M/s. A. surti Developers Pvt Ltd

FORM-1 (I) Basic Information

Sr. Item Details No 1 Name of the Project Proposed Residential cum commercial Project 2 S. No. in the Schedule 8(b) 3 Proposed capacity/area /length/tonnage to be Total plot area: 7176.91 Sq.m handled/command area/lease area/ number of FSI area 22649.72 Sq.m wells to be drilled Non FSI area 20501.14 Sq.m Total Construction area: 43150.86 Sq.m 4 New/Expansion/Modernization New

5 Existing Capacity/Area etc. In the plot area admeasuring 7176.91 Sq.m,2 buildings with total construction area 43150.86 Sq.m with configuration are proposed: Building Wings Configuration

Building 1 Wing A St + P + 22 floors

Building 2 Wing A 2B + Gr (pt) + 1st to 4th commercial (pt) + 18 floors Wing B 2B + Gr + 18 floors

Wing C 2B + Gr + 18 floors

6 Category of Project i.e. ‘A’ or ‘B’ ‘B’ 7 Does it attract the general condition? If Yes, 10% BUA to be handed over to MMRDA Please specify 8 Does it attract the specific condition? If yes, Not applicable Please specify 9 Location Oshiwara District Centre, Jogeshwari Plot/Survey/Khasra No. CTS No. 288 B Village Bandivali Tehsil Andheri District Suburban District State 10 Nearest railway station/airport along with Ram Mandir Railway Station (0.84 km) distance in km. Jogeshwari railway Station (0.88 km) Chhatrapati Shivaji International Airport (5.10 km) 11 Nearest Town, City, District Headquarters Mumbai along with distance in km. 12 Village Panchayats, ZillaParishad, Municipal Mumbai Metropolitan Region Development Authority

1 M/s. A. surti Developers Pvt Ltd

Corporation, Local body (complete postal (MMRDA) addresses with telephone nos. to be given) 13 Name of the applicant A surti Developers Pvt Ltd 14 Registered Address CTS No.288, Amrut Nagar, Bandivali Village, Jogeshwari (W), Mumbai 400102 15 Address for correspondence: As above Name Mr. Narayan Pagarani Designation(Owner/Partner/CEO) Director Address as above Pin Code 400102 E-mail [email protected] Telephone No. 26782802/26766146 Fax No. -- 16 Details of Alternative Sites examined, If any. This is being Residential / Commercial plot leased by Location of these sites should be shown on a MMRDA Authority. No alternate site is examined. topo sheet 17 Interlinked Projects No 18 Whether separate application of interlinked No project has been submitted? 19 If yes, date of submission Not Applicable 20 If no, reason Not Applicable 21 Whether the proposal involves approval/clearance under: if yes, details of the same and their status to be given. Not Applicable The Forest (Conservation) Act, 1980? The Wildlife (Protection) Act, 1972? The C.R.Z. Notification, 1991? 22 Whether there is any Government No Order/Policy relevant/relating to the site? 23 Forest land involved (hectares) No 24 Whether there is any litigation pending No against the project and/or land in which the project is propose to be set up? Name of the Court/ Case No./ Orders/directions of the Court, if any and its Relevance with the proposed project. * Capacity corresponding to sectorial activity (such as production capacity for manufacturing, mining lease area and production capacity for mineral production, area of mineral exploration, length for linear transport infrastructure, generation capacity for power generation etc.)

2

M/s. A. surti Developers Pvt Ltd

(II) Activity 1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) Sr. Information/Checklist Yes/No Details thereof (with approximate quantities/ rates, No. Confirmation wherever possible) with source of information data 1.1 Permanent or No • No change in land use. temporary change in • The developers have proposed residential/commercial land use, land cover or Buildings. The land use will be Residence being the topography including area developed as per govt. Notification (MMRDA). • increase in intensity of There shall be green area development plan to provide beautification and natural environment to the land use (with respect site. to local land use plan) 1.2 Clearance of existing The plot is vacant. There is no clearance of vegetation or land, vegetation and No building required. building? 1.3 Creation of new land No Land use remains the same. uses 1.4 Pre-construction Yes Geo-Technical investigations have been carried out. investigations e.g. bore houses, soil testing? 1.5 Construction Works? Yes In the plot area of 7176.91 sq.m The work of construction of Building 1 with the configuration St + P + 22 floors as approved by local planning Authority i.e. MMRDA for the FSI area of 9425.88 sq.m as per the FSI potential prevailing at the time of approval & Non FSI area 8551.96 sq.m (Total construction area) was commenced and completed as per the CC dtd 16th February 2010. It is now proposed to add Bldg no. 2 with the configuration as under due to allocation of additional FSI by MMRDA.

Building Wings Configuration

Building 2 Wing A 2B + Gr (pt) + 1st to 4th commercial (pt) + 18 floors Wing B 2B + Gr + 18 floors

Wing C 2B + Gr + 18 floors

Thus total project details are as under Building Wings Configuration

Building 1 Wing A St + P + 22 floors

3

M/s. A. surti Developers Pvt Ltd

Sr. Information/Checklist Yes/No Details thereof (with approximate quantities/ rates, No. Confirmation wherever possible) with source of information data Building 2 Wing A 2B + Gr (pt) + 1st to 4th commercial (pt) + 18 floors Wing B 2B + Gr + 18 floors

Wing C 2B + Gr + 18 floors

Since the bldg no. 1 is already completed & occupied, the environmental parameters required to be operated as per EIA Notification 2006 shall be implemented for the Bldg no.2 1.6 Démolition Works? No Not Applicable 1.7 Temporary sites used Yes • During the construction phase, 25 Labors will be for construction works provided with housing facilities which is of purely on or housing of temporary basis. construction workers? • The site has temporary store rooms and site office during construction phase, which will be later demolished. The demolition waste will be used within the site to the best possible extent. 1.8 Above ground Yes Proposed construction includes configuration: buildings, structures or Building Wings Configuration earthworks including linear structures, cut Building 1 Wing A St + P + 22 floors and fill or excavations. Building 2 Wing A 2B + Gr (pt) + 1st to 4th commercial (pt) + 18 floors Wing B 2B + Gr + 18 floors

Wing C 2B + Gr + 18 floors

1.9 Underground works Yes No underground works including mining / Tunneling is including mining or required except activities like excavation of earth only for tunneling? basement, , lay down of pipes, underground storage tank, electric cables, soak pits etc. 1.10 Reclamation works? No Not envisaged 1.11 Dredging? No Not envisaged 1.12 Offshore structures? No Not envisaged 1.13 Production and No The proposal is for residential / commercial complex. manufacturing Production and manufacturing is not involved. Process?

4

M/s. A. surti Developers Pvt Ltd

Sr. Information/Checklist Yes/No Details thereof (with approximate quantities/ rates, No. Confirmation wherever possible) with source of information data 1.14 Facilities for storage of Yes Separate raw material storage yard will be provided which goods or materials? will be temporary. Construction Phase: • Cement will be separately stored under cover in bales. • Sand will be stacked neatly under tarpaulin cover. • Bricks and steel will be laid in open. Operation Phase: Storage area for solid waste, Manure and Sludge will be provided. Biodegradable waste 255 Kg/Day Non- Biodegradable waste 109 Kg/Day Treatment & Disposal : • The biodegradable waste will be treated in OWC. Manure obtained shall be used as manure for landscaping. • Non- Biodegradable waste will be handed over to recyclers. • Sewage sludge will be used as manure for gardening. • Wastewater (99 KLD) will be treated in STP of capacity 103 KLD. Treated water will be utilized as follows; Flushing - 43 KLD Gardening - 8 KLD 1.15 Facilities for treatment Yes Construction Phase: or disposal of solid Solid waste generated during construction phase is majorly waste or liquid re-sable. effluents? Waste material like empty cement bags, scrap metal, etc. shall be sold to local vendors for recycling. Broken tiles shall be used as mosaic of terraces and skirting purposes. During the construction phase, temporary septic tanks will be provided treatment of wastewater generated from construction labours and other manpower. Temporary sanitary toilets will be provided.

Operation Phase: Total solid wastes 364 Kg/Day Biodegradable waste 255 Kg/Day Non- Biodegradable waste 109 Kg/Day

Treatment & Disposal : As per SWM Rule - 2016 • The biodegradable waste will be treated in an OWC Manure obtained shall be used as manure for landscaping.

5

M/s. A. surti Developers Pvt Ltd

Sr. Information/Checklist Yes/No Details thereof (with approximate quantities/ rates, No. Confirmation wherever possible) with source of information data • Non- Biodegradable waste will be handed over to local recyclers. • Sewage sludge will be used as manure for gardening. • Wastewater (99 KLD) will be treated in STP of capacity 103 KLD. Treated water ( 92 KLD) meeting the discharge norms of CPCB after reuse for flushing & gardening as follows; Flushing 43KLD Gardening 8KLD

1.16 Facilities for long term No Not Applicable housing of operational workers? 1.17 New road, rail or sea No Access through 13.40 m wide D.P. road & 25.00 m wide D.P. traffic during road. There will be no new road and rail proposed at this construction of juncture. operation? 1.18 New road, rail, air, No No new Rail proposal is with government as of now. Road waterborne or other infrastructure already exists. However it will be augmented transport infrastructure time to time to meet the need of the time including new or altered routes and stations, ports, airports etc.? 1.19 Closure or diversion of No There will be no diversion or closure of the existing transport existing transport routes and infrastructure. routes or infrastructure leading to changes in traffic movements? 1.20 New or diverted No Not Applicable transmission lines or pipelines? 1.21 Impoundment, No No impoundment, damming, culverting, realignment or other damming, culverting, changes to the hydrology of surface water courses is realignment or other envisaged. changes to the hydrology of watercourses or aquifers? 1.22 Stream crossings? No Not Applicable 1.23 Abstraction or transfers No Water requirement in construction phase will be supplied of water from ground from tanker (10 KLD). Total water requirement of 114 KLD

6

M/s. A. surti Developers Pvt Ltd

Sr. Information/Checklist Yes/No Details thereof (with approximate quantities/ rates, No. Confirmation wherever possible) with source of information data or surface waters? will be met from MCGM/ recycled water. 1.24 Changes in water No The project location is in well-developed urbanized area. bodies or the land SWD network is available around the project. SWD network surface affecting designed for project shall be connected to the SWD provided drainage or run-off. by corporation. This will be in line with the natural drainage pattern of area and the same shall be approved by corporation. There is no change in the present drainage course of water body. 1.25 Transport of personnel No 25.00 m wide & 13.40 m wide D.P. road will be utilized for or materials for the transportation of material. Workers required for construction, operation construction activity are provided with labor quarters. Any or decommissioning? additional demand for peak time will be deployed from local or nearby area. The material will be transported through the vehicles fulfilling the PUC norms & fitness renewal certificates. 1.26 Long-term dismantling No Not Applicable or decommissioning or restoration works? 1.27 Ongoing activity No Not Applicable during decommissioning which could have an impact on the environment? 1.28 Influx of people to an Yes Construction Phase: area in either Around 50 labors will come to site during peak construction temporarily or phase. 25 shall be provided with temporary housing facilities. permanently? Operation Phase: On completion of the project, there will be regular movement of residents, visitors, staff and related personals. 1.29 Introduction of alien No Native species will be planted. species? 1.30 Loss of native species No Not applicable. or genetic diversity? 1.31 Any other actions? No Not applicable

2. Use of Natural resources for construction or operation of project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply).

7

M/s. A. surti Developers Pvt Ltd

Sr. Information/Checklist Yes/No Details thereof (with approximate quantities/ rates, No. Confirmation wherever possible) with source of information data 2.1 Land specially No Agricultural land not involved. undeveloped or The land use as per MMRDA Authority is agricultural land (ha) residential/commercial 2.2 Water (expected source Yes Construction Phase: Around 50 labors will come to site & competing users) during peak construction phase. 25 shall be provided with unit KLD temporary housing facilities. The water demand will be met by water tankers. Operation Phase Total water demand of the project is expected to be 210 KLD; Particulars Quantity Source Domestic 70 KLD MCGM Flushing 43 KLD From treated Gardening 8 KLD water of STP

2.3 Minerals (MT) Yes Minerals used for the construction project are - Cement, Sand, Stone, Aluminum or Iron for windows frames. Cement/Gypsum for plastering etc. 2.4 Construction material – Yes The construction materials will be procured from local stone, aggregates, dealer. and/soil (expected source-MT) 2.5 Forests and timber Yes Certified Timber will be purchased from nearby markets. (source-MT) 2.6 Energy including Yes • Operation Phase : electricity and fuels Connected load: 2859 KW (source, competing Maximum Demand: 1161 KW users) Unit: fuel (MT), 1 DG set of 400 KVA will be proposed as backup during energy (KW) power failure. HSD will be used as fuel to run standby D.G. sets. 2.7 Any other natural No No other natural resources will be used. resources (use appropriate standard units)

1. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health Sr. Information/Checklist Yes/No Details thereof (with approximate quantities/ rates, No. Confirmation wherever possible) with source of information data 3.1 Use of substances or No Discarded containers of paints, solvents etc. during

8

M/s. A. surti Developers Pvt Ltd

Sr. Information/Checklist Yes/No Details thereof (with approximate quantities/ rates, No. Confirmation wherever possible) with source of information data materials, which are construction phase. They will be stored separately and will hazardous (as per be handed over only to authorized processor for the facility. MSIHC rules) to human health or the environment (flora, fauna, and water supplies) 3.2 Changes in occurrence No Regular Pest control and adequate fumigation will be done. of disease or affect Precautions to avoid formations of water ponds to avoid disease vectors (e.g. any water bound diseases. insect or water borne diseases) 3.3 Affect the welfare of No The living conditions of the people are expected to be people e.g. by changing improved. living conditions? 3.4 Vulnerable groups of No There are school and other infrastructures within 500 m people who could be radius area of the project. However traffic planning and affected by the project waste management during construction and operation phase e.g. hospital patients, shall mitigate the adverse effect, if any. children, the elderly etc., 3.5 Any other causes No Not Applicable

4 Production of solid wastes during construction or operation or decommissioning (MT/month) Sr. Information/Checklist Yes/No Details thereof (with approximate quantities/ rates, No. Confirmation wherever possible) with source of information data 4.1 Spoil, overburden or No Not Applicable. mine wastes 4.2 Municipal waste Yes Particulars Quantity (Kg/Day) (domestic and or Total solid wastes 364 Kg/Day commercial wastes) Biodegradable waste 255 Kg/Day Non- Biodegradable waste 109 Kg/Day

4.3 Hazardous wastes (as No Not Applicable per hazardous waste management rules) 4.4 Other industrial process No Not Applicable wastes 4.5 Surplus product No Not Applicable 4.6 Sewage sludge or other Yes Dried sludge from STP will be used as manure for the sludge from effluent plants.

9

M/s. A. surti Developers Pvt Ltd

Sr. Information/Checklist Yes/No Details thereof (with approximate quantities/ rates, No. Confirmation wherever possible) with source of information data treatment

4.7 Construction or Yes Construction waste will be used within project only. demolition wastes Unusable and excess construction debris will be disposed at designated places as per local permission through authorized contractor

WASTE QTY MANAGEMENT

Cement Empty bags to be handed over 12945 bags Bags to recycler Paint container 647 nos. To be handed over to recycler (@20L) Scrap metal 4.3 MT 100 % to be sold for recycling generated Waste tiles to be used for Broken skirting. Broken pieces to be 617 sq.mt Tiles used for china mosaic waterproofing terrace. To be used as a layer for Aggregates 8.3 MT internal roads and building boundary wall

4.8 Redundant machinery No Not Applicable or equipment 4.9 Contaminated soils or Yes During painting, spillage of oil, diesel. Any such spillage other materials shall be mitigated immediately once observed by isolating the area and removing spilled material.

5.Release of pollutants or any hazardous, toxic or noxious substances to air (kg/hr)

Sr. Information/Checklist Yes/No Details thereof (with approximate quantities/ rates, No. Confirmation wherever possible) with source of information data 5.1 Emissions from Yes • Emission will be generated from vehicular transport to the combustion of fossil project. But same will be within the prescribed limit as fuels from stationary or vehicles with possessed PUC. mobile sources 5.2 Emission from No Not Applicable

10

M/s. A. surti Developers Pvt Ltd

Sr. Information/Checklist Yes/No Details thereof (with approximate quantities/ rates, No. Confirmation wherever possible) with source of information data production processes 5.3 Emissions from Yes • Emissions will be generated while handling and materials handling transportation of materials like cement, sand etc. to site including storage or and will be temporary in nature. transport • RMC shall be used preferably to reduce fugitive emissions due to material handling. • Regular water sprinkling shall be done to reduce dust generation • Transportation shall be done in covered trucks. 5.4 Emissions from Yes The project may cause rise in dust level during construction construction activities phase. Precautions will be taken to reduce dust generation including plant and during construction phase. equipment • RMC use will eliminate the handling of cement, sand and concrete; thus dust emission will be minimized. • Tarpaulins will be used to cover trucks carrying materials. • Water sprinkling will be done at regular intervals to reduce dust generation. • Net lawn will be used during construction. 5.5 Dust or odors from Yes Dust generation will be controlled as described above handling of materials proper ventilation will be provided around STP including construction During operation phase, municipal solid waste shall be materials, sewage and treated in OWC to produce manure. waste Sewage shall be treated in established technology like MBBR. 5.6 Emissions from No Not Applicable incineration of waste 5.7 Emissions from burning No Not Applicable of waste in open air (e.g. slash materials, construction debris) 5.8 Emissions from any No Not Applicable other sources

6 Generation of Noise and vibration, and emissions of Light and heat.

Sr. Information/Checklist Yes/No Details thereof (with approximate quantities/ rates, No. Confirmation wherever possible) with source of information data 6.1 From operation of Yes Noise generation from construction equipment’s used for equipment e.g. engines, drilling, cutting operations.

11

M/s. A. surti Developers Pvt Ltd

Sr. Information/Checklist Yes/No Details thereof (with approximate quantities/ rates, No. Confirmation wherever possible) with source of information data ventilation plant, During Operation Phase, Noise will be generated due to crushers operation of DG sets. For control of noise following measures shall be adopted: • Equipment’s used shall be conforming to the present norms to meet the noise standards • Equipment’s shall be regularly maintained • Any high noise generating construction activities would be carried out only during day time with all necessary precaution with noise barriers along the project activity. • Personal Protective Equipment’s (PPE) shall be provided to construction workers. • Acoustic enclosure for DG Set with stack height as per norm will be provided. • Noise level will be monitored and enhancement in the mitigation measure will be taken if required.. 6.2 From industrial or No Not Applicable similar processes 6.3 From construction or Yes The construction activities will include the following noise demolition generating activities; 1. Excavation activities etc. 2. Concreting and mixing. 3. Heavy vehicle movement. Following precautions shall be taken to control noise pollution : • High noise generating activities shall be carried out during day time only. • Workers working near high noise machinery would be provided with ear muffs/ear plugs. 6.4 From blasting or piling Yes Only during piling work. 6.5 From construction or Yes During Construction Phase: operational traffic There will be transport of materials for construction work. Precautions will be taken to reduce the impacts of the vehicular movement such as vehicular trips will be at peak traffic hours. All vehicles used will be meeting the statutory requirements of operation and maintenance.

During Operation Phase: The vehicular parking will be restricted only in the adequate parking area provided, which would help in reducing noise pollution due to traffic congestion. Adequate tree plantation will also help to reduce the noise level and enhance air quality

12

M/s. A. surti Developers Pvt Ltd

Sr. Information/Checklist Yes/No Details thereof (with approximate quantities/ rates, No. Confirmation wherever possible) with source of information data 6.6 From lighting or cooling No Not Applicable systems 6.7 From any other sources No Not Applicable

7 Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea Sr. Information/Checklist Yes/No Details thereof (with approximate quantities/ rates, No. Confirmation wherever possible) with source of information data 7.1 From handling, storage, Yes Negligible quantity use or spillage of hazardous materials 7.2 From discharge of Yes The total wastewater generated (99 KLD) from the buildings sewage or other effluents will be treated in STP of capacity of 103 KLD and the to water or the land Recycled water (51 KLD) will be utilized for landscaping and flushing purpose. Excess treated water will be send to (expected mode and existing municipal drain. place of discharge) 7.3 By deposition of No Dust will be generated during construction phase from pollutants emitted to air earthworks and movement of vehicles. Appropriate fugitive into the land or into dust control measures, including water sprinkling of exposed areas and dust covers for trucks, will be provided to water minimize any impacts. During Operation Phase, DG exhaust will be discharged at stipulated height by providing adequate stack height. 7.4 From any other sources No Not Applicable 7.5 Is there a risk of long No Not Applicable term buildup of pollutants in the environment from these sources?

8. Risk of accidents during construction or operation of the project, which could affect human health or the environment Sr. Information/Checklist Yes/No Details thereof (with approximate quantities/ rates, No. Confirmation wherever possible) with source of information data 8.1 From explosions, No During construction all construction workers will be spillages, fires etc from provided with suitable Personal Protective Equipment as storage, handling, use or required under the health & safety norms. Suitable production of hazardous firefighting measures will be provided to reduce damage due substances to fire-accidents. 8.2 From any other causes No Not envisaged

13

M/s. A. surti Developers Pvt Ltd

8.3 Could the project be Yes This area falls under seismic zone –III according to Indian affected by natural Standard Seismic zoning map. disasters causing environmental damage (e.g. floods, earthquakes, landslides, could burst etc)?

9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality Sr. Information/Checklist Yes/No Details thereof (with approximate quantities/ rates, No. Confirmation wherever possible) with source of information data 9.1 Lead to development of supporting, utilities, ancillary development or development stimulated Yes Supporting and ancillary development will take place by the project which could have impact on the environment e.g.:

Supporting infrastructure Yes Internal Roads, Rainwater Harvesting, STP etc. will be (roads, power supply, provided. waste or waste water treatment, etc) Housing development Yes The project provides a well-designed residential housing Extractive industries No area for the occupants. Supply industries No Other No 9.2 Lead to after use of the No Not Applicable site, which could have an impact on the environment 9.3 Set a precedent for later Yes This will create job opportunity for support staff like developments security, maintenance, household workers etc. 9.4 Have cumulative effects Yes The project proposed is in the residential/commercial zone due to proximity to other of MCGM. As per development plan of MMRDA, the existing or planned provision of adequate water, Storm Water Drainage, projects with similar availability of electricity, Traffic management and effects mitigation are the component of considered in the approved DCR

(iii) Environmental Sensitivity

Sr. Areas Name/ Aerial distance (with 15 km) Proposed project No. Identity location boundary 1 Areas protected under No Not Applicable

14

M/s. A. surti Developers Pvt Ltd

Sr. Areas Name/ Aerial distance (with 15 km) Proposed project No. Identity location boundary international conventions, national or local legislation for their ecological, landscape, cultural or other related value 2 Areas which are Sanjay Gandhi 0.85 km important or sensitive of National Park. ecological reasons – Vihar Lake 5.89 km wetlands, water courses Lake 5.82 km or other water bodies, Thane creek 12.89 km coastal zone, biospheres, mountains, forests 3 Areas used by protected, Sanjay Gandhi 0.85 km important or sensitive National Park. species of flora or fauna Vihar Lake 5.89 km for breeding, nesting, Powai Lake 5.82 km foraging, resting, over Thane creek 12.89 km wintering, migration. 4 Inland, coastal, marine or Vihar Lake 5.89 km underground waters Powai Lake 5.82 km Thane creek 12.89 km

5 State, national No The project is located within Municipal limits- boundaries MCGM 6 Routes or facilities used No Not Applicable by the public for access to recreation or other tourist, pilgrim areas 7 Defense installations No Not Applicable 8 Densely populated or Yes Residential, Commercial and Industrial area all built-up area around the site. 9 Areas occupied by Yes Name Distance Direction sensitive man made land from project uses (hospitals, schools, (km) Nearest Ruby places of worship, 0.50 Hospital hospital West community facilities) Nearest Fatima 0.50 West School School Nearest Millal 1.26 West College College

15 M/s. A. surti Developers Pvt Ltd

Sr. Areas Name/ Aerial distance (with 15 km) Proposed project No. Identity location boundary 10 Areas containing No Not Applicable important, high quality or scarce resources (ground water resource, surface resources, forestry, agriculture, fisheries, tourism, minerals) 11 Areas already subjected No Not Applicable to pollution or environmental damage. (those where existing legal environmental standards are exceeded) 12 Areas susceptible to No This area falls under seismic zone –III according to natural hazard which Indian Standard Seismic zoning map. could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions)

16