Draft Priority Projects for the TMACOG region 2015‐2045 Regional Transportation Plan February 18, 2015

Estimated cost in Estimated Project Cost (from Estimated millions- from County Rank Project Name Project Description Potential Sponsor cost in Fiscal Constraint) Mode Construction Year Fiscal millions- total with Inflation** Constraint* Lucas 1 Reconstruct Anthony Wayne Trail Complete reconstruction of the Anthony Wayne Trail in City (Detroit to South Ave.); add bike of Toledo from Detroit Ave. to South Ave. including addition ODOT, Toledo 2016-2025 $55.0 $55.0 $59.3 Road path of multi-use path along parkway right-of-way Lucas 2 Access management and ped Access management and pedestrian improvements to Navarre Ave, White St. to Lallendorf Rd., to improve corridor improvements to Navarre Ave. Oregon,Toledo 2021-2025 $10.0 $10.0 $11.3 Road (White St. to Lallendorf Rd.) safety Lucas 3 Add downtown Toledo transit hub Add transit hub in downtown Toledo (Jackson Blvd. Transit Center); eliminate transit loop; reconfigure bus lanes on TARTA 2017 $17.0 $17.0 $17.5 Transit Jefferson, Summit, and Erie Sts. Wood 4 Add turn lanes to US 20 (City of Add turn lanes on US 20/23 from Rossford limits to SR 420 Rossford to SR 420) where needed ODOT 2016-2035 $10.0 $10.0 $11.6 Road Wood 5 Improvements to I-75/US 20 Improve I-75/US 20 interchange in Perrysburg to better interchange in Perrysburg handle truck traffic from westbound US 20 with minimal ODOT 2026-2035 $25.0 $25.0 $31.3 Road delays. Lucas 6 Provide ped/bike facilities on Airport Provide Airport Hwy ped/bike facilities from Holland- Sylvania Rd., across I-475 and accessing Spring Meadows ODOT, Lucas Co., Hwy (Holland-Sylvania to McCord 2021-2025 $5.4 $5.4 $6.1 Road Springfield Twp. Rd.) shopping center, to McCord Rd. Lucas 7 Widen I-475 (US 23 to Talmadge Widen I-475 to 6 lanes from US 23 to Talmadge Rd. Rd.) ODOT 2036-2045 $100.0 $100.0 $125.0 Expressway Lucas 8 Upgrade US 23/SR 51 (Monroe St.) Upgrade the US 23/SR 51 (Monroe St) interchange in Sylvania; add capacity to US 23 NB off-ramp; improve/add interchange; improve Monroe St. ODOT, Sylvania 2026-2035 $40.0 $40.0 $50.0 Expressway corridor in vicinity capacity to Monroe St. in vicinity of US 23 (including pedestrian, possibly bike, improvements) Wood 9 Upgrade I-75/SR 64 interchange Upgrade the interchange at I-75 / SR 64 (Wooster Street) in and add pedestrian facilities Bowling Green to add roundabouts and pedestrian ODOT, Bowling Green 2021-2025 $5.4 $5.4 $6.1 Road accommodation on Wooster across I-75 Lucas 10 Upgrade NHS Connector from I-75 Upgrade NHS Connector from I-75 to River Terminals to River Terminals (South Ave., (South Ave., Kuhlman and Edwin Drives including bridge); Kuhlman and Edwin Drives consider 4-way stop at Kuhlman/South. Toledo 2016-2025 $5.0 $5.0 $5.4 Road including bridge)

Lucas 11 Build a new NHS intermodal Build a new NHS Intermodal Connector between the NS terminal and I-75, as a long-term solution to heavy truck connector from NS Toledo Toledo 2026-2035 $30.0 $30.0 $37.5 Road Intermodal Terminal to I-75 traffic moving between Airline Yard and I-75. Lucas 12 Implement Lucas County-wide Implement Lucas County-wide public transit, expanding from public transit current limited service area. TARTA 2020 $20.0 $20.0 $21.5 Transit Lucas 13 Resurface Anthony Wayne Trail Resurface Anthony Wayne Trail from Monclova Rd. to (Monclova Rd. to Detroit Ave) Detroit Ave.; add a dedicated left turn signal at W. Wayne Maumee 2020 $4.0 $4.0 $4.3 Road St. Lucas 14 Improvements to Build Douglas/Laskey/Tremainsville roads intersection Douglas/Laskey/Tremainsville improvements Toledo 2025 $7.0 $7.0 $8.1 Road intersection Lucas 15 Improvements to I-475/US 24 Improve EB and WB US 24 (Anthony Wayne Trail) at I-475 interchange interchange where on-ramp and off-ramp traffic share the ODOT 2036-2045 $80.0 $80.0 $116.1 Road same merging lane. Lucas 16 Build rail grade separation at Build rail grade separation bridge at Matzinger Rd./AA & Matzinger Rd./AA & CSX crossing CSX crossing to eliminate rail/highway conflict in North Toledo industrial area; provide access to "Iron Triangle" and Toledo 2016-2025 $28.0 $28.0 $30.2 Rail to/from Jeep plant. Lucas 17 I-75/Collingwood NHS Connector Improve I-75 NB off-ramp to Collingwood Blvd. to better ramp/Logan St. handle trucks including separation of Logan Street from ramp (widen turn radii, improve curb clearance, reconstruct pavement, divert Logan into S. St Clair, revert Newton to two Toledo, ODOT 2016-2025 $2.5 $2.5 $2.7 Road way, improve lane markings, intersection channels and signage) Lucas 18 Riverside Trail East Riverside Trail East: Construct a path from Hollywood Casino north along the to Miami St. at Oakdale Ave.; continue north along Miami St. to Riverside Toledo 2016-2025 $1.1 $1.1 $1.2 Non-Motorized Dr. to Front St. where the trail would turn into a bike lane north to Millard Rd. Wood 19 Add paved berms to SR 65 (Village Add paved berms on SR 65 from Grand Rapids to Fort of Grand Rapids to City of Meigs Rd., and from East Boundary to Lime City Rds. ODOT 2021-2030 $5.0 $5.0 $5.8 Non-Motorized Rossford) Lucas 20 Swan Creek Trail Swan Creek Trail: Construct a facility from Manley to Garden to Holland-Sylvania Rd.into Swan Creek Metropark to connect to Byrne Rd. to Arlington Ave., then to the Toledo, Metroparks 2016-2025 $6.0 $6.0 $6.5 Non-Motorized Chessie Circle Trail

*Estim. Cost from Fiscal Constraint: Amount deducted from expected Plan funding; excludes full cost of projects needing special funds ** Cost with Inflation: year‐of‐project cost using 1.5% /yr inflation factor Draft Priority Projects for the TMACOG region 2015‐2045 Regional Transportation Plan February 18, 2015

Estimated cost in Estimated Project Cost (from Estimated millions- from County Rank Project Name Project Description Potential Sponsor cost in Fiscal Constraint) Mode Construction Year Fiscal millions- total with Inflation** Constraint* Lucas 21 Trilby-Washington Trail Trilby-Washington Trail: Construct a bike facility on Sylvania Ave. from Talmadge to Harvest Ln., then bike lanes north to McGregor Ln., then east to Ruth Ave. to Tremainsville Rd. to Whitmer Dr. to Edgar St. to Douglas Rd. to Bucklew Dr. Toledo 2016-2025 $5.7 $5.7 $6.1 Non-Motorized through Jackman Park to the Chessie Circle Trail and through various residential streets to Eleanor Ave. to Bennett Rd. to Sylvania Ave. to Lagrange St. to the Overland Trail Lucas 22 Widen US 20/Central Ave. Widen US 20 (Central Ave) from Centennial to west of (Centennial to west of Crissey Rd.) Crissey Rd. (increase to 5 lanes) ODOT, Lucas County 2021-2030 $10.0 $10.0 $11.6 Road Lucas & 23 Chessie Circle Trail Bridge over the Construct a bridge over the Maumee River as part of the Wood County Port Authority Wood Maumee River Chessie Circle Trail multi-use path from Laskey Rd. in (Toledo, Univ. of Toledo, Lucas County to WW Knight Preserve in Wood County 2021-2030 $8.3 $3.0 $3.5 Non-Motorized Metroparks , Wood Co. Parks District)

Lucas 24 Overland Trail Overland Trail: Construct a multi-use path from the Chessie Circle Trail at Ottawa Park through Jermain Park, to the Overland Industrial Park, to Manhattan Ave. bike lanes, then Toledo 2016-2025 $7.0 $7.0 $7.5 Non-Motorized a sidepath from Expressway Dr. to Chrysler Dr., to Manhattan Ave. to the existing facilities on Summit St. Lucas 25 Widen I-475 (Talmadge to Douglas Widen I-475 to 6 lanes from Talmadge Rd. to Douglas Rd. Rd.) ODOT 2026-2035 $130.0 $130.0 $162.5 Expressway Monroe 26 Reconstruct I-75 in Monroe County, Reconstruct I-75, state line to Otter Creek Rd., in Ohio state line to Otter Creek Rd. southern Monroe County (freight transportation corridor) MDOT, Monroe County 2016-2025 $130.0 $130.0 $140.0 Expressway

Lucas 27 Construct a Regional Central Traffic Construct a Regional Central Traffic Control System including adaptive traffic control for major arterial corridors Control System Toledo 2016-2025 $3.5 $3.5 $3.8 Road on Monroe St., Talmadge Rd., Alexis Rd., Anthony Wayne Trail, Woodville Rd., Airport Hwy., and Reynolds Rd. Lucas 28 Cherry-University Trail Cherry-University Trail: Construct a sidepath along Dorr St. from Douglas Rd. to 17th St. where the trail would turn north into bike lanes to Franklin Ave. and continue as bike lanes Toledo 2016-2025 $1.2 $1.2 $1.3 Non-Motorized until Cherry St. where it would turn northwest into a sidepath to meet the Overland Trail Lucas & 29 Construct Chessie Circle Trail Chessie Circle Trail: Construct multi-use path (rail-trail), Wood Laskey Road to WW Knight Preserve (excludes two Toledo, UT, Metroparks, 2016-2025 $5.7 $5.7 $6.1 Non-Motorized separate projects, path from river to Glanzman and new Wood Co. Parks District Maumee River bridge) Lucas 30 Riverside Trail Riverside Trail: Construct a multi-use path from Cullen Park south along Summit St., to Water St., along the riverfront to Owens Corning Pkwy, to bike lanes on Ottawa St. and Toledo 2016-2025 $2.0 $2.0 $2.2 Non-Motorized Emerald Ave. and construct / connect to a sidepath along the Anthony Wayne Trail to the Chessie Circle Trail. Lucas 31 Add US 20A interchange on I-475 Build new interchange on I-475 connecting to US 20A (Maumee-Western Rd.) Cost to be underwritten in part via a ODOT/Lucas Co. (TID) 2016-2025 $24.0 $24.0 $25.9 Expressway Transportation Improvement District (TID)

Lucas & 32 Increase passenger train service to Increase passenger train service to Toledo, east-west and to Northern Ohio Rail Alliance Monroe Toledo, east-west and to Michigan Michigan: upgrade stations, add passing tracks, and (TMACOG, Erie Reg'l MPO, increase service to 5 round trips/day, Toledo to Cleveland; NOACA), TLC Port 2021-2030 $300.0 $3.0 $3.5 Rail add service, Toledo-Detroit airport-Detroit Authority, MDOT, SEMCOG, Amtrak Lucas 33 Chessie Circle Trail Alternate Chessie Circle Trail Alternate Routes: provide bike facilities Routes to bypass the active rail section (Dorr St. to Glanzman Rd.) Toledo 2016-2025 $1.5 $1.5 $1.6 Non-Motorized Lucas 34 Greenhouse Trail Greenhouse Trail: Construct a facility from the University/ Parks Trail at Reynolds Rd. to Elmer Dr., then south through Toledo Botanical Gardens to Bancroft St., west to Olimphia Rd., then south to Nebraska Ave., east on Nebraska Ave. to a path through Keil Farm to Hill Ave., then a path through Toledo 2016-2025 $2.1 $2.1 $2.3 Non-Motorized Winterfield Park to Wenz Rd. south to Airport Hwy, then west on the existing sidepath to Eastgate and Cass Rd. facilities to the Turnpike Lucas 35 Add Maumee River passenger/ Add Maumee River passenger and freight rail bridge (2 tracks) with cantilevered ped/bike path, adjoining NS NS, Amtrak, Northern Ohio freight rail bridge with bike path, 2026-2035 $250.0 $2.5 $3.1 Rail adjoining NS bridge mainline bridge in central Toledo Rail Alliance Lucas 36 Add Dorr St. interchange on I-475 Add interchange on I-475 at Dorr St. (SR 246); address potential capacity issues between McCord and Holland- Sylvania. Cost to be underwritten in part via a ODOT/Lucas Co. (TID) 2016-2025 $12.0 $12.0 $12.9 Expressway Transportation Improvement District (TID) Lucas 37 Improvements to McCord Rd. McCord Rd. corridor improvements from Angola Rd. to (Angola Rd. to Bancroft St>) Bancroft St. - access management, and intersection Lucas County 2025 $10.0 $10.0 $11.6 Road improvements (Hill Ave., Dorr St., and Bancroft St.)

*Estim. Cost from Fiscal Constraint: Amount deducted from expected Plan funding; excludes full cost of projects needing special funds ** Cost with Inflation: year‐of‐project cost using 1.5% /yr inflation factor Draft Priority Projects for the TMACOG region 2015‐2045 Regional Transportation Plan February 18, 2015

Estimated cost in Estimated Project Cost (from Estimated millions- from County Rank Project Name Project Description Potential Sponsor cost in Fiscal Constraint) Mode Construction Year Fiscal millions- total with Inflation** Constraint* Wood 38 Bowling Green City Bicycle Network Bowling Green City Bicycle Network: Provide a group of facilities to create a bicycle network, such as facilities to connect BGSU to downtown and key east-west and north- Bowling Green 2016-2025 $2.1 $2.1 $2.3 Non-Motorized south connections in BG and to surrounding Wood County communities. Lucas 39 Buckeye Basin Trail Buckeye Basin Trail: Construct a facility to provide connection to the Uptown District with a trail starting at the corner of Woodruff/Franklin Aves., then following the Toledo 2016-2025 $0.2 $0.2 $0.2 Non-Motorized existing Greenbelt Pkwy trail to the Overland Trail via Buckeye Street. Lucas 40 Maumee City Bicycle Network Maumee City Bicycle Network: Provide a group of facilities to create a bicycle network, such as from Broadway St. in Toledo to Side Cut Metropark, and along the Anthony Maumee 2016-2025 $1.2 $1.2 $1.3 Non-Motorized Wayne Trail to eventually reach the Chessie Circle Trail in Toledo, and on Gibbs St., Key St., and Manley Rd. Lucas 41 Improvements to Improvements to the intersection of Sylvania Ave., Jackman Rd., and Tremainsville Rd. Sylvania/Jackman/Tremainsville Toledo 2026-2035 $5.5 $5.5 $6.9 Road intersection Lucas 42 Improvements to Build Detroit/Telegraph/Laskey roads intersection improvements, possibly a roundabout Detroit/Telegraph/Laskey Toledo 2025 $5.0 $5.0 $5.8 Road intersection Lucas 43 Downtown Toledo Bicycle facilities Downtown Toledo Facilities: Add a sidepath on Jefferson Ave. and connect to existing facilities on Bancroft St. via Toledo 2016-2025 $0.4 $0.4 $0.4 Non-Motorized share-the-road facilities on Scottwood, Woodruff, and Parkwood Aves. Lucas Complete the City of Oregon bike network 44 Complete Oregon bike network Oregon 2016-2025 $1.7 $1.7 $1.8 Non-Motorized Wood 45 Add turn lanes to US 6 corridor Add additional turn lanes where needed on two-lane portion (City of Bowling Green bypass) of US 6 between Bowling Green Rd. West and Bowling ODOT 2026-2045 $2.0 $2.0 $2.7 Road Green Rd. East Lucas 46 Implement fixed guideway public Implement fixed guideway public transit using advanced technology in one or more heavily travelled corridors, transit using advanced technology TARTA 2045 $300.0 $15.0 $23.4 Transit replacing standard bus with bus rapid transit, light rail, etc.

Lucas 47 Phillips Ave./ NS rail grade crossing Construct rail grade separation of Phillips Ave. and NSRR to separation improve access to the Phillips/I-75 interchange. Project limits Burnham St. to Detroit Ave. Includes underpass, Toledo, NSRR 2026-2035 $22.0 $22.0 $27.5 Rail service roads and right-or-way acquisition Lucas 48 Oregon Trail Oregon Trail: Construct a path/sidepath to connect Craig St. Bridge path and Seaman Rd., to connect Cities of Toledo Toledo 2016-2025 $0.6 $0.6 $0.6 Non-Motorized and Oregon Wood 49 Build an efficient truck connection Build efficient truck connection between I-75 Exit 168 (Eagleville Rd.) and Stearns Rd. west of City of Fostoria; from City of Fostoria to I-75 Fostoria/, Wood Co 2036-2045 $60.0 $60.0 $87.1 Road improve Stearns Rd to handle truck traffic where needed

Lucas 50 Construct US 20A roundabouts Build roundabouts at US 20A/Whitehouse-Spencer Rd. intersection and US 20A/SR 295 intersection (with a ODOT / TLC Port Authority 2016-2025 $3.0 $3.0 $3.2 Road connector to S. Airfield Rd. from the SR 295 roundabout).

Lucas & 51 Implement a transit connection Implement a transit connection between Toledo and Bowling Wood Green TARTA or other transit between Toledo and Bowling Green 2035 $5.0 $5.0 $6.7 Transit provider

Wood 52 Replace pavement on Oregon Rd. Replace pavement on Oregon Rd. (from US 20 to Northwood corporation line); one bridge replacement (US 20 to Northwood); one bridge Wood County 2016-2025 $2.3 $2.3 $2.4 Road replacement

Lucas 53 Improvements to Secor Rd. Improvements (lane widening, access management) to Secor Rd. from Bancroft St. to Central Ave. Possible (Bancroft St. to Central Ave.) Toledo 2026-2035 $15.0 $15.0 $18.8 Road roundabouts at Bancroft/Kenwood Blvd. and Bancroft/Indian Rd. Wood 54 Tracy Rd. improvements (SR 795 to Improve Tracy Rd between SR 795 and Walbridge Rd. to accommodate truck traffic (increase weight limit to handle Walbridge Rd.) Wood County 2016-2025 $2.0 $2.0 $2.2 Road trucks; minor widening; improve guardrails). Add sidewalks

Wood 55 Improvements to Tracy/Wales Rd. Improve Tracy Rd./Wales Rd. intersection to better intersection accommodate trucks (widen turning radius; possible left turn Northwood 2016-2025 $1.2 $1.2 $1.3 Road lanes, and traffic signal) Lucas 56 Widen and managed access, US Upgrade US 20A from I-475 to - widening and managed access to better serve freight 20A (I-475 to Toledo Express ODOT, Lucas County 2026-2035 $26.9 $26.9 $33.6 Road Airport) movement, pending environmental impact evaluation () Wood 57 Implement a Wood County Rural Implement a rural transit system throughout Wood County Transit System Wood County 2025 $4.0 $4.0 $4.6 Transit

*Estim. Cost from Fiscal Constraint: Amount deducted from expected Plan funding; excludes full cost of projects needing special funds ** Cost with Inflation: year‐of‐project cost using 1.5% /yr inflation factor Draft Priority Projects for the TMACOG region 2015‐2045 Regional Transportation Plan February 18, 2015

Estimated cost in Estimated Project Cost (from Estimated millions- from County Rank Project Name Project Description Potential Sponsor cost in Fiscal Constraint) Mode Construction Year Fiscal millions- total with Inflation** Constraint* Lucas & 58 Erie Township and Overland Trail Erie Township and Overland Trail Connector: Provide a Monroe County, Toledo, Monroe Connector facility starting on Stickney Ave. at Manhattan Ave., north to 2016-2025 $0.6 $0.6 $0.6 Non-Motorized Benore Rd. to Dixie Hwy Erie Township Lucas 59 Richards Rd. connector Richards Rd. connector: Construct a facility from University Parks Trail south on Richards Rd., west on Hill Ave., and Toledo 2016-2025 $0.4 $0.4 $0.4 Non-Motorized south on Wenz Rd. to connect to Greenhouse Trail facility. Lucas 60 Safe Routes to School - Toledo Safe Routes to School - Toledo: Complete facilities outlined in approved Toledo Public Schools travel plan Toledo 2016-2025 $5.2 $5.2 $5.6 Non-Motorized Wood 61 Upgrade I-75/Cygnet Rd. Upgrade the interchange at I-75 and Cygnet Rd. in Cygnet interchange ODOT 2021-2030 $25.0 $25.0 $29.0 Expressway Lucas 62 Improvements to Perrysburg- Improvements to Perrysburg-Holland Road from the Ohio Turnpike to I-475, including the Heatherdowns/ Garden/ Holland Rd. (Ohio Turnpike to I- Toledo 2021-2030 $8.0 $8.0 $9.3 Road 475) Manley intersection Wood 63 Widen SR 795 (Lemoyne Rd. to I- Widen SR 795 to 4 lanes between Lemoyne Rd. and I-280 280) interchange, including I-280 overpass bridge widening ODOT 2025 $15.0 $15.0 $17.4 Road

Lucas 64 Transit stop improvements Upgrade most frequently-used transit stops to make them TARTA, member 2020 $5.0 $5.0 $5.4 Transit user friendly and handicapped accessible jurisdictions All 65 Ohio Hub high speed passenger rail Build Ohio Hub high speed passenger rail system; Toledo area improvements may include passenger rail/rail overpass implementation Ohio Rail Development in Northwood, new Maumee River bridge, upgrade MLK 2035 $300.0 $3.0 $4.0 Rail Commission Plaza infrastructure and passenger access to multiple rail lines, etc. Lucas 66 Reconstruct Sylvania Ave. (Secor to Reconstruct Sylvania Ave. from Secor to Douglas roads to Douglas Rd.) improve safety Toledo 2016-2025 $5.0 $5.0 $5.4 Road Lucas 67 Sylvania Ave. capacity and safety Sylvania Ave. capacity and safety improvements, McCord improvements, McCord Rd. to I- Rd. to I-475, add lanes and/or build roundabout (to be 475, additional lanes and/or determined via a safety study) Lucas County 2023 $2.0 $2.0 $2.3 Road roundabout

Lucas 68 Albon Rd./NS grade separation Albon Rd. grade separation at NS railroad, includes paved shoulders for bikes on the approaches and new sidewalks Lucas County 2040 $20.0 $20.0 $29.0 Road for pedestrians All 69 Safe Routes to School Safe Routes to School: Complete facilities outlined in Cities of Oregon, Sylvania, implementation - Other approved school travel plans (excluding Toledo Public and other districts with 2016-2025 $2.5 $2.5 $2.7 Non-Motorized Schools, listed as separate project) travel plans Lucas 70 Construct a pedestrian bridge over Construct a pedestrian bridge over Douglas Rd., connecting the Chessie Circle Trail and Marwood Ave. to University of Douglas Rd. (Chessie Circle Trail , Toledo campus at Savage Hall 2016-2025 $5.4 $4.4 $4.7 Non-Motorized and Marwood Ave. to University of Toledo Toledo)

Lucas & 71 Implement north-south train service, Implement north-south passenger train service, Toledo to Wood Bowling Green to Lima/Columbus; possibly form JPA/joint Ohio Rail Development Toledo to Bowling Green to 2026-2035 $300.0 $3.0 $3.8 Rail Lima/Columbus powers authority (local and regional governments) to Commission, JPA implement Lucas 72 One-call/one-click center Implement a one-call/one-click center for Toledo metro area (transit) --transportation users call in for centralized TARTA 2016 $0.2 $0.2 $0.2 Transit information or access an online database Lucas 73 Cherry-University Trail to Riverside Cherry-University Trail to Riverside Trail connector: Trail Connector Construct a bike lane on City Park Ave. between Dorr St. and Anthony Wayne Trail at Emerald Ave., to connect Toledo 2016-2025 $0.2 $0.2 $0.2 Non-Motorized Cherry University Trail with Riverside Trail and the proposed facility on Emerald Ave. Monroe 76 Add center turn lanes to Sterns Add center turn lane on Sterns Rd. between Adler Rd (Adler Rd. to Telegraph/US 24) and & Telegraph/US 24; add center turn lane on Smith Rd Smith Rds. (Whiteford to Telegraph) between Whiteford Rd. & Telegraph Rd, in Monroe Monroe County 2021-2030 $30.0 $30.0 $34.8 Road County, MI in Monroe Co.

Lucas Replace TARTA bus fleet (2 cycles of replacement). 77 Replace TARTA bus fleet TARTA 2016-2025 $140.0 $140.0 $150.8 Transit Lucas 78 Reconstruct Collingwood Blvd., Monroe St. to I-75, with Reconstruct Collingwood Blvd. with roundabout at Monroe. Realign local street access to Toledo 2021-2025 5.5 5.5 $6.2 Road roundabout at Monroe St. and enhance gateway area.

Lucas 80 Construct a railroad grade Construct a railroad grade separation (bridge) over Norfolk Southern in Lucas County, at either SR 295 or Eber Road separation in Lucas County (at SR ODOT, Lucas County, NS 2026-2035 $20.0 $20.0 $25.0 Road 295 or Eber Rd)

*Estim. Cost from Fiscal Constraint: Amount deducted from expected Plan funding; excludes full cost of projects needing special funds ** Cost with Inflation: year‐of‐project cost using 1.5% /yr inflation factor Draft Priority Projects for the TMACOG region 2015‐2045 Regional Transportation Plan February 18, 2015

Estimated cost in Estimated Project Cost (from Estimated millions- from County Rank Project Name Project Description Potential Sponsor cost in Fiscal Constraint) Mode Construction Year Fiscal millions- total with Inflation** Constraint* Monroe 81 Secor Rd reconstruction & widening Secor Rd. reconstruction, widen to 3 lanes, & intersection improvements, Ohio states line to Summerfield Rd. & intersection improvements, Ohio Monroe Co. Road 2021-2030 $2.8 $2.8 $3.2 Road state line to Summerfield Rd. Commission

Lucas 82 North Curtice Rd. roundabouts at Build North Curtice Rd. roundabouts (3) at Seaman, Seaman, Corduroy, and Cedar Corduroy, and Cedar Point Rds., includes paved shoulders Point roads for bikes on the approaches and new sidewalks for peds. Lucas County 2030 $3.0 $3.0 $3.8 Road Road is main entrance to off SR 2

Lucas 83 Toledo train/Intermodal station Toledo train/intermodal station upgrades: upgrade MLK upgrades Plaza/Toledo Amtrak station infrastructure and passenger TLC Port Authority, Amtrak, 2016-2020 $1.1 $1.1 $1.2 Rail access to: multiple rail lines, local & intercity transit, taxis, Toledo and passenger pick up/drop off Lucas 85 Albon and Monclova Rds. Build Albon/Monclova Rds. roundabout, includes paved roundabout shoulders for bikes on the approaches and new sidewalks Lucas County 2022 $1.0 $1.0 $1.1 Road for peds within the roundabout.

Lucas 89 Bancroft St./Crissey Rd. Build Bancroft St./Crissey Road roundabout, includes paved roundabout shoulders for bikes on the approaches and new sidewalks Lucas County 2035 $1.0 $1.0 $1.3 Road for peds within the roundabout Lucas 90 Frankfort/Crissey Rds. roundabout Build Frankfort Rd./Crissey Rd. roundabout, includes paved shoulders for bikes on the approaches and new sidewalks Lucas County 2045 $1.0 $1.0 $1.6 Road for peds within the roundabout Lucas 91 Brint/Centennial Rds. roundabout Build Brint/Centennial Rds. roundabout, includes paved shoulders for bikes on the approaches and new sidewalks Lucas County 2025 $1.0 $1.0 $1.2 Road for peds within the roundabout Wood 95 Realign Wales Rd and build grade Realign Wales Rd. between Tracy Rd. and East Broadway St. to make a direct east-west connection to Wales; includes separation (Tracy Rd. to E. Northwood, CSX 2036-2045 $13.0 $13.0 $18.9 Road Broadway St.) grade separation at CSX RR Lucas 96 Provide signal prioritization for Provide signal prioritization for transit and emergency TARTA & various transit and emergency vehicles vehicles, extending green light as they approach 2020 $2.0 $2.0 $2.2 Transit intersection jurisdictions Lucas 97 Crissey Rd./Dorr St. roundabouts Build two Crissey Rd./Dorr St. roundabouts, includes paved shoulders for bikes on the approaches and new sidewalks Lucas County 2030 $2.0 $2.0 $2.5 Road for peds within the roundabout Lucas 98 Crissey Rd./ Angola Rd. (E) Build Crissey Rd./Angola Rd. (E) roundabout, includes roundabout paved shoulders for bikes on the approaches and new Lucas County 2025 $1.0 $1.0 $1.2 Road sidewalks for peds within the roundabout Lucas 99 Albon/Garden Rds. intersection Albon and Garden Roads intersection improvements, improvements includes constructing turn lanes and paved shoulders (for Lucas County 2030 $1.0 $1.0 $1.3 Road bikes) on the approaches. Lucas 100 Waterville-Monclova Rd. / Monclova Waterville-Monclova Rd./Monclova Rd. intersection improvement, includes paved shoulders for bikes on the Rd. intersection improvement Lucas County 2022 $1.5 $1.5 $1.7 Road approaches and new sidewalks for peds

Lucas 102 Rail grade separation at Manhattan Find solution to blocked rail crossing at Summit St./CSX, Blvd. or other location for impeding access to Point Place (possible grade separation unimpeded access to Point Place at Manhattan or Summit) Toledo 2026-2035 $15.0 $15.0 $18.8 Rail

Wood 103 Solve rail/roadway conflict in North Find a solution to blocked CSX rail crossings in Village of North Baltimore - possible grade separation and/or North Baltimore /Wood Baltimore 2016-2025 $17.0 $17.0 $18.3 Rail pedestrian bridge; or advance warning signals for blocked County crossings (if alternate route exists) Wood 104 Resurface Pemberville Rd. (US Resurface Pemberville Rd. from US 20/23 (Fremont Pike) to 20/23 to Pemberville) Village of Pemberville. High traffic section will serve heavy truck traffic to/from Home Depot facility. Includes Wood County 2016-2025 $4.0 $4.0 $4.3 Road improvements to CSX rail crossing north of Pemberville (AAR 228829T) Lucas 106 Expand the Norfolk Southern Expand the Norfolk Southern Toledo Intermodal Terminal Toledo Intermodal Terminal (Airline (Airline Yard) to accommodate up to 120,000 truck/train Yard) transfers (lifts) per year; also build new terminal access road Norfolk Southern 2016-2020 $2.0 $1.0 $1.0 Rail from Westwood Ave. (Cost is a placeholder; actual cost TBD; private funding or public-private partnership) Wood 107 Reconstruct pavement, Liberty Hi Reconstruct pavement on Liberty Hi Rd (SR 18 to Cygnet Rd. (SR 18 to Cygnet Rd.) and Rd) and Cygnet Rd. (Liberty Hi Rd. to I-75); replace two Cygnet Rd. (Liberty Hi Rd. to I-75); bridges; to serve CSX Intermodal Yard truck traffic Wood County 2026-2035 $4.2 $4.2 $5.3 Road replace two bridges

Wood 108 Widen Lime City Rd. in Rossford Widen Lime City Rd. in City of Rossford (SR 65-Buck Rd.); and widen in Wood County (I-75 to SR 795) and in Wood County (I-75 to SR Rossford, Wood County 2021-2030 $2.5 $2.5 $2.9 Road 795)

*Estim. Cost from Fiscal Constraint: Amount deducted from expected Plan funding; excludes full cost of projects needing special funds ** Cost with Inflation: year‐of‐project cost using 1.5% /yr inflation factor Draft Priority Projects for the TMACOG region 2015‐2045 Regional Transportation Plan February 18, 2015

Estimated cost in Estimated Project Cost (from Estimated millions- from County Rank Project Name Project Description Potential Sponsor cost in Fiscal Constraint) Mode Construction Year Fiscal millions- total with Inflation** Constraint* Lucas 109 Centennial Rd./Hill Ave. roundabout Build Centennial Rd./Hill Ave. roundabout; includes paved shoulders for bikes on the approaches and new sidewalks Lucas County 2030 $1.0 $1.0 $1.3 Road for peds within the roundabout

Lucas 110 Infrastructure improvements to Improve infrastructure at the Port of Toledo by developing Ironville Terminal Ironville Terminal south of Front St for potential industry TLC Port Authority 2016-2035 $50.0 $10.0 $11.6 Waterborne (possible rail spur and/or access road) Lucas 111 Monclova Rd. roundabout at Coder Build Monclova Rd./Coder Rd. roundabout, and widen Rd. and widen (Coder to Waterside Monclova to 3 lanes, Coder to Waterside Blvd.; includes Lucas County 2025 $1.6 $1.6 $1.9 Road Blvd.) paved shoulders for bikes, and elimination of gaps in sidewalks for peds Wood 112 Five Point/Hull Prairie Rds. Build roundabout at Five Point and Hull Prairie Rds. roundabout Wood County 2021-2025 $2.0 $2.0 $2.3 Road Lucas 113 Salisbury/Albon Rds. roundabout Construct a roundabout at intersection of Salisbury and Albon Rds. Lucas County 2026-2030 $1.0 $1.0 $1.2 Road Lucas 114 Nebraska Ave./Centennial Rd. Build Nebraska Ave./Centennial Rd. roundabout, includes roundabout paved shoulders for bikes on approaches and new Lucas County 2025 $1.0 $1.0 $1.2 Road sidewalks for peds within the roundabout Wood 116 Roachton/Hull Prairie Rds. Install roundabout at Roachton and Hull Prairie roads Roundabout Wood County 2016-2020 $1.2 $1.2 $1.3 Road Wood 117 Reconstruct SR 25 (Cygnet to Reconstruct pavement on SR 25 between City of Bowling Bowling Green) Green and Village of Cygnet ODOT, Wood County 2021-2030 $35.0 $35.0 $40.6 Road Lucas 118 TARTA facilities improvements TARTA facilities improvements (increase capacity and maintain TARTA building as warranted) TARTA 2018 $7.0 $7.0 $7.3 Transit Lucas 126 Reduce conflicts, SR 18/SR Find a solution to blocked rail crossing at SR 235/SR 18 and CSX in Village of Hoytville (possible grade separation and/or Hoytville/ Wood County/ 235/CSX in Hoytville (possible 2026-2035 $12.0 $12.0 $15.0 Rail overpass and/or highway bypass) highway bypass). ODOT

Wood 129 Improve Poe Rd (Green to Range Improve/widen Poe Road (Green Rd. to Range Line Rd.); Line Rd); realign at railroad realignment at railroad crossing; bridge crossing; bridge replacement replacement Wood County 2016-2030 $1.3 $1.3 $1.4 Road

Wood 131 Napoleon/Campbell Hill Rds. Install roundabout at Napoleon and Campbell Hill roads roundabout Wood County 2021-2025 $0.8 $0.8 $0.9 Road Lucas 132 Widen Harroun Rd. (Kroger Widen Harroun Rd (Kroger driveway to Flower Hospital) driveway to Flower Hospital) Sylvania 2036-2045 $2.0 $2.0 $2.9 Road Wood 135 Replace Rudolph Rd./ Middle Replace bridge on Rudolph Road over Middle Branch Branch Portage River bridge Portage River Wood County 2016-2030 $0.6 $0.6 $0.7 Road Lucas 136 Improvements to Angola Rd. (near Improvements to Angola Road near King Road, including King Rd.) widening to three lanes and a roundabout Lucas County 2021-2025 $3.2 $3.2 $3.6 Road Wood 139 Widen and improve shoulders, Widen and improve shoulders, Emerson Rd. (Pelton Rd. to Mermill Rd.) - road is narrow and has shoulder issues Emerson Rd. (Pelton to Mermill Rd.) Wood County 2016-2030 $2.0 $2.0 $2.3 Road

Wood 140 Widen Glenwood Rd (SR 65-SR Widen Glenwood Rd to 3 lanes, bridge replacements/ 795) upgrades, and signal upgrades (SR 65 to SR 795) Rossford, Wood County 2026-2035 $11.7 $11.7 $14.6 Road Lucas 141 Clean air-alternative fueling stations Install clean air-alternative fueling stations for TARTA vehicles and public use TARTA 2020 $10.0 $10.0 $10.8 Transit

Lucas 142 Toledo Shipyard infrastructure Improve infrastructure at the Toledo Shipyard facility at the improvements Port of Toledo (dry dock and gate improvements) TLC Port Authority 2016-2035 $4.0 $4.0 $4.6 Waterborne Wood Replace bridge on Bridge St .over Middle Branch Portage 146 Replace Bridge St./Middle Branch Wood County; Village of River 2016-2030 $1.0 $1.0 $1.1 Road Portage River bridge Pemberville Wood 147 Replace Luckey Rd./Toussaint Replace bridge on Luckey Road over Toussaint Creek Creek bridge Wood County 2016-2030 $0.7 $0.7 $0.8 Road Wood 148 Replace Potter Rd./Middle Branch Replace bridge on Potter Road over Middle Branch Portage Portage River bridge River Wood County 2016-2030 $0.5 $0.5 $0.6 Road Wood 149 Replace Wintergreen Rd./Beaver Replace bridge on Wintergreen Road over Beaver Creek Creek bridge Wood County 2016-2030 $0.9 $0.9 $1.0 Road Lucas 153 Perrysburg-Holland Bridge Replace Perrysburg-Holland Bridge #616 over Cairl replacement over Cairl Creek Creek, south of Airport Hwy Lucas County 2024 $1.0 $1.0 $1.1 Road Wood 154 Replace Hull Prairie Rd./Ditch 2089 Replace bridge on Hull Prairie Road over Ditch 2090 bridge Wood County 2016-2030 $0.9 $0.9 $1.0 Road

*Estim. Cost from Fiscal Constraint: Amount deducted from expected Plan funding; excludes full cost of projects needing special funds ** Cost with Inflation: year‐of‐project cost using 1.5% /yr inflation factor