IN: KOSI BASIN DEVELOPMENT PROJECT (P127725)

I. General Public Disclosure Authorized 1. Bank’s approval Date of the procurement Plan: Draft Procurement Plan dated May 20, 2015 Revision 0 agreed by the Bank on May 20, 2015

2. Date of General Procurement Notice: May 29 2014

3. Period covered by this procurement plan: 18 months

II. Goods and Works and non-consulting services.

1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Public Disclosure Authorized

Procurement Methods and Threshold Category Method of Procurement Threshold (US$ Equivalent) Goods and Non-consultant ICB >3,000,000 services LIB Wherever agreed by the Bank NCB Up to 3,000,000 (with NCB conditions) Shopping Up to 50,000 DC As per Para 3.7 of the Bank Guidelines, wherever agreed and with prior agreement with the Bank Public Disclosure Authorized Force Account As per Para 3.9 of Guidelines Framework Agreements As per Para 3.6 of Guidelines Works and Supply and ICB >40,000,000 Installation NCB Up to 40,000,000 (with NCB conditions) Shopping Up to 50,000 carried out through a qualified local contractor selected through shopping (after inviting a minimum of three quotations in response to a written invitation with a minimum of 15 days notice period) Force Account As per Para 3.9 of Guidelines Public Disclosure Authorized DC As per Para 3.7 of Guidelines,

1. Prior Review by the Bank. The Bank will prior review the following contracts: • Works: All contracts more than US$ 10.0 million equivalent; • Goods: All contracts more than US$ 1.0 million equivalent; • Non-Consulting Services: All contracts more than US$ 1.0 million equivalent; 2. First contract issued by each implementing agency will be prior reviewed by the Bank irrespective of value. In addition, the justifications for all contracts to be issued on LIB, single- source (>US$ 50,000) or direct contracting (>US$ 50,000) basis will be subject to prior review. These thresholds are for the initial 18 months period and are based on the procurement performance of the project, these thresholds will be modified. In addition, the Bank will carry out an annual ex post procurement review of the procurement falling below the prior review threshold mentioned above.

All contracts not covered under prior review will be subject to post review during supervision missions, and/or review by consultants to be appointed by the by Bank.

2. Prequalification. Not applicable

3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable]

4. Reference to Project Operational/Procurement Manual: BAPEPS has prepared the Project Procurement Manual and agreed with the Bank. All the contracts issued under the project will follow the World Bank’s Guidelines: Bank’s “Guidelines: Procurement under IBRD Loans and IDA Credits” dated January 2011and revised in July 2014and “Guidelines: Selection and Employment of Consultants by World Bank Borrowers” dated January 2011 and revised in July 2014, In case of any inconsistency between the Procurement Manual or Bihar Government Procurement Procedures and the Bank Guidelines, the latter shall prevail.

5. Any Other Special Procurement Arrangements: The bid evaluation will be carried out as per agreed timeline in the Procurement Manual.

NCB will be conducted in accordance with paragraph 3.3 and 3.4 of the Guidelines and the following provisions: The Standard Bidding documents of the Bank as agreed with GoI task force (and as amended from time to time) for all procurement under NCB will be used. For ICB/LIB contracts Bank’s latest Standard Bidding Documents (SBDs) only will be used. The following conditions must be met in order for the bidding process under NCB to be acceptable to the Bank:

• only the model bidding documents for NCB agreed with the GOI Task Force (and as amended from time to time) shall be used for bidding; • invitations to bid shall be advertised in at least one widely circulated national daily newspaper or on a widely used website or electronic portal with free national and international access along with an abridge version of the said advertisement being published in a widely circulated national daily newspapers inter-alia giving the website/electronic portal details from which the details of the invitation to bid can be downloaded, at least 30 days prior to the deadline for the submission of bids; • no special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises or enterprises from any given state; • except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder; • extension of bid validity shall not be allowed with respect to Contracts subject to Bank Prior review, without the prior concurrence of the Bank (i) for the first request for extension if it is longer than four weeks; and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by the Bank only in cases of Force Majeure and circumstance beyond the control of the Purchaser/Employer; • re-bidding shall not be carried out with respect to contracts subject to Bank Prior Review, without the prior concurrence of the Bank. The system of rejecting bids outside a pre- determined margin or “bracket” of prices shall not be used in the project; • Framework agreement using DGS&D rate contracts can be used to procure goods up to NCB threshold contracts will need to comply with the following :

 Use of DGS&D rate contracts as Framework Agreement must be reflected in the procurement plan agreed by the Bank for particular goods.  Before issuing the purchasing order, the Task Team will have to advise the government on carrying out a price analysis on the specific good that is intended to be purchased. If after this due diligence the GoB concludes and Bank agrees that the DGS&D rate contract is not suitable, then the GoB will have to proceed using NCB or shopping depending on the value.  To meet the Bank's requirements for right to audit and F&C, these clauses may be included in the Purchase Orders, in case the purchasers are directly placing the purchase orders to DGS&D rate contract holders. On the other hand, if indent is placed through DGS&D, the Purchaser has the option to sign a separate undertaking with DGS&D rate contract holder, where Bank’s right to audit and F&C clauses could be mentioned; and  two or three envelop system shall not be used

6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness : Available in separate Excel file. III. Selection of Consultants

1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants:

Category Method of Procurement Threshold (US$ Equivalent) Consultants’ Services CQS/LCS Up to 300,000 per contract SSS As per Para 3.9-3.11 of Guidelines Individuals As per Section V of Guidelines Use of NGO As per Para 3.16 of Guidelines QCBS/QBS/FBS For all other cases (i) International shortlist > 800,000 (ii) Shortlist may comprise Up to 800,000 national consultants only Prior Review by the Bank. The Bank will prior review the following contracts:

• Consultancy Services: All contracts more than US$ 500,000 equivalent for firm; and • Consultancy Services: All contracts more US$ 200,000 equivalent for individuals. First contract issued by each implementing agency will be prior reviewed by the Bank irrespective of value. In addition, the justifications for all contracts to be issued on single-source (>US$ 50,000) or direct contracting (>US$ 50,000) basis will be subject to prior review. These thresholds are for the initial 18 months period and are based on the procurement performance of the project, these thresholds will be modified. In addition, the Bank will carry out an annual ex post procurement review of the procurement falling below the prior review threshold mentioned above.

All contracts not covered under prior review will be subject to post review during supervision missions, and/or review by consultants to be appointed by the by Bank.

2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines.

3. Any Other Special Selection Arrangements: The finalization of consulting services shall follows the timeline agreed in the Procurement Manual

4. Consultancy Assignments with Selection Methods and Time Schedule Available as separate Excel file E-procurement and use of SEPA:

1. Currently many undertakings of the government of Bihar following e-procurement system for State and centrally funded projects through portal system. The NIC portal system has been reviewed by the Bank and has been cleared to be used for Bank financed project. Therefore, e-procurement shall be adopted for this project. Further, use of procurement plan monitoring tool SEPA has also been discussed and agreed to be used for this project.

2. Procurement Review by BAPEPS: Independent review or audit will be undertaken for the project for BAPEPS’s own internal due diligence, and as agreed in the implementation arrangements for the project.

1. BAPEPS will review procurement documents for procurement of works and goods by IAs for all post review cases. For prior review cases, BAPEPS will carry out initial review and then forward it to the Bank for no-objection. 2. External audit: The external auditor appointed by BAPEPS will conduct the audit of all implementing agencies and BAPEPS including procurement review/audit. In case there is any procurement related observation made by the external auditor in their audit report, the same shall be shared with Bank along with the comments of BAPEPS. PROCUREMENT : IN: BIHAR KOSI BASIN DEVELOPMENT PROJECT PLAN General Information

Country: India Bank’s Approval Date of the Original Procurement Plan: 2016-09-09 Revised Plan Date(s): (comma delineated, leave blank if none)2018-08-30 Project ID: P127725 GPN Date: Project Name: IN: BIHAR KOSI BASIN DEVELOPMENT PROJECT Loan / Credit No: IDA / 56960 Executing Agency(ies):Rural Works Department, Bihar, Bihar Aapda Punarwas Evam Punarnirman Society, Bihar Pul Nirman Nigam Ltd., Water Resources Department, Bihar, Animal and Fisheries Resources Department, Bihar

WORKS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

BKBDP/RD/SA-1A / I) From REO road D. Jha House to Devna Temple Under Single Stage - Two Road wth 5 year maint. IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2016-09-08 2016-09-08 2016-09-22 2016-12-30 2017-02-27 2018-08-27 Envelope II) From PMGSY Road at on D. Maharatha to Bangaon Road wth 5 yr maint.

BKBDP/RD/MA-1 / I) From PMGSY Road L. Sah Land to Arun Swarnkar residance via Shivala wth 5 yr maint. Under II) From NH-107 to Malia Single Stage - Two IDA / 56960 Post Request for Bids Open - National 859,362.09 Implementati 2016-09-08 2016-09-08 2016-09-22 2017-01-20 2017-03-08 2018-09-05 Yadav Tola with 5 yr Envelope on maint. III) NH-107 Jitapur Chamgarh to Nayanagar Khirkiya with 5 yr maint.

BKBDP/RD/MA-II / i) Ghailad Balua Dhruvpatti Single Stage - Two IDA / 56960 Prior Request for Bids Open - National 823,056.20 Signed 2016-09-08 2016-09-08 2016-09-22 2017-01-25 2017-03-13 2018-09-10 to Yadav Tola, Envelope

Kamalpurand road with 5 yr maint.

BKBDP/RD/MA III A / I) Garha Rampur M. School to Under Single Stage - Two M. Chawk Via K Yadav IDA / 56960 Post Request for Bids Open - National 1,734,596.10 Implementati 2016-09-08 2016-09-08 2016-09-22 2016-12-15 2017-01-20 2018-07-20 Envelope Satsang Bhawan incl HL on Bridge. with 5 Yr Maint.

WBP/PH-2/PACKAGE- 6/2014-15 / Construction of H.L. R.C.C Bridge with its approach road in 7th K.m Single Stage - Two of Saraigarh- IDA / 56960 Prior Request for Bids Open - National 2,648,760.30 Signed 2016-09-08 2016-09-08 2016-09-08 2016-09-08 2016-11-05 2018-11-05 Envelope Lalganj-Ganpatganj road and 7th K.m of Mehasimar- Ganpatganj road in the district of .

WBP/PH-2PACKAGE-2/2014- 15 / Construction of H.L. R.C.C. Bridge in 2nd K.m. Single Stage - Two IDA / 56960 Prior Request for Bids Open - National 2,304,147.92 Signed 2016-09-08 2016-09-08 2016-09-08 2016-10-08 2016-12-05 2018-12-05 Karpuri Chowk-Patarghat Envelope road in the district of Madhepura.

BKBDP/RD/MA-IIIB / (i)From Mahuli To Kandua Noniyari With 5Year Maint. (ii)From Dhanaha BT Road Under Single Stage - Two To S MushahariWith 5Year IDA / 56960 Post Request for Bids Open - National 831,620.99 Implementati 2016-09-08 2016-09-08 2016-09-22 2017-01-20 2017-02-24 2018-08-24 Envelope Maint. on (iii)From Rauta PMGSY Road To Sukhasan With 5Year Maint.

BKBDP/RD/MA-IVA / Bhatni Main Road To Under Single Stage - Two Semrahi Tola via pattahi IDA / 56960 Post Request for Bids Open - National 930,482.80 Implementati 2016-09-08 2016-09-08 2016-09-22 2017-01-30 2017-03-06 2018-09-03 Envelope lakshminiya with 5 year on maint.

Page 1 WBP/PH-2/PACKAGE- 01/2014-15 / Construction of H.L. R.C.C. Bridge in 1st Under Single Stage - Two K.m. & 6th K.m. of IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2016-09-09 2016-09-09 2016-09-09 2016-09-09 2016-09-09 2019-02-21 Envelope Saraigarh-Lalganj- on Ganpatganj road in the district of Supaul.

BKBDP/RD/MA-V / (i)From MMGSY Road of Gopalpur panchayat to World Bank Road via Gopalpur,Mandal tola etc. (ii)From Baliya Middle Single Stage - Two IDA / 56960 Post Request for Bids Open - National 2,302,819.66 Signed 2016-09-10 2016-09-10 2016-09-10 2016-09-10 2016-09-10 2017-11-25 school to Udakishungaj Envelope canal via Lashakri RWD road. (iii)From Bhaluahi MMGSY BT Road to Sekhpura chaman village.

BKBDP/RD MA-VI / (i)from BansawaraPWD Road To Navagachhia Basa via M. tola G. m. Basa (ii)From Athagama Basa RWD road to Bhawanipur Basa Single Stage - Two IDA / 56960 Post Request for Bids Open - National 2,565,513.27 Signed 2016-09-10 2016-09-10 2016-09-10 2016-09-10 2016-09-10 2018-03-10 (iii)From RWD Road B Envelope market To Gauchidih (iv)FromPMGSY Road at Aurai East to Singhybhita via A.Ghanbasa,Terpahari,D.Tha kurba

BKBDP/RD/SA-IB / (i)From PMGSY road Araha to S.BhawanDubbhi tola via Mahadalit tola with 5 year Single Stage - Two IDA / 56960 Post Request for Bids Open - National 1,629,735.66 Signed 2016-09-12 2016-09-12 2016-09-22 2017-01-20 2017-03-10 2018-09-07 maint. Envelope

(ii)From Saur patarghat main road to thenga south tola with 5 year maint.

BKBDP/RD/SA-IC / (i)From NH-107 Tiri bhagawati Single Stage - Two IDA / 56960 Post Request for Bids Open - National 639,116.17 Signed 2016-09-12 2016-09-12 2016-09-22 2017-01-21 2017-02-25 2018-08-25 asthan To Chakla with 5 Envelope year maint.

BKBDP/RD/MA-VII / (i)From Arajpur chausa Road Krishna tola To Kalasan High school(near RWD road) via Ghandhi Single Stage - Two Tola Tilahari &panchayat IDA / 56960 Post Request for Bids Open - National 2,250,830.62 Signed 2016-09-13 2016-09-13 2016-09-13 2016-09-13 2016-09-13 2017-10-13 Envelope bhawan with 5 year maint. (ii)From Basalpur dhuriya chiraudi Basti To Baba Vishuvarawat with 5 year maint.

BKBDP/RD/MA-IVB / Under FromWorld Bank Road Single Stage - Two IDA / 56960 Post Request for Bids Open - National 776,428.82 Implementati 2016-09-13 2016-09-13 2016-09-22 2017-01-20 2017-02-24 2018-08-24 Pokhariya To Khuttirahi Envelope on with 5 year maint.

BKBDP/RD/SU-II / From i) Tulpatti to Badrakhiy tola with 5 year's Maint. ii) T02 (MDR) to M. Chakla with 5 year's Under Maint. Single Stage - Two IDA / 56960 Post Request for Bids Open - National 1,535,946.52 Implementati 2016-09-14 2016-09-14 2016-09-22 2017-01-20 2017-02-24 2018-08-24 iii) P. Yadav Envelope on tola to K. North tola with 5 year's Maint. iv) L058 to Asanpur Mushari with 5 year's Maint.

Page 2 BKBDP/RD/SA-III / Construction of Road from i) Road no. 17 to Veer Single Stage - Two IDA / 56960 Post Request for Bids Open - National 1,676,649.05 Signed 2016-09-28 2016-09-28 2016-09-28 2017-01-03 2017-02-13 2018-08-13 goan. ii) Telhar Hospital to Envelope

Road no. 22 with 5 years maintenance.

BKBDP/RD/SA-IV / Cons. of road from i) Chandrayan REO rd. to Jori Bandh ii) REO rd. Rajwanpur to Jori Single Stage - Two IDA / 56960 Post Request for Bids Open - National 807,846.42 Signed 2016-09-28 2016-09-28 2016-09-28 2017-01-06 2017-02-16 2018-08-16 S. Tola and iii) Balwa Envelope koshi bandh to Dhenga via Shahpur with 5 year maintenance.

BKBDP/RD/SA-V / const. of rd. from i)Durgapur to Bhaddi border ii)REO Rd. Pachatri mor to sahsol border iii) sahpur to Sirarhi Single Stage - Two Village iv) Santhali tola IDA / 56960 Post Request for Bids Open - National 3,664,279.90 Signed 2016-09-28 2016-09-28 2016-10-06 2017-02-06 2017-03-20 2018-09-17 Envelope Raghunathpur to Mahua bazar and v) Main canal in kash nagar panchayat to Lokmanya tola chowk with 5 years maintenance.

BKBDP/RD/SA-VI / Const. of road from i) Karua BT rd. in vill. Panchayat Saroja to Kosi bandh via parlahi & 1 no. HL bridge Under Single Stage - Two ii) Baidi in vill. pan. IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2016-09-28 2016-09-28 2016-09-28 2016-09-28 2016-09-28 2017-11-28 Envelope Mahmadpur to kosi bandh on via belbara punarwas with 1 no. HL Bridge & iii) Chakmaka NH 107 to Saroja chowk with 5 years maint.

BKBDP/RD/SA-VII / Const. of road from i) Barkurba BT Road to Kosi Dam & 1 No. HL Bridge ii) Nepal Single Stage - Two IDA / 56960 Post Request for Bids Open - National 3,081,103.44 Signed 2016-09-28 2016-09-28 2016-10-24 2017-02-21 2017-04-03 2018-10-01 Road to Khajuraha via Envelope

Sharma Tola & 1 No. HL Bridge with 5 years maintenance

BKBDP/RD/SA-VIII A / Const. of road from i) Under Gordah Purnawasi to Single Stage - Two IDA / 56960 Post Request for Bids Open - National 942,627.84 Implementati 2016-09-28 2016-09-28 2016-10-06 2017-02-06 2017-03-13 2018-09-10 Chaurahi Road ii) Raghuni Envelope on Baba Sthan to Hansari with 5 years maintenance.

BKBDP/RD/SA-VIII B / Const. of road from i) Sonbarsa PWD Road to Under Fodar Rajak Basa ii) Single Stage - Two IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2016-09-28 2016-09-28 2016-10-06 2017-02-06 2017-03-13 2018-09-10 PMGSY Road at Teliya Envelope on Haat to Fensaha Dhala via Mubarakpur with maintenance for 5 years

BKBDP/RD/SA-IX / Const. of road from i) Keshawpur Road To Bishakarma Chowk in Dhabauli East ii) Bank Single Stage - Two IDA / 56960 Post Request for Bids Open - National 1,118,851.34 Signed 2016-09-29 2016-09-29 2016-09-29 2016-12-16 2017-01-20 2018-07-20 More To Samudaik Bhawan Envelope in Pasawan Harizan Tola of Dhabauli West with maintenance for 5 years.

BKBDP/RD/SA-II / (I)from pwd road to nandlali muslim tola with 5 year Single Stage - Two maint. IDA / 56960 Prior Request for Bids Open - National 1,321,176.51 Signed 2016-09-08 2016-09-08 2016-09-08 2016-09-08 2016-09-08 2017-08-30 Envelope (II)from panchgachhiato sattar village via mehta tola With 5Year Maint.

Page 3 BKBDP/RD/SU-I / Construction of Roads from (i) Ramdatt patti to Bishanpur (ii) Bishanpur Under Single Stage - Two Mushahari To Paswan Tola IDA / 56960 Post Request for Bids Open - National 3,713,007.88 Implementati 2016-09-12 2016-09-12 2016-10-23 2017-02-20 2017-03-27 2018-09-24 Envelope (iii) Sukhpur To Solahani on and (iv) Sati Tola To Kamat Tola with HL Bridge & 5 year maintenance period.

BKBDP/RD/MA-VIII / (i)From PMGSY Road at Parasi chowk To Parasiya Jairam with 5 year maint. Single Stage - Two IDA / 56960 Post Request for Bids Open - National 747,731.52 Signed 2016-09-12 2016-09-12 2016-09-12 2016-11-15 2016-12-20 2018-06-19 (ii) From Envelope

Januantpara(Bhabangama)To Mahtab Das Tola with 5 year maint.

BKBDP/RD/SU-IV / I)FromRoad No 31 to Mahadalit Tola, ViaPO and residence of Chhedilal Yadav, II) From Gocharghat to Satrughan Mehta Tola Single Stage - Two III) S.S Shivji Temple IDA / 56960 Prior Request for Bids Open - National 0.00 Canceled 2016-09-08 2016-09-08 2016-09-08 2016-09-08 2016-10-21 2018-04-20 Envelope Sharma Tola to PMGSY Road IV) Lakhminian to Madhubani V) PMGSY Road Near residance of DP Yadav to SH.

BKBDP/RD-SU-IV / I)FromRoad No 31 to Mahadalit Tola, ViaPO and residence of Chhedilal Yadav, II) From Gocharghat to Satrughan Mehta Tola Single Stage - Two IDA / 56960 Prior Request for Bids Open - National 7,433,529.43 Signed 2016-10-24 2016-10-29 2016-12-10 2017-02-22 2017-03-29 2017-09-25 III) S.S Shivji Temple Envelope

Sharma Tola to PMGSY Road IV) Lakhminian to Madhubani V) PMGSY Road Near residance of DP Yadav to SH

BKBDP/RD/SU-III / Construction of Road from 1. L036 to Kumhar Tola 2. T03 to Muslim Tola & Mallah Tola 3. T04 Yadav Under Single Stage - Two Tola to Haripur West Tola IDA / 56960 Post Request for Bids Open - National 3,448,127.81 Implementati 2016-10-27 2016-10-27 2016-10-27 2017-01-15 2017-02-13 2018-08-13 Envelope 4. T04 to Punarwas Harijan on Tola 5. T02 (Koshi Bund) to Jhinuwa & 6. T01 (P.W.D.) to Parsauni & 1 No. HL Bridge with 5 years maint.

BKBDP/RD/SU-VI / Const. of road from 1. Tulapatti Siniyog PWD Road 2. PWD Road Link to Ram Tola 3. Kataiya main Canal Road Under Single Stage - Two 4. Sadanand Birbal's IDA / 56960 Post Request for Bids Open - National 3,066,237.05 Implementati 2016-10-27 2016-10-27 2016-10-27 2017-02-24 2017-03-31 2018-09-28 Envelope residence to Garhi Tola 5. on NH-106 to Canal 6. Govindpur to Shreepur & 7. NH106 in Karjain Panchayat to Sitpur with 5 years maint

BKBDP/RD/SU-VII / Const. of road from 1. Gamhariya Koriyapatti Menor of Devipur Panchayat to Kamat Tola 2. NH-57 to Under Single Stage - Two Shreepur Via Bhawanipur IDA / 56960 Post Request for Bids Open - National 4,082,874.63 Implementati 2016-10-27 2016-10-27 2016-10-27 2017-01-25 2017-03-01 2018-08-29 Envelope & 3. Residence of Jairam on Choudhary to Jainagara Sukhanagar Middle School & 1 No. HL Bridge with 5 years maint.

Page 4 BKBDP/RD/SU-VIII / Cons. of road from 1. Santalal Shah to Gospur Mehta Tola 2. NH-57 of Rambishnupur Panchayat to Haripur Under Middle School 3. PWD Single Stage - Two IDA / 56960 Post Request for Bids Open - National 3,003,066.49 Implementati 2016-10-27 2016-10-27 2016-10-27 2016-10-27 2016-10-27 2017-12-15 Satsang Bhawan of Envelope on Majhauwa to Sukhasan border & 4. Gadhiya Mahadalit Tola to Shahpur Pula Chowk PMGSY Road with 5 years maint.

BKBDP/RD/SU-V / Cons. of road from 1. PWD Road residence of Kusaha Nanki Singh to Mehta Tola Gajahar 2. Latona Mission Under to Kasha residence of Single Stage - Two IDA / 56960 Post Request for Bids Open - National 3,146,267.49 Implementati 2016-10-27 2016-10-27 2016-10-27 2016-10-27 2016-12-01 2018-05-31 Yogendra Yadav 3. PMGSY Envelope on Road Baherwa to PMGSY Road Nonisari & 4. PWD Mahadev Sthan to main road via Guriya Tola with 5 years maint

IN- BIHAR/BKBDP/WRD/WORK S/PK-2 / Protection and Restoration works of 14 Single Stage - Two IDA / 56960 Prior Request for Bids Open - National 0.00 Canceled 2016-09-08 2016-09-20 2016-11-01 2017-01-14 2017-02-18 2018-08-18 nos. of spurs between Km Envelope

15.5 to Km 28.2 of Eastern Kosi Embankment (Package- 2)

BKBDP/BAPEPS/WRD/COE/ WORKS/01/2016-17 / Renovation of existing Single Stage - Two building for Mathematical IDA / 56960 Post Request for Bids Open - National 90,419.53 Signed 2017-02-16 2017-02-21 2017-04-04 2017-06-17 2017-07-22 2017-11-22 Envelope Modeling Centre (MMC) at Jal Sansadhan Bhawan, Anisabad, Patna

WBP/PH-2/PACKAGE- 24/2014-15 / Construction of H.L. R.C.C. Bridge with its Single Stage - Two approach road in 15th K.m IDA / 56960 Prior Request for Bids Open - National 2,753,203.68 Signed 2017-03-17 2017-03-17 2017-03-17 2017-04-26 2017-06-07 2019-06-07 Envelope of Ranginiya- Sonebarsa road in the district of .

WBP/PH-2/PACKAGE- 04/2014-15 / Construction of H.L. R.C.C. Bridge with its approach road in 3rd K.m Under Single Stage - Two of Belghachhi-(PWD) Via IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2017-03-17 2017-03-17 2017-03-17 2017-03-17 2017-03-17 2017-05-26 Envelope Nitendra-Kalimandir- on Machhatta-Geria (Section- Palsa to Kalimandir) road in the district of Purnia.

WBP/PH-2/PACKAGE- 03/2014-2015 / Construction of H.L. R.C.C. Bridge with its approach road in 3rd Under Single Stage - Two K.m of Panchgachhiya- IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2017-04-03 2017-04-03 2017-04-03 2017-04-03 2017-04-03 2018-12-20 Envelope road & 7th K.m on of Panchgachhiya-Nauhatta road in the district of Saharsa.

WBP/PH-2/PACKAGE- 07/2014-2015 / Construction of H.L. R.C.C. Bridge with its approach road in 10th K.m of Khurhan-Parail- Under Ratwara-Kapasia (Extended Single Stage - Two IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2017-04-03 2017-04-03 2017-04-03 2017-04-03 2017-04-03 2018-11-06 Part of RCD road 0 to 15 Envelope on K.m) road & 5th K.m of Alamnagar-Budhma-Mali (near Khurhan-Parail more) road in the district of Madhepura.

Page 5 IN- BIHAR/BKBDP/WRD/WORK S/PK-2/RE-BIDDING / Protection & Restoration works between Km 15.50 to Single Stage - Two IDA / 56960 Prior Request for Bids Open - National 16,447,818.74 Signed 2017-07-27 2017-08-01 2017-09-12 2017-11-25 2017-12-30 2018-06-28 Km 28.20 of Eastern Kosi Envelope

Embankment ( Package 2) under Bihar Kosi Basin Development Project

IN- BIHAR/BKBDP/WRD/WORK S/PK-2 RE-BIDDING / Protection and Restoration Single Stage - Two works of 14 nos. of Spurs IDA / 56960 Prior Request for Bids Open - National 0.00 Canceled 2017-02-09 2017-02-09 2017-02-28 2017-04-20 2017-05-18 2018-11-18 Envelope between Km 15.50 to Km 28.20 of Eastern Kosi Embankment (Package-2)-Re bidding

WBP/PH-2/PACKAGE- 08/2014-15 / Construction of H.L. R.C.C. Bridge (3x33m) Under with its approach road in Single Stage - Two IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2017-07-20 2017-07-20 2017-07-20 2017-07-20 2017-07-20 2019-03-26 5th K.m of Baluwahat Kosi Envelope on Bandh via Aghori-Sakra- Paharpur- road in the district of Saharsa.

WBP/PH-2/PACKAGE- 09/2014-15 / Construction of H.L. R.C.C. Bridge with its Under approach road in 4th K.m Single Stage - Two IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2017-07-20 2017-07-20 2017-07-20 2017-07-20 2017-07-20 2019-03-26 and 8th K.m of Baisi- Envelope on Amour-Bahadurganj- Dighalbank (SH-99) road in the district of Purnia.

WBP/PH-2/PACKAGE- 10/2014-15 / Construction of H.L. R.C.C Bridge with its Under Single Stage - Two approach road in 11th K.m IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2017-07-20 2017-07-20 2017-07-20 2017-07-20 2017-07-20 2018-09-23 Envelope of Chandradei-Bangama- on Matiyari-Mogra road in the district of Araria.

WBP/PH-2/PACKAGE- 11/2014-15 / Construction of H.L, R.C.C Bridge with its Under approach road in Tharbitya- Single Stage - Two IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2017-07-20 2017-07-20 2017-07-20 2017-07-20 2017-07-20 2020-01-09 Bisanpur (near Parsa) road Envelope on and in Tharbitya-Bisanpur (near Sindhiyan) road in the district of Supaul.

WBP/PH-2/PACKAGE- 12/2014-15 / Construction of H.L. R.C.C. Bridge in 13th K.m (1st cutting) at Khapur Under Single Stage - Two Culvert of Kurhan-Parail- IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2017-07-20 2017-07-20 2017-07-20 2017-07-20 2017-07-20 2019-12-05 Envelope Ratwara-Kapasia (Extended on part of RCD road 0 to 15K.m) road in the district of Madhepura.

WBP/PH-2/PACKAGE- 13/2014-15 / Construction of H.L. R.C.C. Bridge with its Under approach road in 3rd Km Single Stage - Two IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2017-07-20 2017-07-20 2017-07-20 2017-09-18 2017-10-09 2020-11-05 of Baluwahat Kosibandh via Envelope on Aghori-Sakra-Paharpur- Baghwa road in the district of Saharsa.

WBP/PH-2/PACKAGE- 14/2014-15 / Construction of H.L. R.C.C. Bridge with its Under Single Stage - Two approach road in 16th K.m IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2017-07-20 2017-07-20 2017-07-20 2017-07-20 2017-07-20 2019-03-26 Envelope and 18th K.m of Kadava- on Sonouli road in the district of Purnia.

Page 6 WBP/PH-2/PACKAGE- 15/2014-15 / Construction of Under H.L. R.C.C. Bridge with its Single Stage - Two IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2017-07-20 2017-07-20 2017-07-20 2017-07-20 2017-07-20 2018-06-22 approach road in 5th K.m Envelope on of Jokihat-Dalmalpur road in the district of Araria.

WBP/PH-2/PACKAGE- 16/2014-15 / Construction of H.L. R.C.C. Bridge with its approach road in 1st K.m. Under of Persarma-Chikni, 4th Single Stage - Two IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2017-07-20 2017-07-20 2017-07-20 2017-07-20 2017-08-02 2020-08-29 K.m of Persarma-Chikni (on Envelope on Khardaha Dhar) and 4th K.m. of Persarma-Chikni (Barwari Station-Simra) road in the district of Supaul.

WBP/PH-2/PACKAGE- 17/2014-15 / Construction of H.L, R.C.C Bridge with its approach road in 13th Km (2nd Cutting) Khurhan- Under Single Stage - Two Parel-Ratwara-Kapasia road IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2017-07-26 2017-07-26 2017-07-26 2017-07-26 2017-07-26 2020-01-09 Envelope in between Rudho-Mandal on Tola and Pandit Tola in the district of Madhepura. (Extended part of RCD road 0 to 15 k.m.)

WBP/PH-2/PACKAGE- 18/2014-15 / Construction of H.L, R.C.C Bridge with its approach road in 11th Under Single Stage - Two K.M. of Baluwahat koshi IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2017-07-26 2017-07-26 2017-07-26 2017-07-26 2017-07-26 2019-10-27 Envelope bandh via Aghori-Sakra- on Paharpur-Baghwa road in Place of SP Bridge in the district of Saharsa.

WBP/PH-2/PACKAGE- 19/2014-15 / Construction of H.L. R.C.C. Bridge with its approach road in 4th K.m of Falka-Sripur-Bhawanipur- Under Single Stage - Two Karman Chowk (at Sripur IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2017-07-26 2017-07-26 2017-07-26 2017-07-26 2017-07-26 2019-03-26 Envelope Ghat) road & 25th K.m of on Falka-Sripur-Bhawanipur- Karman Chowk (at Balia Ghat) road in the district of Purnia.

WBP/PH-2/PACKAGE- 21/2014-15 / Construction of H.L. R.C.C. Bridge with its approach road in 3rd K.m Under of Supaul Station to Bariya Single Stage - Two IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2017-07-26 2017-07-26 2017-07-26 2017-07-26 2017-07-26 2019-03-26 Manch road & 3rd K.m of Envelope on Sesouni-East Kosi Embankment (Near Khakhi) road in the district of Supaul.

WBP/PH-2/PACKAGE- 20/2014-15 / Construction of H.L. R.C.C. Bridge with its Under Single Stage - Two approach road in 3rd K.m IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2017-07-26 2017-07-26 2017-07-26 2017-07-26 2017-07-26 2018-06-29 Envelope of Nasir Chowk-Belwa- on Mazgama-Mongara road in the district of Araria.

WBP/PH-2/PACKAGE- 22/2014-15 / Construction of H.L, R.C.C Bridge with its Under approach road in Single Stage - Two IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2017-07-26 2017-07-26 2017-07-26 2017-07-26 2017-07-26 2018-06-23 Chandradei-Kamaldha- Envelope on Paratha road along Laliahi Dhar in 2nd Km in the district of Araria.

Page 7 WBP/PH-2/PACKAGE- 25/2014-15 / Construction of H.L. R.C.C. Bridge with its Under Single Stage - Two approach road in 5th K.m IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2017-07-26 2017-07-26 2017-07-26 2017-07-26 2017-07-26 2020-03-12 Envelope of Chatapur-Girdharpatti- on Chuni road in the district of Supaul.

WBP/PH-2/PACKAGE- 26/2014-15 / Construction of H.L, R.C.C Bridge with its Under approach road in 2nd K.M. Single Stage - Two IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2017-07-26 2017-07-26 2017-07-26 2017-07-26 2017-07-26 2019-03-26 of Mehadipur-Fatehpur on Envelope on river surser (Near wooden Bridge) road in the district of Supaul.

WBP/PH-2/PACKAGE- 27/2014-15 / Construction of H.L. R.C.C. Bridge with its approach road in 11th K.m Under of Sonebarsa-Gwalpara road, Single Stage - Two IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2017-07-27 2017-07-27 2017-07-27 2017-07-27 2017-07-27 2020-01-02 17th K.m (1st cutting) of Envelope on Sonebarsa-Gwalpara road and 17th K.m (2nd cutting) of Sonebarsa-Gwalpara road in the district of Saharsa

WBP/PH-2/PACKAGE- 28/2014-15 / Construction of H.L. R.C.C. Bridge with its Under Single Stage - Two approach road in 6th K.m IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2017-07-27 2017-07-27 2017-07-27 2017-07-27 2017-07-27 2018-06-23 Envelope of Balua-Baysi road in on Place of Murli Branch Canal road in the district of Supaul

WBP/PH-2/PACKAGE- 30/2014-15 / Construction of H.L. R.C.C. Bridge with its Under Single Stage - Two approach road in 8th K.m IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2017-07-27 2017-07-27 2017-07-27 2017-07-27 2017-07-27 2019-11-11 Envelope of Simri-Bakhtiyarpur- on Salkhua road in the district of Saharsa

WBP/PH-2/PACKAGE- 32/2014-15 / Construction of H.L. R.C.C. Bridge with its Under Single Stage - Two approach road in 14th K.m IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2017-07-27 2017-07-27 2017-07-27 2017-07-27 2017-07-27 2018-09-23 Envelope of Chaughara-Amha-Lokha- on Saharsa road in the district of Saharsa.

WBP/PH-2/PACKAGE- 33/2014-15 / Construction of H.L. R.C.C. Bridge with its Under Single Stage - Two approach road in 3rd K.m IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2017-07-27 2017-07-27 2017-07-27 2017-07-27 2017-07-27 2018-06-23 Envelope of Belgachhi-Chandpur to on Rouniya-Kanharia road in the district of Purnia.

WBP/PH-2/PACKAGE- 34/2014-15 / Construction of H.L. R.C.C. Bridge with its approach road in Dubhari- Under Single Stage - Two Chakla Ghat to Kosi IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2017-07-27 2017-07-27 2017-07-27 2017-07-27 2017-07-27 2019-11-13 Envelope Embankment road (Near on Spur) on 57.20 R.D. of Kosi Embankment in the district of Supaul.

WBP/PH-2/PACKAGE- 35/2014-15 / Construction of H.L. R.C.C. Bridge with its approach road over Tilyuga Under river in Parrari-Kadmaha Single Stage - Two IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2017-07-27 2017-07-27 2017-07-27 2017-07-27 2017-08-10 2019-03-26 road in Marona Block & Envelope on over Tilyuga river Hariyahia-Haripur village road near Islampur village road in the district of Supaul.

Page 8 WBP/PH-2/PACKAGE- 36/2014-15 / Construction of H.L. R.C.C. Bridge with its approach road over Marne river near primary school Under Single Stage - Two Gordh Ratho to Koni village IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2017-07-27 2017-07-27 2017-07-27 2017-07-27 2017-07-27 2019-03-26 Envelope road in Marona South on Panchyat & over Marne river near Sikhariya- Khushyali village road in the district of Supaul.

WBP/PH-2/PACKAGE- 37/2014-15 / Construction of H.L., R.C.C. Bridge with its approach road over Khardaha river near Bela Under village in Veena-Jharkha Single Stage - Two IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2017-07-27 2017-07-27 2017-07-27 2017-07-27 2017-07-27 2019-03-26 road & H.L. R.C.C. Bridge Envelope on in place of Screw Pile Bridge with its approach road in Veena-Bela-Jhura- Amha road over Tilave river.

WBP/PH-2/PACKAGE- 38/2014-15 / Construction of HL RCC Bridge over Tilyuga river besides screw pile bridge in Kewtapatti- Under Nirmali Bazar road in Single Stage - Two IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2017-07-27 2017-07-27 2017-07-27 2017-07-27 2017-07-27 2020-03-13 Nirmali Block & over Envelope on Tilyuga river in Theho village-Sonapur road in Dagmara Panchyat of Nirmali Block in the district of Supaul.

WBP/PH-2/PACKAGE- 39/2014-15 / Construction of H.L. R.C.C. Bridge with its Under approach road in Basba Single Stage - Two IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2017-07-27 2017-07-27 2017-07-27 2017-07-27 2017-07-27 2018-06-23 Gaon in Basbitti Panchayat Envelope on near 62.6 R.D of Kosi Embankment in the district of Supaul .

WBP/PH-2/PACKAGE- 40/2014-15 / Construction of H.L. R.C.C. Bridge with its Under approach road over Tilyuga Single Stage - Two IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2017-07-27 2017-07-27 2017-07-27 2017-07-27 2017-07-27 2019-10-27 river at Barmotra Ghat in Envelope on Manga to Barmotra road under Marona Block in the district of Supaul.

WBP/PH-2/PACKAGE- 41/2014-15 / Construction of H.L. R.C.C. Bridge with its Under approach road in 24th K.m Single Stage - Two IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2017-07-27 2017-07-27 2017-07-27 2017-07-27 2017-07-27 2018-09-23 of Chandradei-Bangama- Envelope on Paktola-Matiyari-Mongra (along Kakurwa Dhar) in the district of Araria

WBP/PH-2/PACKAGE- 42/2014-15 / Construction of H.L R.C.C Bridge with its approach road in Bhawesa Under Single Stage - Two Dhar near Khanwa Santhali IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2017-07-27 2017-07-27 2017-07-27 2017-07-27 2017-07-27 2018-06-23 Envelope Tola of Kukron West on Panchayat of Dhamdaha Block in the District of Purnia.

WBP/PH-2/PACKAGE- 43/2015-16 / Construction of H.L.R.C.C Bridge with its Under approach road in Khurhan- Single Stage - Two IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2017-07-27 2017-07-27 2017-07-27 2017-07-27 2017-07-27 2019-03-26 Parail-Ratwara-Kapsiya path Envelope on on West Side of Screw Pile Bridge in the district of Madhepura.

Page 9 AFRD/WORKS-01 / Pending Construction of Building of Single Stage - Two IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2018-03-12 2018-03-17 2018-04-28 2018-07-11 2018-08-15 2020-02-11 Training Centres at 05 Envelope on Districts HQ.

BKBDP/BAPEPS/WRD/COE/ PMC/WORKS/01/2018 / Establishment of Physical Pending Single Stage - Two Modeling Center (PMC) at IDA / 56960 Prior Request for Bids Open - National 0.00 Implementati 2018-04-01 2018-04-06 2018-05-18 2018-07-31 2018-09-04 2020-03-04 Envelope Birpur under Bihar Kosi on Basin Development Project (BKBDP)

IN- BIHAR/BKBDP/WRD/WORK S/PK-3/BIDDING / Pending Single Stage - Two Protection & Restoration of IDA / 56960 Prior Request for Bids Open - National 0.00 Implementati 2018-09-10 2018-09-15 2018-10-27 2019-01-09 2019-02-13 2021-02-12 Envelope km 17.25 to km 19.50 & on Km 25.14 to km 26.00 of Eastern Kosi Embankment

RESTRUCTURED - BKFRP/WRD/EED/01C / Pending Protection and restoration Single Stage - One IDA / 56960 Prior Direct Selection Direct 0.00 Implementati 2018-08-21 2018-08-21 2018-08-21 2018-08-21 of 17 Nos. spurs between Envelope on km 78.00 to km 84.00 of eastern Kosi embankment.

GOODS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

IN-BIHAR/BAPEPS/WRD- GOODS-RFB-01 / Pending Open - Single Stage - Two Procurement of 2 Nos. IDA / 56960 Prior Request for Bids 0.00 Implementati 2018-01-16 2018-01-21 2018-03-04 2018-05-17 2018-06-21 2018-12-18 International Envelope Dredgers including O & M on for 5 years.

IN- BIHAR/BAPEPS/WRD/GOOD S/03 / Supply, Installation, Testing & Commissioning of Computer System for Single Stage - Two IDA / 56960 Post Request for Bids Open - National 79,483.99 Signed 2017-02-22 2017-02-27 2017-04-06 2017-04-28 2017-05-24 2017-09-20 Mathematical Modeling Envelope

Centre (MMC), Centre of Excellence (CoE) at Jal Sansadhan Bhawan, Anisabad, Patna

IN- BIHAR/WRD/FMISC/BKBDP/ GOODS/01/17-18 / Procurement of New MIKE Under HYDRO RIVER Software IDA / 56960 Post Direct Selection Direct 0.00 Implementati 2017-05-05 2017-05-05 2017-05-26 2017-11-22 (HD,RR,AD,River on Control,DA) + MIKE FLOOD (Inclusive of MIKE 21 HD,MIKE 21 FM)

IN- BIHAR/WRD/FMISC/BKBDP/ GOODS/02/17-18 / Procurement of MIKE Pending HYDRO RIVER- IDA / 56960 Post Direct Selection Direct 0.00 Implementati 2017-06-16 2017-06-21 2017-07-26 2018-01-22 ST+RR+AD+River on Control+DA) MIKE FLOOD(21 HD +FM) Perpetual License for 2 Users

IN- BIHAR/BAPEPS/WRD/GO- RFB/02/16-17 / Procurement Single Stage - Two IDA / 56960 Prior Request for Bids Open - National 0.00 Canceled 2016-12-17 2017-01-10 2017-02-09 2017-05-04 2017-06-08 2018-12-06 of Real Time Data Envelope

Acquisition System for Kosi and Bagmati Basin.

Page 10 BIHAR/ BAPEPS/ WRD/ GOODS/ 02/ 17-18 / Procurement of Goods and Related Services for Supply, Installation, Testing, Under Single Stage - Two Commissioning and IDA / 56960 Prior Request for Bids Open - National 0.00 Implementati 2017-08-18 2017-09-01 2017-11-02 2018-01-15 2018-02-19 2018-11-16 Envelope Maintenance of Real Time on Data Acquisition System for the Kosi & Bagmati - Adhwara Basins in Bihar, India

IN- BIHAR/BAPEPS/WRD/GOOD S/03/RE-BID / Rebidding of Lot-2 & Lot-3 under Supply, Installation, Testing Single Stage - Two & Commissioning of IDA / 56960 Post Request for Bids Open - National 212,759.36 Signed 2017-08-24 2017-08-26 2017-09-23 2017-12-06 2018-01-10 2018-07-09 Envelope Computer System for Mathematical Modeling Centre (MMC), Centre of Excellence (CoE) at Jal Sansadhan Bhawan, Anisabad, Patna

BIHAR/ BAPEPS/ WRD/ GOODS/ 02/ 17-19 / PROCUREMENT OF GOODS AND RELATED SERVICES FOR SUPPLY, Under INSTALLATION, TESTING, Open - Single Stage - Two IDA / 56960 Prior Request for Bids 0.00 Implementati 2017-09-11 2017-09-21 2017-11-20 2018-02-03 2018-03-11 2018-12-06 COMMISSIONING AND International Envelope on MAINTENANCE OF REAL TIME DATA ACQUISITION SYSTEM FOR THE KOSI & BAGMATI -ADHWARA BASINS IN BIHAR, INDIA

IN- BIHAR/BAPEPS/WRD/GOOD S/03/RE-BID-2 / Rebidding of Lot-4 under Supply, Installation, Testing & Single Stage - Two Commissioning of Computer IDA / 56960 Post Request for Bids Open - National 33,537.90 Signed 2017-09-26 2017-10-01 2017-11-12 2018-01-11 2018-02-15 2018-08-14 Envelope System for Mathematical Modeling Centre (MMC), Centre of Excellence (CoE) at Jal Sansadhan Bhawan, Anisabad, Patna

GOODS/AFRD-15 / Pending Purchase of Almeerah and Request for Single Stage - One IDA / 56960 Post Limited 0.00 Implementati 2017-12-20 2018-02-14 2018-08-13 File Cabinet for Quotations Envelope on SPIU/DPIU/BMT

IN- BIHAR/BAPEPS/WRD/GOOD S/03/RE-BID3 / Rebidding of Lot-3 using shopping mode of procurement under Supply, Installation, Testing Pending Request for Single Stage - One & Commissioning of IDA / 56960 Post Limited 0.00 Implementati 2018-01-05 2018-03-02 2018-08-29 Quotations Envelope Computer System for on Mathematical Modeling Centre (MMC), Centre of Excellence (CoE) at Jal Sansadhan Bhawan, Anisabad, Patna

GOODS/AFRD-14 / Pending Request for Single Stage - One Purchase of Fan for IDA / 56960 Post Limited 0.00 Implementati 2017-12-02 2018-01-27 2018-07-26 Quotations Envelope SPIU/DPIU/BMT on

GOODS/AFRD-09 / Pending Request for Single Stage - One Purchase of IT Periferals IDA / 56960 Post Limited 0.00 Implementati 2018-01-03 2018-02-28 2018-08-27 Quotations Envelope for SPIU/DPIU/BMT on

GOODS/AFRD-11 / Pending Request for Single Stage - One Purchase of Projector for IDA / 56960 Post Limited 0.00 Implementati 2018-02-10 2018-04-07 2018-10-04 Quotations Envelope SPIU/DPIU on

GOODS/AFRD-12 / Pending Request for Single Stage - One Computer Networking IDA / 56960 Post Limited 0.00 Implementati 2018-02-10 2018-04-07 2018-10-04 Quotations Envelope (Wired and Wireless) on

Page 11 GOODS/AFRD-16 / Pending Request for Single Stage - One Purchase of Fridge & Water IDA / 56960 Post Limited 0.00 Implementati 2017-12-25 2018-02-19 2018-08-18 Quotations Envelope Purifier for SPIU on

GOODS/AFRD-18 / Pending Request for Single Stage - One Purchase of Training IDA / 56960 Post Limited 0.00 Implementati 2017-12-20 2018-02-14 2018-08-13 Quotations Envelope Accessaries (TV+Audio Set) on

GOODS/AFRD-19 / Pending Purchase of DG Set for Request for Single Stage - One IDA / 56960 Post Open - National 0.00 Implementati 2018-06-20 2018-08-15 2019-02-11 Block Level Veterniray Quotations Envelope on Hospital.

GOODS/AFRD-21 / Pending Purchase of Portable Power Request for Single Stage - One IDA / 56960 Post Limited 0.00 Implementati 2018-06-20 2018-08-15 2019-02-11 Genset for Mobile Vet. Quotations Envelope on Clinic.

GOODS/AFRD-22 / Pending Purchase of Deep Freezers Request for Single Stage - One IDA / 56960 Post Open - National 0.00 Implementati 2018-07-20 2018-09-14 2019-03-13 and Chest Coolers for Block Quotations Envelope on Vat. Hospitals.

GOODS/AFRD-03 / Pending Request for Single Stage - One Purchase of DG Set for IDA / 56960 Post Limited 0.00 Implementati 2017-12-20 2018-02-14 2018-08-13 Quotations Envelope SPIU on

GOODS/AFRD-06 / Pending Request for Single Stage - One Purchase of Laptops for IDA / 56960 Post Limited 0.00 Implementati 2017-12-20 2018-02-14 2018-08-13 Quotations Envelope SPIU/DPIU/BMT. on

GOODS/AFRD-01 / Pending Request for Single Stage - One Refurbishment of Office IDA / 56960 Post Limited 0.00 Implementati 2017-12-02 2018-01-27 2018-07-26 Quotations Envelope Space ( SPIU-AFRD) on

GOODS/AFRD-02 / Pending Request for Single Stage - One Purchase of office furniture IDA / 56960 Post Limited 0.00 Implementati 2017-12-02 2018-01-27 2018-07-26 Quotations Envelope for SPIU/DPIU/BMT on

GOODS/AFRD-04 / Pending Request for Single Stage - One Purchase of Desktops for IDA / 56960 Post Limited 0.00 Implementati 2017-12-20 2018-02-14 2018-08-13 Quotations Envelope SPIU/DPIU/BMT on

GOODS/AFRD-05 / Pending Request for Single Stage - One Purchase of UPS for IDA / 56960 Post Limited 0.00 Implementati 2017-12-20 2018-02-14 2018-08-13 Quotations Envelope SPIU/DPIU on

GOODS/AFRD-08 / Pending Request for Single Stage - One Purchase of Photocopier IDA / 56960 Post Limited 0.00 Implementati 2017-12-30 2018-02-24 2018-08-23 Quotations Envelope cum Printers for SPIU. on

GOODS/AFRD-17 / Pending Request for Single Stage - One Purchase of Air Cooler for IDA / 56960 Post Limited 0.00 Implementati 2018-02-04 2018-04-01 2018-09-28 Quotations Envelope DPIU on

GOODS/AFRD-20 / Pending Request for Single Stage - One Purchase of Solar Backup IDA / 56960 Post Open - National 0.00 Implementati 2018-06-25 2018-08-20 2019-02-16 Quotations Envelope for Veterinary Hospital on

GOODS/AFRD-25 / Plant Pending Request for Single Stage - One and Machineries for Fish IDA / 56960 Post Open - National 0.00 Implementati 2018-08-20 2018-10-15 2019-04-13 Quotations Envelope Feed Mill. on

GOODS/AFRD-27 / Pending Single Stage - Two Procurement of Tools for AI IDA / 56960 Post Request for Bids Open - National 0.00 Implementati 2018-10-15 2018-10-20 2018-12-01 2019-02-13 2019-03-20 2019-09-16 Envelope Centers. on

GOODS/AFRD-23 / Pending Purchase of small Request for Single Stage - One IDA / 56960 Post Limited 0.00 Implementati 2018-07-05 2018-08-30 2019-02-26 Refrigerators for mobile Quotations Envelope on Clinic.

Pending GOODS/AFRD-24 / Request for Single Stage - One IDA / 56960 Post Open - National 0.00 Implementati 2018-10-20 2018-12-15 2019-06-13 Refrigerataed Van (Fish) Quotations Envelope on

Page 12 GOODS/AFRD-26 / Pending Purchase of Tablets for Request for Single Stage - One IDA / 56960 Post Limited 0.00 Implementati 2018-12-20 2019-02-14 2019-08-13 Small Riminant Resource Quotations Envelope on Persons.

GOODS/AFRD-07 / Pending Request for Single Stage - One Purchase of Printers & IDA / 56960 Post Limited 0.00 Implementati 2017-12-25 2018-02-19 2018-08-18 Quotations Envelope Scanners. on

GOODS/AFRD-10 / Pending Request for Single Stage - One Purchase of Digital Camera IDA / 56960 Post Limited 0.00 Implementati 2018-01-08 2018-03-05 2018-09-01 Quotations Envelope for SPIU/DPIU/BMT on

Pending GOODS/AFRD-13 / Request for Single Stage - One IDA / 56960 Post Limited 0.00 Implementati 2017-12-02 2018-01-27 2018-07-26 Purchase of AC for SPIU Quotations Envelope on

NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

WRD-LIDAR-BKBDP / Aerial Survey using ALS- DC(LIDAR-DC) Sensor, Generation of Geo-Spatial IDA / 56960 Prior Direct Selection Direct 4,018,204.08 Signed 2017-01-10 2017-01-15 2017-02-19 2019-02-18 data base of Kosi basin of Bihar and Supply of data products.

AFRD/NON- Pending CONSULTANCY-03 / Request for Single Stage - One IDA / 56960 Post Limited 0.00 Implementati 2018-01-20 2018-03-17 2018-09-13 Networking accessories and Quotations Envelope on services.

AFRD/NON- Pending Request for Single Stage - One CONSULATANCY-01 / IDA / 56960 Post Limited 0.00 Implementati 2018-04-20 2018-06-15 2018-12-12 Quotations Envelope Hiring of Vehicles. on

AFRD/NON- Pending Request for Single Stage - One CONSULTANCY-02 / AMC IDA / 56960 Post Limited 0.00 Implementati 2018-10-20 2018-12-15 2019-06-13 Quotations Envelope for Computers. on

CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Interest Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

IN-BAPEPS-1445-CS-QCBS / Hiring of consultant for third party quality audit Quality And Cost- IDA / 56960 Prior Open - National 0.00 Canceled 2016-09-12 2016-10-03 2016-11-16 2016-12-14 2017-01-13 2017-02-17 2017-03-24 2019-03-24 and quality assurance for Based Selection roads, bridges and embankment works.

IN- BIHAR/BAPEPS/WRD/CONS ULTANCY/01/16-17 / Consultancy Services for Managing Mathematical Quality And Cost- Open - Modeling Centre (MMC) of IDA / 56960 Prior 2,157,577.54 Signed 2017-02-15 2017-03-08 2017-04-21 2017-05-19 2017-06-18 2017-07-23 2017-08-27 2020-09-27 Based Selection International the Centre of Excellence for

Water Resources Research & Development under Water Resources Department, Bihar

Page 13 IN- BIHAR/BAPEPS/WRD/CONS ULTANCY/02/2017 / HIRING OF CONSULTANCY SERVICE FOR PREPARATION OF Quality And Cost- Under IDA / 56960 Post Open - National 0.00 2017-03-25 2017-03-29 2017-05-12 2017-06-09 2017-07-09 2017-08-13 2017-09-17 2018-04-15 DETAILED PROJECT Based Selection Implementation

REPORT FOR PROCUREMENT OF DREDGER UNDER BIHAR KOSI BASIN DEVELOPMENT PROJECT

IN-BAPEPS-1453-CS-QCBS / Hiring of Statutory Quality And Cost- Under IDA / 56960 Post Open - National 0.00 2017-09-22 2017-09-22 2017-10-05 2017-10-30 2017-11-04 2017-11-14 2017-11-24 2018-02-22 auditor for the Financial Based Selection Implementation

Year 2016-17

AFRD/CONSULTANCY-3 / Consultancy services for Quality And Cost- Pending IDA / 56960 Post Open - National 0.00 2018-11-01 2018-11-22 2019-01-05 2019-02-02 2019-03-04 2019-04-08 2019-05-13 2021-05-12 training to small ruminants Based Selection Implementation

Resource Persons ( Women)

AFRD/CONSULTANCY-2 / Consultancy Services for Quality And Cost- Pending IDA / 56960 Post Open - National 0.00 2018-10-15 2018-10-27 2018-12-21 2019-01-05 2019-01-15 2019-02-04 2019-03-11 2021-02-03 training to artificial Based Selection Implementation

Insemination ( AI) Workers

AFRD/CONSULTANCY-04 / Hiring of Service Provider Quality And Cost- Pending for Formation Facilitation IDA / 56960 Post Open - National 0.00 2018-01-15 2018-02-05 2018-03-21 2018-04-18 2018-05-18 2018-06-22 2018-07-27 2019-07-27 Based Selection Implementation and Management of Poultry Value Chain.

AFRD/CONSULTANCY-05 / Hiring of Service Provider Quality And Cost- Pending for formation facilitation IDA / 56960 Post Open - National 0.00 2018-01-15 2018-02-05 2018-03-21 2018-04-18 2018-05-18 2018-06-22 2018-07-27 2019-07-27 Based Selection Implementation and management of Goatry Value Chain.

AFRD/CONSULTANCY-06 / Hiring of Service Provider Quality And Cost- Under for formation facilitation IDA / 56960 Post Open - National 0.00 2018-01-15 2018-02-05 2018-03-21 2018-04-18 2018-05-18 2018-06-22 2018-07-27 2019-07-27 Based Selection Implementation and management of Fishries Value Chain.

IN-BAPEPS-1452-CS-QCBS / Hiring of HR recruitment Quality And Cost- Pending IDA / 56960 Post Open - National 0.00 2018-06-01 2018-06-22 2018-08-05 2018-09-02 2018-10-02 2018-11-06 2018-12-11 2019-12-11 Agency for selection of Based Selection Implementation human resources for BKBDP

BAPEPS/CONSULTANCY/TP QA-01 / Hiring of consultancy services of Quality And Cost- Under IDA / 56960 Prior Open - National 0.00 2018-03-15 2018-03-15 2018-03-29 2018-04-26 2018-05-26 2018-06-30 2018-08-04 2019-08-04 Third Party Quality Audit Based Selection Implementation and Quality Assurance for BKBDP

INDIVIDUAL CONSULTANTS

Page 14