TRAFFIC ANNOUNCEMENT UPDATES ON TRAFFIC MANAGEMENT PLAN FOR MRT CONSTRUCTION ALONG PERSIARAN SURIAN AND DAMANSARA-PUCHONG HIGHWAY (LDP HIGHWAY) 5 SEPTEMBER 2016

1. CONTINUATION OF CLOSURE ALONG DAMANSARA- PUCHONG HIGHWAY (LDP HIGHWAY) AND PERSIARAN BANDAR UTAMA (KEPONG-BOUND AND SS2-BOUND) Date 6 September 2016 – 2 October 2016 Time 12:00AM – 6:00AM Duration 26 Days Reason To facilitate mobilisation of construction vehicles, link bridge installation and other works at the Bandar Utama MRT station

There will be a continuation of the closure along the LDP Highway and Persiaran Bandar Utama from 6 September 2016 – 2 October 2016 from 12:00AM to 6:00AM .The closures will be done intermittently and are as follow:

 Closure of one lane in front to Damansara Utama SS21 (Kepong-bound)  Closure of Persiaran Bandar Utama (both bounds) from Dataran Bandar Utama to exit into LDP Highway  Closure along LDP Highway from Sri Pentas junction to One Utama (New Wing) junction

During these closures, the following diversions will take place (please see map appended below): ( ) Motorists from SS2 on LDP Highway (Kepong-bound) / Motorists from Jalan Damansara wanting to turn into Persiaran Bandar Utama are to drive 250m ahead and turn left into Persiaran Surian where they can access the Bandar Utama area by making another left turn at Dataran Bandar Utama. ( ) Motorists from the Sprint Highway intending to go to Bandar Utama may also continue to travel on the Sprint Highway (E23) and approach One Utama from the southern entry i.e. Lebuh Bandar Utama.

Signages, safety barriers, traffic cones and flagmen will be in place to ensure road users are alerted of the closure and on-going works.

Page 1 of 4

MAP 1: CONTINUATION OF CLOSURE ALONG DAMANSARA- PUCHONG HIGHWAY (LDP HIGHWAY) AND PERSIARAN BANDAR UTAMA (KEPONG-BOUND AND SS2-BOUND)

Page 2 of 4

2. SHORT TERM TRAFFIC MANAGEMENT PLAN ALONG PERSIARAN SURIAN NEAR PELANGI DAMANSARA AND PELANGI SQUARE Date 8 September - 19 September 2016 Time 11:00PM - 6:00AM Duration 11 Nights Reason To facilitate the delivery, assembly and launching of steel truss at pedestrian link bridge in the vicinity of Pelangi Astana and Pelangi Square

There will be a short term traffic management plan (TMP) along the Persiaran Surian from 8 September 2016 - 19 September 2016 from 11:00PM to 6:00AM in the vicinity of Pelangi Astana and Pelangi Square. The closures will be conducted in two phases as follow:

Phase 1 : Delivery and Assembly of Steel Truss from 8 September to 11 September 2016 (4 nights)  Single bound closure (-bound) will be implemented along Persiaran Surian in front of Pelangi Astana for a stretch of 250M. During this closure, motorists will be diverted to use the inner road within the parking area of Pelangi Astana (shown by purple arrows).

MAP 2 (PHASE 1): DELIVERY AND ASSEMBLY OF STEEL TRUSS

Page 3 of 4

Phase 2: Launching of Truss from 13 September 2016 to 19 September 2016 (7 nights)  Closure of exit into Pelangi Damansara Block G-K and Pelangi Astana on Persiaran Surian (Kota Damansara bound) for a stretch of 250M.During this closure, motorists will be diverted to use the inner road within the parking areas of Pelangi Astana (shown by green and purple arrows)

MAP 2 (PHASE 2): LAUNCHING OF TRUSS

For media enquiries, please contact: Adeline De Cruz Tel: +6012 217 2017 [email protected] Siti Fadzillah Ismail Tel: +603 7493 3965 [email protected]