Name of Work AMRUT Scheme to PROJECT COMPONENTS SL Project Name Project RevisedAS Tendered RevisedA Work Agreeme Name of Targetted date of completion NO Cost (Rs. In / To be S (Rs. Order nt No. Contract (Rs. In Crore) Tendered In Crore) Amount date or Crore) GO(Rt) (on) GO(Rt) and Date No. No. (Rs. In 36/2020/L 36/2020/L Crore) SGD dted SGD dted TVM TVM 4.1.2020 4.1.2020 WATER SUPPLY 1 Laying pumping main of 16.50 Re- Rs.5,87,18 No.10/201 Sali P 31-05-2021 (NHAI & Railway 500mm DI pipe from Tendered ,745/- 8- Mathayi permissions) JnNURM WTP at on dated 10/SE/PH to Pumphouse 12/02/201 25/06/201 C/CHN at Thammanam for 8 8 dated 08- additional pumping of 10-2018 water (upto 18mld) to Kochi city in Kochi Corporation 16-17.

2 Laying rider main from 3.25 3.65 Tendered 3.65 Rs.1,10,57 No.14/201 M/s 20-11-2020 to on ,343/- 7- Minartech Elamkulam, Chettichira, 23/01/201 dated 06- 18/SE/PH Developer Ponnurunni areas and 8 03-2018 C/CHN s Pvt Ltd distribution lines in dated 14- Chakkaraparambu,Chal 03-2018 ikkavattom areas in Kochi Corporation 2016-17.

3 Construction of 17 LL 7.75 Tendered Rs.7,00,00 No.11/201 A.Domini 31-07-2021 capacity OHSR and on ,000/- 9- c CWR at . 15/02/201 20/SE/PH 8 . C/CHN Retendered dated 11- on 23-10- 11-2019 2018 4 Construction of 15LL 7.75 Re- Rs.4,90,13 No.13/201 Sri.M.J.T 31-03-2021 OHSR and 2 LL CWR Tendered ,290/- 8- homas at Vadathode, on dated 22- 19/SE/PH Cheranalloor. 26/03/201 12-2018 C/CHN 8 dated 04- Retendered 01-2019 on 23-10- 5 Water supply sector - 7.65 7.76 Re- 7.76 Rs.4,22,18 No.08/201 Sri. Shaji 31-12-2020 Kochi Corporation - Tendered ,108/- 8- K. Laying 500mm DI line on dated 23- 19/SE/PH Mathew from Pump house at 06/03/201 06-2018 C/CHN Thammanam to OHSR 8 dated 28- at Kadavanthara. 07-2018 6 Laying of 500mm 10.70 Tendered Rs.5,47,39 No.03/201 Sri. 31-03-2021 transmission line form on ,016/- 8- Paulson Kathrikadavu to 07/12/201 dated 09- 19/SE/PH Chacko proposed Pachalam 7 04-2018 C/CHN CWR. dated 24- 04-2018 7 Construction of 13LL 6.00 Tendered 4,07,15,69 No.14/201 Smt.Rema 31-07-2021 capacity OHSR at on 8/- dated 8- ni S.Nair Edakochi 23/01/201 31-12- 19/SE/PH 8. 2018 C/CHN Retendered dated 19- on 23-10- 01-2019 8 Construction of 25 LL 11.65 Tendered2018 Rs.8,34,19 No.04/201 Sri. Abu 30-11-2021 OHSR at Karuvelippady on ,073/- 9- Mathew 15/02/201 dated 07- 20/SE/PH 8. 03-2019 C/CHN Retendered Dated 27- on 23-10- 06-2019 2018 9 Construction Of 40 LL 15.00 Tendered Rs.13,87,0 No.10/201 M/s Noble 30-09-2021 capacity OHSR at on 13-02- 0,000/- 9- Tech 2019 20/SE/PH Engg C/CHN dated 31- 10-2019 10 Laying 400mm DI K9 pipe 4.40 Tendered Rs.1,38,65 No.09/201 M/s.East Considering the Number of pipes line from Perumanoor To on ,995/- 8- and cables present in Old for a length of 17/02/201 dated 23- 19/SE/PH Engineers road and MG road KWA has 1270m 8 06-2018 C/CHN proposed to use the existing dated 28- 450mm CI pipe for 870m, out of 07-2018 1270m . But worshipful Mayor has not accepted this proposal and the alternate route proposed by the Worshipful Mayor is not tehnically feasible and hence the work was stopped . Now as per the direction of ACS on 9/10/2020, the district collector has directed to test the 450mm CI pipe and exiting OHSR at Ravipuram. The testing will be started in this week

11 Replacement of 5000 5.00 damaged serviced water connections

12 Shifting of existing water ######### Rs.16,41,1 No.21/201 Sri. A.B. 31-03-2021 connections and bye lane 98.00 9-20 Gopalakri connections to the newly Dt.20.07.2 Dt.19.11.2 shnan laid 160mm PVC line 019 019 allied to laying rider main from Kathrikkadavu to Elamkulam, Chettichira ######## and Ponnurunni areas and distribution lines in Chakkarapparambu and Chalikkavattom areas in Kochi Corporation SEWERAGE Tendered on Rehabilitation of 5 MLD 15/02/201 1 13.70 STP plant at Elamkulam 8 Retendered on 23-10-

DAILY WORK PROGRESS DATE Work REMARKS 40 LL OHSR at Kaloor- Pile cap reinforcement and shuttering work in progress, Perumanoor Ravipuram - Testing work in progress, 25 LL OHSR at Karuvelippady - 5th pile concreting completed and 6th pile boring in progress. 15 LL OHSR at Cheranalloor: Form work and reinforcement work of 17.12.2020 floor beam and bottom slab of OHSR in progress, 17 LL OHSR at Pachalam- sheet piling work for construction of sump is going on.Shifting connections- work completed (100%)

40 LL OHSR at Kaloor- Pile cap reinforcement and shuttering work in progress, Perumanoor Ravipuram - Testing work in progress, 25 LL OHSR at Karuvelippady - 4th pile concreting completed and 5th & 6th pile boring in progress. 13 LL OHSR at Edakochi - Work stopped due to union problems. 16.12.2020 Kathrikkadavu - Pachalam pipe line- Work stopped due to union problems. 15 LL OHSR at Cheranalloor: Form work and reinforcement work of floor beam and bottom slab of OHSR in progress, 17 LL OHSR at Pachalam- sheet piling work for construction of sump is going on. 40 LL ohsr at kaloor- 14Nos Pile cap concreting is going on Perumanoor Ravipuram - Testing work in progress. 25 LL OHSR at Karuvelippady -4th pile boring completed.5th pile boring in progress. 13 LL OHSR at Edakochi - Work stopped due to union problems. Kathrikkadavu - Pachalam pipe line - Work stopped due to union 15.12.2020 problems. Cheranalloor tank: Form work and reinforcement work of floor beam and bottom slab of tank . 17 LL OHSR at Pachalam- sheet piling work for construction of sump is going on.

40 LL ohsr at kaloor- Pile cap of reinforcement work and earth filling Perumanoor Ravipuram - Testing work in progress. 25 LL OHSR at Karuvelippady -Boring of Pile work in progress. . 13 LL OHSR at Edakochi - Work stopped due to union problems. . Thammanam - pipe line - 500mm DI pipe laying 14.9m(3486.88m/3465m) completed. Kathrikkadavu - Pachalam 14.12.2020 pipe line - Replacing 150mm AC pipe with 160mm PVC pipe work started. Cheranalloor tank: Form work and reinforcement work of beam and bottom slab of tank . 17 LL OHSR at Pachalam- sheet piling work for construction of sump is going on.

40 LL ohsr at kaloor- 14 Nos pile cap concreting Perumanoor Ravipuram - testing work in progress. 25 LL OHSR at Karuvelippady - 3rd pile boring going on. Elamkulam -Chettichira shifting of 336 Nos out of 310 Nos completed and 5by lane interconnection work completed out of 44Nos (98% completed). 13 LL OHSR at Edakochi - Reinforcement work going on. Thammanam - Kadavanthra pipe line - Contractor informed that the work will started on 12.12.2020. Kathrikkadavu - Pachalam pipe line - Contractor informed that the work will started on 14.12.2020. Maradu - Thammanam pipe line 9.12.2020 work: NHAI informed that the crossing along underpass is not acceptable.Also they informed that as per clause 9 of the Ministry Policy circular dated 22.11.2016,ROW is restricted the utility services can be allowed beneath the carriage way of service road, if available, the subject to the condition that the utility services be laid in concrete ductwhich will design to carry traffic on top.The width of the duct shallnot be lass than 1 lane.Cheranalloor tank: Form work and reinforcement work of stair case is going on

17 LL ohsr at pachalam- Shifting load testing equipments from the site. 15LL ohsr at cheranelloor- Reinforcement work and shuttering work of stair case in progress. 40 LL ohsr at kaloor- Pile cap reinforcement and shuttering work in progress. Perumanoor Ravipuram - Excavation is going on at Perumanoor pump house for tracing out the existing 450mm CI line to be tested. For testing the OHSR at Ravipuram - Arrangements are made to fill the OHSR. 25 08.12.2020 LL OHSR at Karuvelippady - 3rd pile boring going on. Elamkulam - Chettichira shifting of 336 Nos out of 310 Nos completed and 5by lane interconnection work completed out of 44Nos. 13 LL OHSR at Edakochi - Reinforcement work going on. Thammanam - Kadavanthra pipe line - A meeting was convened by SE, Corporation, Kochi, It was decided to restart the pipe line after election. Kathrikkadavu - Pachalam pipe line - A meeting was convened by SE, Corporation, Kochi, It was decided to restart the pipe line after election. 17 LL ohsr at pachalam- Pile load test completed and dismantling of load is carried out. 15LL ohsr at cheranelloor- 3rd stage column concreting-7 Nos. 40 LL ohsr at kaloor- Pile cap reinforcement and shuttering work in progress. Perumanoor Ravipuram - Excavation started at Perumanoor pump house for tracing out the existing 450mm CI line to be tested. 25 LL OHSR at Karuvelippady - 07.12.2020 2nd pile boring work completed. Elamkulam -Chettichira shifting of 334 Nos out of 310 Nos completed and 5by lane interconnection work completed out of 44Nos. 13 LL OHSR at Edakochi - No progress in work. A meeting was proposed to convene in the division office today with the contractor to discuss the sloww progress of the work. contractor has informed the EE her in convenience to attend the meeting today and has requested to postpone the same to Wednesday 17 LL ohsr at pachalam- Pile load test successfully completed. 15LL ohsr at cheranelloor- 3rd stage second shift column concreting -11 Nos. completed. 40 LL ohsr at kaloor- Pile cap reinforcement and 05.12.2020 shuttering work in progress. Perumanoor Ravipuram - Excavation started at Perumanoor pump house for tracing the 450mm CI line to be tested. 25 LL OHSR at Karuvelippady - 2nd pile boring in progress. 17 LL ohsr at pachalam- Pile load test is going on. 15LL ohsr at cheranelloor- 3rd stage column concreting is going on. 40 LL ohsr at 04.12.2020 kaloor- Pile cap reinforcement and shuttering work in progress. Perumanoor Ravipuram - Arrangement of pressure testing of existing 450 mm CI pipe line in progress. Elamkulam -Chettichira shifting of 305 Nos out of 310 Nos completed. 17 LL ohsr at pachalam- loading for pile load test is going on. 15LL ohsr at cheranelloor- concreting of Ist lift of 4 nos third stage column and 7 Nos. second lift column completed. 40 LL ohsr at kaloor- concreting of 7 Nos. pile cap completed. 25 LL OHSR at 03-12-2020 Karuvelippady - Piling work in progress. 1 No. pile completed. Perumanoor Ravipuram - Arrangement of pressure testing of existing 450 mm CI pipe line. Elamkulam -Chettichira shifting of 305 Nos out of 310 Nos completed. 13 LL OHSR at Edakochi - Pile cap reinforcement work going on. 17 LL ohsr at pachalam- loading for pile load test is going on 15LL ohsr at cheranelloor- concreting of Ist lift of11 nos third stage column completed. 40 LL ohsr at kaloor- pile cap reinforcement and shuttering work completed for seven pile caps. 25 LL OHSR at Karuvelippady - Piling work in progress. boring of 1 No. Pile completed Perumanoor Ravipuramfor conducting pipe test of 02-12-2020 existing 450mm CI line letters were given to obtain traffic permission,informed KSEB and BSNL regarding the work.kseb informed that during our excavation work they need to take shut down for that special permission is required till 16nth of this month considering election work. .Elamkulam -Chettichira shifting of 299Nos out of 310 Nos completed and 5by lane interconnection work completed out of 44Nos

Pile cap concreting for Kaloor 40 LL OHSR. Preparation for pile load test in progress at pachalam OH tank site.Third stage column concreting for Cheranelloor OHSR.Pile cap reinforcement work in 01-12-2020 progress for Edakochi tank. Piling work going on at Karuvelippady tank site.Elamkulam -Chettichira shifting of 295Nos out of 310 Nos completed and 5by lane interconnection work completed out of 44Nos Pile boring started at Karuvelippady OHSR. Concreting of columns (half) of 11 Columns above second brace level completed at Cheranelloor 30-11-20 OHSR, Reinforcement work of Pile cap is going on at Kaloor OHSR, Mud removal completed from Pachalam OHSR site after completion of pile work.

Mobilizing Equipments for Piling is going on at Karuvelippady OHSR. 27-11-20 Reinforcement work and shuttering work of Columns above second brace level is going on at Cheranelloor OHSR, Reinforcement work of Pile cap is going on at Kaloor OHSR, Removing mud from Pachalam OHSR site after completion of pile work.

Setting out of OHSR is completed at Karuvelippady OHSR. Reinforcement 25-11-20 work of Columns above second brace level is going on at Cheranelloor OHSR, Reinforcement work of Pile cap is going on at Kaloor OHSR, Removing mud from Pachalam OHSR site after completion of pile work.