RP946 v4

GOVERNMENT OF PUBLIC WORKS DEPARTMENT KARNATAKA STATE HIGHWAYS IMPROVEMENT PROJECT - II Public Disclosure Authorized

RESETTLEMENT IMPLEMENTATION PLAN WAP 3 (Shikaripura – Hanagal)

Public Disclosure Authorized

Public Disclosure Authorized

Public Disclosure Authorized

June 2012

Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Contents

ABBREVIATIONS ...... iii EXECUTIVE SUMMARY ...... 1 I. INTRODUCTION ...... 3 Objectives of RIP ...... 4 Main activities of RIP ...... 4 Minimization of Impacts and Corridor of Impact ...... 4 II. LAND ACQUISITION AND RESETTLEMENT IMPACTS ...... 6 Land Acquisition Status ...... 6 Guidance Value ...... 6 Negotiation Committee ...... 6 Method of Price Negotiation ...... 7 Records to be submitted by the Land Owners ...... 7 Failure of KHA and Appellate Committee ...... 7 Conclusion of Negotiation ...... Error! Bookmark not defined. Valuation of Assets on land under LA ...... 8 Valuation of Crops ...... 8 Valuation of other structures/assets ...... 8 Site Requirement for Residential and Commercial impacts ...... 8 Loss of Community Assets ...... 8 III. BASELINE CENSUS SURVEYS AND CONSULTATIONS ...... 10 Characteristics of displaced households ...... 10 Major and Minor Impacts ...... 11 Vulnerable groups ...... 13 Consultations...... 13 IV. IMPLEMENTATION MECHANISMS ...... 15 Institutional Arrangements ...... 15 Extending R& R Assistance to PAPs ...... 15 Implementation support by NGOs ...... 17 IR Activities ...... 18 Monitoring and Evaluation support for RAP ...... 19 Grievance Redressal mechanism ...... 19 Resettlement Colonies and Vendor Markets ...... 20 Protection of RoW ...... 20 Impacts on Municipal Towns ...... 21

i Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Data Base Management ...... 21 Co –ordination between R&R and Civil works ...... 21 Monitoring and R&R Activities ...... 23 Additional Impacts ...... 23 Budget ...... 23 Disclosure ...... 24 Annexure 1 Guidance Value as on August 2011 ...... 25 Annexure 2: Details of PAFs of Link T21 ...... 28 Annexure 3: PAF Details of Link M7A ...... 31 Annexure 4: Details of PAFs of Link M7B ...... 36 Annexure 5: Details of PAFs Link M7C ...... 40

List of Tables Table 1- 1: Package Details ...... 3 Table 1- 2: Summary Tables on Impacts ...... 5

Table 2- 2: Summary Table on Community Assets ...... 8

Table 3- 1: Baseline Socio Economic information WAP3 - for Major impacts ...... 10 Table 3- 2: Distribution of PAFs by Major and Minor Impacts for WAP 3 ...... 11 Table 3- 3: Consultation Summary ...... 13

Table 4- 1: R& R Assistance ...... 15 Table 4- 2: Time line for Key LA and R & R Activities ...... 22 Table 4- 3: Time line for LA and R & R Activities ...... Error! Bookmark not defined. Table 4- 4: Monitoring Indicators for Physical Progress ...... 23 Table 4- 5: Budget ...... 23 Table 4- 6: Guidance Value for Link M7A ...... 25 Table 4- 7: Guidance Value for Link M7B ...... 26 Table 4- 8: Guidance Value for Link M7C ...... 26 Table 4- 9: Guidance Value for Link T21 ...... 27 Table 4- 10: Details of PAFs T21 ...... 28 Table 4- 11: PAF Structure details of link M7A ( - Shikaripura) ...... 31 Table 4- 12: PAF Structure details of link M7B (Shikaripura - Togarsi) ...... 36 Table 4- 13: PAF Structure details of link M7C (Anvatti - )...... 40 Table 4- 14: Community Asset Details of link T21 (Shikaripura - Anandapuram (on NH-206)) ...... 47 Table 4- 15: Community Assets M7A ...... 48 Table 4- 16: Community Assets M7B ...... 50 Table 4- 17: Community Assets M7C ...... 53

List of Figures Figure 1- 1: Distribution of PAFs for Package WAP3 ...... 12 Figure 1- 2: Distribution of PAFs by Major Impact for Package WAP3 ...... 12

ii Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

ABBREVIATIONS

AC Assistant Commissioner ADSW Assistant Director Social Welfare CAO Chief Administrative Officer CPO Chief Project Officer CPR Common Property Resources COI Corridor of Impact DC Deputy Commissioner DPR Detail Project Report EWS Economically Weaker Section EPC Engineering Procurement Contract GOI Government of GOK Government of Karnataka GRC Grievance Redressal Cell ID Identity Card IPDP Indigenous People Development Plan IR Income Restoration KHA Karnataka Highways Act KSHIP Karnataka State Highways Improvement Project LAA Land Acquisition Act LAO Land Acquisition Officer LAP Land Acquisition Plan NGO Non-Governmental Organization PAF Project Affected Family PAG Project Affected Group PAP Project Affected Person PIU Project Implementation Unit PGB Project Governing Body PWD Public Works Department PU Pre University PGB Project Governing Body RTC Record of Rights R & R Resettlement and Rehabilitation RAP Resettlement Action Plan ROW Right of Way SIA Social Impact Assessment SDO Social Development Officer SDRC Social Development Resettlement Cell SWI Social Welfare Inspector SC Scheduled Caste SR Schedule of Rates ST Scheduled Tribes SHG Self Help Group

iii Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

SIA Social Impact Assessment ToR Terms of Reference UR Upgradation ZP Zilla Panchayat

iv Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

EXECUTIVE SUMMARY The Karnataka State Highways Improvement Project (KSHIP) – II, covers a length of 826.6 kms. The roads have been categorized into two types of contracts EPC and Annuity. It consists of 269.4 kms of EPC roads consisting of 5 packages and 557.3 kms of roads under annuity contract consisting of 4 packages. Contract package WAP 3, is an Annuity package which covers 154 kms consisting of 4 links, passing through the districts of Shimoga, Davangere and . This Resettlement Implementation Plan covers the implementation requirements for Package WAP 3. In this package about 114 acres 22 ¾ guntas land has to be acquired, of this 43 acre 18 ½ guntas is dry land, 30 acres 27 ¾ is wet land, 1 acre 4 guntas is plantation and 24 acres 14 ½ is kharab land. As a result of land acquisition and related impacts, 1104 PAFs will lose part of their land; and another 439 PAFs lose their house hold/commercial/ assets /livelihood are getting affected. In addition, 223 community assets will also be affected. Out of these impacts, 172 PAFs are in the major impact category losing their houses/shop and livelihood and 1371 PAFs in the minor impact category who loses only part of their land or assets and the remaining land and asset is sufficient to continue their shelter and livelihoods A baseline survey was conducted amongst affected people which indicate that Hindus dominate with 85.00 percent followed by Muslims at 15 percent. Distribution of PAPs by occupation indicates that 63 percent are in agriculture; agricultural labourers account for 10.61 percent; commerce and trade supports 14.94 percent. In this package 30.18 percent of population has income less than Rs.26,000. 65.8 percent of the population falls within the age group of 18-60, which happens to be the working age group. In this package illiterate population accounts for 10.01percent; those with primary education account for 10.99 percent and those with secondary education account for 25.23 percent. Public consultations were held at 4 important locations along this corridor in January, 2009 and 295 persons participated in these consultations. The consultations focused on mainly in explaining the entitlements under the R&R policy and measures taken to minimize the impacts and receive the suggestions from the participants. The consultations have helped in not only in disseminating the policy provisions to deal with land acquisition related impacts , but also assisted in gathering suggestions for mitigation of adverse impacts, improvement in designs and facilitating inputs for the resettlement plan preparation and implementation. During Consultations a number of issues have been raised, some of which include reduction of COI at Navile Lake, this has been taken into consideration during design with a specific cross section for this location, there were a number of queries related to the lake, however these did not have relevance to this project; people did not want further widening in Shimoga, this has to be addressed collectively by the various authorities concerned with Shimoga and the government; other questions related to the entitlements which was explained; In Hanagal town people did not want further widening - however widening has been proposed with minimal impacts ; at Solur also people did not want widening due to the likely impacts, however here too the design cross sections have been reduced to 10 m to minimise impacts. Besides this, safety concerns have been addressed by building foot paths in built up area, providing foot path barricades, school/village signages, rumble strips and road humps There are no major potential land acquisition and resettlement issues in this package. In locations such as Navile Lake, Solur village and Hanagal town, the cross section has been reduced to minimize

1 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal) impacts. There are 11 cross section options adopted in this package to minimize impacts, the COI width varies from 11 m to 26 m. The GOK has adopted the Resettlement and Rehabilitation (R&R) Policy for KSHIP- II consistent with the NRRP, 2007 and the World Bank policy on involuntary resettlement to address the adverse impacts arising out of this project. Land Acquisition will be done through the Karnataka Highways Act 1964. Land acquisition under this Act will help the PAPs to receive the market price/replacement cost of land as compensation is negotiated through negotiation. Negotiation Committee has been constituted to negotiate the price of land with the landlord. The minimum negotiated price will be twice the current guidance value for Shimoga, Davangere and Haveri districts. Some of the entitlements include payment of compensation through negotiation according to the Karnataka Highways Act, 1964; additional compensation for those becoming marginal farmers; grant for replacement of cattle shed; alternative house or developed plot +construction cost for those losing house; additional 25% compensation for partially affected structures towards re-construction; support for purchase of income generating assets; rental allowance for affected tenants; support for non-title holders to provide alternative houses or developed plots; construction cost; support for providing alternate shop or income generating asset to those who are losing commercial structures; employees losing livelihood will be given onetime payment; vulnerable group including physically challenged and those above 60 years will be assisted to get Government pension, if they are eligible or given a lump sum amount as assistance; and all community assets will be replaced and reconstructed. This RIP will be implemented by Karnataka PWD-PIU Social Development Resettlement Cell with support from the NGO - STEM (Centre for Symbiosis of Technology Environment Management). The SDRC is responsible for monitoring the implementation of all resettlement and rehabilitation activities, including land acquisition The Special Deputy Commissioner, Land Acquisition, will be responsible for land acquisition activities while the Chief Administrative Officer will be responsible for all Resettlement and Rehabilitation works. A Grievance Redressal Cell with 3 members is constituted with Deputy Commissioner of the District as the Chairman. An independent agency viz., Samaj Vikas has been hired for Monitoring and Evaluation support. The SDRC, PIU will facilitate land acquisition and compensation, relocation and resettlement, distribution of assistance for the PAPs. WAP 1 will be implemented by KHSIP Division, Shimoga. The SDO and SWIs appointed for the Shimoga division will take care of R&R activities of this package. The civil works for this package is likely to commence in December 2012. The R&R and land acquisition is targeted to be completed by August 2012. Implementation activities include land acquisition process, relocation and rehabilitation and monitoring. The budget estimated for land acquisition and R&R activities for this package is Rs.16.26 crores which forms a part of the overall budget approved by the GoK. All cash allowances to be paid to the PAPs is adjusted for inflation for 2012-13 and those who receive the assistance beyond April, 2013 will further be adjusted by 10% as needed. This RIP will be disclosed through public consultations, Government of Karnataka/PWD Website. In addition, copies will be kept in: (i) State Government Library at Bangalore; (ii) - District library of Shimoga, Davangere and Haveri districts; and (iii) in the Panchayat offices along the project roads.

2 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

I. INTRODUCTION

1. The Karnataka State Highways Improvement Project (KSHIP) – II Phase-I initial priority roads cover 826.6 kms. In this connection a detailed Resettlement Action plan has been prepared in consultation with the affected persons, PIU and other stakeholders. This document includes, among other things, legal frame work and Resettlement Policy Provisions, Land acquisition and compensation payment, Social impact assessment and base line Socio-Economic characteristic and the implementation arrangement. The Government approved the Resettlement Action plan vide its order dated 28th July 2010. This has been published in the PWD web sites in the month of August 2010. This Resettlement Implementation Plan outlines the steps for resettlement and rehabilitation of PAFs/PAPs losing their land and structures and relocation of community assets for WAP 3. 2. Contract package WAP 3 covers 154 kms consisting of 4 links. The details about the package are given in Table 1. In the Annexure the lists of those losing structures after verification has been provided which are enumerated in 2007-08 and verified by NGO in 2011. Details of those losing land are given in the Notifications issued under Sec.15 of the KHA. The list of vulnerable people will be subsequently prepared and assistance extended as needed. Any additional people moved into the ROW after the cut-off date and are not served notices subsequently will be identified through additional verification by 31st July 2012. The question of extending assistance to them will be examined on case to case basis. In case of those who are mobile type of shops will not be provided any assistance since they keep on changing on regular basis and they can easily find another alternative place to continue their petty business provided after verification.

Table 1- 1: Package Details

Link Description Length Districts Taluks Cutoff date Shikaripura - T21 Anandapuram (on 32.24 Shimoga Shikaripura, Sagara 23.12.2008 NH-206) Shimoga - Savalanga Shimoga, Shimoga, Honnali 27.12.2008 M7A 49.79 – Shikaripura Davanagere Shikaripura - Shimoga Shikaripura, 01.01.2009 M7B Shiralakoppa - 45.41 Togarsi Anvatti - Gondi – Shimoga, Soraba, Hanagal 27.12.2009 M7C 26.21 Hangal Haveri

3. WAP 3 falls within the Central Karnataka Plateau which covers the districts of Bellary, Chikkamagalur, Chitradurga, Davanagere, Dharwad, Gadag, Haveri, Raichur, Koppal and Shimoga. The region represents the transitional surface between the Northern Karnataka Plateau with relatively higher surface. By and large, this region represents the area of Tungabhadra basin. The general elevation varies between 450 and 700 meters. However, this transitional ground is broken by several sets of parallel ridges mainly made up of Dharwar system of rocks. The height of such residual hills is about 900 meters above mean sea level. The general slope of this region is towards the east. The major

3 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

crops growing in these places are Sunflower, Paddy, Maize, Groundnut, Cotton, Flowers, Wheat, Ragi, Bajra, Chillies, Coconut and Arecanut.

4. The entire package is regarded as a single milestone. All the R&R and land acquisition has to be completed at the time handing over of package to the contractor.

5. In this package 114 acres 22 ¾ guntas land has to be acquired. Of this 43 acre 18 ½ guntas is dry land, 30 acres 27 ¾ is wet land, 1 acre 4 guntas is plantation and 24 acres 14 ½ is kharab land; there are 439 PAFs whose house hold/commercial structures/ assets/ livelihood is getting affected and 1104 PAFs losing land; There are 223 community assets getting affected. The PAPs listed in this RIP is as recorded during the cut-off date and further verified by the NGOs.

6. There are no major potential land acquisition and resettlement issues in this package. In locations such as Navile Lake, Solur village and Hanagal town, the cross section has been reduced to minimize impacts. There are 11 cross section options adopted in this package to minimize impacts, the COI width varies from 11 m to 26 m.

Objectives of RIP 7. The objective of this RIP is to provide a package specific guideline for implementation for R&R activities. The implementation plan identifies the persons affected, the type of entitlements to be provided for specific losses, what are the steps that will be adopted in getting compensation, details of members of the Negotiation Committee and the GRC members in the package, time table and steps to be taken by the PIU for protecting right ROW. Overall it provides how the RAP will be implemented in this particular package.

Main activities of RIP 8. The main activities to be carried out in finalising the RIP includes, Joint verification, distribution of ID cards, identification of sites for relocation, identification of income generating options, identification of vulnerable groups, identification of resettlement centers and vendor markets, negotiations for land acquisition, payment of compensation, relocation and shifting of community assets. The members of the GRC and Negotiation committees have to be identified and informed, as mentioned in the RIP. The RIP after finalization will be disclosed.

Minimization of Impacts and Corridor of Impact 9. There are 11 cross section options adopted in this package to minimize impacts, the COI width varies from 10 m to 26m. In places such as Solur the cross section has been reduced to 10 m to mitigate impacts. Besides this, safety concerns have been addressed by building footpaths in built up area, providing footpath barricades, school/village signages, rumble strips and road humps The different cross sections used are:

4 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

1. UR1A Rural Cross section with paved shoulders varying from 18-26 m 2. UR1B Rural Cross Section without paved shoulder varying from 18m to 26 m. 3. UR2 Rural Cross section through village width varying from 11m to 22m. 4. UR3 Urban Cross Section in built up area with covered drain with a maximum width of 22m 5. UR4 Urban Dual lane Cross section in built up area with covered drain with a maximum width of 24 m. 6. UR5 Rural Cross section in Sugarcane belt 7. UR6 Rural Cross section in Hilly Terrain 8. UR7 rural cross section cutting 9. UR 18 Cross section at lake location M7A (ch 2+050 to 2+700) 10. UR 24 Urban dual lane cross section in built up area with uncovered drain varying from 10m to 24 m. 11. UR25 Urban dual lane cross section in built up area with covered drain with covered drain varying from 22m to 24m.

Table 1- 2: Summary Tables on Impacts

Land Major Impact Minor Community Description LA Pvt Link Transfer Impact Assets

Shikaripura - 28.33 ½ 7.04 ¼ 13 T21 Anandapuram (on 242 59

NH-206)

Shimoga - Savalanga 20.33 ½ 10.09 ¾ 57 436 71 M7A – Shikaripura Shikaripur - M7B Shiralakoppa - 32.06 5.08 37 424 59 Togarsi Anvatti - Gondi – 8.15 ¼ 1.32 ½ 65 334 34 M7C Hangal 90.08 ¼ 24.14 ½ 172 1436 223 Total

5 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

II. LAND ACQUISITION AND RESETTLEMENT IMPACTS

10. This chapter provides an overview of the extent of land acquisition and the process of land price negotiations and details of documents to be submitted. It also provides the impacts of the project on community assets. 11. In this package, total land required is 94 acres 13 1/2 guntas. 19.20 ¾ acres of government land has to be transferred. The details of the PAFs losing land is given in Notification issued under section 15 of the KHA 1964 in connection with land acquisition. There are 229 PAFs who are losing 5 guntas and more of agricultural land as per preliminary notification. Land Acquisition Status 12. The Notifications under section 15 under the KHA for WAP 3 is as follows: 1. M7A: No. PWD :104: EAP : 2011, Bangalore, date d19 .7.2011 M7A: No. PWD :104: EAP : 2011, Bangalore, dated 13 .9.2011 Additional 2. M7B: No. PWD :119: EAP : 2011, Bangalore, dated 8 .9.2011 3. M7C: No. PWD :114: EAP : 2011, Bangalore, dated 30 .7.2011 4. T21 - No. PWD :105: EAP : 2011, Bangalore, dated 19 .7.2011

Guidance Value 13. The Guidance Value of land for different categories of land, for the villages along the project road in is given in Annexure 1. This guidance value will be referred to by the Negotiation Committee. 14. The rates will be revised annually by 10% on the 1st of April every year, in case Government has not revised it. The guidance value varies from a minimum of Rs. 30,000 per acre in Kanivenahalli village to Rs 6,00,000 per acre in Guluru village. Negotiation Committee 15. The Replacement Cost of land for consent award will be determined by the Negotiation Committee. In this package the Negotiation Committee has been constituted vide GO No. PWD 215 EAP 2007 dated 24-10-2009. This Committee consists the following members:

1. Assistant Commissioner of the concerned Sub Division : Chairman 2. Assistant Commissioner of KSHIP : Member Secretary 3. Executive Engineer KSHIP Division, : Member 4. Zilla Panchayat Member of the concerned jurisdiction : Member.

16. The details about the committee members will be updated and confirmed by 30th June 2012.

6 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Method of Price Negotiation 1. The concerned Land Acquisition officer who is the member secretary of the Negotiation Committee will call for a meeting; 2. Dates for price negotiation will be given village wise. Negotiation will be conducted village wise calling all the land losers together for negotiation. This is to ensure transparency. 3. The PIU will provide information on the guidance value of the land to land losers before negotiations. 4. The minimum negotiated price will be twice the current guidance value for . 5. The Negotiation Committee will negotiate the price with the landlord; 6. Based on the decision of the Negotiation Committee the Special Land Acquisition Officer will initiate action to collect documents after obtaining the approval of competent authority in the PIU. 7. Compensation will be given within 30 days of receiving all the necessary documents by the Special LA officer. In case of delay, 9% interest will be given to the beneficiary upto a period of one year and after which, it will be increased to15% . (This is as per the provisions of the LA Act). 8. On approval of the award by the Special DC or PD, the Special Land Acquisition Officer will make the payments accordingly. 9. Possession of Land will be taken vide Section 19, which will be only after the payment of compensation.

Records to be submitted by the Land Owners 17. As soon as Notification u/s 19 is issued, the NGO shall collect the following documents in respect of lands to be acquired, before inviting for negotiations:

1. Original copy of RTC for current year; 2. Original or attested copy of mutation in respect of land and Khatha Certificate in respect of site / building; 3. Encumbrance Certificate for 13 years; 4. No Tenancy Certificate and Certificate regarding 79A, 79B and 66; 5. Bank Account details; 6. Land holding / small / marginal farmers Certificate whenever necessary; and 7. G. Tree.

After offering of compensation, the NGO shall collect the remaining documents such as –

1. Attested copy of Sale Deed/Partition Deed/Saguvali Chit/Regrant Order etc., to prove title of land; 2. Indemnity Bond; 3. Agreement and Affidavit and submit them to the Assistant Commissioner for processing for compensation. Any fees incurred by the NGO in obtaining the documents shall be reimbursed by the Executive Engineer of the Division

Failure of KHA and Appellate Committee 18. Even after the minimum negotiation price as per the RAP is offered and the land owner does not agree for it, then the negotiation will be treated as failed and award will be passed as per the general LA Act.

7 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

The price offered and the price demanded by the land owner in such cases will be recorded in the proceedings. The provisions of the LA amendment bill will be followed when they come into force. Valuation of Assets on land under LA 19. The valuation of structures and other assets will be carried out by Government approved valuators appointed by the Executive Engineer in consultation with PIU. Valuation will be done on the basis of current PWD Schedule of Rates, without depreciation. Based on the valuation, another 30% will be given as top up to those who come forward for consent award. Trees will be valued by the Agriculture / Horticulture / Forest department. Valuation of Crops 20. Crop loss will be compensated based on the valuation done by the Agriculture/Horticulture Department. Valuation of other structures/assets 21. The valuation of structures and other assets will be carried out as mentioned above. However, this will be verified and approved by the concerned Executive Engineer. Site Requirement for Residential and Commercial impacts 22. Actual requirement of sites in each package has been indicated in the Joint Verification report of NGO. In this package 4 sites are required for Non- titleholders. Verification for titleholders is under progress. As for as possible, Government land will be identified for formation of sites and allotted to the eligible PAFs/PAPs. Where Government land is not available then the PIU, KSHIP shall examine alternatives such as - cash in lieu of sites or purchase of private land - on case to case basis, based on local factors. Loss of Community Assets 23. In the contract package WAP 3, 223 community Assets getting affected.

Table 2- 1: Summary Table on Community Assets Sl. Type of Community Asset No No. 1. Temple/Shrines 28 2. Aralikatte 8 3. Bus Shelters 34 4. Hand Pumps 39 5. MWS/Water supply tanks 19 6. Borewells 27 7. Others 68 Total 223 24. All community assets on Government land will be shifted by PIU. All assets on private land will be shifted with assistance of NGO. There are seven community assets belonging to private trust and another two CPRs on private land. In case these assets are affected, compensation has to be paid according to the entitlement matrix.

8 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

25. For Temple/shrine, Aralikatte, new site has to be identified by NGO in coordinating with SDO/SWI at the Divisional level. This site should be a Grama thana land or land given as donation. For land that is donated the concerned Engineer has to take a site consent letter from the donor of the site in prescribed format which will be prepared by NGO. The format will have Donor name and address, Site details(Survey nos, place, boundary) with measurement,; the signatures of at least 3 persons from the village is necessary on the letter for evidence. The donor has to also sign on the consent letter. The letter will be submitted to the Executive Engineer of the division. The EE will then have to construct the new community structure/Temple/Shrine/ Aralikatte etc. After the construction of the new structure the SDO/SWI and NGO will jointly convince the concerned village people to demolish the existing structure, and shift the activities to the new place. 26. Bus shelters, Hand pump, MWS tanks, Bore wells and other community assets will be relocated and reconstructed. The KSHIP divisional staff will be taking necessary action with assistance of SDO/SWI. The chainage wise community assets details are given in Annexure 6.

9 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

III. BASELINE CENSUS SURVEYS AND CONSULTATIONS

Characteristics of displaced households 27. This chapter outlines the characteristics of displaced households. As a part of the project, a census survey of Project Affected Families / Persons (PAFs and PAPs) was carried out. The findings of the census survey provided the magnitude of social impacts on the PAFs and PAPs. In this chapter, baseline socio-economic analysis has been done separately for the major impacted families. 28. Among religious groups, Hindus dominate with 85.00 percent followed by Muslims at 15 percent. Distribution of PAPs by occupation indicates that 63 percent are in agriculture; agricultural labourers account for 10.61 percent; commerce and trade supports 14.94 percent. In this package 30.18 percent of population has income less than Rs.26,000. 65.8 percent of the population falls within the age group of 18-60, which happens to be the working age group. In this package illiterate population accounts for 10.01; those with primary education account for 10.99 percent; those with secondary education account for 25.23 percent. . Average land holding size is 6.39 acres. A look at the ownership of household assets indicate 45.37 percent own televisions; 12.96 percent own cooking gas; 32.65 percent own 2/4 wheelers while only 7.88 percent own refrigerators. Some of the baseline parameters identified for those with major impacts are given in the table below. The details of the PAPs losing structures are given in Annexure 2,3,4 and 5.

Table 3- 1: Baseline Socio Economic information WAP3 - for Major impacts 1. Losing total house (including residential cum 26 commercial) 2. Average area 14.86 sq.m 3. % of houses electrified 9.88% 4. % of houses having water supply 1.16% 5. Average earning Rs. 24,434/- 6. % of earners 27.78% 7. % of PAPs earning less than Rs.26,000* 16.67% 8. Average land holding (A-G) 6-39 Acres 9. % of Farmers having less than 2.20 acres of holding 25% 10. % of PAPs in agriculture 4.76% 11. % of PAPs working as agriculture labour 8.73% 12. % of PAPs in the service sector - 13. % of PAPs in Commerce and Trade 18.25% 14. Loss of commercial structures 146 15. Type of commercial structure 1 Pucca 59.86% 2. Semi pucca 31.29% 3. Kutcha 8.84% 16. Average area of commercial structure 11.42 sqm 17. Type of shops affected (majority) 1. Pan/cigarette – 7.48% 2. Tea shop/hotel - 8.16% 3. Barber- 7.48% 18. Average monthly turnover of shops 1. Rs.23,000/-

19. Ownership of Household assets 1. Television - 13.37% 2. Refrigerator – 1.16% 3. Telephone – 3.49% 4. Cooking Gas – 2.33%

10 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

5. 2/4 wheeler - 2.91%

Note: * Rs.26,000 has been taken as the cut off for BPL Major and Minor Impacts 29. The list of major and minor impacts for this package is given below.

Table 3- 2: Distribution of PAFs by Major and Minor Impacts for WAP 3 Sl. Extent of Loss Owner Tenant Squatter Encroacher Total No. Major Impact 1 Losing Total House 22 2 1 0 25 2 Losing Total Com. Struc. 23 0 22 0 45 Losing Total House and Com. 3 1 0 0 0 Struc. 1 4 Tenants Losing Total Livelihood 0 101 0 0 101 Total Major Impact 46 103 23 0 172 Minor Impact 1 Losing only Part of House 141 0 0 0 141 2 Losing Part of Com. Struc. 76 0 1 0 77 Losing Part of House and Com. 3 31 0 0 0 Struc. 31 4 Partial Plot 0 0 0 0 0 5 Total Boundary Wall 1 0 0 0 1 6 Partial Boundary Wall 0 0 0 0 0 7 Total Cattle shed 4 0 0 0 4 8 Farmers 1104 0 0 0 1104 9 Others 13 0 0 0 13 Total Minor Impact 1370 0 1 0 1371 Total (Major & Minor Impacts) 1416 103 24 0 1543

11 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Figure 1- 1: Distribution of PAFs for Package WAP3

Figure 1- 2: Distribution of PAFs by Major Impact for Package WAP3

12 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Vulnerable groups 30. Based on the Census survey there are 491 PAPs who come within the purview of vulnerable group. The categories include 77 widows; 403 persons above the age of 60 and 11 persons with disabilities. However this is only an enlistment of all persons coming under the vulnerable category. Only after verification by the NGO it will be confirmed whether these people are vulnerable. If so it will be verified further whether are getting pension/ or other assistance from the government. If the person is already receiving pension / assistance, then this offer will not be extended. Only after such verification will the person be entitled to assistance under this category

Consultations 31. Four consultations were carried out in this package. The outcome of the consultation are summarized below Table 3- 3: Consultation Summary Section Details Issued Raised Response of project Authority M7 A Date: 07.01.2009  Due to curve straightening people are losing  It was informed that it will take into Place: Shimoga their 10-15 pucca residential structures. They asked consideration and once again project authority to avoid affecting their structures and maintain equal will examine the particular spot and take the No. of Participants: 180 width form the existing center line near Navale decision to save those residential and Lake.. community structures.

 At the same place 3 major temples are getting  Navale lake and ring road matter will examine and take the decision by project affected. authority.  The people don’t want road widening the town limit, because in the town limit the new road was already constructed with median and box drain very recently.  The participants brought to the notice Navale lake was handed over to the urban development authority for construction of cricket stadium. And also they informed Shimoga town have a plan of ring road from Honnali road via Tavare chattanahalli –to Savalanga Road and connected to Shimoga Sagar road. M7B Date: 12-01-2009  People wanted to alternative site for  It was informed that the project authority Place: Thogarsi construction new houses will take into consideration

No. Of  Land losers wanted to land compensation in  The demand for compensation at market Participants: 80 present market rate value rates could be taken care by the KHA through

 Participants want to restrict the road width with the process of negotiation in the town and village limit.  It was informed that tenants will get rental

 Tenants wanted to know what type assistance to value be given by the project  Residential BPL squatter will get EWS

 Squatters wanted alternative site and assistance. house & shifting and subsistence allowance, and commercial BPL squatter will get 10x15  Participants was demanding proposed road

13 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Section Details Issued Raised Response of project Authority width has to be restrict in the village limit site and shifting & subsistence allowance

 Participants wants to know after completion of  Wherever the more structures will getting new road construction the Govt. will make toll affected in the village limit road width have collection or not already restricted In this matter the Government will take decision M7C&D Date: 13-01-2009  Squatters wanted alternative site and assistance.  Residential BPL squatter will get EWS

Place: Hanagal  Tenants wanted to know what type assistance to house & shifting and subsistence allowance, and commercial BPL squatter will get 10x15 No. Of be given by the project Participants: 185 site and shifting & subsistence allowance  Land losers wanted to land compensation in present market rate value  It was informed that tenants will get rental Hanagal town shopkeepers (squatters) don’t want value road widening, they said, in the Hanagal town limit the existing road was already widened with median  The demand for compensation at market and had pucca foot path. According them it is rates could be taken care by the KHA through enough for vehicle movement. the process of negotiation  It was informed that project will looked into the matter T21 Date: 07-01-2009  Squatters wanted alternative site and assistance.  Residential BPL squatter will get EWS

Place: Salur  Land losers wanted to land compensation in house & shifting and subsistence allowance, and commercial BPL squatter will get 10x15 No. Of present market rate Participants were strongly Participants: 35 opposed widening of road in the Salur village limit, site and shifting & subsistence allowance because last year only PWD people demolished their  The demand for compensation at market road side buildings and constructed new drain. Some rates could be taken care by the KHA through of the disturbed householders still under the process of negotiation

constructing of their half portion demolished  Regarding road widening project officials structures. In the meanwhile again the same will take the decision during implementation. structure demolition is not possible. In case the

Govt. will interest make new road participants  All the community Assets and public demanded Bypass road for Salur village. utilities will shift before commencing of  Asked for relocation of community assets and civil work. public utilities.

14 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

IV. IMPLEMENTATION MECHANISMS

Institutional Arrangements 32. This chapter outlines the implementation mechanism specifically for this package, including the tasks of the NGO and the GRC. It also outlines the assistance to be paid to affected persons and provides the tasks to be completed before the start of civil works. 33. The SDRC PIU will facilitate land acquisition and compensation, relocation and resettlement, distribution of assistance for the PAPs. The SDRC is responsible for monitoring the implementation of all resettlement and rehabilitation activities, including land acquisition. WAP 3 will be implemented by KHSIP Division, Shimoga. The SDO and SWIs appointed for the division will take care of R&R activities of this package. The SDRC will be supported by the NGO for implementation of RAP. Extending R& R Assistance to PAPs 34. R& R assistance will be disbursed according to the R&R Policy. The NGO will verify the PAPs and ensure that they get the assistance in accordance with their entitlements. The entitlements given here are accurate as far as possible; however, because only preliminary notification for land losers has been given at this stage, the exact details about entitlements need to be updated at the time of paying R&R assistance. The cash allowances are updated for 2012-13 and will be further adjusted as needed for 2013-14 and beyond. The exact number of disbursements made for each year will be computed after all assistance is given. The annually revised amounts are mentioned in the Implementation Manual. . Table 4- 1: R& R Assistance Entitlement Category of loss Entitlement Category 1a 1104 PAF losing  Negotiation as per Karnataka State Highway Act, 1964; land  Amount equivalent to current stamp duty and registration charges on compensation amount;  **Additional 25% compensation in case remaining land is severed;  Crop/tree damage compensation as assessed by concerned Departments;  *In case land owners becomes landless or marginal families, the following additional entitlements will be offered: (a) subsistence allowance of Rs. 36,300 for land less and marginal; and, (b) assistance for creating Income generation asset valued upto Rs.90,750 for those becoming marginal farmers and landless only;  Additional amount of Rs.24,2001 will be restricted to those who loose narrow stretch of land as additional compensation in lieu of

1 Narrow stretch of land is defined as persons losing upto 5 guntas of land. *These entitlements will be applicable only when the farmers submit the landholding/ marginal farmer document, and if found applicable. ** This will be verified after Section 19.

15 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Entitlement Category of loss Entitlement Category all other benefits. Additional amount of Rs 24,200 to those who lose more than a narrow stretch and are not eligible for any other additional benefits.  *For those becoming landless and all marginal farmers training assistance will be provided for income generating vocational training and skill upgradation options as per affected persons choice ;  Employment opportunity for affected persons as per his skills and availability of suitable work in road construction work. Ib 22 owners losing  Compensation at current PWD scheduled rates without total residential depreciation and 30% solatium 2 structure  Alternative houses in resettlement colony or developed plot and construction cost of Rs. 60,000 linked to construction progress.  Shifting assistance of Rs. 12,100  Subsistence allowance of Rs. 36,300 1b 141 owners losing  Compensation at current PWD scheduled rates without partial residential depreciation and 30% solatium structures  Additional 25% compensation for partially affected structures towards reconstruction Ic 23 owners losing  Compensation at current PWD scheduled rates without commercial depreciation and 30% solatium structure  Alternative shop or assistance for income generation asset valuated upto Rs. 90,750  Shifting assistance of Rs. 12,100  Subsistence allowance of Rs. 36, 300 1d 1 owners losing  Compensation at current PWD scheduled rates without residential cum depreciation and 30% solatium. commercial  Alternative shop or assistance for income generation asset structure valuated upto Rs. 90,750 or Alternative houses in resettlement colony or developed plot and construction cost of Rs. 60,000 linked to construction progress.  Shifting assistance of Rs. 12,100  Subsistence allowance of Rs. 36,300  Additional amount of Rs. 30,250 as grant. 1c 76 owner PAFs  Compensation at current PWD scheduled rates without losing partial depreciation and 30% solatium commercial  Additional 25% compensation for partially affected structures towards reconstruction

1d 31owner PAFs  Compensation at current PWD scheduled rates without losing partial depreciation and 30% solatium commercial cum  Additional 25% compensation for partially affected structures residential towards reconstruction

structure 1 10owners losing  Compensation at current PWD scheduled rates without other partial assets depreciation and 30% solatium 1 4 owners losing  A grant of Rs. 18,150 for replacement of Cattle shed; cattle shed

2 Developed plot will be restricted to those who do not have any homestead land.

16 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Entitlement Category of loss Entitlement Category II b 101 tenants losing  Rental allowance for 6 months @ Rs. 1,210 per month in rural commercial  Shifting assistance of Rs. 12,100 structure  Assistance for income generation asst up to Rs. 90,750 IIa 2 tenants losing  Rental allowance for 6 months @ Rs. 605 per month in rural and residential Rs. 1210 in urban areas structure  Shifting assistance of Rs. 12,100 IIIa 1 Squatter s losing  House in resettlement colony or developed plot and construction residential cost of Rs. 40,000 linked to construction progress. structure  Subsistence allowance of Rs.18,150;  Shifting Allowance of Rs.6050. IIIb 23 Squatter losing  Alternative shop of 100 sq.ft or assistance for income generation commercial asset valuated upto Rs. 36,300 structures  Subsistence allowance of Rs.18,150  Shifting Allowance of Rs.6050

Implementation support by NGOs 35. The work of the NGO will include consultations and counseling of PAPs, encouraging PAPs for productive utilization of compensation and rehabilitation grants, facilitating PAP access to income generating assets, increasing the social acceptability, ensuring effectiveness of training programs organized for PAPs electing participation in self employment schemes etc. 36. The NGO will work as a link between the PIU - SDR Cell and the affected community. For this section the NGO is: STEM (Centre for Symbiosis of Technology Environment Management). The division office of this NGO is located in Shikaripura. They will educate the PAPs on the need to implement the Project, on aspects relating to LA and R&R measures and ensure proper utilization of various compensations extended to the PAPs under the R&R entitlement package. The tasks of the NGO will be to facilitate the resettlement process. The responsibilities of the NGOs include 1. Identification, verification and updating of PAP Census, includes verification of properties of PAPs and estimation of their type and level of losses; 2. Educate PAPs on their rights, entitlements, and obligations under the RAP; Assist the PAPs to identify suitable alternate land for resettlement purposes; 3. Preparation and Distribution of Entitlement cum Identity Card. All eligible project affected families will be issued Identity Cards, giving details of the type of losses and type of entitlements. 4. Ensure that PAPs receive their full entitlements; Where options are available, the NGO will provide advice to PAPs on benefits of each option; Ensure proper utilization by the PAPs of various compensations available under the R&R package; Assist the PAPs in getting benefits from various government development programs; 5. Rehabilitation of Affected Families and restoration of Income and Livelihood. The NGO will help the communities derive maximum benefits out of the project without losing their livelihoods and the least impact on socio-cultural aspects of their lives. 6. Assist PAPs on grievance redressal through the established system; and

17 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

7. Will relocate PAPs. Assist PIU in making arrangements for the smooth relocation of the PAPs; No Physical relocation from agriculture land, residential units, commercial establishments or other immovable properties will begin before alternate arrangements are made. 8. Any other responsibility that may be assigned by the PIU for the welfare of the affected communities. 37. In order to carry out the above tasks, NGO staff will be stationed in the site office in Shimoga. Besides contacting the PAPs on an individual basis to regularly update the baseline information, group meetings and village-level meetings will be conducted by the support agency on a regular basis. The frequencies of such meetings will depend on the requirements of the PAPs but should occur at least once a month. The support agency will have to encourage participation of individual APs in such meeting by discussing their problems regarding LA, R&R and other aspects relating to their socio-economic lives. Such participation will make it easier to find a solution acceptable to all involved. IR Activities 38. There are two types of IR activities, i.e. short term and long term. Process of identifying income generating options for those losing commercial structures/ livelihood is under progress. 39. Short Term IR activities: Short-term IR activities mean restoring APs’ income during periods immediately before and after relocation. For this, the NGO shall ensure that: compensation and R&R assistance as provided in the entitlement matrix such as subsistence allowance and shifting allowance are provided to the PAPs. Other works of the NGO include facilitating employment to the PAPs in the project construction activities, depending on their skill and other allied activities. 40. Long Term IR Activities: This includes provision of shops for those losing their total livelihood to re-establish their commercial activities. It also includes providing of a shop plot in a commercial block or purchase of income generating assets upto Rs.36,300 in case of commercial squatters.

41. The steps to be followed for income restoration include:

Step 1: Identification of Target Groups – NGOs need to identify the affected persons; Step 2: Identification of IR Activities - Prepare a list of possible and feasible income restoration options. While identifying IR options, the following factors shall also be considered: (i) Education level of APs; (ii) Skill possession;(iii)Likely economic activities in the post displacement period; (iii) Extent of land left; (iii) Suitability of economic activity to supplement the income; (iv)Market potential and marketing facilities. Based on socio-economic characteristics and options preferred by APs, the NGO may have to re-assign trades to PAPs. Options include (i) petty trade (iii) skill related schemes and loans for pumps, bore wells, bullock carts etc to increase productivity. The NGO will assist PAPs in identifying appropriate alternative economic rehabilitation schemes through counseling and consultation. Step 3: Training: Option for training for skill enhancement for those losing their livelihood has been provided in the Entitlement Matrix for owners losing commercial structure and employees losing their livelihood.

18 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Step 4: Identification of Trainers / Training Institutes: Based on trades selected, NGO shall have to identify master trainer and/or training institute for different trades / activities who can provide on the job training. Step 5: Training Arrangement: NGO shall make different groups of PAPs as per trades selected and make all the arrangements such as fixing the venue etc. Step 6: Monitoring of APs: After training the NGO shall monitor the PAPs in order to take mid-term correction measures, if required.

Monitoring and Evaluation support for RAP 42. An external monitoring and evaluation agency, Samaj Vikas, has been appointed to concurrently monitor and evaluate R&R activities on periodical basis with NGOs. The role of such an agency will facilitate process of R&R and thus provide support in the proper implementation of rehabilitation programmes. And the M&E Consultant will ensure and certify that the stretch is free from all encumbrances related R&R measures at every stage prior to issue of bids, prior to signing concession agreement, prior to appointed date and prior to hand over the second milestone stretches to the developer. The end evolution will be carried out through independent consultant not associated with the implementation to verify as to how the R&R objectives are realized and the changes in the living conditions of the PAPs which will be compared with the baseline data on key impact indicators related to income, occupation, assets, housing conditions, land ownership pattern, etc. Grievance Redressal mechanism 43. The project will establish a Grievance Redressal process with district-level committees. The following persons constitute the District Level Grievance Redressal Cell :

1. Deputy Commissioner of the District – Chairman 2. Academician (to be selected by the DC) – Member 3. Representative from PAPs (to be selected by the DC) – Member 4. Divisional EE – Convener The members of the GRC to be selected by the DC and representatives from the PAPs are under progress and will be completed by 30th June 2012.

44. The main functions of the GRC will be:

a. to provide support to PAPs on problems arising out of eligibility for RAP-provided entitlements and assistance provided; b. to record the grievances of the PAPs, and categorize, prioritize and solve them within one month; c. to inform PIU of serious cases within one week; and d. to report to the aggrieved parties about the developments regarding their grievance and decisions of the PIU, within one month. 45. The Grievance Committees will meet regularly during implementation of the RAP, at least once a month. The committees will suggest corrective measures at the field level itself and fix

19 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

responsibilities for implementation of its decisions. However the NGOs will form the first level of intervention in resolving PAP related grievances and attempt to motivate the PAP to facilitate implementation of the R&R program. Details regarding registering complaints, response times, communication modes, and mechanisms for appeal or approaching civil courts if other provisions fail are: 1. At the first level intervention the NGO will attempt to resolve the grievance; 2. Next the CAO will attempt to address land related grievance and the ADSW will address the non- land related grievances; 3. The third step will be to approach the Grievance Redressal Committee; 4. Next the PAP can approach the Regional Commissioner who is the Appellate Authority. 5. If all the above fails, the PAPs can approach the court. It is the responsibility of the SDRC/NGO to inform the affected person’s decisions of the GRC to make it effective. Resettlement Colonies and Vendor Markets 46. In this package there is no requirement for resettlement colony, as more than 20 families are not losing their residential structure in this stretch. Protection of RoW 47. Section 5 of the KHA mentions the Highway Authority will exercise power and discharge duties in accordance with provisions of the KHA for restriction of ribbon development along the highways and for prevention and removal of encroachments. The Highway Authority under Section 7 has power to fix boundary of building and control lines of highways. Section 21 mentions prevention of unauthorized occupation of highway. Thus the onus of protecting the COI/RoW lies with the Project Authority. Once the COI/Row has been identified and frozen, the COI/RoW has to be clearly marked with boundary stones.

48. Any new encroachment into the area will be monitored by the concerned KSHIP Division. The Divisional Engineers shall visit the project roads periodically, at least once in three months, in order to ensure that no new encroachments take place and submit quarterly reports in this regard. To avoid future encroachments, it is proposed to construct drains at the edge of ROW and ROW stones will also be laid.

49. The NGOs shall take photographs of the affected structures at the time of Joint Verification and also after their shifting / demolition of the affected portion and prepare documentation of structures.

50. Those Non-titleholders already identified by the project will be issued Identity Cards by the PIU. All new encroachers / squatters not present during the time of survey, will have to be verified by the NGO/PIU. All squatter and encroachers have to be shifted from out of the COI and RoW. Those who remain in the Row will not be eligible to entitlements.

20 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Impacts on Municipal Towns

51. Verification for non-titleholders has already been completed on this package. All the persons identified at the time of survey and verified by the NGOs at the time of joint verification but subsequently shifted by the Municipalities will be extended assistance as per the RAP.

52. KSHIP shall address all the Municipalities in the Project Roads informing them of the Rehabilitation and Resettlement Policy of the Government under KSHIP-II and the details of persons identified as Project Affected Persons in their jurisdiction. If the Municipality wants to shift any of them for their development works, they may do so after providing them assistance as per the R&R Policy of the Government or inform the details of such persons to KSHIP for extending assistance under the project

53. In this package the project road passes through the Municipality areas of Shikaripura and Hanagal. It also passes through the Corporation limits of Shimoga. All these Municipalities and City Corporation will be addressed informing them of the Rehabilitation and Resettlement policy of Government under KSHIP-II project and the details of the persons identified as ‘Project Affected Persons’ in their respective jurisdiction. In case the Municipalities / Corporation desire to shift any of the Project Affected Person on account of development work, they may do so after providing assistance to them as per the R&R Policy of Government or inform the details of such displaced persons to KSHIP for extending assistance to them under the project.

Data Base Management 54. The database generated will be used for tracking progress of this package by PIU. The data in the HQ will be updated based on the information sent by the division office. PIU will be responsible for tracking payments, generation of ID cards etc through the Data Base Management Consultants. The socio-economic data for all PAPs are recorded in the database and will be used for monitoring and impact evaluation and other purposes. Co –ordination between R&R and Civil works 55. The resettlement program will be co-coordinated with the timing of civil works. The Civil works for this package is expected to start in December 2012. R&R and land acquisition is estimated to be completed by August 2012. Under the Annuity Packages all land has to be handed over at one stage. This will be after issue of Notification under Section 19 of KHA. The timeline for key activities is given below. 56. The implementation of RIP will be performed in coordination with the procurement process and civil works. The key milestone in the process includes issue of bids, signing of concession agreement, appointed date and handing over of second milestone stretches within 3 months of appointed date. The various land acquisition and resettlement implementation actions to be completed prior to those milestones which are listed below with respective target dates. The completion of these actions will be certified through certification and confirmation by the M&E consultant.

21 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Table 4- 2: Time line for Key LA and R & R Activities Tasks Target Date Prior to Event I Land Acquisition Land Acquisition Plans Section 15 Notification (first June 2012 Issue of bids notification) Section 27 (negotiation ) August, 2012 Signing of concession agreement Section 28(award declaration) September, 2012 Appointed Date Notification Section 19 Possession of land December, 2012 Appointed Date Section 39 (compensation offer and November 2012 Appointed Date payment ) Transfer/ No objection received for October 2012 Appointed Date Government land

II R&R Implementation activities PIU Approval and Disclosure of Mid June 2012 Issue of bids RIP Completion of additional joint 31-5-2012 Signing concession verification for identification of agreement additional PAPs Issue of ID cards 30-6-2012 Issue of bids Constitution of GRCs 30-6-2012 Signing concession agreement Completion of structure valuation 31-5-2012 Signing of concession agreement Relocation of Community assets November, 2012 Appointed Date completed Identification of alternative sites October , 2012 Signing Concession and options agreement Disbursement of assistance October, 2012 Appointed Date Completion of allotment of November, 2012 Appointed Date developed Sites and first installment of construction grant

III Resettlement Relocation of PAPs March, 2013 Handing over second mile stone stretches Handing over of CPRs to Novemenbr,2012/March, Appointed Date/Second community 2013 mile stone stretches Certification by M&E consultants As needed Prior to each event for site readiness

22 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Joint Inspection of site : Prior to appointed date, representatives of KSHIP and Developer will be undertaken a joint site visit to ascertain the encumbrance free site on the ground and record any encumbrance noticed and accordingly a time frame for mitigating those encumbrances within the agreed time frame and accordingly measures will be taken to mitigation encumbrances

Monitoring and R&R Activities 57. The R&R Monitoring indictors for physical progress are given in the table below.

Table 4-3: Monitoring Indicators for Physical Progress % against Implementa Revised Progress Cumulati Sl. Monitoring Indicators for Physical Revised tion Target Implementati This ve No Progress Implementati Nos on Target Month Progress on Target 1 Land Acquired- private 90.08 ¼

2 Land transferred – Government 24.14 ½

3 PAFs paid compensation for land 1104 Construction cost for residential

owners 22 Construction cost for residential 4 squatters 1 Alternative plot or IGA for owner

commercial 23 Alternative plot or IGA for 5 Commercial squatter 22 6 Subsistence allowance for squatters 23 7 Shifting allowance for squatters 23 8 Community Assets 223

Additional Impacts 58. Any additional impacts identified during the implementation will be considered in accordance with RAP and the project entitlement matrix given therein. Any observation on additional impacts will be forwarded by the Division to the PIU. The NGO will follow up the matter in the field. A note will be prepared for the concurrence of the CPO. Budget 59. The budget for land acquisition and R&R activities for this package is Rs.16.26 crores which forms a part of the overall budget approved by the GoK. The details of the budget have been given in the RAP. Any additional budget need, will be obtained through additional approvals. Table 4- 4: Budget Sl. No Category Total (INR) 1. Land Acquisition 94130000 2. Alternative site cost 9910000 3. Structure cost 5143146

23 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

4. R&R assistance 53594000 WEP 4 total 162677146

Disclosure 60. The RIP will be disclosed on the KSHIP website and the document will be available in PIU HQ and the respective PIU division office at Belgaum, and Taluk offices of Mudhol and Chikkodi. General consultations will also be done for the package and documented and recorded. As part of disclosure of RIP, public consultations will be held at important locations to explain the contents of RIP and make them understand the process of implementation of RAP and also information about whether the document and the list of PAPs will be available for their information. The details of grievance redress process will also be explained. In addition, the periodical progress reports and other studies carried out in relation to R&R will also be disclosed in the website.

24 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Annexure 1 Guidance Value as on August 2011 Table 4- 5: Guidance Value for Link M7A

Dry Land Wet Land Garden Land Sl. No. District Taluk Village Name Minimum Maximum Minimum Maximum Minimum Maximum 1 Shimoga Shimoga Mullakere NA 2 Shimoga Shimoga Navali NA 3 Shimoga Shimoga Channmumbapura NA 4 Shimoga Shimoga Matthodu NA 5 Shimoga Shimoga Abalageri NA 6 Shimoga Shimoga Kommanala NA 7 Shimoga Shimoga Bikkavvanahalli NA 8 Shimoga Shimoga Beeranakere NA 9 Shimoga Shimoga Kunchenahalli NA 10 Shimoga Shimoga Kallapura NA 11 Shimoga Shimoga Suttukote NA 12 Davangere Honnali Savalanga 53000 83000 120000 260000 340000 13 Davangere Honnali Machigondanahalli 43000 63000 100000 235000 280000 14 Davangere Honnali Chinnakatte 43000 63000 100000 235000 280000 15 Davangere Honnali Bidarahalli 38000 73000 95000 235000 280000 16 Davangere Honnali Shiddapura 33000 58000 90000 235000 280000 17 Davangere Honnali Joga 43000 63000 100000 235000 280000 18 Davangere Honnali Belalakatte 38000 63000 95000 235000 280000 19 Shimoga Shikaripura Attibailu 40000 55000 80000 175000 290000 20 Shimoga Shikaripura Harogoppa 35000 55000 75000 150000 250000 21 Shimoga Shikaripura Yarakatta 30000 45000 75000 100000 180000 22 Shimoga Shikaripura Tharlagatta 40000 60000 95000 160000 260000 23 Shimoga Shikaripura Nandihalli 40000 65000 80000 160000 270000 24 Shimoga Shikaripura Thimalapura 60000 90000 120000 210000 260000 25 Shimoga Shikaripura Dhupadahalli 58000 110000 130000 170000 290000 Haliyuru 26 Shimoga Shikaripura (Shikaripura) 80000 125000 150000 200000 275000

25 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Table 4-6: Guidance Value for Link M7B

Dry Land Wet Land Garden Land Sl. No. District Taluk Village Name Minimum Maximum Minimum Maximum Minimum Maximum 1 Shimoga Shikaripura Kanoor 95000 100000 145000 190000 300000 2 Shimoga Shikaripura Gabbur 90000 100000 135000 200000 270000 3 Shimoga Shikaripura Kotta 40000 45000 75000 150000 290000 4 Shimoga Shikaripura Kutrahalli 40000 45000 100000 150000 260000 5 Shimoga Shikaripura Jakkanahalli 40000 45000 110000 160000 230000 6 Shimoga Shikaripura Punedahalli 38000 48000 85000 140000 240000 7 Shimoga Shikaripura Bhadhrapura 35000 40000 75000 160000 240000 8 Shimoga Shikaripura Udugani 40000 50000 65000 150000 230000 9 Shimoga Shikaripura Thadagani 40000 45000 80000 130000 210000 10 Shimoga Shikaripura Shiralakoppa 70000 80000 110000 200000 320000 11 Shimoga Shikaripura Belagavi 40000 50000 75000 150000 230000 12 Shimoga Shikaripura Devikoppa 35000 40000 75000 140000 210000 13 Shimoga Shikaripura Idakina Hosakoppa 35000 40000 65000 140000 220000 14 Shimoga Shikaripura Thogarshi 40000 48000 75000 140000 230000 15 Shimoga Shikaripura Thandagunda 35000 40000 70000 115000 190000 16 Shimoga Soraba Kanukoppa 53000 55000 75000 82000 17 Shimoga Soraba Tathuru 54000 55000 66000 78000 18 Shimoga Soraba Negavadi 52000 55000 65000 75000 19 Shimoga Soraba Nellikoppa 55000 58000 66000 78000 20 Shimoga Soraba Chikka Idagodu 55000 66000 78000 21 Shimoga Soraba Hunasavalli 52000 55000 64000 74000 22 Shimoga Soraba Talluru 55000 58000 66000 78000 23 Shimoga Soraba Anavatti 55000 80000 88000 95000

Table 4-7: Guidance Value for Link M7C

Dry Land Wet Land Sl. No. District Taluk Village Name Minimum Maximum Minimum Maximum 1 Shimoga Soraba Anavatti 55000 80000 88000 95000 2 Shimoga Soraba Devastanada Hakkalu 55000 58000 66000 78000 3 Shimoga Soraba Neralige 55000 58000 66000 78000 4 Shimoga Soraba Agasanahalli 52000 55000 65000 78000 5 Shimoga Soraba Bommarashikoppa 55000 66000 78000 6 Haveri Hanagal Gondi 45000 55000 65000 85000 7 Haveri Hanagal Hirekanshi 45000 55000 65000 80000 8 Haveri Hanagal Makaravalli 45000 55000 65000 80000 9 Haveri Hanagal Kondoji 45000 55000 65000 80000

26 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Dry Land Wet Land Sl. No. District Taluk Village Name Minimum Maximum Minimum Maximum 10 Haveri Hanagal Mudur 45000 55000 65000 80000 11 Haveri Hanagal Makoppa 45000 55000 65000 80000 12 Haveri Hanagal Baluru 45000 55000 65000 80000 13 Haveri Hanagal Gejjihalli 50000 60000 70000 85000 14 Haveri Hanagal Girisinakoppa 50000 60000 70000 85000 15 Haveri Hanagal Hanagal (Halekoti) 80000 85000 95000 100000

Table 4-8: Guidance Value for Link T21

Dry Land Wet Land Garden Land Sl. No. District Taluk Village Name Minimum Maximum Minimum Maximum Minimum Maximum 1 Shimoga Shikaripura Kanoor 95000 100000 145000 190000 300000 2 Shimoga Shikaripura Gabbur 90000 100000 135000 200000 270000 3 Shimoga Shikaripura Kalenahalli 42000 55000 110000 170000 280000 4 Shimoga Shikaripura Gama 50000 60000 120000 190000 260000 5 Shimoga Shikaripura Salur 45000 50000 125000 165000 255000 6 Shimoga Shikaripura Hariharapura 35000 40000 75000 110000 200000 7 Shimoga Shikaripura Ambligolla 40000 43000 95000 180000 295000 8 Shimoga Sagara Bairapur 43500 62500 331000 373500 9 Shimoga Sagara Gouthamapur 58000 68500 457000 497000 10 Shimoga Sagara Kannur 56500 71000 581000 662500 11 Shimoga Sagara Malandur 47000 157500 365000 415500

27 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Annexure 2: Details of PAFs of Link T21 Table 4-9: Details of PAFs T21

Sl. Chainage Side Village Name Occu. Status Loss Type No.

Sabjaansab S/o 1 0.350 RHS Shikaripura Owner Residential Budensab Ismailsab S/o 2 0.375 RHS Shikaripura Legal Tenant Commercial Husainsab Ameer V J S/o Abdul 3 0.378 RHS Shikaripura Legal Tenant Commercial Jabbarsab Gauspeer S/o 4 0.380 RHS Shikaripura Owner Residential/Commercial Gareebsab Jagadish S/o K 5 1.010 LHS Shikaripura Owner Residential Shekarappa

6 5.190 LHS Chunchinakoppa Bojaraj S/o Jayappa Owner Residential/Commercial

Jayamma W/o 7 5.225 RHS Chunchinakoppa Owner Residential Narayan Rao 8 5.275 RHS Chunchinakoppa Yogesh S/o Veerappa Owner Residential Shivamurthaiah S/o 9 8.060 RHS Solur Owner Residential Chennaiah Gangadharappa S/o 10 8.080 RHS Solur Owner Commercial Sadashivappa M P Sugandappa S/o 11 8.110 LHS Solur Owner Residential Palakshappa Kashi Vishwanath S/o 12 8.120 LHS Solur Owner Residential Palakshappa Basavarajappa S/o 13 8.143 LHS Solur Owner Residential Gowri Holeyappa Basavarajappa S/o 14 8.220 RHS Solur Owner Residential/Commercial Bojappa H Kumar S/o 15 8.225 RHS Solur Owner Residential Holebasappa Basavanagowda S/o 16 8.280 RHS Solur Owner Cattle Shed Basavanyappa Ravi Kumar S/o 17 8.348 RHS Solur Owner Residential Mahadevappa

18 11.180 LHS Chikkapura Naganna S/o Halappa Owner Residential

Nanjamma W/o 19 11.205 LHS Chikkapura Owner Residential Erappa Huliyappa S/o 20 11.963 RHS Kanasogi Owner Residential Paramanna Basavaraj S/o 21 12.165 RHS Kanasogi Owner Residential Revanappa

28 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Sl. Chainage Side Village Name Occu. Status Loss Type No.

Mahabala Shetty S/o 22 13.200 LHS Ambligola Owner Residential/Commercial Sheshanna Shetty Mohammad Ali S/o 23 13.210 LHS Ambligola Owner (O),Projection Mohammad Budensab Yakubsab S/o 24 13.370 LHS Ambligola Owner Commercial Andakunni Munnavarsab S/o 25 13.400 LHS Ambligola Owner Residential Aarunsab Munnavarsab S/o 26 13.410 LHS Ambligola Legal Tenant Residential Aarunsab Munnavarsab S/o 27 13.413 LHS Ambligola Owner Residential/Commercial Aarunsab Attar Najeersab S/o 28 13.450 LHS Ambligola Owner Residential Shekh Fareed Jameed Ahmad S/o 29 13.455 LHS Ambligola Owner Residential Nabisab Ahmad Sharif S/o 30 13.459 LHS Ambligola Owner Residential Nabisab Anwarsab S/o Nazeer 31 13.463 LHS Ambligola Owner Residential Basha Iqbal Baigh S/o 32 13.470 RHS Ambligola Owner Residential Mardan Baigh Yusuf S/o Abeed 33 13.510 LHS Ambligola Owner Residential Sharif Mehaboobsab S/o 34 13.545 LHS Ambligola Owner Residential Rasoolsab Yusuf Ali Khan S/o 35 13.550 LHS Ambligola Owner (O),Projection Husain Khan Mohammad Sharif S/o 36 13.550 LHS Ambligola Owner (O),Projection Mohiddinsab Munafsab S/o 37 13.580 LHS Ambligola Owner Residential Chamansab Mohammad Bashasab 38 13.580 RHS Ambligola Owner Residential S/o Madarsab Ataulla S/o 39 13.583 LHS Ambligola Legal Tenant Residential/Commercial Chamansab Gaussab S/o 40 13.595 LHS Ambligola Owner Residential Chamansab Pyareejaan W/o 41 13.596 LHS Ambligola Owner (O),Projection Shabbir Ahmad

42 13.700 RHS Ambligola Vacant House Owner Residential

Mahadevamma W/o 43 14.860 RHS Hosur Owner Residential Late Shivanna Manjappa S/o 44 15.208 RHS Hosur Owner (O),Bathroom Kannappa

29 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Sl. Chainage Side Village Name Occu. Status Loss Type No.

Peersab S/o 45 21.200 RHS Peerana Kanive Owner Residential Mohammadsab Bhavanamma W/o 46 24.080 LHS Gauthampura Owner (O),Projection Late Shankara Rao

47 25.390 RHS Narasipura Ravi S/o Manjappa Owner Residential/Commercial

Manjamma W/o Late 48 26.892 LHS Taligere Owner Residential Nagappa Manjunath S/o 49 27.145 RHS Kannur Owner Residential Thimmaiah Vasudevappa S/o 50 27.168 LHS Kannur Owner (O),Pump House Kappa Naik Annamma W/o Late 51 28.302 RHS Kannur Owner Residential Krishnappa B N Ramachandraiah 52 29.210 RHS Malandur Owner Residential S/o Narayanapa Subramanya (Tamil 53 30.230 LHS Malandur Owner Commercial Nadu)

54 30.885 RHS Malandur Mahadevamma Legal Tenant Residential

Sadhu Pujari S/o 55 30.906 LHS Malandur Owner Residential Chandu Pujari

56 30.910 LHS Malandur Mahadevamma Owner Commercial

57 30.928 LHS Malandur Lokesh S/o Ranganath Owner Residential/Commercial Basavaraj S/o 58 30.945 RHS Malandur Owner Residential/Commercial Thulajappa Jayamma W/o 59 30.951 RHS Malandur Owner Commercial Narayanappa

60 30.963 RHS Malandur Yellappa S/o Halappa Owner Residential

Somanna S/o 61 31.560 LHS Dasanakoppa Owner Residential Lakshmaiah Nanjamma W/o 62 31.750 LHS Dasanakoppa Owner Residential Appanna Fayaz Ahmad S/o 63 31.935 LHS Dasanakoppa Owner Residential Basheer Ahmad B Hucchappa S/o 64 32.075 RHS Dasanakoppa Owner (O),Projection Basappa Masthappa S/o Sanna 65 32.262 RHS Dasanakoppa Owner Commercial Manjappa

30 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Annexure 3: PAF Details of Link M7A Table 4- 30: PAF Structure details of link M7A (Shimoga - Shikaripura) Sl. Chainage Side Village Name Occu. Status Loss Type No. 1 0.320 LHS Shimoga G Murgyappa Legal Tenant Commercial D R Keshav S/o D N 2 0.330 LHS Shimoga Owner Commercial Ramachandrappa D R Keshav S/o D N 3 0.332 LHS Shimoga Legal Tenant Commercial Ramachandrappa 4 0.420 LHS Shimoga Prasad S/o Thirthappa Owner Commercial K R Bharathi W/o Late 5 0.600 RHS Shimoga Owner Commercial Ramesh R R Rudrappa S/o R T 6 0.650 LHS Shimoga Owner Commercial Rangappa 7 0.670 LHS Shimoga Venkatesh S/o Vasudev Owner Commercial S P Devaraj S/o Late A D 8 0.940 LHS Shimoga Owner Boundary Wall Das 9 0.940 LHS Shimoga Devaraj Legal Tenant Commercial 10 0.945 LHS Shimoga Devaraj Legal Tenant Commercial 11 0.948 LHS Shimoga Devaraj Legal Tenant Commercial 12 0.950 LHS Shimoga Devaraj Legal Tenant Commercial President, Vidya 13 0.960 RHS Shimoga Owner Commercial Samsthe 14 0.960 RHS Shimoga Nandi Vidya Samsthe Legal Tenant Commercial 15 0.96 RHS Shimoga Nandi Vidya Samsthe Legal Tenant Commercial President Nandi Vidya 16 0.960 RHS Shimoga Legal Tenant Commercial Samsthe President Nandi Vidya 17 0.96 RHS Shimoga Legal Tenant Commercial Samsthe President Nandi Vidya 18 0.960 RHS Shimoga Legal Tenant Commercial Samsthe President Nandi Vidya 19 0.960 RHS Shimoga Legal Tenant Commercial Samsthe Armugam S/o D M 20 0.975 LHS Shimoga Owner Commercial Govindaswamy 21 1.020 RHS Shimoga Lakshmi Darshini Hotel Owner Commercial Channappa S/o 22 1.080 LHS Shimoga Owner Commercial Mahadevappa Basavaraj S/o Residential/Com 23 1.100 LHS Shimoga Owner Vamadevaiah mercial Veerabhadrappa S/o 24 1.140 LHS Shimoga Owner Commercial Mallikarjunappa Tippaiah S/o N C 25 1.147 LHS Shimoga Owner Commercial Shivashankarappa 26 1.150 LHS Shimoga Basavaraj S/o Tippeswamy Owner Commercial

31 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Sl. Chainage Side Village Name Occu. Status Loss Type No. 27 1.210 LHS Shimoga N S Shalimaji & Sons Owner Residential 28 1.228 RHS Shimoga Mahendra S/o Basappa Legal Tenant Commercial 29 1.232 RHS Shimoga Mahendra Legal Tenant Commercial 30 1.236 RHS Shimoga Latha W/o Sunil Owner Commercial 31 1.244 RHS Shimoga Rajappa S/o Siddappa Owner Commercial Dr. Shivaraj Vard S/o 32 1.260 LHS Shimoga Owner Commercial Chennabasappa 33 1.520 RHS Shimoga Narayanappa Owner Commercial 34 1.960 LHS Navile Krishnappa S/o Mallappa Owner Residential 35 1.967 LHS Navile Mohan S/o Durugappa Legal Tenant Commercial 36 1.971 LHS Navile Mohan S/o Durgappa Legal Tenant Commercial 37 1.975 LHS Navile Mohan S/o Durgappa Legal Tenant Commercial Sarojamma W/o Late Residential/Com 38 1.976 LHS Navile Owner Papanna mercial 39 2.020 LHS Navile Hulagappa S/o Hucchappa Owner Commercial

40 2.040 LHS Navile Ramappa S/o Maradappa Owner Residential

Saraswathi W/o Late 41 2.050 RHS Navile Owner Commercial Chandra Prakash Shetty 42 2.058 RHS Navile Vijay Kumar Legal Tenant Commercial Manjunath S/o Residential/Com 43 2.060 LHS Navile Owner Hanumanthappa mercial Vijay Kumar S/o Chandra 44 2.063 RHS Navile Owner Residential Shekaraiah H N Ramesh S/o H D 45 2.080 RHS Navile Owner Commercial Nanjappa K H Beerappa S/o Residential/Com 46 2.124 RHS Navile Owner Hanumanthappa mercial Shadakharappa S/o Residential/Com 47 2.190 RHS Navile Owner Veerappa mercial 48 2.225 LHS Navile Revanna S/o Giddappa Owner Commercial Shadaksharappa S/o 49 2.230 RHS Navile Owner Residential Beeranna Murthy S/o 50 2.235 RHS Navile Owner Residential Ningappa Dillyara 51 2.240 RHS Navile Call Refused Owner Residential 52 2.245 LHS Navile Papanna S/o Rangappa Owner Commercial Residential/Com 53 2.250 LHS Navile Bharathraj S/o Tontaradhya Owner mercial 54 2.264 LHS Navile Thimmaraj Owner Residential 55 2.269 LHS Navile Annappa S/o Thimmanna Owner Residential 56 2.540 RHS Navile Siddappa S/o Ramappa Owner Residential 57 2.560 RHS Navile Chandrashekar Owner Commercial

32 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Sl. Chainage Side Village Name Occu. Status Loss Type No. 58 2.720 RHS Navile Susheela W/o Mani Owner Residential Kuppamma W/o 59 2.728 RHS Navile Owner Commercial Dharmanna Residential/Com 60 2.760 RHS Navile Navulappa Legal Tenant mercial 61 2.765 RHS Navile Navalappa Owner Commercial Sudhakar S/o 62 2.940 LHS Navile Owner Commercial Mahabalashetty Perfect Allay Components 63 3.320 LHS Navile Owner (O),Industry Pvt. Ltd Parameshwarappa S/o Late Residential/Com 64 3.360 RHS Navile Owner Hanumanthappa mercial Anjanadri Stationary & 65 3.440 RHS Navile Owner Commercial Telelinks Kallappa S/o Santhosh 66 3.520 RHS Navile Legal Tenant Commercial Mohan 67 3.625 RHS Navile Mary George Owner Commercial Gauthami Communication Residential/Com 68 3.631 RHS Navile Owner & Xerox mercial 69 3.642 RHS Navile Haleeshappa S/o Mallappa Legal Tenant Commercial Hanumanthappa S/o 70 3.672 RHS Navile Legal Tenant Commercial Mallappa Hanumanthappa S/o 71 3.682 RHS Navile Legal Tenant Commercial Mallappa Hanumanthappa S/o 72 3.685 RHS Navile Legal Tenant Commercial Mallappa Hanumanthappa S/o 73 3.687 RHS Navile Legal Tenant Commercial Mallappa 74 3.720 RHS Navile Devendrappa S/o Mallappa Owner Residential 75 3.740 RHS Navile Murali S/o Sreenivasa Owner Cattle Shed Chennamu 76 4.022 RHS Annappa S/o Basavanappa Owner Commercial mbapura Chennamu 77 4.030 RHS Revamma W/o Kondappa Owner Commercial mbapura Chennamu Pushpamma W/o Late 78 4.035 RHS Owner Commercial mbapura Jyothi Chennamu Shankamma W/o 79 4.060 RHS Owner Commercial mbapura Govindappa Chennamu 80 4.080 RHS Chandru S/o Late Thimma Owner Residential mbapura Chennamu 81 4.080 LHS Bus Stand Complex Legal Tenant Commercial mbapura Chennamu 82 4.102 RHS Ramakka W/o Shettyappa Owner Residential mbapura

33 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Sl. Chainage Side Village Name Occu. Status Loss Type No. Chennamu 83 4.105 RHS Ramakka W/o Shettyappa Legal Tenant Commercial mbapura Chennamu 84 4.138 RHS Ramappa Legal Tenant Commercial mbapura Chennamu N C Manohar S/o Late Residential/Com 85 4.175 RHS Owner mbapura Thukaram Rao mercial Chennamu Basamma W/o Late 86 4.496 LHS Owner Commercial mbapura Thimmaiah Jayamma W/o 87 6.300 RHS Abbalagere Owner Residential Sadashivappa 88 9.980 RHS Boodigere Manjappa S/o Basappa Owner (O),Pump House 89 10.200 LHS Boodigere Gramapanchyath Legal Tenant Commercial Beekanahal Umesh Naik S/o Govinda 90 10.780 LHS Owner (O),Toilet li Naik Beekanahal Govindappa S/o 91 10.830 LHS Owner Residential li Munnarswamy Beekanahal Kuber Naik S/o Gamya Residential/Com 92 10.842 LHS Owner li Naik mercial Beekanahal A M Eshawarappa S/o 93 10.980 RHS Owner Cattle Shed li Mallappa Beeranaker 94 13.103 RHS Kubendrappa S/o Beerappa Owner Residential e Kunchanah Shankra Naik S/o Chenna 95 15.480 LHS Owner Residential alli Naik Kunchanah Saroja bai W/o Lokesh 96 15.620 LHS Owner Commercial alli Naik Kunchanah Sakkre Naik S/o Rama 97 15.680 RHS Owner Commercial alli Naik Kunchanah 98 15.690 RHS Gangibai W/o Manja Naik Owner Commercial alli Kunchanah 99 15.740 RHS Mandal Panchyath Legal Tenant Commercial alli Kunchanah 100 15.745 LHS Vasu S/o Vallya Naik Owner Commercial alli Kunchanah 101 15.790 RHS Bharath H R Owner Commercial alli Kunchanah Deekya Naik S/o Rekya 102 15.998 LHS Owner Commercial alli Naik Kunchanah Chandru Naik S/o Laxma 103 16.490 LHS Owner Residential alli Naik 104 20.410 RHS Suttakote Thippeshappa S/o Hanuma Owner Cattle Shed Yellamma W/o Late 105 20.430 RHS Suttakote Owner Residential Shankrappa Machigond Krishna Murthy S/o Dodda 106 25.003 RHS Owner Residential anahalli Hanumanthappa

34 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Sl. Chainage Side Village Name Occu. Status Loss Type No. Machigond Hanumanthamma W/o Late (O),Compost 107 25.760 RHS Owner anahalli Halappa Tub Ramakrishnappa S/o 108 33.203 RHS Jayanagar Legal Tenant Commercial Siddappa Yellappa Sangli S/o 109 33.210 LHS Jayanagar Owner Residential Ramappa Sangli Basavanyappa S/o H S Residential/Com 110 33.210 LHS Jayanagar Owner Rudrappa mercial Mahadevap 111 36.060 LHS Ganesh S/o Kollappa Owner Residential ura Colony Chokla Naik S/o Verjina 112 38.080 LHS Haroguppa Owner Residential Naik 113 38.085 LHS Haroguppa Leshappa Legal Tenant Commercial Haroguppa Roopla Naik S/o Sheethali 114 38.092 RHS Owner Residential Cross Naik Haroguppa Laxmibai W/o Paramesh 115 38.092 LHS Squatter Commercial Cross Naik Haroguppa Madhusudhan S/o 116 38.130 LHS Owner Commercial Cross Vishwanath Reddy 117 45.460 LHS Nandihalli Girish S/o Laxman Rao Owner Farm House Malatheshappa S/o 118 47.000 LHS Shikaripura Owner (O),Projection Mallasathyappa Pushpanjali W/o 119 48.550 LHS Shikaripura Squatter Commercial Veerabhadrappa 120 48.970 RHS Shikaripura Suresh T H S/o Halappa Owner Residential 121 49.770 RHS Shikaripura Manohar Legal Tenant Commercial Gayathri W/o Late Bhanu 122 49.776 RHS Shikaripura Legal Tenant Commercial Prakash 123 49.790 RHS Shikaripura Halappa Legal Tenant Commercial 124 49.794 RHS Shikaripura Halappa Legal Tenant Commercial 125 49.798 RHS Shikaripura Halappa Legal Tenant Commercial 126 49.820 RHS Shikaripura Raghavendra S/o Gururaj Legal Tenant Commercial

127 49.844 RHS Shikaripura Raghavendra S/o Gururaj Legal Tenant Commercial Jeerahalli Mallappa S/o 128 49.860 RHS Shikaripura Owner Commercial Mallappa 129 49.892 RHS Shikaripura Raghavendra S/o Gururaj Owner Commercial 130 49.900 RHS Shikaripura Ningappa Owner Commercial

35 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Annexure 4: Details of PAFs of Link M7B Table 4- 41: PAF Structure details of link M7B (Shikaripura - Togarsi)

Sl. Occu. Chainage Side Village Name Loss Type No. Status Mohan Rao S/o 1 0.350 LHS Shikaripura Squatter Commercial Shivaji Rao Begum bee W/o 2 1.450 LHS Shikaripura Owner Residential Ahmad Sharifsab Nagarathnamma W/o 3 1.625 LHS Shikaripura Owner Residential Anantharam Shivayogappa S/o Legal 4 1.630 LHS Shikaripura Karibasappa Tenant Residential Shivayogi S/o Legal 5 1.635 LHS Shikaripura Residential Karibasappa Tenant Ganapatheppa S/o 6 1.640 LHS Shikaripura Owner Residential Gadigeppa Basavana Gowda S/o 7 2.270 RHS Shikaripura Owner Residential Kushalappa Gowda (O),Bore Well & Pump 8 3.16 LHS Shikaripura Jeenahalli Ningappa Owner House Legal 9 6.810 RHS Kanvemavu Manju S/o Puttappa Commercial Tenant Manjappa S/o 10 6.835 LHS Kanvemavu Squatter Commercial Siddappa Basavanthappa S/o 11 8.830 LHS Jakkanahalli Squatter Commercial Durgappa Renukamma W/o 12 8.860 RHS Jakkanahalli Squatter Commercial Chenna Basappa Malleshappa S/o 13 9.830 LHS Punadhahalli Squatter Commercial Hanumanthappa Kanthappa S/o 14 15.830 RHS Udugani Squatter Commercial Mariyappa 15 17.660 LHS Thandagani Nagaraja S/o Basappa Squatter Commercial Mallikarjuna S/o 16 17.700 RHS Thandagani Squatter Commercial Mruthyunjayappa Rajanna S/o 17 17.765 RHS Thandagani Owner Commercial Shivalingappa Sangappa S/o 18 18.550 LHS Thandagani Squatter Commercial Shambulingappa Jayaram S/o 19 19.230 LHS Shiralkoppa Owner Residential Hucchanna Babu Rao S/o 20 19.470 RHS Shiralkoppa Owner (O),Toilet Sangappa Somashekharappa S/o 21 19.547 RHS Shiralkoppa Owner Residential Mudiyappa

36 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Sl. Occu. Chainage Side Village Name Loss Type No. Status Chandrashekhar S/o 22 19.560 RHS Shiralkoppa Owner Residential Veerappa Gowdru Prema W/o 23 19.582 RHS Shiralkoppa Owner Residential Shivamurthaiah Bangaramma W/o 24 19.587 RHS Shiralkoppa Owner Residential Shivamurthy Gowda Raju S/o Dodda 25 19.673 LHS Shiralkoppa Owner Residential Obalappa Honnurappa S/o 26 19.679 LHS Shiralkoppa Owner Residential Peddaiah Gopal S/o 27 19.680 RHS Shiralkoppa Owner Residential Siddaramappa Nagabushan S/o 28 19.700 LHS Shiralkoppa Owner Commercial Basashettappa Nazirulla S/o Abdul 29 19.710 RHS Shiralkoppa Owner Commercial Samasasab Gangashetty S/o Legal 30 19.732 LHS Shiralkoppa Commercial Bangarappa Tenant Murugaraj S/o 31 19.737 LHS Shiralkoppa Owner Commercial Jayadevappa 32 19.745 RHS Shiralkoppa Kotresha Owner Commercial Legal 33 19.764 RHS Shiralkoppa Lokesh Commercial Tenant Chennaveerappa S/o 34 19.772 RHS Shiralkoppa Owner Commercial Muppanna Mallikarjuna S/o 35 19.780 RHS Shiralkoppa Owner Commercial Shiva Rudrappa Arun S/o 36 19.797 RHS Shiralkoppa Owner Commercial Rajashekharappa Shivashankar S/o 37 19.885 RHS Shiralkoppa Owner Commercial Shivanandappa Legal 38 20.140 LHS Shiralkoppa Anjuman Majood Commercial Tenant 39 20.860 RHS Shiralkoppa Ashok Owner Residential Hucchamma W/o 40 22.800 LHS Belligali Owner Commercial Devendrappa 41 24.420 LHS Javgatti Puttappa S/o Budeppa Squatter Commercial Savithramma W/o 42 24.620 RHS Javgatti Owner Residential Siddappa Akkamma W/o 43 29.410 LHS Togarsi Squatter Commercial Guddappa Legal 44 29.414 RHS Togarsi Mandal Panchayath Commercial Tenant Legal 45 29.417 RHS Togarsi Mandal Panchayath Commercial Tenant Muralidhara S/o 46 29.430 LHS Togarsi Owner Commercial Nagendrappa

37 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Sl. Occu. Chainage Side Village Name Loss Type No. Status Legal 47 29.430 RHS Togarsi Mandal Panchayath Commercial Tenant Legal 48 29.434 RHS Togarsi Mandal Panchayath Commercial Tenant Shivananda S/o 49 29.436 LHS Togarsi Owner Residential Vittappa Rudrappa S/o 50 29.445 LHS Togarsi Owner Residential Nagappa Parameshwara S/o 51 29.450 LHS Togarsi Owner Residential Malikappa Veerappa S/o 52 29.454 LHS Togarsi Owner Residential Nagappa Byadagi Megharaj S/o 53 29.558 LHS Togarsi Owner Residential Shivappa Anandappa S/o 54 29.570 LHS Togarsi Owner Residential Hanumanthappa Legal 55 29.590 RHS Togarsi Veeranna Residential Tenant Legal 56 29.605 LHS Togarsi B L Nayka Commercial Tenant Chinnamma W/o 57 31.285 RHS Tadagunda Squatter Residential Guddappa Karibasappa S/o 58 31.360 RHS Tadagunda Squatter Commercial Basappa Srikanth S/o 59 31.438 RHS Tadagunda Owner Residential Shekharappa Gangappa S/o 60 34.197 RHS Hirekabbur Squatter Commercial Fakirappa Basavarajappa S/o 61 34.937 RHS Tattur Owner Commercial Kollingappa Krishnappa S/o 62 34.955 RHS Tattur Owner Commercial Govindappa Basavarajappa S/o 63 35.010 LHS Tattur Owner Residential Shubhappa Rudrappa S/o 64 35.020 LHS Tattur Owner Residential Kallappa Parvathamma W/o 65 35.062 LHS Tattur Owner Residential Shivappa 66 35.580 LHS Tattur Basavaraj S/o Halappa Owner Residential Mehaboob Ali S/o 67 35.587 RHS Tattur Owner Residential Ayasab Anwarsab S/o 68 35.602 RHS Tattur Owner Residential Imamsab Ayathirsab S/o 69 35.607 RHS Tattur Owner Residential Muktumsab Hiremagadi Majibul Khan S/o 70 36.310 RHS Owner Commercial Cross Saptar Khan

38 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Sl. Occu. Chainage Side Village Name Loss Type No. Status Chikkaedugo Prakashappa S/o 71 38.162 RHS Owner Residential du Malleshappa Chikkaedugo Fakirappa S/o 72 38.180 LHS Squatter Commercial du Dasappa Mailarappa S/o 73 40.275 RHS Hunasavalli Owner Residential Guddappa Mailarappa S/o 74 40.290 LHS Hunasavalli Squatter Commercial Guddappa Kotrachar S/o Sanna 75 40.310 LHS Hunasavalli Owner Residential Veerappa Veerendra Gowda S/o 76 40.340 LHS Hunasavalli Owner Commercial Devadhara Gowda Hanuma Gowdru S/o 77 40.390 LHS Hunasavalli Owner Residential Ningapa Holelingappa S/o 78 45.320 RHS Anvatti Owner Commercial Channabasappa Ramananda Shetty S/o 79 45.440 LHS Anvatti Owner Commercial Ganapathi Shetty

39 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Annexure 5: Details of PAFs Link M7C Table 4- 52: PAF Structure details of link M7C (Anvatti - Hangal) Sl. Chainage Side Village Name Occu. Status Loss Type No. Khadar Basha S/o 1 0.340 RHS Anvatti Owner Commercial Usmansab C S Noor Ahmad S/o 2 0.343 RHS Anvatti Owner Residential Peersab Jangele Hashamsab S/o 3 0.353 RHS Anvatti Hajarathsab Owner Residential Kamara Vajeersab S/o 4 0.361 RHS Anvatti Owner Residential Fareedsab Mohammad 5 0.380 LHS Anvatti Owner Residential Haneef S/o Ullusab Jaffarsab S/o 6 0.388 LHS Anvatti Owner Residential Jubeeda bee Anwarsab S/o 7 0.395 LHS Anvatti Owner Residential Rehmansab Asimsab S/o 8 0.426 RHS Anvatti Owner Commercial Hazarathsab Moulaalisab S/o 9 0.430 RHS Anvatti Owner Residential Hasan Moulaalisab Jareena bee W/o 10 0.432 LHS Anvatti Owner Residential Shabbirsab Issak Ahmad S/o 11 0.435 RHS Anvatti Owner Residential Mardansab Noorjaan W/o 12 0.440 RHS Anvatti Owner Residential Sharifsab Kiyamad S/o 13 0.446 LHS Anvatti Owner Residential Khadarsab Razaksab S/o 14 0.450 LHS Anvatti Owner Residential Imamsab Budenbee W/o 15 0.458 LHS Anvatti Owner Residential Mardansab Amanaulla Khan 16 0.458 RHS Anvatti Owner Residential S/o Abbas Khan Neerala Manthesha S/o 17 1.860 RHS Owner Residential gi Guttappa Agasana Malleshappa S/o 18 4.840 LHS Owner Residential halli Adeveppa Basavaraj S/o 19 7.885 LHS Gondi Squatter Commercial Shankarappa Jayasheela W/o 20 8.040 RHS Gondi Ananda Gowda Owner Residential Patila

40 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Sl. Chainage Side Village Name Occu. Status Loss Type No. Chandrashekar S/o 21 8.060 LHS Gondi Gadigeppa Owner Residential Mallamma W/o 22 8.065 LHS Gondi Basavanneppa Owner Residential koppa Shanthavva W/o (O),Cattleshed 23 8.282 LHS Gondi Late Owner & Boundary Channabasappa Gondi Basavaraj S/o 24 9.89 LHS Squatter Commercial Cross Shankarappa Makara Basavaraj S/o 25 12.310 LHS Owner Residential valli Thimmappa Maviko Belliyappa S/o 26 17.737 RHS Owner Residential ppa Rekhappa Maviko Banappa S/o 27 17.762 LHS Owner Residential ppa Tippanna Maviko Tippanna S/o 28 18.250 LHS Owner Residential ppa Bommanna Maviko Shanthavva W/o 29 18.337 LHS Owner Residential ppa Kaliveerappa Maviko Parameshwarappa 30 19.460 LHS Owner Commercial ppa S/o Thavarappa Maviko 31 19.470 LHS Ravi S/o Valappa Owner Commercial ppa 4th Pasashuram S/o 32 20.550 LHS Squatter Commercial Cross Hemagiriyappa 20.557 RHS Kalivenkappa Squatter Commercial

Gejjehal Shivananda S/o 33 22.180 RHS Owner Residential li Rudrappa 34 24.990 RHS Hangal Venkatesh Javali Legal Tenant Commercial 35 24.995 RHS Hangal Venkatesha Javali Legal Tenant Commercial 36 24.998 RHS Hangal Venkatesha Javali Legal Tenant Commercial 37 25.002 RHS Hangal Venkatesha Javali Legal Tenant Commercial Shivaji S/o 38 25.018 RHS Hangal Legal Tenant Commercial Ganteppa Shivaji S/o 39 25.021 RHS Hangal Legal Tenant Commercial Eshappa Shivaji S/o 40 25.025 RHS Hangal Legal Tenant Commercial Eshappa 41 25.026 LHS Hangal Ramarao Owner Commercial 42 25.033 RHS Hangal Maharaja Prathap Owner Commercial Sambaji Rao S/o 43 25.036 RHS Hangal Owner Residential Peerappa Raghurama S/o 44 25.042 LHS Hangal Owner Residential Vasanthrao

41 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Sl. Chainage Side Village Name Occu. Status Loss Type No. Narayana S/o 45 25.140 RHS Hangal Krishnappa Owner Residential Hebbara Venkappaiah S/o 46 25.175 LHS Hangal Owner Residential Subbaiah Arjunappa S/o 47 25.194 RHS Hangal Owner Residential Chenna Basappa Kairunnissa W/o 48 25.210 RHS Hangal Owner Residential Makbul Ahmad Mohammad Rafi 49 25.215 LHS Hangal Owner Commercial S/o Allauddin Dilshad bee W/o 50 25.215 RHS Hangal Owner Residential Babasab Mustaq Ahmad S/o 51 25.238 LHS Hangal Owner Commercial Allauddin Shabbir Ahmad 52 25.264 RHS Hangal Owner Residential S/o Nannesab Nannesab S/o 53 25.265 LHS Hangal Owner Residential Mehaboobsab Jaffarsab S/o 54 25.268 LHS Hangal Owner Residential Mehaboobsab Sattar Ahmad S/o 55 25.271 LHS Hangal Owner Residential Mehaboobsab Mohammad Gaus 56 25.274 LHS Hangal Owner Residential S/o Mehaboobsab Abdul Aziz S/o 57 25.277 RHS Hangal Owner Residential Husainsab Abdul Sattar S/o 58 25.278 LHS Hangal Owner Residential Abdul Khadar Vajulunnissa W/o 59 25.280 RHS Hangal Owner Residential Moulasab Mehaboob Ali S/o 60 25.284 RHS Hangal Owner Commercial Rehmansab Ambajappa A 61 25.301 LHS Hangal Legal Tenant Commercial Katekar Nanneba S/o 62 25.312 RHS Hangal Owner Residential Gondisab Imamsab S/o 63 25.317 RHS Hangal Owner Residential Miyasab Hasan Khan S/o 64 25.330 LHS Hangal Owner Commercial Imam Khan Gulamsab S/o 65 25.330 RHS Hangal Owner Residential Davalsab Gondi Kutheja S/o 66 25.336 RHS Hangal Owner Residential Husainmiya Munnavar Khan 67 25.338 LHS Hangal Owner Commercial S/o Imam Kasim

42 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Sl. Chainage Side Village Name Occu. Status Loss Type No. Khan

Moulalik S/o 68 25.342 RHS Hangal Mohammad Owner Commercial Usman Abdul Jaleel 69 25.345 RHS Hangal Ahmad S/o Owner Residential Rehmansab Mohammadsab S/o 70 25.350 RHS Hangal Owner Residential M Khajri Rehman Khan S/o 71 25.352 LHS Hangal Owner Commercial Imam Khan Baramappa S/o 72 25.364 LHS Hangal Owner Commercial Kariyappa Vardi Babalal S/o 73 25.366 RHS Hangal Owner Residential Babajaan Nasipudi Moulali S/o 74 25.378 LHS Hangal Owner Commercial Nannesab 75 25.393 LHS Hangal Yusufia Masjid Legal Tenant Commercial Masjid Yusufia 76 25.396 LHS Hangal Legal Tenant Commercial Trust Masjid Yusufia 77 25.401 LHS Hangal Legal Tenant Commercial Trust Masjid Yusufia 78 25.405 LHS Hangal Legal Tenant Commercial Trust Masjid Yusufia 79 25.409 LHS Hangal Legal Tenant Commercial Trust Masjid Yusufia 80 25.412 LHS Hangal Legal Tenant Commercial Trust Masjid Yusufia 81 25.416 LHS Hangal Legal Tenant Commercial Trust Masjid Yusufia 82 25.419 LHS Hangal Legal Tenant Commercial Trust Masjid Yusufia 83 25.427 LHS Hangal Legal Tenant Commercial Trust Masjid Yusufia 84 25.431 LHS Hangal Legal Tenant Commercial Trust Masjid Yusufia 85 25.434 LHS Hangal Legal Tenant Commercial Trust Manjunatha S/o 86 25.435 RHS Hangal Owner Commercial Mailarappa Masjid Yusufia 87 25.439 LHS Hangal Legal Tenant Commercial Trust Gramadevi 88 25.460 LHS Hangal Padakatti Legal Tenant Commercial Samudaya Kalandar S/o 89 25.490 LHS Hangal Squatter Commercial Abdul Rehmansab

43 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Sl. Chainage Side Village Name Occu. Status Loss Type No. Kalandar S/o 90 25.492 LHS Hangal Legal Tenant Commercial Kakasab Suleman Basha S/o 91 25.495 LHS Hangal Owner Commercial Ibrahimsab Abdulgani S/o 92 25.499 LHS Hangal Owner Residential Moulasab Narayana S/o 93 25.505 LHS Hangal Owner Commercial Mahadevappa Masjid Yusufia 94 25.516 LHS Hangal Legal Tenant Commercial Trust 95 25.521 LHS Hangal Ashoka Bodaki Legal Tenant Commercial Mukbul Ahmad 96 25.521 RHS Hangal Owner Residential S/o Nannesab 97 25.526 LHS Hangal Ashoka Bodaki Legal Tenant Commercial 98 25.530 LHS Hangal Ashok Bondagi Legal Tenant Commercial 99 25.535 LHS Hangal Ashok Bodaki Legal Tenant Commercial 100 25.540 LHS Hangal Ashok Bodaki Legal Tenant Commercial Abdulsab S/o 101 25.545 LHS Hangal Owner Residential Kasimsab 102 25.550 LHS Hangal Shahimitti Masjid Legal Tenant Commercial 103 25.555 LHS Hangal Shahimitti Masjid Legal Tenant Commercial 104 25.557 LHS Hangal Shahimitt Masjid Legal Tenant Commercial 105 25.560 LHS Hangal Shahimitti Masjid Legal Tenant Commercial 106 25.565 LHS Hangal Shahimitti Masjid Legal Tenant Commercial 107 25.567 LHS Hangal Shahimitti Masjid Legal Tenant Commercial Yallappa 108 25.577 RHS Hangal Legal Tenant Commercial Sherkhani 109 25.600 LHS Hangal Kamarsab Owner Commercial Syedali S/o 110 25.604 LHS Hangal Legal Tenant Commercial Bashasab Dattusa S/o 111 25.610 LHS Hangal Owner Commercial Shankarasa 112 25.612 RHS Hangal Vabsab Lohar Legal Tenant Commercial Prathap S/o 113 25.617 RHS Hangal Owner Commercial Ramegowda Dinesh S/o 114 25.624 LHS Hangal Owner Residential Yallappa Sahadeva S/o 115 25.627 LHS Hangal Owner Residential Rangappa 116 25.635 RHS Hangal Ramakrishnappa Owner Residential Alisab S/o 117 25.652 LHS Hangal Owner Residential Husainsab Ramalinga Yuvaka 118 25.655 RHS Hangal Legal Tenant Commercial Mandali Hanumanthavva 119 25.662 RHS Hangal Squatter Commercial W/o Late Erappa 120 25.670 RHS Hangal Manjapa S/o Owner Residential

44 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Sl. Chainage Side Village Name Occu. Status Loss Type No. Fakirappa Shankara S/o 121 25.675 LHS Hangal Owner Commercial Hanumanthappa Prakasha S/o 122 25.694 RHS Hangal Owner Commercial Rachotappa Venkubai W/o 123 25.722 LHS Hangal Owner Residential Nagendrappa Najeer Ahmad S/o 124 25.730 RHS Hangal Owner Commercial Mohammad Yusuf Venkappa S/o 125 25.740 LHS Hangal Legal Tenant Commercial Valakajappa Venkappa S/o 126 25.744 LHS Hangal Legal Tenant Commercial Valakajappa Abdul Khadar S/o 127 25.747 RHS Hangal Mohammad Legal Tenant Commercial Haneef Sahebjaan S/o 128 25.747 RHS Hangal Owner Residential Husainsab Mohammad Ismail 129 25.753 RHS Hangal Owner Residential S/o Madarsab Parasappa S/o 130 25.776 LHS Hangal Owner Residential Tippanna Tukaram S/o 131 25.800 RHS Hangal Owner Residential Rachappa Nagappa S/o 132 25.812 RHS Hangal Owner Commercial Durgappa 133 25.818 LHS Hangal Raghava Owner Commercial Ramanna S/o 134 25.820 LHS Hangal Owner Residential Karisiddappa Shivaputrappa S/o 135 25.832 LHS Hangal Owner Residential Karisiddappa Abdul Samad S/o 136 25.895 RHS Hangal Owner Commercial Abdul Sukur Mahanthesha S/o 137 25.898 LHS Hangal Owner Commercial Nagendrappa Devendrappa S/o 138 25.923 RHS Hangal Owner Commercial Shivappa Malathesh S/o 139 25.925 LHS Hangal Owner Commercial Appajappa Ramakrishna S/o 140 25.935 RHS Hangal Legal Tenant Commercial Neelappa 141 26.010 LHS Hangal Narayana Legal Tenant Commercial 142 26.184 LHS Hangal Fakirappa Koravar Legal Tenant Commercial Fakirappa S/o 143 26.187 LHS Hangal Legal Tenant Commercial Tirappa Guthyavva 144 26.200 LHS Hangal Legal Tenant Commercial Tirukappa Goravar

45 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Sl. Chainage Side Village Name Occu. Status Loss Type No. Tippanna S/o 145 26.204 LHS Hangal Owner Commercial Yallappa Barki Ashoka S/o Babu 146 26.220 RHS Hangal Owner Commercial Rao Kalal 147 26.267 LHS Hangal Ambaji Katikar Legal Tenant Commercial

46 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Annexure 6: Community Assets

Table 4- 63: Community Asset Details of link T21 (Shikaripura - Anandapuram (on NH-206)) Area in Sq.m

Total % of Str. Sl. Chaina Affected Side District Taluk Village Typeof Asset Owner Type Structur Getting No. ge Strcture e Affected

1 0.170 RHS Shimoga Shikaripura Shikaripura Public Toilet Government 116.40 3.60 3.09 2 0.170 RHS Shimoga Shikaripura Shikaripura Samadhi Community 36.00 27.00 75.00 3 0.345 RHS Shimoga Shikaripura Shikaripura Bore Hole Panchayat 11.55 2.25 19.48 4 0.370 RHS Shimoga Shikaripura Shikaripura Mosque Community 110.70 10.80 9.76 5 3.550 LHS Shimoga Shikaripura Kalenahalli Bus Stand Panchayat 69.00 15.00 21.74 3.690 RHS Shimoga Shikaripura Kalenahalli Compound Pvt. Trust 480.00 12.00 2.50 6 Wall 7 5.195 LHS Shimoga Shikaripura Chunchinakoppa Hand Pump Panchayat 10.50 0.45 4.29 8 7.475 LHS Shimoga Shikaripura Solur Hand Pump Panchayat 21.00 0.45 2.14 7.477 RHS Shimoga Shikaripura Solur Handloom Government 73.50 3.50 4.76 9 House 7.560 LHS Shimoga Shikaripura Solur Compound Government 224.00 6.00 2.68 10 Wall 11 7.900 LHS Shimoga Shikaripura Solur Well Panchayat 19.50 0.90 4.62 12 8.100 RHS Shimoga Shikaripura Solur Well Panchayat 10.50 0.90 8.57 13 8.190 RHS Shimoga Shikaripura Solur Projection Government 30.00 5.00 16.67 8.330 RHS Shimoga Shikaripura Solur Compound Panchayat 30.00 1.50 5.00 14 Wall 15 8.335 RHS Shimoga Shikaripura Solur Library Panchayat 18.00 0.90 5.00 9.420 RHS Shimoga Shikaripura Chikkasalur Compound Government 540.00 18.00 3.33 16 Wall 17 11.060 LHS Shimoga Shikaripura Chikkapura Temple Community 6.00 0.30 5.00 18 11.100 RHS Shimoga Shikaripura Chikkapura Bus Stand Panchayat 31.00 1.20 3.87 19 11.183 LHS Shimoga Shikaripura Chikkapura Hand Pump Panchayat 8.50 1.00 11.76 11.185 LHS Shimoga Shikaripura Chikkapura Mini Water Panchayat 16.60 4.00 24.10 20 Supply Tank 11.240 LHS Shimoga Shikaripura Chikkapura Mini Water Panchayat 15.00 4.00 26.67 21 Supply Tank 12.020 RHS Shimoga Shikaripura Shikaripura Mini Water Panchayat 21.00 3.00 14.29 22 Supply Tank 12.215 RHS Shimoga Shikaripura Kanasogi Mini Water Panchayat 17.00 4.00 23.53 23 Supply Tank 24 12.390 RHS Shimoga Shikaripura Kanasogi Temple Community 85.50 9.00 10.53 25 12.450 RHS Shimoga Shikaripura Kanasogi Shrine Community 12.00 4.00 33.33 12.640 LHS Shimoga Shikaripura Kanasogi Bore Hole & Panchayat 41.25 2.25 5.45 26 Pump House 27 13.170 RHS Shimoga Shikaripura Ambligola Aralikatte Community 44.00 22.00 50.00 28 13.310 RHS Shimoga Shikaripura Ambligola Aralikatte Community 11.00 3.00 27.27 29 13.590 RHS Shimoga Shikaripura Ambligola Mosque Community 52.00 4.00 7.69 13.603 LHS Shimoga Shikaripura Ambligola Mini Water Panchayat 15.00 7.00 46.67 30 Supply Tank 31 13.720 LHS Shimoga Shikaripura Ambligola Bore Hole Panchayat 5.00 1.00 20.00 32 13.770 LHS Shimoga Shikaripura Ambligola Temple Community 5.70 1.00 17.54

47 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Area in Sq.m

Total % of Str. Sl. Chaina Affected Side District Taluk Village Typeof Asset Owner Type Structur Getting No. ge Strcture e Affected

33 13.780 RHS Shimoga Shikaripura Ambligola Hand Pump Panchayat 11.25 2.25 20.00 14.380 LHS Shimoga Shikaripura Ambligola Mini Water Panchayat 16.50 2.25 13.64 34 Supply Tank 35 14.805 RHS Shimoga Sagara Hosur Hand Pump Panchayat 9.00 2.25 25.00 36 14.840 RHS Shimoga Sagara Hosur Bore Hole Panchayat 6.00 1.00 16.67 37 15.340 LHS Shimoga Sagara Hosur Water Tank Panchayat 125.00 55.00 44.00 38 17.710 RHS Shimoga Sagara Bolanakunte Bus Stand Panchayat 49.00 24.50 50.00 39 19.288 LHS Shimoga Sagara Byrapura Hand Pump Panchayat 8.00 1.00 12.50 40 19.303 LHS Shimoga Sagara Byrapura Water Tank Panchayat 12.00 1.00 8.33 41 21.100 RHS Shimoga Sagara Byrapura Temple Community 5.00 1.00 20.00 42 23.848 RHS Shimoga Sagara Gauthampura Pump House Panchayat 22.50 9.00 40.00 43 23.848 LHS Shimoga Sagara Gauthampura Bore Hole Panchayat 7.70 1.00 12.99 44 24.280 RHS Shimoga Sagara Gauthampura Aralikatte Community 37.00 29.60 80.00 24.610 RHS Shimoga Sagara Gauthampura Bore Hole & Panchayat 10.50 2.25 21.43 45 Pump House 46 25.403 RHS Shimoga Sagara Narasipura Bus Stand Panchayat 57.75 26.25 45.45 47 25.422 RHS Shimoga Sagara Narasipura Water Tank Panchayat 7.00 1.00 14.29 48 26.035 LHS Shimoga Sagara Narasipura Water Tank Panchayat 15.00 5.00 33.33 49 26.375 LHS Shimoga Sagara Narasipura Hand Pump Panchayat 7.50 1.00 13.33 50 27.405 RHS Shimoga Sagara Kannur Hand Pump Panchayat 8.40 1.00 11.90 51 28.291 RHS Shimoga Sagara Kannur Bus Stand Panchayat 88.00 32.00 36.36 28.950 LHS Shimoga Sagara Malandur Compound Government 1897.50 69.00 3.64 52 Wall 53 29.182 RHS Shimoga Sagara Malandur Bus Stand Panchayat 40.00 10.00 25.00 54 30.340 LHS Shimoga Sagara Malandur Temple Community 10.00 5.00 50.00 55 30.917 LHS Shimoga Sagara Malandur Bus Stand Panchayat 41.63 15.75 37.84 56 31.040 LHS Shimoga Sagara Malandur Hand Pump Panchayat 9.75 2.25 23.08 32.137 RHS Shimoga Sagara Dasanakoppa Mini Water Panchayat 9.15 1.35 14.75 57 Supply Tank 58 32.147 RHS Shimoga Sagara Dasanakoppa Hand Pump Panchayat 6.20 0.80 12.90 32.185 LHS Shimoga Sagara Dasanakoppa Compound Government 108.75 4.50 4.14 59 Wall

Table 4-14: Community Assets M7A

% of Str. Total Sl. Chaina Affected Gettin Side District Taluk Village Typeof Asset Owner Type Structur No. ge Strcture g e Affecte d

1 0.460 RHS Shimoga Shimoga Shimoga Compound Wall Private 156.00 4.50 2.88 2 0.475 RHS Shimoga Shimoga Shimoga Compound Wall Private 156.00 4.50 2.88 3 0.540 LHS Shimoga Shimoga Shimoga Compound Wall Government 139.50 4.65 3.33

48 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

% of Str. Total Sl. Chaina Affected Gettin Side District Taluk Village Typeof Asset Owner Type Structur No. ge Strcture g e Affecte d

4 0.680 LHS Shimoga Shimoga Shimoga Compound Wall Private 320.25 9.15 2.86 5 1.040 LHS Shimoga Shimoga Shimoga Temple Community 47.50 7.50 15.79 6 1.185 LHS Shimoga Shimoga Shimoga Compound Wall Private 183.15 3.70 2.02 7 1.316 LHS Shimoga Shimoga Shimoga Others Government 12.00 12.00 100.00 8 2.170 RHS Shimoga Shimoga Navule Temple Community 78.00 78.00 100.00 9 2.520 RHS Shimoga Shimoga Navule Temple Community 52.50 25.00 47.62 10 2.530 RHS Shimoga Shimoga Navule Hand Pump Panchayat 7.00 1.00 14.29 11 2.535 RHS Shimoga Shimoga Navule Arch Community 115.50 7.00 6.06 12 2.940 LHS Shimoga Shimoga Shimoga Hand Pump Panchayat 14.00 1.00 7.14 2.955 RHS Shimoga Shimoga Navule Mini Water Supply Panchayat 20.00 4.00 20.00 13 Tank 14 3.180 RHS Shimoga Shimoga Navule Bus Stand Panchayat 40.00 10.00 25.00 15 3.190 LHS Shimoga Shimoga Shimoga Compound Wall Private 1840.00 48.00 2.61 16 3.350 RHS Shimoga Shimoga Navule Water Tub Panchayat 7.00 0.70 10.00 17 3.390 LHS Shimoga Shimoga Navule Compound Wall Private 4144.00 111.00 2.68 18 3.700 RHS Shimoga Shimoga Navule Hand Pump Panchayat 12.00 1.00 8.33 19 3.780 LHS Shimoga Shimoga Navule Compound Wall Government 2610.00 54.00 2.07 20 4.080 LHS Shimoga Shimoga Chennamumbapura Bus Stand Panchayat 40.00 20.00 50.00 21 4.390 LHS Shimoga Shimoga Chennamumbapura Compound Wall Government 3834.00 81.00 2.11 22 4.440 LHS Shimoga Shimoga Chennamumbapura Hand Pump Panchayat 7.00 1.00 14.29 23 4.460 LHS Shimoga Shimoga Chennamumbapura Primaty School Government 600.00 112.50 18.75 24 4.690 RHS Shimoga Shimoga Chennamumbapura Hand Pump Panchayat 40.00 15.00 37.50 25 6.315 RHS Shimoga Shimoga Abbalagere Primaty School Government 411.60 92.40 22.45 26 6.340 RHS Shimoga Shimoga Abbalagere Bus Stand Panchayat 50.00 10.00 20.00 27 8.370 LHS Shimoga Shimoga Abbalagere Pump House Panchayat 90.00 1.00 1.11 28 10.010 LHS Shimoga Shimoga Beekanahalli Bus Stand Panchayat 35.00 5.00 14.29 29 10.200 LHS Shimoga Shimoga Boodigere Cross Bus Stand Panchayat 81.00 24.00 29.63 30 10.840 LHS Shimoga Shimoga Beekanahalli Hand Pump Panchayat 6.00 1.00 16.67 11.140 LHS Shimoga Shimoga Beekanahalli Bore Hole & Pump Panchayat 8.00 1.00 12.50 31 House 32 13.060 RHS Shimoga Shimoga Beeranakere Water Tub Panchayat 46.00 5.00 10.87 33 14.270 LHS Shimoga Shimoga Beeranakere Temple Community 17.00 15.00 88.24 34 15.110 LHS Shimoga Shimoga Kunchenahalli Temple Community 39.00 9.00 23.08 35 15.640 LHS Shimoga Shimoga Kunchenahalli Temple Community 11.25 2.25 20.00 36 15.692 RHS Shimoga Shimoga Kunchenahalli Hand Pump Panchayat 5.50 1.00 18.18 37 15.730 RHS Shimoga Shimoga Kunchenahalli Bus Stand Panchayat 30.00 10.00 33.33 38 16.260 RHS Shimoga Shimoga Kunchenahalli Temple Community 85.25 66.00 77.42 39 16.660 RHS Shimoga Shimoga Kunchenahalli Bus Stand Panchayat 51.00 3.00 5.88 16.666 RHS Shimoga Shimoga Kunchenahalli Mini Water Supply 13.20 0.30 2.27 40 Panchayat Tank 41 16.800 LHS Shimoga Shimoga Kunchenahalli Temple Community 14.00 12.25 87.50 42 17.650 RHS Shimoga Shimoga Kallapura Hand Pump Panchayat 9.50 1.00 10.53 43 20.493 LHS Shimoga Shimoga Suttakote Bus Stand Panchayat 35.00 9.00 25.71 22.340 LHS Davanagere Honnali Savalanga Noodal Niranthara Government 60.00 4.00 6.67 44 Kalika Kendra

49 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

% of Str. Total Sl. Chaina Affected Gettin Side District Taluk Village Typeof Asset Owner Type Structur No. ge Strcture g e Affecte d

45 22.800 RHS Davanagere Honnali Savalanga Hand Pump Panchayat 9.00 1.00 11.11 46 24.990 LHS Davanagere Honnali Machigondanahalli Hand Pump Panchayat 11.50 0.50 4.35 47 25.000 RHS Davanagere Honnali Machigondanahalli Bus Stand Panchayat 47.50 2.50 5.26 48 27.157 RHS Davanagere Honnali Chinnikatte Hand Pump Panchayat 7.80 0.20 2.56 49 27.160 RHS Davanagere Honnali Chinnikatte Bore Hole Panchayat 5.00 1.00 20.00 50 27.320 LHS Davanagere Honnali Chinnikoppa Temple Community 6.25 0.75 12.00 27.470 RHS Davanagere Honnali Chinnikatte Bore Hole & Pump Panchayat 7.00 0.50 7.14 51 House 52 27.940 RHS Davanagere Honnali Chinnikatte Temple Community 30.00 25.00 83.33 53 30.090 RHS Davanagere Honnali Siddapura Temple Panchayat 8.00 1.00 12.50 54 31.940 LHS Davanagere Honnali Joga Bus Stand Panchayat 29.60 14.00 47.30 55 33.200 RHS Davanagere Honnali Jayanagar Bus Stand Panchayat 76.00 20.00 26.32 56 33.202 LHS Davanagere Honnali Jayanagar Bus Stand Panchayat 9.75 2.25 23.08 35.260 LHS Shimoga Shikaripura Attibele Bore Hole & Pump Panchayat 12.75 2.25 17.65 57 House 37.360 RHS Shimoga Shikaripura Haragoppa Mini Water Supply Panchayat 11.25 0.75 6.67 58 Tank 59 38.080 LHS Shimoga Shikaripura Haragoppa Cross Bus Stand Panchayat 64.40 24.50 38.04 60 38.125 RHS Shimoga Shikaripura Haragoppa Cross Pump House Panchayat 11.30 0.20 1.77 61 38.500 LHS Shimoga Shikaripura Haragoppa Cross Hand Pump Panchayat 11.80 1.00 8.47 62 38.500 RHS Shimoga Shikaripura Haragoppa Cross Primaty School Government 107.50 2.50 2.33 63 40.842 RHS Shimoga Shikaripura Yarakatte Bore Hole Panchayat 6.50 1.00 15.38 64 41.140 RHS Shimoga Shikaripura Yarakatte Aralikatte Community 14.00 12.00 85.71 65 43.480 LHS Shimoga Shikaripura Taralagatta Aralikatte Community 22.50 12.50 55.56 66 45.440 LHS Shimoga Shikaripura Nandihalli Bus Stand Panchayat 25.00 20.00 80.00 67 46.550 LHS Shimoga Shikaripura Shikaripura Temple Community 5.00 1.00 20.00 68 47.025 LHS Shimoga Shikaripura Shikaripura Bus Stand Panchayat 31.50 13.50 42.86 69 47.095 LHS Shimoga Shikaripura Shikaripura Water Tank Panchayat 11.50 1.00 8.70 70 49.090 RHS Shimoga Shikaripura Shikaripura APML Shop Government 15.00 2.00 13.33 71 49.700 LHS Shimoga Shikaripura Shikaripura Flag Pole Community 10.00 1.00 10.00

Table 4- 75: Community Assets M7B Area in Sq.m

% of Str. Total Sl. Chainag Affected Gettin Side District Taluk Village Typeof Asset Owner Type Structur No. e Strcture g e Affecte d

0.600 LHS Shimoga Shikaripura Shikaripura Pump House & Bore Panchayat 13.50 2.25 16.67 1 Hole 2 0.960 LHS Shimoga Shikaripura Shikaripura Arch Panchayat 36.00 4.00 11.11 3 1.080 LHS Shimoga Shikaripura Shikaripura Hospital Government 332.50 17.50 5.26 4 1.110 LHS Shimoga Shikaripura Shikaripura Compound Wall Public Trust 240.00 9.00 3.75

50 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Area in Sq.m

% of Str. Total Sl. Chainag Affected Gettin Side District Taluk Village Typeof Asset Owner Type Structur No. e Strcture g e Affecte d

5 1.230 RHS Shimoga Shikaripura Shikaripura Circle Panchayat 90.00 60.00 66.67 6 1.325 RHS Shimoga Shikaripura Shikaripura Compound Wall Government 307.50 15.00 4.88 7 2.085 LHS Shimoga Shikaripura Shikaripura Temple Public Trust 137.50 106.25 77.27 8 2.120 LHS Shimoga Shikaripura Shikaripura Hand Pump Panchayat 10.50 2.25 21.43 9 2.205 RHS Shimoga Shikaripura Shikaripura Temple Community 63.00 36.00 57.14 10 2.255 RHS Shimoga Shikaripura Shikaripura Hostel Government 11 2.880 RHS Shimoga Shikaripura Shikaripura Compound Wall Government 1520.00 80.00 5.26 6.920 LHS Shimoga Shikaripura Kanvemane Pump House & Bore Panchayat 6.00 2.25 37.50 12 Well 13 8.833 LHS Shimoga Shikaripura Jakkanahalli Bus Stand Panchayat 45.00 24.00 53.33 14 9.785 LHS Shimoga Shikaripura Pundanahalli Bus Stand Panchayat 35.00 20.00 57.14 15 15.190 LHS Shimoga Shikaripura Udagani Aralikatte Community 15.00 4.50 30.00 16 15.430 RHS Shimoga Shikaripura Udagani Bus Stand Panchayat 41.65 3.85 9.24 17 15.860 RHS Shimoga Shikaripura Udagani Hand Pump Panchayat 7.50 2.25 30.00 18 17.590 RHS Shimoga Shikaripura Tadagani Compound Wall Government 10.00 6.00 60.00 17.665 RHS Shimoga Shikaripura Tadagani Mini Water Supply Panchayat 13.50 2.25 16.67 19 Tank 20 17.738 LHS Shimoga Shikaripura Tadagani Hand Pump Panchayat 10.50 2.25 21.43 17.780 RHS Shimoga Shikaripura Tadagani Mini Water Supply Panchayat 13.50 2.25 16.67 21 Tank 17.840 RHS Shimoga Shikaripura Tadagani Mini Water Supply 12.00 2.25 18.75 22 Panchayat Tank 23 17.920 RHS Shimoga Shikaripura Tadagani Hand Pump Panchayat 14.25 2.25 15.79 17.950 RHS Shimoga Shikaripura Tadagani Mini Water Supply Panchayat 14.25 2.25 15.79 24 Tank 18.380 RHS Shimoga Shikaripura Tadagani Pump House & Bore 11.25 2.25 20.00 25 Panchayat Well 18.670 RHS Shimoga Shikaripura Tadagani Mini Water Supply 13.50 2.25 16.67 26 Panchayat Tank 27 19.410 RHS Shimoga Shikaripura Shiralkoppa Aralikatte Community 12.00 12.00 100.00 28 19.920 RHS Shimoga Shikaripura Shiralkoppa Aralikatte Community 90.00 30.00 33.33 29 21.720 LHS Shimoga Shikaripura Balligavi Temple Government 330.00 45.00 13.64 30 22.795 LHS Shimoga Shikaripura Balligavi Hand Pump Panchayat 9.00 2.25 25.00 31 24.415 RHS Shimoga Shikaripura Javagatti Bus Stand Panchayat 15.00 3.00 20.00 24.600 RHS Shimoga Shikaripura Javagatti Mini Water Supply Panchayat 10.50 2.25 21.43 32 Tank 33 24.750 RHS Shimoga Shikaripura Javagatti Bore Hole Panchayat 15.00 2.25 15.00 34 26.090 RHS Shimoga Shikaripura Devikoppa Temple Community 21.00 9.00 42.86 26.116 RHS Shimoga Shikaripura Devikoppa Mini Water Supply Panchayat 13.50 2.25 16.67 35 Tank 26.140 RHS Shimoga Shikaripura Devikoppa Pump House & Bore Panchayat 15.00 2.25 15.00 36 Hole 26.210 RHS Shimoga Shikaripura Devikoppa Mini Water Supply Community 15.00 2.25 15.00 37 Tank 38 29.170 RHS Shimoga Shikaripura Togarsi Forest House Government 378.00 112.00 29.63 39 29.200 RHS Shimoga Shikaripura Togarsi Bore Hole Panchayat 18.00 2.25 12.50 40 29.380 RHS Shimoga Shikaripura Togarsi Panchayath Society Panchayat 160.00 48.00 30.00 41 29.422 RHS Shimoga Shikaripura Togarsi Bus Stand Panchayat 51.00 27.00 52.94

51 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Area in Sq.m

% of Str. Total Sl. Chainag Affected Gettin Side District Taluk Village Typeof Asset Owner Type Structur No. e Strcture g e Affecte d

42 29.440 RHS Shimoga Shikaripura Togarsi Compound Wall Government 180.00 7.50 4.17 43 29.620 LHS Shimoga Shikaripura Togarsi Temple Public Trust 60.00 27.00 45.00 31.410 LHS Shimoga Shikaripura Tandgunda Pump House & Bore Panchayat 12.00 2.25 18.75 44 Hole 45 34.195 RHS Shimoga Shikaripura Hirekabbur Bus Stand Panchayat 33.00 24.00 72.73 46 34.260 RHS Shimoga Soraba Hirekabbur Bore Hole Panchayat 15.00 2.25 15.00 34.610 LHS Shimoga Soraba Hirekabbur Pump House & Bore Panchayat 11.25 2.25 20.00 47 Hole 48 34.840 RHS Shimoga Soraba Thothur Compound Wall Government 720.00 2.25 0.31 49 34.895 RHS Shimoga Soraba Thothur Hand Pump Panchayat 10.50 2.25 21.43 36.230 LHS Shimoga Soraba Thothur Pump House & Bore Panchayat 15.00 2.25 15.00 50 Hole 51 38.170 LHS Shimoga Soraba Chikkaedagodu Bus Stand Panchayat 37.50 4.50 12.00 52 40.240 LHS Shimoga Soraba Hunsivahalli Compound Wall Government 225.00 7.50 3.33 53 40.320 LHS Shimoga Soraba Hunsivahalli Temple Public Trust 33.75 2.25 6.67 42.595 RHS Shimoga Soraba Hiremagadi Panchayat 35.00 20.00 57.14 54 Bus Stand Cross 55 44.880 LHS Shimoga Soraba Anvatti Temple Public Trust 53.75 6.25 11.63 56 44.980 LHS Shimoga Soraba Anvatti Compound Wall Government 575.00 25.00 4.35 57 45.160 RHS Shimoga Soraba Anvatti Compound Wall Government 1100.00 50.00 4.55 58 45.225 LHS Shimoga Soraba Anvatti Compound Wall Government 100.00 4.00 4.00 59 45.500 RHS Shimoga Soraba Anvatti Compound Wall Government 805.00 35.00 4.35

52 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

Table 4- 86: Community Assets M7C Area in Sq.m

Total % of Str. Sl. Chaina Affected Side District Taluk Village Typeof Asset Owner Type Structur Getting No. ge Strcture e Affected

1 0.358 LHS Shimoga Soraba Anvatti Pump House Panchayat 11.25 1.00 8.89 2 1.210 LHS Shimoga Soraba Kothipura Compound Wall Public Trust 90.00 15.00 16.67 3 1.300 LHS Shimoga Soraba Kothipura Bus Stand Panchayat 33.00 9.00 27.27 4 1.630 RHS Shimoga Soraba Kothipura Over Head Tank Panchayat 36.00 4.00 11.11 5 1.800 RHS Shimoga Soraba Neralagere Hand Pump Panchayat 10.50 2.25 21.43 6 1.820 LHS Shimoga Soraba Neralagere Temple Public Trust 16.50 1.50 9.09 7 2.390 LHS Shimoga Soraba Neralagere Hand Pump Panchayat 9.00 2.25 25.00 8 7.770 RHS Haveri Hangal Gondi Hand Pump Panchayat 7.50 1.50 20.00 9 7.900 LHS Haveri Hangal Gondi Temple Public Trust 9.00 4.00 44.44 10 7.910 LHS Haveri Hangal Gondi Bus Stand Panchayat 42.00 17.50 41.67 11 8.290 LHS Haveri Hangal Gondi Bore Hole Panchayat 9.00 2.25 25.00 12 9.870 RHS Haveri Hangal Gondi Hand Pump Panchayat 13.50 2.25 16.67 12.310 RHS Haveri Hangal Makarvalli Mini Water Supply 14.25 1.50 10.53 13 Panchayat Tank 14 12.315 RHS Haveri Hangal Makarvalli Hand Pump Panchayat 7.50 2.25 30.00 15 18.330 LHS Haveri Hangal Mavukoppa Bus Stand Panchayat 36.00 24.00 66.67 18.960 RHS Haveri Hangal Mavukoppa Pump House & Bore Panchayat 10.50 2.25 21.43 16 Hole 17 19.080 LHS Haveri Hangal Mavukoppa Bore Hole Panchayat 12.00 2.25 18.75 18 19.482 RHS Haveri Hangal Mavukoppa Hand Pump Panchayat 10.50 0.75 7.14 19 20.540 LHS Haveri Hangal 4th Cross Bus Stand Panchayat 49.00 28.00 57.14 20 21.780 LHS Haveri Hangal Gejjehalli Hand Pump Panchayat 9.75 0.75 7.69 21 22.260 RHS Haveri Hangal Gejjehalli Hand Pump Panchayat 15.00 2.25 15.00 22 22.780 RHS Haveri Hangal Gejjehalli Hand Pump Panchayat 15.00 2.25 15.00 23.360 RHS Haveri Hangal Hangal Pump House & Bore 7.50 2.25 30.00 23 Panchayat Hole 24 23.560 LHS Haveri Hangal Hangal Bore Hole Panchayat 18.00 2.25 12.50 25 23.745 RHS Haveri Hangal Hangal Cementry Public Trust 45.00 3.00 6.67 26 24.010 LHS Haveri Hangal Hangal Bore Hole Panchayat 12.00 2.25 18.75 27 25.060 LHS Haveri Hangal Hangal Compound Wall Public Trust 495.00 27.50 5.56 28 25.060 RHS Haveri Hangal Hangal Compound Wall Government 450.00 25.00 5.56 29 25.110 LHS Haveri Hangal Hangal Temple Public Trust 185.00 15.00 8.11 30 25.145 RHS Haveri Hangal Hangal Arch Panchayat 80.00 8.00 10.00 31 25.337 RHS Haveri Hangal Hangal Hand Pump Panchayat 14.25 2.25 15.79 32 25.464 LHS Haveri Hangal Hangal Compound Wall Public Trust 112.50 7.50 6.67 33 25.515 LHS Haveri Hangal Hangal Hand Pump Panchayat 12.00 2.25 18.75 34 25.770 RHS Haveri Hangal Hangal Stair Case Panchayat 32.00 10.00 31.25

53 Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-3 (Shikaripura - Hanagal)

54