62 Sabah Electricity Sdn

Total Page:16

File Type:pdf, Size:1020Kb

62 Sabah Electricity Sdn SABAH ELECTRICITY SDN BHD During the year, Sabah Electricity Sdn Bhd (SESB) focused its activities to improve the quality of electricity supply in the state. A number of projects were implemented to strengthen the supply as well as the transmission system in Sabah and the Federal Territory of Labuan. As a result, the number of interruptions recorded in 2003 was 1,733, down from 1,853 in 2002. SESB Generation The generation system of SESB is currently firm with an installed capacity of 758MW (including from CORPORATE REPORT 2003 REPORT CORPORATE five IPPs). During the year under review, the total units generated registered 2,940,360MWh with an Energy Generation Mix described below. Oil (SESB) 29% Tenaga Nasional Berhad Tenaga Gas (IPP) 25% 62 Hydro (SESB) 15% Gas (SESB) 15% Oil (IPP) 16% Several generation projects that had been identified for implementation such as the installation of additional steam turbines (conversion to combine cycle mode) in Patau-Patau Power Station and the construction of the Kayumadang open-cycle turbine, were deliberated. The company decided to replace them with the Sepangar Bay Corporation (SBPC) IPP Project. SESB had a series of negotiations with SBPC and decided to focus on the implementation of a 100MW Combine Cycle. The agreement on the best acceptable tariff has been approved. SESB has also initiated negotiations for Renewable Energy Purchase Agreement (REPA) with SREP Entrepreneurs. Two agreements have been signed. The first was with Bio-Energy Sdn Bhd (10MW) in Kunak in October 2002, and the second was with Kalansa Energy Corporation Sdn Bhd (5MW) in Beluran in August 2003. Meanwhile, the Patau-Patau Power Station was awarded the ISO 9001:2000 certification in September 2002. 63 Tenaga Nasional Berhad CORPORATE REPORT 2003 SESB Transmission During the year, SESB continued the implementation of the Northern Transmission Grid Project that included the extension of the West Coast Grid connecting the main stations in the northern part of Sabah, namely Kudat, Kota Belud and Kota Marudu through a 170 km transmission line. The objective of this project is to reduce the operational cost in the northern region where these power stations will halt operations by early 2004. SESB also undertook the East-Coast Transmission Grid Project to connect the IPP stations to SESB’s main power stations in the east coast namely Sandakan, Lahad Datu, Semporna and Tawau through a 327 km transmission line. It was completed in August 2003 and helped reduce operation costs in this region. The Lahad Datu Power Station and Semporna Power Station are expected to stop operations. The East-West Interconnection Project connects the East-Coast Grid and West-Coast Grid through a 250 km transmission line. Here, the overall operational cost will be further reduced when the transfer and utilisation of cheaper source of energy from the west coast of Sabah takes effect. The above projects were financed under the Seventh and Eighth Malaysia Plan. With the completion of the projects, SESB would enhance its services to the people especially the industrial and commercial sectors in the east-coast and northern region of Sabah. SESB Distribution The most important programme undertaken by the SESB Distribution Division during the financial year 2003 was the implementation of the T7 strategy. The key initiatives were:- CORPORATE REPORT 2003 REPORT CORPORATE Reduce distribution system loss Improve supply reliability @ Quality Improve revenue collection A new disconnection system as a credit control device had been implemented. Several customers including Maxis and Celcom have been incorporated in the bulk payment system. Tenaga Nasional Berhad Tenaga 64 The total number of customers in Sabah according to tariff is 318,585 and recorded as follows:- Tariff Nos. % DM 265,795 83 300,000 CM1 47,472 15 265,795 CM2 78 0 250,000 ID1 2,479 1 200,000 ID2 119 0 PL 2,672 1 150,000 100,000 50,000 47,472 2,479 2,672 78 0 119 PL ID1 ID2 DM CM2 CM1 Energy sold in GWh according to tariff is 2,290.42 and recorded as follows:- Tariff Energy Sold(GWh) % DM 708.88 31 800 CM1 668.42 29 708.88 CM2 201.88 9 700 668.42 ID1 173.18 8 600 505.58 ID2 505.58 22 500 PL 32.48 1 400 300 65 201.88 200 173.18 100 32.48 0 PL ID1 ID2 DM CM1 CM2 Energy sold according to tariff is RM581,299,533 as follows:- 2003 REPORT CORPORATE Tariff Energy Sold (RM) DM 160,718,620 CM1 196,830,664 196,830,664 CM2 56,795,692 200,000,000 Nasional Berhad Tenaga ID1 47,529,393 160,718,620 ID2 109,765,857 150,000,000 PL 9,659,307 109,765,857 100,000,000 56,795,692 47,529,393 50,000,000 9,659,307 0 PL ID1 ID2 DM CM1 CM2 EDUCATION & RESEARCH DIVISION Introduction During the year, the Education and Research Division emphasised on the effort to make education and learning, a major organisational process and business, and its contribution to the national agenda whilst turning education into a major revenue earner and a source for professional resources. The synergistic relationship between UNITEN and TNB Research Sdn Bhd (TNBR) in particular provided a useful platform for education and knowledge advancement through research while Tenaga Nasional CORPORATE REPORT 2003 REPORT CORPORATE Foundation rendered an important contribution by way of financial assistance to deserving students. The long term strategic reviews currently undertaken for UNITEN are among others, an attempt to put in place a better strategic fit where UNITEN’s maturity into a world class engineering university and centre of excellence, will provide the needed alignment and higher educational values as seen from the quality of its programmes, faculty resources, facilities and graduates. The division through its Tenaga Nasional Berhad Tenaga coordinating activities, has laid down the mechanism where renewal and change become the ingredients 66 for continuous improvement in Universiti Tenaga Nasional. Universiti Tenaga Nasional Universiti Tenaga Nasional created history when it successfully implemented the Quality System that met the MS 9001:2000 Quality Management Systems for support services and was awarded the Quality System Registration Certificate by SIRIM on 20 June 2003. At the Private Education Night 2003 held on 9 June 2003, the university won two awards from the Minister of Education for “Excellence in Research and Development R&D” and for the highest number of courses accredited by the National Accreditation Board (LAN). These accolades from external bodies have given recognition to Universiti Tenaga Nasional as an excellent university in Malaysia. The academic programmes offered at Universiti Tenaga Nasional have also been given recognition by professional bodies. Its Bachelor of Engineering degrees are recognised by the Board of Engineers, Malaysia (BEM) and the Institution of Engineers Malaysia (IEM) whilst the Bachelor of Accounting degree is recognised by the Malaysian Institute of Accountants (MIA). At the international level, the accounting degree is recognised by the Association of Certified Chartered Accountants (ACCA), Chartered Institute of Management Accountants (CIMA) and the Institute of Chartered Secretaries and Administrators (ICSA) – all from the United Kingdom. Effort is being made to also gain recognition from the Chartered Public Accountants, Australia (CPA Australia). Universiti Tenaga Nasional has successfully sealed a Memorandum of Understanding (MoU) with several prestigious foreign universities on cooperation/collaboration for mutual benefit. The universities are the University of Strathclyde, University of Southampton, Lancaster University, University of Liverpool, University of Sussex, University of Newcastle, University of Stirling and the University of Brighton – all from the United Kingdom. Universiti Tenaga Nasional continues to attract students for higher education in the fields of engineering, information technology, business management and accountancy. As at August 2003, the total number of students was 6,851 of which 5,520 students are in the main campus in Bangi and 1,331 students at the Muadzam Shah Campus in Pahang. The latter number was achieved when the accommodation infrastructure for 1,000 students was completed in May/June 2003. 67 Tenaga Nasional Berhad CORPORATE REPORT 2003 At the convocation ceremony from 16-17 August 2003, 1,363 graduates received their diploma and bachelor degrees – 771 graduates in the fields of engineering and information technology as well as 575 graduates in business management and accountancy. 17 graduates were awarded postgraduate Master degrees. More than 11,000 applications have been received from potential students wishing to gain admission into Universiti Tenaga Nasional. However, only 1,984 students were successfully accepted. Tenaga Nasional Foundation Annually, a few high achievers of SPM are given the opportunity to study overseas, selected according to the competitive criterias that have been set by the Foundation. These students undertake their pre-university studies locally before pursuing their first year overseas. The Tenaga Nasional Foundation is pleased to mention that some of these scholars were awarded with notable prestigious awards, eg. the Tony Davies Memorial Prize, the National Grid Company Prize and the Electronic Engineering Prize for the Shell Technology Enterprise Programme (STEP). In terms of welfare funding, the Tenaga Nasional Foundation has achieved success in organising the Kem Remaja Bestari 2003, an annual event comprising more than 1,000 students across the peninsula. CORPORATE REPORT 2003 REPORT CORPORATE This camp gives them further insights on study skills, time management and other tips on how to be successful in their study life. The Tenaga Nasional Foundation is also continuing the establishment and operation of nurseries and kindergartens at various workplaces of TNB, to serve the need of young mothers, especially those who are TNB employees. The Tenaga Nasional Foundation is currently funding and monitoring the running of nurseries and kindergartens at 19 workplaces (catering to 717 children) and 35 tuition centres (catering to 1,987 students).
Recommended publications
  • Buying Renewable Energy in Malaysia
    MAY 2021 Buying Renewable Energy in Malaysia Corporate Renewable Energy and Low Carbon Supply Chain Series Malaysia’s electricity market provides corporate buyers of Population Average Electricity Price (Est.) renewable energy with multiple procurement pathways, Malaysia 32,644,524 $.09 - .10/kWh including corporate power purchase agreements (PPAs) and a variety of other bundled and unbundled options. at a Glance Current Renewable Energy Mix Projected PPA Cost (Est.) The volume of corporate transactions has thus far been (Incl. Large Hydro) $0.07 - .09/kWh limited, but attractive osite PPA opportunities are 23% emerging and will be a private sector demand driver in the coming years. With prices that are increasingly cost Renewable Energy Goal Estimated Unbundled EAC Price (Incl. Large Hydro) $1 - 2/MWh competitive and an ability to create significant carbon 31% by 2025 benefits due to the country’s heavy reliance on coal and natural gas, Malaysia is well positioned to facilitate the Grid Emissions Factor Bundled EAC Price growing appetite for renewable energy by multinational 0.64 kgCO2/kWh $19/MWh and local companies alike. Renewable Energy Procurement Options RE100/CDP Procurement Option Availability Key Considerations Eligibility Process Supportive Policies, Contact Local Solar Onsite Renewables Limited Generation Providers TNB Is Single Retail Subscribe To myGreen+ Retail Renewable Energy Provider Oering From TNB Both I-RECs and TIGRs Procure Using mGATS Platform Unbundled EACs Available. I-RECs Associated or Directly From Projects
    [Show full text]
  • Energy Malaysia
    Energy Malaysia Towards a World-Class Energy Sector Volume 15 | 2018 www.st.gov.my MEASURING THE ENERGY Volume 15 Volume A Brand New COMMission’s SUCCESS Energy Industry Energy Malaysia highlights the achievements during RP2 Leading the Way a successful for a Brighter Future Regulatory Period 1. ENHANCING sabah’s supplY Energy Malaysia KDN: PP 18540/08/2014(033966) KDN: PP shines a spotlight on SAIDI 100 Lab, an initiative to improve Sabah’s SAIDI and Sabah Electricity Supply Industry (SESI). MYR 8.00 Volume 15 www.st.gov.my Front Cover v1.indd 1 10 /7/18 6:46 PM S NT E 20 ONT C FEATures INNOVATION 02 12 20 Chairman’s Message What Happens Now? A Technological Change With a successful RP1, the Artificial Intelligence (AI) is the future, industries are looking forward to invading one aspect of our life at a time. 03 the second regulatory period. Energy Matters We take a look at how AI is changing Energy Malaysia examines the the energy sector globally and how the The latest news and updates on changes within industries and how their nation’s energy sector is coping industry developments, government development is parallel to the with the digital invasion. initiatives and innovations in the energy industry’s transition. Malaysian energy sector. FEATURES FEATures 24 15 SAIDI 100 Lab: COVER STORY Keeping Up with the KPIs Powering up Sabah Energy Malaysia takes a look at The Sabah Electricity Supply Industry how the Energy Commission (SESI) has been facing various has achieved its targets during challenges. We took a look at SAIDI RP1 towards becoming a 100 Lab and its mission to improve more efficient regulatory body.
    [Show full text]
  • Integration of Renewable Energy Into Grid System – the Sabah Green Grid
    Integration of Renewable Energy into Grid System – The Sabah Green Grid Aeni Haryati Hashim, Ahmad Khairulnizam Khairuddin and Joon B. Ibrahim, Member IEEE Single Buyer Department, Regulatory Economics and Planning Division Tenaga Nasional Berhad Kuala Lumpur, Malaysia [email protected], [email protected], [email protected] Abstract—In Malaysia, renewable energy made its official debut the national energy mix under the 8th Malaysia Plan in 2001. in 2001 through the 8th Malaysia Plan whereby renewable In this plan, Malaysia had set a target of 5 percent of total energy target was embedded in the national energy mix. Since generation capacity to come from renewables by 2005 [2]. then, the government has rolled out several policies and act to However, to date, there is less than one percent renewables in promote renewable generation but the take up rate was very the generation mix whereas natural gas and coal continue to slow. The introduction of Feed in Tariff (FiT) in 2011 in dominate with 55 percent and 40 percent of the total Peninsula Malaysia, managed to heighten the interest in generation mix respectively [3]. commercial renewable energy generation, predominantly from solar producers. The scope of FiT was then expanded to include Nevertheless, the failure to meet the initial penetration Sabah and WP Labuan beginning 2014. Sabah, being the largest level for renewable energy in the national generation mix is crude palm oil producing state in Malaysia, hosts a huge not due to the lack of initiatives from the government. Various potential for biomass integration to the grid via this scheme.
    [Show full text]
  • An Evaluation of the Prospects for Interconnections Among the Borneo
    AN EVALUATION OF THE PROSPECTS FOR INTERCONNECTIONS AMONG THE BORNEO AND MINDANAO POWER SYSTEMS AN EVALUATION OF THE PROSPECTS FOR INTERCONNECTIONS AMONG THE BORNEO AND MINDANAO POWER SYSTEMS Final Report November 2014 The views expressed in this publication are those of the authors and do not necessarily reflect the views and policies of the Asian Development Bank (ADB) or its Board of Governors or the governments they represent. ADB does not guarantee the accuracy of the data included in this publication and accepts no responsibility for any consequence of their use. By making any designation of or reference to a particular territory or geographic area, or by using the term “country” in this document, ADB does not intend to make any judgments as to the legal or other status of any territory or area. ADB encourages printing or copying information exclusively for personal and noncommercial use with proper acknowledgment of ADB. Users are restricted from reselling, redistributing, or creating derivative words for commercial purposes without the express, written consent of ADB. Contents Abbreviation v Common Technical and Financial Acronyms used in this Report vii Currency viii Physical Measurement Units and their Application ix Acknowledgments x Report Summary and Recommendations xi 1 Overview and Study Objectives 1 2 Eastern ASEAN Grid Development Planning 2 2.1 Overview of ASEAN Region Power Development Plans 2 2.2 Energy Security within the ASEAN Power Market 4 2.3 Grouping of ASEAN and BIMP/EAGA sub-regional power systems 4 2.4 Eastern
    [Show full text]
  • 45076-001: an Evaluation of the Prospects for Interconnections
    AN EVALUATION OF THE PROSPECTS FOR INTERCONNECTIONS AMONG THE BORNEO AND MINDANAO POWER SYSTEMS AN EVALUATION OF THE PROSPECTS FOR INTERCONNECTIONS AMONG THE BORNEO AND MINDANAO POWER SYSTEMS Final Report November 2014 The views expressed in this publication are those of the authors and do not necessarily reflect the views and policies of the Asian Development Bank (ADB) or its Board of Governors or the governments they represent. ADB does not guarantee the accuracy of the data included in this publication and accepts no responsibility for any consequence of their use. By making any designation of or reference to a particular territory or geographic area, or by using the term “country” in this document, ADB does not intend to make any judgments as to the legal or other status of any territory or area. ADB encourages printing or copying information exclusively for personal and noncommercial use with proper acknowledgment of ADB. Users are restricted from reselling, redistributing, or creating derivative words for commercial purposes without the express, written consent of ADB. Contents Abbreviation v Common Technical and Financial Acronyms used in this Report vii Currency viii Physical Measurement Units and their Application ix Acknowledgments x Report Summary and Recommendations xi 1 Overview and Study Objectives 1 2 Eastern ASEAN Grid Development Planning 2 2.1 Overview of ASEAN Region Power Development Plans 2 2.2 Energy Security within the ASEAN Power Market 4 2.3 Grouping of ASEAN and BIMP/EAGA sub-regional power systems 4 2.4 Eastern
    [Show full text]
  • Rehabilitation of the Tenom Pangi Hydropower Project
    Malaysia Rehabilitation of The Tenom Pangi Hydropower Project Field Survey: August 2003 1. Project Profile and Japan’s ODA Loan Tenon Pangi Site location map Entrance to Tenom Pangi Hydroelectric Power Plant 1.1. Background Tenom Pangi Hydroelectric Power Plant went into operation in 1984 as the core power plant supplying electricity to western coastal regions of Sabah state, Malaysia (an area centered round Kota Kinabalu that accounts for 40% of the state’s electricity consumption), and is the only large-scale hydroelectric power plant in the state. It is situated on the banks of the Padas river on the outskirts of Tenom city some 120 kilometers to the south of the state capital, Kota Kinabalu. The plant has a generation capacity of 66 MW (3 × 22 MW generators) and covered a little over 50 percent of peak demand (123.1 MW) in the west coast region when the operation started. However, the Padas river flooded as the result of heavy rains throughout September 1988 (250.1mm of rain was recorded for the month) causing damage to the water intake gate and other facilities (trash protection, vertical gates, etc.) and hindering the operation of the power plant. This resulted in the suspension of power supplies due to the unplanned suspension of operations at the plant, leading to the loss of stable power supplies. In order to put an end to this problem and restore the plant to its original state, the implementation of urgent and appropriate rehabilitation work was a pressing issue. 1.2. Objectives To eliminate problems relating to the operation and maintenance of the Tenom Pangi Hydroelectric Power Plant through the rehabilitation of those existing facilities and equipment that had sustained damage due to flooding and thereby, to contribute to efficient supply of power.
    [Show full text]
  • Rural Electrification in East Malaysia - Achieving Optimal Power Generation System and Sustainability of Rural Electrification Projects
    Rural Electrification in East Malaysia - Achieving optimal power generation system and sustainability of rural electrification projects Tian Shen Liang Master of Science Thesis KTH School of Industrial Engineering and Management Energy Technology EGI-2016-069 SE-100 44 STOCKHOLM Master of Science Thesis EGI-2016-069 Rural Electrification in East Malaysia - Achieving optimal power generation system and sustainability of rural electrification projects Tian Shen Liang Approved Examiner Supervisor 26/1/2016 Viktoria Martin Viktoria Martin Commissioner Contact person Tian Shen Liang 1 Abstrakt Syftet med detta projekt är att föreslå förbättringar till en icke-statlig organisation i Malaysia, Lightup Borneo, för utformning av ett optimalt elproduktionssystem som kontinuerligt kan leverera el. Dessutom diskuteras hur hållbarhet kan uppnås i elektrifieringsprojekt på landsbyggden. Projektet har sträckt sig över sex månader, och inkluderar resultat från faktainsamling, fältarbete, samt en datorsstödd fallstudieanalys med hjälp av mjukvaran Homer. Statliga program för elektrifiering har undersökts, och verkar som referenser för genomförande av projektets mål. Kampung Mantapok valdes som föremål för fallstudien. Det system som för närvarande är installerat i denna by består endast av en 10 kW mikrovattenkraftverk med en enkel kontrollmodul. Byns totala elbehov är 53.72 kWh/d, med dagliga toppbelastningar kl 11 samt 17. Ett antal systemkonfigurationer, baserade på faktorförsök har utvärderas med HOMER. En systemkonfiguration bestående av en 10 kW mikrogenerator för vattenkraft, en 3 kW inverter samt två 280 Ah batterier valdes. I denna utformning erhölls det lägsta COE och NPC – RM 0.181 (US$ 0.045) respektive RM 46,230 (US$ 11,558). Denna konfiguration tillgodoser 100% av elbehovet på årsbasis.
    [Show full text]
  • Malaysia: Roadmap for a Smart, Efficient & Reliable Grid to Meet Future Electricity Demand
    Planning for Smart Grid in TNB System PECon2010 2010 IEEE Conference on Power and Energy Sunway Resort Hotel & Spa Mohd Yusof Rakob Tenaga Nasional Berhad, Malaysia [email protected] 1 Contents of presentation • Introduction • Electric power utility companies in Malaysia • Overview of demand – supply of TNB’s grid system • Overview of TNB’s grid system Coal • Identifying drivers for developing smart grid • Features of TNB’s smart grid • TNB’s smart grid implementation plan • Future prospects and opportunities “Powering The Nation” 2 Electric power utility companies in Malaysia Peninsular Malaysia Tenaga Nasional Berhad (TNB) Sabah Sabah Electricity Sendirian Berhad (SESB) (80% owned by TNB) Sarawak Sarawak Energy Berhad (SEB) 3 General profile of power utilities in Malaysia TNB (P. Malaysia) SEB (Sarawak) SESB (Sabah) • Operates in Peninsular • Operates in Sarawak • Operates in Sabah Malaysia • Total generation • Total generation • Total generation capacity: 1230 MW capacity is 866.4 MW capacity is 21,051 MW (2009) (2010) (2010) • Customer is 499,618 • Customer is 413,983 • Customer is 7,593,684 • Max demand : 1036 • Max demand :760 MW • Max demand: MW • Gen mix (2009): 15,072MW • Gen mix (2009): – 57% oil • Gen mix (2010): –53% gas – 31% gas – 54% gas – 34% coal – 9% hydro – 40% coal –8% hydro – 3% biomass. – 5.2% hydro –5% diesel – 0.2% distillate NOTE: Electricity supply industry in Malaysia is a fully regulated. TNB, SEB and SESB are vertically integrated and operate along with independent power producers (IPPs). 4 Overview Of TNB
    [Show full text]
  • Chapter 4. Distributed Energy System in Malaysia
    Chapter 4 Distributed Energy System in Malaysia Introduction Off-grid power generation is meant to supply remote or rural areas, where grid connection is almost impossible in terms of cost and geography, such as island, aboriginal villages, and areas where nature preservation is a concern. Harnessing abundant renewable energy sources using versatile hybrid power systems can offer the best, least-cost alternative solution for extending modern energy services to remote and isolated communities. The Tenth Malaysia Plan (2011–2015) prioritised rural development to enhance inclusivity as the nation progressed towards becoming an advanced inclusive nation. Rural development focused on uplifting the well-being of the rural community and stimulating economic activities based on land and natural resources. It also emphasised providing rural basic infrastructure, which resulted in the increase of rural water and electricity supply as well as nationwide road coverage. The coverage of rural roads expanded by 11.7% from 45,905 kilometres (km) in 2009 to 51,262 km in 2014. In Sarawak, 250 km of ex-logging roads were upgraded to provide access to 31,512 people in underserved rural areas. In terms of utilities, coverage of rural electricity reached 97.6% and water supply 93.8%; 188,270 water tanks were also provided to supply clean water to 251,200 rural households in the remote areas of Sabah and Sarawak. Under the Eleventh Malaysia Plan (2016–2020), the Rural Electricity Supply Programme will continue to focus on off-grid generation for remote and isolated areas. The government will also establish partnerships with non-governmental organisations to develop renewable energy sources for the rural community.
    [Show full text]
  • Malaysia Energy Landscape
    MALAYSIA ENERGY LANDSCAPE August 2018 ©2018 Business France. All Rights Reserved August 2018 1 MALAYSIAN ELECTRICITY MARKET ©2018 Business France. All Rights Reserved August 2018 2 INSTALLED CAPACITY IN ASEAN Thailand Population Installed Cap. Vietnam (million) (kw/person) Philippines FR 67 2.0 Myanmar SG 5 2.8 MY 30 1.2 Other TH 67 0.7 ASEAN (Brunei, Lao, Cambodia) VN 90 0.4 5 GW ID 250 0.3 48 GW 40 GW 23 GW PH 100 0.2 MM 54 0.1 Indonesia Global average ~0.8kW/person Malaysia 9 GW Installed Capacity (GW) Singapore Coal 65 Gas 97 Hydro 45 Renewables 12 14 GW Oil 20 36 GW Nuclear 0 64 GW TOTAL ~239 Low per capita installed base … Significant future addition requirements Source: GE Power Marketing – MACA 2017 ©2018 Business France. All Rights Reserved August 2018 3 MALAYSIA ELECTRIVITY KEY FIGURES Key Figures ELECTRICITY MARKET Pop. (Millions) GDP per Capita GDP 2016 GDP 2017 (USD) Tenaga Nasional Berhad (TNB) 32.3 9 982 + 4.2 % + 5.9 % (National electricity operator) 2017 : 47.4 b MYR (9.5 b EUR) 2016 : 44.5 b MYR (8.9 b EUR) Market Characteristics Electricity access : rd 3 User Market in ASEAN • Peninsula : 99,8 % World Bank has globally ranked Malaysia at 8th place (right after Switzerland) in • Sarawak : 91 % term of Getting Electricity rank within the Doing Business report. • Sabah : 94,1 % Electricity demand is expected to grow by 3.5% per year over the next 10 Electricity network: years, and 2.7% within 20 years. The average annual electric consumption • Peninsula : 21 469 km within the period of 2015-2020 is at 3.1%.
    [Show full text]
  • Investor Presentation
    INVESTOR PRESENTATION COE – INVESTOR RELATIONS 01 INTRODUCTION TO TENAGA 02 REGULATORY AGENDA 03 BUSINESS STRATEGY & DIRECTION 04 DIVIDEND 05 FY2021 OUTLOOK 06 APPENDIX 2 INTRODUCTION TO TENAGA Regulatory & Shareholding Structure REGULATORY & SHAREHOLDING STRUCTURE LEADERSHIP POSITION PRIME MINISTER / TNB Market Cap CABINET As at 3rd March 2021: RM58.9bn • Ranked 1st for Utilities Company • Ranked 4th in KLCI Shareholders Policy Maker Sabah Electricity Ministry of Energy and Natural Ministry of Finance Holds Sdn Bhd (SESB) ‘Golden’ Resources (KeTSA) (83% owned by TNB) Share a) Khazanah Dependable Capacity: 1,223MW b) PNB c) EPF 70.7% Implementor Tenaga Nasional Bhd (TNB) d) KWAP ENERGY COMMISSION (Regulator) e) Other Govt. Agencies - Promote competition - Protect interests of consumers Local Corp. & Retail 16.4% - Issue licenses MALAYSIA - Tariff regulation Foreign 12.9% Market Participant Sarawak Energy Bhd Tenaga Nasional Berhad IPP (SEB) CONSUMERS Note: Data / Info as at Dec 2020 3 INTRODUCTION TO TENAGA Regulated & Non-Regulated Business Generation Grid/Transmission Distribution Network & Retail Non-Regulated Business Regulated Business TNB Generation Mix: Installed Capacity: Distribution Network Length: 25,212MW Transmission Network Length: 683,008KM TNB: 14,561MW @ 57.9% Solar 0.1% IPP: 10,854MW @ 42.1% 23,964KM Distribution Substations: Hydro 6.2% Generation Market Share: 83,467 Transmission Substations: Core Business Core 61.3% 456 Gas & LNG 28.8% SAIDI: Equivalent Availability Factor 45.0mins (EAF): Transmission System Minutes: Coal 64.9% 87.4% Customer Satisfaction Index (CSI): Note: TNB installed capacity & Market Share 0.08 mins are based on gross capacity 8.1 Source: TNB Data / Info as at Dec 2020 Main Subsidiaries Non-Regulated Business Operation &Maintenance (O&M) Renewables, Energy Efficiency & Other Services Education & Research • TNB Repair & Maintenance Sdn.
    [Show full text]
  • Economic Analysis in Restructured Electricity Supply Industry \(ESI\)
    MATEC Web of Conferences 40, 007 03 (2016) DOI: 10.1051/matecconf/20164007003 C Owned by the authors, published by EDP Sciences, 2016 Economic Analysis in Restructured Electricity Supply Industry (ESI) for Malaysian Market Model N. Mohamad1 , P.D Abdul Aziz2, and F.Z. Hamidon3 1Electrical Technology Section, Universiti Kuala Lumpur British Malaysian Institute, Malaysia 2Electrical Technology Section, Universiti Kuala Lumpur British Malaysian Institute, Malaysia 3Electrical Technology Section, Universiti Kuala Lumpur British Malaysian Institute, Malaysia Abstract. Before 1980s, the generation, transmission and distribution vertically related sectors have typically been tied together within a utility. It has been either, investor owned and state-regulated or owned by the local municipality. Each sector was thought of as a natural monopoly. During that era, there were two main reasons accelerated for restructuring needs. The first one was to widen up the choices of electricity for customers. And the second one was due to rapid expansion capacity needs in generation, transmission and distribution. In Malaysia, the Malaysian Electricity Supply Industry (MESI) has aimed to restructure its current model to become a wholesale market model. In 1992, by introducing the Independent Power Producers (IPPs) in the loop, MESI applies Single Buyer model. Single Buyer model is one of the existing models available under the restructuring apart from Pool and Bilateral. This paper evaluates the economic benefits for Malaysia with the current structure from the side of electricity provider. A case study with load variation for three different maximum demands is considered in this paper. The mathematical equation developed by zero Loss of Load Probability is applied to evaluate the economic benefits.
    [Show full text]