Appeal by Tesco Stores Ltd Former Smiths Industries Aerospace Ltd, The Harrow Way, , RG22 4BF PINS Ref No. (APP/H1705/A/12/2182975)

Proof of Evidence of Scott Marshall Highways & Transport Matters

January 2013

Atkins Highways & Transportation Woodcote Grove Ashley Road Epsom KT18 5BW Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

CONTENTS

1. INTRODUCTION 1-1 Qualifications & Experience 1-1 Scope of My Involvement & This Proof of Evidence 1-1 Reasons for Refusal 1-3 Structure of Evidence 1-4

2. REASON FOR REFUSAL 3: PART 1 – INSUFFICENT DETAIL REGARDING THE IN-PRINCIPLE PROPOSED HIGHWAYS PLANS 2-1 Policy Context 2-1 Insufficient Detail 2-2 Part 1: Summary 2-4

3. REASON FOR REFUSAL 3: PART 2 – INSUFFICENT DETAIL REGARDING TRANSPORT ASSESSMENT 3-1 Best Practice Guidance 3-1 Transport Assessment – Insufficient Detail 3-2 Traffic Data – Insufficient Detail 3-4 Part 2: Summary 3-5

4. REASON FOR REFUSAL 3: PART 3 – DESIGN OF OFF-SITE HIGHWAYS WORKS 4-1 LINSIG Traffic Modelling – General Points 4-1 Highway Safety – General Points 4-1 Design of Off-Site Highways Works – Detailed Considerations 4-3 The Harrow Way / Tesco Site Access 4-3 The A30 Road / Brighton Hill Retail Park Access / Site Access 4-4 The Proposed Highway Works at The Harrow Way / Lister Road Junction 4-5 The Proposed Highway Works at Brighton Hill Roundabout 4-6 The Proposed Highway Works at the Winchester Road Roundabout 4-9 The Proposed Highway Works On The Harrow Way 4-10 Reason for Refusal 3 Summary 4-11

5. REASON FOR REFUSAL 4: BRIGHTON HILL ROUNDABOUT 5-1 Policy Context 5-1 The Proposed Highway Works at Brighton Hill Roundabout 5-3 Effect on Vulnerable Road Users 5-3 Walk Distances 5-5 Walk Times 5-6 Road Safety Assessment 5-8

ii Former Smiths Industries Aerospace Ltd, The Harrow Way, Scott Marshall POI v1.doc Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

Interuption of Traffic 5-10 Reason for Refusal 4 Summary 5-11

6. OTHER RELATED MATTERS 6-1 Agreed Statement on Transport Matters 6-1 Gross Floor Area 6-2 Trip Distribution 6-4 Future Maintenance Liability 6-4

7. CONCLUSIONS 7-1

iii Former Smiths Industries Aerospace Ltd, The Harrow Way, Scott Marshall POI v1.doc Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

1. INTRODUCTION

QUALIFICATIONS & EXPERIENCE

1.1 My name is Scott Marshall and I am employed as a Managing Consultant within

Atkins Highways & Transportation, part of the Atkins Group. I hold a Bachelor of

Engineering Degree in Civil Engineering from The University of Liverpool. I am a

Chartered Civil Engineer, a Member of The Institution of Civil Engineers and a

Member of The Chartered Institution of Highways & Transportation.

1.2 I have over 12 years of consultancy experience in transport planning, traffic

engineering and highway engineering. I currently hold the position of Managing

Consultant within the Development & Public Realm Business, which provides

consultancy services with respect to all aspects of land development and

regeneration. Within this business I lead the Development Planning sector

nationally.

1.3 I have extensive experience of preparing Transport Statements, Transport

Assessments and Travel Plans and associated development led highway

engineering schemes, for a variety of developments throughout the UK.

SCOPE OF MY INVOLVEMENT & THIS PROOF OF EVIDENCE

1.4 In November 2012, I was appointed by Basingstoke & Deane Borough Council to

represent the Council on transport and highways matters related to the appeal at

the proposed development at Former Smiths Industries Aerospace Ltd Site, The

Harrow Way, Basingstoke.

1-1 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

1.5 A planning application (number BDB/75056) was submitted for “Erection of a

Class A1 (retail) foodstore with associated car park, landscaping and in-principle

proposed off-site highway works.” The application was refused by Basingstoke

& Deane Borough Council (hereafter referred to as “the Council”) at

Development Control Planning Committee, dated 25th July 2012, and

subsequent Refusal Notice, dated 16th August 2012 (Core Document 8.2). This

application forms the subject of this appeal.

1.6 I have undertaken a comprehensive site visit for the purposes of the appeal, and

thus have a good knowledge of the site and the surrounding transport network.

1.7 I have met with highways officers of the Council and County Council

(HCC) for the purposes of the appeal.

1.8 I have reviewed the webcast of the Planning Committee meeting to satisfy

myself that I could support Members reasons for refusal. My summary notes

have been included in Appendix A.

1.9 This Proof of Evidence refers to the appellant’s Transport Assessment (26th

August 2011) (Core Document 6.4) prepared for the site, as well as drawings of

the in-principle proposed off-site highways works (Core Document 7.5 &

Appendix B), prepared by the appellant. It also refers to key HCC letters dated

November 2011 and dated 15th May 2012 (Appendix 2 and 3 of Katherine Miles

Proof of Evidence) and the Final Draft Agreed Statement on Transport Matters,

as to be agreed between the appellant and HCC dated 4th January 2013 (Core

Document 9.12).

1-2 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

1.10 In evaluating the Council’s case I considered three specific aspects of the

highways case, namely: -

(i) The LinSig traffic modelling that underpins the proposed highway

changes as covered by Appendix C;

(ii) The road safety aspects of the proposals as covered in by Road Safety

Assessment presented in Appendix D; and

(iii) The design of the Brighton Hill Roundabout as covered by the technical

review presented in Appendix E.

REASONS FOR REFUSAL

1.11 Planning permission was refused for five reasons; the first and second reasons

were on retail planning grounds and will be covered in the Proof of Evidence

presented by Jonathon Baldock. The third and fourth reasons relate to highways

matters and are covered by the scope of this Proof of Evidence. The fifth reason

relates to the proposed mechanism for securing off-site highways works and will

be covered in the Proof of Evidence presented by Katherine Miles, appeal Case

Officer.

1.12 I include the relevant reasons for refusal below that will be subsequently covered

by my evidence:

Reason 3, which states “The in-principle design of the off-site highways works,

including site accesses, does not include sufficient detail to satisfactorily

demonstrate that the proposed highway works would adequately mitigate against

the significant impact of the proposed development for all highways users. It has

also not been demonstrated that safe and suitable access to the site can be

achieved and that the proposed highway works can be effectively undertaken

1-3 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

within the transport network in such a way as to mitigate the significant impacts

of the development. As such, the proposed development would be contrary to

Saved Policy E1 of the Basingstoke and Deane Borough Local Plan 1996-2011;

and paragraph 32 of the National Planning Policy Framework (March 2012).

Reason 4, which states “It is considered that the proposed development, through

the proposed associated highways works at Brighton Hill roundabout, would not

adequately cater for the needs of vulnerable road users including pedestrians

and cyclists resulting in severance across established movement routes. As

such the severance of such routes would add hazards for vulnerable users with

the proposed works to the Brighton Hill roundabout resulting in danger,

inconvenience, obstruction and interruption of the movement of traffic. The

proposed works to the Brighton Hill Roundabout do not provide safe and

convenient movement for all potential users nor do they integrate the

development into the existing surrounding movement network, contrary to Saved

Policies E1 and A2 of the Basingstoke and Deane Borough Local Plan 1996-

2011 and the National Planning Policy Framework (March 2012).”

STRUCTURE OF EVIDENCE

1.13 In this Proof of Evidence I present evidence to support reasons for refusal 3 and

4, then provide further material relevant to the Council’s case, before concluding

remarks in light of policy.

1.14 In reading reasons for refusal 3 and 4 it should be recognised that there is some

overlap between them and accordingly my proof is structured as follows: -

(i) Reason for refusal 3: Part 1 – Insufficient Detail regarding the In-Principle

Proposed Highway Plans;

1-4 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

(ii) Reason for refusal 3: Part 2 – Insufficient Detail regarding Transport

Assessment;

(iii) Reason for refusal 3: Part 3 – Design of off-site highways works;

(iv) Reason for refusal 4: Brighton Hill Roundabout;

(v) Other Relevant Matters; and

(vi) Conclusion.

1.15 The section on Reason for refusal 3: Part 1 and Part 2 specifically address

Members’ concerns over not having sufficient information and detail upon which

to base an informed decision. In Part 3 I will cover reason 3 in much greater

depth to demonstrate that Members were justified in their position.

1.16 The section, Reason for refusal 4, will cover those matters not previously

covered by Reason for refusal 3.

1.17 I include a final section called Other Relevant Matters that I believe are pertinent

to the Appeal and should be drawn to the Inspector’s attention.

1-5 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

2. REASON FOR REFUSAL 3: PART 1 – INSUFFICENT

DETAIL REGARDING THE IN-PRINCIPLE PROPOSED

HIGHWAYS PLANS

POLICY CONTEXT

2.1 I set out Policy Context here in Part 1 and this applies to all remaining sections

of my proof.

2.2 Reason for refusal 3 states that the proposed development would be contrary to

Saved Policy E1 of the Basingstoke and Deane Borough Local Plan 1996-2011

and paragraph 32 of the National Planning Policy Framework (March 2012).

2.3 Saved Policy E1 of the Basingstoke and Deane Borough Local Plan 1996-2011

(Core Document 3.1) states:

“Proposals for new development will be permitted provided that they...do not

result in inappropriate traffic generation or compromise highway safety. All

development proposals should therefore...not generate traffic of a type or

amount inappropriate for roads, properties or settlements in the locality, and

provide safe and convenient access for all potential users, integrating into

existing movement networks and open spaces...”

2.4 Paragraph 32 of the National Planning Policy Framework, March 2012 (Core

Document 1.1) states:

“All developments that generate significant amounts of movement should be

supported by a Transport Statement or Transport Assessment. Plans and

decisions should take account of whether:

2-1 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

 the opportunities for sustainable transport modes have been taken up

depending on the nature and location of the site, to reduce the need for

major transport infrastructure;

 safe and suitable access to the site can be achieved for all people; and

 improvements can be undertaken within the transport network that cost

effectively limit the significant impacts of the development. Development

should only be prevented or refused on transport grounds where the residual

cumulative impacts of development are severe.”

INSUFFICIENT DETAIL

2.5 The in-principle proposed highways drawings supporting the appeal were

described in the Committee Report as in italics below. These are included in

Appendix B: -

(i) “full signalisation of the existing Brighton Hill roundabout, the provision of

4 lanes through the centre of the existing roundabout island to create a

through-about and widening of the existing circulatory carriageway and

approaches as shown in principle on Drawing No 208084 124 Rev B;

(ii) partial signalisation of the A30 Winchester Road roundabout including the

widening of approaches and increasing the width of the circulatory

carriageway as shown in principle on Drawing No 208084 125;

(iii) signalisation of The Harrow Way/Lister Road junction as show in principle

on Drawing No 208084 118 Rev A;

(iv) improvements along The Harrow Way including the provision of a

segregated shared use footway/cycleway and associated crossings and

2-2 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

the provision of central hatching as shown in principle on Drawings

208084 108 Rev B 1 to 3;

(v) improvement to the A30 Winchester Road/Retail Park signals to increase

the length of the left turn as shown in principle on Drawing No 208084

113 Rev C;

(vi) construction of a new access in the form of a signalised junction to the

proposed development from The Harrow Way as shown in principle on

Drawing 208084 111 Rev C.”

2.6 The fundamental concern is that the drawings were ‘stand alone’ and

unaccompanied by an up-to-date Transport Assessment report. This is covered

specifically in the following section.

2.7 I have scrutinised the plans and make the following observations that are

relevant: -

(i) On some of the drawings there is limited information to assist in

understanding their orientation. There is no north point on Drawing No

208084: 108B (1/2/3); 111C; 118A; 124B. This is a feature of 6 out of 8

of the proposed drawings. The lack of a north point on a drawing does

not assist the viewer to interpret the proposals;

(ii) Many of the title boxes of the drawings are blank or incomplete. Most of

the drawings do not have any drawing status, and do not appear to have

been checked;

(iii) It is not easy to see the differences between existing and proposed

layouts for ease of comparison;

2-3 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

(iv) I have been unable to find a simple overview plan that shows all junctions

in relation to each other;

(v) Road names are not marked; and

(vi) The drawings include limited annotation.

2.8 I will cover specific detail matters drawing by drawing in Reason for refusal 3:

Part 3 later.

PART 1: SUMMARY

2.9 The drawings were unsupported by a Transport Assessment report.

2.10 They were not prepared to a standard that would assist the confidence of

decision maker. This is evidenced on the drawings themselves – by a lack of:

basic detail including annotation; an overview plan; ease of reference between

existing and proposed; and a number of drawings being incomplete.

2-4 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

3. REASON FOR REFUSAL 3: PART 2 – INSUFFICENT

DETAIL REGARDING TRANSPORT ASSESSMENT

BEST PRACTICE GUIDANCE

3.1 A development of this scale and land-use requires a Transport Assessment and

this is the case for food retail, with a floor area greater than 800m2. The

overarching guidance that covers this assessment is covered by the Department

for Communities and Local Government and Department for Transport

“Guidance on Transport Assessment” published in March 2007 (relevant extracts

have been included in Appendix F). Hereafter, this is referred to as “Guidance

on Transport Assessment”. A Transport Assessment report is often referred to

as a TA.

3.2 Section 1.2 in Guidance on Transport Assessment states that: “A TA is a

comprehensive and systematic process that sets out transport issues relating to

a proposed development. It identifies what measures will be taken to deal with

the anticipated transport impacts of the scheme and to improve accessibility and

safety of all modes of travel, particularly for alternatives to the private car such

as walking, cycling and public transport.”

3.3 Figures 4.1 and 4.2 and Section 4.4 of this guidance demonstrate the iterative

process of the preparation of a Transport Assessment report. It should be noted

that it is common practice for a Transport Assessment Addendum, or Revised

Transport Assessment, to be provided following changes in the assessment

process. I refer to this as final Transport Assessment as in Figure 4.1.

3-1 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

TRANSPORT ASSESSMENT – INSUFFICIENT DETAIL

3.4 An original Transport Assessment report dated 26th August 2011 supported the

application. This was superseded when HCC wrote their letter to the Council in

November 2011, advising that they were unable to support the highway

proposals included within it.

3.5 Following this I understand that additional highway analysis work was

undertaken by Waterman Boreham, in conjunction with HCC, to agree highway

proposals that would mitigate for the forecast development traffic arising from the

development. The result of this work was an entirely new set of proposed

highway drawings submitted by the applicant in support of their application, that

accompanied the Committee Report, and were supported by HCC’s 15th May

2012 letter. These proposals were significantly different to the original

proposals.

3.6 I have been unable to find a final Transport Assessment report, and I am advised

that this was not provided to HCC and/or the Council during the course of the

application. It is my considered opinion that this constitutes a significant

omission on the appellants behalf. From my review of material and

correspondence I consider that this should have been provided in April or May

2012, which was the time when HCC and Waterman Boreham were concluding

highways matters. In my opinion Members were therefore correct in stating at

the 25th July 2012 Committee Meeting that there was not a robust report on

highways matters before the Committee. In my opinion the absence of a final

Transport Assessment report makes the development proposals non-compliant

with the requirements of NPPF.

3-2 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

3.7 In my opinion the final Transport Assessment report should have been prepared

and submitted to provide the following: -

(i) A multi-modal transport assessment based on person trip generation,

rather than vehicular trip generation alone. This should have quantified

all users by mode, existing and proposed, and assessed forecast

impacts;

(ii) Final agreed parking provision disaggregated by user (car user, Disabled

car user, Parent & Child car user, motorcycle, cycle) and other material

considerations within the site, especially servicing and home delivery

(dot.com). This would reflect the latest internal site layout 6459_P501

Rev B and any changes agreed since that drawing revision;

(iii) A comprehensive description of the reasons why HCC could not support

the original TA (as outlined in their November 2011 letter) and how their

concerns were overcome (as outlined in their May 2012 letter);

(iv) A description of why the Viables roundabout and Lister Road / Wella

Road junction originally needed to be changed, but no longer require

improvement as part of the latest set of proposals;

(v) Comparable summary tables that would have enabled readers to clearly

distinguish between the existing and forecast junction performance. This

would have helped decision makers, because this fundamental summary

information was entirely absent prior to Committee,.

(vi) Clearly show the changes that are to be introduced to the highway

network in plan form – as described in Part 1;

(vii) Include specific assessment and commentary by mode in the later

section(s) of the report, comparing existing Personal Injury Accident data

3-3 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

with potential change in safety performance due to the proposed highway

changes. Such an assessment would also normally be supported by a

Road Safety Audit (covered later); and

(viii) Provide clarity on the Gross Floor Area of the development (see Other

Relevant Matters).

TRAFFIC DATA – INSUFFICIENT DETAIL

3.8 The traffic data that the original Transport Assessment was based upon was

collected on Friday 7th and Saturday 8th November 2008. According to Section

4.18 of Guidance on Transport Assessment “The assessment should include

recent counts (normally surveyed within the last three years) for peak period

turning movements at critical junctions.”

3.9 The manual classified turning count data was older than 3 years.

3.10 Section 4.19 of Guidance on Transport Assessment states that traffic data

should be collected in neutral months and avoid seasonal variations, with neutral

months being April, May, June, September and October. It should be noted that

neither the November 2008 traffic data or the “infill” data (March 2011) was

collected in a neutral month. I consider that data should have been collected in

a neutral month, given the significant scale of this development.

3.11 The traffic data collected for the highway network would have included for

cyclists, but no use has been made of this baseline information on cyclists.

3.12 Apart from some pedestrian count data collected specifically at Brighton Hill

Roundabout in February 2012 (Appendix G), I can find no information that

covers the baseline pedestrian flow data.

3-4 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

PART 2: SUMMARY

3.13 I consider that the following are relevant summary points supporting the reasons

for refusal: -

(i) The failure of the appellant to provide a final multi-modal Transport

Assessment report is a significant omission – a fact that sufficient detail

has not been provided;

(ii) The lack of this report, supporting the proposed in-principle highway

changes, the appellant has not demonstrated that the proposals are

robust, or safe, or convenient, or suitable to provide access for all future

users by each mode of transport;

(iii) Pedestrians and cyclists have not been adequately considered in existing

and future scenarios.

3-5 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

4. REASON FOR REFUSAL 3: PART 3 – DESIGN OF OFF-

SITE HIGHWAYS WORKS

LINSIG TRAFFIC MODELLING – GENERAL POINTS

4.1 LinSig is a traffic modelling software tool that is used in both the design process

for new junctions and assessment of the performance of existing junctions. It

has been used by the appellant’s consultant to develop all in-principle off-site

highways works required to mitigate the traffic impact of the development.

4.2 There are errors in the traffic modelling work and there are some significant

differences between what has been modelled in LinSig and presented on the

drawings. These errors suggest that the assessment work has both

overestimated and underestimated future junction performance. The Technical

Note in Appendix C provides detail and plan references.

HIGHWAY SAFETY – GENERAL POINTS

4.3 Highway safety features in both reasons for refusal. In addition to this local

residents raised concerns over highway safety, including a local Head teacher,

during consultation.

4.4 Guidance on Transport Assessment Section 4.25 states that: “Local authorities

should take account of the likely effect on road safety of any modification, and

should require road safety audits where appropriate.”

4.5 Further Guidance on Transport Assessment Section 4.93 states that: “If the

mitigation measures require physical improvements to the highway network, the

developer should ensure that, in any design of mitigation works, appropriate

4-1 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

design guides and parameters are used. Road Safety Audits may be required for

any development-related highway works and, when produced, should be

conducted in compliance with the relevant standards.”

4.6 Design Manual for Roads and Bridges (DMRB) at Volume 5 Section 2 Part 2

(HD19/03) states in Section 2.21 that: “Stage 1 Road Safety Audits will be

undertaken at the completion of preliminary design.....and for development-led

Highway Improvement Schemes before planning consent where possible.”

4.7 HCC’s Practice Note: “Offsite Highway Works Carried Out By Developers On

Behalf Of The Highway Authority” Fourth Edition, Revised February 2010, in

Section 2.2(c), and Appendix 11, requires that “All schemes are subject to a full

highway safety audit procedure; i.e. Preliminary, Detail...”

4.8 HCC’s Practice Note: Section 2.2(d) states: “All schemes shall be subject to a

Non Motorised User Context Assessment in accordance with HD 42 and as

described in Appendix 13. The aim of this assessment is to review the existing

provision for Non Motorised Users (NMUs) and identify opportunities to improve

conditions for pedestrians, mobility impaired, cyclists and where appropriate,

equestrians. This assessment should be carried out during the initial planning

stage for the offsite highway works and supplied as part of the Preliminary

Design Check.”

4.9 In considering the above, the scale of the development and the scale of the

mitigation proposals I consider that the lack of Stage 1 Road Safety Audits are a

significant omission. The appellant, in not undertaking a Stage 1 Road Safety

Audit, has left a greater degree of uncertainty over the mitigations proposals by

not proactively undertaking this at an earlier stage. It is therefore evident that

4-2 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

the appellant has not demonstrated that the proposals are safe or otherwise for

any user.

DESIGN OF OFF-SITE HIGHWAYS WORKS – DETAILED CONSIDERATIONS

4.10 I now review the detail of each proposed in-principle highway drawing in turn

with my own conclusions. I draw on the Atkins’ Technical Notes on LinSig

junction assessment (Appendix C) and Road Safety Assessment (Appendix D).

THE HARROW WAY / TESCO SITE ACCESS

4.11 Reference should be made to Drawing No 208084 111C & 108B (1) in Appendix

B.

4.12 Examination of the LinSig model indicates that the capacity of the right turn for

vehicles exiting the site is likely to overestimate its capacity as it has been

modelled in LinSig as a full lane (with a default ‘storage’ of 60 Passenger Car

Units (PCU)) where the drawing suggests a short lane with a capacity of 7

PCUs.

4.13 The Road Safety Assessment (Appendix D: Location E) has identified the

following safety related issues: -

(i) The property “Redruth” is prejudiced by the proposed changes. Given

the proximity to the junction, stop line and island, the design of the

junction may not be suitable and may increase the risk of collision for

drivers turning right out of that property.

(ii) A shared use footway/cycleway should have an effective width of 3

metres – it should be free from obstructions such as signal/sign posts and

street lighting poles. The shared way appears to be 3 metres wide but I

4-3 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

consider that there will be poles and/or street lighting that will constrain

this effective width.

THE A30 WINCHESTER ROAD / BRIGHTON HILL RETAIL PARK ACCESS /

SITE ACCESS

4.14 Reference should be made to Drawing No 208084 113C.

4.15 Examination of the LinSig model has indicated that: -

(i) The right turn lane of the A30 Winchester Road eastbound arm has been

allocated a default storage of 60 PCUs, although the drawing provided

indicates that only 16 PCUs can be stored in this lane. This

overestimates capacity in this location;

(ii) Both egress lanes from the Brighton Hill Retail Park access are allocated

a default storage of 60 PCUs each lane, although there is only

approximately 6 PCUs of separate provision. This significantly

overestimates capacity in this location.

4.16 The Road Safety Assessment (Location B) identified the following safety issues:

(i) The proposed layout does not prohibit vehicles wishing to turn right into

the store from Brighton Hill Retail Park. Vehicles can then exit the car

park to the Harrow Way. There is a risk that vehicles turn right and if they

do there will be a conflict with vehicles entering from the A30 Winchester

Road, pedestrians walking to and from the retail park and vehicles

prohibited from exiting the retail park (Appendix J); and

(ii) There is no provision for cyclists to exit via the A30 Winchester Road

from the proposed store. Cyclists may decide to travel against the flow of

4-4 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

traffic, which could result in collisions between cyclists and pedestrians or

traffic.

THE PROPOSED HIGHWAY WORKS AT THE HARROW WAY / LISTER

ROAD JUNCTION

4.17 Reference should be made to Drawing No 208084 118A and 108B (2).

4.18 Examination of the LinSig model has indicated that: -

(i) The time required for pedestrians to cross the proposed pedestrian

crossings has been calculated using a rate of 1.2 metres per second (the

Department for Transport: Puffin Crossings Good Practice Guide –

Release 1 (2006) section 4.7 on page 16 identifies that the average

walking speed of 85 percent of pedestrians is 1.2 metres per second or

greater). Table 2.1 below compares the time allocated in the LinSig

model and the time required to cross the crossings.

Table 2.1 – Crossing times at The Harrow Way / Lister Road junction

Time allocated in Required time

LinSig model (seconds)

(seconds)

Arm 1 The Harrow Way Westbound 6 9

Arm 2 The Harrow Way Eastbound 5 8

Arm 3 Lister Road 9 13

Table 2.1 shows a significant shortfall between the allocated and required

crossing times which would need to be addressed by reducing the

4-5 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

amount of ‘green signal time’ allocated to vehicles. Accordingly the

forecast junction performance has been overestimated.

(ii) There is an overly long wait time for those pedestrians at the junction,

with pedestrians only able to cross during an “all red” stage, which occurs

once during a 240 second cycle (4 minutes). In my opinion this would

encourage pedestrians to cross when the ‘red man’ is displayed when it

is not safe to do so.

4.19 The Road Safety Assessment (Location F) has identified safety related issues: -

(i) There is a lack of detail, such as poles, lighting columns, push buttons,

signal heads and signing (particularly for cyclists) and it is unclear

whether 3m effective clear width would be provided for the shared

footway/cycleway, particularly at the easternmost crossing of the junction;

and

(ii) No advance stop lines for cyclists are shown.

THE PROPOSED HIGHWAY WORKS AT BRIGHTON HILL ROUNDABOUT

4.20 Reference should be made to drawings reference 124B.

4.21 General observations: -

(i) It is proposed to significantly increase the width of the circulatory

carriageway prior to Western Way. This requires reducing the grass

verge and the introduction of a new footway adjacent to third party land.

The proposed footway is narrower than the existing footway of 2 metres.

I have measured clockwise the proposed dimensions as 1.6 metres and

1.7 metres respectively at the two pinch points that can be observed on

4-6 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

the drawing. To replicate a like-for-like footway it would be necessary to

acquire third party land or redesign the junction. It is unclear whether the

effective width would be further constrained by signage, lighting and/or

traffic signal pole equipment. The number of pedestrians using this

footway currently, or in the future has not been recorded or predicted by

the appellant.

(ii) There is an unexplained loss of footway continuity on the plan at the

south eastern and north eastern subway.

4.22 Examination of the LinSig model and drawings show the following

inconsistencies:

Western Way – Entering roundabout

4.23 The nose of the splitter island on the Winchester Road egress will obstruct the

path of vehicles entering the junction on Western Way attempting to make a

manoeuvre beyond the Winchester Road turn;

4.24 The allocated capacity of the ‘short lane’ on the offside is 10 PCU. This does not

appear to have been shown on the drawing as there is no sign of tapering over

the 50 metres shown, suggesting that capacity is underestimated; and

4.25 A pedestrian crossing on this arm is shown on the drawing, but has not been

modelled in LinSig. On the understanding that the crossing would be provided

then the capacity of the junction is currently overestimated.

4-7 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

The Harrow Way

4.26 On the circulatory carriageway, an allocated radius of 10 metres has been given

to the left turning lane, whilst measurement suggests that the left radius is 20

metres. .

4.27 On the circulatory carriageway, the remaining lanes have been allocated a

radius of 20 metres. The drawing suggests that the carriageway is broadly

straight and therefore an ‘infinite’ radius would be more appropriate.

Brighton Way

4.28 Additional pedestrian crossings have been modelled on the carriageway in

LinSig but these have not been shown on the drawing. It is unclear why these

have been modelled because they are not shown on this drawing.

A30 Winchester Road (West)

4.29 The nearside lane on the circulatory carriageway should be a ‘short lane’ with a

circulatory capacity of 3 PCUs. This is modelled as a long lane with a capacity

of 60 PCUs. This overestimates available capacity if demand for use of that lane

is greater than 3 PCU.

Winchester Road (Old)

4.30 The lane that exits the circulatory carriageway at Winchester Road is not

signalised within the LinSig model. A crossing is shown on the drawing that

would indicate that the model should include this – without the crossing this

would significantly overestimate traffic capacity.

4.31 The Road Safety Assessment is covered in Section 5.

4-8 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

THE PROPOSED HIGHWAY WORKS AT THE WINCHESTER ROAD

ROUNDABOUT

4.32 Reference should be made to Drawing No 208084 125.

Winchester Road (East)

4.33 It would appear that there is a forecast queue in this location in future year 2017

PM peak period 1700-1800 hours of 13.9 PCUs. The other arms of the junction

are forecast to operate either close to capacity or with significant residual

capacity in the PM peak. The reason for this is not clear when capacity could be

better balanced to reduce forecast queuing on this arm.

Ringway South

4.34 The twin left turn lanes have been allocated an infinite radius in LinSig, but the

radius has been measured as 45 metres. I consider that this will overestimate

capacity.

Ringway West

4.35 The LinSig assessment has measured the nearside lane entering the

roundabout as a ‘short lane’ with capacity of 5 PCUs. It appears to be a ‘full lane’

in the drawing. I consider that this will underestimate capacity.

4.36 The Road Safety Assessment (Location C) established a number of safety

issues: -

(i) The number of lanes on the circulatory carriageway on certain sections is

being increased from 2 to 3, which in my opinion results in narrower

lanes. This may present increased side swipe accidents particularly for

4-9 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

HGV’s and shunts due to those drivers seeking to avoid a side swipe;

and

(ii) Approach speeds may increase on Ringway West and Ringway South

approach arms to the roundabout as a result of the proposals. This could

result in a vehicle losing control on these entry arms. In my opinion the

situation is more complicated on the Ringway South approach because of

the nearside lane is initially formed as a continuation of Wella Road.

There is increased risk of conflict between weaving traffic in this short

section with higher approach traffic speeds. The increased risk of conflict

would be due to greater difficulty in judging speed of other vehicles in this

section of highway.

THE PROPOSED HIGHWAY WORKS ON THE HARROW WAY

4.37 References should be made to Drawing No 208084 108B (1), (2) & (3).

4.38 The section of The Harrow Way at its junction with Cumberland Avenue is

missing from the plans.

4.39 There is no commentary to explain how the shared cycleway is integrated into

the proposed store’s new access to facilitate pedestrians and cyclists and

encourage more use of these modes to travel to the proposed new foodstore.

4.40 The Road Safety Assessment (Location D & G) has highlighted some areas of

concern over the suitability of the footway/cycleway: -

(i) The potential conflict between signal, or lighting poles, and cyclists;

4-10 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

(ii) The level differences at the rear of the shared way would present a

hazard particularly for cyclists approaching each other and manoeuvring

to avoid collision, particularly at night and in inclement conditions; and

(iii) No advance stop lines for cyclists are shown.

REASON FOR REFUSAL 3 SUMMARY

4.41 Part 1 and Part 2 confirmed that insufficient detail had been provided and this is

further supported by my conclusions regarding Part 3.

4.42 The most significant omission is the lack of a final Transport Assessment report

that covers all modes of highway user. The proposed junctions should be

supported by this report.

4.43 I have identified that there are a significant number of errors in the junction

modelling underpinning the proposed mitigation. There are errors in the LinSig

modelling and inconsistencies between drawings and models. This is sufficient

to cast doubt upon the reliability of the process used to design and assess the

impact of the proposals.

4.44 Therefore, as quoted in reason for refusal 3,: “the in-principle design of the off-

site highways works, including site accesses, does not include sufficient detail to

satisfactorily demonstrate that the proposed highway works would adequately

mitigate against the significant impact of the proposed development for all

highways users.”

4.45 I am satisfied the proposed mitigation does present safety issues and these

would lead to hazards and danger to future road users. In my view the appellant

should have carried out Stage 1 Road Safety Audits to demonstrate that the

4-11 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

proposed mitigation was deliverable, and where unsafe, that it is possible to

provide the alternative within the public highway boundary.

4.46 Therefore, as quoted in reason for refusal 3,: “It has also not been demonstrated

that safe and suitable access to the site can be achieved”; and

4.47 Simply by virtue of the above, and the lack of detail supporting the design it is

impossible to state definitively: “that the proposed highway works can be

effectively undertaken within the transport network in such a way as to mitigate

the significant impacts of the development.

4.48 The proposed development does not comply with Saved Policy E1 of the

Basingstoke and Deane Borough Local Plan 1996-2011 and paragraph 32 of the

National Planning Policy Framework (March 2012).

4-12 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

5. REASON FOR REFUSAL 4: BRIGHTON HILL

ROUNDABOUT

POLICY CONTEXT

5.1 Reason for refusal 4 states that the proposed development would be contrary to

Saved Policies E1 and A2 of the Basingstoke and Deane Borough Local Plan

1996-2011 and the National Planning Policy Framework (March 2012).

5.2 I have already outlined Saved Policy E1 of the Basingstoke and Deane Borough

Local Plan 1996-2011 in Section 2. Saved Policy A2 states:

“The Borough Council will only grant planning permission for developments with

vehicular and pedestrian generation implications where:

i. cycling and walking infrastructure are integrated with the development

and linked with surrounding networks; and

ii. development takes account of the needs of public transport.

Elsewhere within the Plan area opportunities will be examined to improve

provision for pedestrians, cyclists and to encourage the use of public transport

including community transport in areas not served by conventional public

transport...”

5.3 There are several sections within the National Planning Policy Framework that I

consider relevant to reason for refusal 4. Under “Core Planning Principles”,

paragraph 17 states: -

5-1 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

“...planning should...actively manage patterns of growth to make the fullest

possible use of public transport, walking and cycling”

5.4 Under “Promoting Sustainable Transport”, I outlined paragraph 32 in Section 2,

while paragraph 35 states:

“...developments should be located and designed where practical to...

 give priority to pedestrian and cycle movements, and have access to high

quality public transport facilities;

 create safe and secure layouts which minimise conflicts between traffic and

cyclists or pedestrians...; and

 consider the needs of people with disabilities by all modes of transport.”

5.5 Under “Requiring good design”, paragraph 58 states:

“Planning policies and decisions should aim to ensure that

developments...support local facilities and transport networks...”

5.6 I consider that the design of the Brighton Hill through-about does not comply with

the above policies for the reasons listed below: -

(i) It would worsen provision for pedestrians and cyclists;

(ii) It would reduce priority for pedestrians and cyclists; and

(iii) It would not create safe and secure layouts that minimise conflicts

between traffic and cyclists or pedestrians.

5-2 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

THE PROPOSED HIGHWAY WORKS AT BRIGHTON HILL ROUNDABOUT

5.7 This section reviews Brighton Hill Roundabout and I summarise the findings of

the Atkins’ Technical Note presented in Appendix E.

5.8 This section examines reason for refusal 4 and the following specific points

about the proposed highways works in particular:

(i) They would not adequately cater for the needs of vulnerable road users;

(ii) They would add to the hazards and result in severance, danger,

inconvenience, obstruction and interruption of the movement of traffic;

(iii) They do not provide safe and convenient movement for all users; and

(iv) They do not integrate the development into the existing surrounding

network.

5.9 The remainder of this section is set out as follows:

(i) Effect on vulnerable road users; and

(ii) Road Safety Assessment.

EFFECT ON VULNERABLE ROAD USERS

5.10 Vulnerable road users include pedestrians, cyclists, powered two wheelers,

wheelchair users and equestrians.

5.11 At present, vulnerable road users can negotiate the Brighton Hill Roundabout

without interacting with road traffic as the four subways link in the centre of the

roundabout to the surrounding street network as follows: -

(i) The North-eastern subway links the centre of the roundabout to the east

side of the A30 North-eastern arm and North side of The Harrow Way;

5-3 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

(ii) The South-eastern subway links the centre of the roundabout to the south

side of The Harrow Way and east side of Brighton Way;

(iii) The south-western subway links the centre of the roundabout to the south

side of Winchester Road / west side of the A30 south-western arm; and

(iv) The north-western subway links the centre of the roundabout to the north

side of Winchester Road and west side of Western Way.

5.12 As such, there are two approaches to each existing subway, so that there are

eight approaches, or origin/destination points, in total as shown in Table 3.1

below.

Table 3.1 – Pedestrian / cyclist subways at Brighton Hill Roundabout

Subway Approaches to subway Approach reference

From the east side of the A A30 East North-eastern subway From the north side of B The Harrow Way From the south side of C The Harrow Way South-eastern subway From the east side of D Brighton Way From the west side of the E A30 West South-western subway From the south side of F Winchester Road

From the north side of G Winchester Road North-western subway From the west side of H Western Way

5.13 The pedestrian surveys from February 2012 (Appendix G) showed the highest

pedestrian flows are between the North-western and South-eastern subways.

5-4 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

This predominant movement includes pedestrians, including a proportion of

school children, and cyclists.

5.14 The works at Brighton Hill Roundabout create a new dual two lane carriageway

through the centre of the roundabout. As such, the existing segregated

pedestrian and cycle links across the roundabout would be severed.

5.15 The proposal is to remove the two western subways and require the installation

of nine at-grade pedestrian crossings. This will mean that pedestrians will be

required to cross a minimum of four new at grade pedestrian crossings to travel

between the centre of the roundabout and the western side of the roundabout.

WALK DISTANCES

5.16 In order to assess the impact of the proposed layout on pedestrians and cyclists,

the distances between the eight origin/destination points have been measured

for the existing and proposed layouts. The difference in distances is shown in

Table 3.2 below, as extracted from the Technical Note in Appendix E.

Table 3.2 – Existing & proposed walk distances at Brighton Hill Roundabout

Origin / A B C D E F G H Destination A - - -94m -64m +35m +35m +48m +83m B - - -140m -110m -11m -11m +2m +37m C -94m -140m - - +9m -30m -17m +18m D -64m -110m - - +39m 0m +13m +48m E +35m -11m +9m +39m - - -5m -34m F +35m -11m -30m 0 - - +65m +18m G +48m +2m -17m +13m -5m +65m - - H +83m +37m +18m +48m -34m +18m - -

5-5 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

5.17 Table 3.2 shows that walking distances decrease for 10 out of 24 routes,

increase for 13 routes and do not change for one route, while the proposed

layout results in an overall decrease of 132m across the 24 routes.

5.18 However, for the busiest pedestrian route between the North-western and South-

eastern subways (G & H to/from C & D), the proposed layout results in an

increase of 56 metres using the South-eastern subway, based on distance

alone.

WALK TIMES

5.19 The walking times between the origin/destination points have been calculated

based on a walking speed of 1.2 metres per second.

5.20 Walk times for the proposed layout include signal times from the LinSig model

for the pedestrian crossings. The model assessed three scenarios in 2012,

namely AM Peak (0800-0900 hours); PM Peak (1700-1800 hours); Saturday

Peak (1100-1200 hours) and three scenarios in 2017 for the same time periods.

5.21 Table 3.3 shows the proposal would result in an increase in walk times overall

and for the busiest pedestrian route. The minimum increase is 39 seconds

between Winchester Road Eastbound and The Harrow Way Westbound /

Brighton Way (2012 Saturday) and a maximum increase of 151 seconds

between Western Way and The Harrow Way Westbound/Brighton Way.

Table 3.3 – Difference between existing and proposed walking times

Scenario Difference in walking times (seconds) Overall Winchester Road E - The Western Way - The Harrow Way Harrow Way W / Brighton Way W / Brighton Way 2012 AM +3,670 +93 +118 2012 PM +2,590 +67 +92 2012 Sat +1,974 +39 +64

5-6 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

Scenario Difference in walking times (seconds) Overall Winchester Road E - The Western Way - The Harrow Way Harrow Way W / Brighton Way W / Brighton Way 2017 AM +3,502 +108 +133 2017 PM +2,406 +67 +92 2017 Sat +4,006 +126 +151

5.22 In addition, the proposed development will result in an increase in traffic using

the roundabout as outlined in Table 3.4 below. Whilst all arms will see an

increase in traffic volumes, The Harrow Way arm has been included as the

highest percentage increases are forecast here, of all six approaches to the

junction.

Table 3.4 – Percentage increases in traffic flows at Brighton Hill roundabout with store

Scenario Overall % increase The Harrow Way arm

2012 Friday AM 3.2% 14.1% 2012 Friday PM 6.8% 49.4% 2012 Saturday mid 11.1% 77.3%

5.23 Table 3.4 shows that there will be an 11.1% increase in traffic overall and a

77.3% increase in traffic on The Harrow Way arm for the Saturday peak scenario

(1100-1200 hours). This is considered a significant increase in traffic in this

location. Increased traffic on approach arms and the links between junctions

leads, in my opinion to increased severance and a barrier to pedestrian

movement across those links.

5.24 To summarise the impact on vulnerable road users at the Brighton Hill

Roundabout as follows: -

5-7 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

(i) The existing arrangement provides full segregation between pedestrians

and vehicular traffic. This would no longer be the case.

(ii) There would be an increase in distance for most of the routes affected by

the proposed layout, including a 56 metre increase in the busiest

pedestrian route between the North-western and South-eastern subways;

(iii) The proposed layout would result in significantly increased walking times

both overall and for the busiest pedestrian route between the North-

western and South-eastern subways; and

(iv) The proposed development will increase traffic using the Brighton Hill

roundabout leading to increased severance on approach arms to the

roundabout. In my opinion increased traffic volumes detract from the

adjacent pedestrian and residential environment

5.25 It can therefore be concluded that the proposed layout would result in an

increase in severance for vulnerable road users.

ROAD SAFETY ASSESSMENT

5.26 The Road Safety Assessment (Appendix D: Location A) identified the following

issues: -

(i) Pedestrian safety will be negatively impacted by the at-grade signalised

pedestrian crossings of the new link road and also deletion of two

subways, giving rise to additional at-grade pedestrian/cyclist crossings at

junction arms. At-grade facilities will be associated with an increased

number of accidents compared to subway facilities. TRL report PPR507

“Puffin pedestrian crossing accident study” shows that there were 0.38

pedestrian accidents per year and 1.58 overall accidents per crossing site

from the sample researched. The existing accident record at Brighton Hill

5-8 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

Roundabout shows that only one pedestrian accident (Accident reference

100528705) occurred as a result of crossing the roundabout within the

nine year period ending 31st December 2012. This occurred on 17th

December 2010 when a 14 year boy was knocked down after crossing

the carriageway at-grade from the central island. Pedestrian accidents at

the roundabout are therefore currently extremely low and I consider that

numbers are likely to increase;

(ii) No Advance Stop lines are provided for cyclists;

(iii) There is potential for injudicious crossing of the A30 through-about link

pedestrian crossings; the drawing does not indicate if central reserve

guard railing will be provided to ensure users are directed safely through

a staggered arrangement to the next crossing point, while on demand

facilities would minimise the risk of crossing against a red signal;

(iv) There is no inclusion of vehicle restraints to safeguard vehicular users

and pedestrians below in the event that a vehicle leaves the carriageway,

given the difference in levels between the A30 through-about links and

subways on the eastern side of the roundabout;

(v) The proposed stop line at the pedestrian crossing on Winchester Road is

very close to the roundabout exit so drivers may not have time to react to

red signals and pedestrians crossing the road;

(vi) The Western Way exit from the roundabout would appear to be the only

unsignalised arm of the whole junction. Use of this crossing by

pedestrians is likely to increase as it is a pedestrian route towards the

proposed store and it should be clarified why there is no proposed signal

controlled crossing here;

5-9 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

(vii) The proposal does not include measures to dissuade pedestrians from

taking short-cuts across arms that will not have a pedestrian facility.

Islands and verge areas that are not intended for pedestrian use should

be marked on the drawing and measures included to dissuade accidental

or deliberate use as a short-cut, such as guard railing;

(viii) A signing and signalling strategy for the junction has not been developed,

both of which often require significant space. This infrastructure could

require poles or lighting columns in footways;

(ix) No details of lighting for the new through-about links or widened areas of

carriageway are provided;

(x) There is a lack of information on levels, making it difficult to assess the

proposed gradients and whether existing gradients will be made worse by

the proposed development; and

(xi) No yellow box or keep clear markings are indicated, which would keep

entry points and pedestrian crossings clear of stopped traffic as there is

potential for blocking back during busy periods. Without these I would

consider there is a risk the queues of traffic would block other traffic

movements which would result in a poorer level of junction performance

than represented by the LinSig junction capacity assessments.

INTERRUPTION OF TRAFFIC

5.27 The proposals at Brighton Hill Roundabout require the traffic signals to be

operational 24/7. This would interrupt the smooth flow of traffic off peak.

5-10 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

REASON FOR REFUSAL 4 SUMMARY

5.28 The proposal increases both the walking distances and the walk times for most

routes. The predominant pedestrian desire line is negatively impacted by the

proposals.

5.29 The proposals are significant in scale and the infilling of two of the four subways

requires nine at-grade crossings. This introduces a significant safety issue

because the existing subway network has a very low accident rate, whereas the

proposal introduces at-grade crossings, where there is evidence to suggest that

the likelihood of a collision involving a pedestrian and a vehicle are significantly

raised.

5.30 The proposal at Brighton Hill Roundabout would: -

(i) Increase the risk of an accident between pedestrians and a vehicle;

(ii) Be significantly less attractive and reduce the priority of pedestrians and

cyclists;

(iii) Reduce priority and convenience for pedestrians and cyclists; and

(iv) Interrupt the smooth flow of traffic outside of peak times

5.31 I therefore agree “...that the proposed development, through the proposed

associated highways works at Brighton Hill roundabout, would not adequately

cater for the needs of vulnerable road users including pedestrians and cyclists

resulting in severance across established movement routes. As such the

severance of such routes would add hazards for vulnerable users with the

proposed works to the Brighton Hill roundabout resulting in danger,

inconvenience, obstruction and interruption of the movement of traffic.

5-11 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

5.32 I have evidenced that “the proposed works to the Brighton Hill Roundabout do

not provide safe and convenient movement for all potential users nor do they

integrate the development into the existing surrounding movement network”

5.33 The proposed development is contrary to Saved Policies E1 and A2 of the

Basingstoke and Deane Borough Local Plan 1996-2011 and the relevant

paragraphs of the National Planning Policy Framework (March 2012).”

5-12 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

6. OTHER RELATED MATTERS

AGREED STATEMENT ON TRANSPORT MATTERS

6.1 I have reviewed the ‘Final Draft Agreed Statement on Transport Matters’ (Core

Document 9.12) which is agreed between the appellant and Hampshire County

Council. I make some observations on the Statement below. This is not a

Statement of Common Ground.

6.2 Reference is made in Section 4 (of the Statement) to the savings in accidents

forecast at the Brighton Hill roundabout, Winchester Rd roundabout and the

junction of Harrow Way / Lister Road on account of their proposed signalisation.

I have examined these assumptions in relation to the combined accident rates

(for junctions in built up areas) as summarised in DMRB Volume 13 Economic

Assessment. The results of this analysis do not lead me to conclude that partial

or complete signalisation – as in the case of Harrow Way / Lister Road junction –

will actually confer any benefits in terms of a reduction of accidents, and may

actually result in a slight increase at the Harrow Way / Lister Road junction. This

said, I do acknowledge the benefits of signalising the Harrow Way / Lister Rd

junction for both pedestrians and cyclists.

6.3 It is commonly assumed that signalisation of free flow junctions will automatically

result in a reduction in accidents for the reasons described in the Statement.

This is not necessarily the case as signalised junctions are themselves prone to

other aspects of driver behaviour such as ‘shooting’ through red lights which

accentuate the risk of collision with opposing vehicles.

6.4 I note in Section 12 reference to the following junctions being at or close to

capacity in 2012 and 2017 in the existing situation.

6-1 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

(i) Brighton Hill roundabout

(ii) Winchester Road roundabout, and

(iii) Lister Road / Wella Road

6.5 No reference is made in the original Transport Assessment to the 2012 existing

situation in respect of Brighton Hill or Winchester Road roundabouts.

6.6 It is noted that there does not appear to be any comparison of existing (2012)

predictions with actual observations recorded as part of the traffic surveys at

these and other junctions. The lack of such a comparison, effectively validating

the existing LinSig models before use, in respect of 2012 and 2017 forecasts,

greatly weakens any assessment of benefits when comparing the existing

arrangement with proposed alternative arrangements in these years.

GROSS FLOOR AREA

6.7 On behalf of a food store operator I have sought planning permission for a

number of retail foodstores and it is my opinion that the proposed development

constitutes A1 food retail development in excess of 8,240m2 gross floor area.

6.8 There is confusion over the size of the store in the application. The size of the

store is a fundamental measurement that is used in the calculation of the store’s

trip generating potential. The industry standard trip database TRICs, correctly

used by the appellants consultant, provides trip rates that are applied to

development floor areas. These trip rates are based upon Gross Floor Area

(GFA). If the GFA is incorrect then this has a direct, and potentially significant,

impact on all downstream analysis work. This point is particularly relevant

6-2 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

because each of the in-principle proposed off-site highways junctions relies on

correct GFA in the underpinning analysis work.

6.9 I believe that clarification is required because conflicting advice on this matter

has been provided. The appellants planning consultant advised, as shown on

the planning application form and replicated in the appellants Statement of Case,

that the store is 8,240m2 Gross Internal Area (GIA). The appellant’s highways

consultant advises that the Gross Floor Area (GFA) is 8,240m2. It should be

noted that GIA is not equal to GFA. GIA does not include the walls, overhanging

canopies and other features of a building. The more appropriate equivalent of

Gross Floor Area is Gross External Area (GEA).

6.10 Typically the difference between GEA and GIA lies approximately between 3%

and 10%, although there are exceptions to this range. I consider that a typical

portal frame or warehouse type structure would be at the lower end of the range

and an urban historic building would be in the region of 10%. As there was

conflicting material provided on this matter, the Council has measured the Gross

Internal Area as equivalent to the planning application 8,240m2. In scaling off

the site layout plan (DWG. 6459_P501 rev B) the total Gross External Area,

including the cages area, would be 8,530.75m². This would suggest that GEA is

3%-4% higher than GIA for this store.

6.11 Trip rates (per 100m2) are directly multiplied by GFA the number of vehicles on

the highway network going to and from the store would be higher. Therefore in

my opinion, the analysis work under represents the potential impact of traffic on

the highway network by approximately 3-4%.

6-3 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

TRIP DISTRIBUTION

6.12 I consider that the trip distribution methodology is acceptable, though it is unclear

which retail impact assessment data it is based upon. It is my view that the use

of GL Hearn retail impact assessment data, prepared in support of a previously

withdrawn application in 2009, rather than that provided by Martin Robeson,

lacks consistency for the application.

FUTURE MAINTENANCE LIABILITY

6.13 Significant improvements to the highway are proposed and it is unknown to what

extent future maintenance liability has been considered.

6.14 The highway improvements required to mitigate development, include the

introduction of: -

(i) traffic signals;and

(ii) significant additional areas of carriageway, supporting structure and

footways

All will need future maintenance.

6.15 Any future maintenance costs would lie with the residents of Basingstoke and

Hampshire and I do not believe that this has been suitably thought through within

the Section 106 agreement. I consider that the introduction of additional

financial burden upon residents to maintain infrastructure to facilitate private

sector development is inappropriate.

6-4 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

7. CONCLUSIONS

7.1 The appellant is seeking approval of application (number BDB/75056) for the

“Erection of a Class A1 (retail) foodstore with associated car park, landscaping

and in-principle proposed off-site highway works.” The application was refused

by Basingstoke & Deane Borough Council (hereafter referred to as “the Council”)

at Development Control Planning Committee, dated 25th July 2012, and

subsequent Refusal Notice, dated 16th August 2012, (Core Document 8.2).

7.2 Reason for refusal 3 states that there is insufficient detail to demonstrate the

proposals will mitigate against the significant impact of development. I have

demonstrated that a comprehensive and suitably robust final multi-modal

Transport Assessment report was not provided by the appellant. This is a

fundamental omission.

7.3 The drawings showing the proposed highway changes were lacking consistent

detail, it appeared that certain information was missing or incomplete. The lack

of road names on some drawings did not assist the reader.

7.4 The in-principle offsite highways works and their assessment include errors and

are lacking in detail to satisfactorily demonstrate that the proposed highway

works would adequately mitigate the significant impacts of the proposed

development for all highway users.

7.5 It has also been evidenced that safe and suitable access to the site has not been

demonstrated. There are a number of concerns and outstanding safety issues

that would highlight that the proposed changes to the highway network are not

safe, as demonstrated by the Road Safety Assessment.

7-1 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

7.6 It has also been demonstrated that suitable access is in question because of the

scale of the changes that are required to the highway network that appear to

cater for traffic, but at the expense of other highway users, particularly the

pedestrian and the cyclist. In my opinion the Transport Assessment has the feel

of a historically traditional approach biased towards the car, when this is

considered in light of current best practice.

7.7 As such, the proposed development would be contrary to Saved Policy E1 of the

Basingstoke and Deane Borough Local Plan 1996-2011; and paragraph 32 of

the National Planning Policy Framework (March 2012).

7.8 Reason for refusal 4 relates specifically to the proposed changes at Brighton Hill

Roundabout. The required changes to mitigate development in this location are

significant. The proposals seek to increase the number of lanes circulating the

roundabout from two to three and the introduction of a through about introduces

a further 4 lanes through the middle of the roundabout. This means that there

are 12 traffic lanes to cross and 6 crossings on the predominant pedestrian

desire line.

7.9 The predominant route for vulnerable road users bisects these new lanes and

the proposals do introduce significant additional at-grade crossings that would

need to be negotiated, whereas before the subway provided a direct segregated

route for pedestrians.

7.10 It is not easy to see the scale of the changes proposed from the drawing from

existing to proposed, particularly the loss of verge south of Western Way. There

are inconsistencies over crossings of the two western circulating carriageway

exits that remain unclear.

7-2 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

7.11 The Road Safety Assessment has raised a number of safety matters that

demonstrate that the proposals represent a worsening for highway users. The

introduction of at-grade crossings would likely increase the risk of an accident

involving a pedestrian and vehicle, over and above the existing situation. It

should be noted that pedestrian accidents at this roundabout are extremely low

in the current arrangement and evidence from national research demonstrates

that a worsening of pedestrian accidents is highly likely.

7.12 Journey times are increased across the roundabout, particularly for predominant

movement, to the detriment of vulnerable road users over the current form of

crossing. It is noted that there are improvements in certain pedestrian

movements, though it is unknown how many pedestrians would benefit from

these.

7.13 It is therefore considered that the proposed development, through the proposed

associated highways works at Brighton Hill Roundabout, would not adequately

cater for the needs of vulnerable road users including pedestrians and cyclists

resulting in severance across established movement routes.

7.14 As such the proposals do introduce hazards to pedestrians that are not currently

there. Therefore it is agreed that the proposals at Brighton Hill Roundabout do

introduce danger, inconvenience and obstruction to pedestrians and cyclists.

7.15 The proposals do require the introduction of signal operation 24 hours a day 7

days per week. If the subways were retained it may be possible to have part

time working of signals, thereby not interrupting the movement of traffic at all

times. At non peak times free flow conditions would be preferable.

7-3 Former Smiths Industries Aerospace Ltd, The Harrow Way, Basingstoke

Proof of Evidence of Scott Marshall

7.16 It can be therefore be summarised that the proposed works to the Brighton Hill

Roundabout do not provide safe and convenient movement for all potential users

nor do they integrate the development into the existing surrounding movement

network.

7.17 This is contrary to Saved Policies E1 and A2 of the Basingstoke and Deane

Borough Local Plan 1996-2011 and the National Planning Policy Framework

(March 2012).”

7.18 The proposed food store has a gross floor area in excess of 8,240m2 gross floor

area, 3-4% more than assessed. The trip distribution used within the Transport

Assessment is based upon data within a withdrawn application. Development of

this scale is significant and it proposes significant changes to the highway

network to mitigate against the impact of development. I have concerns over the

technical assessment approach that is not robust.

7.19 The cost of future maintenance will ultimately rest with HCC and Basingstoke

and it is my opinion that this should not be the case.

7.20 In my judgment the highways issues I have identified suggest that the appeal

should be dismissed.

7-4