Application form for Environmental Clearance Project Name: Residential Project, Ambi, APPENDIX - I (See paragraph – 6) FORM 1 (I) Basic Information Sr. No. Item Details 1 Name of the project/s Residential project Xrbia Developers Limited At Village Ambi, Taluka- Maval, District- Pune. 2 S. No. in the Schedule 8 (a) 3 Proposed capacity / area/ Total Plot Area 45,481.14 m2 length/tonnage to be handled/ Deduction in Road Widening 645.76 m2 command area/lease area/ number of Deduction in Amenity 6725.30 m2 wells to be drilled. Net plot area 34299.07 m2 FSI area 67483.38 m2 No n FSI area 12863.04 m2 Total construction area 80346.42 m2 Detailed Area Statement is attached as Annexure I 4 New / Expansion / Modernization New Project 5 Existing Capacity/ Area etc. Not applicable 6 Category of project i.e. A or B B Category 7 Does it attract the general condition? if No yes, please specify 8 Does it attract the specific condition? If No yes, please specify 9 Location Village- Ambi Taluka- Maval, District- Pune Plot/Survey/ Khasra No. Plot bearing Gat No. 36, 37, 39,40, 339 Village Ambi Tehsil Maval District Pune State 10 Nearest railway station/port along with Talegaon railway station-3 km distance in kms. 11 Nearest Town, city, District Headquarters along with distance in Distance 3 km kms. 12 Village Panchayat, Zilla Parishad, Village Panchayat - Ambi, Municipal Corporation, Local Zilla Parishad - Pune, body(complete postal addresses with telephone nos. to be given) Town Planning – PMRDA. 13 Name of the applicant Xrbia Developers Limited 14 Registered address Xrbia Developers Limited 929, Mantri House, First Floor, F.C. Road, Shivajinagar, Pune - 411 004 Tel.no. : 020- 66877030 Fax : 020- 66877030 Email : [email protected] 15 Address for correspondence: Xrbia Developers Limited 929, Mantri House, First Floor, F.C. Road, Shivajinagar, Pune - 411 004 Tel.no. : 020- 66877030 Fax : 020- 66877030 Email : [email protected]

Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 1

Application form for Environmental Clearance Project Name: Residential Project, Ambi, Pune Name Mr. Veer Bharati Kouls Designation(Owner/ Partner/ CEO) Director Address Xrbia Developers Limited 929, Mantri House, First Floor, F.C. Road, Shivajinagar, Pune Pin code 411 004 E-mail [email protected] Telephone No. 020- 66877030 Fax No. 020- 66877030 16 Details of alternative sites examined, if Village-District-State any. Location of these sites should be We are developing residential project on our own land shown on a toposheet. 17 Interlinked projects Not Applicable 18 Whether separate application of No interlinked project has been submitted? 19 If yes, date of submission Not Applicable 20 If No, Reason Stand alone construction project 21 Whether the proposal involves No approval/clearance under: if ,yes details of the same and their status to be given a) The Forest (Conservation) Act, 1980? b) The wildlife (protection) Act, 1972? c) The CRZ Notification, 1991? 22 Whether there is any Government No Order/policy relevant/relating to the site? 23 Forest land involved ( hectares) No forest land involved in proposed project site 24 Whether there is any litigation pending No such litigation pending against the project against the project and/or land in which the project is propose to be set up? a) Name of the court b) Case No. c) Orders/ Directions of the court if any and its relevance with the proposed project.

Capacity corresponding to sectoral activity (such as production capacity for manufacturing, mining lease area and production capacity for mineral production, area for mineral exploration, length for linear transport infrastructure, generation capacity for power generation etc.,)

(II) Activity

1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)

Sr.No. Information/Checklist Yes/No Details thereof (with approximate quantities confirmation /rates, wherever possible) with source of information data 1.1 Permanent or temporary Yes Permanent change in land use change in land use, land Land reserved for Residential Project cover or topography including increase in intensity of land use (with respect to local land use plan)

2 Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 2 Application form for Environmental Clearance Project Name: Residential Project, Ambi, Pune 1.2 Clearance of existing land, No vegetation and buildings? 1.3 Creation of new land uses? No Residential Project

1.4 Pre-construction Yes Soil samples taken within the plot premises for investigations e.g. bore geotechnical investigation houses, soil testing? 1.5 Construction works? No

1.6 Demolition works? No

1.7 Temporary sites used for Yes Temporary sheds will be provided for workers construction works or Housing of construction workers? 1.8 Above ground buildings, Yes Total Top Soil Excavation quantity: 500 m3 structures or earthworks including linear structures, cut and fill or excavations 1.9 Underground works including No mining or tunnelling ? 1.10 Reclamation works? No

1.11 Dredging? No

1.12 Offshore structures? No

1.13 Production and No manufacturing processes?

1.14 Facilities for storage of Yes Only construction material will be stored in temporary goods or materials? storage site

1.15 Facilities for treatment or Yes Municipal Solid Waste Disposal System, OWC disposal of solid waste or Composting and Sewage Treatment Plant liquid effluents? 1.16 Facilities for long term No housing of operational workers? 1.17 New road, rail or sea traffic Yes Movements of trucks for material transport while during construction or construction operation?

1.18 New road, rail, air No Existing road will be used for the transport purpose. waterborne or other transport infrastructure including new or altered routes and stations, ports, airports etc?

1.19 Closure or diversion of No existing transport routes or infrastructure leading to changes in traffic movements?

1.20 New or diverted No transmission lines or pipelines? 1.21 Impoundment, damming, No culverting, realignment or other changes to the hydrology of watercourses or aquifers? 1.22 Stream crossings? No

3 Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 3 Application form for Environmental Clearance Project Name: Residential Project, Ambi, Pune 1.23 Abstraction or transfers of No water form ground or surface waters? 1.24 Changes in water bodies or No There will not be any changes in water bodies or the the land surface affecting land surface drainage or r un -off? 1.25 Transport of personnel or Yes Construction workers and construction material materials for construction, operation or decommissioning? 1.26 Long-term dismantling or No decommissioning or restoration works? 1.27 Ongoing activity during No There will not be any impact on the Environment decommissioning which could have an impact on the environment? 1.28 Influx of people to an area in No On ly Construction workers will stay till construction either temporarily or completes permanently? 1.29 Introduction of alien No No introduction of alien species will occur as this is species? purely residential project

1.30 Loss of native species or No No threat of species loss will occur genetic diversity?

1.31 Any other actions? No No

2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): Sr.No. Information/checklist Yes/No Details thereof (with approximate quantities confirmation /rates, wherever possible) with source of information data 2.1 Land especially undeveloped No or agricultural land (ha) 2.2 Water (expected source & Yes Particulars Water Unit competing users) unit: KLD Consumption Fresh water 619 m3/day

Recycled water 305 m3/day Total Water 923 m3/day Requirement Source: Ambi Grampanchayat 2.3 Minerals (MT) 2.4 Yes Stone aggregates demand will be met from the clay / construction material – stone, soil generated after excavation and cutting of rocks aggregates, sand / soil (expected source – MT) 2.5 Forests and timber (source – Yes Only door frames (if so planned) MT) 2.6 Energy including electricity Yes Energy consumption and fuels (source, competing users) Unit: fuel (MT), energy Total Energy 2,468 kW (MW) consumption

Source: MSEDCL 2.7 Any other natural resources No (use appropriate standard units)

3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health.

Sr.No. Information/Checklist Yes/No Details thereof (with approximate confirmation quantities/rates, wherever possible) with

4 Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 4 Application form for Environmental Clearance Project Name: Residential Project, Ambi, Pune source of information data 3.1 Use of substances or No No hazardous material will be used for construction materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies) 3.2 Changes in occurrence of No disease or affect disease vectors (e.g. insect or water borne diseases) 3.3 Affect the welfare of people No Proposed Project will not effect the welfare of people e.g. by changing living conditions? 3.4 Vulnerable groups of people No Proposed Project will not affect h ospital patients, who could be affected by the children etc. project e.g. hospital patients, children, the elderly etc., 3.5 Any other causes No

4. Production of solid wastes during construction or operation or decommissioning (MT/month)

Sr.No. Information/Checklist Yes/No Details thereof (with approximate confirmation quantities/rates, wherever possible) with source of information data 4.1 Spoil, overburden or mine No wastes 4.2 Municipal waste (domestic Yes Use Quantity Unit and or commercial wastes) Dry waste 1,368 kg/day Wet waste 2,052 kg/day Total Solid Waste 3,420 kg/day 4.3 Hazardous wastes (as per No No hazardous waste will be generated as this is Hazardous Waste Residential Project Management Rules) 4.4 Other industrial process No No, This is a Residential Project wastes 4.5 Surplus product No Not Applicable

4.6 Sewage sludge or other Yes Used as manure after drying. sludge from effluent treatment 4.7 Construction or demolition No Not Applicable wastes 4.8 Redundant machinery or No Not Applicable equipment 4.9 Contaminated soils or other No Not Applicable materials 4.10 Agricultural wastes No Not Applicable

4.11 Other solid wastes No Not Applicable

5. Release of pollutants or any hazardous, toxic or noxious substances to air (kg/hr)

Details thereof (with approximate Sr.No. Information/Checklist Yes/No quantities/rates, wherever possible) with confirmation source of information data 5.1 Emissions from combustion No Not Applicable of fossil fuels from stationary or mobile sources 5.2 Emissions from production No Not Applicable processes 5.3 Emissions from materials Yes Fugitive emission from handling such as sand handling including storage or transport

5 Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 5 Application form for Environmental Clearance Project Name: Residential Project, Ambi, Pune 5.4 Emissions from construction Yes Transportation of construction material, DG sets etc. activities including plant and equipment 5.5 Dust or odours from Yes Transportation, loading and unloading of material will handling of materials generate dust including construction materials, sewa ge and waste 5.6 Emissions from incineration No Not Applicable of waste 5.7 Emissions from burning of No Not Applicable waste in open air (e.g. slash materials, construction debris) 5.8 Emissions from any other No Not Applicable sources

6. Generation of Noise and Vibration, and Emissions of Light and Heat:

Details thereof (with approximate Sr. No. Information/Checklist Yes/No quantities/rates, wherever possible) with confirmation source of information data with source of information dat a 6.1 From operation of equipment Yes Construction equipment, mixers, vehicles, etc. e.g. engines, ventilation plant, crushers 6.2 From industrial or similar No Not Applicable processes 6.3 From construction or Yes Minor construction machiner y as Ready Mix demolition Concrete will be used 6.4 From blasting or piling No Open Foundation 6.5 From construction or Yes By movement of trucks for material & Ready Mix operational traffic Concrete 6.6 From lighting or cooling No Not Applicable systems 6.7 From any other sources No Not Applicable

7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:

Sr.No. Information/Checklist Yes/No Details thereof (with approximate confirmation quantities/rates, wherever possible) with source of information data 7.1 From handling, storage, use or No Not Applicable spillage of hazardous materials 7.2 From discharge of sewage or No STP will be used to treat the sewage. T reated water other effluents to water or the will be used for flushing, gardening , vehicle land (expected mode and washing & construction activity purpose place of discharge) 7.3 By deposition of pollutants No Not Applicable emitted to air into the land or into water 7.4 From any other sources No Not Applicable

Is there a risk of long term 7.5 build up of pollutants in the No Not Applicable environment from these sources?

8. Risk of accidents during construction or operation of the Project, which could affect human health or the environment

Sr.No. Information/Checklist Yes/No Details thereof (with approximate confirmation quantities/rates, wherever possible) with source of information data 8.1 From explosions, spillages, No Not Applicable fires etc from storage, handling, use or production of hazardous substances 6 Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 6 Application form for Environmental Clearance Project Name: Residential Project, Ambi, Pune 8.2 From any other causes No Not Applicable

8.3 Could the project be affected No The proposed structure is designed as per Seismic by natural disasters causing Zone III standards. environmental damage (e.g. floods, earthquakes, landslides, cloud burst etc)?

9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality

Sr. No. Information/Checklist Yes/No Details thereof (with approximate confirmation quantities/rates, wherever possible) with source of information data

9.1 Lead to development of No supporting. facilities, ancillary development or development stimulated by the project which could have impact on the environment e.g.:

• Supporting infrastructure (roads, power supply, waste or waste water treatment, etc.) • housing development

• extractive industries

• supply industries

• other

9.2 Lead to after-use of the site, No Not Applicable which could have an impact on the environment 9.3 Set a precedent for later No Not Applicable developments 9.4 Have cumulative effects due No Not Applicable to proximity to other existing or planned projects with similar effects

(III) Environmental Sensitivity

Sr. No. Areas Name/ Aerial distance (within 15 km.) Identity Proposed project location boundary

1 Areas protected under No international conventions, national or local legislation for their ecological, landscape, cultural or other related value 2 Areas which are important or No Not Applicable sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests 3 Areas used by protected, No important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration 7 Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 7 Application form for Environmental Clearance Project Name: Residential Project, Ambi, Pune 4 Inland, coastal, marine or No Not Applicable underground waters 5 State, National boundari es No 6 Routes or facilities used by the No public for access to recreation or other tourist, pilgrim areas 7 Defence installations No

8 Densely populated or built-up Yes Fully urbanised area area

9 Areas occupied by sensitive Yes Hospitals, schools, colleges, community facilities & man-made land uses places of worship are present around the Project (hospitals, schools, places of site. worship, community facilities) 10 Areas containing important, No high quality or scarce resources (ground water resources, surface resources, forestry, agriculture, fisheries, tourism, minerals) 11 Areas already subjected to No pollution or environmental damage. (those where existing legal environmental standards are exceeded) 12 Areas susceptible to natural No hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions )

8 Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 8 Application form for Environmental Clearance Project Name: Residential Project, Ambi, Pune (IV). Proposed Terms of Reference for EIA studies Not Applicable

I hereby given undertaking that the data & information given in the application & enclosures are true to the best of my knowledge & belief & I am aware that if any part of the data and information submitted is found to be false or misleading at any stage, the project will be rejected and clearance give, if any to the project will be revoked at our risk and cost.

Date:20.07.2015 Mr. Veer Bharati Kouls Place: Thane Xrbia Developers Limited 929, Mantri House, First Floor, F.C. R oad, Shivajinagar, Pune - 411 004

Signature of the applicant With name & full address (Project proponent/Authorised signatory)

NOTE:

1) The projects involving clearance under Coastal Regulation Zone Notification, 1991 shall submit with the application a C.R.Z map duly demarcated by one of the authorized agencies, showing the project activities, w.r.t C.R.Z(at the stage of TOR) and the recommendations of the State Coastal Zone management Authority(at the stage of EC). Simultaneous action shall also be taken to obtain the requisite clearance under the provisions of the C.R.Z Notification, 1991 for the activities to be located in the CRZ.

2) The projects to be located within 10 km of the national Parks, Sanctuaries, Biosphere Reserves, Migratory Corridors of Wild Animals, the project proponent shall submit the map duly authenticated by Chief Wildlife Warden showing these features vis-avis the project location and the recommendations or comments of the chief Wildlife thereon.(at the stage of EC)

3) All correspondence with the ministry of Environment & Forests including submission of application for TOR/Environmental Clearance, subsequent clarifications as may be required from time to time, participation in the EAC meeting on behalf of the project proponent shall be made by the authorised signatory only. The authorised signatory should also submit a document in support of his claim of being an authorised signatory for the specific project.

9 Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 9 Application form for Environmental Clearance Project Name: Residential Project, Ambi, Pune APPENDIX - II (See paragraph 6)

FORM-1 A (only for construction projects listed under item 8 of the Schedule)

CHECK LIST OF ENVIRONMENTAL IMPACTS

(Project proponents are required to provide full information and wherever necessary attach explanatory notes with the Form and submit along with proposed environmental management plan & monitoring programme)

1. LAND ENVIRONMENT

(Attach panoramic view of the project site and the vicinity)

1.1 Will the existing landuse get The existing land use will not get altered from the project. significantly altered from the project As per the zoning structure the area comes under that is not consistent with the residential area. surroundings? (Proposed landuse must Proposed development is in line with D. P of Following conform to the approved Master Plan / documents are attached as supporting documents. Development Plan of the area. Change of landuse if any and the statutory 1. Conceptual Plan and Detailed Tenement statement approval from the competent authority are attached as Annexure II be submitted). Attach Maps of (i) site location, (ii) surrounding features of the proposed site (within 500 meters) and (iii) the site (indicating levels & contours) to appropriate scales. If not available attach only conceptual plans.

1.2 List out all the major project Total Plot Area 45,481.14 m2

requirements in terms of the land 2 area, built up area, water Deduction in Amenity 645.76 m consumption, power requirement, Net plot area 6725.30 m2 connectivity, community facilities, parking needs, etc . FSI area 34299.07 m2

Non FSI ar ea 67483.38 m2

Total construction area 12863.04 m2

Water consumption

Fresh water requirement 619 m3/day

Recycled water 319 m3/day

Total water requirement 923 m3/day

Energy Consumption

Total Energy 2,468 kW Consumption

Parking Provi ded

Detail Parking numbers Unit

2 wheeler 1,368 Nos.

Cycle 1,368 Nos.

4 wheeler 56 Nos.

Total Parking 2,792 Nos.

10 Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 10 Application form for Environmental Clearance Project Name: Residential Project, Ambi, Pune

Proposed site is accessible by Connectivity 1) MIDC Road - Annexure III

1.3 What are the likely impacts of the The project being a well planned activity will result in proposed activity on the existing organized open spaces and green areas. The biodiversity facilities adjacent to the proposed site? in the area will increase due to proposed green areas. (Such as open spaces, community facilities, details of the existing Community cum recreational facilities will be developed landuse, disturbance to the local hence no stress on the existing facility is anticipated. ecology).

1.4. Will there be any significant land The main reasons for erosion are overexploitation of disturbance resulting in erosion, groundwater, instable slopes, landslides etc. The proposed subsidence & instability? (Details of construction will involve cutting and filling operations. The soil type, slope analysis, vulnerability project will involve construction of roads and development to subsidence, seismicity etc may be of green areas, which would reduce the chances of erosion given). and subsidence.

Subsidence is not anticipated as ground water would not be used as a source of water supply.

As per seismic-zoning map of India, the project site falls under zone III. Structural design requirements will be as per zone III.

1.5 Will the proposal involve alteration of The proposed development is planned in such a manner natural drainage systems? (Give that it will not alter the existing drainage pattern of the details on a contour map showing the area. natural drainage near the proposed project site)

1.6 What are the quantities of earthwork Cutting and filling for construction activity are balanced, involved in the construction activity- so no transportation of earth will be required cutting, filling, reclamation etc. (Give details of the quantities of earthwork involved, transport of fill materials from outside the site, etc.)

1.7 Give details regarding water supply, waste handling etc during the Supply Source: Ambi Grampanchayat construction period.

1.8 Will the low lying areas & wetlands get No wet lands and low-lying areas on the site. altered? (Provide details of how low lying and wetlands are getting modified from the proposed activity)

1.9 Whether construction debris & waste No health hazard. Minor quantity of construction debris during construction cause health will be generated which will be sent out side. hazard? (Give quantities of various types of wastes generated during construction including the construction labour and the means of disposal)

2. WATER ENVIRONMENT

2.1 Give the total quantity of water Particulars Water Unit requirement for the proposed project consumption with the break up of requirements for 3 various uses. How will the water Fresh water requirement 619 m /day requirement met? State the sources & Recycled water 305 m3/day quantities and furnish a water balance statement. Total w ater requirement 923 m3/day

Source:- Ambi Grampanchayat Detailed water balance chart & diagram is attached as Annexure IV

11 Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 11 Application form for Environmental Clearance Project Name: Residential Project, Ambi, Pune

2.2 What is the capacity (dependable flow The proposed water demand will be met from Pej River or yield) of the proposed source of water?

2.3 What is the quality of water required, in Sr. Parameters Unit Drinking case, the supply is not from a municipal water source? (Provide physical, chemical, biological characteristics with class of 1. pH - 6.5-8.7 water quality) 2. Colour (units on - 5 Platinum Cobalt scale) 3. Odour - Unobjectionable 4. Turbidity NTU 5 5. Total Hardness (as mg/l 300

CaCO 3) 6. Chlorides mg/l 250 7. Sulphates mg/l 200 8. Fluorides mg/l 1 9. Nitrates mg/l 45 10. Lead mg/l 0.05 11. Arsenic mg/l 0.01 12. Cadmium mg/l 0.01

2.4 How much of the water requirement Treated water from STP will be used for flushing in toilet can be met from the recycling of and gardening,

treated wastewater? (Give the details of 3 quantities, sources and usage) Total sewage generated 739 m /day Total STP capacity 750 m3/day

Treated water recycled for flushing 305 m3/day

Treated water reuse for gardening 25 m3/day

Treated water reuse for vehicle 10 m3/day washing

Sludge generated 207 m3/day

Excess Treated Water to artificial pond 387 m3/day

2.5 Will there be diversion of water from No diversion is anticipated other users? (Please assess the impacts of the project on other existing uses and quantities of consumption)

2.6 What is the incremental pollution load The total sewage is about 739 m3/day will be generated from wastewater generated from the from the complex. The composition of waste water is proposed activity? (Give details of the given in the table indicating the quality of raw waste quantities and composition of water before treatment wastewater generated from the proposed activity) Parameters Values Units pH 7-8 mg/l

BOD 250-300 mg/l

COD 450-600 mg/l

O & G/ ABS 10 -20 mg/l

TSS 100 -200 mg/l

Mitigation measures: Domestic Effluent will be treated in the Sewage Treatment plant of capacity 750 m3/day . The treated sewage water will be reused for flushing, gardening & vehicle washing.

12 Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 12 Application form for Environmental Clearance Project Name: Residential Project, Ambi, Pune

2.7 Give details of the water requirements The project activity shall have rainwater harvesting only met from water harvesting? Furnish of rainfall on terraces. details of the facilities created.

2.8. What would be the impact of the land Proposed development is in tune with DP of Pune Town use changes occurring due to the Planning proposed project on the runoff The project will have proper storm water drainage facility characteristics (quantitative as well as as per Strom Water Drain Remarks by concerned qualitative) of the area in the post authority. So there will be no problem of water logging construction phase on a long term due to this project. basis? Would it aggravate the problems of flooding or water logging in any way?

2.9 What are the impacts of the proposal In the proposed development there will be no tapping of on the ground water? (Will there be groundwater. Water demand for the construction as well tapping of ground water; give the as operational phase will be met from sources such as details of ground water table, Alibaug Town Planning. recharging capacity, and approvals

obtained from competent authority, if Rainwater harvesting scheme will be practiced for any) groundwater recharge, which will have a positive impact on the ground water table.

2.10 What precautions/measures are taken To prevent degradation and maintain the quality of water to prevent the run-off from construction source, adequate control measures have been proposed activities polluting land & aquifers? to check the surface run-off, as well as uncontrolled flow (Give details of quantities and the measures taken to avoid the adverse of water into any water body. impacts) • Avoid excavation during monsoon season. • Rainwater harvesting can serve as a solution to water problem in worst case scenario.

Following methods can increase efficiency of rainwater harvesting and recharging groundwater. • Catch drainage all along the periphery of plot to prevent surface runoff. • Reduce and filter surface runoff. • Use vegetated swales and depressions to reduce runoff.

2.11 How is the storm water from within the During rainy season, after the rainfall some part of the site managed?(State the provisions rainwater percolates into the ground and joins ground made to avoid flooding of the area, water table, a part is retained as soil moisture, some part details of the drainage facilities is lost in evapotranspiration and the remaining part provided along with a site layout overflows as storm water run off. The quantity of runoff indication contour levels) reaching the sewers or drains is considerable as compared with sanitary sewage The project will have proper storm water drainage facility as per Strom Water Drain Remarks by concerned authority. So there will no be problem of water logging due to this project.

2.12 Will the deployment of construction No, the deployment of construction labourers will not lead labourers particularly in the peak period to any unsanitary condition. The construction labourers lead to unsanitary conditions around will be provided with temporary shelter shades within the the project site (Justify with proper project premises. The unsanitary condition will be explanation) removed by means of providing readymade septic tanks & soak pits. Solid waste will be disposed off in municipal waste disposal system.

2.13 What on-site facilities are provided for The Sewage Treatment Plant (STP) is designed to treat the collection, treatment & safe disposal the raw waste water generated from Residential building. of sewage? (Give details of the Sewage Generation: 739 m3/day quantities of wastewater generation, STP capacity: 750 m3/day treatment capacities with technology & facilities for recycling and disposal) STP details are attached as Annexure V

13 Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 13 Application form for Environmental Clearance Project Name: Residential Project, Ambi, Pune

2.14 Give details of dual plumbing system if Not Applicable treated waste used is used for flushing of toilets or any other use.

3. VEGETATION

3.1 Is there any threat of the project to the There is no sensitive ecosystem present at site that will biodiversity? (Give a description of the be disturbed by the project, as existing land use in local ecosystem with it’s unique surrounding area is Residential features, if any)

3.2 Will the construction involve extensive No. There is very scanty vegetation of grasses and shrubs clearing or modification of vegetation? along with very common fauna prevalent elsewhere in (Provide a detailed account of the trees the area. & vegetation affected by the project)

3.3 What are the measures proposed to be About 5,000 m2 areas are provided for the development taken to minimize the likely impacts on of Green belt in the premises. The green belt will be important site features (Give details of developed for control of pollution and aesthetic view of proposal for tree plantation, the complex. landscaping, creation of water bodies etc along with a layout plan to an appropriate scale)

4. FAUNA

4.1 Is there likely to be any displacement No. The proposed site and its surroundings do not support of fauna- both terrestrial and aquatic or any habitat for any group of wild animals creation of barriers for their movement? Provide the details.

4.2 Any direct or indirect impacts on the No. There will be no direct or indirect impact on the avifauna of the area? Provide details. avifauna of the area.

4.3 Prescribe measures such as corridors, Since the Proposed Project would not have any adverse fish ladders etc to mitigate adverse impact on fauna hence mitigation measure not relevant impacts on fauna

5. AIR ENVIRONMENT

5.1 Will the project increase atmospheric The Project will result in negligible increase in the concentration of gases & result in heat atmospheric concentrations of gases due to D.G. islands? (Give details of background air operations (back up power only) and the increased traffic. quality levels with predicted values The proposed activity will not result in the formation of based on dispersion models taking into any heat islands, as it does not involve any significant account the increased traffic generation change in the land use pattern or the concreting of areas. as a result of the proposed constructions)

5.2 What are the impacts on generation of Diesel generator sets operated for back-up power supply dust, smoke, odorous fumes or other are identified as the only major sources of gaseous and hazardous gases? Give details in particulate emission. Impact of vehicular is not relation to all the meteorological significant. SO 2, SPM, NO X and CO emissions are parameters. expected due to fuel combustion in generator sets.

5.3 Will the proposal create shortage of Detail Parking Provided no. Unit parking space for vehicles? Furnish details of the present level of transport 2 wheeler 1368 No. infrastructure and measures proposed for improvement including the traffic cycle 1368 No . management at the entry & exit to the 4 wheeler 56 No. project site. Total parking 2,792 No .

Total parking area 11,256 m2

14 Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 14 Application form for Environmental Clearance Project Name: Residential Project, Ambi, Pune

5.4 Provide details of the movement Internal roads, footpaths / pedestrian pathways have patterns with internal roads, bicycle been planned within the proposed complex tracks, pedestrian pathways, footpaths etc., with areas under each category.

5.5 Will there be significant increase in Considering the addition of vehicles due to the proposed traffic noise & vibrations? Give details project with the existing roads and vehicles plying on of the sources and the measures them, there will be marginal increase in the noise levels proposed for mitigation of the above. but will not result in an impact.

5.6 What will be the impact of DG sets & DG set will be used in construction and operation phase other equipment on noise levels & only in case of power failure. vibration in & ambient air quality The DG Sets shall be as per the guide lines laid down by around the project site? Provide details. EPR for specific noise emission standards. Measures shall be taken for reduction of noise by using acoustic enclosures. Noise emissions are expected from various construction equipment and machinery but will not result in an impact.

6. AESTHETICS

6.1 Will the proposed constructions in any The proposed land use of the site would be mainly way result in the obstruction of a view, residential and will not result in obstruction of view, scenic amenity or landscapes? Are scenic amenity or landscape. However, the buildings will these considerations taken into account be planned in such a way that the organised open areas by the proponents? and landscaped areas are at the centre so that all can enjoy the green areas.

6.2 Will there be any adverse impacts from Internal roads, footpaths/ pedestrian pathways have new constructions on the existing been planned within the proposed complex structures? What are the considerations taken into account?

6.3 Whether there are any local The Project has been designed as per the department of considerations of urban form & urban town planning, Government of Maharashtra. design influencing the design criteria? They may be explicitly spelt out.

6.4 Are there any anthropological or No anthropological or archaeological sites or artefacts are archaeological sites or artefacts found near the site area. nearby? State if any other significant features in the vicinity of the proposed site have been considered.

7. SOCIO-ECONOMIC ASPECTS

7.1 Will the proposal result in any changes No. Majority of the labour will be recruited locally and to the demographic structure of local only minimal skilled workers would be from outside, which population? Provide the details. is anticipated to be very small and will not alter the existing demographic profile of the area.

7.2 Give details of the existing social The Project comes in Residential area and has all basic infrastructure around the proposed infrastructural facilities as schools, medical project. establishments, shops, etc.

7.3 Will the project cause adverse effects No. The Project will have positive impact on local on local communities, disturbance to communities. sacred sites or other cultural values? What are the safeguards propos ed?

8. BUILDING MATERIALS

8.1 May involve the use of building The buildings will have Sewage Treatment Plant, materials with high-embodied energy. Rainwater harvesting systems, Solar hot water system, Are the construction materials Solar lighting in common areas and RG produced with energy efficient processes? (Give details of energy

15 Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 15 Application form for Environmental Clearance Project Name: Residential Project, Ambi, Pune

conservation measures in the selection of building materials and their energy efficiency)

8.2 Transport and handling of materials Adequate mitigative measures will be adopted. during construction may result in Construction equipment with idling control technologies pollution, noise & public nuisance. What will be used. Regular maintenance of the equipments will measures are taken to minimize the be carried out. The construction activities will be carried impacts? out during the daytime only. The workers exposed to high noise generating would be provided with earplugs earmuffs. As per Environmental Management Plan .

8.3 Are recycled materials used in roads Fly ash in cement concrete. Typically 20-25 % of fly ash is and structures? State the extent of substituted in cement. savings achieved?

8.4 Give details of the methods of The bio-degradable and non-bio degradable waste will be collection, segregation & disposal of the segregated at source of waste generation. garbage generated during the Solid waste generated: 3,420 kg/day operation phases of the project.

9. ENERGY CONSERVATION

9.1 Give details of the power requirements, Source of power supply: MSEDCL source of supply, backup source etc. What DG Set will be provided as emergency backup. is the energy consumption assumed per square foot of built-up area? How have you Total Energy 2,468 kW tried to minimize energy consumption? Consumption

9.2 What type of, and capacity of, power back- DG Set will be provided as emergency backup for up to you plan to provide? lighting in common areas, one lift per building and fire pump in each building. DG Set capacity – 200 kVA

9.3 What are the characteristics of the glass Double glazed glass for residential building you plan to use? Provide specifications of its characteristics related to both short wave and long wave radiation?

9.4 What passive solar architectural features The building structure will be designed in such a way are being used in the building? Illustrate that solar light can be utilised maximum for day time. the applications made in the proposed project.

9.5 Does the layout of streets & buildings Solar street lights are proposed in areas such as open maximise the potential for solar energy spaces, pathways, RG etc. Also solar hot water system devices? Have you considered the use of for Residential Buildings street lighting, emergency lighting and solar hot water systems for use in the building complex? Substantiate with details.

9.6 Is shading effectively used to reduce Yes. Shading has been effectively used to reduce the cooling/heating loads? What principles have cooling loads. been used to maximize the shading of Walls on the East and the West and the Roof? How much energy saving has been effected?

9.7 Do the structures use energy-efficient Yes. The rooms will be so dimensioned that effective space conditioning, lighting and mechanical air conditioning can be carried out. Public areas will be systems? Provide technical details. Provide cooled by natural ventilation. The design of the details of the transformers and motor building will be such that maximum use of natural efficiencies, lighting intensity and air- ventilation can be achieved. The walls, roofs and conditioning load assumptions? Are you openings will be so designed that influx of heat is using CFC and HCFC free chillers? Provide minimum. specifications.

16 Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 16 Application form for Environmental Clearance Project Name: Residential Project, Ambi, Pune

9.8. What are the likely effects of the building Heat emission from the proposed construction can be activity in altering the micro-climates? from the following sources: Provide a self assessment on the likely Heat absorbed from the concrete structures, heat impacts of the proposed construction on generated from equipments/ appliances, and due to creation of heat island & inversion effects? increased population in the proposed development. However the heat generated will not be significant and will be dissipated in the lush greens and open areas provided within. Hence it can be concluded that the heat island effect shall not be a concern for the proposed project.

9.9. What are the thermal characteristics of the U value in Watts/hr/m 2/°C building envelope? (a) roof; (b) external walls; and (c) fenestration? Give details of Roof 0.409 2 ° the material used and the U-values or the Watts/hr/m / C R values of the individual components. Wall 0.352 Watts/hr/m 2/°C

9.10 What precautions & safety measures are The fire fighting system shall compromise of hydrant proposed against fire hazards? Furnish system and portable extinguishers. Smoke detectors details of emergency plans. will be provided along with manual call points. External yard hydrants shall be installed around all buildings in the complex in galvanized steel fire hose cabinet (weather proof). All external yard hydrants shall be at one meter height from finished ground level as per National Building Code. External fire hydrants shall be located such that no portion of any building is more than 45 m from a hydrant, and the external hydrants are not vulnerable to mechanical or vehicular damage. Proper Fire Escape routes.

9.11 If you are using glass as wall material Not Applicable provides details and specifications including emissivity and thermal characteristic s.

9.12 What is the rate of air infiltration into the The following measures will be adopted to mitigate the building? Provide details of how you are effects of infiltration: mitigating the effects of infiltration. • Aluminium windows with rubber gasket, so that the windows are sealed, will be provided. • Summer cross section ventilation will be maximum.

9.13 To what extent the non-conventional Not Applicable energy technologies are utilised in the overall energy consumption? Provide details of the renewable energy technologies used.

10. Environment Management Plan

The Environment Management Plan would Enclosed as Annexure VI consist of all mitigation measures for each item wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project. It would also delineate the environmental monitoring plan for compliance of various environmental regulations. It will state the steps to be taken in case of emergency such as accidents at the site including fire.

17 Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 17 Application form for Environmental Clearance Project Name: Residential Project, Ambi, Pune

Annexure I Area Statement

Details Area in m 2 Total Plot Area 45,481.14 Deduction in Road Widening 645.76 Deduction in Amenity 6725.30 Net plot area 34299.07 FSI area 67483.38 Non FSI area 12863.04 Total construction area 80346.42

Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 18

Application form for Environmental Clearance Project Name: Residential Project, Ambi, Pune

Tenement Details

Type of No. of Floors No. of Building No. of Flats building Residential Stilt + 12 floors 10 1080 Stilt + 18 floors 2 288 Club House 1 Total 13 1,368

19 Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 19 Application form for Environmental Clearance Project Name: Residential Project, Ambi, Pune

Annexure II Conceptual plan

Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 20

Application form for Environmental Clearance Project Name: Residential Project, Ambi, Pune

Annexure III Location plan

Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 21

Application form for Environmental Clearance Project Name: Residential Project, Ambi, Pune

Annexure IV Water Balance Diagram

= population x 135

Total water budget (Dry Season) 923

Fresh water Recycled water required 619 350

Human Non-human Gardening Vehicle washing Contact contact 619 305 25 20

Garden area As per need

Sewage Loss generation 185 739

Treated Water Loss water recycled 15 724 330 38% Excess to Sludge drain 7 387

Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 22

Application form for Environmental Clearance Project Name: Residential Project, Ambi, Pune

Quantity in m 3/day

Dry Season Wet Season

Total water budget 923 923

Fresh water 619 619 requirement

Human contact 619 619

Non-human contact 305 305

Gardening 25 13

Vehicle washing 20 20

Losses (total) & sludge 207 207

Sewage generation 739 739

Treated water 724 724

Water recycled 350 338

Excess to drain 387 399

% recycled 38 37

Rounded off to Integer v alues

Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 23 Application form for Environmental Clearance Project Name: Residential Project, Ambi, Pune Annexure V Sewage Treatment Plant

Calculation for STP Capacity:

Total estimated population = 6,840 persons

Total Water demand = 923 m3/day

Total sewage generation = 739 m3/day

The STP is designed of 750 m3/day

The expected characteristics of raw sewage and Treated sewage are given below;

Sr. Parameters Raw Sewage Treated Sewage

1 pH 6.5 - 7.5 7.0 - 8.5 2 Suspended Solids 100 – 200 mg/l <1 mg/l 3 BOD (3 days 28°C) 280 – 350 mg/l 5 mg/l 4 COD 500 – 600 mg/l <40 mg/lit 5 Oil & Grease 30 – 60 mg/l - 6 Total Coli form <2

Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 24 Application form for Environmental Clearance Project Name: Residential Project, Ambi, Pune

Annexure VI Environmental Management Plan during Construction Phase

Sr. Environmental Probable source of Predicted Impacts Mitigation Measures Remarks No. Components Impact CONSTRUCTION PHASE 1. Ambient Air Quality Negativ e impact Dust emissions from Dust reduction measures Impacts are temporary inside construction excavation, air such as road watering. during construction site premises. No emissions from Periodic maintenance of phase. Impacts will be negative impact machinery and other construction equipment. Use confined to short outside site. construction activities of good quality fuels. Use of distances, as coarse at site. Personal Protective particles will settle Equipments within the short distance from activities. 2. Noise Negative impact Noise generated from Use of well maintained Temporary impacts near noise construction activities equipment. during construction generation sources and operation of Heavy construction activity phase. No blasting or inside premises. No construction limited to day- time hours other high noise significant impact on equipment and DG only. Use of noise mufflers in activities envisaged. ambient noise levels sets and construction vehicle. in the surrounding Use of earplugs/muffs by area. construction staff. 3. Water No significant Surface runoff from Silt fences to reduce run -off Labour will be negative impact. project site. Oil/fuel Secondary containment and employed to reduce and waste spills. dykes in material storage size of labour camps. Improper debris areas. Sewage treatment in No perennial surface disposal. Discharge of septic tanks. water resource sewage from labour adjacent to site. No camp. excavation work will be 4. Land Minor negative Excavation, Reutilization and recycling of - impact Construction debris, construction debris waste from labour Waste from labour camps camp. will be collected and composted on site. Non compostable waste will be transported to landfill site. Topsoil will be conserved and used for landscaping in functional phase. 5. Aesthetics Minor negative Construction activities The impacts will be Short term impact impacts and Excavation compensated by extensive restricted only in the tree plantation and initial stages of gardening in the use phase. construction.

Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 25 Application form for Environmental Clearance Project Name: Residential Project, Ambi, Pune Environmental Management Plan during Functional Phase

Sr. Environmental Probable Source Of Predicted Impacts Mitigation Measures Remarks No. Components Impact FUNCTIONAL PHASE 1. Ambient Air Minor Negative Particulate and gaseous Use of low sulphur good DG sets will be used. Quality impact emissions from DG sets fuel and vehicle movement Periodic maintenance of DG sets Use of CNG/LPG as a fuel should be encouraged. 2. Noise Minor negative Noise fr om vehicle Housing of DG sets in -- impact inside movement and operation buildings with appropriate premises. of diesel generator sets acoustics. during power failure. Traffic management measures to reduce noise Appropriate trees which will act as noises barriers will be planted in the premises and along roadside. 3. Water No significant Oil/ fuel and waste spills Sewage water will be Recycled water will be adverse impact in vehicle parking area. treated and recycled. used for gardening and Discharge of sewage. Rainwater harvesting and flushing purpose. Discharge of recharge of groundwater contaminated storm water aquifer is proposed. Good housekeeping and storm water management will be followed. 4. Land No negative impact Storage and disposal of Treatment and reuse of Segregation of dry and solid wastes. sewage water. wet garbage before will Discharge of sewage. Integrated waste be done before Fuel and material spills. management and spill disposal. control plan Dry garbage will be sent for recycling and wet garbage will be composted. 5. Biological Overall Positive Habitat disturbance Green spaces inside the Landscaping will help in impact premises will help to reducing any adverse compensate the earlier impacts on air and effect from vegetation. noise quality. Landscaping and extensive plantation in the premises. 6. Socio -economic Overall positive Increased job opportunity -- Positive and long term impact in household impact- maintenance and ancillary services. FUNCTIONAL PHASE 7. Traffic Pattern No significant Impact Th e complex is likely to Traffic Management add moderately to the practises will be traffic flow considered employed. during peak hour. Adequate parking space will be provided in the premises.

Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 26