Welcome

Country Hills Boulevard N.E. Study Area 128 Avenue N.E. Study Area

N N

STONEY TRAIL

COVENTRY HILLS DEERFOOT TR

NOSE CREEK 115 AVE NE

COUNTRY HILLS BLVD FREEPORT DRIVE NE CP RAIL NE BARLOW TR NE 14 ST NE COVENTRY BLVD NE COUNTRY HILLS BLVD NE

128 AVENUE NE

COVENTRY HILLS HARVEST HILLS GATE NE BARLOW TR NE HARVEST HILLS 15 STREET NE

DEERFOOT TR

DEERFOOT TR

NOSE CREEK Objectives Objectives • Develop widening plan along Country Hills Boulevard N.E. • Plan for a new connection for 128 Avenue N.E. between between and Coventry Boulevard N.E. from and that will accommodate all four to six lanes, including continuous multi-use pathways. modes of transportation. • Examine widening strategies for existing bridges over CP • Review previous interchange plans at both Deerfoot Trail Rail, Nose Creek and Deerfoot Trail. and Stoney Trail. • Better accommodate and improve safety for both current • Examine new crossings over CP Rail and Nose Creek. and future travel modes in the study area. • Incorporate safety best practices considering all travel modes within the study area. .ca/CountryHillsWidening | calgary.ca/128AveNE | contact 311 Study Process

 Gather and  Conduct existing  Develop design  Final  Develop preferred Submit review conditions studies concepts and review study area plan for City available conduct preliminary / and approval project initial evaluation evaluation process information 

      

Discover ideas, opportunities, Explore challenges and potential Present develop evaluation concepts and preferred criteria for the Review evaluation Review plan to Review study area stakeholder results with stakeholder stakeholders feedback with stakeholders and public stakeholders and public and the and refine Post final  and the public.  feedback  and the public feedback  public  plan  plan online   We are here

calgary.ca/CountryHillsWidening | calgary.ca/128AveNE | contact 311 What We Heard: Country Hills Boulevard N.E.

Overall Themes We Heard in the Discover Phase

Pathways and Connectivity: Traffic Operations: Bridge Widening: • It is important to accommodate • Concerns about • The width of the bridge pedestrians and cyclists along merging to and from across the creek constricts the study corridor. Deerfoot Trail N.E. how many lanes of traffic • There are missing segments • Desire to see improved can travel Country Hills of pathways. traffic flow and Boulevard N.E. • It is important to design reduced congestion. • Desire to see improvements pathways with safety in mind. to the bridge crossing Deerfoot Trail.

Key Project Priorities Combining feedback from Calgarians in the Discover Phase and City priorities identified the following key project priorities which were used to evaluate options.

Legend

Key Project Priorities

Key Priorities for Calgarians calgary.ca/website | contact 311 Country Hills Boulevard N.E. The City is undertaking a functional planning study to widen Country Hills Boulevard N.E. and address key issues between Deerfoot Trail N.E. and Coventry Boulevard N.E. Using technical analysis andCOVENTRY feedback HILLS from Calgarians in the Discover Phase, we STONEY INDUST

have developed several concepts and options and would like your feedback to develop the recommended plan. 115 AVE NE NOSE CREEK Key Considerations Map

CP RAIL 14 ST NE COUNTRY HILLS BLVD NE FUTURE 11 ST NE COUNTRY HILLS BLVD NE COVENTRY HILLS For more information see page: STONEY INDUSTRIAL COVENTRY BLVD NE STONEGATE LANDING Deerfoot Trail to 14 Street N.E. For more information see page: For more information see page: Country Hills Boulevard at Deerfoot Trail Bridges - Harvest Hills Way N.E. and at Harvest HIlls Gate N.E 115 AVE NE Loop Ramp Options NOSE CREEK

For more information see page: 110 AVE NE GATE NE HARVEST HILLS

Deerfoot Trail Bridges - DEERFOOT TRAIL Bridge Deck Options HARVEST HILLS

CP RAIL HARVEST HILLS WAY NE BARLOW TRAIL NE 14 ST NE FUTURE 11 ST NE COUNTRY HILLS BLVD NE COUNTRY HILLS BLVD NE COUNTRY HILLS BLVD NE FREEPORT DRIVE NE COVENTRY BLVD NE

For more information see page: CP Rail Bridge Widening Legend 110 AVE NE 2 Lanes GATE NE HARVEST HILLS For more information see page: DEERFOOT TRAIL 3 Lanes Nose Creek Bridge Widening Existing pathway / sidewalk HARVEST HILLS HARVEST HILLS WAY NE Intersecting roadways

Project Objectives Key Considerations • Develop widening plan along Pathway Connections: Country Hills Boulevard N.E. Look for on the map to see existing pathways and sidewalks. Note: between Deerfoot Trail N.E. and • Missing south-side connection from 14 Street N.E across Deerfoot Trail N.E. CoventryLegend Boulevard N.E. from four • Missing north-side connection from Harvest Hills Gate N.E. to 14 Street N.E. to six lanes, including continuous • Future pathway connection under Nose Creek Bridge (by others). multi-use pathways.2 Lanes • Examine widening3 Lanes strategies for Traffic Operations: existing bridgesExisting over pathway CP Rail, Nose / sidewalk Anticipate significant increased traffic along Country Hills Boulevard N.E. when the surrounding industrial area fully develops resulting in: Creek and DeerfootIntersecting Trail. roadways • Long eastbound queue along Country Hills Boulevard N.E. at 14 Street N.E. • Long westbound left turn queue at Country Hills Boulevard N.E. at 14 Street N.E. affects traffic coming off southbound Deerfoot Trail N.E. • Better accommodate and improve safety for both current and future • Several sections of Country Hills Boulevard N.E. will require widening to three lanes (See on the map). travel modes in the study area. • Westbound Country Hills Boulevard N.E. requires widening to three lanes from Deerfoot Trail N.E. to Coventry Boulevard N.E. and Harvest Hills Way N.E.

Bridge Widening: • How to widen three existing bridges (see symbols on map) to accomodate 4 m paths on both sides and three traffic lanes in each direction. calgary.ca/CountryHillsWidening | calgary.ca/128AveNE | contact 311 Deerfoot Trail Interchange 14 ST NE 14 ST NE

COUNTRY HILLS BLVD NE

Legend

Traffic Signal Intersection DEERFOOT TRAIL Key Movement

Existing Pathway

Legend Deerfoot Trail N.E. to 14 Street N.E.: Bridge Loop Ramps: Bridge Widening: ThereTraffic Signalare challenges Intersection travelling from Changes to the bridges over Deerfoot There are two existing bridges southboundKey Movement Deerfoot Trail N.E. to Trail N.E. provide an opportunity crossing over Deerfoot Trail N.E. southboundExisting Pathway 14 Street N.E. as drivers to explore the exit ramps. We have and we have developed bridge need to weave across multiple lanes of developed two options for your input. replacement and widening options for your input. traffic. We have developed four options For more information see page: as potential solutions for your input. Deerfoot Trail Bridges - For more information see page: For more information see page: Loop Ramp Options. Deerfoot Trail Bridges - Deerfoot Trail N.E. to 14 Street N.E. Bridge Deck Options.

calgary.ca/CountryHillsWidening | calgary.ca/128AveNE | contact 311 Deerfoot Trail Bridges – Bridge Deck Options Using what we heard from Calgarians in the Discover Phase, the project team developed three options for widening the Deerfoot Trail Bridges. RFOOT TRAIL BRIDGE RFOOT TRAIL BRIDGE Existing Bridge Conditions: All options provide the following: North bridge provides two westbound lanes and exit ramp. RFOOT TRAIL BRIDGE • Six lanes on Country Hills 2.5 m sidewalk on the north side. Boulevard N.E. South bridge provides two eastbound lanes. • Continuous pathway or sidewalk No pathway connection on the south side. connections along both sides of Country Hills Boulevard N.E. RFOOT TRAIL BRIDGEDEERFOOT TRAIL EXISTING BRIDGE CROSS SECTION • New south bridge.

Option A – Widen North Bridge Cost: $$$ (6.6 m of bridge widening and 27.6 m of new bridge width). Widen north-side pathway width along Deerfoot Trail Bridge. Widen north bridge to the south to accommodate additional westbound lane and pathway widening to 4 m. Construct new south bridge to accommodate future eastbound lanes and 4 m south-side pathway. DEERFOOT TRAIL OPTION A BRIDGE CROSS SECTION

Option B – North Bridge Remains Cost: $ (21.6 m of new bridge width). Modify lane markings on north bridge to accommodate three westbound lanes and right turn merge lane to exit ramp. North sidewalk to remain at 2.5 m wide. Construct new south bridge to accommodate three eastbound lanes, right turn merge lane to exit ramp and south-side pathway. Add 4 m pedestrian connection on the south bridge.

DEERFOOT TRAIL OPTION B BRIDGE CROSS SECTION

Option C – Build Separate Pedestrian Bridge Cost: $$ (24.5 m of new bridge width and 4.9 m wide pedestrian bridge).

Option C with Construct a separate pedestrian bridge on the north side to accommodate a 4 m pathway. Pedestrian Bridge Use space for existing pathway on north bridge to accommodate three westbound lanes and ramp. Construct new south bridge to accommodate future eastbound lanes, a ramp and south-side Option B with Pedestrian Bridge pathway. Add 4 m pedestrian connection on the south bridge.

DEERFOOT TRAIL OPTION C BRIDGE CROSS SECTION

calgary.ca/CountryHillsWidening | calgary.ca/128AveNE | contact 311 Deerfoot Trail to 14 Street N.E. Using what we heard from Calgarians in the Discover Phase, the project team developed four options for Deerfoot Trail N.E. to 14 Street N.E. Option A: Base Case (Existing) Option B: Median from Deerfoot Trail N.E. to 14 Street N.E. 14 ST NE 14 ST NE 14 ST NE 14 ST NE 14 ST NE 14 ST NE 14 ST NE 14 ST NE 11 ST NE 11 ST NE 11 ST NE 11 ST NE 11 ST NE 11 ST NE 11 ST NE 11 ST NE COUNTRYCOUNTRY HILLS HILLSCOUNTRY BLVDCOUNTRY BLVD NE HILLSNE HILLS BLVD BLVD NE NE Description: COUNTRYCOUNTRY HILLS HILLSCOUNTRY BLVDCOUNTRY BLVD NE HILLSNE HILLS BLVD BLVD NE NE Description: Cost: $ Cost: $ 14 ST NE 14 ST NE 14 ST NE 11 ST NE 14 ST NE 11 ST NE 11 ST NE • Vehicles coming from 11 ST NE

COUNTRY HILLS BLVD NE 14 ST NE • Restrict left turns from

COUNTRY HILLS BLVD NE 14 ST NE

11 ST NE COUNTRY HILLS BLVD NE

11 ST NE COUNTRY HILLS BLVD NE COUNTRYsouthbound HILLS BLVD NE Deerfoot Trail COUNTRY HILLS BLVD NE

14 ST NE southbound Deerfoot Trail N.E. 14 ST NE 14 ST NE 11 ST NE 14 ST NE 11 ST NE 11 ST NE N.E. onto westbound11 ST NE Country COUNTRY HILLS BLVD NE COUNTRY HILLS BLVD NE COUNTRY HILLS BLVD NE COUNTRY HILLS BLVD NE to southbound 14 Street N.E. Hills Boulevard N.E. making left DEERFOOTDEERFOOT TRAIL TRAILDEERFOOTDEERFOOT TRAIL TRAIL DEERFOOTDEERFOOT TRAIL TRAILDEERFOOTDEERFOOT TRAIL TRAIL turns at 14 Street N.E. and 11 Alternate Route: DEERFOOT TRAIL 110110 AVE AVE NE NE 110 110AVE AVE NE NE 110110 AVE AVE NE NE 110 110AVE AVE NE NE DEERFOOT TRAIL • Redirect traffic to turn 110 AVE NE Street N.E. 110 AVE NE DEERFOOT TRAIL DEERFOOT TRAIL DEERFOOT TRAIL DEERFOOT TRAIL southbound at 11 Street N.E. Operating Issues: 110 AVE NE 110 AVE NE 110 AVE NE 110 AVE NE Base Case DEERFOOT TRAIL Median Blockage from DEERFOOT TRAIL DEERFOOT TRAIL • Traffic weaving issue between DEERFOOT TRAIL BaseBase Case CaseBaseBase Case Case MedianMedian BlockageMedian BlockageMedian Blockage from BlockagefromDeerfoot from from Trail to 14 Street 110 AVE NE Deerfoot Trail N.E. west 110 AVE NE 110 AVE NE 110 AVE NE For roadway lane details see page: junction andDeerfootDeerfoot 14 Street DeerfootTrail TrailDeerfoot N.E. to to 14 Trail14 StreetTrail Street to to14 14 Street Street Deerfoot Bridges - Bridge Loop Ramp Options - Option B Base Case Base Case Median Blockage from Median Blockage from Deerfoot Trail to 14 Street Deerfoot Trail to 14 Street 14 ST NE 14 ST NE 11 ST NE 11 ST NE Base CaseCOUNTRY HILLS BLVD NE COUNTRY HILLS BLVD NE Median Blockage from Option C: MedianBase from Case Deerfoot Trail N.E. to 14 Street N.E. Roundabout Median BlockageOption from D: SignalizedDeerfoot DualTrail to Right 14 Street Turn Description: Deerfoot Trail to 14 Street Description: Cost: $$ Cost: $ 14 ST NE 14 ST NE 14 ST NE 14 ST NE 14 ST NE 14 ST NE 14 ST NE 14 ST NE 11 ST NE 11 ST NE 11 ST NE 11 ST NE 11 ST NE 11 ST NE 11 ST NE DEERFOOT TRAIL DEERFOOT TRAIL COUNTRYCOUNTRY HILLS HILLSCOUNTRY BLVDCOUNTRY BLVD NE HILLSNE HILLS BLVD BLVD NE NE COUNTRYCOUNTRY HILLS HILLSCOUNTRY BLVDCOUNTRY BLVD NE HILLSNE HILLS BLVD BLVD NE NE 110 AVE NE • Restrict left turns from 110 AVE NE • Provide signalized dual right

southbound Deerfoot Trail N.E. INSET turn for vehicles coming 14 ST NE 14 ST NE 14 ST NE 14 ST NE 11 ST NE 11 ST NE 11 ST NE 11 ST NE COUNTRY HILLS BLVD NE COUNTRYto southbound HILLS BLVD NE 14 Street N.E. COUNTRY HILLS BLVD NE COUNTRY HILLS BLVD NE from southbound Deerfoot Median Blockage from Deerfoot Trail Dual signalized right

14 ST NE Trail N.E. onto westbound 14 ST NE 11 ST NE to 14 StreetAlternate Roundabout Route: 11 ST NE 14 ST NE 14 ST NE

11 ST NE COUNTRY HILLS BLVD NE Country Hills Boulevard N.E.

11 ST NE COUNTRY HILLS BLVD NE COUNTRY HILLS BLVD NE • Provide roundabout at 14 DEERFOOTDEERFOOT TRAIL TRAILDEERFOOTDEERFOOT TRAIL TRAIL COUNTRYDEERFOOT HILLSDEERFOOT BLVD TRAIL TRAIL NEDEERFOOTDEERFOOT TRAIL TRAIL to eliminate safety issues Proposed Roadway Street N.E. and 115Permitted Avenue SB DT to SB N.E. 14 Street Movement and provide a direct route. 110110 AVE AVE NE NE 110 110AVE AVE NE NE 110110 AVE AVE NE NE 110 110AVE AVE NE NE Traffic Signal Intersectionto accomodate southboundPermitted WB CHB to SB 14 Street Movement DEERFOOT TRAIL travel on 14 Street N.E.DEERFOOT TRAIL DEERFOOT TRAIL DEERFOOT TRAIL Restricted Traffic Movement Alternative Route INSETINSET INSETINSET Legend: 110 AVE NE 110 AVE NE for vehicles110 AVE coming NE from 110 AVE NE ALIGNED WITH PRIORITIES DEERFOOT TRAIL For roadway lane details seeDEERFOOT page: TRAIL southbound Deerfoot Trail N.E.. Deerfoot Bridges - Bridge Loop INSET LESS ALIGNED WITH INSET MedianMedian BlockageMedian BlockageMedian Blockage from Blockagefrom Deerfoot Deerfoot from from DeerfootTrail TrailDeerfoot Trail Trail DEERFOOT TRAIL DualDual signalized signalizedDualDual signalized rightsignalized right right right 110 AVE NE 110 AVE NE DEERFOOT TRAIL Ramp Options - Option A PRIORITIES toto 14 14 Street Streetto to14 Roundabout 14 RoundaboutStreet Street Roundabout Roundabout LEAST ALIGNED 110 AVE NE 110 AVE NE WITH PRIORITIES INSET Median Blockage from Deerfoot TrailMedian Blockage from Deerfoot Trail Dual signalized right Dual signalized right to 14 Street Roundabout to 14 Street Roundabout Benefits and Impacts Option A Option B Option C Option D Public and City Key Priorities Option AINSETOption B Option C Option D Median Blockage from Deerfoot Trail Eliminates traffic weaving Dual signalized right Traffic safety ProposedProposed Roadway ProposedRoadwayProposed Roadway Roadway PermittedPermitted SB PermittedSB DTPermitted DT to toSB SBSB 14 SB DT14 Street DT Streetto SBto Movement SB 14Movement 14Street Street Movement Movement Median Blockage from Deerfoot Trail to 14 Street Roundabout between Dualinterchange signalized right Community access junction and 14 Street N.E. TrafficTraffic Signal SignalTraffic IntersectionTraffic Intersection Signal Signalto Intersection 14 Intersection Street RoundaboutPermittedPermitted WB PermittedWB CHBPermitted CHB to toWBSB SBWB 14CHB 14 StreetCHB Streetto SBto Movement SB 14Movement 14Street Street Movement Movement Improved vehicle travel times Proposed Roadway Proposed RoadwayPermitted SB DT to SB 14 Street MovementDirect routePermitted to access SB DT to SB 14 Street Movement businesses and Pedestrian accommodation RestrictedRestricted TrafficRestricted TrafficRestricted Movement Movement Traffic Traffic Movement Movement AlternativeAlternative RouteAlternative RouteAlternative Route Route Traffic Signal Intersection commercial areas Traffic Signal Intersection Proposed RoadwayPermitted WB CHB to SB 14 Street MovementPermittedPermitted SBWB DT CHB to toSB SB 14 14 Street Street Movement Movement Bicycle accommodation Environmental sustainability Proposed Roadway Restricted Traffic Movement TrafficRestricted Signal TrafficAlternative IntersectionPermitted Movement Route SB DT to SB 14 Street MovementAlternative Route Permitted WB CHB to SB 14 Street Movement Pathway connectivity calgary.ca/CountryHillsWideningTraffic Signal Intersection | calgary.ca/128AveNE | contact 311 Construction costs Restricted TrafficPermitted Movement WB CHB to SB 14 Street MovementAlternative Route Deerfoot Bridges – Bridge Loop Ramp Options

Option A: Large Radius Exits

For more information about the dual Cost: $$$ signalized right turn shown see page: Deerfoot Trail to 14 Street N.E. - Option D OPTION A • 50 km/h speed at crosswalk.

Large Radius • Requires north bridge widening.

COUNTRY HILLS BLVD NE • Requires a larger south bridge. • Requires more loop ramp modification.

Large Radius

DEERFOOT TRAIL

Legend

Traffic Signal Intersection Existing Pathway Proposed Pathway Proposed Roadway For more information about the free Existing Pedestrian Bridge Option B: Small Radius Exits flow right turnProposed and the Bridge left turn bay to Proposed Pedestrian Bridge 14 Street S.E. shown see page: Deerfoot Trail to 14 Street N.E. - Cost: $$ Options B and C

OPTION B • 30 km/h speed at crosswalk.

Small Radius • No widening of north bridge required. COUNTRY HILLS BLVD NE COUNTRY HILLS BLVD NE • Requires a smaller south bridge. • Minimal loop ramp modification required.

Small Radius

Public and City Key Priorities Option A Option B

DEERFOOT TRAIL

DEERFOOT TRAIL Traffic safety Community access Legend Legend Traffic Signal Intersection Existing Pathway Improved vehicle travel times Traffic Signal Intersection ProposedExisting Pathway Pathway Proposed Roadway ExistingProposed Pedestrian Pathway Bridge Pedestrian accommodation Proposed Roadway Proposed Bridge ProposedExisting Pedestrian Pedestrian Bridge Bridge Proposed Bridge Proposed Pedestrian Bridge Bicycle accommodation Environmental sustainability Legend: Pathway connectivity ALIGNED WITH SOMEWHAT ALIGNED LESS ALIGNED PRIORITIES WITH PRIORITIES WITH PRIORITIES Construction costs calgary.ca/CountryHillsWidening | calgary.ca/128AveNE | contact 311 EEK BRIDGE EEK BRIDGE Nose Creek Bridge Widening The project team reviewed how to widen the existing Nose Creek bridges.

N O R T H S O U T H Existing Bridges Condition: N O R T H S O U T H All stages provide the following: North bridge provides two westbound lanes. • Six lanes on Country Hills South bridge provides two eastbound lanes. Boulevard N.E. • Pathways along both sides of 1.35 m sidewalk on the north side. Country Hills Boulevard N.E. 2.5 m sidewalk on the south side. 1.35 3.7 3.7 3.7 3.7 2.5 MEDIAN MEDIAN 1.35 3.7 3.7 3.7 3.7 2.5 WALK WB WB MEDIAN MEDIAN EB EB WALK WALK WB WB EB EB WALK This bridge was planned to accommodate 3 m wide paths with 2.5 m vertical clearance.

NOSE CREEK EXISTING BRIDGE CROSS SECTION NOSENOSE CREEKCREEK EXISTING EXISTING BRIDGE BRIDGE CROSS CROSS SECTION SECTION Nose Creek Bridge Widening Highlights: Modify existing bridge median to accommodate three westbound and three N O R T H S O U T H N O R T H S O U T H eastbound lanes. This improves mobility along Country Hills Boulevard N.E. The south bridge will be widened to accommodate both a single left turn or a dual 4.0 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 4.0 parallel left turn for eastbound Country Hills Boulevard N.E. to northbound 11 Street PATH4.0 WB3.5 WB3.5 WB3.5 EBL3.5 3.5EB 3.5EB 3.5EB EBR3.5 PATH4.0 PATH WB WB WB EBL EB EB EB EBR PATH N.E. traffic. A single left turn lane is planned, but it could be converted to a dual left turn in the future. The south bridge can be widened to better accommodate eastbound Country Hills 4.0 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5NOSE CREEK3.5 4.0 PATH4.0 WB3.5 WB3.5 WB3.5 EBL3.5 EBL3.5 3.5EB 3.5EB 3.5EB EBR3.5 PATH4.0 Boulevard N.E. to southbound 11 Street N.E. traffic with the an additional PATH WB WB WB EBL EBL EB EB EB EBR PATH right-turn lane. NOSENOSE CREEKCREEK PROPOSED PROPOSED BRIDGE BRIDGE CROSS CROSS SECTION SECTION

NOSE CREEK PROPOSED BRIDGE CROSS SECTION 11 STREET NE North pathway widened from 1.35 m to 4 m. South pathway widened from 2.6 m to 4 m.

COUNTRY HILLS BLVD NE Single Eastbound Left Turn Lane at Country Hills NOSE CREEK Boulevard and 11 Street N.E. Previously Considered in Development Plans:

11 STREET NE • Uses wider lane widths from approved area planning. • Left turn capacity acceptable. Public and City Key Priorities Existing Proposed COUNTRY HILLS BLVD NE • Separated left-turn lane. Traffic safety • More distance from bridge barrier. Community access Improved vehicle travel times Pedestrian accommodation Legend: Bicycle accommodation ALIGNED WITH PRIORITIES Traffic Signal Intersection Existing Pathway Environmental sustainability Proposed Pathway LESS ALIGNED WITH Proposed Roadway PRIORITIES Proposed Bridge Future Pathways (By Others) Pathway connectivity LEAST ALIGNED Proposed Single EB Left Construction costs WITH PRIORITIES Proposed Dual EB Left

calgary.ca/CountryHillsWideningTraffic Signal Intersection | calgary.ca/128AveNEExisting Pathway | contact 311 Proposed Roadway Proposed Pathway Proposed Bridge Future Pathways (By Others) L BRIDGE CP Rail Bridge Widening Using what we heard from Calgarians in the Discover Phase, the project team reviewed how to widen the existing CP Rail bridge.

N O R T H S O U T H Existing Bridges Condition: N O R T H S O U T H All stages provide the following: North bridge provides two westbound lanes. • Six lanes on Country Hills Boulevard N.E. South bridge provides two eastbound lanes. • Pathways along both sides of 1.5 m sidewalk on the north side. Country Hills Boulevard N.E. 1.5 3.7 3.7 3.7 3.7 2.5 1.5 3.7 3.7 3.7 3.7 2.5 WALK WB WB EB EB WALK WALK1.5 WB3.7 WB3.7 3.7EB 3.7EB WALK2.5 WALK WB WB EB EB WALK 2.5 m sidewalk on the south side.

CP RAIL EXISTING BRIDGE CROSS SECTION CPCP RAIL RAIL EXISTING EXISTING BRIDGE BRIDGE CROSS CROSS SECTION SECTION

N O R T H S O U T H N O R T H S O U T H Stage 1 Widen both bridges to accommodate three westbound and eastbound lanes to improve mobility along Country Hills Boulevard N.E. Widen north pathway from 1.5 m to 4 m.

4.0 3.5 3.5 3.5 3.5 3.5 3.5 3.85 4.0 3.5 3.5 3.5 3.5 3.5 3.5 3.85 PATH WB WB WB EB EB EB PATH PATH4.0 WB3.5 WB3.5 WB3.5 3.5EB 3.5EB 3.5EB PATH3.85 Widen south pathway from 2.5 m to 3.85 m. PATH WB WB WB EB EB EB PATH

CP RAIL PROPOSED STAGE 1 BRIDGE CROSS SECTION CPCP RAIL RAIL PROPOSED PROPOSED STAGE STAGE 1 BRIDGE 1 BRIDGE CROSS CROSS SECTION SECTION Stage 2 N O R T H S O U T H N O R T H S O U T H Construct a separate pedestrian bridge on the north side to accommodate 4 m pathway. Modify westbound lane markings to accommodate a longer westbound left turn lane to southbound Harvest Hills Way N.E. 4.0 4.0 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.85 PATH4.0 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.85 PATH WB3.5 WB3.5 WB3.5 WBL3.5 3.5EB 3.5EB 3.5EB PATH3.85 PATH WB WB WB WBL EB EB EB PATH WB WB WB WBL EB EB EB PATH

CPCP RAIL RAIL PROPOSED PROPOSED STAGE STAGE 2 BRIDGE 2 BRIDGE CROSS CROSS SECTION SECTION CP RAIL PROPOSED STAGE 2 BRIDGE CROSS SECTION

Public and City Key Priorities Existing Proposed Public and City Key Priorities Existing Proposed Legend: ALIGNED WITH Traffic safety Bicycle accommodation PRIORITIES Community access Environmental sustainability LESS ALIGNED WITH PRIORITIES Improved vehicle travel times Pathway connectivity LEAST ALIGNED WITH PRIORITIES Pedestrian accommodation Construction costs calgary.ca/CountryHillsWidening | calgary.ca/128AveNE | contact 311 Country Hills Boulevard at Harvest Hills Way N.E. and at Harvest Hills Gate N.E. The project team reviewed how the staged widening of the CP Rail Bridge aligns with nearby intersections to the west. Stage 1 Stage 2 COVENTRY BLVD NE COVENTRY BLVD NE COVENTRY BLVD NE COVENTRY BLVD NE COVENTRY BLVD NE COUNTRY HILLS BLVD NE COUNTRYCOUNTRYCOUNTRY HILLS HILLSCOUNTRY BLVDCOUNTRY BLVD NE HILLS HILLS NE HILLS BLVD BLVD BLVD NE NE NE COVENTRY BLVD NE

CP RAIL CP RAIL CP RAIL CP RAIL HARVEST HILLS WAY NE HARVEST HILLS WAY NE HARVEST HILLS WAY NE HARVEST HILLS WAY NE HARVEST HILLS GATE NE HARVEST HILLS GATE NE HARVEST HILLS GATE NE HARVEST HILLS GATE NE

CP RAIL

CP RAIL

TrafficTraffic Signal SignalTrafficTraffic Intersection IntersectionSignal Signal Intersection Intersection ExistingExisting PathwayExisting PathwayExisting Pathway Pathway Proposed Roadway Proposed Pathway

ProposedProposed Roadway ProposedRoadway Roadway ProposedProposed Pathway ProposedPathway Pathway HARVEST HILLS WAY NE

ProposedProposed BridgeProposed ProposedBridge Bridge Bridge ExistingExisting PedestrianExisting PedestrianExisting Pedestrian Bridge Pedestrian Bridge Bridge Bridge HARVEST HILLS GATE NE HARVEST HILLS WAY NE ProposedProposed LeftProposed ProposedLeft Turn Turn Left Left Turn Turn ProposedProposed PedestrianProposed ProposedPedestrian Pedestrian Bridge Pedestrian Bridge Bridge Bridge HARVEST HILLS GATE NE Stage 1 - Harvest Hills Gate Stage 1 - Harvest Hills Way Stage 2 - CP Bridge Highlights: Intersection Highlights: Intersection Highlights: Build new pedestrian bridge north of Modify single westbound left turn lane ProvideTraffic 3 m missing Signal Intersection pathway connection Existing Pathwaythe existing CP Rail Bridge. Traffic Signal Intersection Existing Pathway to dual left turn lane. to northProposed side of Roadwaythe CP Rail Bridge. Proposed PathwayModify westbound lane markings Proposed Roadway Proposed Pathway Two westbound lanes remain. AccomodateProposed three Bridge westbound and three Existing Pedestrianon Country Bridge Hills Boulevard N.E. to Proposed Bridge eastboundExistingProposed Pedestrian lanes Left through Turn Bridge the intersection Proposed Pedestrianaccomodate Bridge a longer left turn lane to Provide 3 m pathway connection to andProposed across the Pedestrian CP Rail Bridge. Bridge southbound Harvest Hills Way N.E. existingProposed north pathway. Left Turn Widen the sidewalk on the north side of the bridge to become 4 m path and widen the pathway on the south side of the bridge to 3.85 m. calgary.ca/CountryHillsWidening | calgary.ca/128AveNE | contact 311 Options Summary: Country Hills Boulevard N.E.

We have summarized the various options developed to address key issues. For more details on any of these options, please see the page(s) identified on the map below.

COVENTRY HILLS For more information see page: STONEY INDUSTRIAL STONEGATE LANDING Deerfoot Trail to 14 Street N.E. For more information see page: For more information see page: Country Hills Boulevard at Deerfoot Trail Bridges - Harvest Hills Way N.E. and at Loop Ramp Options Harvest HIlls Gate N.E 115 AVE NE NOSE CREEK

For more information see page: Deerfoot Trail Bridges - Bridge Deck Options

CP RAIL BARLOW TRAIL NE 14 ST NE FUTURE 11 ST NE COUNTRY HILLS BLVD NE COUNTRY HILLS BLVD NE COUNTRY HILLS BLVD NE FREEPORT DRIVE NE COVENTRY BLVD NE

For more information see page: CP Rail Bridge Widening

110 AVE NE GATE NE HARVEST HILLS For more information see page: Nose Creek Bridge Widening DEERFOOT TRAIL

HARVEST HILLS HARVEST HILLS WAY NE

Project Objectives What We Have Explored • DevelopLegend widening plan along Country Hills Pathway Connections and Widths: Boulevard N.E.Proposed between widening Deerfoot to Trail 3 lanes N.E. and • Provide pathway continuity along both sides of Country Hills Boulevard N.E. from Harvest Hills Gate N.E. to Barlow Trail N.E.. Coventry BoulevardExisting N.E.pathway from four/ sidewalk to six lanes, • Various pathway widening and pedestrian bridge options were explored along Country Hills Boulevard N.E. including continuous multi-use pathways. Proposed pathway / sidewalk Traffic Operations: • Examine wideningIntersecting strategies roadways for existing bridges over CP Rail, Nose Creek and Deerfoot Trail. • Four options to improve westbound operations between Deerfoot Trail N.E. to 14 Street N.E. • Single and dual eastbound left turn operations at Country Hills Boulevard N.E. and 11 Street N.E. • Better accommodate and improve safety for both • Staging options at Country Hills Boulevard N.E. and Harvest Hills Way N.E. to improve westbound operation. current and future travel modes in the study area. • Dual westbound left turn at Country HIlls Boulevard N.E. and Harvest Hills Gate N.E. to improve westbound operation. • Widen Country Hills Boulevard N.E. to three lanes from Deerfoot Trail N.E. to Coventry Boulevard N.E. and Harvest Hills Way N.E.

Bridge Widening: • Widening options to accommodate wide paths and three traffic lanes in each direction at Deerfoot Trail Bridge, Nose Creek Bridge and CP Rail Bridge. calgary.ca/CountryHillsWidening | calgary.ca/128AveNE | contact 311 What We Heard: 128 Avenue N.E.

Overall Themes We Heard in the Discover Phase

Pathways and Connectivity: • It is important to accommodate pedestrians and cyclists along the study corridor. • There are missing segments of pathways. • Desire for safe active modes crossing of Deerfoot Trail.

Traffic Accommodation: • Provide connection for all modes of transportation. • Support for industrial growth and goods movement.

Environment: • Nose Creek alignment and protection is a priority.

Design Constraints: • Participants expressed concern about the proximity of the 128 Avenue N.E. interchange to the one at Stoney Trail N.E. and Deerfoot Trail, however the 128 Avenue N.E. interchange location is in alignment with the existing transportation plans of the Provincial Government.

calgary.ca/website | contact 311 128 Avenue N.E. The City is undertaking a functional planning study to provide an east-west connection through the Stoney Industrial Area between Stoney Trail N.E. and Barlow Trail N.E. Using technical analysis and feedback from Calgarians in the Discover Phase, we have developed concepts and alignment options and would like your feedback to develop the recommended plan. Key Considerations Map

Pathway and Community Connectivity: Traffic Accommodations: Design Constraints West of 15 Street N.E.: • Multiple existing and planned pathways within • Ultimate cross section is six lanes, divided. • Multiple utilities impacted (e.g., watermain, and adjacent to the 128 Avenue N.E. study area, • Accommodate all modes of travel along overhead power lines). with a number of gaps or missing links. the corridor. • Significant east-west grade difference , with new • The 128 Avenue N.E. corridor will be important in • Access management and spacing grade-separated crossings of the CP Rail lines and closing multiple gaps in the pathway system. requirements, with multiple intersections Nose Creek. Creek realignment will be required at • Linkage to the Coventry Hills community required. along 128 Avenue N.E. to service the crossing point. adjacent land. • Access requirements for adjacent developable land. calgary.ca/CountryHillsWidening | calgary.ca/128AveNE | contact 311 128 Avenue N.E. Alignment – West of 15 Street N.E.

Option 1: Option 2: Maintain Existing 15 Street N.E. Intersection Relocate 15 Street N.E. Intersection

All Options Provide the Following: 11 ST NE ST 11 11 ST NE ST 11 Ultimate six-lane divided cross STONEY TRAIL STONEY TRAIL section proposed for 128

Legend Legend Avenue N.E. OPTION 1A PROPOSED ROAD OPTION 2 PROPOSED ROAD

PROPOSED BRIDGE CROSSING PROPOSED BRIDGE CROSSING 3.5 m pathways to be provided ROAD CLOSURES ENMAX TOWER - BUFFER LIMIT ENMAX TOWER - BUFFER LIMIT along both sides of 128 Avenue N.E., with connectivity to existing COVENTRY HILLS COVENTRY HILLS and future pathway network.

15 ST NE 15 ST NE Future transit-only connection and pathway link with Coventry Hills community confirmed. 12 A8 VE NE

TRANSIT-ONLY TRANSIT-ONLY CONN ECTION CONNECTION 12 A8 VE NE WITH PATHWAY CPR WITH PATHWAY CPR

15 ST NE

15 ST NE

STONEY TRANSIT STONEY TRANSIT NOSE CREEK FACILITY NOSE CREEK FACILITY All Options Will Require: Raising Enmax power lines for Option 1 Option 2 adequate clearance above • No impact on 15 Street N.E. intersection. • Requires reconstruction of a portion of 128 Avenue N.E. 128 Avenue N.E. • Minimal construction impacts. • Some disruption during construction. Realignment and protection • Most impact on deep utilities. • Increased property impact (east of 15 Street N.E.). of Nose Creek at the crossing point. Realignment and • Immediately adjacent to Enmax tower. • Least impact on deep utilities (compared to Option 1). mitigation measures to be • Largest offset from Enmax tower. confirmed once a preferred alignment is identified.

calgary.ca/CountryHillsWidening | calgary.ca/128AveNE | contact 311 128 Avenue N.E. Corridor – Cross Sections

Roadway Cross Section

SOUTH NORTH

3.5 3.7 3.5 3.5 6.0 3.5 3.5 3.7 3.5 PATH BLVD. EB EB EB MEDIAN WB WB WB BLVD. PATH

TRAIL TRAIL BARLOW

DR NE DEERFOOT DR NE STONEY 128 AVE NE STONEY UNDER REVIEW 19 ST NE 15 ST NE For more information see page: 128 Avenue N.E. Corridor – 15 Street N.E. to Barlow Trail N.E. STONEY TRANSIT FACILITY

Deerfoot Trail Bridge Cross Section

SOUTH NORTH

2.5 4.2 3.7 3.5 3.5 3.5 3.5 3.5 3.7 4.2 SHY MED. SHY PATH EB EB EB LT WB WB WB PATH

calgary.ca/CountryHillsWidening | calgary.ca/128AveNE | contact 311 128 Avenue N.E. Corridor – 15 Street N.E. to Barlow Trail N.E.

15 Street N.E. to 19 Street N.E. DR NE

128 AVE NE STONEY 15 ST NE DR NE STONEY

128 AVE NE DR NE 15 ST NE

128 AVE NE STONEY 15 ST NE 19 ST NE 19 ST NE 19 ST NE 19 Street N.E. to Deerfoot Trail N.E.

128 AVE NE 128128 AVE AVE NE NE UNDER REVIEWUNDER UNDERREVIEW REVIEW REVIEWREVIEW DR NE

TRAIL STONEY DR NE 19 ST NE

TRAIL DR NE

TRAIL STONEY DEERFOOT STONEY 19 ST NE 19 ST NE

DEERFOOT DEERFOOT Deerfoot Trail N.E. to Barlow Trail N.E. • Ultimate six-lane divided cross 128 AVE NE 128128 AVE AVE NE NE section on 128 Avenue N.E.

• Interim stages for roadway and Deerfoot Trail interchange to be determined based on progress of area development activity. TRAIL

TRAIL TRAIL

DEERFOOT BARLOW TRAIL NE

DEERFOOT BARLOW TRAIL NE DEERFOOT BARLOW TRAIL NE calgary.ca/CountryHillsWidening | calgary.ca/128AveNE | contact 311 128 Avenue N.E. Alignment - Deerfoot Trail Interchange

A “Half Diamond” interchange configuration 128 AVE NE has been confirmed. This is consistent with UNDER previous planning for this interchange. No REVIEW viable alternative configurations were identified or evaluated. East and west ramp terminal intersections will

TRAIL be signal controlled.

DR NE DEERFOOT STONEY Staged implementation of the interchange can be considered, depending on the location, intensity and pace of area development. Operating conditions between 128 Avenue N.E. and Country Hills Boulevard N.E. interchanges have been assessed and determined to be acceptable.

calgary.ca/CountryHillsWidening | calgary.ca/128AveNE | contact 311 Area Pathway Connectivity

There are multiple existing and planned pathways within and adjacent to the 128 Avenue N.E. study area, with a number of gaps or

11 ST NE STONEY TRAIL missing links.

Completion of the 128 Avenue N.E. corridor, with pathways along both

11 ST NE STONEY TRAIL COVENTRY sides and a crossing of 128 AVENUE NE Legend HILLS Deerfoot Trail N.E., will close Rotary Mattamy Greenwaymultiple gaps in the

The Greatpathway Trail system.

Regional pathways (per COVENTRY various Area Structure 128 AVENUE NE Legend Plans) HILLS The Coventry Hills 15 ST NE Rotary Mattamy 128 Avenue/ 11 Street Greenway (Multi-usecommunity Trails on both will be linked to sides) The Great Trail the pathway system with the Community pathway Regional pathways (per connection various Area Structure proposed connection (jointly Plans) Existing pathway

15 ST NE 128 Avenue/ 11 Street with a transit-only link). BARLOW TRAIL NE (Multi-use Trails on both NOSE CREEK sides) DEERFOOT TRAIL Community pathway connection

Existing pathway

BARLOW TRAIL NE NOSE CREEK DEERFOOT TRAIL COUNTRY HILLS BLVD NE

COUNTRY HILLS BLVD NE

calgary.ca/CountryHillsWidening | calgary.ca/128AveNE | contact 311 Next Steps

1. Discover Phase: Document and Assess Existing Conditions (Completed December 2019) 2. Explore Phase: Development and Analyze Concepts (January - July 2020) • The online survey is open until July 26, 2020 at calgary.ca/CountryHillsWidening or calgary.ca/128AveNE 3. Reveal Phase: Presentation of Recommended Plan (August - December 2020)

How will public feedback be used? The City will prepare a What We Heard report summarizing all feedback following this and future public engagement sessions. Your input will help inform the design concept and the preferred plan for the Country Hills Boulevard N.E. and 128 Avenue N.E. study areas. For ongoing project updates, information regarding future engagement events, or to sign up for email updates, visit calgary.ca/CountryHillsWidening or calgary.ca/128AveNE. Thank you for your interest. Please take a moment to provide your feedback online. Your feedback will help us improve our future engagement events.

calgary.ca/CountryHillsWidening | calgary.ca/128AveNE | contact 311