Metrowest and Rail Update

Total Page:16

File Type:pdf, Size:1020Kb

Metrowest and Rail Update West of England Joint Transport Board 12 December 2014 MetroWest and Rail Update Purpose 1. This report provides an update on MetroWest and other rail issues. It includes high level reporting on costs and funding for MetroWest Phase 1 and 2 as shown below. MetroWest Phase 1 and 2 – Scheme Cost and Profile MetroWest Phase 1 £58.2m Cost* MetroWest Phase 2** £43m Total £101.2m Devolved Major Schemes £81.4m Early development costs £5.6m Funding Local Growth Fund £11.7m Total £98.7m Shortfall £2.5m * outturn costs including 30% contingency ** Phase 2 costs based on Halcrow Study of 2012, which assumed a Henbury ‘spur’ Funding Local Profile Devolved Allocation Growth Local Fund Total Shortfall 2015/16 - 2021/22 – 2015/16- 2020/21 2024/25 2018/19 MetroWest £3.5m £44.9m - £8.5m £56.9m £1.3m Phase 1 MetroWest £2.1m - £36.5m £.3.2m £41.8m £1.2m Phase 2 Notes: Figures have been rounded. Implementation of Phase 2 currently planned to start in 20/21 in advance of the next tranche of devolved funding being available in 21/22. 2. The tables above have been updated with the £11.7m successfully bid for through the Strategic Economic Plan Local Growth Fund intervention for Phase 1 capital and Phase 2 development costs. This has substantially reduced the 1 overall MetroWest shortfall from £14.9m to £2.5m. As reported to the Joint Transport Board on 12 September 2014 the £1.3m shortfall for Phase 1 will be explored through the production of the Outline Business Case for completion by November 2015. For more detail of the cost and funding profiles for MetroWest Phase 1 and 2 from 2015/16 to 2024/25 see Figure One. Phasing Opportunities for Phase 2 3. It should be noted that capital funding for Phase 2 through the devolved major scheme allocation only comes on stream in 2021/22 and therefore opening the scheme in 2021 will be a significant challenge. 4. Phasing opportunities to bring forward funding for Phase 2 include: Seek agreement for early drawdown of devolved funding for 2021/22 for Phase 2. Borrow against 2021/22 allocation to enable start in 2020/21. Economic Development Fund with the opportunity to use retained business rates to fund the shortfall. MetroWest Progress 5. The Board receives a high level report on progress on MetroWest Phases 1 and 2 and the latest versions in the new simplified format can be found in Appendix One and Two. A summary of recent, current and planned activities over the next few months is provided below. MetroWest Phase 1 Development Consent Order (DCO) – North Somerset Council will be the sole promoter and legal team procurement is taking place. Case to be submitted to the Office of Rail Regulation on the ‘exceptional circumstances’ required for a level crossing at Quays Avenue in Portishead. GRIP Stage 3-4 brief issued. Network Rail to issue tender in December 2014 with appointment of consultants anticipated by February 2015. Updated Initial Promotion Agreement to be signed by the four local authorities covering all work streams for the Outline Business Case. MetroWest Phase 2 Network Rail capability (timetable) analysis work feeding into GRIP 1-2 study. South Gloucestershire Council signed GRIP Stage 1-2 Development Services Agreement with Network Rail. Network Rail has appointed URS to produce the GRIP Stage 1-2 report and work has started. GRIP Stage 1-2 work currently underway. CH2MHill started work on the Preliminary Business Case work, September 2014. 2 Bristol New Stations High Level Assessment Study work on new stations at Ashley Down and Horfield (with alternative site at Constable Road) feeding into GRIP Stage 1-2 work. Timescales for Phase 1 and 2 Key decisions/milestones Date Phase 1 Phase 1 Preliminary Business Case endorsed by the Joint September 2014 Transport Board to progress to Outline Business Case (Programme Entry) for GRIP Stage 3. Phase 1 Outline Business Case and seek powers and Autumn 2015 procurement decision by Joint Transport Body. Phase 1 Development Consent Order application Spring 2016 Phase 1 Full Approval decision by Joint Transport Body Autumn 2017 Phase 1 construction December 2017 to May 2019 Phase 1 opening May 2019 Phase 2 Phase 2 Preliminary Business Case and single option (for GRIP June 2015 Stage 3) decision by Joint Transport Body. Phase 2 Outline Business Case and seek powers and June 2016 procurement decision by Joint Transport Body. Phase 2 Full Approval decision by Joint Transport Body March 2020 Phase 2 construction April 2020 to March 2021 Phase 2 opening May 2021 3 Figure One: MetroWest Scheme Cost and Profile (£M) Pre Scheme 15/16 16/17 17/18 18/19 19/20 20/21 21/22 22/12 23/24 24/25 Total 15/16 Phase 1 £1.28 £2.99 £2.53 £18.94 £29.93 £2.49 - - - - - £58.16 Phase 2 £0.69 £1.41 £0.42 £0.87 £0.89 £0.24 £29.25 £9.23 - - - £43.00 Total £1.97 £4.4 £2.95 £19.81 £30.82 £2.73 £29.25 £9.23 - - - £101.16 MetroWest Funding and Profile (£M) Scheme Pre 15/16 16/17 17/18 18/19 19/20 20/21 21/22 22/12 23/24 24/25 Total 15/16 Confirmed Local £1.97 - - - - - - - - - - £1.97 Funding Other Local Funding £3.62* £3.62 Devolved Major - - - £28.40 £16.50 - - - - - - £44.90 Schemes Phase 1 Devolved Major - - - - - - - £36.50 - - - £36.50 Schemes Phase 2 Local Growth Fund - 1.60 1.60 4.25 4.25 - - - - - - £11.70 Total £1.97 £5.22 £1.60 £32.65 £20.75 - - £36.50 - - - £98.69 * Full local authority funding for Phase 1 in 2015/16 still to be confirmed Shortfall (-Surplus) £0 -£0.82 £1.35 -£12.84 £10.07 £2.73 £29.25 -£27.27 - - - £2.47 4 Stakeholder Engagement 6. Stakeholder meetings now take place after each Joint Transport Board. The most recent one was held in Kingswood on 22 September 2014. First Great Western provided an update on their activities with Network Rail explaining the GRIP process followed by a detailed run through the MetroWest Phase 1 Preliminary Business Case. Whilst the attendance was disappointing there was a lively question and answer session covering issues around funding, passenger forecasting, revenue protection, alternative train services and improving access to stations. The next meeting is at the Campus in Worle on 17 December 2014, 4pm to 6pm. Risk 7. Key risks will form part of the quarterly reporting to the Board. Risks at the project and programme level will be managed through the Rail Programme Board. Equalities Implications 8. New stations and services provided under MetroWest will be designed to meet all statutory accessibility standards. Affordability issues will need to be considered as evidence shows that people from minority ethnic backgrounds, disabled and older people have a lower ability to pay. Consultation will ensure wide opportunities for diverse groups to have their say. Equality Impact Assessments will be undertaken and maintained and updated as the MetroWest projects progress. Resources (financial and personnel) 9. This Board at its meeting on 2 December 2013 endorsed the MetroWest Phase 1 budget of £1.53m and Phase 2 budget of £0.4m for 2014/15 for approval by the four councils. These budgets have now been approved. 10. Delivering MetroWest will require additional resources and funding. MetroWest Phase 1 and Phase 2 train services will require financial support from the local authorities for the first three years. Subject to meeting value for money criteria the Department for Transport may fund the services from then on. Environmental Impact Assessment 11. Whilst rail’s share of journeys to work is modest, modern rolling stock contributes less carbon emissions than other forms of transport. Reinstating the railway line between Pill and Portishead, new services on the Portishead and Henbury Lines and the construction of new stations under Phase 1 and Phase 2 will have a visual and environmental impact. 5 Other rail updates Western Route Study 12. Network Rail’s Western Route Study, October 2014 sets out a strategy for developing rail services to 2043. It predominately covers the area of the current First Great Western Franchise and includes the Great Western Main Line to Bristol and Bath as well local and freight only lines. Whilst it covers a 30 year time frame the detail is focused on proposals for the next Control Period (CP6 2019 to 2024). 2019 is taken as the starting point or baseline so schemes such as the four tracking of Filton Bank, electrification of the Great Western Main Line, new platforms at Bristol Parkway and Temple Meads and signalling renewal in the Bristol area are all assumed to have happened. Points to note for the West of England are: Inclusion of MetroWest Phase 1 and 2 in the 2019 baseline. Enhanced renewal of Bristol East Junction needed during Control Period 5 (2014 to 2019) to provide capacity for post 2019 train services including MetroWest Phase 2. Passenger capacity interventions at Bristol Temple Meads and Bristol Parkway. Capacity constraints at Westerleigh Junction (for services to Yate and the Midlands) and between Westerleigh and Stoke Gifford. Future electrification proposals for Bristol to Weston-super-Mare, Bristol to Birmingham and to Avonmouth and Portbury docks. Additional and faster services train services for Bristol to Gloucester (1 train per hour Bristol to Cardiff (2 tph with extensions beyond Bristol), Cardiff to Birmingham via Bristol Parkway (2 tph), Bristol to Exeter (1 tph), Bristol to the South Coast (1 tph), Bath to Oxford (1 tph) and freight (1 tph).
Recommended publications
  • Appendix F CAPABILITY MODELLING
    Ref: 139797 Version: 1.1 Date: June 2015 Appendix F CAPABILITY MODELLING Governance of Railway Investment Projects Ref: 139797 Version: 1.1 Date: June 2015 This page left deliberately blank Governance of Railway Investment Projects Group Strategy - Capability Analysis MetroWest Phase 2 Report Rhys Bowen Group Strategy – Capability Analysis MetroWest Phase 2 Report Document Control Scheme Name MetroWest Phase 2 Report Document Ref. No. Document V:\SAP-Project\CA000000 - MetroWest RSV8 TH\004 Report\Phase Two Location Version No. 1.0 Status Final Author Rhys Bowen Version Date 15/12/2014 Security Level Unrestricted Authorisation Control Lee Mowle Signature Date Project Manager –Capability Analysis (Document Owner) Alistair Rice Signature Date Major Schemes Project Manager - South Gloucester council Andrew Holley Signature Date Senior development Manager - Network Rail Group Strategy – Capability Analysis MetroWest Phase 2 Report DOCUMENT CONTROL & ADMINISTRATION Change Record Version Date Author(s) Comments 0.1 12/09/14 Rhys Bowen First Draft 0.2 17/09/14 Rhys Bowen Amended after diagrams added 0.3 18/09/14 Rhys Bowen Amended after review 0.4 23/09/14 Rhys Bowen Amended after review 0.5 26/09/14 Rhys Bowen Draft for external review 0.6 04/11/14 Rhys Bowen Final draft for internal review 0.7 07/11/14 Rhys Bowen Final draft for external review 0.8 28/11/14 Toby Hetherington Minor amendments to final draft. Further minor amendments and report 1.0 15/12/14 Toby Hetherington finalised. Reviewers Version Date Reviewer(s) Review Notes Structure
    [Show full text]
  • Agenda Item 3 Bristol City Council Extraordinary Full
    AGENDA ITEM 3 BRISTOL CITY COUNCIL EXTRAORDINARY FULL COUNCIL MEETING 27 AUGUST 2015 Report of: Shahzia Daya, Interim Service Director – Legal & Democratic Services Title: Call-in referral - West of England Joint Transport Board decision: Metrowest Phase 2 preliminary business case RECOMMENDATION That the Full Council debates the West of England (WoE) Joint Transport Board decision on Metrowest Phase 2 preliminary business case, in light of the call-in of this decision, and that the Full Council determines either: a. To object to the decision and refer it back to the Joint Transport Board, together with its views; or: b. Not to object to the decision, in which case the decision becomes effective immediately. BACKGROUND The Joint Transport Board’s decision: 1. A report was submitted to the Joint Transport Board (JTB) on Friday 17th July 2015. The report updated the JTB on the MetroWest Phase 2 Preliminary Business Case (PBC), and recommended to take the scheme option forward to Outline Business Case (Programme Entry) stage. 2. A copy of the 17th July Joint Transport Board report is attached at Appendix A. 3. On 17th July 2015, the Joint Transport Board took the following decision: The Board: i Endorsed the Preliminary Business Case and the progressing of Option 1A (Henbury Spur plus Yate Turn-back), without Constable Road Station, to the Outline Business Case (Programme Entry). ii That the long-term prospects for the Henbury Loop and Constable Road Station be considered by the WoE Joint Spatial Plan and Future Transport Study. iii To undertake public consultation on the site for a station at Henbury.
    [Show full text]
  • Ten Year Rail Delivery Plan 2030 to 2045 25 Year SOBC
    TEN YEAR RAIL DELIVERY PLAN DECEMBER 2020 West of England 10 Year Rail Delivery Plan for Investment: 2020 – 2030 November 2020 Document Control Document title West of England 10 Year Rail Delivery Plan Version and date v1 24/04/2020 v2 27/04/2020 Shared with Network Rail v3 09/06/2020 Issued to Strategic Rail Programme Board 09/06/2020 v4 15/07/2020 Issued to Strategic Rail Programme Steering Group 12/08/2020 v5 23/09/2020 Issued to Strategic Rail Working Group 25/09/2020 v6 16/10/2020 Issued to Strategic Rail Working Group and Strategic Rail Programme Steering Group on 16/10/2020. Minor changes made. v7 10/11/2020 Minor changes made following Transport Board on 04/11/2020 and other comments. v7.1 27/11/2020 Minor changes following comments made at Leaders and Mayor’s meeting Author James White, WECA Reviewed by Tamsin Dangerfield, Network Rail Strategic Rail Programme Steering Group Strategic Rail Working Group 1 Contents Introduction Summary 1. Objectives for the 10 Year Rail Delivery Plan 2. What all schemes need to demonstrate 3. Beyond Coivd-19 - legacy and future planning 4. Existing schemes for delivery in the first five years of the 10 Year Rail Delivery Plan 5. Pipeline Projects, New Stations Fund, Restoring Your Railway and other schemes that could come forward 2020 to 2030 6. New schemes for delivery and development 2020 to 2030 – Table One 7. Business Case approach to delivering schemes 8. Governance 9. Programme 10. Funding 11. Risks 12. Longer term – 25 Year Strategic Outline Business Case 13.
    [Show full text]
  • 5.4 Construction Strategy
    Portishead Branch Line (MetroWest Phase 1) TR040011 Applicant: North Somerset District Council 5.4 Construction Strategy The Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations 2009, 5(2)(q) Author: Network Rail Date: November 2019 Document Purpose This technical document was produced by Network Rail as part of the Governance for Railway Investment Projects Stage 4 single option development and technical assessment, in accordance with Network Rail document formatting requirements. The purpose of this document is to give the background to information presented and assessed in the Environmental Statement (submitted as part of the Portishead Branch Line (MetroWest Phase 1) DCO Scheme ("DCO Scheme")) of the likely construction methods of the DCO Scheme. Some of the information presented in this document has been superseded as Network Rail has undertaken further work to inform construction, for example the access points presented on page 82 have changed. Where information presented in the Construction Strategy has been superseded the Environmental Statement presents the latest information as informed by the Network Rail project team. The construction approach for the DCO scheme is described in Chapter 4 of the Environmental Statement (DCO document 6.7). Version Version Update Issued by Date 1 First draft Victoria Smale 25.04.18 1.1 Minor updates following further Victoria Smale 17.05.18 reviews. 1.2 Update to draft version following Victoria Smale 31.05.18 further reviews with North Somerset Council (NSC). 1.3 Further update to Quarry Victoria Smale 31.07.18 Underbridge number 2, use of Avonmouth Docks included, Ham Green compound updated as not suitable for RRV access.
    [Show full text]
  • Public Forum West of England Joint Committee Statements 27 July 2018
    Public Forum West of England Joint Committee Statements 27 July 2018 Public Forum Statements Received Statement Name, organisation 1. David Redgewell, SWTN/Bus Users UK West of England Transport Links 2. David Redgewell, SWTN/Bus Users UK MetroBus 3. Christina Biggs, FOSBR FOSBR Rail Plan 2018 Proposals 4. Martyn Hall (Christina Biggs to speak on behalf of) Thornbury Railway Public Forum West of England Joint Committee Statements 27 July 2018 Statement 1 David Redgewell SWTN/Bus Users UK West of England Transport Links 1. The Chocolate Path Bristol We support plans to reinstate the path and make it fit for purpose for walking and cycling. 2. MetroWest We welcome the DfT and Metro Mayor study into the suburban rail network for Greater Bristol and the investment in Severn Beach – Westbury and the proposed Portishead – Westbury lines. We also welcome studies into Bristol – Gloucester and Bristol – Henbury Loop, noting that the Henbury loop will need a higher level of service if indeed the Arena is sited at Filton North Station. We feel it is very important to make progress for the City Region and we must ensure that all stations are fully accessible eg Lawrence Hill and Stapleton Road. 3. Congestion Task Group We welcome the work undertaken especially on bus priority and bus infrastructure and the potential Quick Wins on the A38 corridor. The Group worked on getting progress on Temple Meads station works which are now receiving funding. We believe that through Partnership working with First Bus division, First Rail division and Network Rail we are getting funding released and are making real progress.
    [Show full text]
  • Great Western Electrification: Unlocking Future Growth
    Research Spring 2 017 Great Western Electrification: Unlocking future growth 08449 02 03 04 gva.co.uk Setting the scene 235 miles of railway to be electrified Over 100 million passengers a year are Future growth in the West of England predicted to travel on Great Western services will also be delivered through local and by 2019, according to Network Rail, in addition national infrastructure schemes that run to road and bus commuting in the region. in parallel to the electrification of the GWML. Investment in road, bus and rail networks is These include Crossrail, MetroWest, Bus Rapid essential to accommodate these growing Transit schemes and proposed investment numbers of commuters to unlock future in additional motorway junctions along the economic growth in key areas along the M49 and M4. Great Western route, ensuring our Core City Our report focuses on four key locations Region remains the only City outside of in the West of England region: Bath, Bristol, London to positively contribute to GDP. Chippenham and Swindon, all of which The electrification of the Great Western will benefit from electrification by having Main Line (GWML) will deliver a significant a commuting distance of under 90 minutes enhancement to the connectivity and capacity to London and enhanced interurban services. of services in the West of England. The project We will examine how transport connectivity, will bring new high-speed electric trains, a major local infrastructure projects, and investment in redevelopment of Bristol Temple Meads and station upgrades (to accommodate capacity Paddington Stations (to be known as Paddington and commuter flow) will play a critical role Place), and modernisation of signals and in unlocking new economic growth and stations along 235 miles of railway corridor.
    [Show full text]
  • The Fosbr Newsletter
    FOSBR Newsletter. #76 SPRING 2011. ¡WIRES COME WEST! SPARKING Mid April. Electric Spring: Getting ready for peak oil? Government extends electrification to Cardiff taking in Bristol and Bath. Funding continues for the Severn Beach Line. Infrastructure creep: Ticket machines at some Severn Beach Line stations. Capacity improvements of local Bristol Lines come closer. Positive noises heard about the Portishead Rail Corridor. The Great Western Hub. At last the coalition government has confirmed that the Great Western Main Line including both the lines via Bristol Parkway and Bath through the Severn Tunnel to Cardiff are to be electrified, implementing something that should have occurred in the 80’s together with the late British Rail’s Advance Passenger Train (where do you think the Pendolino’s tilting technology came from?). Instead of running innovative British Technology in the spirit of Brunel we shall have custom- designed bi-mode Hitachi Trains possibly assembled in the north of England to run electrically as far as Cardiff switching to Diesel mode (should I be saying self powered?) to reach Swansea where it is currently deemed not cost effective to rig the wires. Perhaps it is time for the Irish to take up the lobbying from the Welsh to have this European strategic route electrified all the way to Fishguard. However electrification to Swansea has not been ruled out completely and when it sinks in that it would mean that the new trains would not need to carry a diesel engine per carriage that would only be used for the last 40 miles then there is a chance that common sense will prevail.
    [Show full text]
  • FOSBR Newsletter Number 85 April 2014
    FOSBR Newsletter Number 85 April 2014 17 May 2013 Stapleton Road station – on the new footbridge FOSBR invited MPs, the Mayor of Bristol, local councillors, trade unionists, transport campaigners and passengers to show local support for funding four-tracking and local electrification – it worked! 1 Local Rail 2008–14: What we've achieved so far... (Rob Dixon) We were thinking the other day about what we have achieved in the last few years. Although we haven't seen as many changes as we'd like, there has been definite movement in favour of rail – just look at the recent letter and opinion pages of the Bristol Post. What we've achieved through people power so far: • We persuaded Bristol City Council to pay the train operator £420,000 p.a. to provide an additional train and train crew on weekdays to Avonmouth/Severn Beach and an hourly Sunday service. In Sept 2011 the subsidy was renegotiated by BCC to £200,000, due to the increase in passengers. In Sept 2012 a long- existing gap in the evening service was filled with one extra round trip of the train, leaving Temple Meads at 21.37. This was achieved through sustained campaigning from FOSBR and allies and was negotiated by Bristol City Council at no extra subsidy cost. • This more reliable 40-minute service, which started in May 2008, reached one million passenger trips in 2013. Bristol City Council funding ended in 2014 as DfT took over the enhanced service into the franchise. FOSBR would like the council to reinvest the money saved to kickstart a new improvement – such as extra trains stopping at Bedminster and Parson Street or filling the gaps in the Severn Beach line evening service.
    [Show full text]
  • Analysis and Forecasting Interim Report Nov 2013
    Network Rail – Analysis & Forecasting MetroWest Interim Report November 2013 Rob Brewer Network Rail – Analysis & Forecasting MetroWest Interim Report TABLE OF CONTENTS 1. Executive Summary ...................................................................................................................................... 4 2. Introduction .................................................................................................................................................. 6 3. MetroWest Proposals ................................................................................................................................... 7 3.1 MetroWest Phase 1 ............................................................................................................................... 7 3.1.1 Re-Opening of the Portishead Line ................................................................................................. 7 3.1.2 Increasing Service Frequencies on Existing Routes ........................................................................ 8 3.2 MetroWest Phase 2 ............................................................................................................................... 8 3.2.1 Re-Introduction of Passenger Services on the Henbury Line ......................................................... 8 3.2.2 Additional Increase of Service Frequencies on Existing Routes ..................................................... 9 4. A summary of work completed .................................................................................................................
    [Show full text]
  • Joint Local Transport Plan 3 2O11 — 2O26
    West of England Joint Local Transport Plan 3 2O11 — 2O26 March 2011 The Joint Local Transport Plan 3 is produced under the requirements of the Transport Act 2000 S108 as amended by the Local Transport Act 2008. It meets in full the duty to develop and implement policies for transport. Contents Executive Summary.................................................................................. 5 1 Setting the Scene...................................................................................... 13 2 Visions, Goals and Challenges.............................................................. 19 3 Engagement ............................................................................................... 29 4 Strategic Environmental Assessment and Option Testing........ 35 5 Reducing Carbon Emissions ................................................................. 43 6 Support Economic Growth.................................................................... 55 7 Accessibility................................................................................................. 75 8 Safety, Health, Security ........................................................................... 89 9 Quality of Life.............................................................................................. 101 10 Delivery Plan............................................................................................... 113 11 Major Schemes........................................................................................... 117 12 Indicators and
    [Show full text]
  • Phase 2 Preliminary Business Case July 2015
    Phase 2 Preliminary Business Case July 2015 Document History MetroWest Phase 2 Preliminary (Strategic Outline) Business Case West of England Authorities This document has been issued and amended as follows: Version Date Description Created by Verified by Approved by 1.0 8 May 2015 Draft JE/GW HS AR 1.1 23 June 2015 Revised draft JE/GW HS AR 1.2 23 June 2015 Final draft JE/GW HS AR 1.3 8 July 2015 Final JE/GW HS AR METROWEST PHASE 2 Contents Section Page Acronyms and Abbreviations .............................................................................................................. vi Introduction ......................................................................................................................... 1‐1 1.1 Project overview .............................................................................................................. 1‐1 1.2 Purpose of this report ...................................................................................................... 1‐3 1.3 Methodology .................................................................................................................... 1‐4 1.4 Structure of remainder of this document ........................................................................ 1‐4 Strategic Case ....................................................................................................................... 2‐1 2.1 Introduction ..................................................................................................................... 2‐1 2.2 Business strategy
    [Show full text]
  • Strategic Case
    Chapter 1: Strategic Case Contents Page 1.1 Introduction ................................................................................................................. 1-2 1.1.1 The MetroWest Programme ...................................................................................... 1-2 1.1.2 Structure of this Chapter ........................................................................................... 1-4 1.2 Sub-Regional Context .................................................................................................... 1-5 1.2.1 Sub-Region Overview ................................................................................................. 1-5 1.2.2 Sub-Region Strategic Aims ......................................................................................... 1-5 1.2.3 Sub-Region Transport Network Overview ................................................................. 1-7 1.2.4 Sub-Region Rail Network Overview ........................................................................... 1-8 1.3 Project Overview ........................................................................................................ 1-12 1.3.1 Scheme Scope .......................................................................................................... 1-12 1.3.2 Scheme Programme ................................................................................................. 1-20 1.3.3 Scheme Estimated Cost ........................................................................................... 1-21 1.3.4
    [Show full text]