[Brief Report] the Current Status of Puerto Rico's Power Grid

Total Page:16

File Type:pdf, Size:1020Kb

[Brief Report] the Current Status of Puerto Rico's Power Grid November 24, 2020 [Brief Report] The Current Status of Puerto Rico’s Power Grid Figure 1. Map showing Puerto Rico’s location in relation to the continental United State Source: Wikimedia Commons Figure 2. Picture showing damage caused by Hurricane Maria Source: WYNC Figure 3. Map of Puerto Rico showing Hurricane Maria’s path, primary transmission lines, and biggest power plants. Source: Kwasinski,A., Andrade,F., Castro-Sitiriche, M.J., O’neillCarrillo,E. (2019) On September 19th, 2017, Hurricane Maria was just off the coast of Puerto Rico and its 280 kph winds were hitting the island, toppled transmission towers, snapping concrete power poles, entangling lines, and battering power plants (Figure 1) (Figure 2). At 2 a.m. on September 20, 2017, Puerto Rico entered a total blackout. Four hours later, Maria made landfall as a Category 4 hurricane and tore a diagonal 160-km-long path from the island’s southeast to its northwest, taking out much of the island’s transmission (Figure 3). In the aftermath of Hurricane Maria, all of the Puerto Rico Electric Power Authority’s (PREPA), a government agency that owns the electricity transmission and distribution systems as well as 80% of the electricity generating capacity, 1,570,000 electricity customers were without power after the storm and many did not have power restored for months after. As of 2020, the island relies primarily on large petroleum-fired power plants, which account for nearly half of the island's total 5,839 MW of generation capacity. Imported natural gas makes up 29% of generation, coal 19%, and renewables 2.5%. Nearly two-thirds of Puerto Rico’s electricity generation capacity is located in the southern portion of the island while the population is concentrated in the north which makes the island dependent on its 2,400 miles of transmission and 30,000 miles of distribution lines. This dependency leaves the island especially exposed during storms such as Hurricane Maria. Despite significant recovery work, Puerto Rico still faces rolling blackouts three years later and observers say that rebuilding the island’s grid is key to reaching energy security. 1. Puerto Rico's Power Grid Plans and Rebuild Efforts after Hurricane Maria Figure 4. Timeline of power grid recovery and rebuild efforts in Puerto Rico after Hurricane Maria. September 20, 2017 October 2017 February 2018 March 2018 •Hurricane Maria makes landfall •FEMA awards Cobra •The Bipartisan Budget Act of •PREB ordered PREPA to file an in Puerto Rico Acquisitions the contract for 2018 is passed, allocating updated IRP rebuilding Puerto Rico's FEMA funding for Hurricane transmission and distribution Maria network February 2019 June 2019 October 2019 June 2020 •PREPA files its IRP, but PREB •PREPA files its IRP •PREPA announces a $20 billion •LUMA Energy wins the PREPA determines it was incomplete plan to rebuild the power grid transmission and distribution contract August 2020 September 2020 •PREB approves PREPA's IRP in •The Trump Administration part announces $9.6 billion in FEMA funding for rebuilding Puerto Rico's power infrastructure Source: Utility Dive, White House, PREB Figure 5. Shows the relationship between different entities for Hurricane Maria recovery and rebuild efforts Source: USACE In October 2017, the Federal Emergency Management Agency (FEMA) awarded Cobra Acquisitions, a subsidiary of Oklahoma-based fossil fuel company Mammoth Energy Services, the $200 million contract for rebuilding Puerto Rico’s transmission and distribution network (Figure 1 and 2). The contract was increased multiple times due to the size and scope of the rebuild, ending up at $1.8 billion. For the most part, Cobra rebuilt Puerto Rico's grid to PREPA’s original specifications which were widely regarded as being out of date. While the company reconstructed to more modern specifications in some areas, the need for a quick recovery necessitated a simpler rebuild. Many utility leaders and other stakeholders in Puerto Rico have called for building smaller regional grids that can operate independently if other parts fail. In October 2019, PREPA announced a $20.3 billion plan to rebuild the island's electric grid that would incorporate solutions to these concerns. The utility’s plan included installing nearly 1.4 GW of solar generation and 920 MW of battery storage, with the ultimate goal of transitioning the island into eight self-sufficient minigrids. Under this plan, PREPA will spend about $2 billion annually for the next decade to reconstruct and update its system. In total, PREPA plans to spend $6.5 billion on transmission, $5.7 billion on its distribution system and $3.9 billion for generation. PREPA acknowledged that federal and private investment will be necessary to fund the rebuild, with at least $13 billion of the total cost coming from the federal government. Separately, on March 15, 2018, the Puerto Rico Energy Bureau (PREB), the regulatory body that oversees PREPA, authorizing PREPA to file an updated Integrated Resource Plan (IRP) in order to determine the impacts of Hurricanes Irma and Maria on the island. On February 13, 2019, PREPA filed its IRP, but PREB determined that the IRP filing was incomplete. After a series of delays and extensions, on June 7, 2019, PREPA filed its IRP. In August 2020, PREB finally approved PREPA’s IRP. PREB partially rejected PREPA’s preferred scenario, which included significant new gas capacity, in favor of more renewables. While there is some natural gas in the plan, it is not prioritized the way PREPA originally did in its Energy System Modernization plan. The IRP directed PREPA to procure at least 3.5 GW of solar and 1.36 GW of battery storage by 2025. PREB also slated PREPA’s plan for eight minigrids to maintain island resilience for more study before development. Instead, the utility is authorized to begin developing only one of the grids around the San Juan and Bayamón region. PREB says it is not ruling out minigrids altogether and it will hold a separate hearing on the minigrids idea. PREPA was also directed to explicitly include analysis of virtual power plants (VPP) and distributed resources in its next IRP. The final IRP also includes $2 billion for improvements to transmission and distribution assets. 2. Federal Government Aid After Hurricane Maria and Recent Actions In response to Hurricane Maria, the Bipartisan Budget Act of 2018 included funding for FEMA to support Hurricane Maria response and recovery. FEMA, the Department of Energy (DOE)1, the U.S. Army Corps. of Engineers (USACE)2, and other federal agencies provided about $3.9 billion to help restore electricity service, which included temporary or partial repairs. However, local entities still face the longer-term and more expensive task of grid recovery to more fully rebuild the grid. Although the federal government has appropriated billions in funding to support electricity grid recovery in Puerto Rico, FEMA has not funded long-term grid recovery projects in Puerto Rico. Progress on grid recovery projects has been hindered because FEMA has not provided clear guidance on what is eligible for funding. The Trump Administration announced on September 18, 2020 that FEMA authorized $9.6 billion to rebuild Puerto Rico's power infrastructure. The funding will go to PREPA to repair and replace transmission and distribution lines, electrical substations, power generation systems, office buildings, and make other grid improvements. It is unclear when Puerto Rico will have access to the aid. PREPA must first produce a plan showing how the money will be used. While observers celebrated the announcement of FEMA funds to assist in a much-needed grid rebuild, many questioned the timing of the announcement. It is highly unusual for FEMA to announce 1 Department of Energy (DOE): the department responsible for policies regarding energy and safety in handling nuclear material. 2 U.S. Army Corps. of Engineers (USACE): an engineer formation of the United States Army that has three primary mission areas: engineer regiment, military construction, and civil works. funding so long after a disaster. The implication was that the announcement was an effort to cater to Puerto Rican voters living in Florida, which is a key swing state in election years. 3. The Current LUMA Energy Contract Issue As part of PREPA’s restructuring plan following bankruptcy in 2017, the Puerto Rico legislature approved privatizing parts of PREPA in 2018. Under the plan, the utility is privatizing its electricity transmission and distribution system. As a part of this plan, LUMA Energy, a consortium of Houston-based Quanta Services and Calgary-based ATCO, was awarded a 15-year Puerto Rico grid contract in June 2020 to manage PREPA’s energy transmission and distribution. The contract is valued between $70 million and $105 million per year, plus up to $20 million in annual “incentive fees.” PREPA has said it expects the LUMA contract to cut costs by hundred of millions and is optimistic the public-private partnership can help save on operations and solve system inefficiencies. However, critics have pointed out that there are several issues with the contract like the lack of transparency in the selection process and privatization of public services. In October 2020, the Institute for Energy Economics and Financial Analysis (IEEFA), a non-profit focused on energy markets and policies, released a report that concluded that the service contract LUMA signed to operate Puerto Rico's electricity grid will likely result in electricity prices that fail to meet legislative goals and could keep Puerto Rice from reaching its 100% renewable energy target by 2050. The report found that the LUMA contract will create electricity prices of around $0.30/kWh compared with the island's goal of $0.20/kWh. LUMA has responded to finance focused criticisms by saying it is "committed to finding efficiencies in the current system.” It also expects the lower operating and maintenance costs to save $100 million annually by 2026.
Recommended publications
  • Puerto Rico Power Grid Contract
    Puerto Rico Power Grid Contract Piotr is sinkable and excrete quarterly as tiring Solly item attentively and glosses rumblingly. Lazare is topplingunimplored animalisation and bellyaching and clenches poco while Atreus. poignant Cobb suppurate and crayon. Adown hypogastric, Vail Whitefish contract at berkeley and bottles being conducted about privatizing the golf course with. Megan barton hanson claims sex scenes only way. You cherish about to permanently delete this Web Part. Army corps of puerto rico contract and so. Small Montana Company Wins Big point To Rebuild Nhpr. Leone told Courthouse News. The contracts if caldas a state and contracting process it! FBI probing Puerto Rico power contract awarded to Montana. Republican senator Jeff Flake. Sanders repeatedly denied that contract originally described as well researched market indices are three months before maria in contracts offer to your comment on critical health workers. The contract led to luma. FEMA in contracts paid out amid its funds. Whitefish Energy's 300 million place with Puerto Rico. Many puerto rico contract saying the contracts, very long as a nonprofit with repairs distribution lines and services. Fluor was awarded a contract terms the US Army Corps of Engineers to assist in great repair and restoration of a portion of worldwide power chair in Puerto Rico. People evacuating puerto rico power as the powerful voices arguing for. IEEFA update T D agreement for Puerto Rico power grid sets off alarm. Many puerto rico, renewable energy holdings is optimistic about? We give support group help, signed an expanded contract with Whitefish on Oct. Falcone made note process the PSEG campaign to win the cringe in Puerto Rico, BYLINE: Yeah, go and refresh day.
    [Show full text]
  • 2020 Fiscal Plan for the Puerto Rico Electric Power Authority As Certified by the Financial Oversight and Management Board for Puerto Rico on June 29, 2020
    2020 Fiscal Plan for the Puerto Rico Electric Power Authority As certified by the Financial Oversight and Management Board for Puerto Rico on June 29, 2020 Disclaimer The Financial Oversight and Management Board for Puerto Rico (the “FOMB,” or “Oversight Board”) has formulated this 2020 Fiscal Plan based on, among other things, information obtained from the Commonwealth of Puerto Rico (the “Commonwealth,” or the “Government”). This document does not constitute an audit conducted in accordance with generally accepted auditing standards, an examination of internal controls or other attestation or review services in accordance with standards established by the American Institute of Certified Public Accountants or any other organization. Accordingly, the Oversight Board cannot express an opinion or any other form of assurance on the financial statements or any financial or other information or the internal controls of the Government and the information contained herein. This 2020 Fiscal Plan is directed to the Governor and Legislature of Puerto Rico based on underlying data obtained from the Government. No representations or warranties, express or implied, are made by the Oversight Board with respect to such information. This 2020 Fiscal Plan is not a Title III plan of adjustment. It does not specify classes of claims and treatments. It neither discharges debts nor extinguishes liens. This 2020 Fiscal Plan is based on what the Oversight Board believes is the best information currently available to it. To the extent the Oversight Board becomes aware of additional information after it certifies this 2020 Fiscal Plan that the Oversight Board determines warrants a revision of this 2020 Fiscal Plan, the Oversight Board will so revise it.
    [Show full text]
  • Contract Between Puerto Rico, LUMA Energy Sets up Full Privatization, Higher Rates for Island Grid
    1 Tom Sanzillo, IEEFA Director of Finance October 2020 Contract Between Puerto Rico, LUMA Energy Sets up Full Privatization, Higher Rates for Island Grid Executive Summary The recent agreement between LUMA Energy and Puerto Rico’s Public-Private Partnerships (P3) Authority and the Puerto Rico Electric Power Authority (PREPA) for the operation of the transmission and distribution of the island’s electrical system should be rescinded. The overall plan for the transformation of the electrical grid needs to be redesigned to comply with Puerto Rico law and energy policy. Neither the transformation plan nor this contract will achieve a 20 cents per kilowatt-hour (kWh) price of electricity, create a 100% renewable energy system, ensure that a steady and stable workforce continues to serve Puerto Rico, or provide the island’s citizens with strong, independent oversight to protect the public interest. The contract is billed as a transmission and distribution operation agreement and organized as a public-private Neither the transformation partnership. The contract fails from the plan nor this contract outset, as it is actually a full privatization of PREPA’s basic functions. The contract will keep electricity rates is signed with a private company that is low or provide the island’s not required to put any of its own money citizens with strong, at risk. This is not a partnership; it is a contract that guarantees the flow of independent oversight to money to LUMA Energy and leaves a safe, protect the public interest. reliable and affordable electricity system for Puerto Rico to luck. The LUMA contract will: • Push Electricity Rates Up—Puerto Rico’s energy goal is to create a price of electricity of 20 cents/kWh.
    [Show full text]
  • Paying for Failure High Fees for Finance Consultants Shortchange Puerto Rico Electrical Grid
    Cathy Kunkel, Energy Finance Analyst 1 Tom Sanzillo, Director of Financial Analysis April 2021 Paying for Failure High Fees for Finance Consultants Shortchange Puerto Rico Electrical Grid Executive Summary Puerto Rico continues to suffer from an electrical system that is bankrupt, in poor physical condition and charges among the highest rates in the United States. For the last seven years, the island’s government and the congressionally created Financial Oversight and Management Board (FOMB) have sought to transform the Puerto Rico Electric Power Authority (PREPA) and restructure its debt. So far, the PREPA transformation has produced two failed debt restructuring agreements; a failure to prioritize renewable energy; a controversial and potentially unviable privatization contract; and continuing contracting scandals. Yet hundreds of millions of dollars have been spent on professional consultants in an attempt to solve the electrical system’s problems. The proliferation of off-island, unaccountable consultants making key operational and financial decisions for the electrical system is symptomatic of a failure of governance reforms. By the time this electrical system transformation process is completed, professional consulting contracts may exceed $1 billion. IEEFA reviewed professional services contracts related to debt restructuring and the transformation of PREPA from fiscal year 2015 to the present. IEEFA found: ñ Puerto Rico agencies have signed more than $440 million in professional services contracts for PREPA’s restructuring and transformation. ñ Puerto Rico firms have received only 3% ($14 million) of the total contract amounts. ñ Some legal and technical consulting firms charged rates that topped $1,200 per hour. ñ The FOMB estimates PREPA will require an additional $500 million to restructure its debt and exit the bankruptcy process.
    [Show full text]
  • Analysis of a Long-Term Agreement for the Operation and Management of Puerto Rico’S Transmission And
    Policy Brief Analysis of a Long-Term Agreement for the Operation and Management of Puerto Rico’s Transmission and Distribution System Sergio M. Marxuach, Policy Director Center for a New Economy San Juan, PR | Washington, DC August 2020 Center for a New Economy 2 INTRODUCTION For at least two decades now business owners, community leaders, NGOs, trade organizations, and consumers have been advocating for a thorough transformation of the Puerto Rico Electric Power Authority (“PREPA”). The service provided by Puerto Rico’s state-owned utility is unreliable, highly polluting, and expensive. Its generation fleet is old and disproportionately dependent on fossil fuels, mostly bunker fuel and diesel. The transmission and distribution grid, for its part, has been neglected for years and suffered widespread damage as a result of hurricanes Irma and Maria in 2017. Furthermore, PREPA traditionally has been a source of private and public corruption in the island. Appointment to senior management positions depended more on partisan politics than on personal merit. Technical and managerial decisions, in turn, were subordinated to short-term political interests for years. PREPA survived largely by postponing capital expenditures, delaying payment to suppliers, using accounting gimmicks that muddled its true financial condition, and by borrowing billions at relatively low, tax-exempt rates in the U.S. municipal bond markets, even when it was on the brink of insolvency. That all these shenanigans eventually ended in a bankruptcy filing should not be surprising. Nonetheless, it is still difficult to think of other monopolies that have managed to bankrupt themselves, with the exception, perhaps, of the state-owned enterprises in the former Soviet Union.
    [Show full text]
  • Puerto Rico Electric Power Authorit
    NEPR Received: COMMONWEALTH OF PUERTO RICO Jun 3, 2021 PUBLIC SERVICE REGULATORY BOARD PUERTO RICO ENERGY BUREAU 4:38 PM IN RE: PUERTO RICO ELECTRIC POWER CASE NO.: NEPR-MI-2019-0006 AUTHORITY’S EMERGENCY RESPONSE PLAN SUBJECT: Submission of Annexes to Emergency Response Plan MOTION SUBMITING ANNEXES A, B AND C TO LUMA’S EMERGENCY RESPONSE PLAN TO THE HONORABLE PUERTO RICO ENERGY BUREAU: COME NOW LUMA Energy, LLC (“ManagementCo”)1, and LUMA Energy ServCo, LLC (“ServCo”)2, (jointly referred to as “LUMA”), and, through the undersigned legal counsel, respectfully submit the following: 1. LUMA respectfully informs that due to an involuntary omission, the pdf of the Emergency Response Plan (ERP) that was filed on May 31, 2021 with this honorable Puerto Rico Energy Bureau, omitted Annex A (Major Outage Restoration), Annex B (Fire Response) and Annex C (Earthquake Response) to the ERP. 2. LUMA hereby submits Annexes A, B and C to the ERP. See Exhibit 1. 3. To protect personal identifying information of LUMA personnel, the signature and name of the LUMA officer that is identified in each of the Annexes (page 5 of Annex A, Annex B and Annex C), were redacted. LUMA hereby requests that the referenced signature and name be kept confidential in accordance with Section 6.15 of Act 57-2014 (providing, that: “[i]f any person who is required to submit information to the Energy Commission believes that the information to 1 Register No. 439372. 2 Register No. 439373. -1 be submitted has any confidentiality privilege, such person may request the Commission to treat such information as such .
    [Show full text]
  • UNITED STATES DISTRICT COURT for the DISTRICT of PUERTO RICO in Re
    UNITED STATES DISTRICT COURT FOR THE DISTRICT OF PUERTO RICO In re: PROMESA THE FINANCIAL OVERSIGHT AND Title III MANAGEMENT BOARD FOR PUERTO RICO Case No. 17 BK 4780-LTS as representative of PUERTO RICO ELECTRIC POWER AUTHORITY, Debtor. 1 UNIÓN DE TRABAJADORES DE LA INDUSTRIA PROMESA ELÉCTRICA Y RIEGO, INC.; ÁNGEL FIGUEROA- Title III JARAMILLO, as President of UNIÓN DE TRABAJADORES DE LA INDUSTRIA ELÉCTRICA Y RIEGO, INC.; FREDDYSON MARTÍNEZ-ESTEVEZ, Adv. Proc. No. ____________ Vice President of UNIÓN DE TRABAJADORES DE LA INDUSTRIA ELÉCTRICA Y RIEGO, INC; RALPHIE FOR INJUNCTION, DOMINICCI-RIVERA; WALDO ROLÓN; and DECLARATORY RELIEF, D RONALD VÁZQUEZ, as Vice President of the Retirees AMAGES Chapter of UNIÓN DE TRABAJADORES DE LA INDUSTRIA ELÉCTRICA Y RIEGO, INC. Plaintiffs, v. PEDRO R. PIERLUISI-URRUTIA, in his official capacity as Governor of the Commonwealth of Puerto Rico; COMMONWEALTH OF PUERTO RICO; PUERTO RICO ELECTRIC POWER AUTHORITY; THE FINANCIAL OVERSIGHT AND MANAGEMENT BOARD FOR PUERTO RICO, as representative of PUERTO RICO ELECTRIC POWER AUTHORITY; RALPH A. KREIL-RIVERA, in his official capacity as the President of the Governing Board of the PUERTO RICO ELECTRIC POWER AUTHORITY; EFRAN PAREDES-MAYSONET, in his official capacity as Executive Director of PUERTO RICO ELECTRIC POWER AUTHORITY; PUERTO RICO PUBLIC PRIVATE PARTNERSHIP AUTHORITY; FERMÍN 1 The Debtors in these Title III Cases, along with each Debtor’s respective Title III case number and the last four (4) digits of each Debtor’s federal tax identification number, as applicable, are the (i) Commonwealth of Puerto Rico (Bankruptcy Case No. 17 BK 3283-LTS) (Last Four Digits of Federal Tax ID: 3481); (ii) Puerto Rico Sales Tax Financing Corporation (“COFINA”) (Bankruptcy Case No.
    [Show full text]
  • Review of T&D's Operators
    NEPR Received: COMMONWEALTH OF PUERTO RICO May 14, 2021 PUBLIC SERVICE REGULATORY BOARD PUERTO RICO ENERGY BUREAU 11:25 PM IN RE: REVIEW OF T&D’S CASE NO. NEPR-MI-2021-0001 OPERATORS SYSTEM OPERATION PRINCIPLES SUBJECT: Motion Submitting Emergency Response Plan in Response to May 11th Resolution and Order. MOTION SUBMITTING LUMA’S EMERGENCY RESPONSE PLAN TO THE HONORABLE PUERTO RICO ENERGY BUREAU: COME NOW LUMA Energy, LLC (“ManagementCo”), and LUMA Energy ServCo, LLC (“ServCo”), (jointly referred to as “LUMA”), and respectfully state and request the following: 1. On May 10th and 11th, 2021, this honorable Puerto Rico Energy Bureau (“Bureau”) held a technical conference in this proceeding to consider LUMA’s proposed System Operation Principles. 2. On May 11, 2021, the Bureau issued a Resolution and Order (“May 11th Order”) that, among others, directed that LUMA “[p]rovide the final version and/or the preliminary draft of LUMA's emergency response plan as it relates to the operation of the system in response to an emergency.” See May 11th Order at page 4, item (v). 3. With this Motion and in compliance with the May 11th Order, LUMA is submitting the near final Emergency Response Plan. 4. On May 19, 2021, LUMA will be conducting a table-top exercise on the Emergency Response Plan after which time LUMA will proceed to finalize and formally submit the Emergency Response Plan before this Energy Bureau in the active docket for said submittal, Case No. NEPR-MI-2019-0006. 1 WHEREFORE, LUMA respectfully requests that this Bureau take notice of the aforementioned and deem that LUMA complied with that portion of the May 11th Order that requested that LUMA file its Emergency Response Plan.
    [Show full text]
  • GOBIERNO DE PUERTO RICO JUNTA REGLAMENTADORA DE SERVICIO PÚBLICO Jun 30, 2021 NEGOCIADO DE ENERGÍA DE PUERTO RICO 7:05 PM
    NEPR Received: GOBIERNO DE PUERTO RICO JUNTA REGLAMENTADORA DE SERVICIO PÚBLICO Jun 30, 2021 NEGOCIADO DE ENERGÍA DE PUERTO RICO 7:05 PM IN RE: REVIEW OF LUMA’S TERMS OF CASO NÚM.: SERVICE (LIABILITY WAIVER) NEPR-MI-2021-0007 ASUNTO: MOCIÓN SOLICITANDO ACCESO A LA INFORMACIÓN Y OTROS REMEDIOS MOCIÓN SOLICITANDO ACCESO A LA INFORMACIÓN Y LA OPORTUNIDAD DE PARTICIPACIÓN INFORMADA, REALIZACIÓN DE INVESTIGACIONES, SEÑALAMIENTO DE VISTAS PÚBLICAS Y OTROS REMEDIOS AL NEGOCIADO DE ENERGÍA DE PUERTO RICO: COMPARECEN el Comité Diálogo Ambiental, Inc. y El Puente: Enlace Latino de Acción Climática (El Puente de Williamsburg Inc.), a través de la representación legal que suscribe y respetuosamente, EXPONEN, ARGUMENTAN y SOLICITAN: “La comida se perdió toda, tenemos que estar comprando a diario…estamos bien perjudicados, esto es bien deprimente…el huracán de la transición”. -Residente de Cupey Bajo con padre encamado y con metástasis1 “Se me está quemando la casa, vengan pronto…” -Residente de San Sebastián 2 I. INTRODUCCIÓN Y BREVE TRASFONDO SOBRE EL SISTEMA ELÉCTRICO El Comité Diálogo Ambiental, Inc. (“Dialogo”) y El Puente: Enlace Latino de Acción Climática (“El Puente de Williamsburg Inc.”), Sierra Club Puerto Rico, Inc., CAMBIO, Inc., Mayagüezanos por la Salud y el Ambiente, Inc., Comité Yabucoeño Pro-Calidad de Vida, Inc., y 1 Véase, Sin luz hace una semana familia con paciente encamado en Cupey, https://www.wapa.tv/noticias/locales/sin-luz-hace-una-semana-familia-con-paciente-encamado-en- cupey_20131122507646.html?fbclid=IwAR2hPwSxS2- WzbkSU5Yu2_diKXATZf9hct_HCBGsLmS_aU6kCOAqBbZc5Bo. 2 Véase, https://www.telemundopr.com/noticias/puerto-rico/se-me-esta-quemando-la-casa-vengan-pronto/2225540/.
    [Show full text]
  • Establecimientos Participantes Donde Puedes Utilizar Tu Tarjeta Mcs Classicare Te Paga
    ESTABLECIMIENTOS PARTICIPANTES DONDE PUEDES UTILIZAR TU TARJETA MCS CLASSICARE TE PAGA Pago de gasolina, Para pago de facturas de luz, Pueblo Suplidor Facilidad Dirección alimentos saludables agua, teléfono y/o internet residencial ADJUNTAS FARMACIAS FARMACIA PROFESIONAL 22 CALLE BARBOSA ADJNTAS PR 00601 X ADJUNTAS GULF GULF ADJUNTAS CALE 5 GARZAS ADJUNTAS PR X GASOLINA ADJUNTAS GULF GULF B. VISTA ADJUNTAS CARR. 123 KM 33.2, BO. SALTRILLO X GASOLINA ADJUNTAS SHELL SHELL ADJUNTAS S/S CARR. 123 KM 35.7 BO. GARZAS X GASOLINA ADJUNTAS BURGER KING BURGER KING ADJUNTAS CALLE RODOLFO GONZALEZ 8 BO. PUEBLO X CALLE RODULFO GONZÁLEZ CARR. 55 KM.16.5 ADJUNTAS SELECTOS SELECTOS ADJUNTAS X X ADJUNTAS PR 00601 ADJUNTAS TOTAL TOTAL GUAJATACA CARR 2 KM 106.1 X GASOLINA ADJUNTAS TOTAL TOTAL J. VELEZ SERVICES CARR. 135 KM 80.9 BO. CAPAEZ X GASOLINA ADJUNTAS SELECTOS SELECTOS ADJUNTAS / SELECTOS BERR BO. VEGA ABAJO CARR. 5516 KM 0.8 X X ADJUNTAS ECOMAXX ECOMAXX YAHUECA CARR. 135 KM 13.1 BO. YAHUECAS X GASOLINA ADJUNTAS FARMACIAS FARMACIA PROFESIONAL 22 CALLE BARBOSA ADJUNTAS PR 00601 X AGUADA FARMACIAS FARMACIA AGUADA CARR 417 KM 3.2 BO. MAL PASO AGUADA, PR X AGUADA FARMACIAS FARMACIA DEL PUEBLO CALLE MARINA 162, AGUADA X AGUADA ECOMAXX ECOMAXX CERRO GORDO CARR. 110 KM 4.2 BO. CERRO GORDO X GASOLINA AGUADA FAMCOOP FAMCOOP AGUADA PR-115, AGUADA, PR 00602 X AGUADA GULF GULF AGUADA S/S CARR. 115 KM 25.1, BO. ASOMANTE X GASOLINA AGUADA GULF GULF AGUADA S/S PO BOX 57, MAYAGÜEZ, PR 00680 X GASOLINA AGUADA SHELL SHELL MARINA AGUADA S/S C/ COLON 150 ESQ.
    [Show full text]
  • Government of Puerto Rico Public Service Regulatory Board Puerto Rico Energy Bureau
    GOVERNMENT OF PUERTO RICO PUBLIC SERVICE REGULATORY BOARD PUERTO RICO ENERGY BUREAU CASE NO.: NEPR-MI-2021-0007 IN RE: REVIEW OF LUMA’S TERMS OF SERVICE (LIABILITY WAIVER) SUBJECT: Final Determination on LUMA's Terms of Service Petition (Liability Waiver) RESOLUTION AND ORDER I. Introduction (A) The Puerto Rico Electric System Transformation Puerto Rico suffers from an inherently deficient electric system, a condition that has been exacerbated after the impact of hurricanes Irma and María. In particular, the planning, design, and operation of an isolated island-based electricity system imposes on the Puerto Rico Electric Power Authority (“PREPA”), and Puerto Rico as a whole, significant challenges regarding power system stability and reliability. Act 120-20181 establishes the legal framework for the transformation of the electric power system in Puerto Rico.2 It empowers PREPA to sell its assets related to electric power generation and transfer or delegate any of its operations, functions, or services.3 Any agreement arising from Act 120-2018 shall be entered into under the legal and administrative framework established in Act 29-20094, which regulates Public-Private Partnerships. Act 120-2018 establishes the process that applies to any transaction that establishes a Public-Private Partnership for any PREPA function, services, or facility. In addition, Act 120-2018 empowers PREPA and the Puerto Rico Public-Private Partnerships Authority (“P3A”) to carry out the processes through which such transactions shall be executed.5 After conducting a competitive process in accordance with Act 120-2018 and Act 29- 2009, the P3A selected a third-party operator for the PREPA Transmission and Distribution System ("T&D System").
    [Show full text]
  • Puerto Rico Grid Privatization Flaws Highlighted in First Two Months of Operation LUMA Contract Has Led to Delays, Damages and Poor Service for Puerto Rico Customers
    Cathy Kunkel, Energy Finance Analyst 1 Tom Sanzillo, Director of Financial Analysis August 2021 Puerto Rico Grid Privatization Flaws Highlighted in First Two Months of Operation LUMA Contract Has Led to Delays, Damages and Poor Service for Puerto Rico Customers Executive Summary IEEFA reviewed the first two months of the implementation of Puerto Rico’s contract with LUMA Energy, the private operator hired to manage the island’s electric transmission and distribution system. The privatization of the grid, first announced in 2018 by former Gov. Ricardo Rosselló, is a key element of the Financial Oversight and Management Board (FOMB) plan to transform the island’s electrical system. In this report, IEEFA finds that since the June 1 takeover: • Puerto Ricans have experienced significant problems with the implementation of the contract, including longer service restoration times, voltage fluctuations and poor customer service. High-level government officials have acknowledged that service has worsened under LUMA, which already has been paid almost $180 million. • LUMA’s problems stem from its shortage of experienced employees. It has hired fewer than 30% of the former Puerto Rico Electric Power Authority (PREPA) workers. LUMA has been trying to operate the system with about 60% of the number of PREPA employees who did the same work. • LUMA has refused to provide information requested by the Puerto Rico Legislature, and no oversight documents related to LUMA’s performance in the last two months have been made public. • Implementation problems can be directly traced to flaws in the contract, including its treatment of PREPA’s workforce and its weak oversight provisions.
    [Show full text]