 8 2.5 Commercialframework 9

Chapter3 Projectdescription 11 3.1 Introduction 11 3.2 Railloop 11 3.3 Stockyard 12 3.4 Conveyorsystem 12 3.5 Berths 12 3.6 Ancillaryfacilitiesandactivities 13

Chapter4 Approvalrequirements 17 4.1 Introduction 17 4.2 NSWEnvironmentalPlanningandAssessmentAct1979 17 4.2.1 Approvalprocess 17 4.2.2 OtherStateapprovals 18 4.3 CommonwealthEnvironmentProtectionandBiodiversityConservationAct1999 19 4.4 Otherapprovals 20 4.4.1 ProtectionoftheEnvironmentOperationsAct1999 20 4.4.2 RoadsAct1993 21 4.4.3 WaterManagementAct2000 21 4.4.4 CrownLandsAct1989 21 4.4.5 EnvironmentProtection(SeaDumping)Act1981 21 4.4.6 Otherapprovals 21

iii

TableofContents(Cont'd)

Chapter5 Stakeholderengagement 23 5.1 Introduction 23 5.2 Objectives 23 5.3 Stakeholderengagementstrategy 23 5.3.1 Initialstakeholderidentification 23 5.3.2 Stakeholderassessment 24 5.3.3 Stakeholderengagement 24 5.4 StakeholderEngagementTools 24

Chapter6 Preliminaryenvironmentalassessment 25 6.1 Introduction 25 6.2 Soilsandfoundationconditions 26 6.2.1 Existingenvironment 26 6.2.2 Proposedassessmentapproach 26 6.3 Groundwater 26 6.3.1 Existingenvironment 26 6.3.2 Proposedassessmentapproach 27 6.4 Surfacewater 27 6.4.1 Existingenvironment 27 6.4.2 Proposedassessmentapproach 28 6.5 Ecology 28 6.5.1 Existingenvironment 28 6.5.2 Proposedassessmentapproach 31 6.6 Airqualityandodour 32 6.6.1 Existingenvironment 32 6.6.2 Proposedassessmentapproach 33 6.7 Noiseandvibration 33 6.7.1 Existingenvironment 33 6.7.2 Proposedassessmentapproach 34 6.8 Trafficandtransport 34 6.8.1 Existingenvironment 34 6.8.2 Proposedassessmentapproach 35 6.9 Infrastructure 35 6.9.1 Existingenvironment 35 6.9.2 Proposedassessmentapproach 36 6.10 Heritage 36 6.10.1Existingenvironment 36 6.10.2Proposedassessmentapproach 36

iv

TableofContents(Cont'd) 6.11 Visualamenity 37 6.11.1Existingenvironment 37 6.11.2Proposedassessmentapproach 37 6.12 Energyuse,greenhousegasandclimatechange 37 6.12.1Existingenvironment 37 6.12.2Proposedassessmentapproach 38 6.13 Hazards 38 6.13.1Existingenvironment 38 6.13.2Proposedassessmentapproach 38 6.14 Socioeconomic 38 6.14.1Existingenvironment 38 6.14.2Proposedassessmentapproach 39

Chapter7 Conclusion 41

References

Acronyms

Tables

4.1 Part3Aapprovalprocess 18 6.1 ThreatenedfaunaspeciesrecordedwithinoradjacenttotheT4Projectarea 31

Figures

1.1 Localityplan 4 1.2 TheT4Project 5 1.3 HunterValleyCoalChain 6 3.1 TheT4ProjectwithRailOption5 14 3.2 TheT4ProjectwithRailOption3 15 6.1 Vegetationcommunities 30

v

“Thispagehasbeenintentionallyleftblank”

vi

1 Introduction

1.1 Projectoverview

PortWaratahCoalServicesLimited(PWCS)ownsandoperatestheKooragangCoalTerminal(KCT)located at Kooragang Island and the Carrington Coal Terminal (CCT) located at Carrington, both in the Port of Newcastle.Additionalcoalexportcapacityisrequiredattheporttoaccommodatethecontractedand projected future coal exports from the Hunter Valley and broader New South Wales (NSW). This is underpinnedbyrequirementsoftherecentlyendorsedCapacityFrameworkArrangements,whichforma criticalpartofthelongtermexportplanforcoalproducedintheregion,andarediscussedfurtherin Sections1.4and2.5ofthisreport.

TheCapacityFrameworkArrangementsprovidethatPWCSmustexpandtheCCTandKCTtotheextent that it is capable of being expanded to cover any capacity shortfall. To fulfil its obligations, PWCS is undertakingtechnicalinvestigationstodeterminethepotentialtoexpandtheKCTtothewest,knownas theTerminal4Project(T4Project).Thelandbeinginvestigatediszonedforportdevelopmentpurposes andwasformerlyusedasalandfill.Theexpansionwouldincludearailloop,stockyard,conveyorsystem, shippingberths,coalloadinginfrastructureandfacilitiessharedwiththoseexistingattheKCT.

ApprovalfortheT4ProjectisbeingsoughtunderPart3AoftheEnvironmentalPlanningandAssessment Act1979(EP&AAct).

1.2 Theproponent

TheproponentoftheT4ProjectisPWCS,whichisanincorporatedjointventurebetweenanumberof coal producers and other participants in the Hunter Valley coal industry, including exporters and importers.PWCSwasformedin1976,atwhichtimeitacquiredtheCCT.ItacquiredtheKCTin1990. The KCT is now the world’s largest (in terms of throughput) and most efficient export coal handling facility.

PWCSprovidescoalhandlingservicestocoalexporters,thatis,thereceival,assemblyandstockpilingof coal,withsubsequentreclaimingofcoalandloadingofshipsforexport.ThroughtheCCTandKCT,PWCS services coal mines throughout the Hunter Valley and broader NSW, known as the Hunter Valley Coal Chain, and which is illustrated in Figure 1.3. It is the largest coal export chain in the world, currently consistingofapproximately40coalminesownedby14coalproducers.

1.3 Sitedescription

The T4 Project is proposed to be located on Kooragang Island, which is situated approximately two kilometres(km)upstreamofthemouthoftheHunterRiver,intheNewcastleLocalGovernmentArea(see Figure1.1).

KooragangIslandisapproximately2,600hectares(ha)insize,predominatelycomprisingreclaimedland. ItisboundedbythesouthandnortharmsoftheHunterRiver.VehicleaccesstoKooragangIslandis availablebytheTourleStreetBridgeandtheStocktonBridge.

Thesoutheasternpartoftheisland,wheretheT4Projectareaislocated,isoccupiedbyheavyandlight industries,transportanddistributioninfrastructure,wasteemplacementfacilitiesandportfacilities.This includes,butisnotlimitedto,theKCT,NewcastleCoalInfrastructureGroup(NCIG)coalterminal,Boral Cementcementmanufacturinganddistributionfacility,OricaAustraliachemicalmanufacturingfacility,

1

IncitecPivotfertilisermanufacturingfacilityandtheCargillOilseedProcesser.Tothenorthandwestof theKooragangindustrialandportareaareestuarinewetlands,mangroves,saltmarshandpasturedand forested lands, subject to agricultural and conservation activities. This includes the Hunter Estuary NationalParkwhichformspartofadesignatedRamsarsite.ThenearestresidentialareastoKooragang IslandareatFernBayandStocktontotheeastandsoutheast,andMayfieldandWarabrooktothesouth andsouthwest(seeFigure1.2).AhistoryofthedevelopmentofKooragangIslandisprovidedinChapter 2.

TheT4Projectareacomprisestheproposedlocationsofarailloop,stockyard,conveyorsystem,shipping berthsandancillaryfacilities.Itisgenerallyboundbyanexistingraillinetothenorthandwest,beyond whichistheHunterEstuaryNationalParkandcrownlandproposedtobeincorporatedintothenational park.Industrialfacilities,includingtheKCTandNCIGcoalterminal,adjointheT4Projectareatotheeast, andthesoutharmoftheHunterRiveristothesouth.TheT4Projectareaandindicativelocationsofthe proposedprojectcomponentsareillustratedinFigures1.2,3.1and3.2.

The proposed location of the rail loop, stockyard, conveyor system and ancillary facilities is on an approximate205haareaoflandimmediatelywestoftheKCTandNCIGcoalterminals.Thislandispart privatelyowned land owned by PWCS and part public land. PWCS has a formal agreement with Newcastle Ports Corporation (NPC) for a long term lease of the public land, provided PWCS can demonstrate that it can successfully build and operate a coal terminal on the site. This land has previously been used for disposal of industrial waste and dredgematerial andcomprises a completely modifiedlandscape.Itisdominatedbygrassland,alongwithartificiallyconstructeddrainagedepressions and ponds, which now support wetland communities and provide habitat for a range of native and migratoryfaunaspecies.AdescriptionofpastlandusesisprovidedinSection2.2.

Theshipping berthsareproposedtobelocatedalongthenorthernandsouthernbanksoftheHunter Riversoutharm,tothesouthoftheproposedlandbasedfacilitiesandCormorantRoad,andtothewest oftheexistingberths(seeFigures1.2,3.1and3.2).Thereiscurrentlyastripofremnantmangroveand saltmarshvegetationonthenorthernbankoftheHunterRiversoutharm,inthelocationoftheproposed shippingberths.

1.4 NeedfortheProject

TheneedfortheprojectisdrivenbytherequirementforadditionalcoalexportcapacityatthePortof Newcastle. From a revenue perspective, coal is NSW’s and Australia’s largest commodity export, exportingtomorethan30countries.Bituminouscoalaccountedforaround$12.9billionofNSWexport revenuein20082009,whichisaroundathirdofthetotalNSWexportrevenueforthisperiod(Australian BureauofStatistics,2010).ThegreatestportionofthisisshippedfromthePortofNewcastle.

Inrecentyearstherehasbeenasubstantialincreaseinthedemandfor,andproductionof,HunterValley andGunnedahbasincoal.WhilstPWCShasrespondedtotheincreaseddemandwithalmostcontinual upgrades and expansion since 1996, regional coal production and export demand has outstripped the capacityoftheport’scoalexportfacilities,leadingtoreducedefficiencies,largeoffshorevesselqueues and associated environmental, safety and economic costs and risks. The recently endorsed Capacity FrameworkArrangementsweredevelopedtounderpinthelongtermoperationoftheHunterValleyCoal Chainandprovideasolutiontothegrowingcapacityconstraints.

AspartofitsobligationsundertheCapacityFrameworkArrangements,PWCShasenteredintolongterm contractswithcoalproducersandisresponsibleforensuringitsportfacilitieshavesufficientcapacityto handle the contracted coal throughputs. Where a capacity shortfall is predicted which cannot be accommodatedbyfurtherexpansionoftheexistingPWCScoalloadingterminals,theCapacityFramework

2

ArrangementsincludealegalobligationforPWCStobuildanewterminal(T4).Constructionofanew terminalmustbefinalisedwithinfouryearsofthecapacityshortfallbeingformallyacknowledged.

ThecurrentinstalledcapacityofbothKCTandCCTis113milliontonnesperannum(Mtpa);approvalsare inplacetoliftcapacityto145Mtpa.Evenwiththeadditionalcapacityandefficienciesprovidedbythe approved upgrades and expansions, PWCS contracted allocations are forecast to exceed capacity in approximately2015.Furtherincreasesincoalproductionareanticipated.

Accordingly,undertheprovisionsoftheCapacityFrameworkArrangements,newcapacityisrequiredand PWCSmustbuildtheT4Project,eitheratthecurrentlyproposedlocationoratanalternativelocation withinthePortofNewcastle.FurtherdiscussionofthedriversandprovisionsoftheCapacityFramework ArrangementsisprovidedinSection2.5.

1.5 PurposeandcontentofthisPreliminaryEnvironmentalAssessment

ThepurposeofthisPreliminaryEnvironmentalAssessment(PEA)istoaccompanyaProjectApplicationby PWCSfortheproposedT4Project,inaccordancewithsection75EoftheEP&AAct.Thisdocumentis intended to brief the NSW Department of Planning (DoP) and other relevant government agencies as referred to by DoP, including the Commonwealth Department of Sustainability, Environment, Water, PopulationandCommunities(DSEWPC)andNewcastleCityCouncil(NCC)abouttheProjectApplication.

Specifically,thisdocumentprovidesthebasisfordiscussionsatthePlanningFocusMeeting(PFM)andfor theprovisionofEnvironmentalAssessmentRequirements(EARs)bytheDirectorGeneralofPlanning.

Thebodyofthisreportdescribes:

 thelocationandhistoryoftheT4Projectarea;

 theneedfortheT4Project;

 thedevelopmentproposalfortheT4Project;

 statutoryrequirementsforprojectdetermination;

 theproposedstakeholderengagementstrategy;

 aninitialassessmentofpotentialenvironmentalimpacts;and

 conclusionsidentifyingkeyareasforfocusintheEnvironmentalAssessment(EA).

3 The Terminal 4 Project | Preliminary Environmental Assessment Report

Aberdeen Davis Creek Kayuga N New South WalesCastle Rock Muswellbrook AY ILW RA OK RO NEWCASTLELB EL SSYDNEYW U M - N A L U

Denman Dungog Stroud NNEW ENGLAND HIGHWAY E W E Inset N Ravensworth G L A Booral N D H Jerrys Plains IG H W A Y NORTH COAST RAILWAY

Warkworth Singleton AY W 2 H Clarence Town IG H C WOLLEMI FI CI NATIONAL PPACIFICA HIGHWAY PARK Bulga Branxton Karuah

Soldiers Point Maitland The T4 Project Area Broke Raymond Terrace Anna Bay

Williamtown Kurri Kurri Cessnock The T4 Project Area

Stockton NEWCASTLE Putty

Toronto

Morisset

Wyee

Budgewoi

Wyong

Somersby The Entrance Ourimbah

GOSFORD TASMAN SEA Terrigal

Woy Woy

Integrated Design Solutions Integrated Kilcare Brooklyn Kurrajong Richmond Palm Beach Windsor

KEY National park Mona Vale Hornsby State forest Highway Railway Main road Manly Parramatta Water course Town SYDNEY 05101520 25km

030418 Option 3-5 F1.1 Locality plan Rev E - 24 November 2010 © E - 24 November plan Rev 030418 Option 3-5 F1.1 Locality FIGURE 1.1 EMGA MitchellMcLennan Locality plan N

FIGURE 1.2

d

a

o

R

y The T4 Project a

B

n FERN BAY

o

s

l

e UTRRVR-NrhArm North - RIVER HUNTER

Nelson Bay Road Bay Nelson

N STOCKTON

STOCKTON BRIDGE STOCKTON Walsh Point

HARBOUR NEWCASTLE n l l o t a a g n n i i n i r m m r r r a e e T T C

l l S a a l C o o a Coal Terminal C National Park National C W n Hunter Estuary Hunter

i PWCS Carrington PWCS P g n m r a e g t a

r t r o

o HUNTER RIVER - South Arm o EAST p K

x S e

C l MAYFIELD The Terminal 4 Project | Preliminary Environmental Assessment Report Assessment Environmental | Preliminary 4 Project The Terminal a W o PWCS Kooragang Coal Terminal Kooragang P PWCS c

) y G

I a

C w

N h (NCIG) coal export terminal export ( (NCIG) coal

e g

i

T

R

I P P E R

/ C

O

N

V EYE Y O

R

RAR

A II L v

i MAYFIELD H Reserve r

c D i f

l i

a c i 3 NORTH

2 a Kooragang Nature Kooragang

T R

I P P E R R E / C A R O N r RAR V A E II L Y O

R

RRA F A ROR II LL O

N

T

R

A IIL L

S

H

UTU

T T L E

T R

A V E L

S H

UTU

T TLT L E

T R

A V EEL L t PPacific Highway

R

E A R

R R TRT

A R ILI II L P P E R/R

/ C

O

N

V E Y

ORO MAYFIELD

R

R R

A ILI L

s u

1

d

n

nutilDrive I Industrial WARATAH WEST MAYFIELD

d a o R d

ISLAND n la it

KOORAGANG a LAMBTON

BRIDGE MMaitland Road

Wetlands

Kooragang

d

a

TOURLE STREET TOURLE o

R

ain Road d MMain Road

n

e

d s

l

a l

a

o

R

Wallsend Road W Wallsend

e

l

t

s

a c

TOMAGO

w

e

ecsl Road N Newcastle

y

a

w Swamp Hexam

h Reserve Nature

g

i

H

c

i

f i

c

a

aii Highway Pacific P WALLSEND HEXHAM MARYLAND FLETCHER LENAGHAN

BERESFORD

e

v

i

r

D

w

a

h McLennan

s

n

e R

2 2.5

n

h

o

onRnhwDrive Renshaw J John 1.5 t e e r Mitchell t S 1 le t s

a Existing railway stockyard Proposed rai (RailProposed option 3 shown) berths Proposed c 0.5 w e

NNewcastle Street 1 2 3 0 3km

KEY

EMGA Integrated Design Solutions Design Integrated 030418 Options 3-5 F2 Re v C- 24 November 2010 © 2010 November 24 C- v Re F2 3-5 Options 030418 The Terminal 4 Project | Preliminary Environmental Assessment Report

N

BOGGABRI

WHITEHAVEN Tamworth GUNNEDAH Gunnedah Curlewis

Werris Creek WERRIS CREEK Quirindi

WillowTree Ardglen

Murrurundi New South Wales Parkville Scone

Aberdeen Gloucester DARTBROOK STRATFORD ULAN BENGALLA Ulan ANVIL HILL

Coggan’s Creek Kerrabee Muswellbrook Sandy Hollow DURALIE Gulgong WILPINJONG MOUNT ARTHUR St. Helliers Grasstree DRAYTON Antiene LIDDELL NEWDELL HUNTER VALLEY MOUNT OWEN RAVENSWORTH MACQUARIE GENERATION UNLOADER CAMBERWELL WAMBO LOOP ASHTON RIXS CREEK Singleton MTCL 1

MTCL 2 BULGA Cessnock Maitland NCIG KOORAGANG ISLAND PWCS AUSTAR PWCS

Integrated Design Solutions Integrated BLOOMFIELD TERALBA NEWCASTLE NEWSTAN Broadmeadow

Morisset UNLOADER VALES PT. UNLOADER

TASMAN SEA Sydney

KEY

Ship loading facility Mine loading facility Powerstation unloading facilites Town

030418 Option 3-5 F1-3 Rev B - 19 November 2010 © B - 19 November Coal Chain Rev Valley 030418 Option 3-5 F1-3 Hunter FIGURE 1.3 EMGA MitchellMcLennan Hunter Valley Coal Chain

2 Background

2.1 HistoryofKooragangIsland

KooragangIslandwasoriginallyaseriesoflowlyingdeltaicislands,includingAsh,DempseyandMoscheto Islands,locatedintheHunterRiverestuary.PriortoEuropeansettlementtheseislandswereoccupiedby theWorimiandAwabakalpeople.FollowingEuropeansettlementandupuntiltheearly1900s,landuse waspredominatelyagricultural.

LandreclamationcommencedinpartsoftheHunterRiverestuaryinthe1880s,usingdredgespoilfrom NewcastleHarbour,andtheareabegandevelopingastheindustrialcentreforNewcastleintheearlyto mid1900s.Intheearly1950s,withthecommencementoftheKooragangIslandDevelopmentScheme and the Newcastle Harbour Improvements Act 1953, the NSW Department of Public Works was given ownership of the islands and the responsibility to construct a ‘single land mass’ for industrial developmentandportrelatedactivities.Extensivelandreclamationwassubsequentlyundertaken,using dredgespoil,andtheislandswerejoinedtoformKooragangIsland.

Developmentofheavyandlightindustries,transportanddistributioninfrastructure,wasteemplacement facilitiesandportfacilitieshascontinuedsincethistimewithinthesoutheasternportionoftheisland (seeFigure1.2).ThishasincludedestablishmentoftheKCTand,morerecently,NCIGhascommenced construction and operation of Newcastle’s third coal export terminal on land adjacent to the KCT. DredgingofthesoutharmoftheHunterRiverinassociationwiththedevelopmentandoperationofport facilitieshasbeenongoing.

ThelandtothenorthoftheKooragangindustrialandportareawasdedicatedasanaturereserve,the KooragangNatureReserve,in1983.ThisreservewassubsequentlyincorporatedintotheHunterEstuary National Park. It forms part of the broader ‘Hunter Estuary Wetlands’, which were designated as a Ramsarsitein1984.

2.2 HistoryoftheT4ProjectArea

Much of the T4 Project area has been used for disposal of industrial waste and dredge material. The southern and western parts of the T4 Project area comprise the former Kooragang Island Waste EmplacementFacility,whichisstilllicensedasaSolidWasteClass2landfill.Thiswasteemplacement facilitywasoperationalfrom1972until1999,duringwhichtimewasteproductsfromtheformerBHP Steelworkswereburiedacrossthesite.Thisincludedslag,sludges,coalwasheryfinesandcoarserejects, andarangeofindustrialandgeneralwaste,includingasbestos.UponclosureoftheBHPSteelworksin 1999, ownership of the waste emplacement facility was transferred to the NSW Government and its operationceased.

TheothersignificantwasteemplacementtooccurwithintheT4Projectareahasbeenthedisposalof wastefromanelectrolysismanganesedioxide(EMD)plantinpurposebuilttrenchesacrossitsnorthern extent.ThishasbeenundertakenbytheAustralianManganeseCompanyLimited(asubsidiaryofBHP Billiton), and then by Delta EMD Australia Pty Limited, since 1989. The EMD plant closed in 2008, although periodic waste disposal continued to occur up until late 2009 in association with the plant closureactivities.TheDeltaEMDsiteislicensedasawasteemplacementarea.

7

2.3 HistoryoftheKooragangCoalTerminal

The KCT, originally owned and operated by Kooragang Coal Loader Limited, commenced operation in 1984,withaninitialthroughputcapacityof21Mtpa.ItwasacquiredbyPWCSin1990.TheKCTincludes rail receival infrastructure, stockpiling areas, coal stackers and reclaimers and a dedicated conveyor systemwhichcarriesthecoaltoshiploadersforexporttomarket.

PartofthelandonwhichtheKCTissituatedisleasedfromtheNSWGovernment.Theleaserequiresthat theKCTbeoperatedasa‘commonuserfacility’,whereinPWCSisrequiredtoprovideaccessonanon discriminatorybasistoallproducerswhowishtoshipcoal.

To meet the increasing demand for NSW coal, and associated growth of the coal industry, PWCS has implemented a continuous program of expansion and efficiency improvements. This has included additionofasecondandthirdterminaltotheKCT.Mostrecently,developmentconsent(DA060189) wasmodifiedtoallowtheconstructionandoperationofafourthdumpstation,fourthshiploaderand associatedcoalhandlingandtransportinfrastructuretoprovidefor‘sprintcapacity’,referredtoasthe ‘Stage4Project’.ConstructionoftheStage4Projecthasnowcommenced.

TheKCTisanintegralcomponentoftheHunterValleyCoalChainandistheworld’slargest(intermsof throughput)andmostefficientcoalhandlingfacility,withanapprovedthroughputcapacityof120Mtpa. Additionalcapacityisnowrequired,andtheT4Project,subjectofthisPEA,isproposedtoprovidethis.

2.4 Existingmaritimeapprovals

TheNSWMaritimehasStateapproval(DA13432003i)fortheextensionofshippingchannelswithinthe port,toapointjusteastoftheTourleStreetBridge,andinclusiveofaswingbasinforturningofvessels. Theapprovedactivitiesincludedredging,excavation,treatmentanddisposalofsedimentsfromthesouth armoftheHunterRiver,toprovidedeepwateraccesstofutureberthsites,inclusiveoftheproposed berthsitesfortheT4Project.

TheapprovedactivitiesaredetailedinaStrategicDredgingProgram,whichwasdevelopedbytheNSW Maritime,andcomprisessevenphases ofworks. Eachphaseisforadifferentpartofthechannel,as requiredbythevariousprojectsandproponentsalongtheHunterRiversoutharm,includingexpansionof coalexportfacilitiesbyNCIGandPWCS.Phases1and2arelocatedattheeasternextentoftheshipping channelsextensionarea,commencingapproximatelyoppositetheexistingKCTberths,andPhase7isat the western extent, near the Tourle Street Bridge. It is noted that the private sector proponents proposingtocarryoutdredgingworksinthesoutharmoftheHunterRiverunderDA13432003imust seekapprovalsanddredginglicensesfromtheoverallconsentholderNSWMaritimeinadditiontothe requisitelicences,permitsandapprovalsfromotherauthorities.

TheStrategicDredgingProgramwasdeemeda‘controlledaction’undertheEnvironmentProtectionand Biodiversity Conservation Act 1999 (EPBC Act) by the Department of Environment and Heritage (now DSEWPC),andaccordinglyisalsosubjecttoaCommonwealthapprovalundertheEPBCAct(Reference: 2003/950),grantedtoNPCon30May2007.TheexistingCommonwealthapprovaldoesnotcoverPhases 6and7oftheStrategicDredgingProgram,althoughthesewereincludedintheoriginalEPBCActreferral toDSEWPC.

Severalmodificationshavebeenmadetotheoriginalconsent.ApplicationsbyNPCtomodifyDA1343 2003iandtheCommonwealthapproval,torelocatetheproposedswingbasinapproximately400metres (m)downstream(east)ofthecurrentapprovedlocation,arecurrentlypending.

8

TheStrategicDredgingProgramcommencedin2007,andisongoingforworksassociatedwithPhases1 to4.Noprojectstodatehavetriggeredtheneedforshippingchannelstoextendtothewesternlimitof theirapprovedextentand,assuch,Phases5,6and7havenotyetcommenced.Thesephaseswould likelyrequireamodificationtotheexistingCommonwealthapproval,andarelikelytorequireanewEPBC Actreferral.

It is noted that any sea disposal of dredged material associated with the T4 Project would require separate permit(s) under the Commonwealth Environment Protection (Sea Dumping) Act 1981 and a licenceundertheNSWCrownLandsAct1989(seeSections4.4.4and4.4.5).

2.5 Commercialframework

As outlined in Sections 1.1 and 1.4, PWCS is bound by the provisions of the Capacity Framework Arrangements for the Port of Newcastle, as approved by the Australian Competition and Consumer Commission(ACCC)in2009.TheCapacityFrameworkArrangementsweredevelopedfollowingextensive discussions and negotiations between the NSW Government and the Hunter Valley coal industry, and formacriticalpartofthelongtermcoalexportplanfortheregion.Theytookeffecton1January2010 andapplyuntil31December2024.

TheCapacityFrameworkArrangementsareintendedtoprovideasolutiontotheuncertaintyandongoing capacityconstraintsexperiencedintheHunterValleyCoalChain,byfacilitatinglongtermcontractsto underpin and align more efficient and timely investment and promote optimal operation of the coal chain. They also seek to reduce offshore vessel queues and associated demurrage costs and environmentalandsafetyrisks,andmaintainorimprovetheinternationalreputationandperformanceof theHunterValleycoalindustry.

KeycomponentsoftheCapacityFrameworkArrangementsincludethefollowing.

 TheallocationofportcapacitytoaccessseekersatthePWCSterminalsunderlongtermcontracts, inaccordancewithprescribednominationandallocationprocedures.

 TriggersandprocessesfordeterminingwhetherandwhenexpansionsofthePWCScoalloading terminals are required (including the construction of a new terminal where necessary). This includes a requirement that PWCS must expand its existing coal loading terminals to provide additionalcapacityif:

- theaggregatePWCScontractedallocationsexceedtheaggregatePWCSavailablecapacity (thatis,CapacityShortfall);and

- theCapacityShortfallcannotbefulfilledthoughvoluntarycontractedallocationreductions.

 ArequirementthatiftheexistingPWCScoalloadingterminalsarenotcapableofbeingexpanded toprovidetheadditionalcapacitytosatisfytheCapacityShortfall,thenPWCSmustbuildanew terminal(T4).

AspartofitsobligationsundertheCapacityFrameworkArrangements,PWCShasenteredintolongterm ‘shiporpay’contractswithcoalproducers,wherebythecoalproducersmustpayforcontractedcapacity atthePWCSterminalsregardlessofactualcapacityused.Inturn,tohonouritscontractualobligations, and manage the ongoing export demand for Hunter Valley and Gunnedah basin coal, PWCS has the responsibility of ensuring its port facilities have sufficient capacity to handle the contracted coal throughputs.

9

As mentioned in Section 1.4, PWCS contracted allocations are forecast to exceed capacity in approximately2015,withdemandexpectedtocontinuetoincreasebeyondthistime.Accordingly,under theprovisionsoftheCapacityFrameworkArrangements,newcapacityisrequiredandtheT4Projecthas beentriggered.

ItshouldbenotedthatiftheT4Projectisunabletoprovidesufficientcapacitytohandlecontractedcoal throughputsinthefuture,PWCSwillberequiredtodevelopanothercoalterminalinNewcastle.

10

3 Projectdescription

3.1 Introduction

PWCS proposes to extend the KCT to the west to provide additional coal throughput capacity, in accordancewithitsobligationsundertheCapacityFrameworkArrangements.Theproposedextension would enable optimisation of synergies with the existing infrastructure, systems and workforce at the KCT. This would include some sharing of facilities and environmental management and monitoring systems.

A number of design options for the key project components are currently being investigated, with considerationtooperational,environmentalandeconomicfactors.Thefinaldesignwillbeinfluencedby thefindingsoftheEAandwillbepresentedandassessedaspartoftheEA.KeycomponentsoftheT4 Projectareoutlinedinthefollowingandthefootprintsunderconsiderationforeachofthesecomponents areillustratedschematicallyonFigures1.2,3.1and3.2.

3.2 Railloop

Severaloptionsforaraillooptoreceivecoalarebeingexamined.Thetwopreferredoptionsatthisstage areRailOptions5and3.

RailOption5includestheprovisionofraillinestothewestandnorthoftheexistingraillinesservicing KooragangIsland(refertoFigure3.1).Trainswouldgenerallyfollowthesamealignmentastheexisting raillineservicingKCT.Whilethislandtothewestandnorthiszonedforportfacilities,itismostlyowned by the Department of Environment, Climate Change and Water (DECCW) and is proposed to be incorporatedintotheHunterEstuaryNationalPark.

RailOption3generallyfollowsthesamealignmentasNCIG’srailloop(bothexistingandapproved).Rail lineswouldbeprovidedontheoutsideofNCIG’srailloop(refertoFigure3.2).LikeRailOption5,this optioninvolvestheconstructionofraillinesonDECCWownedland,tothewestofthejunctionofthe NCIGrailloop.

Bothoptionsincludeaflyoveroverthemainbranchtoavoidbottleneckingfrominboundtrainswaiting for outbound trains to exit Kooragang Island. Construction of the flyover would also necessitate the constructionofatemporaryraillinearoundtheconstructionsite,ontheDECCWland.Thistemporaryrail line would facilitate uninterrupted rail access for all current Kooragang branch users throughout the constructionphase.

Toavoidtheneedforaflyover,therearealsooptionsfordivertingtheexistingdeparturetracksonthe KooragangmainbranchonanewalignmentacrosstheeasternendoftheT4Projectareaandaroundthe southernsideoftheNCIGrailloop.ConstructionofraillinesacrosstheeasternendoftheT4Projectarea wouldrestrictaccessbetweenKCTandtheT4Projectareaandwouldreducethesizeandcapacityofthe proposedstockyard.

Thefinalpreferredrailoptionwillbeinfluencedbytechnicalassessmentsandoutcomesofconsultation withrelevantstakeholders,andwillbepresentedintheEA.

11

3.3 Stockyard

The stockyard, incorporating coal stockpiles, stacking, reclaiming and coal transport systems, e.g. conveyors and transfer stations, would be located immediately west of the existing KCT and NCIG stockyards(seeFigures3.1and3.2).Duringconstruction,cutandfillearthworkswouldbeundertaken acrosstheproposedstockyardarea.Currentestimatessuggestthatintheorderof4to5millioncubic metresoffillcouldberequired,dependingonthefinaldesignofthestockyard.Thisfillisproposedtobe sourced as dredge material from the Hunter River, potentially supplemented by fill trucked in from elsewhere.

A range of stockyard configurations and development programs are being investigated, with consideration to various stockpile types, stockyard machines and stockyard capacities. Filling and developmentofthestockyardmaybeundertakenacrossthewholesiteattheoutset,orbeundertaken progressively.Thecurrentpreferredoption(Type3AStockyard)ispresentedinFigures3.1and3.2.The final preferred option will be influenced by technical assessments and outcomes of consultation with relevantstakeholders,andwillbepresentedintheEA.

Thestockyardreclamationareawouldbedividedintotwomainareas,fillpondsforhydraulicplacement of dredged material, and settlement ponds for managing return water and settling out fines prior to dischargeofreturnwaterbackintotheHunterRiver.

Closure and capping of waste emplacement areas is proposed to be undertaken prior to or during developmentoftheT4Project.

3.4 Conveyorsystem

The coal conveyor and feeder system is proposed to extend throughout the stockyard, to deliver coal fromrailreceivaltothestockpiles.Conveyorswouldalsoextendsouth,totheberthsalongtheHunter River,todelivercoaltotheshiploaders.ThiswouldinvolveaconveyorcrossingofCormorantRoadand theHunterRiver.

3.5 Berths

Berthing, wharf and shiploading facilities are proposed to be located along the northern and southern banks of the Hunter River south arm, immediately south of the landbased facilities and west of the existingberths(refertoFigures3.1and3.2).

Atthisstage,uptofiveberthsareproposed,toprovideberthingforavarietyofvesselsrangingfrom Handysize(35,000tonnes)toCapesize(150,000tonnes).Maximisingthepotentialthroughputofthese berthswouldrequiretheinstallationofshiploadersonallwharves.

Dredging for extension of the shipping channels and access to the berth sites would be carried out in accordance with the existing NSW Maritime development consent (DA13432003i) and any Commonwealth approvals. Accordingly, it does not form part of the current Project Application. Sea dumping permits for dredge material unsuitable for use as engineering fill would be sourced under parallelprocesses,ifrequired.

12

3.6 Ancillaryfacilitiesandactivities

AncillaryfacilitiesproposedtosupporttheT4Projectincludethefollowing:

 electricitysupplyandanew33kV/11kVsubstation;

 switchrooms;

 dustsuppressionandfirefightingsystems;

 washdownfacilities;

 waterandwastewatermanagementsystems;

 securityfences;

 ITanddatalinks;

 refuellingfacilities;

 amenities;

 administrationandworkshopbuildings;

 internalaccessroads;and

 externalaccessroad(s).Accessroadalignmentsareyettobefinalised,butaccesstothestockyard andberthswouldmostlikelybefromCormorantRoad.

TheancillaryrequirementsarereducedbytheproposedsharingofthefacilitiesattheexistingKCT.

Construction of the T4 Project would potentially require relocation of some existing services such as transmissionlines,gaslines,waterlines,fibreopticcableandroads.ThismayincludepartofCormorant Road,toaccommodatetheproposedrailloopunderRailOption3.

13 N N O T FIGURE 3.1 K Fern Bay Fern C O T

S STOCKTON

UTRRVR-NrhArm North - RIVER HUNTER

STOCKTON BRIDGE STOCKTON Greenleaf Road Greenleaf The T4 Project with Rail Option 5 The T4 Project 12 WALSH POINT WALSH

NEWCASTLE HARBOUR NEWCASTLE

11 eo Road Heron The Terminal 4 Project | Preliminary Environmental Assessment Report Assessment Environmental | Preliminary 4 Project The Terminal l a n i m r e T

l a o C

n o t g n i r r a C 10

S

Raven Street 14 C Hunter Estuary National Park National Estuary Hunter

W ge Street Egret PWCS Carrington Coal Terminal Carrington P PWCS 9 D L E T I S F A Y E HUNTER RIVER - South Arm EAST A M MAYFIELD (NCIG) coal export terminal export (NCIG) coal D L PWCS Kooragang Coal Terminal Kooragang PWCS D E L I H Pacific Highway F E T

I

Y rvt cesRa PcfcNational) (Pacific Road access Private R F A Y 7 O 13 A M MAYFIELD N NORTH M MAYFIELD

T R

I P P E R

// C

O

N

V E Y OO

R

RR

AA IIL L

5 Cormorant Road Cormorant 6

6 Industrial Drive Industrial

T R

I P P E R R E / A C R O

N R V A E II L Y O

RR

R F A R II O LL

N

T

R

A I L

S H

U

T T L E

TTR R

A V E L

S H

U

T T L E

T R

A V E L

R

E A R

R T A R II I L P P E R

/ C

O

N

V E Y O

RR

RR

AA II LL

D 2 3 Street Tourle L 1 T E I S F E Y WEST W A MAYFIELD M STREET TOURLE 15 McLennan 2 0.4 0.6 0.8 8 Mitchell 4 0.2 T4 Project area T4 Project Existing railway stockyard type 3A Proposed pond locations Potential conveyor Proposed rail option 3 Proposed T4 dumpstation marine option 2 Proposed swing basin Proposed Approved NCIG rail line Boral Cement Cargill Oilseed Processor Manufacturing Fertilizer Incitec Pivot Orica OneSteel BHP Land Former BHP Billiton emplacement area 7 8 9 6 5 1 2 3 4 10 11 12 13 14 15 0 1km

Pacific Highway KEY

EMGA Integrated Design Solutions Design Integrated 030418 Option 3-5 F1 Re v C- 24 November 2010 © 2010 November 24 C- v Re F1 3-5 Option 030418 N N O T FIGURE 3.2 K Fern Bay Fern C O T

S STOCKTON

UTRRVR-NrhArm North - RIVER HUNTER

STOCKTON BRIDGE STOCKTON Greenleaf Road Greenleaf The T4 Project with Rail Option 3 The T4 Project 12 WALSH POINT WALSH

NEWCASTLE HARBOUR NEWCASTLE

11 eo Road Heron The Terminal 4 Project | Preliminary Environmental Assessment Report Assessment Environmental | Preliminary 4 Project The Terminal l a n i m r e T

l a o C

n o t g n i r r a C 10

S

Raven Street 14 C Hunter Estuary National Park National Estuary Hunter

W ge Street Egret PWCS Carrington Coal Terminal Carrington P PWCS 9 D L E T I S F A Y E HUNTER RIVER - South Arm EAST A M MAYFIELD (NCIG) coal export terminal export (NCIG) coal D L PWCS Kooragang Coal Terminal Kooragang PWCS D E L I H Pacific Highway F E T

I

Y rvt cesRa PcfcNational) (Pacific Road access Private R F A Y 7 O 13 A M MAYFIELD N NORTH M MAYFIELD

T R

I P P E R

// C

O

N

V E Y OO

R

RR

AA IIL L

5 Cormorant Road Cormorant 6 4

6 Industrial Drive Industrial

T R

I P P E R R E / A C R O

N R V A E II L Y O

RR

R F A R II O LL

N

T

R

A I L

S H

U

T T L E

TTR R

A V E L

S H

U

T T L E

T R

A V E L

R

E A R

R T A R II I L P P E R

/ C

O

N

V E Y O

RR

RR

AA II LL

D 2 3 Street Tourle L 1 T E I S F E Y WEST W A MAYFIELD M TOURLE STREET BRIDGE STREET TOURLE 15 McLennan 2 0.4 0.6 0.8 8 Mitchell T4 Project area T4 Project Existing railway stockyard type 3A Proposed pond locations Potential conveyor Proposed rail option 3 Proposed T4 dumpstation marine option 2 Proposed swing basin Proposed Approved NCIG rail line Boral Cement Cargill Oilseed Processor Manufacturing Fertilizer Incitec Pivot Orica OneSteel BHP Land Former BHP Billiton emplacement area 0.2 7 8 9 6 5 1 2 3 4 10 11 12 13 14 15 0 1km

Pacific Highway KEY

EMGA Integrated Design Solutions Design Integrated 030418 Option 3-5 F2 Re v C - 24 November 2010 © 2010 November 24 - C v Re F2 3-5 Option 030418

“Thispagehasbeenintentionallyleftblank”

16

4 Approvalrequirements

4.1 Introduction

TheT4ProjectwillbeassessedundertheprovisionsofPart3AoftheEP&AAct.

A referral will be made under the Commonwealth EPBC Act. If an approval is required under this legislation,theintentionwouldbethatCommonwealthmattersareassessedviathePart3Aprocess,in accordancewithabilateralagreementbetweentheCommonwealthandtheState.

ThischapterdescribestheapprovalprocessunderboththeEP&AActandEPBCAct.Anoverviewofother approvalsthatmayberequiredfortheT4Projectisalsoprovided.

4.2 NSWEnvironmentalPlanningandAssessmentAct1979

4.2.1 Approvalprocess

The EP&AActandtheEnvironmentalPlanningandAssessmentRegulation2000providetheframework for environmental planning and assessment in NSW. Part 3A of the EP&A Act relates to major developmentdeemedtobesignificanttotheState.Section75B(1)oftheActstatesthatPart3Aapplies to:

“…thecarryingoutofdevelopmentthatisdeclaredunderthissectiontobeaprojecttowhichthisPart applies:

(a) byaStateenvironmentalplanningpolicy,or

(b) byorderoftheMinisterpublishedintheGazette.”

State Environmental Planning Policy (Major Projects) 2005 (Major Projects SEPP) defines certain developmentsthatfallunderPart3A,i.e.developmentdeemedtobesignificanttoNSW.Clause6ofthe MajorProjectsSEPPstates:

“(1) Developmentthat,intheopinionoftheMinister,isdevelopmentofakind:

(a) thatisdescribedinSchedule1or2,or

isdeclaredtobeaprojecttowhichPart3AoftheActapplies.”

PortsandwharffacilitiesareaformofdevelopmentdescribedinSchedule1oftheMajorProjectSEPP. Clause22ofSchedule1definesportsandwharffacilitiesas:

“Development for the purpose of shipping berths or terminals or wharfside facilities (and related infrastructure)thathascapitalinvestmentvalueofmorethan$30million.”

TheT4Projectmeetsthisdefinitionasitisadevelopmentforthepurposeofshippingberthsandwharf sidefacilitiesthathasanestimatedcapitalvalueintheorderof$3,500million.

UnderPart3A,theMinisterforPlanningistheconsentauthority.

17

Assuch,theT4ProjectwillbeassessedundertheprovisionsofPart3AoftheEP&AAct.Therearenine main steps in this process, starting with a declaration by the Minister that a development is a major projectandendingwiththeMinister’sdetermination.EachstepisdescribedinTable4.1below.

Table4.1 Part3Aapprovalprocess

Step Actions 1.Declaration TheproponentmakesaformalrequesttotheMinisterforPlanningtodeclarethe projectasamajorprojecttobeassessedunderPart3A. TheMinistermakesanassessmentwhethertodeclaretheproject. 2.ProjectApplication AProjectApplicationissubmittedtotheDoP,whichcanbeaccompaniedbyaPEA,to obtaintermsofreferenceknownasEARs. 3.PlanningFocusMeeting APFMiscommonlyheldwithgovernmentagenciestodiscusstheproposal. 4.EARs TheDirectorGeneraloftheDoPissuesEARsfortheproposeddevelopmentwhich mustbeaddressedinanEA. 5.PreparedraftEA AdraftEAispreparedbytheproponentaddressingtheEARsissuedbytheDirector General. DuringpreparationofthedraftEA,theproponentconsultswithrelevant stakeholdersincludingthecouncil,governmentagenciesandthecommunity. Oncesubmitted,theDirectorGeneralassessestheadequacyofthedraftEAagainst theEARs. 6.Publicexhibition Ifadequate,theEAisfinalisedandplacedonpublicexhibitionforaperiodofnotless than30days. 7.Considerationofsubmissions Theproponentrespondstoallsubmissionsmadeduringthepublicexhibition process. Ifchangesaremadetotheproposeddevelopmenttoaddressconcerns,the proponentgenerallypreparesapreferredprojectreport. 8.Assessmentreport TheDirectorGeneralprovidesanassessmentreporttotheMinisterwitha recommendationastowhethertheproposeddevelopmentshouldbeapprovedor refused. 9.Determination TheMinisterapprovesandsetsassociatedconditionsorrefusestheapplication.

4.2.2 OtherStateapprovals

Thereareanumberofapprovals,authorisationsandlicencesunderotherlegislationthatapplytotheT4 Project.ItisimportanttonotethatiftheprojectisapprovedunderPart3Atherearealsoanumberof approvalsthatcannotberefused,althoughnecessaryconditionscanbeapplied.

Section 75U of the EP&A Act lists the approvals under other legislation that do not apply to projects approvedunderPart3Aandtheseare:

 theconcurrenceunderPart3oftheCoastalProtectionAct1979oftheMinisteradministeringthat PartoftheAct;

 permitsundersection201,205or219oftheFisheriesManagementAct1994;

 anapprovalunderPart4,oranexcavationpermitundersection139,oftheHeritageAct1977;

 a permit under section 87 or a consent under section 90 of the National Parksand WildlifeAct 1974;

 anauthorisationreferredtoinsection12oftheNativeVegetationAct2003(orunderanyActtobe repealedbythatAct)toclearnativevegetationorStateprotectedland;

18

 apermitunderPart3AoftheRiversandForeshoresImprovementAct1948;

 abushfiresafetyauthorityundersection100BoftheRuralFiresAct1997;

 awateruseapprovalundersection89,awatermanagementworkapprovalundersection90oran activityapprovalundersection91oftheWaterManagementAct2000;and

 Division 8 of Part 6 of the Heritage Act 1977 does not apply to prevent or interfere with the carryingoutofanapprovedprojectunderPart3A.

Section 75V of the EP&A Act lists the authorisations and licences under other legislation thatmust be obtainedbutcannotberefusediftheyarenecessaryforcarryingoutprojectsapprovedunderPart3A.Of relevancetotheT4Projecttheseare:

 anenvironmentprotectionlicence(EPL)undertheProtectionoftheEnvironmentOperationsAct 1997(POEOAct);

 aconsentundersection138oftheRoadsAct1993;and

 alicenceunderthePipelinesAct1967.

4.3 CommonwealthEnvironmentProtectionandBiodiversityConservationAct 1999

The EPBC Act aims to protect matters deemed to be of national environmental significance (NES) including:

 worldheritageproperties;

 placeslistedontheNationalHeritageRegister;

 Ramsarwetlandsofinternationalsignificance;

 threatenedfloraandfaunaspeciesandecologicalcommunities;

 migratoryspecies;

 Commonwealthmarineareas;and

 nuclearactions(includinguraniummining).

Ifanaction(orproject)will,orislikelyto,haveasignificantimpactonanyofthemattersofNES,itis deemedtobeaControlledActionandrequiresapprovalfromtheCommonwealthEnvironmentMinister ortheMinister’sdelegate.TodeterminewhetheraproposedactionwillorislikelytobeaControlled Action,anactionmaybereferredtoDSEWPC.

AsdiscussedinSection6.5,theT4ProjectmayhaveanimpactonthefollowingmattersofNES:Ramsar wetlands; threatened flora and fauna species and ecological communities; and migratory species. A referral is currently being prepared for the T4 Project for DSEWPC’s consideration. This referral will considerandassesswhethertheT4Projectwill,orislikelyto,haveasignificantonthesemattersofNES.

19

WhereanactionisdesignatedaControlledAction,theDSEWPCdecidesontheapproachtobeusedfor assessingtherelevantimpactsfromanyofthefivedifferentpathways.Oneoftheassessmentpathways is by an accredited process whereby a State or territory manages the assessment on behalf of the Commonwealth(oftenreferredtoasabilateralagreement).

On 17 June 2002, the Commonwealth accredited the NSW EA process under both the EP&A Act and ThreatenedSpeciesConservationAct1995(TSCAct).IftheT4ProjectisdeemedtobeaControlledAction andapprovalisrequiredundertheEPBCAct,theCommonwealthmayelectthattheactionisassessed undertheNSWbilateralagreementcoordinatedbytheDoP.

Ifabilateralagreementisused,acopyofDoP’sassessmentreportwouldbeforwardedtoDSEWPCon completionoftheStateprocess.TheCommonwealthEnvironmentMinistermustthenmakeadecision on whether to approve the taking of the action within 30 business days of receiving the assessment report.

The approvals schedule for the T4 Project has been developed to enable integration of the Commonwealthapprovalsprocess,ifrequired,intotheStateprocessunderabilateralagreement.The timing of the EPBC Act referral and Commonwealth Minister’s decision is such that if it is found that approval is required under the EPBC Act, the EARs could be developed to incorporate Commonwealth assessmentrequirements.

4.4 Otherapprovals

4.4.1 ProtectionoftheEnvironmentOperationsAct1999

TheT4ProjectwouldrequireanEPLundertheprovisionsofthePOEOAct.UnderSchedule1ofthePOEO Act,‘coalworks’requireanEPLiftheyhaveacapacitytohandlemorethan500tonnesperdayofcoalor they have the capacity to store more than 5,000 tonnes of coal. The T4 Project would meet these requirements.

TheT4ProjectareacurrentlyhasthreeEPLsthatrelatetoexistingusesonthesite:

 EPL6437heldbyHunterDevelopmentCorporation;

 EPL7675heldbyPWCSsinceitspurchaseofthesitefromDeltaEMDAustraliaPtyLimitedinJuly 2010;and

 EPL1552heldbyPWCS.

EPLs6437and7675permitwastedisposalassociatedwiththeKooragangIslandWasteFacility.EPL1552 permitscoalworksandshippinginbulkandisassociatedwiththeKCT.

Should the T4 Project proceed, full or partial surrender, consolidation or transfer of the three existing EPLswouldberequired.

The EA for the T4 Project will provide details on the above EPLs and the proposed process for surrendering,consolidatingortransferringtheselicencesintoanEPLfortheT4Project.

Aspreviouslystated,undertheprovisionsoftheEP&AAct,anEPLcannotberefusedifitisnecessaryfor carryingoutaprojectapprovedunderPart3A.

20

4.4.2 RoadsAct1993

Undersection138orPart9,Division3oftheRoadsAct1993,apersonmustnotundertakeanyworks thatimpactonaroad,includingconnectingaroad(whetherpublicorprivate)toaclassifiedroad,without approval of the relevant authority, being either the Roads and Traffic Authority or local council, dependinguponclassificationoftheroad.

AnapprovalundertheRoadsAct1993wouldberequiredfortheT4Projectgiventhatitisexpectedto necessitateanumberofworkstoCormorantRoad,potentiallyincluding:

 realignmentofpartoftheroad;

 provisionofnewaccesstotheroad;and

 provisionofpotentialconveyororservicescorridorsacrosstheroad.

Onceagain,undertheprovisionsoftheEP&AAct,anapprovalundersection138orPart9,Division3of theRoadsAct1993cannotberefusedifitisnecessaryforcarryingoutaprojectapprovedunderPart3A.

4.4.3 WaterManagementAct2000

Itislikelythatactivityapprovalswouldberequiredundersection91oftheWaterManagementAct2000 as part of the construction activities for the T4 Project, including controlled activity approval and an aquiferinterferenceapproval.

Onceagain,undertheprovisionsoftheEP&AAct,approvalsundersection91oftheWaterManagement Act2000cannotberefusediftheyarenecessaryforcarryingoutaprojectapprovedunderPart3A.

4.4.4 CrownLandsAct1989

Dredgematerialunsuitableforuseasengineeringfillisproposedtobedisposedofatsea.Accordingly,a licence would be required from the NSW Land and Property Management Authority under the Crown Lands Act 1989 to temporarily use certain Crown Land within the Coastal Waters of NSW for the deposition of dredge spoil. Provided this licence is obtained, approval for this activity would not be requiredundertheCoastalProtectionAct1979.

4.4.5 EnvironmentProtection(SeaDumping)Act1981

TheNPCreceivedinprincipleapprovalforseadisposalofallmaterialinthesoutharmdredgingfootprint from the DSEWPC (then Department of Environment and Heritage) in December 2003. However, DSEWPChassinceadvisedthatseadumpingpermitsneedtobesoughtbytheorganisationresponsible forthedredginganddisposaloperations.Accordingly,PWCSwouldberequiredtoseekCommonwealth approvalundertheEnvironmentProtection(SeaDumping)Act1981fordisposalofdredgedmaterialat sea.

4.4.6 Otherapprovals

Acomprehensivereviewofallrelevantlegislationandpolicieswillbeundertakenduringthepreparation oftheEA.AllapprovalsandlicencesrequiredfortheconstructionandoperationoftheT4Projectwillbe identifiedandreportedintheEA.Relevantapprovalsandlicenceswillalsobediscussedwithgovernment agenciesduringthestakeholderengagementprocess(refertoChapter5).

21

“Thispagehasbeenintentionallyleftblank”

22

5 Stakeholderengagement

5.1 Introduction

The T4 Project has the potential to generate considerable interest from stakeholders, including governmentagencies,thelocalcommunityandspecialinterestgroups.Inparticular,potentialecological, traffic, noise and dust impacts associated directly with the T4 Project, and related wider issues – expansion of coal mining, greenhouse gas emissions and climate change – all have the potential to generatecommunityconcern.

Toaddressthechallengesofidentifyingandengagingwiththerelevantstakeholdersandensuringissues raised are effectively addressed as part of the project planning and assessment, a stakeholder engagementstrategyhasbeenpreparedspecificallyfortheT4Project.Engagementhascommencedin accordancewiththisstrategyandissummarisedinthischapter.

5.2 Objectives

Theobjectivesofthestakeholderengagementstrategyincludethefollowing:

 to identify all relevant stakeholders who have an interest in the T4 Project and the ongoing operations of PWCS, including community groups who may identify themselves as the ‘affected community’;

 toprovidestakeholderswithaccurateandtimelyinformationontheT4Project;

 toidentifyandunderstandtheaspectsoftheT4Projectwhichareofmostinteresttostakeholders;

 to seek feedback on the design of the T4 Project and the proposed approaches to minimising impactsonthelocalcommunity,andidentifyopportunitiestoaccommodatecommunityfeedback intotheprojectdesign;and

 toestablishrelationshipswiththecommunitywhichcanbeutilisedinthefuturetothebenefitof thecommunityandPWCS,suchaspartneringinlongtermcommunitydevelopmentprojects.

5.3 Stakeholderengagementstrategy

The key components of the stakeholder engagement strategy are initial stakeholder identification, stakeholderassessmentandstakeholderengagement.Eachofthesecomponentsisdescribedbelow.

5.3.1 Initialstakeholderidentification

The initial stakeholder identification process is complete. This task involved compiling a list of all stakeholderslikelytoberelevanttotheT4Project.ItlargelydrewonPWCSexistinginformationand understandingofthecommunityinwhichitoperates.

The broad stakeholder groups identified include NCC, State and Commonwealth government agencies, the local community and nearest residential neighbours, special interest groups, Aboriginal groups, neighbouring industry, industry representative groups, employees of PWCS, State and Commonwealth membersandministersandthemedia.

23

ThestakeholderlistwillberegularlyreviewedandupdatedthroughouttheEAandthedevelopmentof theT4Project.

5.3.2 Stakeholderassessment

Following the ‘initial stakeholder identification’, an assessment of the stakeholders was undertaken to furtherunderstandtheextenttowhichthevariouspartieswerelikelytobeimpactedbyand/orhavean interestintheT4Project.Thepurposeofthisexercisewastoinformthedevelopmentofappropriately tailoredstakeholderengagementstrategiesandschedule.

5.3.3 Stakeholderengagement

Theinitialroundofstakeholderengagementhascommencedwithintroductionoftheprojectconceptto anumberofstakeholders.

Once sufficient detail has been prepared on potential development options for the T4 Project, it is proposedtoreengagewithallstakeholders.Thiswouldbetoprovideanupdateonprojectprogress, introducetheoptionsbeingconsidered,andseekfeedbackonthese.

As the project progresses additional stakeholder engagement would be undertaken. This would be to discuss the preferred option selected, expected environmental and community impacts, and planned mitigation, and seek feedback on these. As part of this engagement, it would be possible to provide feedbackonhowtheresultsofpreviousengagementhavebeentakenintoaccountintheprojectdesign.

StakeholderengagementisproposedtocontinuethroughouttheimplementationoftheT4Project.

5.4 StakeholderEngagementTools

A range of formal and informal stakeholder engagement tools will be used according to the particular needsofindividualstakeholders.Thesewillincludephonecalls,meetingsandbriefingsessions,public displays, newsletters and factsheets. In addition, a T4 Project webpage will be developed to provide informationabouttheT4Projectandaccesspointstoraiseconcernsorrequestfurtherinformation.The webpagewillberegularlyupdated.

FormalconsultationwithgovernmentagencieswillincludeaPFM,heldafterlodgmentofthisPEA,aswell asmeetingsandbriefingstodiscussspecificaspectsoftheT4Project.

24

6 Preliminaryenvironmentalassessment

6.1 Introduction

This chapter provides a preliminary assessment of the potential environmental and socioeconomic impactsoftheT4Project.ThereisconsiderablebaselineenvironmentaldataavailablefortheT4Project area, Kooragang Island and the surrounding areas from past and ongoing studies. This includes monitoring,modellingandassessmentundertakenforexistingandproposeddevelopmentsbyPWCSand other industrial facilities. In particular, the KCT and NCIG studies provide an understanding of the environmentalinteractionsofcoalterminaloperationsinthelocalarea.

Thischapterhasbeenpreparedfollowingadesktopreviewoftheexistinginformation,asitevisitandan analysisoftheproposedT4Projectfootprintandactivities,tocharacterisetheexistingenvironmentand identify potential environmental impacts and areas for further investigation in the EA. Detailed assessmentsofeachenvironmentalaspectareproposedaspartoftheEA,usingtheapproachessetoutin thischapter.

Aspectsconsideredinthischapterare:

 soilsandfoundationconditions;

 groundwater;

 surfacewater;

 ecology;

 airqualityandodour;

 noiseandvibration;

 trafficandtransport;

 infrastructure;

 heritage;

 visual;

 energyuse,greenhousegasesandclimatechange;

 hazards;and

 socioeconomic.

25

6.2 Soilsandfoundationconditions

6.2.1 Existingenvironment

There is considerable existing data on soil and geotechnical conditions within and adjacent to the T4 Projectarea,sourcedfromhundredsoftestbores,monitoringwells,testpitsandconepenetrationtests. TheT4Projectareabroadlycomprisesfill(industrialwasteanddredgedfines),underlainbysoftalluvial soils,comprisingclays,siltsandsands,whichextendtothebedrock. Coalwasheryrejectandnatural alluvialclayswithintheT4Projectareamayincludepotentialacidsulphatesoils(PASS).

Arangeofcontaminantsarepresentatelevatedlevelsassociatedwithpastlandfilling(referSection2.2). The principal contaminants are polycyclic aromatic hydrocarbons, benzo(a)pyrene, total petroleum hydrocarbons, phenols, asbestos, ammonia, cyanide, manganese and other metals (Douglas Partners, 2010). Monitoring data indicates that contaminant migration has occurred beyond the waste emplacement areas, however, the extent of contaminant migration has not been defined (Douglas Partners,2010).NoneofthelandfillsiteswithintheformerKooragangIslandWasteEmplacementFacility haveengineeredbaseorsideliningsystems,andallbutonedonothavealeachatecollectionsystem.

ClosureandcappingplanshavebeenpreparedforformerlandfillsintheT4Projectareaaspartofthe existingEPLconditions.Theseplans,orrevisionsthereof,wouldbeimplementedpriortooraspartofthe developmentoftheT4Project,andwillbedescribedintheEA.

6.2.2 Proposedassessmentapproach

AsoilsandgeotechnicalassessmentwillbeundertakenaspartoftheEA.Thekeyareasproposedfor investigationinclude:

 theriskandimplicationsofinterception,exposureand/ormobilisationofcontaminantsandPASS, forinstancefromtheproposeddrainageandearthworks;

 suitability of the foundation materials to accommodate the T4 Project, including potential for settlingunderload;and

 interaction of the T4 Project components with site capping, including implications for piling and designoffoundations.

Thesoilsandgeotechnicalinvestigationwilluseexistinginformation,supplementedbyadditionalsoiltest pitsandboresacrosstheT4Projectareaandattheproposedfillextractionandberthlocationsinthe HunterRiver.Managementandmitigationmeasureswillbedeveloped,includingsafeguardsandground preparation requirements for construction over fill and weak natural soils. Due to the potential interactions and contaminant pathways, the soil/ geotechnical investigation is proposed to be closely linkedtothegroundwaterinvestigation.

6.3 Groundwater

6.3.1 Existingenvironment

GroundwaterwithintheT4Projectareaiscontainedwithintwoprincipalaquifers,anupperunconfined aquifer within the fill strata, and a semiconfined aquifer within the underlying estuarine sediments (Douglas Partners, 2010). These aquifers are partially separated by a discontinuous clay aquitard, althoughthetwosystemsaregenerallyconsideredtobeconnected,withadownwardgradientfromfill

26 toestuarinegroundwater(GHD,2009).Athirddeeperaquiferispotentiallypresentwherestiffestuarine claylayersseparatethedeepersandlayers(DouglasPartners,2010).

Groundwaterflowwithinthefillstrataisprimarilysubhorizontal,towardstheclosestsurface drainage features although, some downward leakage also occurs (Douglas Partners, 2010). Flow within the estuarineaquiferisprimarilytothesoutharmoftheHunterRiver,withsomeflowtothenorthaswell (DouglasPartners,2010).

Groundwater monitoring is and will continue to be undertaken within and surrounding the T4 Project area.Resultstodateindicatethatgroundwaterhasbeencontaminatedbyhistoricuseoftheareaasan industrial waste facility. Concentrations of total petroleum hydrocarbons, benzo(a)pyrene, polycyclic aromatichydrocarbons,phenols,ammonia,cyanide,sulphate,manganese,leadandothermetalshave exceededtherelevantwaterqualityguidelinelimitsonvariousoccasions(DouglasPartners,2010).

6.3.2 Proposedassessmentapproach

A groundwater assessment is proposed as part of the EA. This will draw on existing information and monitoring data, supplemented by additional testing, where necessary. The existing hydrogeological modelofthesiteaquiferswillbefurtherdevelopedandgroundwatermodellingundertakentopredict potentialcontaminantpathwaysandthepotentialimpactsoftheT4Projectongroundwaterflowsand thereceivingenvironments.Suitablemanagementandmonitoringstrategieswillbedeveloped.

Thekeyareasproposedforinvestigationarethepotentialfor:

 exacerbation or migration of existing contamination and/ or new contamination, such as from mobilisation of soil contaminants into groundwater, additional loading and ‘squeezing’ of the ground,connectionofgroundwateraquifersystemsfrompenetrationoftheclayaquitardand/or migrationofpotentiallycontaminatedwaterthataccumulatesintheT4Projectarea;

 changestogroundwaterrechargeandflowregimes,suchasfromfillingandcappingofthesite, infiltrationofsalinewaterfromdredgematerialusedasfillandotherprojectrelatedalterationsto thesurfacewaterregime;

 potentialimpactsongroundwaterdependentecosystems,includingadjacentwetlandsoutsideof theT4Projectarea;and

 potentialimpactsonanygroundwaterusersonKooragangIsland.

6.4 Surfacewater

6.4.1 Existingenvironment

Surface hydrology within the T4 Project area has been completely modified by land reclamation, earthworks and artificial drainage structures, including floodgates, bridges, culverts, drains and levees. Theexistingsurfacedrainagenetworkcomprisesartificiallyconstructeddepressionsandpondswhichfill withwaterinresponsetorainfall,andultimatelydraintotheHunterRiversoutharm.

WaterqualitymonitoringhasbeenundertakenatpondswithinandsurroundingtheT4Projectareasince 2000,inaccordancewithEPL6437.Themonitoringresultsindicatethatwaterqualityhasbeendegraded by past land uses including waste dumping, with the ponds periodically characterised by low levels of contaminants (Resource Strategies, 2006). The measured pH, electrical conductivity, phenols, free cyanide,leadandzinclevelshaveperiodicallyexceededtherelevantguidelinelimits(ResourceStrategies,

27

2006).WaterqualitymonitoringdataisalsoavailablefortheHunterRiverupstreamanddownstreamof theT4Projectarea.

The existing surface water management system at the KCT includes direction of process water and stormwaterrunofffromoperationalareasofthesitetosettlingpondsforremovaloffinespriortoreuse onthesite.Thissystemisdesignedtocontainallsitewateruptoandincludingthe1in100yearstorm event.DischargesonlyoccurwhenthesestoragesexceedcapacityandtheyarereportabletoDECCW.

TheKCTuseswaterfordustsuppression,firefighting,vehiclewashdown,vesselwatersupplies,liquid resistors, wharf activities, amenities and landscape irrigation. These demands are met by stormwater capturedonsiteandrecycledprocesswater,augmentedbypotablewatersourcedfromHunterWater.

6.4.2 Proposedassessmentapproach

Thekeyareasproposedforinvestigationinthesurfacewaterassessmentarethedrainageimplications from infilling of ponds within the T4 Project area and the potential for water quality impacts during construction and operations, giving consideration to contamination and PASS present across the T4 Project area. The surface water assessment will set out principles for water management during constructionandoperations,includingoptionsforreuseandrecyclingofwater.Giventhatthewater managementsystemwilllikelybeintegratedwiththatatKCT,itisproposedtorevisethecurrentKCT waterbalancemodeltoincludetheT4Project,andconfirmthatwaterdemandscanbemet.Assessment ofthepotentialforfloodingimpactswillalsorequireconsideration.

6.5 Ecology

6.5.1 Existingenvironment

TheecologyoftheT4Projectareaandsurroundshasbeeninvestigatedaspartofpreviousandongoing ecologicalinvestigations.PreviousinvestigationshavebeenreviewedbyUmwelt(2010),inthecontextof theT4Project,andkeyfindingsaresummarisedinthefollowing. i Vegetationcommunities

TheT4Projectareaisahighlymodifiedenvironmentandpredominatelycomprisesareasofbareground anddisturbedgrasslanddominatedbyintroducedspecies.Theartificialpondsarecurrentlymappedas comprising saltmarsh, freshwater wetland and Phragmites swamp communities. Saltmarsh and a mangrovecomplexarepresentalongtheedgeoftheHunterRiver,attheproposedberthlocation.An aerial photograph showing the locations of currently mapped vegetation communities within the T4 ProjectareaispresentedasFigure6.1.Itisnotedthatwhilstpreviousecologicalinvestigationshavebeen undertakenwithintheT4Projectarea,thevegetationofthewholeoftheT4Projectareahasnotbeen recentlymapped.

TheT4ProjectareadoesnotincludeanyvegetationcommunitieslistedundertheEPBCAct.However, someofthesaltmarsh,freshwaterwetlandandPhragmitesswampcommunitiescurrentlymappedmay correspondtothefollowingendangeredecologicalcommunities(EECs)listedundertheTSCAct:

 CoastalSaltmarshintheNSWNorthCoast,SydneyBasinandSouthEastCornerBioregions;and

 FreshwaterWetlandsonCoastalFloodplainsoftheNSWNorthCoast,SydneyBasinandSouthEast CornerBioregions.

28

ThemangrovecomplexisaffordedsomeprotectionundertheFisheriesManagementAct1994,butisnot listedundertheTSCActortheEPBCAct. ii Faunahabitats

Umwelt (2010) identified that the T4 Project area contains three different fauna habitat types, being grassland,estuarineandwetlandhabitats.

Thegrasslandhabitatsareonlyexpectedtoprovidehabitatforalowdiversityofnativefaunaspecies. However, they may provide habitat for the eastern grass owl (Tyto longimembris) which is listed as vulnerableundertheTSCAct,andhasbeenrecordedlocally.Further,dispersalofsomeaquaticspecies suchasthegreenandgoldenbellfrogmayoccuracrosstheseareas.

Aquatic habitats within the T4 Project area are expected to provide habitat for fauna species such as migratoryshorebirdsandmicrobats(Umwelt,2010).TheT4Projectareaislocatedwithinthe‘Lower Hunter Estuary’, which supports a large variety of migratory and resident bird species during critical stagesoftheirbreedingcycles,andprovidesarefugeforbirdspeciesduringinlanddrought.Whilerichin birdlife,theestuaryshowsalowdiversityofnativeamphibian,reptileandmammalspecies.Muchofthe nativefaunahasbeendisplacedbyhabitatdestructionandpredationbyintroducedspecies.

WetlandhabitatswithintheT4ProjectareaincludeanareaknownastheDeepPondandfoursmaller pondsimmediatelywestofDeepPond(refertoFigure6.1).DeepPondprovideshabitatforarangeof wetlanddependentspecies,includingdeepdivingducks,migratorywadersandshorebirds.Theseinclude a number of threatened species, such as the bluebilled duck (Oxyura australia) and freckled duck (Stictonettanaevosa).Thefoursmallpondsmentionedaboveprovidehabitatforthethreatenedgreen andgoldenbellfrog(Litoriaaurea).

TherearenowetlandslistedunderStateEnvironmentalPlanningPolicyNo.14–CoastalWetlands(SEPP 14)locatedwithintheT4Projectareabutthreesuchwetlands(844,844aand823)arelocatedadjacent totheT4Projectarea. iii Threatenedflora

Onethreatenedfloraspecies,Zannichelliapalustris,hasbeenrecordedwithintheT4Projectarea.This speciesislistedasendangeredundertheTSCAct.Areviewoftheconservationstatusofthisspecieshas been recommended, given that it is not considered to be endemic to the area (Umwelt, 2010). The likelihoodofidentifyinganyotherthreatenedfloraspecieswithintheT4Projectareaislow. iv Threatenedandmigratoryfauna

TheHunterEstuaryWetlandsRamsarsite,locatedadjacenttotheT4Projectarea,provideshabitatforat least42ofthe66birdspecieslistedunderinternationalmigratoryspeciesconventions.Someofthese specieshavealsobeenrecordedwithintheT4Projectarea,attheDeepPond.

ThethreatenedfaunaspecieswhichhavebeenrecordedwithinorincloseproximitytotheT4Project areaarelistedinTable6.1,alongwiththeirconservationstatusandthelocationoftherecording(s).

29 N N O T FIGURE 6.1 K Fern Bay Fern C O T

S STOCKTON UTRRVR-NrhArm North - RIVER HUNTER

Vegetation Communities Vegetation

STOCKTON BRIDGE STOCKTON Greenleaf Road Greenleaf 4 WALSH POINT WALSH

NEWCASTLE HARBOUR NEWCASTLE 3 eo Road Heron The Terminal 4 Project | Preliminary Environmental Assessment Report Assessment Environmental | Preliminary 4 Project The Terminal l a n i m r e T

l a o C

n o t g n i r r a 2 C

S

Raven Street 7 C Hunter Estuary National Park National Estuary Hunter

W ge Street Egret PWCS Carrington Coal Terminal Carrington P PWCS 1 D L E T I S F A Y E HUNTER RIVER - South Arm EAST A M MAYFIELD NCIG coal export terminal export NCIG coal D L PWCS Kooragang Coal Terminal Kooragang PWCS D E L I H Pacific Highway F E T

I

Y rvt cesRa PcfcNational) (Pacific Road access Private 5 R F A Y 6 O A M MAYFIELD N NORTH

M MAYFIELD

Cormorant Road Cormorant Industrial Drive Industrial

D oreStreet Tourle L T E I S F E Y WEST W A MAYFIELD M TOURLE STREET BRIDGE STREET TOURLE McLennan Deep pond 0.4 0.6 0.8 Mitchell T4 Project Area T4 Project Railway Boral Cement Cargill Oilseed Processor Maunfacturing Fertilizer Incitec Pivot Orica swing basin Proposed OneSteel BHP Land Former Grassland wetland Freshwater Coastal saltmarsh Mangroves 0.2 7 5 6 1 2 3 4 Vegetation communities Vegetation 0 1km

Pacific Highway KEY

EMGA Integrated Design Solutions Design Integrated 030418 Option 3-5 F6.1 Re v F - 24 November 2010 © 2010 November 24 - F v Re F6.1 3-5 Option 030418

Table6.1 ThreatenedfaunaspeciesrecordedwithinoradjacenttotheT4Projectarea

Speciesname Conservationstatus Locationrecorded Commonname Scientificname TSCAct EPBCAct Greenandgoldenbell Litoriaaurea E V Numerousrecordsovermultiple frog surveyperiods Easternosprey Pandionhaliaetus V MAR,MIG DeepPond Easterngrassowl Tytolongimembris V AdjacenttoT4Projectarea Australasianbittern Botauruspoiciloptilus E AdjacenttoT4Projectarea Blacktailedgodwit Limosalimosa V MAR,MIG DeepPondandadjacenttoT4 Projectarea Bluebilledduck Oxyuraaustralia V MIG DeepPondandadjacenttoT4 Projectarea Freckledduck Stictonettanaevosa V MIG DeepPond Magpiegoose Anseranassemipalmata V MAR DeepPond Blackneckedstork Ephippiorhynchus E DeepPond asiaticus Redbackedbutton Turnixmaculosa V NearDeepPond quail Spottedharrier Circusassimilis V MIG NearDeepPond Greyheadedflyingfox Pteropuspoliocephalus V V T4Projectarea Easternbentwingbat Miniopterusschreibersii V AdjacenttoT4Projectarea oceanensis Easternfreetailbat Mormopterus V T4Projectarea norfolkensis Littlebentwingbat Miniopterusaustralis V T4Projectarea Easternfalsepipistrelle Falsistrellustasmaniensis V T4Projectarea Largefootedmyotis Myotismacrotarsus V T4Projectarea Notes: 1.Source:Umwelt(2010) 2.E–endangered;V–vulnerable;MAR–marine;MIGmigratory.

6.5.2 Proposedassessmentapproach

To assess the potential impacts of the T4 Project on the ecological values of the T4 Project area and surrounding environments, a detailed ecology assessment will be undertaken. The assessment will include,butnotnecessarilybelimitedto,thefollowingactivities.

 Adetailedreviewoftheecologicalinvestigationspreviouslyundertakenwithinandadjacenttothe T4Projectarea,includingfloracommunities,andfloraandfaunaspeciesrecorded.

 Additional field surveys of terrestrial and aquatic habitats to fill information gaps or target particularfloraorfaunaspecies.

 ResearchintothegreenandgoldenbellfrogconductedbytheUniversityofNewcastlethroughout the2010/2011spring–autumnperiod.Thisresearchhasalreadybeencommissioned.Itwillaim tocontributetoanunderstandingofthegreenandgoldenbellfrogpopulationsizeandhabitat utilisation on Kooragang Island. Knowledge gained from this research will assist in the developmentofmanagementstrategiesforitslongtermconservation.

31

 Animpactassessmentanddevelopmentofmitigationmeasures,includingrecommendationsfor compensatoryhabitatrequirements.

AkeyconsiderationwillbetheimpactofinfillingpondsintheT4Projectarea.Thiswillincludeimpactsto threatenedandmigratoryspecieswhichutilisetheseponds,includingthegreenandgoldenbellfrogand migratorybirds,andtoanyEECswhichmayoccurwithintheseponds.Otherkeyconsiderationsrelateto the clearing of mangrove vegetation to accommodate the berthing facilities and potential impacts to surroundinghabitats,includingSEPP14wetlandsandtheHunterEstuaryWetlandsRamsarsite.

6.6 Airqualityandodour

6.6.1 Existingenvironment

AirqualityatKooragangIslandandsurroundingareasisinfluencedbydustemissionsfromindustrialand nonindustrialsources,includingtheKCT.Industryintheareageneratesemissionsfromfuelcombustion andenergyuse,includingnitrogenoxides,sulphuroxidesandcarbondioxide.Thirdpartyemissionsfrom shipsintheportarealsoasourceofemissions,particularlysulphurdioxide,whichisgeneratedbythe combustionofheavybunkeroils.

ThereisanetworkofairmonitoringequipmentinandaroundtheKCT,operatedbyDECCW,PWCSand otherindustrialfacilities,whichprovidesdataonexistingairqualityinthelocalarea.Dustdeposition gaugesmonitorthelevelsofdustdeposition,andhighvolumeairsamplersmonitorparticulatematter concentrations.TherearealsotwoweathermonitoringstationsoperatedwithintwokilometresoftheT4 Project area, located at the KCT and Mayfield West, respectively. This data, in conjunction with air dispersion modelling and assessment undertaken for existing and proposed industrial developments provideagoodunderstandingofexistingairqualityanddispersioncharacteristicsinthelocalarea.

Themonitoringdatafor2008indicatethatannualaveragetotalsuspendedparticulates(TSP)andPM10, anddustdepositionlevelsarewellbelowtheDECCWassessmentcriteria.AirqualitypredictionsbyPAE Holmes(2006,2009)indicatethatthisisthecaseevenwhenconsideringpredictedfutureemissionsfrom NCIG and KCT (Stage 4). Periodic exceedences of the maximum 24average PM10 criterion of 50 micrograms per cubic metre (g/m3) have been recorded, such as on two days in 2008 at Fern Bay, possiblyduetoduststormsorbushfiresratherthanindustrialemissions.

Basedonthedataavailable,PAEHolmes(2009)calculatedbackgrounddustconcentrationsatresidential areasinthevicinityofKCTtobe:

3 3  annualaverageTSPof45g/m (DECCWcriterionis90g/m );

3 3  annualaveragePM10of21g/m (DECCWcriterionis30g/m );and

 annualaveragedustdepositionof2g/m2/month(DECCWcriterionis4g/m2/month).

ThenearestresidentialareastotheT4ProjectareaareatMayfieldandWarabrook.Airdispersiontoward theseareas,andaccordinglythepotentialfordustimpacts,ispotentiallyenhancedbywindsfromthe westnorthwestandnorthwest,whichonanannualbasis,arethemostcommonwindsinthearea(PAE Holmes,2009).

OdoursaregeneratedbysomeindustrialfacilitiesonKooragangIsland,however,theexistingoperations attheKCTdonotgenerateanysignificantodouremissions.

32

Anarrayofdustcontrolsandsafeguardsarecurrentlyinplacetoensurethatairqualityofsurrounding areas is not adversely affected by KCT operations. This includes regular monitoring of air quality undertakeninaccordancewithrelevantdevelopmentconsentandDECCWlicensingconditions.

6.6.2 Proposedassessmentapproach

Anairqualityassessmentwillassessthepotentialforconstructionandoperationalimpactsatsensitive receivers.Itwillincludequantitativedispersionmodellingofdustemissionstopredictfuturedustlevels in the surrounding area, taking into account existing meteorological and air monitoring data. Key considerationswillincludethepotentialforcumulativeimpacts,includingtheriskofexceedingthe24 hourmaximumPM10 criterion,andtheimplicationsoftheT4Projectarealocation,tothewestofthe existingKCTsite,whichmaynecessitateconsiderationofadditional,morewesterlyassessmentlocations tothoseadoptedforthepreviousKCTassessments,possiblyincludingWarabrook,SandgateandMayfield West.

Theairqualityassessmentwillalsoconsidernondustemissions,suchasnitrogenoxides,sulphuroxides andcarbondioxideassociatedwiththeT4Project,andthepotentialcumulativeeffectsofsulphurdioxide emissionsfromshipsassociatedwiththeT4Projectwhilebeingloaded.Giventherelativelymodestfuel consumption anticipated, these are not expected to be significant, and the assessment of nondust emissions will be predominately in the context of the greenhouse gas, energy use and climate change assessment,describedinSection6.12.2.

ProjectrelatedairqualityimpactswillbeconfinedtotheT4Project.However,impactsassociatedwith theexistingKCTwillbeconsideredaspartofcumulativeairqualityimpacts.Thecumulativeassessment will consider emissions from all sources in the area surrounding the T4 Project area, including other industryonKooragangIsland.

NoodoursourceshavebeenidentifiedinassociationwiththeT4Project,otherthanpotentialtemporary odours from dredging, or any onsite treatment of contaminated materials required to facilitate construction.Nevertheless,anodourassessmentwillbeconductedthatiscommensuratewiththelevel ofrisk.

6.7 Noiseandvibration

6.7.1 Existingenvironment

TheexistingacousticenvironmentofKooragangIslandandthesurroundingresidential,commercialand industrialareasisinfluencedbynoisefromtransport,domestic,naturalandindustrialsources,including from the existing KCT. Noise levels within these areas have been well characterised by monitoring, modellingandassessmentundertakenforexistingandproposedindustrialdevelopments.Thisincludes ongoing noise monitoring undertaken by PWCS at the KCT, Fern Bay and Stockton, and continuous meteorologicalmonitoringundertakenattheweatherstationsmentionedinSection6.6.1.

RecentmonitoringbyHeggies(2010),undertakeninMay2010,indicatesthatKCTgeneratednoiselevels complywithrelevantnoisecriteriasetoutinapprovalsatnearbyresidentiallocationsinStocktonand FernBayandatotherindustrialsiteswithinKooragangIsland.Theresultsindicatethat:

 noiselevelsgeneratedbyKCTatresidentiallocationsinStocktonandFernBayrangebetween41 and42dBALeq(15minute),whichare1to2dBAlowerthanthecriteriaof43dBA;and

 noiselevelsatindustriallocationsonKooragangIslandrangebetween59and70dBALeq(15 minute), whichisbeloworatthecriteriaof70dBA.

33

PWCSactivelymanagesandmonitorsnoiseattheKCTtominimisethepotentialforimpacts,complywith regulatoryandPWCSnoiselimits,andimprovenoiseperformance.Thisisdoneinaccordancewiththe conditions of consent, an approved Noise Management Plan, and a continuous noise improvement programwhichincludesacousticaldesign,procurement,constructionandcommissioningprocesses.

6.7.2 Proposedassessmentapproach

An acoustic assessment of the T4 Project will be undertaken in accordance with the DECCW (2000) IndustrialNoisePolicy.Itwillassessthepotentialfornoiseandvibrationimpactsatsensitivereceivers, and develop mitigation measures to ameliorate the potential for adverse impacts. The assessment is proposedtoaddresspotentialconstructionandoperationalimpacts,andincludequantitativemodelling ofnoiseemissions.

Existingmeteorologicalandnoisemonitoringdatawillbeused,supplementedbyadditionalmonitoring where necessary. Key considerations will include the potential for cumulative noise impacts, and the geographic location of the T4 Project area, west of the existing KCT site, which may necessitate the inclusionofother,morewesterlyassessmentlocationstothoseadoptedforthepreviousKCTacoustic assessments,suchasatWarabrook,SandgateandMayfieldWest.

Noiseimpactsfromroadtrafficareexpectedtobeminimal,giventhatroadtrafficgeneratedbysimilar proposals on Kooragang Island was predicted to have negligible noise impact (e.g. Umwelt, 2009; Resource Strategies, 2006). However, this will be quantitatively assessed in accordance with DECCW requirements.

ThepotentialfornoiseassociatedwithrailandshippingfortheT4Projectwillalsobeassessedwhereitis directlyrelatedtotheprojectitself.Thiswillincludetheimpactofrailandshippingnoisegeneratedby operationswithintheT4Projectarea.Separatestudieswillberequiredtoaddressincreasesinrailand shipmovementsoutsidetheT4Projectarea.

6.8 Trafficandtransport

6.8.1 Existingenvironment i Roadnetwork

TheroadnetworksurroundingtheT4ProjectareaisshownonFigure1.2.Thekeyroadsinthevicinity areidentifiedinthefollowing.

 IndustrialDrive(arterialroad)andTourleStreet,whichprovideaccesstoKooragangIslandfrom NewcastleandthePacificHighway,viatheTourleStreetbridge.

 FullertonRoad,whichprovidesaccesstoKooragangIslandfromStockton,FernBayandNelsons Bay,viatheStocktonBridge.

 Cormorant Road and Teal Street, which together comprise the main arterial route through Kooragang Island, connecting the Tourle Street Bridge and the Stockton Bridge. This route comprisesthemainarteriallinkbetweenNewcastle,theNewcastleAirportandNelsonsBay.Itis usedbythroughtrafficaswellasvehiclesaccessingindustrialfacilitiesonKooragangIsland.

34

 Local roads at the eastern end of Kooragang Island, including Egret Street, Raven Street, Heron RoadandGreenleafRoad,whichprovideaccesstovariousindustrialfacilities.

 PrivateaccessroadsandvehicletrackswithinandadjacenttotheT4Projectarea,whichservice thevariouslandparcelsandindustrialfacilitiesonKooragangIsland.

TheroadnetworktoandfromKooragangIslandgenerallycompriseswideroadswithbroadshouldersand turningapronstoaccommodatelargevehicles,andexcellentsightdistances.Mostofthenetworkcaters forallvehicletypes.Similarly,StapletonTransportation&PlanningPtyLimited(STAP)(2009)identified that the road network on Kooragang Island operates at a high level of service with significant spare capacity.

STAP(2009)reportedthatthekeyintersectionsinthevicinityoftheT4Projectarea,i.e.CormorantRoad/ IndustrialDrive,CormorantRoad/TealStreetandCormorantRoad/EgretStreetalloperateatagoodor satisfactorylevelofserviceduringpeakperiods,withtheexceptionoftheillegalrightturnfromEgret StreettoCormorantRoadwhichissubjecttoconsiderabledelays.Countermeasureshavebeeninstalled topreventrighthandturnsatthislocation.

TrafficcountsbytheNSWRoadsandTrafficAuthorityandbySTAP(2005,2009)havefoundthatthere hasbeennegligibleincreaseintrafficvolumesontheroadnetworksurroundingtheT4Projectareain recentyears.Peaktrafficflowsgenerallyoccuronthelocalroadnetworkbetween6.00amand9.00amin themorningandbetween3.00pmand5.00pmintheafternoon/evening(STAP,2009). ii Railnetwork

ThereisanexistingraillineonKooragangIsland,inclusiveofrailloopsandcoalreceivalfacilitiesatthe KCTandtheNCIGcoalterminal(seeFigure1.2).AllcoaltransporttotheKCTandtheNCIGcoalterminal isbyrail.ThisraillinealsoservicesotherindustrialfacilitiesonKooragangIsland,includingBoralCement andotherfacilitiesonWalshPoint.

6.8.2 Proposedassessmentapproach

AdetailedtrafficandtransportassessmentoftheT4Projectwillbeundertaken.Keyconsiderationswill bethepotentialimpactsofconstructionandoperationaltrafficonperformanceofthelocalroadnetwork and parking availability. However, given the existingtraffic conditions and the fact that theNCIG and PWCS Stage 4 construction workforce peaks will be completed well before the T4 Project commences construction,additionaltrafficgeneratedbytheT4Projectisnotexpectedtobeamajorissue.Theother keyareasforassessmentwillbeimpactsofthepotentialrealignmentandconveyorcrossingofCormorant Road,proposedroadaccesstotheT4Projectarea,driversafetyinthevicinityoftheT4Projectarea.

6.9 Infrastructure

6.9.1 Existingenvironment

ThereareexistingsurfaceandsubsurfaceservicesandeasementslocatedwithinandadjacenttotheT4 Projectareaincludingwatermains,fibreopticcables,Telstracables,sewermain,gasmains,overhead high voltage powerlines, navigational aides and an Energy Australia wind turbine. Transport infrastructureisdiscussedaboveinSection6.8.

35

6.9.2 Proposedassessmentapproach

TheEAwilldocumentanyserviceswhichwouldberelocatedaspartoftheT4Project,andtheoutcomes of consultation undertaken with service providers. The assessments of potential construction impacts undertakenfortheEAwillcoverrelocationofservices.

6.10 Heritage

6.10.1 Existingenvironment

Searches of Commonwealth, State and local government heritage databases and a review of heritage investigationsundertakenatKooragangIslandbyResourceStrategies(2006),HLA(2005),Umwelt(2003), ProtechSteel(2001)andERMMitchellMcCotter(1996),identifiedthatnoitemsorplacesofindigenous ornonindigenousheritagesignificancehavebeenrecordedwithintheT4Projectarea.

OnlytwoAboriginalheritageplacesareregisteredonKooragangIsland.Oneislocatedtothenorthofthe T4Projectarea,andtheother,whichwasrecordedneartheTourleStreetBridge,hasbeendestroyed (Resource Strategies, 2006). No traditional owners have raised any concerns regarding existing operations at the T4 Project area, and consultation with local Aboriginal groups regarding other developmentsonKooragangIslandhasnotidentifiedanysignificantculturalheritagevaluesassociated withtheisland.

ThenonindigenousheritageitemsonKooragangIslandaretheTonguesTreeFig,131RadarIglooand SchoolMaster’sHouse,locatedonthewesternpartofAshIsland,morethan2.5kmfromtheT4Project area,andaPalmonGreenleafRoad,atWalshPoint.ThesearealllocalheritageitemsontheNewcastle LEP.

TheHunterEstuaryWetlands,partofwhicharelocatedintheHunterEstuaryNationalParktothenorth oftheT4Projectarea(seeFigure1.2)arearegisteredplaceontheRegisteroftheNationalEstate.

Itisconsideredunlikelythatanypreviouslyunrecordeditemsofheritagesignificancewouldbepresentin theT4Projectarea,giventheresultsofpreviousassessmentsandgiventhattheareahasbeenheavily disturbed, including by land filling and reclamation. This would likely have destroyed any evidence of formeroccupationofthearea.

6.10.2 Proposedassessmentapproach

TheT4Projectisnotlikelytoimpactknownitemsorplacesofheritagesignificance,withthepossible exceptionoftheHunterEstuaryWetlands,giventhatnonearelocatedwithintheT4Projectarea.The potentialforanyimpactsonthewetlandswillbeinvestigatedaspartofthegroundwaterandecology investigations.Giventhehighlydisturbednatureofthesite,andthelowpotentialforanyheritagevalues tobeattachedtotheland,theheritageassessmentwilllargelyfocusonareviewofexistinginformation, consultationwithlocalAboriginalgroups,andassessmentofwhethertheheritagelistedPalmislikelyto beimpacted.Surveyswillbeundertakenonlandnotsubjecttopreviousassessmentsandundisturbed land.

36

6.11 Visualamenity

6.11.1 Existingenvironment i Visualsetting

ThevisualsettingoftheT4Projectareaandsurroundsisdominatedbythelargescaleindustrialandport facilitiesonKooragangIslandandalongthesouthernbankoftheHunterRiver,totheeastandsouthof the T4 Project area. These include coal stockpiles, coal stackers/ reclaimers, conveyors, wharves, shiploaders,ships,bulkliquidstoragetanks,shedsandadministrationbuildings.

Builtandnaturallandscapesarealsofeaturesofthelocalandregionalviewscapes,includingtothenorth, eastandsouthoftheT4Projectarea.Theseincludebodiesofwaterandvegetationwithintheriverine, estuarineandwetlandenvironmentsofHunterEstuaryNationalPark,theHunterRiverandcoastline,as wellascommercialandresidentialareasofNewcastle.Othervisiblefeaturesofthelocalsettinginclude roads,bridges,raillines,electricitytransmissionlinesandawindturbineonKooragangIsland.

TheT4Projectareaitselfcomprisesflattohummockyterrain,shapedbypreviouslandfillactivities,with grasslandsandartificialponds. ii Lighting

Thelocalareaisgenerallywelllitbyfixedlightingatexistingindustrialandportfacilitieswhichoperate24 hoursperday,vehiclelightsalongtheroadnetworkandlightingfromshipsutilisingtheport. iii Viewpoints

TheT4ProjectareaisvisiblefromviewpointsalongtheHunterRiver,adjacentroads(theclosestofwhich is Cormorant Road) and at surrounding industrial facilities. More distant views are available from the elevatedresidentialareasonthemainland,e.g.atMayfield,MayfieldWest,WarabrookandSandgate. Interveninglandform,vegetationandbuildingsprovidesomescreeningofviews.

6.11.2 Proposedassessmentapproach

AvisualassessmentwillbecompletedaspartoftheEA.Thiswillidentifypotentiallysensitiveviewpoints, assesspotentialchangestoviewscapesanddevelopmitigationmeasures.Keyconsiderationswillbethe appearance of the proposed infrastructure and night lighting (albeit that these would be visually consistentwiththeadjoiningcoalterminals);removaloffeatures,suchaspondsandastripofmangroves atthewater’sedge;andthelocationoftheT4Projectareafurtherwestthantheexistingcoalterminals, constitutinganextensionoftheindustrialviewscapesandpotentiallyexposingittoreceiverswhodonot currentlyhaveviewsofthesefacilities.

6.12 Energyuse,greenhousegasandclimatechange

6.12.1 Existingenvironment

Energyefficiencyandgreenhousegas(GHG)reductioninitiativesarecurrentlyimplementedbyPWCSand willcontinuetobedevelopedandimplementedforitsoperationsastechnologiesandpoliciesevolve.An investigationofKCTenergyusageandGHGemissionswasundertakenbySEESustainabilityConsulting (SEE)(2007),andincludedquantitativecalculationsofScope1,2and3emissions.Scope1emissionsare direct emissions from onsite activities. Scope 2 emissions are indirect emissions from the onsite

37 consumptionofelectricity,steamorheatproducedbyanotherorganisation.Accordingly,Scope1and2 emissionsareduetotheactualoperationofaproject.Scope3emissionsaretheindirectemissionsfrom transportandenduseofthecoal.

TheSEE(2007)assessmentresultswereunchangedbythesubsequentStage4proposal(SEE,2009).SEE (2007, 2009) identified that consumption of purchased electricity, diesel and petrol were the key contributors to onsite energy usage at the KCT and Scope 1 and 2 emissions. Scope 3 emissions are associatedwithcoaltransportandcombustion,includingshippingandrailingofcoal.

6.12.2 Proposedassessmentapproach

Anenergyuse,greenhousegasandclimatechangeassessmentoftheT4Projectwillbeundertaken.This willincludeenergyusageandScope1,2and3GHGemissioncalculations;ananalysisofthelikelyeffects of the predicted emissions; and a review of existing PWCS energy efficiency and emissions reductions measurestoidentifyanypotentialimprovements.TheestimatedScope1,2and3GHGemissionswillbe calculatedinthecontextoftheircontributiontoglobalemissionsandclimatechange.Broaderissuesof theroleandefficiencyofcoalasanenergysourcewillalsobeexamined.

TheassessmentwillalsoconsiderthepotentialforclimatechangetoaffecttheT4Project;thatis,from sealevelriseandpotentiallyhigherintensitystormevents.

6.13 Hazards

6.13.1 Existingenvironment

PotentialhazardsidentifiedinassociationwithexistingKCToperationsrelatetothepotentialforspillsor leaksofhazardousmaterialsandforfiresfromspontaneouscoalcombustion.PWCShasexistingsafety systemsandproceduresinplacetoreduceandrespondtosuchincidents,includingafirefightingsystem. Storage and handling of potentially hazardous materials is in accordance with the relevant statutory requirements.

6.13.2 Proposedassessmentapproach

A preliminary hazard analysis (PHA) will be undertaken to identify and evaluate the potential hazards associated with the T4 Project, in accordance with the requirements of State Environmental Planning PolicyNo.33–hazardousandoffensivedevelopment.ThekeyissuesexpectedtobecoveredinthePHA relate tothepotential for spills, leaks or fires associated with storage, handling and use of potentially hazardous materials, i.e. diesel, petrol, hydrocarbons and gas cylinders; general construction and operational activities such as conveyor operations and stockpiling; failure of structures and water managementsystems;roadmodifications;transportofoversizedequipment;andrailoperations.

TheEAwillalsoincludeanassessmentofpotentialimpactsonmaritimesafety.

6.14 Socioeconomic

6.14.1 Existingenvironment

The existing PWCS operations contribute to the local and regional economies by providing direct and indirectemploymentandincome,withpotentialflowonbenefitstosociety.PWCSdirectlyemploys440 fulltimepeopleandengagesafurther400contractors,mostofwhomarelocallybased.PWCSdonates

38 close to $500,000 per annum to a range of local institutions including the Hunter Medical Research InstituteandNewcastleSurfLifeSavingClub.

Inaddition,theKCTandCCTareintegralcomponentsoftheHunterValleyCoalChainandcontributeto thesocialandeconomicbenefitsofthebroadercoalindustry.Theseincludeemploymentgenerationand fuelforlowcostelectricitygenerationandindustrieslikesteelmaking.ThecoalindustryisNSW’sand Australia’slargestsourceofexportrevenueandthroughroyalties,employment,investmentandrevenue generation,isamajorcontributortothesocialandeconomicdevelopmentofregionalAustralia.

ThermalcoalsuppliedfromtheHunterValleyCoalChainisusedtogenerateelectricityinanumberof countriesaroundtheworld,includingcountriesinAsia,providingsignificanteconomicandsocialbenefits tothosecountries.

WhilecommunityengagementundertakenbyPWCSaspartofitsongoingoperationsandforassessment ofpreviousproposals,hasidentifiedissuesregardingpotentialimpactsthroughnoiseanddust,ithasalso identified wide support for PWCS operations and the measures it incorporates into its operations to reduceimpactsonthelocalarea

6.14.2 Proposedassessmentapproach

AsocialimpactandeconomicassessmentoftheT4Projectwillbeundertaken.Thiswillseektoidentify andaddressthesocial/communityimpactsoftheT4Project,quantifytheeconomiccontributionofthe T4Projecttothelocalandregionalcommunity,andqualitativelyassessthepotentialflowonbenefits.In particular,theT4Projectwouldcreatedirectemployment,revenuethroughtaxesandroyaltiesandis expectedtobeasignificantcontributortosecurityofemploymentandrevenuethroughouttheHunter ValleyCoalChainandthecommunitiesinwhichitoperates.

Thesocioeconomicassessmentwillalsoincludeeffectssuchasnoise,airquality,ecology,greenhouse gas and climate change, visual, traffic and transport and contamination. The results will be used to commentonactualandperceivedimpactsonamenityandcommunityvaluesidentifiedinthecommunity consultationprogram.ThecostsandbenefitswillbeweigheduptoassesswhethertheT4Projectwould beofnetbenefit.Thiswillbeundertakenthroughabenefitcostanalysis(BCA),whichwillcomparethe quantification and valuation of the T4 Project’s incremental benefits and costs against a no project scenario.TheBCAwillincludeachoicemodellingstudytoestimatemonetaryvaluesforthepotential environmental,culturalandsocialimpactsorexternalitiesoftheT4Project.

AsoutlinedinChapter5,communityengagementfortheT4Projecthascommencedinaccordancewitha projectspecificengagementstrategy,andwillcontinuethroughouttheT4Project.

At this stage, no significant social or community impacts such as population growth or impacts on housing,communityservices,infrastructureorfacilitiesintheNewcastleregionareanticipatedasaresult oftheT4Project.However,demographicinformationwillbeanalysedtocharacterisethepopulation.

39

“Thispagehasbeenintentionallyleftblank”

40

7 Conclusion

TheHunterValleyishometotheworld’slargestandmostcomplexcoalchain,responsibleforhandling oneofAustralia’smostsignificantcommodityexports.Itincludes14coalproducers,40coalminesand 80brandsofprimarilythermalcoal.Itcreatesmanythousandsofdirectandindirectjobs.

The most important part of the HunterValley Coal Chain is the harbourbased terminal/vessel loading operations.In2010,PWCS,theworld’slargestcoalexportterminal,willloadsome97milliontonnesof coalwithanestimatedvalueof$10billionontowellover1,000exportvessels.ThismakesPWCSacritical mainstay of economic activity locally, statewide, nationally and internationally. Although PWCS has committed$1.6billiontocoalloadinginfrastructureinvestmentanddeliveryoverthepastdecade,itis currently at one of the most critical junctures in its history as it prepares to handle booming and unprecedenteddemandforcoalloadingservices.

RecognisingthevitaleconomicimportanceoftheHunterValleyCoalChain,theNSWGovernmentandthe Hunter Valley coal industry recently negotiated a long term operational framework – the Capacity FrameworkArrangements–toensurethatadequatecoalhandlinginfrastructureisdevelopedinthemost efficientandtimelymannertomeetthegrowingdemandsofinternationalcoalcustomersandincreasing coalthroughput.ThearrangementsarealsointendedtominimisecostlyvesselqueuesoffNewcastle,a problematicoccurrenceinrecentyearsduetobroadandhistoricflawsinthewaytheoverallCoalChain operates.Thearrangementscameintoeffecton1January2010.

A central part of the plan is an expectation that PWCS will build the T4 Project, a new coal loading terminal adjacent to the KCT, to cater for future coal loading operations when existing terminal operations have reached capacity. The long term viability of the entire coal chain and Australia’s reputation as an efficient and reliable coal exporter depends on the ability of PWCS to deliver the T4 Project.

Tofulfilitsobligations,PWCShasspentmuchof2010undertakingtechnicalinvestigationstodetermine thepotentialtodelivertheT4Project.UpongrantingPWCStherighttobuildtheT4Project,subjectto environmental and planning approvals, the NSW Government recognised that the T4 Project area is generallyzonedforportdevelopmentpurposesandwasformerlyusedasalandfill.TheT4Projectwould includearailloop,stockyard,conveyorsystem,shippingberths,coalloadinginfrastructureandfacilities sharedwiththoseexistingatKCT.

TheT4ProjectrequiresapprovalunderPart3AoftheNSWEP&AAct.Areferralisbeingpreparedto determinewhethertheprojectalsorequiresapprovalundertheCommonwealthEPBCAct.Ifanapproval isrequiredunderthislegislation,theintentionwouldbethatCommonwealthmattersbeassessedunder theNSWGovernment’scurrentPart3Aprocess,inaccordancewithabilateralagreementbetweenthe CommonwealthandtheState.

StakeholderswillbeconsultedthroughoutthepreparationoftheEAonthedesignoftheT4Projectand themitigationsmeasuresproposedtoreduceimpactsonthelocalenvironmentandcommunity.Thiswill include identification of opportunities to accommodate community feedback into the project design. Preliminarystakeholderconsultationsarealreadywelladvanced,withPWCSmanagementarticulatingthe broadT4Projectintentiontothecommunity,local,StateandCommonwealthgovernmentagenciesand politicalofficesandthemedia.

The T4 Project has the potential for positive and negative impacts. Potential positive impacts would include substantial capitalinvestment into the local area, tax payments, increased employment (direct and indirect) and the beneficial use of a landfill area. Potential negative impacts include impacts on

41 groundwater,ecology,airquality,noiseandvibration.AnEAwillbepreparedtoaddressallpotential positiveandnegativeimpacts.TheresultsofthepreliminaryassessmentsinChapter6willbeusedto guide the relative priorities for further assessment and mitigation strategies. Accordingly, the study scopesproposedinChapter6havebeendevelopedcommensuratewiththelevelofassociatedpotential risk.

The EA will be assessed by the NSW DoP, and if an approval is required under the EPBC Act, the Commonwealth DSEWPC. If approval is required under the EPBC Act, the DoP and DSEWPC would provide an assessment report to the NSW Minister for Planning and Commonwealth Minister for Sustainability, Environment, Water, Population and Communities respectively, recommending whether theprojectshouldbeapprovedorrefused.ShouldtheT4Projectobtainapproval(s)andproceed,the benefitstothelocalarea,theStateandAustraliawouldpotentiallybesignificant.

42

References

Australian Bureau of Statistics (2010) 1338.1 NSW State and Regional Indicators, September 2010. Onlineresourceathttp://www.abs.gov.au/ausstats/[email protected]/mf/1338.1,viewed2November2010. DECCW(2000)NSWIndustrialNoisePolicy. Douglas Partners (2010) Report on Geotechnical & Geoenvironmental Assessment – Concept Stage: ProposedTerminal4KooragangIsland.PreparedforPortWaratahCoalServicesLimited&Newcastle PortCorporation.

ERM Mitchell McCotter (1996) Kooragang Coal Terminal Stage 3 Expansion – Environmental Impact Statement.PreparedforPortWaratahCoalServices.

GHD(2009)HunterDevelopmentCorporation–ReportonKIWEF,RevisedFinalLandformandCapping Strategy.

Heggies (2010) PWCS Kooragang Coal Terminal Stages 1, 2, 3A, 3 (Steps 14) Plant Operating Noise Results,JuneQuarter2010.PreparedforPortWaratahCoalServices.

HLA (2005) Expansion of the Cargill Oilseed Processing Facility Kooragang Island Environmental Assessment.PreparedforCargillAustraliaLimited.

PAEHolmes(thenHolmesAirSciences) (2006)AirQualityImpactAssessment:NewcastleCoalExport Terminal.

PAEHomes(2009)AirQualityImpactAssessment:KooragangCoalTerminalStage4Project–Fourth DumpStationandFourthShiploader,Appendix4ofUmwelt(2009). ProtechSteel(2001)ProposedColdMillFacilityKooragangIslandEIS.

ResourceStrategies(2006)NewcastleCoalInfrastructureGroupCoalExportTerminalEnvironmental Assessment.PreparedforNewcastleCoalInfrastructureGroup.

SEE (2007) Scope 1,2 and 3 Greenhouse Gas and Energy assessment for Kooragang Coal Terminal Project.

SEE(2009)GreenhouseGasEmissionsStudyforPortWaratahCoalServices:KooragangCoalTerminal Stage4Project–FourthDumpStationandShiploaderProject,Appendix9ofUmwelt(2009). STAP(2005)TrafficAssessmentReport,ExpansionoftheOilseedProcessingFacility,KooragangIsland EnvironmentalAssessment. PreparedforCargillAustraliaLimited.

STAP(2009)KooragangCoalTerminalStage4Project–TrafficImpactAssessment(Final),Appendix8of Umwelt(2009).

Umwelt(2003)AboriginalCulturalHeritageAssessment,ProposedExtensionofShippingChannels,Port ofNewcastle.PreparedforNewSouthWalesWaterwaysAuthority.

Umwelt (2009) Environmental Assessment Kooragang Coal Terminal Stage 4 Project: Fourth Dump StationandFourthShiploader.PreparedonbehalfofPortWaratahCoalServices. Umwelt (2010) Ecological Constraints Analysis – T4 Conceptual Studies. Prepared on behalf of Port WaratahCoalServices.

Acronyms μg/m3 microgramspercubicmetre ACCC AustralianCompetitionandConsumerCommission BCA benefitcostanalysis dBA Noiseismeasuredinunitscalleddecibels(dB).Thereareseveralscalesfor describingnoise,themostcommonbeingthe‘Aweighted’scale.Thisattempts tocloselyapproximatethefrequencyresponseofthehumanear. CCT CarringtonCoalTerminal DECCW DepartmentofEnvironment,ClimateChangeandWater DoP DepartmentofPlanning DSEWPC DepartmentofSustainability,Environment,Water,PopulationandCommunities E endangered EA EnvironmentalAssessment EARs EnvironmentalAssessmentRequirements EEC endangeredecologicalcommunity EMD electrolysismanganesedioxide EP&AAct EnvironmentalPlanningandAssessmentAct1979 EPBCAct EnvironmentProtectionandBiodiversityConservationAct1999 EPL EnvironmentProtectionLicence GHG greenhousegas ha hectares KCT KooragangCoalTerminal km kilometres Leq(15minute) TheAweightedsoundpressurelevelaveragedonanenergybasisovera15 minuteperiod. m metres MajorProjectsSEPP StateEnvironmentalPlanningPolicy(MajorProjects)2005 MAR marine MIG migratory Mtpa milliontonnesperannum NCC NewcastleCityCouncil NCIG NewcastleCoalInfrastructureGroup NES nationalenvironmentalsignificance NPC NewcastlePortsCorporation NSW NewSouthWales PASS potentialacidsulphatesoils PEA PreliminaryEnvironmentalAssessment PFM PlanningFocusMeeting PHA preliminaryhazardanalysis PM10 particulatematterwithequivalentaerodynamicdiametersof10μmorless POEOAct ProtectionoftheEnvironmentOperationsAct1997 PWCS PortWaratahCoalServicesLimited SEE SEESustainabilityConsulting SEPP StateEnvironmentalPlanningPolicy SEPP14 StateEnvironmentalPlanningPolicyNo.14– CoastalWetlands STAP StapletonTransportation&PlanningPtyLimited T4Project TheTerminal4Project TSCAct ThreatenedSpeciesConservationAct1995 TSP totalsuspendedparticulates V vulnerable

EMGA MitchellMcLennan

Planning + Environment + Acous cs PWCS

SYDNEY NEWCASTLE Ground  oor, Suite 01, 20 Chandos Street Level 1, 6 Bolton Street St Leonards, New South Wales, 2065 Newcastle, New South Wales, 2300 T 02 9493 9500 F 02 9493 9599 T 02 4927 0506 F 02 4926 1312

www.emgamm.com