Summer Edition2018Summer -2019

The WORKS CONTENTS

2 THE WORKS DIRECTOR'S McMAHON SERVICES TRANSFORMATION McMAHON SERVICES MESSAGE WEIGHS IN WITH A FOR ST MARK’S DELIVERS 26,000M2 3000T SILO DESIGN AND COLLEGE OF ROOFING AND WALL 05 06 CONSTRUCT 08 10 CLADDING 11 McMAHON SERVICES KICKING GOALS AT FORMER FOOTBALL PARK 12 HISTORY IN THE MAKING AT LOT FOURTEEN

INTRACT-McMAHON SERVICES MULTI-FACETED PROJECT BIG STEPS FORWARD JOINT VENTURE DELIVERING INTRACT MEANS UNDERTAKEN IN THE FOR WESTERN AUSTRALIA CIVIL INFRASTRUCTURE BUSINESS 14 HEART OF THE 16 18 WORKS AT OSBORNE 19 ADELAIDE CBD NAVAL SHIPYARDS WOOMERA RANGE MOUNT BUNDEY RAAF BASE INAUGRAL SAFETY AND CONTROL TRAINING AREA ROAD TINDAL TREE REMOVAL IN-HOUSE NAIDOC EVENT REMEDIATION SITE MAINTENANCE REPAIRS AND REPLACEMENT 20 WORKS 21 22 23

CIVIL ENGINEERING NEW GENERAL MANAGER GROUP EXPANSION FOR BALLESTRIN 24 25 CONSTRUCTION SERVICES

SOMERO S-485 LASER CHRISTMAS ISLAND SCREED IMPROVES THE PHOSPHATES ASBESTOS PRODUCTION AND SAFETY REMEDIATION AND 25 OF CONCRETE DELIVERY 26 STRUCTURAL WORKS

AUGUSTA POWER STATIONS WORLD DECOMMISSIONING - DEMOLITION SCAFFOLDING AND METAL AWARDS 28 SCRAPPING 29

McMAHON SERVICES RAIL FACILITY NATIONAL ENVIRONMENTAL CRUSHING DEMOLITION HEADS UP SCHOOL ASBESTOS INCIDENT AND SPILL AT OLYMPIC DAM REFURBISHMENT FOR REMEDIATION WORKS RESPONSE SERVICES 30 STEM WORKS PROGRAM 31 32 33

McMAHON SERVICES NT ROAD TO ANOTHER SHOWS THEIR SUPPORT LAND 121 STAGE NEW ADDITIONS SUCCESSFUL PROJECT FOR THE HAYDEN TWO UNIT TO FLEET 34 36 REYNOLDS TIWI COLLEGE 37 SUSTAINMENT 38 GARDEN PROJECT FACILITIES

McMAHON SERVICES McMAHON SERVICES HEALTH & ADELAIDE MAKES THE MOVE OPENS SAFETY FESTIVAL ACROSS THE UPDATE CENTRE DRIVE 40 TASMAN SEA 41 OFFICE 41 42 UPGRADE

McMAHON SERVICES SHOWS SUPPORT FOR THE CHARLES STURT MULTI-DISCIPLINARY NEW SENIOR WOMEN’S & CHILDREN’S INDUSTRIAL ESTATE PROJECT LEAVES BROADCAST APPOINTMENTS 44 HOSPITAL BEACH HOUSE 45 DEMOLITION WORKS 46 AUSTRALIA HOPEFUL 47 PROJECT THE WORKS 3 4 THE WORKS Director's MESSAGE

Above: Managing Director, David McMahon and Director, Andrew McMahon

Looking back on 2018 it has been a year of the New Indoor Sports Centre and Science the completion of additional large-scale diversification. We have delivered a number Centre Refurbishment for St Mark’s College roof replacement works over operating of projects that have required a change in Port Pirie comprising of indoor courts, processing plants, silos, conveyor belts, in how we deliver our service capabilities learning areas, glass facades, a mezzanine ship loading stacks, and over the ocean – and approach to high-risk works. Those level and a single court gymnasium. all on a remote island in the Indian Ocean. challenges have proved to be positive, In Victoria we delivered roof replacement increasing the breadth and depth of our We completed several multidisciplinary works for two supersheds at Incitec Pivot capabilities in multidisciplinary project projects that brought together the superphosphates plant facing similar delivery. expertise of our various service offering operational plant challenges. teams. The Adelaide Botanic High School An example of this is our work we have Redevelopment project is a good example Our plant and equipment fleet capability undertaken in the heart of Adelaide for the of this with personnel from our Demolition, also diversified this year. Our new plant Lot Fourteen Redevelopment, completing Asbestos, Civil and Scaffolding teams aiding acquisitions now allows for wider service the first stage of demolition works at the client Lendlease in their delivery of South offerings such as a laser screed increasing former Royal Adelaide Hospital site. This Australia’s first vertical high school in the our capabilities in monolithic concrete was a complex and challenging project heart of Adelaide’s central business district. pours, a mobile crushing plant that for many reasons including the restricted transforms demolition waste into site won fill access of the site, environmental sensitivity Demolition had another productive year material reducing haulage costs, and high of the works due to the site being adjacent completing projects at Olympic Dam mine pressure pumps for rapid industrial cleaning to the Adelaide Botanic Gardens and local site, the Charles Sturt Industrial Estate, and hydro-demolition of concrete. residents, scaffolding and encapsulation the Former Football Park and thr Augusta requirements, community and stakeholder Power Stations Decommissioning project. We made big steps toward gender equality engagement, and the management of With the latter proving to be a complex and with several women taking up management asbestos and other hazardous materials on challenging project, which was recognised roles across the Company, both through site. globally with a shortlist in the World external recruitment and promotion Demolition Awards for our collaborative internally. We continue to take practical One of the more complex construction partnership with client Flinders Power. steps to combat our industry’s gender projects undertaken by the Company inequality challenges as we strive to create a was completed this year, the design and Intract had an impressive 2018 delivering diverse and inclusive work culture. construction of a 3000t fully bolted steel silo some of their largest projects to date. Two at Morgan Cement’s Port Kembla cement key projects were remote road remediation We thank our loyal staff for the hard work clinker grinding facility. The 26m silo was works at both Woomera, throughout the year. We challenge everyday erected using a synchronised jacking and Mount Bundey in the Northern Territory. what McMahon Services can achieve. process allowing it to be built from ground In Adelaide, Intract and McMahon Services We put our collective minds to a task, see level significantly reducing working at are working collaboratively on our largest projects through to completion and strive heights risks. jointly delivered project yet, the civil for continuous improvement and client infrastructure package of works for the satisfaction. Delivery of the silo required complex Osborne South Development Project, which trucking, rail and shipping logistics when completed will support current and We thank our clients for their support from Kansas in the United States where future naval ship development, operations and ongoing opportunities to delivery the component parts of the silo were and maintenance programs in South infrastructure enabling works across manufactured. High risk crane works were Australia. multiple industry sectors. We look forward required to install two 30t conveyor galleries to strengthening our relationships and linking a 40m access tower and the existing Our Roofing team has had an excellent year continuing to achieve great things in the plant during a tight weekend shutdown delivering some of the most difficult and year ahead. window. high-risk projects they have undertaken to date. Roof replacement at Downer Rail’s David McMahon 2018 saw our Building Services team facility in Port Augusta not only dealt with Managing Director expand their capabilities delivering asbestos contaminated materials requiring a significant number of high-quality full encapsulation of the work site, but Andrew McMahon architectural finish projects for a variety also required works over operational rail Director of clients in the Defence and education infrastructure. Our long-term relationship sectors. Their standout project this year was with Christmas Island Phosphates saw THE WORKS 5 3000T SILO McMAHON SERVICES CONSTRUCTED WITH 565 CARBON WEIGHS IN WITH A 3000T SILO STEEL PLATES AND DESIGN AND CONSTRUCT 72,882 BOLTS

ADELAIDE BRIGHTON GROUP Morgan Cement International was erected. All asbestos containing material PRODUCES AND MARKETS seeking to increase the productivity at was wrapped in double layer 200µm CLINKER, CEMENT AND their Port Kembla site and engaged plastic and disposed of at EPA licenced LIME PRODUCTS UNDER McMahon Services to design and stations. Other preliminary works THE ADELAIDE BRIGHTON construct an additional 3000t silo to included bulk excavation, backfilling and achieve this outcome. a piled foundation consisting of fourteen CEMENT AND COCKBURN bored piles of 1.2m diameter socketed CEMENT BRANDS. into 4m of hard rock into geotechnically challenging ground conditions. Morgan Cement International is a Scope of Work subsidiary of the Adelaide Brighton McMahon Services led the design and Structural works included design and Group operating a cement clinker construction of the access tower, stairs, grinding facility in Port Kembla, New construct project to deliver the 3000t fully bolted steel silo 26m in height and 14m galleries for air slides and walkways South Wales. The facility was first amounting to over 180t of structural steel. constructed in the 1920s and underwent in diameter, with associated mechanical major capital upgrades in the 1950s and equipment including air slide conveyors The 3000t silo was manufactured in the 1990s. and a 40m bucket elevator. The silo was erected using a synchronised Kansas, United States and transported in jacking process that allowed it to be fourteen shipping containers to Australia. The original site had two cement storage built from ground level. This process Logistics included trucking and rail silos which each held 400t of cement. receives the highest safety ratings by from Kansas to Los Angeles, shipping Two additional storage silos, holding significantly reducing working at heights across the Pacific Ocean to Sydney, then 1000t of cement each were constructed and bringing cost savings to the overall trucking to the project site in Port Kembla. in 2008. An additional 400t silo was project delivery. McMahon Services managed the entire constructed in 2014 providing a total logistics process including customs and site storage capability of 3200t for both Preliminary site works included asbestos statutory requirements and clearance general purpose and shrinkage limited applications. cements. removal and demolition on the existing slag shed where the silo was to be

6 THE WORKS 565 carbon steel plates and 72,882 bolts undertaken within a constrained site were used to construct the silo. 38,690 inside an operational industrial facility High Risk Cranage nuts on exposed surfaces were covered with shutdown works being minimised to with plastic caps to eliminate corrosion perform tie ins to the existing plant. The A major challenge on the project was in the harsh marine environment. plant was designed and constructed to lifting two double deck conveyor galleries simplify maintenance and serviceability each weighing 30t between the top of the Water leak tests were performed of equipment including interchangeability new 40m access tower and the existing during construction of the silo ensuring of spare parts with existing plant material. plant. McMahon Services worked closely each section was leak proof prior to with Morgan Cement International to commencing to the succeeding section. ensure nil hold ups to plant operations ‘27,000 work hours and to reduce health and safety risks Piping works included PVC cement inherent in the lifting works. pipelines, electrical conduits, instrument lost time injury air piping and all associated valves. Installation was achieved using a 450t (LTI) and medical crane in heavy lift configuration. Works Electrical and instrumentation works treatment injury were completed within a tight weekend included design and construction of the shutdown window outside of cement complete electrical and controls system (MTI) free.’ trucking times resulting in nil impacts for the entire plant, switch room, lighting, of plant logistics. Wind monitoring was power supply, cabling, grounding, The silo design and construction was conducted at all times to ensure safety process control system, PLCs and compliant to Australian and European with all crane operations. SCADA including air controls and alarm standards, undergoing two independent systems. third party design reviews as well as several reviews by specialist engineering Wallbridge Gilbert Aztec were engaged consultants during construction. as the design consultants who prepared 3D design models of the silo and associated plant. All works were

THE WORKS 7 8 THE WORKS TRANSFORMATION FOR ST MARK’S COLLEGE

ST MARK’S COLLEGE IS Specialist trade works included LOCATED ON THE SOUTHERN installation of a timber sprung floor FRINGE IN THE CITY OF PORT to the sports centre, installation of PIRIE AND CATERS FOR gym equipment including retractable STUDENTS FROM RECEPTION basketball back boards, sports netting and a dividing curtain, stage seating, TO YEAR 12. installation of a glass façade to the STEM entrance, Vitra panel cladding, In 2017 the College identified an prefinished Ariaply plywood linings opportunity to strategically invest in in external and internal finishes with the existing secondary school campus feature perforated and fire rated to facilitate its teaching and learning requirements, Everbright roofing and requirements as well as provide sport cladding, acoustic sliding doors, and recreation opportunities for the perforated panel balustrades and wider Port Pirie community. sunshade finishes, external specific insignia school signage, Maxline The project works included new profiled cladding, artificial sporting purpose-built buildings, refurbishment surface, classroom laboratory of existing buildings and associated installations with chemical resistance external works. McMahon Services joinery and incorporated gas, electrical, were engaged by the college as the mechanical and water services. Principal Contractor to deliver the works through a competitive tendering process. Delivery Performance The project work comprised of a new Sports Centre with indoor courts, Due to value management design learning areas totalling 2720m2 and changes during construction, the team a new Science Centre comprising were required to fast track the program of the refurbishment and mezzanine through altering the sequences of level from an existing single court works to meet the overall program gymnasium for a total of 1080m2, objectives. Electrical and hydraulic and with the installation of an eight works were managed outside the passenger 630kg capacity lift. construction area and coordinated around school operations to assist in achieving the program. Demolition works included a detailed deconstruction of the existing gymnasium building with a new Works were undertaken within an Science, Technology, Engineering operational school environment. and Math (STEM) Building and site Project personnel received appropriate preparation for the new indoor sports Department of Communities and centre with civil works including Social Inclusion (DCIS) and Catholic stormwater installation. Education clearances with regards to working around children before commencing on site. Work zones Building works included reinforced were segregated and protected concrete footings, concrete topping with security fencing to ensure no slab and suspended slab finishes, permissible student entry to occur. 37m long structural steel roof truss with Daily activities were planned to partial onsite fabrication to the sports ensure site ingress and egress centre, with differing painted finishes activities do not occur around peak or fire protective coatings, blockwork student pick-up and drop-off times. and brick construction, architectural roofing and cladding finishes. ‘49,000 work hours

completed’

THE WORKS 9 McMAHON SERVICES DELIVERS 26,000M2 OF ROOFING AND WALL CLADDING

INCITEC PIVOT IS A GLOBAL Works included the removal and and 300mm PVC flying downpipes. DIVERSIFIED INDUSTRIAL installation of 26,000m2 of new Protective coatings were applied to all CHEMICALS COMPANY. THEIR roof cladding, gallery roof and wall protective purlins before reinstatement FERTILISER BUSINESS IS cladding. Additional works included to form a liquid membrane. Stainless THE LARGEST IN AUSTRALIA the replacement of existing damaged safety mesh was fitted to the roof. deteriorated purlins, a full-length AND DISPATCHES TWO skylight using translucent sheeting ran MILLION TONNES EACH from the ridge to the gutter line with YEAR FOR THE USE IN a 60ft boom lift providing additional AUSTRALIAN GRAIN, COTTON, access to the structure, and supporting Scaffolding Works PASTURE, DIARY, SUGAR AND the roofing and cladding removal and A major challenge on the project was HORTICULTURE INDUSTRIES. replacement process. the erection of scaffolding between the two super sheds in a width of only Incitec Pivot’s North Shore Geelong All roof sections were removed by a 1.4m between sheds. Complicating the facility produces superphosphates, crane with a drop box utilising 100t and scaffolding erection was that one roof the most commonly used fertiliser 200t cranes. Two work crews installed was higher than the other requiring the for improving pastures. The roofing and cladding using hand tools installation of two access platforms, facility includes a superphosphate and battery drills. Crews ensured that one on top of the other. All scaffolding manufacturing plant, fertiliser blends at the end of each work day no section materials had to be brought in by hand storage and dispatch centre, liquid of the roof was ever left uncovered. and erected as there was no access fertiliser blending plant, fluorosillcic Safety mesh and harnesses protected for cranes or other support equipment. acid manufacturing plant, storage and crews from the risks of working at dispatch, sulphuric acid storage and o heights on the 35 pitch roof. Scaffolding had to be staged working dispatch, and a production chemical around operational requirements of testing laboratory. Roof and wall sheeting consisted the fertiliser plant. Therefore, a full of 0.48 Zincalume Custom Orb and time scaffolding crew remained on site Ampelite Webglas GC, with opal at all times erecting and dismantling translucent skylights in Custom sections of the scaffolds to meet Scope of Work Orb profile to match Zincalume roof client operational requirements and sheeting. Flashing installation works the roof team’s delivery program. The The scope included the re-roof of ensured a watertight roof system. scaffolding was constructed along the super sheds 1 and 2 at the North Shore length of the two 322m long buildings Geelong fertiliser facility, delivered in a Stormwater upgrade works included to a height of 19.5m. staged work sequence. 500m of new gutters and 150mm

10 THE WORKS McMAHON SERVICES KICKING GOALS AT FORMER FOOTBALL PARK

ON TUESDAY 21ST AUGUST, Once cutting was complete, the 9t (which will be remaining) and the internal McMAHON SERVICES section was then lifted vertically and strip out and mechanical demolition of ACHIEVED A MAJOR carefully lowered to the ground adjacent stadiums and grandstands. MILESTONE FOR THE to the remaining tower structure. A 25t DEMOLITION WORKS AT Franna crane ensured that the light tower Over 2000t of steel and 70,000t of could be laid horizontally to minimise concrete and brick will be demolished THE WEST DEVELOPMENT damage to the tower and maximise the and recycled by project completion. OF THE FORMER FOOTBALL salvageability of its component parts. PARK IN WEST LAKES 14KM The demolition of the original members FROM ADELAIDE, WITH THE The process was then successfully grandstand will be occurring in January SUCCESSFUL DISMANTLING repeated two more times through the 2019, with the project completion date to OF THE FIRST OF FOUR 63M various tower levels, with ground level be March 2019. The former site will be LIGHT TOWERS, ACHIEVED deconstruction being achieved. utilised for the future WEST development, THROUGH A SERIES OF offering an array of residential and retail COMPLEX CRANE LIFTS AND This was the first of four light towers to offerings. OXY-LPG CUTTING WORKS. be dismantled at the former Football Park ground, which once had a seating Using a combination of a 250t Liebherr capacity of 62,000. ‘Four 63m light hydraulic crane with a reach of 72 vertical meters and guide plates welded inside McMahon Services has since completed towers demolished the structure, the light tower was held the remaining light tower deconstructions in place while one tradesperson cut the and have also completed other with a 250t Liebherr metal frame and another tradesperson demolition works on site including service crane with a reach of acted as a spotter. disconnections, asbestos removal and remediation, structural works around the separation of the Checkside Tavern 72m.’

THE WORKS 11 HISTORY IN THE MAKING AT LOT FOURTEEN

THE REDEVELOPMENT OF strip away asbestos containing LOT FOURTEEN, THE FOR- Scope of Work coatings at the rate of ten labourers MER ROYAL ADELAIDE HOS- or more, creating a perfectly cleaned Demolition and remediation works metal surface. PITAL SITE, AS AUSTRALIA’S included: FIRST CREATION AND INNO- Over 2579 drums of predominately VATION NEIGHBOURHOOD, ff 6m high Cobalt Wing, friable asbestos contaminated IS A MAJOR ECONOMIC DE- ff 9m high Hone Wing, and materials totalling approximately 298t VELOPMENT OPPORTUNITY ff 28m high East Wing. were sealed and removed from site. FOR SOUTH AUSTRALIA. Asbestos was discovered in many All medical, chemical and other unexpected locations and was 50% The first stage of this redevelopment hazardous materials associated greater than first expected. The project is the demolition and remediation with the hospital were removed team took on the risk of remediating work for the 6m high Cobalt Wing, 9m and relocated to the new Royal all discovered asbestos and despite high Hone Wing and 28m high East Adelaide Hospital prior to works the additional works required, kept the Wing buildings, as well as the former commencing. Early works included project to program. Emergency Carpark on North Terrace. erecting hoarding and isolating and decommissioning services including Other works included the installation Renewal SA engaged McMahon electrical, communications, water, of reinforced blockwork infill walls Services to undertake the Stage 1 medical gases and wet and dry fire in supply tunnels, link corridors and works, which included self-performing systems. services tunnels to other operational all scaffolding works, based on our buildings within the hospital precinct. past track record in similar projects, McMahon Services utilised its high- Mechanical demolition was undertaken and on the breadth and depth of our pressure Hammelmann Pump to by deconstruction excavators with systems, people, plant and equipment. produce 140MPa pressure at 70L/m high reach booms and a variety of using a Conjet Nalta 101 attachment attachments including shears, hammers to create sufficient pressure to and grabs. hydro-demolish asbestos containing fire-rated materials, coating steel Detailed 3D demolition staging plans beams within sealed sections of the were developed for the project in buildings. The Hammelmann Pump conjunction with our design partner demonstrated that it could completely Wallbridge Gilbert Aztec.

12 THE WORKS vicinity of commercial, Government was 50m long and 25m high making and residential properties, as well as it one of Adelaide’s largest temporary '6000t of bricks the Adelaide Botanic Gardens only outdoor art pieces. The art piece also a matter of metres from the main provided shade for the construction and concrete and demolition works. Significant effort was workers as well as minimising dust 1747t of steel was expended in minimising the impact of and debris, while delivering activation our operations for site tenants, local to Adelaide’s prominent East End. The demolished and stakeholders and members of the artwork changed and developed over public. time as it came down piece by piece in recycled. With 95% of conjunction with the demolition. the materials being recycled into new Scaffolding Works Community and products through The scaffolding works required the provision of 9600m2 of containment Stakeholder Engagement our sister company scaffolding constructed to a height ResourceCo.' of 30m around selected structures. The project delivery team included Decks and frames were constructed dedicated community and stakeholder Civil reinstatement works occurred to encapsulate asbestos and other specialists to work closely with toward the end of the project and hazardous materials works inside the Renewal SA, ensuring all parties included reconnection of sewer pipes, three buildings. affected by the works received regular backing and compacting earthworks, and appropriate communications. paving footpaths, and capping and Included in the scope of works was the Such communications included a sealing stormwater infrastructure. construction of a 25m or seven storey project website, a 1300 number, chute for materials removal, installation an email address, fact sheets and Plant and equipment utilised on of a major temporary artwork (designed timelines for the works, as well as the tightly constrained site included by Vans the Omega) as part of the regular and an-needed updates and PC1250, PC850 and PC450 demolition scaffold wrap and the construction activity notifications. The project excavators, a PC320 excavator, skid of a temporary emergency access team regularly provided Renewal steers, 25t Franna crane, 100t boom bridge scaffold structure to replace a SA with advice noting any upcoming crane and a dust suppression system demolished gantry bridge previously demolition, asbestos removals or that hooks directly into the local water linking two buildings. other works that had the potential to mains network reducing the need for impact stakeholders. water trucks which would otherwise Scaffolding work was ongoing for congest the worksite unnecessarily. The the duration of the works, catering The project team supported various PC1250 demolished structures at a rate to the work programs of the internal Renewal SA public engagement of 200t per day and the PC850 at 50t per strip-out, hazardous materials and projects, including a major community day. demolition crews’ requirements. open day in July 2018, with McMahon Workforce peaked at 10 personnel Services providing a 25t excavator Workforce peaked at 80 personnel delivering 7500 workhours without and 3t bobcat for attendees to climb achieving 89,860 workhours over the life incurring a single work health, safety on board and have their photo taken. of the project. or environmental incident. McMahon Services also assisted in establishing a viewing platform on site Stringent environmental and noise The East Wing was transformed with to enable the general public to watch controls, community and stakeholder a large-scale art piece by South the demolition and redevelopment engagement, and traffic management Australian artist Vans the Omega, works in progress at set viewing times. strategies were implemented for which was printed on shade cloth to the project due to the site’s close encapsulate the building. The artwork THE WORKS 13 MULTI-FACETED PROJECT UNDERTAKEN IN THE HEART OF THE ADELAIDE CBD

THE $100 MILLION ADELAIDE Asbestos remediation included internal Civil demolition works included stripping BOTANIC HIGH SCHOOL sheeting, floor and vinyl tiles, removal grass and disposal, stripping 100mm of WILL OPEN FROM TERM 1 of windows and sealants containing topsoil and stockpiling for reuse, removal 2019, PROVIDING STUDENTS asbestos, grinding and infill of existing of existing kerbing, asphalt and concrete, FROM INNER-CITY SUBURBS concrete floors to remove asbestos tree removal, removal of existing street adhesives and removal of cement furniture such as fencing, benches WITH GREATER ACCESS TO sheeting. Over 50t of asbestos containing and bike racks, and the removal of two HIGH QUALITY SECONDARY materials were remediated from site, concrete tanks. LEARNING. THE SCHOOL double wrapped in encapsulating 200µm WILL START WITH YEAR 8 plastic sheeting then trucked to EPA Bulk earthworks for the basement AND 9 STUDENTS INITIALLY, licenced asbestos receiving stations. included preparing piled platform for GROWING TO 1,250 piling rig, removal of the platform and STUDENTS BY 2021. Due to the restricted access within the stockpiling surplus material on site, bulk Reid building, all works were undertaken excavation to bench level for basement Adelaide Botanic High School is the by hand using manual demolition and stockpiling surplus material on first vertical school in South Australia. techniques. site, trim and compaction of basement, The design features the completely supply and placement of 150mm PM refurbished Reid building which has six 2/20 for basement, backfilling basement learning levels plus a basement and Scaffolding around the retaining wall with site won open-planned plaza space at ground material, Agri pipe and screenings, and level. This building is linked by a glass Scaffolding works included full height retrimming and compacting basement atrium to a brand new seven-storey scaffold to the north and south ready for detailed excavation. building also with a basement and elevations, building encapsulations for rooftop terrace. asbestos removal works, construction Stormwater system works included the of a 30m drop chute for removal of supply and installation of pits, pipes Leadlease as the Principal Contractor demolition waste and scaffolding on and hydro-system, backfill with Sa-C for the project engaged McMahon the internal atrium levels. Over 3000m2 sand and site won material, supply Services to undertake various works of scaffolding was erected across the and installation of two pump stations on site including asbestos remediation construction phases utilising McMahon including rising main system. and internal strip out demolition of the Services Layher Modular and Ringlock Reid building, scaffolding and access scaffolding systems. Building Code of Other works included the construction of solutions and site earthworks and Australia compliant edge protection was access roads with concrete and spray stormwater works. installed with all scaffolding. seal, the construction of access paths, excavation of pile caps and all footings in the basement, backfilling pipe caps and Demolition and Asbestos Bulk Earthworks and dewatering. Earthworks totalled 22,000m2 and Remediation Stormwater stormwater totalled 300m of reinforced concrete and uPVC pipe installed. The demolition scope included external Civil works included all services The project required extensive traffic plant enclosure, external façades, identification, isolation and management and the detailed application ground floor northern balcony and disconnections, diversion of the existing of staged works in a restricted and tight link-way floor penetrations, internal stormwater system, pavement and workspace. basement and ground demolition and underground tank demolition, clear and internal demolition of level 1 to 5, removal grub, bulk earthworks, construction of a of a slab and retaining wall on the temporary access road, construction of northern and eastern sides of the site, all hardstands comprised of compacted ‘95% recycling and coring and cutting of penetrations subgrade and 150mm crushed rock, for new services. Over 730t of brick earthworks to prepare for piling platforms for demolished and concrete, 140t of construction with a 400kPa bearing capacity, and demolition waste and 90t of scrap basement earthworks, temporary materials’ metal were removed and sent offsite retaining wall construction, excavation for recycling. The project achieved a of pile caps and footings, landscaping 95% recycling for demolished materials. earthworks, stormwater and drainage.

14 THE WORKS 22,000M2 OF EARTHWORKS 3,000M2 OF SCAFFOLDING 44,000 WORK HOURS COMPLETED

THE WORKS 15 BIG STEPS FORWARD FOR WESTERN AUSTRALIA

IN 2018 McMAHON SERVICES instrumental to the successful delivery INVESTED IN AND EXPANDED of several of our most complex projects Pilbara Expansion – THE OPERATIONS OF OUR including the $24 million Nelson Point WESTERN AUSTRALIAN North Yard Decommissioning, the What it entails? BUSINESS ALONG WITH $672 million Strategic Indigenous Housing and Infrastructure Program In 2018 McMahon Services clocked A RESTRUCTURE OF OUR and the Airlie Island Hydrocarbon over 14 years of continuous operations MANAGEMENT TEAM. Storage Tanks and Infrastructure in the Pilbara and committed to Deconstruction to name a few. increase our presence, and range of Austin McWilliams, a 10-year veteran services we offer to clients throughout with McMahon Services who has Adam Keenan accepted an expanded Northern Western Australia. delivered some of our largest projects role of Manager – Scrap Metal including the $24 million Nelson Point Recycling, responsible for all Australian This decision was made on the North Yard Decommissioning was scrap metal recycling, operations, back of the tremendous effort appointed as Manager – Western trading and business development. and achievements by the team at Australia. Austin brings to the company Adam has project managed our Metalcom in Karratha along with the a wealth of experience in the mining, largest scrap metal projects including successful demolition, remediation shutdown and statutory compliance the 50,000t of steel for the Augusta and decommissioning projects carried industry sectors and has a strong Power Stations Decommissioning and out for BHP, Rio Tinto and other industry 15-year track record managing the Rio Tinto Scrap Rail Project which leaders. projects throughout Western Australia. processed up to 30,000t tonnes of obsolete rail per annum over 15 years. These achievements coupled with a Phil Bubner, our former Western resurgence of investment in the iron Australia Manager and McMahon . ore, oil and gas and the mining sectors Services 40-year expert veteran took have been the drivers behind the on the important role of Manager – company’s decision to strengthen our Northern Western Australia. Phil was Pilbara business.

16 THE WORKS Adam Keenan Austin McWilliams

Kate McWilliams Phil Bubner

McMahon Services and Metalcom Both the SafeCheck and Metalcom SafeCheck Acquirement clients. Eventually McMahon Services business names will continue trading will expand SafeCheck into other as they are. However, the company An important part of the new Western States and Territories across Australia. entity will be McMahon Services Australia structure was the purchase Australia Pty Ltd. of SafeCheck, a statutory compliance Manager Kate McWilliams took inspection, risk management and on responsibility of the SafeCheck These new investment initiatives have consultation business. business as an integral component been made on the back of all the hard of the purchase and we are excited work and achievements made by the The SafeCheck business has a to have Kate and the SafeCheck Western Australian team members and successful track record since staff onboard and wish them a warm we sincerely thank all those involved commencing operations in Kalgoorlie welcome to the McMahon Services to date and ask everyone to embrace in 2008. SafeCheck was founded by family. Along with Kate we are joined the new expansion plans and the Austin and Kate McWilliams with a by Operations Manager Kira Burnie, opportunities they will present to us all. team today of three employees and Supervisor Goldfields Region Brad over ten subcontractors. Nicklin and Statutory Inspection Technician Adina Newman. McMahon Services believe SafeCheck presents a strategic opportunity for the company, whereby we will be able to expand on the services SafeCheck offer to their existing customer base and in turn, we can immediately offer all SafeCheck services to the existing

THE WORKS 17 INTRACT-McMAHON SERVICES JOINT VENTURE DELIVERING CIVIL INFRASTRUCTURE WORKS AT OSBORNE NAVAL SHIPYARDS

SINCE EARLY 2018, INTRACT facilities including haul roads, carparks, business in a meaningful way that AUSTRALIA AND McMAHON and hardstands for a temporary site would go above and beyond the SERVICES HAVE WORKED precast yard. mandatory contract requirements set COLLABORATIVELY ON by Government. The Intract-McMahon THEIR LARGEST JOINTLY The project is currently delivering a 18% Services team provided the optimal Indigenous participation result, with the outcome for Leadlease as Intract could DELIVERED PROJECT, majority of Indigenous personnel on site provide Indigenous ‘boots on the THE DELIVERY OF CIVIL being made up of plant operators and ground’ while McMahon Services were INFRASTRUCTURE site labourers who are receiving ongoing able to mobilise quickly and utilise their PACKAGE OF WORKS AT on the job training. civil construction expertise and track FOR THE OSBORNE SOUTH record to deliver the civil infrastructure DEVELOPMENT PROJECT. The project’s Indigenous trainee safety works. advisor, James Fry, has progressed in his To date the Intract-McMahon Services skills development whilst on the project With the current works under contract, team has delivered a variety of and is now a fully qualified Site Safety the Intract-McMahon Services delivery civil infrastructure works across Advisor leading safety management for team will continue on site well into 2019. the 185,000m2 site including bulk the project team across the project. earthworks, detailed earthworks, piling When complete, the Osborne Naval pads, demolition works, pile trimming, The opportunity for this jointly delivered Shipyards will support current and future heavy-duty pavement construction, project came about when the Osborne naval ship development, operations and asbestos remediation, soil management, South Development Project Managing maintenance programs. stormwater management, common Contractor, Lendlease Building, were services trenching and temporary site looking to engage with an Indigenous

18 THE WORKS INTRACT MEANS BUSINESS

ON WEDNESDAY 26TH John and Warren discussed numerous Warren is currently a columnist for The SEPTEMBER, JOHN BRIGGS topics including the services we provide Australian and hosts his own show on Sky WAS FORTUNATE ENOUGH our clients, our mission for our Indigenous News Australia, Mundine Means Business, TO BE INTERVIEWED BY work force and how Intract maximise which airs on Sky News at 4.30pm ACST INDIGENOUS LEADER the use of local Indigenous goods and and 5.00pm AEST each Sunday. services. WARREN MUNDINE, FOR You can watch the informative interview HIS SKY NEWS TV SHOW, Warren Mundine is an Australian with Mundine and John on the Intract MUNDINE MEANS BUSINESS. Aboriginal leader and the former National website. President of the Australian Labor Party. Mundine Means Business www.intract.com.au/intract-means- highlights the success and For his entire life, Warren has been fighting business/ entrepreneurship of Australia’s racism and discrimination and is one of Indigenous society and examines Australia’s most recognised, respected where potential for improvement lies. and revered activists and agents for improving his people’s standing.

THE WORKS 19 19KM OF ROADWORKS

WOOMERA RANGE SAFETY AND CONTROL REMEDIATION SITE WORKS

THE DEPARTMENT OF The Woomera Test Range is managed Plant and equipment utilised included DEFENCE'S WOOMERA by Air Force Test Ranges Squadron, a a D6 dozer, 22t excavator, 140M and RANGE COMPLEX IS LOCATED command unit of the Air Warfare Centre. 14M graders, two 10t rollers, two 40t IN SOUTH AUSTRALIA, articulated dump trucks, three 15,000L APPROXIMATELY 500KM Due to the ageing systems for aerospace and two 26,000L water trucks and two test, evaluation and development trials W380 loaders. NORTHWEST OF ADELAIDE, at the Woomera Test Range, Defence AND COMPRISES OF BOTH operators were restricted in their ability Works totalled 137,700m2 of road THE WOOMERA TEST RANGE to execute complex activities from using base materials approximating 19km AND THE NURRUNGAR TEST obsolete range equipment. of roadworks, 10,400m2 of hardstand RANGE. pavements and two wastewater National Aboriginal Construction lagoons. Workforce peaked at 14 The function of the Woomera Test Partners Projects (NACP Projects) personnel completing 16,800 work Range is to provide a specialised were engaged by the Department of hours across all sites. operations environment in support of Defence to deliver the Woomera Range directed whole-of-Defence activities for Safety and Control System Remediation the testing of war materiel and other project. Four of the civil work packages 2 activities in the wider national interest. for the project were awarded by NACP 137,700m of road The range also supports a wide variety Projects to Intract Australia. base materials of trials covering many Defence related technologies including ground based Project works included the delivery of weapons systems, explosive ordnance building hardstand plateaus, spray seal 2 and hazardous materials, and pavement areas, concrete footpaths, 10,400m of specialised force preparation activities. wastewater lagoons, stormwater, hardstand reinforced concrete box culverts, swales and ponds, access roads and pavements compounds using 150mm thick PM 2/20 rubble materials and security fencing in several remote outback locations in the Woomera Defence Range.

20 THE WORKS 25% OF ALL EMPLOYEES ON SITE WERE FEMALES

INDIGENOUS PARTICIPATION OF 30% ACROSS THE PROJECT

MOUNT BUNDEY TRAINING AREA ROAD MAINTENANCE REPAIRS THE MOUNT BUNDEY Road repair works across all locations TRAINING AREA IS A LARGE followed a consistent methodology that Indigenous Participation DEFENCE TRAINING AREA included light reformation grading and stabilising, ripping and reformation up Indigenous participation for the project LOCATED APPROXIMATELY was 30% with three full time Indigenous 120KM EAST SOUTHEAST OF to 150mm deep, medium reformation, grading and stabilising, ripping and personnel on the Intract delivery team. DARWIN AND SPREAD OVER reformation up to 300mm deep, heavy 117,300HA. reforming, grading and stabilising, and An Indigenous Junior Project ripping and reformation up to 500mm Indigenous Junior Project Manager In accordance with the Federal deep. Nicole Brown supported the Project Government’s Indigenous Procurement Manager through the delivery of Policy, Intract were invited to tender Rock drop dams were placed along the works. She was provided with for and were ultimately awarded the drainage lines to dissipate runoff upskilling and on the job training and project to undertake road repair and water, reduce flow velocities and was responsible for subcontractor upgrade works across the Mount capture sediment and nutrients that engagement, progress claims, client Bundey Training Area. would otherwise be lost from the site. deliverables, scheduling, inspection and test plan development, and Several concrete floodways were Hand Over Take Over (HOTO) constructed at various intervals to documentation. Scope of Work prevent erosion of the roadway during weather event. Construction included Nicole concurrently undertook tertiary The scope of works required the all associated ground preparation, study in project management during delivery of 27km of road construction formwork, concrete construction the works. comprising of 145,000m3 of detailed totalling 120m3, curing and the earth works over a large geographic installation of road signage. Other area. Several project teams were works included the installation of road mobilised at various sites to deliver the furniture and signage. works on multiple fronts.

THE WORKS 21 43% INDIGENOUS PARTICIPATION RAAF BASE TINDAL TREE REMOVAL 75 AUSTRALIAN NATIVE AND REPLACEMENT MILKWOOD TREES PLANTED

ROYAL AUSTRALIAN AIR A secondary risk was that 1% of flying FORCE’S BASE TINDAL IS foxes carried Australian Bat Lyssavirus 15KM OUTSIDE KATHERINE (ABLV). If the virus is transferred to Scope of Work AND 320KM BY ROAD humans through bites or scratches and SOUTHEAST OF DARWIN IN not treated before symptoms set in, it The scope of works included felling 52 causes serious illness which results in THE NORTHERN TERRITORY. African Mahogany trees spread across paralysis, delirium, convulsions and ALTHOUGH THE AIRFIELD the Base including trees adjacent to death. operation Base buildings, removing WAS CONSTRUCTED stumps and root balls and storing IN 1942, IT IS THE AIR The Department of Defence identified all timber in a designated area. The FORCE’S YOUNGEST MAJOR that the majority of the fruit bats nested wood was then mulched producing OPERATIONAL BASE AND in 52 African Mahogany trees across over 1000t of wood chips. The ONE OF AUSTRALIA’S MOST the base. The African Mahogany is second component of the works was IMPORTANT DEFENCE also considered an invasive species in the excavation of planter holes then INSTALLATIONS. Australia and therefore it was decided planting and irrigating 75 Australian that the trees should be replaced native Northern Territory Milkwood Two species of flying fox prominent with native trees, simultaneously trees (Alstonia actinophylla) across the in the Katherine region, the little red sending the flying foxes off the Base Base. The project team established fruit bat (Pteropus scapulatus) and to find elsewhere away from human and implemented a maintenance black flying fox (Pteropus alecto), habitation. elsewhere away from program for the new trees for a period had become prevalent on the Base human habitation. of 18 months following completion of with numbers reaching as high as the works. 500,000. Although the risks were small, Through a competitive tendering the density of fruit bats on the Base process managed by Aurecon, Intract Other works included service presented a collision risk potentially Australia was awarded the project to detections, sediment control, damaging aircraft engines during take- remove the African Mahoganies and implementing safety barriers to protect off and landing. plant new native trees across the Base the Milkwood trees, traffic management, in their place. laying and commissioning irrigation lines, watering, fertilizing, pruning, weeding and applying pesticides. A local arborist was consulted during the works to ensure maximised tree 22 THE WORKS propagation. INAUGRAL IN-HOUSE NAIDOC EVENT ON THURSDAY 12TH JULY Staff participated in the painting of our It was great to bring the Adelaide office INTRACT AUSTRALIA AND ‘Spirit of One’ transportation vehicle, personnel together and celebrate McMAHON SERVICES designed by proud female Aboriginal NAIDOC Week. Thank you to all staff CELEBRATED THEIR FIRST artists Susan Betts and Gabriel and site personnel who participated INAUGURAL IN-HOUSE Stengle. in this event, we look forward to celebrating again next year! NAIDOC EVENT, HELD AT THE All personnel were lucky enough to ADELAIDE OFFICE. indulge in some delicious bush tucker provided by Tauondi College – a post- Aboriginal Elders Uncle Fred Aguis secondary Indigenous school, and a and Aunty Georgina Williams opened beautiful music performance by proud the event with a traditional Welcome Anangu woman Bianca Leicester. to Country and Smoking Ceremony.

THE WORKS 23 GROUP CIVIL ENGINEERING EXPANSION 2018 HAS SEEN A SIGNIFICANT INVESTMENT IN NEW PEOPLE IN THE CIVIL ENGINEERING GROUP FOR SOUTH AUSTRALIA. AS PART OF OUR STRATEGY IN ESTABLISHING THE INFRASTRUCTURE AND TRANSPORT DIVISION UNDER MEHDI JAVANMARD, WE HAVE A SECURED NUMBER OF CIVIL CONSTRUCTION LEADERS TO BRING ADDITIONAL ENGINEERING AND CONSTRUCTION EXPERTISE INTO THE GROUP.

With an existing strong engineering base diverse as the Cook Islands, East Timor, the including developing win strategies and within the Civil Division and completed United States, New Zealand and Australia. first principles estimating. Alan has led projects bolstering our track record we are and won major civil infrastructure projects ready to take our next steps in our planned He joins the Civil Engineering team taking for clients as diverse as the Department of strategic growth. up management of the estimating team and Planning, Transport and Infrastructure, SA leading business development activities for Water and AGL. civil projects, focused predominately on local government and developers. Alan is responsible for managing cross- divisional proposals and provides bid management leadership for major projects across all operations. Alan’s attention to client needs is born from understanding operational requirements of assets and developing engineering methods and innovations to deliver maximum value for Steve Kochergen money to clients. Manager, Infrastructure and Transport

Steve Kochergen has joined McMahon Carmine Pastore Services as our new Manager - Infrastructure Senior Estimator and Transport. Steve will be responsible for driving new business opportunities Carmine joins the Civil Engineering team in the utilities, major infrastructure and as a Senior Estimator, bringing over 35 transportation sectors. He assists with years of experience in civil estimating, strategic business development across with experience across earthworks, the company and aligns our client account concrete works, roads, bridges and water management processes to ensure infrastructure. Adam Polkinghorne the full breadth of our capabilities are Programmer / Scheduler communicated to our client base. He has led major tender estimates for a variety of civil construction projects delivered Adam has over 16 years of programming, Steve has over 20 years of experience in across South Australia and nationally for a scheduling, cash flows, resource engineering design, project management, variety of government and private sector histograms and staging plan experience construction management, strategic infrastructure asset developers and owners in a variety of industries including rail, business development and state including the Department of Planning, construction, services, power, resources, management roles in the civil construction Transport and Infrastructure and SA Water. transport and water sectors. His industry. qualifications include a Certificate IV in Business Human Resources.

This team has been responsible for the tendering and successful delivery of many construction projects around Australia.

The Civil Engineering Group including the addition of the new team members will assist Alan Pollitt in our strategic growth in infrastructure, Charles Hatcher Pre-Contracts Manager nationally targeting projects in transport Business Manager (roads, bridges, rail, and intermodal), water Alan joins the Civil Engineering team and power and will also work strategically Charles has 18 years of experience bringing to our company more than to assist our other divisions, states and in contract management, business 15 years of experience in engineering regional operations. development, biosecurity, resource construction in both project delivery and planning and logistics in locations as estimating. His expertise in tendering

24 THE WORKS SOMERO S-485 LASER SCREED NEW GENERAL IMPROVES THE PRODUCTION AND SAFETY MANAGER OF CONCRETE DELIVERY During the early planning stages of a major Department of Defence project which required significant concrete works, the Ballestrin team FOR BALLESTRIN identified that the use of a laser screed would significantly reduce labour costs, improve safety through minimised manual handling, dramatically improve quality and accuracy of finished concrete levels CONSTRUCTION and tolerances, and allow for a series of continuous monolithic, joint- free pour for the slab that is over 5000m2.

SERVICES Together with McMahon Service’s Plant and Equipment team and the Work, Health, Safety, Environmental and Safety team, Ballestrin identified that the best laser screed on the market was the Somero IN ADDITION TO OUR NEWEST TEAM S-485. Only developed and released to the market in 2017, the Somero MEMBERS WE ALSO WELCOME S-485 offered many advantages that would put Ballestrin at the forefront MICHAEL HYDE TO THE McMAHON of floor slabs concrete. SERVICES FAMILY! Advantages of the Somero S-485 include: Michael joins us from York Civil, and brings over ff Reducing labour costs on larger pours: instead of two rakers and 20 years’ experience in the civil industry, delivering one shovel behind a hand screed, one operator can work the a wide range of infrastructure projects including machine transport (roads, bridges and rail), water, power, marine, resources and mining and has a strong ff Easily overcomes difficulties posed by hand screeding fibre focus on major concrete structures. reinforced concrete ff Quality and accuracy of levels and tolerances is dramatically With Michael’s leadership we see this as a significant improved through laser guiding technology opportunity to capitalise on Ballestrin’s expertise and apply it to growing the business with the significant ff Safety is dramatically improved by minimising the risks of back or infrastructure spend forecast for South Australia and other injury caused by hand screeding such as sprains, strains and nationally. factures, and skin irritation and chemical burns from prolonged contact between fresh concrete and skin surfaces and eyes Michael will also provide support to the Civil ff The Somero S-485 has the capacity to screed in two planes, and Engineering Group leveraging his experience and can be upgraded to three-dimensional operation existing relationships to maximise current and future opportunities ff Can operate on fabric reinforcement, bar reinforcement and fibre.

McMahon Services purchased the laser screed in mid-2018 making it one of the first Somero S-485 to operate in South Australia. Ballestrin have successfully used the S-485 on the remote Defence site in outback South Australia, and will also deliver concrete slab works at McMahon Services’ head office in Adelaide.

THE WORKS 25 CHRISTMAS ISLAND PHOSPHATES ASBESTOS REMEDIATION AND STRUCTURAL WORKS

CHRISTMAS ISLAND IS Loading roof, 2000m2 of roofing for practices ensured that no rain event LOCATED IN THE INDIAN the Upgraded Warehouse, 5000m2 for impacted mine operations at any time. OCEAN 3,400KM FROM the Sample Shed, two Transfer Sheds 2 AUSTRALIA WITH A LOCAL totalling 300m , 24 houses including Project peaked at 14 personnel with 2 POPULATION OF 2,000 timber repairs totalling 5800m , and an average workforce of 10 delivering 2000m2 of roofing for conveyor belts the works over an almost continuous RESIDENTS. CHRISTMAS and walkways. Over 30,000m2 of roof three-year period. 98,000 work hours ISLAND PHOSPHATES was replaced across the mine. were completed without a single Lost MINES AND EXPORTS Time Injury (LTI), Medical Treatment APPROXIMATELY 650,000T Many of the structures were situated on Injury (MTI) or environmental incident OF BULK PHOSPHATE ROCK ship loading infrastructure over water recorded against the project. AND 72,000T OF BAGGED or on buildings construction on top of PHOSPHATE PER ANNUM. silos requiring works to be undertaken Plant and equipment utilised on the at heights of up to 40m. Many roofs project included two 45ft boom lifts After the success of McMahon Services were constructed at up to 35o to the and a 100t crane. All three items first asbestos removal and remediation horizon. These challenging conditions were purchased by Christmas Island of several warehouses and workshops required stringent safe work method Phosphates. McMahon Services on the mine, Christmas Island statements including the use of safety personnel trained local mine personnel Phosphates reengaged McMahon harness, cranes and scaffolding with on how to safely operate and maintain Services to undertake additional works edge protection which progressively each item. The high humidity on of a similar nature on site. followed work fronts. Over a 100t of the island occasionally affected the scaffolding was utilised on the project electrics on the crane requiring a on a continuous basis. full-time electrician onsite to ensure all plant and equipment operated Scope of Work Mine operations were temporarily shut at capacity at all times. Works were down in roof remediation work areas as undertaken on a fly in fly out roster of The project involved removing roofing required. Due to the humidity and the five weeks on site and one week offsite. materials containing asbestos and heavy and often unpredictable rainfall, replacing with iron roofs and purlin all roofing works were completed at Asbestos containing roofing materials 2 replacements. Works included 3000m2 the end of each work day. On days totalled 30,000m which were wrapped of roof replacement for the Drier and of high likelihood of rain works were in 200µm plastic in 15 sheet lots Transfer Hut, 600m2 for the Wet Bin postponed. Tarpaulin covers were and disposed of under asbestos roof, 8500m2 of roofing and 2000m2 used as an additional measure to conditions at the local waste receiving of cladding for the Rock Bin and Ship keep rain out of mine buildings. These station. Replacement roofing materials were procured in Perth with a six-week lead time for delivery. Complicating procurement were the swells in Christmas Island’s harbor which sometimes resulted in ships being unable to berth for up to two weeks until swells calmed. This risk was OVER incorporated into all delivery programs. 2 30,000M '98,000 work hours without a single LTI OF ROOF WAS or MTI' REPLACED ACROSS THE MINE.

26 THE WORKS THE WORKS 27 AUGUSTA POWER STATIONS DECOMMISSIONING - SCAFFOLDING AND METAL SCRAPPING

THE AUGUSTA POWER In September 2015, Flinders scaffolding, delivered internally STATIONS ARE LOCATED ON Power entered into an eight month by McMahon Services Events and THE TIP OF THE SPENCER collaborative planning period with Scaffolding team. GULF, AND HAVE PROVIDED McMahon Services on how best THE SOUTH AUSTRALIAN to demolish, asset salvage and Scaffolding works were ongoing and decommission the three power constantly changing during the life of AND NATIONAL ELECTRICITY stations and associated assets. A key the project. Scaffolding was erected for MARKET WITH POWER SINCE objective was the development of a manual internal demolition works and 1954. methodology that ensured a safe and for hazardous materials containment, effective demolition process whilst especially for asbestos remediation The stations included the 90MW maintaining a strong legacy for the works. Over 400t of steel or 22,000m2 Playford A Power Station, the 240MW business in the region. of scaffolding was continuously Playford B Power Station, and the erected and dismantled following the 544MW Northern Power Station. The two companies then entered work crews for the various stages of Generation was secured through the into a formal alliance contracting the works. Scaffolding crews were sole supply of coal from the Leigh arrangement to create a single team equipped with full hazardous materials Creek Coalfields. Coal was delivered working unanimously, collaboratively, personnel protective equipment during to the power stations via a 250km cooperatively and acting in good faith the cleaning of and dismantling of dedicated rail line. to make best-for-project decisions. scaffolds for contained work areas. Early works documentation and On 9th May 2016, the Augusta Power planning was undertaken between 2 Stations generated power for the last October 2015 and May 2016 working '22,000m of time and was then disconnected from with Flinders Power during the final the power network, ready to commence operations and shutdown period. scaffolding was the demolition and decommissioning Detailed programs and cost plans were erected' of the facilities. developed during this period which complemented a full suite of project Major risks for the project were The decision to close the Augusta plans endorsed by client, regulator working at heights, hot weather, Power Stations was made at the and independent consultants. working adjacent to mechanical conclusion of a detailed Alinta Energy demolition works undertaken by Board strategic review. During this demolition excavators and hazardous process Flinders Power consulted materials. Despite these risks, works extensively and investigated a range were completed to schedule with of options with key stakeholders, Scaffolding the main demolition works and were including the South Australian completed without incident. Workforce Government. McMahon Services mobilised to site in June 2016 and the first demolition peaked at 10 and performed 10,000 works commenced shortly thereafter. work hours over the life of the project. 28 THE WORKS A key component of the work was WORLD DEMOLITION AWARDS

McMahon Services is pleased to announce that in collaboration with Flinders Power and Precision Demolition, we were shortlisted for this year’s World Demolition Award for the Augusta Power Stations Decommissioning project in the 'Collaboration in Demolition' category. they were craned out and loaded onto The project committed 330,000 work Metal Scrapping barges with 1200t capacity per barge. hours with only one variation in the two The barges then proceeded up river to years due to unforeseen asbestos. The A significant outcome of the project the steel mill. Scrap was discharged at use of the world’s largest demolition was the 50,000t of ferrous and non- the mill using a similar method used excavator significantly reduced the ferrous scrap metals generated during at the port. the demolition works, which was sold risks of manual demolition crews working inside the plant. Thirty-five local as lotted assets on open national and At the mill, scrap was tipped into employees were engaged on the project international markets. a storage bay then charged direct and still work for McMahon Services into the induction furnaces using a today. Project key performance lead All scrap was sold under Institute magnet. Once scrap was melted it and lag indicators for health, safety, of Scrap Recycling Industries (ISRI) was continuously cast into billets environmental and quality control were Specification. Processed scrap was 100mm by 100mm and cut into 12m met or exceeded. transported in 10,000t lots to a wharf lengths. Billets were then sold to at Port Pirie 80km from the project site. rolling mills, were sold as construction The World Demolition Awards are This loading process was completed reinforcement bars or passed through presented by Demolition & Recycling using nine semi tippers and road- a series of rollers to become 40m International magazine in co-operation trains over a 17-day period for each lot. lengths of wire rod and then sold. Shipping vessels were loaded over a 72- with the European Demolition Association and with the support of the hour continuous period before shipping Non-ferrous metals were separated National Demolition Association of the to South East Asia for re-use resulting in from ferrous mental then classified United States. 100% recycling of the materials. by metal type and sold separately.

At Port Pirie, Sennebogen material This year’s event was held in Dublin, Ireland handlers loaded scrap at a rate of '50,000t of scrap on 8th November 2018 and was attended 142t/hour into bin trucks. When the by key personnel from the project. bins were full they were lifted with four metals generated chains and a spreader bar. The back Whilst we didn't win the award, we are hooks on the bins were fixed and the during demolition extremely proud of being shortlisted and front were j hooks, which allowed for works' having the chance to attend and meet the bin’s contents to be easily tipped with demolition industry companies from into the cargo holds. around the globe.

Once the scrap arrived at port in South East Asia, excavators with grapples were craned into the cargo holds to load the scrap into similar bins for transport. Once bins reached capacity THE WORKS 29 McMAHON SERVICES HEADS UP SCHOOL REFURBISHMENT FOR STEM WORKS PROGRAM

THE DEPARTMENT OF McMahon Services were contracted by Structural steel supply and PLANNING, TRANSPORT the Department of Planning, Transport construction works included columns, AND INFRASTRUCTURE’S and Infrastructure as part of the roof beams, operable wall beams, tie SCIENCE, TECHNOLOGY, STEM program to undertake design beams, wall braces and steel to steel ENGINEERING AND completion and refurbishment works fasteners. A new floor was fitted within for existing buildings at Surrey Downs the retained structures. MATHEMATICS (STEM) R-7 School. WORKS PROGRAM PROVIDES Partition, ceiling and lining works $250 MILLION FUNDING OVER Demolition works included the removal included supply and install of new THREE YEARS TO REFURBISH of doors and frames, suspended WA:02 walls which contained 76mm AND REDEVELOP 139 ceiling tiles, floor coverings, landings, steel track and stud framing, 70mm PRIMARY AND SECONDARY steps and a ramp to front entry to allow thick R2.0 insulations batts, 12mm SCHOOL FACILITIES for a new entrance to be constructed. high impact plasterboard up to FOR THE PROVISION OF Additional removal and disposal work 1200mm high and 13mm plasterboard CONTEMPORARY STEM included removal of dividing walls and 1200mm high, all flushed and sanded PROGRAMS. THE NEW air conditioning bulkheads. ready for painting. LEARNING FACILITIES WILL SUPPORT AND ENHANCE The civil and earthworks included Other works included the demolition the cut and preparation of the and reinstallation of hydraulic services, STUDENT ENGAGEMENT entrance area to allow ramp and step mechanical services, fire services, IN STEM RELATED installation, importation of new rubble security services and electrical AREAS TO ENCOURAGE for compaction, detailed excavation services, as well as the supply and FUTURE INNOVATION AND for internal footings, concrete pour for installation of a new 10kW solar PRODUCTIVITY. pad footings and the placement and system. The building was completed finishing of concrete slabs. with new joinery, painting and signage.

30 THE WORKS RAIL FACILITY ASBESTOS REMEDIATION WORKS

DOWNER RAIL IS A FULL Scaffolding was used extensively on RAIL SERVICE PROVIDER Scope of Work the project to significantly reduce COVERING ALL SECTORS the risks of working at heights up The project team undertook the to 16m, working over rail and to FROM ROLLING STOCK TO remediation of asbestos and INFRASTRUCTURE AND IN fully encapsulate the asbestos associated contamination at the remediation areas. A total of 2300m2 EVERY PROJECT PHASE, Downer Rail Facility on Carlton Parade of scaffolding was erected on site and FROM MANUFACTURING TO in Port Augusta. Asbestos containing was progressively moved to different THROUGH-LIFE-SUPPORT materials included switchboards, work areas as the program of works AND OPERATIONS. cupboards, structural beams, dirt progressed. Scaffolding was also outside the facility and window sills of erected with waterproofing materials to Downer’s track record spans project the main workshop building. Roofing protect all plant and equipment inside management services, engineering materials included sheeting, guttering, the facility during the works. design, systems engineering, downpipes, ridge capping, barge supply chain engagement, systems capping eaves and facia on the main The project team faced various integration, manufacturing, logistics, workshop building, the majority of challenges during the works including testing, commissioning, asset which bonded asbestos material. working over operational and electrified management, fleet maintenance, rail Comprehensive decontamination of rail, working on steep saw-tooth roof infrastructure design and construction. all areas was undertaken on a full- configurations and working in strong time basis during the works within full winds blowing off the nearby Spencer In November 2017 Downer announced encapsulated work areas. Gulf Ocean. it was selling its freight rail business 2 to Progress Rail, the sale included Over 8910m of roofing was replaced A major challenge was the heat. facilities located at Malaga, Port equating to 142t of asbestos Daytime temperatures often reached Augusta and Clyde as well as other containing materials remediated. All 390C or more which was compounded licensed facilities, and associated asbestos containing materials were by another 100C radiating off the assets and liabilities. encapsulated in protective 200µm roofs and an additional 120C from plastic sheeting and transported to EPA working in full encapsulated asbestos McMahon Services were engaged licenced asbestos receiving stations. remediation suits. Despite these 2 by Downer Rail to replace asbestos 2600m of wonder glass sheeting was challenges, works were completed on containing roofing and other installed in 18 bays to provide natural time and without incident. A total of 19 infrastructure at the Port Augusta lighting to the interior of the facility. personnel delivered the works. Plant facility, completing the work ready for and equipment utilised included a 200t the transfer to Progress Rail ownership. and 250t cranes.

THE WORKS 31 NATIONAL ENVIRONMENTAL INCIDENT AND SPILL RESPONSE SERVICES

THE AUSTRALIAN RAIL successful track record in providing for variation in the vacuum to efficiently TRACK CORPORATION similar oil spill emergency response extract water, hydrocarbons, thick sludge (ARTC) IS A FEDERAL services on a state-wide basis for SA and other liquid materials of varying AUSTRALIAN GOVERNMENT Power Networks. density and viscosity. This feature saves OWNED STATUTORY on both fuel and time taken to complete The incident response and management remediation works. A 5000psi (34MPa) CORPORATION, services are a national operation high-pressure hydro unit allows for ESTABLISHED IN JULY 1998, coordinating people, plant and fast and efficient site clean ups after THAT MANAGES, BUILDS, equipment from McMahon Services vacuuming is complete. OPERATES, MAINTAINS, offices in Adelaide, Perth, Brisbane, EXTENDS AND UPGRADES Sydney, Melbourne and Port Pirie. The two units will services different THE MAJORITY OF regions. One will be active in the north AUSTRALIA'S INTERSTATE McMahon Services also expanded its operating between Port Pirie, Ceduna RAIL NETWORK. fleet of vacuum trucks with the purchase and Port Lincoln. The other will service of two new Jamieson 8x4 Combo Isuzu Adelaide and the southern regions down McMahon Services were contracted for vacuum trucks for use on the incident to Mount Gambier. a two-year period to deliver 24/7 call and response and management services environmental incident response and contract for the South Australian region. The vacuum trucks have been co- management services for the ARTC rail branded as McMahon Services and network across Queensland, Western The new vacuum trucks were selected in Intract Australia. Australia, New South Wales, Victoria and part for their shorter lengths which allows South Australia. them to operate in constrained sites that our other models were not able to 'The units are McMahon Services are contracted to achieve. Despite their small sizes, they support ARTC in metropolitan, regional are still capable of transporting up to capable of and country locations along 8,500km of 10,000L of liquid waste materials from ARTC owned and operated track. sites. transporting up to

The contract was awarded in part Each truck is fitted with dual 1500cfm 10,000L of liquid because of McMahon Services’ (42m3/min) liquid ring pumps that allows waste' 32 THE WORKS CRUSHING DEMOLITION AT OLYMPIC DAM

OLYMPIC DAM MINE McMahon Services were selected by BHP, The redundant structures were LOCATED 560KM NORTH through a competitive tender process to mechanically demolished using OF ADELAIDE, IS ONE OF undertake the demolition works. demolition excavators to mitigate the risk THE WORLD’S LARGEST of personnel being close to structures DEPOSITS OF COPPER, during majority of the demolition, which also meant utilising minimal manual GOLD AND URANIUM AND Scope of Work labour to air gap the structures to be ALSO HAS A SIGNIFICANT demolished to the structures that were DEPOSIT OF SILVER. BHP’S Demolition of all plant, equipment, steel, to remain. The scrap steelwork and OLYMPIC DAM MINE footings and other items which were concrete were processed to minimise OPERATES AS A FULLY associated with the Razorback Crushing transport loads with maximum weight. INTEGRATED PROCESSING Plant were removed, returning the area FACILITY TRANSFORMING to bare compacted earth. This plant was Over 200t of steel was scrapped ORE TO METAL. located in the northern section of the and reclaimed, over 200L of oil and existing CAF plant at the Olympic Dam other fluids were drained from the The Olympic Dam mine operation mine site. infrastructure and 6600m3 of earthworks includes a Cement Aggregate Fill (CAF) were undertaken to remediate the site plant which combines sands, aggregate, In-situ tertiary crushers were required to back to its original state. 13t of conveyor cement and other products to create be removed from structures. Sections of belts and 1460t of concrete rubble were CAF used to backfill mined stopes plant and equipment which were to be also remediated on site. underground. Aggregate is crushed removed from site include feeder tunnels, and stockpiled along with sand in the conveyor belts, all slabs and footings to Workforce peaked at 17 completing area surrounding the CAF to be used at depth, structural steelwork, substation 10,000 work hours. Plant and equipment a later point in time. shed and tyres. Remediation earthworks utilised on the project included a were required onsite to ensure it was Komatsu PC850 demolition excavator Part of this original plant used to crush returned to the correct reduced levels with shear, Komatsu PC450 demolition rock and manage the stockpiles of sands and compaction to the correct BHP excavator with shear, Komatsu PC300 and aggregate became redundant and Olympic Dam specifications. Works excavator with various attachments, required removal allowing BHP to better also included draining fluids from all Komatsu WA200 loader, water truck, oxy/ utilise the area for stockpile storage equipment including gearboxes, air LPG cutting tools and equipment and a as well as make the area available for conditioner and their transport to BHP’s 40t Dump truck for carting materials to installation of new plant and equipment onsite Resource Recovery Centre. the Resource Recovery Centre. and other mine operations. THE WORKS 33 Hydrocarbon Storage Tank Deconstruction, Turtle Nests and Flotillas in the Indian Ocean

The workforce ROAD TO ANOTHER peaked at 20 and achieved 13,000 SUCCESSFUL PROJECT work hours.

IN 2018, BUNNINGS totalling six poles and luminaires along concrete pipes ranging from 375mmm WAREHOUSE AND Adelaide Road to improve the road to 450mm, 15 new stormwater pits and COLES SUPERMARKET safety. 7000m2 of landscaping. COMMENCED THE $25 MILLION CONSTRUCTION OF Road works included concrete works for Traffic management strategies for new kerbs and gutters, traffic islands and Adelaide Road with a daily traffic of 4,900 NEW RETAIL FACILITIES ON pram ramps, and construction of new vehicles per day were developed before THE CORNER OF ADELAIDE road pavement for the road widening, construction works commenced and ROAD (NOARLUNGA-VICTOR left turn slip lanes and the new access were implemented at all times during HARBOR ROAD) AND to the site and upgrades to the existing the works. Works were also undertaken HINDMARSH ROAD. road with the placement of new, thicker adjacent to operating businesses bitumen to improve pavement life and requiring additional pedestrian and The works required upgrades to the road rideability. access traffic management strategies. roundabout at the crossover point of the new road and upgrades to the existing Additional scope included construct Variable message signs were set up for roads adjacent to the retail site. of a new 2.5m wide shared path along advanced notice of work commencement the new development, new signage and and to communicate traffic restrictions line marking. Tree removal was planned during the deep lift asphalt work. Letter in advanced through early engagement drops and face to face communication Scope of Work with City of Victor Harbor council. with local businesses adjacent to the works were conducted prior to deep lift The scope of works for the roundabout Over 30m of redundant asbestos piping asphalt work. and road upgrade project included were excavated, treated and disposed of 5000m3 of bulk earthworks to construct at a licenced EPA receiving station. The new road batter and the detention basin, project team delivered 500m of new road a new underground stormwater system, construction, 4500m2 of new asphalt, and the supply and install of road lighting 375m of new stormwater reinforced

34 THE WORKS invert chambers to avoid the more-costly protecting the concrete in the long term Construction around live task of relocating the watermain. from environmental damage compared services to traditional concrete. Minor modifications to the lighting Overhead powerlines were present design allowed for a common service on site and this was a key risk during trench for stormwater and the electrical the bulk earthworks and road batter conduits, dramatically reduced trenching Deep lift asphalt construction phases. Safe Work Method and backfilling works. Statements were developed that limited Changes to the Adelaide Road design the height excavators could raise their from granular pavement to deep lift booms while spotters were in place at asphalt minimised impacts to traffic all times to ensure people, plant and Fibre reinforced concrete and local businesses, reducing this equipment remained well outside the component of the works from 30 days powerline exclusion zones. Fibre reinforced concrete was used for to 3 days and eliminating the need to the construction of drainage structures. work through the night. The thickness An existing watermain and low voltage This improved productivity as the of the new pavement was reduced from electrical conduits crossing the work materials are 75% lighter than traditional 365mm to 275mm significantly reducing site had not been identified during the concrete and the high strength of pipe the risks to break the existing watermain design phase and conflicted with the sections allowed for stability over longer and risks related to wet weather delays. new underground stormwater system. lengths during transport and placement, The project team developed a new 4.0m versus 2.5m for steel reinforced design for the stormwater comprising concrete pipes. Fibre reinforced concrete of additional pits, pipe alignments and also has better corrosive properties THE WORKS 35 McMAHON SERVICES NT SHOWS THEIR SUPPORT FOR THE HAYDEN REYNOLDS TIWI COLLEGE GARDEN PROJECT

INTRACT AUSTRALIA AND Intract's involvement in the college has Most recently, Intract Australia and MCMAHON SERVICES HAVE been one we are proud of and it has McMahon Services NT hosted two ALWAYS BEEN A STRONG been inspiring to see the growth of the students, John and Clinton, who SUPPORTER OF THE College and the development of the undertook mandatory induction training MATTHEW HAYDEN AND GUY students through the Guides Program. in our Darwin office before commencing onsite at various job locations. REYNOLDS TIWI COLLEGE Over the past four years Intract and GARDEN PROJECT. McMahon Services NT have been Skills acquired whilst with us included site supporting the Tiwi College Project clean-up for demobilisation, use of hand Located at Pickataramoor on Melville and for the past two years have been held power tools and trade assistant to Island, Tiwi College is an exciting and ‘Centurion Club’ sponsors, providing carpenters installing the framework for dynamic secondary boarding school funding to sustain the fantastic work the wall panels. initiated and governed by the local Hayden and Reynolds team have been residents of the island, who provide well- undertaking. Both John and Clinton have excelled being and quality education for the Tiwi over the placement with positive Island youth and students. Every year, the Tiwi College brings feedback from their supervisors about between 10-20 male students aged 15- their eagerness to learn new things. The Matthew Hayden and Guy Reynolds 18 years into Darwin to complete work Tiwi College Garden Project was achieved for one week in various industries to give We look forward to replicating this on through the commitment and influence the student some visibility across options a yearly basis and we have thoroughly of positive role models from the sporting for career pathways moving forward, enjoyed having the boys join our team. and entertainment sector, as well as a and viable industry connections for cross section of corporate executives, employment post-secondary education. who share an interest in sharing their experiences and opportunities that will enhance social change.

36 THE WORKS LAND 121 STAGE TWO UNIT SUSTAINMENT FACILITIES

LAND 121 IS A MULTI- structures and services, bulk earthworks, concrete interlocking pavement works PHASED NATIONAL pavement works, stormwater drainage, were completed using a mechanical AUSTRALIAN DEFENCE and the installation of utility services to paving machine which increased FORCE PROJECT TO support future buildings. Other works efficiencies in labour and project delivery DELIVER CURRENT- included centralised vehicle facilities time. upgrades at Robertson Barracks with the GENERATION, HIGH- installation of a new weighbridge facility A hazmat decontamination unit was set CAPABILITY FIELD VEHICLES, and an AdBlue dispensing facility (which up in the early stages of the works while MODULES AND TRAILERS. converts atmospheric polluting nitrogen asbestos remediation was underway. oxides into harmless nitrogen and water All asbestos containing materials Approximately 7,500 protected and steam), and a new hardstand storage were removed by fully trained Class A unprotected vehicles to provide Defence area at RAAF Base Darwin. qualified technicians and disposed of at with battlefield mobility, logistics support an approved Environmental Protection and tactical training will be procured Weighbridge and AdBlue tank works Agency (EPA) receiving site. during the project. at Robertson Barracks included the demolition of existing infrastructure Across both sites, 960t of asbestos LAND 121 Unit Sustainment Facilities including the existing loading ramp containing materials, 2500m3 of project will support the delivery of and approaches, lighting upgrades, contaminated soils, 240t of concrete vehicles by providing new and upgraded electrical switchboard upgrades, all and 13t of steel were remediated, and facilities at nine Defence establishments associated electrical works including were applicable, recycled off site. Over nationally. These facilities will improve trenching, backfill and compaction of 14,500m3 of earthworks, 5600m2 of the maintenance, support and ongoing conduits, under boring for conduits, and pavement works, 285m3 of concrete sustainment of the new vehicle capability. service installation. works, 170m of electrical conduits and 1700m2 of landscaping works were The 5300m2 hardstand storage works at completed. RAAF Base Darwin included demolition Scope of Work of existing infrastructure, asbestos All project personnel, subcontractors remediation, stormwater upgrades, and suppliers were source from the local McMahon Services were engaged by subsoil drainage, kerbing, spray Darwin area. Indigenous participation for Managing Contractor Lendlease to seal, mechanical laying of concrete the project was 15%, with Indigenous undertake LAND 121 works at Robertson interlocking pavers, lighting works, supervision and labour utilised on the Barracks and RAAF Base Darwin, in electrical switchboard upgrade works weighbridge portion of the works. the Northern Territory. Scope included including trenching, conduit and cable the demolition of existing buildings, installation, and landscaping. The THE WORKS 37 NEW ADDITIONS TO FLEET

McMAHON SERVICES OPERATES AND MAINTAINS ONE OF AUSTRALIA’S LARGEST FLEETS OF CONSTRUCTION AND DEMOLITION PLANT AND EQUIPMENT. OUR $80 MILLION NETWORK OF COMPANY-OWNED PLANT AND EQUIPMENT IS CAPABLE OF SERVICING PROJECTS IN URBAN, RURAL AND REMOTE LOCATIONS ANYWHERE IN AUSTRALIA.

Over 400 major plant items comprise of dozers, demolition and civil excavators, graders, rollers, loaders, dump trucks, batching plants, service trucks, water trucks, soil blending machines, prime movers, hook lift bin trucks, low loaders, semi-tippers and cranes.

The list below is a summary of those items added in 2018.

Light Vehicles Materials Handling Equipment Hilux Utes 36 Hyster 3.0t Forklift 3 Hiace Vans 6 Sennebogen 830 Material Handler 1 Sennebogen 835 Material Handler 1 Trucks and Trailers Smag Grab 2 Isuzu Flat Top 1 Omega 45t Forklift 1 Volvo FM13 Rigid Tipper and 3 Axle Dog Trailer 2 Isuzu 6t Tipper 1 Specialised Custom Service trailer 1 Somero S-438 Laser Screed 1 Tandem Excavator trailer 1 Hammelman High Pressure Pump and Conjet 1 Volvo FH 16 Prime Mover 1 Jetframe Nalta 101 Kobelco Crawler Crane 1 Civil Earthmoving Equipment Genesis GXT1555R Demolition Shear 1 PC1250 Excavator 1 Genesis GXT995 Demolition Shear 1 PC850 Excavator 1 Copex CVM630 Scrap Shear/Baler 1 PC750 Excavator 1 Doosan 500kVA Generator 1 PC300 Excavator 1 Kohler 300kVA Generator 1 Bobcat T450 Skidsteer loader 1 Kubota SQ3200 20kVA Generator 3 Bobcat E17 Excavator 1 Isuzu 10,000L Vacuum Truck 2 Bobcat E32 Excavator 1 Rammer City 777 Hydraulic Hammer 1 Bobcat E35 Excavator 1 Salmon Pulveriser 1 Bobcat Sweeper attachments 2 PR Dust Suppression Unit 1 Bobcat Grapple Bucket 2 Siltbuster silt separator 1 Wheel wash 2 E20 Bobcat Excavator 1 Powerscreen Premietrak 600 Cone Crusher 1 A45G Articulated Dump Truck 2 6t Swivel Site Dump Truck 2 38 THE WORKS 216B Skidsteer Loader 3 Powerscreen Premiertrack 600 diverts demolition waste away from landfills THIS YEAR McMAHON SERVICES INVESTED IN THE POWERSCREEN PREMIERTRACK 600, A MOBILE CRUSHING PLANT DESIGNED FOR LARGE AND MEDIUM SCALE OPERATION IN QUARRYING, DEMOLITION, RECYCLING AND MINING OPERATIONS.

With the Premiertrack 600, McMahon Services can now crush and transform demolition and construction waste into aggregates and fill material. This brings both cost and environmental savings to clients by significantly reducing quantities of construction and demolition waste otherwise transported and processed off site.

The 69t Premiertrack 600 is equipped with a single toggle jaw with an adjustable hydraulic setting able to crush materials with material strengths of up to 500kN, reducing materials into sizes between 75mm to 200mm. Materials are fed into the crusher through a 9.3m3 hopper. A troughed conveyor belt deposits crushed materials at a discharge height of 4.0m to produce stockpile volumes of 136m3.

The heavy-duty crawler tracks and a climb grade rate of 30o ensures that the Premiertrack 600 is mobile on site so it can be relocated continuously to adapt to staged works projects. It also features an inbuilt dust suppression system.

The Premiertrack 600 has provided significant savings to demolition projects across South Australia including the Charles Sturt Industrial Estate Demolition works, the Augusta Power Stations Decommissioning and the Former Football Park demolition project.

Hammelmann High Pressure Pump Cuts Straight through Concrete

McMAHON SERVICES HAS EXPANDED ITS SERVICE CAPABILITIES THROUGH THE PURCHASE OF A HIGH-PRESSURE HAMMELMANN PUMP THAT CAN PRODUCE 1000 BAR (10MPA) PRESSURE AT 100L/M OR CONVERTED TO PRODUCE 1400 BAR (140MPA) PRESSURE AT 70L/M.

The 1000 bar setting allows for cleaning of any type of industrial surface and the insides of tanks using a specialised cleaning head attachment.

The 1400 bar setting uses a Conjet Nalta 101 attachment that creates sufficient pressure to hydro-demolish concrete. This is ideal for exposing corroded reinforced steel bars so they can be treated and then resurfaced.

The unit is confined within a 6.0m by 2.4m wide by 2.4m high container for easy transport on the back of a truck, making the unit highly mobile.

The first project were McMahon Services successfully used the Hammelmann High Pressure Pump was on was the Former Royal Adelaide Hospital Stage 1 Demolition Works.

THETHE WORKS WORKS 39 39 Robert Tester

Anthony Woods

McMAHON SERVICES MAKES

THE MOVE ACROSS THE TASMAN SEA Tim Boys

McMAHON SERVICES HAS of the Australian model of asbestos roofing industries. Transitioning from his EXPANDED INTO THE NEW treatment and disposal. role as Roofing and Cladding Manager ZEALAND ENVIRONMENTAL in South Australia —where Robert has AND INFRASTRUCTURE Since MOTAT, McMahon Services have delivered more than a quarter of a million MARKETS, AND been provided with many opportunities square meters of roofing — Robert to bring our expertise to the country will take up an operational role in New CONSEQUENTLY OPENED and we see New Zealand as a growth Zealand. OUR FIRST OFFICE IN opportunity for our business. We are AUCKLAND IN AUGUST 2018. already providing site remediation Tim Boys, a New Zealand local, has more and demolition works for a major than 25 years’ professional experience in Interest in New Zealand began in petrochemical company near Wellington. the commercial and residential property 2017 when McMahon Services were industries. Tim is an experienced Senior approached to provide asbestos Our Auckland operations has initially Project Manager, with experience in the remediation solutions for contaminated been managed by two veterans of the design and management of demolition historical vehicles at Auckland’s asbestos and roofing and cladding and remediation projects. He has proven Museum of Technology and Transport industries, and one new employee success in meeting strategic deadlines, (MOTAT). The opportunity resulted in who has 25 years’ experience in the team leadership and motivation, McMahon Services remediating 14 commercial and residential property operational planning, assessment and antique cars, ambulances, fire engines industries. analysis reporting he brings a wealth of and construction machinery dating knowledge to the team. from the 1910s to the 1960s after they Anthony Woods, Construction Manager had been contaminated by asbestos for McMahon Services’ Asbestos and McMahon Services New Zealand particles falling from the roof where they Hazardous Waste division will relocate will initially concentrate on industry were stored. on a temporary basis to Auckland sectors where there is a demand to establish the office and take on a for new and experienced operators. The project gathered local interest and business development role locally. Service offerings will include asbestos soon McMahon Services were approach Tony brings his extensive Australian and hazardous waste remediation, by various consulting firms with an interest experience in asbestos removal and environmental remediation, demolition in servicing the growing remediation abatement works to the New Zealand and decommissioning, civil construction, market and utilising McMahon Services market. building construction and services, as an industry partner. New Zealand was roofing and cladding, and scaffolding and still is going through the process of Supporting Tony is Robert Tester, with and access solutions. achieving higher compliance in asbestos over 45 years of experience in the remediation by adopting many elements asbestos remediation, building and

40 THE WORKS McMAHON SERVICES OPENS PORT AUGUSTA OFFICE

From left to right: Craig Rutjens, Tim Cotton, Mel Milosevic, James Stockdale, Jess Desmond and Poshia Sulaimany.

HEALTH & SAFETY UPDATE

THE CONSTRUCTION Another safety achievement was the first stages implement development IN JULY 2018, McMAHON INDUSTRY IS FRAUGHT WITH RISK AND THE of a new WHSEQ Performance SERVICES EXPANDED OUR Management System, a scorecard OPERATIONS WITH THE POTENTIAL FOR SERIOUS HARM, AND IS management system that will OPENING OF A NEW OFFICE track individual business groups CONSIDERED TO BE ONE IN PORT AUGUSTA. performance in health, safety, OF THE MOST HAZARDOUS environmental and quality tasks, rated The new regional office is managed by INDUSTRIES IN AUSTRALIA. from base compliance to world’s Craig Cresp, a highly experienced Project industry best practice. It will be an Manager and design manager originally As an operator in the construction evidence-based system that will be from Port Augusta who has spent many industry, McMahon Services takes the easily measurable to ensure we meet years managing major infrastructure safety risks to our work seriously. We all legislative, industry, client and upgrades, maintenance and shutdown therefore operate a dedicated Work company requirements. The system projects at Olympic Dam. Health, Safety, Environmental and will be subject to data analysis to Quality (WHSEQ) Team to ensure that identify trends and align work activities Craig will continue to support existing every task we undertake is completed with company objectives. relationships in the region including BHP, in the safest possible way. OZ Minerals, Flinders Power and Santos. Two new recruits joined WHSEQ He will also investigate opportunities in While safety is the responsibility of Manager Craig Rutjens, WHSEQ Site providing capital works, site remediation, everyone in the company, the WHSEQ Manager Tim Cotton and WHSEQ maintenance and shutdown services Team ensures that our workforce has Advisor James Stockdale in 2018 for the $5 billion in energy projects access to the latest work health and to assist with the team’s ever- expected to occur in the region in the safety information, tools, procedures growing workload. Return to Work next five years. These projects include and practices. Manager Mel Milosevic became the solar thermal farms, windfarms, battery company's contact with respect to storage and pumped hydro projects One of the team’s major return to work issues and incidents offering opportunities to enter into the achievements in 2018 was obtaining as they occur, and to ensure they are boom renewables market. national environmental and quality correctly guided and mitigated as management systems certification appropriate. Graduate Safety Advisor Craig and the Port Augusta team will be to the new ISO14001:2015 and Poshia Sulaimany assists with the supported through our well-established ISO9001:2015 standards, bringing the maintenance of the management Port Pirie and Whyalla offices and head company up to date with legislative system, meeting our accreditation office support from Adelaide. requirements. requirements, researching legislation and performing auditing.

41 THE WORKS THE WORKS 41 IN MARCH 2015, RENEWAL SA EMBRACED AN OPPORTUNITY TO LEVERAGE OTHER ADELAIDE FESTIVAL DEVELOPMENTS HAPPENING IN AND AROUND THE ADELAIDE RIVERBANK BY DEVELOPING A PROPOSAL WITH WALKER GROUP CENTRE DRIVE HOLDINGS FOR THE INTEGRATED REDEVELOPMENT OF THE ADELAIDE FESTIVAL PLAZA SITE.

The plaza redevelopment envisioned would UPGRADE provide 16,500m2 of public space established in the areas surrounding the Adelaide Festival Centre, Adelaide Railway Station, Adelaide Casino, Parliament House and Old Parliament House and Station Road.

Per the early works agreement construction WORKFORCE PEAKED began in November 2016 and involved the lowering of Festival Drive, separating vehicle and AT 10 PERSONNEL WHO pedestrian movements and enabling direct on- foot access between the Riverbank Footbridge COMPLETED and Adelaide Railway Station. The scope included the early foundation work required to support the Adelaide Casino expansion and to drop the existing access road to allow new 20,000 overhead building works. WORKHOURS Lendlease was awarded the contract and engaged McMahon Services to deliver the early works package. Based on the success of the

42 THE WORKS delivery for the first package, Lendlease 15,000m3 or 30,000t of bulk earth were then awarded McMahon Services the transported offsite for treatment and Project Challenges hydraulic package through Hindmarsh recycling that ultimately ended up as Plumbing who was also working for fill material for the Northern Connector The work site was extremely congested Lendlease, and main civil package of project concurrently underway in with operational and occupied buildings works for the overarching project. Adelaide’s northern suburbs. An addition adjacent to the works on all sides including 1800t of asbestos containing and low the casino, hotel, festival centre and train level contaminated soils were removed station. Environmental considerations and disposed of offsite at EPA licenced were at the forefront of project planning receiving stations. and execution, and included noise and Scope of Work dust mitigation strategies to minimise impacts on adjacent buildings. McMahon Services delivered the project Civil and road construction works in three stages. The first stage was the included the construction of a piling Sewer and other water lines required early works to alter traffic lights on Festival platform for approximately 400 continual pumping to ensure flooding did Drive connecting traffic to King William continuous flight auger piles (CFA) not occur on site. Material stockpiles had Road, installing bollards and preparing installed by another contractor, lowering to be carefully managed so not to further the site for the main construction works. construction works for 120m of the Festival Drive road including base course constrain the site. Many items of plant 2 3 had to be lifted into and out of site via The second stage required locating and 1000m of bitumen asphalt, 200m of a 60t crane due to the highly restrictive watermains, sewers, electrical cable and concrete shotcreting, the construction of access. stormwater, then relocating all services 400m of new stormwater lines, kerbing, within 7m below the ground level as they signage and line marking. The road Another key congestion challenge would otherwise risk being damaged was constructed inside two pile derived was maintaining access to the loading during latter construction stages. Over retaining walls leading into a tunnel under dock for servicing the Adelaide Festival 150m of sewer lines and 150m of water the Festival Centre area. Portions of the Centre, the Intercontinental Hotel and the mains were relocated. road works were undertaken beneath a suspended concrete slab. Skycity Casino, which was located within and adjacent the construction site. The The third stage comprised of the loading docks had to remain accessible bulk of the works. Ground conditions and open at all times and often featured proved challenging with former building long lines of trucks loading and unloading structures including a retaining wall goods. dating back to the 1920s requiring demolition and remediation. Over

THE WORKS 43 McMAHON SERVICES SHOWS SUPPORT FOR THE WOMEN'S & CHILDREN'S HOSPITAL BEACH HOUSE PROJECT

IN SOUTH AUSTRALIA, THERE physical and emotional stresses of IS NO PURPOSE-BUILT the hospital setting - yet strategically ACCOMMODATION FOR located near a hospital should the Make a Difference... FAMILIES OF CHILDREN WITH need arise. COMPLEX MEDICAL NEEDS. If you choose to donate, your The vision is that the WCH Foundation donation will contribute to an ongoing Beach House will provide an The Women’s and Children’s Hospital endowment to maintain the house and environment in which the whole family (WCH), located in Adelaide, wanted support services once it’s completed can rest, recharge and create special to be able to provide children and and well into the future, making the memories together, providing them their families with a space to unwind Beach House a lifelong sanctuary for with the break they need to continue and forget about the four walls of the some of the Women’s and Children’s their journey. hospital, which is where many of them Hospital’s most deserving families. spend their days. After hearing about this amazing Please join us on this journey and help foundation McMahon Services The WCH Foundation Beach House us to make The Beach House a reality Managing Director David McMahon is a major project aiming to provide for the children and families of the generously agreed to donate labour respite accommodation for families Women’s and Children’s Hospital. A resources to assist Bella Build & caring around-the-clock for children place where families can enjoy a beach Design with the contract process of requiring significant care and support side getaway where they can take a the Beach House, located south of due to a long-term and / or life-limiting much needed break to share special Adelaide, Encounter Lakes, Victor illnesses. The project aims to raise experiences that will last a lifetime. Harbor. $2.5 million to construct a purpose- built holiday home and develop an Donate here: ongoing support program for families Building commenced September 2018, where a team from McMahon Services to create special memories. www.wchfoundation.org.au/projects/ performed a scope of works consisting the-beach-house-project/ of steel fixing, formwork and pouring The Beach House will be the first the concrete slab, contributing to the holiday accommodation built We commend all people involved in this development of this beautiful home, especially for, and available to WCH project, and we cannot wait to see the ready for families by March 2019. families with these specialised needs. finished product. It will offer a welcoming, calm and peaceful environment far from the

44 THE WORKS CHARLES STURT INDUSTRIAL ESTATE DEMOLITION WORKS

CHARLES STURT Initial works were the identification and Other works included site clearances, INDUSTRIAL ESTATE IS safe decommissioning of electrical, demolition of approximately 26,000m2 A NEW INDUSTRIAL AND stormwater, water main, sewers, of concrete footing and crushing of BULKY GOODS ESTATE telecommunication and gas services concrete, excavating and remediating DEVELOPED BY ISPT ON and then relocating and connecting contaminated areas to a depth of 3m, these services to the new Nerve and backfilling pits, sumps, tunnels THE SITE OF THE ORIGINAL Centre building located adjacent to the and excavations. 25,000t of concrete GENERAL MOTORS HOLDEN demolition site. and masonry were demolished and ASSEMBLY PLANT IN THE recycled. 2,000t was recovered from NORTHERN ADELAIDE Asbestos remediation works included structural steel supports and salvaged SUBURB OF WOODVILLE. the safe removal and disposal of heavy equipment on site. 29 large THE ASSEMBLY PLANT HAD 100,000m2 of asbestos deep 6 sheet presses ranging from 40t to 65t were CLOSED IN OCTOBER 2017. roofing from the saw tooth roof also removed from site. configuration prevalent across the plant. Through a competitive tendering process Third party air monitoring was applied Additional works included the McMahon Services was awarded the during asbestos clearance activities. replacement of a SA Power Networks project for the demolition of the former All asbestos containing materials were 33kVA transformer used by the adjacent General Motors Holden main assembly packaged in double layer 200µm plastic Bunnings Waterhouse facility. plant, Charles Sturt Industrial Estate wrap and disposed of at an approved Building and the surrounding pavements EPA licenced waste facility receiving Plant and equipment used on site and hardstand located in the north- station. Hazardous waste removed from includes one small forklift, two large western area of the site. site included 100,000L of transformer forklifts, five elevated work platforms, and subterranean tunnel oil. trucks, 13t, 30t and 45t excavators with Works included the decommissioning, hydraulic shears demolition and environmental Mechanical demolition works was remediation of the former General undertaken with three demolition Motors Holden Main Assembly Plant excavators fitted with hydraulic shear within the Charles Sturt Industrial Estate. attachments working to a height of 16m.

THE WORKS 45 MULTI-DISCIPLINARY PROJECT LEAVES BROADCAST AUSTRALIA HOPEFUL

BROADCAST AUSTRALIA Furthermore, the existing Sleeping remediation, demolition of the sleeping PROVIDES TELEVISION Quarters and Tool Store located on the quarters and adjacent carpark, roofing AND RADIO BROADCAST north east side of the building had been and cladding works, building works TRANSMISSION SERVICES uninhabitable for a period due to an and repairs, and mechanical works. ACROSS AUSTRALIA infestation of termites, the weakening Works in the Transmitter Building of the building structure due to the and Emergency Power Plant Room THROUGH ONE OF THE subsidence of the supporting soil, included asbestos remediation, mould WORLD’S MOST EXTENSIVE and the large quantity of deteriorating remediation, roof sheeting, gable-end TRANSMISSION NETWORKS asbestos containing materials within panels, eave soffit linings, roof sarking, COVERING METROPOLITAN, the building. guttering and downpipes, and the REGIONAL AND REMOTE replacement of timber and fire rated LOCATIONS. THEIR MOUNT The cooling systems supplying the doors. HOPEFUL BROADCAST Transmitter Hall had been originally SITE SERVICES THE designed for the now obsolete Mechanical and electrical works ROCKHAMPTON AREA OF analogue television (PAL) transmission included decommissioning and QUEENSLAND. era and no longer suited the current removal of existing under ceiling split transmission arrangement on site. air conditioners, installation of a new Broadcast Australia identified The plenum (an air-distribution heating, ventilation and air conditioning asbestos containing materials in the box attached directly to the supply (HVAC) system, installation of variable Emergency Power Plant Room ceiling outlet of the heating, ventilation speed drive systems for existing and eave soffit linings to the buildings and air-conditioning equipment that plenum room supply-air fans, and which were in generally poor condition heats or cools the air to make the the replacement of external security and required remediation. Additionally, building comfortable) was currently lighting. the roof sheeting, roofing accessories positively pressurised due to the over- and rainwater infrastructure on the proportionate amount of the supply-air Workforce peaked at six Class A Main Transmitter Building, Emergency to this room resulting in unconditioned asbestos technicians, a five-person Power Plant Room and foyer were air spilling into the Transmitter Hall. demolition crew and three-person reaching their end of service life and roofing crew. Plant and equipment required replacing. McMahon Services were engaged included scaffolding, 14t excavator, to undertake multidisciplinary works asbestos bins, four body trucks and on site that included friable and non- site vehicles. friable asbestos remediation, mould 46 THE WORKS NEW SENIOR APPOINTMENTS

Julia Swift, Mel Milosevic, General Counsel SA Return to Work Manager SA

Julia joins the McMahon Services team bringing 13 years Mel is highly experienced in return to work injury of legal experience to the company. She has specialised in management across a variety of industries. Her construction commercial litigation, employment, industrial relations and and heavy industry experience include previous roles with work health and safety law. Master Builders Association South Australia and Adelaide Brighton Cement, and she has managed injuries and Julia was a Special Counsel in private practice, and then return to work strategies for over 40 construction industry as General Counsel in the civil construction industry. She businesses. is an experienced lawyer in reviewing risks in tendering and contract management, and ultimately working with our Mel’s experience includes managing work injury claims, clients to ensure compliance with contracts. ensuring rehabilitation and return to work plans are developed, implemented and reviewed on an ongoing basis, Julia’s qualifications included a Master of Laws (Employment as well as facilitating the return to work process across the and Industrial Relations), Bachelor of Law (Honours) and a company. Mel also manages internal communications and Bachelor of Commerce (Marketing). stakeholder engagement with respect to her role.

Julia is providing specialised legal services to the McMahon With a background in and aligning work practices to the Services’ group including preparation, review and South Australian Workers Rehabilitation and Compensation negotiation of various contracts at tender stage through Act and ReturnToWorkSA, Mel is now focused on meeting to facilitation of project handovers from tender award to Australia wide Federal and State requirements. commencement of the works. Julia’s role also involves advising on WHS obligations, and ensuring suitable contract Her qualifications include a Certificate IV in Personal Injury management of projects. Management (Claims Management) and a Certificate II in Information Technology.

Mel is the company’s contact with respect to return to work issues or incidents as they occur, to ensure they can be correctly guided and mitigated as required. THE WORKS 47 Brand Guidelines. For mor Only useblueand/orwhite. Squar Social icon e detailscheckoutour e CONTACT US Supply NationCertifiedsupplier. owned andoperatedfamilybusiness Printed byPrintJunction,anIndigenous E T 33 CrawfordStreet,KatherineEast0850 Katherine E T PO Box903KarrathaWA 6714 Lot 104ExplorationDrive,GapRidgeWA6714 Karratha E T PO Box80Welshpool WA 6986 1/19 CheethamStreet,KalgoorlieWA 6430 Kalgoorlie E T NT0821 PO Box36546Winnellie 41 BishopStreet,Woolner NT0800 Darwin E T PO Box155CapalabaQLD4157 14/1440 NewClevelandRoad,ChandlerQLD4155 Brisbane E T PO Box4545AliceSpringsNT0870 202 StuartHighway, AliceSpringsNT0870 Alice Springs E T PO Box542EnfieldPlazaSA5085 26 DuncanRoad,DryCreekSA5094 Adelaide www.mcmservices.com.au (08)89302500 (08)91839500 (08)90916686 (08)89302500 (07)36344300 0417820221 (08)82033100 [email protected] [email protected] [email protected] [email protected] [email protected] [email protected] [email protected] E T PO Box54WhyallaSA5540 350 BroadbentTerrace, WhyallaSA5600 Whyalla E T PO Box544GarbuttEast,Townsville QLD4814 Mount StJohnQLD4818 68 CrocodileCrescent, Townsville E T Alexandria NSW2015 PO Box7064AlexandriaBusinessHub 86 BourkeRoad,AlexandriaNSW2015 Sydney E T PO Box143Port PirieSA5540 30 EllenStreet,Port PirieSA5540 Port Pirie E T PO Box542EnfieldPlazaSA5085 2A StirlingRoad,Port Augusta5700 Port Augusta E T PO Box80Welshpool WA 6986 Unit 11/524AbernethyRoad,Kewdale WA 6105 Perth E T PO Box82AltonaNorthVIC3025 1 CawleyRoad,BrooklynVIC3012 Melbourne (08)86444400 (07)47743056 (02)93079900 (08)86335400 (08)82033100 (08)63507000 (03)93517800 [email protected] [email protected] [email protected] [email protected] [email protected] [email protected] [email protected]

The WORKS