GALVESTON DISTRICT Dredging Schedules
Tricia C. Campbell, P.E. Operations Manager Navigation Branch - Galveston District November 15, 2016
Galveston District – Dredging Meeting Custodians of the Texas Coast
US Army Corps of Engineers
BUILDING STRONG® GALVESTON DISTRICT FACTS
Texas #2 in Nation in Maritime Commerce Texas Ports moved 538M+ tons at $320B in 2014 Galveston District Ports National Rank Houston (2) Beaumont (4) Corpus Christi (6) Texas City (15) Port Arthur (20) Freeport (32) Matagorda (48) Galveston (52) Brownsville (67) Galveston Victoria District – Dredging Meeting(70) Custodians of the Texas Coast Gulf Intracoastal Waterway (3)
GIWW-TX 73M+ tons at $43B in 2014 21.3% Nation’s Import/Export/Domestic Tonnage US24.8% Army Corpsof Nation’s of Engineers Total Export tonnage 50,000 square miles BUILDING27.5% of Nation’s STRONG Total ®Import tonnage GALVESTON NAVIGATION OM FUNDING
FY-16 Execution President’s Budget $110,404,000
FY-16 Allocation $151,869,000 Carry-in $ 21,837,000 Available to Obligate $173,706,000
Obligated ~$161,000,000 Percent Execution ~93%
FY-17 Funding Outlook President’s Budget $107,815,000 Carry-in $ 13,727,000 Total Anticipated $121,542,000
BUILDING STRONG® GALVESTON NAVIGATION OM FUNDING
BUILDING STRONG® FY17 CONTRACT SCHEDULES SABINE-NECHES WATERWAY
Galveston District – Dredging Meeting - Custodians of the Texas Coast
BUILDING STRONG® SABINE-NECHES WATERWAY NECHES RIVER
Project: Sabine-Neches Waterway Neches River
Dredging Depth: 42 ft. Required Depth Dredging Width: ~200 ft Dredging Length: Varies Dredging Quantity: 600,000 cubic yards Material Type: Silt Placement Area: Various Upland PAs Distance to Placement 1-2 Miles Area: Type of Equipment: Pipeline Env. Window: NA Reason for Window: NA Est. Start Date: April 2017 Est. Completion Date: August 2017
Galveston District – Dredging Meeting - Custodians of the Texas Coast
BUILDING STRONG® SABINE-NECHES WATERWAY PA-11 SHORELINE STABILIZATION
Project: 15 Sabine-Neches Waterway 17 PA-11 Shoreline Stabilization 16 1413 Dredging Depth: NA 12 Dredging Width: NA Dredging Length: NA Port Arthur Dredging Quantity: NA Material Type: Silt Placement Area: PA-11 11 Distance to Placement NA Area: Dragline/Earthmoving Type of Equipment: equipment Port Arthur Env. Window: NA Turning Basin Reason for Window: NA 8 Est. Start Date: September 2017 9 Est. Completion Date: March 2018
Galveston District – Dredging Meeting - Custodians of the Texas Coast
BUILDING STRONG® FY17 CONTRACT SCHEDULES GALVESTON-TEXAS CITY-HOUSTON
Galveston District – Dredging Meeting - Custodians of the Texas Coast
BUILDING STRONG® HOUSTON SHIP CHANNEL SIMS BAYOU TO TURNING BASIN
Project: Houston Ship Channel Sims Bayou to Turning Basin Dredging Depth: 39.5 ft. Required Depth Dredging Width: 250 - 300 ft. Dredging Length: 3 miles Dredging Quantity: 500,000 cubic yards Material Type: Silt Placement Area: West Clinton Distance to Place 3 – 5 Miles Area: Type of Equipment: Pipeline Dredge Env. Window: NA Reason for Window: NA Est. Start Date: February 2017 Est. Completion Date: November 2017
Galveston District – Dredging Meeting - Custodians of the Texas Coast
BUILDING STRONG® TEXAS CITY CHANNEL MAIN CHANNEL AND TURNING BASIN
Project: Texas City Channel Main Channel and Turning Basin Dredging Depth: 48 ft. Required Depth Dredging Width: 400 - 1200 ft. Dredging Length: 6 Miles Dredging Quantity: 1,400,000 cubic yards Material Type: Silt/Sand Placement Areas: SPPA 3, 4, 5
Distance to Place Area: 3 Mile Average
Type of Equipment: Pipeline Env. Window: NA Reason for Window: NA Est. Start Date: March 2017 Est. Completion Date: September 2017
Galveston District – Dredging Meeting - Custodians of the Texas Coast
BUILDING STRONG® GALVESTON ENTRANCE CHANNEL AND HSC - BOLIVAR ROADS TO REDFISH
Project: Galveston Harbor - Morgan’s Point Galveston Entrance Channel and Houston Ship Channel - Bolivar Roads to Redfish Dredging Depth: 48-50 ft. Required Depth Dredging Width: 530 – 1,000 ft. Dredging Length: 17 miles Dredging Quantity: 2,500,000 cubic yards Material Type: Sand / Silt Placement Area: Offshore
Distance to Place Area: 1 - 15 Mile
Type of Equipment: Hopper Env. Window: NA Reason for Window: NA Est. Start Date: March 2017 Est. Completion Date: September 2017
Galveston District – Dredging Meeting - Custodians of the Texas Coast
BUILDING STRONG® HOUSTON SHIP CHANNEL LOST LAKE PA DEWATERING
Project: Houston Ship Channel Lost Lake PA Dewatering
Type of Work: Dewatering Lost Lake Dewatering Dredging Width: NA Lost Lake Dredging Length: NA Dredging Quantity: NA Green’s Material Type: Silt/Clay Bayou PA Placement Area: NA
Goat Island Distance to Place Area: NA
Marsh Buggy/ Excavation Peggy Lake Type of Equipment: Equipment
West & East Env. Window: NA Jones Alexander Reason for Window: NA Island PA Est Start Date: April 2017 Est. Completion Date: December 2017
Galveston District – Dredging Meeting - Custodians of the Texas Coast
BUILDING STRONG® HOUSTON SHIP CHANNEL PEGGY LAKE PA DEWATERING
Project: Houston Ship Channel Peggy Lake PA Dewatering
Type of Work: Dewatering Dredging Width: NA Lost Lake Dredging Length: NA Dredging Quantity: NA Green’s Material Type: Silt/Clay Bayou PA Placement Area: NA
Goat Island Distance to Place Area: NA
Marsh Buggy/ Excavation Peggy Lake Dewatering Peggy Lake Type of Equipment: Equipment
West & East Env. Window: NA Jones Alexander Reason for Window: NA Island PA Est. Start Date: June 2017 Est. Completion Date: October 2017
Galveston District – Dredging Meeting - Custodians of the Texas Coast
BUILDING STRONG® HOUSTON SHIP CHANNEL ALEXANDER ISLAND PA DEWATERING
Project: Houston Ship Channel Alexander Island Dewatering
Type of Work: Dewatering Peggy Lake Dredging Width: NA
Alexander Dredging Length: NA Island Dredging Quantity: NA Material Type: Silt/Clay Alexander Island PA Dewatering Spilman Placement Area: Alexander Island PA Island Atkinson Is. La Porte Distance to Place Area: NA 16 Marsh Buggy/ Excavation Type of Equipment: Equipment Env. Window: NA 15 Reason for Window: NA Est. Start: November 2017 14 Est. Completion: July 2018
Galveston District – Dredging Meeting - Custodians of the Texas Coast
BUILDING STRONG® HOUSTON SHIP CHANNEL – SPILMAN ISLAND PA CONTAINMENT DIKE RAISE Project: Houston Ship Channel Lost Lake Spilman Island PA Containment Dike Raise Type of Work: Dike Raising Dredging Width: NA Dredging Length: NA Goat Island Dredging Quantity: NA Peggy Lake Material Type: Silt/Clay Placement Area: Spilman Island
Alexander Distance to Place Area: NA Island Dragline/Earthmoving Type of Equipment: equipment Spilman Env. Window: NA Island Reason for Window: NA Est. Start Date: September 2017 Est. Completion Date: September 2018
Galveston District – Dredging Meeting - Custodians of the Texas Coast
BUILDING STRONG® HOUSTON SHIP CHANNEL MID BAY PLACEMENT AREA DEWATERING
Morgan’s Point Project: Houston Ship Channel Mid Bay PA Dewatering
Type of Work: Dewatering Dredging Width: NA Dredging Length: NA Dredging Quantity: NA Material Type: Silt/Clay Placement Area: Mid Bay
Distance to Place Area: NA
Marsh Buggy/ Excavation Type of Equipment: Equipment Env. Window: August 31-March 1 (open) Reason for Window: Migratory Birds Est. Start Date: September 2017 Est. Completion Date: March 2018
Galveston District – Dredging Meeting - Custodians of the Texas Coast
BUILDING STRONG® HOUSTON SHIP CHANNEL – HOUSE TRACT AND CLINTON PA CONTAINMENT DIKE RAISE
Project: Houston Ship Channel House-Stimson House Tract & Clinton Filter-Bed Tracts Containment Dike Raise Glendale Type of Work: Dike Raising Dredging Width: NA Dredging Length: NA Dredging Quantity: NA Material Type: Silt/Clay Placement Area: House Tract & Clinton
Distance to Place Area: NA
Dragline/Earthmoving Type of Equipment: Equipment Env. Window: NA Reason for Window: NA Estimated Start Date: October 2017 Est. Completion Date: October 2018
Galveston District – Dredging Meeting - Custodians of the Texas Coast
BUILDING STRONG® FY17 CONTRACT SCHEDULES FREEPORT HARBOR
Galveston District – Dredging Meeting - Custodians of the Texas Coast
BUILDING STRONG® FREEPORT HARBOR & MATAGORDA ENTRANCE CHANNELS Project: Freeport Harbor & Matagorda Entrance Channels 48 & 42 ft. Required Dredging Depth: Depth
85 Dredging Width: Varies Dredging Length: Varies
88 Dredging Quantity: 3,000,000 cubic yards Lavaca Bay Material Type: Sand/Silt Point Comfort Carancahua Placement Area: Offshore 19 Bay Port 23 18 Lavaca 22 17 21 16 Distance to Place Area: 2.5 Mile Avg. 20 15 14 12 Type of Equipment: Hopper 11 10 9 Env. Window: NA 8 76 Reason for Window: NA 5 Est. Start Date: July 2017 Est. Completion Date: December 2017
1 Galveston District – Dredging Meeting - Custodians of the Texas Coast
BUILDING STRONG® FREEPORT HARBOR PA-1 CONTAINMENT DIKE RAISE Project: Freeport Harbor PA-1 Containment Dike Raise Dredging Depth: NA Dredging Width: NA 1 7 Dredging Length: NA Dredging Quantity: NA Material Type: Sand/Silt 85 Placement Area: PA-1
Distance to Place Area: NA
Dragline/Earthmoving Dragline/Earthmoving 88 equipment equipment Env. Window: NA Reason for Window: NA Est. Start Date: January 2017 Est. Completion Date: July 2017
Galveston District – Dredging Meeting - Custodians of the Texas Coast
BUILDING STRONG® FY17 CONTRACT SCHEDULES MATAGORDA SHIP CHANNEL
Galveston District – Dredging Meeting - Custodians of the Texas Coast
BUILDING STRONG® RAPID RESPONSE MATAGORDA ENTRANCE CHANNEL Project: Rapid Response Lavaca Bay Matagorda Entrance Channel
Point Comfort Dredging Depth: 42 ft. Required Depth Carancahua Bay Port 19 Dredging Width: Varies 23 18 Lavaca 22 17 Dredging Length: Varies 21 16 20 15 14 Dredging Quantity: 300,000 cubic yards
12 Material Type: Sand/Silt 11 10 Placement Area: Offshore 9 8 Distance to Place Area: 2 Mile Avg. 7 6
5 Type of Equipment: Hopper Env. Window: NA Reason for Window: NA Est. Start Date: December 2016 1 Est. Completion Date: December 2016
Galveston District – Dredging Meeting - Custodians of the Texas Coast
BUILDING STRONG® FY17 CONTRACT SCHEDULES CORPUS CHRISTI SHIP CHANNEL
Galveston District – Dredging Meeting - Custodians of the Texas Coast
BUILDING STRONG® CORPUS CHRISTI SHIP CHANNEL PA 13 CONTAINMENT DIKE RAISE
Project: Corpus Christi Ship Channel Aransas PA 13 Containment Dike PA 13 Aransas Pass Pass Raise Containment Dike Raise PA 13 Ingleside Type of Work: Dike Raising Nueces Ingleside Nueces Bay 2 Dredging Width: NA Bay PA 10 Port Port Dredging Length: NA Aransas1 1 CorpusCorpus Christi Christi Aransas Dredging Quantity: NA Corpus ShipShip Channel Channel BCN 82 Material Type: NA CorpusChristi BCN 82 Christi Placement Area: PA 13 Distance to Placement NA Area: Dragline/Earthmoving Type of Equipment: Equipment Env. Window: NA Reason for Window: NA Est. Start Date: June 2017 Est. Completion Date: June 2018
Galveston District – Dredging Meeting - Custodians of the Texas Coast
BUILDING STRONG® CORPUS CHRISTI SHIP CHANNEL PA 10 & 3 CONTAINMENT DIKE RAISE
Project: Corpus Christi Ship Channel AransasAransas PA 10 & 3 Containment Dike Pass Pass Raise PA 3 PA 13 Ingleside Type of Work: Dike Raising Nueces Ingleside Nueces Bay 2 Dredging Width: NA Bay PA 10 Port Port Dredging Length: NA Aransas 1 CorpusCorpus Christi Christi Aransas Dredging Quantity: NA Corpus ShipShip Channel Channel BCN 82 Material Type: NA CorpusChristi BCN 82 Christi PA 10 Placement Area: PA 3 & PA10 Distance to Placement NA Area: Dragline/Earthmoving Type of Equipment: Equipment Env. Window: NA Reason for Window: NA Est. Start Date: September 2017 Est. Completion Date: March 2018
Galveston District – Dredging Meeting - Custodians of the Texas Coast
BUILDING STRONG® FY17 CONTRACT SCHEDULES BRAZOS ISLAND HARBOR
Galveston District – Dredging Meeting - Custodians of the Texas Coast
BUILDING STRONG® BRAZOS ISLAND HARBOR
Aransas JETTY CHANNEL Pass Project: Brazos Island Harbor Brownsville Jetty Channel 1 Dredging Depth: 44 ft. Required Depth T E X A S Port Isabel Dredging Width: 300 - 400 ft. Dredging Length: Varies 3 2 Dredging Quantity: 500,000 cubic yards Material Type: Sand 4 Placement Area: Beach / BU
Distance to Place Area: 1-5 Miles Avg.
Type of Equipment: Hopper / Pipeline Port of Brownsville Env. Window: 1 Oct - 14 Mar (open) 5 Reason for Window: Turtle Nesting / Tourism Est. Start Date: October 2017 7 M E X I C O Est. Completion Date: January 2018 8
Galveston District – Dredging Meeting - Custodians of the Texas Coast
BUILDING STRONG® FY17 CONTRACT SCHEDULES GULF INTRACOASTAL WATERWAY
Galveston District – Dredging Meeting - Custodians of the Texas Coast
BUILDING STRONG® GULF INTRACOASTAL WATERWAY FACILITY ELECTRICAL REPAIRS Project: Gulf Intracoastal Waterway CRL and BRFG Electrical Repairs Dredging Depth: NA Dredging Width: NA Dredging Length: NA
Brazos River Flood Gates Dredging Quantity: NA Material Type: NA Colorado River Locks Placement Area: NA Distance to Placement NA Area: Type of Equipment: Electrical Env. Window: NA Reason for Window: NA Est. Start Date: March 2017 Est. Completion Date: September 2017
Galveston District – Dredging Meeting - Custodians of the Texas Coast
BUILDING STRONG® GULF INTRACOASTAL WATERWAY TURNSTAKE TO LIVE OAK
Project: Gulf Intracoastal Waterway 1 Turnstake to Live Oak 2 Dredging Depth: 16 ft. Required Depth Beneficial Use Dredging Width: 125 ft. Site ‘A’ Dredging Length: Varies Dredging Quantity: 600,000 cubic yards Material Type: Fine Silt/Sand Placement Area: Open/BU Sites Distance to Placement 1 Mile Avg. Area: Type of Equipment: Pipeline Env. Window: Apr 15 – Oct 15 (Open) Reason for Window: Whooping Cranes Est. Start Date: June 2017 Est. Completion Date: October 2017 Beneficial Use Site ‘B’
Galveston District – Dredging Meeting - Custodians of the Texas Coast
BUILDING STRONG® GULF INTRACOASTAL WATERWAY SCOUR HOLE REPAIRS
Project: Gulf Intracoastal Waterway Scour Hole Repairs BRFG & CRL Dredging Depth: NA Dredging Width: NA Dredging Length: Varies Dredging Quantity: NA Material Type: Rock Brazos River Floodgates Placement Area: Within Channel Distance to Placement NA Area: Type of Equipment: Crane Barge Env. Window: N/A Reason for Window: N/A Est. Start Date: June 2017 Est. Completion Date: November 2017
Colorado River Locks Galveston District – Dredging Meeting - Custodians of the Texas Coast
BUILDING STRONG® GULF INTRACOASTAL WATERWAY PA 86 & 87 CONTAINMENT DIKE RAISE
Gulf Intracoastal Waterway Brazos HarborUpper Brazosport Project: PA 86 & 87 Containment Turning BasinTurning Basin Turning Basin Surfside Dike Raise and Channel Type of Work: Dike Raising 1 Quintana Dredging Width: NA 7 Dredging Length: NA
85 Dredging Quantity: NA Material Type: Silt/Clay Placement Area: PA 86 & 87
88 Distance to Place Area: NA 1-A Type of Equipment: Dragline Buffer Zone Env. Window: NA Reason for Window: NA Est. Start Date: July 2017 Est. Completion Date: February 2018
Galveston District – Dredging Meeting - Custodians of the Texas Coast
BUILDING STRONG® GULF INTRACOASTAL WATERWAY HI HIGH ISLAND TO ROLLOVER PASS & BOLIVAR FLARE
Project: Gulf Intracoastal Waterway High Island to Rollover & Bolivar Flare Dredging Depth: 15 ft. Required Depth Dredging Width: 125 ft. Dredging Length: Varies Dredging Quantity: 800,000 cubic yards Material Type: Fine Silt/Sand Upland, Semi-Confined & Placement Area: Beneficial-Use Distance to Placement 2 Miles Avg. Area: Type of Equipment: Pipeline Env. Window: N/A Reason for Window: N/A Est. Start Date: October 2017 Est. Completion Date: February 2018
Galveston District – Dredging Meeting - Custodians of the Texas Coast
BUILDING STRONG® CHANNEL TO VICTORIA MIDDLE REACH PA IMPROVEMENTS
Project: Channel to Victoria Middle 9 Reach PA Improvements
Type of Work: Improvements 8-C 7 Dredging Width: NA 6A 8-B 8-A Dredging Length: NA Dredging Quantity: NA Material Type: Silt/Clay 5 Placement Area: NA
Distance to Place Area: NA Channel to Long Mott Type of Equipment: Earthwork Equipment 3 Env. Window: NA Tivoli Reason for Window: NA Est. Start Date: July 2017 Est. Completion Date: January 2018
Galveston District – Dredging Meeting - Custodians of the Texas Coast
BUILDING STRONG® CHANNEL TO HARLINGEN
Project: Channel to Harlingen
Dredging Depth: 13 ft. Required Depth 3 2 4 1 6 Dredging Width: Varies 8 Dredging Length: Varies 7 5 Dredging Quantity: 600,000 10 9 Material Type: Fine Silt/Sand 11 Arroyo City Placement Area: PAs 2-3, 8, 23 12 Distance to Placement 15 13 2 Miles Avg. Area: 14 16 Type of Equipment: Pipeline Dredge 17 18 Laguna Atascosa Env. Window: N/A 19 National Wildlife Refuge Reason for Window: N/A Rio Hondo Est. Start Date: October 2017 20 21 Est. Completion Date: January 2018 22 23
Galveston District – Dredging Meeting - Custodians of the Texas Coast
BUILDING STRONG® BUFFALO BAYOU Roller Compacted Concrete Spillway Repairs
Project: Buffalo Bayou-Addicks and Barker Dam, Roller Compacted Concrete Spillway Repairs Dredging Depth: N/A Dredging Width: N/A Dredging Length: N/A Dredging Quantity: N/A Material Type: N/A Placement Area: N/A Distance to Placement N/A Area: Type of Equipment: Concrete Repair Env. Window: N/A Reason for Window: N/A Est. Start Date: August 2017 Est. Completion Date: February 2018
Galveston District – Dredging Meeting - Custodians of the Texas Coast
BUILDING STRONG® GALVESTON DISTRICT NAVIGATION
Questions/Comments? http://www.swg.usace.army.mil/Missions/Navigation.aspx
Galveston District – Dredging Meeting - Custodians of the Texas Coast
BUILDING STRONG®