Epping Forest District Local Highway Panel - Approved Works Programme
Schemes Key Completed Cancelled Update
Approved Schemes - Prioritised for 2018/19 delivery
Scheme Ref Cost Code Scheme Parish Finish Scheme Stage Works Description Allocated Budget Category
Passenger 1 LEPP165004 Bushfields, Loughton - 1500IM399B (Parkmead) - PT Loughton 2018/19 Total Scheme Install metal bus shelter £8,500 Transport
Design Only. Traffic 2 LEPP152001 Church Road, Buckhurst Hill - One way Buckhurst Hill 2018/19 Design Letter drop for informal consultation with residents for £2,000 Management possible one way system
Traffic 3 LEPP162065 Pick Hill, Waltham Abbey Waltham Abbey 2018/19 Feasibility To look at the feasibility if Pick Hill can be made a one way £7,000 Management
Traffic 3x advanced signs to be installed on the approaches to 4 LEPP162003 Church Lane and Harlow Road Sheering - signage Sheering 2018/19 Total Scheme £11,500 Management Church Lane - unsuitable for HGV's
Traffic 5 LEPP162024 A113 Romford Road - Drainage Stanford Rivers 2018/19 Total Scheme Drainage works £21,000 Management
Change link road fronting war memorial to footway and Traffic 6 LEPP142011 War Memorial Lyndsay Street , Epping Epping 2018/19 Design associated junction improvements at Lyndsey Street/High £7,000 Management Street Epping Forest District Local Highway Panel - Approved Works Programme
Schemes Key Completed Cancelled Update
Coopersale Street, bend 200m south east of Traffic Land dedication arrangements to facilitate the installation 7 Epping 2018/19 Design £6,500 LEPP182001 Houblons Hill Management signing improvements at the bend
To look at feasibility of installing a footway and dropped 8 LEPP133015 Hemnall Street , Epping - Footway Epping Walking 2018/19 Feasibility kerbing as there is currently no footpath and pedestrians £6,500 including school children are walking in the road
1)To install additional bollards along the footway for a distance of 54m, from the first property in Forest Road to the junction of Smarts Lane Loughton Central and Loughton Traffic 9 LEPP162011 Forest Road j/w Smarts Lane, Loughton 2018/19 Implementation 2) Install double yellow line restriction just passed the priority £20,000 South Management working 3) Install junction protection markings at Smarts Lane to prevent vehicles parking on the junction
A feasibility study to investigate if a footway between Eldon Traffic 10 LEPP162069 Dobbs Weir, Roydon - Footway Roydon 2018/19 Feasibility Road and Lee Valley Regional Park Authority entrance is £7,000 Management feasible
Request for footway from the corner of Garnon Mead, 11 LEPP173003 Garnon Mead/Garnon Bushes Pathway - Footway Epping Walking 2018/19 Design Coopersale, near Epping, Essex passed the Garnon Bushes £7,000 Public House to join the existing footpath
Request for a footpath to make access to The Rabbits bus 12 LEPP163001 Church Lane to The Rabbits bus stop- Footway Stapleford Abbotts Walking 2018/19 Design £7,000 stop easier for residents that live down Church Lane
Passenger 13 LEPP175006 Outside Stewards Green - Bus shelter Epping 2018/19 Total Scheme Install wooden bus shelter £13,000 Transport Epping Forest District Local Highway Panel - Approved Works Programme
Schemes Key Completed Cancelled Update
Passenger 14 LEPP175005 Opposite Carpenters Arms, Thornwood - Bus shelter Epping 2018/19 Total Scheme Install metal bus shelter £8,000 Transport
Speed Table - replace with new material to current Pyrles Lane, Chester Road, Hillyfields - Traffic specification 15 LEPP142039 Loughton 2018/19 Implementation £38,000 Implementation of a speed table Management Signing improvements, replace guard railing
Traffic Further improvements to fingerposts within the Epping Forest 16 LEPP172005 District Wide Fingerposts District Wide 2018/19 Total Scheme £12,000 Management District
Forest Lane j/w New Forest Lane & Manor Road - Traffic 17 LEPP162066 Chigwell 2018/19 Feasibility Request to look into safety improvements at the junction £7,000 Junction improvement Management
Request for traffic calming measures to reduce speed of Traffic 18 LEPP172034 Piercing Hill Theydon Bois - Traffic calming Theydon Bois 2018/19 Total Scheme vehicles £20,000 Management
Request for traffic calming measures to reduce speed of Loughton Lane & Debden Lane Theydon Bois - Traffic 19 LEPP172033 Loughton 2018/19 Total Scheme vehicles £20,000 Traffic calming Management
Recommendations from feasibility study to implement a no Traffic 20 LEPP162014 Lower Road, Loughton - Loughton 2018/19 Design entry to southbound traffic at the junction with A121 Goldings £6,000 Management Hill, and Goldings Road
Traffic To implement Scheme Proposal 4.4 Advisory Lorry Route 21 LEPP162064 HGV Routing for Lea Valley Glasshouses Epping Forest 2018/19 Total Scheme £18,000 Management Signing, to amend and install new lorry route signage: Epping Forest District Local Highway Panel - Approved Works Programme
Schemes Key Completed Cancelled Update
Traffic Recommendations from feasibility study to update and 22 LEPP162016 Motts Street, Waltham Abbey Waltham Abbey 2018/19 Total Scheme £19,000 Management implement signage to advise roads are unsuitable for HGV.
Recommendations from feasibility study to realign the junction Traffic 23 LEPP162027 Tidy's Lane, Epping - TMI Epping 2018/19 Total Scheme by creating a larger carriageway area and increasing the kerb £17,000 Management line radius.
Approved Schemes- 2018/19 Delivery - Safer Road Schemes
Scheme Ref Cost Code Scheme Parish Finish Scheme Stage Works Description Allocated Budget Category
Reduce northbound section of Chigwell Lane to single 24 LEPP181001 Chigwell Lane A1168 M11 Motorway Loughton Safer Roads 2018/19 Total Scheme £21,500 carriageway
25 LEPP181002 A113 Abridge Road j/w entrance to Virgin Active Chigwell Safer Roads 2018/19 Design Junction realignment and carriageway lining £7,000
Two Gates Tylers Road Location 500m West of j/w 26 LEPP181003 Roydon Safer Roads 2018/19 Total Scheme Install bend ahead, horse warning sign and chevron signs £15,500 B181
A414 j/w Blake Hall Road , Lower Bobbingworth 27 LEPP181004 Ongar Safer Roads 2018/19 Total Scheme Install verge marker posts £15,500 Green
28 LEPP181005 High Road, j/w Upland Road B1393 Upland Road Epping Safer Roads 2018/19 Total Scheme Install side road ahead warning sign £4,000